A. UPAH KERJA
B. KEBUTUHAN MATERIAL
Pondasi
V = 1.8 M3
Kebutuhan Semen = 163 kg x 1.8 m3 = 293,4/40 kg = 7,33 (8sak) X Rp 60.000 =Rp 480.000
V = 0.54
= 4 x 18m = 72m/12m
= Begel
= 18/0.20 = 90 bh
= 90 x 0.80 = 72m/12m
Dinding
Vol 18
=1m3 = Rp200.000
Plester
Vol : 32m2
Acian
Vol : 32m2
Semen=3.25kg
Cat
1 lt = 6.5 m2
1 pile 20 lt x 6.5m = 130 m2 (kebutuhan luasan cat yang dibutuhkan hanya 36m2) ?
= ½ pile Rp 450.000
RIT
VOL = 60 M3
P = 3 L = 20 T = 1M
= 3 X 20 X 1 = 60 M3