TIME SCHEDULE

PROYEK : REHABILITASI REPLACEMENT ( RR ) GUDANG TA. 2016

PEKERJAAN : REHAB JALAN GSP APALA

PERUM BULOG : SUB DIVRE WAJO

LOKASI : KOMPLEK GSP APALA

TAHUN ANGGARAN : 2016

JADWAL WAKTU PELAKSANAAN = 120 HARI KALENDER

NO URAIAN PEKERJAAN BOBOT% BULAN I BULAN II BULAN III BULAN IV KET

1 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
2

I PEKERJAAN PERSIAPAN 0.94 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06

II PEKERJAAN JALAN BETON 83.50 10.44 10.44 10.44 10.44 10.44 10.44 10.44 10.44

III PEKERJAAN CANSTING 10.48 1.31 1.31 1.31 1.31 1.31 1.31 1.31 1.31

IV PEKERJAAN DUIKER 4.54 1.51 1.51 1.51

V PEKERJAAN SERBA-SERBI 0.55 0.27 0.27

Jumlah 100.00

A RENCANA PERMINGGU 0.06 1.37 1.37 1.37 1.37 1.37 11.81 11.81 11.81 10.50 10.50 10.50 12.01 12.01 1.84 0.33

B KOMULATIF RENCANA 0.06 1.43 2.80 4.16 5.53 6.90 18.71 30.51 42.32 52.82 63.31 73.81 85.82 97.82 99.67 100.00

Wajo, 29 Juni 2016


KONTRAKTOR PELAKSANA
PT. RATU ARTA PRIMA

Hj. HASNAWATI SALAHUDDIN


Direktris
REKAPITULASI RAB
BERDASARKAN KLARIFIKASI DAN NEGOSIASI

PROYEK : REHABILITASI REPLACEMENT ( RR ) GUDANG TA. 2016

PEKERJAAN : REHAB JALAN KOMPLEK PERGUDANGAN APALA

PERUM BULOG : SUB DIVRE WAJO

LOKASI : KOMPLEK GSP APALA

TAHUN ANGGARAN : 2016

NO URAIAN PEKERJAAN TOTAL HARGA

I PEKERJAAN PERSIAPAN Rp 9,000,000.00

II PEKERJAAN JALAN BETON Rp 818,209,457.29

III PEKERJAAN CANSTING Rp 142,294,894.74

IV PEKERJAAN DUIKER Rp 31,306,246.52

V PEKERJAAN SERBA-SERBI Rp 3,750.000.00

Jumlah Rp 1,004,560,598.56

REAL COST Rp. 1,004,560,598.56

PPN 10 % Rp. 100,456,059.86

TOTAL Rp. 1,105,016,658.41

DIBULATKAN Rp. 1,105,000,000.00

Terbilang : Satu Milyar Seratus Lima Juta Rupiah

Wajo 13 Juli 2016

PANITIA PENGADAAN BARANG DAN JASA KONTRAKTOR PELAKSANA


SUB DIVRE WAJO PT. RATU ARTA PRIMA

SITRIANINGSIH Hj. HASNAWATI SALAHUDDIN


Ketua Direktris
RENCANA ANGGARAN BIAYA (RAB)

PROYEK : REHABILITASI REPLACEMENT ( RR ) GUDANG TA. 2016


PEKERJAAN : REHAB JALAN KOMPLEK PERGUDANGAN APALA
PERUM BULOG : SUB DIVRE WAJO
LOKASI : KOMPLEK GSP APALA
TAHUN ANGGARAN : 2016

NO URAIAN PEKERJAAN SAT VOLUME KODE HARGA SAT. JML.HARGA TOTAL HARGA

(RP) (RP) (RP)


I PEKERJAAN PERSIAPAN

I.1 PEKERJAAN PERSIAPAN


1 Pek. Persiapan Ls 1.000 - 2,000,000.00 2,000,000.00
2 Pengukuran / pas Bouwplank Ls 1.000 - 3,000,000.00 3,000,000.00
3 Pek. Pembersihan Ls 1.000 - 2,500,000.00 2,500,000.00
5 Dokumentasi, Laporan Ls 1.000 - 1,500,000.00 1,500,000.00
9,000,000.00
II PEKERJAAN JALAN BETON

1 Pekerjaan Pasir Di bawah Lantai Kerja (Tebal =5 cm) m3 155.400 A.1 220,076.37 34,199,867.34
2 Pekerjaan Beton Lantai Kerja K 100 (Tebal =5 cm) m3 155.400 D. 3 929,506.00 144,445,231.95
3 Pekerjaan Jalan Beton K 300 (Tebal = 15 cm) m3 466.200 D.2 1,255,151.12 585,151,449.99
4 Pekerjaan Pembesian Jalan Beton kg 3302.849 D. 4 14,827.78 48,973,908.01
5 Pek. Pasangan Plastik Cor T = 0.4 mm m2 3108.000 - 1,750.00 5,439,000.00
818,209,457.29
III PEKERJAAN CANSTING

III.1 PEKERJAAN CANSTING


1 Pekerjaan Pas.Casting CA
-. Pek. Pembobokan Casting Existing ls 1.000 - 5,000,000.00 5,000,000.00
-. Pekerjaan Beton Casting CA m3 8.895 D. 1 1,111,358.52 9,885,617.36
-. Pekerjaan Pembesian Casting CA kg 452.093 D. 4 14,827.78 6,703,538.24
-. Pekerjaan Pas. Bekisting Casting CA m2 69.466 D. 5 103,952.00 7,221,160.48
-. Pekerjaan Plesteran Casting CA m2 110.130 C.1 54,566.54 6,009,385.58
-. Pek Pipa Pengucur dia 2 inc (Dalam Cansting) jarak 1,5 m m' 20.637 E.1 42,828.75 883,838.67
2 Pekerjaan Pas.Casting CB
-. Pekerjaan Galian Pondasi/Pembongkaran Casting Lama ls 1.000 - 6,500,000.00 6,500,000.00
-. Pekerjaan Pondasi Batu Gunung Casting m3 56.534 B.1 629,091.39 35,564,895.59
-. Pekerjaan Beton Casting CB m3 24.229 D. 1 1,111,358.52 26,926,827.66
-. Pekerjaan Pembesian Casting CB kg 116.000 D. 4 14,827.78 1,720,025.93
-. Pekerjaan Pas. Bekisting Casting CB m2 132.451 D. 5 103,952.00 13,768,493.74
-. Pekerjaan Plesteran Casting CB m2 197.061 C.1 54,566.54 10,752,909.33
-. Pek Pipa Pengucur dia 2 inc (Dalam Cansting) jarak 1,5 m m' 38.874 E.1 42,828.75 1,664,911.27
3 Pekerjaan Acian Casting CA & CB m2 307.190 C.2 31,554.71 9,693,290.89
142,294,894.74
IV PEKERJAAN DUIKER

IV.1 PEKERJAAN PLAT DUIKER


1 Balok Plat Duiker m3 0.960 D.6 5,956,511.48 5,718,251.03
2 Plat Duiker m3 4.272 D.7 5,989,699.32 25,587,995.50
31,306,246.52
V PEKERJAAN SERBA-SERBI

V.1 PEKERJAAN AKHIR


1 Perbaikan Dan Pengangkatan Pintu Pagar Ls 1.000 - 3,500,000.00 2,750,000.00
2 Pembersihan Akhir Ls 1.000 - 2,000,000.00 1,000,000.00
3,750,000.00
A. PEKERJAAN TANAH
A.1 MENGURUG 1 M3 PASIR URUG
Bahan
1.200 M3 Pasir urug @ Rp. 163,396.97 Rp. 196,076.37
Rp. 196,076.37
Tenaga
0.300 org/hr Pekerja @ Rp. 75,000.00 Rp. 22,500.00
0.010 org/hr Mandor @ Rp. 150,000.00 Rp. 1,500.00
Rp. 24,000.00
Total Jumlah Rp. 220,076.37

B. PEKERJAAN PONDASI
B.1 MEMASANG 1 M3 PONDASI BATU BELAH, CAMPURAN 1 PC : 5 PP
Bahan
1.200 M3 Batu Belah 15 cm / 20 cm @ Rp. 142,474.19 Rp. 170,969.03
136.000 Kg Semen Portland @ Rp. 1,170.68 Rp. 159,212.42
0.544 M3 Pasir Pasang @ Rp. 166,884.10 Rp. 90,784.95
Rp. 420,966.39
Tenaga
1.500 org/hr Pekerja @ Rp. 75,000.00 Rp. 112,500.00
0.750 org/hr Tukang Batu @ Rp. 100,000.00 Rp. 75,000.00
0.075 org/hr Kepala Tukang Batu @ Rp. 125,000.00 Rp. 9,375.00
0.075 org/hr Mandor @ Rp. 150,000.00 Rp. 11,250.00
Rp. 208,125.00
Total Jumlah Rp. 629,091.39

C. PEKERJAAN PLESTERAN
C.1 MEMASANG 1 M2 PLESTERAN 1 PC : 3 PP, TEBAL 15 MM
Bahan
7.776 Kg Semen Portland @ Rp. 1,170.68 Rp. 9,103.20
0.023 m3 Pasir Pasang @ Rp. 166,884.10 Rp. 3,838.33
Rp. 12,941.54
Tenaga
0.300 org/hr Pekerja @ Rp. 75,000.00 Rp. 22,500.00
0.150 org/hr Tukang Batu @ Rp. 100,000.00 Rp. 15,000.00
0.015 org/hr Kepala Tukang Batu @ Rp. 125,000.00 Rp. 1,875.00
0.015 org/hr Mandor @ Rp. 150,000.00 Rp. 2,250.00
Rp. 41,625.00
Total Jumlah Rp. 54,566.54

C.2 MEMASANG 1 M2 ACIAN


Bahan
3.250 Kg Semen (PC) @ Rp. 1,170.68 Rp. 3,804.71
Rp. 3,804.71

Tenaga
0.200 org/hr Pekerja @ Rp. 75,000.00 Rp. 15,000.00
0.100 org/hr Tukang Batu @ Rp. 100,000.00 Rp. 10,000.00
0.010 org/hr Kepala Tukang Batu @ Rp. 125,000.00 Rp. 1,250.00
0.010 org/hr Mandor @ Rp. 150,000.00 Rp. 1,500.00
Rp. 27,750.00
Total Jumlah Rp. 31,554.71

D. PEKERJAAN BETON
D. 1 MEMBUAT 1 M3 BETON MUTU F'c =19,3 Mpa (K 225), SLUMP (12 ± 2) CM, W/C = 0,58
Bahan
371.000 Kg PC (Semen Portland) @ Rp. 1,170.68 Rp. 434,322.10
698.000 Kg PB (Pasir Beton) @ Rp. 186.31 Rp. 130,046.06
1047.000 Kg KR (Maksimum 30 mm) @ Rp. 359.67 Rp. 376,577.22
215.000 Liter Air @ Rp. 14.94 Rp. 3,213.14
Rp. 944,158.52

Tenaga
1.650 org/hr Pekerja @ Rp. 75,000.00 Rp. 123,750.00
0.275 org/hr Tukang Batu @ Rp. 100,000.00 Rp. 27,500.00
0.028 org/hr Kepala Tukang Batu @ Rp. 125,000.00 Rp. 3,500.00
0.083 org/hr Mandor @ Rp. 150,000.00 Rp. 12,450.00
Rp. 167,200.00
Total Jumlah Rp. 1,111,358.52
D.2 MEMBUAT 1 M3 BETON MUTU F'c = 26,4 MPa (K 300), SLUMP (12 ± 2) CM, W/c = 0,52
Bahan
413.00 Kg PC (Semen Portland) @ Rp. 1,170.68 Rp. 483,490.64
681.00 Kg PB (Pasir Beton) @ Rp. 186.31 Rp. 126,878.75
1,021.00 Kg KR (Maksimum 30 mm) @ Rp. 359.67 Rp. 367,225.73
215.00 Liter Air @ Rp. 14.94 Rp. 3,213.14
0.14 Ls Alat Bantu Peralatan/mobiler @ Rp. 750,000.00 Rp. 107,142.86
Rp. 1,087,951.12
Tenaga
1.650 org/hr Pekerja @ Rp. 75,000.00 Rp. 123,750.00
0.275 org/hr Tukang Batu @ Rp. 100,000.00 Rp. 27,500.00
0.028 org/hr Kepala Tukang Batu @ Rp. 125,000.00 Rp. 3,500.00
0.083 org/hr Mandor @ Rp. 150,000.00 Rp. 12,450.00
Rp. 167,200.00
Total Jumlah Rp. 1,255,151.12
D. 3 MEMBUAT 1 M3 LANTAI KERJA BETON MUTU F'c = 7,4 MPa (K 100), SLUMP (3 - 6) CM, W/C = 0,87
Bahan
230.000 Kg PC (Semen Portland) @ Rp. 1,170.68 Rp. 269,256.29
893.000 Kg PB (Pasir Beton) @ Rp. 186.31 Rp. 166,376.97
1027.000 Kg KR (Maksimum 30 mm) @ Rp. 359.67 Rp. 369,383.76
200.000 Liter Air @ Rp. 14.94 Rp. 2,988.97
Rp. 808,006.00
Tenaga
1.200 org/hr Pekerja @ Rp. 75,000.00 Rp. 90,000.00
0.200 org/hr Tukang Batu @ Rp. 100,000.00 Rp. 20,000.00
0.020 org/hr Kepala Tukang Batu @ Rp. 125,000.00 Rp. 2,500.00
0.060 org/hr Mandor @ Rp. 150,000.00 Rp. 9,000.00
Rp. 121,500.00
Total Jumlah Rp. 929,506.00
D. 4 PEMBESIAN 10 Kg DENGAN BESI POLOS ATAU BESI ULIR
Bahan
10.500 Kg Besi Beton (Polos Ulir) @ Rp. 12,503.85 Rp. 131,290.46
0.150 Kg Kawat Ikat Beton @ Rp. 22,915.43 Rp. 3,437.31
Rp. 134,727.78
Upah
0.070 org/hr Pekerja @ Rp. 75,000.00 Rp. 5,250.00
0.070 org/hr Tukang Besi @ Rp. 100,000.00 Rp. 7,000.00
0.007 org/hr Kepala Tukang Besi @ Rp. 100,000.00 Rp. 700.00
0.004 org/hr Mandor @ Rp. 150,000.00 Rp. 600.00
Rp. 13,550.00
Total Jumlah 10 Kg Rp. 148,277.78
Total Jumlah 1 Kg Rp. 14,827.78

D. 5 MEMASANG 1 M2 BEKISTING UNTUK CASTING


Bahan
0.045 M3 Kayu Kelas III @ Rp. 2,864,428.63 Rp. 128,899.29
0.300 Kg Paku biasa 5 - 10 cm @ Rp. 19,428.30 Rp. 5,828.49
0.100 Ltr Minyak Bekisting @ Rp. 10,262.13 Rp. 1,026.21
Rp. 135,753.99

Upah tiap M2 Pembuatan Bekisting


0.520 org/hr Pekerja @ Rp. 75,000.00 Rp. 39,000.00
0.260 org/hr Tukang Kayu @ Rp. 100,000.00 Rp. 26,000.00
0.026 org/hr Kepala Tukang Kayu @ Rp. 125,000.00 Rp. 3,250.00
0.026 org/hr Mandor @ Rp. 150,000.00 Rp. 3,900.00
Rp. 72,150.00
Total Jumlah Rp. 207,903.99
PEMAKAIAN 2 KALI Total Jumlah Rp. 103,952.00
D.6 Membuat 1 m3 Balok Beton Bertulang ( 150 kg Besi + Bekisting )
Bahan
0.320 m3 Kayu Kelas III @ Rp. 2,864,428.63 Rp. 916,617.16
3.200 Kg Paku 5 cm - 12 cm @ Rp. 19,428.30 Rp. 62,170.56
1.600 Lt Minyak bekisting @ Rp. 10,262.13 Rp. 16,419.40
157.500 Kg Besi Beton Polos @ Rp. 12,503.85 Rp. 1,969,356.95
3.000 Kg Kawat Beton @ Rp. 22,915.43 Rp. 68,746.29
336.000 Kg PC (Semen Portland) @ Rp. 1,170.68 Rp. 393,348.32
0.540 m3 PB (Pasir Beton) @ Rp. 186,312.40 Rp. 100,608.70
0.810 m3 KR (Maksimum 30 mm) @ Rp. 359,672.60 Rp. 291,334.81
0.140 m3 Kayu Kelas II Balok @ Rp. 4,126,271.70 Rp. 577,678.04
2.800 Lbr Plywood 9 mm @ Rp. 130,020.15 Rp. 364,056.42
16.000 Btg Dolken kayu galam Ø 8-10/4 m @ Rp. 18,631.24 Rp. 298,099.84
Rp. 5,058,436.48
Tenaga
6.350 OH Pekerja @ Rp. 75,000.00 Rp. 476,250.00
0.275 OH Tukang Batu @ Rp. 100,000.00 Rp. 27,500.00
1.650 OH Tukang kayu @ Rp. 100,000.00 Rp. 165,000.00
1.400 OH Tukang besi @ Rp. 100,000.00 Rp. 140,000.00
0.333 OH Kepala Tukang @ Rp. 125,000.00 Rp. 41,625.00
0.318 OH Mandor @ Rp. 150,000.00 Rp. 47,700.00
Rp. 898,075.00
Total Jumlah Rp. 5,956,511.48
D.7 MEMBUAT 1 M3 PLAT LANTAI BETON BERTULANG (150 KG BESI + BEKESTING)
Bahan
0.320 m3 Kayu Kelas III @ Rp. 2,864,428.63 Rp. 916,617.16
3.200 Kg Paku 5 cm - 12 cm @ Rp. 19,428.30 Rp. 62,170.56
1.600 Lt Minyak bekisting @ Rp. 10,262.13 Rp. 16,419.40
157.500 Kg Besi Beton Polos @ Rp. 12,503.85 Rp. 1,969,356.95
2.250 Kg Kawat Beton @ Rp. 22,915.43 Rp. 51,559.72
336.000 Kg PC (Semen Portland) @ Rp. 1,170.68 Rp. 393,348.32
0.540 m3 PB (Pasir Beton) @ Rp. 186,312.40 Rp. 100,608.70
0.810 m3 KR (Maksimum 30 mm) @ Rp. 359,672.60 Rp. 291,334.81
0.120 m3 Kayu Kelas II Balok @ Rp. 4,126,271.70 Rp. 495,152.60
2.800 Lbr Plywood 9 mm @ Rp. 130,020.15 Rp. 364,056.42
32.000 Btg Dolken kayu galam Ø 8-10/4 m @ Rp. 18,631.24 Rp. 596,199.68
Rp. 5,256,824.32
Tenaga
5.300 OH Pekerja @ Rp. 75,000.00 Rp. 397,500.00
0.275 OH Tukang Batu @ Rp. 100,000.00 Rp. 27,500.00
1.300 OH Tukang kayu @ Rp. 100,000.00 Rp. 130,000.00
1.050 OH Tukang besi @ Rp. 100,000.00 Rp. 105,000.00
0.265 OH Kepala Tukang @ Rp. 125,000.00 Rp. 33,125.00
0.265 OH Mandor @ Rp. 150,000.00 Rp. 39,750.00
Rp. 732,875.00
Total Jumlah Rp. 5,989,699.32

E. PEKERJAAN SANITASI
E.1 MEMASANG 1 M' PIPA PVC TIPE AW DIAMETER 2''
Bahan
1.200 m' Pipa PVC @ Rp. 18,225.00 Rp. 21,870.00
0.350 35% HBPerlengkapan @ Rp. 18,225.00 Rp. 6,378.75
Rp. 28,248.75
Upah
0.054 org/hr Pekerja @ Rp. 75,000.00 Rp. 4,050.00
0.090 org/hr Tukang Batu @ Rp. 100,000.00 Rp. 9,000.00
0.009 org/hr Kepala Tukang Batu @ Rp. 125,000.00 Rp. 1,125.00
0.0027 org/hr Mandor @ Rp. 150,000.00 Rp. 405.00
Rp. 14,580.00
Rp. 42,828.75
A. DAFTAR HARGA BAHAN BANGUNAN

NO JENIS BAHAN BANGUNAN SATUAN HARGA

1 2 3 4
A BAHAN DASAR
1 Batu
- Batu belah 15 /20 cm m3 @ Rp 142,474.19
- Krikil 0.5 - 2 cm m3 @ Rp 359,672.60
- Krikil 0.5 - 2 cm kg @ Rp 359.67
2 Pasir dan Tanah
- Pasir Beton m3 @ Rp 186,312.40
- Pasir Beton kg @ Rp 186.31
- Pasir Pasangan m3 @ Rp 166,884.10
- Pasir Urug m3 @ Rp 163,396.97
-Air Liter @ Rp 14.94
3 Semen Portland
Semen 50 Kg (Tonasa) P.C Zak @ Rp 58,533.98
Semen 50 Kg (Tonasa) P.C Kg @ Rp 1,170.68

B BAHAN BESI
1 Besi Beton Biasa U.24 Dia. 08 - 19 mm Kg @ Rp 12,503.85
2 Paku biasa 5 - 12 cm Kg @ Rp 19,428.30
4 Kawat Ikat Beton Kg @ Rp 22,915.43

C BAHAN KAYU
3 Kayu Kls.II (Balok) M3 @ Rp 4,126,271.70
4 Kayu Kls.III (Papan) M3 @ Rp 2,864,428.63
5 Dolken Kayu M' @ Rp 18,631.24

D BAHAN FINISHING
7 minyak bekesting Ltr @ Rp 10,262.13
16 Plastik Cor m2 @ Rp 1,750.00
E BAHAN PERPIPAAN
3 Pipa PVC dia. 2 Inch - 4 m Maspion m' @ Rp 18,225.00
F BAHAN LANGIT-LANGIT/ ATAP
2 Pliwood 9 mm Lbr @ Rp 130,020.15
B. DAFTAR HARGA UPAH KERJA
NO U R A I A N SATUAN HARGA

Pekerja Org / Hari @ Rp 75,000.00


TUKANG
Tukang Kayu Org / Hari @ Rp 100,000.00
Tukang Batu Org / Hari @ Rp 100,000.00
Tukang Cat Org / Hari @ Rp 100,000.00
Tukang Listrik Org / Hari @ Rp 100,000.00
Tukang Pipa Org / Hari @ Rp 100,000.00
Tukang Besi Org / Hari @ Rp 100,000.00
KEPALA TUKANG
Kepala Tukang Kayu Org / Hari @ Rp 125,000.00
Kepala Tukang Batu Org / Hari @ Rp 125,000.00
Kepala Tukang Listrik Org / Hari @ Rp 125,000.00
Kepala Tukang Cat Org / Hari @ Rp 125,000.00
Kepala Tukang Pipa Org / Hari @ Rp 125,000.00
Kepala Tukang Besi Org / Hari @ Rp 125,000.00
Mandor Org / Hari @ Rp 150,000.00