BIAYA PEKERJAAN
NO. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH BIAYA
(Rp.) (Rp.)
1 2 3 4 5 6
TERBILANG : SATU MILYAR TUJUH RATUS TIGA JUTA DELAPAN RATUS TIGA PULUH RIBU RUPIAH
Dibuat Oleh :
PT. MITRA ANTARA BENUA
HERIANTO GANI
Direktur
16.6087001
#REF!
#REF!
1,110,835,075.48
(592,994,924.52)
BILL OF QUANTITY
PEKERJAAN : URUGAN JALAN ASR. KHATULISTIWA
LOKASI : ASRAMA KHATULISTIWA SIANTAN
TAHUN ANGGARAN : 2017
BIAYA PEKERJAAN
NO. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN
(Rp.)
1 2 3 4 5
I. PEKERJAAN PERSIAPAN
1. Penyiapan Badan Jalan M2 3,741.00 8,532.13
JUMLAH I
TERBILANG : SATU MILYAR SERATUS LIMA JUTA TIGA RATUS DELAPAN PULUH DUA RIBU RUPIAH
Dibuat Oleh :
PT. MITRA ANTARA BENUA
HERIANTO GANI
Direktur
BILL OF QUANTITY
BIAYA PEKERJAAN
JUMLAH BIAYA
(Rp.)
31,918,679.63
31,918,679.63
62,574,012.33
190,190,968.36
48,108,036.08
300,873,016.77
418,141,498.14
18,340,705.33
19,757,920.97
2,112,503.16
78,071,323.37
536,423,950.96
130,828,885.34
4,848,405.39
135,677,290.73
1,004,892,938.08
100,489,293.81
1,105,382,231.89
1,105,382,000.00
TU MILYAR SERATUS LIMA JUTA TIGA RATUS DELAPAN PULUH DUA RIBU RUPIAH
HERIANTO GANI
Direktur
6.22693323
29.9408032
0
0
41.610552
#REF!
#REF!
ANALISA HARGA SATUAN PEKERJAAN
TAHUN ANGGARAN 2017
HARGA BIAYA
NO. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
(Rp.) (Rp.)
1 2 3 4 5 6
A. TENAGA
1. Pekerja OH 79,600.00 0.100 7,960.00
2. Mandor OH 114,425.00 0.005 572.13
Jumlah 8,532.13
B. BAHAN
Jumlah -
C. ALAT
Jumlah -
D. Jumlah A + B + C 8,532.13
E. Overhead & Profit 15% x D -
F. Harga Satuan (D + E) 8,532.13
HARGA BIAYA
NO. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
(Rp.) (Rp.)
1 2 3 4 5 6
A. TENAGA
1. Pekerja OH 79,600.00 0.300 23,880.00
2. Mandor OH 114,425.00 0.010 1,144.25
Jumlah 25,024.25
B. BAHAN
1. Pasir Urug m3 118,534.35 1.200 142,241.22
Jumlah 142,241.22
C. ALAT
Jumlah -
D. Jumlah A + B + C 167,265.47
E. Overhead & Profit 15% x D -
F. Harga Satuan (D + E) 167,265.47
HARGA BIAYA
NO. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
(Rp.) (Rp.)
1 2 3 4 5 6
A. TENAGA
1. Pekerja OH 79,600.00 0.250 19,900.00
2. Mandor OH 114,425.00 0.025 2,860.63
Jumlah 22,760.63
B. BAHAN
1. Tanah Urug / Tanah Datang M3 60,991.51 1.200 73,189.81
Jumlah 73,189.81
C. ALAT
1. VIBRATORY ROLLER 5-8 T Sewa/Jam 22,500.00 0.0076 171.00
2. WATER TANKER 3000-4500 L Sewa/Jam 22,500.00 0.0071 159.75
Jumlah 330.75
D. Jumlah A + B + C 96,281.19
E. Overhead & Profit 15% x D -
F. Harga Satuan (D + E) 96,281.19
M3 JALAN COR BETON
HARGA BIAYA
NO. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
(Rp.) (Rp.)
1 2 3 4 5 6
A. TENAGA
1. Pekerja OH 79,600.00 1.650 131,340.00
2. Tukang Batu OH 99,500.00 0.275 27,362.50
3. Kepala Tukang OH 114,425.00 0.028 3,203.90
4. Mandor OH 114,425.00 0.083 9,497.28
Jumlah 171,403.68
B. BAHAN
1. Semen Portland Zak 74,453.86 7.680 571,805.64
2. Pasir Beton m3 142,258.14 0.499 70,986.81
3. Batu Split Pecah Mesin 1/2 m3 391,147.44 0.776 303,530.41
Jumlah 946,322.86
C. ALAT
Jumlah -
D. Jumlah A + B + C 1,117,726.54
E. Overhead & Profit 15% x D -
F. Harga Satuan (D + E) 1,117,726.54
HARGA BIAYA
NO. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
(Rp.) (Rp.)
1 2 3 4 5 6
A. TENAGA
1. Pekerja OH 79,600.00 0.100 7,960.00
2. Mandor OH 114,425.00 0.010 1,144.25
Jumlah 9,104.25
B. BAHAN
1. Kayu Cerucuk /Dolken ø 8-10 - Pj. 4 M Btg 14,283.23 1.000 14,283.23
Jumlah 14,283.23
C. ALAT
Jumlah -
D. Jumlah A + B + C 23,387.48
E. Overhead & Profit 15% x D -
F. Harga Satuan (D + E) 23,387.48
HARGA BIAYA
NO. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
(Rp.) (Rp.)
1 2 3 4 5 6
A. TENAGA
1. Pekerja OH 79,600.00 5.800 461,680.00
2. Tukang Batu OH 99,500.00 0.350 34,825.00
3. Tukang Kayu OH 99,500.00 2.800 278,600.00
4. Tukang Besi OH 99,500.00 1.050 104,475.00
5. Kepala Tukang OH 114,425.00 0.420 48,058.50
6. Mandor OH 114,425.00 0.190 21,740.75
Jumlah 949,379.25
B. BAHAN
1. Kayu Bekesting m3 2,717,096.25 0.210 570,590.21
2. Paku biasa 2"-5" Kg 29,634.09 3.200 94,829.07
3. Minyak Bekisting Ltr 6,965.00 1.600 11,144.00
4. Besi Tulangan Beton (Polos / Ulir) Kg 17,977.66 150.000 2,696,649.00
5. Kawat Beton (Bendrat) Kg 20,521.88 2.250 46,174.22
6. Semen Portland Kg 1,489.52 323.000 481,113.35
7. Pasir Beton m3 142,258.14 0.520 73,974.23
8. Batu Split Pecah Mesin 1/2 m3 391,147.44 0.780 305,095.00
9. Papan Kayu Kelas III ( Tidak Ketam ) m3 2,264,384.19 0.121 273,990.49
10. Kayu Cerucuk /Dolken ø 8-10 - Pj. 4 M Btg 14,283.23 16.000 228,531.60
Jumlah 4,782,091.16
C. ALAT
Jumlah -
D. Jumlah A + B + C 5,731,470.41
E. Overhead & Profit 15% x D -
F. Harga Satuan (D + E) 5,731,470.41
1 M3 PEKERJAAN PLAT LANTAI BETON TEBAL 12 CM
HARGA BIAYA
NO. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
(Rp.) (Rp.)
1 2 3 4 5 6
A. TENAGA
Jumlah -
B. BAHAN
1. Plat Lantai Beton Tebal 12 cm M2 658,600.00 8.333 5,488,311.38
Jumlah 5,488,311.38
C. ALAT
Jumlah -
D. Jumlah A + B + C 5,488,311.38
E. Overhead & Profit 15% x D -
F. Harga Satuan (D + E) 5,488,311.38
HARGA BIAYA
NO. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
(Rp.) (Rp.)
1 2 3 4 5 6
A. TENAGA
1. Pekerja OH 79,600.00 1.650 131,340.00
2. Tukang Batu OH 99,500.00 0.275 27,362.50
3. Kepala Tukang OH 114,425.00 0.028 3,203.90
4. Mandor OH 114,425.00 0.083 9,497.28
Jumlah 171,403.68
B. BAHAN
1. Semen Portland Zak 74,453.86 7.680 571,805.64
2. Pasir Beton m3 142,258.14 0.499 70,986.81
3. Batu Split Pecah Mesin 1/2 m3 391,147.44 0.776 303,530.41
Jumlah 946,322.86
C. ALAT
Jumlah -
D. Jumlah A + B + C 1,117,726.54
E. Overhead & Profit 15% x D -
F. Harga Satuan (D + E) 1,117,726.54
HARGA BIAYA
NO. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
(Rp.) (Rp.)
1 2 3 4 5 6
A. TENAGA
1. Pekerja OH 79,600.00 1.650 131,340.00
2. Tukang Batu OH 99,500.00 0.275 27,362.50
3. Kepala Tukang OH 114,425.00 0.028 3,203.90
4. Mandor OH 114,425.00 0.083 9,497.28
Jumlah 171,403.68
B. BAHAN
1. Semen Portland Zak 74,453.86 6.520 485,439.17
2. Pasir Beton m3 142,258.14 0.543 77,246.17
3. Batu Split Pecah Mesin 1/2 m3 391,147.44 0.762 298,054.35
Jumlah 860,739.68
C. ALAT
Jumlah -
D. Jumlah A + B + C 1,032,143.35
E. Overhead & Profit 15% x D -
F. Harga Satuan (D + E) 1,032,143.35
M3 TURAP BATU KALI
HARGA BIAYA
NO. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
(Rp.) (Rp.)
1 2 3 4 5 6
A. TENAGA
1. Pekerja OH 79,600.00 2.250 179,100.00
2. Tukang Batu OH 99,500.00 0.600 59,700.00
3. Kepala Tukang OH 114,425.00 0.060 6,865.50
4. Mandor OH 114,425.00 0.020 2,288.50
Jumlah 247,954.00
B. BAHAN
1. Batu Kali m 3
260,217.38 1.200 312,260.85
2. Semen Portland Zak 74,453.86 3.520 262,077.59
3. Pasir Pasang m 3
118,534.35 0.380 45,043.05
Jumlah 619,381.49
C. ALAT
Jumlah -
D. Jumlah A + B + C 867,335.49
E. Overhead & Profit 15% x D -
F. Harga Satuan (D + E) 867,335.49
M3 TURAP ABUTMENT
HARGA BIAYA
NO. URAIAN PEKERJAAN SATUAN SATUAN KUANTITAS SATUAN
(Rp.) (Rp.)
1 2 3 4 5 6
A. TENAGA
1. Pekerja OH 79,600.00 2.250 179,100.00
2. Tukang Batu OH 99,500.00 0.600 59,700.00
3. Kepala Tukang OH 114,425.00 0.060 6,865.50
4. Mandor OH 114,425.00 0.020 2,288.50
Jumlah 247,954.00
B. BAHAN
1. Batu Kali m 3
260,217.38 1.200 312,260.85
2. Semen Portland Zak 74,453.86 3.520 262,077.59
3. Pasir Pasang m 3
118,534.35 0.380 45,043.05
Jumlah 619,381.49
C. ALAT
Jumlah -
D. Jumlah A + B + C 867,335.49
E. Overhead & Profit 15% x D -
F. Harga Satuan (D + E) 867,335.49
DAFTAR UPAH TENAGA KERJA DAN HARGA SATUAN MATERIAL /
BAHAN
PEKERJAAN URUGAN JALAN ASR. KHATULISTIWA + SIRTU
TAHUN ANGGARAN 2017
HARGA
NO. TENAGA KERJA SATUAN SATUAN
(Rp.)
HARGA
NO. MATERIAL SATUAN SATUAN
(Rp.)
UPAH
1. Pekerja = 3,741.00 x 0.10 = 374.10
= 374.10 x 79,600.00 = Rp. 29,778,360.00
2. Mandor = 3,741.00 x 0.01 = 18.71
= 18.71 x 114,425.00 = Rp. 2,140,319.63
BAHAN
1. Pasir Urug = 374.10 x 1.20 = 448.92
= 448.92 x 118,534.35 = Rp. 53,212,440.40
UPAH
1. Pekerja = 374.10 x 0.30 = 112.23
= 112.23 x 79,600.00 = Rp. 8,933,508.00
2. Mandor = 374.10 x 0.01 = 3.74
= 3.74 x 114,425.00 = Rp. 428,063.93
BAHAN
1. Tanah Urug / Tanah Datang = 1,975.37 x 1.20 = 2,370.44
= 2,370.44 x 60,991.51 = Rp. 144,576,958.93
UPAH
1. Pekerja = 1,975.37 x 0.25 = 493.84
= 493.84 x 79,600.00 = Rp. 39,309,863.00
2. Mandor = 1,975.37 x 0.03 = 49.38
= 49.38 x 114,425.00 = Rp. 5,650,792.81
ALAT
1. VIBRATORY ROLLER 5-8 T = 1,975.37 x 0.0076 = 15.01
= 15.01 x 22,500.00 = Rp. 337,788.27
2. WATER TANKER 3000-4500 L = 1,975.37 x 0.0071 = 14.03
= 14.03 x 22,500.00 = Rp. 315,565.36
BAHAN
1. Kayu Cerucuk /Dolken ø 8-10 - Pj. 4 M = 2,057.00 x 1.00 = 2,057.00
= 2,057.00 x 14,283.23 = Rp. 29,380,593.83
UPAH
1. Pekerja = 2,057.00 x 0.10 = 205.70
= 205.70 x 79,600.00 = Rp. 16,373,720.00
2. Mandor = 2,057.00 x 0.01 = 20.57
= 20.57 x 114,425.00 = Rp. 2,353,722.25
BAHAN
1. Semen Portland = 374.10 x 7.68 = 2,873.09
= 2,873.09 x 74,453.86 = Rp. 213,912,491.72
2. Pasir Beton = 374.10 x 0.50 = 186.68
= 186.68 x 142,258.14 = Rp. 26,556,165.38
3. Batu Split Pecah Mesin 1/2 = 374.10 x 0.78 = 290.30
= 290.30 x 391,147.44 = Rp. 113,550,726.22
UPAH
1. Pekerja = 374.10 x 1.65 = 617.27
= 617.27 x 79,600.00 = Rp. 49,134,294.00
2. Tukang Batu = 374.10 x 0.28 = 102.88
= 102.88 x 99,500.00 = Rp. 10,236,311.25
3. Kepala Tukang = 374.10 x 0.03 = 10.47
= 10.47 x 114,425.00 = Rp. 1,198,578.99
4. Mandor = 374.10 x 0.08 = 31.05
= 31.05 x 114,425.00 = Rp. 3,552,930.58
BAHAN
1. Kayu Bekesting = 3.20 x 0.21 = 0.67
= 0.67 x 2,717,096.25 = Rp. 1,825,888.68
2. Paku biasa 2"-5" = 3.20 x 3.20 = 10.24
= 10.24 x 29,634.09 = Rp. 303,453.03
3. Minyak Bekisting = 3.20 x 1.60 = 5.12
= 5.12 x 6,965.00 = Rp. 35,660.80
4. Besi Tulangan Beton (Polos / Ulir) = 3.20 x 150.00 = 480.00
= 480.00 x 17,977.66 = Rp. 8,629,276.80
5. Kawat Beton (Bendrat) = 3.20 x 2.25 = 7.20
= 7.20 x 20,521.88 = Rp. 147,757.50
6. Semen Portland = 3.20 x 323.00 = 1,033.60
= 1,033.60 x 1,489.52 = Rp. 1,539,562.70
7. Pasir Beton = 3.20 x 0.52 = 1.66
= 1.66 x 142,258.14 = Rp. 236,717.54
8. Batu Split Pecah Mesin 1/2 = 3.20 x 0.78 = 2.50
= 2.50 x 391,147.44 = Rp. 976,304.00
9. Papan Kayu Kelas III ( Tidak Ketam ) = 3.20 x 0.12 = 0.39
= 0.39 x 2,264,384.19 = Rp. 876,769.56
10 Kayu Cerucuk /Dolken ø 8-10 - Pj. 4 M = 3.20 x 16.00 = 51.20
= 51.20 x 14,283.23 = Rp. 731,301.12
UPAH
1. Pekerja = 3.20 x 5.80 = 18.56
= 18.56 x 79,600.00 = Rp. 1,477,376.00
ANALISA TEKNIS SATUAN PEKERJAAN (URUGAN JALAN ASRAMA KHATULISTIWA + SIRTU)
UPAH
1. Pekerja = 3,741.00 x 0.10 = 374.10
= 374.10 / 1.00 = 374.10 Hari
= 374.10 / 30.00 = 12.47 Hari
2. Mandor = 3,741.00 x 0.01 = 18.71
= 18.71 / 1.00 = 18.71 Hari
= 18.71 / 1.00 = 18.71 Hari
UPAH
1. Pekerja = 374.10 x 0.300 = 112.23
= 112.23 / 1.00 = 112.23 Hari
= 112.23 / 18.00 = 6.24 Hari
2. Mandor = 374.10 x 0.010 = 3.74
= 3.74 / 1.00 = 3.74 Hari
= 3.74 / 1.00 = 3.74 Hari
UPAH
1. Pekerja = 1,975.37 x 0.25 = 493.84
= 493.84 / 1.00 = 493.84 Hari
= 493.84 / 25.00 = 19.75 Hari
2. Mandor = 1,975.37 x 0.03 = 49.38
= 49.38 / 1.00 = 49.38 Hari
= 49.38 / 1.00 = 49.38 Hari
ALAT
1. VIBRATORY ROLLER 5-8 T = 1,975.37 x 0.01 = 15.01
= 15.01 / 1.00 = 15.01 Jam
= 15.01 / 1.00 = 15.01 Jam
2. WATER TANKER 3000-4500 L = 1,975.37 x 0.01 = 14.03
= 14.03 / 1.00 = 14.03 Jam
= 14.03 / 1.00 = 14.03 Jam
UPAH
1. Pekerja = 2,057.00 x 0.25 = 514.25
= 514.25 / 1.00 = 514.25 Hari
= 514.25 / 18.00 = 28.57 Hari
2. Mandor = 2,057.00 x 0.03 = 51.43
= 51.43 / 1.00 = 51.43 Hari
= 51.43 / 1.00 = 51.43 Hari
UPAH
1. Pekerja = 374.10 x 1.65 = 617.27
= 617.27 / 1.00 = 617.27 Hari
= 617.27 / 18.00 = 34.29 Hari
2. Tukang Batu = 374.10 x 0.28 = 102.88
= 102.88 / 1.00 = 102.88 Hari
= 102.88 / 18.00 = 5.72 Hari
3. Kepala Tukang = 374.10 x 0.03 = 10.47
= 10.47 / 1.00 = 10.47 Hari
= 10.47 / 1.00 = 10.47 Hari
4. Mandor = 374.10 x 0.08 = 31.05
= 31.05 / 1.00 = 31.05 Hari
= 31.05 / 1.00 = 31.05 Hari
UPAH
1. Pekerja = 3.20 x 5.80 = 18.56
= 18.56 / 1.00 = 18.56 Hari
= 18.56 / 30.00 = 0.62 Hari
2. Tukang Batu = 3.20 x 0.35 = 1.12
= 1.12 / 1.00 = 1.12 Hari
= 1.12 / 18.00 = 0.06 Hari
3. Tukang Kayu = 3.20 x 2.80 = 8.96
= 8.96 / 1.00 = 8.96 Hari
= 8.96 / 18.00 = 0.50 Hari
4. Tukang Besi = 3.20 x 1.05 = 3.36
= 3.36 / 1.00 = 3.36 Hari
= 3.36 / 18.00 = 0.19 Hari
5. Kepala Tukang = 3.20 x 0.42 = 1.34
= 1.34 / 1.00 = 1.34 Hari
= 1.34 / 1.00 = 1.34 Hari
6. Mandor = 3.20 x 0.19 = 0.61
= 0.61 / 1.00 = 0.61 Hari
= 0.61 / 1.00 = 0.61 Hari
UPAH
1. Pekerja = 1.89 x 1.65 = 3.12
= 3.12 / 1.00 = 3.12 Hari
= 3.12 / 18.00 = 0.17 Hari
2. Tukang Batu = 1.89 x 0.28 = 0.52
= 0.52 / 1.00 = 0.52 Hari
= 0.52 / 5.00 = 0.10 Hari
3. Kepala Tukang = 1.89 x 0.03 = 0.05
= 0.05 / 1.00 = 0.05 Hari
= 0.05 / 1.00 = 0.05 Hari
4. Mandor = 1.89 x 0.08 = 0.16
= 0.16 / 1.00 = 0.16 Hari
= 0.16 / 1.00 = 0.16 Hari
8. M3 LANTAI KERJA TURAP BATU KALI 10 CM = 75.64 M3
UPAH
1. Pekerja = 75.64 x 1.65 = 124.81
= 124.81 / 1.00 = 124.81 Hari
= 124.81 / 18.00 = 6.93 Hari
2. Tukang Batu = 75.64 x 0.28 = 20.80
= 20.80 / 1.00 = 20.80 Hari
= 20.80 / 12.00 = 1.73 Hari
3. Kepala Tukang = 75.64 x 0.03 = 2.12
= 2.12 / 1.00 = 2.12 Hari
= 2.12 / 1.00 = 2.12 Hari
4. Mandor = 75.64 x 0.08 = 6.28
= 6.28 / 1.00 = 6.28 Hari
= 6.28 / 1.00 = 6.28 Hari
UPAH
1. Pekerja = 150.84 x 2.25 = 339.39
= 339.39 / 1.00 = 339.39 Hari
= 339.39 / 30.00 = 11.31 Hari
2. Tukang Batu = 150.84 x 0.60 = 90.50
= 90.50 / 1.00 = 90.50 Hari
= 90.50 / 18.00 = 5.03 Hari
3. Kepala Tukang = 150.84 x 0.06 = 9.05
= 9.05 / 1.00 = 9.05 Hari
= 9.05 / 1.00 = 9.05 Hari
4. Mandor = 150.84 x 0.02 = 3.02
= 3.02 / 1.00 = 3.02 Hari
= 3.02 / 1.00 = 3.02 Hari
UPAH
1. Pekerja = 5.59 x 2.25 = 12.58
= 12.58 / 1.00 = 12.58 Hari
= 12.58 / 18.00 = 0.70 Hari
2. Tukang Batu = 5.59 x 0.60 = 3.35
= 3.35 / 1.00 = 3.35 Hari
= 3.35 / 5.00 = 0.67 Hari
3. Kepala Tukang = 5.59 x 0.06 = 0.34
= 0.34 / 1.00 = 0.34 Hari
= 0.34 / 1.00 = 0.34 Hari
4. Mandor = 5.59 x 0.02 = 0.11
= 0.11 / 1.00 = 0.11 Hari
= 0.11 / 1.00 = 0.11 Hari
REKAPITULASI ANALISA TEKNIS HARGA SATUAN PEKERJAAN
UPAH
1. Pekerja 0.30 112.23 OH 18.00 Orang 6.24 0.89
2. Mandor 0.01 3.74 OH 1.00 Orang 3.74 0.53
UPAH
1. Pekerja 0.25 493.84 OH 25.00 Orang 19.75 2.82
2. Mandor 0.03 49.38 OH 1.00 Orang 49.38 7.05
ALAT
1. VIBRATORY ROLLER 5-8 T 0.0076 15.01 JAM
2. WATER TANKER 3000-4500 L 0.0071 14.03 JAM
UPAH
1. Pekerja 0.25 514.25 OH 18.00 Orang 28.57 4.08
2. Mandor 0.03 51.43 OH 1.00 Orang 51.43 7.35
UPAH
1. Pekerja 1.65 617.27 OH 18.00 Orang 34.29 4.90
2. Tukang Batu 0.28 102.88 OH 18.00 Orang 5.72 0.82
3. Kepala Tukang 0.03 10.47 OH 1.00 Orang 10.47 1.50
4. Mandor 0.08 31.05 OH 1.00 Orang 31.05 4.44
UPAH
1. Pekerja 5.80 18.56 OH 30.00 Orang 0.62 0.09
2. Tukang Batu 0.35 1.12 OH 18.00 Orang 0.06 0.01
3. Tukang Kayu 2.80 8.96 OH 18.00 Orang 0.50 0.07
4. Tukang Besi 1.05 3.36 OH 18.00 Orang 0.19 0.03
5. Kepala Tukang 0.42 1.34 OH 1.00 Orang 1.34 0.19
6. Mandor 0.19 0.61 OH 1.00 Orang 0.61 0.09
UPAH
1. Pekerja 1.65 3.12 OH 18.00 Orang 0.17 0.02
2. Tukang Batu 0.28 0.52 OH 5.00 Orang 0.10 0.01
3. Kepala Tukang 0.03 0.05 OH 1.00 Orang 0.05 0.01
4. Mandor 0.08 0.16 OH 1.00 Orang 0.16 0.02
UPAH
1. Pekerja 1.65 124.81 OH 18.00 Orang 6.93 0.99
2. Tukang Batu 0.28 20.80 OH 12.00 Orang 1.73 0.25
3. Kepala Tukang 0.03 2.12 OH 1.00 Orang 2.12 0.30
4. Mandor 0.08 6.28 OH 1.00 Orang 6.28 0.90
URAIAN ANALISA ALAT
A. URAIAN PERALATAN
1. Jenis Peralatan VIBRATORY ROLLER 5-8 T E17
2. Tenaga Pw 75.0 HP
3. Kapasitas Cp 8.0 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 0 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir / Mekanik U1 12,500.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir / Pmb.Mekanik U2 10,000.00 Rp./Jam
4. Bahan Bakar Bensin Mb 0.00 Liter
5. Bahan Bakar Solar Ms 0.00 Liter
6. Minyak Pelumas Mp 0.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT
A. URAIAN PERALATAN
1. Jenis Peralatan WATER TANKER 3000-4500 L E23
2. Tenaga Pw 100.0 HP
3. Kapasitas Cp 4,000.00 Liter
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 0 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 12,500.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 10,000.00 Rp./Jam
4. Bahan Bakar Bensin Mb 0.00 Liter
5. Bahan Bakar Solar Ms 0.00 Liter
6. Minyak Pelumas Mp 0.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
LAPORAN KEMAJUAN FISIK MINGGUAN
RENCANA REALISASI
NO. URAIAN PEKERJAAN SATUAN VOLUME BOBOT S/D MINGGU LALU MINGGU INI S/D MINGGU PERSENTASE TERTIMBANG
(%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13
RENCANA REALISASI
NO. URAIAN PEKERJAAN SATUAN VOLUME BOBOT S/D MINGGU LALU MINGGU INI S/D MINGGU PERSENTASE TERTIMBANG
(%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13
RENCANA REALISASI
NO. URAIAN PEKERJAAN SATUAN VOLUME BOBOT S/D MINGGU LALU MINGGU INI S/D MINGGU PERSENTASE TERTIMBANG
(%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13
RENCANA REALISASI
NO. URAIAN PEKERJAAN SATUAN VOLUME BOBOT S/D MINGGU LALU MINGGU INI S/D MINGGU PERSENTASE TERTIMBANG
(%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13
RENCANA REALISASI
NO. URAIAN PEKERJAAN SATUAN VOLUME BOBOT S/D MINGGU LALU MINGGU INI S/D MINGGU PERSENTASE TERTIMBANG
(%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13
RENCANA REALISASI
NO. URAIAN PEKERJAAN SATUAN VOLUME BOBOT S/D MINGGU LALU MINGGU INI S/D MINGGU PERSENTASE TERTIMBANG
(%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13
RENCANA REALISASI
NO. URAIAN PEKERJAAN SATUAN VOLUME BOBOT S/D MINGGU LALU MINGGU INI S/D MINGGU PERSENTASE TERTIMBANG
(%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13
RENCANA REALISASI
NO. URAIAN PEKERJAAN SATUAN VOLUME BOBOT S/D MINGGU LALU MINGGU INI S/D MINGGU PERSENTASE TERTIMBANG
(%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13
RENCANA REALISASI
NO. URAIAN PEKERJAAN SATUAN VOLUME BOBOT S/D MINGGU LALU MINGGU INI S/D MINGGU PERSENTASE TERTIMBANG
(%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13
RENCANA REALISASI
NO. URAIAN PEKERJAAN SATUAN VOLUME BOBOT S/D MINGGU LALU MINGGU INI S/D MINGGU PERSENTASE TERTIMBANG
(%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13
RENCANA REALISASI
NO. URAIAN PEKERJAAN SATUAN VOLUME BOBOT S/D MINGGU LALU MINGGU INI S/D MINGGU PERSENTASE TERTIMBANG
(%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13
RENCANA REALISASI
NO. URAIAN PEKERJAAN SATUAN VOLUME BOBOT S/D MINGGU LALU MINGGU INI S/D MINGGU PERSENTASE TERTIMBANG
(%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13
RENCANA REALISASI
NO. URAIAN PEKERJAAN SATUAN VOLUME BOBOT S/D MINGGU LALU MINGGU INI S/D MINGGU PERSENTASE TERTIMBANG
(%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13
RENCANA REALISASI
NO. URAIAN PEKERJAAN SATUAN VOLUME BOBOT S/D MINGGU LALU MINGGU INI S/D MINGGU PERSENTASE TERTIMBANG
(%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13
RENCANA REALISASI
NO. URAIAN PEKERJAAN SATUAN VOLUME BOBOT S/D MINGGU LALU MINGGU INI S/D MINGGU PERSENTASE TERTIMBANG
(%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13
TOTAL
URAIAN PEKERJAAN
BARANG /
DN LN Ribu % GABUNGAN
JASA
Rp. KDN
1 2 3 4 5 6 7
BARANG
1. Pasir
2. Batu Pecah
3. Semen PC
4. Tanah
5. Besi Tulangan
6. Kawat Ikat
7. Papan Mal
8. Paku
9. Kusen Alumunium
JASA
I. Manajemen Proyek dan Perekayasaan 0.00 0.00 0.00 0.00 0.00 0.00
II. Alat Kerja / Fasilitas Kerja 0.00 0.00 0.00 0.00 0.00 0.00
III. Konstruksi dan Fabrikasi 0.00 0.00 0.00 0.00 0.00 0.00
HERIANTO GANI
Direktur
REKAPITULASI PERHITUNGAN KOMPONEN DALAM NEGERI ( TKDN )
TOTAL
URAIAN PEKERJAAN
BARANG /
DN LN Ribu % GABUNGAN
JASA
Rp. KDN
1 2 3 4 5 6 7
BARANG
1. Pasir
2. Batu Pecah
3. Semen PC
4. Tanah
5. Besi Tulangan
6. Kawat Ikat
7. Papan Mal
8. Paku
9. Kusen Alumunium
JASA
I. Manajemen Proyek dan Perekayasaan 0.00 0.00 0.00 0.00 0.00 0.00
II. Alat Kerja / Fasilitas Kerja - 0.00 0.00 0.00 0.00 0.00
III. Konstruksi dan Fabrikasi 0.00 0.00 0.00 0.00 0.00 0.00
HERIANTO GANI
Direktur
LAPORAN KEMAJUAN FISIK MINGGUAN
RENCANA REALISASI
NO. URAIAN PEKERJAAN SATUAN VOLUME BOBOT S/D MINGGU LALU MINGGU INI S/D MINGGU PERSENTASE TERTIMBANG
(%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13
RENCANA REALISASI
NO. URAIAN PEKERJAAN SATUAN VOLUME BOBOT S/D MINGGU LALU MINGGU INI S/D MINGGU PERSENTASE TERTIMBANG
(%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13
RENCANA REALISASI
NO. URAIAN PEKERJAAN SATUAN VOLUME BOBOT S/D MINGGU LALU MINGGU INI S/D MINGGU PERSENTASE TERTIMBANG
(%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13
RENCANA REALISASI
NO. URAIAN PEKERJAAN SATUAN VOLUME BOBOT S/D MINGGU LALU MINGGU INI S/D MINGGU PERSENTASE TERTIMBANG
(%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13
RENCANA REALISASI
NO. URAIAN PEKERJAAN SATUAN VOLUME BOBOT S/D MINGGU LALU MINGGU INI S/D MINGGU PERSENTASE TERTIMBANG
(%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13
RENCANA REALISASI
NO. URAIAN PEKERJAAN SATUAN VOLUME BOBOT S/D MINGGU LALU MINGGU INI S/D MINGGU PERSENTASE TERTIMBANG
(%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13
RENCANA REALISASI
NO. URAIAN PEKERJAAN SATUAN VOLUME BOBOT S/D MINGGU LALU MINGGU INI S/D MINGGU PERSENTASE TERTIMBANG
(%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13
RENCANA REALISASI
NO. URAIAN PEKERJAAN SATUAN VOLUME BOBOT S/D MINGGU LALU MINGGU INI S/D MINGGU PERSENTASE TERTIMBANG
(%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT (%) (%)
1 2 3 4 5 6 7 8 9 10 11 12 13
BULAN
BOBOT
NO. URAIAN PEKERJAAN KETERANGAN
(%) MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU
KE - 1 KE - 2 KE - 3 KE - 4 KE - 5 KE - 6 KE - 7 KE - 8 KE - 9 KE - 10 KE - 11 KE - 12 KE - 13 KE - 14 KE - 15 KE - 16 KE - 17 KE - 18 KE - 19 KE - 20 KE - 21 KE - 22 KE - 23 KE - 24
7.5
Khatulistiwa + Sirtu
100
1. Pekerjaan Persiapan 1.25 0.62 0.62
90
2. Pekerjaan Tanah 11.78 0.79 0.79 0.79 0.79 0.79 0.79 0.79 0.79 0.79 0.79 0.79 0.79 0.79 0.79 0.79
80
3. Pekerjaan Beton 21.00 1.05 1.05 1.05 1.05 1.05 1.05 1.05 1.05 1.05 1.05 1.05 1.05 1.05 1.05 1.05 1.05 1.05 1.05 1.05 1.05
70
4. Pekerjaan Pasangan 5.31 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35
60
50
40
1. Urugan Tanah Pilihan Dengan Alat Berat 42.21 2.48 2.48 2.48 2.48 2.48 2.48 2.48 2.48 2.48 2.48 2.48 2.48 2.48 2.48 2.48 2.48 2.48 20
2. Tanam Rumput Klekep 8.37 1.20 1.20 1.20 1.20 1.20 1.20 1.20 10
3. Parit Pasangan 60 x 60 x 40 cm 10.07 1.01 1.01 1.01 1.01 1.01 1.01 1.01 1.01 1.01 1.01 0
JUMLAH 100.00
RENCANA MINGGUAN (%) 1.63 4.12 4.28 4.63 5.68 5.68 5.68 5.68 5.68 5.68 4.67 4.67 4.67 4.67 4.67 4.67 4.67 5.08 2.25 2.25 2.25 2.25 2.25 2.25
KUMULATIF RENCANA MINGGUAN (%) 1.63 5.75 10.02 14.65 20.33 26.01 31.69 37.37 43.05 48.73 53.41 58.08 62.75 67.43 72.10 76.77 81.44 86.53 88.77 91.02 93.26 95.51 97.75 100.00
REALISASI MINGGUAN (%) 8.84 9.67 8.96 8.72 5.81 1.89 2.52 1.64 7.84 8.70 6.96 6.09 5.22 4.35 3.93 0.25 0.25 1.20 1.20 1.20 1.20 1.20 2.39
KUMULATIF REALISASI MINGGUAN (%) 8.84 18.50 27.46 36.18 41.99 43.88 46.40 48.04 55.88 64.58 71.54 77.63 82.85 87.20 91.13 91.38 91.63 92.83 94.02 95.22 96.41 97.61 100.00 100.00 #REF!
DEVIASI (%) 7.21 12.76 17.44 21.53 21.66 17.87 14.71 10.66 12.82 15.84 18.13 19.55 20.10 19.77 19.03 14.61 10.19 6.30 5.25 4.20 3.15 2.10 2.25 -
KET : REALISASI
RENCANA