BILL OF QUANTITY

PEKERJAAN : LAPANGAN BOLA MAKODAM XII / TANJUNGPURA


LOKASI : MAKODAM XII / TANJUNGPURA KABUPATEN KUBU RAYA
TAHUN ANGGARAN : 2017

BIAYA PEKERJAAN
NO. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH BIAYA
(Rp.) (Rp.)

1 2 3 4 5 6

1. Urugan Tanah Pilihan Dengan Alat Berat M3 2,425.82 444,387.28 1,078,003,559.07


2. Tanam Rumput Klekep M2 5,698.00 37,500.00 213,675,000.00
3. Parit Pasangan 60 x 60 x 40 cm M1 400.00 643,145.68 257,258,272.73
JUMLAH I 1,548,936,831.80
JUMLAH I 1,548,936,831.80
PPN 10 % 154,893,683.18
JUMLAH TOTAL 1,703,830,514.98
DIBULATKAN 1,703,830,000.00

TERBILANG : SATU MILYAR TUJUH RATUS TIGA JUTA DELAPAN RATUS TIGA PULUH RIBU RUPIAH

Pontianak, 08 April 2017

Dibuat Oleh :
PT. MITRA ANTARA BENUA

HERIANTO GANI
Direktur
16.6087001

PPN 10 % #REF! NILAI PENAWARAN #REF!


Setelah PPN #REF! PNN 10% #REF!
PPH 2% #REF! #REF!
HARGA NETTO #REF! PPH 2% #REF!
#REF! NETTO #REF!

#REF!
#REF!

1,110,835,075.48
(592,994,924.52)
BILL OF QUANTITY
PEKERJAAN : URUGAN JALAN ASR. KHATULISTIWA
LOKASI : ASRAMA KHATULISTIWA SIANTAN
TAHUN ANGGARAN : 2017

BIAYA PEKERJAAN
NO. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN
(Rp.)

1 2 3 4 5

I. PEKERJAAN PERSIAPAN
1. Penyiapan Badan Jalan M2 3,741.00 8,532.13
JUMLAH I

II. PEKERJAAN TANAH


1. Urugan Pasir Tebal 10 cm M3 374.10 167,265.47
2. Urugan Tanah Datang Tebal 35 cm M3 1,975.37 96,281.19
3. Pas. Cerucuk Bh 2,057.00 23,387.48
JUMLAH II

III. PEKERJAAN BETON


1. Jalan Cor Beton M3 374.10 1,117,726.54
2. Gelegar Jemabatan M3 3.20 5,731,470.41
3. Plat Jembatan M3 3.60 5,488,311.38
4. Buis Beton Dia. 80 cm ( 6 Buah ) M3 1.89 1,117,726.54
5. Lantai Kerja Turap Batu Kali Tebal 10 cm M3 75.64 1,032,143.35
JUMLAH III

IV. PEKERJAAN PASANGAN


1. Turap Batu Kali M3 150.84 867,335.49
2. Turap Abutment M3 5.59 867,335.49
JUMLAH IV
JUMLAH I + II + III + IV
PPN 10 %
JUMLAH TOTAL
DIBULATKAN

TERBILANG : SATU MILYAR SERATUS LIMA JUTA TIGA RATUS DELAPAN PULUH DUA RIBU RUPIAH

Pontianak, 09 April 2017

Dibuat Oleh :
PT. MITRA ANTARA BENUA

HERIANTO GANI
Direktur
BILL OF QUANTITY

BIAYA PEKERJAAN
JUMLAH BIAYA
(Rp.)

31,918,679.63
31,918,679.63

62,574,012.33
190,190,968.36
48,108,036.08
300,873,016.77

418,141,498.14
18,340,705.33
19,757,920.97
2,112,503.16
78,071,323.37
536,423,950.96

130,828,885.34
4,848,405.39
135,677,290.73
1,004,892,938.08
100,489,293.81
1,105,382,231.89
1,105,382,000.00

TU MILYAR SERATUS LIMA JUTA TIGA RATUS DELAPAN PULUH DUA RIBU RUPIAH

Pontianak, 09 April 2017


1,110,835,075.48
Dibuat Oleh : 5,453,075.48
PT. MITRA ANTARA BENUA

HERIANTO GANI
Direktur
6.22693323

29.9408032
0
0
41.610552

PPN 10 % #REF! NILAI PENAWARAN #REF!


Setelah PPN #REF! PNN 10% #REF!
PPH 2% #REF! #REF!
HARGA NETTO #REF! PPH 2% #REF!
#REF! NETTO #REF!

#REF!
#REF!
ANALISA HARGA SATUAN PEKERJAAN
TAHUN ANGGARAN 2017

M2 PEMBERSIHAN LAPANGAN DAN PERATAAN TANAH

HARGA BIAYA
NO. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
(Rp.) (Rp.)

1 2 3 4 5 6
A. TENAGA
1. Pekerja OH 79,600.00 0.100 7,960.00
2. Mandor OH 114,425.00 0.005 572.13
Jumlah 8,532.13
B. BAHAN

Jumlah -
C. ALAT
Jumlah -
D. Jumlah A + B + C 8,532.13
E. Overhead & Profit 15% x D -
F. Harga Satuan (D + E) 8,532.13

M3 MENGURUG PASIR URUG TEBAL 10 CM

HARGA BIAYA
NO. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
(Rp.) (Rp.)

1 2 3 4 5 6
A. TENAGA
1. Pekerja OH 79,600.00 0.300 23,880.00
2. Mandor OH 114,425.00 0.010 1,144.25
Jumlah 25,024.25
B. BAHAN
1. Pasir Urug m3 118,534.35 1.200 142,241.22
Jumlah 142,241.22
C. ALAT

Jumlah -
D. Jumlah A + B + C 167,265.47
E. Overhead & Profit 15% x D -
F. Harga Satuan (D + E) 167,265.47

M3 URUGAN TANAH DATANG TEBAL 35 CM

HARGA BIAYA
NO. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
(Rp.) (Rp.)

1 2 3 4 5 6
A. TENAGA
1. Pekerja OH 79,600.00 0.250 19,900.00
2. Mandor OH 114,425.00 0.025 2,860.63
Jumlah 22,760.63
B. BAHAN
1. Tanah Urug / Tanah Datang M3 60,991.51 1.200 73,189.81
Jumlah 73,189.81
C. ALAT
1. VIBRATORY ROLLER 5-8 T Sewa/Jam 22,500.00 0.0076 171.00
2. WATER TANKER 3000-4500 L Sewa/Jam 22,500.00 0.0071 159.75
Jumlah 330.75
D. Jumlah A + B + C 96,281.19
E. Overhead & Profit 15% x D -
F. Harga Satuan (D + E) 96,281.19
M3 JALAN COR BETON

HARGA BIAYA
NO. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
(Rp.) (Rp.)

1 2 3 4 5 6
A. TENAGA
1. Pekerja OH 79,600.00 1.650 131,340.00
2. Tukang Batu OH 99,500.00 0.275 27,362.50
3. Kepala Tukang OH 114,425.00 0.028 3,203.90
4. Mandor OH 114,425.00 0.083 9,497.28
Jumlah 171,403.68
B. BAHAN
1. Semen Portland Zak 74,453.86 7.680 571,805.64
2. Pasir Beton m3 142,258.14 0.499 70,986.81
3. Batu Split Pecah Mesin 1/2 m3 391,147.44 0.776 303,530.41
Jumlah 946,322.86
C. ALAT

Jumlah -
D. Jumlah A + B + C 1,117,726.54
E. Overhead & Profit 15% x D -
F. Harga Satuan (D + E) 1,117,726.54

1 TTK PANCANG KAYU BULAT / MERAH / DOLKEN

HARGA BIAYA
NO. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
(Rp.) (Rp.)

1 2 3 4 5 6
A. TENAGA
1. Pekerja OH 79,600.00 0.100 7,960.00
2. Mandor OH 114,425.00 0.010 1,144.25
Jumlah 9,104.25
B. BAHAN
1. Kayu Cerucuk /Dolken ø 8-10 - Pj. 4 M Btg 14,283.23 1.000 14,283.23
Jumlah 14,283.23
C. ALAT
Jumlah -
D. Jumlah A + B + C 23,387.48
E. Overhead & Profit 15% x D -
F. Harga Satuan (D + E) 23,387.48

1 M3 MEMBUAT BALOK BETON ( 150 Kg Besi + Bekesting )

HARGA BIAYA
NO. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
(Rp.) (Rp.)

1 2 3 4 5 6
A. TENAGA
1. Pekerja OH 79,600.00 5.800 461,680.00
2. Tukang Batu OH 99,500.00 0.350 34,825.00
3. Tukang Kayu OH 99,500.00 2.800 278,600.00
4. Tukang Besi OH 99,500.00 1.050 104,475.00
5. Kepala Tukang OH 114,425.00 0.420 48,058.50
6. Mandor OH 114,425.00 0.190 21,740.75

Jumlah 949,379.25
B. BAHAN
1. Kayu Bekesting m3 2,717,096.25 0.210 570,590.21
2. Paku biasa 2"-5" Kg 29,634.09 3.200 94,829.07
3. Minyak Bekisting Ltr 6,965.00 1.600 11,144.00
4. Besi Tulangan Beton (Polos / Ulir) Kg 17,977.66 150.000 2,696,649.00
5. Kawat Beton (Bendrat) Kg 20,521.88 2.250 46,174.22
6. Semen Portland Kg 1,489.52 323.000 481,113.35
7. Pasir Beton m3 142,258.14 0.520 73,974.23
8. Batu Split Pecah Mesin 1/2 m3 391,147.44 0.780 305,095.00
9. Papan Kayu Kelas III ( Tidak Ketam ) m3 2,264,384.19 0.121 273,990.49
10. Kayu Cerucuk /Dolken ø 8-10 - Pj. 4 M Btg 14,283.23 16.000 228,531.60
Jumlah 4,782,091.16
C. ALAT

Jumlah -
D. Jumlah A + B + C 5,731,470.41
E. Overhead & Profit 15% x D -
F. Harga Satuan (D + E) 5,731,470.41
1 M3 PEKERJAAN PLAT LANTAI BETON TEBAL 12 CM

HARGA BIAYA
NO. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
(Rp.) (Rp.)

1 2 3 4 5 6
A. TENAGA

Jumlah -
B. BAHAN
1. Plat Lantai Beton Tebal 12 cm M2 658,600.00 8.333 5,488,311.38
Jumlah 5,488,311.38
C. ALAT
Jumlah -
D. Jumlah A + B + C 5,488,311.38
E. Overhead & Profit 15% x D -
F. Harga Satuan (D + E) 5,488,311.38

M3 BUIS BETON DIA. 80 CM ( 6 Buah )

HARGA BIAYA
NO. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
(Rp.) (Rp.)

1 2 3 4 5 6
A. TENAGA
1. Pekerja OH 79,600.00 1.650 131,340.00
2. Tukang Batu OH 99,500.00 0.275 27,362.50
3. Kepala Tukang OH 114,425.00 0.028 3,203.90
4. Mandor OH 114,425.00 0.083 9,497.28
Jumlah 171,403.68
B. BAHAN
1. Semen Portland Zak 74,453.86 7.680 571,805.64
2. Pasir Beton m3 142,258.14 0.499 70,986.81
3. Batu Split Pecah Mesin 1/2 m3 391,147.44 0.776 303,530.41
Jumlah 946,322.86
C. ALAT

Jumlah -
D. Jumlah A + B + C 1,117,726.54
E. Overhead & Profit 15% x D -
F. Harga Satuan (D + E) 1,117,726.54

M3 LANTAI KERJA TURAP BATU KALI 10 CM

HARGA BIAYA
NO. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
(Rp.) (Rp.)

1 2 3 4 5 6
A. TENAGA
1. Pekerja OH 79,600.00 1.650 131,340.00
2. Tukang Batu OH 99,500.00 0.275 27,362.50
3. Kepala Tukang OH 114,425.00 0.028 3,203.90
4. Mandor OH 114,425.00 0.083 9,497.28
Jumlah 171,403.68
B. BAHAN
1. Semen Portland Zak 74,453.86 6.520 485,439.17
2. Pasir Beton m3 142,258.14 0.543 77,246.17
3. Batu Split Pecah Mesin 1/2 m3 391,147.44 0.762 298,054.35
Jumlah 860,739.68
C. ALAT

Jumlah -
D. Jumlah A + B + C 1,032,143.35
E. Overhead & Profit 15% x D -
F. Harga Satuan (D + E) 1,032,143.35
M3 TURAP BATU KALI

HARGA BIAYA
NO. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
(Rp.) (Rp.)

1 2 3 4 5 6
A. TENAGA
1. Pekerja OH 79,600.00 2.250 179,100.00
2. Tukang Batu OH 99,500.00 0.600 59,700.00
3. Kepala Tukang OH 114,425.00 0.060 6,865.50
4. Mandor OH 114,425.00 0.020 2,288.50
Jumlah 247,954.00
B. BAHAN
1. Batu Kali m 3
260,217.38 1.200 312,260.85
2. Semen Portland Zak 74,453.86 3.520 262,077.59
3. Pasir Pasang m 3
118,534.35 0.380 45,043.05
Jumlah 619,381.49
C. ALAT

Jumlah -
D. Jumlah A + B + C 867,335.49
E. Overhead & Profit 15% x D -
F. Harga Satuan (D + E) 867,335.49

M3 TURAP ABUTMENT

HARGA BIAYA
NO. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
(Rp.) (Rp.)

1 2 3 4 5 6
A. TENAGA
1. Pekerja OH 79,600.00 2.250 179,100.00
2. Tukang Batu OH 99,500.00 0.600 59,700.00
3. Kepala Tukang OH 114,425.00 0.060 6,865.50
4. Mandor OH 114,425.00 0.020 2,288.50
Jumlah 247,954.00
B. BAHAN
1. Batu Kali m 3
260,217.38 1.200 312,260.85
2. Semen Portland Zak 74,453.86 3.520 262,077.59
3. Pasir Pasang m 3
118,534.35 0.380 45,043.05
Jumlah 619,381.49
C. ALAT

Jumlah -
D. Jumlah A + B + C 867,335.49
E. Overhead & Profit 15% x D -
F. Harga Satuan (D + E) 867,335.49
DAFTAR UPAH TENAGA KERJA DAN HARGA SATUAN MATERIAL /
BAHAN
PEKERJAAN URUGAN JALAN ASR. KHATULISTIWA + SIRTU
TAHUN ANGGARAN 2017

HARGA
NO. TENAGA KERJA SATUAN SATUAN
(Rp.)

1. Pekerja Org/hari 79,600.00


2. Tukang Org/hari 99,500.00
3. Kepala Tukang Org/hari 114,425.00
4. Mandor Org/hari 114,425.00
5. Operator Org/Jam 12,437.50
6. Pembantu Operator Org/Jam 9,950.00

HARGA
NO. MATERIAL SATUAN SATUAN
(Rp.)

1 Batu Kali m³ 260,217.38


2 Pasir Urug m³ 118,534.35
3 Pasir Pasang m³ 118,534.35
4 Tanah Urug / Tanah Datang m³ 60,991.51
5 Semen Portland Zak 74,453.86
6 Semen Portland Kg 1,489.52
7 Kayu Bekesting m³ 2,717,096.25
8 Paku biasa 2"-5" Kg 29,634.09
9 Pasir Beton m³ 142,258.14
10 Papan Kayu Kelas III ( Tidak Ketam ) m³ 2,264,384.19
11 Kayu Cerucuk /Dolken ø 8-10 - Pj. 4 M Btg 14,283.23
12 Batu Split Pecah Mesin 1/2 m³ 391,147.44
13 Besi Tulangan Beton (Polos / Ulir) Kg 17,977.66
14 Kawat Beton (Bendrat) Kg 20,521.88
15 Minyak Bekisting Ltr 6,965.00
16 Minyak Pelumas Ltr 26,268.00
17 Sirtu ( Pasir Koral ) m³ 250,971.34
18 Kayu Bekesting m³ 2,717,096.25
ANALISA TEKNIS HARGA SATUAN PEKERJAAN

1. M2 PEMBERSIHAN LAPANGAN DAN PERATAAN TANAH = 3,741.00 M2

UPAH
1. Pekerja = 3,741.00 x 0.10 = 374.10
= 374.10 x 79,600.00 = Rp. 29,778,360.00
2. Mandor = 3,741.00 x 0.01 = 18.71
= 18.71 x 114,425.00 = Rp. 2,140,319.63

JUMLAH Rp. 31,918,679.63

2. M3 MENGURUG PASIR URUG TEBAL 10 CM = 374.10 M3

BAHAN
1. Pasir Urug = 374.10 x 1.20 = 448.92
= 448.92 x 118,534.35 = Rp. 53,212,440.40
UPAH
1. Pekerja = 374.10 x 0.30 = 112.23
= 112.23 x 79,600.00 = Rp. 8,933,508.00
2. Mandor = 374.10 x 0.01 = 3.74
= 3.74 x 114,425.00 = Rp. 428,063.93

JUMLAH Rp. 62,574,012.33

3. M3 URUGAN TANAH DATANG TEBAL 35 CM = 1,975.37 M3

BAHAN
1. Tanah Urug / Tanah Datang = 1,975.37 x 1.20 = 2,370.44
= 2,370.44 x 60,991.51 = Rp. 144,576,958.93
UPAH
1. Pekerja = 1,975.37 x 0.25 = 493.84
= 493.84 x 79,600.00 = Rp. 39,309,863.00
2. Mandor = 1,975.37 x 0.03 = 49.38
= 49.38 x 114,425.00 = Rp. 5,650,792.81
ALAT
1. VIBRATORY ROLLER 5-8 T = 1,975.37 x 0.0076 = 15.01
= 15.01 x 22,500.00 = Rp. 337,788.27
2. WATER TANKER 3000-4500 L = 1,975.37 x 0.0071 = 14.03
= 14.03 x 22,500.00 = Rp. 315,565.36

JUMLAH Rp. 190,190,968.36

4. 1 TTK PANCANG KAYU BULAT / MERAH / DOLKEN = 2,057.00 Bh

BAHAN
1. Kayu Cerucuk /Dolken ø 8-10 - Pj. 4 M = 2,057.00 x 1.00 = 2,057.00
= 2,057.00 x 14,283.23 = Rp. 29,380,593.83
UPAH
1. Pekerja = 2,057.00 x 0.10 = 205.70
= 205.70 x 79,600.00 = Rp. 16,373,720.00
2. Mandor = 2,057.00 x 0.01 = 20.57
= 20.57 x 114,425.00 = Rp. 2,353,722.25

JUMLAH Rp. 48,108,036.08

5. M3 JALAN COR BETON = 374.10 M3

BAHAN
1. Semen Portland = 374.10 x 7.68 = 2,873.09
= 2,873.09 x 74,453.86 = Rp. 213,912,491.72
2. Pasir Beton = 374.10 x 0.50 = 186.68
= 186.68 x 142,258.14 = Rp. 26,556,165.38
3. Batu Split Pecah Mesin 1/2 = 374.10 x 0.78 = 290.30
= 290.30 x 391,147.44 = Rp. 113,550,726.22
UPAH
1. Pekerja = 374.10 x 1.65 = 617.27
= 617.27 x 79,600.00 = Rp. 49,134,294.00
2. Tukang Batu = 374.10 x 0.28 = 102.88
= 102.88 x 99,500.00 = Rp. 10,236,311.25
3. Kepala Tukang = 374.10 x 0.03 = 10.47
= 10.47 x 114,425.00 = Rp. 1,198,578.99
4. Mandor = 374.10 x 0.08 = 31.05
= 31.05 x 114,425.00 = Rp. 3,552,930.58

JUMLAH Rp. 418,141,498.14

6. 1 M3 MEMBUAT BALOK BETON ( 150 Kg Besi + Bekesting ) = 3.20 M3

BAHAN
1. Kayu Bekesting = 3.20 x 0.21 = 0.67
= 0.67 x 2,717,096.25 = Rp. 1,825,888.68
2. Paku biasa 2"-5" = 3.20 x 3.20 = 10.24
= 10.24 x 29,634.09 = Rp. 303,453.03
3. Minyak Bekisting = 3.20 x 1.60 = 5.12
= 5.12 x 6,965.00 = Rp. 35,660.80
4. Besi Tulangan Beton (Polos / Ulir) = 3.20 x 150.00 = 480.00
= 480.00 x 17,977.66 = Rp. 8,629,276.80
5. Kawat Beton (Bendrat) = 3.20 x 2.25 = 7.20
= 7.20 x 20,521.88 = Rp. 147,757.50
6. Semen Portland = 3.20 x 323.00 = 1,033.60
= 1,033.60 x 1,489.52 = Rp. 1,539,562.70
7. Pasir Beton = 3.20 x 0.52 = 1.66
= 1.66 x 142,258.14 = Rp. 236,717.54
8. Batu Split Pecah Mesin 1/2 = 3.20 x 0.78 = 2.50
= 2.50 x 391,147.44 = Rp. 976,304.00
9. Papan Kayu Kelas III ( Tidak Ketam ) = 3.20 x 0.12 = 0.39
= 0.39 x 2,264,384.19 = Rp. 876,769.56
10 Kayu Cerucuk /Dolken ø 8-10 - Pj. 4 M = 3.20 x 16.00 = 51.20
= 51.20 x 14,283.23 = Rp. 731,301.12
UPAH
1. Pekerja = 3.20 x 5.80 = 18.56
= 18.56 x 79,600.00 = Rp. 1,477,376.00
ANALISA TEKNIS SATUAN PEKERJAAN (URUGAN JALAN ASRAMA KHATULISTIWA + SIRTU)

1. M2 PEMBERSIHAN LAPANGAN DAN PERATAAN TANAH = 3,741.00 M2

UPAH
1. Pekerja = 3,741.00 x 0.10 = 374.10
= 374.10 / 1.00 = 374.10 Hari
= 374.10 / 30.00 = 12.47 Hari
2. Mandor = 3,741.00 x 0.01 = 18.71
= 18.71 / 1.00 = 18.71 Hari
= 18.71 / 1.00 = 18.71 Hari

2. M3 MENGURUG PASIR URUG TEBAL 10 CM = 374.10 M3

UPAH
1. Pekerja = 374.10 x 0.300 = 112.23
= 112.23 / 1.00 = 112.23 Hari
= 112.23 / 18.00 = 6.24 Hari
2. Mandor = 374.10 x 0.010 = 3.74
= 3.74 / 1.00 = 3.74 Hari
= 3.74 / 1.00 = 3.74 Hari

3. M3 URUGAN TANAH DATANG TEBAL 35 CM = 1,975.37 M3

UPAH
1. Pekerja = 1,975.37 x 0.25 = 493.84
= 493.84 / 1.00 = 493.84 Hari
= 493.84 / 25.00 = 19.75 Hari
2. Mandor = 1,975.37 x 0.03 = 49.38
= 49.38 / 1.00 = 49.38 Hari
= 49.38 / 1.00 = 49.38 Hari
ALAT
1. VIBRATORY ROLLER 5-8 T = 1,975.37 x 0.01 = 15.01
= 15.01 / 1.00 = 15.01 Jam
= 15.01 / 1.00 = 15.01 Jam
2. WATER TANKER 3000-4500 L = 1,975.37 x 0.01 = 14.03
= 14.03 / 1.00 = 14.03 Jam
= 14.03 / 1.00 = 14.03 Jam

4. 1 TTK PANCANG KAYU BULAT / MERAH / DOLKEN = 2,057.00 Bh

UPAH
1. Pekerja = 2,057.00 x 0.25 = 514.25
= 514.25 / 1.00 = 514.25 Hari
= 514.25 / 18.00 = 28.57 Hari
2. Mandor = 2,057.00 x 0.03 = 51.43
= 51.43 / 1.00 = 51.43 Hari
= 51.43 / 1.00 = 51.43 Hari

5. M3 JALAN COR BETON = 374.10 M3

UPAH
1. Pekerja = 374.10 x 1.65 = 617.27
= 617.27 / 1.00 = 617.27 Hari
= 617.27 / 18.00 = 34.29 Hari
2. Tukang Batu = 374.10 x 0.28 = 102.88
= 102.88 / 1.00 = 102.88 Hari
= 102.88 / 18.00 = 5.72 Hari
3. Kepala Tukang = 374.10 x 0.03 = 10.47
= 10.47 / 1.00 = 10.47 Hari
= 10.47 / 1.00 = 10.47 Hari
4. Mandor = 374.10 x 0.08 = 31.05
= 31.05 / 1.00 = 31.05 Hari
= 31.05 / 1.00 = 31.05 Hari

6. 1 M3 MEMBUAT BALOK BETON ( 150 Kg Besi + Bekesting ) = 3.20 M3

UPAH
1. Pekerja = 3.20 x 5.80 = 18.56
= 18.56 / 1.00 = 18.56 Hari
= 18.56 / 30.00 = 0.62 Hari
2. Tukang Batu = 3.20 x 0.35 = 1.12
= 1.12 / 1.00 = 1.12 Hari
= 1.12 / 18.00 = 0.06 Hari
3. Tukang Kayu = 3.20 x 2.80 = 8.96
= 8.96 / 1.00 = 8.96 Hari
= 8.96 / 18.00 = 0.50 Hari
4. Tukang Besi = 3.20 x 1.05 = 3.36
= 3.36 / 1.00 = 3.36 Hari
= 3.36 / 18.00 = 0.19 Hari
5. Kepala Tukang = 3.20 x 0.42 = 1.34
= 1.34 / 1.00 = 1.34 Hari
= 1.34 / 1.00 = 1.34 Hari
6. Mandor = 3.20 x 0.19 = 0.61
= 0.61 / 1.00 = 0.61 Hari
= 0.61 / 1.00 = 0.61 Hari

7. M3 BUIS BETON DIA. 80 CM ( 6 Buah ) = 1.89 M3

UPAH
1. Pekerja = 1.89 x 1.65 = 3.12
= 3.12 / 1.00 = 3.12 Hari
= 3.12 / 18.00 = 0.17 Hari
2. Tukang Batu = 1.89 x 0.28 = 0.52
= 0.52 / 1.00 = 0.52 Hari
= 0.52 / 5.00 = 0.10 Hari
3. Kepala Tukang = 1.89 x 0.03 = 0.05
= 0.05 / 1.00 = 0.05 Hari
= 0.05 / 1.00 = 0.05 Hari
4. Mandor = 1.89 x 0.08 = 0.16
= 0.16 / 1.00 = 0.16 Hari
= 0.16 / 1.00 = 0.16 Hari
8. M3 LANTAI KERJA TURAP BATU KALI 10 CM = 75.64 M3

UPAH
1. Pekerja = 75.64 x 1.65 = 124.81
= 124.81 / 1.00 = 124.81 Hari
= 124.81 / 18.00 = 6.93 Hari
2. Tukang Batu = 75.64 x 0.28 = 20.80
= 20.80 / 1.00 = 20.80 Hari
= 20.80 / 12.00 = 1.73 Hari
3. Kepala Tukang = 75.64 x 0.03 = 2.12
= 2.12 / 1.00 = 2.12 Hari
= 2.12 / 1.00 = 2.12 Hari
4. Mandor = 75.64 x 0.08 = 6.28
= 6.28 / 1.00 = 6.28 Hari
= 6.28 / 1.00 = 6.28 Hari

9. M3 TURAP BATU KALI = 150.84 M3

UPAH
1. Pekerja = 150.84 x 2.25 = 339.39
= 339.39 / 1.00 = 339.39 Hari
= 339.39 / 30.00 = 11.31 Hari
2. Tukang Batu = 150.84 x 0.60 = 90.50
= 90.50 / 1.00 = 90.50 Hari
= 90.50 / 18.00 = 5.03 Hari
3. Kepala Tukang = 150.84 x 0.06 = 9.05
= 9.05 / 1.00 = 9.05 Hari
= 9.05 / 1.00 = 9.05 Hari
4. Mandor = 150.84 x 0.02 = 3.02
= 3.02 / 1.00 = 3.02 Hari
= 3.02 / 1.00 = 3.02 Hari

10. M3 TURAP ABUTMENT = 5.59 M3

UPAH
1. Pekerja = 5.59 x 2.25 = 12.58
= 12.58 / 1.00 = 12.58 Hari
= 12.58 / 18.00 = 0.70 Hari
2. Tukang Batu = 5.59 x 0.60 = 3.35
= 3.35 / 1.00 = 3.35 Hari
= 3.35 / 5.00 = 0.67 Hari
3. Kepala Tukang = 5.59 x 0.06 = 0.34
= 0.34 / 1.00 = 0.34 Hari
= 0.34 / 1.00 = 0.34 Hari
4. Mandor = 5.59 x 0.02 = 0.11
= 0.11 / 1.00 = 0.11 Hari
= 0.11 / 1.00 = 0.11 Hari
REKAPITULASI ANALISA TEKNIS HARGA SATUAN PEKERJAAN

KOEFISIEN DARI KEBUTUHAN DI ALOKASIKAN ALOKASI WAKTU PENYELESAIAN


NO. Uraian Pekerjaan / Pekerja dan Bahan VOL SAT HARGA SATUAN PEKERJAAN PEKERJAAN DALAM HARI DALAM MINGGU
BAHAN DAN ALAT BAHAN DAN ALAT HARI / MINGGU PEMBUATAN
1 2 3 4 5 6 7 8 1 1

1. M2 PEMBERSIHAN LAPANGAN DAN PERATAAN TANAH 3,741.00 M2


3.000
UPAH
1. Pekerja 0.100 374.10 OH 30.00 Orang 12.47 1.78
2. Mandor 0.005 18.71 OH 1.00 Orang 18.71 2.67

2. M3 MENGURUG PASIR URUG TEBAL 10 CM 374.10 M3


3.000
BAHAN
1. Pasir Urug 1.20 448.92 M3

UPAH
1. Pekerja 0.30 112.23 OH 18.00 Orang 6.24 0.89
2. Mandor 0.01 3.74 OH 1.00 Orang 3.74 0.53

3. M3 URUGAN TANAH DATANG TEBAL 35 CM 1,975.37 M3


3.000
BAHAN
1. Tanah Urug / Tanah Datang 1.20 2,370.44 M3

UPAH
1. Pekerja 0.25 493.84 OH 25.00 Orang 19.75 2.82
2. Mandor 0.03 49.38 OH 1.00 Orang 49.38 7.05

ALAT
1. VIBRATORY ROLLER 5-8 T 0.0076 15.01 JAM
2. WATER TANKER 3000-4500 L 0.0071 14.03 JAM

4. 1 TTK PANCANG KAYU BULAT / MERAH / DOLKEN 2,057.00 Bh


3.000
BAHAN
1. Kayu Cerucuk /Dolken ø 8-10 - Pj. 4 M 1.00 2,057.00 Btg

UPAH
1. Pekerja 0.25 514.25 OH 18.00 Orang 28.57 4.08
2. Mandor 0.03 51.43 OH 1.00 Orang 51.43 7.35

5. M3 JALAN COR BETON 374.10 M3


3.000
BAHAN
1. Semen Portland 7.68 2,873.09 Zak
2. Pasir Beton 0.50 186.68 M3
3. Batu Split Pecah Mesin 1/2 0.78 290.30 M3

UPAH
1. Pekerja 1.65 617.27 OH 18.00 Orang 34.29 4.90
2. Tukang Batu 0.28 102.88 OH 18.00 Orang 5.72 0.82
3. Kepala Tukang 0.03 10.47 OH 1.00 Orang 10.47 1.50
4. Mandor 0.08 31.05 OH 1.00 Orang 31.05 4.44

6. 1 M3 MEMBUAT BALOK BETON ( 150 Kg Besi + Bekesting ) 3.20 M3


3.000
BAHAN
1. Kayu Bekesting 0.21 0.67 M3
2. Paku biasa 2"-5" 3.20 10.24 Kg
3. Minyak Bekisting 1.60 5.12 Liter
4. Besi Tulangan Beton (Polos / Ulir) 150.00 480.00 Kg
5. Kawat Beton (Bendrat) 2.25 7.20 Kg
6. Semen Portland 323.00 1,033.60 Kg
7. Pasir Beton 0.52 1.66 M3
8. Batu Split Pecah Mesin 1/2 0.78 2.50 M3
9. Papan Kayu Kelas III ( Tidak Ketam ) 0.12 0.39 M3
10. Kayu Cerucuk /Dolken ø 8-10 - Pj. 4 M 16.00 51.20 Btg

UPAH
1. Pekerja 5.80 18.56 OH 30.00 Orang 0.62 0.09
2. Tukang Batu 0.35 1.12 OH 18.00 Orang 0.06 0.01
3. Tukang Kayu 2.80 8.96 OH 18.00 Orang 0.50 0.07
4. Tukang Besi 1.05 3.36 OH 18.00 Orang 0.19 0.03
5. Kepala Tukang 0.42 1.34 OH 1.00 Orang 1.34 0.19
6. Mandor 0.19 0.61 OH 1.00 Orang 0.61 0.09

7. 1 M3 PEKERJAAN PLAT LANTAI BETON TEBAL 12 CM 3.60 M3


3.000
BAHAN
1. Plat Lantai Beton Tebal 12 cm 8.333 30.00 M3

8. M3 BUIS BETON DIA. 80 CM ( 6 Buah ) 1.89 M3


3.000
BAHAN
1. Semen Portland 7.68 14.52 Zak
2. Pasir Beton 0.50 0.94 M3
3. Batu Split Pecah Mesin 1/2 0.78 1.47 M3

UPAH
1. Pekerja 1.65 3.12 OH 18.00 Orang 0.17 0.02
2. Tukang Batu 0.28 0.52 OH 5.00 Orang 0.10 0.01
3. Kepala Tukang 0.03 0.05 OH 1.00 Orang 0.05 0.01
4. Mandor 0.08 0.16 OH 1.00 Orang 0.16 0.02

9. M3 LANTAI KERJA TURAP BATU KALI 10 CM 75.64 M3


3.000
BAHAN
1. Semen Portland 6.52 493.17 Zak
2. Pasir Beton 0.54 41.07 M3
3. Batu Split Pecah Mesin 1/2 0.76 57.64 M3

UPAH
1. Pekerja 1.65 124.81 OH 18.00 Orang 6.93 0.99
2. Tukang Batu 0.28 20.80 OH 12.00 Orang 1.73 0.25
3. Kepala Tukang 0.03 2.12 OH 1.00 Orang 2.12 0.30
4. Mandor 0.08 6.28 OH 1.00 Orang 6.28 0.90
URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan VIBRATORY ROLLER 5-8 T E17
2. Tenaga Pw 75.0 HP
3. Kapasitas Cp 8.0 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 0 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 0 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.29832 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 0.00 Rupiah
W

b. Asuransi, dll = 0.002 x B F 0.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 0.00 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 0.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 0.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 0


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 0.00 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 12,500.00 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 10,000.00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 22,500.00 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 22,500.00 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir / Mekanik U1 12,500.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir / Pmb.Mekanik U2 10,000.00 Rp./Jam
4. Bahan Bakar Bensin Mb 0.00 Liter
5. Bahan Bakar Solar Ms 0.00 Liter
6. Minyak Pelumas Mp 0.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan WATER TANKER 3000-4500 L E23
2. Tenaga Pw 100.0 HP
3. Kapasitas Cp 4,000.00 Liter
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 0 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 0 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.29832 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 0.00 Rupiah
W

b. Asuransi, dll = 0.002 x B F 0.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 0.00 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 0.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 0.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 0 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 0.00 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 12,500.00 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 10,000.00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 22,500.00 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 22,500.00 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 12,500.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 10,000.00 Rp./Jam
4. Bahan Bakar Bensin Mb 0.00 Liter
5. Bahan Bakar Solar Ms 0.00 Liter
6. Minyak Pelumas Mp 0.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
LAPORAN KEMAJUAN FISIK MINGGUAN

PEKERJAAN : PEMBANGUNAN PRASARANA MAKODAM XII / TPR


LOKASI : KABUPATEN KUBU RAYA MINGGU KE : I (Satu)
TAHUN ANGGARAN : 2017 HARI : Awal Kontrak s/d Minggu
TANGGAL : 03 - 07 MEI 2017

RENCANA REALISASI
NO. URAIAN PEKERJAAN SATUAN VOLUME BOBOT S/D MINGGU LALU MINGGU INI S/D MINGGU PERSENTASE TERTIMBANG
(%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13

A. Urugan Jalan Asrama Khatulistiwa +


Sirtu
I. PEKERJAAN PERSIAPAN
1. Penyiapan Badan Jalan M2 3,741.00 1.25 - - 1,870.50 0.62 1,870.50 0.62 50.00 0.62
JUMLAH I 1.25 - 0.62 0.62 0.62

II. PEKERJAAN TANAH


1. Urugan Pasir Tebal 10 cm M3 374.10 2.45 - - 93.53 0.61 93.53 0.61 25.00 0.61
2. Urugan Tanah Datang Tebal 35 cm M3 1,975.37 7.45 - - 493.84 1.86 493.84 1.86 25.00 1.86
3. Pas. Cerucuk Bh 2,057.00 1.88 - - 685.67 0.63 685.67 0.63 33.33 0.63
JUMLAH II 11.78 - 3.10 3.10 3.10

III. PEKERJAAN BETON


1. Jalan Cor Beton M3 374.10 16.37 - - 74.82 3.27 74.82 3.27 20.00 3.27
2. Gelegar Jemabatan M3 3.20 0.72 - - - - - - - -
3. Plat Jembatan M3 3.60 0.77 - - - - - - -
4. Buis Beton Dia. 80 cm ( 6 Buah ) M3 1.89 0.08 - - - - - - -
5. Lantai Kerja Turap Batu Kali Tebal 10 cm M3 75.64 3.06 - - 18.91 0.76 18.91 0.76 25.00 0.76
JUMLAH III 21.00 - 4.04 4.04 4.04

IV. PEKERJAAN PASANGAN


1. Turap Batu Kali M3 150.84 5.12 - - 30.17 1.02 30.17 1.02 20.00 1.02
2. Turap Abutment M3 5.59 0.19 - - 1.40 0.05 1.40 0.05 25.00 0.05
JUMLAH IV 5.31 - 1.07 1.07 20.18 1.07

B. Lapangan Bola Makodam XII / TPR


I. URUGAN TANAH PILIHAN
DENGAN ALAT BERAT M3 2,425.82 42.21 - - - - - - - -
II. TANAM RUMPUT KLEKEP M2 5,698.00 8.37 - - - - - - - -
III. PARIT PASANGAN 60 x 60 x 40 cm M1 400.00 10.07 - - - - - - -
JUMLAH V 60.65 - - - - -
- 8.84 8.84 8.84

TOTAL BOBOT 100.00 - 8.84 8.84 8.84


LAPORAN KEMAJUAN FISIK MINGGUAN

PEKERJAAN : PEMBANGUNAN PRASARANA MAKODAM XII / TPR


LOKASI : KABUPATEN KUBU RAYA MINGGU KE : II (Dua)
TAHUN ANGGARAN : 2017 HARI : Senin s/d Minggu
TANGGAL : 08 - 14 MEI 2017

RENCANA REALISASI
NO. URAIAN PEKERJAAN SATUAN VOLUME BOBOT S/D MINGGU LALU MINGGU INI S/D MINGGU PERSENTASE TERTIMBANG
(%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13

A. Urugan Jalan Asrama Khatulistiwa +


Sirtu
I. PEKERJAAN PERSIAPAN
1. Penyiapan Badan Jalan M2 3,741.00 1.25 1,870.50 0.62 1,870.50 0.62 3,741.00 1.25 100.00 1.25
JUMLAH I 1.25 0.62 0.62 1.25 1.25

II. PEKERJAAN TANAH


1. Urugan Pasir Tebal 10 cm M3 374.10 2.45 93.53 0.61 93.53 0.61 187.05 1.23 50.00 1.23
2. Urugan Tanah Datang Tebal 35 cm M3 1,975.37 7.45 493.84 1.86 493.84 1.86 987.69 3.72 50.00 3.72
3. Pas. Cerucuk Bh 2,057.00 1.88 685.67 0.63 685.67 0.63 1,371.33 1.26 66.67 1.26
JUMLAH II 11.78 3.10 3.10 6.20 6.20

III. PEKERJAAN BETON


1. Jalan Cor Beton M3 374.10 16.37 74.82 3.27 74.82 3.27 149.64 6.55 40.00 6.55
2. Gelegar Jemabatan M3 3.20 0.72 - - 1.60 0.36 1.60 0.36 50.00 0.36
3. Plat Jembatan M3 3.60 0.77 - - 1.80 0.39 1.80 0.39 50.00 0.39
4. Buis Beton Dia. 80 cm ( 6 Buah ) M3 1.89 0.08 - - 1.89 0.08 1.89 0.08 100.00 0.08
5. Lantai Kerja Turap Batu Kali Tebal 10 cm M3 75.64 3.06 18.91 0.76 18.91 0.76 37.82 1.53 50.00 1.53
JUMLAH III 21.00 4.04 4.87 8.91 8.91

IV. PEKERJAAN PASANGAN


1. Turap Batu Kali M3 150.84 5.12 30.17 1.02 30.17 1.02 60.34 2.05 40.00 2.05
2. Turap Abutment M3 5.59 0.19 1.40 0.05 1.40 0.05 2.80 0.09 50.00 0.09
JUMLAH IV 5.31 1.07 1.07 2.14 40.36 2.14

B. Lapangan Bola Makodam XII / TPR


I. URUGAN TANAH PILIHAN
DENGAN ALAT BERAT M3 2,425.82 42.21 - - - - - - - -
II. TANAM RUMPUT KLEKEP M2 5,698.00 8.37 - - - - - - - -
III. PARIT PASANGAN 60 x 60 x 40 cm M1 400.00 10.07 - - - - - - -
JUMLAH V 60.65 - - - - -
8.84 9.67 18.50 18.50

TOTAL BOBOT 100.00 8.84 9.67 18.50 18.50


LAPORAN KEMAJUAN FISIK MINGGUAN

PEKERJAAN : PEMBANGUNAN PRASARANA MAKODAM XII / TPR


LOKASI : KABUPATEN KUBU RAYA MINGGU KE : III (Tiga)
TAHUN ANGGARAN : 2017 HARI : Senin s/d Minggu
TANGGAL : 15 - 21 MEI 2017

RENCANA REALISASI
NO. URAIAN PEKERJAAN SATUAN VOLUME BOBOT S/D MINGGU LALU MINGGU INI S/D MINGGU PERSENTASE TERTIMBANG
(%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13

A. Urugan Jalan Asrama Khatulistiwa +


Sirtu
I. PEKERJAAN PERSIAPAN
1. Penyiapan Badan Jalan M2 3,741.00 1.25 3,741.00 1.25 - 3,741.00 1.25 100.00 1.25
JUMLAH I 1.25 1.25 - 1.25 1.25

II. PEKERJAAN TANAH


1. Urugan Pasir Tebal 10 cm M3 374.10 2.45 187.05 1.23 93.53 0.61 280.58 1.84 75.00 1.84
2. Urugan Tanah Datang Tebal 35 cm M3 1,975.37 7.45 987.69 3.72 493.84 1.86 1,481.53 5.59 75.00 5.59
3. Pas. Cerucuk Bh 2,057.00 1.88 1,371.33 1.26 685.67 0.63 2,057.00 1.88 100.00 1.88
JUMLAH II 11.78 6.20 3.10 9.31 9.31

III. PEKERJAAN BETON


1. Jalan Cor Beton M3 374.10 16.37 149.64 6.55 74.82 3.27 224.46 9.82 60.00 9.82
2. Gelegar Jemabatan M3 3.20 0.72 1.60 0.36 1.60 0.36 3.20 0.72 100.00 0.72
3. Plat Jembatan M3 3.60 0.77 1.80 0.39 1.80 0.39 3.60 0.77 100.00 0.77
4. Buis Beton Dia. 80 cm ( 6 Buah ) M3 1.89 0.08 1.89 0.08 - 1.89 0.08 100.00 0.08
5. Lantai Kerja Turap Batu Kali Tebal 10 cm M3 75.64 3.06 37.82 1.53 18.91 0.76 56.73 2.29 75.00 2.29
JUMLAH III 21.00 8.91 4.78 13.69 13.69

IV. PEKERJAAN PASANGAN


1. Turap Batu Kali M3 150.84 5.12 60.34 2.05 30.17 1.02 90.50 3.07 60.00 3.07
2. Turap Abutment M3 5.59 0.19 2.80 0.09 1.40 0.05 4.19 0.14 75.00 0.14
JUMLAH IV 5.31 2.14 1.07 3.22 60.54 3.22

B. Lapangan Bola Makodam XII / TPR


I. URUGAN TANAH PILIHAN
DENGAN ALAT BERAT M3 2,425.82 42.21 - - - - - - - -
II. TANAM RUMPUT KLEKEP M2 5,698.00 8.37 - - - - - - - -
III. PARIT PASANGAN 60 x 60 x 40 cm M1 400.00 10.07 - - - - - - -
JUMLAH V 60.65 - - - - -
18.50 8.96 27.46 27.46

TOTAL BOBOT 100.00 18.50 8.96 27.46 27.46


LAPORAN KEMAJUAN FISIK MINGGUAN

PEKERJAAN : PEMBANGUNAN PRASARANA MAKODAM XII / TPR


LOKASI : KABUPATEN KUBU RAYA MINGGU KE : IV (Empat)
TAHUN ANGGARAN : 2017 HARI : Senin s/d Minggu
TANGGAL : 22 - 28 MEI 2017

RENCANA REALISASI
NO. URAIAN PEKERJAAN SATUAN VOLUME BOBOT S/D MINGGU LALU MINGGU INI S/D MINGGU PERSENTASE TERTIMBANG
(%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13

A. Urugan Jalan Asrama Khatulistiwa +


Sirtu
I. PEKERJAAN PERSIAPAN
1. Penyiapan Badan Jalan M2 3,741.00 1.25 3,741.00 1.25 - 3,741.00 1.25 100.00 1.25
JUMLAH I 1.25 1.25 - 1.25 1.25

II. PEKERJAAN TANAH


1. Urugan Pasir Tebal 10 cm M3 374.10 2.45 280.58 1.84 93.53 0.61 374.10 2.45 100.00 2.45
2. Urugan Tanah Datang Tebal 35 cm M3 1,975.37 7.45 1,481.53 5.59 493.84 1.86 1,975.37 7.45 100.00 7.45
3. Pas. Cerucuk Bh 2,057.00 1.88 2,057.00 1.88 - 2,057.00 1.88 100.00 1.88
JUMLAH II 11.78 9.31 2.47 11.78 11.78

III. PEKERJAAN BETON


1. Jalan Cor Beton M3 374.10 16.37 224.46 9.82 74.82 3.27 299.28 13.10 80.00 13.10
2. Gelegar Jemabatan M3 3.20 0.72 3.20 0.72 - 3.20 0.72 100.00 0.72
3. Plat Jembatan M3 3.60 0.77 3.60 0.77 - 3.60 0.77 100.00 0.77
4. Buis Beton Dia. 80 cm ( 6 Buah ) M3 1.89 0.08 1.89 0.08 - 1.89 0.08 100.00 0.08
5. Lantai Kerja Turap Batu Kali Tebal 10 cm M3 75.64 3.06 56.73 2.29 18.91 0.76 75.64 3.06 100.00 3.06
JUMLAH III 21.00 13.69 4.04 17.73 17.73

IV. PEKERJAAN PASANGAN


1. Turap Batu Kali M3 150.84 5.12 90.50 3.07 30.17 1.02 120.67 4.10 80.00 4.10
2. Turap Abutment M3 5.59 0.19 4.19 0.14 1.40 0.05 5.59 0.19 100.00 0.19
JUMLAH IV 5.31 3.22 1.07 4.29 80.71 4.29

B. Lapangan Bola Makodam XII / TPR


I. URUGAN TANAH PILIHAN
DENGAN ALAT BERAT M3 2,425.82 42.21 - - - - - - - -
II. TANAM RUMPUT KLEKEP M2 5,698.00 8.37 - - - - - - - -
III. PARIT PASANGAN 60 x 60 x 40 cm M1 400.00 10.07 - - 45.00 1.13 45.00 1.13 11.25 1.13
JUMLAH V 60.65 - 1.13 1.13 1.87 1.13
27.46 8.72 36.18 36.18

TOTAL BOBOT 100.00 27.46 8.72 36.18 36.18


LAPORAN KEMAJUAN FISIK MINGGUAN

PEKERJAAN : PEMBANGUNAN PRASARANA MAKODAM XII / TPR


LOKASI : KABUPATEN KUBU RAYA MINGGU KE : V (Lima)
TAHUN ANGGARAN : 2017 HARI : Senin s/d Minggu
TANGGAL : 29 MEI - 04 JUNI 2017

RENCANA REALISASI
NO. URAIAN PEKERJAAN SATUAN VOLUME BOBOT S/D MINGGU LALU MINGGU INI S/D MINGGU PERSENTASE TERTIMBANG
(%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13

A. Urugan Jalan Asrama Khatulistiwa +


Sirtu
I. PEKERJAAN PERSIAPAN
1. Penyiapan Badan Jalan M2 3,741.00 1.25 3,741.00 1.25 - 3,741.00 1.25 100.00 1.25
JUMLAH I 1.25 1.25 - 1.25 1.25

II. PEKERJAAN TANAH


1. Urugan Pasir Tebal 10 cm M3 374.10 2.45 374.10 2.45 - 374.10 2.45 100.00 2.45
2. Urugan Tanah Datang Tebal 35 cm M3 1,975.37 7.45 1,975.37 7.45 - 1,975.37 7.45 100.00 7.45
3. Pas. Cerucuk Bh 2,057.00 1.88 2,057.00 1.88 - 2,057.00 1.88 100.00 1.88
JUMLAH II 11.78 11.78 - 11.78 11.78

III. PEKERJAAN BETON


1. Jalan Cor Beton M3 374.10 16.37 299.28 13.10 74.82 3.27 374.10 16.37 100.00 16.37
2. Gelegar Jemabatan M3 3.20 0.72 3.20 0.72 - 3.20 0.72 100.00 0.72
3. Plat Jembatan M3 3.60 0.77 3.60 0.77 - 3.60 0.77 100.00 0.77
4. Buis Beton Dia. 80 cm ( 6 Buah ) M3 1.89 0.08 1.89 0.08 - 1.89 0.08 100.00 0.08
5. Lantai Kerja Turap Batu Kali Tebal 10 cm M3 75.64 3.06 75.64 3.06 - 75.64 3.06 100.00 3.06
JUMLAH III 21.00 17.73 3.27 21.00 21.00

IV. PEKERJAAN PASANGAN


1. Turap Batu Kali M3 150.84 5.12 120.67 4.10 30.17 1.02 150.84 5.12 100.00 5.12
2. Turap Abutment M3 5.59 0.19 5.59 0.19 - 5.59 0.19 100.00 0.19
JUMLAH IV 5.31 4.29 1.02 5.31 100.00 5.31

B. Lapangan Bola Makodam XII / TPR


I. URUGAN TANAH PILIHAN
DENGAN ALAT BERAT M3 2,425.82 42.21 - - - - - - - -
II. TANAM RUMPUT KLEKEP M2 5,698.00 8.37 - - - - - - - -
III. PARIT PASANGAN 60 x 60 x 40 cm M1 400.00 10.07 45.00 1.13 60.00 1.51 105.00 2.64 26.25 2.64
JUMLAH V 60.65 1.13 1.51 2.64 4.36 2.64
36.18 5.81 41.99 41.99

TOTAL BOBOT 100.00 36.18 5.81 41.99 41.99


LAPORAN KEMAJUAN FISIK MINGGUAN

PEKERJAAN : PEMBANGUNAN PRASARANA MAKODAM XII / TPR


LOKASI : KABUPATEN KUBU RAYA MINGGU KE : VI (Enam)
TAHUN ANGGARAN : 2017 HARI : Senin s/d Minggu
TANGGAL : 05 - 11 JUNI 2017

RENCANA REALISASI
NO. URAIAN PEKERJAAN SATUAN VOLUME BOBOT S/D MINGGU LALU MINGGU INI S/D MINGGU PERSENTASE TERTIMBANG
(%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13

A. Urugan Jalan Asrama Khatulistiwa +


Sirtu
I. PEKERJAAN PERSIAPAN
1. Penyiapan Badan Jalan M2 3,741.00 1.25 3,741.00 1.25 - 3,741.00 1.25 100.00 1.25
JUMLAH I 1.25 1.25 - 1.25 1.25

II. PEKERJAAN TANAH


1. Urugan Pasir Tebal 10 cm M3 374.10 2.45 374.10 2.45 - 374.10 2.45 100.00 2.45
2. Urugan Tanah Datang Tebal 35 cm M3 1,975.37 7.45 1,975.37 7.45 - 1,975.37 7.45 100.00 7.45
3. Pas. Cerucuk Bh 2,057.00 1.88 2,057.00 1.88 - 2,057.00 1.88 100.00 1.88
JUMLAH II 11.78 11.78 - 11.78 11.78

III. PEKERJAAN BETON


1. Jalan Cor Beton M3 374.10 16.37 374.10 16.37 - 374.10 16.37 100.00 16.37
2. Gelegar Jemabatan M3 3.20 0.72 3.20 0.72 - 3.20 0.72 100.00 0.72
3. Plat Jembatan M3 3.60 0.77 3.60 0.77 - 3.60 0.77 100.00 0.77
4. Buis Beton Dia. 80 cm ( 6 Buah ) M3 1.89 0.08 1.89 0.08 - 1.89 0.08 100.00 0.08
5. Lantai Kerja Turap Batu Kali Tebal 10 cm M3 75.64 3.06 75.64 3.06 - 75.64 3.06 100.00 3.06
JUMLAH III 21.00 21.00 - 21.00 21.00

IV. PEKERJAAN PASANGAN


1. Turap Batu Kali M3 150.84 5.12 150.84 5.12 - 150.84 5.12 100.00 5.12
2. Turap Abutment M3 5.59 0.19 5.59 0.19 - 5.59 0.19 100.00 0.19
JUMLAH IV 5.31 5.31 - 5.31 100.00 5.31

B. Lapangan Bola Makodam XII / TPR


I. URUGAN TANAH PILIHAN
DENGAN ALAT BERAT M3 2,425.82 42.21 - - - - - - - -
II. TANAM RUMPUT KLEKEP M2 5,698.00 8.37 - - - - - - - -
III. PARIT PASANGAN 60 x 60 x 40 cm M1 400.00 10.07 105.00 2.64 75.00 1.89 180.00 4.53 45.00 4.53
JUMLAH V 60.65 2.64 1.89 4.53 7.47 4.53
41.99 1.89 43.88 43.88

TOTAL BOBOT 100.00 41.99 1.89 43.88 43.88


LAPORAN KEMAJUAN FISIK MINGGUAN

PEKERJAAN : PEMBANGUNAN PRASARANA MAKODAM XII / TPR


LOKASI : KABUPATEN KUBU RAYA MINGGU KE : VII (Tujuh)
TAHUN ANGGARAN : 2017 HARI : Senin s/d Minggu
TANGGAL : 12 - 18 JUNI 2017

RENCANA REALISASI
NO. URAIAN PEKERJAAN SATUAN VOLUME BOBOT S/D MINGGU LALU MINGGU INI S/D MINGGU PERSENTASE TERTIMBANG
(%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13

A. Urugan Jalan Asrama Khatulistiwa +


Sirtu
I. PEKERJAAN PERSIAPAN
1. Penyiapan Badan Jalan M2 3,741.00 1.25 3,741.00 1.25 - 3,741.00 1.25 100.00 1.25
JUMLAH I 1.25 1.25 - 1.25 1.25

II. PEKERJAAN TANAH


1. Urugan Pasir Tebal 10 cm M3 374.10 2.45 374.10 2.45 - 374.10 2.45 100.00 2.45
2. Urugan Tanah Datang Tebal 35 cm M3 1,975.37 7.45 1,975.37 7.45 - 1,975.37 7.45 100.00 7.45
3. Pas. Cerucuk Bh 2,057.00 1.88 2,057.00 1.88 - 2,057.00 1.88 100.00 1.88
JUMLAH II 11.78 11.78 - 11.78 11.78

III. PEKERJAAN BETON


1. Jalan Cor Beton M3 374.10 16.37 374.10 16.37 - 374.10 16.37 100.00 16.37
2. Gelegar Jemabatan M3 3.20 0.72 3.20 0.72 - 3.20 0.72 100.00 0.72
3. Plat Jembatan M3 3.60 0.77 3.60 0.77 - 3.60 0.77 100.00 0.77
4. Buis Beton Dia. 80 cm ( 6 Buah ) M3 1.89 0.08 1.89 0.08 - 1.89 0.08 100.00 0.08
5. Lantai Kerja Turap Batu Kali Tebal 10 cm M3 75.64 3.06 75.64 3.06 - 75.64 3.06 100.00 3.06
JUMLAH III 21.00 21.00 - 21.00 21.00

IV. PEKERJAAN PASANGAN


1. Turap Batu Kali M3 150.84 5.12 150.84 5.12 - 150.84 5.12 100.00 5.12
2. Turap Abutment M3 5.59 0.19 5.59 0.19 - 5.59 0.19 100.00 0.19
JUMLAH IV 5.31 5.31 - 5.31 100.00 5.31

B. Lapangan Bola Makodam XII / TPR


I. URUGAN TANAH PILIHAN
DENGAN ALAT BERAT M3 2,425.82 42.21 - - - - - - -
II. TANAM RUMPUT KLEKEP M2 5,698.00 8.37 - - - - - - -
III. PARIT PASANGAN 60 x 60 x 40 cm M1 400.00 10.07 180.00 4.53 100.00 2.52 280.00 7.05 70.00 7.05
JUMLAH V 60.65 4.53 2.52 7.05 11.63 7.05
43.88 2.52 46.40 46.40

TOTAL BOBOT 100.00 43.88 2.52 46.40 46.40


LAPORAN KEMAJUAN FISIK MINGGUAN

PEKERJAAN : PEMBANGUNAN PRASARANA MAKODAM XII / TPR


LOKASI : KABUPATEN KUBU RAYA MINGGU KE : VIII (Delapan)
TAHUN ANGGARAN : 2017 HARI : Senin s/d Minggu
TANGGAL : 19 - 25 JUNI 2017

RENCANA REALISASI
NO. URAIAN PEKERJAAN SATUAN VOLUME BOBOT S/D MINGGU LALU MINGGU INI S/D MINGGU PERSENTASE TERTIMBANG
(%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13

A. Urugan Jalan Asrama Khatulistiwa +


Sirtu
I. PEKERJAAN PERSIAPAN
1. Penyiapan Badan Jalan M2 3,741.00 1.25 3,741.00 1.25 - 3,741.00 1.25 100.00 1.25
JUMLAH I 1.25 1.25 - 1.25 1.25

II. PEKERJAAN TANAH


1. Urugan Pasir Tebal 10 cm M3 374.10 2.45 374.10 2.45 - 374.10 2.45 100.00 2.45
2. Urugan Tanah Datang Tebal 35 cm M3 1,975.37 7.45 1,975.37 7.45 - 1,975.37 7.45 100.00 7.45
3. Pas. Cerucuk Bh 2,057.00 1.88 2,057.00 1.88 - 2,057.00 1.88 100.00 1.88
JUMLAH II 11.78 11.78 - 11.78 11.78

III. PEKERJAAN BETON


1. Jalan Cor Beton M3 374.10 16.37 374.10 16.37 - 374.10 16.37 100.00 16.37
2. Gelegar Jemabatan M3 3.20 0.72 3.20 0.72 - 3.20 0.72 100.00 0.72
3. Plat Jembatan M3 3.60 0.77 3.60 0.77 - 3.60 0.77 100.00 0.77
4. Buis Beton Dia. 80 cm ( 6 Buah ) M3 1.89 0.08 1.89 0.08 - 1.89 0.08 100.00 0.08
5. Lantai Kerja Turap Batu Kali Tebal 10 cm M3 75.64 3.06 75.64 3.06 - 75.64 3.06 100.00 3.06
JUMLAH III 21.00 21.00 - 21.00 21.00

IV. PEKERJAAN PASANGAN


1. Turap Batu Kali M3 150.84 5.12 150.84 5.12 - 150.84 5.12 100.00 5.12
2. Turap Abutment M3 5.59 0.19 5.59 0.19 - 5.59 0.19 100.00 0.19
JUMLAH IV 5.31 5.31 - 5.31 100.00 5.31

B. Lapangan Bola Makodam XII / TPR


I. URUGAN TANAH PILIHAN
DENGAN ALAT BERAT M3 2,425.82 42.21 - - - - - - -
II. TANAM RUMPUT KLEKEP M2 5,698.00 8.37 - - - - - - -
III. PARIT PASANGAN 60 x 60 x 40 cm M1 400.00 10.07 280.00 7.05 65.00 1.64 345.00 8.69 86.25 8.69
JUMLAH V 60.65 7.05 1.64 8.69 14.33 8.69
46.40 1.64 48.04 48.04

TOTAL BOBOT 100.00 46.40 1.64 48.04 48.04


LAPORAN KEMAJUAN FISIK MINGGUAN

PEKERJAAN : PEMBANGUNAN PRASARANA MAKODAM XII / TPR


LOKASI : KABUPATEN KUBU RAYA MINGGU KE : IX (Sembilan)
TAHUN ANGGARAN : 2017 HARI : Senin s/d Minggu
TANGGAL : 26 JUNI - 02 JULI 2017

RENCANA REALISASI
NO. URAIAN PEKERJAAN SATUAN VOLUME BOBOT S/D MINGGU LALU MINGGU INI S/D MINGGU PERSENTASE TERTIMBANG
(%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13

A. Urugan Jalan Asrama Khatulistiwa +


Sirtu
I. PEKERJAAN PERSIAPAN
1. Penyiapan Badan Jalan M2 3,741.00 1.25 3,741.00 1.25 - 3,741.00 1.25 100.00 1.25
JUMLAH I 1.25 1.25 - 1.25 1.25

II. PEKERJAAN TANAH


1. Urugan Pasir Tebal 10 cm M3 374.10 2.45 374.10 2.45 - 374.10 2.45 100.00 2.45
2. Urugan Tanah Datang Tebal 35 cm M3 1,975.37 7.45 1,975.37 7.45 - 1,975.37 7.45 100.00 7.45
3. Pas. Cerucuk Bh 2,057.00 1.88 2,057.00 1.88 - 2,057.00 1.88 100.00 1.88
JUMLAH II 11.78 11.78 - 11.78 11.78

III. PEKERJAAN BETON


1. Jalan Cor Beton M3 374.10 16.37 374.10 16.37 - 374.10 16.37 100.00 16.37
2. Gelegar Jemabatan M3 3.20 0.72 3.20 0.72 - 3.20 0.72 100.00 0.72
3. Plat Jembatan M3 3.60 0.77 3.60 0.77 - 3.60 0.77 100.00 0.77
4. Buis Beton Dia. 80 cm ( 6 Buah ) M3 1.89 0.08 1.89 0.08 - 1.89 0.08 100.00 0.08
5. Lantai Kerja Turap Batu Kali Tebal 10 cm M3 75.64 3.06 75.64 3.06 - 75.64 3.06 100.00 3.06
JUMLAH III 21.00 21.00 - 21.00 21.00

IV. PEKERJAAN PASANGAN


1. Turap Batu Kali M3 150.84 5.12 150.84 5.12 - 150.84 5.12 100.00 5.12
2. Turap Abutment M3 5.59 0.19 5.59 0.19 - 5.59 0.19 100.00 0.19
JUMLAH IV 5.31 5.31 - 5.31 100.00 5.31

B. Lapangan Bola Makodam XII / TPR


I. URUGAN TANAH PILIHAN
DENGAN ALAT BERAT M3 2,425.82 42.21 - - 400.00 6.96 400.00 6.96 16.49 6.96
II. TANAM RUMPUT KLEKEP M2 5,698.00 8.37 - - - - - - -
III. PARIT PASANGAN 60 x 60 x 40 cm M1 400.00 10.07 345.00 8.69 35.00 0.88 380.00 9.57 95.00 9.57
JUMLAH V 60.65 8.69 7.84 16.53 27.25 16.53
48.04 7.84 55.88 55.88

TOTAL BOBOT 100.00 48.04 7.84 55.88 55.88


LAPORAN KEMAJUAN FISIK MINGGUAN

PEKERJAAN : PEMBANGUNAN PRASARANA MAKODAM XII / TPR


LOKASI : KABUPATEN KUBU RAYA MINGGU KE : X (Sepuluh)
TAHUN ANGGARAN : 2017 HARI : Senin s/d Minggu
TANGGAL : 03 - 09 JULI 2017

RENCANA REALISASI
NO. URAIAN PEKERJAAN SATUAN VOLUME BOBOT S/D MINGGU LALU MINGGU INI S/D MINGGU PERSENTASE TERTIMBANG
(%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13

A. Urugan Jalan Asrama Khatulistiwa +


Sirtu
I. PEKERJAAN PERSIAPAN
1. Penyiapan Badan Jalan M2 3,741.00 1.25 3,741.00 1.25 - 3,741.00 1.25 100.00 1.25
JUMLAH I 1.25 1.25 - 1.25 1.25

II. PEKERJAAN TANAH


1. Urugan Pasir Tebal 10 cm M3 374.10 2.45 374.10 2.45 - 374.10 2.45 100.00 2.45
2. Urugan Tanah Datang Tebal 35 cm M3 1,975.37 7.45 1,975.37 7.45 - 1,975.37 7.45 100.00 7.45
3. Pas. Cerucuk Bh 2,057.00 1.88 2,057.00 1.88 - 2,057.00 1.88 100.00 1.88
JUMLAH II 11.78 11.78 - 11.78 11.78

III. PEKERJAAN BETON


1. Jalan Cor Beton M3 374.10 16.37 374.10 16.37 - 374.10 16.37 100.00 16.37
2. Gelegar Jemabatan M3 3.20 0.72 3.20 0.72 - 3.20 0.72 100.00 0.72
3. Plat Jembatan M3 3.60 0.77 3.60 0.77 - 3.60 0.77 100.00 0.77
4. Buis Beton Dia. 80 cm ( 6 Buah ) M3 1.89 0.08 1.89 0.08 - 1.89 0.08 100.00 0.08
5. Lantai Kerja Turap Batu Kali Tebal 10 cm M3 75.64 3.06 75.64 3.06 - 75.64 3.06 100.00 3.06
JUMLAH III 21.00 21.00 - 21.00 21.00

IV. PEKERJAAN PASANGAN


1. Turap Batu Kali M3 150.84 5.12 150.84 5.12 - 150.84 5.12 100.00 5.12
2. Turap Abutment M3 5.59 0.19 5.59 0.19 - 5.59 0.19 100.00 0.19
JUMLAH IV 5.31 5.31 - 5.31 100.00 5.31

B. Lapangan Bola Makodam XII / TPR


I. URUGAN TANAH PILIHAN
DENGAN ALAT BERAT M3 2,425.82 42.21 400.00 6.96 500.00 8.70 900.00 15.66 37.10 15.66
II. TANAM RUMPUT KLEKEP M2 5,698.00 8.37 - - - - - - -
III. PARIT PASANGAN 60 x 60 x 40 cm M1 400.00 10.07 380.00 9.57 - 380.00 9.57 95.00 9.57
JUMLAH V 60.65 16.53 8.70 25.23 41.60 25.23
55.88 8.70 64.58 64.58

TOTAL BOBOT 100.00 55.88 8.70 64.58 64.58


LAPORAN KEMAJUAN FISIK MINGGUAN

PEKERJAAN : PEMBANGUNAN PRASARANA MAKODAM XII / TPR


LOKASI : KABUPATEN KUBU RAYA MINGGU KE : XI (Sebelas)
TAHUN ANGGARAN : 2017 HARI : Senin s/d Minggu
TANGGAL : 10 - 16 JULI 2017

RENCANA REALISASI
NO. URAIAN PEKERJAAN SATUAN VOLUME BOBOT S/D MINGGU LALU MINGGU INI S/D MINGGU PERSENTASE TERTIMBANG
(%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13

A. Urugan Jalan Asrama Khatulistiwa +


Sirtu
I. PEKERJAAN PERSIAPAN
1. Penyiapan Badan Jalan M2 3,741.00 1.25 3,741.00 1.25 - 3,741.00 1.25 100.00 1.25
JUMLAH I 1.25 1.25 - 1.25 1.25

II. PEKERJAAN TANAH


1. Urugan Pasir Tebal 10 cm M3 374.10 2.45 374.10 2.45 - 374.10 2.45 100.00 2.45
2. Urugan Tanah Datang Tebal 35 cm M3 1,975.37 7.45 1,975.37 7.45 - 1,975.37 7.45 100.00 7.45
3. Pas. Cerucuk Bh 2,057.00 1.88 2,057.00 1.88 - 2,057.00 1.88 100.00 1.88
JUMLAH II 11.78 11.78 - 11.78 11.78

III. PEKERJAAN BETON


1. Jalan Cor Beton M3 374.10 16.37 374.10 16.37 - 374.10 16.37 100.00 16.37
2. Gelegar Jemabatan M3 3.20 0.72 3.20 0.72 - 3.20 0.72 100.00 0.72
3. Plat Jembatan M3 3.60 0.77 3.60 0.77 - 3.60 0.77 100.00 0.77
4. Buis Beton Dia. 80 cm ( 6 Buah ) M3 1.89 0.08 1.89 0.08 - 1.89 0.08 100.00 0.08
5. Lantai Kerja Turap Batu Kali Tebal 10 cm M3 75.64 3.06 75.64 3.06 - 75.64 3.06 100.00 3.06
JUMLAH III 21.00 21.00 - 21.00 21.00

IV. PEKERJAAN PASANGAN


1. Turap Batu Kali M3 150.84 5.12 150.84 5.12 - 150.84 5.12 100.00 5.12
2. Turap Abutment M3 5.59 0.19 5.59 0.19 - 5.59 0.19 100.00 0.19
JUMLAH IV 5.31 5.31 - 5.31 100.00 5.31

B. Lapangan Bola Makodam XII / TPR


I. URUGAN TANAH PILIHAN
DENGAN ALAT BERAT M3 2,425.82 42.21 900.00 15.66 400.00 6.96 1,300.00 22.62 53.59 22.62
II. TANAM RUMPUT KLEKEP M2 5,698.00 8.37 - - - - - - -
III. PARIT PASANGAN 60 x 60 x 40 cm M1 400.00 10.07 380.00 9.57 - 380.00 9.57 95.00 9.57
JUMLAH V 60.65 25.23 6.96 32.19 53.08 32.19
64.58 6.96 71.54 71.54

TOTAL BOBOT 100.00 64.58 6.96 71.54 71.54


LAPORAN KEMAJUAN FISIK MINGGUAN

PEKERJAAN : PEMBANGUNAN PRASARANA MAKODAM XII / TPR


LOKASI : KABUPATEN KUBU RAYA MINGGU KE : XII (Dua Belas)
TAHUN ANGGARAN : 2017 HARI : Senin s/d Minggu
TANGGAL : 17 - 23 JULI 2017

RENCANA REALISASI
NO. URAIAN PEKERJAAN SATUAN VOLUME BOBOT S/D MINGGU LALU MINGGU INI S/D MINGGU PERSENTASE TERTIMBANG
(%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13

A. Urugan Jalan Asrama Khatulistiwa +


Sirtu
I. PEKERJAAN PERSIAPAN
1. Penyiapan Badan Jalan M2 3,741.00 1.25 3,741.00 1.25 - 3,741.00 1.25 100.00 1.25
JUMLAH I 1.25 1.25 - 1.25 1.25

II. PEKERJAAN TANAH


1. Urugan Pasir Tebal 10 cm M3 374.10 2.45 374.10 2.45 - 374.10 2.45 100.00 2.45
2. Urugan Tanah Datang Tebal 35 cm M3 1,975.37 7.45 1,975.37 7.45 - 1,975.37 7.45 100.00 7.45
3. Pas. Cerucuk Bh 2,057.00 1.88 2,057.00 1.88 - 2,057.00 1.88 100.00 1.88
JUMLAH II 11.78 11.78 - 11.78 11.78

III. PEKERJAAN BETON


1. Jalan Cor Beton M3 374.10 16.37 374.10 16.37 - 374.10 16.37 100.00 16.37
2. Gelegar Jemabatan M3 3.20 0.72 3.20 0.72 - 3.20 0.72 100.00 0.72
3. Plat Jembatan M3 3.60 0.77 3.60 0.77 - 3.60 0.77 100.00 0.77
4. Buis Beton Dia. 80 cm ( 6 Buah ) M3 1.89 0.08 1.89 0.08 - 1.89 0.08 100.00 0.08
5. Lantai Kerja Turap Batu Kali Tebal 10 cm M3 75.64 3.06 75.64 3.06 - 75.64 3.06 100.00 3.06
JUMLAH III 21.00 21.00 - 21.00 21.00

IV. PEKERJAAN PASANGAN


1. Turap Batu Kali M3 150.84 5.12 150.84 5.12 - 150.84 5.12 100.00 5.12
2. Turap Abutment M3 5.59 0.19 5.59 0.19 - 5.59 0.19 100.00 0.19
JUMLAH IV 5.31 5.31 - 5.31 100.00 5.31

B. Lapangan Bola Makodam XII / TPR


I. URUGAN TANAH PILIHAN
DENGAN ALAT BERAT M3 2,425.82 42.21 1,300.00 22.62 350.00 6.09 1,650.00 28.71 68.02 28.71
II. TANAM RUMPUT KLEKEP M2 5,698.00 8.37 - - - - - - -
III. PARIT PASANGAN 60 x 60 x 40 cm M1 400.00 10.07 380.00 9.57 - 380.00 9.57 95.00 9.57
JUMLAH V 60.65 32.19 6.09 38.28 63.12 38.28
71.54 6.09 77.63 77.63

TOTAL BOBOT 100.00 71.54 6.09 77.63 77.63


LAPORAN KEMAJUAN FISIK MINGGUAN

PEKERJAAN : PEMBANGUNAN PRASARANA MAKODAM XII / TPR


LOKASI : KABUPATEN KUBU RAYA MINGGU KE : XIII (Tiga Belas)
TAHUN ANGGARAN : 2017 HARI : Senin s/d Minggu
TANGGAL : 24 - 30 JULI 2017

RENCANA REALISASI
NO. URAIAN PEKERJAAN SATUAN VOLUME BOBOT S/D MINGGU LALU MINGGU INI S/D MINGGU PERSENTASE TERTIMBANG
(%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13

A. Urugan Jalan Asrama Khatulistiwa +


Sirtu
I. PEKERJAAN PERSIAPAN
1. Penyiapan Badan Jalan M2 3,741.00 1.25 3,741.00 1.25 - 3,741.00 1.25 100.00 1.25
JUMLAH I 1.25 1.25 - 1.25 1.25

II. PEKERJAAN TANAH


1. Urugan Pasir Tebal 10 cm M3 374.10 2.45 374.10 2.45 - 374.10 2.45 100.00 2.45
2. Urugan Tanah Datang Tebal 35 cm M3 1,975.37 7.45 1,975.37 7.45 - 1,975.37 7.45 100.00 7.45
3. Pas. Cerucuk Bh 2,057.00 1.88 2,057.00 1.88 - 2,057.00 1.88 100.00 1.88
JUMLAH II 11.78 11.78 - 11.78 11.78

III. PEKERJAAN BETON


1. Jalan Cor Beton M3 374.10 16.37 374.10 16.37 - 374.10 16.37 100.00 16.37
2. Gelegar Jemabatan M3 3.20 0.72 3.20 0.72 - 3.20 0.72 100.00 0.72
3. Plat Jembatan M3 3.60 0.77 3.60 0.77 - 3.60 0.77 100.00 0.77
4. Buis Beton Dia. 80 cm ( 6 Buah ) M3 1.89 0.08 1.89 0.08 - 1.89 0.08 100.00 0.08
5. Lantai Kerja Turap Batu Kali Tebal 10 cm M3 75.64 3.06 75.64 3.06 - 75.64 3.06 100.00 3.06
JUMLAH III 21.00 21.00 - 21.00 21.00

IV. PEKERJAAN PASANGAN


1. Turap Batu Kali M3 150.84 5.12 150.84 5.12 - 150.84 5.12 100.00 5.12
2. Turap Abutment M3 5.59 0.19 5.59 0.19 - 5.59 0.19 100.00 0.19
JUMLAH IV 5.31 5.31 - 5.31 100.00 5.31

B. Lapangan Bola Makodam XII / TPR


I. URUGAN TANAH PILIHAN
DENGAN ALAT BERAT M3 2,425.82 42.21 1,650.00 28.71 300.00 5.22 1,950.00 33.93 80.39 33.93
II. TANAM RUMPUT KLEKEP M2 5,698.00 8.37 - - - - - - -
III. PARIT PASANGAN 60 x 60 x 40 cm M1 400.00 10.07 380.00 9.57 - 380.00 9.57 95.00 9.57
JUMLAH V 60.65 38.28 5.22 43.50 71.72 43.50
77.63 5.22 82.85 82.85

TOTAL BOBOT 100.00 77.63 5.22 82.85 82.85


LAPORAN KEMAJUAN FISIK MINGGUAN

PEKERJAAN : PEMBANGUNAN PRASARANA MAKODAM XII / TPR


LOKASI : KABUPATEN KUBU RAYA MINGGU KE : XIV (Empat Belas)
TAHUN ANGGARAN : 2017 HARI : Senin s/d Minggu
TANGGAL : 31 JULI - 06 AGUSTUS 2017

RENCANA REALISASI
NO. URAIAN PEKERJAAN SATUAN VOLUME BOBOT S/D MINGGU LALU MINGGU INI S/D MINGGU PERSENTASE TERTIMBANG
(%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13

A. Urugan Jalan Asrama Khatulistiwa +


Sirtu
I. PEKERJAAN PERSIAPAN
1. Penyiapan Badan Jalan M2 3,741.00 1.25 3,741.00 1.25 - 3,741.00 1.25 100.00 1.25
JUMLAH I 1.25 1.25 - 1.25 1.25

II. PEKERJAAN TANAH


1. Urugan Pasir Tebal 10 cm M3 374.10 2.45 374.10 2.45 - 374.10 2.45 100.00 2.45
2. Urugan Tanah Datang Tebal 35 cm M3 1,975.37 7.45 1,975.37 7.45 - 1,975.37 7.45 100.00 7.45
3. Pas. Cerucuk Bh 2,057.00 1.88 2,057.00 1.88 - 2,057.00 1.88 100.00 1.88
JUMLAH II 11.78 11.78 - 11.78 11.78

III. PEKERJAAN BETON


1. Jalan Cor Beton M3 374.10 16.37 374.10 16.37 - 374.10 16.37 100.00 16.37
2. Gelegar Jemabatan M3 3.20 0.72 3.20 0.72 - 3.20 0.72 100.00 0.72
3. Plat Jembatan M3 3.60 0.77 3.60 0.77 - 3.60 0.77 100.00 0.77
4. Buis Beton Dia. 80 cm ( 6 Buah ) M3 1.89 0.08 1.89 0.08 - 1.89 0.08 100.00 0.08
5. Lantai Kerja Turap Batu Kali Tebal 10 cm M3 75.64 3.06 75.64 3.06 - 75.64 3.06 100.00 3.06
JUMLAH III 21.00 21.00 - 21.00 21.00

IV. PEKERJAAN PASANGAN


1. Turap Batu Kali M3 150.84 5.12 150.84 5.12 - 150.84 5.12 100.00 5.12
2. Turap Abutment M3 5.59 0.19 5.59 0.19 - 5.59 0.19 100.00 0.19
JUMLAH IV 5.31 5.31 - 5.31 100.00 5.31

B. Lapangan Bola Makodam XII / TPR


I. URUGAN TANAH PILIHAN
DENGAN ALAT BERAT M3 2,425.82 42.21 1,950.00 33.93 250.00 4.35 2,200.00 38.28 90.69 38.28
II. TANAM RUMPUT KLEKEP M2 5,698.00 8.37 - - - - - - -
III. PARIT PASANGAN 60 x 60 x 40 cm M1 400.00 10.07 380.00 9.57 - 380.00 9.57 95.00 9.57
JUMLAH V 60.65 43.50 4.35 47.85 78.90 47.85
82.85 4.35 87.20 87.20

TOTAL BOBOT 100.00 82.85 4.35 87.20 87.20


LAPORAN KEMAJUAN FISIK MINGGUAN

PEKERJAAN : PEMBANGUNAN PRASARANA MAKODAM XII / TPR


LOKASI : KABUPATEN KUBU RAYA MINGGU KE : XV (Lima Belas)
TAHUN ANGGARAN : 2017 HARI : Senin s/d Minggu
TANGGAL : 07 - 13 AGUSTUS 2017

RENCANA REALISASI
NO. URAIAN PEKERJAAN SATUAN VOLUME BOBOT S/D MINGGU LALU MINGGU INI S/D MINGGU PERSENTASE TERTIMBANG
(%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13

A. Urugan Jalan Asrama Khatulistiwa +


Sirtu
I. PEKERJAAN PERSIAPAN
1. Penyiapan Badan Jalan M2 3,741.00 1.25 3,741.00 1.25 - 3,741.00 1.25 100.00 1.25
JUMLAH I 1.25 1.25 - 1.25 1.25

II. PEKERJAAN TANAH


1. Urugan Pasir Tebal 10 cm M3 374.10 2.45 374.10 2.45 - 374.10 2.45 100.00 2.45
2. Urugan Tanah Datang Tebal 35 cm M3 1,975.37 7.45 1,975.37 7.45 - 1,975.37 7.45 100.00 7.45
3. Pas. Cerucuk Bh 2,057.00 1.88 2,057.00 1.88 - 2,057.00 1.88 100.00 1.88
JUMLAH II 11.78 11.78 - 11.78 11.78

III. PEKERJAAN BETON


1. Jalan Cor Beton M3 374.10 16.37 374.10 16.37 - 374.10 16.37 100.00 16.37
2. Gelegar Jemabatan M3 3.20 0.72 3.20 0.72 - 3.20 0.72 100.00 0.72
3. Plat Jembatan M3 3.60 0.77 3.60 0.77 - 3.60 0.77 100.00 0.77
4. Buis Beton Dia. 80 cm ( 6 Buah ) M3 1.89 0.08 1.89 0.08 - 1.89 0.08 100.00 0.08
5. Lantai Kerja Turap Batu Kali Tebal 10 cm M3 75.64 3.06 75.64 3.06 - 75.64 3.06 100.00 3.06
JUMLAH III 21.00 21.00 - 21.00 21.00

IV. PEKERJAAN PASANGAN


1. Turap Batu Kali M3 150.84 5.12 150.84 5.12 - 150.84 5.12 100.00 5.12
2. Turap Abutment M3 5.59 0.19 5.59 0.19 - 5.59 0.19 100.00 0.19
JUMLAH IV 5.31 5.31 - 5.31 100.00 5.31

B. Lapangan Bola Makodam XII / TPR


I. URUGAN TANAH PILIHAN
DENGAN ALAT BERAT M3 2,425.82 42.21 2,200.00 38.28 225.82 3.93 2,425.82 42.21 100.00 42.21
II. TANAM RUMPUT KLEKEP M2 5,698.00 8.37 - - - - - - -
III. PARIT PASANGAN 60 x 60 x 40 cm M1 400.00 10.07 380.00 9.57 - 380.00 9.57 95.00 9.57
JUMLAH V 60.65 47.85 3.93 51.78 85.37 51.78
87.20 3.93 91.13 91.13

TOTAL BOBOT 100.00 87.20 3.93 91.13 91.13


REKAPITULASI PERHITUNGAN KOMPONEN DALAM NEGERI ( TKDN )

NILAI GABUNGAN BARANG/JASA (Rp) TKDN

TOTAL
URAIAN PEKERJAAN
BARANG /
DN LN Ribu % GABUNGAN
JASA
Rp. KDN

1 2 3 4 5 6 7

BARANG

I. Material Langsung 780,034,735.29 0.00 780,034.74 100 100% 77.62%

1. Pasir
2. Batu Pecah
3. Semen PC
4. Tanah
5. Besi Tulangan
6. Kawat Ikat
7. Papan Mal
8. Paku
9. Kusen Alumunium

II. Peralatan 653,353.63 0.00 653.35 0 0.08% 0.07%


1. Molen
2. Viberator
3. Pompa Air
4. Alat Bantu

A. Sub Total Barang 780,688,088.92 0.00 780,688.09 100 100% 77.69%

JASA
I. Manajemen Proyek dan Perekayasaan 0.00 0.00 0.00 0.00 0.00 0.00

II. Alat Kerja / Fasilitas Kerja 0.00 0.00 0.00 0.00 0.00 0.00

III. Konstruksi dan Fabrikasi 0.00 0.00 0.00 0.00 0.00 0.00

IV. Jasa Umum 224,204,849.17 0.00 224,204.85 100 100% 22.31%


1. Upah
2. Mobilisasi

B. Sub Total Jasa 224,204,849.17 0.00 224,204.85 100 100% 22.31%

C. Sub Total Biaya ( A + B ) 1,004,892,938.08 0.00 1,004,892.94 100 100%

Pontianak, 09 April 2017


PT. MITRA ANTARA BENUA

HERIANTO GANI
Direktur
REKAPITULASI PERHITUNGAN KOMPONEN DALAM NEGERI ( TKDN )

NILAI GABUNGAN BARANG/JASA (Rp) TKDN

TOTAL
URAIAN PEKERJAAN
BARANG /
DN LN Ribu % GABUNGAN
JASA
Rp. KDN

1 2 3 4 5 6 7

BARANG

I. Material Langsung 2,158,602,613.36 0.00 2,158,602.61 100 99% 84.52%

1. Pasir
2. Batu Pecah
3. Semen PC
4. Tanah
5. Besi Tulangan
6. Kawat Ikat
7. Papan Mal
8. Paku
9. Kusen Alumunium

II. Peralatan 26,234,173.64 0.00 26,234.17 0 1.20% 1.03%


1. Molen
2. Viberator
3. Pompa Air
4. Alat Bantu

A. Sub Total Barang 2,184,836,787.00 0.00 2,184,836.79 100 100% 85.55%

JASA
I. Manajemen Proyek dan Perekayasaan 0.00 0.00 0.00 0.00 0.00 0.00

II. Alat Kerja / Fasilitas Kerja - 0.00 0.00 0.00 0.00 0.00

III. Konstruksi dan Fabrikasi 0.00 0.00 0.00 0.00 0.00 0.00

IV. Jasa Umum 368,992,982.88 0.00 368,992.98 100 100% 14.45%


1. Upah
2. Mobilisasi

B. Sub Total Jasa 368,992,982.88 0.00 368,992.98 100 100% 14.45%

C. Sub Total Biaya ( A + B ) 2,553,829,769.88 0.00 2,553,829.77 100 100%

Pontianak, 09 April 2017


PT. MITRA ANTARA BENUA

HERIANTO GANI
Direktur
LAPORAN KEMAJUAN FISIK MINGGUAN

PEKERJAAN : PEMBANGUNAN PRASARANA MAKODAM XII / TPR


LOKASI : KABUPATEN KUBU RAYA MINGGU KE : XVI (Enam Belas)
TAHUN ANGGARAN : 2017 HARI : Senin s/d Minggu
TANGGAL : 14 - 20 AGUSTUS 2017

RENCANA REALISASI
NO. URAIAN PEKERJAAN SATUAN VOLUME BOBOT S/D MINGGU LALU MINGGU INI S/D MINGGU PERSENTASE TERTIMBANG
(%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13

A. Urugan Jalan Asrama Khatulistiwa +


Sirtu
I. PEKERJAAN PERSIAPAN
1. Penyiapan Badan Jalan M2 3,741.00 1.25 3,741.00 1.25 - 3,741.00 1.25 100.00 1.25
JUMLAH I 1.25 1.25 - 1.25 1.25

II. PEKERJAAN TANAH


1. Urugan Pasir Tebal 10 cm M3 374.10 2.45 374.10 2.45 - 374.10 2.45 100.00 2.45
2. Urugan Tanah Datang Tebal 35 cm M3 1,975.37 7.45 1,975.37 7.45 - 1,975.37 7.45 100.00 7.45
3. Pas. Cerucuk Bh 2,057.00 1.88 2,057.00 1.88 - 2,057.00 1.88 100.00 1.88
JUMLAH II 11.78 11.78 - 11.78 11.78

III. PEKERJAAN BETON


1. Jalan Cor Beton M3 374.10 16.37 374.10 16.37 - 374.10 16.37 100.00 16.37
2. Gelegar Jemabatan M3 3.20 0.72 3.20 0.72 - 3.20 0.72 100.00 0.72
3. Plat Jembatan M3 3.60 0.77 3.60 0.77 - 3.60 0.77 100.00 0.77
4. Buis Beton Dia. 80 cm ( 6 Buah ) M3 1.89 0.08 1.89 0.08 - 1.89 0.08 100.00 0.08
5. Lantai Kerja Turap Batu Kali Tebal 10 cm M3 75.64 3.06 75.64 3.06 - 75.64 3.06 100.00 3.06
JUMLAH III 21.00 21.00 - 21.00 21.00

IV. PEKERJAAN PASANGAN


1. Turap Batu Kali M3 150.84 5.12 150.84 5.12 - 150.84 5.12 100.00 5.12
2. Turap Abutment M3 5.59 0.19 5.59 0.19 - 5.59 0.19 100.00 0.19
JUMLAH IV 5.31 5.31 - 5.31 100.00 5.31

B. Lapangan Bola Makodam XII / TPR


I. URUGAN TANAH PILIHAN
DENGAN ALAT BERAT M3 2,425.82 42.21 2,425.82 42.21 - - 2,425.82 42.21 100.00 42.21
II. TANAM RUMPUT KLEKEP M2 5,698.00 8.37 - - - - - - -
III. PARIT PASANGAN 60 x 60 x 40 cm M1 400.00 10.07 380.00 9.57 10.00 0.25 390.00 9.82 97.50 9.82
JUMLAH V 60.65 51.78 0.25 52.03 85.79 52.03
91.13 0.25 91.38 91.38

TOTAL BOBOT 100.00 91.13 0.25 91.38 91.38


LAPORAN KEMAJUAN FISIK MINGGUAN

PEKERJAAN : PEMBANGUNAN PRASARANA MAKODAM XII / TPR


LOKASI : KABUPATEN KUBU RAYA MINGGU KE : XVII (Tujuh Belas)
TAHUN ANGGARAN : 2017 HARI : Senin s/d Minggu
TANGGAL : 21 - 27 AGUSTUS 2017

RENCANA REALISASI
NO. URAIAN PEKERJAAN SATUAN VOLUME BOBOT S/D MINGGU LALU MINGGU INI S/D MINGGU PERSENTASE TERTIMBANG
(%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13

A. Urugan Jalan Asrama Khatulistiwa +


Sirtu
I. PEKERJAAN PERSIAPAN
1. Penyiapan Badan Jalan M2 3,741.00 1.25 3,741.00 1.25 - 3,741.00 1.25 100.00 1.25
JUMLAH I 1.25 1.25 - 1.25 1.25

II. PEKERJAAN TANAH


1. Urugan Pasir Tebal 10 cm M3 374.10 2.45 374.10 2.45 - 374.10 2.45 100.00 2.45
2. Urugan Tanah Datang Tebal 35 cm M3 1,975.37 7.45 1,975.37 7.45 - 1,975.37 7.45 100.00 7.45
3. Pas. Cerucuk Bh 2,057.00 1.88 2,057.00 1.88 - 2,057.00 1.88 100.00 1.88
JUMLAH II 11.78 11.78 - 11.78 11.78

III. PEKERJAAN BETON


1. Jalan Cor Beton M3 374.10 16.37 374.10 16.37 - 374.10 16.37 100.00 16.37
2. Gelegar Jemabatan M3 3.20 0.72 3.20 0.72 - 3.20 0.72 100.00 0.72
3. Plat Jembatan M3 3.60 0.77 3.60 0.77 - 3.60 0.77 100.00 0.77
4. Buis Beton Dia. 80 cm ( 6 Buah ) M3 1.89 0.08 1.89 0.08 - 1.89 0.08 100.00 0.08
5. Lantai Kerja Turap Batu Kali Tebal 10 cm M3 75.64 3.06 75.64 3.06 - 75.64 3.06 100.00 3.06
JUMLAH III 21.00 21.00 - 21.00 21.00

IV. PEKERJAAN PASANGAN


1. Turap Batu Kali M3 150.84 5.12 150.84 5.12 - 150.84 5.12 100.00 5.12
2. Turap Abutment M3 5.59 0.19 5.59 0.19 - 5.59 0.19 100.00 0.19
JUMLAH IV 5.31 5.31 - 5.31 100.00 5.31

B. Lapangan Bola Makodam XII / TPR


I. URUGAN TANAH PILIHAN
DENGAN ALAT BERAT M3 2,425.82 42.21 2,425.82 42.21 - - 2,425.82 42.21 100.00 42.21
II. TANAM RUMPUT KLEKEP M2 5,698.00 8.37 - - - - - - -
III. PARIT PASANGAN 60 x 60 x 40 cm M1 400.00 10.07 390.00 9.82 10.00 0.25 400.00 10.07 100.00 10.07
JUMLAH V 60.65 52.03 0.25 52.28 86.21 52.28
91.38 0.25 91.63 91.63

TOTAL BOBOT 100.00 91.38 0.25 91.63 91.63


LAPORAN KEMAJUAN FISIK MINGGUAN

PEKERJAAN : PEMBANGUNAN PRASARANA MAKODAM XII / TPR


LOKASI : KABUPATEN KUBU RAYA MINGGU KE : XVIII (Delapan Belas)
TAHUN ANGGARAN : 2017 HARI : Senin s/d Minggu
TANGGAL : 28 AGST - 03 SEPT 2017

RENCANA REALISASI
NO. URAIAN PEKERJAAN SATUAN VOLUME BOBOT S/D MINGGU LALU MINGGU INI S/D MINGGU PERSENTASE TERTIMBANG
(%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13

A. Urugan Jalan Asrama Khatulistiwa +


Sirtu
I. PEKERJAAN PERSIAPAN
1. Penyiapan Badan Jalan M2 3,741.00 1.25 3,741.00 1.25 - 3,741.00 1.25 100.00 1.25
JUMLAH I 1.25 1.25 - 1.25 1.25

II. PEKERJAAN TANAH


1. Urugan Pasir Tebal 10 cm M3 374.10 2.45 374.10 2.45 - 374.10 2.45 100.00 2.45
2. Urugan Tanah Datang Tebal 35 cm M3 1,975.37 7.45 1,975.37 7.45 - 1,975.37 7.45 100.00 7.45
3. Pas. Cerucuk Bh 2,057.00 1.88 2,057.00 1.88 - 2,057.00 1.88 100.00 1.88
JUMLAH II 11.78 11.78 - 11.78 11.78

III. PEKERJAAN BETON


1. Jalan Cor Beton M3 374.10 16.37 374.10 16.37 - 374.10 16.37 100.00 16.37
2. Gelegar Jemabatan M3 3.20 0.72 3.20 0.72 - 3.20 0.72 100.00 0.72
3. Plat Jembatan M3 3.60 0.77 3.60 0.77 - 3.60 0.77 100.00 0.77
4. Buis Beton Dia. 80 cm ( 6 Buah ) M3 1.89 0.08 1.89 0.08 - 1.89 0.08 100.00 0.08
5. Lantai Kerja Turap Batu Kali Tebal 10 cm M3 75.64 3.06 75.64 3.06 - 75.64 3.06 100.00 3.06
JUMLAH III 21.00 21.00 - 21.00 21.00

IV. PEKERJAAN PASANGAN


1. Turap Batu Kali M3 150.84 5.12 150.84 5.12 - 150.84 5.12 100.00 5.12
2. Turap Abutment M3 5.59 0.19 5.59 0.19 - 5.59 0.19 100.00 0.19
JUMLAH IV 5.31 5.31 - 5.31 100.00 5.31

B. Lapangan Bola Makodam XII / TPR


I. URUGAN TANAH PILIHAN
DENGAN ALAT BERAT M3 2,425.82 42.21 2,425.82 42.21 - - 2,425.82 42.21 100.00 42.21
II. TANAM RUMPUT KLEKEP M2 5,698.00 8.37 - - 814.00 1.20 814.00 1.20 14.29 1.20
III. PARIT PASANGAN 60 x 60 x 40 cm M1 400.00 10.07 400.00 10.07 - - 400.00 10.07 100.00 10.07
JUMLAH V 60.65 52.28 1.20 53.48 88.18 53.48
91.63 1.20 92.83 92.83

TOTAL BOBOT 100.00 91.63 1.20 92.83 92.83


LAPORAN KEMAJUAN FISIK MINGGUAN

PEKERJAAN : PEMBANGUNAN PRASARANA MAKODAM XII / TPR


LOKASI : KABUPATEN KUBU RAYA MINGGU KE : XIX (Sembilan Belas)
TAHUN ANGGARAN : 2017 HARI : Senin s/d Minggu
TANGGAL : 04 - 10 SEPT 2017

RENCANA REALISASI
NO. URAIAN PEKERJAAN SATUAN VOLUME BOBOT S/D MINGGU LALU MINGGU INI S/D MINGGU PERSENTASE TERTIMBANG
(%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13

A. Urugan Jalan Asrama Khatulistiwa +


Sirtu
I. PEKERJAAN PERSIAPAN
1. Penyiapan Badan Jalan M2 3,741.00 1.25 3,741.00 1.25 - 3,741.00 1.25 100.00 1.25
JUMLAH I 1.25 1.25 - 1.25 1.25

II. PEKERJAAN TANAH


1. Urugan Pasir Tebal 10 cm M3 374.10 2.45 374.10 2.45 - 374.10 2.45 100.00 2.45
2. Urugan Tanah Datang Tebal 35 cm M3 1,975.37 7.45 1,975.37 7.45 - 1,975.37 7.45 100.00 7.45
3. Pas. Cerucuk Bh 2,057.00 1.88 2,057.00 1.88 - 2,057.00 1.88 100.00 1.88
JUMLAH II 11.78 11.78 - 11.78 11.78

III. PEKERJAAN BETON


1. Jalan Cor Beton M3 374.10 16.37 374.10 16.37 - 374.10 16.37 100.00 16.37
2. Gelegar Jemabatan M3 3.20 0.72 3.20 0.72 - 3.20 0.72 100.00 0.72
3. Plat Jembatan M3 3.60 0.77 3.60 0.77 - 3.60 0.77 100.00 0.77
4. Buis Beton Dia. 80 cm ( 6 Buah ) M3 1.89 0.08 1.89 0.08 - 1.89 0.08 100.00 0.08
5. Lantai Kerja Turap Batu Kali Tebal 10 cm M3 75.64 3.06 75.64 3.06 - 75.64 3.06 100.00 3.06
JUMLAH III 21.00 21.00 - 21.00 21.00

IV. PEKERJAAN PASANGAN


1. Turap Batu Kali M3 150.84 5.12 150.84 5.12 - 150.84 5.12 100.00 5.12
2. Turap Abutment M3 5.59 0.19 5.59 0.19 - 5.59 0.19 100.00 0.19
JUMLAH IV 5.31 5.31 - 5.31 100.00 5.31

B. Lapangan Bola Makodam XII / TPR


I. URUGAN TANAH PILIHAN
DENGAN ALAT BERAT M3 2,425.82 42.21 2,425.82 42.21 - - 2,425.82 42.21 100.00 42.21
II. TANAM RUMPUT KLEKEP M2 5,698.00 8.37 814.00 1.20 814.00 1.20 1,628.00 2.39 28.57 2.39
III. PARIT PASANGAN 60 x 60 x 40 cm M1 400.00 10.07 400.00 10.07 - - 400.00 10.07 100.00 10.07
JUMLAH V 60.65 53.48 1.20 54.68 90.15 54.68
92.83 1.20 94.02 94.02

TOTAL BOBOT 100.00 92.83 1.20 94.02 94.02


LAPORAN KEMAJUAN FISIK MINGGUAN

PEKERJAAN : PEMBANGUNAN PRASARANA MAKODAM XII / TPR


LOKASI : KABUPATEN KUBU RAYA MINGGU KE : XX (Dua Puluh)
TAHUN ANGGARAN : 2017 HARI : Senin s/d Minggu
TANGGAL : 11 - 17 SEPT 2017

RENCANA REALISASI
NO. URAIAN PEKERJAAN SATUAN VOLUME BOBOT S/D MINGGU LALU MINGGU INI S/D MINGGU PERSENTASE TERTIMBANG
(%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13

A. Urugan Jalan Asrama Khatulistiwa +


Sirtu
I. PEKERJAAN PERSIAPAN
1. Penyiapan Badan Jalan M2 3,741.00 1.25 3,741.00 1.25 - 3,741.00 1.25 100.00 1.25
JUMLAH I 1.25 1.25 - 1.25 1.25

II. PEKERJAAN TANAH


1. Urugan Pasir Tebal 10 cm M3 374.10 2.45 374.10 2.45 - 374.10 2.45 100.00 2.45
2. Urugan Tanah Datang Tebal 35 cm M3 1,975.37 7.45 1,975.37 7.45 - 1,975.37 7.45 100.00 7.45
3. Pas. Cerucuk Bh 2,057.00 1.88 2,057.00 1.88 - 2,057.00 1.88 100.00 1.88
JUMLAH II 11.78 11.78 - 11.78 11.78

III. PEKERJAAN BETON


1. Jalan Cor Beton M3 374.10 16.37 374.10 16.37 - 374.10 16.37 100.00 16.37
2. Gelegar Jemabatan M3 3.20 0.72 3.20 0.72 - 3.20 0.72 100.00 0.72
3. Plat Jembatan M3 3.60 0.77 3.60 0.77 - 3.60 0.77 100.00 0.77
4. Buis Beton Dia. 80 cm ( 6 Buah ) M3 1.89 0.08 1.89 0.08 - 1.89 0.08 100.00 0.08
5. Lantai Kerja Turap Batu Kali Tebal 10 cm M3 75.64 3.06 75.64 3.06 - 75.64 3.06 100.00 3.06
JUMLAH III 21.00 21.00 - 21.00 21.00

IV. PEKERJAAN PASANGAN


1. Turap Batu Kali M3 150.84 5.12 150.84 5.12 - 150.84 5.12 100.00 5.12
2. Turap Abutment M3 5.59 0.19 5.59 0.19 - 5.59 0.19 100.00 0.19
JUMLAH IV 5.31 5.31 - 5.31 100.00 5.31

B. Lapangan Bola Makodam XII / TPR


I. URUGAN TANAH PILIHAN
DENGAN ALAT BERAT M3 2,425.82 42.21 2,425.82 42.21 - - 2,425.82 42.21 100.00 42.21
II. TANAM RUMPUT KLEKEP M2 5,698.00 8.37 1,628.00 2.39 814.00 1.20 2,442.00 3.59 42.86 3.59
III. PARIT PASANGAN 60 x 60 x 40 cm M1 400.00 10.07 400.00 10.07 - - 400.00 10.07 100.00 10.07
JUMLAH V 60.65 54.68 1.20 55.87 92.12 55.87
94.02 1.20 95.22 95.22

TOTAL BOBOT 100.00 94.02 1.20 95.22 95.22


LAPORAN KEMAJUAN FISIK MINGGUAN

PEKERJAAN : PEMBANGUNAN PRASARANA MAKODAM XII / TPR


LOKASI : KABUPATEN KUBU RAYA MINGGU KE : XXI (Dua Puluh Satu)
TAHUN ANGGARAN : 2017 HARI : Senin s/d Minggu
TANGGAL : 18 - 24 SEPT 2017

RENCANA REALISASI
NO. URAIAN PEKERJAAN SATUAN VOLUME BOBOT S/D MINGGU LALU MINGGU INI S/D MINGGU PERSENTASE TERTIMBANG
(%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13

A. Urugan Jalan Asrama Khatulistiwa +


Sirtu
I. PEKERJAAN PERSIAPAN
1. Penyiapan Badan Jalan M2 3,741.00 1.25 3,741.00 1.25 - 3,741.00 1.25 100.00 1.25
JUMLAH I 1.25 1.25 - 1.25 1.25

II. PEKERJAAN TANAH


1. Urugan Pasir Tebal 10 cm M3 374.10 2.45 374.10 2.45 - 374.10 2.45 100.00 2.45
2. Urugan Tanah Datang Tebal 35 cm M3 1,975.37 7.45 1,975.37 7.45 - 1,975.37 7.45 100.00 7.45
3. Pas. Cerucuk Bh 2,057.00 1.88 2,057.00 1.88 - 2,057.00 1.88 100.00 1.88
JUMLAH II 11.78 11.78 - 11.78 11.78

III. PEKERJAAN BETON


1. Jalan Cor Beton M3 374.10 16.37 374.10 16.37 - 374.10 16.37 100.00 16.37
2. Gelegar Jemabatan M3 3.20 0.72 3.20 0.72 - 3.20 0.72 100.00 0.72
3. Plat Jembatan M3 3.60 0.77 3.60 0.77 - 3.60 0.77 100.00 0.77
4. Buis Beton Dia. 80 cm ( 6 Buah ) M3 1.89 0.08 1.89 0.08 - 1.89 0.08 100.00 0.08
5. Lantai Kerja Turap Batu Kali Tebal 10 cm M3 75.64 3.06 75.64 3.06 - 75.64 3.06 100.00 3.06
JUMLAH III 21.00 21.00 - 21.00 21.00

IV. PEKERJAAN PASANGAN


1. Turap Batu Kali M3 150.84 5.12 150.84 5.12 - 150.84 5.12 100.00 5.12
2. Turap Abutment M3 5.59 0.19 5.59 0.19 - 5.59 0.19 100.00 0.19
JUMLAH IV 5.31 5.31 - 5.31 100.00 5.31

B. Lapangan Bola Makodam XII / TPR


I. URUGAN TANAH PILIHAN
DENGAN ALAT BERAT M3 2,425.82 42.21 2,425.82 42.21 - - 2,425.82 42.21 100.00 42.21
II. TANAM RUMPUT KLEKEP M2 5,698.00 8.37 2,442.00 3.59 814.00 1.20 3,256.00 4.78 57.14 4.78
III. PARIT PASANGAN 60 x 60 x 40 cm M1 400.00 10.07 400.00 10.07 - - 400.00 10.07 100.00 10.07
JUMLAH V 60.65 55.87 1.20 57.07 94.09 57.07
95.22 1.20 96.41 96.41

TOTAL BOBOT 100.00 95.22 1.20 96.41 96.41


LAPORAN KEMAJUAN FISIK MINGGUAN

PEKERJAAN : PEMBANGUNAN PRASARANA MAKODAM XII / TPR


LOKASI : KABUPATEN KUBU RAYA MINGGU KE : XXII (Dua Puluh Dua)
TAHUN ANGGARAN : 2017 HARI : Senin s/d Minggu
TANGGAL : 25 SEPT - 01 OKT 2017

RENCANA REALISASI
NO. URAIAN PEKERJAAN SATUAN VOLUME BOBOT S/D MINGGU LALU MINGGU INI S/D MINGGU PERSENTASE TERTIMBANG
(%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13

A. Urugan Jalan Asrama Khatulistiwa +


Sirtu
I. PEKERJAAN PERSIAPAN
1. Penyiapan Badan Jalan M2 3,741.00 1.25 3,741.00 1.25 - 3,741.00 1.25 100.00 1.25
JUMLAH I 1.25 1.25 - 1.25 1.25

II. PEKERJAAN TANAH


1. Urugan Pasir Tebal 10 cm M3 374.10 2.45 374.10 2.45 - 374.10 2.45 100.00 2.45
2. Urugan Tanah Datang Tebal 35 cm M3 1,975.37 7.45 1,975.37 7.45 - 1,975.37 7.45 100.00 7.45
3. Pas. Cerucuk Bh 2,057.00 1.88 2,057.00 1.88 - 2,057.00 1.88 100.00 1.88
JUMLAH II 11.78 11.78 - 11.78 11.78

III. PEKERJAAN BETON


1. Jalan Cor Beton M3 374.10 16.37 374.10 16.37 - 374.10 16.37 100.00 16.37
2. Gelegar Jemabatan M3 3.20 0.72 3.20 0.72 - 3.20 0.72 100.00 0.72
3. Plat Jembatan M3 3.60 0.77 3.60 0.77 - 3.60 0.77 100.00 0.77
4. Buis Beton Dia. 80 cm ( 6 Buah ) M3 1.89 0.08 1.89 0.08 - 1.89 0.08 100.00 0.08
5. Lantai Kerja Turap Batu Kali Tebal 10 cm M3 75.64 3.06 75.64 3.06 - 75.64 3.06 100.00 3.06
JUMLAH III 21.00 21.00 - 21.00 21.00

IV. PEKERJAAN PASANGAN


1. Turap Batu Kali M3 150.84 5.12 150.84 5.12 - 150.84 5.12 100.00 5.12
2. Turap Abutment M3 5.59 0.19 5.59 0.19 - 5.59 0.19 100.00 0.19
JUMLAH IV 5.31 5.31 - 5.31 100.00 5.31

B. Lapangan Bola Makodam XII / TPR


I. URUGAN TANAH PILIHAN
DENGAN ALAT BERAT M3 2,425.82 42.21 2,425.82 42.21 - - 2,425.82 42.21 100.00 42.21
II. TANAM RUMPUT KLEKEP M2 5,698.00 8.37 3,256.00 4.78 814.00 1.20 4,070.00 5.98 71.43 5.98
III. PARIT PASANGAN 60 x 60 x 40 cm M1 400.00 10.07 400.00 10.07 - - 400.00 10.07 100.00 10.07
JUMLAH V 60.65 57.07 1.20 58.26 96.06 58.26
96.41 1.20 97.61 97.61

TOTAL BOBOT 100.00 96.41 1.20 97.61 97.61


LAPORAN KEMAJUAN FISIK MINGGUAN

PEKERJAAN : PEMBANGUNAN PRASARANA MAKODAM XII / TPR


LOKASI : KABUPATEN KUBU RAYA MINGGU KE : XXIII (Dua Puluh Tiga)
TAHUN ANGGARAN : 2017 HARI : Senin s/d Minggu
TANGGAL : 02 - 08 OKT 2017

RENCANA REALISASI
NO. URAIAN PEKERJAAN SATUAN VOLUME BOBOT S/D MINGGU LALU MINGGU INI S/D MINGGU PERSENTASE TERTIMBANG
(%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13

A. Urugan Jalan Asrama Khatulistiwa +


Sirtu
I. PEKERJAAN PERSIAPAN
1. Penyiapan Badan Jalan M2 3,741.00 1.25 3,741.00 1.25 - 3,741.00 1.25 100.00 1.25
JUMLAH I 1.25 1.25 - 1.25 1.25

II. PEKERJAAN TANAH


1. Urugan Pasir Tebal 10 cm M3 374.10 2.45 374.10 2.45 - 374.10 2.45 100.00 2.45
2. Urugan Tanah Datang Tebal 35 cm M3 1,975.37 7.45 1,975.37 7.45 - 1,975.37 7.45 100.00 7.45
3. Pas. Cerucuk Bh 2,057.00 1.88 2,057.00 1.88 - 2,057.00 1.88 100.00 1.88
JUMLAH II 11.78 11.78 - 11.78 11.78

III. PEKERJAAN BETON


1. Jalan Cor Beton M3 374.10 16.37 374.10 16.37 - 374.10 16.37 100.00 16.37
2. Gelegar Jemabatan M3 3.20 0.72 3.20 0.72 - 3.20 0.72 100.00 0.72
3. Plat Jembatan M3 3.60 0.77 3.60 0.77 - 3.60 0.77 100.00 0.77
4. Buis Beton Dia. 80 cm ( 6 Buah ) M3 1.89 0.08 1.89 0.08 - 1.89 0.08 100.00 0.08
5. Lantai Kerja Turap Batu Kali Tebal 10 cm M3 75.64 3.06 75.64 3.06 - 75.64 3.06 100.00 3.06
JUMLAH III 21.00 21.00 - 21.00 21.00

IV. PEKERJAAN PASANGAN


1. Turap Batu Kali M3 150.84 5.12 150.84 5.12 - 150.84 5.12 100.00 5.12
2. Turap Abutment M3 5.59 0.19 5.59 0.19 - 5.59 0.19 100.00 0.19
JUMLAH IV 5.31 5.31 - 5.31 100.00 5.31

B. Lapangan Bola Makodam XII / TPR


I. URUGAN TANAH PILIHAN
DENGAN ALAT BERAT M3 2,425.82 42.21 2,425.82 42.21 - - 2,425.82 42.21 100.00 42.21
II. TANAM RUMPUT KLEKEP M2 5,698.00 8.37 4,070.00 5.98 1,628.00 2.39 5,698.00 8.37 100.00 8.37
III. PARIT PASANGAN 60 x 60 x 40 cm M1 400.00 10.07 400.00 10.07 - - 400.00 10.07 100.00 10.07
JUMLAH V 60.65 58.26 2.39 60.65 100.00 60.65
97.61 2.39 100.00 100.00

TOTAL BOBOT 100.00 97.61 2.39 100.00 100.00


JADWAL WAKTU PELAKSANAAN PEKERJAAN

PEKERJAAN : PEMBANGUNAN PRASARANA MAKODAM XII / TPR


LOKASI : KABUPATEN KUBU RAYA
TAHUN ANGGARAN : 2017

BULAN
BOBOT
NO. URAIAN PEKERJAAN KETERANGAN
(%) MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU

KE - 1 KE - 2 KE - 3 KE - 4 KE - 5 KE - 6 KE - 7 KE - 8 KE - 9 KE - 10 KE - 11 KE - 12 KE - 13 KE - 14 KE - 15 KE - 16 KE - 17 KE - 18 KE - 19 KE - 20 KE - 21 KE - 22 KE - 23 KE - 24
7.5

A. Urugan Jalan Asrama

Khatulistiwa + Sirtu
100
1. Pekerjaan Persiapan 1.25 0.62 0.62
90
2. Pekerjaan Tanah 11.78 0.79 0.79 0.79 0.79 0.79 0.79 0.79 0.79 0.79 0.79 0.79 0.79 0.79 0.79 0.79
80
3. Pekerjaan Beton 21.00 1.05 1.05 1.05 1.05 1.05 1.05 1.05 1.05 1.05 1.05 1.05 1.05 1.05 1.05 1.05 1.05 1.05 1.05 1.05 1.05
70
4. Pekerjaan Pasangan 5.31 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35
60

50

40

B. Lapangan Bola Makodam XII / TPR 30

1. Urugan Tanah Pilihan Dengan Alat Berat 42.21 2.48 2.48 2.48 2.48 2.48 2.48 2.48 2.48 2.48 2.48 2.48 2.48 2.48 2.48 2.48 2.48 2.48 20

2. Tanam Rumput Klekep 8.37 1.20 1.20 1.20 1.20 1.20 1.20 1.20 10

3. Parit Pasangan 60 x 60 x 40 cm 10.07 1.01 1.01 1.01 1.01 1.01 1.01 1.01 1.01 1.01 1.01 0

JUMLAH 100.00

RENCANA MINGGUAN (%) 1.63 4.12 4.28 4.63 5.68 5.68 5.68 5.68 5.68 5.68 4.67 4.67 4.67 4.67 4.67 4.67 4.67 5.08 2.25 2.25 2.25 2.25 2.25 2.25

KUMULATIF RENCANA MINGGUAN (%) 1.63 5.75 10.02 14.65 20.33 26.01 31.69 37.37 43.05 48.73 53.41 58.08 62.75 67.43 72.10 76.77 81.44 86.53 88.77 91.02 93.26 95.51 97.75 100.00

REALISASI MINGGUAN (%) 8.84 9.67 8.96 8.72 5.81 1.89 2.52 1.64 7.84 8.70 6.96 6.09 5.22 4.35 3.93 0.25 0.25 1.20 1.20 1.20 1.20 1.20 2.39

KUMULATIF REALISASI MINGGUAN (%) 8.84 18.50 27.46 36.18 41.99 43.88 46.40 48.04 55.88 64.58 71.54 77.63 82.85 87.20 91.13 91.38 91.63 92.83 94.02 95.22 96.41 97.61 100.00 100.00 #REF!

DEVIASI (%) 7.21 12.76 17.44 21.53 21.66 17.87 14.71 10.66 12.82 15.84 18.13 19.55 20.10 19.77 19.03 14.61 10.19 6.30 5.25 4.20 3.15 2.10 2.25 -

KET : REALISASI
RENCANA