Anda di halaman 1dari 1

REKAPITULASI FINAL QIANTITY

ALTERNATIF, 1 (BALANCE BUDGET)

Nama Paket : Rekonsrtuksi Jalan Bukit Kaba


Prov / Kab : Bengkulu / Rejang Lebong
Sumber Dana : APBD PROVINSI BENGKULU
No. Kontrak : 602.1/20.180/IX/G.IV-DPU-TR/2021
Tgl. Kontrak : 6 September 2021
Nilai Kontrak : Rp 1,839,605,276.07
Kontraktor : CV. PERI BROTHERS
Konsultan : CV.GENIUS ENGINEERING CONS
VOLUME JUMLAH HARGA ( Rp ) TAMBAH / KURANG
NO MATA SATUA HARGA SATUAN
JENIS PEKERJAAN VOLUME (+) (-)
PEMBAYARAN N ( Rp )
KONTRAK FILD ENGINEEER KONTRAK FILD ENGINEEER
TAMBAH KURANG ( Rp ) ( Rp )
a b c d e f g=(dxf) h=(exf) i=(e-d) j=(d-c) k = (h-g) l=(g-h)
DIVISI. I U M U M
1.2 Mobilisasi Ls 1.00 1.00 46,920,000.00 46,920,000.00 46,920,000.00 - - - -
1.8.(1) Manajemen dan Keselamatan Lalu Lintas Ls 1.00 1.00 10,800,000.00 10,800,000.00 10,800,000.00 - - - -
1.119 Keselamatan kerja Ls 1.00 1.00 27,390,000.00 27,390,000.00 27,390,000.00 - - - -
1.21 Manajemen Mutu (Quality dan Quantity Control) Ls 1.00 1.00 15,183,333.33 15,183,333.33 15,183,333.33 - - - -
100,293,333.33 100,293,333.33
DIVISI. II DRAINASE 0.36
2.1 Pek. Galian untuk Selokan Drainase dan Sal. Air M3 112.00 53.70 33,774.97 3,782,796.21 1,813,558.60 - 58.30 - 1,969,237.61
2.2 Pasangan Batu dengan Mortar M3 18.62 20.48 727,575.16 13,547,449.54 14,897,101.47 1.86 - 1,349,651.93 -
0.49 0.18 17,330,245.75 16,710,660.06
DIVISI . III PEKERJAAN TANAH
3.1.(8) Galian Perkerasan berbutir M3 198.000 194.24 78,815.90 15,605,548.33 15,308,885.28 - 3.76 - 296,663.05
3.2.(2a) Timbunan Pilihan dari sumber galian M3 90.000 90.62 237,427.83 21,368,504.36 21,515,071.52 0.62 - 146,567.16 -
3.3.(1) Penyiapan Badan Jalan M3 3,465.00 1,649.03 7,829.77 27,130,156.97 12,911,515.74 - 1,815.97 - 14,218,641.23
472.60 64,104,209.66 34,426,587.27

DIVISI. V.PERKERASAN BERBUTIR


5.1(1) Lapis Pondasi Agregat Klas. A M3 519.75 547.14 590,396.28 306,858,464.69 323,028,311.71 27.39 - 16,169,847.02 -
5.1(2) Lapis Pondasi Agregat Klas. B M3 72.00 72.07 547,536.90 39,422,656.73 39,460,676.32 0.07 - 38,019.59 -
346,281,121.41 362,488,988.03
DIVISI. VI. PEKERJAAN ASPAL
6.1 (1)(a) Lapis Resap Pengikat - Aspal Cair Ltr 3,465.00 3,590.00 11,979.86 41,510,219.45 43,007,702.11 125.00 - 1,497,482.66 -
6.1 (1)(b) Lapis Resap Pengikat - Aspal Emulsi Ltr 1,039.50 1,077.00 12,765.74 13,269,988.44 13,748,703.75 37.50 - 478,715.31 -
6.3(5a) Laston Lapis Aus (AC-WC) Ton 321.55 323.10 1,256,984.03 404,183,214.25 406,131,539.49 1.55 - 1,948,325.24 -
6.3(6a) Laston Lapis Antara (AC-BC) Ton 482.33 486.80 1,281,018.33 617,873,573.28 623,604,849.31 4.47 - 5,731,276.03 -
6.3.(8) Bahan anti pengelupasan Kg 127.33 131.80 53,302.50 6,787,007.33 7,025,205.09 4.47 - 238,197.77 -
#REF! 1,083,624,002.75 1,093,517,999.76
DIVISI 9. PEKERJAAN HARIAN & PEKERJAAN LAIN-LAIN
9.2.(1) Marka Jalan Termoplastik M2 277.20 261.41 219,103.61 60,735,519.90 57,276,421.70 - 15.79 - 3,459,098.20
60,735,519.90 57,276,421.70

SUB. TOTAL (A) 0.00 1,672,368,432.79 1,672,368,432.79 0.00 27,598,082.72 19,943,640.09


PAJAK PERTAMBAHAN NILAI (PPN) = 10 % X A 0.0000 167,236,843.28 167,236,843.28 0.00
TOTAL 1,839,605,276.07 1,839,605,276.07
Mengetahui Diperiksa Oleh 0.00
PEJABAT PELAKSANA TEKNIS KEGIATAN (PPTK) Konsultan Supervisi Kontraktor
Rekonsrtuksi Jalan Bukit Kaba CV.GENIUS ENGINEERING CONS CV. PERI BROTHERS

NURHIMAT, ST SUGIANTO
Nip. 19650411 1993 1 004 Supervision Engineer Direktur