PROGRESS BULANAN
PROGRESS BULAN LALU PROGRESS BULAN INI PROGRESS S/D BULAN INI
NO URAIAN PEKERJAAN KETERANGAN
JUMLAH BOBOT (%)
JUMLAH HARGA JUMLAH HARGA
VOLUME BOBOT (%) VOLUME JUMLAH HARGA (RP) BOBOT (%) VOLUME BOBOT (%)
(RP) (RP)
1 2 6 7 8 9 11 12 13 14 15 16 17
I PEKERJAAN PERSIAPAN 80.020.000,00 9,2345 - - 0,70 56.014.000,00 6,4642 0,70 56.014.000,00 6,4642 SEMENTARA DIKERJAKAN
II PEKERJAAN BONGKARAN DAN PERAPIHAN/PEMBERSIHAN EXISTING 4.806.420,00 0,5547 0,90 4.325.778,00 0,4992 0,90 4.325.778,00 0,4992 SEMENTARA DIKERJAKAN
III PEKERJAAN INTERIOR 108.919.269,00 12,5696 - - - - - - BELUM DIKERJAKAN
IV PEKERJAAN PINTU 91.869.432,00 10,6020 - - - - - - BELUM DIKERJAKAN
V PEKERJAAN FINISHING 16.981.728,00 1,9597 - - - - - - BELUM DIKERJAKAN
VI PEKERJAAN BRANDING 73.047.600,00 8,4299 - - - - - - BELUM DIKERJAKAN
VII PEKERJAAN SANITAIR 12.593.000,00 1,4533 - - - - - - BELUM DIKERJAKAN
VIII PEKERJAAN FURNITURE DAN KURSI 127.931.325,00 14,7637 - - - - - - BELUM DIKERJAKAN
IX PEKERJAAN MEKANIKAL DAN ELEKTRIKAL 345.332.700,00 39,8524 - - - - - - BELUM DIKERJAKAN
X PEKERJAAN LAIN-LAIN 5.027.500,00 0,5802 - - - - - - BELUM DIKERJAKAN
Page 1 of 1 MC01 PEMBANGUNAN RUANG GURU BESERTA PERABOTNYA SDN 012 SANDARAN