Anda di halaman 1dari 1

BUKIT SEMARANG BARU

TALUD RUMAH DOWNSLOOF TP 170


HILAGO
BUKIT SEMARANG BARU
NO URAIAN PEKERJAAN SAT VOL HARGA SATUAN TOTAL

A PEKERJAAN TALUD unit 18.00 54,672,084 984,097,512


Q.
1. Galian tanah m3 20.82 40,000 832,808
1. Galian tanah Type 1 m3 14.53
1. Galian tanah Type 2 m3 6.29
2. Urugan pasir m3 0.98 275,000 270,594
2. Urugan pasir Type 1 m3 0.66
2. Urugan pasir Type 2 m3 0.33
3. Talut batu belah Type 1 1:6 m3 35.80 675,000 24,164,200
4. Talut batu belah Type 2 1:6 m3 15.44 675,000 10,424,827
5. Berabenan m2 72.22 10,000 722,200
6. Plester m2 65.65 40,000 2,626,182
7. Acian MU m2 65.65 20,000 1,313,091
8. Waterproofing m2 65.65 150,000 9,848,183
9. Buang tanah ls 1.00 1,170,000 1,170,000
10. Geo membrane m2 66.00 50,000 3,300,000

TOTAL 984,097,512
+ CONTI 5% 1,033,302,387
GRANDTOTAL 1,034,000,000
Semarang, 05 Juli 2021
Note : PT. KARYADEKA ALAM LESTARI
Pekerjaan untuk 18 unit rumah (Blok B)
RAB rumah (approve) include pekerjaan talud terlampir

Dibuat, Diketahui, Disetujui,

Garit Dani H Okta Nur R Suwondo Wawan Susilo M. Aryabhekti Andy Iriawan
Estimator QS. Proyek Ass.Mngr. Proyek Mngr. Proyek Assc. Direktur Direktur

Yonathan Gayus
PAE