PROJECT : PEKERJAAN RUMAH BELAJAR QURAN TBQ SYANAYYA
PEKERJAAN : PERSIAPAN, STRUKTUR, ARSITEK, DAN MEP LOKASI : Depok PEMILIK RUMAH (OWNER) : TBQ Syanayya TAHUN ANGGARAN : 2021
HARGA SAT JML HARGA
URAIAN PEKERJAAN SAT VOL (Rp) (Rp) I. PEKERJAAN PERSIAPAN 1 Uitzet dan Bowplank titik 15.00 Rp 115,942.50 Rp 1,739,137.50 2 Pembersihan Lapangan m2 55.00 Rp 14,600.00 Rp 803,000.00 3 Listrik dan Air Kerja Ls 1.00 Rp 2,000,000.00 Rp 2,000,000.00 SUBTOTAL Rp 4,542,137.50
II. PEKERJAAN TANAH
1 Galian tanah pondasi PC-1 60 x 60 x 30 cm (Kolom Pilar) m3 1.92 Rp 94,000.00 Rp 180,480.00 2 Galian tanah pondasi batu kali m3 50.00 Rp 94,000.00 Rp 4,700,000.00 3 Galian Sloof S1 15x20 m3 1.88 Rp 94,000.00 Rp 176,250.00 4 Galian tanah pondasi talud batu kali m3 38.50 Rp 94,000.00 Rp 3,619,000.00 5 Urugan Pasir Padat Bawah Pondasi PC-1 Tbl. 10 cm m3 0.19 Rp 270,700.00 Rp 51,974.40 6 Urugan Pasir Padat Bawah Pondasi Batu Kali m3 5.00 Rp 270,700.00 Rp 1,353,500.00 7 Urugan Pasir Padat Bawah Pondasi Talud m3 1.65 Rp 270,700.00 Rp 446,655.00 8 Urugan tanah kembali m3 16.14 Rp 68,000.00 Rp 1,097,418.00 9 Urugan tanah peninggian m3 71.50 Rp 92,600.00 Rp 6,620,900.00 SUBTOTAL Rp 18,246,177.40
III. PEKERJAAN PONDASI
1 Lantai Kerja PC-1 60 x 60 x 30 Tbl. 5 cm, fc = 7.4 Mpa m3 0.05 Rp 844,575.00 Rp 45,607.05 2 Pondasi Batu Kali m3 25.00 Rp 1,042,267.50 Rp 26,056,687.50 3 Talud Dinding Batu Kali m3 27.50 Rp 1,042,267.50 Rp 28,662,356.25 4 Beton Pile Cap PC-1 60 x 60 x 30 cm - Beton K-200 m3 0.32 Rp 1,042,025.50 Rp 337,616.26 - Pembesian kg 38.87 Rp 16,045.38 Rp 623,699.77 - Bekisting m2 4.50 Rp 77,455.63 Rp 348,550.31 5 Sloof S1 15x20 cm - Beton K-200 m3 1.88 Rp 1,042,025.50 Rp 1,953,797.81 - Pembesian kg 153.61 Rp 16,045.38 Rp 2,464,747.88 - Bekisting m2 37.50 Rp 83,690.00 Rp 3,138,375.00 SUBTOTAL Rp 63,631,437.84 IV. PEKERJAAN STRUKTUR 4.1 STRUKTUR LT. 1 (Elv. + 0.000) 1 Kolom K1 diameter 30 cm (Koridor) - Beton K-200 m3 0.74 Rp 1,042,025.50 Rp 773,000.57 - Pembesian kg 92.73 Rp 16,045.38 Rp 1,487,857.54 - Bekisting m2 8.40 Rp 130,152.50 Rp 1,093,281.00 2 Kolom K2 20x20 cm - Beton K-200 m3 0.60 Rp 1,042,025.50 Rp 625,215.30 - Pembesian kg 75.00 Rp 16,045.38 Rp 1,203,403.13 - Bekisting m2 6.00 Rp 130,152.50 Rp 780,915.00 3 Kolom KP 12 x 12 cm m1 52.50 Rp 104,785.50 Rp 5,501,238.75 4 Balok Latei 12 x 12 cm m1 13.50 Rp 129,422.63 Rp 1,747,205.44 SUBTOTAL Rp 13,212,116.72 4.2 STRUKTUR ATAP (Elv. + 4.000) 1 Balok B1 20 x 40 - Beton K-200 m3 1.20 Rp 1,042,025.50 Rp 1,250,430.60 - Pembesian kg 180.00 Rp 16,045.38 Rp 2,888,167.50 - Bekisting m2 15.00 Rp 143,688.75 Rp 2,155,331.25 2 Balok Balok Ring Dinding 12 x 20 - Beton K-200 m3 1.88 Rp 1,042,025.50 Rp 1,953,797.81 - Pembesian kg 281.25 Rp 16,045.38 Rp 4,512,761.72 - Bekisting m2 40.63 Rp 143,688.75 Rp 5,837,355.47 3 Rangka baja ringan profil C 75.35.0,75 mm m2 156.00 Rp 148,170.00 Rp 23,114,520.00 4 Penutup Atap UPVC Rooftop m2 156.00 Rp 180,775.00 Rp 28,200,900.00 5 Penutup Sisi Atap GRC m2 20.50 Rp 126,332.50 Rp 2,589,816.25 SUBTOTAL Rp 72,503,080.60 HARGA SAT JML HARGA URAIAN PEKERJAAN SAT VOL (Rp) (Rp) V. PEKERJAAN ARSITEKTUR 5.1 PEKERJAAN PASANGAN DINDING 1 Pas. Dinding Bata Merah Area Bangunan m2 160.10 Rp 126,397.95 Rp 20,236,311.80 2 Pas. Dinding Bata Merah Area Talud m2 9.38 Rp 126,397.95 Rp 1,185,612.77 3 Plester Dinding Area Bangunan m2 320.20 Rp 80,907.20 Rp 25,906,485.44 4 Acian Dinding Lt.1 dan Lt. 2 m2 320.20 Rp 68,003.75 Rp 21,774,800.75 5 Benangan (Rong Pintu & Jendela ) m' 57.00 Rp 29,789.50 Rp 1,698,001.50 SUBTOTAL Rp 70,801,212.26 5.2 PEKERJAAN PENGECATAN 1 Cat Dinding Interior m2 219.70 Rp 36,713.00 Rp 8,065,846.10 2 Cat Dinding Eksterior m2 100.50 Rp 49,943.00 Rp 5,019,271.50 3 Cat Plafond m2 165.00 Rp 25,921.50 Rp 4,277,047.50 SUBTOTAL Rp 17,362,165.10 5.3 PEKERJAAN PLAFOND 1 Plafond Gypsumboard 9 mm m2 55.00 Rp 139,015.00 Rp 7,645,825.00 2 Palfond Kalsieboard 4 mm m2 91.00 Rp 149,275.00 Rp 13,584,025.00 3 List Plafond m1 102.00 Rp 22,075.00 Rp 2,251,650.00 SUBTOTAL Rp 23,481,500.00 5.4 PEKERJAAN LANTAI KERAMIK 1 Keramik Lantai 40 x 40 Granite Tile m2 131.00 Rp 259,325.00 Rp 33,971,575.00 2 Keramik Lantai Kamar Mandi 40 x 40 Kasar m2 12.00 Rp 259,325.00 Rp 3,111,900.00 3 Keramik Dinding Kamar Mandi 40 x 40 m2 31.50 Rp 259,325.00 Rp 8,168,737.50 SUBTOTAL Rp 45,252,212.50 VI. PEKERJAAN KUSEN PINTU DAN JENDELA 6.1 PEKERJAAN KUSEN PINTU DAN JENDELA 1 Kusen Pintu P1 (Depan) unit 3.00 Rp 3,800,000.00 Rp 11,400,000.00 2 Kusen Pintu P2 (Toilet) unit 3.00 Rp 1,200,000.00 Rp 3,600,000.00 3 Kusen Jendela J1 (Depan) unit 3.00 Rp 2,000,000.00 Rp 6,000,000.00 4 Glassbox unit 6.00 Rp 250,000.00 Rp 1,500,000.00 5 Jalusi unit 3.00 Rp 350,000.00 Rp 1,050,000.00 SUBTOTAL Rp 23,550,000.00 VII. PEKERJAAN MEKANIKAL, ELEKTRIKAL, DAN PLUMBING 7.1 PEKERJAAN INSTALASI LISTRIK LT. 1 1 Instalasi Lampu titik 10.00 Rp 192,125.00 Rp 1,921,250.00 2 Instalasi Stop Kontak titik 6.00 Rp 222,125.00 Rp 1,332,750.00 3 Pemasangan MCB titik 2.00 Rp 470,800.00 Rp 941,600.00 4 Pemasangan Lampu Downlight LED 12 watt titik 7.00 Rp 79,750.00 Rp 558,250.00 5 Pemasangan Lampu Downlight LED 9 watt titik 3.00 Rp 53,500.00 Rp 160,500.00 6 Pemasangan Saklar Ganda titik 4.00 Rp 29,700.00 Rp 118,800.00 7 Pemasangan Stop Kontak Dinding titik 6.00 Rp 31,350.00 Rp 188,100.00 SUBTOTAL Rp 5,221,250.00 7.2 PEKERJAAN SANITASI AIR BERSIH, BEKAS, dan KOTOR 1 Pipa Air Bersih dia. 3/4" m1 20.00 Rp 138,154.50 Rp 2,763,090.00 2 Pipa Kotoran dia. 4" m1 25.00 Rp 127,520.25 Rp 3,188,006.25 3 Pipa Air Hujan dia. 4" m1 12.00 Rp 127,520.25 Rp 1,530,243.00 4 Kloset Duduk unit 3.00 Rp 4,125,110.00 Rp 12,375,330.00 5 Jet Washer unit 3.00 Rp 497,590.50 Rp 1,492,771.50 6 Kran Air unit 3.00 Rp 172,755.00 Rp 518,265.00 7 Avour unit 3.00 Rp 156,255.00 Rp 468,765.00 8 Wastafel unit 3.00 Rp 2,270,664.00 Rp 6,811,992.00 9 Shower unit 3.00 Rp 1,758,350.00 Rp 5,275,050.00 10 Biotank Kapasitas 1000 m3 unit 1.00 Rp 3,000,000.00 Rp 3,000,000.00 SUBTOTAL Rp 37,423,512.75