Anda di halaman 1dari 3

Job Description : Pege 1_ of _1_ JSA No.

Date : NEW REVISED


( Uraian Pekerjaan ) Hal 1 dari 1 JSA No. Tanggal : Baru. X Revisi
Membuka muster pin di raising jack __________/__________/___________
Time :
JOB SAFETY ANALYSIS Area / Location : JOB TEAM :
( Analisa Keselamatan Pekerjaan ) Minas,4B-81E
ABS Drilling Team
FACILITY OWNER : FACILITY / EQUIPMENT : JOB TEAM LEADER : SH & E MESSAGE
( Pemilik Fasilitas ) ( Fasilitas / Peralatan ) ( Penanggung Jawab Pekerjaan ) Pesan Tentang SH & E
PT. ALAM BERSEMI SENTOSA
" KESELAMATAN ADALAH KUNCI KEBERHASILAN
UNTUK MASA DEPAN "
REQUIRED / RECOMMENDED PPE : 1. SAFETY SHOES 3. SAFETY GLASS 5. EAR PLUG
PPE Yang Dibutukan / Disarankan 2. SAFETY HAT 4. HAND GLOVE

BASIC SEQUENCES OF JOB STEPS HAZARD POTENTIAL HAZARDS RECOMMENDED ACTIONS OR PROCEDURES PIC SUPERVISION
( URUTAN PEKERJAAN ) IDENTIFICATION ( BAHAYA YANG TERKAIT ) ( LANGKAH / PROSEDUR YANG DISARANKAN )
Pergerakan crane harus selalu dipandu oleh signalman
1. Set Crane pada posisi yang level Motion Crane menabrak euipment lain /orang lain Crane oprt TP
2. Pasang sling pengangkat pada hook crane Crane oprt TP
Motion Terjepit antara master link dan lock door hook crane Hindari titik jepit antara master link dan lock door hook crane
Gravity Tertimpa hook block crane yang melorot Hindari daerah berbahaya, posisikan badan dalam kondisi aman
3. Ikat raising ramp/jack dengan sling pengangkat Motion Tangan terjepit oleh sling Posisikan tangan ditempat yang aman Mechanic TP
4. Atur ketegangan sling sampai posisi master Gravity Sling putus Memberi aba-aba yang benar kepada crane operator Signalman crane TP
pin dan eye pad longgar
Gravity Tertimpa hook block crane yang melorot Hindari daerah berbahaya, posisikan badan dalam kondisi aman
5. Buka safety pin /cutter pin dan keluarkan master pin Floorman TP
dengan menggunakan martil secara pelan-pelan Motion martil bisa lepas dan menghantam orang lain Pegang martil dengan erat
Gravity Pin yang dibuka jatuh dan menimpa orang Jangan ada orang berada dibawah raising jack
6. Turunkan raising jack pelan-pelan sampai keluar
dari posisi eye pad Gravity Tertimpa raising jack karena ikatan sling lepas Pastikan sling terikat dengan benar Floorman TP
7. Lakukan prosedur NDT eye pad by lekommaras Chemical Terkena percikan chemical untuk NDT Gunakan sarung tangan karet dan PPE tambahan lainnya Lekommaras Lekommaras

8 .Angkat raising ramp pelan-pelan sampai pada


posisi eye pad dan posisikan lobangnya sudah center Motion Badan terjepit oleh raising jack Posisikan badan ditempat yang aman Mechanic TP

9. Pasang kembali muster pin dengan martil secara


pelan-pelan sampai posisinya benar dan pasang cutter pin Motion Tangan terpukul oleh martil Posisikan jari tangan ditempat yang aman Mechanic TP

DISTRIBUTION : ORIGINAL AT JOB TL PREPARED BY : APPROVED BY : AKNOWLEDGE BY :


COPY FOR SHE COORDINATOR (FILE ) (DIBUAT OLEH ) ( DISETUJUI OLEH )
DISTRIBUSI : ASLI DISIMPAN PENANGGUNG JAWAB PEKERJAAN
SALINAN DISIMPAN SH&E COORDINATOR (ARSIP)
Job Description : Pege 1_ of _1_ JSA No. Date : NEW REVISED
( Uraian Pekerjaan ) Hal 1 dari 1 JSA No. Tanggal : Baru. X Revisi
Membuka muster pin di bottom mast __________/__________/___________
Time :
JOB SAFETY ANALYSIS Area / Location : JOB TEAM :
( Analisa Keselamatan Pekerjaan ) Minas,4B-81E
ABS Drilling Team
FACILITY OWNER : FACILITY / EQUIPMENT : JOB TEAM LEADER : SH & E MESSAGE
( Pemilik Fasilitas ) ( Fasilitas / Peralatan ) ( Penanggung Jawab Pekerjaan ) Pesan Tentang SH & E
PT. ALAM BERSEMI SENTOSA
" KESELAMATAN ADALAH KUNCI KEBERHASILAN
UNTUK MASA DEPAN "
REQUIRED / RECOMMENDED PPE : 1. SAFETY SHOES 3. SAFETY GLASS 5. EAR PLUG
PPE Yang Dibutukan / Disarankan 2. SAFETY HAT 4. HAND GLOVE

BASIC SEQUENCES OF JOB STEPS HAZARD POTENTIAL HAZARDS RECOMMENDED ACTIONS OR PROCEDURES PIC SUPERVISION
( URUTAN PEKERJAAN ) IDENTIFICATION ( BAHAYA YANG TERKAIT ) ( LANGKAH / PROSEDUR YANG DISARANKAN )
Pergerakan crane harus selalu dipandu oleh signalman
1. Set Crane pada posisi yang level Motion Crane menabrak euipment lain /orang lain Crane oprt TP
2. Pasang sling pengangkat pada hook crane Crane oprt TP
Motion Terjepit antara master link dan lock door hook crane Hindari titik jepit antara master link dan lock door hook crane
Gravity Tertimpa hook block crane yang melorot Hindari daerah berbahaya, posisikan badan dalam kondisi aman
3. Ikatkan sling angkat ke mast dengan benar dan pastikan pos Motion Tangan terjepit oleh sling Posisikan tangan ditempat yang aman Mechanic TP
4. Buka safety pin /cutter pin dan keluarkan master pin Gravity Sling putus Memberi aba-aba yang benar kepada crane operator Signalman crane TP
dengan menggunakan martil secara pelan-pelan
Gravity Tertimpa hook block crane yang melorot Hindari daerah berbahaya, posisikan badan dalam kondisi aman
5. Turunkan mast pelan-pelan sampai keluar dari posisi Floorman TP
eye pad Motion martil bisa lepas dan menghantam orang lain Pegang martil dengan erat
Gravity Pin yang dibuka jatuh dan menimpa orang Jangan ada orang berada dibawah raising jack

6. Lakukan prosedur NDT eye pad by lekommaras Chemical Terkena percikan chemical untuk NDT Gunakan sarung tangan karet dan PPE tambahan lainnya Lekommaras Lekommaras
7 .Angkat Mast pelan-pelan sampai pada posisi eye
pad dan posisikan lobangnya sudah center Motion Badan terjepit oleh Mast Posisikan badan ditempat yang aman Mechanic TP

8. Pasang kembali muster pin dengan martil secara


pelan-pelan sampai posisinya benar dan pasang cutter pin Motion Tangan terpukul oleh martil Posisikan jari tangan ditempat yang aman Mechanic TP

DISTRIBUTION : ORIGINAL AT JOB TL PREPARED BY : APPROVED BY : AKNOWLEDGE BY :


COPY FOR SHE COORDINATOR (FILE ) (DIBUAT OLEH ) ( DISETUJUI OLEH )
DISTRIBUSI : ASLI DISIMPAN PENANGGUNG JAWAB PEKERJAAN
SALINAN DISIMPAN SH&E COORDINATOR (ARSIP)

Anda mungkin juga menyukai