Anda di halaman 1dari 3

LAPORAN KEMAJUAN PEKERJAAN MINGGUAN

KONTRAKTOR
MINGGU KE- PERIODE TANGGAL KONSULTAN PENGAWAS
PELAKSANA
KEMENTRIAN AGAMA REPUBLIK INDONESIA
KANTOR KEMENTRIAN AGAMA KABUPATEN KEPULAUAN ARU 21 Agustus 2022
JL. PEMDA I TELP/FAX (0917) 22121 M-IV S/D
27 Agustus 2022
CV. TRIIASA MANDIRI CV. DELTA DIMENSI CONSULTAN

BOBOT PRESTASI S/D BOBOT PRESTASI MINGGU BOBOT PRESTASI S/D JUMLAH HARGA S/D MINGGU INI
Nomor Kontrak Fisik : 09/SP-PL/PPK-PUPR/VI/2021 MINGGU LALU (%) INI (%) MINGGU INI (%) (RUPIAH) + PPn 10%
No Kontrak : II.A/KK.25.06/3/SP-KONSTRUKSI/06/2022
: PEMBANGUNAN GEDUNG BALAI NIKAH DAN MANASIK HAJI 44,70% 2,02% 46,72% Rp 560.661.718,86
KOLAMAR KABUPATEN KEP.ARU
DATA KONTRAK DATA MUTUAL CHECK REALISASI
S/D MINGGU LALU MINGGU INI S/D MINGGU INI
HARGA SATUAN
NO. URAIAN PEKERJAAN SATUAN HARGA SATUAN JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT BOBOT (%)
VOL VOL JUMLAH SATUAN
( RUPIAH ) ( RUPIAH ) (%) ( RUPIAH ) ( RUPIAH ) (%) VOL BOBOT (%) VOL BOBOT (%) VOL THDP
REAL (RUPIAH)
ITEM
(1) 2 3 (4) (5) (6) (7) (8) (9) (11) (12) (14) (15) (16) (17)

PEKERJAAN PERSIAPAN
1 Pembersihan Lapangan M2 225,00 Rp 22.425,00 Rp 5.045.625,00 0,47 225,00 22.425,00 5.045.625,00 0,47 225,00 0,47 - 225,00 0,47 100,00 Rp 5.045.625,00
2 Pengukuran dan Pemasangan bowplank M1 40,00 Rp 93.932,00 Rp 3.757.280,00 0,35 40,00 93.932,00 3.757.280,00 0,35 40,00 0,35 - 40,00 0,35 100,00 Rp 3.757.280,00
3 Pembuatan Direksi keet dan Gudang M2 9,00 Rp 1.537.205,00 Rp 13.834.845,00 1,28 9,00 1.537.205,00 13.834.845,00 1,28 9,00 1,28 - 9,00 1,28 100,00 Rp 13.834.845,00
4 Papan Nama Proyek Ls 1,00 Rp 1.000.000,00 Rp 1.000.000,00 0,09 1,00 1.000.000,00 1.000.000,00 0,09 1,00 0,09 - 1,00 0,09 100,00 Rp 1.000.000,00
5 Biaya Penerapan SMK3 Ls 1,00 Rp 16.000.000,00 Rp 16.000.000,00 1,48 1,00 16.000.000,00 16.000.000,00 1,48 1,00 1,48 - 1,00 1,48 100,00 Rp 16.000.000,00
6 Mobilisasi Alat dan Bahan Ls 1,00 Rp 15.000.000,00 Rp 15.000.000,00 1,39 1,00 15.000.000,00 15.000.000,00 1,39 1,00 1,39 - 1,00 1,39 100,00 Rp 15.000.000,00
7 Dokumentasi Dan Pelaporan Ls 1,00 Rp 2.100.000,00 Rp 2.100.000,00 0,19 1,00 2.100.000,00 2.100.000,00 0,19 - - - - - Rp -
8 AsBuild Drawing Ls 1,00 Rp 4.000.000,00 Rp 4.000.000,00 0,37 1,00 4.000.000,00 4.000.000,00 0,37 - - - - - Rp -
9 Pembersihan akhir Ls 1,00 Rp 2.500.000,00 Rp 2.500.000,00 0,23 1,00 2.500.000,00 2.500.000,00 0,23 - - - - - Rp -
JUMLAH HARGA PEKERJAAN PERSIAPAN Rp 63.237.750,00 5,85 63.237.750,00 5,85 - 5,05 - 5,05 Rp 54.637.750,00
PEKERJAAN PONDASI
1 Galian Tanah Biasa
- Untuk Pondasi Utama M3 50,00 Rp 54.740,00 Rp 2.737.000,00 0,25 50,00 54.740,00 2.737.000,00 0,25 50,00 0,25 - 50,00 0,25 100,00 Rp 2.737.000,00
- Untuk Pondasi Selasar M3 5,00 Rp 54.740,00 Rp 273.700,00 0,03 5,00 54.740,00 273.700,00 0,03 5,00 0,03 - 5,00 0,03 100,00 Rp 273.700,00
2 Urugan Kembali -
- Untuk Pondasi Utama M3 17,00 Rp 26.231,50 Rp 445.935,50 0,04 17,00 26.231,50 445.935,50 0,04 17,00 0,04 - 17,00 0,04 100,00 Rp 445.935,50
- Untuk Pondasi Selasar M3 2,00 Rp 26.231,50 Rp 52.463,00 0,00 2,00 26.231,50 52.463,00 0,00 2,00 0,00 - 2,00 0,00 100,00 Rp 52.463,00
3 Urugan Pasir Bawah Pondasi M3 3,00 Rp 864.685,00 Rp 2.594.055,00 0,24 3,00 864.685,00 2.594.055,00 0,24 3,00 0,24 - 3,00 0,24 100,00 Rp 2.594.055,00
4 Pasangan Pondasi Batu Kali 1:4 -
- Untuk Pondasi Utama M3 27,00 Rp 2.714.172,50 Rp 73.282.657,50 6,78 27,00 2.714.172,50 73.282.657,50 6,78 27,00 6,78 - 27,00 6,78 100,00 Rp 73.282.657,50
- Untuk Pondasi Selasar M3 13,00 Rp 2.714.172,50 Rp 35.284.242,50 3,26 13,00 2.714.172,50 35.284.242,50 3,26 13,00 3,26 - 13,00 3,26 100,00 Rp 35.284.242,50
5 Pasangan Pondasi Batu Kosong M3 9,00 Rp 1.606.199,25 Rp 14.455.793,25 1,34 9,00 1.606.199,25 14.455.793,25 1,34 9,00 1,34 - 9,00 1,34 100,00 Rp 14.455.793,25
Rp -
JUMLAH HARGA PEKERJAAN JEMBATAN Rp 129.125.846,75 11,94 129.125.846,75 11,94 11,94 - 11,94 Rp 129.125.846,75
PEKERJAAN STRUKTUR

1 Sloof Beton Bertulang ( 200 Kg + Bekesting ) M3 3,00 Rp 11.045.019,75 Rp 33.135.059,25 3,06 3,00 11.045.019,75 33.135.059,25 3,06 3,00 3,06 - 3,00 3,06 100,00 Rp 33.135.059,25
2 Kolom Beton Bertulang ( 200 Kg + Bekisting ) M3 3,00 Rp 14.989.100,00 Rp 44.967.300,00 4,16 3,00 14.989.100,00 44.967.300,00 4,16 3,00 4,16 - 3,00 4,16 100,00 Rp 44.967.300,00
3 Balok Beton Bertulang ( 150 Kg + Bekisting ) M3 3,00 Rp 13.065.552,50 Rp 39.196.657,50 3,63 3,00 13.065.552,50 39.196.657,50 3,63 3,00 3,63 - 3,00 3,63 100,00 Rp 39.196.657,50
4 Plat Beton Bertulang ( 120 Kg + Bekisting ) M3 1,00 Rp 11.558.845,50 Rp 11.558.845,50 1,07 1,00 11.558.845,50 11.558.845,50 1,07 1,00 1,07 - 1,00 1,07 100,00 Rp 11.558.845,50
5 Kolom Praktis M1 12,00 Rp 174.823,00 Rp 2.097.876,00 0,19 12,00 174.823,00 2.097.876,00 0,19 12,00 0,19 - 12,00 0,19 100,00 Rp 2.097.876,00
6 Balok Praktis M1 12,50 Rp 197.794,25 Rp 2.472.428,13 0,23 12,50 197.794,25 2.472.428,13 0,23 12,50 0,23 - 12,50 0,23 100,00 Rp 2.472.428,13
Rp -
0 Rp 133.428.166,38 12,34 133.428.166,38 12,34 12,34 - 12,34 Rp 133.428.166,38
PEKERJAAN LANTAI
Urugan Tanah Bawah Lantai
1 - Bagian dalam M3 11,00 Rp 862.212,50 Rp 9.484.337,50 0,88 11,00 862.212,50 9.484.337,50 0,88 11,00 0,88 - 11,00 0,88 100,00 Rp 9.484.337,50
- Bagian luar M3 23,00 Rp 862.212,50 Rp 19.830.887,50 1,83 23,00 862.212,50 19.830.887,50 1,83 23,00 1,83 - 23,00 1,83 100,00 Rp 19.830.887,50
Urugan Pasir Bawah Lantai
2 - Bagian dalam M3 3,00 Rp 864.685,00 Rp 2.594.055,00 0,24 3,00 864.685,00 2.594.055,00 0,24 - 1,50 0,12 1,50 0,12 50,00 Rp 1.297.027,50
- Bagian luar M3 6,00 Rp 864.685,00 Rp 5.188.110,00 0,48 6,00 864.685,00 5.188.110,00 0,48 - 5,00 0,40 5,00 0,40 83,33 Rp 4.323.425,00
Pas. Lantai keramik 60x60 M2 110,00 Rp 1.032.763,25 Rp 113.603.957,50 10,51 110,00 1.032.763,25 113.603.957,50 10,51 - - - - - Rp -
Pas. Lantai keramik 40x40 M2 6,00 Rp 3.057.664,85 Rp 18.345.989,10 1,70 6,00 3.057.664,85 18.345.989,10 1,70 - - - - - Rp -
Beton Tumbuk 1 : 3 : 5 M2 9,00 Rp 255.035,50 Rp 2.295.319,50 0,21 9,00 255.035,50 2.295.319,50 0,21 9,00 0,21 - 9,00 0,21 100,00 Rp 2.295.319,50

Rp -
0 Rp 171.342.656,10 15,85 171.342.656,10 15,85 2,92 0,52 3,44 Rp 37.230.997,00
LAPORAN KEMAJUAN PEKERJAAN MINGGUAN
KONTRAKTOR
MINGGU KE- PERIODE TANGGAL KONSULTAN PENGAWAS
PELAKSANA
KEMENTRIAN AGAMA REPUBLIK INDONESIA
KANTOR KEMENTRIAN AGAMA KABUPATEN KEPULAUAN ARU 21 Agustus 2022
JL. PEMDA I TELP/FAX (0917) 22121 M-IV S/D
27 Agustus 2022
CV. TRIIASA MANDIRI CV. DELTA DIMENSI CONSULTAN

BOBOT PRESTASI S/D BOBOT PRESTASI MINGGU BOBOT PRESTASI S/D JUMLAH HARGA S/D MINGGU INI
Nomor Kontrak Fisik : 09/SP-PL/PPK-PUPR/VI/2021 MINGGU LALU (%) INI (%) MINGGU INI (%) (RUPIAH) + PPn 10%
No Kontrak : II.A/KK.25.06/3/SP-KONSTRUKSI/06/2022
: PEMBANGUNAN GEDUNG BALAI NIKAH DAN MANASIK HAJI 44,70% 2,02% 46,72% Rp 560.661.718,86
KOLAMAR KABUPATEN KEP.ARU
DATA KONTRAK DATA MUTUAL CHECK REALISASI
S/D MINGGU LALU MINGGU INI S/D MINGGU INI
HARGA SATUAN
NO. URAIAN PEKERJAAN SATUAN HARGA SATUAN JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT BOBOT (%)
VOL VOL JUMLAH SATUAN
( RUPIAH ) ( RUPIAH ) (%) ( RUPIAH ) ( RUPIAH ) (%) VOL BOBOT (%) VOL BOBOT (%) VOL THDP
REAL (RUPIAH)
ITEM
(1) 2 3 (4) (5) (6) (7) (8) (9) (11) (12) (14) (15) (16) (17)

PEKERJAAN DINDING
1 Pasangan 1/2 batu bata 1 : 4 M2 300 Rp 448.155,00 Rp 134.446.500,00 12,44 300,00 448.155,00 134.446.500,00 12,44 300,00 12,44 - 300,00 12,44 100,00 Rp 134.446.500,00
2 Pasangan Plesteran 1 : 5 ( T. 15 ) M2 600,00 Rp 108.209,25 Rp 64.925.550,00 6,01 600,00 108.209,25 64.925.550,00 6,01 - 150,00 1,50 150,00 1,50 25,00 Rp 16.231.387,50
3 Pas. Pintu Panel Kls I M2 15,00 Rp 687.987,50 Rp 10.319.812,50 0,95 15,00 687.987,50 10.319.812,50 0,95 - - - - - Rp -
4 Pas. Pintu dan jendela kaca Kls I M2 10,00 Rp 564.190,00 Rp 5.641.900,00 0,52 10,00 564.190,00 5.641.900,00 0,52 - - - - - Rp -
5 Pas. Kusen Pintu dan Jendela Kls I M3 2,00 Rp 8.575.550,00 Rp 17.151.100,00 1,59 2,00 8.575.550,00 17.151.100,00 1,59 - - - - - Rp -
6 Pas. Dinding keramik 20x20 untuk KM/WC M2 26,00 Rp 3.064.433,75 Rp 79.675.277,50 7,37 26,00 3.064.433,75 79.675.277,50 7,37 - - - - - Rp -
7 Benangan Dinding M1 40,00 Rp 75.000,00 Rp 3.000.000,00 0,28 40,00 75.000,00 3.000.000,00 0,28 - - - - - Rp -
8 Pas. Kaca Polos 5 mm M2 15,00 Rp 94.147,63 Rp 1.412.214,38 0,13 15,00 94.147,63 1.412.214,38 0,13 - - - - - Rp -
Rp -
0 Rp 316.572.354,38 29,28 316.572.354,38 29,28 12,44 1,50 13,94 Rp 150.677.887,50
PEKERJAAN PLAFOND
-
1 Pas. Plafon Tripleks M2 166,00 Rp 66.441,25 Rp 11.029.247,50 1,02 166,00 66.441,25 11.029.247,50 1,02 Rp -
2 Pas. Rangka Plafon Kayu Klas II M2 166,00 Rp 117.967,00 Rp 19.582.522,00 1,81 166,00 117.967,00 19.582.522,00 1,81 - Rp -
3 Pas. List plafon profil M1 112,00 Rp 114.465,25 Rp 12.820.108,00 1,19 112,00 114.465,25 12.820.108,00 1,19 - - - - - Rp -
Rp -
0 Rp 43.431.877,50 4,02 43.431.877,50 4,02 - - - Rp -
PEKERJAAN ATAP

1 Pas. Atap Metal Roof M2 216,00 Rp 109.526,00 Rp 23.657.616,00 2,19 216,00 109.526,00 23.657.616,00 2,19 Rp -
3 Pas. Bubungan/Nok bulat Metal Roof M2 46,00 Rp 157.141,75 Rp 7.228.520,50 0,67 46,00 157.141,75 7.228.520,50 0,67 - Rp -
4 Pas. Isolasi Atap Aluminium Foil M2 216,00 Rp 41.653,00 Rp 8.997.048,00 0,83 216,00 41.653,00 8.997.048,00 0,83 - - - - - Rp -
5 Pas. Lisplank 2 x (3x20) Kls I M1 56,00 Rp 140.144,75 Rp 7.848.106,00 0,73 56,00 140.144,75 7.848.106,00 0,73 Rp -
6 Pas. Kuda-kuda Kls I M2 1,72 Rp 7.858.755,00 Rp 13.545.978,82 1,25 1,72 7.858.755,00 13.545.978,82 1,25 - - - - - Rp -
7 Pasang gording kayu klas II M3 1,80 Rp 5.221.115,00 Rp 9.398.007,00 0,87 1,80 5.221.115,00 9.398.007,00 0,87 - Rp -
8 Pas. Kaso 5/7 + Reng Kls II M2 216,00 Rp 81.017,50 Rp 17.499.780,00 1,62 216,00 81.017,50 17.499.780,00 1,62 Rp -
Rp -
0 Rp 88.175.056,32 8,16 88.175.056,32 8,16 - - - Rp -
PEKERJAAN UTILITAS

1 Bak kontrol batu bata 30x30 Buah 6,00 Rp 744.200,00 Rp 4.465.200,00 0,41 6,00 744.200,00 4.465.200,00 0,41 Rp -
3 Saluran Air Keliling M' 52,00 Rp 400.000,00 Rp 20.800.000,00 1,92 52,00 400.000,00 20.800.000,00 1,92 - Rp -
4 Pas. kunci tanam antik Buah 2,00 Rp 646.265,50 Rp 1.292.531,00 0,12 2,00 646.265,50 1.292.531,00 0,12 - - - - - Rp -
5 Pas. kunci tanam biasa Buah 4,00 Rp 323.265,00 Rp 1.293.060,00 0,12 4,00 323.265,00 1.293.060,00 0,12 Rp -
6 Pas. kunci tanam Kamar Mandi Buah 2,00 Rp 326.370,00 Rp 652.740,00 0,06 2,00 326.370,00 652.740,00 0,06 Rp -
7 Pas. engsel pintu Buah 31,00 Rp 70.572,63 Rp 2.187.751,38 0,20 31,00 70.572,63 2.187.751,38 0,20 Rp -
8 Pas. engsel jendela Buah 40,00 Rp 68.131,75 Rp 2.725.270,00 0,25 40,00 68.131,75 2.725.270,00 0,25 Rp -
9 Pas. kait angin Buah 40,00 Rp 47.572,63 Rp 1.902.905,00 0,18 40,00 47.572,63 1.902.905,00 0,18 Rp -
10 Pas. Grendel Jendela Buah 20,00 Rp 127.908,75 Rp 2.558.175,00 0,24 20,00 127.908,75 2.558.175,00 0,24 Rp -
11 Genset Kapsitas 2000 Watt Buah 1,00 Rp 8.000.000,00 Rp 8.000.000,00 0,74 1,00 8.000.000,00 8.000.000,00 0,74 Rp -
12 MCB 10 Ampere Bh 1,00 Rp 150.000,00 Rp 150.000,00 0,01 1,00 150.000,00 150.000,00 0,01 Rp -
13 Instalasi Listrik Lengkap Vetting & kabel Ttk 16,00 Rp 350.000,00 Rp 5.600.000,00 0,52 16,00 350.000,00 5.600.000,00 0,52 Rp -
14 Stop Kontak Tanam Bh 6,00 Rp 85.600,00 Rp 513.600,00 0,05 6,00 85.600,00 513.600,00 0,05 Rp -
15 Saklar Tunggal Tanam Bh 8,00 Rp 85.600,00 Rp 684.800,00 0,06 8,00 85.600,00 684.800,00 0,06 Rp -
16 Lampu Jari-jari 18 Watt Bh 16,00 Rp 100.000,00 Rp 1.600.000,00 0,15 16,00 100.000,00 1.600.000,00 0,15 Rp -
17 Pas. Water Tank Steinliss Kapasitas 1000Ltr + Dudukan Unit 1,00 Rp 15.000.000,00 Rp 15.000.000,00 1,39 1,00 15.000.000,00 15.000.000,00 1,39 Rp -
18 Kloset Duduk Toto/Lengkap Set 2,00 Rp 3.500.000,00 Rp 7.000.000,00 0,65 2,00 3.500.000,00 7.000.000,00 0,65 Rp -
19 Wastafel Taplo Toto Set 1,00 Rp 1.600.000,00 Rp 1.600.000,00 0,15 1,00 1.600.000,00 1.600.000,00 0,15 Rp -
20 Instalasi air bersih dan pembuangan air kotor Lot 1,00 Rp 3.581.000,00 Rp 3.581.000,00 0,33 1,00 3.581.000,00 3.581.000,00 0,33 Rp -
LAPORAN KEMAJUAN PEKERJAAN MINGGUAN
KONTRAKTOR
MINGGU KE- PERIODE TANGGAL KONSULTAN PENGAWAS
PELAKSANA
KEMENTRIAN AGAMA REPUBLIK INDONESIA
KANTOR KEMENTRIAN AGAMA KABUPATEN KEPULAUAN ARU 21 Agustus 2022
JL. PEMDA I TELP/FAX (0917) 22121 M-IV S/D
27 Agustus 2022
CV. TRIIASA MANDIRI CV. DELTA DIMENSI CONSULTAN

BOBOT PRESTASI S/D BOBOT PRESTASI MINGGU BOBOT PRESTASI S/D JUMLAH HARGA S/D MINGGU INI
Nomor Kontrak Fisik : 09/SP-PL/PPK-PUPR/VI/2021 MINGGU LALU (%) INI (%) MINGGU INI (%) (RUPIAH) + PPn 10%
No Kontrak : II.A/KK.25.06/3/SP-KONSTRUKSI/06/2022
: PEMBANGUNAN GEDUNG BALAI NIKAH DAN MANASIK HAJI 44,70% 2,02% 46,72% Rp 560.661.718,86
KOLAMAR KABUPATEN KEP.ARU
DATA KONTRAK DATA MUTUAL CHECK REALISASI
S/D MINGGU LALU MINGGU INI S/D MINGGU INI
HARGA SATUAN
NO. URAIAN PEKERJAAN SATUAN HARGA SATUAN JUMLAH HARGA BOBOT JUMLAH HARGA BOBOT BOBOT (%)
VOL VOL JUMLAH SATUAN
( RUPIAH ) ( RUPIAH ) (%) ( RUPIAH ) ( RUPIAH ) (%) VOL BOBOT (%) VOL BOBOT (%) VOL THDP
REAL (RUPIAH)
ITEM
(1) 2 3 (4) (5) (6) (7) (8) (9) (11) (12) (14) (15) (16) (17)

21 Bak Cuci Stanliss 2 Mata + Dudukan Unt 1,00 Rp 2.000.000,00 Rp 2.000.000,00 0,18 1,00 2.000.000,00 2.000.000,00 0,18 Rp -
22 Kran dinding Set 3,00 Rp 149.600,00 Rp 448.800,00 0,04 3,00 149.600,00 448.800,00 0,04 - - - - - Rp -
23 Floor drain Bh 2,00 Rp 100.000,00 Rp 200.000,00 0,02 2,00 100.000,00 200.000,00 0,02 - Rp -
24 Septictank & Peresapan Lengkap Unit 2,00 Rp 7.500.000,00 Rp 15.000.000,00 1,39 2,00 7.500.000,00 15.000.000,00 1,39 Rp -
Rp -
PEKERJAAN FINISHING Rp 99.255.832,38 9,18 99.255.832,38 9,18 - - - Rp -
PEKERJAAN FINISHING

1 Pengecatan kayu baru = ( 1 x Plamir ) 1 cat dasar, 2 lapis cat M2 129,30 Rp 89.769,00 Rp 11.607.562,59 1,07 129,30 89.769,00 11.607.562,59 1,07 - - - - - Rp -
2 Pengecatan tembok baru = ( 1 x Plamir ) 1 cat dasar, 2 lapis cat M2 600,00 Rp 32.512,23 Rp 19.507.335,00 1,80 600,00 32.512,23 19.507.335,00 1,80 - - - - - Rp -
3 Pengecatan Plafon = ( 1 x Plamir ) 1 cat dasra, 2 lapis cat M2 166,00 Rp 32.512,23 Rp 5.397.029,35 0,50 166,00 32.512,23 5.397.029,35 0,50 - - - - - Rp -
-
JUMLAH HARGA PEKERJAAN AKHIR Rp 36.511.926,94 3,38 36.511.926,94 3,38 - - - Rp -

JUMLAH HARGA (RUPIAH) Rp 1.081.081.466,73 100,00 1.081.081.466,73 100,00 44,70 2,02 46,72 Rp 505.100.647,63
PPN 11% Rp 118.918.961,34 118.918.961,34 Rp 55.561.071,24
GRAND TOTAL (RUPIAH) Rp 1.200.000.000,00 1.200.000.000,00 Rp 560.661.718,86

Anda mungkin juga menyukai