NO : P01974
011 BETON K300 untuk Plat Injak (2x4m) 6.00 M3 1,750,000.00 1,050,000.00 9,450,000.00
Perbaikan Jembatan Muara Maung
Permintaan : Doni Kuncoro
DP 50%, Balance 50% after job finished + bast | VENDOR TANPA PERBANDINGAN DENGAN CURRENCY IDR
PERSETUJUAN.
SUB TOTAL 205,315,200.00
DISCOUNT 22,812,800.00
PPN 20,531,520.00
PPH 0.00
Kind regards,
PT. BARA ALAM UTAMA
NUR ALAWIYAH
SERVICE ORDER
NO : P01975
T.O.P JASA: DP 50% saat PO , Pelunasan setelah selesai+BAST VENDOR TANPA PERBANDINGAN CURRENCY IDR
DENGAN PERSETUJUAN.
SUB TOTAL 205,315,200.00
DISCOUNT 22,812,800.00
PPN 20,531,520.00
PPH 4,106,304.00
NUR ALAWIYAH
PURCHASE ORDER
NO : P01976
DP 50%, Balance 50% after job finished + bast | VENDOR TANPA PERBANDINGAN DENGAN CURRENCY IDR
PERSETUJUAN.
SUB TOTAL 196,514,100.00
DISCOUNT 21,834,900.00
PPN 19,651,410.00
PPH 0.00
Kind regards,
PT. BARA ALAM UTAMA
NUR ALAWIYAH