LAPORAN QUANTITY MINGGUAN BULAN OKTOBER 2019

PERIODE MINGGU KE

PEKERJAAN : PEMBANGUNAN RUMAH SAKIT ROYAL BIRINGKANAYA 01 Okt 2019


LOKASI : Jalan Pajjaiang - Makassar S/D 30
TAHUN : 2019 06 Okt 2019

REALISASI

NO URAIAN PEKERJAAN SAT VOLUME BOBOT S/D Minggu Lalu Minggu Ini S/D Minggu Ini

Volume Progress Bobot Volume Progress Bobot Volume Progress Bobot

Pekerjaan Dinding Basement


1 Pek. Dinding Beton tbl. 25 cm
- Cor beton K-300 m³ 195,21 0,2270 15,7869 8,09% 0,0184 0,0000 0,00 % 0,0000 15,7869 8,09 % 0,0184
- Besi Beton kg 18.802,87 0,2319 18.802,8680 100,00% 0,2319 0,0000 0,00 % 0,0000 18.802,8680 100,00 % 0,2319
- Bekisting m2 1.561,70 0,4013 126,2950 8,09% 0,0325 83,2000 5,33 % 0,0214 209,4950 13,41 % 0,0538
2 Pek. Waterproofing integral m³ 195,21 0,0378 15,7869 8,09% 0,0031 0,0000 0,00 % 0,0000 15,7869 8,09 % 0,0031
3 Pek. Stop Cor m' 151,00 0,0388 0,0000 0,00% 0,0000 0,0000 0,00 % 0,0000 0,0000 0,00 % 0,0000
SUB TOTAL PEKERJAAN STRUKTUR LANTAI BASEMENT 0,9368 0,2858 0,0214 0,3071

LAPORAN QUANTITY MINGGUAN BULAN OKTOBER 2019


PERIODE MINGGU KE

PEKERJAAN : PEMBANGUNAN RUMAH SAKIT ROYAL BIRINGKANAYA 07 Okt 2019


LOKASI : Jalan Pajjaiang - Makassar S/D 31
TAHUN : 2019 13 Okt 2019

REALISASI

NO URAIAN PEKERJAAN SAT VOLUME BOBOT S/D Minggu Lalu Minggu Ini S/D Minggu Ini

Volume Progress Bobot Volume Progress Bobot Volume Progress Bobot

Pekerjaan Dinding Basement


1 Pek. Dinding Beton tbl. 25 cm
- Cor beton K-300 m³ 195,21 0,2270 0,0000 0,00% 0,0000 7,1500 3,66 % 0,0083 7,1500 3,66 % 0,0083
- Besi Beton kg 18.802,87 0,2319 0,0000 0,00% 0,0000 0,0000 0,00 % 0,0000 0,0000 0,00 % 0,0000
- Bekisting m2 1.561,70 0,4013 0,0000 0,00% 0,0000 83,2000 5,33 % 0,0214 83,2000 5,33 % 0,0214
2 Pek. Waterproofing integral m³ 195,21 0,0378 0,0000 0,00% 0,0000 7,1500 3,66 % 0,0014 7,1500 3,66 % 0,0014
3 Pek. Stop Cor m' 151,00 0,0388 0,0000 0,00% 0,0000 5,6000 3,71 % 0,0014 5,6000 3,71 % 0,0014
SUB TOTAL PEKERJAAN STRUKTUR LANTAI BASEMENT 0,9368 0,0000 0,0325 0,0325
LAPORAN QUANTITY MINGGUAN BULAN OKTOBER 2019
PERIODE MINGGU KE

PEKERJAAN : PEMBANGUNAN RUMAH SAKIT ROYAL BIRINGKANAYA 14 Okt 2019


LOKASI : Jalan Pajjaiang - Makassar S/D 32
TAHUN : 2019 20 Okt 2019

REALISASI

NO URAIAN PEKERJAAN SAT VOLUME BOBOT S/D Minggu Lalu Ming gu In i S/D Minggu Ini

Volume Pro gress Bobo t Volume Progress Bobot Volu me Progress Bob ot

b. Pekerjaan Dinding Basement


1 Pek. Dinding Beton tbl. 25 cm
- Cor beton K-300 m³ 195,21 0,2270 22,9369 11,75% 0,0267 9,7500 4,99 % 0,0113 32,6869 16,74 % 0,0380
- Besi Beton kg 18.802,87 0,2319 18.802,8680 100,00% 0,2319 0,0000 0,00 % 0,0000 18.802,8680 100,00 % 0,2319
- Bekisting m2 1.561,70 0,4013 292,6950 18,74% 0,0752 119,6000 7,66 % 0,0307 412,2950 26,40 % 0,1060
2 Pek. Waterproofing integral m³ 195,21 0,0378 22,9369 11,75% 0,0044 9,7500 4,99 % 0,0019 32,6869 16,74 % 0,0063
3 Pek. Stop Cor m' 151,00 0,0388 5,6000 3,71% 0,0014 2,8000 1,85 % 0,0007 8,4000 5,56 % 0,0022
SUB TOTAL PEKERJAAN STRUKTUR LANTAI BASEMENT 0,9368 0,3397 0,0447 0,3843

LAPORAN QUANTITY MINGGUAN BULAN OKTOBER 2019


PERIODE MINGGU KE

PEKERJAAN : PEMBANGUNAN RUMAH SAKIT ROYAL BIRINGKANAYA 21 Okt 2019


LOKASI : Jalan Pajjaiang - Makassar S/D 33
TAHUN : 2019 27 Okt 2019

REALISASI

NO URAIAN PEKERJAAN SAT VOLUME BOBOT S/D Minggu Lalu Minggu Ini S/D Minggu Ini

Volume Progress Bobot Volume Progress Bobot Volume Progress Bobot

Pekerjaan Dinding Basement


1 Pek. Dinding Beton tbl. 25 cm
- Cor beton K-300 m³ 195,21 0,2270 32,6869 16,74% 0,0380 7,2131 3,70 % 0,0084 39,9000 20,44 % 0,0464
- Besi Beton kg 18.802,87 0,2319 18.802,8680 100,00% 0,2319 0,0000 0,00 % 0,0000 18.802,8680 100,00 % 0,2319
- Bekisting m2 1.561,70 0,4013 412,2950 26,40% 0,1060 20,2050 1,29 % 0,0052 432,5000 27,69 % 0,1111
2 Pek. Waterproofing integral m³ 195,21 0,0378 32,6869 16,74% 0,0063 7,2131 3,70 % 0,0014 39,9000 20,44 % 0,0077
3 Pek. Stop Cor m' 151,00 0,0388 8,4000 5,56% 0,0022 2,8000 1,85 % 0,0007 11,2000 7,42 % 0,0029
SUB TOTAL PEKERJAAN STRUKTUR LANTAI BASEMENT 0,9368 0,3843 0,0157 0,4000
LAPORAN QUANTITY MINGGUAN BULAN OKTOBER 2019
PERIODE MINGGU KE

PEKERJAAN : PEMBANGUNAN RUMAH SAKIT ROYAL BIRINGKANAYA 28 Okt 2019


LOKASI : Jalan Pajjaiang - Makassar S/D 34
TAHUN : 2019 03 Nov 2019

REALISASI

NO URAIAN PEKERJAAN SAT VOLUME BOBOT S/D Minggu Lalu Minggu Ini S/D Minggu Ini

Volume Progress Bobot Volume Progress Bobot Volume Progress Bobot

Pekerjaan Dinding Basement


1 Pek. Dinding Beton tbl. 25 cm
- Cor beton K-300 m³ 195,21 0,2270 39,9000 20,44% 0,0464 17,4950 8,96 % 0,0203 57,3950 29,40 % 0,0667
- Besi Beton kg 18.802,87 0,2319 18.802,8680 100,00% 0,2319 0,0000 0,00 % 0,0000 18.802,8680 100,00 % 0,2319
- Bekisting m2 1.561,70 0,4013 432,5000 27,69% 0,1111 102,5800 6,57 % 0,0264 535,0800 34,26 % 0,1375
2 Pek. Waterproofing integral m³ 195,21 0,0378 39,9000 20,44% 0,0077 17,4950 8,96 % 0,0034 57,3950 29,40 % 0,0111
3 Pek. Stop Cor m' 151,00 0,0388 11,2000 7,42% 0,0029 5,6000 3,71 % 0,0014 16,8000 11,13 % 0,0043
SUB TOTAL PEKERJAAN STRUKTUR LANTAI BASEMENT 0,9368 0,4000 0,0515 0,4516

LAPORAN QUANTITY MINGGUAN BULAN NOVEMBER 2019


PERIODE MINGGU KE

PEKERJAAN : PEMBANGUNAN RUMAH SAKIT ROYAL BIRINGKANAYA 04 Nov 2019


LOKASI : Jalan Pajjaiang - Makassar S/D 35
TAHUN : 2019 10 Nov 2019

REALISASI

NO URAIAN PEKERJAAN SAT VOLUME BOBOT S/D Minggu Lalu Minggu Ini S/D Minggu Ini

Volume Progress Bobot Volume Progress Bobot Volume Progress Bobot

Pekerjaan Dinding Basement


1 Pek. Dinding Beton tbl. 25 cm
- Cor beton K-300 m³ 195,21 0,2270 57,3950 29,40% 0,0667 8,1900 4,20 % 0,0095 65,5850 33,60 % 0,0763
- Besi Beton kg 18.802,87 0,2319 18.802,8680 100,00% 0,2319 0,0000 0,00 % 0,0000 18.802,8680 100,00 % 0,2319
- Bekisting m2 1.561,70 0,4013 535,0800 34,26% 0,1375 27,5600 1,76 % 0,0071 562,6400 36,03 % 0,1446
2 Pek. Waterproofing integral m³ 195,21 0,0378 57,3950 29,40% 0,0111 8,1900 4,20 % 0,0016 65,5850 33,60 % 0,0127
3 Pek. Stop Cor m' 151,00 0,0388 16,8000 11,13% 0,0043 2,8000 1,85 % 0,0007 19,6000 12,98 % 0,0050
SUB TOTAL PEKERJAAN STRUKTUR LANTAI BASEMENT 0,9368 0,4516 0,0189 0,4705
LAPORAN QUANTITY MINGGUAN BULAN NOVEMBER 2019
PERIODE MINGGU KE

PEKERJAAN : PEMBANGUNAN RUMAH SAKIT ROYAL BIRINGKANAYA 11 Nov 2019


LOKASI : Jalan Pajjaiang - Makassar S/D 36
TAHUN : 2019 17 Nov 2019

REALISASI

NO URAIAN PEKERJAAN SAT VOLUME BOBOT S/D Minggu Lalu Minggu Ini S/D Minggu Ini

Volume Progress Bobot Volume Progress Bobot Volume Progress Bobot

Pekerjaan Dinding Basement


1 Pek. Dinding Beton tbl. 25 cm
- Cor beton K-300 m³ 195,21 0,2270 65,5850 33,60% 0,0763 0,0000 0,00 % 0,0000 65,5850 33,60 % 0,0763
- Besi Beton kg 18.802,87 0,2319 18.802,8680 100,00% 0,2319 0,0000 0,00 % 0,0000 18.802,8680 100,00 % 0,2319
- Bekisting m2 1.561,70 0,4013 562,6400 36,03% 0,1446 77,1600 4,94 % 0,0198 639,8000 40,97 % 0,1644
2 Pek. Waterproofing integral m³ 195,21 0,0378 65,5850 33,60% 0,0127 0,0000 0,00 % 0,0000 65,5850 33,60 % 0,0127
3 Pek. Stop Cor m' 151,00 0,0388 19,6000 12,98% 0,0050 5,6000 3,71 % 0,0014 25,2000 16,69 % 0,0065
SUB TOTAL PEKERJAAN STRUKTUR LANTAI BASEMENT 0,9368 0,4705 0,0213 0,4917

LAPORAN QUANTITY MINGGUAN BULAN NOVEMBER 2019


PERIODE MINGGU KE

PEKERJAAN : PEMBANGUNAN RUMAH SAKIT ROYAL BIRINGKANAYA 18 Nov 2019


LOKASI : Jalan Pajjaiang - Makassar S/D 37
TAHUN : 2019 24 Nov 2019

REALISASI

NO URAIAN PEKERJAAN SAT VOLUME BOBOT S/D Minggu Lalu Minggu Ini S/D Minggu Ini

Volume Progress Bobot Volume Progress Bobot Volume Progress Bobot

Pekerjaan Dinding Basement


1 Pek. Dinding Beton tbl. 25 cm
- Cor beton K-300 m³ 195,21 0,2270 65,5850 33,60% 0,0763 6,4450 3,30 % 0,0075 72,0300 36,90 % 0,0838
- Besi Beton kg 18.802,87 0,2319 18.802,8680 100,00% 0,2319 0,0000 0,00 % 0,0000 18.802,8680 100,00 % 0,2319
- Bekisting m2 1.561,70 0,4013 639,8000 40,97% 0,1644 27,1000 1,74 % 0,0070 666,9000 42,70 % 0,1714
2 Pek. Waterproofing integral m³ 195,21 0,0378 65,5850 33,60% 0,0127 6,4450 3,30 % 0,0012 72,0300 36,90 % 0,0140
3 Pek. Stop Cor m' 151,00 0,0388 25,2000 16,69% 0,0065 2,8000 1,85 % 0,0007 28,0000 18,54 % 0,0072
SUB TOTAL PEKERJAAN STRUKTUR LANTAI BASEMENT 0,9368 0,4917 0,0164 0,5082
LAPORAN QUANTITY MINGGUAN BULAN NOVEMBER 2019
PERIODE MINGGU KE

PEKERJAAN : PEMBANGUNAN RUMAH SAKIT ROYAL BIRINGKANAYA 25 Nov 2019


LOKASI : Jalan Pajjaiang - Makassar S/D 38
TAHUN : 2019 30 Nov 2019

REALISASI

NO URAIAN PEKERJAAN SAT VOLUME BOBOT S/D Minggu Lalu Minggu Ini S/D Minggu Ini

Volume Progress Bobot Volume Progress Bobot Volume Progress Bobot

Pekerjaan Dinding Basement


1 Pek. Dinding Beton tbl. 25 cm
- Cor beton K-300 m³ 195,21 0,2270 0,0000 0,00% 0,0000 14,7350 7,55 % 0,0171 14,7350 7,55 % 0,0171
- Besi Beton kg 18.802,87 0,2319 0,0000 0,00% 0,0000 0,0000 0,00 % 0,0000 0,0000 0,00 % 0,0000
- Bekisting m2 1.561,70 0,4013 0,0000 0,00% 0,0000 129,1400 8,27 % 0,0332 129,1400 8,27 % 0,0332
2 Pek. Waterproofing integral m³ 195,21 0,0378 0,0000 0,00% 0,0000 14,7350 7,55 % 0,0029 14,7350 7,55 % 0,0029
3 Pek. Stop Cor m' 151,00 0,0388 0,0000 0,00% 0,0000 2,8000 1,85 % 0,0007 2,8000 1,85 % 0,0007
SUB TOTAL PEKERJAAN STRUKTUR LANTAI BASEMENT 0,9368 0,0000 0,0539 0,0539

LAPORAN QUANTITY MINGGUAN BULAN DESEMBER 2019


PERIODE MINGGU KE

PEKERJAAN : PEMBANGUNAN RUMAH SAKIT ROYAL BIRINGKANAYA 01 Des 2019


LOKASI : Jalan Pajjaiang - Makassar S/D 39
TAHUN : 2019 08 Des 2019

REALISASI

NO URAIAN PEKERJAAN SAT VOLUME BOBOT S/D Minggu Lalu Minggu Ini S/D Minggu Ini

Volume Progress Bobot Volume Progress Bobot Volume Progress Bobot

Pekerjaan Dinding Basement


1 Pek. Dinding Beton tbl. 25 cm
- Cor beton K-300 m³ 195,21 0,2270 86,7650 44,45% 0,1009 0,0000 0,00 % 0,0000 86,7650 44,45 % 0,1009
- Besi Beton kg 18.802,87 0,2319 18.802,8680 100,00% 0,2319 0,0000 0,00 % 0,0000 18.802,8680 100,00 % 0,2319
- Bekisting m2 1.561,70 0,4013 796,0400 50,97% 0,2046 0,0000 0,00 % 0,0000 796,0400 50,97 % 0,2046
2 Pek. Waterproofing integral m³ 195,21 0,0378 86,7650 44,45% 0,0168 0,0000 0,00 % 0,0000 86,7650 44,45 % 0,0168
3 Pek. Stop Cor m' 151,00 0,0388 30,8000 20,40% 0,0079 0,0000 0,00 % 0,0000 30,8000 20,40 % 0,0079
SUB TOTAL PEKERJAAN STRUKTUR LANTAI BASEMENT 0,9368 0,5621 0,0000 0,5621