TIME SCHEDULE

CV. KAIRAWI BANGUN NUSANTARA

PROGRAM : PENGELOLAAN DAN PENGEMBANGAN SISTEM PENYEDIAAN AIR MINUM


PAKET PEKERJAAN : PENGEMBANGAN JARINGAN DISTRIBUSI DAN SAMBUNGAN RUMAH DESA DORAU
LOKASI : DISTRIK KEPULAUAN AMBAI - KABUPATEN KEPULAUAN YAPEN
TAHUN ANGGARAN : 2022

BOBOT JANGKA WAKTU PELAKSANAAN


NO. URAIAN PEKERJAAN APRIL MEI JUNI JULI AGUSTUS SEPTEMBER OKTOBER KET.

% I II III IV V VI VII VIII IX X XI XII XIII XIV XV XVI XVII XVIII XIX XX XXI XXII XXIII XXIV

I. PEMBUATAN INTAKE/PENANGKAP 11.22 2.24417 2.244168 2.244168 2.244168 2.244168 100%

II. PEMBUATAN BAK RESERVOIR KAPS. 23 M3 62.81 4.831176 4.831176 4.831176 4.831176 4.831176 4.831176 4.831176 4.831176 4.831176 4.831176 4.831176 4.831176 4.831176

III. PENGADAAN & PEMASANGAN PIPA Ø 150 MM 8.73 1.746154 1.746154 1.746154 1.746154 1.746154 75%

IV. PENGADAAN & PEMASANGAN PIPA Ø 100 MM 12.96 2.592258 2.592258 2.592258 2.592258 2.592258

50%
V. PENGADAAN & PEMASANGAN ACCESSORIES PIPA 2.03 0.675213 0.675213 0.675213

VI. PENGADAAN DAN PEMASANGAN SAMBUNGAN RUMAH (SR) 0.96 RENCANA 0.96

25%
VII. PEKERJAAN AKHIR
- Pembuatan Laporan, As Built Drawing & Dokumentasi 1.29 1.29

100.00 0%
PERMINGGU 2.24417 2.24417 7.07534 7.07534 7.07534 4.83118 4.83118 4.83118 4.83118 4.83118 4.83118 4.83118 6.57733 6.57733 6.57733 4.33841 4.33841 2.59226 2.59226 3.26747 0.67521 0.67521 0.96397 1.2921915
RENCANA
KOMULATIF 2.24417 4.48834 11.5637 18.639 25.7144 30.5455 35.3767 40.2079 45.0391 49.8703 54.7014 59.5326 66.1099 72.6873 79.2646 83.603 87.9414 90.5337 93.1259 96.3934 97.0686 97.7438 98.7078 100
DEVIASI ( + / - )

CV. KAIRAWI BANGUN NUSANTARA

PAKMOS MAYY
DIREKTUR