RENCANA ANGGARAN PEMBUATAN PINTU HANDERSON GUDANG PALIMANAN

Harga
No Uraian Volume Satuan Total Harga
Satuan

A Pekerjaan Persipaan
1 Mobilisasi 1 Ls 1,000,000 1,000,000

B Pembuatan Pintu Gudang Tyoe Handerson p= 5.5 , t=4.2 @3


1 Besi Hollow 60x40x1.6 48 btg 413,125 19,830,000
2 Besi Plat Tebal 2mm 18 Lembar 1,013,333 18,240,000
3 Dudukan Rel Atas UNP 100x50x2.9mm 6 Btg 809,000 4,854,000
4 Besi Siku Cremona 9 Btg 227,500 2,047,500
4 Rel Atas 33 m 389,364 12,849,000
5 Rel bawah 33 m 137,000 4,521,000
6 Roda Rel Atas 18 Unit 82,000 1,476,000
7 Roda Rel Bawah 18 Unit 47,000 846,000
8 Engsel 63 Unit 57,000 3,591,000
9 Wiremesh 24.75 m2 130,000 3,217,500
10 Slot Grendel Atas Bawah 12 pcs 85,000 1,020,000
11 Pengecetan 138.6 m2 70,000 9,702,000

C Pembuatan Pintu Gudang Tyoe Handerson p= 5.7 , t=4.2 @1


1 Besi Hollow 60x40x1.6 18 btg 413,125 7,436,250
2 Besi Plat Tebal 2mm 6.5 Lembar 1,013,333 6,586,667
3 Dudukan Rel Atas UNP 100x50x2.9mm 2.5 Btg 809,000 2,022,500
4 Besi Siku Cremona 3.5 Btg 227,500 796,250
4 Rel Atas 12 m 389,364 4,672,364
5 Rel bawah 12 m 137,000 1,644,000
6 Roda Rel Atas 6 Unit 82,000 492,000
7 Roda Rel Bawah 6 Unit 47,000 282,000
8 Engsel 21 Unit 57,000 1,197,000
9 Wiremesh 8.55 m2 130,000 1,111,500
10 Slot Grendel Atas Bawah 4 pcs 85,000 340,000
11 Pengecetan 47.88 m2 70,000 3,351,600
Total 113,126,130

Cirebon, 01 November 2021

Maulana