S Kurve 10 Nov
S Kurve 10 Nov
Sep-19 Okt-19
No. URAIAN PEKERJAAN Volume Satuan Bobot Hari 16/Sep 23/Sep 30/Sep 7/Okt 14/Okt 21/Okt 28/Okt 4/Nop
(%) 22/Sep 29/Sep 6/Okt 13/Okt 20/Okt 27/Okt 3/Nop 10/Nop
I PEKERJAAN PERSIAPAN
1 Survey Awal Lokasi Kerja 1.00 Lot 0.11 7 0.1100
II SURFACE PREPARATION
Pengupasan Permukaan Pipa 4.355 m2 34.87 21 11.62333 11.62333 11.62333
(menggunakan bahan paint remover dan alat bantu mekanis)
3 PRIMER COATING (JOTUN JOTAMASTIC 80 Red OR Eqv ) 4.355 m2 26.92 28 6.7300 6.7300 6.7300 6.7300
4 INTERMEDIATE COATING (JOTUN JOTAMASTIC 80 Grey or Eqv ) 4.355 m2 14.02 28 3.5050 3.5050 3.5050 3.5050
PROGRESS 100.0 245 0.11000 7.70000 11.43500 31.46667 30.49667 18.36167 0.20000 0.25000
KUMULATIF PROGRESS - 0.11 7.81 19.25 50.71 81.21 99.57 99.77 100
24.00
Nop-19
11/Nop 18/Nop 25/Nop
17/Nop 24/Nop 1/Des
0.0100
- - 0.01000
100.02 100.02 100
Diperiksa dan disetujui oleh,
Ast. Manager Planning
PT. Pertamina Gas
??