Anda di halaman 1dari 48

PEMERINTAH KOTA SINGKAWANG

DINAS TATA KOTA, PERTANAHAN DAN CIPTA KARYA


Jalan A. Yani No. 74 Telepon (0562) 638701 Fax. (0562) 638701
SINGKAWANG
Kode Pos 79123

HARGA PERHITUNGAN SENDIRI


(HPS)

PEKERJAAN :
PEMBANGUNAN WC UMUM DENGAN TANGKI SEPTIK
PANTI ASUHAN NURUL HAMID

LOKASI :
KOTA SINGKAWANG

SUMBER DANA :
DAU KOTA SINGKAWANG
TAHUN ANGGARAN 2016
REKAPITULASI HARGA
ENGINEER ESTIMATE (EE)

KEGIATAN : PENGELOLAAN DAN PENGEMBANGAN SISTEM AIR LIMBAH DOMESTIK DALAM DAERAH KABUPATEN/KOTA
SUB KEGIATAN : SUPERVISI/REHABILITASI/PENINGKATAN/PERLUASAN SISTEM PENGOLAHAN AIR LIMBAH DOMESTIK TERPUSAT SKALA PERMUKIMAN
PEKERJAAN : PEMBANGUNAN WC UMUM DENGAN TANGKI SEPTIK PANTI ASUHAN NURUL HAMID
LOKASI : KECAMATAN SAMBAS
TAHUN ANGGARAN : 2021

JUMLAH BIAYA TOTAL BIAYA


NO URAIAN PEKERJAAN
(Rp.) (Rp.)

I PEKERJAAN PENDAHULUAN 1,605,000.00

II PEKERJAAN PONDASI 14,735,225.84

III PEKERJAAN STRUKTUR 9,927,538.35

IV PEKERJAAN LANTAI, DINDING DAN PLAFOND 31,952,225.19

V PEKERJAAN ATAP 6,217,369.20

VI PEKERJAAN INSTALASI LISTRIK 1,306,000.00

VII PEKERJAAN INSTALASI AIR BERSIH & KOTOR 2,710,182.00

VIII PEK. TANGKI SEPTIK -

IX. PEKERJAAN DUDUKAN TANGKI AIR BERSIH 2,836,611.14

X. PEKERJAAN PENGECATAN 5,215,970.15

XI. PEKERJAAN LAIN - LAIN 1,782,500.00

JUMLAH 78,288,621.87
PPN 10% 6,214,460.49
JUMLAH TOTAL 84,503,082.36
DIBULATKAN 84,500,000.00
Terbilang : Enam Puluh Delapan Juta Tiga Ratus Lima Puluh Ribu Rupiah

Sambas, Juni 2021


Diperiksa Oleh : Dibuat Oleh :
Staff Teknis Konsultan Perencana
CV. GLOBAL MULTI KARYA

YUDHI DIAH MELIANI, ST


NIP. 19780514 200701 1 013 Team Leader

Mengetahui/ Menyetujui :
PEJABAT PEMBUAT KOMITMEN
( PPK )
HADI ISMANTO, ST
NIP. 19791011 200902 1 003
RENCANA ANGGARAN BIAYA

KEGIATAN : PENGELOLAAN DAN PENGEMBANGAN SISTEM AIR LIMBAH DOMESTIK DALAM DAERAH KABUPATEN/KOTA
SUB KEGIATAN : SUPERVISI/REHABILITASI/PENINGKATAN/PERLUASAN SISTEM PENGOLAHAN AIR LIMBAH DOMESTIK TERPUSAT SKALA PERMUKIMAN
PEKERJAAN : PEMBANGUNAN WC UMUM DENGAN TANGKI SEPTIK PANTI ASUHAN NURUL HAMID
LOKASI : KECAMATAN SAMBAS
TAHUN ANGGARAN : 2021

HARGA SUB TOTAL JUMLAH TOTAL


KODE
NO URAIAN PEKERJAAN VOLUME UNIT SATUAN HARGA HARGA
ANALISA
( Rp. ) ( Rp. ) ( Rp. )

1 2 3 4 5 6 7 8
I. PEKERJAAN PENDAHULUAN
1 Sistem Manajemen Keselamatan dan Kesehatan Kerja (SMK3) 1.000 Lsm Ls 855,000.00 855,000.00
2 Papan Nama Proyek 1.000 Lsm Ls 250,000.00 250,000.00
3 Pembersihan Lokasi 1.000 Lsm Ls 500,000.00 500,000.00
Sub Total I 1,605,000.00
II. PEKERJAAN PONDASI
1 Galian Tanah 4.968 M³ 2.3.1.1 123,481.25 613,454.85
2 Urugan Tanah Kembali 1.739 M³ 2.3.1.9.a 41,160.42 71,569.73
3 Urugan Pasir t = 10 cm 0.432 M³ 2.3.1.11.a 673,987.40 291,162.56
4 Cerucuk dia. 10-12 panjang 400 cm 48.000 Btg - 18,400.00 883,200.00
5 Lantai Kerja t = 5 cm 0.216 M³ 4.1.1.4. 2,197,075.87 474,568.39
6 Pek.Pondasi
- Pek. Beton Camp.1:2:3 0.648 M³ 4.1.1.7.a 2,480,270.20 1,607,215.09

- Pekerjaan Pembesian Dia. 10 mm 88.848 Kg 4.1.1.17 25,421.21 2,258,623.67

- Bekisting Pondasi 1.080 M² 4.1.1.20.a 192,376.49 207,766.60


7 Kolom Pondasi Beton Bertulang Uk. 15 x 15 cm
- Pek. Beton Camp.1:2:3 0.230 M³ 4.1.1.7.a 2,480,270.20 569,222.01

- Pekerjaan Pembesian Dia. 6 mm 12.787 Kg 4.1.1.17.a 20,832.71 266,392.03

- Pekerjaan Pembesian Dia. 10 mm 41.462 Kg 4.1.1.17 25,421.21 1,054,024.38

- Bekisting 2.520 M² 4.1.1.22.b 392,186.05 988,308.85


8 Sloof Beton Bertulang Uk.15/20 cm
- Pek. Beton Camp.1:2:3 0.765 M² 4.1.1.7.a 2,480,270.20 1,897,406.70

- Pekerjaan Pembesian Dia. 6 mm 26.573 Kg 4.1.1.17.a 20,832.71 553,595.94

- Pekerjaan Pembesian Dia. 10 mm 62.934 Kg 4.1.1.17 25,421.21 1,599,858.43

- Bekisting Sloof 3.506 M³ 4.1.1.21 228,860.35 802,441.60


9 Plesteran Tutup Kolong 5.100 M³ A.4.4.2.3. 116,944.12 596,415.01
Sub Total II 14,735,225.84
III. PEKERJAAN STRUKTUR
1 Kolom Beton Bertulang Uk. 15 x15 cm

- Pek. Beton Camp.1:2:3 0.702 M³ 4.1.1.7.a 2,480,270.20 1,741,149.68

- Pekerjaan Pembesian Dia. 6 mm 30.370 Kg 4.1.1.17.a 20,832.71 632,681.07

- Pekerjaan Pembesian Dia. 10 mm 77.002 Kg 4.1.1.17 25,421.21 1,957,473.84

- Bekisting Kolom 4.680 M² 4.1.1.22.b 392,186.05 1,835,430.73


2 Plesteran Kolom 9.360 M³ 4.4.2.3. 116,944.12 1,094,596.96
3 Ring Balok Beton Bertulang 10/10 cm
- Pek. Beton Camp.1:2:3 0.125 M³ 4.1.1.5.a 2,480,270.20 309,909.76

- Pekerjaan Pembesian Dia. 6 mm 10.629 Kg 4.1.1.17.a 20,832.71 221,438.37

- Pekerjaan Pembesian Dia. 10 mm 62.934 Kg 4.1.1.17 25,421.21 1,599,858.43

- Bekisting Balok 1.339 M³ 4.1.1.23.b 399,626.15 534,999.51


Sub Total III 9,927,538.35
IV. PEKERJAAN LANTAI, DINDING DAN PLAFOND
1 Urugan Pasir 2.500 M³ 2.3.1.11.a 673,987.40 1,684,968.50
2 Lantai Beton Bertulang

- Pek. Beton Camp.1:2:3 1.730 M³ 4.1.1.7.a 2,480,270.20 4,290,867.45


3 Keramik Lantai Wc/km Uk. 20 x 20 cm 10.340 M² A.4.4.3.36 344,807.51 3,565,309.68
4 Keramik Dinding Wc/Km Uk. 20 x 25 cm 8.250 M² A.4.4.3.54.a 362,583.57 2,991,314.48
5 Dinding Batako 31.338 M² 4.4.1.17.b 190,151.02 5,958,952.77
6 Kerawang rooster 16.000 Bh - 9,163.20 146,611.20
7 Plesteran Dinding Batako 62.676 M² 4.4.2.3. 116,944.12 7,329,589.61
8 Rangka Plafond 21.000 M² 4.2.1.21.b 214,860.25 4,512,065.25
9 Plafond GRC 21.000 M² 4.5.1.7.a 70,121.25 1,472,546.250
Sub Total IV 31,952,225.19
HARGA SUB TOTAL JUMLAH TOTAL
KODE
NO URAIAN PEKERJAAN VOLUME UNIT SATUAN HARGA HARGA
ANALISA
( Rp. ) ( Rp. ) ( Rp. )

1 2 3 4 5 6 7 8
V. PEKERJAAN ATAP
1 Rangka Atap 21.000 M² Ls 143,750.00 3,018,750.00
2 Pemasangan 1 m2 genteng metal 0.30 mm 21.000 M² A.4.5.2.40.e 152,315.20 3,198,619.20
Sub Total V 6,217,369.20
VI. PEKERJAAN INSTALASI LISTRIK
1 Lampu LED 4.000 Bh Ls 86,250.00 345,000.00
2 Saklar 3.000 Bh Ls 40,250.00 120,750.00
3 Stop Kontak 1.000 Bh Ls 40,250.00 40,250.00
4 Instalasi Listrik 8.000 Titik Ls 100,000.00 800,000.00
Sub Total VI 1,306,000.00
VII. PEKERJAAN INSTALASI AIR BERSIH & KOTOR
1 Instalasi Air Bersih
- Pipa 1/2" Aw 16.000 M' 5.1.1.25. 27,651.75 442,428.00
2 Instalasi Air Kotor
- Pipa 3" Aw 8.000 M' 5.1.1.31. 95,772.00 766,176.00
- Pipa 2" Aw 4.000 M' 5.1.1.29. 67,769.50 271,078.00
3 Kloset Jongkok 2.000 Set Ls 287,500.00 575,000.00
4 Kran Air 6.000 Bh Ls 74,750.00 448,500.00
5 Floor Drain 4.000 Bh Ls 51,750.00 207,000.00
Sub Total VI 2,710,182.00
IX. PEKERJAAN DUDUKAN TANGKI AIR BERSIH
1 Galian Tanah 0.720 M³ 2.3.1.1 123,481.25 88,906.50
2 Urugan Pasir t = 10 cm 0.432 M³ 2.3.1.11.a 673,987.40 291,162.56
3 Cerucuk dia. 10-12 panjang 400 cm 32.000 Btg - 18,400.00 588,800.00
4 Pengecoran Lantai Kerja 0.144 M³ 4.1.1.4. 2,197,075.87 316,378.92
5 Pasangan Batu Belah 15/20 CM 0.576 M³ A.3.2.1.1. 2,206,071.66 1,270,697.27
6 Plesteran Pasangan Batu Belah T= 15 mm 2.400 M3 4.4.2.3. 116,944.12 280,665.89

Sub Total IX 2,836,611.14


X. PEKERJAAN PENGECATAN
1 Cat Tembok 43.838 M² 4.7.1.10 71,614.30 3,139,427.46
2 Cat Tembok Luar 31.338 M² 4.7.1.10.c 66,262.77 2,076,542.69
Sub Total X 5,215,970.15
XI. PEKERJAAN LAIN - LAIN
1 Pintu Aluminium 2.000 Set Ls 667,000.00 1,334,000.00
2 Talang air 6.000 M Ls 74,750.00 448,500.00

Sub Total XI 1,782,500.00


JUMLAH SUB TOTAL 78,288,621.87

DIBULATKAN 78,288,000.00
BACK UP DATA QUANTITY

KEGIATAN : PENGELOLAAN DAN PENGEMBANGAN SISTEM AIR LIMBAH DOMESTIK DALAM DAERAH KABUPATEN/KOTA
PEKERJAAN : PEMBANGUNAN WC UMUM DENGAN TANGKI SEPTIK PANTI ASUHAN NURUL HAMID
LOKASI : KECAMATAN SAMBAS
TAHUN ANGGARAN : 2021

NO URAIAN PEKERJAAN VOLUME SATUAN KETERANGAN

1 2 3 4 5

Jlh Pondasi = 12.00 Bh Uk = 0.60 x 0.60 M


Kedalaman = 1.00 M
Jarak begel = 0.15 M Bekisting = 4.00 x pakai
T Cor Pondasi = 0.15 M
T Kolom = 2.60 M Luas = 2.50 x 5.00 M
Dimensi Pondasi = 0.150 0.150
Panjang Sloof = 25.50 M Uk = 0.15 x 0.20 M
Dimensi Kolom = 0.150 0.150

I. PEKERJAAN PENDAHULUAN
1 Pembersihan dan Pembongkaran 1.00 Lsm 1.00 = 1.00 Lsm
2 Papan Nama Proyek 1.00 Lsm 1.00 = 1.00 Lsm

II. PEKERJAAN PONDASI Tinggi Jlh Koef


1 Galian Tanah 4.97 M³ 1.15 x 0.60 x 0.60 12.00 = 4.97 M³
2 Urugan Tanah Kembali 1.74 M³ 4.97 x 0.35 = 1.74 M³
3 Urugan Pasir t = 10 cm 0.43 M³ 0.10 x 0.60 x 0.60 12.00 = 0.43 M³
4 Cerucuk dia. 10-12 panjang 400 cm 48.00 Btg 4.00 x 12.00 = 48.00 Btg
5 Lantai Kerja t = 5 cm 0.22 M³ 0.05 x 0.60 x 0.60 12.00 = 0.22 M³
6 Pek.Pondasi
- Pek. Beton Camp.1:2:3 0.65 M³ 0.15 x 0.60 x 0.60 12.00 = 0.65 M³

- Pekerjaan Pembesian Dia. 10 mm 88.85 Kg 10.00 x 0.60 12.00 2.00 Lapis 0.617 = 88.85 Kg

- Bekisting Pondasi 1.08 M² 0.15 x 2.40 / 4.00 x pakai 12.00 = 1.08 M²


7 Kolom Pondasi Beton Bertulang Uk. 15 x 15 cm
- Pek. Beton Camp.1:2:3 0.23 M³ 0.85 x 0.15 x 0.15 12.00 = 0.23 M³

- Pekerjaan Pembesian Dia. 6 mm 12.79 Kg 8.00 x 0.60 12.00 0.222 = 12.79 Kg

- Pekerjaan Pembesian Dia. 10 mm 41.46 Kg 1.40 x 4.00 12.00 0.617 = 41.46 Kg

- Bekisting 2.52 M² 1.40 x 0.60 / 4.00 x pakai 12.00 = 2.52 M²


8 Sloof Beton Bertulang Uk.15/20 cm
- Pek. Beton Camp.1:2:3 0.77 M² 0.200 x 0.150 x 25.50 = 0.77 M²

- Pekerjaan Pembesian Dia. 6 mm 26.57 Kg 171.00 x 0.70 0.222 = 26.57 Kg

- Pekerjaan Pembesian Dia. 10 mm 62.93 Kg 25.50 x 4.00 0.617 = 62.93 Kg

- Bekisting Sloof 3.51 M³ 25.50 x 0.55 / 4.00 x pakai = 3.51 M²


9 Plesteran Tutup Kolong 5.10 M³ 25.50 x 0.20 = 5.10 M²

III. PEKERJAAN STRUKTUR


1 Kolom Beton Bertulang Uk. 15 x15 cm

- Pek. Beton Camp.1:2:3 0.70 M³ 2.60 x 0.150 x 0.150 12.00 = 0.70 M³

- Pekerjaan Pembesian Dia. 6 mm 30.37 Kg 19.00 x 0.60 12.00 0.222 = 30.37 Kg

- Pekerjaan Pembesian Dia. 10 mm 77.00 Kg 2.60 x 4.00 12.00 0.617 = 77.00 Kg

- Bekisting Kolom 4.68 M² 2.60 x 0.60 / 4.00 x pakai 12.00 = 4.68 M²


2 Plesteran Kolom 9.36 M³ 2.60 x 0.30 12.00 = 9.36 M²
3 Ring Balok Beton Bertulang 10/10 cm
- Pek. Beton Camp.1:2:3 0.12 M³ 0.070 x 0.070 x 25.50 = 0.12 M³

- Pekerjaan Pembesian Dia. 6 mm 10.63 Kg 171.00 x 0.28 0.222 = 10.63 Kg

- Pekerjaan Pembesian Dia. 10 mm 62.93 Kg 25.50 x 4.00 0.617 = 62.93 Kg

- Bekisting Balok 1.34 M³ 25.50 x 0.21 / 4.00 x pakai = 1.34 M²

IV. PEKERJAAN LANTAI, DINDING DAN PLAFOND


1 Urugan Pasir 2.50 M³ 0.20 x 2.50 x 5.00 = 2.50 M³
2 Lantai Beton Bertulang

- Pek. Beton Camp.1:2:3 1.25 M³ 0.10 x 2.50 x 5.00 = 1.25 M³


3 Keramik Lantai Wc/km Uk. 20 x 20 cm 10.34 M² 4.70 x 2.20 = 10.34 M²
4 Keramik Dinding Wc/Km Uk. 20 x 25 cm 8.25 M² 11.00 x 0.75 = 8.25 M²

5 Dinding Batako 31.34 M² 2.60 x 10.13 = 26.34 = 31.34 M²


1.00 x 5.00 = 5.00

6 Plesteran Dinding Batako 62.68 M² 31.34 x 2.00 = 62.68 M²


7 Rangka Plafond 21.00 M² 3.50 x 6.00 = 21.00 M²
8 Plafond GRC 21.00 M² 3.50 x 6.00 = 21.00 M²
NO URAIAN PEKERJAAN VOLUME SATUAN KETERANGAN

1 2 3 4 5
V. PEKERJAAN ATAP
1 Rangka Atap 21.00 M² = 21.00 M²
2 Atap steel sheet 0.30 lurus 0,30 21.00 M² 3.50 x 6.00 = 21.00 M²

VII. PEKERJAAN INSTALASI AIR BERSIH & KOTOR


1 Instalasi Air Bersih
- Pipa 1/2" Aw 16.00 M' 16.00 = 16.00 M'
2 Instalasi Air Kotor
- Pipa 3" Aw 8.00 M' 8.00 = 8.00 M'
- Pipa 2" Aw 4.00 M' 4.00 = 4.00 M'
3 Kloset Jongkok 2.00 M' 2.00 = 2.00 Bh
5 Kran Air 6.00 Unit 3.00 + 3.00 6.00 Unit
6 Floor Drain 4.00 Unit 4.00 4.00 Unit
7 Washtafel lengkap 1.00 Unit 1.00 1.00 Unit
8 Pek. Tangki Septik
- Galian Tanah 6.75 M³ 1.50 x 1.50 x 3.00 = 6.75 M³
- Urugan Pasir t = 10 cm 0.45 M³ 0.10 x 1.50 x 3.00 = 0.45 M³
- Cerucuk dia. 10-12 panjang 400 cm 45.00 Btg 45.00 x 1.00 = 45.00 Btg
- Lantai Kerja t = 5 cm 0.23 M³ 0.05 x 1.50 x 3.00 = 0.23 M³
Pek. Lantai Kerja
- Pek. Beton Camp.1:2:3 0.45 M³ 0.10 x 1.50 x 3.00 = 0.45 M³
Pek. Tutup Tangki Septik
- Pek. Beton Camp.1:2:3 0.68 M³ 0.15 x 1.50 x 3.00 = 0.68 M³
Pekerjaan Perpipaan
- Pipa 3" Aw 4.00 M' = 4.00 M'
- Pipa 2" Aw 4.00 M' = 4.00 M'
- Pipa 1/2" Aw 2.00 M' = 2.00 M'
- Tee 3" Aw 1.00 Bh = 1.00 Bh
- Tee 2" Aw 2.00 Bh = 2.00 Bh

VIII. PEKERJAAN PENGECATAN


1 Cat Tembok 52.34 M² 62.68 / 2.00 = 31.34 M²
21.00 = 21.00 -
2 Cat Tembok Luar 31.34 M² 62.68 / 2.00 = 31.34 M²

IX. PEKERJAAN LAIN - LAIN


STANDARISASI HARGA UPAH KERJA

HARGA SATUAN
NO. JENIS DAN NAMA BARANG/JASA SATUAN KET
(Rp.)

1 2 3 4 5
A. STANDAR UPAH KERJA

1 Kepala Tukang Hari 238,050.00


2 Mandor Hari 178,250.00

3 Mekanik Hari 177,726.75

4 Mekanik Pembantu Hari 141,136.05


5 Operator (semi terlatih) Hari 146,363.95

6 Operator (terlatih) Hari 177,726.75


7 Pekerja Hari 158,700.00

8 Pembantu Operator Hari 141,136.05


9 Pembantu Sopir/kenek Hari 141,136.05

10 Penjaga Malam Hari 120,226.75

11 Sopir Hari 177,726.75


12 Tukang Hari 172,500.00

121
STANDAR HARGA SATUAN DASAR BAHAN

HARGA SATUAN
NO MATERIAL SATUAN
(Rp)

A. BAHAN PENGISI
1 Batu Kong M³ 741,681.00###
2 Batu pecah 15-20 cm M³ 794,817.27###
3 Batu pecah 10-15 cm M³ 783,196.00###
4 Batu pecah 5-7 cm M³ 874,299.00###
5 Batu pecah 3-5 cm M³ 901,945.00###
6 Batu pecah 2-3 cm M³ 792,810.00###
7 Batu pecah 1-2 cm M³ 1,163,800.00###
8 Pasir Beton M³ 881,484.20###
9 Pasir Pasang (Halus) M³ 881,484.20###
10 Pasir Urug M³ 520,495.75###
11 Semen PC Zak 108,928.00
12 Semen PC Kg 2,178.56
13 Tanah Datang M³ 492,792.25
14 Batako 20 x 40 x 7 cm Bh 4,945.00
15 Kerawang ( roster ) 20 x 20 cm Bh 9,163.20
16 Kerawang ( roster ) 30 x 30 cm Bh 84,841.25
17 Keramik Lantai 20 x 20 cm Ktk 86,595.00
18 Keramik 30 x 30 cm Ktk 97,290.00
19 Keramik 40 x 40 cm Ktk 98,900.00
20 List Keramik WC. 8 x 20 cm Bh 5,750.00
21 Keramik dinding 20 x 25 cm Ktk 86,710.00
-
B. BAHAN KAYU -
1 Ky Klas I :18/18-20/20cmx4m M³ 5,577,684.00
2 Kayu Kls II 4/6 cm x 4 m M³ 4,509,150.00
3 Kayu Kls II 3/5 cm x 4 m M³ 6,314,650.00
4 Kayu Kls III M³ 3,450,000.00
5 Papan mal klas III M³ 2,803,700.00
6 Kayu cerucuk /dolken ø 6 - 8 - Pj. 4 M Btg 16,008.00
7 Kayu cerucuk /dolken ø 8 - 10 - Pj. 4 M Btg 18,400.00
8 Air Ltr 40.00
-
C. BAHAN CAT -
1 Amplas Lbr 7,178.30
2 Plamur tembok Kg 43,725.30
3 Cat Dasar Kg 104,420.00
4 Cat kilat Kg 85,396.70
5 Cat tembok interior Kg 156,630.00
6 Cat tembok eksterior Kg 176,208.75
7 Oker Kg 28,750.00
8 Kuas" Bh 28,750.00
9 Water Proofing Kg 156,078.00
10 Thiner Kg 50,600.00
-
HARGA SATUAN
NO MATERIAL SATUAN
(Rp)

D. BAHAN BESI DAN ALUMINIUM -


1 Besi Tulangan Beton Dia. 6 mm Kg 16,721.00
2 Besi Tulangan Beton Dia. 8 mm Kg 16,721.00
3 Besi Tulangan Beton Dia. 10 mm Kg 16,721.00
4 Besi Tulangan Beton Dia. 13 mm Kg 21,091.00
5 Besi wire mesh ø 5 Kg 33,752.50
6 Kawat baja/bendrat Kg 47,955.00
7 Rangka Plafond M1 10,925.00
-
E. BAHAN PENGGANTUNG -
1 Pintu Aluminium Bh 667,000.00
2 Handle Pintu Bh 229,724.00
3 Engsel pintu Bh 39,809.55
4 Slot pintu Bh 25,451.80
5 Kunci tanam biasa Bh 11,500.00
6 Paku Seng Kg 58,190.00
7 Paku campuran 1" - 5 " Kg 31,970.00
8 Paku beton Kg 56,197.05
9 Paku GRC Kg 39,100.00
10 Paku Zincalum Kg 42,550.00
11 Sekrup Gibsum Kg 86,181.00
12 Sekrup Zincalume Bh 747.50
-
F. BAHAN ATAP -
1 Genteng Metal 0.30 Lbr 90,447.50
2 Genteng Metal 0.25 Lbr 75,555.00
3 Nok bubungan genteng metal 1/2 lingkaran 0.35 (pj 40cm) Bh 57,500.00
4 Seng Gelombang Bjls 20 Lbr 63,250.00
5 Seng Plat Bjls 20 Lbr 51,750.00
6 Zincalume Plat 0.2 Lbr 97,750.00
7 Rangka Plafond Metal Furing + Pemasangan M2 218,500.00
-
G. BAHAN KACA -
1 Kaca Polos, t = 5 mm M² 161,000.00
2 Sealent Kg 178,250.00
-
H. BAHAN TRIPLEK -
1 Multiplex t = 4 mm Lbr 111,573.00
2 Multiplex t = 9 mm Lbr 213,555.00
3 Panel GRC 120 x 240 x 40 Lbr 107,812.50
4 GypsumBoard t = 9mm Lbr 121,509.00
5 Lisplank Woodplank Lbr -
-
I. BAHAN SANITASI -
1 Wastafel Bh 414,000.00
2 Kloset jongkok Bh 287,500.00
3 Bak air fibreglass Bh 391,575.00
4 Floordrain Bh 51,750.00
5 Sealtape Bh 25,300.00
6 Kran air uk 1/2" Bh 74,750.00
HARGA SATUAN
NO MATERIAL SATUAN
(Rp)

7 Pipa PVC dia 1/2" AW Btg 25,300.00


8 Pipa PVC dia 3/4" AW Btg 40,250.00
9 Pipa PVC dia 1" AW Btg 52,900.00
10 Pipa PVC dia 2" AW Btg 105,800.00
11 Pipa PVC dia 3" AW Btg 143,750.00
12 Pipa PVC dia 4" AW Btg 299,000.00
13 Stop kran dia 1/2" Bh 59,388.30
14 Stop kran dia 3/4" Bh 73,746.05
15 Tangki air 1000 liter Bh 1,667,500.00
16 Tangki air 2000 liter Bh 2,875,000.00
17 Tangki air 250 liter Bh 517,500.00
18 Tangki air 500 liter Bh 977,500.00
19 Tee 4" Bh 63,250.00
20 Tee 2" Bh 40,250.00
-
J. BAHAN ALAT-ALAT LISTRIK -
1 Lampu LED Bh 86,250.00
2 Saklar Bh 40,250.00
3 Stop Kontak Bh 40,250.00
DAFTAR HARGA BAHAN BANGUNAN
UNTUK TAHUN 2016

HARGA
NO. UPAH SPESIFIKASI SATUAN
SATUAN
1 2 3 4

1 Pekerja Hari / Org 69,600.00


2 Tukang Hari / Org 97,600.00
3 Mandor Hari / Org 111,200.00
4 Kepala Tukang Hari / Org 118,400.00

HARGA
NO. JENIS DAN NAMA BARANG SPESIFIKASI SATUAN
SATUAN
1 2 3 4 5
A. BATU, PASIR DAN TANAH
1 Batu Pecah 10 - 15 cm m³ 200,000
5 - 7 cm m³ 200,000
3 - 5 cm m³ 320,976
2 - 3 cm m³ 200,000
1 - 2 cm m³ 400,000
1 - 1 cm m³ 450,000
0.5 - 1 cm m³ 446,600
2 Debu Batu 0 - 0.5 cm m³ 355,336
3 Greece / Serbi - Kg 37,170
2 Pasir Beton - m³ 116,667
3 Pasir Pasang - m³ 116,667
4 Pasir Urug - m³ 83,333
5 Sirtu - m³ 189,800
6 Tanah Urugan biasa m³ 36,667
pilihan m³ 227,790
9 Tanah/batu Kong - 1 Truck 3 m³ 116,667

B. BAHAN CETAKAN
1 Batako uk. 20 x 40 x 7 cm bh 2,000
HARGA
NO. JENIS DAN NAMA BARANG SPESIFIKASI SATUAN
SATUAN
1 2 3 4 5
2 Paving Blok K-300 bh 3,150

C. BAHAN PEREKAT
1 Semen PC 50 kg 1 zak 75,000
HARGA
NO. JENIS DAN NAMA BARANG SPESIFIKASI SATUAN
SATUAN
1 2 3 4 5
E. BAHAN PENUTUP ATAP
1 Genteng Metal Prima t. 0,3 mm Lembar 40,000
2 Seng Datar
Warna BJLS 0.20 Lembar 35,000
3 Zincalume t.0,3 mm tipe panjang M2 46,000
4 Lisplank GRC + Pemasangan ex. Woodplank, 0.2 x 4 m M 17,000

F. BAHAN KAYU
1 Cerucuk dia. 6-8 cm,panjang 400 cm btg 8,000
dia. 8-10 cm,panjang 400 cm btg 18,400
10-12 cm, panjang 400 cm btg
15-20 cm,panjang 1200 cm btg 150,000
2 Kayu KELAS BELIAN
Balok (ketam) m³ 13,775,510
KELAS I
Balok (ketam) m³ 7,142,857
Papan (ketam) m³ 11,574,074
KELAS II
Balok 4/6 cm m³ 4,166,667
Balok 5/10 cm m³ 8,750,000
KELAS III
Balok m³ 1,250,000
Papan m³ 1,759,259

H. BAHAN LANTAI DAN DINDING


KERAMIK

1 Keramik POLOS KW 1
20 x 20 cm Kotak/m2 80,000
20 x 25 cm Kotak/m 2
80,000
40 x 40 cm (Decogress) Kotak/m 2
150,000
HARGA
NO. JENIS DAN NAMA BARANG SPESIFIKASI SATUAN
SATUAN
1 2 3 4 5
60 x 60 cm (Decogress) Kotak/m2 255,000
I. BAHAN BESI DAN BAJA -
1 Baja Tegangan leleh 100 kg/cm2 Kg -
2 Besi Siku rata-rata btg -
Hollow 40.40.4 mm btg -
Hollow 80.40.4 mm btg -
Tempa M2 -
3 Besi Plat Polos (2 mm) Lembar -
Kembang (2 mm) Lembar -
Rata-rata 1 s.d 5 mm Kg -
Rata-rata 6 s.d 10 mm Kg -
Rata-rata 11 s.d 15 mm Kg -
2 Besi Tulangan Beton POLOS Kg 6,857
ULIR Kg 7,105
Besi Wiremesh Kg 8,285
3 Rangka Atap Baja Ringan harga terpasang, termasuk paku m2 127,000
ripet dan acc. Ex Smart truss;
Prima Truss

J. BAHAN ALUMINIUM
1 Kusen Aluminium 3" Silver Alm. 3" m 70,200
2 Kusen Alm. 3" PC m 80,000
5 Rangka Pintu Alm. CA m 140,400
6 Rangka Pintu Alm. PC m 153,000
9 Handle Pintu ex Solid; termasuk Kunci set 120,000

K. ALAT PENGUNCI DAN PENGGANTUNG


1 Engsel Uk. 3" Pasang 15,000
Uk. 4" Pasang 30,000
2 Kunci Double Slagh Besar Buah 140,000
3 Paku Paku Atap Seng Kg 20,000
4 Screw Zincalume - Bh 500.00
HARGA
NO. JENIS DAN NAMA BARANG SPESIFIKASI SATUAN
SATUAN
1 2 3 4 5
L. LANGIT - LANGIT
1 Gipsum 9 mm Lembar 66,000
2 GRC / Asbes / Kalsiboard 1,2 X 2,4 X 0,04 M Lembar 52,000
HARGA
NO. JENIS DAN NAMA BARANG SPESIFIKASI SATUAN
SATUAN
1 2 3 4 5
M. BAHAN SANITARI
1 Kloset Duduk Komplet dan Acc Unit 2,009,000
2 Kloset Jongkok Komplet dan Acc Buah 259,000
3 Pipa PVC dia 1/2" AW ex Wavin Btg 18,000
4 Pipa PVC dia 3/4" AW ex Wavin Btg 24,000
5 Pipa PVC dia 1" AW ex Wavin Btg 30,000
6 Pipa PVC dia 2" AW ex Wavin Btg 65,000
7 Pipa PVC dia 3" AW ex Wavin Btg 127,000
8 Pipa PVC dia 4" AW ex Wavin Btg 200,000
9 Tangki Air 1000 L Setara Penguin Bh 1,650,000
10 Pompa Jet Pump Kap. 250 Watt Bh 450,000

P. BAHAN PENUTUP ATAP


1 Zincalume t.0,2 mm tipe panjang m2 46,000
2 Seng Plat BJLS 20 L. 90 cm Lbr 35,000

Q. KAWAT / MESH
1 Kawat Bendrat Kawat Beton kg 15,000

R. BAHAN KACA
3 Kaca Polos Uk. 5 mm M2 50,000

S. BAHAN PAKU DAN MUR BAUT


1 Paku Paku Campur 1" - 5" Kg 12,000
Paku Belian Kg 20,000
Paku Triplek Kg 20,000
Paku Jembatan Kg 20,000
Paku GRC Kotak 20,000
Paku Gipsum Kotak 35,000
HARGA
NO. JENIS DAN NAMA BARANG SPESIFIKASI SATUAN
SATUAN
1 2 3 4 5
T. BAHAN FINISHING / CAT
1 Amplas Amplas Kayu Lembar 2,000
2 Cat Dasar ex Mowilex Kg 86,000
3 Cat Interior ex Mowilex Kg 92,000
4 Cat Eksterior ex Mowilex Kg 114,000
5 Cat Cat Kilat Kg 55,000
6 Dempul Besi/Kayu Kg 41,400
7 Kwas Cat - Buah 18,000
8 Oker - Kg 15,000
9 Plamir Tembok Kg 15,000
10 Thiner ND Kg 16,000
11 Meni - Kg 52,440

U. BAHAN PEMBANTU
1 Lem Kayu kg 16,471
2 Seal tape bh 5,490
3 Pelumas Ltr 3,330
4 Sealent Kg 24,000
5 Sewa Molen Hari 200,000

BAHAN ALAT-ALAT LISTRIK


Traffo HPL-N 80 Watt Buah 104,960.00
Traffo HPL-N 125 Watt Buah 136,408.00
Traffo BSN SON T 400 Watt Buah 461,824.00
Traffo BSN SON T 250 Watt Buah 262,360.00
Traffo BSN SON T 150 Watt Buah 185,000.00
Traffo BSN 'SON T 70 Watt Buah 125,000.00
Traffo Neon 40 Watt Buah 35,000.00
Traffo Neon 20 Watt Buah 35,000.00
HPL-N 80 Watt Buah 33,523.20
HPL-N 125 Watt Buah 37,753.60
Bola Lampu SON 400 Watt Buah 136,408.00
HARGA
NO. JENIS DAN NAMA BARANG SPESIFIKASI SATUAN
SATUAN
1 2 3 4 5
Bola Lampu SON 250 Watt Buah 125,952.00
Bola Lampu SON 150 Watt Buah 125,000.00
Bola Lampu SON 70 Watt Buah 120,000.00
Bola Lampu HPIT 400 Watt Buah 247,673.60
Pijar 5 Watt Buah 3,000.00
Pijar 25 Watt Buah 4,000.00
Pijar 40 Watt Buah 4,000.00
Pijar 60 Watt Buah 4,000.00
Pijar 75 Watt Buah 5,000.00
Pijar 100 Watt Buah 5,000.00
Neon 40 Watt Buah 16,000.00
Neon 20 Watt Buah 13,000.00
Neon 10 Watt Buah 10,000.00
Lampu Fisikom 25 Watt Buah 55,000.00
Lampu Fisikom 23 Watt Buah 40,000.00
Lampu Fisikom 18 Watt Buah 38,000.00
Lampu Par LED 54 x 1 Watt Buah 1,750,000.00
Lampu LED Philips 3 Watt / 3,5 Watt Buah 30,000.00
Lampu LED Philips 4 Watt Buah 35,000.00
Lampu LED Philips 5 Watt Buah 60,000.00
Lampu LED Philips 6 Watt Buah 50,000.00
Lampu LED Philips 7 Watt / 7,5 Watt 65,000.00
Lampu LED Philips 9 Watt Buah 75,000.00
Lampu LED Philips 10 Watt Buah 100,000.00
Lampu LED Philips 10,5 Watt Buah 105,000.00
Lampu LED Philips 12,5 Watt Buah 110,000.00
Lampu LED Philips 13 Watt / 14 Watt Buah 120,000.00
Lampu LED Philips 18 Watt Buah 160,000.00
NYY 2 x 1.5 mm Meter 10,000.00
NYY 3 x 2.5 mm Meter 16,000.00
NYY 3 x 1,5 mm Meter 12,000.00
NYY 3 x 6 mm Meter 35,000.00
HARGA
NO. JENIS DAN NAMA BARANG SPESIFIKASI SATUAN
SATUAN
1 2 3 4 5
NYY 2 x 2.5 mm Meter 12,000.00
NYY 2 x 4 mm Meter 22,000.00
NYY 2 x 6 mm Meter 23,067.20
NYY 2 x 10 mm Meter 33,523.20
NYY 3 x 4 mm Meter 24,000.00
NYY 4 x 2.5 mm Meter 20,000.00
NYY 4 x 4 mm Meter 30,000.00
NYY 4 x 6 mm Meter 44,000.00
NYY 4 x 10 mm Meter 69,000.00
NYY 4 x 16 mm Meter 110,000.00
NYY 4 x 25 mm Meter 180,000.00
NYA 1 x 1,5 mm Meter 2,500.00
NYA 1 x 2,5 mm Meter 3,500.00
NYA 1 x 4 mm Meter 6,000.00
NYA 1 x 6 mm Meter 9,000.00
NYA 1 x 10 mm Meter 15,000.00
NYA 1 x 16 mm Meter 25,000.00
NYA 1 x 25 mm Meter 35,000.00
NYA 1 x 50 mm Meter 59,000.00
NYM 2 x 4 mm Meter 15,000.00
NYM 2 x 2,5 mm Meter 9,000.00
NYM 2 x 1,5 mm Meter 7,000.00
NYM 3 x 4 mm Meter 20,000.00
NYM 3 x 2,5 mm Meter 12,000.00
NYM 3 x 1,5 mm Meter 9,000.00
NYM 4 x 4 mm Meter 27,000.00
NYM 4 x 2,5 mm Meter 17,000.00
NYM 4 x 1,5 mm Meter 12,000.00
NYMHY 2 x 0,75 mm Meter 5,500.00
NYMHY 2 x 1,5 mm Meter 11,000.00
Kabel TC 2 x 10 mm Meter 4,649.20
Box MCB 1 Group Buah 3,500.00
HARGA
NO. JENIS DAN NAMA BARANG SPESIFIKASI SATUAN
SATUAN
1 2 3 4 5
Box MCB 2 Group Buah 5,000.00
Box MCB 4 Group Buah 5,000.00
Fitting Gantung E 27 Buah 5,000.00
Fitting Duduk E 27 Buah 5,000.00
Fitting Atom Buah 5,000.00
Fitting Gantung E 40 WD Buah 15,684.00
Fitting Duduk E 40 Keramik Buah 19,914.40
Full Breket Buah 25,000.00
Isolasi Unibel Buah 8,000.00
Ignitor SN 58 Buah 50,000.00
Kap Hijau E 27 Buah 25,000.00
MCB 1.A Buah 30,000.00
MCB 2.A Buah 18,000.00
MCB 4 A Buah 18,000.00
MCB 6 A Buah 18,000.00
MCB 10 A Buah 20,000.00
MCB 16 A Buah 20,000.00
MCB 25 A Buah 30,000.00
MCB 32 A Buah 30,000.00
MCB 40 A Buah 30,000.00
MCB 50 A Buah 30,000.00
Multimeter analog Buah 1,108,345.60
Obeng Plus Buah 6,000.00
Obeng Minus Buah 6,000.00
Rel MCB meter 12,531.20
Saklar Tunggal setara Broco Buah 12,000.00
Saklar Tunggal setara Panasonic Buah 10,000.00
Saklar Double setara Broco Buah 15,000.00
Saklar Double setara Panasonic Buah 15,000.00
Saklar Engkel setara Broco Buah 13,000.00
Solder Pistol Buah 32,000.00
Steker Arde Buah 5,000.00
HARGA
NO. JENIS DAN NAMA BARANG SPESIFIKASI SATUAN
SATUAN
1 2 3 4 5
Steker T Buah 8,000.00
Stop Kontak setara Broco 1 lubang outbow Buah 12,000.00
Stop Kontak setara Broco 2 lubang outbow Buah 27,000.00
Stop Kontak setara Panasonic 1 lubang outbow Buah 12,000.00
Sadel No. 6 Bungkus 2,000.00
Sadel No. 8 Bungkus 2,000.00
Sadel No. 9 Bungkus 2,000.00
Sadel No. 10 Bungkus 2,500.00
Sadel No. 12 Bungkus 7,000.00
Sadel No. 14 Bungkus 8,000.00
Sadel No. 19 Bungkus 10,000.00
Sadel No. 22 Bungkus 35,000.00
Stater Buah 5,000.00
Tang Amper Buah 135,000.00
Tang Potong Buah 25,000.00
Tang Kombinasi Buah 25,000.00
Tang Buaya Buah 22,000.00
Time Swicht Theben Buah 450,000.00
Taping Conector 1 baut Buah 15,000.00
Tespen Buah 5,000.00
Kabel Tie Bungkus 7,000.00
Kabel Tie Bungkus 10,000.00
Kabel Tie Bungkus 5,000.00
Kabel Tie Bungkus 19,000.00
Kabel Tie Bungkus 22,000.00
Outlet Telepon Panasonic (Inbow) Set 51,000.00
Outlet TV Panasonic (Inbow) Set 51,000.00
Outlet Internet Panasonic (Inbow) Set 86,000.00
4.2.1. HARGA SATUAN PEKERJAAN BESI DAN ALUMUNIUM
4.2.1.17 Pemasangan 1 m² jendela nako dan tralis

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

A TENAGA
1 Pekerja L.01 OH 0.200 158,700.00 31,740.00
2 Tukang L.03 OH 0.200 172,500.00 34,500.00
3 Kepala Tukang L.03 OH 0.020 238,050.00 4,761.00
4 Mandor L.04 OH 0.001 178,250.00 178.25
JUMLAH TENAGA KERJA 71,179.25
B BAHAN
Jendela nako (rangka + kaca
1 m² 1.100 250,000.00 275,000.00
5mm)
2 Paku 1 cm - 2,5 cm buah 10.000 19,900.00 199,000.00
3 Besi strip Kg 7.000 13,500.00 94,500.00
JUMLAH HARGA BAHAN 568,500.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 639,679.25
E Overhead & Profit (Contoh 15%)
F Harga Satuan Pekerjaan (D+E) 639,679.25

4.2.1.18 Pemasangan 1 m² talang datar/jurai seng bjls 28 lebar 90 cm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

A TENAGA
1 Pekerja L.01 OH 0.200 158,700.00 31,740.00
2 Tukang L.03 OH 0.200 97,600.00 19,520.00
3 Kepala Tukang L.03 OH 0.020 118,400.00 2,368.00
4 Mandor L.04 OH 0.001 111,200.00 111.20
JUMLAH TENAGA KERJA 53,739.20
B BAHAN
1 Seng plat m² 1.050 35,000.00 36,750.00
2 Paku 1 cm - 2,5 cm Kg 0.015 20,000.00 300.00
3 Papan kayukelas II m³ 0.019 8,460,000.00 160,740.00
JUMLAH HARGA BAHAN 197,790.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 251,529.20
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E) 251,529.20
A.2.2.1. HARGA SATUAN PEKERJAAN PERSIAPAN

A.2.2.1.4.a Pengukuran dan Pemasangan 1m Bouplank

Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp)
(Rp)
A TENAGA
1 Pekerja L.01 OH 0.100 158,700.00 15,870.00
2 Tukang Kayu L.02 OH 0.100 172,500.00 17,250.00
3 Kepala Tukang L.03 OH 0.010 238,050.00 2,380.50
4 Mandor L.04 OH 0.005 178,250.00 891.25
JUMLAH TENAGA KERJA 36,391.75
B BAHAN
Kayu Pancang (Dolken) d = 6-8 cm, p = 4m Btg 1.000 16,008.00 16,008.00
Paku Kg 0.020 31,970.00 639.40
Papan Kayu Kelas III M3 0.007 2,803,700.00 19,625.90
JUMLAH HARGA BAHAN 36,273.30
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 72,665.05


E Overhead & Profit
F Harga Satuan Pekerjaan (D+E) 72,665.05

2.2.1.9 Pembersihan 1m² lapangan dan perataan

Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp)
(Rp)
A TENAGA
1 Pekerja L.01 OH 0.100 158,700.00 15,870.00
2 Mandor L.02 OH 0.050 178,250.00 8,912.50
JUMLAH TENAGA KERJA 24,782.50
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 24,782.50


E Overhead & Profit (Contoh 15%)
F Harga Satuan Pekerjaan (D+E) 24,782.50
STANDAR HARGA SATUAN DASAR BAHAN

HARGA SATUAN
NO MATERIAL SATUAN
(Rp)

A. BAHAN PENGISI
1 Batu Kong M³ 741,681.00###
2 Batu pecah 15-20 cm M³ 794,817.27###
3 Batu pecah 10-15 cm M³ 783,196.00###
4 Batu pecah 5-7 cm M³ 874,299.00###
5 Batu pecah 3-5 cm M³ 901,945.00###
6 Batu pecah 2-3 cm M³ 792,810.00###
7 Batu pecah 1-2 cm M³ 1,163,800.00###
8 Pasir Beton M³ 881,484.20###
9 Pasir Pasang (Halus) M³ 881,484.20###
10 Pasir Urug M³ 520,495.75###
11 Semen PC Zak 108,928.00
12 Semen PC Kg 2,178.56
13 Tanah Datang M³ 492,792.25
14 Batako 20 x 40 x 7 cm Bh 4,945.00
15 Kerawang ( roster ) 20 x 20 cm Bh 9,163.20
16 Kerawang ( roster ) 30 x 30 cm Bh 84,841.25
17 Keramik Lantai 20 x 20 cm Ktk 86,595.00
18 Keramik 30 x 30 cm Ktk 97,290.00
19 Keramik 40 x 40 cm Ktk 98,900.00
20 List Keramik WC. 8 x 20 cm Bh 5,750.00
21 Keramik dinding 20 x 25 cm Ktk 86,710.00
-
B. BAHAN KAYU -
1 Ky Klas I :18/18-20/20cmx4m M³ 5,577,684.00
2 Kayu Kls II 4/6 cm x 4 m M³ 4,509,150.00
3 Kayu Kls II 3/5 cm x 4 m M³ 6,314,650.00
4 Kayu Kls III M³ 3,450,000.00
5 Papan mal klas III M³ 2,803,700.00
6 Kayu cerucuk /dolken ø 6 - 8 - Pj. 4 M Btg 16,008.00
7 Kayu cerucuk /dolken ø 8 - 10 - Pj. 4 M Btg 18,400.00
8 Air Ltr 40.00
-
C. BAHAN CAT -
1 Amplas Lbr 7,178.30
2 Plamur tembok Kg 43,725.30
3 Cat Dasar Kg 104,420.00
4 Cat kilat Kg 85,396.70
5 Cat tembok interior Kg 156,630.00
6 Cat tembok eksterior Kg 176,208.75
7 Oker Kg 28,750.00
8 Kuas" Bh 28,750.00
9 Water Proofing Kg 156,078.00
10 Thiner Kg 50,600.00
-
HARGA SATUAN
NO MATERIAL SATUAN
(Rp)

D. BAHAN BESI DAN ALUMINIUM -


1 Besi Tulangan Beton Dia. 6 mm Kg 16,721.00
2 Besi Tulangan Beton Dia. 8 mm Kg 16,721.00
3 Besi Tulangan Beton Dia. 10 mm Kg 16,721.00
4 Besi Tulangan Beton Dia. 13 mm Kg 21,091.00
5 Besi wire mesh ø 5 Kg 33,752.50
6 Kawat baja/bendrat Kg 47,955.00
7 Rangka Plafond M1 10,925.00
-
E. BAHAN PENGGANTUNG -
1 Pintu Aluminium Bh 667,000.00
2 Handle Pintu Bh 229,724.00
3 Engsel pintu Bh 39,809.55
4 Slot pintu Bh 25,451.80
5 Kunci tanam biasa Bh 11,500.00
6 Paku Seng Kg 58,190.00
7 Paku campuran 1" - 5 " Kg 31,970.00
8 Paku beton Kg 56,197.05
9 Paku GRC Kg 39,100.00
10 Paku Zincalum Kg 42,550.00
11 Sekrup Gibsum Kg 86,181.00
12 Sekrup Zincalume Bh 747.50
-
F. BAHAN ATAP -
1 Genteng Metal 0.30 Lbr 90,447.50
2 Genteng Metal 0.25 Lbr 75,555.00
3 Nok bubungan genteng metal 1/2 lingkaran 0.35 (pj 40cm) Bh 57,500.00
4 Seng Gelombang Bjls 20 Lbr 63,250.00
5 Seng Plat Bjls 20 Lbr 51,750.00
6 Zincalume Plat 0.2 Lbr 97,750.00
7 Rangka Plafond Metal Furing + Pemasangan M2 218,500.00
-
G. BAHAN KACA -
1 Kaca Polos, t = 5 mm M² 161,000.00
2 Sealent Kg 178,250.00
-
H. BAHAN TRIPLEK -
1 Multiplex t = 4 mm Lbr 111,573.00
2 Multiplex t = 9 mm Lbr 213,555.00
3 Panel GRC 120 x 240 x 40 Lbr 107,812.50
4 GypsumBoard t = 9mm Lbr 121,509.00
5 Lisplank Woodplank Lbr -
-
I. BAHAN SANITASI -
1 Wastafel Bh 414,000.00
2 Kloset jongkok Bh 287,500.00
3 Bak air fibreglass Bh 391,575.00
4 Floordrain Bh 51,750.00
5 Sealtape Bh 25,300.00
6 Kran air uk 1/2" Bh 74,750.00
HARGA SATUAN
NO MATERIAL SATUAN
(Rp)

7 Pipa PVC dia 1/2" AW Btg 25,300.00


8 Pipa PVC dia 3/4" AW Btg 40,250.00
9 Pipa PVC dia 1" AW Btg 52,900.00
10 Pipa PVC dia 2" AW Btg 105,800.00
11 Pipa PVC dia 3" AW Btg 143,750.00
12 Pipa PVC dia 4" AW Btg 299,000.00
13 Stop kran dia 1/2" Bh 59,388.30
14 Stop kran dia 3/4" Bh 73,746.05
15 Tangki air 1000 liter Bh 1,667,500.00
16 Tangki air 2000 liter Bh 2,875,000.00
17 Tangki air 250 liter Bh 517,500.00
18 Tangki air 500 liter Bh 977,500.00
19 Tee 4" Bh 63,250.00
20 Tee 2" Bh 40,250.00
-
J. BAHAN ALAT-ALAT LISTRIK -
1 Lampu LED Bh 86,250.00
2 Saklar Bh 40,250.00
3 Stop Kontak Bh 40,250.00
A.2.3.1. HARGA SATUAN PEKERJAAN TANAH
A.2.3.1.1 Penggalian 1 m³ tanah biasa sedalam 1m
Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp)
(Rp)
A TENAGA
1 Pekerja L.01 OH 0.750 158,700.00 119,025.00
2 Mandor L.04 OH 0.025 178,250.00 4,456.25
JUMLAH TENAGA KERJA 123,481.25
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 123,481.25


E Overhead & Profit
F Harga Satuan Pekerjaan (D+E) 123,481.25

A.2.3.1.9.a Pengurugan kembali 1 m³ galian tanah biasa


Pengurugan kembali 1 m³ galian dihitung dari 1/3 kali dari koefisien pekerjaan galiaan
Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp)
(Rp)
A TENAGA
1 Pekerja L.01 OH 0.250 158,700.00 39,675.00
2 Mandor L.04 OH 0.008 178,250.00 1,485.42
JUMLAH TENAGA KERJA 41,160.42
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 41,160.42


E Overhead & Profit
F Harga Satuan Pekerjaan (D+E) 41,160.42
A.2.3.1.11 Pengurugan 1 m³ dengan pasir urug

Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp)
(Rp)
A TENAGA
1 Pekerja L.01 OH 0.300 158,700.00 47,610.00
2 Mandor L.04 OH 0.010 178,250.00 1,782.50
JUMLAH TENAGA KERJA 49,392.50
B BAHAN
Pasir Urug 1.200 520,495.75 624,594.90
JUMLAH HARGA BAHAN 624,594.90
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 673,987.40


E Overhead & Profit
F Harga Satuan Pekerjaan (D+E) 673,987.40

A.2.3.1.11.a Pengurugan 1 m³ dengan tanah

Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp)
(Rp)
A TENAGA
1 Pekerja L.01 OH 0.300 158,700.00 47,610.00
2 Mandor L.04 OH 0.010 178,250.00 1,782.50
JUMLAH TENAGA KERJA 49,392.50
B BAHAN
Tanah 1.200 492,792.25 591,350.70
JUMLAH HARGA BAHAN 591,350.70
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 640,743.20


E Overhead & Profit
F Harga Satuan Pekerjaan (D+E) 640,743.20

A.3.2.1.1. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 3PP


Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
1 Pekerja L.01 OH 1.500 158,700.00 238,050.00
2 Tukang Batu L.02 OH 0.750 172,500.00 129,375.00
3 Kepala Tukang L.03 OH 0.075 238,050.00 17,853.75
4 Mandor L.04 OH 0.075 178,250.00 13,368.75
JUMLAH TENAGA KERJA 398,647.50
B BAHAN
Batu Belah M3 1.200 783,196.00 939,835.20
Semen Portland Kg 202.000 2,178.56 440,069.12
Pasir M3 0.485 881,484.20 427,519.84
JUMLAH HARGA BAHAN 1,807,424.16
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 2,206,071.66
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E) 2,206,071.66
A.3.2.1 HARGA SATUAN PEKERJAAN PONDASI
A.3.2.1.1 Pemasangan 1 m³ pondasi batu belah campuran 1SP:3PP

Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp)
(Rp)
A TENAGA
1 Pekerja L.01 OH 1.500 69,600.00 104,400.00
2 Tukang L.02 OH 0.750 97,600.00 73,200.00
3 Kepala Tukang L.03 OH 0.075 118,400.00 8,880.00
4 Mandor L.04 OH 0.075 111,200.00 8,340.00
JUMLAH TENAGA KERJA 194,820.00
B BAHAN
1 Batu Belah m³ 1.200 783,196.00 939,835.20
2 Semen Portland Kg 202.000 2,178.56 440,069.12
3 Pasir Pasang m³ 0.485 881,484.20 427,519.84
JUMLAH HARGA BAHAN 1,807,424.16
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 2,002,244.16


E Overhead & Profit
F Harga Satuan Pekerjaan (D+E) 2,002,244.16

3.2.1.2 Pemasangan 1 m³ pondasi batu belah campuran 1SP:4PP

Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp)
(Rp)
A TENAGA
1 Pekerja L.01 OH 1.500 69,600.00 104,400.00
2 Tukang L.02 OH 0.750 97,600.00 73,200.00
3 Kepala Tukang L.03 OH 0.075 118,400.00 8,880.00
4 Mandor L.04 OH 0.075 111,200.00 8,340.00
JUMLAH TENAGA KERJA 194,820.00
B BAHAN
1 Batu Belah m³ 1.200 783,196.00 939,835.20
2 Semen Portland Kg 163.000 2,178.56 355,105.28
3 Pasir Pasang m³ 0.520 881,484.20 458,371.78
JUMLAH HARGA BAHAN 1,753,312.26
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1,948,132.26


E Overhead & Profit (Contoh 15%)
F Harga Satuan Pekerjaan (D+E) 1,948,132.26
3.2.1.9 Pemasangan 1 m³ batu kosong (anstamping)

Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp)
(Rp)
A TENAGA
1 Pekerja L.01 OH 0.780 69,600.00 54,288.00
2 Tukang L.02 OH 0.390 97,600.00 38,064.00
3 Kepala Tukang L.03 OH 0.039 118,400.00 4,617.60
4 Mandor L.04 OH 0.039 111,200.00 4,336.80
JUMLAH TENAGA KERJA 101,306.40
B BAHAN
1 Batu Belah m³ 1.200 783,196.00 939,835.20
2 Pasir Urug m³ 0.432 520,495.75 224,854.16
JUMLAH HARGA BAHAN 1,164,689.36
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1,265,995.76


E Overhead & Profit (Contoh 15%)
F Harga Satuan Pekerjaan (D+E) 1,265,995.76

3.2.1.10 Pemasangan 1 m³ pondasi siklop, 60% beton campuran 1SP:2PB:3Kr dan 40% batu belah

Harga Satuan
No Uraian Kode Satuan Koefisien Jumlah Harga (Rp)
(Rp)
A TENAGA
1 Pekerja L.01 OH 3.400 69,600.00 236,640.00
2 Tukang L.02 OH 0.850 97,600.00 82,960.00
3 Kepala Tukang L.03 OH 0.085 118,400.00 10,064.00
4 Mandor L.04 OH 0.170 111,200.00 18,904.00
JUMLAH TENAGA KERJA 348,568.00
B BAHAN
1 Batu Belah m³ 0.480 783,196.00 375,934.08
2 Semen Portlan Kg 194.000 2,178.56 422,640.64
3 Pasir Beton m³ 0.312 881,484.20 275,023.07
4 Kerikil m³ 0.468 792,810.00 371,035.08
5 Besi Beton Kg 16,721.00 -
6 Kawat Beton Kg 47,955.00 -
JUMLAH HARGA BAHAN 1,444,632.87
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1,793,200.87


E Overhead & Profit (Contoh 15%)
F Harga Satuan Pekerjaan (D+E) 1,793,200.87
A.4.1.1 HARGA SATUAN PEKERJAAN BETON
A.4.1.1.4 Membuat 1 m³ lantai kerja beton mutu f'c =7,4 Mpa ( K 100), slump (3-6) cm ,w/c =0,87

No Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

A TENAGA
1 Pekerja OH 1.200 158,700.00 190,440.00
2 Tukang OH 0.200 172,500.00 34,500.00
3 Kepala Tukang OH 0.020 238,050.00 4,761.00
4 Mandor OH 0.060 178,250.00 10,695.00
JUMLAH TENAGA KERJA 240,396.00
B BAHAN
1 Semen Portlan Kg 230.000 2,178.56 501,068.80
2 Pasir Beton Kg 893.000 629.63 562,260.99
3 Kerikil (Maks 30mm) Kg 1,027.000 862.07 885,350.07
4 Air Liter 200.000 40.00 8,000.00
JUMLAH HARGA BAHAN 1,956,679.87
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 2,197,075.87


E Overhead & Profit
F Harga Satuan Pekerjaan (D+E) 2,197,075.87

A.4.1.1.7.a Membuat 1 m³ beton mutu f'c =19,3 Mpa ( K 225), slump (12 ± 2) cm ,w/c = 0,58

No Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

A TENAGA
1 Pekerja OH 1.323 158,700.00 209,960.10
2 Tukang OH 0.189 172,500.00 32,602.50
3 Kepala Tukang OH 0.019 238,050.00 4,522.95
4 Mandor OH 0.066 178,250.00 11,764.50
JUMLAH TENAGA KERJA 258,850.05
B BAHAN
1 Semen Portlan Kg 371.000 2,178.56 808,245.76
2 Pasir Beton Kg 698.000 629.63 439,482.84
3 Kerikil (Maks 30mm) Kg 1,047.000 862.07 902,591.56
4 Air Liter 215.000 40.00 8,600.00
JUMLAH HARGA BAHAN 2,158,920.15
C PERALATAN
Sewa Molen Sewa-hari 0.250 250,000.00 62,500.00
JUMLAH HARGA ALAT 62,500.00

D Jumlah (A+B+C) 2,480,270.20


E Overhead & Profit
F Harga Satuan Pekerjaan (D+E) 2,480,270.20
bobot pasir =1.400 Kg/m³, Bobot isi kerikil = 1.350 Kg/m³, Buckling factor pasir =20%

A.4.1.1.17 Pembesian 1 Kg dengan besi Dia.13 mm

No Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

A TENAGA
1 Pekerja OH 0.070 158,700.00 11,109.00
2 Tukang OH 0.070 172,500.00 12,075.00
3 Kepala Tukang OH 0.007 238,050.00 1,666.35
4 Mandor OH 0.004 178,250.00 713.00
JUMLAH TENAGA KERJA 25,563.35
B BAHAN
1 Besi Beton Kg 10.500 21,091.00 221,455.50
2 Kawat Beton Kg 0.150 47,955.00 7,193.25
JUMLAH HARGA BAHAN 228,648.75
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 254,212.10
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E) 254,212.10
G Harga Satuan Pekerjaan (D+E) per 1 kg 25,421.21
A.4.1.1.17.a Pembesian 1 Kg dengan besi Dia.8 mm

No Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

A TENAGA
1 Pekerja OH 0.070 158,700.00 11,109.00
2 Tukang OH 0.070 172,500.00 12,075.00
3 Kepala Tukang OH 0.007 238,050.00 1,666.35
4 Mandor OH 0.004 178,250.00 713.00
JUMLAH TENAGA KERJA 25,563.35
B BAHAN
1 Besi Beton Kg 10.500 16,721.00 175,570.50
2 Kawat Beton Kg 0.150 47,955.00 7,193.25
JUMLAH HARGA BAHAN 182,763.75
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 208,327.10
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E) 208,327.10
G Harga Satuan Pekerjaan (D+E) per 1 kg 20,832.71

A.4.1.1.19 Pemasangan 10 Kg jaring kawat baja (wiremesh)

No Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

A TENAGA
1 Pekerja OH 0.025 158,700.00 3,967.50
2 Tukang OH 0.025 172,500.00 4,312.50
3 Kepala Tukang OH 0.025 238,050.00 5,951.25
4 Mandor OH 0.001 178,250.00 178.25
JUMLAH TENAGA KERJA 14,409.50
B BAHAN
1 Jaring kawat baja dilas Kg 10.200 33,752.50 344,275.50
2 Kawat Beton Kg 0.050 47,955.00 2,397.75
JUMLAH HARGA BAHAN 346,673.25
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 361,082.75
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E) 361,082.75
G Harga Satuan Pekerjaan (D+E) per 1 kg 36,108.28

A.4.1.1.20.b Pemasangan berulang 1m² bekisting untuk pondasi (papan mal)

No Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

A TENAGA
1 Pekerja OH 0.520 158,700.00 82,524.00
2 Tukang OH 0.260 172,500.00 44,850.00
3 Kepala Tukang OH 0.026 238,050.00 6,189.30
4 Mandor OH 0.026 178,250.00 4,634.50
JUMLAH TENAGA KERJA 138,197.80
B BAHAN
1 Papan Mal kelas III m³ 0.031 2,803,700.00 86,914.70
2 Paku Campuran Kg 0.300 31,970.00 9,591.00
3 Cerucuk ф 6-8 cm - panj 4 m Btg 0.125 16,008.00 2,001.00
JUMLAH HARGA BAHAN 98,506.70
JUMLAH HARGA BAHAN x 55 % 54,178.69
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 192,376.49


E Overhead & Profit
F Harga Satuan Pekerjaan (D+E) 192,376.49
A.4.1.1.21 Pemasangan 1m² bekisting untuk sloof

No Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

A TENAGA
1 Pekerja OH 0.520 158,700.00 82,524.00
2 Tukang OH 0.260 172,500.00 44,850.00
3 Kepala Tukang OH 0.026 238,050.00 6,189.30
4 Mandor OH 0.026 178,250.00 4,634.50
JUMLAH TENAGA KERJA 138,197.80
B BAHAN
1 Kayu kelas III m³ 0.045 3,450,000.00 155,250.00
2 Paku Campuran Kg 0.300 31,970.00 9,591.00
JUMLAH HARGA BAHAN 164,841.00
JUMLAH HARGA BAHAN x 55 % 90,662.55
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 228,860.35


E Overhead & Profit
F Harga Satuan Pekerjaan (D+E) 228,860.35

A.4.1.1.22 b Pemasangan berulang 1m² bekisting untuk kolom (papan mal)

No Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

A TENAGA
1 Pekerja OH 0.660 158,700.00 104,742.00
2 Tukang OH 0.330 172,500.00 56,925.00
3 Kepala Tukang OH 0.033 238,050.00 7,855.65
4 Mandor OH 0.033 178,250.00 5,882.25
JUMLAH TENAGA KERJA 175,404.90
B BAHAN
1 Kayu kelas III m³ 0.040 3,450,000.00 138,000.00
2 Paku Campuran Kg 0.400 31,970.00 12,788.00
3 Balok kayu kelas II m³ 0.015 4,509,150.00 67,637.25
4 Papan Mal kelas III m³ 0.022 6,314,650.00 138,922.30
5 Dolken kayu ф 8-10 cm - panj 4 m Batang 2.000 18,400.00 36,800.00
JUMLAH HARGA BAHAN 394,147.55
JUMLAH HARGA BAHAN x 55 % 216,781.15
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 392,186.05


E Overhead & Profit
F Harga Satuan Pekerjaan (D+E) 392,186.05

4.1.1.24.b Pemasangan berulang 1m² bekisting untuk lantai (papan mal)

No Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

A TENAGA
1 Pekerja OH 0.660 158,700.00 104,742.00
2 Tukang OH 0.330 172,500.00 56,925.00
3 Kepala Tukang OH 0.033 238,050.00 7,855.65
4 Mandor OH 0.033 178,250.00 5,882.25
JUMLAH TENAGA KERJA 175,404.90
B BAHAN
1 Kayu kelas III m³ 0.040 3,450,000.00 138,000.00
2 Paku Campuran Kg 0.400 31,970.00 12,788.00
3 Balok kayu kelas II m³ 0.015 4,509,150.00 67,637.25
4 Papan Mal kelas III m³ 0.022 6,314,650.00 138,922.30
5 Dolken kayu ф 8-10 cm - panj 4 m Batang 6.000 18,400.00 110,400.00
JUMLAH HARGA BAHAN 467,747.55
JUMLAH HARGA BAHAN x 55 % 257,261.15
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 432,666.05
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E) 432,666.05
A.4.4.1. HARGA SATUAN PEKERJAAN PASANGAN DINDING

A.4.4.1.17.b Pemasangan 1 m² dinding batako 20/40/7

No Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

A TENAGA
1 Pekerja OH 0.350 158,700.00 55,545.00
2 Tukang batu OH 0.150 172,500.00 25,875.00
3 Kepala Tukang OH 0.015 238,050.00 3,570.75
4 Mandor OH 0.018 178,250.00 3,208.50
JUMLAH TENAGA KERJA 88,199.25
B BAHAN
1 Batako 20/40/7 Bh 12.500 4,945.00 61,812.50
2 Semen Portland Kg 7.500 2,178.56 16,339.20
3 Pasir pasang m³ 0.027 881,484.20 23,800.07
JUMLAH HARGA BAHAN 101,951.77
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 190,151.02
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E) 190,151.02

4.4.1.23.a Pemasangan 1 m² dinding terawang (rooster) 20x20 campuran 1SP:4PP

No Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

A TENAGA
1 Pekerja OH 0.300 158,700.00 47,610.00
2 Tukang batu OH 0.100 172,500.00 17,250.00
3 Kepala Tukang OH 0.010 238,050.00 2,380.50
4 Mandor OH 0.015 178,250.00 2,673.75
JUMLAH TENAGA KERJA 69,914.25
B BAHAN
1 Rooster 20 x 20 cm Bh 25.000 9,163.20 229,080.00
2 Semen portland Kg 11.000 2,178.56 23,964.16
3 Pasir pasang m³ 0.035 881,484.20 30,851.95
JUMLAH HARGA BAHAN 283,896.11
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 353,810.36
E Overhead & Profit (Contoh 15%) 15% x D
F Harga Satuan Pekerjaan (D+E) 353,810.36
A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN
A.4.4.2.3 Pemasangan 1 m² plesteran 1SP:3PP tebal 15mm

No Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

A TENAGA
1 Pekerja OH 0.300 158,700.00 47,610.00
2 Tukang batu OH 0.150 172,500.00 25,875.00
3 Kepala Tukang OH 0.015 238,050.00 3,570.75
4 Mandor OH 0.015 178,250.00 2,673.75
JUMLAH TENAGA KERJA 79,729.50
B BAHAN
1 PC Kg 7.776 2,178.56 16,940.48
2 PP m³ 0.023 881,484.20 20,274.14
JUMLAH HARGA BAHAN 37,214.62
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 116,944.12
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E) 116,944.12

A.4.4.2.14 Pemasangan 1 m² plesteran 1SP: 3PP tebal 20mm

No Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

A TENAGA
1 Pekerja OH 0.260 158,700.00 41,262.00
2 Tukang batu OH 0.200 172,500.00 34,500.00
3 Kepala Tukang OH 0.020 238,050.00 4,761.00
4 Mandor OH 0.013 178,250.00 2,317.25
JUMLAH TENAGA KERJA 82,840.25
B BAHAN
1 PC Kg 10.368 2,178.56 22,587.31
2 PP m³ 0.031 881,484.20 27,326.01
JUMLAH HARGA BAHAN 49,913.32
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 132,753.57


E Overhead & Profit
F Harga Satuan Pekerjaan (D+E) 132,753.57

A.4.4.2.27 Pemasangan 1 m² acian

No Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

A TENAGA
1 Pekerja OH 0.200 158,700.00 31,740.00
2 Tukang batu OH 0.100 172,500.00 17,250.00
3 Kepala Tukang OH 0.010 238,050.00 2,380.50
4 Mandor OH 0.010 178,250.00 1,782.50
JUMLAH TENAGA KERJA 53,153.00
B BAHAN
1 Semen PC Kg 3.250 2,178.56 7,080.32
JUMLAH HARGA BAHAN 7,080.32
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 60,233.32
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E) 60,233.32
A.4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING
A.4.4.3.34.a Pemasangan 1 m² lantai keramik 40 cm x 40 cm

No Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

A TENAGA
1 Pekerja OH 0.700 158,700.00 111,090.00
2 Tukang batu OH 0.350 172,500.00 60,375.00
3 Kepala Tukang OH 0.035 238,050.00 8,331.75
4 Mandor OH 0.035 178,250.00 6,238.75
JUMLAH TENAGA KERJA 186,035.50
B BAHAN
1 keramik 40 X 40 cm Bh 6.630 16,483.33 109,284.50
2 Semen Portlan Kg 8.190 2,178.56 17,842.41
3 Pasir pasang m³ 0.045 881,484.20 39,666.79
4 Semen warna Kg 0.150 28,750.00 4,312.50
JUMLAH HARGA BAHAN 171,106.20
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 357,141.70
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E) 357,141.70

A.4.4.3.36 Pemasangan 1 m² lantai keramik 20 cm x 20 cm

No Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

A TENAGA
1 Pekerja OH 0.700 158,700.00 111,090.00
2 Tukang batu OH 0.350 172,500.00 60,375.00
3 Kepala Tukang OH 0.035 238,050.00 8,331.75
4 Mandor OH 0.035 178,250.00 6,238.75
JUMLAH TENAGA KERJA 186,035.50
B BAHAN
1 Keramik 20 x 20 cm Bh 26.500 3,463.80 91,790.70
2 Semen Portlan Kg 10.400 2,178.56 22,657.02
3 Pasir pasang m³ 0.045 881,484.20 39,666.79
4 Semen warna Kg 0.162 28,750.00 4,657.50
JUMLAH HARGA BAHAN 158,772.01
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 344,807.51
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E) 344,807.51

A.4.4.3.54.a Pemasangan 1 m² dinding keramik 20 cm x 25 cm

No Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)

A TENAGA
1 Pekerja OH 0.900 158,700.00 142,830.00
2 Tukang batu OH 0.450 172,500.00 77,625.00
3 Kepala Tukang OH 0.045 238,050.00 10,712.25
4 Mandor OH 0.045 178,250.00 8,021.25
JUMLAH TENAGA KERJA 239,188.50
B BAHAN
1 Keramik 20 x 25 cm Bh 20.000 4,335.50 86,710.00
2 Semen portlan Kg 9.300 2,178.56 20,260.61
3 Pasir pasng m³ 0.018 881,484.20 15,866.72
4 Semen warna Kg 0.019 28,750.00 557.75
JUMLAH HARGA BAHAN 123,395.07
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 362,583.57
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E) 362,583.57
A.4.5.1.SATUAN PEKERJAAN LANGIT-LANGIT (PLAFOND)

A.4.5.1.7. Pemasangan 1 m2 langit-langit gypsum board ukuran (120x240x9) mm, tebal 9 mm


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
1 2 3 5 4 6
A TENAGA
1 Pekerja OH 0.100 158,700.00 15,870.00
2 Tukang kayu OH 0.050 172,500.00 8,625.00
3 Kepala Tukang OH 0.005 238,050.00 1,190.25
4 Mandor OH 0.005 178,250.00 891.25
Jumlah 26,576.50
B BAHAN
1 Gypsum board Lembar 0.364 121,509.000 44,229.28
2 Paku Skrup Kg 0.110 86,181.000 9,479.91
Jumlah 53,709.19
C Jumlah A + B 80,285.69
E Overhead & Profit
E Harga Satuan Pekerjaan ( C+D) 80,285.69

A.4.5.1.7.a Pemasangan 1 m2 langit-langit GRC (120x240x4) mm, tebal 4 mm


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
1 2 3 5 4 6
A TENAGA
1 Pekerja OH 0.100 158,700.00 15,870.00
2 Tukang kayu OH 0.050 172,500.00 8,625.00
3 Kepala Tukang OH 0.005 238,050.00 1,190.25
4 Mandor OH 0.005 178,250.00 891.25
Jumlah 26,576.50
B BAHAN
1 GRC Board (120 x 240 x 4) Lembar 0.364 107,812.500 39,243.75
2 Paku GRC Kg 0.110 39,100.000 4,301.00
Jumlah 43,544.75
C Jumlah A + B 70,121.25
E Overhead & Profit
E Harga Satuan Pekerjaan ( C+D) 70,121.25
A.4.5.2.HARGA SATUAN PEKERJAAN PENUTUP ATAP

A.4.5.2.32. Pemasangan 1 m2 genteng metal 0.30 mm


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 0.200 158,700.00 31,740.00
2 Tukang kayu OH 0.100 172,500.00 17,250.00
3 Kepala Tukang OH 0.010 238,050.00 2,380.50
4 Mandor OH 0.001 178,250.00 178.25
Jumlah 51,548.75
B BAHAN
1 Genteng metal 0.30 Bh 1.020 90,447.50 92,256.45
2 Paku biasa ½"-1" Kg 0.200 42,550.00 8,510.00
Jumlah 100,766.45
C Jumlah A + B 152,315.20
E Overhead & Profit
E Harga Satuan Pekerjaan ( C+D) 152,315.20

A.4.5.2.38.a Pemasangan 1 m2 atap seng gelombang BJLS 30


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
1 2 3 5.000 4 6
A TENAGA
1 Pekerja OH 0.120 158,700.00 19,044.00
2 Tukang kayu OH 0.060 172,500.00 10,350.00
3 Kepala Tukang OH 0.006 238,050.00 1,428.30
4 Mandor OH 0.006 178,250.00 1,069.50
Jumlah 31,891.80
B BAHAN
1 Seng gelombang bjls 30 Lbr 0.700 63,250.000 44,275.00
2 Paku seng ½"-1" Kg 0.020 58,190.000 1,163.80
Jumlah 45,438.80
C Jumlah A + B 77,330.60
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D) 77,330.60
A.4.5.2.39. Pemasangan 1 m’ nok atap seng BJLS 30
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
1 2 3 5.000 4 6
A TENAGA
1 Pekerja OH 0.150 158,700.00 23,805.00
2 Tukang kayu OH 0.070 172,500.00 12,075.00
3 Kepala Tukang OH 0.007 238,050.00 1,666.35
4 Mandor OH 0.006 178,250.00 1,069.50
Jumlah 38,615.85
B BAHAN
1 Seng plat 3"x6" bjls.30 lebar 90 cm Lbr 0.300 51,750.000 15,525.00
2 Paku biasa ½"-1" Kg 0.040 42,550.000 1,702.00
Jumlah 17,227.00
C Jumlah A + B 55,842.85
E Overhead & Profit
E Harga Satuan Pekerjaan ( C+D) 55,842.85

A.4.5.2.40.e Pemasangan 1 m2 atap steel sheet 0.30 lurus (silver)


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
1 2 3 5.000 4 6
A TENAGA
1 Pekerja OH 0.150 158,700.00 23,805.00
2 Tukang kayu OH 0.750 172,500.00 129,375.00
3 Kepala Tukang OH 0.080 238,050.00 19,044.00
4 Mandor OH 0.006 178,250.00 1,069.50
Jumlah 173,293.50
B BAHAN
1 Atap Steel Sheet 0.30 lurus (silver) M2 1.050 97,750.000 102,637.50
2 Screw Zincalume Bh 5.000 747.500 3,737.50
Jumlah 106,375.00
C Jumlah A + B 279,668.50
E Overhead & Profit
E Harga Satuan Pekerjaan ( C+D) 279,668.50
catatan : harga bahan atap steel sheet dikali 1,18 lembar
A.4.6.1.HARGA SATUAN PEKERJAAN KAYU

A.4.6.1.1. Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas I
HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
1 2 3 5 4 6
A TENAGA
1 Pekerja OH 7.00 158,700.00 1,110,900.00
2 Tukang kayu OH 21.00 172,500.00 3,622,500.00
3 Kepala Tukang OH 2.10 238,050.00 499,905.00
4 Mandor OH 0.35 178,250.00 62,387.50
Jumlah 5,295,692.50
B BAHAN
1 Balok Kayu m3 1.10 5,577,684.000 6,135,452.40
2 Paku Campuran Kg 1.25 31,970.000 39,962.50
3 Lem kayu Kg 1.00 18,000.000 18,000.00
Jumlah 6,193,414.90
C Jumlah A + B 11,489,107.40
E Overhead & Profit
E Harga Satuan Pekerjaan ( C+D) 11,489,107.40

A.4.6.1.20.Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu kelas II


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
1 2 3 5 4 6
A TENAGA
1 Pekerja OH 0.20 158,700.00 31,740.00
2 Tukang kayu OH 0.30 172,500.00 51,750.00
3 Kepala Tukang OH 0.03 238,050.00 7,141.50
4 Mandor OH 0.01 178,250.00 1,782.50
Jumlah 92,414.00
B BAHAN
1 m3 0.0163 4,509,150.000 73,499.15
Kaso-kaso 5 x 7 cm

2 Paku Campuran Kg 0.25 31,970.000 7,992.50


Jumlah 81,491.65
C Jumlah A + B 173,905.65
E Overhead & Profit
E Harga Satuan Pekerjaan ( C+D) 173,905.65

4.2.1.21.b Pemasangan 1 m² rangka hollow galvalum modul 60x60 cm, plafond


No Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A TENAGA
1 Pekerja OH 0.350 158,700.00 55,545.00
2 Tukang OH 0.350 172,500.00 60,375.00
3 Kepala Tukang OH 0.035 238,050.00 8,331.75
4 Mandor OH 0.018 178,250.00 3,208.50
JUMLAH TENAGA KERJA 127,460.25
B BAHAN
1 Rangka Plafond M1 4.000 10,925.00 43,700.00
2 assesoris (perkuatan, sekrup dll) Ls 100%xrangka 43,700.00 43,700.00
JUMLAH HARGA BAHAN 87,400.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 214,860.25
E Overhead & Profit
F Harga Satuan Pekerjaan (D+E) 214,860.25
A.4.6.2.HARGA SATUAN PEKERJAAN KUNCI DAN KACA

A.4.6.2.17. Pemasangan 1 m2 kaca tebal 5 mm


HARGA BIAYA
No. URAIAN PEKERJAAN SATUAN KOEFISIEN SATUAN SATUAN
( Rp. ) ( Rp. )
1 2 3 5 4 6
A TENAGA
1 Pekerja OH 0.015 158,700.00 2,380.50
2 Tukang kayu OH 0.150 172,500.00 25,875.00
3 Kepala Tukang OH 0.015 238,050.00 3,570.75
4 Mandor OH 0.001 178,250.00 142.60
Jumlah 31,968.85
B BAHAN
1 Kaca tebal 5 mm m² 1.100 161,000.000 177,100.00
2 Sealant Kg 0.050 178,250.000 8,912.50
Jumlah 186,012.50
C Jumlah A + B 217,981.35
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D) 217,981.35
A.4.7.1. HARGA SATUAN PEKERJAAN PENGECATAN
A.4.7.1.4. 1 m2 Pengecatan bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
Harga Satuan
No Uraian Satuan Koefisien Jumlah Harga (Rp)
(Rp)
A TENAGA
1 Pekerja OH 0.070 158,700.00 11,109.00
2 Tukang cat OH 0.009 172,500.00 1,552.50
3 Kepala tukang OH 0.006 238,050.00 1,428.30
4 Mandor OH 0.003 178,250.00 534.75
JUMLAH TENAGA KERJA 14,624.55
B BAHAN
1 Cat menie Kg 0.200 43,725.30 8,745.06
2 Cat penutup (cat kilat) Kg 0.260 176,208.75 45,814.28
3 Kuas Bh 0.010 28,750.00 287.50
4 Pengecer Kg 0.030 50,600.00 1,518.00
5 Ampelas Lbr 0.200 7,178.30 1,435.66
JUMLAH HARGA BAHAN 57,800.50
C PERALATAN

JUMLAH HARGA ALAT 0.00


D Jumlah (A + B + C) 72,425.05
D Overhead & Profit
F Harga Satuan Pekerjaan ( C+D) 72,425.05

A.4.7.1.10. Pengecatan 1 m2 tembok baru ( 1lapis plamur, 1 lapis cat dasar, 2 lapis cat penutup)
Harga Satuan
No Uraian Satuan Koefisien Jumlah Harga (Rp)
(Rp)
A TENAGA
1 Pekerja OH 0.020 158,700.00 3,174.00
2 Tukang cat OH 0.063 172,500.00 10,867.50
3 Kepala tukang OH 0.006 238,050.00 1,499.72
4 Mandor OH 0.003 178,250.00 534.75
JUMLAH TENAGA KERJA 16,075.97
B BAHAN
1 Plamur Kg 0.100 43,725.30 4,372.53
2 Cat dasar Kg 0.100 104,420.00 10,442.00
3 Cat penutup Kg 0.260 156,630.00 40,723.80
JUMLAH HARGA BAHAN 55,538.33
C PERALATAN

JUMLAH HARGA ALAT 0.00


D Jumlah (A + B + C) 71,614.30
D Overhead & Profit
F Harga Satuan Pekerjaan ( C+D) 71,614.30

4.7.1.10.c Pengecatan 1 m2 tembok baru exterior ( 1lapis plamur, 1 lapis cat dasar, 2 lapis cat penutup)
Harga Satuan
No Uraian Satuan Koefisien Jumlah Harga (Rp)
(Rp)
A TENAGA
1 Pekerja OH 0.020 158,700.00 3,174.00
2 Tukang cat OH 0.063 172,500.00 10,867.50
3 Kepala tukang OH 0.006 238,050.00 1,499.72
4 Mandor OH 0.003 178,250.00 534.75
JUMLAH TENAGA KERJA 16,075.97
B BAHAN
1 Palmmur Kg 0.100 43,725.30 4,372.53
2 Cat exterior Kg 0.260 176,208.75 45,814.28
JUMLAH HARGA BAHAN 50,186.81
C PERALATAN

JUMLAH HARGA ALAT 0.00


D Jumlah (A + B + C) 66,262.77
D Overhead & Profit
F Harga Satuan Pekerjaan ( C+D) 66,262.77
A.5.1.1.HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG
A.5.1.1.25. Pemasangan 1 m’ pipa PVC tipe AW diameter 1/2”
No. URAIAN PEKERJAAN SATUAN KOEFISIEN HARGA BIAYA
SATUAN SATUAN
( Rp. ) ( Rp. )
1 2 3 5 4 6
A TENAGA
1 Pekerja OH 0.036 158,700.00 5,713.20
2 Tukang batu OH 0.060 172,500.00 10,350.00
3 Kepala tukang OH 0.006 238,050.00 1,428.30
4 Mandor OH 0.002 178,250.00 356.50
Jumlah 17,848.00
B BAHAN
1 Pipa PVC 1/2" M 1.200 6,325.000 7,590.00
2 Perlengkapan % 35.000 6,325.000 2,213.75
Jumlah 9,803.75
C Jumlah A + B 27,651.75
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D) 27,651.75

A.5.1.1.26. Pemasangan 1 m’ pipa PVC tipe AW diameter 3/4”


No. URAIAN PEKERJAAN SATUAN KOEFISIEN HARGA BIAYA
SATUAN SATUAN
( Rp. ) ( Rp. )
1 2 3 5 4 6
A TENAGA
1 Pekerja OH 0.036 158,700.00 5,713.20
2 Tukang batu OH 0.060 172,500.00 10,350.00
3 Kepala tukang OH 0.006 238,050.00 1,428.30
4 Mandor OH 0.002 178,250.00 356.50
Jumlah 17,848.00
B BAHAN
1 Pipa PVC 3/4" M 1.200 10,062.500 12,075.00
2 Perlengkapan % 35.000 10,062.500 3,521.88
Jumlah 15,596.88
C Jumlah A + B 33,444.88
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D) 33,444.88

A.5.1.1.29. Pemasangan 1 m’ pipa PVC tipe AW diameter 2”


No. URAIAN PEKERJAAN SATUAN KOEFISIEN HARGA BIAYA
SATUAN SATUAN
( Rp. ) ( Rp. )
1 2 3 5 4 6
A TENAGA
1 Pekerja OH 0.054 158,700.00 8,569.80
2 Tukang batu OH 0.090 172,500.00 15,525.00
3 Kepala tukang OH 0.009 238,050.00 2,142.45
4 Mandor OH 0.003 178,250.00 534.75
Jumlah 26,772.00
B BAHAN
1 Pipa PVC dia 1/2" M 1.200 26,450.000 31,740.00
2 Perlengkapan % 35.000 26,450.000 9,257.50
Jumlah 40,997.50
C Jumlah A + B 67,769.50
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D) 67,769.50
A.5.1.1.31. Pemasangan 1 m’ pipa PVC tipe AW diameter 3”
No. URAIAN PEKERJAAN SATUAN KOEFISIEN HARGA BIAYA
SATUAN SATUAN
( Rp. ) ( Rp. )
1 2 3 5 4 6
A TENAGA
1 Pekerja OH 0.081 158,700.00 12,854.70
2 Tukang batu OH 0.135 172,500.00 23,287.50
3 Kepala tukang OH 0.014 238,050.00 3,213.68
4 Mandor OH 0.004 178,250.00 713.00
Jumlah 40,068.88
B BAHAN
1 Pipa PVC 3” M 1.200 35,937.500 43,125.00
2 Perlengkapan % 35.000 35,937.500 12,578.13
Jumlah 55,703.13
C Jumlah A + B 95,772.00
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D) 95,772.00

A.5.1.1.32. Pemasangan 1 m’ pipa PVC tipe AW diameter 4”


No. URAIAN PEKERJAAN SATUAN KOEFISIEN HARGA BIAYA
SATUAN SATUAN
( Rp. ) ( Rp. )
1 2 3 5 4 6
A TENAGA
1 Pekerja OH 0.081 158,700.00 12,854.70
2 Tukang batu OH 0.135 172,500.00 23,287.50
3 Kepala tukang OH 0.014 238,050.00 3,213.68
4 Mandor OH 0.004 178,250.00 713.00
Jumlah 40,068.88
B BAHAN
1 Pipa PVC 4” M 1.200 74,750.000 89,700.00
2 Perlengkapan % 35.000 74,750.000 26,162.50
Jumlah 115,862.50
C Jumlah A + B 155,931.38
D Overhead & Profit
E Harga Satuan Pekerjaan ( C+D) 155,931.38

Anda mungkin juga menyukai