SCHEDULE MINGGUAN
PT. TUNAS JAYA SANUR
JL. BY PASS. NGURAH RAI 52 XX SANUR DENPASAR
10-May-23
11-May-23
12-May-23
13-May-23
14-May-23
24-Apr-23
25-Apr-23
26-Apr-23
27-Apr-23
28-Apr-23
29-Apr-23
30-Apr-23
1-May-23
2-May-23
3-May-23
4-May-23
5-May-23
6-May-23
7-May-23
8-May-23
9-May-23
MINGGUN HARIAN MINGGUN HARIAN PLAND ACTUAL START SELESAI DURASI START SELESAI DURASI
Pek. PASANG BATU KALI PLANTER, DUDUKAN PLAND 55.32 8.00 8 8-May-23 15-May-23 8
4 m3 0%
STYLE BALI DAN TANGGA ACTUAL
B PEKERJAAN PILE CAP
1 P1,P2,P3 & PS
PLAND 17 5.00 8 1-May-23 3-May-23 3
1 PABRIKASI BESI unit 0%
ACTUAL
PLAND 92 9.00 3 1-May-23 12-May-23 12
2 URUGAN PASIR unit 0%
ACTUAL
PLAND 92 9.00 6 1-May-23 12-May-23 12
3 RABATAN unit 0%
ACTUAL
PLAND 92 9.00 6 2-May-23 13-May-23 12
4 INSTALL BESI unit 0%
ACTUAL
PLAND 92 9.00 4 2-May-23 13-May-23 12
5 INSTALL BEGESTING unit 0%
ACTUAL
PLAND 92 9.00 4 3-May-23 14-May-23 12
6 COR BETON unit 0%
ACTUAL
C PEKERJAAN STUMP KOLOM
PLAND 91 6.50 12 1-May-23 15-May-23 15
1 PABRIKASI BESI unit 0%
ACTUAL
PLAND 91 7.00 6 2-May-23 15-May-23 14
2 INSTALL BESI unit 0%
ACTUAL
PLAND 94 7.00 4 3-May-23 17-May-23 15
3 INSTALL BEGESTING unit 0%
ACTUAL
PLAND 94 7.00 4 4-May-23 18-May-23 15
4 COR BETON unit 0%
ACTUAL
D PEKERJAAN KOLOM
PLAND 91 6.50 12 1-May-23 15-May-23 15
1 PABRIKASI BESI unit 0%
ACTUAL
PLAND 91 7.00 6 2-May-23 15-May-23 14
2 INSTALL BESI unit 0%
ACTUAL