a b c
A. UPAH
4 Mandor OH
10 Pekerja OH
11 Tukang OH
12 Kepala Tukang OH
B. MATERIAL/BAHAN
a Bahan Batu
1 Batu Kali m3
2 Batu Tela bh
3 Batu Pecah 2-3 cm m3
b Bahan Pasir
1 Pasir Pasang ( Lokal ) m3
2 Pasir Beton/Cor m3
3 Pasir Plester m3
4 Pasir Urug m3
d Bahan Semen
1 Semen 50 Kg Zak
2 Semen Putih Kg
d Bahan Kayu
1 Balok Kayu Besi 10 x 10 m3
2 Balok Kayu Besi 5 x 10 m3
3 Balok Kayu Matoa 5 x 10 m3
4 Balok Kayu Matoa 5 x 5 m3
5 Papan Kayu Besi 3 x 30 x 4 m3
6 Papan Kayu Matoa 2 x 20 x 4 m3
7 Tripleks 4mm Lbr
8 List Kayu Profil m1
e Bahan Atap
1 Seng Gelombang Bjls 0.30 Warna Lbr
2 Seng Plat Bjls 0.30 m1
f Besi Beton
1 Besi Diameter 8 Btg
2 Besi Diameter 10 Btg
3 Besi Diameter 12 Btg
4 Besi Diameter 16 Btg
5 Kawat Ikat Kg
g Bahan Cat
1 Cat Tembok Merk Dullux Kg
2 Plamir Kg
3 Cat Dasar
4 Cat Kayu Glotekx 900grm Kg
5 Thiner Kg
6 Amplas Bh
7 Kuas Rool Bh
8 Kuas 2" Bh
9 Minyak Bekisting Ltr
10 Lem Kayu Kg
i sanitasi
1 Kloset duduk, putih unit
2 Kloset jongkok, porselin putih unit
3 Wastafel lengkap, porselin unit
4 Bak cuci piring (2 mata) unit
5 Floor Drain, Stainless Steel, 3" bh
6 Waterdrain untuk bak cuci piring bh
7 Kran air 3/4" bh
8 Kran wastafel, Angsa bh
9 Kran klosed bh
10 Shower tangan set
11 Seal tape bh
12 Stop kran PVC Ø3/4" bh
13 Stop kran PVC Ø2" bh
14 Roof Drain dia. 10" bh
15 Roof Drain dia. 4" bh
16 Tangki air fiber kapasitas 1 m3 + dudukan unit
17 Pompa air besar set
18 Pipa PVC Ø1/2" - AW m'
19 Pipa PVC Ø3/4" - AW m'
20 Pipa PVC Ø1" - AW m'
21 Pipa PVC Ø2" - AW m'
22 Pipa PVC Ø3" - AW m'
23 Pipa PVC Ø4" - AW m'
F. BAHAN LANGIT - LANGIT & DINDING PARTISI
N KAB. RAJA AMPAT (WASAI)
GARAN 2019
maksud (PPN)
USULAN HARGA
HARGA SATUAN SATUAN KET
2019 ( Rp ) 2019 ( Rp )
d e f
160,000 160,000
100,000 100,000
150,000 150,000
150,000 150,000
500,000 500,000
7,125 7,125
3,489,115 3,489,115
665,000 665,000
2,375,000 2,375,000
2,375,000 2,375,000
617,500 617,500
142,500 142,500
172,900 172,900
113,335 113,335
125,400 125,400
3,600,000 3,600,000
3,700,000 3,700,000
2,400,000 2,400,000
2,500,000 2,500,000
4,125,000 4,125,000
2,500,000 2,500,000
128,250 128,250
85,500 85,500
95,000 95,000
29,165 29,165
351,500 351,500
57,950 57,950 28,975
26,125 26,125 13,063
25,270 25,270 12,635
18,478 18,478
20,900 20,900
21,850 21,850
20,900 20,900
66,500 66,500
13,110 13,110
46,075 46,075
46,360 46,360
20,140 20,140
8,360 8,360
18,050 18,050
9,025 9,025
15,000 15,000
-
-
30,000 30,000
-
22,000 22,000
25,000 25,000
35,000 35,000
350,000 350,000
65,000 65,000
500,000 500,000 10000
10,000 10,000
-
-
1,750,000.00 1,750,000
450,000.00 450,000
715,000.00 715,000
340,000.00 340,000
50,000.00 50,000
50,000.00 50,000
40,000.00 40,000
65,000.00 65,000
40,000.00 40,000
240,000.00 240,000
10,000.00 10,000
20,000.00 20,000
70,000.00 70,000
70,000.00 70,000
40,000.00 40,000
2,100,000.00 2,100,000
1,250,000.00 1,250,000
25,000.00 25,000
30,000.00 30,000
70,000.00 70,000
110,000.00 110,000
150,000.00 150,000
250,000.00 250,000
A.2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN
SNI TAHUN 2013
A. 2.2.1.3. Pembersihan 1m2 lapangan dan peralatan
Pengurugan kembali 1 m3 galian dihitung dari 1/3 kali dari koefisien pekerjaan galian
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.500 100,000.00 50,000.00
Mandor L.04 OH 0.050 160,000.00 8,000.00
JUMLAH TENAGA KERJA 58,000.00
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 58,000.00
E Overhead & Profit (Contoh 10 %) 15% x D 8,700.00
F Harga Satuan Pekerjaan (E) 66,700.00
Pemadatan tanah 1 m3 tanah ( per 20 cm)
B. BAHAN
PC Semen Kg 230.000 5,605.00 1,289,150.00
PB Pasir Beton M3 0.638 2,375,000.00 1,514,910.71
KR Koral M3 0.761 3,489,115.00 2,654,311.93
Air Liter 200.000 7,000.00 1,400,000.00
C. PERALATAN
Pemasangan 1m2 dinding bata Telah (7x14x26) cm tebal 1/2 batu campuran 1SP :4PP
Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas I
B. BAHAN
1 PC Semen Kg 10.400 280,250.00 2,914,600.00
2 Semen Warna Kg 1.620 8,835.00 14,312.70
3 Pasir Pasang M3 0.045 665,000.00 29,925.00
4 Keramik anti selip uk. 40 x 40 M2 1.000 172,900.00 172,900.00
C. PERALATAN
B. BAHAN
1 PC Semen Kg 10.400 280,250.00 2,914,600.00
2 Semen Warna Kg 1.620 8,835.00 14,312.70
3 Pasir Pasang M3 0.045 665,000.00 29,925.00
4 Keramik 20 x 20 M2 1.060 113,335.00 120,135.10
C. PERALATAN
B. BAHAN
1 PC Semen Kg 9.300 280,250.00 2,606,325.00
2 Semen Warna Kg 2.750 8,835.00 24,296.25
3 Pasir Pasang M3 0.018 665,000.00 11,970.00
4 Keramik 20 x 25 M2 1.325 125,400.00 166,155.00
C. PERALATAN
D Jumlah harga tenaga, bahan dan peralatan ( A + B + C ) 2,980,196.25
E Overhead & profit ( 15 % x D ) 447,029.44
F Harga satuan pekerjaan ( D + E ) 3,427,225.69
PEKERJAAN ATAP
PEKERJAAN PLAFOND
PEKERJAAN ELEKTRIKAL
1 Titik instalasi lampu
m2 Pengecatan bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
m2 Pengecatan bidang Tripleks baru ( 1 lapis cat dasar, 2 lapis cat penutup)
Pengecatan 1 m2 tembok baru ( 1lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
Pemasangan 1 m2 acian.
Pembersihan Awal 43
x
Pemasangan Bowplank 10
Cerucuk Ø10Cm 9
#NAME? 74
Kolom 50 x 50 cm K-250 (Bangunan dan Pondasi)
PONDASI 0.5
K1 0.5
Kolom 15 x 15 cm K-250
LANTAI 1 0.15
MENARA 0.15
#NAME? 0.1
#NAME?
lantai 1 52
lantai 2 15
#NAME? 10
#NAME? 4
Profil Dinding
type 1 22
type 2 35
Pasangan Dinding 1/2 Bt Camp. 1 : 4 A1
L1 73
L2 61.4262
L3 1
BUKAAN KUSEN 19.0526
PINTU
Ventilasi v1
1.1458
Nok / Bubungan
atap 1 40
menara 1.63
List Plafond
dalam a 20
dalam b 24
samping 4
teras 4
belakang 14.44
altar
Pas. Batu 1/2 Batu Camp. 1:4 28
Timbunan Tanah 22
Pas. Batu Tangga 1/2 Batu Camp. 1:4 2.16
Pas. Batu Bata Tangga Keliling 1/2 Batu Camp. 1:4 68.3
22 946
y
8 18
1 0.2 26
0.8 0.2 27.2
53.2
22 0.5 473
10 0.5 50
523
22 0.02 18.92
10 0.02 2
20.92
19 171
0.5 0.5 75
0.5 3 14 7.35
0.15 4 5 0.45
0.15 2.5 15 0.84375
1.29375
A2
4 292
13.5 74.9262
2.5 4 10
27.8433 46.8959
JENDELA 330.0303
2.5 9 36
0.8 3 5.04
0.7 1 1.47
42.51
1.45 12 12.18
1.95 6 4.68
1.15 3 2.415
19.275
v2 v3
3.1596 0.3834 4.6888
l2 l3
22 45 110
2 3 15
0.05 0.1 20 4
0.05 0.1 0.0442
4.0442
p2
44 130
8.77 2 701.6
1.63 4 4.5966
706.1966
40
4 6.52
46.52
16 160
7 84
40 2 160
3 6
1 2 14.44
424.44
32 52
14 38
80 2 168
6 10
2 2 32.88
300.88
1.1 30.8
7 0.9 138.6
1 2 4.32
0.48 32.784
2 2 4.4
0.5 3.625
8.025
2 2 4.4
0.5 3.625
8.025
0.2 2 3.536
0.2 2 2.04
0.2 3 3
0.2 6 14.964
0.2 6 5.88
0.2 3 2.976
32.396
4 2 10.92
3.2 10 20.1056
31.0256
0.6 2 9.228
1.3 9.945
19.173
RENCANA ANGGARAN BIAYA
PEKERJAAN :
LOKASI :
JUMLAH
HARGA
HARGA
No. URAIAN PEKERJAAN SAT VOLUME SATUAN
(Rp)
(Rp)
1 2 3 4 5 6
A UMUM
I. PEKERJAAN PERSIAPAN
1 Pembersihan Awal M² 946.00 20,700.00 19,582,200.00
2 Pemasangan Bowplank M1 18.00 383,200.70 6,897,612.60
3 Direksi Keet Ls 1.00 5,000,000.00 5,000,000.00
4 Foto Dokumentasi + Laporan Ls 1.00 2,000,000.00 2,000,000.00
5 Papan Nama Proyek Ls 1.00 500,000.00 500,000.00
6 Listrik & Air Kerja Ls 1.00 2,000,000.00 2,000,000.00
Jumlah 35,979,812.60
B PEKERJAAN STRUKTUR DAN ARSITEKTUR
I. PEKERJAAN TANAH DAN PONDASI
1 Galian Tanah Pondasi M³ 592.56 90,850.00 53,834,076.00
2 Pas. Pondasi Batu Kali Camp. 1:4 M³ 73.58 1,845,939.75 135,815,017.11
3 Pas. Batu Kosong M³ 53.20 1,167,652.50 62,119,113.00
4 Penimbunan Kembali Hasil Galian M³ 177.77 66,700.00 11,857,125.60
5 Penimbunan dan Pemadatan (lantai, dan Teras) M³ 523.00 140,443.75 73,452,081.25
6 Urugan Pasir Bawah Pondasi (Telapak dan Menerus) M³ 3.27 888,490.00 2,908,560.86
7 Urugan Pasir Bawah Lantai (Dalam, Teras, Tangga dan Altar) M³ 20.92 888,490.00 18,587,210.80
8 Cerucuk Ø10Cm Btg 171.00 50,000.00 8,550,000.00
Jumlah 367,123,184.62
II. PEKERJAAN BETON BERTULANG
1 Sloop 50 x 50 cm K-250 M³ 75.00 5,648,357.25 423,626,793.75
2 Kolom 50 x 50 cm K-250 (Bangunan dan Pondasi) M³ 28.13 13,852,657.70 389,605,997.67
3 Kolom 35 x 50 cm K-250 M³ 7.35 13,852,657.70 101,817,034.06
4 Kolom Spiral Ø55 cm K-250 M³ 60.79 13,852,657.70 842,108,602.34
5 Kolom 15 x 15 cm K-250 M³ 1.29 13,852,657.70 17,921,875.89
6 Ring Balok 50 X 50 cm K-250 M³ 36.75 5,942,389.25 218,382,804.94
7 Foot Plat 150 x 150 x 30 Cm K-250 M³ 12.83 12,847,520.32 164,769,448.10
8 Cor Lantai Beton Tumbuk t = 8 cm (Dalam, Luar dan Altar) M³ 75.68 3,420,571.50 258,868,851.12
9 Dak Beton t = 10 Cm K-250 M³ 51.19 3,420,571.50 175,099,055.09
10 Cor Lantai Kerja t = 10 cm K-125 (Pondasi Telapak) M³ 4.28 8,074,118.54 34,516,856.76
11 Profil Dinding M³ 3.20 -
Jumlah 2,626,717,319.72
III. PEKERJAAN BATU, DINDING & PLESTERAN
1 Pasangan Dinding 1/2 Bt Camp. 1 : 4 M² 330.03 150,860.74 49,788,614.46
2 Pekerjaan Plesteran Dinding 1 : 4 M² 330.03 3,360,993.11 1,109,229,562.74
Jumlah 1,159,018,177.20
IV. PEKERJAAN PINTU DAN JENDELA
1 Kusen Pintu, Jendela Kayu Dan Ventilasi Kelas I M³ 0.81 10,007,443.75 8,105,028.69
2 Daun Pintu Panel Kayu M² 42.51 1,057,856.25 44,969,469.19
3 Daun Jendela Panel M² 19.28 989,287.50 19,068,516.56
4 Ventilasi M² 4.69 110,000.00 515,768.00
5 Batu Angin Bh 12.00 55,000.00 660,000.00
Jumlah 73,318,782.44
V. PEKERJAAN LANTAI
1 Keramik 40 x 40 (Dalam, Teras, Tangga, dan Altar) M² 110.00 3,754,850.86 413,033,594.05
2 Keramik 20 x 20 (Kamar Mandi dan WC) M² 15.00 3,694,171.22 55,412,568.30
3 Keramik Dinding 20x 25 (Kamar Mandi dan WC) M² 12.21 3,427,225.69 41,846,425.64
Jumlah 510,292,587.99
VI. PEKERJAAN ATAP
1 Rangka Kuda² Kayu 5/10 Kelas II M³ 3.18 7,839,550.00 24,910,562.10
2 Rangka Gording Kayu 5/10 Kelas II M³ 4.04 9,243,240.00 37,381,511.21
3 Listplank Kayu Kelas I M1 130.00 96,519.50 12,547,535.00
4 Penutup Atap Seng Gelombang Bjls 30 M² 706.20 107,789.50 76,120,578.42
5 Nok / Bubungan M1 46.52 42,703.53 1,986,567.98
Jumlah 152,946,754.71
VII. PEKERJAAN PLAFOND
1 Rangka Kayu 5 x 5 + plafon Triplex + Penggantung M² 424.44 193,085.86 81,953,363.48
2 List Plafond M1 300.88 118,926.10 35,782,484.97
Jumlah 117,735,848.45
VIII. PEKERJAAN PENGGANTUNG DAN PENGUNCI
1 Kunci Pintu Bh 6.00 501,170.00 3,007,020.00
2 Engsel Pintu 4" - Stainles Steel Bh 27.00 96,977.20 2,618,384.40
3 Engsel jendela Kupu-kupu Bh 24.00 50,260.75 1,206,258.00
4 Grendel Jendela Bh 6.00 68,433.63 410,601.75
5 Kait Angin Bh 24.00 47,184.50 1,132,428.00
Jumlah 8,374,692.15
IX. PEKERJAAN ELEKTRIKAL
1 Lampu Philips 18 Watt Bh 48.00 81,477.50 3,910,920.00
2 Lampu Philips 10 Watt Bh 6.00 75,727.50 454,365.00
3 Stop Kontak Bh 15.00 69,977.50 1,049,662.50
4 Saklar Ganda Bh 9.00 55,027.50 495,247.50
5 Saklar Tunggal Bh 9.00 58,477.50 526,297.50
6 Panel Listrik Bh 1.00 524,515.00 524,515.00
7 Instalasi Listrik Ttk 63.00 2,679,289.17 168,795,217.49
8 Sambungan Baru Ls 1.00 2,679,289.17 2,679,289.17
Jumlah 178,435,514.15
X. PEKERJAAN ACIAN & PENGECATAN
1 Acian Dinding M² 330.03 1,091,249.38 360,145,358.61
2 Pengecatan Dinding M² 330.03 41,496.03 13,694,945.58
3 Pengecatan Kolom Pilar M² 31.03 41,496.03 1,287,439.07
4 Cat Listplank Papan M² 39.00 66,954.96 2,611,243.25
5 Cat Plafond Triplex M² 424.44 67,299.96 28,564,792.90
6 Cat List Plafond M² 15.04 67,299.96 1,012,460.52
7 Cat Kusen Pintu dan Jendela M² 32.40 66,954.96 2,169,072.72
8 Cat Profil Beton M² 19.17 67,299.96 1,290,342.04
Jumlah 410,775,654.69
XI. PEKERJAAN SANITASI
1 Pemasangan Meteran Air Unit 1.00 200,000.00 200,000.00
2 Pemasangan Kran air 1/2" Bh 3.00 55,947.50 167,842.50
3 Pipa PVC 1/2" (Air Bersih) M1 20.00 97,614.88 1,952,297.50
4 Pemasangan Kloset Jongkok Bh 3.00 2,949,635.00 8,848,905.00
5 Pipa PVC Ø 2.5" (Air Kotor) M1 15.00 51,709.75 775,646.25
6 Pipa PVC Ø 4" (Air Limbah) M1 25.00 65,164.75 1,629,118.75
7 Floor Drain Bh 3.00 59,225.00 177,675.00
8 Pembuatan Bak Bh 3.00 2,100,000.00 6,300,000.00
9 Sepicktank Unit 1.00 1,800,000.00 1,800,000.00
Jumlah 21,851,485.00
XII. PEKERJAAN LAIN - LAIN
1 Pembuatan Altar
- Pas. Batu 1/2 Batu Camp. 1:4 M² 30.80 150,860.74 4,646,510.72
- Timbunan Tanah M³ 138.60 66,700.00 9,244,620.00
- Pas. Batu Tangga 1/2 Batu Camp. 1:4 M² 4.32 150,860.74 651,718.39
2 Pas. Batu Bata Tangga Keliling 1/2 Batu Camp. 1:4 M² 32.78 150,860.74 4,945,818.42
3 Pas. Batu Bata Penebalan Kolom dan Dincing Camp. 1:4 M² 8.03 1,091,249.38 8,757,276.23
4 Plesteran Penebalan Kolom dan Dinding Camp. 1:3 M² 8.03 3,360,993.11 26,971,969.67
5 Pemasangan Salib Pipa Stenless Ø2.5" Ls 1.00 1,000,000.00 1,000,000.00
6 Pembuatan Patung Malaikat Ls 2.00 50,000,000.00 100,000,000.00
7 Pembersihan Akhir Ls 1.00 5,000,000.00 5,000,000.00
Jumlah 161,217,913.42
A. TOTAL 5,823,787,727.15
REKAPITULASI BIAYA
PEKERJAAN :
LOKASI :
JUMLAH HARGA
No. URAIAN PEKERJAAN
(Rp)
1 2 3
A UMUM
I. PEKERJAAN PERSIAPAN 35,979,812.60
B PEKERJAAN STRUKTUR DAN ARSITEKTUR
I. PEKERJAAN TANAH DAN PONDASI 367,123,184.62
II. PEKERJAAN BETON BERTULANG 2,626,717,319.72
III. PEKERJAAN BATU, DINDING & PLESTERAN 1,159,018,177.20
IV. PEKERJAAN PINTU DAN JENDELA 73,318,782.44
V. PEKERJAAN LANTAI 510,292,587.99
VI. PEKERJAAN ATAP 152,946,754.71
VII. PEKERJAAN PLAFOND 117,735,848.45
VIII. PEKERJAAN PENGGANTUNG DAN PENGUNCI 8,374,692.15
IX. PEKERJAAN ELEKTRIKAL 178,435,514.15
X. PEKERJAAN ACIAN & PENGECATAN 410,775,654.69
XI. PEKERJAAN SANITASI 21,851,485.00
XII. PEKERJAAN LAIN - LAIN 161,217,913.42
A. TOTAL 5,823,787,727.15
B. PAJAK PERTAMBAHAN NILAI ( 10 % ) 582,378,772.71
C. JUMLAH TOTAL BIAYA PEKERJAAN 6,406,166,499.86
E NILAI PERENCANAAN (3,90%) 249,840,493.49
F NILAI PENGAWASAN (2,73%) 174,888,345.45
G JUMLAH TOTAL ( D + E + F) 6,830,895,338.80
D. FAKTOR PEMBULATAN 6,830,800,000.00
Terbilang : " Enam Milyar Delapan Ratus Tiga Puluh Juta Delapan Ratus Ribu Rupiah "
…………………………………….. ............................................
NIP. ……………………………………….. DIREKTUR
RENCANA ANGGARAN BIAYA
PEKERJAAN :
LOKASI :
JUMLAH
HARGA
HARGA
No. URAIAN PEKERJAAN SAT VOLUME SATUAN
(Rp)
(Rp)
1 2 3 4 5 6
A UMUM
I. PEKERJAAN PERSIAPAN
1 Pembersihan Awal M² 946.00 20,700.00 19,582,200.00
2 Pemasangan Bowplank M1 18.00 383,200.70 6,897,612.60
3 Direksi Keet Ls 1.00 5,000,000.00 5,000,000.00
4 Foto Dokumentasi + Laporan Ls 1.00 2,000,000.00 2,000,000.00
5 Papan Nama Proyek Ls 1.00 500,000.00 500,000.00
6 Listrik & Air Kerja Ls 1.00 2,000,000.00 2,000,000.00
Jumlah 35,979,812.60
B PEKERJAAN STRUKTUR DAN ARSITEKTUR
I. PEKERJAAN TANAH DAN PONDASI
1 Galian Tanah Pondasi M³ 592.56 90,850.00 53,834,076.00
2 Pas. Pondasi Batu Kali Camp. 1:4 M³ 73.58 1,845,939.75 135,815,017.11
3 Pas. Batu Kosong M³ 53.20 1,167,652.50 62,119,113.00
4 Penimbunan Kembali Hasil Galian M³ 177.77 66,700.00 11,857,125.60
5 Penimbunan dan Pemadatan (lantai, dan Teras) M³ 523.00 140,443.75 73,452,081.25
6 Urugan Pasir Bawah Pondasi (Telapak dan Menerus) M³ 3.27 888,490.00 2,908,560.86
7 Urugan Pasir Bawah Lantai (Dalam, Teras, Tangga dan Altar) M³ 20.92 888,490.00 18,587,210.80
8 Cerucuk Ø10Cm Btg 171.00 50,000.00 8,550,000.00
Jumlah 367,123,184.62
II. PEKERJAAN BETON BERTULANG
1 Sloop 50 x 50 cm K-250 M³ 75.00 5,648,357.25 423,626,793.75
2 Kolom 50 x 50 cm K-250 (Bangunan dan Pondasi) M³ 28.13 13,852,657.70 389,605,997.67
3 Kolom 35 x 50 cm K-250 M³ 7.35 13,852,657.70 101,817,034.06
4 Kolom Spiral Ø55 cm K-250 M³ 60.79 13,852,657.70 842,108,602.34
5 Kolom 15 x 15 cm K-250 M³ 1.29 13,852,657.70 17,921,875.89
6 Ring Balok 50 X 50 cm K-250 M³ 36.75 5,942,389.25 218,382,804.94
7 Foot Plat 150 x 150 x 30 Cm K-250 M³ 12.83 12,847,520.32 164,769,448.10
8 Cor Lantai Beton Tumbuk t = 8 cm (Dalam, Luar dan Altar) M³ 75.68 3,420,571.50 258,868,851.12
9 Dak Beton t = 10 Cm K-250 M³ 51.19 3,420,571.50 175,099,055.09
10 Cor Lantai Kerja t = 10 cm K-125 (Pondasi Telapak) M³ 4.28 8,074,118.54 34,516,856.76
11 Profil Dinding M³ 3.20 -
Jumlah 2,626,717,319.72
III. PEKERJAAN BATU, DINDING & PLESTERAN
1 Pasangan Dinding 1/2 Bt Camp. 1 : 4 M² 330.03 150,860.74 49,788,614.46
2 Pekerjaan Plesteran Dinding 1 : 4 M² 330.03 3,360,993.11 1,109,229,562.74
Jumlah 1,159,018,177.20
IV. PEKERJAAN PINTU DAN JENDELA
1 Kusen Pintu, Jendela Kayu Dan Ventilasi Kelas I M³ 0.81 10,007,443.75 8,105,028.69
2 Daun Pintu Panel Kayu M² 42.51 1,057,856.25 44,969,469.19
3 Daun Jendela Panel M² 19.28 989,287.50 19,068,516.56
4 Ventilasi M² 4.69 110,000.00 515,768.00
5 Batu Angin Bh 12.00 55,000.00 660,000.00
Jumlah 73,318,782.44
V. PEKERJAAN LANTAI
1 Keramik 40 x 40 (Dalam, Teras, Tangga, dan Altar) M² 110.00 3,754,850.86 413,033,594.05
2 Keramik 20 x 20 (Kamar Mandi dan WC) M² 15.00 3,694,171.22 55,412,568.30
3 Keramik Dinding 20x 25 (Kamar Mandi dan WC) M² 12.21 3,427,225.69 41,846,425.64
Jumlah 510,292,587.99
VI. PEKERJAAN ATAP
1 Rangka Kuda² Kayu 5/10 Kelas II M³ 3.18 7,839,550.00 24,910,562.10
2 Rangka Gording Kayu 5/10 Kelas II M³ 4.04 9,243,240.00 37,381,511.21
3 Listplank Kayu Kelas I M1 130.00 96,519.50 12,547,535.00
4 Penutup Atap Seng Gelombang Bjls 30 M² 706.20 107,789.50 76,120,578.42
5 Nok / Bubungan M1 46.52 42,703.53 1,986,567.98
Jumlah 152,946,754.71
VII. PEKERJAAN PLAFOND
1 Rangka Kayu 5 x 5 + plafon Triplex + Penggantung M² 424.44 193,085.86 81,953,363.48
2 List Plafond M1 300.88 118,926.10 35,782,484.97
Jumlah 117,735,848.45
VIII. PEKERJAAN PENGGANTUNG DAN PENGUNCI
1 Kunci Pintu Bh 6.00 501,170.00 3,007,020.00
2 Engsel Pintu 4" - Stainles Steel Bh 27.00 96,977.20 2,618,384.40
3 Engsel jendela Kupu-kupu Bh 24.00 50,260.75 1,206,258.00
4 Grendel Jendela Bh 6.00 68,433.63 410,601.75
5 Kait Angin Bh 24.00 47,184.50 1,132,428.00
Jumlah 8,374,692.15
IX. PEKERJAAN ELEKTRIKAL
1 Lampu Philips 18 Watt Bh 48.00 81,477.50 3,910,920.00
2 Lampu Philips 10 Watt Bh 6.00 75,727.50 454,365.00
3 Stop Kontak Bh 15.00 69,977.50 1,049,662.50
4 Saklar Ganda Bh 9.00 55,027.50 495,247.50
5 Saklar Tunggal Bh 9.00 58,477.50 526,297.50
6 Panel Listrik Bh 1.00 524,515.00 524,515.00
7 Instalasi Listrik Ttk 63.00 2,679,289.17 168,795,217.49
8 Sambungan Baru Ls 1.00 2,679,289.17 2,679,289.17
Jumlah 178,435,514.15
X. PEKERJAAN ACIAN & PENGECATAN
1 Acian Dinding M² 330.03 1,091,249.38 360,145,358.61
2 Pengecatan Dinding M² 330.03 41,496.03 13,694,945.58
3 Pengecatan Kolom Pilar M² 31.03 41,496.03 1,287,439.07
4 Cat Listplank Papan M² 39.00 66,954.96 2,611,243.25
5 Cat Plafond Triplex M² 424.44 67,299.96 28,564,792.90
6 Cat List Plafond M² 15.04 67,299.96 1,012,460.52
7 Cat Kusen Pintu dan Jendela M² 32.40 66,954.96 2,169,072.72
8 Cat Profil Beton M² 19.17 67,299.96 1,290,342.04
Jumlah 410,775,654.69
XI. PEKERJAAN SANITASI
1 Pemasangan Meteran Air Unit 1.00 200,000.00 200,000.00
2 Pemasangan Kran air 1/2" Bh 3.00 55,947.50 167,842.50
3 Pipa PVC 1/2" (Air Bersih) M1 20.00 97,614.88 1,952,297.50
4 Pemasangan Kloset Jongkok Bh 3.00 2,949,635.00 8,848,905.00
5 Pipa PVC Ø 2.5" (Air Kotor) M1 15.00 51,709.75 775,646.25
6 Pipa PVC Ø 4" (Air Limbah) M1 25.00 65,164.75 1,629,118.75
7 Floor Drain Bh 3.00 59,225.00 177,675.00
8 Pembuatan Bak Bh 3.00 2,100,000.00 6,300,000.00
9 Sepicktank Unit 1.00 1,800,000.00 1,800,000.00
Jumlah 21,851,485.00
XII. PEKERJAAN LAIN - LAIN
1 Pembuatan Altar
- Pas. Batu 1/2 Batu Camp. 1:4 M² 30.80 150,860.74 4,646,510.72
- Timbunan Tanah M³ 138.60 66,700.00 9,244,620.00
- Pas. Batu Tangga 1/2 Batu Camp. 1:4 M² 4.32 150,860.74 651,718.39
2 Pas. Batu Bata Tangga Keliling 1/2 Batu Camp. 1:4 M² 32.78 150,860.74 4,945,818.42
3 Pas. Batu Bata Penebalan Kolom dan Dincing Camp. 1:4 M² 8.03 1,091,249.38 8,757,276.23
4 Plesteran Penebalan Kolom dan Dinding Camp. 1:3 M² 8.03 3,360,993.11 26,971,969.67
5 Pemasangan Salib Pipa Stenless Ø2.5" Ls 1.00 1,000,000.00 1,000,000.00
6 Pembersihan Akhir Ls 1.00 5,000,000.00 5,000,000.00
Jumlah 61,217,913.42
A. TOTAL 5,723,787,727.15
REKAPITULASI BIAYA
PEKERJAAN :
LOKASI :
JUMLAH
No. URAIAN PEKERJAAN HARGA
(Rp)
1 2 3
A UMUM
I. PEKERJAAN PERSIAPAN 35,979,812.60
B PEKERJAAN STRUKTUR DAN ARSITEKTUR 367,123,184.62
I. PEKERJAAN TANAH DAN PONDASI 2,626,717,319.72
II. PEKERJAAN BETON BERTULANG 1,159,018,177.20
III. PEKERJAAN BATU, DINDING & PLESTERAN 73,318,782.44
IV. PEKERJAAN PINTU DAN JENDELA 73,318,782.44
V. PEKERJAAN LANTAI 510,292,587.99
VI. PEKERJAAN ATAP 152,946,754.71
VII. PEKERJAAN PLAFOND 117,735,848.45
VIII. PEKERJAAN PENGGANTUNG DAN PENGUNCI 8,374,692.15
IX. PEKERJAAN ELEKTRIKAL 178,435,514.15
X. PEKERJAAN ACIAN & PENGECATAN 410,775,654.69
XI. PEKERJAAN SANITASI 21,851,485.00
XII. PEKERJAAN LAIN - LAIN 61,217,913.42
A. TOTAL 5,797,106,509.59
B. PAJAK PERTAMBAHAN NILAI ( 10 % ) 579,710,650.96
C. JUMLAH TOTAL BIAYA PEKERJAAN 6,376,817,160.55
E NILAI PERENCANAAN (3,90%) 248,695,869.26
F NILAI PENGAWASAN (2,73%) 174,087,108.48
G JUMLAH TOTAL ( D + E + F) 6,799,600,138.29
Terbilang : " Tujuh Milyar Dua Ratus Sembilan Puluh Tujuh Juta "
…………………………………….. ............................................
NIP. ……………………………………….. DIREKTUR