Rab Pra Desain
Rab Pra Desain
NO. MERK/
N A M A / JENIS BARANG SATUAN HARGA SATUAN
TYPE
(Rp)
1 2 3 4 6
A.4.1.1.4 Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87
ANALISA HARGA SATUAN PEKERJAAN
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 1.2000 85,000 102,000.00
Tukang Batu L.02.03 OH 0.2000 130,000 26,000.00
Kepala Tukang L.03.01 OH 0.0200 150,000 3,000.00
Mandor L.04.01 OH 0.0600 110,000 6,600.00
JUMLAH TENAGA KERJA 137,600.00
B BAHAN
Semen portland kg 230.0000 1,575 362,250.00
Pasir Beton kg 893.0000 161 143,517.86
Kerikil (Maks 30 mm) kg 1027.0000 281 288,370.69
Air Liter 200.0000 79 15,750.00
JUMLAH HARGA BAHAN 809,888.55
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 947,488.55
E Overhead & Profit 15% 15% 142,123.28
F Harga Satuan Pekerjaan (D+E) - 1,089,611.00
A.4.1.1.8. Membuat 1 m3 beton mutu f’= 21,7 MPa (K 250), slump (120 ± 20) mm, w/c = 0,56
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 1.6500 85,000 140,250.00
Tukang Batu L.02.03 OH 0.2750 130,000 35,750.00
Kepala Tukang L.03.01 OH 0.0280 150,000 4,200.00
Mandor L.04.01 OH 0.0830 110,000 9,130.00
JUMLAH TENAGA KERJA 189,330.00
B BAHAN
Semen portland kg 384.0000 1,575 604,800.00
Pasir Beton kg 692.0000 161 111,214.29
Kerikil (Maks 30 mm) kg 1039.0000 281 291,740.16
Air Liter 215.0000 79 16,931.25
JUMLAH HARGA BAHAN 1,024,685.70
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 1,214,015.70
E Overhead & Profit 15% 15% 182,102.35
F Harga Satuan Pekerjaan (D+E) - 1,396,118.00
12
SATUAN KERJA : PT PELNI CABANG KENDARI
PEKERJAAN : REHABILITASI GEDUNG KANTOR PELNI CABANG KENDARI
LOKASI : KOTA KENDARI
TAHUN ANGGARAN : 2021
13
SATUAN KERJA : PT PELNI CABANG KENDARI
PEKERJAAN : PEMBANGUNAN GEDUNG KANTOR PELNI CABANG KENDARI
LOKASI : KOTA KENDARI
TAHUN ANGGARAN : 2021
15
SISTEM MANAJEMEN KESELAMATAN KONSTRUKSI
SUB TOTAL
NO. URAIAN PEKERJAAN TOTAL HARGA
HARGA
1 2 3 4
I PEKERJAAN PENDAHULUAN / PERSIAPAN Rp 67,943,289.00
II PEKERJAAN TANAH DAN PASIR Rp 19,342,644.43
III PEKERJAAN BATU DAN PASANGAN Rp 208,846,240.89
IV PEKERJAAN BETON Rp 126,942,316.31
V PEKERJAAN KUSEN Rp 39,283,300.74
VI PEKERJAAN LANTAI Rp 68,992,527.83
VII PEKERJAAN PLAFON Rp 40,771,423.80
VIII PEKERJAAN KUDA-KUDA DAN ATAP Rp 43,074,077.60
IX PEKERJAAN SANITAIR Rp 38,272,574.00
X PEKERJAAN SALURAN Rp 18,702,484.61
XI PEKERJAAN PENGGANTUNG DAN KUNCI Rp 4,338,760.00
XII PEKERJAAN INSTALASI LISTRIIK Rp 9,964,500.00
XIII PEKERJAAN PENGECATAN Rp 47,709,844.14
XIV PEKERJAAN LAIN-LAIN DAN PEMBERSIHAN Rp 12,500,000.00
XV SISTEM MANAJEMEN KESELAMATAN KONSTRUKSI Rp 23,515,785.00
TERBILANG :
DELAPAN RATUS EMPAT PULUH TUJUH DUA RATUS SEPULUH RIBU RUPIAH
….........................................
Nip…........................................... Wakil Direktur
17
REKAPITULASI BIAYA
SUB TOTAL
NO. URAIAN PEKERJAAN TOTAL HARGA
HARGA
1 2 3 4
I PEKERJAAN PENDAHULUAN / PERSIAPAN Rp 51,055,561.00
III PEKERJAAN BATU DAN PASANGAN Rp 157,615,001.04
IV PEKERJAAN BETON Rp 91,351,680.47
V PEKERJAAN KUSEN Rp 39,283,300.74
VI PEKERJAAN LANTAI Rp 68,992,527.83
VII PEKERJAAN PLAFON Rp 40,771,423.80
VIII PEKERJAAN KUDA-KUDA DAN ATAP Rp 43,074,077.60
IX PEKERJAAN SANITAIR Rp 38,272,574.00
X PEKERJAAN SALURAN Rp 18,702,484.61
XI PEKERJAAN PENGGANTUNG DAN KUNCI Rp 4,338,760.00
XII PEKERJAAN INSTALASI LISTRIIK Rp 9,964,500.00
XIII PEKERJAAN PENGECATAN Rp 47,709,844.14
XIV PEKERJAAN LAIN-LAIN DAN PEMBERSIHAN Rp 12,500,000.00
XV SISTEM MANAJEMEN KESELAMATAN KONSTRUKSI Rp 23,515,785.00
TERBILANG :
DELAPAN RATUS DELAPAN JUTA DELAPAN RATUS SEMBILAN PULUH RIBU RUPIAH
….........................................
Nip…........................................... Wakil Direktur