TIMELINE

PROJECT NAME PROJECT MANAGER


START DATE
END DATE
Project sebulan Sawaloka 07-Jul 01-Aug = SELESAI
= MASIH BERJALAN
= BLUM DILAKSANAKAN

TASKS PIC START END DAYS Minggu ke 23-Jun 28-Jun 3-Jul 8-Jul 13-Jul 18-Jul 23-Jul 28-Jul 2-Aug 7-Aug

Pembuatan Patch logo Sawaloka , kartu nama, name tag 7/7 7/8 1 2 Pembuatan Patch logo Sawaloka , kartu nama, name tag 7/7 1
Pembuatan Desain seragam 7/8 7/9 1 2 Pembuatan Desain seragam 7/8 1
ig post ke 7 7/9 7/10 1 2 ig post ke 7 7/9 1
ig post ke 8 7/12 7/13 1 3 ig post ke 8 7/12 1
ig post ke 9 7/13 7/14 1 3 ig post ke 9 7/13 1
ig post ke 10 7/14 7/15 1 3 ig post ke 10 7/14 1
ig post ke 11 7/15 7/16 1 3 ig post ke 11 7/15 1
ig post ke 12 7/16 7/17 1 3 ig post ke 12 7/16 1
ig post ke 13 7/19 7/20 1 4 ig post ke 13 7/19 1
ig post ke 14 7/20 7/21 1 4 ig post ke 14 7/20 1

ig post ke 15 7/21 7/22 1 4 ig post ke 15 7/21 1

ig post ke 16 7/22 7/23 1 4 ig post ke 16 7/22 1

ig post ke 17 7/23 7/24 1 4 ig post ke 17 7/23 1

ig post ke 18 7/24 7/25 1 5 ig post ke 18 7/24 1

ig post ke 19 7/27 7/28 1 5 ig post ke 19 7/27 1


ig post ke 20 7/28 1
ig post ke 20 7/28 7/29 1 5
ig post ke 21 7/29 1
ig post ke 21 7/29 7/30 1 5
ig post ke 22 7/30 1
ig post ke 22 7/30 7/31 1 5