NO URAIAN PEKERJAAN VOLUME SATUAN H.SATUAN JML.HARGA
I PERSIAPAN 1 Survei lokasi 1.00 ls 2 Akomodasi manpower 1.00 ls
3 Safety, Health, and Welfare 1.00 ls
4 Supervisi dan Dokumentasi 1.00 ls 5 Eguipment dan perlengkapan 1.00 ls Sub total
II Perbaikan Lantai Laborat
1 Pembersihan/grinding 250.00 m2 2 Primer, body coates 250.00 m2 3 Sika light grey 250.00 m2 4 Epoxy Coating 250.00 m2 5 Mastertop1210 t = 1.000 micron 6 Coving r 5 128, 51 m2 7 Consumable material 1.00 ls 8 Pembersihan area 1.00 ls Sub total III Jumlah Total I s/d II