RENCANA ANGGARAN BIAYA 09/RAB/INFRA/KAL/X/2019

PEKERJAAN DUCTHING BETON KABEL PLN DAN BAK KONTROL SALURAN


HILAGO
BSB CITY

NO URAIAN PEKERJAAN VOLUME HARGA SATUAN TOTAL HARGA

A. PEKERJAAN DUCTHING BETON KABEL PLN uk 40/60


1 Pengukuran /Bouwplank 183.30 m1 2,500 458,250.00
2 Pasir Urug 6.35 m3 270,000 1,713,150.00
3 Beton K275 Tanpa Tulangan t.10cm 33.84 m3 2,500,000 84,600,000.00
4 Tutup Duching tulangan wiremesh t.15cm 12.69 m3 3,350,000 42,511,500.00
5 Triplek penutup sementara 43.00 lbr 65,000 2,795,000.00

B. PEKERJAAN LANTAI BETON


1 Urugan tanah dipadatkan 33.84 m3 20,000 676,800.00
2 Pasir Urug 8.46 m3 270,000 2,284,200.00
3 Rabat Beton 8.46 m3 900,000 7,614,000.00

C. PEKERJAAN BAK KONTROL


1 Pasangan batu kali 1:8 13.11 m3 550,000 7,210,500.00
2 Rabat beton T.10cm 0.32 m3 900,000 288,000.00
3 Tutup Main hole beton besi wiremesh 1.04 m3 3,350,000 3,484,000.00
4 Plesteran siar 32.00 m2 40,000 1,280,000.00

D. PEKERJAAN SIDE ENTRY PIT


1 Pembelian SEP 26.00 bh 450,000 11,700,000.00
2 Pemasangan SEP 26.00 bh 60,000 1,560,000.00
3 Pipa PVC D.4" Type D 26.00 bh 95,000 2,470,000.00

E. PEKERJAAN SALURAN TEMPORARY P=119m


1 Galian tanah saluran temporary 185.64 m3 35,000 6,497,400.00

177,142,800.00
177,143,000.00

Semarang, 23 Mei 2022


PT. KARYADEKA ALAM LESTARI

Disetujui : Diketahui : Dibuat Oleh :

Andy Iriawan M. Aryabhekti Wawan Susilo Suwondo Garit Dani


Direktur Assc. Direktur Mngr. Proyek Asc. Mngr. Proyek Estimator