TIME SCHEDULE ALAT

(TS)
SATUAN KERJA : SATUAN BRIMOB POLDA MALUKU UTARA
PEKERJAAN : KONSTRUKSI PEMB. RUMAH SUSUN T.1200 KOMPI SULA
LOKASI PEKERJAAN : MAKO KOMPI 1 YON B PELOPOR DESA POHEA KAB. KEPULAUAN SULA
TAHUN ANGGARAN : 2022
SUMBER DANA : SBSN

WAKTU PELAKSANAAN
BULAN I BULAN II BULAN III BULAN IV BULAN V BULAN VI BULAN VII BULAN VIIII

10-May

17-May

24-May

31-May

16-Aug

23-Aug

30-Aug
19-Apr

26-Apr

13-Sep

20-Sep

27-Sep
14-Jun

21-Jun

28-Jun

11-Oct

18-Oct

25-Oct
3-May

2-Aug

9-Aug

1-Nov

8-Nov
12-Jul

19-Jul

26-Jul

6-Sep
7-Jun

4-Oct
5-Jul
BOBOT
NO JENIS PEKERJAAN JUMLAH HARGA (Rp.) KETERANGAN
(%)
s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d

16-May

23-May

30-May

14-Nov
15-Aug

22-Aug

29-Aug
25-Apr

12-Sep

19-Sep

26-Sep

10-Oct

17-Oct

24-Oct

31-Oct
2-May

9-May

13-Jun

20-Jun

27-Jun

7-Nov
11-Jul

18-Jul

25-Jul

1-Aug

8-Aug

5-Sep

3-Oct
6-Jun

4-Jul
I PEKERJAAN PERSIAPAN 237,968,904.00 2.55 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 100

II PEKERJAAN TANAH DAN PONDASI

A PEKERJAAN PERSIAPAN 13,637,904.00 0.15 0.05 0.05 0.05

B PEKERJAAN TANAH & PONDASI 287,222,675.37 3.08 0.77 0.77 0.77 0.77

C PEKERJAAN BETON 620,726,124.75 6.65 1.66 1.66 1.66 1.66

III PEKERJAAN LANTAI I -


A PEKERJAAN BETON 1,587,611,812.32 17.00 2.13 2.13 2.13 2.13 2.13 2.13 2.13 2.13

B PEKERJAAN DINDING DAN PLESTERAN 541,501,822.80 5.80 0.97 0.97 0.97 0.97 0.97 0.97

C PEKERJAAN LANTAI / KERAMIK 540,328,840.29 5.79 1.16 1.16 1.16 1.16 1.16 75

D PEKERJAAN PLAFON 271,477,386.42 2.91 0.73 0.73 0.73 0.73

E PEKERJAAN PINTU, JENDELA , VENTILASI, & PENGGANTUNG/PENGUNCI 403,693,017.33 4.32 0.86 0.86 0.86 0.86 0.86

F PEKERJAAN PENGECATAN 157,554,239.16 1.69 0.56 0.56 0.56

G PEKERJAAN ELEKTRIKAL 204,772,023.00 2.19 0.44 0.44 0.44 0.44 0.44

H PEKERJAAN SANITASI 265,963,936.50 2.85 0.57 0.57 0.57 0.57 0.57

IV PEKERJAAN LANTAI II -
A PEKERJAAN BETON 896,946,029.46 9.61 1.20 1.20 1.20 1.20 1.20 1.20 1.20 1.20 50

PEKERJAAN DINDING DAN PLESTERAN 603,299,836.26 6.46 0.81 0.81 0.81 0.81 0.81 0.81 0.81 0.81

PEKERJAAN LANTAI / KERAMIK 447,114,152.73 4.79 0.96 0.96 0.96 0.96 0.96

PEKERJAAN PLAFON 284,278,934.28 3.04 0.43 0.43 0.43 0.43 0.43 0.43 0.43

PEKERJAAN PINTU, JENDELA , VENTILASI, & PENGGANTUNG/PENGUNCI 384,636,559.53 4.12 0.69 0.69 0.69 0.69 0.69 0.69

PEKERJAAN PENGECATAN 180,125,436.48 1.93 0.64 0.64 0.64

PEKERJAAN ELEKTRIKAL 147,098,643.00 1.58 0.26 0.26 0.26 0.26 0.26 0.26

PEKERJAAN SANITASI 212,752,534.50 2.28 0.38 0.38 0.38 0.38 0.38 0.38 25

V PEKERJAAN ATAP -
A PEKERJAAN KUDA-KUDA DAN ATAP 650,388,331.74 6.97 1.74 1.74 1.74 1.74

VI PEKERJAAN FASAD -
A PEKERJAAN BETON 25,182,769.80 0.27 0.09 0.09 0.09

B PEKERJAAN DINDING DAN PLESTERAN 249,984,938.16 2.68 0.67 0.67 0.67 0.67

C PEKERJAAN PENGECATAN 34,470,401.76 0.37 0.18 0.18

VII PEKERJAAN LAIN - LAIN 87,603,328.98 0.94 0.23 0.23 0.23 0.23 0

A JUMLAH REAL COST 9,336,340,582.62 100.00 - - - - 0.15 0.92 1.49 0.87 2.53 1.76 2.33 3.89 2.22 2.22 5.08 4.07 3.42 3.86 5.20 4.51 5.06 6.37 6.67 7.10 7.37 6.97 4.98 4.22 4.44 2.30

B JUMLAH TOTAL 9,336,340,582.62 - - - - 0.15 1.06 2.55 3.42 5.94 7.70 10.03 13.92 16.14 18.37 23.44 27.51 30.93 34.80 40.00 44.50 49.57 55.93 62.60 69.70 77.07 84.05 89.03 93.25 97.70 100.00

Ternate, 10 April 2022

Penawar:
CV.PILAR NUSANTARA PRIMA

MHD. ISRA R. AMBARAK


Direktur