KEMENTRIAN PEKERJAAN UMUM

PPK PEMBINAAN TEKNIS PENGEMBANGAN PERMUKIMAN


SATKER PENGEMBANGAN KAWASAN PERMUKIMAN DAN
PERBATASAN PROVINSI NAGGROE ACEH DARUSSALAM

KEC. SEUNAGAN
KABUPATEN NAGAN RAYA

MC - 0

PEKERJAAN :
PEMBANGUNAN JALAN POROS
RSH KAWASAN

NOMOR KONTRAK : HK.02.03/022/PKPP/KONT/IV/2011


TANGGAL KONTRAK : 21 APRIL 2011
NILAI KONTRAK : Rp. 1.260.350.000
SUMBER DANA : APBN MURNI
TAHUN ANGGARAN : 2011
LOKASI : KABUPATEN NAGAN RAYA

KONTRAKTOR PELAKSANA :
CV. ARYA DUTA BEUTARI
PEMERINTAH KABUPATEN ACEH BARAT
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
Jln. Sisingamangaraja Lr. BKKBN Telp.(0655) 7006105

KEGIATAN PEMBANGUNAN JALAN


PENINGKATAN JALAN SEPAKAT

CCO-01

KONTRAKTOR PELAKSANA :
CV. DINOVA
Jln. Tanoh Manyang Kec. Teunom Kab. Aceh Jaya
PEMERINTAH KABUPATEN ACEH BARAT
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
Jln. Sisingamangaraja Lr. BKKBN Telp.(0655) 7006105

KEGIATAN PEMBANGUNAN JALAN


PENINGKATAN JALAN SEPAKAT

REKAPITULASI

KONTRAKTOR PELAKSANA :
CV. DINOVA
Jln. Tanoh Manyang Kec. Teunom Kab. Aceh Jaya
PEMERINTAH KABUPATEN ACEH BARAT
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
Jln. Sisingamangaraja Lr. BKKBN Telp.(0655) 7006105

KEGIATAN PEMBANGUNAN JALAN


PENINGKATAN JALAN SEPAKAT

DIVISI. I
UMUM

KONTRAKTOR PELAKSANA :
CV. DINOVA
Jln. Tanoh Manyang Kec. Teunom Kab. Aceh Jaya
PEMERINTAH KABUPATEN ACEH BARAT
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
Jln. Sisingamangaraja Lr. BKKBN Telp.(0655) 7006105

KEGIATAN PEMBANGUNAN JALAN


PENINGKATAN JALAN SEPAKAT

DIVISI - III
PEKERJAAN TANAH

KONTRAKTOR PELAKSANA :
CV. DINOVA
Jln. Tanoh Manyang Kec. Teunom Kab. Aceh Jaya
PEMERINTAH KABUPATEN ACEH BARAT
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
Jln. Sisingamangaraja Lr. BKKBN Telp.(0655) 7006105

KEGIATAN PEMBANGUNAN JALAN


PENINGKATAN JALAN SEPAKAT

DIVISI - IV
PERLEBARAN PERKERASAN DAN BAHU JALAN

KONTRAKTOR PELAKSANA :
CV. DINOVA
Jln. Tanoh Manyang Kec. Teunom Kab. Aceh Jaya
PEMERINTAH KABUPATEN ACEH BARAT
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
Jln. Sisingamangaraja Lr. BKKBN Telp.(0655) 7006105

KEGIATAN PEMBANGUNAN JALAN


PENINGKATAN JALAN SEPAKAT

DIVISI - VI
PERKERASAN ASPAL

KONTRAKTOR PELAKSANA :
CV. DINOVA
Jln. Tanoh Manyang Kec. Teunom Kab. Aceh Jaya
PEMERINTAH KABUPATEN ACEH BARAT
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
Jln. Sisingamangaraja Lr. BKKBN Telp.(0655) 7006105

KEGIATAN PEMBANGUNAN JALAN


PENINGKATAN JALAN SEPAKAT

DIVISI - VII
PEKERJAAN STRUKTUR

KONTRAKTOR PELAKSANA :
CV. DINOVA
Jln. Tanoh Manyang Kec. Teunom Kab. Aceh Jaya
PEMERINTAH KABUPATEN ACEH BARAT
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
Jln. Sisingamangaraja Lr. BKKBN Telp.(0655) 7006105

KEGIATAN PEMBANGUNAN JALAN


PENINGKATAN JALAN SEPAKAT

SCHEDULE

KONTRAKTOR PELAKSANA :
CV. DINOVA
Jln. Tanoh Manyang Kec. Teunom Kab. Aceh Jaya
PEMERINTAH KABUPATEN ACEH BARAT
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
Jln. Sisingamangaraja Lr. BKKBN Telp.(0655) 7006105

KEGIATAN PEMBANGUNAN JALAN


PEMBANGUNAN JALAN PRIBU-KARAK (LANJUTAN)

GRAFIK TALI GITAR

KONTRAKTOR PELAKSANA :
CV. DINOVA
Jln. Tanoh Manyang Kec. Teunom Kab. Aceh Jaya
PEMERINTAH KABUPATEN ACEH BARAT
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
Jln. Sisingamangaraja Lr. BKKBN Telp.(0655) 7006105

KEGIATAN PEMBANGUNAN JALAN


PEMBANGUNAN JALAN PRIBU-KARAK (LANJUTAN)

CCO - 01

KONTRAKTOR PELAKSANA :
CV. DINOVA
Jln. Tanoh Manyang Kec. Teunom Kab. Aceh Jaya
PEMERINTAH KABUPATEN ACEH BARAT
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
Jln. Sisingamangaraja Lr. BKKBN Telp.(0655) 7006105

KEGIATAN PEMBANGUNAN JALAN


PEMBANGUNAN JALAN PRIBU-KARAK (LANJUTAN)

REKAPITULASI

KONTRAKTOR PELAKSANA :
CV. DINOVA
Jln. Tanoh Manyang Kec. Teunom Kab. Aceh Jaya
VOLUME DAN JUMLAH HARGA
REKAYASA LAPANGAN ( MC - 0 )
KEGIATAN : DANA OTONOMI KHUSUS KABUPATEN ACEH BARAT
PEKERJAAN : #REF! B
NO. KONTRAK : #REF! U
NILAI KONTRAK : #REF! L
A
SUMBER DANA : #REF! N
KONTRAKTOR : #REF!

No. S
Kontrak Awal Pekerjaan Kurang Pekerjaan Tambah Kontrak Addendum I E
Mata
VOLUME P
Pembay Uraian Pekerjaan Satuan
( Rp ) Jumlah Harga Jumlah Harga Jumlah Harga
aran Harga Satuan Jumlah Harga Bobot Pekerjaan Pekerjaan Bobot T
Volume ( Ket
Kurang Tambah E
Rp.- % ( Rp ) ( Rp ) Rp ) % M
1 2 3 4 5 6 = (4 x 5) 7 8 9 10 11 12 13 14 15 B
DIVISI 1. UMUM E
R
1.2 Mobilisasi Ls 1.00 125,900,000.00 125,900,000.00 4.16 1.00 125,900,000.00 4.18 Tetap
Sub Total - DIV. I 125,900,000.00 4.16 0.00 0.00 125,900,000.00 4.18
DIVISI 3. PEKERJAAN TANAH
3.1.1 Galian Biasa M3 248.50 35,055.74 8,711,351.39 0.29 343.50 12,041,646.69 592.00 20,752,998.08 0.69 Tambah
3.1.3 Galian Struktur dengan kedalaman 0-2 meter M3 26.60 76,185.96 2,026,546.54 0.07 13.40 1,020,891.87 40.00 3,047,438.41 0.10 Tambah
3.2.1 Timbunan Biasa M3 158.40 88,518.77 14,021,373.17 0.46 138.65 12,273,127.46 19.75 1,748,245.71 0.06 Kurang
3.2.2 Timbunan Pilihan M3 1,020.00 164,447.17 167,736,113.40 5.54 287.54 47,285,632.60 1,307.54 215,021,746.00 7.14 Tambah
3.3 Penyiapan Badan Jalan M2 11,000.00 3,241.77 35,659,470.00 1.18 -1,910.50 -6,193,401.59 12,910.50 41,852,871.59 1.39 Kurang
Sub Total - DIV. III 228,154,854.50 7.53 6,079,725.88 60,348,171.16 282,423,299.78 9.38
DIVISI 4. PELEBARAN PERKERASAAN DAN BAHU JALAN

4.2 2 Lapisan Pondasi Agregat Kelas B M3 300.00 345,362.32 103,608,696.00 3.42 33.75 11,655,978.30 333.75 115,264,674.30 3.83 Tambah
Sub Total - DIV. IV 103,608,696.00 3.42 0.00 11,655,978.30 115,264,674.30 3.83
DIVISI 5. PERKERASAN BERBUTIR DAN PERKERASAN BETON SEMEN
5.1.1 Lapis Pondasi Agregat Kelas A M3 1,395.00 378,001.66 527,312,315.70 17.41 7.18 2,714,051.92 1,402.18 530,026,367.62 17.60 Tambah
5.1.2 Lapis Pondasi Agregat Kelas B M3 2,000.00 351,809.09 703,618,180.00 23.23 -2.50 -879,522.73 2,002.50 704,497,702.73 23.39 Kurang
Sub Total - DIV. V 1,230,930,495.70 40.64 -879,522.73 2,714,051.92 1,234,524,070.34 40.99
DIVISI 6. PERKERASAN ASPAL
6.1(1)(a) Lapis Resap Pengikat - Aspal Cair Liter 7,200.00 11,545.88 83,130,336.00 2.74 48.00 554,202.24 7,248.00 83,684,538.24 2.78 Tamabh
6.3(6a) Laston Lapis Antara (AC-BC) (grdasi halus/kasar) Ton 1,035.00 460,512.63 476,630,572.05 15.74 59.78 27,529,445.02 975.22 449,101,127.03 14.91 Kurang
6.3.8.a Aspal Minyak Ton 57.00 10,750,000.00 612,750,000.00 20.23 -0.30 -3,225,000.00 57.30 615,975,000.00 20.45 Kurang
6.3.10 Bahan Pengisi (Filter) Tambahan Kg 10,350.00 2,500.00 25,875,000.00 0.85 -503.22 -1,258,050.00 9,846.78 24,616,950.00 0.82 Tambah
Sub Total - DIV. VI 1,198,385,908.05 39.57 24,304,445.02 -703,847.76 1,173,377,615.27 38.96
DIVISI 7. STRUKTUR
7.1 (7) Beton Mutu Sedang dengan fc'=20 Mpa (K-250) M3 21.28 1,510,002.83 32,132,860.22 1.06 21.28 32,132,860.22 0.00 - - Kurang
7.1(9) Beton Siklop fc'= 15 Mpa (K-175) M3 15.02 1,022,538.48 15,358,527.97 0.51 15.02 15,358,527.97 0.00 - - Kurang
7.1(10) Beton mutu rendah dengan fc'=10 Mpa (K-125) M3 0.39 832,540.59 324,690.83 0.01 41.30 34,383,926.36 41.69 34,708,617.19 1.15 Tambah
7.3(1) Baja Tulangan BJ 24 Polos Kg 665.10 16,148.00 10,740,034.80 0.35 94.80 1,530,830.40 570.30 9,209,204.40 0.31 Kurang
7.9 Pasangan Batu M3 124.44 668,247.55 83,156,725.12 2.75 69.54 46,469,934.63 54.90 36,686,790.49 1.22 Kurang
Sub Total - DIV. VII 141,712,838.94 4.68 95,492,153.22 34,383,926.36 80,604,612.08 2.68

A JUMLAH TOTAL ( DIV. I + III + IV + V + VI + VII ) 3,028,692,793.19 100.00 124,996,801.39 108,398,279.97 3,012,094,271.78 100.00
B PAJAK PERTAMBAHAN NILAI (PPN 10 %) 302,869,279.32 301,209,427.18 ###

C JUMLAH TOTAL HARGA PEKERJAAN 3,331,562,072.51 3,313,303,698.95 ###


D DIBULATKAN 3,331,562,000.00 124,996,000.00 108,398,000.00 3,313,303,000.00
###

Diketahui Oleh : DiperiksaOleh : Dibuat Oleh :


PEJABAT PELAKSANA TEKNIS KEGIATAN (PPTK) Konsultan Pengawas 16,598,521.41 Kontraktor Pelaksana
DINAS BINA MARGA PT, CITRA SAUDARA
PT. DAYA CREASI MITRA YASA
KAB. ACEH BARAT

Ir. RADEN EFFENDI


HARMAINI HA, ST. ALI FATKAN, ST
Site Engineering
NIP. 19790411 200112 1 003 General Superintenden
GRAFIK TALI GITAR
KEGIATAN : PEMBANGUNAN JALAN DAN JEMBATAN DINAS BINA MARGA DAN CIPTA KARYA ACEH
PEKERJAAN : PEMBANGUNAN JALAN IE SAYANG - BAKAT
NO. KONTRAK : 07/SPKK/PBJ/DBC/OTSUS/IX/2011
NILAI KONTRAK : Rp. 1.869.860.000
SUMBER DANA : APBN (OTSUS)
KONTRAKTOR : CV. ARON PERMAI

0+000

0+050

0+100

0+150

0+200

0+250

0+300

0+350

0+400

0+450

0+500

0+550

0+600

0+650

0+700

0+750

0+800

0+850

0+900

0+950

1+000

1+050

1+100

1+150

1+200

1+250

1+300

1+350

1+400
Uraian Pekerjaan KET.
NO.

1 2
DIVISI 1. UMUM

1.2 Mobilisasi LS

DIVISI 2. DRAINASE

2.1 Galian Untuk Selokan Drainase dan Saluran Air

2.2 Pasangan Batu dengan Mortar

DIVISI 3. PEKERJAAN TANAH

3.1.1 Galian Biasa

3.2.1 Timbunan Biasa

3.2.2 Timbunan Pilihan

3.3 Penyiapan Badan Jalan

DIVISI 4. PELEBARAN PERKERASAAN DAN BAHU JALAN

4.2 2 Lapisan Pondasi Agregat Kelas B

DIVISI 5. PERKERASAN BERBUTIR DAN PERKERASAN BETON SEMEN

5.1.1 Lapis Pondasi Agregat Kelas A

5.1.2 Lapis Pondasi Agregat Kelas B

DIVISI 6. PERKERASAN ASPAL

6.1(1)(a) Lapis Resap Pengikat - Aspal Cair

6.3(6a) Laston Lapis Antara (AC-BC) (grdasi halus/kasar)

6.3.8.a Aspal Minyak

6.3.10 Bahan Pengisi (Filter) Tambahan

DIVISI 7. STRUKTUR

7.1 (7) Beton Mutu Sedang dengan fc'=20 Mpa (K-250)

7.1(9) Beton Siklop fc'= 15 Mpa (K-175)

7.1(10) Beton mutu rendah dengan fc'=10 Mpa (K-125)

7.3(1) Baja Tulangan BJ 24 Polos

7.9 Pasangan Batu

Menyetujui Oleh : - -
PEJABAT PELAKSANA TEKNIS KEGIATAN - -
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG - -

S A I F U L. H - -
Nip. 19721215 199303 1 003 - -
JADWAL PELAKSANAAN PEKERJAAN
( TIME SHEDULE )
PEKERJAAN : PENINGKATAN JALAN GP. TUMPOK LADANG - PESANTREN
LOKASI : KEC. KAWAY XVI KAB. ACEH BARAT
NO. KONTRAK : 620/55/BANG/PUPR/DTU/2019
NILAI KONTRAK : Rp. 330.446.000
SUMBER DANA : DTU
KONTRAKTOR : CV. PURNAMA AGUNG JAYA

Jadwal Pelaksanaan
NO Volume Volume Bobot
Uraian Pekerjaan Sat Jumlah Harga Bulan 1 Bulan 2 Bulan 3 Bulan 4 KET
Divisi Awal CCO (%)
I II III IV I II III IV I II III IV I II III IV

DIVISI 1. UMUM
100
1.2 Mobilisasi 1.00 1.00 Ls 9,830,000.00 3.27 1.09 1.09 1.09
90
DIVIASI 3. PEKERJAAN TANAH
80
3.1(1a) Galian Biasa 14.88 7.36 M3 145,389.81 0.05 0.02 0.02
=
70
3.2(2a) Timbunan Pilihan dari Sumber Galian 1,252.40 1,250.00 M3 221,613,225.00 73.77 4.00 5.50 9.00 11.82 11.82 11.82 11.82 8.00
60
3.2.2 Penyiapan Badan Jalan 6,262.00 5,100.00 M2 15,352,754.40 5.11 5.11
50
DIVISI 7. STRUKTUR
40
7.1(7)a Beton Mutu Rendah Fc'20 MPa 7.32 6.51 M3 10,612,498.75 3.53 1.77 1.77
30
7.1(8) Beton Mutu Rendah Fc'15 MPa 0.29 1.25 M3 1,561,027.95 0.52 0.26 0.26
20
7.1(9) Baja Tulangan U24 Polos 934.93 882.32 Kg 18,677,401.30 6.22 3.11 3.11
10
7.1(10) Pasangan Batu 17.90 23.39 M3 22,615,059.29 7.53 2.51 2.51 2.51
0

JUMLAH 300,407,356.51
JUMLAH BOBOT PEKERJAAN 100.00
JUMLAH PEKERJAAN BULANAN 1.09 5.11 4.00 5.50 9.00 11.82 11.82 12.91 11.82 8.00 0.28 4.90 7.64 2.51 2.51 1.09
RENCANA
KEMAJUAN PEKERJAAN KOMULATIF - 1.09 6.20 10.20 15.70 24.70 36.52 48.34 61.25 73.06 81.06 81.35 86.25 93.89 96.40 98.91 100.00

KEMAJUAN PEKERJAAN KOMULATIF -


REALISASI
KEMAJUAN PEKERJAAN KOMULATIF -

Menyetujui Oleh : Diperiksa Oleh : Diajukan Oleh :


PEJABAT PELAKSANA TEKNIS KEGIATAN Konsultant Pengawas Kontraktor Pelaksana
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG CV. BATOR ACEH CONSULTANT CV. PURNAMA AGUNG JAYA
KAB. ACEH BARAT

S A I F U L. H RIZKI SATRIA, ST NELSON MANURUNG, ST


Nip. 19721215 199303 1 003 Chief Inspector Site Manager