BULAN JUNI 2023 JULI 2023 AGUSTUS 2023 SEPTEMBER 2023 OKTOBER 2023 NOVEMBER 2023 DESEMBER 2023
MINGGU 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
No URAIAN PEKERJAAN PERIODE 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08
% KETERANGAN
BOBOT % 22 29 06 13 20 27 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14
100
A PEKERJAAN PERSIAPAN 1.660 0.237 0.237 , 0.237 0.237 0.237 0.237 0.237
90
B PEKERJAAN STRUKTUR `
I. PEKERJAAN PENGURUGAN LAHAN DAN TALUD KELILING 7.946 1.987 1.987 1.987 1.987
II. PEKERJAAN PONDASI 11.113 1.852 1.852 1.852 1.852 1.852 1.852
80
III. PEKERJAAN BETON LANTAI 1 10.212 1.459 1.459 1.459 1.459 1.459 1.459 1.459
IV. PEKERJAAN BETON LANTAI 2 11.028 1.379 1.379 1.379 1.379 1.379 1.379 1.379 1.379 -
V. PEKERJAAN BETON LANTAI ATAP 4.487 0.641 0.641 0.641 0.641 0.641 0.641 0.641
70
C PEKERJAAN ARSITEKTUR
I. PEKERJAAN ARSITEKTUR LANTAI 1 11.376 0.758 0.758 0.758 0.758 0.758 0.758 0.758 0.758 0.758 0.758 0.758 0.758 0.758 0.758 0.758
II. PEKERJAAN ARSITEKTUR LANTAI 2 18.316 1.409 1.409 1.409 1.409 1.409 1.409 1.409 1.409 1.409 1.409 1.409 1.409 1.409
60
III. PEKERJAAN ARSITEKTUR LANTAI DAK 7.048 0.705 0.705 0.705 0.705 0.705 0.705 0.705 0.705 0.705 0.705
I. PEKERJAAN ELEKTRIKAL 3.784 0.541 0.541 0.541 0.541 0.541 0.541 0.541
II. PEKERJAAN PLUMBING 4.130 0.516 0.516 0.516 0.516 0.516 0.516 0.516 0.516
I. PEKERJAAN PAGAR DEPAN DAN GERBANG 0.936 0.156 0.156 0.156 0.156 0.156 0.156
II. PEKERJAAN JALAN DAN RAMP 2.760 0.460 0.460 0.460 0.460 0.460 0.460
30
F PEKERJAAN INTERIOR
20
10
TARGET PRESTASI TIAP MINGGU (%) 100.000 0.237 0.237 1.852 1.852 4.690 3.231 5.443 5.206 1.459 3.591 3.995 6.162 4.703 3.325 3.562 5.500 5.500 5.399 6.252 4.029 5.002 5.202 5.439 5.376 2.000 0.758
JUMLAH KOMULATIF TIAP MINGGU (%) 0.237 0.474 2.326 4.179 8.868 12.099 17.542 22.748 24.206 27.797 31.792 37.954 42.657 45.982 49.543 55.043 60.543 65.942 72.194 76.223 81.225 86.427 91.866 97.242 99.242 100.000
REALISASI PRESTASI DILAPANGAN (%) - 1.691 2.172 6.908 9.232 12.422 17.337 21.299 22.774 31.301 31.799 37.152 41.534 44.827 49.946 55.155 60.655 71.010
DEVIASI CEPAT/LAMBAT +/- (%) (0.237) 1.217 (0.154) 2.729 0.363 0.323 (0.204) (1.448) (1.432) 3.504 0.008 (0.802) (1.123) (1.155) 0.403 0.112 0.113 5.068
( dr. SITI ROBIAH MUBAROKAH ) ( FARIDA, S.K.M ) ( IWAN PURWANTO ) ( DIAN PRIYADI, ST ) ( Hj. MASITOH )
NIP. 197605032006042017 NIP. 196805051993032012 Direktur Team Leader Direktur
0.811 0.811 0.811 0.811
0.156 0.156 0.156 0.156 0.156 0.156
0.460 0.460 0.460 0.460 0.460 0.460
0.200 0.200 0.200 0.200
0.162 0.162 0.162 0.162 0.162
JUMLAH 100 2.059 3.911 3.911 4.286 3.759 3.759 3.759 3.285
TARGET BOBOT PEKERJAAN KUMULATIF ( % ) 2.059 5.969 9.880 14.166 17.925 21.684 25.442 28.727
3.285 3.285 3.926 3.415 3.415 5.247 5.412 5.824 5.824 6.156 6.356 6.356 6.531 3.388 2.852
32.012 35.297 39.223 42.639 46.054 51.301 56.713 62.537 68.361 74.517 80.873 87.230 93.760 97.148 100
BOGOR, 2023
Penawar,
CV. DELTA SATRIA