LAPORAN PROGGRES PEMBANGUNAN

NO URAIAN PROGGRES KET


PELAKSANAAN

01 02 11

I ADMINISTRASI
I.1 PERIZINAN 100.00%
I.2 SEWA / BELI TANAH 100.00%

II PERSIAPAN
II.1 MOB / DEMOB ALAT 50.00%
II.2 LISTRIK, AIR KERJA DAN PRODUKSI 60.00%
II.3 PEMATANGAN LAHAN 85.00%
II.4 PAGAR KELILING 75.00%

III BATCHING PLANT


III.1 OPRITE - BP 100.00%
III.2 CONTROL KABIN & HOPPER AGGREGAT - BP 100.00%
III.3 PONDASI MIXER & CONVEYOR - BP 100.00%
III.4 SILO - BP 100.00%
III.5 STOK MATERIAL 40.00%
III.6 SEKAT STOCK PILE 0.00%
III.7 UTILITAS BATCHING PLANT
III.7.1 BAK KONTROL 100.00%
III.7.2 BAK PENGOLAH LIMBAH 100.00%
III.7.3 SALURAN LIMBAH 100.00%
III.7.4 SALURAN TERBUKA 90.00%
III.7.5 BAK RENDAM UJI + Atap 100.00%
III.7.6 ERECTION BP & PENANGKAL PETIR 100.00%
III.7.7 AKSES BATCHING PLANT 70.00%
III.7.8 BASE CAMP (KANTOR & GUDANG) 65.00%
III.7.9 KM / TOILET 70.00%
III.7.10 MUSHOLA 0.00%
III.7.11 POS SATPAM 100.00%
III.7.12 RUMAH GENSET 100.00%
III.7.13 TANGKI SOLAR 8000 L + RUMAH TANGKI 100.00%
III.7.14 BAK AIR 30000 L 100.00%

JUMLAH BIAYA I + II + III 26 80.96%


RENCANA USAHA PRODUKSI