LEIGHTON GHP MINING PROJECT

RISK ASSESMENT REPORT


GHP MINING PROJECT
Job No./Name: ID-194 , GHP MINING PROJECT Assessor (s):
Doc. Ref.No: CORP-SAF-FM-003a(01)
Activity: PREPARE AND TOW UNIT DR 514 FROM MINE SITE TO W/SHOP / SIAPKAN DAN DEREK UNIT DR Assessment purpose /Tujuan pelaksanaan:
514 DARI TAMBANG KE W/SHOP Supplementary to method statement / Tambahan pada metoda kerja
Adverse Likelihood Severity Existing Control / Residual
People at risk / Cause to Adverse Effect
Job / Task / Pekerjaan Effect / Efek / Kemung- / Kepa- RFN Pengendalian yang Risk Assessment / Pelaksanaan
Yang berisiko / Sebab efek merugikan
merugikan kinan rahan ada LxS=
Dikerjakan hrs
sesuai intruksi
Persiapan Pekerja Pengawasan yg rendah Cedera Tidak perlu dibuatkan JSA
2 2 4 pengawas 1x2=2
Preparation Worker Poor supervision Injury No need JSA
Follow Supervisor
instruction
Dikerjakan hrs
sesuai intruksi
pengawas
Follow Supervisor
Terburu-buru instruction
Memposisikan D 10 R Very fast Cedera Pengawas harus Tidak perlu dibuatkan JSA
Operator 2 3 6 1x4=4
To fix position D 10 R Pengawasan yg rendah Injury ada ditempat No need JSA
Poor supervision Supervisor/foreman
must be standby
Radio komunikasi
Radio
communication
Dikerjakan hrs
Pasang wire sling ke D10R dan DR Terburu-buru
sesuai intruksi
514 Pekerja Very fast Cedera Tidak perlu dibuatkan JSA
2 3 6 pengawas 1x4=4
Put the wire sling to D10R and DR Helper Pengawasan yg rendah Injury No need JSA
Follow Supervisor
514 Poor supervision
instruction
Dikerjakan hrs
sesuai intruksi
pengawas
Pengawasan yg rendah Follow Supervisor
Poor supervision Cedera instruction
Menarik DR 514 ke w/shop Salah penanganan Injury Pengawas harus Perlu dibuatkan JSA
Operator 3 3 9 2x3=6
Tow DR 514 to W/shop Miss handle Mati ada ditempat Need JSA
Wire sling putus Death Supervisor/foreman
Wire sling break must be standby
Radio komunikasi
Radio
communication

Prepared by / Dipersiapkan oleh: Signature / Ttd.: ___________________ Approved by / Disetujui oleh : Jeremy allen Signature / Ttd. : _________________

Position /Jabatan: Date / Tgl.: ____________________ Position / Jabatan : Project Manager Date / Tgl.: ____________________

Likelihood/Kemungkinan Severity/ Keparahan Risk Factor Number (RFN)


1. Unlikely/improbable / Tak mungkin 1. Negligible / Dapat Abaikan 1-2: Trivial/Acceptable / Dapat diterima
2. Remote / Jauh 2. Slight / Kecil 3-5: Tolerable / dapat ditolerir  Prepare Job Safety Analysis when residual risk is equal to or greater than 6
3. Quite possible/occasional / Agak 3. Moderate / Cukup 6-9: Moderate / Acceptable with review / Siapkan Job Safety Analysis jika resiko sisa sama dengan atau lebih dari 6
mungkin 4. Critical/High / Kritis Dapat diterima dengan review
4. Likely/Probable / Mungkin 5. Catastrophic/very high / 10-15: Substantial
5. Very/probable / Sangat mungkin Bencana 16-25: Intolerable/Unacceptable / Tidak CORP-SAF-FM-003a (01)
dapat diterima