PEKERJAAN PENAMBAHAN TYPE 50/125

Pekerjaan peritem/volume upah kerja

1. Pondasi panjang = 9 m - Rp 40.000


2. Sloff Panjang = 9 m - Rp 50.000
3. Ringbalok Panjang = 9 m - Rp 50.000
4. Pasangan bata Vol = 18 m2 - Rp 40.000
5. Plester Vol = 36 m2 - Rp 25.000
6. Acian Vol = 36 m2 - Rp 15.000
7. Cat Vol = 36 m2 - Rp 7.000

A. UPAH KERJA

1. Pondasi Vol = 9m x Rp 40.000 = Rp 360.000


2. Sloff vol = 9m x Rp 50.000 = Rp 450.000
3. Ringbalok vol= 9m x Rp50.000 = Rp 450.000
4. Pasangan Bata vol = 18mxRp 40.000 = Rp 720.000
5. Plester vol = 36mxRp 25.000 = Rp 900.000
6. Acian vol = 36mxRp 15.000 = Rp 540.000
7. Cat vol = 36mx Rp 7.000 = Rp 252.000

Total Upah Kerja = Rp 3.672,000

B. KEBUTUHAN MATERIAL

Pondasi

V = 1.8 M3

INDEKS SNI X VOL

Kebutuhan Batu Kali = 1.2 m3 x 1,8 m3 = 2.16 m3 (2.5m3) Rp 320.000

Kebutuhan Semen = 163 kg x 1.8 m3 = 293,4/40 kg = 7,33 (8sak) X Rp 60.000 =Rp 480.000

Kebutuhan Pasir = 0.52 x 1.8 m3 = 0.936 m3 (1m3) = Rp 200.000

Sloff + ring balk

V = 0.54

Kebutuhan Semen = 352 kg x 0,54m3 = 4,752 ( 5sak)x Rp 60.000 =Rp300.000

Kebutuhan Pasir = 0.333 m3 x 0.54 m3 = 0.1798 (0.2m3) Rp 100.000

Kebutuhan Split = 0.5m3 x 0.54m3 = 0.27 (0,30m3) Rp 135.000


Kebutuhan Besi = Tulangan Utama

= 4 x 18m = 72m/12m

= 6 batang 10 mm x Rp 96.000 = Rp576.000

= Begel

= (0.15 X 0.20) X 2 = 70 +0.10 = 0.80 m

= 18/0.20 = 90 bh

= 90 x 0.80 = 72m/12m

= 6 batang 8 mm x Rp 72.000 =Rp 432.000

Dinding

Vol 18

INDEKS SNI X VOL : Semen=11.5kg m2, Pasir = 0.043 m3

Kebutuhan Pasir : 0.043 m3 x 18m2 = 0.774m3

=1m3 = Rp200.000

Kebutuhan bata : 70 biji m2 x 32m2 = 2.240 biji

Kebutuhan semen : 11.5kg x 18 = 207 kg/40kg = 5,175(6sak)x Rp60.000 = Rp360.000

Plester

Vol : 32m2

INDEKS SNI X VOL : Semen=6.240kg m2, Pasir = 0.024 m3

Kebutuhan Semen = 32 x 6.240 = 199.680/40kg=4.9(5sak)x Rp60.000 = Rp300.000

Kebutuhan pasir = 32 x 0.024 m3 =0.768(1m3) Rp 200.000

Acian

Vol : 32m2

INDEKS SNI X VOL

Semen=3.25kg

Kebutuhan semen 36m2 x 3,25kg = 117kg/40kg

= 2.9 (3sak) x Rp 60.000 = Rp180.000

Cat

1 lt = 6.5 m2

1 pile 20 lt x 6.5m = 130 m2 (kebutuhan luasan cat yang dibutuhkan hanya 36m2) ?

= ½ pile Rp 450.000
RIT

VOL = 60 M3

P = 3 L = 20 T = 1M

= 3 X 20 X 1 = 60 M3

INDEKS SNI :1.20 X VOL

= 60M3 X 1,20 = 72 M3/4M3 = 18 Mobil x Rp 80.000 = Rp1.440.000

Total Harga Material = Rp 5.673.000

Total harga upah kerja =Rp 3.672.000+

Total material + upah kerja =Rp 9.345.000