Hari Uraian Pekerjaan Sat. Volume Uraian Pekerja QC Non Teknis Ket.

Pengecoran Plat Lantai M3 13.77 Wahono , Iwan


Jml.Pekerja =
Hamzah , Enjang
Usup , Abudin RT
17 Orang
Rabu Jaini , Egi
22-Mar-17 Idris , Amin
Malik , Wawan
Sandi , Lili , Ari
Iwan , Anton

Bongkaran Bekisting Sisi End Stop Plat Lantai M2 32.1 Iwan , Wahono
Jml.Pekerja =

2 Orang
Jum'at
24-Mar-17

Pas. Profil Dinding Hebel Titik 15 Enjang , Iwan


Jml.Pekerja =
Pas. Dinding Hebel 10 cm M2 7.52 Wahono

3 Orang
Sabtu
25-Mar-17

MENGETAHUI,

Ryan Chaniago Anton Iwan


Project Manager Site Engineer MOL