SCHEDULE PEKERJAAN SECANT PILE

PEKERJAAN PEMBANGUNAN UNDERPASS SRIWIJAYA KELURAHAN BAROS KECAMATAN CIMAHI TENGAH KOTA CIMAHI
KONTRAK 2021
JULI AGUSTUS SEPTEMBER OKTOBER NOVEMBER DESEMBER
NO URAIAN PEKERJAAN
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
SATUAN VOLUME
5-Jul 12-Jul 19-Jul 26-Jul 2-Aug 9-Aug 16-Aug 23-Aug 30-Aug 6-Sep 13-Sep 20-Sep 27-Sep 4-Oct 11-Oct 18-Oct 25-Oct 1-Nov 8-Nov 15-Nov 22-Nov 29-Nov 6-Dec 13-Dec 20-Dec 27-Dec
11-Jul 18-Jul 25-Jul 1-Aug 8-Aug 15-Aug 22-Aug 29-Aug 5-Sep 12-Sep 19-Sep 26-Sep 3-Oct 10-Oct 17-Oct 24-Oct 31-Oct 7-Nov 14-Nov 21-Nov 28-Nov 5-Dec 12-Dec 19-Dec 26-Dec 31-Dec
PEKERJAAN SECANT PILE
1 Mobilisasi dan Setting Alat Ls 1,00
2 Tiang bor sekan primer diameter 80 cm (fc 15 MPa) M1 9.700,00
3 Tiang bor sekan sekunder diameter 80 cm (fc 30 MPa) M1 9.700,00

Diketahui Oleh : Disetujui Oleh: Dibuat Oleh :

Suly Yunwati Dhany Firmansyah …..........................


VP Assurance SCM Project Manager