2
UJI KOMPETENSI KEAHLIAN
TAHUN PELAJARAN 2018/2019
I. PETUNJUK UMUM
Nama
No. Spesifikasi Minimal
Alat/Komponen/Bahan
1 2 3
Alat
1. Tang kombinasi 4”
2. Tang pemotong 4”
3. Tang pengupas kabel 0.75 – 4 mm
4. Tang lancip 4“
5. Obeng (+) 4 mm x 4 “
6. Obeng (-) 4 mm x 4 “
7. Pisau cutter Standar
8. Test pen 0 – 500 V
9. Crimping 0.75 – 4 mm2
10. Bor listrik 10 mm-220 V/Hz
11. Multimeter /AVO meter Analog/Digital/0 – 1000 V
12. Tang Ampere Analog/Digital 0–6A
13. Megger Analog/Digital1000 v
14. Gergaji besi Standar
15. Palu besi ½ kg
16. Freet bor/jara Standar
17. Meteran 1m
Komponen
Bahan
1. Kabel NYA 1.5 mm Merah
2. Kabel NYA 1.5 mm Biru
3. Kabel NYA 1.5 mm Kuning strip hijau
4. Pipa PVC 20 mm
5 Stopper TR 10
6 Rel MCB TR 10
7 Separator TR10
8 Klem pipa PVC 20 mm
9 Skrup kayu ½“
10 Skrup kayu ¾“
11 Kabel Ties 10 mm
12 Terminal elemen TR 10
13 Isolasi Band Standar
III. SOAL/TUGAS
Judul Tugas : Instalasi Penerangan satu Fasa, dan Instalasi Tenaga tiga Fasa
Buatlah instalasi panel kontrol motor listrik 3 fasa dengan starting bintang segitiga
otomatis dan instalasi penerangan dengan ketentuan sebagai berikut :
1. Kontrol motor listrik 3 fasa dengan starting bintang–segitiga (star – delta) dengan
cara otomatis menggunakan kontaktor magnet dan Time Delay Relay.
2. Instalasi penerangan 3 ruangan pada sebuah gudang yang hannya dapat dimasuki
dari satu sisi dan letaknya berurutan :
a. S1 dan L1 terletak pada ruang 1, S2 dan L2 terletak pada ruang 2, S3 dan L3
pada ruang 3.
b. L1 menyala apabila S1 pada posisi ON dan S2 pada posisi 1.Posisi S3
sembarang. Pada kondisi ini L2 dan L3 dalam keadaan mati.
F0 F1 F2 F3 F4
100 mm
520 mm
100 mm
K1 K2 K3
F5
55 mm
50 mm
X1 X2
320 mm
H1 H2 H3
EMERGENCY PUSHBUTTON