Anda di halaman 1dari 1

FIELD ENGINEERING

NO DESCRIPTIONS SAT. VOLUME HARGA SATUAN JUMLAH HARGA KET.

1 PEMBERSIHAN M3 137.710,95 15.730,00 2.166.193.243,50 HARGA SATUAN SETELAH DIMASUKKAN KE AHSP


2 GALIAN BIASA UNTUK TIMBUNAN M3 264.106,52 22.193,03 5.861.325.045,24 HARGA SATUAN SETELAH DIMASUKKAN KE AHSP
3 GALIAN BIASA PENGISI MEDIAN M3 2.313,36 22.193,03 51.340.477,72 HARGA SATUAN SETELAH DIMASUKKAN KE AHSP
4 GALIAN BIASA UNTUK DIBUANG M3 94.357,78 22.193,03 2.094.085.443,73 HARGA SATUAN SETELAH DIMASUKKAN KE AHSP
5 GALIAN BATU LUNAK M3 220.592,21 39.562,91 8.727.269.889,17 HARGA SATUAN SETELAH DIMASUKKAN KE AHSP
6 GALIAN BATU M3 34.594,78 41.964,44 1.451.750.702,57 HARGA SATUAN SETELAH DIMASUKKAN KE AHSP
7 COMMON EMBANKMENT M3 351.068,51 43.870,00 15.401.375.533,70 HARGA SATUAN SETELAH DIMASUKKAN KE AHSP
TOTAL : 35.753.340.335,62
PPN 10% : 3.575.334.033,56
GRAND TOTAL : 39.328.674.369,19

INFO :
A PERSENTASE PENAWARAN = 83,505% = 39.328.674.369,187
B ASUMSI PENAWARAN = 98,500% = 46.390.987.397,975
C SELISIH = 14,995% = 7.062.313.028,788

JADI SELISIH MAKSIMAL 14,995%

Anda mungkin juga menyukai