I Pekerjaan Persiapan
1 Survey & perencanaan 1.00 Ls 500,000 WO G-06729, TBS, 11/10/21 500,000 500,000 500,000 500,000 1,500,000 1,500,000
2 Pemasangan bouwplank 1.00 Ls 500,000 WO G-06729, TBS, 11/10/21 500,000 500,000 500,000 500,000 500,000 500,000
3 Pembuatan camp tenaga kerja 1.00 Ls 1,000,000 WO G-06729, TBS, 11/10/21 2,000,000 2,000,000 2,000,000 2,000,000 5,000,000 5,000,000
4 Mobilisasi & demobilisasi alat berat (excavator) 1.00 Ls 2,000,000 WO G-06729, TBS, 11/10/21 2,500,000 2,500,000 2,000,000 2,000,000 6,000,000 6,000,000
5 Mobilisasi & demobilisasi tenaga kerja 1.00 Ls 1,500,000 WO G-06729, TBS, 11/10/21 500,000 500,000 3,000,000 3,000,000 3,000,000 3,000,000
Subtotal - I 6,000,000 8,000,000 16,000,000
II Pekerjaan Galian & Urugan dengan Excavator
1 Galian tanah area kerja 394.92 M3 36,122 WO S-06292, Kumita, 07/01/22 36,122 14,265,300 16,000 6,318,720 53,000 20,930,760
2 Urugan pasir lantai kerja 1.64 M3 284,800 WO S-06292, Kumita, 07/01/22 284,800 467,072 516,000 846,240 950,000 1,558,000
3 Urugan kembali area kerja 236.96 M3 36,960 WO S-06292, Kumita, 07/01/22 36,960 8,758,042 19,000 4,502,240 53,000 12,558,880
4 Normalisasi & timbunan gorong-gorong eksisting 205.72 M3 37,800 WO G-06729, TBS, 11/10/21 40,000 8,228,800 49,000 10,080,280 40,000 8,228,800
- Extraholing 2x
5 Galian connecting p = 50 m (kanan & kiri) 180.00 M3 36,122 WO S-06292, Kumita, 07/01/22 36,122 6,501,960 16,000 2,880,000 53,000 9,540,000
6 Idle excavator 1.00 Ls 5,000,000 WO G-06729, TBS, 11/10/21 1,000,000 1,000,000 13,000,000 13,000,000 45,000 45,000
Subtotal - II 39,221,174 37,627,480 52,861,440
III Pekerjaan Galian & Urugan Manual
1 Galian koperan/pondasi box inlet 2.06 M3 78,600 WO G-06729, TBS, 11/10/21 63,056 129,895 102,000 210,120 170,000 350,200
2 Galian/pondasi koperan slope 1.76 M3 78,600 WO G-06729, TBS, 11/10/21 63,056 110,979 102,000 179,520 170,000 299,200
3 Urugan kembali area koperan 3.25 M3 36,960 WO S-06292, Kumita, 07/01/22 36,960 120,120 123,000 399,750 150,000 487,500
4 Urugan kembali area/samping gorong-gorong buis beton 20.70 M3 36,960 WO S-06292, Kumita, 07/01/22 36,960 765,072 123,000 2,546,100 150,000 3,105,000
*Harga belum termasuk PPN & PPH serta belum ada disc