Anda di halaman 1dari 45

JADWAL PELAKSANAAN

REHABILITASI SEDANG/BERAT PENDOPO I


TAHUN ANGGARAN 2022

KEGIATAN : PENYELENGGARAAN BANGUNAN GEDUNG DI WILAY


BANGUNAN (IMB) DAN SERTIFIKAT LAIK FUNGSI
PEKERJAAN : REHABILITASI SEDANG/BERAT PENDOPO I

LOKASI : KABUPATEN BANGKAL

MINGGU KE
NO. URAIAN KEGIATAN JUMLAH HARGA + PPn BOBOT
I II III IV V VI VII VIII IX X XI XII XIII XIV XV XVI XVII

A. PEKERJAAN PERSIAPAN Rp 15,589,905.60 1.962 0.98 0.98

B. I. PEKERJAAN TANAH Rp 6,483,676.50 0.816 0.82

II. PEKERJAAN PONDASI Rp 14,896,000.20 1.874 1.87

III. PEKERJAAN STRUKTUR Rp 639,759,454.59 80.501 4.03 8.05 8.05 8.05 8.05 8.05 8.05 8.05 8.05 8.05 4.03

IV. PEKERJAAN DINDING Rp 7,811,780.40 0.983 0.49 0.49

V. PEKERJAAN PLAFOND Rp 85,164,861.00 10.716 3.57 3.57 3.57

VI. PEKERJAAN LANTAI Rp 15,584,000.40 1.961 0.65 0.65 0.65

VII. PEKERJAAN PENGECATAN Rp 9,431,092.80 1.187 0.59 0.59

JUMLAH TOTAL 794,720,771.49 100 0.98 1.80 5.90 8.05 8.05 8.05 8.05 8.54 8.54 8.05 8.05 8.05 7.60 4.23 4.23 1.25 0.59

- 0.98 2.78 8.68 16.73 24.78 32.83 40.88 49.42 57.96 66.01 74.06 82.11 89.71 93.93 98.16 99.41 100.00

Bangkalan, 30 Mei 2022

CV. SAHARA

FATHORRACHMAN
Direktur

Page 1
Page 2
REKAPITULASI RENCANA ANGGARAN BIAYA
REHABILITASI SEDANG/BERAT PENDOPO I
TAHUN ANGGARAN 2022

KEGIATAN : PENYELENGGARAAN BANGUNAN GEDUNG DI WILAYAH KABUPATEN / KOTA, PEMBERIAN IZIN MENDIRIKAN
BANGUNAN (IMB) DAN SERTIFIKAT LAIK FUNGSI BANGUNAN GEDUNG
PEKERJAAN : REHABILITASI SEDANG/BERAT PENDOPO I

LOKASI : KABUPATEN BANGKALAN

NO. URAIAN KEGIATAN JUMLAH HARGA + PPn

A. PEKERJAAN PERSIAPAN Rp 15,589,905.60

B. PEKERJAAN KONSTRUKSI BANGUNAN UTAMA Rp 779,130,865.89


I. PEKERJAAN TANAH Rp 6,483,676.50
II. PEKERJAAN PONDASI Rp 14,896,000.20
III. PEKERJAAN STRUKTUR Rp 639,759,454.59
IV. PEKERJAAN DINDING Rp 7,811,780.40
V. PEKERJAAN PLAFOND Rp 85,164,861.00
VI. PEKERJAAN LANTAI Rp 15,584,000.40
VII. PEKERJAAN PENGECATAN Rp 9,431,092.80

JUMLAH TOTAL Rp 794,720,771.49

JUMLAH TOTAL DIBULATKAN Rp 794,720,000.00

Terbilang : Tujuh Ratus Sembilan puluh Empat Juta Tujuh ratus Dua puluh ribu rupiah

###

Bangkalan, 30 Mei 2022

CV. SAHARA

FATHORRACHMAN
Direktur

Page 3
RENCANA ANGGARAN BIAYA

KEGIATAN : PENYELENGGARAAN BANGUNAN GEDUNG DI WILAYAH KABUPATEN / KOTA, PEMBERIAN IZIN MENDIRIKAN

BANGUNAN (IMB) DAN SERTIFIKAT LAIK FUNGSI BANGUNAN GEDUNG

PEKERJAAN : REHABILITASI SEDANG/BERAT PENDOPO I

LOKASI : KABUPATEN BANGKALAN

NO JENIS PEKERJAAN VOLUME SAT HARGA SATUAN JUMLAH PPn (11%) JUMLAH + PPn

1 2 3 4 5 6 7 8

A. PEKERJAAN PERSIAPAN
1 Pek. Pembongkaran Atap & Plafond bangunan existing 274.54 m² Rp 28,000.00 Rp 7,687,120.00 Rp 845,583.20 Rp 8,532,703.20
2 Pek. Pembongkaran Dinding 0.54 m³ Rp 246,000.00 Rp 132,840.00 Rp 14,612.40 Rp 147,452.40
3 Pek. Pembersihan lokasi 285.00 m² Rp 11,000.00 Rp 3,135,000.00 Rp 344,850.00 Rp 3,479,850.00
4 Penyediaan K3
Pembuatan Manual, Prosedur, Instruksi Kerja, Ijin Kerja Dan 1.00 Set Rp 250,000.00 Rp 250,000.00 Rp 27,500.00 Rp 277,500.00
Pembuatan Kartu Identitas Kerja (KIP) 6.00 Lbr Rp 5,000.00 Rp 30,000.00 Rp 3,300.00 Rp 33,300.00
Helm Pelindung (safety helmet) 6.00 Bh Rp 50,000.00 Rp 300,000.00 Rp 33,000.00 Rp 333,000.00
Masker 6.00 Bh Rp 5,000.00 Rp 30,000.00 Rp 3,300.00 Rp 33,300.00
Sepatu Keselamatan (Safety Shoes), Karet 6.00 Psg Rp 100,000.00 Rp 600,000.00 Rp 66,000.00 Rp 666,000.00
Rompi Keselamatan (Safety Vest) 6.00 Bh Rp 30,000.00 Rp 180,000.00 Rp 19,800.00 Rp 199,800.00
BPJS Ketenagakerjaan Dan Kesehatan Kerja 1.00 Ls Rp 1,400,000.00 Rp 1,400,000.00 Rp 154,000.00 Rp 1,554,000.00
Peralatan P3K (Kotak P3K, Obat Luka, Perban,dll) 1.00 ls Rp 300,000.00 Rp 300,000.00 Rp 33,000.00 Rp 333,000.00
Rp 15,589,905.60
B. PEKERJAAN KONTRUKSI
PEKERJAAN LANTAI I
I. PEKERJAAN TANAH
1 Pek. Galian Tanah Strous 48.00 m1 Rp 78,000.00 Rp 3,744,000.00 Rp 411,840.00 Rp 4,155,840.00
2 Pek. Galian Tanah Pondasi 10.23 m³ Rp 83,000.00 Rp 849,090.00 Rp 93,399.90 Rp 942,489.90
3 Pek. Urugan Pasir bawah Pondasi 3.66 m³ Rp 341,000.00 Rp 1,248,060.00 Rp 137,286.60 Rp 1,385,346.60
Rp 6,483,676.50
II. PEKERJAAN PONDASI
1 Pek. Rabatan beton 5 cm bawah Pondasi 0.39 m³ Rp 1,062,000.00 Rp 414,180.00 Rp 45,559.80 Rp 459,739.80
2 Pek. Beton Strous Ø 30cm
Pek. Pembesian - Tul 5 - Ø13mm, Beugel Ø8 - 150mm 239.76 kg Rp 16,000.00 Rp 3,836,160.00 Rp 421,977.60 Rp 4,258,137.60
Pek. Pengecoran, Beton K-225 3.39 m³ Rp 1,318,000.00 Rp 4,468,020.00 Rp 491,482.20 Rp 4,959,502.20
3 Pek. Beton Pile Cap 80.80.30
Pek. Pembesian - besi Ø13mm - 150mm 83.16 kg Rp 16,000.00 Rp 1,330,560.00 Rp 146,361.60 Rp 1,476,921.60
Pek. Pengecoran, Beton K-250 1.38 m³ Rp 1,339,000.00 Rp 1,847,820.00 Rp 203,260.20 Rp 2,051,080.20
Pek. Bekesting Plat pondasi 2 x pakai 1.72 m² Rp 106,000.00 Rp 182,320.00 Rp 20,055.20 Rp 202,375.20

4 Pek. Beton Pile Cap 60.60.30


Pek. Pembesian - besi Ø13mm - 150mm 43.45 kg Rp 16,000.00 Rp 695,200.00 Rp 76,472.00 Rp 771,672.00
Pek. Pengecoran, Beton K-250 0.38 m³ Rp 1,339,000.00 Rp 508,820.00 Rp 55,970.20 Rp 564,790.20
Pek. Bekesting Plat pondasi 2 x pakai 1.29 m² Rp 106,000.00 Rp 136,740.00 Rp 15,041.40 Rp 151,781.40
Rp 14,896,000.20
III. PEKERJAAN STRUKTUR
1 Pek. Sloop S1 15/25
Pek. Pembesian - Tul 5 - Ø13mm, Beugel Ø8 - 150mm 104.18 kg Rp 16,000.00 Rp 1,666,880.00 Rp 183,356.80 Rp 1,850,236.80
Pek. Pengecoran, Beton K-250 0.60 m³ Rp 1,339,000.00 Rp 803,400.00 Rp 88,374.00 Rp 891,774.00
Pek. Bekesting Kolom 2 x Pakai 19.20 m² Rp 252,000.00 Rp 4,838,400.00 Rp 532,224.00 Rp 5,370,624.00
2 Pek. Beton Kolom K1 30/30
Pek. Pembesian - Tul 8 - Ø16mm, Beugel Ø8 - 150mm 723.98 kg Rp 16,000.00 Rp 11,583,680.00 Rp 1,274,204.80 Rp 12,857,884.80
Pek. Pengecoran, Beton K-250 4.45 m³ Rp 1,339,000.00 Rp 5,958,550.00 Rp 655,440.50 Rp 6,613,990.50
Pek. Bekesting Kolom 2 x Pakai 39.60 m² Rp 252,000.00 Rp 9,979,200.00 Rp 1,097,712.00 Rp 11,076,912.00
3 Pek. Beton Kolom K2 25/25
Pek. Pembesian - Tul 6 - Ø13mm, Beugel Ø8 - 150mm 131.62 kg Rp 16,000.00 Rp 2,105,920.00 Rp 231,651.20 Rp 2,337,571.20
Pek. Pengecoran, Beton K-250 1.03 m³ Rp 1,339,000.00 Rp 1,379,170.00 Rp 151,708.70 Rp 1,530,878.70
Pek. Bekesting Kolom 2 x Pakai 16.50 m² Rp 252,000.00 Rp 4,158,000.00 Rp 457,380.00 Rp 4,615,380.00
4 Pek. Beton Kolom K2 15/20
Pek. Pembesian - Tul 4 - Ø13mm, Beugel Ø8 - 150mm 87.10 kg Rp 16,000.00 Rp 1,393,600.00 Rp 153,296.00 Rp 1,546,896.00
Pek.Pengecoran, Beton K-250 0.49 m³ Rp 1,339,000.00 Rp 656,110.00 Rp 72,172.10 Rp 728,282.10
Pek. Bekesting Kolom 2 x Pakai 11.55 m² Rp 252,000.00 Rp 2,910,600.00 Rp 320,166.00 Rp 3,230,766.00
5 Pek. Balok Baja Profil WF 350.175.7.11
Balok Profil WF 350.175.7.11 4,190.20 kg Rp 39,700.00 Rp 166,350,940.00 Rp 18,298,603.40 Rp 184,649,543.40
Plat Stifner & Lekat 10mm 348.86 kg Rp 39,700.00 Rp 13,849,742.00 Rp 1,523,471.62 Rp 15,373,213.62
Baut Angkur M19 - 150mm 112.00 bh Rp 35,000.00 Rp 3,920,000.00 Rp 431,200.00 Rp 4,351,200.00
Baut M19 - 40mm 32.00 bh Rp 10,000.00 Rp 320,000.00 Rp 35,200.00 Rp 355,200.00
6 Pek. Balok Baja Profil WF 250.125.6.9
Balok Profil WF 250.100.5,5.8 1,929.50 kg Rp 39,700.00 Rp 76,601,150.00 Rp 8,426,126.50 Rp 85,027,276.50
Plat Stifner & Lekat 8mm 340.05 kg Rp 39,700.00 Rp 13,499,985.00 Rp 1,484,998.35 Rp 14,984,983.35
Baut M16 - 40mm 240.00 bh Rp 8,000.00 Rp 1,920,000.00 Rp 211,200.00 Rp 2,131,200.00
7 Pek. Balok Baja Profil WF 200.100.5,5.8
Balok Profil WF 200.100.5,5.8 (bekas bongkaran) 1,649.85 kg Rp 8,200.00 Rp 13,528,770.00 Rp 1,488,164.70 Rp 15,016,934.70
Plat Stifner 5mm & Lekat 8mm 139.35 kg Rp 39,700.00 Rp 5,532,195.00 Rp 608,541.45 Rp 6,140,736.45
Plat Siku 50.50.5 489.72 kg Rp 39,700.00 Rp 19,441,884.00 Rp 2,138,607.24 Rp 21,580,491.24
8 Pek. Balok CNP 2 x 150.35.1,8
Balok Profil CNP 150.35.1,8 (bekas bongkaran) 986.96 kg Rp 8,200.00 Rp 8,093,072.00 Rp 890,237.92 Rp 8,983,309.92

Page 4
NO JENIS PEKERJAAN VOLUME SAT HARGA SATUAN JUMLAH PPn (11%) JUMLAH + PPn

1 2 3 4 5 6 7 8
9 Pek. Beton Plat Lantai AAC
Pek. Panel Lantai AAC, t = 12,5 cm 41.34 m³ Rp 4,215,000.00 Rp 174,248,100.00 Rp 19,167,291.00 Rp 193,415,391.00
10 Pek. Konstruksi Tangga
Balok Profil WF 200.100.5,5.8 464.34 kg Rp 39,700.00 Rp 18,434,298.00 Rp 2,027,772.78 Rp 20,462,070.78
Plat Siku 50.50.5 318.94 kg Rp 39,700.00 Rp 12,661,918.00 Rp 1,392,810.98 Rp 14,054,728.98
Plat Lekat 8mm 5.65 m³ Rp 39,700.00 Rp 224,305.00 Rp 24,673.55 Rp 248,978.55
Baut Angkur M16 - 125mm 12.00 bh Rp 25,000.00 Rp 300,000.00 Rp 33,000.00 Rp 333,000.00
Rp 639,759,454.59
IV. PEKERJAAN DINDING
1 Pek. Dinding bata putih, 1 Pc : 6 Ps 12.60 m² Rp 113,000.00 Rp 1,423,800.00 Rp 156,618.00 Rp 1,580,418.00
2 Pek. Plesteran, 1 Pc : 6 Ps 25.20 m² Rp 95,000.00 Rp 2,394,000.00 Rp 263,340.00 Rp 2,657,340.00
3 Pek. Acian dinding & Kolom 74.88 m² Rp 43,000.00 Rp 3,219,840.00 Rp 354,182.40 Rp 3,574,022.40
Rp 7,811,780.40
V. PEKERJAAN PLAFOND
1 Pasang Plafond Gypsumboard 9mm + rangka metal hollow 304.90 m² Rp 134,000.00 Rp 40,856,600.00 Rp 4,494,226.00 Rp 45,350,826.00
2 Pasang Plafond PVC + rangka metal hollow (Eksterior) 89.80 m² Rp 370,000.00 Rp 33,226,000.00 Rp 3,654,860.00 Rp 36,880,860.00
3 Pasang Kembali Peredam Plafond (R. Musik) 105.70 m² Rp 25,000.00 Rp 2,642,500.00 Rp 290,675.00 Rp 2,933,175.00
Rp 85,164,861.00
VI. PEKERJAAN LANTAI
1 Pek. Rabatan beton t = 5cm, Screeding beton 13.22 m² Rp 1,062,000.00 Rp 14,039,640.00 Rp 1,544,360.40 Rp 15,584,000.40
Rp 15,584,000.40
VII. PEKERJAAN PENGECATAN
1 Pengecatan Dinding & Lisplank 74.88 m² Rp 31,000.00 Rp 2,321,280.00 Rp 255,340.80 Rp 2,576,620.80
2 Pengecatan Plafond 199.20 m² Rp 31,000.00 Rp 6,175,200.00 Rp 679,272.00 Rp 6,854,472.00
Rp 9,431,092.80

Page 5
PERHITUNGAN BIAYA SMK3

KEGIATAN : PENYELENGGARAAN BANGUNAN GEDUNG DI WILAYAH KABUPATEN / KOTA, PEMBERIAN IZIN MENDIRIKAN
0 BANGUNAN (IMB) DAN SERTIFIKAT LAIK FUNGSI BANGUNAN GEDUNG
PEKERJAAN : REHABILITASI SEDANG/BERAT PENDOPO I
LOKASI : KABUPATEN BANGKALAN
NILAI PEKERJAAN : Rp 794,720,771.49

NO JENIS PEKERJAAN SAT VOLUME WAKTU HARGA SATUAN JUMLAH

1 2 3 4 5 6 7

1 Penyiapan RK3 terdiri atas :


a Pembuatan Manual, Prosedur, Instruksi Kerja, Ijin Kerja Dan Set 1.00 1 Rp 250,000.00 Rp 250,000.00
b Pembuatan Kartu Identitas Kerja (KIP) Lbr 6.00 1 Rp 5,000.00 Rp 30,000.00
Rp 280,000.00
2 Alat Pelindung Diri, terdiri Atas :
a Helm Pelindung (safety helmet) Bh 6.00 1 Rp 50,000.00 Rp 300,000.00
b Masker Bh 6.00 1 Rp 5,000.00 Rp 30,000.00
c Sepatu Keselamatan (Safety Shoes), Karet Psg 6.00 1 Rp 100,000.00 Rp 600,000.00
d Rompi Keselamatan (Safety Vest) Bh 6.00 1 Rp 30,000.00 Rp 180,000.00
Rp 1,110,000.00
3 Asuransi & Perijinan, terdiri Atas :
a BPJS Ketenagakerjaan Dan Kesehatan Kerja Ls 1.00 1 Rp 1,400,000.00 Rp 1,400,000.00
Rp 1,400,000.00
4 Fasilitas Sarana Kesehatan, terdiri Atas :
a Peralatan P3K (Kotak P3K, Obat Luka, Perban,dll) ls 1.00 1 Rp 300,000.00 Rp 300,000.00
Rp 300,000.00

Jumlah Total Rp 3,090,000.00

Page 6
HARGA SATUAN BAHAN & UPAH KERJA

###
NO. NAMA BAHAN SAT KET
HARGA RATA
I. BAHAN PASIR HARGA DASAR
###
1 Pasir Pasang ( Jawa ) M³ 250,000.00
###
2 Pasir Cor ( Jawa ) M³ 300,000.00
###
###
II. BAHAN KORAL/KERIKIL ###
###
1 Batu Pecah Mesin 2/3 ( Jawa ) M³ 350,000.00
###
###
III. BAHAN BATU BATA ###
###
1 Batu Putih ( Lokal ) Bh 600.00
###
2 Panel Lantai Beton AAC, T = 12,5 cm M³ 2,400,000.00
###
###
IV. PORTLAND CEMENT ( PC ) ###
###
1 Semen Gresik 40 Kg Zak 58,000.00
###
2 Semen Grouting Panel Lantai AAC 40kg Zak 95,000.00
###
3 Semen Perekat Panel Lantai AAC 40kg Zak 110,000.00
###
###
V. BAHAN BESI ###
###
1 Besi Beton Polos (ex.Hanil / setara) Kg 11,800.00
###
2 Kawat Beton / Kawat Bendrat Kg 20,000.00
###
3 Baut Baja + Mur Baja HTB M16 x 40mm bh 8,000.00
4 Baut Baja + Mur Baja HTB M19 x 40mm bh 10,000.00
5 Angkur Baut Baja + Mur Baja M19 x 150mm bh 35,000.00
###
6 Angkur Baut Baja + Mur Baja M16 x 125mm bh 25,000.00
7 Baja Konstruksi / Profil (ex. Gunung Garuda atau setara ) Kg 16,000.00
###
8 Hollow Galvalum 20.40.0,4 x 4m (ex. Aplus) Btg 36,000.00
9 Hollow Galvalum 40.40.0,4 x 4m (ex. Aplus) Btg 48,000.00
10 Wall angle M' 3,500.00
11 Kasa + Compound M² 20,000.00
###
VI. BAHAN KAYU ###
###
1 Kayu Balok / Papan Begesting (klas III) M³ 2,400,000.00
###
2 Kayu Dolken Btg 40,000.00
###
3 Kayu Meranti Balok 3/15, 8/12, 6/12 Klas II M³ 6,500,000.00
###
###
VII. BAHAN ASBES DATAR/GELOMBANG ###
###
1 Gypsum Board 1,22 x 2,44 cm Tebal 9mm Lbr 65,000.00
###
2 WPC Ceilling Board 500 x 9,5 cm ,ex. Duma Lbr ###
110,000.00
###
VIII. BAHAN CAT ###
###
1 Cat Dinding Eksterior ex. Nippon paint 20 Ltr 1,600,000.00
###
2 Cat Dasar Alkali Eksteror ex Nippon paint 20 Ltr 620,000.00
###
3 Amplas Lbr 10,000.00
###
###
IX. BAHAN TRIPLEK / KAYU LAPIS ###
###
1 Multiplek 1,22 x 2,44 x 9 mm Lbr 165,000.00
###
###
X. BAHAN PAKU ###
###
1 Paku Usuk Kg 18,000.00
###
2 Fasting Nails ( Scrup ) Bh 150.00
###
###
XI. BAHAN LAIN-LAIN ###
###
1 Minyak Begisting Ltr 3,500.00
###
2 Minyak Pelumas / Oli Ltr 40,000.00
###
3 Bio Solar Ltr 5,150.00
###
4 Sewa Bor Strous Ø 30cm hr 35,000.00
5 Kawat Listrik Kg 40,000.00
6 Sewa Alat Bantu Erection Jam 150,000.00
7 Alat Las istrik Jam 65,000.00
###

Page 7
NO. NAMA BAHAN SAT KET

XII. UPAH KERJA ###


###
1 Mandor Hari 140,000.00
###
2 Kepala Tukang Gali Tanah Hari 130,000.00
###
3 Kepala Tukang Batu Hari 130,000.00
###
4 Kepala Tukang Kayu Hari 130,000.00
###
5 Kepala Tukang Besi Hari 130,000.00
###
6 Kepala Tukang Cat Hari 130,000.00
###
7 Kepala Tukang Listrik Hari 130,000.00
###
8 Tukang Gali Tanah Hari 120,000.00
###
9 Tukang Batu Hari 120,000.00
###
10 Tukang Kayu Hari 120,000.00
###
11 Tukang Besi Hari 120,000.00
###
12 Tukang Cat / Plitur Hari 120,000.00
###
13 Tukang Listrik Hari 120,000.00
###
14 Tukang Pipa Hari 120,000.00
###
15 Pembantu Tukang Plitur / Pekerja Hari 95,000.00
###
16 Pembantu Tukang Batu / Pekerja Hari 95,000.00
###
17 Pembantu Tukang Kayu / Pekerja Hari 95,000.00
###
18 Pembantu Tukang Cat / Pekerja Hari 95,000.00
###
19 Pembantu Tukang Besi / Pekerja Hari 95,000.00
###
20 Pembantu Tukang Listrik / Pekerja Hari 95,000.00
###
###

Page 8
ANALISA HARGA SATUAN PEKERJAAN

A. HARGA SATUAN PEKERJAAN PERSIAPAN


1. Pembersihan 1 M2 Lapangan dan Perataan
No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.100 95,000.00 9,500.00
Mandor L.04 OH 0.005 140,000.00 700.00
JUMLAH TENAGA KERJA 10,200.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 10,200.00
E Overhead & Profit (mak. 15%) 0.12 x D 1,224.00
F Harga Satuan Pekerjaan (D+E) 11,424.00
Pembulatan 11,000.00
2. Pembongkaran 1 M2 Atap (Penurunan Genting, Pembongkaran Konstruksi atap, berikut Plafond)
No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.167 95,000.00 15,834.13
Mandor L.04 OH 0.067 140,000.00 9,332.40
JUMLAH TENAGA KERJA 25,166.53
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 25,166.53
E Overhead & Profit (mak. 15%) 0.12 x D 3,019.98
F Harga Satuan Pekerjaan (D+E) 28,186.51
Pembulatan 28,000.00
3. Pembongkaran 1 M3 Dinding Bata
No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.333 95,000.00 126,673.00
Mandor L.04 OH 0.667 140,000.00 93,324.00
JUMLAH TENAGA KERJA 219,997.00
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 219,997.00
E Overhead & Profit (mak. 15%) 0.12 x D 26,399.64
F Harga Satuan Pekerjaan (D+E) 246,396.64
Pembulatan 246,000.00

B. HARGA SATUAN PEKERJAAN TANAH


1. Penggalian 1 m³ tanah biasa sedalam 1 m
No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.75 95,000.00 71,250.00
Mandor L.04 OH 0.03 140,000.00 3,500.00
JUMLAH TENAGA KERJA 74,750.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 74,750.00


E Overhead & Profit (mak. 15%) 0.12 x D 8,970.00
F Harga Satuan Pekerjaan (D+E) 83,720.00
Pembulatan 83,000.00
2. Pengeboran Strousz dia. 30cm, 1 M'
No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.20 95,000.00 19,000.00
Mandor L.04 OH 0.30 140,000.00 42,000.00
JUMLAH TENAGA KERJA 61,000.00

Page 9
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN
Sewa Bor Strous 0.25 35,000.00 8,750.00
JUMLAH HARGA ALAT 8,750.00

D Jumlah (A+B+C) 69,750.00


E Jumlah (A+B+C) 0.12 x D 8,370.00
F Harga Satuan Pekerjaan (D+E) 78,120.00
Pembulatan 78,000.00
3. Pengurugan 1 m³ dengan Pasir
No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.300 95,000.00 28,500.00
Mandor L.04 OH 0.010 140,000.00 1,400.00
JUMLAH TENAGA KERJA 29,900.00
B BAHAN
Pasir Pasang ( Jawa ) 1.100 250,000.00 275,000.00
JUMLAH HARGA BAHAN 275,000.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 304,900.00


E Overhead & Profit (mak. 15%) 0.12 x D 36,588.00
F Harga Satuan Pekerjaan (D+E) 341,488.00
Pembulatan 341,000.00

C. HARGA SATUAN PEKERJAAN PASANGAN DINDING


1. Pemasangan 1 m2 dinding bata putih tebal 1/2 bata dengan campuran 1Pc : 6 Ps
No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.300 95,000.00 28,500.00
Tukang L.02 OH 0.100 120,000.00 12,000.00
Kepala Tukang L.03 OH 0.010 130,000.00 1,300.00
Mandor L.04 OH 0.015 140,000.00 2,100.00
JUMLAH TENAGA KERJA 43,900.00
B BAHAN
Bata Putih bh 55.00 600.00 33,000.00
Semen porland kg 8.320 1,450.00 12,064.00
Pasir pasang m3 0.049 250,000.00 12,250.00
JUMLAH HARGA BAHAN 57,314.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 101,214.00


E Overhead & Profit (mak. 15%) 0.12 x D 12,145.68
F Harga Satuan Pekerjaan (D+E) 113,359.68
Pembulatan 113,000.00

D. HARGA SATUAN PEKERJAAN PLESTERAN


1. Plesteran dinding 1 m2 dengan Campuran 1Pc : 6 Ps
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.400 95,000.00 38,000.00
Tukang L.02 OH 0.200 120,000.00 24,000.00
Kepala Tukang L.03 OH 0.020 130,000.00 2,600.00
Mandor L.04 OH 0.022 140,000.00 3,080.00
JUMLAH TENAGA KERJA 67,680.00
B BAHAN
Semen Portland (ex. Gresik) Kg 5.888 1,450.00 8,537.60
Pasir Pasang m3 0.036 250,000.00 9,000.00
JUMLAH HARGA BAHAN 17,537.60
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 85,217.60


E Overhead & Profit (mak. 15%) 0.12 x D 10,226.11
F Harga Satuan Pekerjaan (D+E) 95,443.71
Pembulatan 95,000.00

Page 10
2. Acian plesteran 1 m2 dengan PC
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.200 95,000.00 19,000.00
Tukang L.02 OH 0.100 120,000.00 12,000.00
Kepala Tukang L.03 OH 0.010 130,000.00 1,300.00
Mandor L.04 OH 0.010 140,000.00 1,400.00
JUMLAH TENAGA KERJA 33,700.00
B BAHAN
Semen Gresik 40 Kg Kg 3.250 1,450.00 4,712.50
JUMLAH HARGA BAHAN 4,712.50
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 38,412.50


E Overhead & Profit (mak. 15%) 0.12 x D 4,609.50
F Harga Satuan Pekerjaan (D+E) 43,022.00
Pembulatan 43,000.00

E. HARGA SATUAN PEKERJAAN BETON


1. Membuat 1 m³ beton mutu (K 225)
No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.650 95,000.00 156,750.00
Tukang L.02 OH 0.250 120,000.00 30,000.00
Kepala Tukang L.03 OH 0.025 130,000.00 3,250.00
Mandor L.04 OH 0.080 140,000.00 11,200.00
JUMLAH TENAGA KERJA 201,200.00
B BAHAN
Semen Portland (ex. Gresik) Kg 371.000 1,450.00 537,950.00
Pasir Beton m3 0.499 300,000.00 149,571.43
Kerikil (Maks 30mm) m3 0.776 350,000.00 271,444.44
Air Liter 215.000 80.00 17,200.00
JUMLAH HARGA BAHAN 976,165.87
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,177,365.87


E Overhead & Profit (mak. 15%) 0.12 x D 141,283.90
F Harga Satuan Pekerjaan (D+E) 1,318,649.78
Pembulatan 1,318,000.00
2. Membuat 1 m³ beton mutu (K 250)
No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.650 95,000.00 156,750.00
Tukang L.02 OH 0.275 120,000.00 33,000.00
Kepala Tukang L.03 OH 0.028 130,000.00 3,640.00
Mandor L.04 OH 0.083 140,000.00 11,620.00
JUMLAH TENAGA KERJA 205,010.00
B BAHAN
Semen Portland (ex. Gresik) Kg 384.000 1,450.00 556,800.00
Pasir Beton m3 0.494 300,000.00 148,200.00
Kerikil (Maks 30mm) m3 0.769 350,000.00 269,150.00
Air Liter 215.000 80.00 17,200.00
JUMLAH HARGA BAHAN 991,350.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 1,196,360.00


E Overhead & Profit (mak. 15%) 0.12 x D 143,563.20
F Harga Satuan Pekerjaan (D+E) 1,339,923.20
Pembulatan 1,339,000.00
3. Membuat 1 m³ lantai Kerja /Rabat beton mutu c (K 100)
No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 1.200 95,000.00 114,000.00
Tukang L.02 OH 0.200 120,000.00 24,000.00

Page 11
Kepala Tukang L.03 OH 0.020 130,000.00 2,600.00
Mandor L.04 OH 0.006 140,000.00 840.00
JUMLAH TENAGA KERJA 141,440.00
B BAHAN
Semen Portland (ex. Gresik) Kg 230.000 1,450.00 333,500.00
Pasir Beton m3 0.638 300,000.00 191,357.14
Kerikil (Maks 30mm) m3 0.761 350,000.00 266,259.26
Air Liter 200.000 80.00 16,000.00
JUMLAH HARGA BAHAN 807,116.40
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 948,556.40


E Overhead & Profit (mak. 15%) 0.12 x D 113,826.77
F Harga Satuan Pekerjaan (D+E) 1,062,383.17
Pembulatan 1,062,000.00
4. Membuat 1 m2 begisting untuk pondasi c

No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.520 95,000.00 49,400.00
Tukang L.02 OH 0.260 120,000.00 31,200.00
Kepala Tukang L.03 OH 0.026 130,000.00 3,380.00
Mandor L.04 OH 0.026 140,000.00 3,640.00
JUMLAH TENAGA KERJA 87,620.00
B BAHAN
Kayu Klas III/ Begisting m3 0.040 2,400,000.00 96,000.00
Paku 5 - 10 cm kg 0.300 18,000.00 5,400.00
Minyak Begisting Lt 0.100 3,500.00 350.00
JUMLAH HARGA BAHAN 101,750.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 189,370.00


E Overhead & Profit (mak. 15%) 0.12 x D 22,724.40
F Harga Satuan Pekerjaan (D+E) 212,094.40
( Membuat 1 m2 begisting untuk pondasi 2 x pakai ) 106,047.20
Pembulatan 106,000.00
5. Membuat 1 m2 begisting untuk Kolom c
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.660 95,000.00 62,700.00
Tukang L.02 OH 0.330 120,000.00 39,600.00
Kepala Tukang L.03 OH 0.033 130,000.00 4,290.00
Mandor L.04 OH 0.033 140,000.00 4,620.00
JUMLAH TENAGA KERJA 111,210.00
B BAHAN
Kayu Klas III/ Begisting m3 0.040 2,400,000.00 96,000.00
Paku 5 - 10 cm kg 0.400 18,000.00 7,200.00
Minyak Begisting Lt 0.200 3,500.00 700.00
Balok Kayu Klas II m3 0.015 6,500,000.00 97,500.00
Multiplek Tebal 9 mm lbr 0.350 165,000.00 57,750.00
Dolken Kayu Gelam dia 8-10 Pjg 4 m Btg 2.000 40,000.00 80,000.00
JUMLAH HARGA BAHAN 339,150.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 450,360.00


E Overhead & Profit (mak. 15%) 0.12 x D 54,043.20
F Harga Satuan Pekerjaan (D+E) 504,403.20
( Membuat 1 m2 begisting untuk Kolom 2 x pakai ) 252,201.60
Pembulatan 252,000.00
6. 1 kg Pembesian dengan Besi Polos c
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.007 95,000.00 665.00
Tukang L.02 OH 0.007 120,000.00 840.00
Kepala Tukang L.03 OH 0.001 130,000.00 130.00
Mandor L.04 OH 0.0003 140,000.00 42.00
JUMLAH TENAGA KERJA 1,677.00

Page 12
B BAHAN
Besi Beton Polos (ex.Hanil / setara) kg 1.050 11,800.00 12,390.00
Kawat Bendrad kg 0.015 20,000.00 300.00
JUMLAH HARGA BAHAN 12,690.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 14,367.00


E Overhead & Profit (mak. 15%) 0.12 x D 1,724.04
F Harga Satuan Pekerjaan (D+E) 16,091.04
Pembulatan 16,000.00
7. 1 m3 PEKERJAAN PANEL BETON LANTAI AAC,TEBAL 12,5 cm
No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 4.000 95,000.00 380,000.00
Tukang L.02 OH 2.500 120,000.00 300,000.00
Kepala Tukang L.03 OH 0.250 130,000.00 32,500.00
Mandor L.04 OH 0.125 140,000.00 17,500.00
JUMLAH TENAGA KERJA 730,000.00
B BAHAN
Panel Lantai Beton AAC, T = 12,5 cm m3 1.050 2,400,000.00 2,520,000.00
Pembesian Ø 10mm Kg 11.000 11,800.00 129,800.00
Semen Grouting Zak 2.200 95,000.00 209,000.00
Semen Perekat Zak 0.275 110,000.00 30,250.00

JUMLAH HARGA BAHAN 2,889,050.00


C PERALATAN
(Hoist, dll) 5% 2,889,050.00 144,452.50
JUMLAH HARGA ALAT 144,452.50

D Jumlah (A+B+C) 3,763,502.50


E Overhead & Profit (Max 15 %) 0.12 x D 451,620.30
F Harga Satuan Pekerjaan (D+E) 4,215,122.80
Pembulatan 4,215,000.00

F. HARGA SATUAN PEKERJAAN LANGIT-LANGIT (PLAFOND)


1. Pasang Plafond Gypsumboard 9mm Rangka Hollow Galvalum
No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.100 95,000.00 9,500.00
Tukang L.02 OH 0.200 120,000.00 24,000.00
Kepala Tukang L.03 OH 0.020 130,000.00 2,600.00
Mandor L.04 OH 0.050 140,000.00 7,000.00
JUMLAH TENAGA KERJA 43,100.00
B BAHAN
Gypsumboard 9mm Lbr 0.364 65,000.00 23,660.00
Hollow 2,4 Ljr 0.540 36,000.00 19,440.00
Hollow 4,4 Ljr 0.275 48,000.00 13,200.00
Fasting Nails bh 16.000 150.00 2,400.00
Wall angle M' 4.000 3,500.00 14,000.00
Kasa + Compound M2 0.200 20,000.00 4,000.00
JUMLAH HARGA BAHAN 76,700.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 119,800.00


E Overhead & Profit (mak. 15%) 0.12 x D 14,376.00
F Harga Satuan Pekerjaan (D+E) 134,176.00
Pembulatan 134,000.00
2. 1 m' Pasang Plafond WPVC
No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.120 95,000.00 11,400.00
Tukang L.02 OH 0.240 120,000.00 28,800.00
Kepala Tukang L.03 OH 0.024 130,000.00 3,120.00
Mandor L.04 OH 0.012 140,000.00 1,680.00
JUMLAH TENAGA KERJA 45,000.00
B BAHAN
WPC Ceilling Board 500 x 9,5 cm ,ex. Duma Lbr 2.150 110,000.00 236,500.00
Hollow 2,4 Ljr 0.540 36,000.00 19,440.00

Page 13
Hollow 4,4 Ljr 0.275 48,000.00 13,200.00
Fasting Nails bh 16.000 150.00 2,400.00
Wall angle M' 4.000 3,500.00 14,000.00
JUMLAH HARGA BAHAN 285,540.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 330,540.00


E Overhead & Profit (mak. 15%) 0.12 x D 39,664.80
F Harga Satuan Pekerjaan (D+E) 370,204.80
Pembulatan 370,000.00

G. PEKERJAAN PENGECATAN
1. Pengecatan 1 m² tembok baru (1 lapis cat dasar, 2 lapis cat penutup)
No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.0200 95,000.00 1,900.00
Tukang L.02 OH 0.0630 120,000.00 7,560.00
Kepala Tukang L.03 OH 0.0063 130,000.00 819.00
Mandor L.04 OH 0.0030 140,000.00 420.00
JUMLAH TENAGA KERJA 10,699.00
B BAHAN
Cat Dasar Alkali Eksteror ex Nippon paint Ltr 0.1000 31,000.00 3,100.00
Cat Dinding Eksterior ex. Nippon paint Ltr 0.1500 80,000.00 12,000.00
Ampelas Lbr 0.2600 10,000.00 2,600.00
JUMLAH HARGA BAHAN 17,700.00
C PERALATAN
- - -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 28,399.00


E Overhead & Profit (mak. 15%) 0.12 x D 3,407.88
F Harga Satuan Pekerjaan (D+E) 31,806.88
Pembulatan 31,000.00

H. PEKERJAAN BAJA KONSTRUKSI


1. 1 Kg Pemasangan 1 kg Baja Profil
No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.0600 95,000.00 5,700.00
Tukang L.02 OH 0.0600 120,000.00 7,200.00
Kepala Tukang L.03 OH 0.0060 130,000.00 780.00
Mandor L.04 OH 0.0030 140,000.00 420.00
JUMLAH TENAGA KERJA 14,100.00
B BAHAN
Besi Profil Kg 1.1500 16,000.00 18,400.00
JUMLAH HARGA BAHAN 18,400.00
C PERALATAN
- - -
JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 32,500.00


E Overhead & Profit (mak. 15%) 0.12 x D 3,900.00
F Harga Satuan Pekerjaan (D+E) 36,400.00
Pembulatan 36,000.00
2. Pengerjaan 100 Kg Perakitan Baja

No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.1000 95,000.00 9,500.00
Tukang L.02 OH 0.1000 120,000.00 12,000.00
Kepala Tukang L.03 OH 0.0010 130,000.00 130.00
Mandor L.04 OH 0.0050 140,000.00 700.00
JUMLAH TENAGA KERJA 22,330.00
B BAHAN
Solar Ltr 1.0000 5,150.00 5,150.00
Minyak Pelumas Ltr 0.1000 40,000.00 4,000.00
JUMLAH HARGA BAHAN 9,150.00
C PERALATAN
Sewa Alat abntu erection Jam 0.8000 150,000.00 120,000.00
JUMLAH HARGA ALAT 120,000.00

Page 14
D Jumlah (A+B+C) 151,480.00
E Overhead & Profit (mak. 15%) 0.12 x D 18,177.60
F Harga Satuan Pekerjaan (D+E) 169,657.60
Pembulatan 169,000.00
3. Pengerjaan 10 cm Pengelasan dengan Las Listrik
No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
(Rp.) (Rp.)
A TENAGA
Pekerja L.01 OH 0.0400 95,000.00 3,800.00
Tukang L.02 OH 0.0200 120,000.00 2,400.00
Kepala Tukang L.03 OH 0.0020 130,000.00 260.00
Mandor L.04 OH 0.0020 140,000.00 280.00
JUMLAH TENAGA KERJA 6,740.00
B BAHAN
Kawat Las Listrik Kg 0.4000 40,000.00 16,000.00
Solar Ltr 0.3000 5,150.00 1,545.00
Minyak Pelumas Ltr 0.0400 40,000.00 1,600.00
JUMLAH HARGA BAHAN 19,145.00
C PERALATAN
Sewa Alat Las Jam 0.1700 65,000.00 11,050.00
JUMLAH HARGA ALAT 11,050.00

D Jumlah (A+B+C) 36,935.00


E Overhead & Profit (mak. 15%) 0.12 x D 4,432.20
F Harga Satuan Pekerjaan (D+E) 41,367.20
Pembulatan 41,000.00

4. 1 Kg Pemasangan Rangka Baja


Harga Satuan Jumlah Harga
No. Uraian Satuan Koefisien
(Rp.) (Rp.)
1 Baja Profil Kg 1.0000 36,000.00 36,000.00
2 Perakitan per 100 Kg Kg 0.0100 169,000.00 1,690.00
3 Pengelasan Per 10 cm set 0.0500 41,000.00 2,050.00
JUMLAH 39,740.00
Dibulatkan 39,700.00
5. 1 Kg Pemasangan Rangka Baja (baja profil bekas bongkaran)
No. Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp.) (Rp.)
1 Perakitan per 100 Kg Kg 0.0250 169,000.00 4,225.00
2 Pengelasan Per 10 cm set 0.1000 41,000.00 4,100.00
JUMLAH 8,325.00
Dibulatkan 8,200.00

Page 15
DAFTAR HARGA SATUAN PEKERJAAN

NO JENIS PEKERJAAN SATUAN HARGA (Rp.)

A. HARGA SATUAN PEKERJAAN PERSIAPAN


1 Pembersihan 1 M2 Lapangan dan Perataan m² 11,000.00
2 Pembongkaran 1 M2 Atap (Penurunan Genting, Pembongkaran Konstruksi atap, berikut Plaf m² 28,000.00
3 Pembongkaran 1 M3 Dinding Bata m³ 246,000.00
B. HARGA SATUAN PEKERJAAN TANAH
1 Penggalian 1 m³ tanah biasa sedalam 1 m m³ 83,000.00
2 Pengeboran Strousz dia. 30cm, 1 M' m1
78,000.00
3 Pengurugan 1 m³ dengan Pasir m³ 341,000.00
C. HARGA SATUAN PEKERJAAN PASANGAN DINDING
1 Pemasangan 1 m2 dinding bata putih tebal 1/2 bata dengan campuran 1Pc : 6 Ps m² 113,000.00
D. HARGA SATUAN PEKERJAAN PLESTERAN
1 Plesteran dinding 1 m2 dengan Campuran 1Pc : 6 Ps m² 95,000.00
2 Acian plesteran 1 m2 dengan PC m² 43,000.00
E. HARGA SATUAN PEKERJAAN BETON
1 Membuat 1 m³ beton mutu (K 225) m³ 1,318,000.00
2 Membuat 1 m³ beton mutu (K 250) m³ 1,339,000.00
3 Membuat 1 m³ lantai Kerja /Rabat beton mutu (K 100) m³ 1,062,000.00
4 Membuat 1 m2 begisting untuk pondasi m² 106,000.00
5 Membuat 1 m2 begisting untuk Kolom m² 252,000.00
6 1 kg Pembesian dengan Besi Polos kg 16,000.00
7 1 m3 PEKERJAAN PANEL BETON LANTAI AAC,TEBAL 12,5 cm m³ 4,215,000.00
F. HARGA SATUAN PEKERJAAN LANGIT-LANGIT (PLAFOND)
1 Pasang Plafond Gypsumboard 9mm Rangka Hollow Galvalum m² 134,000.00
2 1 m' Pasang Plafond WPVC m¹ 370,000.00
G. PEKERJAAN PENGECATAN
1 Pengecatan 1 m² tembok baru (1 lapis cat dasar, 2 lapis cat penutup) m² 31,000.00
H. PEKERJAAN BAJA KONSTRUKSI
1 1 Kg Pemasangan Rangka Baja Kg 39,700.00
2 1 Kg Pemasangan Rangka Baja (baja profil bekas bongkaran) Kg 8,200.00

Page 16
ENGINEER'S ESTIMATES (E.E)

REKAPITULASI
RENCANA ANGGARAN BIAYA (R.A.B)

KEGIATAN : PENINGKATAN SARANA DAN PRASARANA PENDIDIKAN


PEKERJAAN : PEMBANGUNAN PERPUSTAKAAN
LOKASI : ........................ - KABUPATEN BANGKALAN

NO. URAIAN KEGIATAN JUMLAH HARGA + PPn

A. PEKERJAAN PERSIAPAN #REF!

B. PEKERJAAN KONSTRUKSI BANGUNAN UTAMA #REF!


I. PEKERJAAN TANAH #REF!
II. PEKERJAAN PONDASI #REF!
III. PEKERJAAN BETON #REF!
IV. PEKERJAAN DINDING #REF!
V. PEKERJAAN RANGKA ATAP & PENUTUP ATAP Rp 6,369,126.50
V. PEKERJAAN PLAFOND Rp 2,554,090.00
VI. PEKERJAAN LANTAI #REF!
VII. PEKERJAAN KUSEN, PINTU, JENDELA & PENGGANTUNG Rp 3,680,600.00
VIII. PEKERJAAN LISTRIK Rp 772,200.00
IX. PEKERJAAN PENGECATAN Rp 7,589,296.00
X. PEKERJAAN SANITASI Rp 338,140.00
XI. PEKERJAAN MEBELAIR Rp 17,600,000.00

JUMLAH TOTAL #REF!

JUMLAH TOTAL DIBULATKAN #REF!

Terbilang : Err:511

#REF!
#REF!

Bangkalan, 09 Februari 2021

Konsultan Perencana
CV. V-STAR KONSULTAN

EPRI TRIMULYONO, ST
Direktur

Page 17
RENCANA ANGGARAN BIAYA

KEGIATAN : PENINGKATAN SARANA DAN PRASARANA PENDIDIKAN


PEKERJAAN : PEMBANGUNAN PERPUSTAKAAN
LOKASI : ........................ - KABUPATEN BANGKALAN

NO JENIS PEKERJAAN VOLUME SAT HARGA SATUAN JUMLAH PPn (10%) JUMLAH + PPn

1 2 3 4 5 6 7 8

A. PEKERJAAN PERSIAPAN
1 Pek. Pembongkaran Atap bangunan lama - m² Rp 28,000.00 Rp - Rp - Rp -
2 Pek. Pembongkaran Dinding bangunan lama - m³ Rp 246,000.00 Rp - Rp - Rp -
3 Pek. Pengukuran & Bowplank - - m' Rp 91,000.00 Rp - Rp - Rp -
4 Pek. Pembersihan lokasi #REF! #REF! m² Rp 11,000.00 #REF! #REF! #REF!
5 Penyediaan K3 1.0000 1.00 ls Rp 3,090,000.00 Rp 3,090,000.00 Rp 309,000.00 Rp 3,399,000.00
#REF!
B. PEKERJAAN KONSTRUKSI PEMBANGUNAN AULA
I. PEKERJAAN TANAH
1 Pek. Galian Tanah Pondasi & Sloop 10.2300 10.23 m³ Rp 83,000.00 Rp 849,090.00 Rp 84,909.00 Rp 933,999.00
2 Pek. Urugan Pasir bawah Pondasi 3.6690 3.66 m³ Rp 341,000.00 Rp 1,248,060.00 Rp 124,806.00 Rp 1,372,866.00
3 Pek. Urugan Tanah kembali #REF! #REF! m³ Rp 61,000.00 #REF! #REF! #REF!
#REF!
II. PEKERJAAN PONDASI
1 Pek. Rabatan beton 5 cm bawah Pondasi & Sloop 0.3960 0.39 m³ Rp 1,062,000.00 Rp 414,180.00 Rp 41,418.00 Rp 455,598.00
2 Pek. Beton Plat Setempat 80.80.30 (PS-1) 83.1668 83.16 m³ Rp 2,085,000.00 Rp 173,388,600.00 Rp 17,338,860.00 Rp 190,727,460.00
3 Pek. Beton Plat Setempat 60.60.25 (PS-2) #REF! #REF! m³ Rp 1,930,000.00 #REF! #REF! #REF!
4 Pek. Pasangan Bata. t = 20cm (Dumping Urugan) #REF! #REF! m³ Rp 113,000.00 #REF! #REF! #REF!
#REF!
III. PEKERJAAN BETON
1 Pek. Beton Sloop 20/30 (S1) #REF! #REF! m³ Rp 2,660,000.00 #REF! #REF! #REF!
2 Pek. Beton Sloop 15/25 (S2) #REF! #REF! m³ Rp 2,750,000.00 #REF! #REF! #REF!
3 Pek. Beton Kolom 20/25 (K1) #REF! #REF! m³ Rp 2,960,000.00 #REF! #REF! #REF!
4 Pek. Beton Kolom 20/20 (K2) #REF! #REF! m³ Rp 3,250,000.00 #REF! #REF! #REF!
5 Pek. Beton Kolom praktis 10/15 (KP) #REF! #REF! m³ Rp 3,250,000.00 #REF! #REF! #REF!
6 Pek. Beton Balok latai 10/15 (BL) 0.3225 0.32 m³ Rp 2,900,000.00 Rp 928,000.00 Rp 92,800.00 Rp 1,020,800.00
7 Pek. Beton Balok Struktur Teras 12/25 (B1) #REF! #REF! m³ Rp 2,750,000.00 #REF! #REF! #REF!
8 Pek. Beton Balok Rink 10/20 (B2') #REF! #REF! m³ Rp 2,550,000.00 #REF! #REF! #REF!
9 Pek. Beton Plat Talang, t = 8 cm #REF! #REF! m³ Rp 3,425,000.00 #REF! #REF! #REF!
#REF!
IV. PEKERJAAN DINDING
1 Pasangan bata putih, 1 Pc : 6 Ps #REF! #REF! m² Rp 113,000.00 #REF! #REF! #REF!
2 Plesteran dinding, 1 Pc : 6 Ps 200.8660 200.86 m² Rp 95,000.00 Rp 19,081,700.00 Rp 1,908,170.00 Rp 20,989,870.00
3 Acian Semen Instan (Dinding & Kolom) - - m² Rp 12,000.00 Rp - Rp - Rp -
#REF!
V. PEKERJAAN RANGKA ATAP & PENUTUP ATAP
1 Rangka atap Baja Ringan elev. 10° Jarak reng 45 cm 65.3782 65.37 m² Rp 45,500.00 Rp 2,974,335.00 Rp 297,433.50 Rp 3,271,768.50
2 Rangka atap Baja Ringan elev. 5° Jarak reng 45 cm 8.4000 8.40 m² Rp 40,000.00 Rp 336,000.00 Rp 33,600.00 Rp 369,600.00
3 Listplank Woodplank 20 cm 7.9000 7.90 m¹ Rp 38,000.00 Rp 300,200.00 Rp 30,020.00 Rp 330,220.00
4 Pasang Atap Bitumen selulose 83.8330 83.83 m² Rp 26,000.00 Rp 2,179,580.00 Rp 217,958.00 Rp 2,397,538.00
5 Pasang bubungan Atap Bitumen Selulose - - m¹ Rp 33,500.00 Rp - Rp - Rp -
Rp 6,369,126.50
V. PEKERJAAN PLAFOND
1 Plafond Gypsumboard 9mm + rangka metal hollow - - m² Rp 134,000.00 Rp - Rp - Rp -
2 Plafond Kalsiboard 4mm + rangka metal hollow 21.7000 21.70 m² Rp 107,000.00 Rp 2,321,900.00 Rp 232,190.00 Rp 2,554,090.00
3 List Plafond Gypsum - m¹ Rp 19,000.00 Rp - Rp - Rp -
Rp 2,554,090.00
VI. PEKERJAAN LANTAI
1 Pek. Urugan Pedel bawah lantai #REF! #REF! m³ Rp 33,000.00 #REF! #REF! #REF!
2 Rabatan beton bawah keramik, t = 5cm 2.1528 2.15 m² Rp 1,062,000.00 Rp 2,283,300.00 Rp 228,330.00 Rp 2,511,630.00
3 Pasang Keramik Lantai 40 x 40 cm #REF! #REF! m² Rp 108,000.00 #REF! #REF! #REF!
3 Pasang Keramik Lantai 40 x 40 cm (Unpolish) 3.1000 3.10 m² Rp 108,000.00 Rp 334,800.00 Rp 33,480.00 Rp 368,280.00
#REF!
VII. PEKERJAAN KUSEN, PINTU, JENDELA & PENGGANTUNG
1 Pintu Aluminuium + Panil Kaca (P-1) 1.00 unit Rp 525,000.00 Rp 525,000.00 Rp 52,500.00 Rp 577,500.00
2 Pintu Aluminuium + Panil Kaca (PJ-1) 1.00 unit Rp 369,000.00 Rp 369,000.00 Rp 36,900.00 Rp 405,900.00
3 Kusen Jendela + Daun Alumunium Casement (J-1) 5.00 unit Rp 310,000.00 Rp 1,550,000.00 Rp 155,000.00 Rp 1,705,000.00
4 Kusen Jendela + Daun Alumunium Casement (J-2) 1.00 unit Rp 410,000.00 Rp 410,000.00 Rp 41,000.00 Rp 451,000.00
5 Kusen Bouvenlight (BV-1) 6.00 unit Rp 82,000.00 Rp 492,000.00 Rp 49,200.00 Rp 541,200.00
Rp 3,680,600.00
VIII. PEKERJAAN LISTRIK
1 Titik lampu + Instalasi 8.00 ttk Rp 45,000.00 Rp 360,000.00 Rp 36,000.00 Rp 396,000.00
2 Pasang stop kontak 450 VA + instalasi 7.00 ttk Rp 23,000.00 Rp 161,000.00 Rp 16,100.00 Rp 177,100.00
3 Pasang Saklar ganda 2.00 bh Rp 11,000.00 Rp 22,000.00 Rp 2,200.00 Rp 24,200.00
4 Pasang Saklar tunggal 1.00 bh Rp 11,000.00 Rp 11,000.00 Rp 1,100.00 Rp 12,100.00
5 Lampu Led Outbow 12 watt 2.00 bh Rp 23,000.00 Rp 46,000.00 Rp 4,600.00 Rp 50,600.00
6 Lampu Led 14,5 watt 6.00 bh Rp 17,000.00 Rp 102,000.00 Rp 10,200.00 Rp 112,200.00
Rp 772,200.00
IX. PEKERJAAN PENGECATAN
1 Pengecatan Plafond 21.70 21.70 m² Rp 31,000.00 Rp 672,700.00 Rp 67,270.00 Rp 739,970.00
2 Pengecatan Dinding Interior 200.87 200.86 m² Rp 31,000.00 Rp 6,226,660.00 Rp 622,666.00 Rp 6,849,326.00
3 Pengecatan Dinding Eksterior - - m² Rp 14,000.00 Rp - Rp - Rp -
Rp 7,589,296.00
X. PEKERJAAN SANITASI
1 Pipa PVC 3" Pembuangan Air Hujan 10.60 10.60 m' Rp 29,000.00 Rp 307,400.00 Rp 30,740.00 Rp 338,140.00
Rp 338,140.00
XI. PEKERJAAN MEBELAIR
1 Rak buku 12.00 unit Rp 750,000.00 Rp 9,000,000.00 Rp 900,000.00 Rp 9,900,000.00
2 Meja Baca Kelompok 16.00 unit Rp 300,000.00 Rp 4,800,000.00 Rp 480,000.00 Rp 5,280,000.00
3 Meja Sirkulasi 1.00 unit Rp 850,000.00 Rp 850,000.00 Rp 85,000.00 Rp 935,000.00
4 Meja Serbaguna 1.00 unit Rp 500,000.00 Rp 500,000.00 Rp 50,000.00 Rp 550,000.00
5 Meja Ketik 1.00 unit Rp 300,000.00 Rp 300,000.00 Rp 30,000.00 Rp 330,000.00
6 Kursi Kerja 2.00 unit Rp 275,000.00 Rp 550,000.00 Rp 55,000.00 Rp 605,000.00
Rp 17,600,000.00

Page 18
12,730,428.51
PERHITUNGAN VOLUME α
Rad α
KEGIATAN : PENYELENGGARAAN BANGUNAN GEDUNG DI WILAYAH KABUPATEN / KOTA, PEMBERIAN IZIN MENDIRIKAN Sin α

PEKERJAAN : REHABILITASI SEDANG/BERAT PENDOPO I Cos α

LOKASI : KABUPATEN BANGKALAN Tan α

VOLUME
NO ITEM PEKERJAAN DIMENSI PENGALI SAT KETERANGAN
LAPANGAN

P L T/T

I. PEKERJAAN PERSIAPAN
1 Pek. Pembongkaran Atap lama Atap Utama Bangunan I 10.00 13.00 1.22 1.00 m2 158.70
Atap Utama Bangunan 2 6.00 14.00 1.43 1.00 m2 119.96

278.67

2 Pembongkaran bata Depan 3.00 0.15 3.25 - m3 -


Bukaan Kusen 2.60 0.15 1.60 - m3 -
2.60 0.15 2.30 - m3 -

3 Pek. Pembersihan lokasi I 19.00 15.00 1.00 1.00 m2 285.00


II

285.00

3 Pek. Bouwplank & Pengukuran H 4.00 1.00 1.00 - m' -


,
-

II PEKERJAAN TANAH

1 Pek. Galian Tanah Strous Ø 30cm 4.00 1.00 1.00 12.00 m' 48.00

25.7142857142857 -
48.00
8

2 Galian Tanah si Setempat (PS -1) 80.80.30 I 0.90 0.90 1.00 9.00 m3 7.29
si Setempat (PS -1) 60.60.30 II 0.70 0.70 1.00 6.00 m3 2.94

10.23

2 Urugan pasir (t.10 cm) bawah pondasi I 0.90 0.90 0.10 9.00 m3 0.73
II 0.70 0.70 1.00 6.00 m3 2.94

3.67

III PEKERJAAN PONDASI

1 Rabatan Beton bawah Plat Setempat & Sloop I 0.80 0.80 0.05 9.00 m3 0.29
II 0.60 0.60 0.05 6.00 m3 0.11

0.40

2 Beton Stros , Ø 30 cm
Besi Tulangan Ø 12mm - 150mm 4.00 5.00 1.00 12.00 kg 239.76
239.76
Pengecoran Beton Strous 0.02 3.14 4.00 12.00 m3 3.39
3.39
Bekesting I - - 0.00 12.00 m2 -
-

2 Beton Plat Pondasi , 80.80.30 cm


Besi Tulangan Ø 13mm - 150mm 1.85 5.00 1.00 9.00 kg 83.17
83.17
Pengecoran Beton 0.80 0.80 0.30 9.00 m3 1.38
1.38
Bekesting I 3.20 0.30 1.00 9.00 m2 2.59
2.59

3 Beton Plat Pondasi , 60.60.30 cm


Besi Tulangan Ø 13mm - 150mm 1.45 5.00 1.00 6.00 kg 43.46
43.46
Pengecoran Beton 0.60 0.60 0.30 6.00 m3 0.39
0.39
Bekesting I 2.40 0.30 1.00 6.00 m2 1.30
1.30

IV PEKERJAAN BETON STRUKTUR


0.20
1 Beton Sloop S1 ( 15/25 )
1.33333333333333
Pengecoran Beton 14.40 0.15 0.25 1.00 m 3
0.54
1.60 0.15 0.25 1.00 m3 0.06
0.60
Pembesian Besi Utama 5 - Ø13mm 16.00 5.00 1.00 1.00 kg 79.92
Beugel Ø8mm - 150mm 16.00 4.33 0.35 1.00 kg 24.27
104.19
Bekesting 16.00 1.20 1.00 1.00 m2 19.20
19.20

2 Beton Kolom K1 ( 30/30 )


1.33333333333333
Pengecoran Beton 5.50 0.30 0.30 9.00 m3 4.46
0.30 0.30 - m3 -
4.46
Pembesian Besi Utama 8 - Ø16mm 49.50 8.00 1.52 1.00 kg 602.71
Beugel Ø8mm - 150mm 49.50 7.00 0.35 1.00 kg 121.28
723.99
Bekesting 49.50 1.20 1.00 1.00 m2 59.40
59.40

2 Beton Kolom K2 ( 25/25 )


1.33333333333333
Pengecoran Beton 5.50 0.25 0.25 3.00 m3 1.03
0.25 0.25 - m3 -
1.03
Pembesian Besi Utama 6 - Ø13mm 16.50 6.00 1.00 1.00 kg 98.90
Beugel Ø8mm - 150mm 16.50 5.67 0.35 1.00 kg 32.73
131.63
Bekesting 16.50 1.00 1.00 1.00 m2 16.50
16.50

3 Beton Kolom K3 ( 15/20 )


1.33333333333333
Pengecoran Beton 5.50 0.15 0.20 3.00 m3 0.50
0.15 0.20 - m3 -
0.50
Pembesian Besi Utama 4 - Ø13mm 16.50 4.00 1.00 1.00 kg 65.93
Beugel Ø8mm - 150mm 16.50 3.67 0.35 1.00 kg 21.18
87.11
Bekesting 16.50 0.70 1.00 1.00 m2 11.55
11.55

6 Beton Plat Beton Lantai, T = 12,5 cm

Panel Lantai 12,5 22.00 15.50 0.125 1.00 m3 42.63


2.52 4.08 0.125 (1.00) m3 (1.28)

41.34
Pembesian Besi Utama Ø10mm-150mm (wiremesh) 330.73 13.33 0.57 1.00 kg 2,513.56

2,513.56
Bekesting 330.73 1.00 1.00 1.00 m2 330.73
330.73

V PEKERJAAN PASANGAN DINDING

1 Pasangan Bata Merah


Akibat Pembongkaran (titik kolom baru) 1.00 1.00 0.30 12.00 m2 3.60
Area R. Penghubung H 3.00 1.00 1.50 2.00 m2 9.00
Area Tangga

Pengurangan Kusen - - 1.40 - m2 -


-

12.60

2 Plesteran bata Merah


I 12.60 1.00 1.00 2.00 m2 25.20
Pengurangan - - 0.00 - m2 -

25.20

3 Acian
I 25.20 1.00 1.00 1.00 m2 25.20
Kolom 30/30 0.90 1.00 4.80 9.00 m2 38.88
Kolom 30/30 0.75 1.00 4.80 3.00 m2 10.80
Pengurangan - - 0.00 - m2 -

74.88

3 Pek. Benangan
Ornamen Kaca 4.00 1.00 1.00 1.00 m2 4.00
8.00 1.00 1.00 1.00 m2 8.00

12.00

2 Penutup Rangka, Kalsiboard 6mm


I 3.05 1.00 3.00 2.00 m2 18.30
II 1.60 1.00 3.00 2.00 m2 9.60
III 5.05 1.00 3.00 2.00 m2 30.30
IV 2.40 1.00 3.00 2.00 m2 14.40
Pengurangan ornamen kaca 0.40 0.40 1.00 (4.00) m2 (0.26)
1.40 0.40 1.00 (4.00) m2 (0.90)
71.45

3 Penutup Rangka, Kalsiboard 4mm


I 2.54 1.00 3.20 2.00 m2 16.26
II 1.40 1.00 3.20 2.00 m2 8.96
III 4.32 1.00 3.20 2.00 m2 27.65
IV - 1.00 3.20 2.00 m2 -

52.86

3 Pek. Ornamen Kaca 5mm


I 0.40 0.40 1.00 4.00 m2 0.26
II 1.40 0.40 1.00 4.00 m2 0.90

1.15

2 Plesteran Semen Instan 0 - - 0.00 - 0 -


#REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF!

#REF! #REF! #REF! #REF! #REF! #REF! #REF!


#REF! #REF! #REF! #REF! #REF! #REF! #REF!

#REF!

3 Acian = LUAS PLESTERAN TOTAL #REF! 1.00 1.00 1.00 m2 #REF!

#REF!

4 Total Dinding Baru V 55.00 1.00 0.65 - m2 -


H 7.15 1.00 0.65 - m2 -
Gewel 7.15 1.00 #REF! - m2 #REF!

#REF!

4 Plasteran Dinding Baru V 55.00 1.00 0.50 - m2 -


H 7.15 1.00 0.50 - m2 -
Gewel 7.15 1.00 #REF! - m2 #REF!

#REF!

VI PEKERJAAN ATAP

1 Rangka Atap A 13.00 3.85 1.00 1.00 m2 50.24

50.24

2 Penutup atap A 13.20 3.95 1.00 1.00 m2 52.34

52.34

4 Rangka Listplank 0.8 H 10.50 1.00 0.80 1.00 m2 8.40


V 8.60 1.00 0.80 1.00 m 2
6.88
H 3.30 1.00 2.20 1.00 m2 7.26
5.90 1.00 1.85 1.00 m2 10.92
V 4.00 1.00 2.20 1.00 m2 8.80

42.26

4 Penutup Kalisboard 6mm 0.8 H 10.50 1.00 1.30 1.00 m2 13.65


V 8.60 1.00 1.30 1.00 m2 11.18
H 3.30 1.00 1.90 1.00 m 2
6.27
5.90 1.00 1.55 1.00 m2 9.15
V 4.00 1.00 1.90 1.00 m2 7.60

47.85

4 Penutup Woodplank 20cm


H 3.30 1.00 2.20 1.00 m2 7.26
5.90 1.00 1.85 1.00 m2 10.92
V 4.00 1.00 2.20 1.00 m2 8.80

26.98

5 ACP 6.30 2.10 1.00 1.00 m2 13.23


16.80 0.20 1.00 1.00 m2 3.36

16.59

5 Sky Light 2.40 1.20 1.00 4.00 m2 11.52

11.52

5 Talang Seng Galvanis 25.80 1.00 1.00 1.00 m' 25.80

25.80

5 Pipa Talang 2.5" 1.00 1.00 3.20 8.00 m' 25.60

25.60

VII PEKERJAAN PLAFON

1 Pasang rangka Hollow Galvalum + Gypsum -


R. MUSIK 105.70 1.00 1.00 1.00 m2 105.70
11.00 1.00 1.00 1.00 m2 11.00
2.50 1.00 1.00 1.00 m2 2.50
R. PENGHUBUNG 105.70 1.00 1.00 1.00 m2 105.70
R. FITNES 80.00 1.00 1.00 1.00 m2 80.00

304.90

2 Pasang rangka plafond Hollow Galvalum + GRC Motif Kayu ex Conwood


89.80 1.00 1.00 1.00 m2 89.80

89.80
2 Pasang Kembali Peredam
105.50 1.00 1.00 1.00 m2 105.50

105.50
VIII PEKERJAAN LANTAI

1 Screeding Lantai Beton


330.73 1.00 0.04 1.00 m3 13.23

13.23
2 Urugan Pasir
0 330.73 1.00 0.10 2.00 m2 66.15
#REF! #REF! #REF! 0.10 1.00 m2 #REF!

#REF!
3 Rabat lantai t 5 cm
0 330.73 1.00 0.05 2.00 m2 33.07
#REF! #REF! #REF! 0.05 1.00 m2 #REF!

#REF!

4 Lapis Lantai 40 x 40 cm
Ruang Kelas 330.73 1.00 1.00 3.00 m2 992.19
Kantor #REF! 1.00 1.00 1.00 m2 #REF!
Teras 27.80 #REF! 1.00 1.00 m 2
#REF!

#REF!

IX PEKERJAAN KUSEN
1 Pemasangan Kusen Pintu P2 1.00 Unit -
2 Pemasangan Kaca Bouvenlight BV1 0.70 1.00 0.50 4.00 Unit 1.40
3 Pemasangan Kaca Bouvenlight BV2 1.30 1.00 0.50 4.00 Unit 2.60

4.00
X. PEKERJAAN LISTRIK
1 Titik instalasi listrik + titik lampu Ttk
2 Pemasangan lampu SL 18 watt Bh
3 Pemasangan lampu SL 14 watt Bh
4 Pemasangan lampu Downlight outbow SL 14 watt Bh
5 Saklar ganda Bh
6 Saklar tungal Bh
7 stop kontak Bh
8 Stop Kontak AC Bh
9 Box panel listrik + mcb 4 grup lokal Bh

XII PEKERJAAN SANITASI


1 Pipa PVC Ø 4" AW air kotor (Kloset) m'
2 Pipa PVC Ø 3" AW air Hujan 1.00 1.00 2.65 4.00 m' 10.60
3 Pipa PVC Ø 3/4" AW air bersih m'
4 Pengeboran Air Tanah Unit
5 Tandon Air Profil Tank (Kapasitas 1100 L ) Unit
6 Pompa air Unit
7 Pembuatan Rumah pompa Ls
8 Pembuatan cor tandon bawah Ls
9 Septictank + Resapan 3 Kompartemen Ukuran Sedang ( 2,60 x 1,10 x 1,20 ) Unit

XIII PEKERJAAN PENGECATAN

1 PENGECATAN KUSEN By CAD

P1 1.00 1.00 7.94 4.00 m2 31.76


J1 10.11 1.00 1.00 7.00 m2 70.77
J2 10.71 1.00 1.00 11.00 m2 117.81

220.34 59.49

Daun Pintu 11.64 1.00 1.00 2.00 m2 23.27


DaunJendela 1 0.38 0.80 1.00 14.00 m2 4.31
DaunJendela 2 0.51 0.80 1.00 22.00 m2 8.95

36.52
PERHITUNGAN VOLUME
KEGIATAN : REHABILITASI SEDANG/BERAT PENDOPO I
PEKERJAAN : REHABILITASI SEDANG/BERAT PENDOPO I
LOKASI : KABUPATEN BANGKALAN

NO PROFIL BAJA DIMENSI PENGALI VOLUME

1 WF 350.175.7.11 4,190.21 Kg
49.60 H 22.00 x 4.00 4,364.80
49.60 H x 1.00 -

Kelekan / Hounch 24.80 H 0.80 x 16.00 317.44


24.80 H 0.40 x 8.00 79.36

1.1 PLAT 10 mm 348.87 Kg


Plat Plendes 7850 0.09 x 9.00 0.010 63.59
7850 0.06 x 3.00 0.010 14.72
Plat Lekat 7850 0.05 x 16.00 0.010 62.80
7850 0.04 x 8.00 0.010 25.12
7850 0.06 x 2.00 0.010 9.62
Stifner 7850 0.06 x 40.00 0.010 173.03

1.2 Baut Angkur 19mm 112.00 Bh


1 4.00 x 12.00 1.00 48.00
1 4.00 x 16.00 1.00 64.00
1 2.00 x 8.00 1.00 16.00

Baut + Mur 19mm 32.00 Bh


1 8.00 x 4.00 1.00 32.00

2 WF 250.125.6.9 1,929.51 Kg
29.60 V 5.43 x 6.00 963.48
29.60 V 5.43 x 4.00 642.32
29.60 V 2.47 x 3.00 218.89
29.60 V 2.47 x 2.00 145.93

Kelekan / Hounch 14.80 H 0.30 x 24.00 106.56


14.80 H 0.30 x 6.00 26.64
14.80 H 0.30 x 16.00 71.04
14.80 H 0.30 x 4.00 17.76

2.1 PLAT 8 mm 340.05 Kg


Ke WF 350 7850 0.11 x 20.00 0.008 131.88
7850 0.11 x 10.00 0.008 65.94
Ke WF 200 7850 0.03 x 22.00 0.008 43.18
Stifner 7850 0.03 x 55.00 0.008 99.06

2.2 Baut Angkur 16mm - Bh


1
1

2.3 Baut + Mur 16mm 240.00 Bh


1 8.00 x 20.00 1.00 160.00
1 8.00 x 10.00 1.00 80.00

3 WF 200.100.5,5.8 1,649.86 Kg
21.30 H 5.10 x 4.00 434.52
21.30 H 4.45 x 4.00 379.14
21.30 H 4.28 x 1.00 91.16
21.30 H 1.66 x 4.00 141.43
21.30 H 2.30 x 2.00 97.94

21.30 V 2.66 x 3.00 169.97


21.30 V 4.06 x 1.00 86.48
21.30 V 1.41 x 5.00 150.17

Kelekan / Hounch 10.65 H 0.30 x 22.00 70.29


10.65 H 0.30 x 9.00 28.76

3.1 WF 200.100.5,5.8 (Bekas bongkaran) 91.60 x 21.30 90% 1,755.97

3.2 Plat Lekat 5mm & Dan Stifner 5mm 139.36 Kg


Ke WF 250 7850 0.03 x 0.00 0.008 -
Ke WF 350 7850 0.03 x 6.00 0.008 11.78
Ke WF 200 7850 0.03 x 7.00 0.008 10.99
Stifner & Penahan CNP 7850 0.02 x 112.00 0.005 98.93
7850 0.02 x 20.00 0.005 17.67

3.3 Plat Siku 50.50.5 489.72 Kg


3.77 60.00 x 2.00 1.00 452.40
3.77 0.08 x 132.00 1.00 37.32

3.4 Baut + Mur 12mm - Bh


Ke WF 250 /350 1 - x 6.00 1.00 -
Ke WF 200 1 - x 6.00 1.00 -

4 CNP 150.35.1,8 (Double) 986.96 Kg


3.14 H 22.00 x 1.00 2.00 138.16
3.14 H 3.40 x 1.00 2.00 21.35
3.14 H 1.67 x 2.00 2.00 20.98
3.14 H 21.85 x 2.00 2.00 274.44
Penambahan Flange WF 200 3.14 V 14.82 x 6.00 2.00 558.42
3.14 V (4.20) x 1.00 2.00 (26.38)

CNP 150.35.1,8 (Bekas bongkaran) 408.00 x 3.14 80% 1,024.90

5 TANGGA
WF 200.100.5,5.8 464.34 Kg
Miring 21.30 H 2.10 x 2.00 89.46
Datar 21.30 H 5.00 x 1.00 106.50
21.30 H 1.20 x 4.00 102.24
21.30 H 2.10 x 2.00 89.46
21.30 H 0.80 x 2.00 34.08
21.30 H 1.00 x 2.00 42.60

Plat Siku 50.50.5 318.94 Kg


Anak Tangga 3.77 3.60 x 1.00 17.00 230.72
Bordes 3.77 7.80 x 1.00 3.00 88.22

PLAT 8 mm 5.65 Kg
Ke Sloop 7850 0.05 x 2.00 0.008 5.65

Baut Angkur 16mm 12.00 Bh


1 6.00 x 2.00 1.00 12.00
6

10

11

12

5
6

10
11

12

13

14

15

16

17

2
3

10
11

12

13

14

15

16

17

18

19

20
12,730,428.51
PERHITUNGAN VOLUME
KEGIATAN : PENYELENGGARAAN BANGUNAN GEDUNG DI WILAYAH KABUPATEN / KOTA, PEMBERIAN IZIN MENDIRIKAN
PEKERJAAN : REHABILITASI SEDANG/BERAT PENDOPO I
LOKASI : KABUPATEN BANGKALAN

VOLUME
NO ITEM PEKERJAAN DIMENSI PENGALI SATUAN
LAPANGAN
P L T/T
A. PEKERJAAN PERSIAPAN

I. PEKERJAAN PERSIAPAN
Pek. Pembongkaran Atap lama - 1.00 1.00 m2 -

Pek. Pembongkaran Dinding lama 0.60 0.10 1.00 m3 -

1 Pek. Bouwplank & Pengukuran H 8.00 1.00 0.25 2.00 m' 4.00
V 9.00 1.00 0.25 2.00 m' 4.50
8.50

4 Pek. Pembersihan Lokasi 8.00 9.00 1.00 1.00 m2 72.00


-
72.00

B. PEKERJAAN PERSIAPAN

LANTAI I
II PEKERJAAN TANAH

1 Galian Tanah Pondasi Setempat (PS -1) PS - 1 0.90 0.90 1.25 8.00 m3 8.10
PS - 2 0.70 0.70 1.25 3.00 m 3
1.84

Rabatan Bawah Sloop 20/30 (S - 1) H 12.40 0.40 0.10 1.00 m3 0.50


V 15.60 0.40 0.10 1.00 m 3
0.62
Bawah Sloop 15/25 (S - 2) H 10.60 0.40 0.10 1.00 m3 0.42
V 4.85 0.40 0.10 1.00 m3 0.19

11.68

2 Urugan pasir (t.10 cm) bawah pondasi PS - 1 0.90 0.90 0.10 8.00 m3 0.65
PS - 2 0.70 0.70 0.10 3.00 m3 0.15
0.80

3 Urugan kembali Dipakai 40% x Galian 11.68 1.00 1.00 40% m3 4.67

4.67

III PEKERJAAN PONDASI

1 Rabatan Beton bawah Plat Setempat & Sloop PS - 1 0.90 0.90 0.05 8.00 m3 0.32
PS - 2 0.70 0.70 0.05 3.00 m3 0.07

Rabatan Beton bawah Sloop Bawah Sloop 20/30 (S - 1) H 16.00 0.40 0.05 1.00 m3 0.32
V 21.00 0.40 0.05 1.00 m3 0.42
Bawah Sloop 15/25 (S - 2) H 12.00 0.40 0.05 1.00 m3 0.24
V 8.75 0.40 0.05 1.00 m3 0.18

1.55

2 Beton Plat Setempat Uk. 80.80.30 (PS - 1) 0.80 0.80 0.30 8.00 m3 1.54
1.54

3 Beton Plat Setempat Uk. 60.60.25 (PS - 2) 0.60 0.60 0.25 3.00 m3 0.27

0.27

5 Pas. Bata Ringan 4.20 1.00 0.30 2.00 m3 2.52

2.52

IV PEKERJAAN BETON
1 Beton Sloof (S1. 20/30) H 16.00 0.20 0.30 1.00 m3 0.96
V 21.00 0.20 0.30 1.00 m3 1.26
2.22

2 Beton Sloof (S2. 15/25) H 12.00 0.15 0.25 1.00 m3 0.45


V 8.75 0.15 0.25 1.00 m3 0.33
0.78

3 Beton Kolom ( K1. 20/25 ) Pedestal 0.20 0.25 0.75 8.00 m3 0.30
Penuh 0.20 0.25 4.05 8.00 m3 1.62
1.92

4 Beton kolom ( K2. 20/20 ) Pedestal 0.20 0.20 0.80 3.00 m3 0.10
Penuh 0.20 0.20 2.55 4.00 m 3
0.41

0.50

5 Beton kolom ( KP. 10/15 ) 0.10 0.15 4.05 5.00 m3 0.30

0.30

6 Beton Balok Latai ( BL. 10/15 ), Teras H 18.75 0.10 0.15 1.00 m3 0.28
V 2.75 0.10 0.15 1.00 m3 0.04
-
0.32

7 Beton Balok ( B1. 12/25 ), Teras H 8.00 0.12 0.25 1.00 m3 0.24
V 8.00 0.12 0.25 1.00 m 3
0.24
-
0.48

8 Beton Balok Rink ( RB. 10/20 ), Teras H 18.75 0.10 0.20 1.00 m3 0.38
V 2.75 0.10 0.20 1.00 m3 0.06
-
0.43

9 Plat Talang + Leuvel, 8 cm Plat Talang (Teras depan) 12.50 0.90 0.08 1.00 m3 0.90
Plat Leuvel (belakang) 4.80 0.50 0.08 1.00 m 3
0.19

1.09

V PEKERJAAN DINDING
LANTAI I
Total Panjang Dinding Horisontal A 7.40 1.00 3.70 1.00 m2 27.38
A' 2.65 1.00 3.70 1.00 m2 9.81
C 7.40 1.00 3.70 1.00 m 2
27.38

VERTIKAL 1 6.60 1.00 3.70 1.00 m2 24.42


3 2.54 1.00 3.70 1.00 m2 9.40
4 6.60 1.00 3.70 1.00 m 2
24.42

Peninggan (dumping Rangka Baja ringan) 30.00 1.00 0.20 1.00 m2 6.00
12.00 1.00 0.20 1.00 m 2
2.40

PENGURANGAN KUSEN P-1 1.70 1.00 2.25 (1.00) m2 (3.83)


PJ-1 0.90 1.00 2.25 (1.00) m2 (2.03)
0.70 1.00 1.60 (1.00) (1.12)
J-1 2.20 1.00 1.20 (5.00) m2 (13.20)
J-2 2.50 1.00 1.60 (1.00) m2 (4.00)
BV-1 2.20 1.00 0.50 (6.00) m2 (6.60)

100.43

2 Plesteran Semen Instan 100.43 1.00 1.00 2.00 m2 200.87


BUKAN KUSEN P-1 6.20 0.12 0.00 1.00 m 2
-
PJ-1 6.80 0.12 0.00 1.00 m2 -
J-1 6.80 0.12 0.00 5.00 m2 -
J-2 8.20 0.12 0.00 1.00 m2 -
BV-1 5.40 0.12 0.00 6.00 m2 -

200.87

3 Acian = LUAS PLESTERAN TOTAL 200.87 1.00 1.00 1.00 m2 200.87


Beton Kolom ( K1. 20/25 ) 0.65 - 4.05 8.00 m2 -
Beton kolom ( K2. 20/20 ) 0.80 - 2.55 3.00 m 2
-

200.87

VI PEKERJAAN ATAP

1 Rangka Atap Baja Ringan Elev 25° 7.900 8.150 1.0154 1.00 m2 65.38

65.38

2 Rangka Atap Baja Ringan (Teras) Elev 5° 8.260 2.000 1.0038 1.00 m2 16.58

16.58

3 Listplank woodplank 20 cm 7.900 1.000 1.0000 1.00 m2 7.90

7.90

4 Penutup Atap Bitumen Selulose Elev 10° 7.97 8.22 1.0154 1.00 m2 66.52
Elev 5° 8.33 2.07 1.0038 1.00 m2 17.31

83.83
5 Bubungan Atap Datar 1.00 1.00 1.00 - m' -
Miring 6.25 1.00 1.02 - m' -

Talang Jurai PVC Miring 1.00 1.02 - m' -

VII PEKERJAAN PLAFON


1 Pasang rangka Hollow Galvalum + Kalsiboard By CAD -
Luar Atap Utama 7.90
Luar Atap Teras 13.80

21.70

LIST DC
2 Pasang rangka plafond Hollow Galvalum + Gypsum Board 12 By CAD m' m'
Ruang Pembelajaran 46.65 -
Ruang Simpan 6.91 -

53.56 - - -

VIII PEKERJAAN LANTAI


LANTAI I
1 Urugan Pasir By CAD
Ruang Pembelajaran 46.65 1.00 0.200 1.00 m2 9.33
Ruang Simpan 6.91 1.00 0.200 1.00 m2 1.38
Teras 18.20 1.00 0.170 1.00 m 2
3.09

13.81

3 Rabat lantai t 5 cm 71.76 1.00 0.03 1.00 m3 2.15

4 Lapis Lantai 40 x 40 cm By CAD m' m'


Ruang Pembelajaran 46.65 1.00 1.000 1.00 m2 46.65
Ruang Simpan 6.91 1.00 1.000 1.00 m2 6.91

53.56
KD
5 LAPIS LANTAI TERAS
TERAS DEPAN 18.20 1.00 1.000 1.00 m2 18.20
18.20

5 KERAMIK DINDING

- m2 -
36.40

6 Granite Tile Kolom Bingkai P1 1.00 4.00 4.00 m2 -


1.00 2.00 3.80 m2 -
-

IX PEKERJAAN KUSEN
1 Pemasangan Kusen Pintu P2 1.00 Unit 1.00
2 Pemasangan Kusen Jendela J1 2.00 Unit 2.00
3 Pemasangan Kusen Bouvenlight BV 2 3.00 Unit 3.00

X. PEKERJAAN LISTRIK
1 Titik instalasi listrik + titik lampu Ttk
2 Pemasangan lampu SL 18 watt Bh
3 Pemasangan lampu SL 14 watt Bh
4 Pemasangan lampu Downlight outbow SL 14 watt Bh
5 Saklar ganda Bh
6 Saklar tungal Bh
7 stop kontak Bh
8 Stop Kontak AC Bh
9 Box panel listrik + mcb 4 grup lokal Bh

XI. PEKERJAAN PENGECATAN

XII PEKERJAAN SANITASI


1 Pipa PVC Ø 4" AW air kotor (Kloset) m'
2 Pipa PVC Ø 3" AW air Hujan 1.00 1.00 2.65 4.00 m' 10.60
3 Pipa PVC Ø 3/4" AW air bersih m'
4 Pengeboran Air Tanah Unit
5 Tandon Air Profil Tank (Kapasitas 1100 L ) Unit
6 Pompa air Unit
7 Pembuatan Rumah pompa Ls
8 Pembuatan cor tandon bawah Ls
9 Septictank + Resapan 3 Kompartemen Ukuran Sedang ( 2,60 x 1,10 x 1,20 ) Unit
XIII PEKERJAAN PENGECATAN
LANTAI II

IV PEKERJAAN BETON

1 Beton Kolom ( K1. 25/25 ) 0.25 4.93 17.00 m3 -


0.25 3.18 4.00 m 3
-

2 Beton Kolom ( K2. 15/25 ) 0.15 3.18 7.00 m3 -


0.15 4.93 1.00 m3 -

3 Beton kolom ( KP. 10/15 ) 0.15 4.93 6.00 m3 -


0.15 3.18 18.00 m3 -
Area Taman 0.15 0.55 7.00 m3 -

4 Beton Balok Latai ( BL. 10/15 ), TL


6.75 H 0.10 0.15 1.00 m3 -
V 0.10 0.15 1.00 m3 -
7.350 H 0.10 0.10 1.00 m 3
-
V 0.10 0.10 1.00 m3 -
8.5 H 0.10 0.15 1.00 m3 -
V 0.10 0.15 1.00 m3 -
Taman 0.10 0.15 1.00 m3 -
-
-

5 Beton Balok ( B2. 15/30 ), TL 7.350 H 0.15 0.25 1.00 m3 -


V 0.15 0.25 1.00 m 3
-
-
-

6 Beton Balok ( B3. 10/30 ), TL Bordes Tangga H 0.10 0.25 1.00 m3 -


V 0.10 0.25 1.00 m3 -
-
-

7 Plat Teras, 10 cm By CAD


Paimaman 1.00 0.10 1.00 m3 -
Teras Depan 1.00 0.10 1.00 m3 -
Oversetek Belakang 1.00 0.10 1.00 m3 -

5 Beton Balok ( B2. 15/30 ), TL 7.350 H 0.10 0.25 1.00 m3 -


V 0.10 0.25 1.00 m3 -
-
-

V PEKERJAAN DINDING
Total Panjang Dinding Horisontal 'A 1.00 3.05 1.00 m2 -
A 1.00 3.05 1.00 m2 -
1.00 1.75 1.00 m2 -
'A 1.00 2.85 1.00 m2 -
B' 1.00 4.80 1.00 m2 -
C 1.00 4.80 1.00 m 2
-
C 1.00 0.20 1.00 m2 -
Taman 1.00 0.40 1.00 m2 -

VERTIKAL '1 1.00 3.05 1.00 m2 -


1 1.00 4.80 1.00 m2 -
2' 1.00 4.80 1.00 m2 -
3 1.00 4.80 1.00 m2 -
3' 1.00 2.85 1.00 m2 -
4 1.00 4.80 1.00 m2 -
6 1.00 4.80 1.00 m 2
-
7 1.00 4.80 1.00 m2 -
8' 1.00 1.75 1.00 m2 -
9 1.00 3.05 1.00 m2 -
Taman 1.00 0.40 1.00 m2 -

PENGURANGAN KUSEN P1 1.00 2.40 (1.00) m2 -


P2 1.00 2.40 (2.00) m2 -
P3 1.00 2.00 (2.00) m2 -
J1 1.00 2.00 (6.00) m2 -
J2 1.00 2.40 (1.00) m 2
-
BV-1 1.00 0.60 (6.00) m2 -
BV-2 1.00 0.60 (7.00) m2 -
BV-2 1.00 0.60 (2.00) m2 -
PENGURANGAN Balok Latai 1.00 0.15 (1.00) m2 -

-
2 Plesteran Semen Instan 1.00 1.00 2.00 m2 -
BUKAN KUSEN P1 0.12 1.00 1.00 m2 -
P2 0.12 1.00 2.00 m2 -
P3 0.12 1.00 2.00 m2 -
J1 0.12 1.00 6.00 m2 -
J2 0.12 1.00 1.00 m 2
-
BV-1 0.12 1.00 6.00 m2 -
BV-2 0.12 1.00 7.00 m2 -
BV-2 0.12 1.00 2.00 m2 -
Pengurangan Keramik Dinding 1.00 1.00 (1.00) m2 -
Pengurangan Ornamen GRC 1.00 1.00 (1.00) m2 -
Pengurangan Pas. Roster 1.00 1.00 (1.00) m2 -

3 Acian = LUAS PLESTERAN TOTAL 1.00 1.00 1.00 m2 -


Beton Kolom ( K1. 25/25 ) 1.00 4.00 17.00 m 2
-
Beton Kolom ( K2. 15/25 ) 1.00 2.85 7.00 m2 -
Acian Balok Latai 1.00 0.15 2.00 m2 -

4 Ornamen GRC Kolom Musholla 1.00 5.00 2.00 m2 -


1.00 3.00 4.00 m2 -

5 Roster 1.00 1.00 2.60 m2 -

VI PEKERJAAN ATAP

1 Rangka Atap Baja Ringan Musholla 25 1.00 1.02 1.00 m2 -


65 1.00 2.37 1.00 m2 -
Aula 25 1.00 1.02 1.00 m2 -
55 1.00 1.74 1.00 m2 -

2 Penutup Genteng Keramik Musholla 25 1.00 1.02 1.00 m2 -


65 1.00 2.37 1.00 m2 -
Aula 25 1.00 1.02 1.00 m2 -
55 1.00 1.74 1.00 m2 -
-

3 Bubungan Atap Datar 1.00 1.00 1.00 m' -


Musholla 25 1.00 1.02 4.00 m2 -
65 1.00 2.37 4.00 m2 -
Aula 25 1.00 1.02 4.00 m2 -
55 1.00 1.74 4.00 m2 -

5 Listplank Woodplank 20cm Musholla 25 1.00 1.00 1.00 m2 -


65 1.00 1.00 1.00 m2 -
Aula 25 1.00 1.02 1.00 m2 -

6 Atap Sky Light Kaca Temperred 12 mm 1.00 1.00 1.00 m2 -

VII PEKERJAAN PLAFON


1 Pasang rangka Hollow Galvalum + Kalsiboard LIST DC
By CAD m' m'
Musholla 23.51
R.Aula 23.51

LIST DC
2 Pasang rangka plafond Hollow Galvalum + Gypsum Board 12 By CAD m' m'
Musholla 23.51 18.72

R.Aula 44.80 35.15


-

68.31 53.87 -

VIII PEKERJAAN LANTAI


LANTAI I
1 Urugan Pasir By CAD
Dalam Ruang 1.00 0.050 1.00 m2 -
Teras 1.00 0.050 1.00 m2 -
KM/WC & T. Wudlu 1.00 0.050 1.00 m2 -

-
2 LAPIS Lantai Granite Tile 60 x 60 cm By CAD m' m'
Musholla 1.00 1.000 1.00 m2 -
R. Aula 1.00 1.000 1.00 m2 -
0.20 1.00 1.00 m2 -

-
KD

3 LAPIS LANTAI TERAS By CAD


TERAS
Tangga & Bordes

4 LAPIS LANTAI KM/WC & Tempat Wudlu By CAD


KM/WC
T. Wudlu

5 KERAMIK DINDING By CAD


KM/WC
T. Wudlu

- m2 -
-

6 Granite Tile Kolom Bingkai P1 1.00 2.40 2.00 m2 -


1.80 1.00 1.00 m2 -
0.60 1.00 1.20 m2 -

IX PEKERJAAN KUSEN
1 Pemasangan Kusen Pintu P1 Unit -
2 Pemasangan Kusen Pintu P2 1.00 Unit 1.00
3 Pemasangan Kusen Pintu P3 (Km/wc) - Unit -
4 Pemasangan Kusen Pintu P4 (Km/wc) - Unit -
5 Pemasangan Kusen Jendela J1 2.00 Unit 2.00
6 Pemasangan Kusen Jendela J2 - Unit -
7 Pemasangan Kusen Bouvenlight BV 2 3.00 Unit 3.00

X. PEKERJAAN LISTRIK
1 Titik instalasi listrik + titik lampu Ttk
2 Pemasangan lampu SL 18 watt Bh
3 Pemasangan lampu SL 14 watt Bh
4 Pemasangan lampu Downlight outbow SL 14 watt Bh
5 Saklar ganda Bh
6 Saklar tungal Bh
7 stop kontak Bh
8 Stop Kontak AC Bh
9 Box panel listrik + mcb 4 grup lokal Bh

XI. PEKERJAAN PENGECATAN


1 Pengecatan Plafond 1.00 1.00 1.00 m2 -
2 Pengecatan Dalam ruang - 1.00 1.00 1.00 m 2
-
3 Pengecatan Luar ruang 1.00 4.40 0.70 m2 -
4 Pengecatan Listplank 0.30 1.00 1.00 m2 -

5 Coating Deck & Talang Beton #REF! 1.00 1.00 1.00 m2 -

XII PEKERJAAN SANITASI


1 Pipa PVC Ø 4" AW air kotor (Kloset) m'
2 Pipa PVC Ø 3" AW air kotor KM/WC m'
3 Pipa PVC Ø 3/4" AW air bersih m'
4 Pengeboran Air Tanah Unit
5 Tandon Air Profil Tank (Kapasitas 1100 L ) Unit
6 Pompa air Unit
7 Pembuatan Rumah pompa Ls
8 Pembuatan cor tandon bawah Ls
9 Septictank + Resapan 3 Kompartemen Ukuran Sedang ( 2,60 x 1,10 x 1,20 ) Unit
XIII PEKERJAAN PENGECATAN
BESTAT BESI
PEMBANGUNAN SARANA & PRASARANA SEKOLAH DASAR Dia.
KABUPATEN BANGKALAN 6
TAHUN 2021 8
10
12
30 13
BESTAT PEMBESIAN UNTUK TIAP 1 M3 M 16
1 LANTAI 1 19
22
No Uraian Panjang Jml. Tul Panjang Total Berat/M' Berat Total
1 2 3 4 5=3x4 6 7=5x6
1 1 BH BETON PLAT SETEMPAT ( PS1 800 x 800 x 300 mm (PS2) = 0.19 M3, 1 M3 (P1) = 5.21 BH
Tul. Vertikal
Tulangan Bawah Ø 12 - 150 mm 0.88 6.00 5.30 0.85 4.50
Tulangan Atas Ø 12 - 150 mm 1.36 6.00 8.18 0.85 6.95
Tul. Horisontal
Tulangan Bawah Ø 12 - 150 mm 0.88 6.00 5.30 0.85 4.50
Tulangan Atas Ø 12 - 150 mm 1.36 6.00 8.18 0.85 6.95

Berat Besi 1 Bh 22.90 Kg

Berat Besi 1 M3 119.28 Kg 119.00


2 1 BH BETON PLAT SETEMPAT ( PS2 600 x 600 x 250 mm (PS2) = 0.09 M3, 1 M3 (P1) = 11.11 BH
Tul. Vertikal
Tulangan Bawah Ø 12 - 175 mm 0.68 4.00 2.74 0.85 2.32
Tulangan Atas Ø 12 - 175 mm 1.06 4.00 4.26 0.85 3.61
Tul. Horisontal
Tulangan Bawah Ø 12 - 175 mm 0.68 4.00 2.74 0.85 2.32
Tulangan Atas Ø 12 - 175 mm 1.06 4.00 4.26 0.85 3.61

Berat Besi 1 M' 11.87 Kg

Berat Besi 1 M3 131.92 Kg 131.00


3 1 M' SLOOF ( S1 ) 200 x 300 mm (S1) = 0.06 M3, 1 M3 ( S1 ) = 16.67 M'
Tul. Utama Ø 13 mm 1.08 - - 1.00 0.00
7 Ø 12 mm 1.07 7.00 7.50 0.85 6.37
Sengkang Ø 8 - 150 mm 0.86 7.00 5.99 0.35 2.10

Berat Besi 1 M' 8.47 Kg

Berat Besi 1 M3 141.13 Kg 141.00


4 1 M' SLOOF ( S2 ) 150 x 300 mm (S1) = 0.05 M3, 1 M3 ( S1 ) = 22.22 M'
Tul. Utama 1 Ø 12 mm 1.07 1.00 1.07 0.85 0.91
5 Ø 10 mm 1.06 5.00 5.30 0.57 3.02
Sengkang Ø 8 - 150 mm 0.76 7.00 5.29 0.35 1.85

Berat Besi 1 M' 5.78 Kg

Berat Besi 1 M3 128.52 Kg 128.00


5 1 M' KOLOM ( K1 ) 300 X 400 mm (K1) = 0.12 M3, 1 M3 ( K1 ) = 8.33 M'
Tul. Utama 8 Ø 12 mm 1.07 8.00 8.58 0.85 7.28
Ø 10 mm 1.06 - - 0.57 0.00
Sengkang Ø 8 - 150 mm 1.30 7.00 9.07 0.35 3.18

Berat Besi 1 M' 10.46 Kg

Berat Besi 1 M3 87.14 Kg 87.00


6 1 M' KOLOM ( K2 ) 200 X 300 mm (K1) = 0.06 M3, 1 M3 ( K1 ) = 16.67 M'
Tul. Utama 6 Ø 12 mm 1.07 6.00 6.43 0.85 5.46
- Ø 10 mm 1.06 - - 0.57 0.00
Sengkang Ø 8 - 150 mm 0.90 7.00 6.27 0.35 2.20

Berat Besi 1 M' 7.66 Kg

Berat Besi 1 M3 127.60 Kg 127.00


7 1 M' KOLOM PRAKTIS ( KP ) 150 X 150 mm (K1) = 0.02 M3, 1 M3 ( K1 ) = 44.44 M'
Tul. Utama Ø 12 mm 1.07 - - 0.85 0.00
4 Ø 10 mm 1.06 4.00 4.24 0.57 2.42
Sengkang Ø 6 - 200 mm 0.47 6.00 2.83 0.20 0.57

Berat Besi 1 M' 2.99 Kg

Berat Besi 1 M3 132.84 Kg 132.00


8 1 M' BALOK STRUKTUR 20/50 ( B1 ) 200 x 500 mm (B1) = 0.10 M3, 1 M3 ( B1 ) = 10.00 M'
Tul. Utama 7 Ø 13 mm 1.08 7.00 7.55 1.00 7.54
2 Ø 12 mm 1.07 2.00 2.14 0.85 1.82
Sengkang Ø 8 - 125 mm 1.30 9.00 11.66 0.35 4.08

Berat Besi 1 M' 13.44 Kg

Berat Besi 1 M3 134.41 Kg 134.00


8 1 M' BALOK STRUKTUR 20/30 ( B1' ) 200 x 300 mm (B1) = 0.06 M3, 1 M3 ( B1 ) = 16.67 M'
Tul. Utama 5 Ø 13 mm 1.08 5.00 5.39 1.00 5.38
2 Ø 12 mm 1.07 2.00 2.14 0.85 1.82
Sengkang Ø 8 - 125 mm 0.90 9.00 8.06 0.35 2.82

Berat Besi 1 M' 10.03 Kg

Berat Besi 1 M3 167.12 Kg 167.00


9 1 M' BALOK STRUKTUR 12/25 ( B2 ) 150 x 250 mm (B1) = 0.04 M3, 1 M3 ( B1 ) = 26.67 M'
Tul. Utama 5 Ø 12 mm 1.07 5.00 5.36 0.85 4.55
2 Ø 10 mm 1.06 2.00 2.12 0.57 1.21
Sengkang Ø 8 - 125 mm 0.70 9.00 6.26 0.35 2.19

Berat Besi 1 M' 7.95 Kg

Berat Besi 1 M3 212.04 Kg 212.00


1 1 M' BALOK STRUKTUR 15/50 ( B2' ) 150 x 500 mm (B1) = 0.08 M3, 1 M3 ( B1 ) = 13.33 M'
Tul. Utama 7 Ø 12 mm 1.07 7.00 7.50 0.85 6.37
2 Ø 10 mm 1.06 2.00 2.12 0.57 1.21
Sengkang Ø 8 - 125 mm 1.20 9.00 10.76 0.35 3.77

Berat Besi 1 M' 11.35 Kg

Berat Besi 1 M3 151.29 Kg 151.00


10 1 M' BALOK LATAI 10/15 ( BL ) 100 x 150 mm (B1) = 0.02 M3, 1 M3 ( B1 ) = 66.67 M'
Tul. Utama Ø 13 mm 1.08 - - 1.00 0.00
4 Ø 10 mm 1.06 4.00 4.24 0.57 2.42
Sengkang Ø 6 - 200 mm 0.37 6.00 2.23 0.20 0.45

Berat Besi 1 M' 2.87 Kg

Berat Besi 1 M3 191.18 Kg 191.00


11 1 M' RINK BALOK 12/20 ( RB ) 150 x 150 mm (B1) = 0.02 M3, 1 M3 ( B1 ) = 44.44 M'
Tul. Utama Ø 13 mm 1.08 - - 1.00 0.00
4 Ø 12 mm 1.07 4.00 4.29 0.85 3.64
Sengkang Ø 8 - 150 mm 0.50 7.00 3.47 0.35 1.22

Berat Besi 1 M' 4.86 Kg

Berat Besi 1 M3 215.81 Kg 215.00

12 1 M' BALOK STRUKTUR 12/30 ( B3 ) 100 x 300 mm (B1) = 0.03 M3, 1 M3 ( B1 ) = 33.33 M'
Tul. Utama 5 Ø 12 mm 1.07 5.00 5.36 0.85 4.55
2 Ø 10 mm 1.06 2.00 2.12 0.57 1.21
Sengkang Ø 8 - 150 mm 0.70 7.00 4.87 0.35 1.71

Berat Besi 1 M' 7.46 Kg

Berat Besi 1 M3 248.81 Kg 248.00


2 LANTAI 2
No Uraian Panjang Jml. Tul Panjang Total Berat/M' Berat Total
1 2 3 4 5=3x4 6 7=5x6

1 1 BH PLAT LANTAI t : 120 mm 1000 x 1000 x 120 mm = 0.12 M3, 1 M3 PLAT = 8.33 BH
Tul. Utama
Tulangan Vertikal Ø 10 - 100 mm 1.37 11.00 15.07 0.57 8.59
Tulangan Horisontal Ø 10 - 100 mm 1.37 11.00 15.07 0.57 8.59
Tul. Bagi
Tulangan Vertikal Ø 8 - 100 mm 0.60 11.00 6.56 0.35 2.29
Tulangan Horisontal Ø 8 - 100 mm 0.60 11.00 6.56 0.35 2.29

Berat Besi 1 Bh 21.77 Kg

Berat Besi 1 M3 181.41 Kg 181.00


2 1 BH PLAT LANTAI t : 100 mm 1000 x 1000 x 100 mm = 0.10 M3, 1 M3 PLAT = 10.00 BH
Tul. Utama
Tulangan Vertikal Ø 10 - 150 mm 1.37 8.00 10.96 0.57 6.25
Tulangan Horisontal Ø - - 150 mm - 8.00 - 0.57 0.00
Tul. Bagi
Tulangan Vertikal Ø 8 - 200 mm 0.60 6.00 3.58 0.35 1.25
Tulangan Horisontal Ø - - 200 mm - 6.00 - 0.35 0.00

Berat Besi 1 Bh 7.50 Kg

Berat Besi 1 M3 74.99 Kg 74.00


3 1 BH PLAT LANTAI t : 150 mm 1000 x 1000 x 150 mm = 0.15 M3, 1 M3 PLAT = 6.67 BH
Tul. Utama
Tulangan Vertikal Ø 12 - 200 mm 1.39 6.00 8.36 0.85 7.10
Tulangan Horisontal Ø 12 - 200 mm 1.39 6.00 8.36 0.85 7.10
Tul. Bagi
Tulangan Vertikal Ø 10 - 200 mm 0.62 6.00 3.72 0.57 2.12
Tulangan Horisontal Ø 10 - 200 mm 0.62 6.00 3.72 0.57 2.12

Berat Besi 1 Bh 18.44 Kg

Berat Besi 1 M3 122.95 Kg 122.00


4 1 BH PLAT LANTAI t : 100 mm 1000 x 1000 x 70 mm = 0.07 M3, 1 M3 PLAT = 14.29 BH
Tul. Utama
Tulangan Vertikal Ø 8 - 200 mm 1.35 6.00 8.08 0.35 2.83
Tulangan Horisontal Ø 8 - 200 mm 1.35 6.00 8.08 0.35 2.83
Tul. Bagi
Tulangan Vertikal Ø 8 - 200 mm 0.60 6.00 3.58 0.35 1.25
Tulangan Horisontal Ø 8 - 200 mm 0.60 6.00 3.58 0.35 1.25

Berat Besi 1 Bh 8.16 Kg

Berat Besi 1 M3 116.52 Kg 116.00


5 1 M' BALOK LISTPLANK ( PL 1 ), 15 cm 150 x 500 mm (B1) = 0.08 M3, 1 M3 ( B1 ) = 13.33 M'
Tul. Atas 4 D 12 mm 1.07 4.00 4.29 0.85 3.64
Tul. Samping 4 Ø 10 mm 1.06 4.00 4.24 0.57 2.42
Tul. Bawah 4 D 12 mm 1.07 4.00 4.29 0.85 3.64
Sengkang Ø 6 - 150 mm 1.17 7.00 8.20 0.20 1.66

Berat Besi 1 M' 11.36 Kg

Berat Besi 1 M3 151.40 Kg 151.00


5 1 M' BALOK ( B2 ) 120 x 400 mm (B1) = 0.05 M3, 1 M3 ( B1 ) = 20.83 M'
Tul. Atas 4 D 10 mm 1.06 4.00 4.24 0.57 2.42
Tul. Samping 4 Ø 12 mm 1.07 4.00 4.29 0.85 3.64
Tul. Bawah 2 D 10 mm 1.06 2.00 2.12 0.57 1.21
Sengkang Ø 6 - 150 mm 0.91 7.00 6.38 0.20 1.29

Berat Besi 1 M' 8.56 Kg

Berat Besi 1 M3 178.24 Kg 178.00


PERHITUNGAN BIAYA SMK3

KEGIATAN : PENYELENGGARAAN BANGUNAN GEDUNG DI WILAYAH KABUPATEN / KOTA, PEMBERIAN IZIN MENDIRIKAN
PEKERJAAN : REHABILITASI SEDANG/BERAT PENDOPO I
LOKASI : KABUPATEN BANGKALAN
WAKTU PELAKSANAAN : 6 BULAN
NILAI PEKERJAAN : Rp 794,720,771.49

NO JENIS PEKERJAAN SAT VOLUME WAKTU HARGA SATUAN JUMLAH

1 2 3 4 5 6 7

1 Penyiapan RK3 terdiri atas :


a Pembuatan Manual, Prosedur, Instruksi Kerja, Ijin Kerja Dan Set 3.00 1 Rp 500,000.00 Rp 1,500,000.00
b Pembuatan Kartu Identitas Kerja (KIP) Lbr 95.00 1 Rp 5,000.00 Rp 475,000.00
Rp 1,975,000.00
2. Sosialisasi & Promosi RK3 terdiri atas :
a Induksi K3 (safety Induction) Org 95.00 1 Rp - Rp -
b. Pengarahan K3 (Safety Briefing) Org 95.00 1 Rp 10,000.00 Rp 950,000.00
c. Pelatihan K3 :
K3 Peralatan Konstruksi Org 1.00 1 Rp 7,500.00 Rp 7,500.00
Analysis Keselamatan Kerja Org 1.00 1 Rp 7,500.00 Rp 7,500.00
Perilaku Berbasis Keselamatan Org 1.00 1 Rp 7,500.00 Rp 7,500.00
P3K Org 2.00 1 Rp 1,750,000.00 Rp 3,500,000.00
d. Simulasi K3 Org 95.00 1 Rp 25,000.00 Rp 2,375,000.00
e. Spanduk (Banner) Lbr 5.00 1 Rp 350,000.00 Rp 1,750,000.00
f. Poster Lbr 5.00 1 Rp 150,000.00 Rp 750,000.00
g. Papan Informasi Bh 2.00 1 Rp 1,500,000.00 Rp 3,000,000.00
Rp 12,347,500.00
3. Alat Pelindung Kerja, terdiri Atas :
a Jaring Pengaman (Safety net) ls 1.00 1 Rp 5,000,000.00 Rp 5,000,000.00
b. Tali Pengaman (Life line) ls 1.00 1 Rp 1,000,000.00 Rp 1,000,000.00
c. Penahan Jatuh (Safety deck) ls 1.00 1 Rp 5,000,000.00 Rp 5,000,000.00
d. Pagar Pengaman (Safety Guard) ls 1.00 1 Rp 3,000,000.00 Rp 3,000,000.00
e. Pembatas Area (Restricted Area) ls 1.00 1 Rp 1,500,000.00 Rp 1,500,000.00
Rp 15,500,000.00
4. Alat Pelindung Diri, terdiri Atas :
a Helm Pelindung (safety helmet) Bh 100.00 1 Rp 50,000.00 Rp 5,000,000.00
b. Pelindung Mata (Googles, Spectacles) Psg 2.00 1 Rp 50,000.00 Rp 100,000.00
c. Tameng Muka (Face shield) Bh 2.00 1 Rp 175,000.00 Rp 350,000.00
d. Masker Selam (Breathing Apparatus) Bh - 1 Rp - Rp -
e. Pelindung Telinga (Ear Plug, Ear Muff) Psg 5.00 1 Rp 50,000.00 Rp 250,000.00
f. Pelindung Pernafasan Dan Mulut (Masker) Bh 100.00 1 Rp 10,000.00 Rp 1,000,000.00
g. Sarung Tangan Keselamatan (Safety Gloves) Psg 20.00 1 Rp 2,500.00 Rp 50,000.00
h. Sepatu Keselamatan (Safety Shoes), Karet Psg 100.00 1 Rp 95,000.00 Rp 9,500,000.00
i. Penunjang Seluruh Tubuh (Full Body Harness) Bh - 1 Rp 300,000.00 Rp -
j. Jaket Pelampung (Life Vest) Bh - 1 Rp 100,000.00 Rp -
k. Rompi Keselamatan (Safety Vest) Bh 100.00 1 Rp 30,000.00 Rp 3,000,000.00
l. Celemek (Apron/Coveralls) Bh 2.00 1 Rp 125,000.00 Rp 250,000.00
m. Pelindung Jatuh (Fall Arrester) Bh - 1 Rp 1,500,000.00 Rp -
Rp 19,500,000.00
5. Asuransi & Perijinan, terdiri Atas :
a BPJS Ketenagakerjaan Dan Kesehatan Kerja ls 1.00 1 Rp 8,450,000.00 Rp 8,450,000.00
b. Surat Ijin Kelaikan Alat Alat/Kend 1.00 1 Rp 4,500,000.00 Rp 4,500,000.00
c. Surat Ijin Operator Lbr/Alat 1.00 1 Rp 5,000,000.00 Rp 5,000,000.00

d. Surat Ijin Pengesahan Panitia Pembina Keselamatan Dan Kesehatan Kerja (P3K2) ls 1.00 1 Rp 500,000.00 Rp 500,000.00

Rp 18,450,000.00
6. Personil K3, terdiri Atas :
a Ahli K3 OB 1.00 6 Rp 7,000,000.00 Rp 42,000,000.00
b. Petugas K3 OB 1.00 6 Rp 4,000,000.00 Rp 24,000,000.00
c. Petugas Tanggap Darurat OB - 6 Rp 3,000,000.00 Rp -
d. Petugas P3K OB - 6 Rp 3,000,000.00 Rp -
e. Petugas Pengatur Lalu Lintas (Flagman) OB 1.00 6 Rp 3,000,000.00 Rp 18,000,000.00
f. Petugas Medis OB - 6 Rp 3,000,000.00 Rp -
Rp 84,000,000.00
7. Fasilitas Sarana Kesehatan, terdiri Atas :
a Peralatan P3K (Kotak P3K, Tandu, Tabung Oksigen, Obat Luka, Perban,dll) ls 1.00 1 Rp 3,000,000.00 Rp 3,000,000.00
b. Ruang P3K (Tempat Tidur Pasien, Stetoskop, Timbangan Berat Badan) ls 1.00 1 Rp 5,000,000.00 Rp 5,000,000.00
c. Peralatan Pengasapan (Fogging) unit 1.00 1 Rp 1,500,000.00 Rp 1,500,000.00
d. Obat Pengasapan Kali 4.00 6 Rp 25,000.00 Rp 600,000.00
Rp 10,100,000.00
8. Rambu - Rambu, terdiri dari :
a Rambu Petunjuk Bh 10.00 1 Rp 50,000.00 Rp 500,000.00
b. Rambu Larangan Bh 5.00 1 Rp 50,000.00 Rp 250,000.00
c. Rambu Peringatan Bh 10.00 1 Rp 50,000.00 Rp 500,000.00
d. Rambu Kewajiban Bh 5.00 1 Rp 50,000.00 Rp 250,000.00
e. Rambu Informasi Bh 5.00 1 Rp 50,000.00 Rp 250,000.00
f. Rambu Pekerjaan Sementara Bh 10.00 1 Rp 50,000.00 Rp 500,000.00
g. Tongkat Pengatur Lalu Lintas (Warning Light Stick) Bh 2.00 1 Rp 50,000.00 Rp 100,000.00
h. Kerucut Lalu Lintas (Traffic Cone) Bh 10.00 1 Rp 50,000.00 Rp 500,000.00
i. Lampu Putar (Rotary Lamp) Bh 2.00 1 Rp 100,000.00 Rp 200,000.00
Page 44
NO JENIS PEKERJAAN SAT VOLUME WAKTU HARGA SATUAN JUMLAH

1 2 3 4 5 6 7
j. Lampu Selang Lalu Lintas ls 1.00 1 Rp 1,000,000.00 Rp 1,000,000.00
Rp 4,050,000.00
9. Lain-lain Terkait Pengendaian Resiko K3, terdiri dari :
a Alat Pemadam Api Ringan (APAR) 5 Kg Bh 4.00 1 Rp 350,000.00 Rp 1,400,000.00
b. Sirine Bh 1.00 1 Rp 100,000.00 Rp 100,000.00
c. Bendera K3 Bh 2.00 1 Rp 50,000.00 Rp 100,000.00
d. Jalur Evakuasi (Escape Route) ls 1.00 1 Rp 500,000.00 Rp 500,000.00
e. Lampu Darurat (Emergency Lamp) Bh 4.00 1 Rp 70,000.00 Rp 280,000.00
f. Program Inspeksi Dan Audit Internal ls 1.00 1 Rp 1,500,000.00 Rp 1,500,000.00
g. Pelaporan Dan Penyidikan Insiden ls 1.00 1 Rp 500,000.00 Rp 500,000.00
Rp 4,380,000.00

Jumlah Total Rp 170,302,500.00

Page 45

Anda mungkin juga menyukai