Anda di halaman 1dari 89

STUDI PENDAHULUAN

PEMBANGUNAN GEDUNG STUDENT CENTER


UNIVERSITAS ISLAM NEGERI WALISONGO SEMARANG
MELALUI SBSN TAHUN 2022

KEMENTERIAN AGAMA RI
UNIVERSITAS ISLAM NEGERI WALISONGO SEMARANG
TAHUN 2024

1
DAFTAR ISI

DAFTAR ISI ..................................................................................................................


A. Pendahuluan ........................................................................................................ 4
B. Dasar Hukum ....................................................................................................... 6
C. Kebutuhan Pengembangan ................................................................................. 7
D. Keterlibatan Proyek dengan Tugas, Fungsi, dan Kewenangan Pemprakarsa
Proyek ........................................................................................................................ 8
E. Keterlibatan Tujuan Proyek dengan RPJMN, Renstra K/L, dari/atau Prioritas
Pembangunan ............................................................................................................ 8
F. Keterkaitan dengan RPJMN................................................................................. 9
G. Ruang Lingkup ..................................................................................................... 9
H. Indikasi Lokasi ................................................................................................... 10
I. Indikasi Biaya dan Potensi Pemanfaatan ........................................................... 11
J. Indikasi Manfaat dan Dampak Ekonomi/Sosial .................................................. 12
K. Indikasi Jadwal Implementasi .......................................................................... 144
L. LAMPIRAN-LAMPIRAN ................................................................................... 155
1. Profil UIN Walisongo ..................................................................................... 155
2. Denah Eksisting Kampus Uin Walisongo Semarang .................................... 377
3. Rekapitulasi Rencana Anggaran BIAYA (RAB) ............................................ 399
4. Gambar Perspektif Gedung Student center ................................................... 71
5. Siteplan Gedung Student center .................................................................... 74
6. Sertifikat Tanah............................................................................................... 79

2
STUDI PENDAHULUAN
PEMBANGUNAN GEDUNG STUDENT CENTER
UNIVERSITAS ISLAM NEGERI WALISONGO SEMARANG
MELALUI SBSN TAHUN 2024

1. JUDUL PROYEK
Proyek pembangunan ini bernama ”Pembangunan Gedung Student center
Universitas Islam Negeri Walisongo Semarang Melalui SBSN Tahun
Anggaran 2024”.
2. PEMRAKARSA
Kementerian : Kementerian Agama RI
Unit Eselon I : Direktorat Jenderal Pendidikan Islam
3. DURASI PELAKSANAAN
Pelaksanaan pekerjaan pembangunan Prasarana dan Sarana pada Universitas
Negeri Walisongo Semarang berdurasi selama 12 (dua belas) bulan.
4. LOKASI
Pekerjaan ini akan dilaksanakan di atas tanah milik Universitas Islam Negeri
Walisongo Semarang berlokasi di Jalan Prof. Dr. Hamka Km. 2-3 Ngaliyan
Semarang 50181.

3
A. Pendahuluan
Dalam rangka mewujudkan jargon “Indonesia Berpenghasilan Menengah-
Tinggi yang Sejahtera, Adil, dan Berkesinambungan”, presiden memberikan
arahan utama pembangunan nasional, yaitu: pembangunan SDM, pembangunan
infrastruktur, penyederhanaan regulasi, penyederhanaan birokrasi, dan
transformasi ekonomi. Kelima arahan tersebut diterjemahkan dalam tujuh agenda
pembangunan nasional, meliputi: (1) ketahanan ekonomi untuk pertumbuhan
berkualitas dan berkeadilan; (2) pengembangan wilayah untuk mengurangi
kesenjangan; (3) SDM berkualitas dan berdaya saing; (4) revolusi mental dan
pembangunan kebudayaan; (5) infrastruktur untuk ekonomi dan pelayanan dasar;
(6) lingkungan hidup, ketahanan bencana, dan perubahan iklim; dan (7) stabilitas
polhukhankam, dan transformasi pelayanan publik. SDM berkualitas dan berdaya
saing menjadi salah satu ujung tombak pembangunan nasional. Sebagaimana
diketahui SDM merupakan modal dasar dalam Sustainable Development Goals
(SDGs) yang menjadi acuan transformasi dunia menuju 2030.
Perguruan Tinggi merupakan produsen yang menghasilkan SDM yang
berkualitas dan berdaya saing. Oleh karena itu, pembangunan layanan pendidikan
perguruan tinggi perlu untuk terus ditingkatkan. Universitas Islam Negeri (UIN)
Walisongo Semarang sebagai Perguruan Tinggi Agama Islam juga selalu
berupaya meningkatkan layanan pendidikan dan kualitas lulusan. Senada dengan
visi Kementerian Agama “Terwujudnya Masyarakat Indonesia yang Taat
Beragama, Rukun, Cerdas, dan Sejahtera Lahir Batin dalam rangka Mewujudkan
Indonesia yang Berdaulat, Mandiri, dan Berkepribadian Berlandaskan Gotong
Royong”, salah satu misi dan tujuan UIN Walisongo Semarang adalah
menghasilkan lulusan yang memiliki kapasitas akademik, profesional, dan
berahlak al-karimah dengan menerapkan kesatuan ilmu pengetahuan.
Misi menghasilkan lulusan yang berkualitas dan berdaya saing ini didukung
dengan berbagai kebijakan dalam Renstra UIN Walisongo Semarang tahun 2020-
2024. Salah satu poin kebijakan tersebut yaitu pengembangan dalam bidang SDM
dan sarana prasarana melalui: (a) penciptaan sistem rekrutmen SDM yang
berkualitas, berintegritas, dan profesional; (b) penciptaan sistem pengembangan
kapasitas SDM yang berkesinambungan; (c) peningkatan sarana dan prasarana
penelitian, dan (d) penyediaan sarana prasarana yang stimulatif, memadai,

4
berkualitas, dan sesuai dengan kebutuhan civitas akademik dalam peningkatan
mutu akademik.
Sarana prasarana stimulatif yang mendukung optimalisasi Unit Kegiatan
Mahasiswa (UKM) sangat dibutuhkan dan urgen untuk dikembangkan. Melalui
UKM, mahasiswa dapat meningkatkan intelektualitas yang komprehensif, softskill,
dan membentuk pribadi yang unggul. Terlebih UIN Walisongo Semarang
mendapatkan penghargaan Diktis Tahun 2021 dalam kategori “PTKI dengan
Mahasiswa Berprestasi Internasional Terbanyak”. Prestasi mahasiswa ini tidak
semata didapat di dalam kelas, namun melalui kreativitas yang lahir dari UKM.
Menilik perannya yang fundamental, pengembangan sarana prasarana yang
mendukung optimalisasi kegiatan mahasiswa perlu untuk dilakukan. UIN
Walisongo memiliki 37 UKM dan Ormawa. Sayangnya, sarana-prasana UKM
tersebut belum memadai dan terintegrasi, tersebut di tiga tempat: Gazebo Racana
Kampus 2, Gedung 2 Lantai PKM Kampus 3, dan GOR Kampus 3. UKM yang
berada di Gedung PKM Kampus 3 saat ini sedang direlokasi karena proses
pembangunan gedung proyek Islamic Develompent Bank (IsDB).
Kondisi eksisting sarana prasana UKM tersebut mendesak UIN Walisongo
untuk melakukan pembangunan dan pengembangan Gedung Student center yang
menjadi pusat kegiatan mahasiswa. Gedung Student center menjadi sarana
prasarana yang dapat menstimulasi mahasiswa untuk semakin mengembangkan
potensi dirinya. Seperti yang diketahui Perguruan Tinggi memiliki fungsi vital yakni
produsen SDM dalam Pembangunan Nasional Berkelanjutan. Kehadiran Gedung
Student center terpusat dan terintegrasi dengan fasilitas yang lengkap menjadi
lahan subur pertumbuhan potensi civitas akademika di UIN Walisongo Semarang.
UIN Walisongo Semarang memiliki upaya yang kuat untuk dapat
membangun Gedung Student center sebagai media layanan dan pengembangan
potensi yang integratif bagi mahasiswa. Salah satunya dengan menyediakan
lahan siap bangun untuk Gedung Student center seluas 3.426 M2. Selain itu telah
dilakukan kajian dan perencanaan dengan membuat masterplan pembangunan
Gedung Student center secara matang. Gedung Student center dipersiapkan
dibangun dalam enam lantai dengan masing-masing lantai memiliki fungsi: (1)
lantai satu berfungsi sebagai media pengembangan akademik seperti pusat riset,
pusat studi, pusat scholarship, dan sebagainya; (2) lantai dua berfungsi sebagai
media pengembangan profesi mahasiswa seperti pusat training dan karir; (3) lantai

5
tiga berfungsi sebagai media pengembangan kewirausahaan seperti klinik bisnis
dan creative-hub; (4) lantai empat berfungsi media pengembangan kesehatan
mental dan well-being seperti mental health corner dan recreation space; (5) lantai
lima berfungsi sebagai media layanan (service center) seperti UKM corner, student
service, community service, dan sebagainya; dan (6) lantai enam berfungsi
sebagai media pengembangan sosial, seni, dan budaya seperti pusat moderasi
beragama, art and culture space, dan sebagainya. Selain dari segi fungsi,
pembangunan Gedung Student center juga dirancang dengan mengusung konsep
“Smart” dan “Green” sesuai distingsi UIN Walisongo Semarang.
Gedung Student center yang dirancang tersebut tidak hanya dapat
dimanfaatkan oleh mahasiswa namun juga oleh masyarakat umum.
Pembangunan dan pengembangan Gedung Student center mengusung model
inovasi Triple Helix yang menekankan keterikatan antara academic (universitas),
business (industri), dan government (pemerintah). Gedung Student center yang
dirancang dapat menstimulasi: (1) ketersediaan human capital yang berkualitas
dengan pengetahuan kewalisongoan, (2) inkubasi bisnis berbasis riset, (3)
ketersediaan teknologi dasar yang mengimplementasikan unity of sciences, dan
(4) ketersambungan antara civitas academica dengan stakeholder dan
masyarakat. Secara lebih luas, fungsi pembangunan Gedung Student center ini
selaras dengan visi Kementerian Agama yang ingin mewujudkan masyarakat taat
beragama dan berkualitas untuk Indonesia yang mandiri dan berdikari.
Menilik fungsi dan perannya yang begitu fundamental, pembangunan Gedung
Student center UIN Walisongo Semarang layak untuk diwujudkan melalui skema
pendanaan Surat Berharga Syariah Negara (SBSN). Sebagaimana diketahui
SBSN merupakan skema pendanaan yang digunakan untuk pembangunan
infrastruktur dan layanan publik dengan karakteristik mendukung kepentingan
strategis nasional. Pembangunan Gedung Student center UIN Walisongo
Semarang mendukung tercapainya SDM yang berkualitas dan berdaya saing yang
menjadi salah satu poin Pembangunan Strategis Nasional. Adapun anggaran yang
diajukan dalam Pembangunan Gedung Student center tersebut adalah Rp
48.174.959.000.,- (Empat puluh delapan miliyar seratus tujuh puluh empat juta
Sembilan ratus lima putuh Sembilan ribu rupiah)

B. Dasar Hukum
1. Undang-undang Nomor 17 Tahun 2013 Tentang Keuangan Negara;
2. Undang-undang Nomor 25 Tahun 2014 Tentang Sistem Perencanaan
Pembangunan Nasional;

6
3. Undang-undang Nomor 17 Tahun 2007 Tentang RPJPN 2005-2025
4. Peraturan Presiden Nomor 2 Tahun 2015 tentang RPJMN 2015-2019;
5. Peraturan Menteri Pekerjaan Umum Nomor 45/PRT/M/2007 tentang
Pedoman Teknis Pembangunan Gedung Negara;
6. Peraturan Presiden Nomor 130 Tahun 2014 tentang Perubahan Status IAIN
Walisongo Menjadi UIN Walisongo Semarang;
7. Peraturan Menteri Agama Republik Indonesia Nomor 54 Tahun 2015
Tentang Organisasi dan Tata Kerja Universitas Islam Negeri Walisongo
Semarang;
8. Peraturan Menteri Agama Republik Indonesia Nomor 57 Tahun 2015 tentang
Statuta Universitas Islam Negeri Walisongo Semarang;
9. Keputusan Direktur Jenderal Pendidikan Islam Nomor 1741 tahun 2013
tentang Penetapan Pedoman Umum Organisasi Kemahasiswaan PTAI.

C. Kebutuhan Pengembangan
Setelah mengalami transformasi dari IAIN menjadi universitas, Universitas
Islam Negeri Walisongo Semarang mengalami perkembangan pesat.
Perkembangan pesat terlihat dari banyaknya penambahan fakultas, program
studi, lembaga, dan unit pendukung baru. Bersamaan dengan transformasi
tersebut jumlah mahasiswa juga semakin meningkat dari tahun ke tahun.
Perkembangan yang signifikan ini perlu untuk mendapatkan pembangunan sarana
prasarana yang memadai.
Salah satunya yang sangat dibutuhkan UIN Walisongo Semarang adalah
Gedung Student center. Seperti yang telah dipaparkan dalam pendahuluan yang
juga telah mendeskripsikan analisis kebutuhan, pergerakan kegiatan mahasiswa
di UIN Walisongo Semarang begitu pesat. Bahkan UIN Walisongo Semarang
mendapatkan Apresiasi Diktis 2021 dalam bidang “PTKI dengan Mahasiswa
Berprestasi Internasional Terbanyak”. Prestasi ini layaknya didukung dengan
sarana prasarana yang menunjang dan menstimulasi potensi mahasiswa.
Pengembangan Gedung Student center bukan sekadar memfasilitasi
mahasiswa dalam mengembangkan potensi dirinya, namun menjadi sarana yang
menyambungkan antara academic (universitas), business (industri/masyarakat),
dan goverment (pemerintah). Seperti diketahui tiga komponen ini menjadi pilar
dalam pembangunan nasional suatu negara. Dibutuhkan pengembangan Gedung

7
Student center yang memiliki fungsi: (1) media pengembangan akademik, (2)
media pengembangan profesi dan karir, (3) media pengembangan
kewirausahaan, (4) media pengembangan kesehatan mental, (5) media layanan
mahasiswa dan masyarakat, dan (6) media pengembangan sosial. Berdasarkan
fungsi tersebut, dibutuhkan pengembangan Gedung Student center dalam enam
lantai dengan ruang indoor dan outdoor yang mengusung konsep “Smart” dan
“Green” sesuai distingsi UIN Walisongo Semarang.
D. Keterlibatan Proyek dengan Tugas, Fungsi, dan Kewenangan Pemprakarsa
Proyek
Sebagai Perguruan Tinggi Agama Islam, UIN Walisongo Semarang memiliki
tugas melaksanakan penyelenggaraan pendidikan tinggi yang meliputi program
pendidikan akademik, vokasi dan/atau profesi, penelitian, dan pengabdian kepada
masyarakat dalam bidang ilmu pengetahuan dan teknologi, keagamaan Islam, dan
ilmu umum sesuai dengan ketentuan peraturan perundang-undangan.
Pembangunan Gedung Student center menjadi salah satu bentuk pelaksanaan
tugas, fungsi, dan wewenang UIN Walisongo Semarang untuk dapat menyediakan
layanan pendidikan tinggi yang berkualitas.
Sebagai upaya untuk menghasilkan lulusan yang berkualitas dan berdaya
saing, diperlukan pembangunan berbagai fasilitas, sarana, dan prasarana yang
mendukung. Pembangunan Gedung Student center yang representatif, tersentral,
dan terintegrasi dapat menstimulasi potensi mahasiswa, antara lain: media
penampung seluruh kegiatan mahasiswa yang terintegrasi, media penyaluran
bakat dan minat mahasiswa, dan media pengembangan softskill bagi mahasiswa.
Pelaksanaan pembangunan Gedung Student center ini sesuai dengan salah satu
poin kebijakan umum yang tertuang dalam Renstra UIN Walisongo Semarang
Tahun 2020-2024, yaitu: penyediaan sarana prasarana yang stimulatif, memadai,
berkualitas, dan sesuai dengan kebutuhan civitas akademik dalam peningkatan
mutu akademik.

E. Keterlibatan Tujuan Proyek dengan RPJMN, Renstra K/L, dari/atau Prioritas


Pembangunan
a. Tujuan
Tujuan yang hendak dicapai dari Pembangunan Gedung Student center
Universitas Islam Negeri Walisongo Semarang adalah:

8
1. Terwujudnya sarana Student center Universitas Islam Negeri Walisongo
Semarang yang memadai guna mendukung proses kegiatan mahasiswa
dalam mengimplementasikan unity of sciences.
2. Terwujudnya ekosistem yang inovatif bagi mahasiswa untuk
mengembangkan potensinya dalam bidang akademik, softskill, dan
keterampilan literasi era 4.0.
3. Terciptanya sistem integratif yang menghubungkan antara mahasiswa
dengan stakeholder sehingga dapat meningkatkan kualitas pendidikan,
sosial, dan ekonomi masyarakat.
4. Terciptanya lulusan UIN Walisongo yang berkualitas, berdaya saing, dan
memiliki akhlak al-karimah yang mendukung pembangunan nasional
menjadi Indonesia Mandiri dan Berdikari.
F. Keterkaitan dengan RPJMN
Pembangunan Gedung Student center UIN Walisongo Semarang
menjadi penyambung implementasi pembangunan SDM yang tertuang dalam
RPJMN 2020-2024 yaitu Meningkatkan Sumber Daya Manusia yang
Berkualitas dan Berdaya Saing. Adapun secara lebih rinci pembangunan
Gedung Student center UIN Walisongo Semarang mendukung RPJMN dalam
bidang:
1. Peningkatan kualitas pengajaran dan pembelajaran dengan penekanan
pada Science, Technology, Engineering, and Mathematics (STEM) dan
kemampuan literasi.
2. Pengembangan riset inovasi dan ekosistem inovasi.
G. Ruang Lingkup
Ruang lingkup kegiatan adalah :
1. Perencanaan dan Pengusulan Proyek Pembangunan
2. Pelaksanaan Proyek, meliputi :
a. Pembangunan Gedung Student center terdiri dari 6 lantai pada kampus III
Universitas Islam Negeri Walisongo Semarang.
b. Pengadaan meubelair dan kelengkapan Gedung Student center
Universitas Islam Negeri Walisongo Semarang.
3. Pengawasan dan pemantauan atas pelaksanaan proyek.
4. Pengelolaan obyek pembiayaan

9
H. Indikasi Lokasi
Universitas Islam Negeri Walisongo Semarang mempunyai 3 Lokasi, yakni
Kampus I, Kampus II dan Kampus III dengan luas tanah: 304.224 m2 dengan
denah sebagai berikut:

Adapun luas pemanfaatan tanah milik UIN Walisongo sekitar 8% dari total
luas tanah.

LUAS PEMANFAATAN TANAH


2% UIN WALISONGO SEMARANG

2%
4%

LUAS TANAH UIN


WALISONGO
KAMPUS I (Rektorat &
Pascasarjana)
KAMPUS II (FITK, FUH,
FPK)
KAMPUS III (FDKH,
FEBI, FSH, FISIP)

92%

10
Dari data di atas, menunjukkan bahwa Kampus III memiliki tanah yang paling
luas, dibandingkan dengan Kampus II dan Kampus I. Hal ini yang menjadi alasan,
rencana pembangunan Gedung Student center akan dibangun di Kampus III.
Selain itu juga, berdekatan dengan gedung-gedung yang digunakan sebagai
penunjang akademik mahasiswa. Seperti Gedung Serba Guna (GSG), Gedung
Aula Utama, General Library, ICT Center, Integrated Laboraroty, Planetarium dan
Observarotium. Dengan adanya Gedung Student center ini diharapkan dapat
mendukung dalam meningkatkan kualitas mahasiswa baik aspek akademik
maupun non akademik. Gedung Student center dengan4 lantai akan dibangun di
atas tanah seluas 1.714 m2 dengan luas total bangunan 3.426 m2 dan luas dasar
bangunan 912 m2.

Berikut ini lahan kosong luas yang rencana akan dibangun Gedung Student
center dengan mempertahankan Green sebagaimana yang diusung oleh UIN
Walisongo Semarang menuju World Class University berbasis Smart and Green.

I. Indikasi Biaya dan Potensi Pemanfaatan


1. Indikasi Biaya
Anggaran biaya yang diperlukan untuk Pembangunan Prasarana dan Sarana
Universitas Islam Negeri Walisongo Semarang tahun 2024 adalah sebesar Rp

11
48.174.959.000,- (Empat puluh delapan miliyar seratus tujuh puluh empat juta
Sembilan ratus lima putuh Sembilan ribu rupiah) terdiri dari:

A Biaya Konstruksi Pembangunan Rp. 43.324.959.000


Gedung

B Biaya Perencanaan Konstruksi Rp. 900.000.000

C Biaya Pengawasan Konstruksi Rp. 1.200.000.000

D Biaya Pengelola Kegiatan / AP Rp. 250.000.000

E Biaya Interior dan Furniture Rp. 2.500.000.000

Jumlah Total Rp. 48.174.959.000

Dibulatkan Rp. 48.174.959.000

Adapun pembiayaan program tersebut akan dibebankan pada Anggaran


SBSN tahun 2024.
2. Potensi pemanfaatan
a. Menunjang kegiatan-kegiatan mahasiswa di bidang akademik dan non-
akademik di tingkat universitas
b. Sebagai wadah kegiatan umum di universitas yang mewakili banyak
kepentingan dari berbagai pihak.

J. Indikasi Manfaat dan Dampak Ekonomi/Sosial


Adanya Gedung Student center akan memiliki dampak dan juga manfaat
bagi civitas akademik UIN Walisongo maupun masyarakat.
1. Output
a. Gedung Student center sebagai penunjang implementasi Tri Dharma
Perguruan Tinggi dengan memberikan fasilitas belajar, meneliti, dan
pengabdian kepada masyarakat.
b. Gedung Student center memberikan ruang untuk pengembangan minat
dan bakat mahasiswa dalam rangka meningkatkan rekognisi UIN
Walisongo melalui pencapaian prestasi mahasiswa di tingkat nasional
maupun internasional.
c. Gedung Student center memenuhi kebutuhan Universitas dalam hal
akademik maupun non akademik sehingga meningkatkan standar kualitas
dan akreditasi perguruan tinggi.

12
d. Gedung Student center meningkatkan peran UIN Walisongo dalam
perekonomian masyarakat dengan mengakomodasi pemasaran produk
lokal dan pengembangan UMKM.
e. Gedung Student center menyediakan layanan yang dapat diakses publik,
seperti wi-fi and literacy corner, training hall, dan ruang terbuka hijau.
f. Gedung Student center dapat bekerjasama dengan masyarakat untuk
menyelenggarakan beberapa kegiatan sosial budaya.
2. Outcome
a. Memberikan kemudahan akses layanan satu pintu untuk segala
kebutuhan akademik dan administrasi mahasiswa.
b. Meningkatkan kesiapan diri dan daya saing mahasiswa dalam
menghadapi tantangan dunia profesional.
c. Mengembangkan minat dan bakat mahasiswa melalui pengembangan
UKM dan fasilitas untuk pengembangan potensi dan kompetensi
mahasiswa.
d. Memberikan ruang dan kesempatan bagi mahasiswa dalam bidang bisnis
(entrepreneurship).
e. Memberikan fasilitas rekreasi mahasiswa yang dapat memberikan
suasana baru dan menunjang kesehatan mental.
3. Impact
a. Meningkatnya kualitas lulusan yang dihasilkan oleh Universitas Islam
Negeri Walisongo Semarang
b. Terbangunnya masyarakat yang berperadaban maju, berwawasan luas,
damai, sejahtera dan religius.
c. Meningkatnya ekonomi masyarakat Indonesia atas peran aktif para alumni
Universitas Islam Negeri Walisongo dalam membuka lapangan kerja dan
pemberdayaan masayarakat.

13
K. Indikasi Jadwal Implementasi
Adapun rencana jadwal tahapan pelaksanaan kegiatan pembangunan
Prasarana dan sarana pada UIN Walisongo Semarang Tahun 2024 dapat
dijelaskan sebagai berikut:
Tahun 2024
No Kegiatan Bulan
1 2 3 4 5 6 7 8 9 10 11 12
1 Proses Lelang Manajemen
Konstruksi
2 Proses Pelaksanaan
Perencanaan
3 Proses Pelalangan
Pelaksana Pekerjaan
4 Proses Pelaksanaan
Pekerjaan
5 Proses Pengawasan

Penanggung Jawab Usulan


Rektor,

Imam Taufiq

14
L. LAMPIRAN-LAMPIRAN
Lampiran I

1. Profil UIN Walisongo


A. Sejarah
Universitas Islam Negeri (UIN) Walisongo berdiri pada tanggal 6 April 1970
melalui Keputusan Menteri Agama RI (KH. M. Dachlan) Nomor 30 dan 31 Tahun
1970. Saat itu masih berstatus Institut Agama Islam Negeri (IAIN) Walisongo.
Pada awal berdirinya, Pendidikan Tinggi Agama Islam ini memiliki lima
Fakultas, yang tersebar di berbagai kota di Jawa Tengah, yakni Fakultas Dakwah
di Semarang, Fakultas Syari’ah di Bumiayu, Fakultas Syari’ah di Demak, Fakultas
Ushuluddin di Kudus dan Fakultas Tarbiyah di Salatiga. Namun demikian, ide dan
upaya perintisannya telah dilakukan sejak tahun 1963, melalui pendirian fakultas-
fakultas Agama Islam di beberapa daerah tersebut yang dilakukan secara sporadis
oleh para ulama sebagai representasi pemimpin agama dan para birokrat santri.
Keberadaan IAIN Walisongo pada awalnya tidak dapat dipisahkan dari
kebutuhan riil masyarakat santri di Jawa Tengah akan terselenggaranya lembaga
pendidikan tinggi yang menjadi wadah pendidikan pascapesantren.
Hal ini disebabkan oleh kenyataan bahwa Jawa Tengah adalah daerah yang
memiliki basis pesantren yang sangat besar. Dengan demikian di satu sisi
lembaga pendidikan tinggi ini harus mampu memposisikan diri sebagai penerus
tradisi pesantren, sementara di sisi lain ia harus memerankan diri sebagai lembaga
pendidikan tinggi yang melakukan kajian dan diseminasi keilmuan, sebagaimana
layaknya perguruan tinggi.
Berdasarkan spirit tersebut, terlihat bahwa IAIN Walisongo memiliki
perbedaan latar belakang sejarah pendirian dengan IAIN Sunan Kalijaga dan IAIN
Jakarta (keduanya sekarang telah berubah menjadi UIN).
Para pendiri, secara sadar memberi nama Walisongo menjadi simbol
sekaligus spirit bagi dinamika sejarah perguruan tinggi agama Islam terbesar di
Jawa Tengah ini, dalam pergulatan meneruskan tradisi dan cita-cita Islam inklusif
ala Walisongo, yang secara terus-menerus menjadi rujukan yang terbuka bagi
dilakukannya tafsir ulang dalam dunia pemikiran ke-Islaman yang diolah secara
cerdas dan kritis dalam bentangan panjang kelestarian (continuity) dan perubahan
(change).

15
Kemudian sejak diterbitkannya Peraturan Presiden nomor 130 tahun 2014,
tertanggal 17 Oktober 2014, maka secara resmi Institut Agama Islam Negeri (IAIN)
Walisongo beralih status menjadi Universitas Islam Negeri (UIN) Walisongo
Semarang. Di tahun 2019, berdasarkan Surat Keputuran Badan Akreditasi
Nasional Perguruan Tinggi (BAN-PT) Nomor 49/SK/BAN-PT/Akred/PT/III/2019
tertanggal 5 Maret 2019 mendapatkan Akreditasi Institusi A sejak 5 Maret 2019
sampai dengan 5 Maret 2022.

B. Visi, Misi dan Tujuan


Visi
“Universitas Islam Riset Terdepan Berbasis pada Kesatuan Ilmu Pengetahuan
untuk Kemanusiaan dan Peradaban pada tahun 2038”

Misi
1. Menyelenggarakan pendidikan dan pengajaran IPTEKS berbasis kesatuan
ilmu pengetahuan untuk menghasilkan lulusan profesional dan berakhlak al-
karimah;
2. Meningkatkan kualitas penelitian untuk kepentingan Islam, ilmu dan
masyarakat;
3. Menyelenggarakan pengabdian yang bermanfaat untuk pengembangan
masyarakat;
4. Menggali, mengembangkan dan menerapkan nilai-nilai kearifan lokal;
5. Mengembangkan kerjasama dengan berbagai lembaga dalam skala regional,
nasional, dan internasional;
6. Mewujudkan tata pengelolaan kelembagaan professional berstandar
internasional.
Tujuan
1. Melahirkan lulusan yang memiliki kapasitas akademik, profesional dan
berakhlakul karimah yang mampu menerapkan dan mengembangkan
kesatuan ilmu pengetahuan;
2. Menghasilkan karya penelitian yang bermanfaat untuk kepentingan islam, ilmu
dan masyarakat.
3. Menghasilkan karya pengabdian yang bermanfaat untuk pengembangan
masyarakat.

16
4. Mewujudkan internalisasi nilai-nilai kearifan lokal dalam Tridharma perguruan
tinggi.
5. Memperoleh hasil yang positif dan produktif dari kerjasama dengan berbagai
lembaga dalam skala regional, nasional dan internasional.
6. Lahirnya tata kelola perguruan tinggi yang profesional berstandar
internasional.

C. Ketersediaan Fakultas dan Program Studi


Berdasarkan PMA Nomor 54 tahun 2015, Universitas Islam Negeri
Walisongo Semarang memiliki 8 (delapan) fakultas, yaitu :
1. Fakultas Syari’ah dan Hukum, memiliki program studi:
a) Program Studi Hukum Keluarga Islam
b) Program Studi Hukum Pidana Islam
c) Program Studi Hukum Ekonomi Islam
d) Program Studi Ilmu Falak
e) Program Studi Ilmu Hukum
2. Fakultas Ushuluddin dan Humaniora, memiliki program studi:
a) Program Studi Akidah Filsafat
b) Program Studi Tafsir Hadits
c) Program Studi Perbandingan Agama
d) Program Studi Tasawuf Psikoterapi
e) Program Studi Ilmu Seni dan Arsitektur Islam
3. Fakultas Ilmu Tarbiyah dan Keguruan, memiliki progam studi :
a) Program Studi Pendidikan Agama Islam
b) Program Studi Pendidikan Bahasa Arab
c) Program Studi Manajemen Pendidikan Islam
d) Program Studi Pendidikan Bahasa Inggris
e) Program Studi Pendidikan Guru Madrasah Ibtidaiyah
f) Program Studi Pendidikan Islam Anak Usia Dini (PIAUD)
4. Fakultas Dakwah dan Komunikasi, memiliki program studi :
a) Program Studi Bimbingan dan Penyuluhan Islam
b) Program Studi Komunikasi dan Penyiaran Islam
c) Program Studi Manajemen Dakwah
d) Program Studi Pengembangan Masyarakat Islam

17
e) Program Studi Manajemen Haji dan Umrah
5. Fakultas Ekonomi dan Bisnis Islam, memiliki program studi :
a) Program Studi Ekonomi Islam
b) Program Studi D3 Perbankan Syari’ah
c) Program Studi S1 Perbankan Syari’ah
d) Program Studi Akuntansi Syari’ah
e) Program Managemen
6. Fakultas Ilmu Sosial dan Politik, memiliki program studi :
a) Program Studi Sosiologi
b) Program Studi Ilmu Politik
7. Fakultas Psikologi dan Kesehatan, memiliki program studi:
a) Program Studi Gizi
b) Program Studi Psikologi
8. Fakultas Sains dan Teknologi, memiliki program studi:
a) Program Studi Matematika
b) Program Studi Fisika
c) Program Studi Kimia
d) Program Studi Biologi
e) Program Studi Pendidikan Matematika
f) Program Studi Pendidikan Fisika
g) Program Studi Pendidikan Kimia
h) Program Studi Pendidikan Biologi
i) Program Studi Teknologi Informasi
Sedangkan pada Pascasarjana Universitas Islam Negeri (UIN) Walisongo
memiliki :
1. Prodi Magister (S2):
a. Ilmu Falak
b. Tafsir
c. Pendidikan Agama Islam
d. Manajemen Pendidikan Islam
e. Studi Islam
f. Komunikasi
g. Ekonomi Syari'ah
2. Prodi Doktor (S3):

18
a. Studi Islam (Konsentrasi disesuaikan dengan minat mahasiswa).
D. Ketersediaan dan Kondisi Sarana Prasarana
Dari sejumlah fakultas dan program studi sebagaimana tersebut, Universitas
Islam Negeri Walisongo memiliki tiga lokasi perkuliahan, yakni:
1. Kampus 1, digunakan untuk gedung Rektorat dan gedung administrasi pusat
serta gedung Pascasarjana dan Pusat Bisnis UIN Walisongo.
2. Kampus 2, digunakan untuk kegiatan perkuliahan Fakultas Ilmu Tarbiyah dan
Keguruan, Fakultas Ushuluddin dan Humaniora serta Fakultas Sains dan
Teknologi.
3. Kampus 3, digunakan untuk Perpustakaan Pusat, kegiatan perkuliahan
Fakultas Syari’ah dan Hukum, Fakultas Dakwah dan Komunikasi, Fakultas
Ekonomi dan Bisnis Islam, Fakultas Ilmu Sosial dan Politik, Fakultas Psikologi
dan Kesehatan serta Pusat Kegiatan Mahasiswa yang berada di kampus 3
yang masih terpisah-pisah untuk semua mahasiswa.

E. Akreditasi Program Studi


Universitas Islam Negeri Walisongo Semarang mendapatkan predikat
Akreditasi Institusi A sebagaimana yang tercantum dalam Surat Keputuran Badan
Akreditasi Nasional Perguruan Tinggi (BAN-PT) Nomor 49/SK/BAN-
PT/Akred/PT/III/2019. Sedangkan akreditasi program studi secara rinci sebagai
berikut:
1. Akreditasi A : 26 Prodi (55,3%)
2. Akreditasi B : 17 Prodi (36,2%)
3. Akreditasi C : 1 Prodi (2,1%)
4. Akreditasi Baik (APS 4.0) : 3 Prodi (6,4%)

19
Akreditasi Prodi UIN Walisongo Semarang

2% 7%

36% 55%

Akreditasi A Akreditasi B Akreditasi C Akreditasi Baik (APS 4.0)

F. Kondisi Mahasiswa
Dalam 5 (lima) tahun terakhir, jumlah mahasiswa UIN Walisongo Semarang
mengalami penambahan.

Adapun jumlah mahasiswa UIN Walisongo Semarang hingga akhir tahun


2022 yang tersebar di beberapa fakultas, sebagaimana rincian berikut ini:

20
Jumlah Mahasiswa Baru Tahun 2022
NO Fakultas Jumlah
1 Fakultas Dakwah dan Komunikasi 712
2 Fakultas Ekonomi dan Bisnis Islam 639
3 Fakultas Ilmu Sosial dan Politik 375
4 Fakultas Ilmu Tarbiyah dan Keguruan 1066
5 Fakultas Psikologi dan Kesehatan 285
6 Fakultas Sains dan Teknologi 882
7 Fakultas Syariah dan Hukum 734
8 Fakultas Ushuluddin dan Humaniora 642
JUMLAH 5332

Jumlah Total Mahasiswa Tahun 2022


NO Fakultas Jumlah
1 Fakultas Dakwah dan Komunikasi 3577
2 Fakultas Ekonomi dan Bisnis Islam 2795
3 Fakultas Ilmu Sosial dan Politik 1712
4 Fakultas Ilmu Tarbiyah dan Keguruan 4127
5 Fakultas Psikologi dan Kesehatan 1583
6 Fakultas Sains dan Teknologi 3753
7 Fakultas Syariah dan Hukum 3871
8 Fakultas Ushuluddin dan Humaniora 3016
Jumlah 24.434

G. Kondisi Organisasi Kemahasiswaan dan Unit Kegiatan


Organisasi Mahasiswa (Ormawa) dan Unit Kegiatan Mahasiswa (UKM) di
lingkungan Universitas Islam Negeri Walisongo Semarang meliputi :
1. Senat Mahasiswa (SEMA) UIN Walisongo
2. Dewan Mahasiswa (DEMA) UIN Walisongo
3. Korp Suka Rela (KSR) UIN Walisongo
4. Bandung Karate Club (BKC) UIN Walisongo
5. Menwa UIN Walisongo
6. Persaudaraan Setia Hati Terate (PSHT) UIN Walisongo
7. Racana Putra UIN Walisongo
8. Racana Putri UIN Walisongo
9. Nadi Walisongo fi Al Lughah Al Arabiyah (NAFILAH) UIN Walisongo
10. Walisongo English Club (WEC) UIN Walisongo
11. Walisongo Sport Club (WSC) UIN Walisongo

21
12. Mahasiswa Walisongo Pecinta Alam (MAWAPALA) UIN Walisongo
13. Mimbar UIN Walisongo
14. Kempo UIN Walisongo
15. Amanat Tabloid UIN Walisongo
16. An Niswa UIN Walisongo
17. Musik UIN Walisongo
18. Koperasi Mahasiswa (KOPMA) UIN Walisongo
19. Kelompok Studi Mahasiswa Walisongo (KSMW) UIN Walisongo
20. Walisongo Carrier Center (WCC) UIN Walisongo
21. Walisongo Entrepreneurship Center
22. Senat Mahasiswa (SEMA) Fakultas Syari'ah dan Hukum
23. Senat Mahasiswa (SEMA) Fakultas Ushuluddin dan Humaniora
24. Senat Mahasiswa (SEMA) Fakultas Ilmu Tarbiyah dan Keguruan
25. Senat Mahasiswa (SEMA) Fakultas Dakwah dan Komunikasi
26. Senat Mahasiswa (SEMA) Fakultas Ekonomi dan Bisnis Islam
27. Senat Mahasiswa (SEMA) Fakultas Ilmu Sosial dan Ilmu Politik
28. Senat Mahasiswa (SEMA) Fakultas Psikologi dan Kesehatan
29. Senat Mahasiswa (SEMA) Fakultas Sains dan Teknologi
30. Dewan Mahasiswa (DEMA) Fakultas Syari'ah dan Hukum
31. Dewan Mahasiswa (DEMA) Fakultas Ushuluddin dan Humaniora
32. Dewan Mahasiswa (DEMA) Fakultas Ilmu Tarbiyah dan Keguruan
33. Dewan Mahasiswa (DEMA) Fakultas Dakwah dan Komunikasi
34. Dewan Mahasiswa (DEMA) Fakultas Ekonomi dan Bisnis Islam
35. Dewan Mahasiswa (DEMA) Fakultas Ilmu Sosial dan Ilmu Politik
36. Dewan Mahasiswa (DEMA) Fakultas Psikologi dan Kesehatan
37. Dewan Mahasiswa (DEMA) Fakultas Sains dan Teknologi
38.
H. Prestasi Mahasiswa Tahun 2021
Di Tahun 2021, mahasiswa UIN Walisongo berhasil meraih prestasi
sebanyak 132 (Seratus Tigapuluh Dua) prestasi, dengan rincian 94 prestasi tingkat
nasional dan 38 prestasi tingkat Internasional.

22
Adapun rincian prestasi kejuraan yang berhasil diraih oleh mahasiswa UIN
Walisongo Semarang, baik tingkat nasional maupun internasional, sebagai
berikut:
1. Prestasi Mahasiswa Tingkat Internasional Tahun 2021
Nama Juara
No Jenis Kejuaraan
Mahasiswa
Taekwondo Bandung Montella Alya 3
1 Internasional E.poomsae Virtual Irfaan Maulana
2021
Taekwondo Bandung Rosita Ihza 1
2 Internasional E.poomsae Virtual Nuringtyas
2021
Taekwondo Bandung Nilam Puspita 3
3 Internasional E.poomsae Virtual Safitri
2021
Taekwondo Bandung Rosdiana Safitri 3
4 Internasional E.poomsae Virtual
2021
Taekwondo Bandung Jihan Faridah 3
5 Internasional E.poomsae Virtual
2021
Taekwondo Bandung Septiani Agustia 3
6 Internasional E.poomsae Virtual Rahma
2021
Taekwondo Bandung Adellia Ersyanti 3
7 Internasional E.poomsae Virtual
2021
Taekwondo Bandung Muhammad Dany 3
8 Internasional E.poomsae Virtual Zakariya
2021

23
Taekwondo Bandung Irmasany 3
9 Internasional E.poomsae Virtual Julianita
2021
Taekwondo Bandung Hamsa Dirham 3
10 Internasional E.poomsae Virtual Deehaq
2021
Taekwondo Bandung Rega Edy 3
11 Internasional E.poomsae Virtual Pratama
2021
Taekwondo Bandung M. Imam Muzaki 3
12 Internasional E.poomsae Virtual
2021
Taekwondo Bandung Maulina Dwi Wiji 3
13 Internasional E.poomsae Virtual lestari
2021
Taekwondondo Gorontalo Montella Alya 2
14 Internasional Virtual Irfaan Maulana
Championship 2021
Taekwondondo Gorontalo Rosita Ihza 2
15 Internasional Virtual Nuringtyas
Championship 2021
Taekwondondo Gorontalo Septiani Agustia 2
16 Internasional Virtual Rahma
Championship 2021
Taekwondondo Gorontalo M Imam Muzaqi 2
17 Internasional Virtual
Championship 2021
Taekwondondo Gorontalo Nilam Puspita 2
18 Internasional Virtual Safitri
Championship 2021
Taekwondondo Gorontalo Maulina Dwi Wiji 3
19 Internasional Virtual Lestari
Championship 2021
Taekwondondo Gorontalo M Ahsin Adaby 3
20 Internasional Virtual
Championship 2021
Taekwondondo Gorontalo Irmasany 3
21 Internasional Virtual Julianita
Championship 2021

24
Taekwondondo Gorontalo Rosdiana Safitri 3
22 Internasional Virtual
Championship 2021
Kejuaraan INTERNATIONAL Sam'ani 3
PSHT CHAMPIONSHIP
TUNGGAL, GANDA, AND
23 BEREGU CATEGORY (Diikuti
oleh Negara Indonesia,
Malaysia, Jepang, Australia,
Thailand)
Kejuaraan INTERNATIONAL Nur Laela 2
PSHT CHAMPIONSHIP
TUNGGAL, GANDA, AND
24 BEREGU CATEGORY (Diikuti
oleh Negara Indonesia,
Malaysia, Jepang, Australia,
Thailand)
Kejuaraan INTERNATIONAL Ridwan Wijaya 2
PSHT CHAMPIONSHIP
Erik Setiawan Aji
TUNGGAL, GANDA, AND
25 BEREGU CATEGORY (Diikuti
oleh Negara Indonesia,
Malaysia, Jepang, Australia,
Thailand)
International Invention MAYA SHOFANI 2
26 Competition Young Mouslim
Scientist 2021
Kejuaraan INTERNATIONAL Ayu Malinda Sari 1
PSHT CHAMPIONSHIP
Malisa Diyah Ayu
TUNGGAL, GANDA, AND
Kusuma
BEREGU CATEGORY (Diikuti
27 oleh Negara Indonesia,
Malaysia, Jepang, Australia,
Thailand)

Kejuaraan INTERNATIONAL Fauzan Adzkiya 1


PSHT CHAMPIONSHIP
Ilham Setiawan
TUNGGAL, GANDA, AND
28 BEREGU CATEGORY (Diikuti Andika Nur
oleh Negara Indonesia, Prayitno
Malaysia, Jepang, Australia,
Thailand)

25
Kejuaraan INTERNATIONAL Tri Handayani 1
PSHT CHAMPIONSHIP
Elsa Anggriani
TUNGGAL, GANDA, AND
29 BEREGU CATEGORY (Diikuti Siti Widayanti
oleh Negara Indonesia,
Malaysia, Jepang, Australia,
Thailand)
Kejuaraan INTERNATIONAL Sulis Nur 2
PSHT CHAMPIONSHIP Khafidzoh
TUNGGAL, GANDA, AND
Ana Nur Karimah
30 BEREGU CATEGORY (Diikuti
oleh Negara Indonesia, Lulu' Ainun Nisa'
Malaysia, Jepang, Australia,
Thailand)
KEJUARAAN FESTIVAL Fauzan Adzkiya 2
VIRTUAL SENI PENCAK SILAT
Ilham Setiawan
31 “ PERSAUDARAAN SETIA HATI
TERATE Andika Nur
Prayitno
Juara 3 Lomba Video Creative Aniq Furayda 2
Competition “International
Siska Teranisa
Innovate Economic Competition”
32 Fatika
UIN Mataram (Team)
Melly Sekarwangi
Putri
Juara Harapan 1 Essay Farid Nur Rohim 3
Competition “International
33 Gani Cahyani
Innovate Economic Competition”
UIN Mataram (Team)
Juara 3 Lomba Paper Reza Reynaldi 3
Accounting Week 2021
Muhamad Fhazal
"Accounting and Sustainable
34 Development Goals After Eqi Suciati
Pandemic" Universitas Widya
Surabaya (Team)

35 MHQ Elya Ghifari 3


MTQ Bazir Abdur 2
36 Rahman
Essay Konferensi Internasional Eka Purwati 2
37 Santri Mendunia 2021

26
International Science and Juliana Ismawati 3
Invention Fair 2021
38 Vida Vania Hadi
Juliana Ismawati

2. Prestasi Mahasiswa Tingkat Internasional Tahun 2021


Berikut adalah rincian prestasi tingkat nasional yang diraih oleh mahasiswa UIN
Walisongo Semarang.

No Jenis Kejuaraan Nama Mahasiswa Juara


KEJUARAAN NASIONAL III Sam'ani 2
PENCAK SILAT
PERSAUDARAAN SETIA
1
HATI TERATE VIRTUAL CUP
KOMISARIAT UNIVERSITAS
MULAWARMAN
1
KEJUARAAN NASIONAL III Fauzan Adzkiya
PENCAK SILAT
Ilham Setiawan
PERSAUDARAAN SETIA
2
HATI TERATE VIRTUAL CUP Andika Nur Prayitno
KOMISARIAT UNIVERSITAS
MULAWARMAN

KEJUARAAN NASIONAL III Tri Handayani 3


PENCAK SILAT
Elsa Anggriani
PERSAUDARAAN SETIA
3 HATI TERATE VIRTUAL CUP Siti Widayanti
KOMISARIAT UNIVERSITAS
MULAWARMAN

KEJUARAAN NASIONAL III Sam'ani 1


PENCAK SILAT
PERSAUDARAAN SETIA
4
HATI TERATE VIRTUAL CUP
KOMISARIAT UNIVERSITAS
MULAWARMAN
KEJUARAAN PENCAK SILAT Maulana Hidayat 2
5
NASIONAL
KEJUARAAN PENCAK SILAT Nur Laela 3
6
NASIONAL

27
KEJUARAAN PENCAK SILAT Lestyowati 2
7
NASIONAL
Fauzan Adzkiya 1
Ilham Setiawan
KEJUARAAN PENCAK SILAT
8 Andika Nur Prayitno
NASIONAL

Tri Handayani 2
Elsa Anggriani
KEJUARAAN PENCAK SILAT
9 Siti Widayanti
NASIONAL

10 Lomba Video Opini Fariz Naufal Susanto 3

11 Lomba Cipta Karya Pramuka Anastya Mawar Dini 1


Lomba Karya Tulis Ilmiah Safira Nurdiana 2
Harlah Forshei UIN
12 Walisongo ke 13 Tahun
2021

13 Lomba Video Opini Nasional Arni Sulistyowati 3

14 Karya Tulis Ilmiah, Essay Ifan Pratama 2


Lomba Essay Pekan Raya Nur Khasanah 1
15 Syari’ah Competition HMJ
Syari’ah Unisula
Arni Sulistyowati 2
Safira Nur Diana
Lomba Karya Tulis Ilmiah
16 Harlah Forshei ke-13 Tri Wulan Ningsih

Lomba Essay HMJ Hukum Nur Khasanah 1


17 Keluarga Islam
Fariz Naufal Susanto 3

18 Arni Sulistyowati
Lomba Video Opini Nasional

19 Lomba Da’i Virtual Miftahul Jannah 2

28
20 Lomba Da’i Miftahul Jannah 1

21 Lomba Menulis Cerpen Islam Faizul Futhona Ulinnuha 1

22 Instagram Photo Contes Lia Barokatus Solikah 1


The1st National Student Eka Mulyo Yunus 1
Leaders in Ststainbility
23 Meeting UIN Raden Intan
Lampung 2021
Spectacular Competition of Sufiatun Handayani 3
24 MASA (Campion Story Telling)

25 The Singing 2021 Competition Irfa Yuhanida Cahyati 3

26 Lomba Da’i Virtual Nasional Eksan Budi Utama 1


Spectacular Competition of Muhammad Ghibran F. 1
27 MASA
(Speechn Winner)
Pelatihan Olimpiade Sains Sefverly Aditya Noorinda 3
28 Indonesia dalam Bidang
Bahasa Inggris
Lomba” Story Telling” Tingkat Sefverly Aditya Noorinda 1
Nasional dalam acara Festival
29 Bahasa secara online yang
diselenggarakan oleh UKM Al-
Izzah dan Stec IAIN Kudus
Poster Digital Pekan Syania Nur Anggraini 3
HIMAKOM 2021 dengan Tema
30 Budaya Indonesia di
Universitas Muhammadiyah
Jakarta
Lomba Infografis pada Moh. Jamalul Lail 1
kegiatan Festifal Iqtaf 2021
yang diselenggarakan ppada
31 23 April – 8 Mei 2021 yang
diselenggarakan oleh
Himpunan Mahasiswa IAT
PTIQ Jakarta
Singing Competition yang Irfa Yuhanida 3
diselenggarakan oleh
32 assosiasi Prodi Bahasa Inggris
FITK UIN Walisongo
Lomba Pidato SPECTATIOSA Muhammad Ghibran F. 1
33
dalam Spectacular of MASA
29
yang diselenggarakan UKM-F
Majelis Bahasa FPK UIN
Walisongo

Lomba Pidato Walisongo Puput Ariyatna 2


dalam Education Festival
34 (EDUFEST) 2021 yang
diselenggarakan oleh FITK
UIN Walisong
Shalahuddin al ayyubi 3
M. Fiqi Fauzul Muna
M Adib Musthofa
Afif Ali Abidin
Ladhaika Izzur Rochman
35
Rebana Muhammad Noor Taufiq
Moh. Iflahul Karim
Zuhhadul Hilmi A.
M. Ilham Akbar
M. Mauris Muttaqim

36 Lomba Puisi Lathifatul Ismi Fauziah 1

37 Cover Sholawat Oseolla Savana 2

38 Da’i Nurul Habibah 1

39 KTI Sosial Tsania Arifati 1

40 Lomba Taqdimul Qishoh Maulida Azmy 3

41 Lomba Taqdimul Qishoh Maulida Azmy 1

42 Lomba Kaligrafi Hariz Nur Fadhlullah 3


Lomba Musabaqoh Qiroatul Achmad Rifqi Al-Charies 1
43 Kutub
Lomba cipta karya kreasi A. Zulfa Muntafa 1
44 cerpen

45 Lomba Cerita Bergambar Clarita Nur Fadhila 1

46 Lomba Cipta Baca Puisi Hikmatun Nazilah 1

47 Lomba Baca Puisi Hikmatun Nazilah 2

30
48 Kejuaraan Pencak Silat Nadila Sasabilla 1
Khaerunnisa 1

49 Yanwar Pratama
Lomba Debat Bahasa Inggris
Nuraini Safira

50 Taqdimul Qishoh Izzul Haq Al-Busyairi 2

51 Taqdimul Qishoh Wahyuni Lailatul Qomariyah 1

52 Insya’ Lutfia Nur 'Aini 3

53 Insya’ Lutfia Nur 'Aini 2

54 Taqdimul Qishoh Izzul Haq Al-Busyairi 1


Eka Purwati 2
55 Essay FOSMI Islamic Festival

Essay Intellectual and Digital Eka Purwati 2


56 Competition
Essai Muslim Animal Eka Purwati 3
57 Husbandry Festival “Ayo Lebih
Baik”
Essay Konferensi Eka Purwati 2
58 Internasional Santri Mendunia
2021
Eka Purwati 3
59 Lomba Menulis Kritis
Tiwi Fadilatul Azna
Lomba video pendek dengan Rahma Safira 1
tema Edukasi Kesehatan
Fiyan Tika N
Mental di Masa Pademi dan
60 Sub Tema Cyber Counseling Anis Sapitri
Universitas Adibuana
Surabaya

61 Lomba Puisi Nasional Aldhania Uswatun Hasanah 3


Anis Sapitri 2
62 Podcast Nasional 10-29
Rahma Safira
Agustus 2021
Lomba Sains Nasional Muhammad Luthfi Muzhaffar 2
63 28-29 Agustus2021
64 Andika Nur Prayitno 1

31
Pencak Silat Fauzan Adzkiya

Bisnis Plan dalam rangka Aniq Furayda 2


65 Festival Akuntansi 2021 di UIN
Amelia Ulfa Rosida
Walisongo (Team)
Nining Sulistyowati 3

66 Eqi Suciati
Essay Nasional Polines 2021
(Team) Tutut Ida Purwatiningsih
Nining Sulistyowati 1
Lomba Call For Paper yang
Reza Reynaldi
diselenggarakan di Universitas
67
Pekalongan (Team) Eqi Suciati

Lomba Video Competition Nurul Fajriatussaadah 1


pada kegiatan Unesa
68 Education Fair yang
diselenggarakan di Universitas
Negeri Surabaya
Lomba Karya Tulis Ilmiah yang Leila Mifta Nur Mahabah 3
69 diselenggarakan di UIN
Walisongo
Lomba Karya Tulis Ilmiah Fitra Istianah Turahman 2
SECTION yang
70 diselenggarakan di IAIN
Pekalongan

71 Temu Ilmiah Nasional FoSSEI Fitra Istianah Turahman 2


Lomba Cipta Quote Event Fitra Istianah Turahman 1
72 kreasi Ep. 5
Lomba Pelatihan Kepenulisan Amelia Ulfa Rosida
Artikel Ilmiah dan Essay yang
73 di selenggarakan di UIN
Walisongo
Shandy Pratama 1
74 Lomba Essay di Universitas
Stikubank
Review Movie Bahasa Inggris Muhammad Bayu Aji 3
75
yang diselenggarakan oleh

32
Walisongo English Club
(WEC)
Lomba KTI yang di Ainun Naim 2
76 selenggarakan oleh HMJ
Manajemen
Lomba Desain Grafis ysng Avi Viqi Fatwa 3
diselenggarakan oleh Resimen
77 Mahasiswa Batalyon 953
Kalimosodo IAIN Salatiga
Kompetisi Sains Indonesia Vika Rachmania Hidayah 3
78 (KSI) POSI Th 2021
Festival Kemahasiswaan Ayu Istiya Wahyuni 1
79 Cabang Lomba Matematika
(IAIN Kudus)
Lomba Media Pembelajaran Adam Wildan Alfikri 2
Tingkat Nasional oleh
80 HIMATIKA Universitas PGRI
Semarang
Lomba Microteaching Nurul Atsna Qonita 2
Walisongo Science
81 Competition

Lomba Microteaching Melida Sholikhah 3


Walisongo Science
82 Dwi Fametya
Competition

Lomba Karya Tulis Ilmiah Latifatul Istianah 2


Walisongo Science
83 Syarifatul Hikam S
Competition
Firman Hardianto

Lomba Inovasi Teknologi dan Maya Shofani 2


Media Pembelajaran
Jannatul Firdausa A.
84 Walisongo Science
Competition Via Amalia

Lomba Mcbot 2021 kategori Tim Robot “Legion” TI 1


85 maze solving

33
Kegiatan Kejuaraan Nasional Siti Widayanti 3
III PSHT Virtual Cup
86 Komisariat Universitas
Mulawarman.
Kegiatan Kejuaraan Nasional Ilham Setiawan 1
III PSHT Virtual Cup
87 Komisariat Universitas
Mulawarman.
Lomba Cover lagu 2021 oleh Zuliyas Eko Wicaksono 1
UNNES dan Dikti
88 Kemendikbud

89 Olimpiade IPA Nailur Muqorrobin 2


OSI (Olimpiade Sains Farras Khirzi Khanifah 3
90 Indonesia)

Olimpiade Biologi POSI Nailatus Sholihah 2


91 Tingkat Nasional

92 Lomba Poster Ilmiah Firman Hardianto 2


Pateron Youth Educational Ely Lestari Wibowo 2
93 Competition Bidang Fisika
Pateron Youth Educational Ely Lestari Wibowo 1
94 Competition Bidang Statistika

Dalam pengembangan bidang organisasi kemahasiswaan dilakukan


penekanan pada penyelenggaraan kegiatan keorganisasian kemahasiswaan,
regulasi keorganisasian dan fasilitas oraganisasi kemahasiswaan yang sah.
Pengembangan ini ditujukan dalam rangka peningkatan kualitas intelektual dan
emosional mahasiswa sebagai langkah untuk keseimbangan kepribadian.
I. Rekognisi UIN Walisongo Tahun 2021
UIN Walisongo Semarang meraih penghargaan sebagai Perguruan Tinggi/
Badan Publik Informatif dari Komisi Informasi Pusat (KIP) pada tahun 2021.
Peringkat Informatif merupakan peringkat tertinggi dari keterbukaan informasi
badan publik. Anugerah sebagai badan publik informatif ini menunjukkan
akuntabilitas, transparansi kelembagaan sebuah institusi. Hasil ini juga juga

34
menunjukkan tingkat kepatuhan badan publik terhadap pelaksanaan UU Nomor
14 Tahun 2008 tentang Keterbukaan Informasi Publik.
UIN Walisongo Semarang juga dinobatkan sebagai juara 1 PTKIN kategori
keterbukaan informasi publik. Penghargaan tersebut diterima UIN Walisongo pada
malam penganugerahan Adiktis 2021 yang diselenggarakan oleh Kementerian
Agama RI pada 10 Desember 2021 di Mercure Convention Center Ancol.
J. Sarana Kegiatan Mahasiswa
Dari sejumlah Organisasi Kemahasiswaan dan Unit Kegiatan Mahasiswa
sebagaimana tersebut di atas, Universitas Islam Negeri Walisongo Semarang saat
ini baru dapat memberikan fasilitas beberapa unit saja, sisanya masih menempati
bangunan yang kurang layak sebagai Official UKM. Kondisi ini sangat tidak
mencerminkan dengan status Universitas Islam Negeri di Semarang sebagai
Lembaga Perguruan Tinggi pembentuk karakter bangsa dan agen-agen
perubahan menuju Indonesia yang maju dan bermartabat.
Ditambah lagi adanya pengembangan kampus dalam bentuk proyek Islamic
Development Bank (IsDB) untuk pemenuhan sarana utama perkuliahan yang
mengharuskan adanya pembongkaran gedung PKM lama sebagai pusat kegiatan
mahasiswa, sementara bangunan pengganti untuk kegiatan-kegiatan
kemahasiswaan belum dapat terakomodir dikarenakan keterbatasan anggaran,
sehingga pusat-pusat kegiatan mahasiswa saat ini untuk sementara waktu
ditempatkan di kanan kiri gedung serba guna (GSG) sembari menunggu
pembangunan gedung pengganti.
Ruang Official Ormawa dan UKM UIN Walisongo Semarang sekarang ini
tersebar di 3 tempat, yakni Gayebo Racana Kampus II, Gedung PKM 2 Lantai
Kampus III dan Gedung Serba Guna (GSG) Kampus III. Secara lokasi, ketiga
lokasi tersebut tidak tersentral, sehingga aktifitas non akademik mahasiswa
kurang optimal. Selain itu juga, fasilitas dan perlengkapan sebagai penunjang
peningkatan bakat dan minat mahasiswa kurang optimal dengan memperhatikan
rasio jumlah mahasiswa UIN Walisongo Semarang.
Oleh karena itu, untuk meningkatan kompetensi bakat dan minat mahasiswa
UIN Walisongo Semarang, sangat diperlukan Gedung Student center dan Fasilitas
yang memadai sebagai pusat aktifitas kegiatan mahasiswa. Hal ini sebagai wadah
untuk membekali mahasiswa untuk menghadapi Era Industri 4.0 dan Society 5.0
serta daya saing di tingkat global.

35
36
Lampiran II

2. Denah Eksisting Kampus Uin Walisongo Semarang


Lokasi Kampus UIN Walisongo Semarang yang terbagi dalam 3 Lokasi.

Denah Kampus III Dan Rencana Lokasi Gedung Student center

37
Lahan Kosong yang Direncanakan Akan Dibangun Gedung Student center

38
Lampiran III

3. Rekapitulasi Rencana Anggaran BIAYA (RAB)


MASING-MASING KOMPONEN KEGIATAN (DIHITUNG BERDASARKAN
TABEL PROSENTASE BIAYA PERENCANAAN PENGAWASAN, MK,
ADMINISTRASI DAN BANGUNAN FISIK)
REKAPITULASI
RENCANA ANGGARAN BIAYA

PEMBANGUNAN GEDUNG STUDENT CENTER UIN WALISONGO SEMARANG


TAHUN 2024

A BIAYA KONSTRUKSI PEMBANGUNAN GEDUNG Rp. 43.324.959.000,00

B BIAYA PERENCANAAN KONSTRUKSI Rp. 900.000.000,00

C BIAYA PENGAWASAN KONSTRUKSI Rp. 1.200.000.000,00

D BIAYA PENGELOLA KEGIATAN / AP Rp. 250.000.000,00

E BIAYA INTERIOR (TERMASUK FURNITURE) Rp. 2.500.000.000,00

(15% DARI BIAYA STANDAR)

JUMLAH TOTAL Rp. 48.174.959.000,00

DIBULATKAN Rp. 48.174.959.000,00

TERBILANG

Empat puluh delapan miliyar seratus tujuh puluh empat juta Sembilan ratus lima putuh
Sembilan ribu rupiah

RINCIAN KONSTRUKSI PEMBANGUNAN GEDUNG

NO URAIAN JUMLAH HARGA

A KONSTRUKSI PEMBANGUNAN GEDUNG


I. PEKERJAAN PERSIAPAN Rp 394.500.000,00
II. PEKERJAAN TANAH Rp 651.429.794,90
III. PEKERJAAN PONDASI Rp 1.649.970.935,04
IV. PEKERJAAN PASANGAN DAN PLESTERAN Rp 2.524.291.103,66
V. PEKERJAAN BETON BERTULANG Rp 11.824.059.505,92
VI. PEKERJAAN ATAP Rp 1.539.980.411,86
VII. PEKERJAAN KUSEN, PINTU, JENDELA Rp 2.874.481.616,07
VIII. PEKERJAAN PLAFOND DAN PENGGANTUNG Rp 1.084.505.252,81

39
IX. PEKERJAAN PENUTUP LANTAI DAN DINDING Rp 5.163.524.134,63
X. PEKERJAAN PENGECATAN DAN WATERPROOFING Rp 1.080.359.495,80
XI. PEKERJAAN SANITERI DAN PLUMBING Rp 651.280.367,70
XII. PEKERJAAN MEKANIKAL ELEKTRIKAL Rp 3.196.878.363,00
XIII. PEKERJAAN LAIN-LAIN Rp 3.924.816.682,00
XIV. PEKERJAAN PENATAAN LINGKUNGAN
A. PEKERJAAN PENATAAN LAHAN/TANAH Rp 645.970.439,36
B. PEKERJAAN PERKERASAN HALAMAN Rp 727.062.933,04
C. PEKERJAAN PASANGAN DAN PLESTERAN Rp 328.275.367,70
D. PEKERJAAN KOLAM AIR MANCUR Rp 352.445.717,21
E. PEKERJAAN PENGECATAN Rp 27.062.546,33
F. PEKERJAAN TAMAN Rp 390.600.000,00

Rp 39.031.494.667,03
PPN (11%) Rp 4.293.464.413,37
JUMLAH TOTAL Rp 43.324.959.080,40
JUMLAH DIBULATKAN Rp 43.324.959.000,00
Terbilang :
Empat puluh delapan miliyar seratus tujuh puluh empat juta Sembilan ratus lima putuh
Sembilan ribu rupiah

40
RINCIAN KONSTRUKSI GEDUNG

HARGA SATUAN JUMLAH HARGA


KODE
NO. URAIAN PEKERJAAN VOLUME
ANALISA
(Rp) (Rp)

I. PEKERJAAN PERSIAPAN
Pekerjaan pembersihan lapangan (dari awal
1 Taksir ls 22.500.000,00
sampai akhir pekerjaan) 1,00 22.500.000,00
Pekerjaan pengukuran dan pasang papan
2 Taksir ls 10.800.000,00
bowplank 1,00 10.800.000,00
Pekerjaan Administarsi (termasuk perijinan) dan
3 Taksir ls 7.200.000,00
dokumentasi 1,00 7.200.000,00
4 Pembuatan bangunan penunjang
Pembangunan direksikeet / kantor
a Dihitung unit 189.000.000,00
sementara 1,00 189.000.000,00
b Pembangunan power house/rumah genset Dihitung unit 112.500.000,00
1,00 112.500.000,00
5 Alat bantu kerja (material hoist) dan lansiran Dihitung ls 52.500.000,00
1,00 52.500.000,00

394.500.000,00
II. PEKERJAAN TANAH
Pekerjaan galian tanah untuk pondasi dan pile
1 2.1. m3 118.443,60
cap 1.100,04 130.293.053,07
2 Pekerjaan urugan kembali tanah galian 2.9. m3 39.481,20
366,68 14.477.005,90
Pekerjaan urugan tanah padas mendatangkan dan
3 2.14. m3 210.250,80
pemadatan tanah (Dalam bangunan) 1.163,38 244.601.365,45
Pekerjaan pemadatan tanah (urugan sisa
4 2.10. m3 64.102,50
galian+urugan mendatangkan) 1.530,06 98.080.671,15
5 Pekerjaan urugan pasir bawah pondasi dan lantai

a Urugan pasir bawah pondasi dan pile cap 2.11. m3 296.950,50


85,41 25.361.651,35
b Urugan pasir bawah lantai 01 dan tritisan 2.11. m3 296.950,50
229,51 68.152.812,30
c Urugan pasir bawah lantai 02 2.11. m3 296.950,50
80,40 23.874.374,77
d Urugan pasir bawah lantai 03 2.11. m3 296.950,50
76,49 22.714.486,12
e Urugan pasir bawah lantai 04 2.11. m3 296.950,50
80,40 23.874.374,77

651.429.794,90
III. PEKERJAAN PONDASI

1 Pekerjaan pas. Batu kosong / aanstamping

a. Pas. Batu kosong/aanstamping type A 3.9. m3 630.426,60


19,47 12.272.514,62
b. Pas. Batu kosong/aanstamping type B 3.9. m3 630.426,60
1,39 873.771,27
c. Pas. Batu kosong/aanstamping type C 3.9. m3 630.426,60
9,92 6.255.407,94
d. Pas. Batu kosong/aanstamping type E 3.9. m3 630.426,60
45,63 28.764.947,30
e. Pas. Batu kosong/aanstamping type F 3.9. m3 630.426,60
86,47 54.511.412,04
f. Pas. Batu kosong/aanstamping type G 3.9. m3 630.426,60
9,51 5.997.248,25

41
g. Pas. Batu kosong/aanstamping type H 3.9. m3 630.426,60
18,29 11.527.823,20
h. Pas. Batu kosong/aanstamping type I 3.9. m3 630.426,60
3,12 1.965.985,35
i. Pas. Batu kosong/aanstamping type K 3.9. m3 630.426,60
1,26 794.337,52
j. Pas. Batu kosong/aanstamping type L 3.9. m3 630.426,60
4,41 2.780.181,31
2 Pekerjaan pondasi pas. Batu belah 1:5

a. Pas. Pondasi batu belah 1:5 type A 3.3. m3 1.106.905,50


72,61 80.369.641,09
b. Pas. Pondasi batu belah 1:5 type B 3.3. m3 1.106.905,50
17,31 19.159.704,03
c. Pas. Pondasi batu belah 1:5 type C 3.3. m3 1.106.905,50
39,56 43.793.609,20
d. Pas. Pondasi batu belah 1:5 type D 3.3. m3 1.106.905,50
17,33 19.177.137,79
e. Pas. Pondasi batu belah 1:5 type E 3.3. m3 1.106.905,50
115,10 127.405.929,96
f. Pas. Pondasi batu belah 1:5 type F 3.3. m3 1.106.905,50
225,90 250.052.442,99
g. Pas. Pondasi batu belah 1:5 type G 3.3. m3 1.106.905,50
29,44 32.583.700,48
h. Pas. Pondasi batu belah 1:5 type G 3.3. m3 1.106.905,50
46,07 50.993.752,75
i. Pas. Pondasi batu belah 1:5 type G 3.3. m3 1.106.905,50
6,66 7.374.481,17
j. Pas. Pondasi batu belah 1:5 type G 3.3. m3 1.106.905,50
31,12 34.449.112,97
k. Pas. Pondasi batu belah 1:5 type G 3.3. m3 1.106.905,50
15,58 17.241.990,25
l. Pas. Pondasi batu belah 1:5 type G 3.3. m3 1.106.905,50
24,51 27.126.933,09
3 Pekerjaan pondasi pile cap

a. Pondasi pile cap PC.1A 4.25A m3 5.112.373,79


4,25 21.740.369,53
b. Pondasi pile cap PC.1B 4.25A m3 5.112.373,79
0,71 3.623.394,92
c. Pondasi pile cap PC.2A 4.25B m3 3.765.160,20
4,25 16.011.343,73
d. Pondasi pile cap PC.3A 4.25C m3 3.596.889,53
8,51 30.591.545,42
e. Pondasi pile cap PC.3B 4.25C m3 3.596.889,53
2,84 10.197.181,81
f. Pondasi pile cap PC.4A 4.25D m3 3.792.122,27
53,16 201.574.999,34
g. Pondasi pile cap PC.4B 4.25D m3 3.792.122,27
12,76 48.377.999,84
h. Pondasi pile cap PC.5A 4.25E m3 3.473.974,66
6,79 23.582.208,47
i. Pondasi pile cap PC.6A 4.25F m3 4.259.115,87
14,88 63.391.615,85
j. Pondasi pile cap PC.7A 4.25G m3 3.735.705,23
17,44 65.132.954,57
k. Pondasi pile cap PC.8 4.25H m3 3.728.993,11
7,75 28.895.967,57
4 Pekerjaan lantai kerja bawah pile cap 4.4 m3 1.338.326,10
10,54 14.101.607,53
Pekerjaan pondasi tiang pancang square pile
5
25x25 cm K500
Pengadaan taing pancang square pile 25x25
a. 3.10. m' 171.678,60
cm K500 1.129,28 193.872.351,02
Mobilisasi dan demobilisasi peraltan dan
b, Taksir ls 22.500.000,00
tenaga pancang 1,05 23.625.000,00
Pemancangan tiang pancang dengan jack
c. 3.12. m' 72.774,00
hamer 752,85 54.787.905,90

42
d. Pemecahan kepala tiang pancang Taksir bh 31.500,00
250,95 7.904.925,00
d. PDA Loading tes (2 titik) dan pelaporan Taksir ttk 3.375.000,00
2,10 7.087.500,00

1.649.970.935,04
IV. PEKERJAAN PASANGAN DAN PLESTERAN

A. PEKERJAAN PASANGAN DAN PLESTERAN LT. 01


Pasang dinding bata ringan dengan perekat
1 Dihit m2 151.164,00
mortar 1.361,72 205.843.646,74
Pekerjaan Plesteran dinding camp. 1:5 tebal 15
2 7.5. m2 78.249,60
mm 2.723,45 213.108.716,62
Pekerjaan Plesteran beton camp. 1:5 tebal 15
3 7.5. m2 78.249,60
mm 546,41 42.756.324,81
4 Pekerjaan Acian 7.27. m2 45.473,40
2.700,85 122.816.923,34
5 Pekerjaan sponengan 7.20. m' 52.386,30
1.692,75 88.676.752,17

673.202.363,67
B. PEKERJAAN PASANGAN DAN PLESTERAN LT. 02
Pasang dinding bata ringan dengan perekat
1 Dihit m2 151.164,00
mortar 1.281,00 193.641.084,00
Pekerjaan Plesteran dinding camp. 1:5 tebal 15
2 7.5. m2 78.249,60
mm 2.562,20 200.491.086,00
Pekerjaan Plesteran beton camp. 1:5 tebal 15
3 7.5. m2 78.249,60
mm 553,00 43.272.302,67
4 Pekerjaan Acian 7.27. m2 45.473,40
2.622,05 119.233.505,73
5 Pekerjaan sponengan 7.20. m' 52.386,30
1.462,90 76.636.023,04

633.274.001,44
C. PEKERJAAN PASANGAN DAN PLESTERAN LT. 03
Pasang dinding bata ringan dengan perekat
1 Dihit m2 151.164,00
mortar 1.217,34 184.017.757,01
Pekerjaan Plesteran dinding camp. 1:5 tebal 15
2 7.5. m2 78.249,60
mm 2.434,68 190.512.501,38
Pekerjaan Plesteran beton camp. 1:5 tebal 15
3 7.5. m2 78.249,60
mm 549,70 43.013.492,12
4 Pekerjaan Acian 7.27. m2 45.473,40
2.434,68 110.713.041,09
5 Pekerjaan sponengan 7.20. m' 52.386,30
1.074,40 56.283.945,49

584.540.737,10
D. PEKERJAAN PASANGAN DAN PLESTERAN LT. 04
Pasang dinding bata ringan dengan perekat
1 Dihit m2 151.164,00
mortar 1.281,00 193.641.084,00
Pekerjaan Plesteran dinding camp. 1:5 tebal 15
2 7.5. m2 78.249,60
mm 2.562,20 200.491.086,00
Pekerjaan Plesteran beton camp. 1:5 tebal 15
3 7.5. m2 78.249,60
mm 553,00 43.272.302,67
4 Pekerjaan Acian 7.27. m2 45.473,40
2.622,05 119.233.505,73
5 Pekerjaan sponengan 7.20. m' 52.386,30
1.462,90 76.636.023,04

43
633.274.001,44

2.524.291.103,66
V. PEKERJAAN BETON BERTULANG

A. PEKERJAAN BETON BERTULANG LT. 01


Beton bertulang Sloof BS.01 (25x50 cm) beton
1 4.26A m3 5.595.471,12
Fc'25 4,07 22.795.949,34
Beton bertulang Sloof BS.02 (25x40 cm) beton
2 4.26B m3 7.094.534,75
Fc'25 20,12 142.727.850,09
3 Beton bertulang Sloof BS3 (25x40 cm) beton Fc'25 4.26C m3 6.026.934,40
35,87 216.174.083,11
Beton bertulang Sloof BS.04 (15x25 cm) beton
4 4.26D m3 7.100.445,48
K175 2,95 20.949.864,38
Beton bertulang Kolom K1.A (45x55 cm) beton Fc'
5 4.27A m3 5.896.947,83
25 8,03 47.367.233,45
Beton bertulang Kolom K1.B (45x45 cm) beton Fc'
6 4.27B m3 6.060.140,75
25 53,41 323.693.327,99
Beton bertulang Kolom K1.C (30x30 cm) beton Fc'
7 4.27C m3 7.488.672,28
25 2,04 15.254.425,43
Beton bertulang Kolom K1.D (25x60 cm) beton Fc'
8 4.27D m3 8.467.407,56
25 3,24 27.472.503,82
Beton bertulang Kolom K1.E (25x35 cm) beton Fc'
9 4.27E m3 9.578.215,74
25 0,95 9.051.413,88
Beton bertulang Kolom KP.1 (15x15 cm) beton
10 4.27F m3 8.382.880,79
K175 11,41 95.678.009,86
Beton bertulang Kolom KP.2 (15x30 cm) beton
11 4.27G m3 6.918.912,72
K175 2,65 18.307.443,06
Beton bertulang Balok B.01 (40x90 cm) beton Fc'
12 4.28A m3 6.384.130,68
25 3,73 23.796.847,13
Beton bertulang Balok B.02 (40x80 cm) beton Fc'
13 4.28B m3 6.046.880,86
25 13,98 84.508.183,42
Beton bertulang Balok B.03 (30x75 cm) beton Fc'
14 4.28C m3 8.075.055,30
25 23,53 190.010.088,77
Beton bertulang Balok B.04 (30x75 cm) beton Fc'
15 4.28D m3 7.209.489,32
25 7,84 56.547.629,49
Beton bertulang Balok B.05 (30x65 cm) beton Fc'
16 4.28E m3 7.117.408,82
25 18,77 133.622.233,12
Beton bertulang Balok B.06 (30x65 cm) beton Fc'
17 4.28F m3 6.978.247,04
25 21,46 149.767.137,93
Beton bertulang Balok B.07 (30x50 cm) beton Fc'
18 4.28G m3 7.153.129,44
25 23,79 170.194.408,65
Beton bertulang Balok B.08 (30x40 cm) beton Fc'
19 4.28H m3 6.900.313,10
25 2,27 15.649.910,11
Beton bertulang Balok B.09 (30x60 cm) beton Fc'
20 4.28I m3 7.033.073,46
25 4,56 32.049.715,76
Beton bertulang Balok B.10 (30x60 cm) beton Fc'
21 4.28J m3 6.935.498,29
25 4,35 30.148.611,07
Beton bertulang Balok B.11 (30x40 cm) beton Fc'
22 4.28K m3 7.114.562,10
25 1,01 7.171.478,60
Beton bertulang Balok B.11A (30x40 cm) beton Fc'
23 4.28L m3 7.153.346,67
25 0,97 6.910.132,88
Beton bertulang Balok B.12 (20x50 cm) beton Fc'
24 4.28M m3 8.790.098,57
25 2,81 24.735.337,36
Beton bertulang Balok B.13 (30x50 cm) beton Fc'
25 4.28N m3 7.838.943,49
25 1,16 9.053.979,73
Beton bertulang Balok B.14 (25x50 cm) beton Fc'
26 4.28O m3 7.333.404,91
25 30,45 223.302.179,45
Beton bertulang Balok B.15 (25x50 cm) beton Fc'
27 4.28P m3 7.333.404,91
25 13,52 99.176.967,98
Beton bertulang Balok B.16 (20x35 cm) beton Fc'
28 4.28Q m3 9.164.795,17
25 15,56 142.613.377,70
Beton bertulang Balok B.17 (20x40 cm) beton Fc'
29 4.28R m3 8.886.116,54
25 1,62 14.368.850,44
Beton bertulang Balok B.18 (25x70 cm) beton Fc'
30 4.28S m3 7.081.282,59
25 5,66 40.076.518,81

44
Beton bertulang Balok B.19 (15x50 cm) beton Fc'
31 4.28T m3 10.432.363,91
25 1,12 11.720.760,85
Beton bertulang Balok B.20 (20x35 cm) beton Fc'
32 4.28U m3 8.770.046,33
25 0,33 2.854.650,08
Beton bertulang Balok B.21 (20x40 cm) beton Fc'
33 4.28V m3 8.390.020,92
25 0,70 5.902.379,72
Beton bertulang Balok Latiu BL.1 (15x20 cm)
34 4.29AN m3 7.890.726,68
beton K175 0,53 4.142.631,51
Beton bertulang Balok Latiu BL.2 (15x15 cm)
35 4.29AO m3 8.982.376,87
beton K175 2,86 25.653.668,34
Beton bertulang Topi-topi T1 (15/20+10/40 cm)
36 4.29AP m3 6.215.545,47
beton K175 1,62 10.050.537,03
Beton bertulang Topi-topi T2 (15/20+10/50 cm)
37 4.29AQ m3 6.042.920,40
beton K175 1,62 9.771.402,28
Beton bertulang Tangga beton dari lt. 01 menuju
38 4.30 m3 7.753.713,75
lt. 02 (berikut pondasi dan balok bordes) 11,08 85.891.764,07
Beton bertulang plat lantai beton lt. 02 tebal 12
39 4.31 m3 7.572.085,04
cm 190,54 1.442.811.586,53
Beton bertulang Balok Lisplank (10x30 cm) beton
40 4.32 m3 9.069.305,36
Fc' 25 0,66 5.999.345,49
Beton bertulang Parapet PR.1 (10x50 cm) beton
41 4.33A m3 6.399.857,33
K175 6,24 39.915.910,19
Beton bertulang Parapet PR.2 (10x23 cm)
42 4.33B m3 8.404.126,54
betonK175 3,27 27.443.675,20
Beton bertulang Parapet PR.3 (10x48 cm)
43 4.33C m3 7.367.077,80
betonK175 3,63 26.764.593,64
Beton bertulang Parapet PR.4 (10x73 cm)
44 4.33D m3 4.105.929,15
betonK175 2,76 11.338.523,34

4.103.437.121,09
B. PEKERJAAN BETON BERTULANG LT. 02
Beton bertulang Kolom K2.A (45x55 cm) beton Fc'
1 4.27H m3 6.957.150,97
25 6,24 43.391.750,61
Beton bertulang Kolom K2.B (45x45 cm) beton Fc'
2 4.27B m3 6.060.140,75
25 40,82 247.399.186,01
Beton bertulang Kolom K1C (30x30 cm) beton Fc'
3 4.27C m3 7.488.672,28
25 0,38 2.830.718,12
Beton bertulang Kolom KP.1 (15x15 cm) beton
4 4.27F m3 8.382.880,79
K175 11,41 95.678.009,86
Beton bertulang Kolom KP.2 (15x30 cm) beton
5 4.27G m3 6.918.912,72
K175 2,98 20.632.197,73
Beton bertulang Balok B.02 (40x80 cm) beton Fc'
6 4.28B m3 6.046.880,86
25 7,36 44.508.066,55
Beton bertulang Balok B.03 (30x75 cm) beton Fc'
7 4.28C m3 8.075.055,30
25 23,53 190.010.088,77
Beton bertulang Balok B.04 (30x65 cm) beton Fc'
8 4.28D m3 7.209.489,32
25 7,84 56.547.629,49
Beton bertulang Balok B.05 (30x65 cm) beton Fc'
9 4.28E m3 7.117.408,82
25 18,77 133.622.233,12
Beton bertulang Balok B.07 (30x50 cm) beton Fc'
10 4.28G m3 7.153.129,44
25 1,68 12.017.257,45
Beton bertulang Balok B.09 (30x60 cm) beton Fc'
11 4.28I m3 7.033.073,46
25 2,38 16.763.330,59
Beton bertulang Balok B.11 (30x40 cm) beton Fc'
12 4.28K m3 7.114.562,10
25 1,97 14.044.145,59
Beton bertulang Balok B.11A (30x40 cm) beton Fc'
13 4.28L m3 7.153.346,67
25 0,97 6.910.132,88
Beton bertulang Balok B.12 (20x50 cm) beton Fc'
14 4.28M m3 8.790.098,57
25 2,79 24.550.745,29
Beton bertulang Balok B.13 (30x50 cm) beton Fc'
15 4.28N m3 7.838.943,49
25 1,89 14.815.603,19
Beton bertulang Balok B.15 (25x50 cm) beton Fc'
16 4.28P m3 7.333.404,91
25 13,70 100.485.980,75
Beton bertulang Balok B.16 (20x35 cm) beton Fc'
17 4.28Q m3 9.164.795,17
25 13,98 128.082.594,95

45
Beton bertulang Balok B.17 (20x40 cm) beton Fc'
18 4.28R m3 8.886.116,54
25 1,62 14.368.850,44
Beton bertulang Balok B.18 (25x70 cm) beton Fc'
19 4.28S m3 7.081.282,59
25 3,09 21.859.919,35
Beton bertulang Balok B.19 (15x50 cm) beton Fc'
20 4.28T m3 10.432.363,91
25 1,12 11.720.760,85
Beton bertulang Balok B.20 (20x35 cm) beton Fc'
21 4.28U m3 8.770.046,33
25 0,33 2.854.650,08
Beton bertulang Balok B.21 (20x35 cm) beton Fc'
22 4.28V m3 8.390.020,92
25 0,33 2.730.951,81
Beton bertulang Balok B.22 (40x90 cm) beton Fc'
23 4.28W m3 6.109.963,65
25 3,73 22.774.889,49
Beton bertulang Balok B.23 (40x80 cm) beton Fc'
24 4.28X m3 6.074.117,36
25 6,62 40.180.286,36
Beton bertulang Balok B.24 (30x65 cm) beton Fc'
25 4.28Y m3 6.642.568,29
25 21,46 142.562.800,62
Beton bertulang Balok B.25 (30x50 cm) beton Fc'
26 4.28Z m3 6.932.241,70
25 13,87 96.153.658,47
Beton bertulang Balok B.26 (30x50 cm) beton Fc'
27 4.28AA m3 7.328.811,11
25 2,28 16.698.696,11
Beton bertulang Balok B.27 (30x60 cm) beton Fc'
28 4.28AB m3 7.328.811,11
25 2,17 15.929.170,95
Beton bertulang Balok B.28 (30x60 cm) beton Fc'
29 4.28AC m3 6.644.701,84
25 2,17 14.442.259,44
Beton bertulang Balok B.29 (25x50 cm) beton Fc'
30 4.28AD m3 7.942.680,20
25 3,05 24.185.461,21
Beton bertulang Balok Latiu BL.2 (30x60 cm)
31 4.28AE m3 8.119.564,18
beton K175 2,95 23.956.774,11
Beton bertulang Topi-topi T1 (15/20+10/40 cm)
32 4.29AP m3 6.215.545,47
beton K175 5,01 31.130.559,50
Beton bertulang Topi-topi T2 (15/20+10/50 cm)
33 4.29AQ m3 6.042.920,40
beton K175 4,84 29.250.756,18
Beton bertulang Tangga beton dari lt. 02 menuju
34 4.30 m3 7.753.713,75
lt. 03 (berikut pondasi dan balok bordes) 11,08 85.891.764,07
Beton bertulang plat lantai beton lt. 03 tebal 12
35 4.31 m3 7.572.085,04
cm 182,10 1.378.888.044,59
Beton bertulang Parapet PR.1 (10x50 cm) beton
36 4.33A m3 6.399.857,33
K175 6,31 40.386.299,71
Beton bertulang Parapet PR.2 (10x23 cm)
37 4.33B m3 8.404.126,54
betonK175 3,30 27.708.405,19
Beton bertulang Parapet PR.3 (10x48 cm)
38 4.33C m3 7.367.077,80
betonK175 3,66 26.996.656,59
Beton bertulang Parapet PR.4 (10x73 cm)
39 4.33D m3 4.105.929,15
betonK175 2,79 11.467.860,11
Beton bertulang Parapet PR.5A (10x48 cm) beton
40 4.33E m3 7.471.344,60
K175 0,46 3.451.761,20
Beton bertulang Parapet PR.6A (10x33 cm) beton
41 4.33F m3 7.714.646,45
K175 0,32 2.430.113,63
Beton bertulang Parapet PR.7A (10x68 cm) beton
42 4.33G m3 6.943.521,43
K175 0,65 4.520.232,45
Beton bertulang Parapet PR.8A (10x18 cm) beton
43 4.33H m3 8.642.501,46
K175 0,35 2.994.626,76

3.247.825.880,26
C. PEKERJAAN BETON BERTULANG LT. 03
Beton bertulang Kolom K2.A (45x55 cm) beton Fc'
1 4.27H m3 6.957.150,97
25 6,24 43.391.750,61
Beton bertulang Kolom K2.B (45x45 cm) beton Fc'
2 4.27B m3 6.060.140,75
25 40,82 247.399.186,01
Beton bertulang Kolom K1C (30x30 cm) beton Fc'
3 4.27C m3 7.488.672,28
25 0,38 2.830.718,12
Beton bertulang Kolom KP.1 (15x15 cm) beton
4 4.27F m3 8.382.880,79
K175 11,41 95.678.009,86
Beton bertulang Kolom KP.2 (15x30 cm) beton
5 4.27G m3 6.918.912,72
K175 2,98 20.632.197,73

46
Beton bertulang Balok B.02 (40x80 cm) beton Fc'
6 4.28B m3 6.046.880,86
25 7,36 44.508.066,55
Beton bertulang Balok B.03 (30x75 cm) beton Fc'
7 4.28C m3 8.075.055,30
25 23,53 190.010.088,77
Beton bertulang Balok B.04 (30x65 cm) beton Fc'
8 4.28D m3 7.209.489,32
25 7,84 56.547.629,49
Beton bertulang Balok B.05 (30x65 cm) beton Fc'
9 4.28E m3 7.117.408,82
25 18,77 133.622.233,12
Beton bertulang Balok B.07 (30x50 cm) beton Fc'
10 4.28G m3 7.153.129,44
25 1,68 12.017.257,45
Beton bertulang Balok B.09 (30x60 cm) beton Fc'
11 4.28I m3 7.033.073,46
25 2,38 16.763.330,59
Beton bertulang Balok B.11 (30x40 cm) beton Fc'
12 4.28K m3 7.114.562,10
25 1,97 14.044.145,59
Beton bertulang Balok B.11A (30x40 cm) beton Fc'
13 4.28L m3 7.153.346,67
25 0,97 6.910.132,88
Beton bertulang Balok B.12 (20x50 cm) beton Fc'
14 4.28M m3 8.790.098,57
25 2,79 24.550.745,29
Beton bertulang Balok B.13 (30x50 cm) beton Fc'
15 4.28N m3 7.838.943,49
25 1,89 14.815.603,19
Beton bertulang Balok B.15 (25x50 cm) beton Fc'
16 4.28P m3 7.333.404,91
25 13,70 100.485.980,75
Beton bertulang Balok B.16 (20x35 cm) beton Fc'
17 4.28Q m3 9.164.795,17
25 13,98 128.082.594,95
Beton bertulang Balok B.17 (20x40 cm) beton Fc'
18 4.28R m3 8.886.116,54
25 1,62 14.368.850,44
Beton bertulang Balok B.18 (25x70 cm) beton Fc'
19 4.28S m3 7.081.282,59
25 3,09 21.859.919,35
Beton bertulang Balok B.19 (15x50 cm) beton Fc'
20 4.28T m3 10.432.363,91
25 1,12 11.720.760,85
Beton bertulang Balok B.20 (20x35 cm) beton Fc'
21 4.28U m3 8.770.046,33
25 0,33 2.854.650,08
Beton bertulang Balok B.21 (20x35 cm) beton Fc'
22 4.28V m3 8.390.020,92
25 0,33 2.730.951,81
Beton bertulang Balok B.22 (40x90 cm) beton Fc'
23 4.28W m3 6.109.963,65
25 3,73 22.774.889,49
Beton bertulang Balok B.23 (40x80 cm) beton Fc'
24 4.28X m3 6.074.117,36
25 6,62 40.180.286,36
Beton bertulang Balok B.24 (30x65 cm) beton Fc'
25 4.28Y m3 6.642.568,29
25 21,46 142.562.800,62
Beton bertulang Balok B.25 (30x50 cm) beton Fc'
26 4.28Z m3 6.932.241,70
25 13,87 96.153.658,47
Beton bertulang Balok B.26 (30x50 cm) beton Fc'
27 4.28AA m3 7.328.811,11
25 2,28 16.698.696,11
Beton bertulang Balok B.27 (30x60 cm) beton Fc'
28 4.28AB m3 7.328.811,11
25 2,17 15.929.170,95
Beton bertulang Balok B.28 (30x60 cm) beton Fc'
29 4.28AC m3 6.644.701,84
25 2,17 14.442.259,44
Beton bertulang Balok B.29 (25x50 cm) beton Fc'
30 4.28AD m3 7.942.680,20
25 3,05 24.185.461,21
Beton bertulang Balok Latiu BL.2 (30x60 cm)
31 4.28AE m3 8.119.564,18
beton K175 2,95 23.956.774,11
Beton bertulang Topi-topi T1 (15/20+10/40 cm)
32 4.29AP m3 6.215.545,47
beton K175 5,01 31.130.559,50
Beton bertulang Topi-topi T2 (15/20+10/50 cm)
33 4.29AQ m3 6.042.920,40
beton K175 4,84 29.250.756,18
Beton bertulang Tangga beton dari lt. 02 menuju
34 4.30 m3 7.753.713,75
lt. 03 (berikut pondasi dan balok bordes) 11,08 85.891.764,07
Beton bertulang plat lantai beton lt. 03 tebal 12
35 4.31 m3 7.572.085,04
cm 182,10 1.378.888.044,59
Beton bertulang Parapet PR.1 (10x50 cm) beton
36 4.33A m3 6.399.857,33
K175 6,31 40.386.299,71
Beton bertulang Parapet PR.2 (10x23 cm)
37 4.33B m3 8.404.126,54
betonK175 3,30 27.708.405,19
Beton bertulang Parapet PR.3 (10x48 cm)
38 4.33C m3 7.367.077,80
betonK175 3,66 26.996.656,59
Beton bertulang Parapet PR.4 (10x73 cm)
39 4.33D m3 4.105.929,15
betonK175 2,79 11.467.860,11

47
Beton bertulang Parapet PR.5A (10x48 cm) beton
40 4.33E m3 7.471.344,60
K175 0,46 3.451.761,20
Beton bertulang Parapet PR.6A (10x33 cm) beton
41 4.33F m3 7.714.646,45
K175 0,32 2.430.113,63
Beton bertulang Parapet PR.7A (10x68 cm) beton
42 4.33G m3 6.943.521,43
K175 0,65 4.520.232,45
Beton bertulang Parapet PR.8A (10x18 cm) beton
43 4.33H m3 8.642.501,46
K175 0,35 2.994.626,76

3.247.825.880,26

-
D. PEKERJAAN BETON BERTULANG LT. 04
Beton bertulang Kolom K2.A (45x55 cm) beton Fc'
1 4.27H m3 4.858.712,10
25 6,24 30.303.787,36
Beton bertulang Kolom K2.B (45x45 cm) beton Fc'
2 4.27B m3 4.051.917,11
25 40,82 165.415.463,93
Beton bertulang Kolom K1C (30x30 cm) beton Fc'
3 4.27C m3 4.956.042,98
25 0,38 1.873.384,25
Beton bertulang Kolom KP.1 (15x15 cm) beton
4 4.27F m3 5.519.597,09
K175 11,41 62.997.921,41
Beton bertulang Kolom KP.2 (15x30 cm) beton
5 4.27G m3 4.523.212,48
K175 2,98 13.488.219,63
Beton bertulang Balok B.02 (40x80 cm) beton Fc'
6 4.28B m3 4.233.237,17
25 7,36 31.158.742,21
Beton bertulang Balok B.03 (30x75 cm) beton Fc'
7 4.28C m3 5.628.761,61
25 23,53 132.447.575,06
Beton bertulang Balok B.04 (30x65 cm) beton Fc'
8 4.28D m3 5.039.652,71
25 7,84 39.528.516,02
Beton bertulang Balok B.05 (30x65 cm) beton Fc'
9 4.28E m3 4.978.756,62
25 18,77 93.471.176,86
Beton bertulang Balok B.07 (30x50 cm) beton Fc'
10 4.28G m3 5.007.060,69
25 1,68 8.411.861,95
Beton bertulang Balok B.09 (30x60 cm) beton Fc'
11 4.28I m3 4.922.466,53
25 2,38 11.732.698,97
Beton bertulang Balok B.11 (30x40 cm) beton Fc'
12 4.28K m3 4.985.136,67
25 1,97 9.840.659,78
Beton bertulang Balok B.11A (30x40 cm) beton Fc'
13 4.28L m3 5.007.208,54
25 0,97 4.836.963,45
Beton bertulang Balok B.12 (20x50 cm) beton Fc'
14 4.28M m3 6.150.024,87
25 2,79 17.177.019,45
Beton bertulang Balok B.13 (30x50 cm) beton Fc'
15 4.28N m3 5.473.829,45
25 1,89 10.345.537,66
Beton bertulang Balok B.15 (25x50 cm) beton Fc'
16 4.28P m3 5.141.290,80
25 13,70 70.448.537,13
Beton bertulang Balok B.16 (20x35 cm) beton Fc'
17 4.28Q m3 6.412.459,90
25 13,98 89.617.333,30
Beton bertulang Balok B.17 (20x40 cm) beton Fc'
18 4.28R m3 6.219.700,34
25 1,62 10.057.255,45
Beton bertulang Balok B.18 (25x70 cm) beton Fc'
19 4.28S m3 4.964.751,99
25 3,09 15.326.189,38
Beton bertulang Balok B.19 (15x50 cm) beton Fc'
20 4.28T m3 7.296.593,68
25 1,12 8.197.723,00
Beton bertulang Balok B.20 (20x35 cm) beton Fc'
21 4.28U m3 6.143.791,69
25 0,33 1.999.804,20
Beton bertulang Balok B.21 (20x35 cm) beton Fc'
22 4.28V m3 5.864.754,50
25 0,33 1.908.977,59
Beton bertulang Balok B.22 (40x90 cm) beton Fc'
23 4.28W m3 4.274.970,24
25 3,73 15.934.951,57
Beton bertulang Balok B.23 (40x80 cm) beton Fc'
24 4.28X m3 4.251.774,49
25 6,62 28.125.488,23
Beton bertulang Balok B.24 (30x65 cm) beton Fc'
25 4.28Y m3 4.655.577,59
25 21,46 99.918.006,14
Beton bertulang Balok B.25 (30x50 cm) beton Fc'
26 4.28Z m3 4.856.723,29
25 13,87 67.365.180,45

48
Beton bertulang Balok B.26 (30x50 cm) beton Fc'
27 4.28AA m3 5.130.955,70
25 2,28 11.690.882,57
Beton bertulang Balok B.27 (30x60 cm) beton Fc'
28 4.28AB m3 5.130.955,70
25 2,17 11.152.132,22
Beton bertulang Balok B.28 (30x60 cm) beton Fc'
29 4.28AC m3 4.658.138,69
25 2,17 10.124.464,45
Beton bertulang Balok B.29 (25x50 cm) beton Fc'
30 4.28AD m3 5.555.966,86
25 3,05 16.917.919,10
Beton bertulang Balok Latiu BL.2 (30x60 cm)
31 4.28AE m3 5.676.355,06
beton K175 2,95 16.748.085,60
Beton bertulang Topi-topi T1 (15/20+10/40 cm)
32 4.29AP m3 4.073.699,96
beton K175 5,01 20.403.126,26
Beton bertulang Topi-topi T2 (15/20+10/50 cm)
33 4.29AQ m3 3.958.948,19
beton K175 4,84 19.163.288,69
Beton bertulang Parapet PR.1 (10x50 cm) beton
34 4.33A m3 4.099.322,31
K175 6,31 25.868.773,43
Beton bertulang Parapet PR.2 (10x23 cm)
35 4.33B m3 5.365.187,30
betonK175 3,30 17.689.022,53
Beton bertulang Parapet PR.3 (10x48 cm)
36 4.33C m3 4.694.084,59
betonK175 3,66 17.201.472,99
Beton bertulang Parapet PR.4 (10x73 cm)
37 4.33D m3 2.695.489,65
betonK175 2,79 7.528.502,59
Beton bertulang Parapet PR.5A (10x48 cm) beton
38 4.33E m3 4.810.098,19
K175 0,46 2.222.265,37
Beton bertulang Parapet PR.6A (10x33 cm) beton
39 4.33F m3 4.916.123,15
K175 0,32 1.548.578,79
Beton bertulang Parapet PR.7A (10x68 cm) beton
40 4.33G m3 4.415.204,19
K175 0,65 2.874.297,93
Beton bertulang Parapet PR.8A (10x18 cm) beton
41 4.33H m3 5.508.910,14
K175 0,35 1.908.837,36

1.224.970.624,32

11.824.059.505,92
VI. PEKERJAAN ATAP
Beton bertulang Kolom K3.A (45x55 cm) beton Fc'
1 Dihit m3 4.051.917,11
25 14,82 60.031.177,88
Beton bertulang Kolom K3.B (45x45 cm) beton Fc'
2 5.13. m3 4.956.042,98
25 14,82 73.426.254,78
Beton bertulang Kolom K1.C (30x30 cm) beton Fc'
3 Dihit m3 5.519.597,09
25 1,72 9.504.746,19
Beton bertulang Kolom KP.1 (15x15 cm) beton
4 Dihit m3 4.523.212,48
K175 15,11 68.343.479,03
Beton bertulang Kolom KP.2 (15x30 cm) beton
5 Dihit m3 4.233.237,17
K175 2,98 12.623.513,25
Beton bertulang Balok B.16 (20x35 cm) beton Fc'
6 Dihit m3 5.628.761,61
25 8,43 47.447.083,11
Beton bertulang Balok B.30 (20x35 cm) beton Fc'
7 VIII m3 5.039.652,71
25 10,89 54.863.675,24
Beton bertulang Balok B.31 (25x40 cm) beton Fc'
8 8.34. m3 4.978.756,62
25 14,89 74.149.618,15
Beton bertulang Balok B.32 (15x30 cm) beton Fc'
9 8.35. m3 5.007.060,69
25 2,65 13.248.682,58
Beton bertulang Balok B.33 (15x30 cm) beton Fc'
10 8.36. m3 4.922.466,53
25 0,95 4.651.730,87
Beton bertulang Balok B.34 (15x30 cm) beton Fc'
11 8.37. m3 4.985.136,67
25 0,53 2.638.134,33
Beton bertulang Balok Lisplank (10x30 cm) beton
12 10.5. m3 5.007.208,54
Fc' 25 1,19 5.962.083,21
13 Beton bertulang plat dag beton atap tebal 13 cm 8.55. m3 6.150.024,87
180,99 1.113.090.233,24

1.539.980.411,86
VII. PEKERJAAN KUSEN, PINTU, JENDELA

49
A. PEKERJAAN KUSEN, PINTU DAN JENDELA LT. 01

1 Kusen dan daun pintu PF Dihit unit 20.493.753,64


2,00 40.987.507,28
2 Kusen dan daun pintu PJ1 Dihit unit 16.686.717,53
2,00 33.373.435,05
3 Kusen dan daun pintu PJ2 Dihit unit 9.610.915,46
1,00 9.610.915,46
4 Kusen dan daun pintu P1 Dihit unit 8.083.945,61
15,00 121.259.184,17
5 Kusen dan daun pintu P2 Dihit unit 4.550.047,37
5,00 22.750.236,86
6 Kusen dan daun pintu P3 Dihit unit 4.608.482,77
5,00 23.042.413,84
7 Kusen dan daun pintu P4 Dihit unit 2.924.825,07
6,00 17.548.950,42
8 Kusen dan daun pintu PS Dihit unit 4.768.345,78
1,00 4.768.345,78
9 Kusen dan daun jendela J1 Dihit unit 10.907.364,20
20,00 218.147.283,90
10 Kusen dan daun jendela J2 Dihit unit 3.785.478,34
16,00 60.567.653,49
11 Kusen dan daun jendela J3 Dihit unit 3.425.072,49
24,00 82.201.739,76
12 Kusen dan daun jendela J4 Dihit unit 8.254.795,38
8,00 66.038.363,05
13 Kusen dan bouven BV1 Dihit unit 2.429.048,52
14,00 34.006.679,31
14 Kusen dan bouven BV2 Dihit unit 3.924.282,65
13,00 51.015.674,48
15 Kusen dan bouven BV3 Dihit unit 2.404.388,81
2,00 4.808.777,61

790.127.160,44
B. PEKERJAAN KUSEN, PINTU DAN JENDELA LT. 02

1 Kusen dan daun pintu PJ2 Dihit unit 9.610.915,46


1,00 9.610.915,46
2 Kusen dan daun pintu PJ3 Dihit unit 10.813.692,60
4,00 43.254.770,41
3 Kusen dan daun pintu P1 Dihit unit 8.083.945,61
6,00 48.503.673,67
4 Kusen dan daun pintu P2 Dihit unit 4.550.047,37
4,00 18.200.189,49
5 Kusen dan daun pintu P3 Dihit unit 4.608.482,77
5,00 23.042.413,84
6 Kusen dan daun pintu P4 Dihit unit 2.924.825,07
6,00 17.548.950,42
7 Kusen dan daun pintu PS Dihit unit 4.768.345,78
1,00 4.768.345,78
8 Kusen dan daun jendela J1 Dihit unit 10.907.364,20
20,00 218.147.283,90
9 Kusen dan daun jendela J2 Dihit unit 3.785.478,34
16,00 60.567.653,49
10 Kusen dan daun jendela J3 Dihit unit 3.425.072,49
24,00 82.201.739,76
11 Kusen dan daun jendela J4 Dihit unit 8.254.795,38
8,00 66.038.363,05
12 Kusen dan daun jendela J5 Dihit unit 4.073.758,75
4,00 16.295.035,02
13 Kusen dan daun jendela J6 Dihit unit 3.877.528,08
6,00 23.265.168,45
14 Kusen dan daun jendela J7 Dihit unit 4.388.060,60
2,00 8.776.121,19
15 Kusen dan daun jendela J8 Dihit unit 63.612.000,00
1,00 63.612.000,00
16 Kusen dan bouven BV1 Dihit unit 2.429.048,52
10,00 24.290.485,22

50
17 Kusen dan bouven BV2 Dihit unit 3.924.282,65
13,00 51.015.674,48
18 Kusen dan bouven BV3 Dihit unit 2.404.388,81
2,00 4.808.777,61

783.947.561,22
C. PEKERJAAN KUSEN, PINTU DAN JENDELA LT. 03

1 Kusen dan daun pintu PJ2 Dihit unit 9.610.915,46


1,00 9.610.915,46
2 Kusen dan daun pintu PJ3 Dihit unit 10.813.692,60
4,00 43.254.770,41
3 Kusen dan daun pintu P1 Dihit unit 8.083.945,61
6,00 48.503.673,67
4 Kusen dan daun pintu P2 Dihit unit 4.550.047,37
4,00 18.200.189,49
5 Kusen dan daun pintu P3 Dihit unit 4.608.482,77
5,00 23.042.413,84
6 Kusen dan daun pintu P4 Dihit unit 2.924.825,07
6,00 17.548.950,42
7 Kusen dan daun pintu PS Dihit unit 4.768.345,78
1,00 4.768.345,78
8 Kusen dan daun jendela J1 Dihit unit 10.907.364,20
20,00 218.147.283,90
9 Kusen dan daun jendela J2 Dihit unit 3.785.478,34
16,00 60.567.653,49
10 Kusen dan daun jendela J3 Dihit unit 3.425.072,49
24,00 82.201.739,76
11 Kusen dan daun jendela J4 Dihit unit 8.254.795,38
8,00 66.038.363,05
12 Kusen dan daun jendela J5 Dihit unit 4.073.758,75
4,00 16.295.035,02
13 Kusen dan daun jendela J6 Dihit unit 3.877.528,08
6,00 23.265.168,45
14 Kusen dan daun jendela J7 Dihit unit 4.388.060,60
2,00 8.776.121,19
15 Kusen dan daun jendela J8 Dihit unit 63.612.000,00
1,00 63.612.000,00
16 Kusen dan bouven BV1 Dihit unit 2.429.048,52
10,00 24.290.485,22
17 Kusen dan bouven BV2 Dihit unit 3.924.282,65
13,00 51.015.674,48
18 Kusen dan bouven BV3 Dihit unit 2.404.388,81
2,00 4.808.777,61

783.947.561,22
PEKERJAAN KUSEN, PINTU DAN JENDELA LT. 04
D.
DAN ATAP
1 Kusen dan daun pintu PJ4 Dihit unit 9.143.830,04
2,00 18.287.660,08
2 Kusen dan daun pintu PJ5 Dihit unit 10.433.402,70
2,00 20.866.805,39
3 Kusen dan daun pintu P1 Dihit unit 8.083.945,61
13,00 105.091.292,94
4 Kusen dan daun pintu P3 Dihit unit 4.608.482,77
4,00 18.433.931,07
5 Kusen dan daun pintu P4 Dihit unit 2.924.825,07
6,00 17.548.950,42
6 Kusen dan daun pintu PS Dihit unit 4.768.345,78
1,00 4.768.345,78
4 Kusen dan daun jendela J1 Dihit unit 10.907.364,20
4,00 43.629.456,78
5 4Kusen dan daun jendela J4 Dihit unit 8.254.795,38
8,00 66.038.363,05

51
6 7Kusen dan daun jendela J7 Dihit unit 4.388.060,60
2,00 8.776.121,19
7 Kusen dan daun jendela J9 Dihit unit 2.525.755,04
2,00 5.051.510,08
8 Kusen dan daun jendela J10 Dihit unit 1.343.867,40
4,00 5.375.469,60
9 Kusen dan daun jendela J11 Dihit unit 2.466.328,01
24,00 59.191.872,25
10 Kusen dan daun jendela J12 Dihit unit 1.127.462,15
8,00 9.019.697,18
11 Kusen dan daun jendela J13 Dihit unit 2.988.991,17
8,00 23.911.929,36
12 Kusen dan daun jendela J14 Dihit unit 2.778.636,37
4,00 11.114.545,46
9 Kusen dan bouven BV1 Dihit unit 2.429.048,52
15,00 36.435.727,83
10 Kusen dan bouven BV2 Dihit unit 3.924.282,65
13,00 51.015.674,48
11 Kusen dan bouven BV3 Dihit unit 2.404.388,81
2,00 4.808.777,61
12 Kusen dan bouven BV4 Dihit unit 3.546.601,32
2,00 7.093.202,64

516.459.333,19

2.874.481.616,07
VIII. PEKERJAAN PLAFOND DAN PENGGANTUNG
PEKERJAAN PLAFOND DAN PENGGANTUNG LT.
A. 01

Pekerjaan plafond gypsum 9mm rangka holow


galvanis
1 9.1. m2 155.292,30
1.490,80 231.509.838,49

Pekerjaan plafond calsiboard 4 mm rangka holow


galvanis
2 9.7. m2 155.292,30
83,63 12.987.483,28

Pekerjaan drof of plafond gypsumboard 8 mm


rangka holow galvanis
3 Dihitun m' 72.000,00
214,31 15.429.960,00

Pekerjaan coumpoun beton ekspose (bawah


tangga)
4 9.5. m2 77.220,90
49,63 3.832.743,54

Pekerjaan plafond Alumunium Composit Panel


(ACP)
5 9.8. m2 1.068.606,00
161,18 172.232.572,05

Pekerjaan lis profil gypsum


6 9.8. m' 23.526,90
1.160,87 27.311.660,64

463.304.258,00
PEKERJAAN PLAFOND DAN PENGGANTUNG LT.
B. 02

Pekerjaan plafond gypsum 9mm rangka holow


1 9.1. m2 155.292,30
galvanis 1.520,56 236.130.871,46
Pekerjaan plafond calsiboard 4 mm rangka holow
2 9.7. m2 155.292,30
galvanis 55,18 8.568.640,88
Pekerjaan drof of plafond gypsumboard 8 mm
3 Dihitun m' 72.000,00
rangka holow galvanis 153,51 11.052.720,00
Pekerjaan coumpoun beton ekspose (bawah
4 9.5. m2 77.220,90
tangga) 49,63 3.832.743,54

52
5 Pekerjaan lis profil gypsum 9.8. m' 23.526,90
737,96 17.361.934,65

276.946.910,53
PEKERJAAN PLAFOND DAN PENGGANTUNG LT.
C. 03

Pekerjaan plafond gypsum 9mm rangka holow


1 9.1. m2 155.292,30
galvanis 1.520,56 236.130.871,46
Pekerjaan plafond calsiboard 4 mm rangka holow
2 9.7. m2 155.292,30
galvanis 55,18 8.568.640,88
Pekerjaan drof of plafond gypsumboard 8 mm
3 Dihitun m' 72.000,00
rangka holow galvanis 153,51 11.052.720,00
Pekerjaan coumpoun beton ekspose (bawah
4 9.5. m2 77.220,90
tangga) 49,63 3.832.743,54
5 Pekerjaan lis profil gypsum 9.8. m' 23.526,90
737,96 17.361.934,65

276.946.910,53
PEKERJAAN PLAFOND DAN PENGGANTUNG LT.
D.
04
Pekerjaan plafond gypsum 9mm rangka holow
galvanis
1 9.1. m2 155.292,30
1.520,56 236.130.871,46

Pekerjaan plafond calsiboard 4 mm rangka holow


galvanis
2 9.7. m2 155.292,30
296,94 46.112.495,56

Pekerjaan coumpoun beton ekspose


3 9.5. m2 77.220,90
49,63 3.832.743,54
Pekerjaan lis profil gypsum
4 9.5. m' 23.526,90
737,96 17.361.934,65

67.307.173,75

1.084.505.252,81
IX. PEKERJAAN PENUTUP LANTAI DAN DINDING
PEKERJAAN PENUTUP LANTAI DAN DINDING LT.
A.
01
Pekerjaan penutup lantai granite tile 60x60 cm
1 8.34. m2 407.399,40
polished 1.619,99 659.983.972,50
Pekerjaan penutup lantai granite tile 60x60 cm
2 8.35. m2 437.653,80
teksture/unpolished 15,75 6.893.047,35
Pekerjaan penutup lantai keramik 30x30 cm
3 8.36. m2 319.007,70
teksture/unpolish 56,07 17.886.761,74
Pekerjaan penutup lantai keramik batu andesit
4 8.37. m2 348.078,60
finishing coating natural 49,12 17.097.272,75
5 Pekerjaan penutup dinding keramik 30x60 cm 8.54. m2 521.486,10
265,05 138.220.673,03
Pekerjaan penutup dinding batu alam andesit
6 8.55. m2 367.784,10
coating natural 124,87 45.923.729,43
Pekerjaan penutup dinding Alumunium Composite
7 Dihit m2 1.068.606,00
Panel (ACP) type PVDF 278,91 298.046.502,37
Pekerjaan penutup dinding (Back Drop) multiplek
8 Dihit m2 556.286,40
12 mm lapis HPL rangka holow galvanish 19,20 10.683.202,17
Pekerjaan step nosing tangga granite tile 10x60
9 8.58. m' 118.916,10
cm 80,64 9.589.394,30
10 Pekerjaan plint lantai granite tile 10x60 cm 8.59. m' 37.255,50
745,66 27.779.842,99
Pekerjaan rabat beton bawah lantai dan tritisan
11 4.4 m3 1.338.326,10
keliling bangunan tebal 5 cm 114,75 153.578.942,44

53
1.385.683.341,09
PEKERJAAN PENUTUP LANTAI DAN DINDING LT.
B.
02
Pekerjaan penutup lantai granite tile 60x60 cm
1 8.34. m2 407.399,40
polished 1.608,05 655.120.234,77
Pekerjaan penutup lantai keramik 30x30 cm
2 8.36. m2 319.007,70
teksture/unpolish 56,07 17.886.761,74
3 Pekerjaan penutup dinding keramik 30x60 cm 8.54. m2 521.486,10
252,35 131.595.192,13
Pekerjaan penutup dinding Alumunium Composite
4 Dihit m2 1.068.606,00
Panel (ACP) type PVDF 264,89 283.067.317,76
Pekerjaan penutup dinding multiplek 12 mm lapis
5 Dihit m2 556.286,40
HPL rangka holow galvanish 228,54 127.135.362,72
Pekerjaan step nosing tangga granite tile 10x60
6 8.58. m' 118.916,10
cm 79,59 9.464.532,40
7 Pekerjaan plint lantai granite tile 10x60 cm 8.59. m' 37.255,50
756,26 28.174.937,57

1.252.444.339,09
PEKERJAAN PENUTUP LANTAI DAN DINDING LT.
C.
03
Pekerjaan penutup lantai granite tile 60x60 cm
1 8.34. m2 407.399,40
polished 1.608,05 655.120.234,77
Pekerjaan penutup lantai keramik 30x30 cm
2 8.36. m2 319.007,70
teksture/unpolish 56,07 17.886.761,74
3 Pekerjaan penutup dinding keramik 30x60 cm 8.54. m2 521.486,10
252,35 131.595.192,13
Pekerjaan penutup dinding Alumunium Composite
4 Dihit m2 1.068.606,00
Panel (ACP) type PVDF 264,89 283.067.317,76
Pekerjaan penutup dinding multiplek 12 mm lapis
5 Dihit m2 556.286,40
HPL rangka holow galvanish 228,54 127.135.362,72
Pekerjaan step nosing tangga granite tile 10x60
6 8.58. m' 118.916,10
cm 79,59 9.464.532,40
7 Pekerjaan plint lantai granite tile 10x60 cm 8.59. m' 37.255,50
756,26 28.174.937,57

1.252.444.339,09
PEKERJAAN PENUTUP LANTAI DAN DINDING LT.
D.
04
Pekerjaan penutup lantai granite tile 60x60 cm
1 Dihit m2 407.399,40
polished 1.608,05 655.120.234,77
Pekerjaan penutup lantai keramik 30x30 cm
2 8.59. m2 319.007,70
teksture/unpolish 56,07 17.886.761,74
3 Pekerjaan penutup dinding keramik 30x60 cm 0 m2 521.486,10
252,35 131.595.192,13
Pekerjaan penutup dinding Alumunium Composite
4 8.34. m2 1.068.606,00
Panel (ACP) type PVDF 264,89 283.067.317,76
Pekerjaan penutup dinding multiplek 12 mm lapis
5 8.34. m2 556.286,40
HPL rangka holow galvanish 265,41 147.643.138,99
Pekerjaan step nosing tangga granite tile 10x60
6 8.54. m' 118.916,10
cm 79,59 9.464.532,40
7 Pekerjaan plint lantai granite tile 10x60 cm Dihit m' 37.255,50
756,26 28.174.937,57

1.272.952.115,37

5.163.524.134,63
PEKERJAAN PENGECATAN DAN
X.
WATERPROOFING
PEKERJAAN PENGECATAN DAN
A.
WATERPROOFING LT. 01

54
Pekerjaan pengecatan dinding eksterior dengan
1 13.10. B m2 47.742,30
cat weathersield 570,21 27.223.280,11
2 Pekerjaan pengecatan dinding interior 13.10. A m2 47.742,30
2.025,64 96.708.664,83
3 Pekerjaan Pengecatan Plafond 13.10. C m2 26.635,50
1.624,07 43.257.823,26
Pekerjaan Screeding dan Waterproofing liquid
4 Dihitung m2 211.365,00
membran (R. KM/WC ) 56,07 11.851.235,55

179.041.003,75
PEKERJAAN PENGECATAN DAN
B.
WATERPROOFING LT. 02
Pekerjaan pengecatan dinding eksterior dengan
1 13.10. B m2 47.742,30
cat weathersield 655,52 31.295.793,78
2 Pekerjaan pengecatan dinding interior 13.10. A m2 47.742,30
1.966,53 93.886.880,06
3 Pekerjaan Pengecatan Plafond 13.10. C m2 26.635,50
2.025,64 53.953.907,58
Pekerjaan Screeding dan Waterproofing liquid
4 Dihitung m2 211.365,00
membran (R. KM/WC dan dag canopy) 149,23 31.541.153,49

210.677.734,92
PEKERJAAN PENGECATAN DAN
C.
WATERPROOFING LT. 03
Pekerjaan pengecatan dinding eksterior dengan
1 13.10. B m2 47.742,30
cat weathersield 655,52 31.295.793,78
2 Pekerjaan pengecatan dinding interior 13.10. A m2 47.742,30
1.966,53 93.886.880,06
3 Pekerjaan Pengecatan Plafond 13.10. C m2 26.635,50
2.025,64 53.953.907,58
Pekerjaan Screeding dan Waterproofing liquid
4 14.15. m2 211.365,00
membran (R. KM/WC dan dag canopy) 149,23 31.541.153,49

210.677.734,92
PEKERJAAN PENGECATAN DAN
D.
WATERPROOFING LT. 04
Pekerjaan pengecatan dinding eksterior dengan
1 13.10. C m2 26.635,50
cat weathersield 608,67 16.212.349,64
2 Pekerjaan pengecatan dinding interior 13.10. B m2 47.742,30
1.826,01 87.178.060,45
3 Pekerjaan Pengecatan Plafond 13.10. B m2 47.742,30
787,59 37.601.572,90
Pekerjaan pengecatan pasangan kerpus/bubungan
4 13.10. C m2 26.635,50
atap 58,33 1.553.582,13
5 Pekerjaan Pengecatan lisplank GRC 13.10. C m2 26.635,50
61,29 1.632.449,84
Pekerjaan Screeding dan Waterproofing liquid
6 14.18. m2 211.365,00
membran (R. Km/WC dan Dag Atap) 1.588,65 335.785.007,25

479.963.022,21

1.080.359.495,80
XI. PEKERJAAN SANITERI DAN PLUMBING

A. PEKERJAAN SANITERI

Lantai 01

1 Pekerjaan pasang closet duduk monoblok 14.1. bh 3.118.203,00


4,00 12.472.812,00
2 Pekerjaan pasang kran air 3/4 " 14.18. bh 91.030,50
10,00 910.305,00

55
3 Pekerjaan pasang floordarin 14.15. bh 110.755,80
5,00 553.779,00
4 Pekerjaan wastafel keramik 14.2A. bh 1.066.251,60
4,00 4.265.006,40
5 Pekerjaan urinoir muslim 14.2.B bh 2.105.751,60
3,00 6.317.254,80
6 Pekerjaan sekat urinoir 14.2.C bh 1.363.251,60
3,00 4.089.754,80
7 Pekerjaan pasang handwash/jetwasher 14.15. m' 135.505,80
4,00 542.023,20
Pekerjaan meja wastafel lapis granite tile rangka
8 Dihitung bh 1.350.000,00
besi siku 2,00 2.700.000,00
9 Pekerjaan pasang kaca cemin Dihitung bh 1.125.000,00
2,00 2.250.000,00
10 Ember besar Dihit bh 180.000,00
4,00 720.000,00

Lantai 02

1 Pekerjaan pasang closet duduk monoblok 14.1. bh 3.118.203,00


4,00 12.472.812,00
2 Pekerjaan pasang kran air 3/4 " 14.18. bh 91.030,50
10,00 910.305,00
3 Pekerjaan pasang floordarin 14.15. bh 110.755,80
5,00 553.779,00
4 Pekerjaan wastafel keramik 14.2A. bh 1.066.251,60
4,00 4.265.006,40
5 Pekerjaan urinoir muslim 14.2.B bh 2.105.751,60
3,00 6.317.254,80
6 Pekerjaan sekat urinoir 14.2.C bh 1.363.251,60
3,00 4.089.754,80
7 Pekerjaan pasang handwash/jetwasher 14.15. m' 135.505,80
4,00 542.023,20
Pekerjaan meja wastafel lapis granite tile rangka
8 Dihitung bh 1.350.000,00
besi siku 2,00 2.700.000,00
9 Pekerjaan pasang kaca cemin Dihitung bh 1.125.000,00
2,00 2.250.000,00
10 Ember besar Dihit bh 180.000,00
4,00 720.000,00

Lantai 03

1 Pekerjaan pasang closet duduk monoblok 14.1. bh 3.118.203,00


4,00 12.472.812,00
2 Pekerjaan pasang kran air 3/4 " 14.18. bh 91.030,50
10,00 910.305,00
3 Pekerjaan pasang floordarin 14.15. bh 110.755,80
5,00 553.779,00
4 Pekerjaan wastafel keramik 14.2A. bh 1.066.251,60
4,00 4.265.006,40
5 Pekerjaan urinoir muslim 14.2.B bh 2.105.751,60
3,00 6.317.254,80
6 Pekerjaan sekat urinoir 14.2.C bh 1.363.251,60
3,00 4.089.754,80
6 Pekerjaan pasang handwash/jetwasher 14.15. m' 135.505,80
4,00 542.023,20
Pekerjaan meja wastafel lapis granite tile rangka
7 Dihitung bh 1.350.000,00
besi siku 2,00 2.700.000,00
8 Pekerjaan pasang kaca cemin Dihitung bh 1.125.000,00
2,00 2.250.000,00
9 Ember besar Dihit bh 180.000,00
4,00 720.000,00

Lantai 04

56
1 Pekerjaan pasang closet duduk monoblok 14.1. bh 3.118.203,00
19,00 59.245.857,00
2 Pekerjaan pasang kran air 3/4 " 14.18. bh 91.030,50
19,00 1.729.579,50
3 Pekerjaan pasang floordarin 14.15. bh 110.755,80
19,00 2.104.360,20
4 Pekerjaan wastafel keramik 14.2A. bh 1.066.251,60
19,00 20.258.780,40
5 Pekerjaan urinoir muslim 14.2.B bh 2.105.751,60
19,00 40.009.280,40
6 Pekerjaan sekat urinoir 14.2.C bh 1.363.251,60
19,00 25.901.780,40
6 Pekerjaan pasang handwash/jetwasher 14.15. m' 135.505,80
19,00 2.574.610,20
Pekerjaan meja wastafel lapis granite tile rangka
7 Dihitung bh 1.350.000,00
besi siku 19,00 25.650.000,00
8 Pekerjaan pasang kaca cemin Dihitung bh 1.125.000,00
19,00 21.375.000,00
9 Ember besar Dihit bh 180.000,00
19,00 3.420.000,00

306.732.053,70
B. PEKERJAAN PLUMBING

PEKERJAAN AIR BERSIH

Pengadaan dan pemasangan Roof Tank unit 4.050.000,00


4,00 16.200.000,00
Pengadaan, Pemasangan Roof Tank
Type
: Tangki Fiber

Kapasitas : 2 x 2.000 liter


Lengkap dengan instalasi, WLC dan accessories
lainnya
Pemipaan Lengkap, accessories + Fitting

Dudukan Frame Stud Support Tanki Air Atas ls 2.700.000,00


2,00 5.400.000,00
Pipa Header Roof Tank

PPR PN-10 : Dia. 3" (Lengkap dengan innstalasi) ls 2.700.000,00


2,00 5.400.000,00
Pipa suplay dari tower air existing

PPR PN-10 : Dia. 2" m 176.491,80


130,00 22.943.934,00
Pipa drain dari roof tank

PVC AW : Dia. 1 1/2" m 38.164,50


130,00 4.961.385,00
Pekerjaan Instalasi

Pemipaan air bersih

Lantai 04

PPR PN-10 : Dia. 1 1/2" m 111.939,30


86,00 9.626.779,80
PPR PN-10 : Dia. 1 " m 49.365,90
154,00 7.602.348,60
PPR PN-10 : Dia. 1/2 " m 32.245,20
40,00 1.289.808,00
PPR PN-10 : Dia. 3/4 " m 25.509,60
42,00 1.071.403,20
Lantai 03

PPR PN-10 : Dia. 1 1/2" m 111.939,30


86,00 9.626.779,80

57
PPR PN-10 : Dia. 1 " m 49.365,90
24,00 1.184.781,60
PPR PN-10 : Dia. 3/4 " m 32.245,20
40,00 1.289.808,00
PPR PN-10 : Dia. 1/2 " m 25.509,60
42,00 1.071.403,20
Lantai 02

PPR PN-10 : Dia. 1 1/2" m 111.939,30


86,00 9.626.779,80
PPR PN-10 : Dia. 1 " m 49.365,90
154,00 7.602.348,60
PPR PN-10 : Dia. 1/2 " m 32.245,20
40,00 1.289.808,00
PPR PN-10 : Dia. 3/4 " m 25.509,60
42,00 1.071.403,20
Lantai 01

PPR PN-10 : Dia. 1 1/2" m 111.939,30


86,00 9.626.779,80
PPR PN-10 : Dia. 1 " m 49.365,90
24,00 1.184.781,60
PPR PN-10 : Dia. 3/4 " m 32.245,20
40,00 1.289.808,00
PPR PN-10 : Dia. 1/2 " m 25.509,60
42,00 1.071.403,20

PEKERJAAN AIR KOTOR DAN AIR BEKAS

INSTALASI UTAMA

Pipa induk air kotor menuju septictank


Pipa PVC
: Dia. 8" m 295.368,30
AW 48,00 14.177.678,40
Pipa PVC
: Dia. 6" m 195.331,50
AW 54,00 10.547.901,00
Galian pipa m 13.500,00
54,00 729.000,00
Bak
bh 540.414,00
kontrol 2,00 1.080.828,00
Septictank bio filter kap. 10 m3 unit 27.000.000,00
2,00 54.000.000,00
Sumur resapan bh 1.980.000,00
2,00 3.960.000,00
INSTALASI DALAM GEDUNG

Pipa riser
Pipa PVC
: Dia. 6" ( Pipa Air Kotor ) m 195.331,50
AW 72,00 14.063.868,00
Pipa PVC
: Dia. 4" ( Air Bekas ) m 134.587,80
AW 72,00 9.690.321,60
Pipa PVC
: Dia. 2" ( Vent ) m 59.815,80
AW 72,00 4.306.737,60
Pemipaan lantai 04
Pipa PVC
: Dia. 6" ( Pipa Air Kotor ) m 195.331,50
AW 14,00 2.734.641,00
Pipa PVC
: Dia. 4" ( Pipa Air Kotor ) m 134.587,80
AW 42,00 5.652.687,60
Pipa PVC
: Dia. 3" ( Air Bekas ) m 82.062,90
AW 14,00 1.148.880,60
Pipa PVC
: Dia. 2" ( Air Bekas ) m 59.815,80
AW 52,00 3.110.421,60
Pipa PVC
: Dia. 1,5" ( Vent ) m 38.164,50
AW 38,00 1.450.251,00
Floor
: Dia. 2" m 83.530,80
Drain 18,00 1.503.554,40

58
Clean Out : Dia. 4" bh 229.500,00
2,00 459.000,00
Clean Out : Dia. 3" bh 193.500,00
2,00 387.000,00
Pemipaan lantai 03
Pipa PVC
: Dia. 6" ( Pipa Air Kotor ) m 195.331,50
AW 14,00 2.734.641,00
Pipa PVC
: Dia. 4" ( Pipa Air Kotor ) m 134.587,80
AW 42,00 5.652.687,60
Pipa PVC
: Dia. 3" ( Air Bekas ) m 82.062,90
AW 14,00 1.148.880,60
Pipa PVC
: Dia. 2" ( Air Bekas ) m 59.815,80
AW 52,00 3.110.421,60
Pipa PVC
: Dia. 1,5" ( Vent ) m 38.164,50
AW 38,00 1.450.251,00
Floor
: Dia. 2" m 83.530,80
Drain 18,00 1.503.554,40
Clean Out : Dia. 4" bh 229.500,00
2,00 459.000,00
Clean Out : Dia. 3" bh 193.500,00
2,00 387.000,00
Pemipaan lantai 02
Pipa PVC
: Dia. 6" ( Pipa Air Kotor ) m 195.331,50
AW 14,00 2.734.641,00
Pipa PVC
: Dia. 4" ( Pipa Air Kotor ) m 134.587,80
AW 42,00 5.652.687,60
Pipa PVC
: Dia. 3" ( Air Bekas ) m 82.062,90
AW 14,00 1.148.880,60
Pipa PVC
: Dia. 2" ( Air Bekas ) m 59.815,80
AW 52,00 3.110.421,60
Pipa PVC
: Dia. 1,5" ( Vent ) m 38.164,50
AW 38,00 1.450.251,00
Floor
: Dia. 2" m 83.530,80
Drain 18,00 1.503.554,40
Clean Out : Dia. 4" bh 229.500,00
2,00 459.000,00
Clean Out : Dia. 3" bh 193.500,00
2,00 387.000,00
Pemipaan lantai 01
Pipa PVC
: Dia. 6" ( Pipa Air Kotor ) m 195.331,50
AW 14,00 2.734.641,00
Pipa PVC
: Dia. 4" ( Pipa Air Kotor ) m 134.587,80
AW 42,00 5.652.687,60
Pipa PVC
: Dia. 3" ( Air Bekas ) m 82.062,90
AW 14,00 1.148.880,60
Pipa PVC
: Dia. 2" ( Air Bekas ) m 59.815,80
AW 52,00 3.110.421,60
Pipa PVC
: Dia. 1,5" ( Vent ) m 38.164,50
AW 38,00 1.450.251,00
Floor
: Dia. 2" m 83.530,80
Drain 18,00 1.503.554,40
Clean Out : Dia. 4" bh 229.500,00
2,00 459.000,00
Clean Out : Dia. 3" bh 193.500,00
2,00 387.000,00

PEKERJAAN AIR HUJAN

Pemipaan air hujan dari roof tank


Pipa PVC
: Dia. 4" m 134.587,80
AW 304,00 40.914.691,20
Roff drain : Dia. 4" bh 202.500,00
24,00 4.860.000,00

59
344.548.314,00

651.280.367,70
XII. PEKERJAAN MEKANIKAL ELEKTRIKAL

A. PEKERJAAN MEKANIKAL ELEKTRIKAL SITEPLAN

1 PEKERJAAN PASANG BARU 240 KVA

Penyambungan langganan PLN 240 kva :

- Bp (Biaya Penyambungan) 240.000 va 1.080,00


259.200.000,00
- Ujl (Uang Jaminan Langganan)

- Materai

- SLO

- SJI BTL

- Pengurusan Penyalaan

2 PANEL CUBICLE PELANGGAN / KONSUMEN

Incoming cubicle IM-SM6 unit 81.000.000,00


1,00 81.000.000,00
IM - SM 6 type Cubicle lengkap dengan
Switch Cubicle (LBS-SF6) 24kV,
-
16kA, 630A
Voltage Indicators 3 Pcs & Heater
-
50 W, 220 VAC 1 unit
- Busbar 630A 3 unit

- CIT Manual Operating Mechanism

Outgoing cubicle QM-SM6 to Trafo unit 85.500.000,00


1,00 85.500.000,00
QM - SM 6 type Cubicle lengkap dengan
Switch Cubicle (LBS-SF6) 24kV,
-
16kA, 630A
1 set Cap. Devider (CVD) & Voltage
-
Indicators 3 Pcs
- Busbar 630A 3 unit

- Earthing Switch w/ SF6

- Heater 50 W, 220 VAC


Fuse Fusarc 100A w/ striker 3 pcs
-
for Trafo 2000kVA
- shunt trip 220 VAC

PEKERJAAN JARINGAN TEGANGAN


3.
MNENGAH 3 PHASA 20 KV
Pengadaan dan pemasangan jaringan listrik
3 phasa,
lengkap terpasan dan berfungsi dengan
baik, pekerjaan sudah
termasuk biaya-biaya yang berkaitan
dengan pekerjaan jaringan listrik
seperti biasa rabas pohon untuk jalur kabel
dan biaya-biaya yang
timbul akibat perluasan jaringan

60
- Kabel AAAC 70mm2 m 40.500,00
910,80 36.887.400,00
Pegadaan dan Pemasagan Tiang
- buah 5.019.840,00
listrik beton C11 berikut accessories 7,00 35.138.880,00
gawa
- Pekerjaan pearikan kabel hantaran 945.000,00
6,00 ng 5.670.000,00
- Terminating 20 KV ls 2.700.000,00
1,00 2.700.000,00
- Material Bantu, Skun dll ls 4.500.000,00
1,00 4.500.000,00
- Setting dan Test Comissioning ls 2.250.000,00
1,00 2.250.000,00

4. PEKERJAAN TRAFO

Transformator, kapasitas 315 kVA unit 157.500.000,00


1,00 157.500.000,00
- Phasa / Freq : 3 Phasa / 50 Hz

- Primer : 20 KV

- Secunder : 380 / 400 V

- Pendingin : Olie ( ONAN )


Accessories : DGPT2, Conservator,
-
Elastimold
Transportasi, akomodasi,
-
pemasangan
Grounding trafo + material bantu titik 4.500.000,00
1,00 4.500.000,00

5. PEKERJAAN GENSET 200 KVA

Genset, kapasitas 200 KVA model silent unit 382.500.000,00


1,00 382.500.000,00
- Phasa / Freq : 3 Phasa / 50 Hz

- Primer : 20 KV

- Secunder : 380 / 400 V

- Pendingin : Olie ( ONAN )


Accessories : DGPT2, Conservator,
-
Elastimold
Transportasi, akomodasi,
-
pemasangan
Grounding trafo + material bantu titik 4.500.000,00
1,00 4.500.000,00

6. PEKERJAAN PANEL TEGANGAN RENDAH


LVMDP + Cap. Bank 150 kvar(6
- buah 135.000.000,00
steps) 1,00 135.000.000,00
- Grounding elektrikal max 2 ohm titik 3.600.000,00
1,00 3.600.000,00

7. PEKERJAAN KABEL FEEDER


Kabel dari Trafo, KWH Meter ke
- m 3.150.000,00
LVMDP : 20,00 63.000.000,00
NYY 4x185mm2 + NYA 150 mm2

61
1.263.446.280,00
B. PEKERJAAN ELEKTRIKAL

1. PEKERJAAN PANEL TEGANGAN RENDAH

a. SDP-GEDUNG 17.082.900,00
1,00 buah 17.082.900,00
b. PP/LP-1 7.595.100,00
1,00 buah 7.595.100,00
c. PP/LP-2 7.678.800,00
1,00 buah 7.678.800,00
d. PP/LP-3 7.595.100,00
1,00 buah 7.595.100,00
e. PP.AC-1 9.777.600,00
1,00 buah 9.777.600,00
f. PP.AC-2 9.777.600,00
1,00 buah 9.777.600,00
g. PP.AC-3 10.194.300,00
1,00 buah 10.194.300,00
h. Grounding elektrikal max 2 ohm titik 3.600.000,00
1,00 3.600.000,00
i. Grounding elektronika max 1 ohm titik 3.600.000,00
1,00 3.600.000,00
2. PEKERJAAN KABEL FEEDER

a. Kabel dari LVMDP ke SDP-GEDUNG : m 1.118.700,00


88,55 99.060.885,00
- NYFGbY 4x185mm2 + NYY
1x150mm2
Kabel dari SDP-GEDUNG ke PP/LP-1
b. 8,00 m 73.800,00
: 590.400,00
- NYY 4x10mm2 + BC 6mm2
Kabel dari SDP-GEDUNG ke PP/LP-2
c. m 73.800,00
: 13,00 959.400,00
- NYY 4x10mm2 + BC 6mm2
Kabel dari SDP-GEDUNG ke PP/LP-3
d. m 73.800,00
: 18,00 1.328.400,00
- NYY 4x10mm2 + BC 6mm2
Kabel dari SDP-GEDUNG ke PP.AC-1
e. m 193.500,00
: 10,00 1.935.000,00
- NYY 4x35mm2 + BC 25mm2
Kabel dari SDP-GEDUNG ke PP.AC-2
f. m 193.500,00
: 15,00 2.902.500,00
- NYY 4x35mm2 + BC 25mm2
Kabel dari SDP-GEDUNG ke PP.AC-3
g. m 193.500,00
: 20,00 3.870.000,00
- NYY 4x35mm2 + BC 25mm2

3. PEKERJAAN INSTALASI LISTRIK


Pengadaan ,pemasangan, kabel,konduit
lampu, rak,bobokan, penggantung, klem
armature, perapihan, training dan tes
commissioning

LANTAI 1
Titik lampu,kabel NYM 3x2,5mm2
a. titik 225.900,00
dalam conduit 20mm2 166,00 37.499.400,00
Titik stop kontak,kabel NYM
b. titik 269.100,00
3x2,5mm2 dalam conduit 20mm2 91,00 24.488.100,00
Titik stop kontak AC,kabel NYM
c. titik 617.400,00
4x4mm2 dalam conduit 20mm2 7,00 4.321.800,00

62
d. Lampu RM 300 TL 2x36 W 804.600,00
72,00 buah 57.931.200,00
e. Down Light E27 Ess 18 W 235.800,00
77,00 buah 18.156.600,00
f. Down Light E27 Ess 8 W 226.800,00
13,00 buah 2.948.400,00
g. Baret E27 Ess 18 W 252.000,00
4,00 buah 1.008.000,00
h. Stop kontak, 1ph. 16A, umum 48.600,00
66,00 buah 3.207.600,00
i. Stop kontak, 1ph. 16A 3 kaki , AC 48.600,00
25,00 buah 1.215.000,00
j Stop kontak, 3ph. 16A 3 kaki , AC 289.800,00
7,00 buah 2.028.600,00
k Saklar tunggal 27.000,00
20,00 buah 540.000,00
l. Saklar ganda 37.800,00
19,00 buah 718.200,00
m. Saklar hotel 30.600,00
2,00 buah 61.200,00
Kabel tray 300x100 mm berikut
n. m 407.700,00
fitting, dan accessories lainnya 81,00 33.023.700,00
Kabel tray 200x100 mm berikut
o. m 336.600,00
fitting, dan accessories lainnya 81,00 27.264.600,00

LANTAI 2
Titik lampu,kabel NYM 3x2,5mm2
a. titik 225.900,00
dalam conduit 20mm2 164,00 37.047.600,00
Titik stop kontak,kabel NYM
b. titik 269.100,00
3x2,5mm2 dalam conduit 20mm2 80,00 21.528.000,00
Titik stop kontak AC,kabel NYM
c. titik 617.400,00
4x4mm2 dalam conduit 20mm2 6,00 3.704.400,00
d. Lampu RM 300 TL 2x36 W 804.600,00
72,00 buah 57.931.200,00
e. Down Light E27 Ess 18 W 235.800,00
79,00 buah 18.628.200,00
f. Down Light E27 Ess 8 W 226.800,00
13,00 buah 2.948.400,00
g. Stop kontak, 1ph. 16A, umum 48.600,00
54,00 buah 2.624.400,00
h. Stop kontak, 1ph. 16A 3 kaki , AC 48.600,00
26,00 buah 1.263.600,00
i. Stop kontak, 3ph. 16A 3 kaki , AC 289.800,00
6,00 buah 1.738.800,00
j Saklar tunggal 27.000,00
19,00 buah 513.000,00
k Saklar ganda 37.800,00
21,00 buah 793.800,00
l. Saklar hotel 30.600,00
2,00 buah 61.200,00
Kabel tray 300x100 mm berikut
m. m 407.700,00
fitting, dan accessories lainnya 81,00 33.023.700,00
Kabel tray 200x100 mm berikut
n. m 336.600,00
fitting, dan accessories lainnya 81,00 27.264.600,00

LANTAI 3
Titik lampu,kabel NYM 3x2,5mm2
a. titik 225.900,00
dalam conduit 20mm2 151,00 34.110.900,00
Titik stop kontak dan stop kontak
b. AC,kabel NYM 3x2,5mm2 dalam titik 269.100,00
98,00 26.371.800,00
conduit 20mm2
c. Lampu RM 300 TL 2x36 W 804.600,00
104,00 buah 83.678.400,00
d. Down Light E27 Ess 18 W 235.800,00
34,00 buah 8.017.200,00

63
e. Down Light E27 Ess 8 W 226.800,00
13,00 buah 2.948.400,00
f. Stop kontak, 1ph. 16A, umum 48.600,00
62,00 buah 3.013.200,00
g. Stop kontak, 1ph. 16A 3 kaki , AC 48.600,00
36,00 buah 1.749.600,00
h. Saklar tunggal 27.000,00
12,00 buah 324.000,00
i. Saklar ganda 37.800,00
45,00 buah 1.701.000,00
Kabel tray 300x100 mm berikut
j m 407.700,00
fitting, dan accessories lainnya 78,00 31.800.600,00
Kabel tray 200x100 mm berikut
k m 336.600,00
fitting, dan accessories lainnya 78,00 26.254.800,00

LANTAI 4
Titik lampu,kabel NYM 3x2,5mm2
a. titik 225.900,00
dalam conduit 20mm2 164,00 37.047.600,00
Titik stop kontak,kabel NYM
b. titik 269.100,00
3x2,5mm2 dalam conduit 20mm2 80,00 21.528.000,00
Titik stop kontak AC,kabel NYM
c. titik 617.400,00
4x4mm2 dalam conduit 20mm2 6,00 3.704.400,00
d. Lampu RM 300 TL 2x36 W 804.600,00
72,00 buah 57.931.200,00
e. Down Light E27 Ess 18 W 235.800,00
79,00 buah 18.628.200,00
f. Down Light E27 Ess 8 W 226.800,00
13,00 buah 2.948.400,00
g. Stop kontak, 1ph. 16A, umum 48.600,00
54,00 buah 2.624.400,00
h. Stop kontak, 1ph. 16A 3 kaki , AC 48.600,00
26,00 buah 1.263.600,00
i. Stop kontak, 3ph. 16A 3 kaki , AC 289.800,00
6,00 buah 1.738.800,00
j Saklar tunggal 27.000,00
19,00 buah 513.000,00
k Saklar ganda 37.800,00
21,00 buah 793.800,00
l. Saklar hotel 30.600,00
2,00 buah 61.200,00
Kabel tray 300x100 mm berikut
m. m 407.700,00
fitting, dan accessories lainnya 81,00 33.023.700,00
Kabel tray 200x100 mm berikut
n. m 336.600,00
fitting, dan accessories lainnya 81,00 27.264.600,00

1.040.072.085,00
C. PEKERJAAAN PENANGKAL PETIR

Air Terminal Electro Static (non radio


1. aktif), Radius Proteksi min 50 Meter, unit 11.250.000,00
2,00 22.500.000,00
berikut tiang dan accessories

2. Obstruction Light led 5 w


-
3. Lighting strike counter bh 3.378.870,00
2,00 6.757.740,00
4. Conductor Cable, BC 50 mm2 dalam conduit bh 2.475.000,00
2,00 4.950.000,00
Cable Clamp, support dan accessories
5. m 198.000,00
lainnya 280,00 55.440.000,00
6. Bak Kontrol berikut grounding max 1 ohm ls 1.350.000,00
2,00 2.700.000,00
7. Material bantu titk 1.125.000,00
5,00 5.625.000,00

64
8. Ijin Depnaker ls 900.000,00
1,00 900.000,00

98.872.740,00
D. PEKERJAAN FIRE ALARM

Pengadaan dan pemasangan lengkap peralatan


instalasi kabel, dudukan dan penggantung,
training dan
tes commissioning

PERALATAN UTAMA

a. MCFA 10 zone c/w battery & charge bh 18.241.200,00


1,00 18.241.200,00
b. Annunciator bh 5.107.500,00
2,00 10.215.000,00

LANTAI 1

Titik fire alarm,kabel NYA 2x1.5mm2 +


a. titik 179.100,00
conduit 20 mm2 45,00 8.059.500,00
b. ROR Detector bh 207.900,00
37,00 7.692.300,00
c. Manual Push Button bh 346.500,00
2,00 693.000,00
d. Alarm Bell bh 240.300,00
2,00 480.600,00
e. Indikator Lamp bh 154.800,00
2,00 309.600,00
f. End of Line bh 81.000,00
2,00 162.000,00
g. Terminal box bh 585.000,00
1,00 585.000,00
h. Kabel dari MCFA ke TBFA.1 m 22.500,00
17,00 382.500,00
Fire Extingusher dry chemical class ABC 6
i. 585.000,00
kg 3,00 buah 1.755.000,00

LANTAI 2

Titik fire alarm,kabel NYA 2x1.5mm2 +


a. titik 179.100,00
conduit 20 mm2 47,00 8.417.700,00
b. ROR Detector bh 207.900,00
39,00 8.108.100,00
c. Manual Push Button bh 346.500,00
2,00 693.000,00
d. Alarm Bell bh 240.300,00
2,00 480.600,00
e. Indikator Lamp bh 154.800,00
2,00 309.600,00
f. End of Line bh 81.000,00
2,00 162.000,00
g. Terminal box bh 585.000,00
1,00 585.000,00
h. Kabel dari MCFA ke TBFA.2 m 22.500,00
8,00 180.000,00
Fire Extingusher dry chemical class ABC 6
i. 585.000,00
kg 3,00 buah 1.755.000,00

LANTAI 3

65
Titik fire alarm,kabel NYA 2x1.5mm2 +
a. titik 179.100,00
conduit 20 mm2 41,00 7.343.100,00
b. ROR Detector bh 207.900,00
33,00 6.860.700,00
c. Manual Push Button bh 346.500,00
2,00 693.000,00
d. Alarm Bell bh 240.300,00
2,00 480.600,00
e. Indikator Lamp bh 154.800,00
2,00 309.600,00
f. End of Line bh 81.000,00
2,00 162.000,00
g. Terminal box bh 585.000,00
1,00 585.000,00
h. Kabel dari MCFA ke TBFA.3 m 22.500,00
17,00 382.500,00
Fire Extingusher dry chemical class ABC 6
i. 585.000,00
kg 3,00 buah 1.755.000,00

LANTAI 4

Titik fire alarm,kabel NYA 2x1.5mm2 +


a. titik 179.100,00
conduit 20 mm2 47,00 8.417.700,00
b. ROR Detector bh 207.900,00
39,00 8.108.100,00
c. Manual Push Button bh 346.500,00
2,00 693.000,00
d. Alarm Bell bh 240.300,00
2,00 480.600,00
e. Indikator Lamp bh 154.800,00
2,00 309.600,00
f. End of Line bh 81.000,00
2,00 162.000,00
g. Terminal box bh 585.000,00
1,00 585.000,00
h. Kabel dari MCFA ke TBFA.2 m 22.500,00
8,00 180.000,00
Fire Extingusher dry chemical class ABC 6
i. 585.000,00
kg 3,00 buah 1.755.000,00

108.529.200,00
E. PEKERJAAN EXHAUST FAN DAN INSTALASI AC

1. PEKERJAAN AC
Pengadaan dan pemasangan AC termasuk
refrigerant berisolasi, pipa kondensat, pipa
drain dan perlengkapannya sesuai gambar
kerja
a. Pekerjaan LT. 01
- Intalasi untuk AC Split System -
unit 7.443.900,00
Wall mounted type, : 18.000 BTU/h 12,00 89.326.800,00
- Intalasi untukAC Split System -
unit 17.596.800,00
Ceiling Caette type, : 18.000 BTU/h 2,00 35.193.600,00
- Intalasi untukAC Split System -
unit 24.984.900,00
Ceiling Caette type, : 28.000 BTU/h 1,00 24.984.900,00

b. Pekerjaan LT. 02
- Intalasi untuk AC Split System -
unit 7.443.900,00
Wall mounted type, : 18.000 BTU/h 7,00 52.107.300,00
- Intalasi untukAC Split System -
unit 17.596.800,00
Ceiling Caette type, : 18.000 BTU/h 2,00 35.193.600,00
- Intalasi untukAC Split System -
unit 24.984.900,00
Ceiling Caette type, : 28.000 BTU/h 4,00 99.939.600,00

66
c. Pekerjaan LT. 03
- Intalasi untuk AC Split System -
unit 7.443.900,00
Wall mounted type, : 18.000 BTU/h 7,00 52.107.300,00
- Intalasi untukAC Split System -
unit 17.596.800,00
Ceiling Caette type, : 18.000 BTU/h 2,00 35.193.600,00
- Intalasi untukAC Split System -
unit 24.984.900,00
Ceiling Caette type, : 28.000 BTU/h 4,00 99.939.600,00

F. Pekerjaan LT. 04
- Intalasi untuk AC Split System -
unit 4.837.500,00
Wall mounted type, : 9.000 BTU/h 20,00 96.750.000,00

2. PEKERJAAN EXHAUST FAN

a. Pekerjaan LT. 01
- Exhaust fan type ceiling mounted
495.000,00
kap. 150 CFM (kamar mandi) 4,00 buah 1.980.000,00
- Pipa pvc aw 6" m 200.658,60
7,00 1.404.610,20
- Pipa pvc aw 4" m 138.258,00
35,00 4.839.030,00
- Instalasi exhaust dengan kabel
titik 225.900,00
NYM 3x2.5mm2 dalam pipa conduit 4,00 903.600,00

b. Pekerjaan LT. 02
- Exhaust fan type ceiling mounted
495.000,00
kap. 150 CFM (kamar mandi) 4,00 buah 1.980.000,00
- Pipa pvc aw 6" m 200.658,60
7,00 1.404.610,20
- Pipa pvc aw 4" m 138.258,00
35,00 4.839.030,00
- Instalasi exhaust dengan kabel
titik 225.900,00
NYM 3x2.5mm2 dalam pipa conduit 4,00 903.600,00

c. Pekerjaan LT. 03
- Exhaust fan type ceiling mounted
495.000,00
kap. 150 CFM (kamar mandi) 4,00 buah 1.980.000,00
- Pipa pvc aw 6" m 200.658,60
7,00 1.404.610,20
- Pipa pvc aw 4" m 138.258,00
35,00 4.839.030,00
- Instalasi exhaust dengan kabel
titik 225.900,00
NYM 3x2.5mm2 dalam pipa conduit 4,00 903.600,00

f. Pekerjaan LT. 04
- Exhaust fan type ceiling mounted
495.000,00
kap. 150 CFM (kamar mandi) 19,00 buah 9.405.000,00
- Pipa pvc aw 6" m 200.658,60
19,00 3.812.513,40
- Pipa pvc aw 4" m 138.258,00
128,00 17.697.024,00
- Instalasi exhaust dengan kabel
titik 225.900,00
NYM 3x2.5mm2 dalam pipa conduit 19,00 4.292.100,00

e. Pekerjaan power house

67
- Exhaust fan type wall mounted
1.080.000,00
kap. 750 CFM 2,00 buah 2.160.000,00
- Instalasi exhaust dengan kabel
titik 236.700,00
NYM 3x4mm2 dalam pipa conduit 2,00 473.400,00

685.958.058,00

3.196.878.363,00
XIII. PEKERJAAN LAIN-LAIN
Pekerjaan logo serta leter stainless canopy dan
1 Dihitung set 67.500.000,00
back drop 1,00 67.500.000,00
2 Pekerjaan hand railling tangga Dihitung m' 1.800.000,00
122,08 219.745.800,00
Pekerjaan saluran keliling U20 termasuk galian
3 15.2. m' 187.214,40
dan pasangan dinding saluran 217,50 40.719.132,00
4 Pekerjaan pembuatan bak kontrol 40x40 cm Dihitung bh 315.000,00
22,00 6.930.000,00
5 Pekerjaan grill penutup saluran Dihitung m' 225.000,00
16,00 3.600.000,00
6 Pekerjaan ornamen GRC Dihitung m2 855.000,00
214,85 183.696.750,00
Pekerjaan pengadaan dan pemasangan lift berikut
7 Dihitung unit 810.000.000,00
acesorienya 1,00 810.000.000,00
8 Solar panel 5.300 W Dihitung bh 54.900.000,00
15,00 823.500.000,00
9 Rain water harvesting Dihitung pkt 450.000.000,00
1,00 450.000.000,00
2 Vertical garden Dihitung pkt 400.000.000,00
1,00 400.000.000,00
3 Sensor Manusia Dihitung bh 225.000,00
165,00 37.125.000,00
4 Lift 6 lantai Dihitung pkt 450.000.000,00
1,00 450.000.000,00
Green
5 Dihitung m 450.000,00
Roof 900,00 405.000.000,00
Studio
6 Dihitung pkt 27.000.000,00
Film 1,00 27.000.000,00

3.924.816.682,00
XIV. PEKERJAAN PENATAAN LINGKUNGAN

A. PEKERJAAN PENATAAN LAHAN/TANAH

1. Pekerjaan urugan tanah padas 2.14. m3 210.250,80


2.053,06 431.657.507,45
Pekerjaan pemadatan tanah (maksimal tiap
2. 2.10. m3 64.102,50
lapisa 20 cm) 2.053,06 131.606.278,65
3. Pekerjaan Urugan Pasir tebal 10 cm 2.11. m3 296.950,50
278,52 82.706.653,26

645.970.439,36
B. PEKERJAAN PERKERASAN HALAMAN
Pekerjaan pavingbock tebal 8 cm mutu
1. 8.60 m2 203.258,70
K300 3.512,64 713.974.639,97
2. Pekerjaan kansteen beton K200 8.61 m' 111.311,10
117,58 13.088.293,07

727.062.933,04
C. PEKERJAAN PASANGAN DAN PLESTERAN

1. Pekerjaan pasangan batu belah 1:5 3.3. m3 1.106.905,50


204,68 226.561.417,74

68
Pekerjaan dinding pot taman pas. Batu bata
2. 6.10 m2 124.992,00
1:5 309,36 38.667.525,12
3. Pekerjaan plesteran dinding 1:5 7.5. m2 78.249,60
309,36 24.207.296,26
4. Pekerjaan acian dinding 7.27. m2 52.386,30
309,36 16.206.225,77
5. Pekerjaan sponengan 7.20. m' 83.639,70
270,60 22.632.902,82

328.275.367,70
D. PEKERJAAN KOLAM AIR MANCUR

1. Pekerjaan rumah pompa Dihitung m2 3.150.000,00


13,52 42.588.000,00
Pekerjaan beton bertulang kolam air
2.
mancur
- Sloof beton 15/20 4.26D m3 7.100.445,48
2,49 17.657.955,85
- Sloof beton 15/20 4.29AO m3 8.982.376,87
2,47 22.150.541,36
- Dinding beton tebal 15 cm 4.31 m3 7.572.085,04
9,89 74.852.695,74
- Plat beton tebal 15 cm 4.31 m3 7.572.085,04
8,48 64.196.137,00
- Balok beton 15/15 4.29AO m3 8.982.376,87
1,87 16.753.570,04
3. Pekerjaan penutup dinding dan lantai

- Penutup lantai keramik 30x30 cm 8.36. m2 319.007,70


58,52 18.668.330,60
- Penutup dinding coating natural 8.55. m2 367.784,10
124,54 45.803.831,81
4. Pekerjaan instalasi air mancur

Pompa air mancur unit 7.200.000,00


4,00 28.800.000,00

Jenis : Centrifugal
Pompa
Kapasitas : 120 liter/menit

Total : 30 meter
Head
Lengkap dengan Panel Control dan
Pengkabelan dari Panel ke Pompa
Instalasi pemipaan
Pipa PVC
: Dia. 3/4" m 18.405,00
AW 24,00 441.720,00
Pipa PVC
: Dia. 1" m 19.800,00
AW 140,00 2.772.000,00
Pipa PVC
: Dia. 2" m 59.815,80
AW 56,00 3.349.684,80
lengkap dengan assesoris yang diperlukan

katup air mancur bh 108.000,00


14,00 1.512.000,00
floor drain 5,00 bh 83.250,00
416.250,00
Kabel instalasi dari panel pompa ke power
m 65.700,00
(power house) NYFGbY 4X4 mm 190,00 12.483.000,00

352.445.717,21
E. PEKERJAAN PENGECATAN

69
1. Pekerjaan penecatan dinding eksterior 13.10. B unit 47.742,30
309,36 14.769.557,93
2. Pekerjaan waterproofing kolam air mancur Dihitung m2 211.365,00
58,16 12.292.988,40

27.062.546,33
F. PEKERJAAN TAMAN

1. Pekerjaaan taman T1 Dihitung unit 49.500.000,00


4,00 198.000.000,00
2. Pekerjaan Taman T2 Dihitung unit 66.600.000,00
2,00 133.200.000,00
3. Pekerjaan taman T3 Dihitung unit 24.300.000,00
1,00 24.300.000,00
4. Pekerjaan taman T4 Dihitung unit 35.100.000,00
1,00 35.100.000,00

390.600.000,00

2.471.417.003,64
JUMLAH TOTAL
39.031.494.667,03

70
Lampiran IV
4. Gambar Perspektif Gedung Student center

TAMPAK DEPAN 2D

TAMPAK BELAKANG 2D

71
TAMPAK SAMPING 2D

72
73
Lampiran V

5. Siteplan dan Tampak Gedung Student center

74
75
76
77
78
Lampiran VI

6. Sertifikat Tanah

79
80
81
82
83
84
85
86
87
88