KEGIATAN :

Pekerja/Kenek AN :
LOKASI : KOTA KENYAM KABUPATEN NDUGA
TAHUN ANGG : 2021

HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

I PEKERJAAN PERSIAPAN
1 100 M2 Pekerjaan Pengukuran Gedung 2,856,666.67
U01 Pekerja/Kenek 8.000 O/h 180,000.00 1,440,000.00
U15 Mandor/Pengawas 2.000 O/h 300,000.00 600,000.00
U16 Pengawas / Ahli Teknik 0.500 O/h 833,333.33 416,666.67
U18 Asisten Ahli Ukur 2.000 O/h 200,000.00 400,000.00
A29 Sewa alat ukur 1.000 Hr -
JUMLAH 2,856,666.67
Untuk 1m2 Pekerjaan Pengukuran 1.00 m2 2,856,666.67 2,856,666.67

2 1 M' Pagar Sementara Dari Kayu Tinggi 2 M 470,969.70


B20 Dolken Kayu Dia. 8-10/400 cm 1.250 Batang 35,000.00 43,750.00
B01 Semen Portland 2.500 Kg 2,500.00 6,250.00
B111 Pasir Beton (m3) 0.005 M3 360,000.00 1,800.00
B96 Kerikil Koral 0.009 M3 480,000.00 4,320.00
B117 Kayu Kelas II Matoa ( Balok ) 0.072 M3 3,500,000.00 252,000.00
B32 Paku Biasa 0.080 Kg 30,000.00 2,400.00
B339 Meni Besi 0.450 Kg 59,666.00 26,849.70
U01 Pekerja/Kenek 0.400 O/h 180,000.00 72,000.00
U04 Tukang Kayu 0.200 O/h 250,000.00 50,000.00
U14 Kepala Tukang 0.020 O/h 280,000.00 5,600.00
U15 Mandor/Pengawas 0.020 O/h 300,000.00 6,000.00
JUMLAH 470,969.70

3 1 M' Pagar Sementara Dari Seng Gelombang Tinggi 2 M 534,120.00


B20 Dolken Kayu Dia. 8-10/400 cm 1.250 Batang 35,000.00 43,750.00
B01 Semen Portland 2.500 Kg 2,500.00 6,250.00
B62 Seng Gelombang BLJS 20 1.200 Lembar 75,000.00 90,000.00
B111 Pasir Beton (m3) 0.005 M3 360,000.00 1,800.00
B96 Kerikil Koral 0.009 M3 480,000.00 4,320.00
B117 Kayu Kelas II Matoa ( Balok ) 0.072 M3 3,500,000.00 252,000.00
B32 Paku Biasa 0.080 Kg 30,000.00 2,400.00
B338 Cat Residu 0.450 Kg -
U01 Pekerja/Kenek 0.400 O/h 180,000.00 72,000.00
U04 Tukang Kayu 0.200 O/h 250,000.00 50,000.00
U14 Kepala Tukang 0.020 O/h 280,000.00 5,600.00
U15 Mandor/Pengawas 0.020 O/h 300,000.00 6,000.00
JUMLAH 534,120.00

4 1 M' Pagar Sementara Dari Kawat Duri Tinggi 1,8 M 817,120.00


B20 Dolken Kayu Dia. 8-10/400 cm 1.250 Batang 35,000.00 43,750.00
B01 Semen Portland 2.500 Kg 2,500.00 6,250.00
B06 Kawat Duri 25.000 Kg 25,000.00 625,000.00
B111 Pasir Beton (m3) 0.005 M3 360,000.00 1,800.00
B96 Kerikil Koral 0.009 M3 480,000.00 4,320.00
B32 Paku Biasa 0.080 Kg 30,000.00 2,400.00
U01 Pekerja/Kenek 0.400 O/h 180,000.00 72,000.00
U04 Tukang Kayu 0.200 O/h 250,000.00 50,000.00
U14 Kepala Tukang 0.020 O/h 280,000.00 5,600.00
733291305.xlsx ANALISA 1 /1
HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

U15 Mandor/Pengawas 0.020 O/h 300,000.00 6,000.00


JUMLAH : 817,120.00

5 1 M' Pengukuran Dan Pemasangan Bouwplank 139,350.00


B117 Kayu Kelas II Matoa ( Balok ) 0.012 M3 3,500,000.00 42,000.00
B120 Kayu Kelas II Matoa ( Papan ) 0.007 M3 3,750,000.00 26,250.00
B32 Paku Biasa 0.020 Kg 30,000.00 600.00
U01 Pekerja/Kenek 0.150 O/h 180,000.00 27,000.00
U03 Tukang 0.150 O/h 250,000.00 37,500.00
U14 Kepala Tukang 0.015 O/h 280,000.00 4,200.00
U15 Mandor/Pengawas 0.006 O/h 300,000.00 1,800.00
JUMLAH : 139,350.00

6 1 M2 Pembuatan Kantor Sementara Dengan Lantai Plesteran 1,728,050.00


B20 Dolken Kayu Dia. 8-10/400 cm 1.700 Batang 35,000.00 59,500.00
B117 Kayu Kelas II Matoa ( Balok ) 0.210 M3 3,500,000.00 735,000.00
B32 Paku Biasa 0.300 Kg 30,000.00 9,000.00
B01 Semen Portland 10.500 Kg 2,500.00 26,250.00
B111 Pasir Beton (m3) 0.030 M3 360,000.00 10,800.00
B96 Kerikil Koral 0.050 M3 480,000.00 24,000.00
B62 Seng Gelombang BLJS 20 1.500 Lembar 75,000.00 112,500.00
U01 Pekerja/Kenek 1.000 O/h 180,000.00 180,000.00
U04 Tukang Kayu 2.000 O/h 250,000.00 500,000.00
U14 Kepala Tukang 0.200 O/h 280,000.00 56,000.00
U15 Mandor/Pengawas 0.050 O/h 300,000.00 15,000.00
JUMLAH : 1,728,050.00

7 1 M2 Pembuatan Rumah Jaga/Konstruksi Kayu 1,816,500.00


B20 Dolken Kayu Dia. 8-10/400 cm 3.000 Batang 35,000.00 105,000.00
B117 Kayu Kelas II Matoa ( Balok ) 0.276 M3 3,500,000.00 966,000.00
B32 Paku Biasa 0.700 Kg 30,000.00 21,000.00
B62 Seng Gelombang BLJS 20 1.500 Lembar 75,000.00 112,500.00
U01 Pekerja/Kenek 1.000 O/h 180,000.00 180,000.00
U04 Tukang Kayu 1.500 O/h 250,000.00 375,000.00
U14 Kepala Tukang 0.150 O/h 280,000.00 42,000.00
U15 Mandor/Pengawas 0.050 O/h 300,000.00 15,000.00
JUMLAH : 1,816,500.00

8 1 M2 Pembersihan Lapangan dan Peralatan 33,000.00


U01 Pekerja/Kenek 0.100 O/h 180,000.00 18,000.00
U15 Mandor/Pengawas 0.050 O/h 300,000.00 15,000.00
JUMLAH : 33,000.00

9 1 M2 Pembuatan Bedeng Buruh 1,628,300.00


B20 Dolken Kayu Dia. 8-10/400 cm 1.250 Batang 35,000.00 43,750.00
B117 Kayu Kelas II Matoa ( Balok ) 0.186 M3 3,500,000.00 651,000.00
B32 Paku Biasa 0.300 Kg 30,000.00 9,000.00
B01 Semen Portland 10.500 Kg 2,500.00 26,250.00
B111 Pasir Beton (m3) 0.030 M3 360,000.00 10,800.00
B96 Kerikil Koral 0.050 M3 480,000.00 24,000.00
B62 Seng Gelombang BLJS 20 1.500 Lembar 75,000.00 112,500.00
B12 Plywood 4 mm 1.350 Lembar - -
U01 Pekerja/Kenek 1.000 O/h 180,000.00 180,000.00
U04 Tukang Kayu 2.000 O/h 250,000.00 500,000.00
U14 Kepala Tukang 0.200 O/h 280,000.00 56,000.00
U15 Mandor/Pengawas 0.050 O/h 300,000.00 15,000.00
JUMLAH : 1,628,300.00

10 1 M2 Pembuatan Stegger dari Bambu Ukuran ( 40 x 40 x 20 ) cm 53,710.00

733291305.xlsx ANALISA 2 /2
HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

B123 Bambu Dia. 6 - 8 / 600 cm 1.000 Batang -


B251 Ijuk 0.250 Kg -
U01 Pekerja/Kenek 0.250 O/h 180,000.00 45,000.00
U04 Tukang Kayu 0.017 O/h 250,000.00 4,250.00
U14 Kepala Tukang 0.002 O/h 280,000.00 560.00
U15 Mandor/Pengawas 0.013 O/h 300,000.00 3,900.00
JUMLAH : 53,710.00

11 1 M2 Pembuatan Jalan Sementara 348,600.00


B90 Batu belah 15/20 0.150 M3 1,000,000.00 150,000.00
B92 Batu pecah 5/7 0.090 M3 -
B110 Pasir Pasang 0.010 M3 360,000.00 3,600.00
U01 Pekerja/Kenek 1.000 O/h 180,000.00 180,000.00
U15 Mandor/Pengawas 0.050 O/h 300,000.00 15,000.00
JUMLAH : 348,600.00

12 1 M3 Bongkaran Beton Bertulang 1,299,960.00


U01 Pekerja/Kenek 6.667 O/h 180,000.00 1,200,060.00
U15 Mandor/Pengawas 0.333 O/h 300,000.00 99,900.00
JUMLAH : 1,299,960.00

13 1 M3 Bongkaran Dinding Tembok Batako 1,209,960.00


U01 Pekerja/Kenek 6.667 O/h 180,000.00 1,200,060.00
U15 Mandor/Pengawas 0.033 O/h 300,000.00 9,900.00
JUMLAH : 1,209,960.00

II PEKERJAAN TANAH
1 1 M3 Galian Tanah Biasa Sedalam 1 M 142,500.00
U01 Pekerja/Kenek 0.750 O/h 180,000.00 135,000.00
U15 Mandor/Pengawas 0.025 O/h 300,000.00 7,500.00
JUMLAH : 142,500.00

2 1 M3 Galian Tanah Biasa Sedalam 2 M 175,500.00


U01 Pekerja/Kenek 0.900 O/h 180,000.00 162,000.00
U15 Mandor/Pengawas 0.045 O/h 300,000.00 13,500.00
JUMLAH : 175,500.00

3 1 M3 Galian Tanah Biasa Sedalam 3 M 209,100.00


U01 Pekerja/Kenek 1.050 O/h 180,000.00 189,000.00
U15 Mandor/Pengawas 0.067 O/h 300,000.00 20,100.00
JUMLAH : 209,100.00

4 1 M3 Galian Tanah Keras Sedalam 1 M 189,600.00


U01 Pekerja/Kenek 1.000 O/h 180,000.00 180,000.00
U15 Mandor/Pengawas 0.032 O/h 300,000.00 9,600.00
JUMLAH : 189,600.00

7 1 M3 Galian Tanah Cadas Sedalam 1 M 288,000.00


U01 Pekerja/Kenek 1.500 O/h 180,000.00 270,000.00
U15 Mandor/Pengawas 0.060 O/h 300,000.00 18,000.00
JUMLAH : 288,000.00

8 1 M3 Galian Tanah Lumpur Sedalam 1 M 229,500.00


U01 Pekerja/Kenek 1.200 O/h 180,000.00 216,000.00
U15 Mandor/Pengawas 0.045 O/h 300,000.00 13,500.00
JUMLAH : 229,500.00

9 1 M3 Pekerjaan Stripping Setinggi 1 M 10,500.00

733291305.xlsx ANALISA 3 /3
HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

U01 Pekerja/Kenek 0.050 O/h 180,000.00 9,000.00


U15 Mandor/Pengawas 0.005 O/h 300,000.00 1,500.00
JUMLAH : 10,500.00

10 1 M3 Pembuangan Tanah Sejauh 15 M 62,400.00


U01 Pekerja/Kenek 0.330 O/h 180,000.00 59,400.00
U15 Mandor/Pengawas 0.010 O/h 300,000.00 3,000.00
JUMLAH : 62,400.00

11 1 M3 Mengurug Kembali Galian 40,260.00


U01 Pekerja/Kenek 0.192 O/h 180,000.00 34,560.00
U15 Mandor/Pengawas 0.019 O/h 300,000.00 5,700.00
JUMLAH : 40,260.00

12 1 M3 Pemadatan Tanah ( per 20 cm) 105,000.00


U01 Pekerja/Kenek 0.500 O/h 180,000.00 90,000.00
U15 Mandor/Pengawas 0.050 O/h 300,000.00 15,000.00
JUMLAH : 105,000.00

13 1 M3 Urugan Pasir 369,000.00


B113 Pasir urug 1.200 M3 260,000.00 312,000.00
U01 Pekerja/Kenek 0.300 O/h 180,000.00 54,000.00
U15 Mandor/Pengawas 0.010 O/h 300,000.00 3,000.00
JUMLAH : 369,000.00

14 1 M3 Urugan Sirtu 364,500.00


B106 Sirtu Timbunan 1.200 260,000.00 312,000.00
U01 Pekerja/Kenek 0.250 O/h 180,000.00 45,000.00
U15 Mandor/Pengawas 0.025 O/h 300,000.00 7,500.00
JUMLAH : 364,500.00

14 1 M3 Urugan Kerikil 649,500.00


B95 Kerikil 1.200 M3 480,000.00 576,000.00
U01 Pekerja/Kenek 0.350 O/h 180,000.00 63,000.00
U15 Mandor/Pengawas 0.035 O/h 300,000.00 10,500.00
JUMLAH : 649,500.00

733291305.xlsx ANALISA 4 /4
HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

15 1 M3 Pembuatan Jalan Sementara, Tebal 25 cm 517,400.00


B90 Batu belah 15/20 0.275 M3 1,000,000.00 275,000.00
B95 Kerikil 0.030 M3 480,000.00 14,400.00
B110 Pasir Pasang 0.050 M3 360,000.00 18,000.00
U01 Pekerja/Kenek 1.000 O/h 180,000.00 180,000.00
U15 Mandor/Pengawas 0.100 O/h 300,000.00 30,000.00
JUMLAH : 517,400.00

16 Pek. Galian Tanah (Cut) Dengan Alat Berat / M3 242,379.55


U01 Pekerja/Kenek 0.109 O/h 180,000.00 19,620.00
U15 Mandor/Pengawas 0.054 O/h 300,000.00 16,200.00
Harga pemakaian alat berat
A10 Excavator 80 - 140 Hp 0.054 Jam 1,867,598.58 100,850.32
A09 Dump Truck 3 - 4 M3 0.100 Jam 1,007,092.31 100,709.23
A38 Alat bantu 1.000 Ls 5,000.00 5,000.00
JUMLAH : 242,379.55

17 Pek Urugan Sirtu (Fill) Dengan Alat Berat / M3 755,099.89


B106 Sirtu Timbunan 1.200 260,000.00 312,000.00
U01 Pekerja/Kenek 0.250 O/h 180,000.00 45,000.00
U15 Mandor/Pengawa 0.025 O/h 300,000.00 7,500.00
Harga pemakaian alat berat
A13 Wheel Loader 1 - 1,6 M3 0.020 jam 1,210,344.64 24,206.89
A09 Dump Truck 3 - 4 M3 0.331 jam 1,007,092.31 333,347.56
A12 Motor Grader > 100 Hp 0.007 jam 1,847,064.37 12,929.45
A14 Vibratory Roller 5 - 8 Ton 0.011 jam 686,805.15 7,554.86
A16 Water Tanker 3000 - 4500 L 0.008 jam 945,142.31 7,561.14
A38 Alat bantu 1.000 ls 5,000.00 5,000.00
JUMLAH : 755,099.89

III PEKERJAAN PONDASI


18 1 M3 Pasangan Pondasi Batu Belah, Campuran 1 PC : 3 PP 2,380,600.00
B110 Pasir Pasang 0.485 M3 360,000.00 174,600.00
B91 Batu Kali 1.200 M3 1,000,000.00 1,200,000.00
B01 Semen Portland 202.000 Kg 2,500.00 505,000.00
U01 Pekerja/Kenek 1.500 O/h 180,000.00 270,000.00
U05 Tukang Batu 0.750 O/h 250,000.00 187,500.00
U14 Kepala Tukang 0.075 O/h 280,000.00 21,000.00
U15 Mandor/Pengawas 0.075 O/h 300,000.00 22,500.00
JUMLAH : 2,380,600.00

19 1 M3 Pasangan Pondasi Batu Belah, Campuran 1 PC : 4 PP 2,295,700.00


B110 Pasir Pasang 0.520 M3 360,000.00 187,200.00
B91 Batu Kali 1.200 M3 1,000,000.00 1,200,000.00
B01 Semen Portland 163.000 Kg 2,500.00 407,500.00
U01 Pekerja/Kenek 1.500 O/h 180,000.00 270,000.00
U05 Tukang Batu 0.750 O/h 250,000.00 187,500.00
U14 Kepala Tukang 0.075 O/h 280,000.00 21,000.00
U15 Mandor/Pengawas 0.075 O/h 300,000.00 22,500.00
JUMLAH : 2,295,700.00

20 1 M3 Pasangan Pondasi Batu Belah, Campuran 1 PC : 5 PP 2,236,840.00


B110 Pasir Pasang 0.544 M3 360,000.00 195,840.00
B91 Batu Kali 1.200 M3 1,000,000.00 1,200,000.00
B01 Semen Portland 136.000 Kg 2,500.00 340,000.00
U01 Pekerja/Kenek 1.500 O/h 180,000.00 270,000.00
U05 Tukang Batu 0.750 O/h 250,000.00 187,500.00
U14 Kepala Tukang 0.075 O/h 280,000.00 21,000.00
733291305.xlsx ANALISA 5 /5
HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

U15 Mandor/Pengawas 0.075 O/h 300,000.00 22,500.00


JUMLAH : 2,236,840.00

21 1 M3 Pasangan Pondasi Batu Belah, Campuran 1 PC : 6 PP 2,195,460.00


B110 Pasir Pasang 0.561 M3 360,000.00 201,960.00
B91 Batu Kali 1.200 M3 1,000,000.00 1,200,000.00
B01 Semen Portland 117.000 Kg 2,500.00 292,500.00
U01 Pekerja/Kenek 1.500 O/h 180,000.00 270,000.00
U05 Tukang Batu 0.750 O/h 250,000.00 187,500.00
U14 Kepala Tukang 0.075 O/h 280,000.00 21,000.00
U15 Mandor/Pengawas 0.075 O/h 300,000.00 22,500.00
JUMLAH : 2,195,460.00

22 1 M3 Pasangan Pondasi Batu Belah, Campuran 1 PC : 8 PP 2,138,740.00


B110 Pasir Pasang 0.584 M3 360,000.00 210,240.00
B91 Batu Kali 1.200 M3 1,000,000.00 1,200,000.00
B01 Semen Portland 91.000 Kg 2,500.00 227,500.00
U01 Pekerja/Kenek 1.500 O/h 180,000.00 270,000.00
U05 Tukang Batu 0.750 O/h 250,000.00 187,500.00
U14 Kepala Tukang 0.075 O/h 280,000.00 21,000.00
U15 Mandor/Pengawas 0.075 O/h 300,000.00 22,500.00
JUMLAH : 2,138,740.00

23 1 M3 Pasangan Batu Kosong (Anstamping) 1,616,040.00


B110 Pasir Pasang 0.432 M3 360,000.00 155,520.00
B91 Batu Kali 1.200 M3 1,000,000.00 1,200,000.00
U01 Pekerja/Kenek 0.780 O/h 180,000.00 140,400.00
U05 Tukang Batu 0.390 O/h 250,000.00 97,500.00
U14 Kepala Tukang 0.039 O/h 280,000.00 10,920.00
U15 Mandor/Pengawas 0.039 O/h 300,000.00 11,700.00
JUMLAH : 1,616,040.00

24 1 M3 Pasangan Pondasi Siklop, 60% Beton Capuran 1 PC : 2 PB : 3 KR dan 40% Batu Belah 4,310,300.00
B91 Batu Kali 0.480 M3 1,000,000.00 480,000.00
B304 Besi beton 75.000 Kg 28,000.00 2,100,000.00
B01 Semen Portland 202.000 Kg 2,500.00 505,000.00
B111 Pasir Beton (m3) 0.320 M3 360,000.00 115,200.00
B95 Kerikil 0.490 M3 480,000.00 235,200.00
B05 Kawat beton 0.800 Kg 67,000.00 53,600.00
U01 Pekerja/Kenek 3.000 O/h 180,000.00 540,000.00
U05 Tukang Batu 0.850 O/h 250,000.00 212,500.00
U14 Kepala Tukang 0.085 O/h 280,000.00 23,800.00
U15 Mandor/Pengawas 0.150 O/h 300,000.00 45,000.00
JUMLAH : 4,310,300.00

8 1 M3 Pasangan Pondasi Sumuran Diameter 100 cm 2,169,400.00


B90 Batu belah 15/20 0.450 M3 1,000,000.00 450,000.00
B01 Semen Portland 280.000 Kg 2,500.00 700,000.00
B111 Pasir Beton (m3) 0.450 M3 360,000.00 162,000.00
B95 Kerikil 0.670 M3 480,000.00 321,600.00
U01 Pekerja/Kenek 2.380 O/h 180,000.00 428,400.00
U05 Tukang Batu 0.300 O/h 250,000.00 75,000.00
U14 Kepala Tukang 0.030 O/h 280,000.00 8,400.00
U15 Mandor/Pengawas 0.080 O/h 300,000.00 24,000.00
JUMLAH : 2,169,400.00

9 1 M' Pembuatan Tiang Pancang ( 40 x 40 ) Cm, Prestressed Beton 2,091,340.00


B113 Pasir Urug 0.019 M3 260,000.00 4,940.00
B111 Pasir Beton (m3) 0.094 M3 360,000.00 33,840.00

733291305.xlsx ANALISA 6 /6
HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

B95 Kerikil 0.150 M3 480,000.00 72,000.00


B01 Semen Portland 60.500 Kg 2,500.00 151,250.00
B304 Besi Beton 45.000 Kg 28,000.00 1,260,000.00
B05 Kawat Beton 0.900 Kg 67,000.00 60,300.00
B117 Kayu Kelas II Matoa ( Balok ) 0.032 M3 3,500,000.00 112,000.00
B32 Paku Biasa 0.120 Kg 30,000.00 3,600.00
B256 Minyak Bekesting 0.090 Liter 15,000.00 1,350.00
B347 Plamur tembok 0.240 Kg 45,000.00 10,800.00
U01 Pekerja/Kenek 1.000 O/h 180,000.00 180,000.00
U05 Tukang Batu 0.670 O/h 250,000.00 167,500.00
U14 Kepala Tukang 0.067 O/h 280,000.00 18,760.00
U15 Mandor/Pengawas 0.050 O/h 300,000.00 15,000.00
JUMLAH : 2,091,340.00

10 1 M' Pembuatan Tiang Pancang ( 35 x 35 ) Cm, Prestressed Beton 1,631,810.00


B113 Pasir Urug 0.016 M3 260,000.00 4,160.00
B111 Pasir Beton (m3) 0.080 M3 360,000.00 28,800.00
B95 Kerikil 0.125 M3 480,000.00 60,000.00
B01 Semen Portland 49.000 Kg 2,500.00 122,500.00
B304 Besi Beton 34.500 Kg 28,000.00 966,000.00
B05 Kawat Beton 0.700 Kg 67,000.00 46,900.00
B117 Kayu Kelas II Matoa ( Balok ) 0.027 M3 3,500,000.00 94,500.00
B32 Paku Biasa 0.120 Kg 30,000.00 3,600.00
B256 Minyak Bekesting 0.090 Liter 15,000.00 1,350.00
B347 Plamur tembok 0.200 Kg 45,000.00 9,000.00
U01 Pekerja/Kenek 0.800 O/h 180,000.00 144,000.00
U05 Tukang Batu 0.500 O/h 250,000.00 125,000.00
U14 Kepala Tukang 0.050 O/h 280,000.00 14,000.00
U15 Mandor/Pengawas 0.040 O/h 300,000.00 12,000.00
JUMLAH : 1,631,810.00

IV PEKERJAAN DINDING
25 1 M2 Pasangan Batu Tela, 1 PC : 1 PP 500,415.00
B125 Batu tela 25.000 Buah 5,500.00 137,500.00
B01 Semen Portland 64.030 Kg 2,500.00 160,075.00
B110 Pasir Pasang 0.059 M3 360,000.00 21,240.00
U01 Pekerja/Kenek 0.650 O/h 180,000.00 117,000.00
U05 Tukang Batu 0.200 O/h 250,000.00 50,000.00
U14 Kepala Tukang 0.020 O/h 280,000.00 5,600.00
U15 Mandor/Pengawas 0.030 O/h 300,000.00 9,000.00
JUMLAH : 500,415.00

26 1 M2 Pasangan Batu Tela, 1 PC : 2 PP 456,650.00


B125 Batu tela 25.000 Buah 5,500.00 137,500.00
B01 Semen Portland 43.500 Kg 2,500.00 108,750.00
B110 Pasir Pasang 0.080 M3 360,000.00 28,800.00
U01 Pekerja/Kenek 0.650 O/h 180,000.00 117,000.00
U05 Tukang Batu 0.200 O/h 250,000.00 50,000.00
U14 Kepala Tukang 0.020 O/h 280,000.00 5,600.00
U15 Mandor/Pengawas 0.030 O/h 300,000.00 9,000.00
JUMLAH : 456,650.00
1M3 4,566,500.00

27 1 M2 Pasangan Batu Tela, 1 PC : 3 PP 434,235.00


B125 Batu tela 25.000 Buah 5,500.00 137,500.00
B01 Semen Portland 32.950 Kg 2,500.00 82,375.00
B110 Pasir Pasang 0.091 M3 360,000.00 32,760.00
U01 Pekerja/Kenek 0.650 O/h 180,000.00 117,000.00
U05 Tukang Batu 0.200 O/h 250,000.00 50,000.00
733291305.xlsx ANALISA 7 /7
HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

U14 Kepala Tukang 0.020 O/h 280,000.00 5,600.00


U15 Mandor/Pengawas 0.030 O/h 300,000.00 9,000.00
JUMLAH : 434,235.00
1M3 4,342,350.00

28 1 M2 Pasangan Batu Tela, 1 PC : 4 PP 418,955.00


B125 Batu tela 25.000 Buah 5,500.00 137,500.00
B01 Semen Portland 26.550 Kg 2,500.00 66,375.00
B110 Pasir Pasang 0.093 M3 360,000.00 33,480.00
U01 Pekerja/Kenek 0.650 O/h 180,000.00 117,000.00
U05 Tukang Batu 0.200 O/h 250,000.00 50,000.00
U14 Kepala Tukang 0.020 O/h 280,000.00 5,600.00
U15 Mandor/Pengawas 0.030 O/h 300,000.00 9,000.00
JUMLAH : 418,955.00
1M3 4,189,550.00

29 1 M2 Pasangan Batu Tela, 1 PC : 5 PP 411,320.00


B125 Batu tela 25.000 Buah 5,500.00 137,500.00
B01 Semen Portland 22.200 Kg 2,500.00 55,500.00
B110 Pasir Pasang 0.102 M3 360,000.00 36,720.00
U01 Pekerja/Kenek 0.650 O/h 180,000.00 117,000.00
U05 Tukang Batu 0.200 O/h 250,000.00 50,000.00
U14 Kepala Tukang 0.020 O/h 280,000.00 5,600.00
U15 Mandor/Pengawas 0.030 O/h 300,000.00 9,000.00
JUMLAH : 411,320.00
1M3 4,113,200.00

25 1 M2 Pasangan Batu Batako Tebal 1 Batako, 1 PC : 1 PP 550,415.00


B127 Batu batako 10 x 18 x 24 cm 25.000 Buah 7,500.00 187,500.00
B01 Semen Portland 64.030 Kg 2,500.00 160,075.00
B110 Pasir Pasang 0.059 M3 360,000.00 21,240.00
U01 Pekerja/Kenek 0.650 O/h 180,000.00 117,000.00
U05 Tukang Batu 0.200 O/h 250,000.00 50,000.00
U14 Kepala Tukang 0.020 O/h 280,000.00 5,600.00
U15 Mandor/Pengawas 0.030 O/h 300,000.00 9,000.00
JUMLAH : 550,415.00
1M3 5,504,150.00

26 1 M2 Pasangan Batu Batako Tebal 1 Batako, 1 PC : 2 PP 506,650.00


B127 Batu batako 10 x 18 x 24 cm 25.000 Buah 7,500.00 187,500.00
B01 Semen Portland 43.500 Kg 2,500.00 108,750.00
B110 Pasir Pasang 0.080 M3 360,000.00 28,800.00
U01 Pekerja/Kenek 0.650 O/h 180,000.00 117,000.00
U05 Tukang Batu 0.200 O/h 250,000.00 50,000.00
U14 Kepala Tukang 0.020 O/h 280,000.00 5,600.00
U15 Mandor/Pengawas 0.030 O/h 300,000.00 9,000.00
JUMLAH : 506,650.00
1M3 5,066,500.00

27 1 M2 Pasangan Batu Batako Tebal 1 Batako, 1 PC : 3 PP 484,235.00


B127 Batu batako 10 x 18 x 24 cm 25.000 Buah 7,500.00 187,500.00
B01 Semen Portland 32.950 Kg 2,500.00 82,375.00
B110 Pasir Pasang 0.091 M3 360,000.00 32,760.00
U01 Pekerja/Kenek 0.650 O/h 180,000.00 117,000.00
U05 Tukang Batu 0.200 O/h 250,000.00 50,000.00
U14 Kepala Tukang 0.020 O/h 280,000.00 5,600.00
U15 Mandor/Pengawas 0.030 O/h 300,000.00 9,000.00
JUMLAH : 484,235.00
1M3 4,842,350.00

733291305.xlsx ANALISA 8 /8
HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

28 1 M2 Pasangan Batu Batako Tebal 1 Batako, 1 PC : 4 PP 468,955.00


B127 Batu batako 10 x 18 x 24 cm 25.000 Buah 7,500.00 187,500.00
B01 Semen Portland 26.550 Kg 2,500.00 66,375.00
B110 Pasir Pasang 0.093 M3 360,000.00 33,480.00
U01 Pekerja/Kenek 0.650 O/h 180,000.00 117,000.00
U05 Tukang Batu 0.200 O/h 250,000.00 50,000.00
U14 Kepala Tukang 0.020 O/h 280,000.00 5,600.00
U15 Mandor/Pengawas 0.030 O/h 300,000.00 9,000.00
JUMLAH : 468,955.00
1M3 4,689,550.00

29 1 M2 Pasangan Batu Batako Tebal 1 Batako, 1 PC : 5 PP 461,320.00


B127 Batu batako 10 x 18 x 24 cm 25.000 Buah 7,500.00 187,500.00
B01 Semen Portland 22.200 Kg 2,500.00 55,500.00
B110 Pasir Pasang 0.102 M3 360,000.00 36,720.00
U01 Pekerja/Kenek 0.650 O/h 180,000.00 117,000.00
U05 Tukang Batu 0.200 O/h 250,000.00 50,000.00
U14 Kepala Tukang 0.020 O/h 280,000.00 5,600.00
U15 Mandor/Pengawas 0.030 O/h 300,000.00 9,000.00
JUMLAH : 461,320.00
1M3 4,613,200.00

30 1 M2 Pasangan Dinding Roster/Terawang (10 X 20 X 20) cm, Campuran Spesi 1 PC : 3 PP 3,207,820.00


B139 Roster/terawang 25.000 Buah 123,000.00 3,075,000.00
B01 Semen Portland 14.000 Kg 2,500.00 35,000.00
B110 Pasir Pasang 0.032 M3 360,000.00 11,520.00
U01 Pekerja/Kenek 0.300 O/h 180,000.00 54,000.00
U05 Tukang Batu 0.100 O/h 250,000.00 25,000.00
U14 Kepala Tukang 0.010 O/h 280,000.00 2,800.00
U15 Mandor/Pengawas 0.015 O/h 300,000.00 4,500.00
JUMLAH : 3,207,820.00

31 1 M2 Pasangan Dinding Roster/Terawang (12 X 11 X 24) cm, Campuran Spesi 1 PC : 4 PP 3,816,400.00


B139 Roster/terawang 30.000 Buah 123,000.00 3,690,000.00
B01 Semen Portland 11.000 Kg 2,500.00 27,500.00
B110 Pasir Pasang 0.035 M3 360,000.00 12,600.00
U01 Pekerja/Kenek 0.300 O/h 180,000.00 54,000.00
U05 Tukang Batu 0.100 O/h 250,000.00 25,000.00
U14 Kepala Tukang 0.010 O/h 280,000.00 2,800.00
U15 Mandor/Pengawas 0.015 O/h 300,000.00 4,500.00
JUMLAH : 3,816,400.00

8 1 M2 Pasangan Dinding Bata Berongga Ekspose (5 X 11 X 24) cm, Campuran Spesi 1 PC : 3 PP 146,720.00
B138 Bata berongga ekspose 70.000 Buah -
B01 Semen Portland 14.000 Kg 2,500.00 35,000.00
B110 Pasir Pasang 0.032 M3 360,000.00 11,520.00
U01 Pekerja/Kenek 0.300 O/h 180,000.00 54,000.00
U05 Tukang Batu 0.150 O/h 250,000.00 37,500.00
U14 Kepala Tukang 0.015 O/h 280,000.00 4,200.00
U15 Mandor/Pengawas 0.015 O/h 300,000.00 4,500.00
JUMLAH : 146,720.00

8 1 M2 Pasangan Dinding Batu bata ringan (Hebel), 10x16x60 cm, Campuran Spesi 1 PC : 3 PP 172,233.00
B01 Semen Portland (ambil koefisien pas bata 1Pc : 3Ps) 14.370 Kg 2,500.00 35,925.00
B131 Batu bata ringan (Hebel), 10x16x60 cm 8.340 BH -
B110 Pasir Pasang (keofesien diragukan) 0.073 M3 360,000.00 26,208.00
U01 Pekerja/Kenek 0.350 O/h 180,000.00 63,000.00
U05 Tukang batu 0.150 O/h 250,000.00 37,500.00

733291305.xlsx ANALISA 9 /9
HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

U14 Kepala Tukang 0.015 O/h 280,000.00 4,200.00


U15 Mandor/Pengawas 0.018 O/h 300,000.00 5,400.00
JUMLAH : 172,233.00

V PEKERJAAN PLESTERAN
32 1 M2 Plesteran, 1 PC : 1 PP, tebal 15 mm 144,720.00
B01 Semen Portland 15.504 Kg 2,500.00 38,760.00
B110 Pasir Pasang 0.016 M3 360,000.00 5,760.00
U01 Pekerja/Kenek 0.300 O/h 180,000.00 54,000.00
U05 Tukang Batu 0.150 O/h 250,000.00 37,500.00
U14 Kepala Tukang 0.015 O/h 280,000.00 4,200.00
U15 Mandor/Pengawas 0.015 O/h 300,000.00 4,500.00
JUMLAH : 144,720.00

33 1 M2 Plesteran, 1 PC : 2 PP, tebal 15 mm 132,960.00


B01 Semen Portland 10.224 Kg 2,500.00 25,560.00
B110 Pasir Pasang 0.020 M3 360,000.00 7,200.00
U01 Pekerja/Kenek 0.300 O/h 180,000.00 54,000.00
U05 Tukang Batu 0.150 O/h 250,000.00 37,500.00
U14 Kepala Tukang 0.015 O/h 280,000.00 4,200.00
U15 Mandor/Pengawas 0.015 O/h 300,000.00 4,500.00
JUMLAH : 132,960.00

34 1 M2 Plesteran, 1 PC : 3 PP, tebal 15 mm 127,920.00


B01 Semen Portland 7.776 Kg 2,500.00 19,440.00
B110 Pasir Pasang 0.023 M3 360,000.00 8,280.00
U01 Pekerja/Kenek 0.300 O/h 180,000.00 54,000.00
U05 Tukang Batu 0.150 O/h 250,000.00 37,500.00
U14 Kepala Tukang 0.015 O/h 280,000.00 4,200.00
U15 Mandor/Pengawas 0.015 O/h 300,000.00 4,500.00
JUMLAH : 127,920.00

35 1 M2 Plesteran, 1 PC : 4 PP, tebal 15 mm 124,440.00


B01 Semen Portland 6.240 Kg 2,500.00 15,600.00
B110 Pasir Pasang 0.024 M3 360,000.00 8,640.00
U01 Pekerja/Kenek 0.300 O/h 180,000.00 54,000.00
U05 Tukang Batu 0.150 O/h 250,000.00 37,500.00
U14 Kepala Tukang 0.015 O/h 280,000.00 4,200.00
U15 Mandor/Pengawas 0.015 O/h 300,000.00 4,500.00
JUMLAH : 124,440.00

36 1 M2 Plesteran, 1 PC : 5 PP, tebal 15 mm 122,520.00


B01 Semen Portland 5.184 Kg 2,500.00 12,960.00
B110 Pasir Pasang 0.026 M3 360,000.00 9,360.00
U01 Pekerja/Kenek 0.300 O/h 180,000.00 54,000.00
U05 Tukang Batu 0.150 O/h 250,000.00 37,500.00
U14 Kepala Tukang 0.015 O/h 280,000.00 4,200.00
U15 Mandor/Pengawas 0.015 O/h 300,000.00 4,500.00
JUMLAH : 122,520.00

37 1 M2 Plesteran, 1 PC : 6 PP, tebal 15 mm 120,960.00


B01 Semen Portland 4.416 Kg 2,500.00 11,040.00
B110 Pasir Pasang 0.027 M3 360,000.00 9,720.00
U01 Pekerja/Kenek 0.300 O/h 180,000.00 54,000.00
U05 Tukang Batu 0.150 O/h 250,000.00 37,500.00
U14 Kepala Tukang 0.015 O/h 280,000.00 4,200.00
U15 Mandor/Pengawas 0.015 O/h 300,000.00 4,500.00
JUMLAH : 120,960.00

733291305.xlsx ANALISA 10 /10


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

38 1 M2 Plesteran Beton, 1 PC : 2 PP, tebal 15 mm 136,030.00


B01 Semen Portland 9.300 Kg 2,500.00 23,250.00
B110 Pasir Pasang 0.018 M3 360,000.00 6,480.00
U01 Pekerja/Kenek 0.260 O/h 180,000.00 46,800.00
U05 Tukang Batu 0.200 O/h 250,000.00 50,000.00
U14 Kepala Tukang 0.020 O/h 280,000.00 5,600.00
U15 Mandor/Pengawas 0.013 O/h 300,000.00 3,900.00
JUMLAH : 136,030.00

39 1 M2 Plesteran Beton, 1 PC : 3 PP, tebal 15 mm 131,535.00


B01 Semen Portland 7.070 Kg 2,500.00 17,675.00
B110 Pasir Pasang 0.021 M3 360,000.00 7,560.00
U01 Pekerja/Kenek 0.260 O/h 180,000.00 46,800.00
U05 Tukang Batu 0.200 O/h 250,000.00 50,000.00
U14 Kepala Tukang 0.020 O/h 280,000.00 5,600.00
U15 Mandor/Pengawas 0.013 O/h 300,000.00 3,900.00
JUMLAH : 131,535.00

40 1 M2 Plesteran Skoning, 1 PC : 2 PP, Lebar 10 mm 132,730.00


B01 Semen Portland 0.500 Kg 2,500.00 1,250.00
B110 Pasir Pasang 0.013 M3 360,000.00 4,680.00
U01 Pekerja/Kenek 0.080 O/h 180,000.00 14,400.00
U05 Tukang Batu 0.400 O/h 250,000.00 100,000.00
U14 Kepala Tukang 0.040 O/h 280,000.00 11,200.00
U15 Mandor/Pengawas 0.004 O/h 300,000.00 1,200.00
JUMLAH : 132,730.00

41 1 M2 Acian 74,925.00
B01 Semen Portland 3.250 Kg 2,500.00 8,125.00
U01 Pekerja/Kenek 0.200 O/h 180,000.00 36,000.00
U03 Tukang 0.100 O/h 250,000.00 25,000.00
U14 Kepala Tukang 0.010 O/h 280,000.00 2,800.00
U15 Mandor/Pengawas 0.010 O/h 300,000.00 3,000.00
JUMLAH : 74,925.00

VI PEKERJAAN KAYU
1 1 M3 Membuat dan Memasang Kusen Pintu dan Jendela Kayu Kelas I 12,703,000.00
B119 Kayu Kelas I (balok ) 1.100 M3 5,000,000.00 5,500,000.00
U01 Pekerja/Kenek 7.000 O/h 180,000.00 1,260,000.00
U04 Tukang Kayu 21.000 O/h 250,000.00 5,250,000.00
U14 Kepala Tukang 2.100 O/h 280,000.00 588,000.00
U15 Mandor/Pengawas 0.350 O/h 300,000.00 105,000.00
JUMLAH : 12,703,000.00

2 1 M3 Membuat dan Memasang Kusen Pintu dan Jendela Kayu Kelas II dan III 10,374,000.00
B115 Kayu kelas II (balok) 1.200 M3 3,500,000.00 4,200,000.00
U01 Pekerja/Kenek 6.000 O/h 180,000.00 1,080,000.00
U04 Tukang Kayu 18.000 O/h 250,000.00 4,500,000.00
U14 Kepala Tukang 1.800 O/h 280,000.00 504,000.00
U15 Mandor/Pengawas 0.300 O/h 300,000.00 90,000.00
JUMLAH : 10,374,000.00

3 1 M3 Membuat dan Memasang Pintu Klamp Standar, Kayu Kelas II 561,800.00


B118 Kayu kelas I (papan) 0.040 M3 5,000,000.00 200,000.00
B32 Paku biasa 0.050 Kg 30,000.00 1,500.00
U01 Pekerja/Kenek 0.350 O/h 180,000.00 63,000.00
U04 Tukang Kayu 1.050 O/h 250,000.00 262,500.00
U14 Kepala Tukang 0.105 O/h 280,000.00 29,400.00
U15 Mandor/Pengawas 0.018 O/h 300,000.00 5,400.00

733291305.xlsx ANALISA 11 /11


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

JUMLAH : 561,800.00

4 1 M2 Membuat dan Memasang Daun Pintu Panel Kayu Kelas I 1,229,000.00


B118 Kayu kelas I (papan) 0.040 M3 5,000,000.00 200,000.00
U01 Pekerja/Kenek 1.000 O/h 180,000.00 180,000.00
U04 Tukang Kayu 3.000 O/h 250,000.00 750,000.00
U14 Kepala Tukang 0.300 O/h 280,000.00 84,000.00
U15 Mandor/Pengawas 0.050 O/h 300,000.00 15,000.00
JUMLAH : 1,229,000.00

5 1 M2 Membuat dan Memasang Pintu dan Jendela Jalusi Kayu Kelas I 1,349,000.00
B118 Kayu kelas I (papan) 0.064 M3 5,000,000.00 320,000.00
U01 Pekerja/Kenek 1.000 O/h 180,000.00 180,000.00
U04 Tukang Kayu 3.000 O/h 250,000.00 750,000.00
U14 Kepala Tukang 0.300 O/h 280,000.00 84,000.00
U15 Mandor/Pengawas 0.050 O/h 300,000.00 15,000.00
JUMLAH : 1,349,000.00

6 1 M2 Membuat dan Memasang Daun Pintu dan Jendela Kaca Kayu Kelas I 1,223,200.00
B118 Kayu kelas I (papan) 0.026 M3 5,000,000.00 130,000.00
B354 Lem kayu 0.300 Kg -
B82 Kaca Polos 5 mm 1.000 M2 270,000.00 270,000.00
U01 Pekerja/Kenek 0.800 O/h 180,000.00 144,000.00
U04 Tukang Kayu 2.400 O/h 250,000.00 600,000.00
U14 Kepala Tukang 0.240 O/h 280,000.00 67,200.00
U15 Mandor/Pengawas 0.040 O/h 300,000.00 12,000.00
JUMLAH : 1,223,200.00

7 1 M2 Membuat Pintu Kayu Lapis (Plywood), Rangkap, Rangka Tertutup Kayu Kelas II (Lebar sampai 90cm) 814,950.00
B116 Kayu kelas II (papan) 0.025 M3 3,750,000.00 93,750.00
B32 Paku biasa 0.030 Kg 30,000.00 900.00
B354 Lem kayu 0.500 Kg -
B10 Plywood tebal 4 mm ( 90 x 220 ) cm 1.000 Lembar -
U01 Pekerja/Kenek 0.700 O/h 180,000.00 126,000.00
U04 Tukang Kayu 2.100 O/h 250,000.00 525,000.00
U14 Kepala Tukang 0.210 O/h 280,000.00 58,800.00
U15 Mandor/Pengawas 0.035 O/h 300,000.00 10,500.00
JUMLAH : 814,950.00

8 1 M2 Membuat Pintu Kayu Lapis (Plywood), Rangkap, Rangka Expose Kayu Kelas I dan II 920,100.00
B116 Kayu kelas II (papan) 0.026 M3 3,750,000.00 96,000.00
B32 Paku biasa 0.030 Kg 30,000.00 900.00
B354 Lem kayu 0.500 Kg -
B10 Plywood tebal 4 mm ( 90 x 220 ) cm 1.000 Lembar -
U01 Pekerja/Kenek 0.800 O/h 180,000.00 144,000.00
U04 Tukang Kayu 2.400 O/h 250,000.00 600,000.00
U14 Kepala Tukang 0.240 O/h 280,000.00 67,200.00
U15 Mandor/Pengawas 0.040 O/h 300,000.00 12,000.00
JUMLAH : 920,100.00

9 1 M2 Pasang Jalusi Kusen Kayu Kelas I 1,081,600.00


B118 Kayu kelas I (papan) 0.060 M3 5,000,000.00 300,000.00
B32 Paku biasa 0.150 Kg 30,000.00 4,500.00
U01 Pekerja/Kenek 0.670 O/h 180,000.00 120,600.00
U04 Tukang Kayu 2.000 O/h 250,000.00 500,000.00
U14 Kepala Tukang 0.200 O/h 280,000.00 56,000.00
U15 Mandor/Pengawas 0.335 O/h 300,000.00 100,500.00
JUMLAH : 1,081,600.00

733291305.xlsx ANALISA 12 /12


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

10 1 M2 Pasang Teakwood Rangkap, Rangka Expose Kayu Kelas I 949,100.00


B118 Kayu kelas I (papan) 0.025 M3 5,000,000.00 125,000.00
B32 Paku biasa 0.030 Kg 30,000.00 900.00
B354 Lem kayu 0.300 Kg -
B18 Teakwood tebal 4 mm ( 90 x 220 ) cm 1.000 Lembar -
U01 Pekerja/Kenek 0.800 O/h 180,000.00 144,000.00
U04 Tukang Kayu 2.400 O/h 250,000.00 600,000.00
U14 Kepala Tukang 0.240 O/h 280,000.00 67,200.00
U15 Mandor/Pengawas 0.040 O/h 300,000.00 12,000.00
JUMLAH : 949,100.00

11 1 M2 Pasang Teakwood Rangkap Lapis Formika, Rangka Expose Kayu Kelas II 969,450.00
B116 Kayu kelas II (papan) 0.025 M3 3,750,000.00 93,750.00
B32 Paku biasa 0.030 Kg 30,000.00 900.00
B354 Lem kayu 0.800 Kg -
B18 Teakwood tebal 4 mm ( 90 x 220 ) cm 1.000 Lembar -
B21 Formika 0.500 Lembar -
U01 Pekerja/Kenek 0.850 O/h 180,000.00 153,000.00
U04 Tukang Kayu 2.550 O/h 250,000.00 637,500.00
U14 Kepala Tukang 0.255 O/h 280,000.00 71,400.00
U15 Mandor/Pengawas 0.043 O/h 300,000.00 12,900.00
JUMLAH : 969,450.00

12 1 M2 Pasang Kaca Tebal 6 Mm


B79 Kaca Polos 1.100 M2 350,000.00 385,000.00
U01 Pekerja/Kenek 0.043 O/h 180,000.00 7,740.00
U03 Tukang 0.043 O/h 250,000.00 10,750.00
U14 Kepala Tukang 0.004 O/h 280,000.00 1,204.00
U15 Mandor/Pengawas 0.002 O/h 300,000.00 630.00
JUMLAH : 405,324.00

13 1 M3 Pasang Konstruksi Kuda-Kuda Konvensional, Kayu Kelas II 9,559,000.00


B115 Kayu kelas II (balok) 1.100 M3 3,500,000.00 3,850,000.00
B48 Besi strip tebal 5 mm 15.000 Kg 95,000.00 1,425,000.00
B32 Paku biasa 5.600 Kg 30,000.00 168,000.00
U01 Pekerja/Kenek 4.000 O/h 180,000.00 720,000.00
U04 Tukang Kayu 12.000 O/h 250,000.00 3,000,000.00
U14 Kepala Tukang 1.200 O/h 280,000.00 336,000.00
U15 Mandor/Pengawas 0.200 O/h 300,000.00 60,000.00
JUMLAH : 9,559,000.00

14 1 M3 Pasang Konstruksi Kuda-Kuda Expose, Kayu Kelas I 14,487,300.00


B119 Kayu Kelas I (balok ) 1.200 M3 5,000,000.00 6,000,000.00
B48 Besi strip tebal 5 mm 15.000 Kg 95,000.00 1,425,000.00
B32 Paku biasa 5.600 Kg 30,000.00 168,000.00
U01 Pekerja/Kenek 6.700 O/h 180,000.00 1,206,000.00
U04 Tukang Kayu 20.100 O/h 250,000.00 5,025,000.00
U14 Kepala Tukang 2.010 O/h 280,000.00 562,800.00
U15 Mandor/Pengawas 0.335 O/h 300,000.00 100,500.00
JUMLAH : 14,487,300.00

15 1 M3 Pasang Konstruksi Gordeng, Kayu Kelas II 7,834,600.00


B115 Kayu kelas II (balok) 1.100 M3 3,500,000.00 3,850,000.00
B48 Besi strip tebal 5 mm 15.000 Kg 95,000.00 1,425,000.00
B32 Paku biasa 3.000 Kg 30,000.00 90,000.00
U01 Pekerja/Kenek 2.400 O/h 180,000.00 432,000.00
U04 Tukang Kayu 7.200 O/h 250,000.00 1,800,000.00
U14 Kepala Tukang 0.720 O/h 280,000.00 201,600.00
U15 Mandor/Pengawas 0.120 O/h 300,000.00 36,000.00
733291305.xlsx ANALISA 13 /13
HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

JUMLAH : 7,834,600.00

16 1 M2 Pasang Rangka Atap Genteng Keramik, Kayu Kelas II 103,800.00


B115 Kayu kelas II (balok) 0.014 M3 3,500,000.00 49,000.00
B122 Reng ( 2 x 3 ) cm 0.004 M3 -
B32 Paku biasa 0.250 Kg 30,000.00 7,500.00
U01 Pekerja/Kenek 0.100 O/h 180,000.00 18,000.00
U04 Tukang Kayu 0.100 O/h 250,000.00 25,000.00
U14 Kepala Tukang 0.010 O/h 280,000.00 2,800.00
U15 Mandor/Pengawas 0.005 O/h 300,000.00 1,500.00
JUMLAH : 103,800.00

17 1 M2 Pasang Rangka Atap Genteng Beton, Kayu Kelas II 103,800.00


B115 Kayu kelas II (balok) 0.014 M3 3,500,000.00 49,000.00
B122 Reng ( 2 x 3 ) cm 0.007 M3 -
B32 Paku biasa 0.250 Kg 30,000.00 7,500.00
U01 Pekerja/Kenek 0.100 O/h 180,000.00 18,000.00
U04 Tukang Kayu 0.100 O/h 250,000.00 25,000.00
U14 Kepala Tukang 0.010 O/h 280,000.00 2,800.00
U15 Mandor/Pengawas 0.005 O/h 300,000.00 1,500.00
JUMLAH : 103,800.00

18 1 M2 Pasang Rangka Atap Sirap, Kayu Kelas II 640,260.00


B115 Kayu kelas II (balok) 0.165 M3 3,500,000.00 577,500.00
B32 Paku biasa 0.200 Kg 30,000.00 6,000.00
U01 Pekerja/Kenek 0.120 O/h 180,000.00 21,600.00
U04 Tukang Kayu 0.120 O/h 250,000.00 30,000.00
U14 Kepala Tukang 0.012 O/h 280,000.00 3,360.00
U15 Mandor/Pengawas 0.006 O/h 300,000.00 1,800.00
JUMLAH : 640,260.00

21 1 M' Pasang Lisplank Ukuran (3 X 20) cm, Kayu Kelas I atau II 132,100.00
B118 Kayu kelas I (papan) 0.011 M3 5,000,000.00 54,000.00
B32 Paku biasa 0.100 Kg 30,000.00 3,000.00
U01 Pekerja/Kenek 0.100 O/h 180,000.00 18,000.00
U04 Tukang Kayu 0.200 O/h 250,000.00 50,000.00
U14 Kepala Tukang 0.020 O/h 280,000.00 5,600.00
U15 Mandor/Pengawas 0.005 O/h 300,000.00 1,500.00
JUMLAH : 132,100.00

23 1 M' Pasang Lisplank Ukuran (3 X 30) cm, Kayu Kelas I atau II 130,600.00
B118 Kayu kelas I (papan) 0.011 M3 5,000,000.00 54,000.00
B32 Paku biasa 0.050 Kg 30,000.00 1,500.00
U01 Pekerja/Kenek 0.100 O/h 180,000.00 18,000.00
U04 Tukang Kayu 0.200 O/h 250,000.00 50,000.00
U14 Kepala Tukang 0.020 O/h 280,000.00 5,600.00
U15 Mandor/Pengawas 0.005 O/h 300,000.00 1,500.00
JUMLAH : 130,600.00

45 1 M' Papan Listplank Kayu Besi 3/30 131,600.00


B118 Kayu kelas I (papan) 0.011 M3 5,000,000.00 55,000.00
B32 Paku Biasa 0.050 Kg 30,000.00 1,500.00
U01 Pekerja/Kenek 0.100 O/h 180,000.00 18,000.00
U03 Tukang 0.200 O/h 250,000.00 50,000.00
U14 Kepala Tukang 0.020 O/h 280,000.00 5,600.00
U15 Mandor/Pengawas 0.005 O/h 300,000.00 1,500.00
131,600.00

24 1 M2 Pasang Rangka Dinding Pemisah (60 X 120) cm , Kayu Kelas II atau III 257,000.00

733291305.xlsx ANALISA 14 /14


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

B115 Kayu kelas II (balok) 0.028 M3 3,500,000.00 98,000.00


B32 Paku biasa 0.150 Kg 30,000.00 4,500.00
U01 Pekerja/Kenek 0.150 O/h 180,000.00 27,000.00
U04 Tukang Kayu 0.450 O/h 250,000.00 112,500.00
U14 Kepala Tukang 0.045 O/h 280,000.00 12,600.00
U15 Mandor/Pengawas 0.008 O/h 300,000.00 2,400.00
JUMLAH : 257,000.00

25 1 M2 Pasang Dinding Pemisah Teakwood Rangkap, Rangka Kayu Kelas II 257,000.00


B115 Kayu kelas II (balok) 0.028 M3 3,500,000.00 98,000.00
B32 Paku biasa 0.150 Kg 30,000.00 4,500.00
B19 Teakwood tebal 4 mm ( 120 x 240 ) cm 0.860 Lembar -
B354 Lem kayu 0.560 Kg -
U01 Pekerja/Kenek 0.150 O/h 180,000.00 27,000.00
U04 Tukang Kayu 0.450 O/h 250,000.00 112,500.00
U14 Kepala Tukang 0.045 O/h 280,000.00 12,600.00
U15 Mandor/Pengawas 0.008 O/h 300,000.00 2,400.00
JUMLAH : 257,000.00

26 1 M2 Pasang Dinding Pemisah Plywood Rangkap, Rangka Kayu Kelas II 308,300.00


B115 Kayu kelas II (balok) 0.028 M3 3,500,000.00 98,000.00
B32 Paku biasa 0.150 Kg 30,000.00 4,500.00
B11 Plywood tebal 4 mm ( 120 x 240 ) cm 0.860 Lembar -
B354 Lem kayu 0.560 Kg -
U01 Pekerja/Kenek 0.200 O/h 180,000.00 36,000.00
U04 Tukang Kayu 0.600 O/h 250,000.00 150,000.00
U14 Kepala Tukang 0.060 O/h 280,000.00 16,800.00
U15 Mandor/Pengawas 0.010 O/h 300,000.00 3,000.00
JUMLAH : 308,300.00

27 1 M2 Pasang Dinding Lambriziring dari Papan Kayu Kelas I 694,400.00


B118 Kayu kelas I (papan) 0.007 M3 5,000,000.00 35,000.00
B32 Paku biasa 0.100 Kg 30,000.00 3,000.00
B37 Paku sekrup 0.150 Kg 260,000.00 39,000.00
U01 Pekerja/Kenek 0.600 O/h 180,000.00 108,000.00
U04 Tukang Kayu 1.800 O/h 250,000.00 450,000.00
U14 Kepala Tukang 0.180 O/h 280,000.00 50,400.00
U15 Mandor/Pengawas 0.030 O/h 300,000.00 9,000.00
JUMLAH : 694,400.00

28 1 M2 Pasang Dinding Partisi Dari Plywood ( 120 X 240 ) Cm 27,290.00


B11 Plywood tebal 4 mm ( 120 x 240 ) cm 0.400 Lembar -
B32 Paku biasa 0.050 Kg 30,000.00 1,500.00
U01 Pekerja/Kenek 0.025 O/h 180,000.00 4,500.00
U04 Tukang Kayu 0.075 O/h 250,000.00 18,750.00
U14 Kepala Tukang 0.008 O/h 280,000.00 2,240.00
U15 Mandor/Pengawas 0.001 O/h 300,000.00 300.00
JUMLAH : 27,290.00

29 1 M2 Pasang Dinding Bilik, Rangka Kayu Kelas II 82,760.00


B124 Bilik bambu 1.500 M2 -
B115 Kayu kelas II (balok) 0.014 M3 3,500,000.00 49,000.00
B32 Paku biasa 0.012 Kg 30,000.00 360.00
B121 Kayu profil 0.003 m -
U01 Pekerja/Kenek 0.100 O/h 180,000.00 18,000.00
U04 Tukang Kayu 0.050 O/h 250,000.00 12,500.00
U14 Kepala Tukang 0.005 O/h 280,000.00 1,400.00
U15 Mandor/Pengawas 0.005 O/h 300,000.00 1,500.00
JUMLAH : 82,760.00

733291305.xlsx ANALISA 15 /15


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

14 1 M2 Pekerjaan Rangka Dinding Pemisah / Partisi (60 X 120) Cm Kayu Besi 299,000.00
B119 Kayu Kelas I (balok ) 0.028 M3 5,000,000.00 140,000.00
B31 Paku campur 0.150 Kg 30,000.00 4,500.00
U01 Pekerja/Kenek 0.150 o/h 180,000.00 27,000.00
U03 Tukang 0.450 o/h 250,000.00 112,500.00
U14 Kepala Tukang 0.045 o/h 280,000.00 12,600.00
U15 Mandor/Pengawas 0.008 o/h 300,000.00 2,400.00
JUMLAH : 299,000.00

15 1 M2 Pekerjaan Dinding Gypsum Board 9 Mm/Satu Sisi " 102,566.67


B22 Gypsum Board 9 mm 0.347 Lbr 120,000.00 41,666.67
B30 Sekrup Gypsum 0.110 Doz 250,000.00 27,500.00
U01 Pekerja/Kenek 0.100 o/h 180,000.00 18,000.00
U03 Tukang 0.050 o/h 250,000.00 12,500.00
U14 Kepala Tukang 0.005 o/h 280,000.00 1,400.00
U15 Mandor/Pengawas 0.005 o/h 300,000.00 1,500.00
JUMLAH : Untuk 1 sisi 102,566.67
Untuk 2 sisi 205,133.33

1 M3 Balok Lantai Dan Skor Kayu Kelas I 11,790,000.00


B119 Kayu Kelas I (balok ) 1.100 M3 5,000,000.00 5,500,000.00
B32 Paku biasa 2.000 Kg 30,000.00 60,000.00
U01 Pekerja/Kenek 6.000 o/h 180,000.00 1,080,000.00
U03 Tukang 18.000 o/h 250,000.00 4,500,000.00
U14 Kepala Tukang 2.000 o/h 280,000.00 560,000.00
U15 Mandor/Pengawas 0.300 o/h 300,000.00 90,000.00

1 m3 gelagar kayu kelas I (BOW) #VALUE!


B119 Kayu Kelas I (balok ) 1,1000 M3 5,000,000.00 #VALUE!
B381 Baut 5/8" panjang 30 cm 52,0000 Bh 15,000.00 #VALUE!
U01 Pekerja/Kenek 5,0000 o/h 180,000.00 #VALUE!
U03 Tukang 15,0000 o/h 250,000.00 #VALUE!
U14 Kepala Tukang 1,5000 o/h 280,000.00 #VALUE!
U15 Mandor/Pengawas 0,2500 o/h 300,000.00 #VALUE!

1 M2 Lantai Papan Kayu Klas I 245,120.00


B118 Kayu Kelas I (Papan) 0.033 M3 5,000,000.00 162,500.00
B31 Paku campur 0.010 Kg 30,000.00 300.00
U01 Pekerja/Kenek 0.080 o/h 180,000.00 14,400.00
U03 Tukang 0.240 o/h 250,000.00 60,000.00
U14 Kepala Tukang 0.024 o/h 280,000.00 6,720.00
U15 Mandor/Pengawas 0.004 o/h 300,000.00 1,200.00

1 m2 lantai papan kayu kelas I diketam (BOW) #VALUE!


B118 Kayu Kelas I (Papan) 0,0254 M3 5,000,000.00 #VALUE!
B31 Paku campur 0,2500 Kg 30,000.00 #VALUE!
U01 Pekerja/Kenek 0,2800 o/h 180,000.00 #VALUE!
U03 Tukang 0,8000 o/h 250,000.00 #VALUE!
U14 Kepala Tukang 0,0800 o/h 280,000.00 #VALUE!
U15 Mandor/Pengawas 0,0140 o/h 300,000.00 #VALUE!

733291305.xlsx ANALISA 16 /16


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

1 M' Pemancangan Cerocok Kayu 221,762.50


B380 Kayu Cerocok 0.033 m 15,000.00 487.50
U01 Pekerja/Kenek 0.900 o/h 180,000.00 162,000.00
U03 Tukang 0.040 o/h 250,000.00 10,000.00
U14 Kepala Tukang 0.120 o/h 280,000.00 33,600.00
U15 Mandor/Pengawas 0.052 o/h 300,000.00 15,675.00

1 M2 Dinding papan dilidah/alur 357,250.00


B116 Kayu Kelas II (Papan) 0.020 M3 3,750,000.00 74,250.00
B32 Paku biasa 0.200 Kg 30,000.00 6,000.00
U01 Pekerja/Kenek 0.280 o/h 180,000.00 50,400.00
U03 Tukang 0.800 o/h 250,000.00 200,000.00
U14 Kepala Tukang 0.080 o/h 280,000.00 22,400.00
U15 Mandor/Pengawas 0.014 o/h 300,000.00 4,200.00

1 M2 Dinding papan susun sirih 328,000.00


B116 Kayu Kelas II (Papan) 0.012 M3 3,750,000.00 45,000.00
B32 Paku biasa 0.200 Kg 30,000.00 6,000.00
U01 Pekerja/Kenek 0.280 o/h 180,000.00 50,400.00
U03 Tukang 0.800 o/h 250,000.00 200,000.00
U14 Kepala Tukang 0.080 o/h 280,000.00 22,400.00
U15 Mandor/Pengawas 0.014 o/h 300,000.00 4,200.00

1 M2 Dinding triplek 4 mm rangka kayu Kls II #N/A


B115 Kayu Kelas II (balok) 0.015 M3 3,500,000.00 52,500.00
Triplek 4 mm 0.400 Lbr #N/A #N/A
B32 Paku biasa 0.150 Kg 30,000.00 4,500.00
U01 Pekerja/Kenek 0.140 o/h 180,000.00 25,200.00
U03 Tukang 0.400 o/h 250,000.00 100,000.00
U14 Kepala Tukang 0.040 o/h 280,000.00 11,200.00
U15 Mandor/Pengawas 0.070 o/h 300,000.00 21,000.00

1 M2 Dinding double triplek 4 mm kayu Kls II #N/A


B115 Kayu Kelas II (balok) 0.015 M3 3,500,000.00 52,500.00
Triplek 4 mm 0.800 Lbr #N/A #N/A
B32 Paku biasa 0.200 Kg 30,000.00 6,000.00
U01 Pekerja/Kenek 0.140 o/h 180,000.00 25,200.00
U03 Tukang 0.400 o/h 250,000.00 100,000.00
U14 Kepala Tukang 0.040 o/h 280,000.00 11,200.00
U15 Mandor/Pengawas 0.070 o/h 300,000.00 21,000.00

1 M2 Dinding double triplek Sungkai rangka kayu Kls II #N/A


B115 Kayu Kelas II (balok) 0.015 M3 3,500,000.00 52,500.00
Triplek Sungkai 0.800 Lbr #N/A #N/A
B32 Paku biasa 0.250 Kg 30,000.00 7,500.00
U01 Pekerja/Kenek 0.140 o/h 180,000.00 25,200.00
U03 Tukang 0.400 o/h 250,000.00 100,000.00
U14 Kepala Tukang 0.040 o/h 280,000.00 11,200.00
U15 Mandor/Pengawas 0.070 o/h 300,000.00 21,000.00

1 Ptg Mencincin/melancip tiang pancang/potong 150,200.00


U01 Pekerja/Kenek 0.200 o/h 180,000.00 36,000.00
U03 Tukang 0.400 o/h 250,000.00 100,000.00

733291305.xlsx ANALISA 17 /17


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

U14 Kepala Tukang 0.040 o/h 280,000.00 11,200.00


U15 Mandor/Pengawas 0.010 o/h 300,000.00 3,000.00

1 M Memancang tiang ke dalam tanah lunak/M 348,675,000.00


B119 Kayu Kelas I (balok ) 0.011 M3 5,000,000.00 55,000.00
U01 Pekerja/Kenek 1,800 o/h 180,000.00 324,000,000.00
U03 Tukang 0,040 o/h 250,000.00 10,000,000.00
U14 Kepala Tukang 0,004 o/h 280,000.00 1,120,000.00
U15 Mandor/Pengawas 0,045 o/h 300,000.00 13,500,000.00

1 Ps Membuat pen dan lobang pada tiang balok pemikul/ 186,000,000.00


U01 Pekerja/Kenek o/h 180,000.00 -
U03 Tukang o/h 250,000.00 -
U14 Kepala Tukang 0,600 o/h 280,000.00 168,000,000.00
U15 Mandor/Pengawas 0,060 o/h 300,000.00 18,000,000.00

1 M Membuat alur dan lidah pada papan bendung 225,300,000.00


U01 Pekerja/Kenek 0,300 o/h 180,000.00 54,000,000.00
U03 Tukang 0,600 o/h 250,000.00 150,000,000.00
U14 Kepala Tukang 0,060 o/h 280,000.00 16,800,000.00
U15 Mandor/Pengawas 0,015 o/h 300,000.00 4,500,000.00

1 M Memancang papan bendung ke dalam tanah lunak 209,781,250.00


B116 Kayu Kelas II (papan) 0.011 M3 3,750,000.00 41,250.00
U01 Pekerja/Kenek 1,000 o/h 180,000.00 180,000,000.00
U03 Tukang 0,080 o/h 250,000.00 20,000,000.00
U14 Kepala Tukang 0,008 o/h 280,000.00 2,240,000.00
U15 Mandor/Pengawas 0,025 o/h 300,000.00 7,500,000.00

1 M Memaku/meratakan kepala papan bendung 62,000,000.00


U01 Pekerja/Kenek o/h 180,000.00 -
U03 Tukang o/h 250,000.00 -
U14 Kepala Tukang 0,200 o/h 280,000.00 56,000,000.00
U15 Mandor/Pengawas 0,020 o/h 300,000.00 6,000,000.00

1 M3 Memasang leger/balok tumbuk #VALUE!


B119 Kayu Kelas I (balok ) 1.100 M3 5,000,000.00 5,500,000.00
B32 Paku biasa 3.000 Kg 30,000.00 90,000.00
U01 Pekerja/Kenek 5,000 o/h 180,000.00 900,000,000.00
U03 Tukang 15,00 o/h 250,000.00 #VALUE!
U14 Kepala Tukang 1,500 o/h 280,000.00 420,000,000.00
U15 Mandor/Pengawas 0,250 o/h 300,000.00 75,000,000.00

1 M3 Pasangan Rangka Bawah Kayu Besi #VALUE!


B119 Kayu Kelas I (balok ) 1.100 M3 5,000,000.00 5,500,000.00
B32 Paku biasa 3.000 Kg 30,000.00 90,000.00
U01 Pekerja/Kenek 5,000 o/h 180,000.00 900,000,000.00
U03 Tukang 13,00 o/h 250,000.00 #VALUE!
U14 Kepala Tukang 1,300 o/h 280,000.00 364,000,000.00
U15 Mandor/Pengawas 0,250 o/h 300,000.00 75,000,000.00

1 M3 Membuat kayu sandaran jembatan #VALUE!

733291305.xlsx ANALISA 18 /18


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

B119 Kayu Kelas I (balok ) 1.100 M3 5,000,000.00 5,500,000.00


B32 Paku biasa 3.000 Kg 30,000.00 90,000.00
U01 Pekerja/Kenek 8,000 o/h 180,000.00 1,440,000,000.00
U03 Tukang 24,00 o/h 250,000.00 #VALUE!
U14 Kepala Tukang 2,400 o/h 280,000.00 672,000,000.00
U15 Mandor/Pengawas 0,400 o/h 300,000.00 120,000,000.00

1 M3 Pasangan Rangka Atas Kayu besi #VALUE!


B119 Kayu Kelas I (balok ) 1.100 M3 5,000,000.00 5,500,000.00
B32 Paku biasa 3.000 Kg 30,000.00 90,000.00
U01 Pekerja/Kenek 12,00 o/h 180,000.00 #VALUE!
U03 Tukang 36,00 o/h 250,000.00 #VALUE!
U14 Kepala Tukang 3,600 o/h 280,000.00 1,008,000,000.00
U15 Mandor/Pengawas 0,600 o/h 300,000.00 180,000,000.00

1 M2 Memasang papan lantai tebal 2 s/d 8 cm 178,267,000.00


B118 Kayu Kelas I (papan) 0.053 M3 5,000,000.00 262,500.00
B32 Paku biasa 0.150 Kg 30,000.00 4,500.00
U01 Pekerja/Kenek 0,200 o/h 180,000.00 36,000,000.00
U03 Tukang 0,500 o/h 250,000.00 125,000,000.00
U14 Kepala Tukang 0,050 o/h 280,000.00 14,000,000.00
U15 Mandor/Pengawas 0,010 o/h 300,000.00 3,000,000.00

VII PEKERJAAN BETON


42 1 M3 Membuat Beton Tumbuk, 1 PC : 3 PS : 5 KR 1,540,300.00
B01 Semen Portland 218.000 Kg 2,500.00 545,000.00
B111 Pasir Beton (m3) 0.520 M3 360,000.00 187,200.00
B97 Koral beton (M3) 0.870 M3 480,000.00 417,600.00
U01 Pekerja/Kenek 1.650 O/h 180,000.00 297,000.00
U05 Tukang batu 0.250 O/h 250,000.00 62,500.00
U14 Kepala Tukang 0.025 O/h 280,000.00 7,000.00
U15 Mandor/Pengawas 0.080 O/h 300,000.00 24,000.00
JUMLAH : 1,540,300.00

43 1 M3 Membuat Beton Tumbuk, 1 PC : 3 PS : 6 KR 1,503,400.00


B01 Semen Portland 197.000 Kg 2,500.00 492,500.00
B111 Pasir Beton (m3) 0.470 M3 360,000.00 169,200.00
B97 Koral beton (M3) 0.940 M3 480,000.00 451,200.00
U01 Pekerja/Kenek 1.650 O/h 180,000.00 297,000.00
U05 Tukang batu 0.250 O/h 250,000.00 62,500.00
U14 Kepala Tukang 0.025 O/h 280,000.00 7,000.00
U15 Mandor/Pengawas 0.080 O/h 300,000.00 24,000.00
JUMLAH : 1,503,400.00

44 1 M3 Membuat Beton Tumbuk, 1 PC : 4 PS : 6 KR 1,445,800.00


B01 Semen Portland 173.000 Kg 2,500.00 432,500.00
B111 Pasir Beton (m3) 0.570 M3 360,000.00 205,200.00
B97 Koral beton (M3) 0.870 M3 480,000.00 417,600.00
U01 Pekerja/Kenek 1.650 O/h 180,000.00 297,000.00
U05 Tukang batu 0.250 O/h 250,000.00 62,500.00
U14 Kepala Tukang 0.025 O/h 280,000.00 7,000.00
U15 Mandor/Pengawas 0.080 O/h 300,000.00 24,000.00
JUMLAH : 1,445,800.00

45 1 M2 Membuat Lantai Kerja Beton mutu fc = 7,4 Mpa (K 100), slump (3 - 6) cm, w/c = 0,87 345,080.00

733291305.xlsx ANALISA 19 /19


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

B01 Semen Portland 10.000 Kg 2,500.00 25,000.00


B111 Pasir Beton (m3) 0.026 M3 360,000.00 9,360.00
B97 Koral beton (M3) 0.044 M3 480,000.00 21,120.00
U01 Pekerja/Kenek 1.200 O/h 180,000.00 216,000.00
U05 Tukang batu 0.200 O/h 250,000.00 50,000.00
U14 Kepala Tukang 0.020 O/h 280,000.00 5,600.00
U15 Mandor/Pengawas 0.060 O/h 300,000.00 18,000.00
JUMLAH : 345,080.00

46 1 M3 Membuat Beton Bertulang, 1 PC : 2 PS : 3 KR 1,540,090.00


B01 Semen Portland 232.000 Kg 2,500.00 580,000.00
B111 Pasir Beton (m3) 0.520 M3 360,000.00 187,200.00
B97 Koral beton (M3) 0.780 M3 480,000.00 374,400.00
U01 Pekerja/Kenek 1.650 O/h 180,000.00 297,000.00
U05 Tukang batu 0.275 O/h 250,000.00 68,750.00
U14 Kepala Tukang 0.028 O/h 280,000.00 7,840.00
U15 Mandor/Pengawas 0.083 O/h 300,000.00 24,900.00
JUMLAH : 1,540,090.00

47 1 M3 Membuat Beton Bertulang, 1 PC : 2 PS : 4 KR 1,692,490.00


B01 Semen Portland 280.000 Kg 2,500.00 700,000.00
B111 Pasir Beton (m3) 0.450 M3 360,000.00 162,000.00
B97 Koral beton (M3) 0.900 M3 480,000.00 432,000.00
U01 Pekerja/Kenek 1.650 O/h 180,000.00 297,000.00
U05 Tukang batu 0.275 O/h 250,000.00 68,750.00
U14 Kepala Tukang 0.028 O/h 280,000.00 7,840.00
U15 Mandor/Pengawas 0.083 O/h 300,000.00 24,900.00
JUMLAH : 1,692,490.00

48 1 M3 Membuat Beton Bertulang, 1 PC : 2 PS : 2,5 KR 1,816,090.00


B01 Semen Portland 352.000 Kg 2,500.00 880,000.00
B111 Pasir Beton (m3) 0.560 M3 360,000.00 201,600.00
B97 Koral beton (M3) 0.700 M3 480,000.00 336,000.00
U01 Pekerja/Kenek 1.650 O/h 180,000.00 297,000.00
U05 Tukang batu 0.275 O/h 250,000.00 68,750.00
U14 Kepala Tukang 0.028 O/h 280,000.00 7,840.00
U15 Mandor/Pengawas 0.083 O/h 300,000.00 24,900.00
JUMLAH : 1,816,090.00

49 1 M3 Membuat Beton Bertulang, 1 PC : 1,5 PS : 3 KR 1,701,390.00


B01 Semen Portland 357.000 Kg 2,500.00 892,500.00
B111 Pasir Beton (m3) 0.420 M3 360,000.00 151,200.00
B97 Koral beton (M3) 0.540 M3 480,000.00 259,200.00
U01 Pekerja/Kenek 1.650 O/h 180,000.00 297,000.00
U05 Tukang batu 0.275 O/h 250,000.00 68,750.00
U14 Kepala Tukang 0.028 O/h 280,000.00 7,840.00
U15 Mandor/Pengawas 0.083 O/h 300,000.00 24,900.00
JUMLAH : 1,701,390.00

50 1 M3 Membuat Beton Bertulang, 1 PC : 1,5 PS : 2,5 KR 1,907,090.00


B01 Semen Portland 386.000 Kg 2,500.00 965,000.00
B111 Pasir Beton (m3) 0.470 M3 360,000.00 169,200.00
B97 Koral beton (M3) 0.780 M3 480,000.00 374,400.00
U01 Pekerja/Kenek 1.650 O/h 180,000.00 297,000.00
U05 Tukang batu 0.275 O/h 250,000.00 68,750.00
U14 Kepala Tukang 0.028 O/h 280,000.00 7,840.00
U15 Mandor/Pengawas 0.083 O/h 300,000.00 24,900.00
JUMLAH : 1,907,090.00

733291305.xlsx ANALISA 20 /20


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

51 1 M3 Membuat Beton Bertulang, 1 PC : 1,5 PS : 2 KR 2,084,390.00


B01 Semen Portland 479.000 Kg 2,500.00 1,197,500.00
B111 Pasir Beton (m3) 0.370 M3 360,000.00 133,200.00
B97 Koral beton (M3) 0.740 M3 480,000.00 355,200.00
U01 Pekerja/Kenek 1.650 O/h 180,000.00 297,000.00
U05 Tukang batu 0.275 O/h 250,000.00 68,750.00
U14 Kepala Tukang 0.028 O/h 280,000.00 7,840.00
U15 Mandor/Pengawas 0.083 O/h 300,000.00 24,900.00
JUMLAH : 2,084,390.00

52 1 M3 Membuat Beton Bertulang, 1 PC : 1 PS : 1 KR 2,731,600.00


B01 Semen Portland 615.000 Kg 2,500.00 1,537,500.00
B111 Pasir Beton (m3) 0.520 M3 360,000.00 187,200.00
B97 Koral beton (M3) 0.520 M3 480,000.00 249,600.00
U01 Pekerja/Kenek 2.000 O/h 180,000.00 360,000.00
U05 Tukang batu 0.350 O/h 250,000.00 87,500.00
U14 Kepala Tukang 0.035 O/h 280,000.00 9,800.00
U15 Mandor/Pengawas 1.000 O/h 300,000.00 300,000.00
JUMLAH : 2,731,600.00

53 1 M3 Membuat Beton dengan Mutu K 225 3,056,252.38


B01 Semen Portland 371.000 Kg 2,500.00 927,500.00
B111 Pasir Beton (m3) 0.499 M3 360,000.00 179,485.71
B103 Split 2 - 3 cm (m3) 0.776 M3 480,000.00 372,266.67
B04 Air Bersih 215.000 Ltr 600.00 129,000.00
U01 Pekerja/Kenek 6.000 O/h 180,000.00 1,080,000.00
U05 Tukang batu 1.000 O/h 250,000.00 250,000.00
U14 Kepala Tukang 0.100 O/h 280,000.00 28,000.00
U15 Mandor/Pengawas 0.300 O/h 300,000.00 90,000.00
JUMLAH : 3,056,252.38

54 1 M3 Membuat Beton dengan Mutu K 250 3,084,365.08


B01 Semen Portland 384.000 Kg 2,500.00 960,000.00
B111 Pasir Beton (m3) 0.494 M3 360,000.00 177,942.86
B103 Split 2 - 3 cm (m3) 0.770 M3 480,000.00 369,422.22
B04 Air Bersih 215.000 Ltr 600.00 129,000.00
U01 Pekerja/Kenek 6.000 O/h 180,000.00 1,080,000.00
U05 Tukang batu 1.000 O/h 250,000.00 250,000.00
U14 Kepala Tukang 0.100 O/h 280,000.00 28,000.00
U15 Mandor/Pengawas 0.300 O/h 300,000.00 90,000.00
JUMLAH : 3,084,365.08

55 1 M3 Membuat Beton dengan Mutu K 275 3,132,685.71


B01 Semen Portland 406.000 Kg 2,500.00 1,015,000.00
B111 Pasir Beton (m3) 0.489 M3 360,000.00 175,885.71
B103 Split 2 - 3 cm (m3) 0.760 M3 480,000.00 364,800.00
B04 Air Bersih 215.000 Ltr 600.00 129,000.00
U01 Pekerja/Kenek 6.000 O/h 180,000.00 1,080,000.00
U05 Tukang batu 1.000 O/h 250,000.00 250,000.00
U14 Kepala Tukang 0.100 O/h 280,000.00 28,000.00
U15 Mandor/Pengawas 0.300 O/h 300,000.00 90,000.00
JUMLAH : 3,132,685.71

56 Membuat 1 m3 beton mutu f’c = 26,4 MPa (K 300), slump (12 ± 2) cm, w/c = 0,52 3,147,636.51
B01 Semen Portland 413.000 Kg 2,500.00 1,032,500.00
B111 Pasir Beton (m3) 0.486 M3 360,000.00 175,114.29
B103 Split 2 - 3 cm (m3) 0.756 M3 480,000.00 363,022.22
B04 Air Bersih 215.000 Ltr 600.00 129,000.00
U01 Pekerja/Kenek 6.000 O/h 180,000.00 1,080,000.00
733291305.xlsx ANALISA 21 /21
HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

U05 Tukang batu 1.000 O/h 250,000.00 250,000.00


U14 Kepala Tukang 0.100 O/h 280,000.00 28,000.00
U15 Mandor/Pengawas 0.300 O/h 300,000.00 90,000.00
JUMLAH : 3,147,636.51

57 Pembesian 10 Kg dengan Besi polos atau Besi Ulir 337,310.00


B304 Besi beton 10.500 Kg 28,000.00 294,000.00
B05 Kawat beton 0.150 Kg 67,000.00 10,050.00
U01 Pekerja/Kenek 0.070 O/h 180,000.00 12,600.00
U06 Tukang besi 0.070 O/h 250,000.00 17,500.00
U14 Kepala Tukang 0.007 O/h 280,000.00 1,960.00
U15 Mandor/Pengawas 0.004 O/h 300,000.00 1,200.00
JUMLAH : 337,310.00
Jumlah harga untuk 1 Kg 33,731.00

17 Memasang 10 Kg Kabel Presstressed Polos/Strands 324,500.00


B304 Besi beton 10.500 Kg 28,000.00 294,000.00
B05 Kawat beton 0.100 Kg 67,000.00 6,700.00
U01 Pekerja/Kenek 0.050 O/h 180,000.00 9,000.00
U06 Tukang besi 0.050 O/h 250,000.00 12,500.00
U14 Kepala Tukang 0.005 O/h 280,000.00 1,400.00
U15 Mandor/Pengawas 0.003 O/h 300,000.00 900.00
JUMLAH : 324,500.00

58 1 M2 Pasang Bekisting untuk Pondasi 334,180.00


B116 Kayu kelas II (papan) 0.040 M3 3,750,000.00 150,000.00
B32 Paku biasa 0.300 Kg 30,000.00 9,000.00
B256 Minyak Bekesting 0.100 Liter 15,000.00 1,500.00
U01 Pekerja/Kenek 0.520 O/h 180,000.00 93,600.00
U04 Tukang Kayu 0.260 O/h 250,000.00 65,000.00
U14 Kepala Tukang 0.026 O/h 280,000.00 7,280.00
U15 Mandor/Pengawas 0.026 O/h 300,000.00 7,800.00
JUMLAH : 334,180.00

59 1 M2 Pasang Bekisting untuk Sloof 352,930.00


B116 Kayu kelas II (papan) 0.045 M3 3,750,000.00 168,750.00
B32 Paku biasa 0.300 Kg 30,000.00 9,000.00
B256 Minyak Bekesting 0.100 Liter 15,000.00 1,500.00
U01 Pekerja/Kenek 0.520 O/h 180,000.00 93,600.00
U04 Tukang Kayu 0.260 O/h 250,000.00 65,000.00
U14 Kepala Tukang 0.026 O/h 280,000.00 7,280.00
U15 Mandor/Pengawas 0.026 O/h 300,000.00 7,800.00
JUMLAH : 352,930.00

60 1 M2 Pasang Bekisting untuk Kolom 590,190.00


B116 Kayu kelas II (papan) 0.040 M3 3,750,000.00 150,000.00
B32 Paku biasa 0.400 Kg 30,000.00 12,000.00
B256 Minyak Bekesting 0.200 Liter 15,000.00 3,000.00
B115 Kayu kelas II (balok) 0.015 M3 3,500,000.00 52,500.00
B15 Plywood 9 mm 0.350 Lembar 235,000.00 82,250.00
B20 Dolken Kayu Dia. 8-10/400 cm 2.000 Batang 35,000.00 70,000.00
U01 Pekerja/Kenek 0.660 O/h 180,000.00 118,800.00
U04 Tukang Kayu 0.330 O/h 250,000.00 82,500.00
U14 Kepala Tukang 0.033 O/h 280,000.00 9,240.00
U15 Mandor/Pengawas 0.033 O/h 300,000.00 9,900.00
JUMLAH : 590,190.00

61 1 M2 Pasang Bekisting untuk Balok 600,690.00


733291305.xlsx ANALISA 22 /22
HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

B116 Kayu kelas II (papan) 0.040 M3 3,750,000.00 150,000.00


B32 Paku biasa 0.400 Kg 30,000.00 12,000.00
B256 Minyak Bekesting 0.200 Liter 15,000.00 3,000.00
B115 Kayu kelas II (balok) 0.018 M3 3,500,000.00 63,000.00
B15 Plywood 9 mm 0.350 Lembar 235,000.00 82,250.00
B20 Dolken Kayu Dia. 8-10/400 cm 2.000 Batang 35,000.00 70,000.00
U01 Pekerja/Kenek 0.660 O/h 180,000.00 118,800.00
U04 Tukang Kayu 0.330 O/h 250,000.00 82,500.00
U14 Kepala Tukang 0.033 O/h 280,000.00 9,240.00
U15 Mandor/Pengawas 0.033 O/h 300,000.00 9,900.00
JUMLAH : 600,690.00

62 1 M2 Pasang Bekisting untuk Plat Lantai 730,190.00


B116 Kayu kelas II (papan) 0.040 M3 3,750,000.00 150,000.00
B32 Paku biasa 0.400 Kg 30,000.00 12,000.00
B256 Minyak Bekesting 0.200 Liter 15,000.00 3,000.00
B115 Kayu kelas II (balok) 0.015 M3 3,500,000.00 52,500.00
B15 Plywood 9 mm 0.350 Lembar 235,000.00 82,250.00
B20 Dolken Kayu Dia. 8-10/400 cm 6.000 Batang 35,000.00 210,000.00
U01 Pekerja/Kenek 0.660 O/h 180,000.00 118,800.00
U04 Tukang Kayu 0.330 O/h 250,000.00 82,500.00
U14 Kepala Tukang 0.033 O/h 280,000.00 9,240.00
U15 Mandor/Pengawas 0.033 O/h 300,000.00 9,900.00
JUMLAH : 730,190.00

63 1 M2 Pasang Bekisting untuk Dinding 642,690.00


B116 Kayu kelas II (papan) 0.040 M3 3,750,000.00 150,000.00
B32 Paku biasa 0.400 Kg 30,000.00 12,000.00
B256 Minyak Bekesting 0.200 Liter 15,000.00 3,000.00
B115 Kayu kelas II (balok) 0.020 M3 3,500,000.00 70,000.00
B15 Plywood 9 mm 0.350 Lembar 235,000.00 82,250.00
B20 Dolken Kayu Dia. 8-10/400 cm 3.000 Batang 35,000.00 105,000.00
B254 Permite/Penjaga jarak bekisting/spacer 4.000 Buah -
U01 Pekerja/Kenek 0.660 O/h 180,000.00 118,800.00
U04 Tukang Kayu 0.330 O/h 250,000.00 82,500.00
U14 Kepala Tukang 0.033 O/h 280,000.00 9,240.00
U15 Mandor/Pengawas 0.033 O/h 300,000.00 9,900.00
JUMLAH : 642,690.00

24 1 M2 Pasang Bekisting untuk Tangga 565,300.00


B116 Kayu kelas II (papan) 0.030 M3 3,750,000.00 112,500.00
B32 Paku biasa 0.400 Kg 30,000.00 12,000.00
B256 Minyak Bekesting 0.150 Liter 15,000.00 2,250.00
B115 Kayu kelas II (balok) 0.015 M3 3,500,000.00 52,500.00
B15 Plywood 9 mm 0.350 Lembar 235,000.00 82,250.00
B20 Dolken Kayu Dia. 8-10/400 cm 2.000 Batang 35,000.00 70,000.00
U01 Pekerja/Kenek 0.700 O/h 180,000.00 126,000.00
U04 Tukang Kayu 0.350 O/h 250,000.00 87,500.00
U14 Kepala Tukang 0.035 O/h 280,000.00 9,800.00
U15 Mandor/Pengawas 0.035 O/h 300,000.00 10,500.00
JUMLAH : 565,300.00

25 1 M2 Pasang Jembatan untuk Pengecoran Beton 290,300.00


B116 Kayu kelas II (papan) 0.026 M3 3,750,000.00 99,000.00
B32 Paku biasa 0.600 Kg 30,000.00 18,000.00
B20 Dolken Kayu Dia. 8-10/400 cm 0.500 Batang 35,000.00 17,500.00
U01 Pekerja/Kenek 0.150 O/h 180,000.00 27,000.00
U04 Tukang Kayu 0.500 O/h 250,000.00 125,000.00
U14 Kepala Tukang 0.005 O/h 280,000.00 1,400.00

733291305.xlsx ANALISA 23 /23


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

U15 Mandor/Pengawas 0.008 O/h 300,000.00 2,400.00


JUMLAH : 290,300.00

64 1 M3 Membuat Pondasi Beton Bertulang (150 kg besi + bekisting ) 8,338,060.00


B116 Kayu kelas II (papan) 0.200 M3 3,750,000.00 750,000.00
B32 Paku biasa 1.500 Kg 30,000.00 45,000.00
B256 Minyak Bekesting 0.400 Liter 15,000.00 6,000.00
B304 Besi beton 150.000 Kg 28,000.00 4,200,000.00
B05 Kawat beton 2.250 Kg 67,000.00 150,750.00
B01 Semen Portland 336.000 Kg 2,500.00 840,000.00
B111 Pasir Beton (m3) 0.540 M3 360,000.00 194,400.00
B97 Koral beton (m3) 0.810 M3 480,000.00 388,800.00
U01 Pekerja/Kenek 5.300 O/h 180,000.00 954,000.00
U05 Tukang Batu 0.275 O/h 250,000.00 68,750.00
U04 Tukang Kayu 1.300 O/h 250,000.00 325,000.00
U06 Tukang besi 1.050 O/h 250,000.00 262,500.00
U14 Kepala Tukang 0.262 O/h 280,000.00 73,360.00
U15 Mandor/Pengawas 0.265 O/h 300,000.00 79,500.00
JUMLAH : 8,338,060.00

65 1 M3 Membuat Sloof Beton Bertulang (200 kg besi + bekisting ) 10,586,790.00


B116 Kayu kelas II (papan) 0.270 M3 3,750,000.00 1,012,500.00
B32 Paku biasa 2.000 Kg 30,000.00 60,000.00
B256 Minyak Bekesting 0.600 Liter 15,000.00 9,000.00
B304 Besi beton 210.000 Kg 28,000.00 5,880,000.00
B05 Kawat beton 3.000 Kg 67,000.00 201,000.00
B01 Semen Portland 336.000 Kg 2,500.00 840,000.00
B111 Pasir Beton (m3) 0.540 M3 360,000.00 194,400.00
B97 Koral beton (m3) 0.810 M3 480,000.00 388,800.00
U01 Pekerja/Kenek 5.650 O/h 180,000.00 1,017,000.00
U05 Tukang Batu 0.275 O/h 250,000.00 68,750.00
U04 Tukang Kayu 1.560 O/h 250,000.00 390,000.00
U06 Tukang besi 1.400 O/h 250,000.00 350,000.00
U14 Kepala Tukang 0.323 O/h 280,000.00 90,440.00
U15 Mandor/Pengawas 0.283 O/h 300,000.00 84,900.00
JUMLAH : 10,586,790.00

66 1 M3 Membuat Kolom Beton Bertulang (300 kg besi + bekisting ) 16,754,200.00


B116 Kayu kelas II (papan) 0.400 M3 3,750,000.00 1,500,000.00
B32 Paku biasa 4.000 Kg 30,000.00 120,000.00
B256 Minyak Bekesting 2.000 Liter 15,000.00 30,000.00
B304 Besi beton 300.000 Kg 28,000.00 8,400,000.00
B05 Kawat beton 4.500 Kg 67,000.00 301,500.00
B01 Semen Portland 323.000 Kg 2,500.00 807,500.00
B111 Pasir Beton (m3) 0.520 M3 360,000.00 187,200.00
B97 Koral beton (m3) 0.780 M3 480,000.00 374,400.00
B115 Kayu kelas II (balok) 0.150 M3 3,500,000.00 525,000.00
B15 Plywood 9 mm 3.500 Lembar 235,000.00 822,500.00
B20 Dolken Kayu Dia. 8-10/400 cm 20.000 Batang 35,000.00 700,000.00
U01 Pekerja/Kenek 7.300 O/h 180,000.00 1,314,000.00
U05 Tukang Batu 0.350 O/h 250,000.00 87,500.00
U04 Tukang Kayu 3.300 O/h 250,000.00 825,000.00
U06 Tukang besi 2.100 O/h 250,000.00 525,000.00
U14 Kepala Tukang 0.570 O/h 280,000.00 159,600.00
U15 Mandor/Pengawas 0.250 O/h 300,000.00 75,000.00
JUMLAH : 16,754,200.00

67 1 M3 Membuat Plat Beton Bertulang (150 kg besi + bekisting ) 11,055,900.00


B116 Kayu kelas II (papan) 0.320 M3 3,750,000.00 1,200,000.00

733291305.xlsx ANALISA 24 /24


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

B32 Paku biasa 3.200 Kg 30,000.00 96,000.00


B256 Minyak Bekesting 1.600 Liter 15,000.00 24,000.00
B304 Besi beton 150.000 Kg 28,000.00 4,200,000.00
B05 Kawat beton 2.250 Kg 67,000.00 150,750.00
B01 Semen Portland 336.000 Kg 2,500.00 840,000.00
B111 Pasir Beton (m3) 0.540 M3 360,000.00 194,400.00
B97 Koral beton (m3) 0.810 M3 480,000.00 388,800.00
B115 Kayu kelas II (balok) 0.120 M3 3,500,000.00 420,000.00
B15 Plywood 9 mm 2.800 Lembar 235,000.00 658,000.00
B20 Dolken Kayu Dia. 8-10/400 cm 32.000 Batang 35,000.00 1,120,000.00
U01 Pekerja/Kenek 5.300 O/h 180,000.00 954,000.00
U05 Tukang Batu 0.275 O/h 250,000.00 68,750.00
U04 Tukang Kayu 1.300 O/h 250,000.00 325,000.00
U06 Tukang besi 1.050 O/h 250,000.00 262,500.00
U14 Kepala Tukang 0.265 O/h 280,000.00 74,200.00
U15 Mandor/Pengawas 0.265 O/h 300,000.00 79,500.00
JUMLAH : 11,055,900.00

68 1 M3 Membuat Balok Beton Bertulang ( 200 Kg Besi + Bekisting ) 12,362,300.00


B116 Kayu kelas II (papan) 0.250 M3 3,750,000.00 937,500.00
B32 Paku biasa 3.200 Kg 30,000.00 96,000.00
B256 Minyak Bekesting 1.600 Liter 15,000.00 24,000.00
B304 Besi beton 200.000 Kg 28,000.00 5,600,000.00
B05 Kawat Beton 3.000 Kg 67,000.00 201,000.00
B01 Semen Portland 323.000 Kg 2,500.00 807,500.00
B111 Pasir Beton (m3) 0.520 M3 360,000.00 187,200.00
B97 Koral beton (m3) 0.780 M3 480,000.00 374,400.00
B115 Kayu kelas II (balok) 0.140 M3 3,500,000.00 490,000.00
B15 Plywood 9 mm 2.800 Lembar 235,000.00 658,000.00
B20 Dolken Kayu Dia. 8-10/400 cm 16.000 Batang 35,000.00 560,000.00
U01 Pekerja/Kenek 5.960 O/h 180,000.00 1,072,800.00
U05 Tukang Batu 0.350 O/h 250,000.00 87,500.00
U04 Tukang Kayu 2.800 O/h 250,000.00 700,000.00
U06 Tukang Besi 1.400 O/h 250,000.00 350,000.00
U14 Kepala Tukang 0.550 O/h 280,000.00 154,000.00
U15 Mandor/Pengawas 0.208 O/h 300,000.00 62,400.00
JUMLAH : 12,362,300.00

69 1 M3 Membuat Balok Beton Bertulang ( 150 Kg Besi + Bekisting ) 11,204,950.00


B116 Kayu kelas II (papan) 0.240 M3 3,750,000.00 900,000.00
B32 Paku biasa 3.200 Kg 30,000.00 96,000.00
B256 Minyak Bekesting 1.600 Liter 15,000.00 24,000.00
B304 Besi beton 150.000 Kg 28,000.00 4,200,000.00
B05 Kawat Beton 2.250 Kg 67,000.00 150,750.00
B01 Semen Portland 323.000 Kg 2,500.00 807,500.00
B111 Pasir Beton (m3) 0.520 M3 360,000.00 187,200.00
B97 Koral beton (m3) 0.780 M3 480,000.00 374,400.00
B115 Kayu kelas II (balok) 0.120 M3 3,500,000.00 420,000.00
B15 Plywood 9 mm 2.800 Lembar 235,000.00 658,000.00
B20 Dolken Kayu Dia. 8-10/400 cm 32.000 Batang 35,000.00 1,120,000.00
U01 Pekerja/Kenek 5.800 O/h 180,000.00 1,044,000.00
U05 Tukang Batu 0.350 O/h 250,000.00 87,500.00
U04 Tukang Kayu 2.800 O/h 250,000.00 700,000.00
U06 Tukang Besi 1.050 O/h 250,000.00 262,500.00
U14 Kepala Tukang 0.420 O/h 280,000.00 117,600.00
U15 Mandor/Pengawas 0.185 O/h 300,000.00 55,500.00
JUMLAH : 11,204,950.00

80 1 M3 Membuat Dinding Beton Bertulang (150 kg besi + bekisting ) 10,582,560.00

733291305.xlsx ANALISA 25 /25


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

B116 Kayu kelas II (papan) 0.240 M3 3,750,000.00 900,000.00


B32 Paku biasa 3.200 Kg 30,000.00 96,000.00
B256 Minyak Bekesting 1.600 Liter 15,000.00 24,000.00
B304 Besi beton 150.000 Kg 28,000.00 4,200,000.00
B05 Kawat beton 2.250 Kg 67,000.00 150,750.00
B01 Semen Portland 323.000 Kg 2,500.00 807,500.00
B111 Pasir Beton (m3) 0.540 M3 360,000.00 194,400.00
B97 Koral beton (m3) 0.810 M3 480,000.00 388,800.00
B115 Kayu kelas II (balok) 0.160 M3 3,500,000.00 560,000.00
B15 Plywood 9 mm 2.800 Lembar 235,000.00 658,000.00
B20 Dolken Kayu Dia. 8-10/400 cm 24.000 Batang 35,000.00 840,000.00
U01 Pekerja/Kenek 5.300 O/h 180,000.00 954,000.00
U05 Tukang Batu 0.275 O/h 250,000.00 68,750.00
U04 Tukang Kayu 1.300 O/h 250,000.00 325,000.00
U06 Tukang Besi 1.050 O/h 250,000.00 262,500.00
U14 Kepala Tukang 0.262 O/h 280,000.00 73,360.00
U15 Mandor/Pengawas 0.265 O/h 300,000.00 79,500.00
JUMLAH : 10,582,560.00

733291305.xlsx ANALISA 26 /26


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

81 1 M3 Membuat Dinding Beton Bertulang (200 kg besi + bekisting ) 11,683,290.00


B116 Kayu kelas II (papan) 0.250 M3 3,750,000.00 937,500.00
B32 Paku biasa 3.000 Kg 30,000.00 90,000.00
B256 Minyak Bekesting 1.200 Liter 15,000.00 18,000.00
B304 Besi beton 200.000 Kg 28,000.00 5,600,000.00
B05 Kawat beton 3.000 Kg 67,000.00 201,000.00
B01 Semen Portland 323.000 Kg 2,500.00 807,500.00
B111 Pasir Beton (m3) 0.540 M3 360,000.00 194,400.00
B97 Koral beton (m3) 0.810 M3 480,000.00 388,800.00
B115 Kayu kelas II (balok) 0.105 M3 3,500,000.00 367,500.00
B15 Plywood 9 mm 2.500 Lembar 235,000.00 587,500.00
B20 Dolken Kayu Dia. 8-10/400 cm 14.000 Batang 35,000.00 490,000.00
U01 Pekerja/Kenek 5.650 O/h 180,000.00 1,017,000.00
U05 Tukang Batu 0.275 O/h 250,000.00 68,750.00
U04 Tukang Kayu 1.560 O/h 250,000.00 390,000.00
U06 Tukang Besi 1.400 O/h 250,000.00 350,000.00
U14 Kepala Tukang 0.323 O/h 280,000.00 90,440.00
U15 Mandor/Pengawas 0.283 O/h 300,000.00 84,900.00
JUMLAH : 11,683,290.00

82 1 M' Membuat Kolom Praktis Beton Bertulang (11 x 11 ) cm 124,055.00


B116 Kayu kelas II (papan) 0.002 M3 3,750,000.00 7,500.00
B304 Besi beton 0.010 Kg 28,000.00 280.00
B256 Minyak Bekesting 3.000 Liter 15,000.00 45,000.00
B05 Kawat beton 0.045 Kg 67,000.00 3,015.00
B01 Semen Portland 4.000 Kg 2,500.00 10,000.00
B111 Pasir Beton (m3) 0.006 M3 360,000.00 2,160.00
B97 Koral beton (m3) 0.009 M3 480,000.00 4,320.00
U01 Pekerja/Kenek 0.180 O/h 180,000.00 32,400.00
U05 Tukang Batu 0.020 O/h 250,000.00 5,000.00
U04 Tukang Kayu 0.020 O/h 250,000.00 5,000.00
U06 Tukang Besi 0.020 O/h 250,000.00 5,000.00
U14 Kepala Tukang 0.006 O/h 280,000.00 1,680.00
U15 Mandor/Pengawas 0.009 O/h 300,000.00 2,700.00
JUMLAH : 124,055.00

83 1 M' Membuat Ring Balok Beton Bertulang (10 x 15 ) cm 178,860.00


B116 Kayu kelas II (papan) 0.003 M3 3,750,000.00 11,250.00
B304 Besi beton 0.020 Kg 28,000.00 560.00
B256 Minyak Bekesting 3.600 Liter 15,000.00 54,000.00
B05 Kawat beton 0.050 Kg 67,000.00 3,350.00
B01 Semen Portland 5.500 Kg 2,500.00 13,750.00
B111 Pasir Beton (m3) 0.009 M3 360,000.00 3,240.00
B97 Koral beton (m3) 0.015 M3 480,000.00 7,200.00
U01 Pekerja/Kenek 0.297 O/h 180,000.00 53,460.00
U05 Tukang Batu 0.033 O/h 250,000.00 8,250.00
U04 Tukang Kayu 0.033 O/h 250,000.00 8,250.00
U06 Tukang Besi 0.033 O/h 250,000.00 8,250.00
U14 Kepala Tukang 0.010 O/h 280,000.00 2,800.00
U15 Mandor/Pengawas 0.015 O/h 300,000.00 4,500.00
JUMLAH : 178,860.00

84 1 M3 Pekerjaan Pondasi Beton Bertulang 8,952,551.25


Beton K.275 1.000 m3 3,132,685.71 3,132,685.71
Besi Tulangan/Pembesian 131.680 Kg 33,731.00 4,441,690.53
Bekisting Pondasi 3.750 m2 334,180.00 1,253,175.00
U09 Tuk.Bongkar Bekisting 0.500 O/h 250,000.00 125,000.00
JUMLAH : 8,952,551.25

733291305.xlsx ANALISA 27 /27


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

85 1 M3 Pekerjaan Pondasi tapak Beton 8,874,060.59


Beton K.275 1.000 m3 3,132,685.71 3,132,685.71
Besi Tulangan/Pembesian 139.210 Kg 33,731.00 4,695,708.21
Bekisting Pondasi 2.381 m2 334,180.00 795,666.67
U09 Tuk.Bongkar Bekisting 1.000 O/h 250,000.00 250,000.00
JUMLAH : 8,874,060.59

86 1 M3 Pekerjaan Kolom Beton Bertulang K1 (20/46) Sumur 12,301,258.38


Beton K.275 1.000 m3 3,132,685.71 3,132,685.71
Besi Tulangan/Pembesian 153.311 Kg 33,731.00 5,171,334.57
Bekisting kolom 6.349 m2 590,190.00 3,747,238.10
U09 Tuk.Bongkar Bekisting 1.000 O/h 250,000.00 250,000.00
JUMLAH : 12,301,258.38

87 1 M3 Pekerjaan Kolom Beton Bertulang K2 (30x30cm)


Beton K.275 1.000 m3 3,132,685.71 3,132,685.71
Besi Tulangan/Pembesian 305.510 Kg 33,731.00 10,305,157.81
Bekisting kolom 13.333 m2 590,190.00 7,869,200.00
U09 Tuk.Bongkar Bekisting 1.000 O/h 250,000.00 250,000.00
JUMLAH : 21,557,043.52

88 1 M3 Pekerjaan Kolom Beton Bertulang K1.a (25x40cm)


Beton K.275 1.000 m3 3,132,685.71 3,132,685.71
Besi Tulangan/Pembesian 316.684 Kg 33,731.00 10,682,058.56
Bekisting kolom 13.000 m2 590,190.00 7,672,470.00
U09 Tuk.Bongkar Bekisting 1.000 O/h 250,000.00 250,000.00
JUMLAH : 21,737,214.27

89 1 M3 Pekerjaan Balok Beton Bertulang B1 (25x40 cm)


Beton K.275 1.000 m3 3,132,685.71 3,132,685.71
Besi Tulangan/Pembesian 225.191 Kg 33,731.00 7,595,917.96
Bekisting balok 10.500 m2 600,690.00 6,307,245.00
U09 Tuk.Bongkar Bekisting 1.000 O/h 250,000.00 250,000.00
JUMLAH : 17,285,848.67

90 1 M3 Pekerjaan Balok Beton Bertulang B2 (25x35 cm)


Beton K.275 1.000 m3 3,132,685.71 3,132,685.71
Besi Tulangan/Pembesian 219.643 Kg 33,731.00 7,408,781.31
Bekisting balok 10.857 m2 600,690.00 6,521,777.14
U09 Tuk.Bongkar Bekisting 1.000 O/h 250,000.00 250,000.00
JUMLAH : 17,313,244.17

91 1 M3 Pekerjaan Balok Beton Bertulang R (25x35 cm)


Beton K.275 1.000 m3 3,132,685.71 3,132,685.71
Besi Tulangan/Pembesian 219.643 Kg 33,731.00 7,408,781.31
Bekisting balok 10.857 m2 600,690.00 6,521,777.14
U09 Tuk.Bongkar Bekisting 1.000 O/h 250,000.00 250,000.00
JUMLAH : 17,313,244.17

92 1 M3 Pekerjaan Balok Beton Bertulang B3 (25x50 cm)


Beton K.275 1.000 m3 3,132,685.71 3,132,685.71

733291305.xlsx ANALISA 28 /28


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

Besi Tulangan/Pembesian 270.708 Kg 33,731.00 9,131,238.60


Bekisting balok 10.000 m2 600,690.00 6,006,900.00
U09 Tuk.Bongkar Bekisting 1.000 O/h 250,000.00 250,000.00
JUMLAH : 18,520,824.31

93 1 M3 Pekerjaan Balok Beton Bertulang B4 (25x40 cm)


Beton K.275 1.000 m3 3,132,685.71 3,132,685.71
Besi Tulangan/Pembesian 229.408 Kg 33,731.00 7,738,176.67
Bekisting balok 10.857 m2 600,690.00 6,521,777.14
U09 Tuk.Bongkar Bekisting 1.000 O/h 250,000.00 250,000.00
JUMLAH : 17,642,639.53

94 1 M3 Pekerjaan Ring Balok Rb (20x30 cm) Sumur 13,933,941.84


Beton K.275 1.000 m3 3,132,685.71 3,132,685.71
Besi Tulangan/Pembesian 177.124 Kg 33,731.00 5,974,570.41
Bekisting balok 7.619 m2 600,690.00 4,576,685.71
U09 Tuk.Bongkar Bekisting 1.000 O/h 250,000.00 250,000.00
JUMLAH : 13,933,941.84

95 1 M3 Pekerjaan Balok Beton Bertulang B5 (20x30 cm)


Beton K.275 1.000 m3 3,132,685.71 3,132,685.71
Besi Tulangan/Pembesian 255.806 Kg 33,731.00 8,628,605.68
Bekisting balok 13.333 m2 600,690.00 8,009,200.00
U09 Tuk.Bongkar Bekisting 1.000 O/h 250,000.00 250,000.00
JUMLAH : 20,020,491.39

96 1 M3 Pekerjaan Beton Bertulang Slof (30x40 cm)


Beton K.275 1.000 m3 3,132,685.71 3,132,685.71
Besi Tulangan/Pembesian 176.566 Kg 33,731.00 5,955,734.25
Bekisting slof 6.667 m2 352,930.00 2,352,866.67
U09 Tuk.Bongkar Bekisting 1.000 O/h 250,000.00 250,000.00
JUMLAH : 11,691,286.63

733291305.xlsx ANALISA 29 /29


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

97 1 M3 Dinding Beton Reservoar 20Cm 15,514,551.68


Beton K.300 1.000 m3 3,147,636.51 3,147,636.51
Besi Tulangan/Pembesian 161.276 Kg 33,731.00 5,440,015.17
Bekisting dinding 10.000 m2 642,690.00 6,426,900.00
U09 Tuk.Bongkar Bekisting 2.000 O/h 250,000.00 500,000.00
JUMLAH : 15,514,551.68

98 1 m3 Beton Precast tebal 25 Cm Type PR 1 9,075,990.18


Beton K.275 1.000 m3 3,132,685.71 3,132,685.71
Besi Tulangan/Pembesian 116.009 Kg 33,731.00 3,913,090.18
Bekisting dinding 2.381 m2 642,690.00 1,530,214.29
U09 Tuk.Bongkar Bekisting 2.000 O/h 250,000.00 500,000.00
JUMLAH : 9,075,990.18

99 1 m3 Beton Precast tebal 25 Cm Type PR 2 20,846,488.30


Beton K.275 1.000 m3 3,132,685.71 3,132,685.71
Besi Tulangan/Pembesian 221.755 Kg 33,731.00 7,480,019.59
Bekisting dinding 9.524 m2 642,690.00 6,120,857.14
U09 Tuk.Bongkar Bekisting 2.000 O/h 250,000.00 500,000.00
JUMLAH : 17,233,562.45

100 1 m3 Beton Precast tebal 25 Cm Type PR 3 20,846,488.30


Beton K.275 1.000 m3 3,132,685.71 3,132,685.71
Besi Tulangan/Pembesian 268.378 Kg 33,731.00 9,052,659.73
Bekisting dinding 12.698 m2 642,690.00 8,161,142.86
U09 Tuk.Bongkar Bekisting 2.000 O/h 250,000.00 500,000.00
JUMLAH : 20,846,488.30

98 1 M3 Dinding Beton Water Tangk 15Cm


Beton K.275 1.000 m3 3,132,685.71 3,132,685.71
Besi Tulangan/Pembesian 189.389 Kg 33,731.00 6,388,273.61
Bekisting dinding 13.333 m2 642,690.00 8,569,200.00
U09 Tuk.Bongkar Bekisting 2.000 O/h 250,000.00 500,000.00
JUMLAH : 18,590,159.33

99 1 M3 Dinding Beton Water Tangk 12Cm


Beton K.275 1.000 M3 3,132,685.71 3,132,685.71
Besi Tulangan/Pembesian 118.368 Kg 33,731.00 3,992,671.01
Bekisting dinding 16.667 M2 642,690.00 10,711,500.00
U09 Tuk.Bongkar Bekisting 2.000 o/h 250,000.00 500,000.00
JUMLAH : 18,336,856.72

100 1 M3 Plat Beton Water Tank 20Cm 12,074,840.92


Beton K.275 1.000 M3 3,132,685.71 3,132,685.71
Besi Tulangan/Pembesian 142.042 Kg 33,731.00 4,791,205.21
Bekisting dinding 5.000 M2 730,190.00 3,650,950.00
U09 Tuk.Bongkar Bekisting 2.000 o/h 250,000.00 500,000.00
JUMLAH : 12,074,840.92

101 1 M3 Plat Beton Lantai 15Cm 17,180,998.66


Beton K.275 1.000 M3 3,132,685.71 3,132,685.71
Besi Tulangan/Pembesian 113.025 Kg 33,731.00 3,812,446.28
Bekisting plat 13.333 M2 730,190.00 9,735,866.67

733291305.xlsx ANALISA 30 /30


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

U09 Tuk.Bongkar Bekisting 2.000 o/h 250,000.00 500,000.00


JUMLAH : 17,180,998.66

102 1 M3 Plat Atap Beton 12Cm 19,129,744.89


Beton K.275 1.000 M3 3,132,685.71 3,132,685.71
Besi Tulangan/Pembesian 98.640 Kg 33,731.00 3,327,225.84
Bekisting plat 16.667 M2 730,190.00 12,169,833.33
U09 Tuk.Bongkar Bekisting 2.000 o/h 250,000.00 500,000.00
JUMLAH : 19,129,744.89

103 1 M3 Plat Atap Beton 10Cm


Beton K.300 1.000 M3 3,132,685.71 3,132,685.71
Besi Tulangan/Pembesian 98.640 Kg 33,731.00 3,327,225.84
Bekisting plat 16.667 M2 730,190.00 12,169,833.33
U09 Tuk.Bongkar Bekisting 2.000 o/h 250,000.00 500,000.00
JUMLAH : 19,129,744.89

104 1 M3 Lisplan Beton 10Cm


Beton K.275 1.000 M3 3,132,685.71 3,132,685.71
Besi Tulangan/Pembesian 118.368 Kg 33,731.00 3,992,671.01
Bekisting lisplan 22.000 M2 730,190.00 16,064,180.00
U09 Tuk.Bongkar Bekisting 2.000 o/h 250,000.00 500,000.00
JUMLAH : 23,689,536.72

96 Pekerjaan Beton Plat Lantai 2 Sistem Bondex / M2 #N/A


Pengecoran/M2 584,451.48
Pekerjaan beton mutu f’c = 19,3 MPa (K 225), slump (12 ± 2) cm, w/c
0.120 M3 3,056,252.38 366,750.29
= 0,58
B01 Semen Portland 42.290 Kg 2,500.00 105,725.00
B112 Pasir beton (kg) 79.570 Kg 257.14 20,460.86
B102 Split 1 - 2 cm (Kg) 119.360 Kg 266.67 31,829.33
B04 Air Bersih 24.510 Ltr 600.00 14,706.00
U01 Pekerja/Kenek 0.190 O/h 180,000.00 34,200.00
U05 Tukang batu 0.030 O/h 250,000.00 7,500.00
U14 Kepala Tukang 0.001 O/h 280,000.00 280.00
U15 Mandor/Pengawas 0.010 O/h 300,000.00 3,000.00
JUMLAH : 584,451.48
Pembesian/M2 #N/A
Besi beton polos untuk angkur 1.172 kg 33,731.00 39,527.44
wiramesh SNI M9 0.218 Lbr #N/A #N/A
B05 Kawat beton 0.085 kg 67,000.00 5,695.00
Pengelasan 20.000 cm 9,565.00 191,300.00
U01 Pekerja/Kenek 0.100 O/h 180,000.00 18,000.00
U06 Tukang besi 0.050 O/h 250,000.00 12,500.00
U14 Kepala Tukang 0.025 O/h 280,000.00 7,000.00
U15 Mandor/Pengawas 0.013 O/h 300,000.00 3,750.00
JUMLAH : #N/A
Bekisting/M2 #N/A
B320 Plat Bondek 1,00 mm X 1 m 1.030 m2 -
Kayu kelas III - m3 #N/A #N/A
B32 Paku biasa 0.100 Kg 30,000.00 3,000.00
Minyak bekisting - ltr #N/A #N/A
B115 Kayu kelas II (balok) 0.030 m3 3,500,000.00 105,000.00
Plywood tebal 9 mm - Lbr #N/A #N/A
B116 Kayu kelas II (pa Beqisting Pinggir 0.034 m2 3,750,000.00 127,500.00
A36 Sewa Schafolding 0.500 Set 50,000.00 25,000.00
U01 Pekerja/Kenek 0.170 O/h 180,000.00 30,600.00

733291305.xlsx ANALISA 31 /31


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

U04 Tukang kayu 0.080 O/h 250,000.00 20,000.00


U14 Kepala tukang 0.015 O/h 280,000.00 4,200.00
U15 Mandor/Pengawas 0.010 O/h 300,000.00 3,000.00
JUMLAH : #N/A
TOTAL #N/A

97 1 M3 Lantai Beton Tumbuk K.100 (Bertulang)


Beton Tumbuk K. 100 1.000 M3 1,540,300.00 1,540,300.00
B304 Besi Beton 49.330 Kg 33,731.00 1,663,950.23
3,204,250.23

VIII PEKERJAAN PENUTUP ATAP


1 1 M2 Pasang Atap Seng Gelombang 110,680.00
B63 Seng Gelombang BJLS 30' 0.700 Lembar 100,000.00 70,000.00
B32 Paku biasa 0.020 Kg 30,000.00 600.00
U01 Pekerja/Kenek 0.120 O/h 180,000.00 21,600.00
U04 Tukang Kayu 0.060 O/h 250,000.00 15,000.00
U14 Kepala Tukang 0.006 O/h 280,000.00 1,680.00
U15 Mandor/Pengawas 0.006 O/h 300,000.00 1,800.00
JUMLAH : 110,680.00

2 1 M2 Pasang Atap Genteng Metal 158,100.00


B75 Genteng Metal 2.250 Lembar -
B35 Paku Atap 0.200 Kg 220,000.00 44,000.00
U01 Pekerja/Kenek 0.200 O/h 180,000.00 36,000.00
U04 Tukang Kayu 0.200 O/h 250,000.00 50,000.00
U14 Kepala Tukang 0.020 O/h 280,000.00 5,600.00
U15 Mandor/Pengawas 0.075 O/h 300,000.00 22,500.00
JUMLAH : 158,100.00

3 1 M1 Pasang Bubungan Genteng Metal 125,600.00


B76 Bubungan Genteng Metal 5.000 Buah -
B116 Kayu kelas II (papan) 0.020 M3 3,750,000.00 75,000.00
B35 Paku Atap 0.015 Kg 220,000.00 3,300.00
U01 Pekerja/Kenek 0.100 O/h 180,000.00 18,000.00
U04 Tukang Kayu 0.100 O/h 250,000.00 25,000.00
U14 Kepala Tukang 0.010 O/h 280,000.00 2,800.00
U15 Mandor/Pengawas 0.005 O/h 300,000.00 1,500.00
JUMLAH : 125,600.00

4 1 M2 Pasang Atap Nok Seng 90,240.00


B65 Seng Plat bjls 30 0.300 Lembar 135,000.00 40,500.00
B32 Paku biasa 0.040 Kg 30,000.00 1,200.00
U01 Pekerja/Kenek 0.150 O/h 180,000.00 27,000.00
U04 Tukang Kayu 0.070 O/h 250,000.00 17,500.00
U14 Kepala Tukang 0.008 O/h 280,000.00 2,240.00
U15 Mandor/Pengawas 0.006 O/h 300,000.00 1,800.00
JUMLAH : 90,240.00

6 1m² Pasang Atap Genteng Palentong Kecil #N/A


Genteng Palentong 25.000 #N/A #N/A #N/A
U01 Pekerja/Kenek 0.150 O/h 180,000.00 27,000.00
U04 Tukang Kayu 0.075 O/h 250,000.00 18,750.00
U14 Kepala Tukang 0.008 O/h 280,000.00 2,240.00
U15 Mandor/Pengawas 0.008 O/h 300,000.00 2,400.00
JUMLAH : #N/A

7 1m² Pasang Atap Genteng Kodok / Glazzur #N/A

733291305.xlsx ANALISA 32 /32


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

Genteng Kodok 25.000 #N/A #N/A #N/A


U01 Pekerja/Kenek 0.150 O/h 180,000.00 27,000.00
U04 Tukang Kayu 0.075 O/h 250,000.00 18,750.00
U14 Kepala Tukang 0.008 O/h 280,000.00 2,240.00
U15 Mandor/Pengawas 0.008 O/h 300,000.00 2,400.00
JUMLAH : #N/A

8 1m² Pasang Atap Genteng Palentong Super / Besar #N/A


Genteng Palento Thursday, August 16, 1906 12.000 #N/A #N/A #N/A
U01 Pekerja/Kenek 0.150 O/h 180,000.00 27,000.00
U04 Tukang Kayu 0.060 O/h 250,000.00 15,000.00
U14 Kepala Tukang 0.006 O/h 280,000.00 1,680.00
U15 Mandor/Pengawas 0.008 O/h 300,000.00 2,400.00
JUMLAH : #N/A

9 1m' Pasang Genteng Bubung Palentong #N/A


Genteng Bubung Palentong 5.000 #N/A #N/A #N/A
B01 Semen Portland 8.000 Kg 2,500.00 20,000.00
B110 Pasir Pasang 0.032 M3 360,000.00 11,520.00
U01 Pekerja/Kenek 0.400 O/h 180,000.00 72,000.00
U04 Tukang Kayu 0.200 O/h 250,000.00 50,000.00
U14 Kepala Tukang 0.020 O/h 280,000.00 5,600.00
U15 Mandor/Pengawas 0.002 O/h 300,000.00 600.00
JUMLAH : #N/A

10 1m' Pasang Genteng Bubung Kodok Glazzur #N/A


Genteng Bubung Kodok 5.000 #N/A #N/A #N/A
B01 Semen Portland 8.000 Kg 2,500.00 20,000.00
B110 Pasir Pasang 0.032 M3 360,000.00 11,520.00
U01 Pekerja/Kenek 0.400 O/h 180,000.00 72,000.00
U04 Tukang Kayu 0.200 O/h 250,000.00 50,000.00
U14 Kepala Tukang 0.020 O/h 280,000.00 5,600.00
U15 Mandor/Pengawas 0.002 O/h 300,000.00 600.00
JUMLAH : #N/A

11 1m' Pasang Genteng Bubung Palentong Besar #N/A


Genteng Bubung Palentong 4.000 #N/A #N/A #N/A
B01 Semen Portland 8.000 Kg 2,500.00 20,000.00
B110 Pasir Pasang 0.032 M3 360,000.00 11,520.00
U01 Pekerja/Kenek 0.400 O/h 180,000.00 72,000.00
U04 Tukang Kayu 0.200 O/h 250,000.00 50,000.00
U14 Kepala Tukang 0.020 O/h 280,000.00 5,600.00
U15 Mandor/Pengawas 0.002 O/h 300,000.00 600.00
JUMLAH : #N/A

12 1m' Pasang Rooflight Fiberglass ( 180 x 90 ) cm #N/A


Roof Light Fiberglass 0.600 #N/A #N/A #N/A
B29 Paku 0.050 Kg 30,000.00 1,500.00
U01 Pekerja/Kenek 0.140 O/h 180,000.00 25,200.00
U04 Tukang Kayu 0.067 O/h 250,000.00 16,750.00
U14 Kepala Tukang 0.007 O/h 280,000.00 1,960.00

733291305.xlsx ANALISA 33 /33


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

U15 Mandor/Pengawas 0.007 O/h 300,000.00 2,100.00


JUMLAH : #N/A

13 1m' Pasang Atap Asbes Gelombang ( 2.50 x 0.92 m ) X 5mm #N/A


Asbes Gelombang 0.500 #N/A #N/A #N/A
B40 Paku Pancing 60 x 230 0.120 Kg -
U01 Pekerja/Kenek 0.140 O/h 180,000.00 25,200.00
U04 Tukang Kayu 0.075 O/h 250,000.00 18,750.00
U14 Kepala Tukang 0.008 O/h 280,000.00 2,240.00
U15 Mandor/Pengawas 0.008 O/h 300,000.00 2,400.00
JUMLAH : #N/A

14 1m' Pasang Atap Asbes Gelombang ( 2.25 x 0.92 m ) X 5mm #N/A


Asbes Gelombang 0.600 #N/A #N/A #N/A
B40 Paku Pancing 60 x 230 0.120 Kg -
U01 Pekerja/Kenek 0.140 O/h 180,000.00 25,200.00
U04 Tukang Kayu 0.075 O/h 250,000.00 18,750.00
U14 Kepala Tukang 0.008 O/h 280,000.00 2,240.00
U15 Mandor/Pengawas 0.008 O/h 300,000.00 2,400.00
JUMLAH : #N/A

15 1m' Pasang Atap Asbes Gelombang ( 2.00 x 0.92 m ) X 5mm #N/A


Asbes Gelombang 0.600 #N/A #N/A #N/A
B40 Paku Pancing 60 x 230 0.120 Kg -
U01 Pekerja/Kenek 0.140 O/h 180,000.00 25,200.00
U04 Tukang Kayu 0.070 O/h 250,000.00 17,500.00
U14 Kepala Tukang 0.007 O/h 280,000.00 1,960.00
U15 Mandor/Pengawas 0.007 O/h 300,000.00 2,100.00
JUMLAH : #N/A

16 1m' Pasang Atap Asbes Gelombang ( 1.80 x 0.92 m ) X 5mm #N/A


Asbes Gelombang 0.750 #N/A #N/A #N/A
B40 Paku Pancing 60 x 230 0.120 Kg -
U01 Pekerja/Kenek 0.140 O/h 180,000.00 25,200.00
U04 Tukang Kayu 0.070 O/h 250,000.00 17,500.00
U14 Kepala Tukang 0.007 O/h 280,000.00 1,960.00
U15 Mandor/Pengawas 0.007 O/h 300,000.00 2,100.00
JUMLAH : #N/A

17 1m² Pasang Atap Asbes Gelombang ( 300 x 1.05 m ) X 4mm #N/A


Asbes Gelombang 0.350 #N/A #N/A #N/A
B40 Paku Pancing 60 x 230 0.120 Kg -
U01 Pekerja/Kenek 0.140 O/h 180,000.00 25,200.00
U04 Tukang Kayu 0.070 O/h 250,000.00 17,500.00
U14 Kepala Tukang 0.007 O/h 280,000.00 1,960.00
U15 Mandor/Pengawas 0.007 O/h 300,000.00 2,100.00
JUMLAH : #N/A

18 1m² Pasang Atap Asbes Gelombang ( 270 x 1.05 m ) X 4mm #N/A


Asbes Gelombang 0.420 #N/A #N/A #N/A
B40 Paku Pancing 60 x 230 0.120 Kg -

733291305.xlsx ANALISA 34 /34


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

U01 Pekerja/Kenek 0.140 O/h 180,000.00 25,200.00


U04 Tukang Kayu 0.070 O/h 250,000.00 17,500.00
U14 Kepala Tukang 0.007 O/h 280,000.00 1,960.00
U15 Mandor/Pengawas 0.007 O/h 300,000.00 2,100.00
JUMLAH : #N/A

19 1m² Pasang Atap Asbes Gelombang ( 240 x 1.05 m ) X 4mm #N/A


Asbes Gelombang 0.440 #N/A #N/A #N/A
B40 Paku Pancing 60 x 230 0.120 Kg -
U01 Pekerja/Kenek 0.140 O/h 180,000.00 25,200.00
U04 Tukang Kayu 0.067 O/h 250,000.00 16,750.00
U14 Kepala Tukang 0.007 O/h 280,000.00 1,960.00
U15 Mandor/Pengawas 0.007 O/h 300,000.00 2,100.00
JUMLAH : #N/A

20 1m² Pasang Atap Asbes Gelombang ( 210 x 1.05 m ) X 4mm #N/A


Asbes Gelombang 0.510 #N/A #N/A #N/A
B40 Paku Pancing 60 x 230 0.120 Kg -
U01 Pekerja/Kenek 0.140 O/h 180,000.00 25,200.00
U04 Tukang Kayu 0.067 O/h 250,000.00 16,750.00
U14 Kepala Tukang 0.007 O/h 280,000.00 1,960.00
U15 Mandor/Pengawas 0.007 O/h 300,000.00 2,100.00
JUMLAH : #N/A

21 1m² Pasang Atap Asbes Gelombang ( 1.5 x 1.05 m ) X 4mm #N/A


Asbes Gelombang 0.800 #N/A #N/A #N/A
B40 Paku Pancing 60 x 230 0.120 Kg -
U01 Pekerja/Kenek 0.140 O/h 180,000.00 25,200.00
U04 Tukang Kayu 0.067 O/h 250,000.00 16,750.00
U14 Kepala Tukang 0.007 O/h 280,000.00 1,960.00
U15 Mandor/Pengawas 0.007 O/h 300,000.00 2,100.00
JUMLAH : #N/A

22 1m² Pasang Atap Asbes Gelombang ( 3.00 x 1.08 m ) X 6mm #N/A


Asbes Gelombang 0.370 #N/A #N/A #N/A
B40 Paku Pancing 60 x 230 0.120 Kg -
U01 Pekerja/Kenek 0.140 O/h 180,000.00 25,200.00
U04 Tukang Kayu 0.067 O/h 250,000.00 16,750.00
U14 Kepala Tukang 0.007 O/h 280,000.00 1,960.00
U15 Mandor/Pengawas 0.007 O/h 300,000.00 2,100.00
JUMLAH : #N/A

23 1m² Pasang Atap Asbes Gelombang ( 2.7 x 1.08 m ) X 6mm #N/A


Asbes Gelombang 0.380 #N/A #N/A #N/A
B40 Paku Pancing 60 x 230 0.120 Kg -
U01 Pekerja/Kenek 0.140 O/h 180,000.00 25,200.00
U04 Tukang Kayu 0.067 O/h 250,000.00 16,750.00
U14 Kepala Tukang 0.007 O/h 280,000.00 1,960.00
U15 Mandor/Pengawas 0.007 O/h 300,000.00 2,100.00
JUMLAH : #N/A

733291305.xlsx ANALISA 35 /35


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

24 1m² Pasang Atap Asbes Gelombang ( 2.4 x 1.08 m ) X 6mm #N/A


Asbes Gelombang 0.460 #N/A #N/A #N/A
B40 Paku Pancing 60 x 230 0.120 Kg -
U01 Pekerja/Kenek 0.140 O/h 180,000.00 25,200.00
U04 Tukang Kayu 0.067 O/h 250,000.00 16,750.00
U14 Kepala Tukang 0.007 O/h 280,000.00 1,960.00
U15 Mandor/Pengawas 0.007 O/h 300,000.00 2,100.00
JUMLAH : #N/A

25 1m² Pasang Atap Asbes Gelombang ( 2.1 x 1.08 m ) X 6mm #N/A


Asbes Gelombang 0.490 #N/A #N/A #N/A
B40 Paku Pancing 60 x 230 0.120 Kg -
U01 Pekerja/Kenek 0.140 O/h 180,000.00 25,200.00
U04 Tukang Kayu 0.067 O/h 250,000.00 16,750.00
U14 Kepala Tukang 0.007 O/h 280,000.00 1,960.00
U15 Mandor/Pengawas 0.007 O/h 300,000.00 2,100.00
JUMLAH : #N/A

26 1m² Pasang Atap Asbes Gelombang ( 1.80 x 1.08 m ) X 6mm #N/A


Asbes Gelombang 0.570 #N/A #N/A #N/A
B40 Paku Pancing 60 x 230 0.120 Kg -
U01 Pekerja/Kenek 0.140 O/h 180,000.00 25,200.00
U04 Tukang Kayu 0.067 O/h 250,000.00 16,750.00
U14 Kepala Tukang 0.007 O/h 280,000.00 1,960.00
U15 Mandor/Pengawas 0.007 O/h 300,000.00 2,100.00
JUMLAH : #N/A

27 1m' Pasang Bubung Stel Gelombang 0.92m #N/A


Asbes Gelombang 2.400 #N/A #N/A #N/A
B40 Paku Pancing 60 x 230 6.000 Kg -
U01 Pekerja/Kenek 0.084 O/h 180,000.00 15,120.00
U04 Tukang Kayu 0.125 O/h 250,000.00 31,250.00
U14 Kepala Tukang 0.013 O/h 280,000.00 3,640.00
U15 Mandor/Pengawas 0.004 O/h 300,000.00 1,200.00
JUMLAH : #N/A

28 1m' Pasang Nok Stel Gelombang 0.92m #N/A


Asbes Gelombang 2.400 #N/A #N/A #N/A
Paku Sekrup 6.000 #N/A #N/A #N/A
U01 Pekerja/Kenek 0.084 O/h 180,000.00 15,120.00
U04 Tukang Kayu 0.125 O/h 250,000.00 31,250.00
U14 Kepala Tukang 0.013 O/h 280,000.00 3,640.00
U15 Mandor/Pengawas 0.004 O/h 300,000.00 1,200.00
JUMLAH : #N/A

29 1m' Pasang Nok Stel Gelombang 1.05m #N/A


Asbes Gelombang 2.100 #N/A #N/A #N/A
B38 Paku Skrup 6.000 bj 1,300.00 7,800.00
U01 Pekerja/Kenek 0.084 O/h 180,000.00 15,120.00
U04 Tukang Kayu 0.125 O/h 250,000.00 31,250.00
U14 Kepala Tukang 0.013 O/h 280,000.00 3,640.00

733291305.xlsx ANALISA 36 /36


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

U15 Mandor/Pengawas 0.004 O/h 300,000.00 1,200.00


JUMLAH : #N/A

30 1m' Pasang Nok Stel Gelombang 1.08m #N/A


Asbes Gelombang 2.050 #N/A #N/A #N/A
B38 Paku Skrup 6.000 bj 1,300.00 7,800.00
U01 Pekerja/Kenek 0.084 O/h 180,000.00 15,120.00
U04 Tukang Kayu 0.125 O/h 250,000.00 31,250.00
U14 Kepala Tukang 0.013 O/h 280,000.00 3,640.00
U15 Mandor/Pengawas 0.004 O/h 300,000.00 1,200.00
JUMLAH : #N/A

31 1m' Pasang Nok Paten 0.92m #N/A


Nok Paten 1.200 #N/A #N/A #N/A
B38 Paku Skrup 6.000 bj 1,300.00 7,800.00
U01 Pekerja/Kenek 0.084 O/h 180,000.00 15,120.00
U04 Tukang Kayu 0.125 O/h 250,000.00 31,250.00
U14 Kepala Tukang 0.013 O/h 280,000.00 3,640.00
U15 Mandor/Pengawas 0.004 O/h 300,000.00 1,200.00
JUMLAH : #N/A

32 1m' Pasang Nok Paten 1.05m #N/A


Nok Paten 1.200 #N/A #N/A #N/A
B38 Paku Skrup 6.000 bj 1,300.00 7,800.00
U01 Pekerja/Kenek 0.084 O/h 180,000.00 15,120.00
U04 Tukang Kayu 0.125 O/h 250,000.00 31,250.00
U14 Kepala Tukang 0.013 O/h 280,000.00 3,640.00
U15 Mandor/Pengawas 0.004 O/h 300,000.00 1,200.00
JUMLAH : #N/A

33 1m' Pasang Nok Paten 1.08m #N/A


Nok Paten 1.200 #N/A #N/A #N/A
B38 Paku Skrup 6.000 bj 1,300.00 7,800.00
U01 Pekerja/Kenek 0.084 O/h 180,000.00 15,120.00
U04 Tukang Kayu 0.125 O/h 250,000.00 31,250.00
U14 Kepala Tukang 0.013 O/h 280,000.00 3,640.00
U15 Mandor/Pengawas 0.004 O/h 300,000.00 1,200.00
JUMLAH : #N/A

34 1m' Pasang Nok Stel rata 0.92m #N/A


Nok Stel rata 1.100 #N/A #N/A #N/A
B38 Paku Skrup 6.000 bj 1,300.00 7,800.00
U01 Pekerja/Kenek 0.100 O/h 180,000.00 18,000.00
U04 Tukang Kayu 0.150 O/h 250,000.00 37,500.00
U14 Kepala Tukang 0.013 O/h 280,000.00 3,640.00
U15 Mandor/Pengawas 0.004 O/h 300,000.00 1,200.00
JUMLAH : #N/A

35 1m' Pasang Nok Stel rata 1.05m #N/A


Nok Stel rata 1.100 #N/A #N/A #N/A
B38 Paku Skrup 6.000 bj 1,300.00 7,800.00

733291305.xlsx ANALISA 37 /37


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

U01 Pekerja/Kenek 0.084 O/h 180,000.00 15,120.00


U04 Tukang Kayu 0.125 O/h 250,000.00 31,250.00
U14 Kepala Tukang 0.013 O/h 280,000.00 3,640.00
U15 Mandor/Pengawas 0.004 O/h 300,000.00 1,200.00
JUMLAH : #N/A

36 1m² Pasang Atap Genteng Beton #N/A


Genteng Beton 11.000 #N/A #N/A #N/A
B32 Paku Biasa 0.030 Kg 30,000.00 900.00
U01 Pekerja/Kenek 0.200 O/h 180,000.00 36,000.00
U04 Tukang Kayu 0.100 O/h 250,000.00 25,000.00
U14 Kepala Tukang 0.010 O/h 280,000.00 2,800.00
U15 Mandor/Pengawas 0.010 O/h 300,000.00 3,000.00
JUMLAH : #N/A

37 1m² Pasang Atap Genteng Aspal #N/A


B129 Genteng Aspal 6.900 -
B12 Plywood 4 mm 0.350 Lembar - -
B32 Paku Biasa 0.030 Kg 30,000.00 900.00
Plastic Aerator 0.500 #N/A #N/A #N/A
U01 Pekerja/Kenek 0.200 O/h 180,000.00 36,000.00
U04 Tukang Kayu 0.300 O/h 250,000.00 75,000.00
U14 Kepala Tukang 0.003 O/h 280,000.00 840.00
U15 Mandor/Pengawas 0.010 O/h 300,000.00 3,000.00
JUMLAH : #N/A

38 1m² Pasang Atap Genteng Metal 70,100.00


B75 Genteng Metal 1.020 Lembar -
B32 Paku Biasa 0.200 Kg 30,000.00 6,000.00
U01 Pekerja/Kenek 0.200 O/h 180,000.00 36,000.00
U04 Tukang Kayu 0.100 O/h 250,000.00 25,000.00
U14 Kepala Tukang 0.010 O/h 280,000.00 2,800.00
U15 Mandor/Pengawas 0.001 O/h 300,000.00 300.00
JUMLAH : 70,100.00

39 1m² Pasang Atap Sirap #N/A


Genteng Sirap 60.000 #N/A #N/A #N/A
B32 Paku Biasa 0.200 Kg 30,000.00 6,000.00
U01 Pekerja/Kenek 0.166 O/h 180,000.00 29,880.00
U04 Tukang Kayu 0.250 O/h 250,000.00 62,500.00
U14 Kepala Tukang 0.025 O/h 280,000.00 7,000.00
U15 Mandor/Pengawas 0.008 O/h 300,000.00 2,400.00
JUMLAH : #N/A

40 1m' Pasang Nok Genteng Beton #N/A


Genteng Beton 3.500 #N/A #N/A #N/A
B32 Paku Biasa 0.050 Kg 30,000.00 1,500.00
Semen abu -abu 10.800 #N/A #N/A #N/A
Pasir Pasang 0.032 #N/A #N/A #N/A
Semen Warna 1.000 #N/A #N/A #N/A
U01 Pekerja/Kenek 0.400 O/h 180,000.00 72,000.00

733291305.xlsx ANALISA 38 /38


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

U04 Tukang Kayu 0.200 O/h 250,000.00 50,000.00


U14 Kepala Tukang 0.020 O/h 280,000.00 5,600.00
U15 Mandor/Pengawas 0.020 O/h 300,000.00 6,000.00
JUMLAH : #N/A

42 1m' Pasang Nok Genteng Aspal #N/A


B129 Genteng Aspal 2.000 -
B32 Paku Biasa 0.050 Kg 30,000.00 1,500.00
Kayu kelas I (balok) 0.004 #N/A #N/A #N/A
U01 Pekerja/Kenek 0.125 O/h 180,000.00 22,500.00
U04 Tukang Kayu 0.250 O/h 250,000.00 62,500.00
U14 Kepala Tukang 0.025 O/h 280,000.00 7,000.00
U15 Mandor/Pengawas 0.006 O/h 300,000.00 1,800.00
JUMLAH : #N/A

42 1m' Pasang Nok Genteng Metal #N/A


Genteng Decra Bond 1.100 #N/A #N/A #N/A
B32 Paku Biasa 0.050 Kg 30,000.00 1,500.00
U01 Pekerja/Kenek 0.250 O/h 180,000.00 45,000.00
U04 Tukang Kayu 0.150 O/h 250,000.00 37,500.00
U14 Kepala Tukang 0.015 O/h 280,000.00 4,200.00
U15 Mandor/Pengawas 0.013 O/h 300,000.00 3,900.00
JUMLAH : #N/A

43 1m' Pasang Nok Genteng Metal #N/A


Genteng Decra Bond 1.100 #N/A #N/A #N/A
B32 Paku Biasa 0.050 Kg 30,000.00 1,500.00
U01 Pekerja/Kenek 0.250 O/h 180,000.00 45,000.00
U04 Tukang Kayu 0.150 O/h 250,000.00 37,500.00
U14 Kepala Tukang 0.015 O/h 280,000.00 4,200.00
U15 Mandor/Pengawas 0.013 O/h 300,000.00 3,900.00
JUMLAH : #N/A

44 1m' Pasang Nok Sirap #N/A


Seng Plat 3" x 6" BJLS 28 0.400 #N/A #N/A #N/A
B32 Paku Biasa 0.060 Kg 30,000.00 1,800.00
B29 Paku 0.050 Kg 30,000.00 1,500.00
Papan Kayu Borneo tebal 3cm 0.004 #N/A #N/A #N/A
U01 Pekerja/Kenek 0.125 O/h 180,000.00 22,500.00
U04 Tukang Kayu 0.250 O/h 250,000.00 62,500.00
U14 Kepala Tukang 0.025 O/h 280,000.00 7,000.00
U15 Mandor/Pengawas 0.006 O/h 300,000.00 1,800.00
JUMLAH : #N/A

45 1m² Pasang Atap Seng Gelombang #N/A


Seng Gelombang 3" x 6" BJLS 28 0.700 #N/A #N/A #N/A
B32 Paku Biasa 0.020 Kg 30,000.00 600.00
U01 Pekerja/Kenek 0.120 O/h 180,000.00 21,600.00
U04 Tukang Kayu 0.060 O/h 250,000.00 15,000.00
U14 Kepala Tukang 0.006 O/h 280,000.00 1,680.00
U15 Mandor/Pengawas 0.006 O/h 300,000.00 1,800.00

733291305.xlsx ANALISA 39 /39


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

JUMLAH : #N/A

46 1m² Pasang Atap Nok Seng #N/A


Seng Plat 3" x 6" BJLS 28 0.300 #N/A #N/A #N/A
B32 Paku Biasa 0.040 Kg 30,000.00 1,200.00
U01 Pekerja/Kenek 0.015 O/h 180,000.00 2,700.00
U04 Tukang Kayu 0.070 O/h 250,000.00 17,500.00
U14 Kepala Tukang 0.008 O/h 280,000.00 2,240.00
U15 Mandor/Pengawas 0.006 O/h 300,000.00 1,800.00
JUMLAH : #N/A

47 1m² Pasang Atap Alluminium #N/A


Atap Alluminium Gelombang tebal 0.55 1.050 #N/A #N/A #N/A
B39 Paku Hak Panjang 15 cm 0.020 Kg 2,600.00 52.00
U01 Pekerja/Kenek 0.015 O/h 180,000.00 2,700.00
U04 Tukang Kayu 0.075 O/h 250,000.00 18,750.00
U14 Kepala Tukang 0.008 O/h 280,000.00 2,240.00
U15 Mandor/Pengawas 0.006 O/h 300,000.00 1,800.00
JUMLAH : #N/A

48 1m² Pasang Nok Alluminium #N/A


Nok standar 40 cm 18, swg 22 1.200 #N/A #N/A #N/A
B39 Paku Hak Panjang 15 cm 0.040 Kg 2,600.00 104.00
U01 Pekerja/Kenek 0.100 O/h 180,000.00 18,000.00
U04 Tukang Kayu 1.000 O/h 250,000.00 250,000.00
U14 Kepala Tukang 0.010 O/h 280,000.00 2,800.00
U15 Mandor/Pengawas 0.010 O/h 300,000.00 3,000.00
JUMLAH : #N/A

49 1m² Pasang Alluminium Foil / Sisalation 60,100.00


B54 Alumunium foil Double Sided 1.050 m2 16,000.00 16,800.00
U01 Pekerja/Kenek 0.150 O/h 180,000.00 27,000.00
U04 Tukang Kayu 0.050 O/h 250,000.00 12,500.00
U14 Kepala Tukang 0.005 O/h 280,000.00 1,400.00
U15 Mandor/Pengawas 0.008 O/h 300,000.00 2,400.00
JUMLAH : 60,100.00

50 1 M2 Pekerjaan Multipleks 12 Mm Pelapis Atap #N/A


B16 Plywood 12 mm 0.336 Lembar -
B34 Paku Plywood 0.020 Kg 30,000.00 600.00
B32 Paku Biasa 0.200 Kg 30,000.00 6,000.00
Sekrup Sekrup 10.000 #N/A #N/A #N/A
Vinil J Channel 0.125 #N/A #N/A #N/A
U01 Pekerja/Kenek 0.100 O/h 180,000.00 18,000.00
U03 Tukang 0.050 O/h 250,000.00 12,500.00
U14 Kepala Tukang 0.005 O/h 280,000.00 1,400.00
U15 Mandor/Pengawas 0.005 O/h 300,000.00 1,500.00
A38 Alat Bantu 1.000 ls 1,000.00 1,000.00
JUMLAH : #N/A

51 1 M2 Pekerjaan Multipleks 9 Mm Pelapis Atap #N/A

733291305.xlsx ANALISA 40 /40


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

B15 Plywood 9 mm 0.336 Lembar 235,000.00 78,960.00


B34 Paku Plywood 0.020 Kg 30,000.00 600.00
B32 Paku Biasa 0.200 Kg 30,000.00 6,000.00
Sekrup Sekrup 10.000 #N/A #N/A #N/A
Vinil J Channel 0.125 #N/A #N/A #N/A
A38 Alat Bantu 1.000 ls 1,000.00 1,000.00
U01 Pekerja/Kenek 0.100 O/h 180,000.00 18,000.00
U03 Tukang 0.050 O/h 250,000.00 12,500.00
U14 Kepala Tukang 0.005 O/h 280,000.00 1,400.00
U15 Mandor/Pengawas 0.005 O/h 300,000.00 1,500.00
JUMLAH : #N/A

52 I M2 Pasang Atap Genteng Shingles (Owens) 84,550.00


B55 Genteng Aspal Shingles Owen 0.367 m2 -
A38 Alat Bantu 1.000 ls 1,500.00 1,500.00
U01 Pekerja/Kenek 0.150 O/h 180,000.00 27,000.00
U04 Tukang Kayu 0.200 O/h 250,000.00 50,000.00
U14 Kepala Tukang 0.020 O/h 280,000.00 5,600.00
U15 Mandor/Pengawas 0.002 O/h 300,000.00 450.00
JUMLAH : 84,550.00

107 1 M2 Pasang Atap Alumunium (Spandek/Super Dek) 312,002.50


B72 Atap Span Deck (type lebar 80 cm) 0.313 Lembar 285,000.00 89,062.50
B35 Paku Atap 0.020 Kg 220,000.00 4,400.00
U01 Pekerja/Kenek 0.150 O/h 180,000.00 27,000.00
U03 Tukang 0.750 O/h 250,000.00 187,500.00
U14 Kepala Tukang 0.008 O/h 280,000.00 2,240.00
U15 Mandor/Pengawas 0.006 O/h 300,000.00 1,800.00
JUMLAH : 312,002.50

1 1 M2 Pemasangan Atap Zincalumn 138,904.50


B72 Atap Span Deck (type lebar 80 cm) 0.313 Lembar 285,000.00 89,062.50
B39 Paku hak panjang 15 cm 0.020 Kg 2,600.00 52.00
U01 Pekerja/Kenek 0.150 O/h 180,000.00 27,000.00
U03 Tukang 0.075 O/h 250,000.00 18,750.00
U14 Kepala Tukang 0.008 O/h 280,000.00 2,240.00
U15 Mandor/Pengawas 0.006 O/h 300,000.00 1,800.00
JUMLAH : 138,904.50

108 1 M' Pasang Nok Atap Alumunium (Spandek/Super Dek 336,600.00


B73 Nok Atap 1.200 m 45,000.00 54,000.00
B35 Paku Atap 0.040 Kg 220,000.00 8,800.00
U01 Pekerja/Kenek 0.100 O/h 180,000.00 18,000.00
U03 Tukang 1.000 O/h 250,000.00 250,000.00
U14 Kepala Tukang 0.010 O/h 280,000.00 2,800.00
U15 Mandor/Pengawas 0.010 O/h 300,000.00 3,000.00
JUMLAH : 336,600.00

109 1 M2 Pemasangan Alumunium Foil Double Sided 60,100.00


B54 Alumunium foil Double Sided 1.050 m2 16,000.00 16,800.00
U01 Pekerja/Kenek 0.150 O/h 180,000.00 27,000.00
U03 Tukang 0.050 O/h 250,000.00 12,500.00
U14 Kepala Tukang 0.005 O/h 280,000.00 1,400.00
U15 Mandor/Pengawas 0.008 O/h 300,000.00 2,400.00
JUMLAH : 60,100.00

733291305.xlsx ANALISA 41 /41


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

110 1 M2 Pekerjaan Glass Wool + Kawat Ram (□ 3 X 3 Cm) 128,350.00


B52 Glasswool Tebal 25mm 1.050 m2 16,000.00 16,800.00
B53 Wiremesh Ø 2 mm (□ 3 x 3 cm) 1.050 m2 65,000.00 68,250.00
U01 Pekerja/Kenek 0.150 O/h 180,000.00 27,000.00
U03 Tukang 0.050 O/h 250,000.00 12,500.00
U14 Kepala Tukang 0.005 O/h 280,000.00 1,400.00
U15 Mandor/Pengawas 0.008 O/h 300,000.00 2,400.00
JUMLAH : 128,350.00

54 1m' Pasang Flasing 161,300.00


B60 Flashing 1.100 m 60,000.00 66,000.00
B58 Membrane Aspal 0.400 m2 -
A38 Alat Bantu 1.000 ls 1,500.00 1,500.00
U01 Pekerja/Kenek 0.125 O/h 180,000.00 22,500.00
U04 Tukang Kayu 0.250 O/h 250,000.00 62,500.00
U14 Kepala Tukang 0.025 O/h 280,000.00 7,000.00
U15 Mandor/Pengawas 0.006 O/h 300,000.00 1,800.00
JUMLAH : 161,300.00

XI PEKERJAAN BESI
106 10 Cm Pengelasan Dengan Las Listrik 95,650.00
B08 Kawat Las Listrik 0.350 Kg 225,000.00 78,750.00
B378 Solar 0.300 Ltr 5,800.00 1,740.00
B379 Minyak Pelumas 0.040 Lter 45,000.00 1,800.00
U01 Pekerja/Kenek 0.040 O/h 180,000.00 7,200.00
U11 Tukang Las 0.020 O/h 250,000.00 5,000.00
U14 Kepala Tukang 0.002 O/h 280,000.00 560.00
U15 Mandor/Pengawas 0.002 O/h 300,000.00 600.00
A34 Peralatan Las 0.167 jam -
JUMLAH : 95,650.00
Untuk 1 cm 9,565.00

111 1 Kg Rangka Baja 28,380.00


B41 Besi Baja IWF X Pabrikasi 1.150 Kg -
U01 Pekerja/Kenek 0.060 O/h 180,000.00 10,800.00
U03 Tukang 0.060 O/h 250,000.00 15,000.00
U14 Kepala Tukang 0.006 O/h 280,000.00 1,680.00
U15 Mandor/Pengawas 0.003 O/h 300,000.00 900.00
JUMLAH : 28,380.00

112 1 Kg Pekerjaan Gording Canal 28,380.00


B42 Gording Canal 1.150 Kg -
U01 Pekerja/Kenek 0.060 O/h 180,000.00 10,800.00
U03 Tukang 0.060 O/h 250,000.00 15,000.00
U14 Kepala Tukang 0.006 O/h 280,000.00 1,680.00
U15 Mandor/Pengawas 0.003 O/h 300,000.00 900.00
JUMLAH : 28,380.00

113 100 Kg Pekerjaan Perakitan Kuda-Kuda Baja 67,080.00


B378 Solar 1.000 Ltr 5,800.00 5,800.00
B379 Minyak Pelumas 0.100 Lter 45,000.00 4,500.00
U01 Pekerja/Kenek 0.100 O/h 180,000.00 18,000.00
U03 Tukang 0.100 O/h 250,000.00 25,000.00
U14 Kepala Tukang 0.001 O/h 280,000.00 280.00
U15 Mandor/Pengawas 0.005 O/h 300,000.00 1,500.00
Sewa Alat 0.800 Jam 15,000.00 12,000.00
JUMLAH : 67,080.00
733291305.xlsx ANALISA 42 /42
HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

Untuk 1 Kg 670.80

107 1 Kg Pekerjaan Erection Konstruksi Baja 13,455.02


B378 Solar 0.125 Ltr 5,800.00 725.00
B379 Minyak Pelumas 0.013 Lter 45,000.00 600.00
U01 Pekerja/Kenek 0.015 O/h 180,000.00 2,769.23
U03 Tukang 0.013 O/h 250,000.00 3,125.00
U14 Kepala Tukang 0.012 O/h 280,000.00 3,294.12
U15 Mandor/Pengawas 0.001 O/h 300,000.00 166.67
Sewa Alat 0.004 Jam 750,000.00 2,775.00
JUMLAH : Jumlah 13,455.02

108 1 Kg Pekerjaan Kuda-Kuda Baja 41,835.02


Besi Baja x Pabrikasi 1.000 Kg 28,380.00 28,380.00
Pemasangan/erction 1.000 Kg 13,455.02 13,455.02
JUMLAH : 41,835.02

109 1 Kg Pekerjaan Pabrikasi Baja (Site) #VALUE!


Besi Baja Ub x Pabrikasi 1.000 kg 28,380.00 28,380.00
B08 Kawat Las Listrik 0.005 Dus Kg #VALUE!
LPG 15 Kg 0.004 Btl 260,000.00 975.00
ACETELIn 0.003 Btl 500,000.00 1,562.50
Mata Gurinda 0.038 Bh 20,000.00 750.00
Cat Baja 0.006 m2 68,416.60 427.60
U01 Pekerja/Kenek 0.018 o/h O/h #VALUE!
U11 Tukang Las 0.018 o/h O/h #VALUE!
U14 Kepala Tukang 0.003 o/h O/h #VALUE!
U15 Mandor/Pengawas 0.001 o/h O/h #VALUE!
alat 0.053 Jam 35,714.29 1,875.00
Pemasangan/erction 1.000 kg 13,455.02 13,455.02
JUMLAH : #VALUE!

110 1 k Pekerjaan Skur Dobel Profil L 60.60.6 91,859.78


B220 Profil L 60.60.6 1.050 Kg - -
Pengelasan 8.197 cm 9,565.00 78,404.76
Pemasangan/erction 1.000 kg 13,455.02 13,455.02
JUMLAH : 91,859.78

111 1m Pekerjaan Tangga Besi Siku L 50 50.5 (Type 1) 533,808.28


Profil L 50 50.5 0.458 Btg 250,000.00 114,583.33
Besi Srip 4 cm 0.638 Btg 95,000.00 60,562.50
Besi Beton Ø12 mm 1.953 kg 33,731.00 65,879.07
Pengelasan 20.000 cm 9,565.00 191,300.00
Pengecatan 0.500 m2 68,416.60 34,208.30
Pemasangan/erction 1.000 m 67,275.08 67,275.08
JUMLAH : 533,808.28

112 1m Pekerjaan Tangga Besi Kotak 40x40 x2,3mm (Type 2) 1,886,415.95


Besi Kotak 40x40 x2,3mm 4.200 m 132,000.00 554,400.00
Besi Kotak 40x20 x 1,2mm 10.500 m 86,000.00 903,000.00
Pengelasan 24.000 cm 9,565.00 229,560.00
Pengecatan 1.932 m2 68,416.60 132,180.87
Pemasangan/erction 1.000 m 67,275.08 67,275.08
JUMLAH : 1,886,415.95

113 1m Pekerjaan Tangga Pipa Giv 2" (Type 3) 594,958.38


Pipa Giv 2 Inc 2.800 m 125,000.00 350,000.00
Pengelasan 15.000 cm 9,565.00 143,475.00
Pengecatan 0.500 m2 68,416.60 34,208.30

733291305.xlsx ANALISA 43 /43


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

Pemasangan/erction 1.000 m 67,275.08 67,275.08


JUMLAH : 594,958.38

114 1m Pekerjaan Tangga Pipa Giv 1,5" (Type 4) 453,291.71


Pipa Giv 1,5 Inc 2.500 m 83,333.33 208,333.33
Pengelasan 15.000 cm 9,565.00 143,475.00
Pengecatan 0.500 m2 68,416.60 34,208.30
Pemasangan/erction 1.000 m 67,275.08 67,275.08
JUMLAH : 453,291.71

115 1 M2 Pasang Pintu Besi Baja 1,157,300.00


B74 Pintu Besi Baja 1.000 m2 850,000.00 850,000.00
U06 Tukang Besi 0.650 O/h 250,000.00 162,500.00
U01 Pekerja/Kenek 0.650 O/h 180,000.00 117,000.00
U14 Kepala Tukang 0.065 O/h 280,000.00 18,200.00
U15 Mandor/Pengawas 0.032 O/h 300,000.00 9,600.00
JUMLAH : 1,157,300.00

116 1 m2 Membuat pintu besi plat baja tebal 2 mm rangkap, rangka baja siku 2,153,266.52
B312 Profil L 15.000 Kg 45,000.00 675,000.00
B221 Besi Plat 2 mm 32.800 kg 25,000.00 820,000.00
B08 Kawat Las Listrik 0.050 Kg 225,000.00 11,250.00
Pengecatan 2.200 m2 68,416.60 150,516.52
U11 Tukang las 1.050 O/h 250,000.00 262,500.00
U14 Kepala Tukang 0.105 O/h 280,000.00 29,400.00
U01 Pekerja/Kenek 1.050 O/h 180,000.00 189,000.00
U15 Mandor/Pengawas 0.052 O/h 300,000.00 15,600.00
2,153,266.52

117 1 m2 Membuat pintu besi plat baja tebal 2 mm 1 Layer, rangka baja siku 1,743,266.52
B312 Profil L 15.000 Kg 45,000.00 675,000.00
B221 Besi Plat 2 mm 16.400 kg 25,000.00 410,000.00
B08 Kawat Las Listrik 0.050 Kg 225,000.00 11,250.00
Pengecatan 2.200 m2 68,416.60 150,516.52
U11 Tukang las 1.050 O/h 250,000.00 262,500.00
U14 Kepala Tukang 0.105 O/h 280,000.00 29,400.00
U01 Pekerja/Kenek 1.050 O/h 180,000.00 189,000.00
U15 Mandor/Pengawas 0.052 O/h 300,000.00 15,600.00
1,743,266.52

14 1 m Pekerjaan Bending Pipa 3-SCH 40 Untuk Kuda-kuda bulat (Dom) 475,140.49


B200 Pipa Ø3" -SCH 40 1.025 M -
Pengelasan 27.000 cm 9,565.00 258,255.00
B379 Minyak Pelumas 0.050 Lter 45,000.00 2,250.00
U01 Pekerja/Kenek 0.036 O/h 180,000.00 6,428.57
U03 Tukang 0.007 O/h 250,000.00 1,785.71
U14 Kepala Tukang 0.001 O/h 280,000.00 400.00
U15 Mandor/Pengawas 0.001 O/h 300,000.00 428.57
A37 Sewa Alat Bending Pipa 0.250 jam -
Pemasangan/erction 15.280 kg 13,455.02 205,592.63
JUMLAH : 475,140.49

15 1 m Pekerjaan Bending Pipa 4-SCH 40 Untuk Kuda-kuda bulat (Dom) 359,397.14


B204 Pipa Ø4" -SCH 40 1.025 M -
Pengelasan 36.000 cm 9,565.00 344,340.00
B379 Minyak Pelumas 0.067 Lter 45,000.00 3,000.00
U01 Pekerja/Kenek 0.048 O/h 180,000.00 8,571.43
U03 Tukang 0.010 O/h 250,000.00 2,380.95
U14 Kepala Tukang 0.002 O/h 280,000.00 533.33

733291305.xlsx ANALISA 44 /44


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

U15 Mandor/Pengawas 0.002 O/h 300,000.00 571.43


A37 Sewa Alat Bending Pipa 0.333 jam -
Pemasangan/erction kg 13,455.02 -
JUMLAH : 359,397.14

16 1 m Pekerjaan Bending Pipa 3-SCH 80 Untuk Kuda-kuda bulat (Dom) 476,432.32


B208 Pipa Ø3" -SCH 80 1.025 M -
Pengelasan 27.000 cm 9,565.00 258,255.00
B379 Minyak Pelumas 0.050 Lter 45,000.00 2,250.00
U01 Pekerja/Kenek 0.041 O/h 180,000.00 7,346.94
U03 Tukang 0.008 O/h 250,000.00 2,040.82
U14 Kepala Tukang 0.002 O/h 280,000.00 457.14
U15 Mandor/Pengawas 0.002 O/h 300,000.00 489.80
A37 Sewa Alat Bending Pipa 0.250 jam -
Pemasangan/erction 15.280 kg 13,455.02 205,592.63
JUMLAH : 476,432.32

17 1 m Pekerjaan Bending Pipa 4-SCH 80 Untuk Kuda-kuda bulat (Dom) 661,556.54


B210 Pipa Ø4" -SCH 80 1.025 M -
Pengelasan 36.000 cm 9,565.00 344,340.00
B379 Minyak Pelumas 0.067 Lter 45,000.00 3,000.00
U01 Pekerja/Kenek 0.048 O/h 180,000.00 8,571.43
U03 Tukang 0.011 O/h 250,000.00 2,721.09
U14 Kepala Tukang 0.002 O/h 280,000.00 609.52
U15 Mandor/Pengawas 0.002 O/h 300,000.00 653.06
A37 Sewa Alat Bending Pipa 0.333 jam -
Pemasangan/erction 22.420 kg 13,455.02 301,661.44
JUMLAH : 661,556.54

18 1 m Pekerjaan Bending Pipa Hollow 4x4x2,3 kaso (Dom) 6,222.04


B379 Minyak Pelumas 0.027 Lter 45,000.00 1,200.00
U01 Pekerja/Kenek 0.019 O/h 180,000.00 3,428.57
U03 Tukang 0.004 O/h 250,000.00 1,088.44
U14 Kepala Tukang 0.001 O/h 280,000.00 243.81
U15 Mandor/Pengawas 0.001 O/h 300,000.00 261.22
A37 Sewa Alat Bending Pipa 0.133 jam -
JUMLAH : 6,222.04

19 1 m Pekerjaan Railing Pengaman Type 1 1,311,650.00


B215 Pipa Kotak 4x4x1,2 ( Hollow) 4.000 M 132,000.00 528,000.00
B216 Pipa Kotak 4x2x1,0 ( Hollow) 8.000 m 86,000.00 688,000.00
Pengelasan 10.000 CM 9,565.00 95,650.00
Pemasangan/erction kg 13,455.02 -
JUMLAH : 1,311,650.00

19 1 Unit Pekerjaan Pemasangan Kuda Kuda Pipa Type K2. 54,609,040.06


B209 Pipa Ø3" -SCH 80 diroll 647.108 Kg -
B211 Pipa Ø4" -SCH 80 diroll 1,185.453 Kg - -
B212 Pipa Ø6" -SCH 80 (41,83 kg/m) 5.456 M -
B220 Profil L 60.60.6 646.985 Kg -
Plat Buhul 10mm 95.700 kg - -
Plat skur sambunga 10mm 59.400 kg - -
Plat sambunga 16mm 351.648 kg - -
Plat gording 8 mm 20.735 kg - -
Mur Baut 19 mm 288.000 Ps - -
Pengelasan 753.121 CM 9,565.00 7,203,605.75
Pemasangan/erction 3,523.254 kg 13,455.02 47,405,434.31
JUMLAH : 54,609,040.06

733291305.xlsx ANALISA 45 /45


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

19 1 Unit Pekerjaan Pemasangan Kuda Kuda Pipa Type K3. 54,093,436.22


B209 Pipa Ø3" -SCH 80 diroll 652.487 Kg -
B211 Pipa Ø4" -SCH 80 diroll 1,208.438 Kg - -
B212 Pipa Ø6" -SCH 80 (41,83 kg/m) 5.456 M -
B220 Profil L 60.60.6 659.202 Kg -
Plat Buhul 10mm 99.000 kg - -
Plat skur sambunga 10mm 52.800 kg - -
Plat sambunga 16mm 312.576 kg - -
Plat gording 8 mm 17.160 kg - -
Mur Baut 19 mm 256.000 Ps - -
Pengelasan 751.780 CM 9,565.00 7,190,772.45
Pemasangan/erction 3,485.887 kg 13,455.02 46,902,663.78
JUMLAH : 54,093,436.22

19 1 Unit Pekerjaan Pemasangan Kuda Kuda Pipa Type K4. 43,629,572.37


B209 Pipa Ø3" -SCH 80 diroll 463.733 Kg -
B211 Pipa Ø4" -SCH 80 diroll 908.006 Kg - -
B212 Pipa Ø6" -SCH 80 (41,83 kg/m) 5.456 M -
B220 Profil L 60.60.6 430.326 Kg -
Plat Buhul 10mm 59.400 kg - -
Plat skur sambunga 10mm 39.600 kg - -
Plat sambunga 16mm 468.864 kg - -
Plat gording 8 mm 25.740 kg - -
Mur Baut 19 mm 192.000 Ps - -
Pengelasan 600.281 CM 9,565.00 5,741,689.09
Pemasangan/erction 2,815.893 kg 13,455.02 37,887,883.27
JUMLAH : 43,629,572.37

19 1 Unit Pekerjaan Pemasangan Kuda Kuda Pipa Type K5. 48,176,254.22


B209 Pipa Ø3" -SCH 80 diroll 453.816 Kg -
B211 Pipa Ø4" -SCH 80 diroll 1,743.603 Kg - -
B212 Pipa Ø6" -SCH 80 (41,83 kg/m) - M -
B220 Profil L 60.60.6 410.755 Kg -
Plat Buhul 10mm 71.775 kg - -
Plat skur sambunga 10mm 46.200 kg - -
Plat sambunga 16mm 136.752 kg - -
Plat gording 8 mm 14.300 kg - -
Mur Baut 19 mm 192.000 Ps - -
Pengelasan 719.300 CM 9,565.00 6,880,107.13
Pemasangan/erction 3,069.201 kg 13,455.02 41,296,147.09
JUMLAH : 48,176,254.22

19 1 Unit Pekerjaan Pemasangan Kuda Kuda Pipa Type Kb1. 31,360,672.17


B209 Pipa Ø3" -SCH 80 diroll 591.642 Kg -
B211 Pipa Ø4" -SCH 80 diroll 605.699 Kg - -
B212 Pipa Ø6" -SCH 80 (41,83 kg/m) - M -
B220 Profil L 60.60.6 410.755 Kg -
Plat Buhul 10mm 96.525 kg - -
Plat skur sambunga 10mm 39.600 kg - -
Plat sambunga 16mm 117.216 kg - -
Plat gording 8 mm 15.730 kg - -
Mur Baut 19 mm 120.000 Ps - -
Pengelasan 469.292 CM 9,565.00 4,488,773.25
Pemasangan/erction 1,997.166 kg 13,455.02 26,871,898.92
JUMLAH : 31,360,672.17

19 1 Unit Pekerjaan Pemasangan Kuda Kuda Pipa Type Kb2. 24,590,781.57


B209 Pipa Ø3" -SCH 80 diroll 356.330 Kg -
B211 Pipa Ø4" -SCH 80 diroll 447.862 Kg - -

733291305.xlsx ANALISA 46 /46


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

B212 Pipa Ø6" -SCH 80 (41,83 kg/m) - M -


B220 Profil L 60.60.6 360.517 Kg -
Plat Buhul 10mm 99.000 kg - -
Plat skur sambunga 10mm 39.600 kg - -
Plat sambunga 16mm 156.288 kg - -
Plat gording 8 mm 10.725 kg - -
Mur Baut 19 mm 96.000 Ps - -
Pengelasan 367.580 CM 9,565.00 3,515,905.67
Pemasangan/erction 1,566.321 kg 13,455.02 21,074,875.91
JUMLAH : 24,590,781.57

19 1 Unit Pekerjaan Pemasangan Kuda Kuda Pipa Type Kb2a. 18,126,849.82


B209 Pipa Ø3" -SCH 80 diroll 169.593 Kg -
B211 Pipa Ø4" -SCH 80 diroll 292.985 Kg - -
B212 Pipa Ø6" -SCH 80 (41,83 kg/m) - M -
B220 Profil L 60.60.6 296.691 Kg -
Plat Buhul 10mm 96.525 kg - -
Plat skur sambunga 10mm 39.600 kg - -
Plat sambunga 16mm 156.288 kg - -
Plat gording 8 mm 10.725 kg - -
Mur Baut 19 mm 96.000 Ps - -
Pengelasan 265.602 CM 9,565.00 2,540,478.54
Pemasangan/erction 1,158.406 kg 13,455.02 15,586,371.28
JUMLAH : 18,126,849.82

19 1 Unit Pekerjaan Pemasangan Kuda Kuda Pipa Type Kb3. 10,466,129.84


B209 Pipa Ø3" -SCH 80 diroll 103.369 Kg -
B211 Pipa Ø4" -SCH 80 diroll 151.671 Kg - -
B212 Pipa Ø6" -SCH 80 (41,83 kg/m) - M -
B220 Profil L 60.60.6 115.684 Kg -
Plat Buhul 10mm 47.850 kg - -
Plat skur sambunga 10mm 39.600 kg - -
Plat sambunga 16mm 117.216 kg - -
Plat gording 8 mm 3.575 kg - -
Mur Baut 19 mm 96.000 Ps - -
Pengelasan 144.741 CM 9,565.00 1,384,452.40
Pemasangan/erction 674.966 kg 13,455.02 9,081,677.44
JUMLAH : 10,466,129.84

19 1 Unit Pekerjaan Pemasangan Kuda Kuda Pipa Type Kb4. 12,462,317.80


B209 Pipa Ø3" -SCH 80 diroll 148.751 Kg -
B211 Pipa Ø4" -SCH 80 diroll 151.671 Kg - -
B212 Pipa Ø6" -SCH 80 (41,83 kg/m) - M -
B220 Profil L 60.60.6 313.271 Kg -
Plat Buhul 10mm 74.250 kg - -
Plat skur sambunga 10mm 26.400 kg - -
Plat sambunga 16mm 78.144 kg - -
Plat gording 8 mm 3.575 kg - -
Mur Baut 19 mm 96.000 Ps - -
Pengelasan 183.094 CM 9,565.00 1,751,295.89
Pemasangan/erction 796.062 kg 13,455.02 10,711,021.91
JUMLAH : 12,462,317.80

19 1 Unit Pekerjaan Pemasangan Kuda Kuda Pipa Type Kb4a. 16,019,471.52


B209 Pipa Ø3" -SCH 80 diroll 168.920 Kg -
B211 Pipa Ø4" -SCH 80 diroll 276.214 Kg - -
B212 Pipa Ø6" -SCH 80 (41,83 kg/m) - M -
B220 Profil L 60.60.6 313.271 Kg -
Plat Buhul 10mm 74.250 kg - -

733291305.xlsx ANALISA 47 /47


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

Plat skur sambunga 10mm 26.400 kg - -


Plat sambunga 16mm 78.144 kg - -
Plat gording 8 mm 3.575 kg - -
Mur Baut 19 mm 96.000 Ps - -
Pengelasan 216.378 CM 9,565.00 2,069,656.60
Pemasangan/erction 1,036.774 kg 13,455.02 13,949,814.92
JUMLAH : 16,019,471.52

19 1 Unit Pekerjaan Pemasangan Kuda Kuda Pipa Type Kb5. 45,042,482.76


B209 Pipa Ø3" -SCH 80 diroll 453.816 Kg -
B211 Pipa Ø4" -SCH 80 diroll 1,743.603 Kg - -
B212 Pipa Ø6" -SCH 80 (41,83 kg/m) - M -
B220 Profil L 60.60.6 410.755 Kg -
Plat Buhul 10mm 71.775 kg - -
Plat skur sambunga 10mm 46.200 kg - -
Plat sambunga 16mm 136.752 kg - -
Plat gording 8 mm 14.300 kg - -
Mur Baut 19 mm 96.000 Ps - -
Pengelasan 661.756 CM 9,565.00 6,329,698.56
Pemasangan/erction 2,877.201 kg 13,455.02 38,712,784.20
JUMLAH : 45,042,482.76

13 1 m Pekerjaan Pemasangan Pipa 2 1/2-SCH 40 Untuk Gording 139,880.41


B199 Pipa Ø2½" -SCH 4 diroll 7.470 Kg -
Pengelasan 2.540 cm 9,565.00 24,295.10
Pemasangan/erction 7.470 kg 15,473.27 115,585.31
JUMLAH : 139,880.41

24 1 m Pekerjaan Pipa Hollow 4x4x2,3 kaso (Dom) #N/A


Pipa Kotak 4x4x2,3 ( Hollow) 1.000 #N/A #N/A #N/A
Pengelasan 7.200 cm 9,565.00 68,868.00
Bending 1.000 m 6,222.04 6,222.04
Pemasangan/erction 2.767 kg 13,455.02 37,225.54
JUMLAH : #N/A

25 1 m Pekerjaan Pipa Ø6" -SCH 80 Untuk Kuda-kuda bulat (Dom) 1,075,203.28


Pipa Ø6" -SCH 80 1.025 m - -
Pengelasan 52.000 cm 9,565.00 497,380.00
Peralatan 1.000 Ls 15,000.00 15,000.00
Pemasangan/erction 41.830 kg 13,455.02 562,823.28
JUMLAH : 1,075,203.28

26 1 kg Pekerjaan Pembuatan Plat Buhul 8mm 40,071.43


B222 Besi Plat 8 mm 1.100 kg -
Pengelasan - cm 9,565.00 -
U01 Pekerja/Kenek 0.143 O/h 180,000.00 25,714.29
U03 Tukang 0.036 O/h 250,000.00 8,928.57
U14 Kepala Tukang 0.007 O/h 280,000.00 2,000.00
U15 Mandor/Pengawas 0.001 O/h 300,000.00 428.57
Peralatan Pemotong/boring 1.000 Ls 3,000.00 3,000.00
Pemasangan/erction kg 13,455.02 -
JUMLAH : 40,071.43

27 1 kg Pekerjaan Pembuatan Plat Buhul 10mm 44,150.00


B223 Besi Plat 10 mm 1.100 kg -
Pengelasan - cm 9,565.00 -
U01 Pekerja/Kenek 0.167 O/h 180,000.00 30,000.00
U03 Tukang 0.033 O/h 250,000.00 8,333.33
U14 Kepala Tukang 0.007 O/h 280,000.00 1,866.67

733291305.xlsx ANALISA 48 /48


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

U15 Mandor/Pengawas 0.001 O/h 300,000.00 200.00


Peralatan Pemotong/boring 1.000 Ls 3,750.00 3,750.00
Pemasangan/erction - kg 13,455.02 -
JUMLAH : 44,150.00

28 1 kg Pekerjaan Pembuatan Plat Buhul/Join 12mm 44,900.00


B224 Besi Plat 12 mm 1.100 kg -
Pengelasan - cm 9,565.00 -
U01 Pekerja/Kenek 0.167 O/h 180,000.00 30,000.00
U03 Tukang 0.033 O/h 250,000.00 8,333.33
U14 Kepala Tukang 0.007 O/h 280,000.00 1,866.67
U15 Mandor/Pengawas 0.001 O/h 300,000.00 200.00
Peralatan Pemotong/boring 1.000 Ls 4,500.00 4,500.00
Pemasangan/erction - kg 13,455.02 -
JUMLAH : 44,900.00

29 1 kg Pekerjaan Pembuatan Plat Buhul/Join 16mm 49,218.75


B225 Besi Plat 16 mm 1.100 kg -
Pengelasan - cm 9,565.00 -
U01 Pekerja/Kenek 0.200 O/h 180,000.00 36,000.00
U03 Tukang 0.025 O/h 250,000.00 6,250.00
U14 Kepala Tukang 0.003 O/h 280,000.00 875.00
U15 Mandor/Pengawas 0.000 O/h 300,000.00 93.75
Peralatan Pemotong/boring 1.000 Ls 6,000.00 6,000.00
Pemasangan/erction kg 13,455.02 -
JUMLAH : 49,218.75

30 1 kg Pekerjaan Pembuatan Plat Buhul/Join 20mm 50,718.75


B228 Besi Plat 20 mm 1.100 kg -
Pengelasan - cm 9,565.00 -
U01 Pekerja/Kenek 0.200 O/h 180,000.00 36,000.00
U03 Tukang 0.025 O/h 250,000.00 6,250.00
U14 Kepala Tukang 0.003 O/h 280,000.00 875.00
U15 Mandor/Pengawas 0.000 O/h 300,000.00 93.75
Peralatan Pemotong/boring 1.000 Ls 7,500.00 7,500.00
Pemasangan/erction - kg 13,455.02 -
JUMLAH : 50,718.75

31 1 kg Pekerjaan Pembuatan Plat Buhul/Join 25mm 52,593.75


B230 Besi Plat 25 mm 1.100 kg -
Pengelasan cm 9,565.00 -
U01 Pekerja/Kenek 0.200 O/h 180,000.00 36,000.00
U03 Tukang 0.025 O/h 250,000.00 6,250.00
U14 Kepala Tukang 0.003 O/h 280,000.00 875.00
U15 Mandor/Pengawas 0.000 O/h 300,000.00 93.75
Peralatan Pemotong/boring 1.000 Ls 9,375.00 9,375.00
Pemasangan/erction - kg 13,455.02 -
JUMLAH : 52,593.75

32 1 Bh Pekerjaan Pemasangan Plat gording 8 mm 146,485.44


Plat Buhul 8mm 1.000 bh 40,071.43 40,071.43
Pengelasan 10.000 cm 9,565.00 95,650.00
Pemasangan/erction 0.800 kg 13,455.02 10,764.01
JUMLAH : 146,485.44

33 1 Bh Pekerjaan Pemasangan Plat Joint Balok FB 100 X 12 198,444.69


Plat Buhul 12mm 1.000 bh 79,093.15 79,093.15
Pengelasan 10.000 cm 9,565.00 95,650.00
Pemasangan/erction 1.762 kg 13,455.02 23,701.55

733291305.xlsx ANALISA 49 /49


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

JUMLAH : 198,444.69

34 1 Bh Pekerjaan Pemasangan Plat Joint Balok PL. 12 THK 280,843.71


Plat Buhul 12mm 1.000 bh 142,493.28 142,493.28
Pengelasan 10.000 cm 9,565.00 95,650.00
Pemasangan/erction 3.174 kg 13,455.02 42,700.43
JUMLAH : 280,843.71

35 1 Bh Pekerjaan Pemasangan Plat Joint Balok PL. 16 THK 1,096,017.84


Plat Buhul 16mm 1.000 bh 760,566.99 760,566.99
Pengelasan 13.333 cm 9,565.00 127,533.33
Pemasangan/erction 15.453 kg 13,455.02 207,917.52
JUMLAH : 1,096,017.84

36 1 Bh Pekerjaan Pemasangan Plat Joint Balok PL. 25 THK 2,153,694.91


Plat Buhul 25mm 1.000 bh 1,579,554.38 1,579,554.38
Pengelasan 17.778 cm 9,565.00 170,044.44
Pemasangan/erction 30.033 kg 13,455.02 404,096.08
JUMLAH : 2,153,694.91

37 1 Bh Pekerjaan Pemasangan Plat Buhul/Sabungan 10mm 229,305.70


Plat Buhul 10mm 1.000 bh 44,150.00 44,150.00
Pengelasan 12.500 cm 9,565.00 119,562.50
Pemasangan/erction 4.875 kg 13,455.02 65,593.20
JUMLAH : 229,305.70

38 1 Bh Pekerjaan Pemasangan Plat Buhul 12mm 267,086.84


Plat Buhul 12mm 1.000 bh 44,900.00 44,900.00
Pengelasan 15.000 cm 9,565.00 143,475.00
Pemasangan/erction 5.850 kg 13,455.02 78,711.84
JUMLAH : 267,086.84

39 1 Bh Pekerjaan Pemasangan Plat Join Kuda Kuda 16mm 361,613.89


Plat Buhul 16mm 1.000 bh ### 49,218.75
Pengelasan 20.000 cm 9,565.00 191,300.00
Pemasangan/erction 9.000 kg 13,455.02 121,095.14
JUMLAH : 361,613.89

40 1 Lbr Pekerjaan Pasangan Base Plat PL.20.900.400mm 4,033,093.54


Base Plat PL.20.900.400mm (58,375 kg) 1.000 Bh 2,960,707.03 2,960,707.03
Pengelasan 30.000 cm 9,565.00 286,950.00
Pemasangan/erction 58.375 kg 13,455.02 785,436.51
JUMLAH : 4,033,093.54

41 1 Lbr Pekerjaan Pasangan Base Plat 20 x623x275 mm 1,942,126.36


Base Plat 20 x623x275 mm (25,784 kg) 1.000 Bh 1,356,077.25 1,356,077.25
Pengelasan 25.000 cm 9,565.00 239,125.00
Pemasangan/erction 25.784 kg 13,455.02 346,924.11
JUMLAH : 1,942,126.36

42 1 Btg Anchor Bolt Øm 28 Mm 522,030.09


ANCHOR BOLT Øm 28 MM x100 cm 1.000 Btg 250,000.00 250,000.00
Pengelasan 20.000 cm 9,565.00 191,300.00
Pemasangan/erction 6.000 kg 13,455.02 80,730.09
JUMLAH : 522,030.09

43 1 Btg Anchor Bolt Øm 19 Mm 207,560.03


ANCHOR BOLT Øm 19 MM X60 cm 1.000 Btg 85,000.00 85,000.00
Pengelasan 10.000 cm 9,565.00 95,650.00

733291305.xlsx ANALISA 50 /50


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

Pemasangan/erction 2.000 kg 13,455.02 26,910.03


JUMLAH : 207,560.03

44 1 Bh Pemasangan baut/mur Angkur Geser Øm 19 MM 29,901.50


Baut Øm 19 MM(Owner) - bh 20,000.00 -
Pengelasan 2.500 cm 9,565.00 23,912.50
Pemasangan/erction 0.445 kg 13,455.02 5,989.00
JUMLAH : 29,901.50

46 1 M' Gording Pipa Medium Dia. 1 ½ "


Pipa Gip dia. 1 ½ " 1.050 #N/A #N/A #N/A
U01 Pekerja/Kenek 0.200 O/h 180,000.00 36,000.00
U03 Tukang 0.200 O/h 250,000.00 50,000.00
U14 Kepala Tukang 0.020 O/h 280,000.00 5,600.00
U15 Mandor/Pengawas 0.001 O/h 300,000.00 300.00
Jumlah #N/A

47 1 M2 Pasang Jendela Nako 7 klip & Tralis 472,500.00


B88 Jendela Nako 1.100 Ser -
B32 Paku Biasa 0.020 Kg 30,000.00 600.00
B48 Besi strip tebal 5 mm 4.000 Kg 95,000.00 380,000.00
U01 Pekerja/Kenek 0.200 O/h 180,000.00 36,000.00
U04 Tukang Kayu 0.200 O/h 250,000.00 50,000.00
U14 Kepala Tukang 0.020 O/h 280,000.00 5,600.00
U15 Mandor/Pengawas 0.001 O/h 300,000.00 300.00
JUMLAH : 472,500.00

48 1 M' Pasang Talang Datar, Seng BJLS 30" 253,241.50


B65 Seng Plat bjls 30 0.500 Lembar 135,000.00 67,500.00
B32 Paku Biasa 0.015 Kg 30,000.00 450.00
B116 Kayu Kelas II (Papan) 0.010 M3 3,750,000.00 36,000.00
B339 Meni Besi 0.250 Kg 59,666.00 14,916.50
U01 Pekerja/Kenek 0.150 O/h 180,000.00 27,000.00
U04 Tukang Kayu 0.400 O/h 250,000.00 100,000.00
U14 Kepala Tukang 0.025 O/h 280,000.00 7,000.00
U15 Mandor/Pengawas 0.001 O/h 300,000.00 375.00
JUMLAH : 253,241.50

49 1 M' Pasang Talang Miring, Seng BJLS 30" 271,674.80


B65 Seng Plat bjls 30 0.500 Lembar 135,000.00 67,500.00
B32 Paku Biasa 0.015 Kg 30,000.00 450.00
B116 Kayu Kelas II (Papan) 0.019 M3 3,750,000.00 71,250.00
B339 Meni Besi 0.300 Kg 59,666.00 17,899.80
U01 Pekerja/Kenek 0.040 O/h 180,000.00 7,200.00
U04 Tukang Kayu 0.400 O/h 250,000.00 100,000.00
U14 Kepala Tukang 0.025 O/h 280,000.00 7,000.00
U15 Mandor/Pengawas 0.001 O/h 300,000.00 375.00
JUMLAH : 271,674.80

50 1 M' Pasang Talang 1/2 Lingkaran D - 10 cm, Seng BJLS 30" 259,125.00
B65 Seng Plat bjls 30 0.300 Lembar 135,000.00 40,500.00
B32 Paku Biasa 0.100 Kg 30,000.00 3,000.00
B116 Kayu Kelas II (Papan) 0.019 M3 3,750,000.00 71,250.00
B48 Besi strip tebal 5 mm 0.500 Kg 95,000.00 47,500.00
U01 Pekerja/Kenek 0.150 O/h 180,000.00 27,000.00
U04 Tukang Kayu 0.250 O/h 250,000.00 62,500.00
U14 Kepala Tukang 0.025 O/h 280,000.00 7,000.00
U15 Mandor/Pengawas 0.001 O/h 300,000.00 375.00
JUMLAH : 259,125.00

733291305.xlsx ANALISA 51 /51


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

51 1 M2 Pemasangan Kuda - kuda baja ringan 373,987.68


B43 Baja ringan profil C 75 0.75 1.488 M1 60,000.00 89,280.00
B44 Baut (screw driver) 28.000 bh 1,500.00 42,000.00
B45 Dynabolt 1.600 bh 15,000.00 24,000.00
B46 Reng 45 3.600 M1 30,000.00 108,000.00
B47 Talang jurai 0.124 M1 271,674.80 33,687.68
U01 Pekerja/Kenek 0.200 O/h 180,000.00 36,000.00
U04 Tukang Kayu 0.450 O/h 250,000.00 112,500.00
U14 Kepala Tukang 0.010 O/h 280,000.00 2,800.00
U15 Mandor/Pengawas 0.050 O/h 300,000.00 15,000.00
JUMLAH : 373,987.68

52 1 m2 Pemasangan Covering Aluminium Composite (ACP) 956,260.00


B382 Alumunium Composite 1.100 m2 450,000.00 495,000.00
B383 Hollow Besi Galvanis Uk 4 x 4 x 1 mm 0.800 btg 125,000.00 100,000.00
B384 Braket Siku / spigot / stiffener 0.267 btg 80,000.00 21,360.00
B385 Paku Beton 0.080 kg 150,000.00 12,000.00
B387 Paku Skrup 0.110 doz 350,000.00 38,500.00
B386 Dinabolt 0.100 bh 15,000.00 1,500.00
B388 Sealant/Silicon 0.250 tube 50,000.00 12,500.00
A36 Sewa Schafolding 0.020 set/Hr 50,000.00 1,000.00
Listrik Kerja 1.000 ls 5,000.00 5,000.00
Alat bantu lainnya 1.000 ls 2,500.00 2,500.00
U01 Pekerja/Kenek 0.390 O/h 180,000.00 70,200.00
U11 Tukang Las 0.700 O/h 250,000.00 175,000.00
U14 Kepala Tukang 0.070 O/h 280,000.00 19,600.00
U15 Mandor/Pengawas 0.007 O/h 300,000.00 2,100.00
JUMLAH : 956,260.00

53 1 m2 Pemasangan Covering GRC Kalsiboard eksterior 6 mm 633,510.00


B389 Kalsiboard eksterior 6 mm 1.100 m2 150,000.00 165,000.00
B383 Hollow Besi Galvanis Uk 4 x 4 x 1 mm 0.800 btg 125,000.00 100,000.00
B384 Braket Siku / spigot / stiffener 0.267 btg 80,000.00 21,360.00
B385 Paku Beton 0.080 kg 150,000.00 12,000.00
B387 Paku Skrup 0.110 doz 350,000.00 38,500.00
B390 Compound 0.250 kg 85,000.00 21,250.00
A36 Sewa Schafolding 0.020 set/Hr 50,000.00 1,000.00
Listrik Kerja 1.000 ls 5,000.00 5,000.00
Alat bantu lainnya 1.000 ls 2,500.00 2,500.00
U01 Pekerja/Kenek 0.390 O/h 180,000.00 70,200.00
U11 Tukang Las 0.700 O/h 250,000.00 175,000.00
U14 Kepala Tukang 0.07 O/h 280,000.00 19,600.00
U15 Mandor/Pengawas 0.007 O/h 300,000.00 2,100.00
JUMLAH : 633,510.00

IX Pekerjaan LANGIT - LANGIT


19 1 M2 Pasang Rangka Langit-Langit (50 X 100) cm, Kayu Kelas II atau III 192,800.00
B115 Kayu kelas II (balok) 0.015 M3 3,500,000.00 53,900.00
B32 Paku biasa 0.200 Kg 30,000.00 6,000.00
U01 Pekerja/Kenek 0.150 O/h 180,000.00 27,000.00
U04 Tukang Kayu 0.300 O/h 250,000.00 75,000.00
U14 Kepala Tukang 0.030 O/h 280,000.00 8,400.00
U15 Mandor/Pengawas 0.075 O/h 300,000.00 22,500.00
JUMLAH : 192,800.00

20 1 M2 Pasang Rangka Langit-Langit (60 X 60) cm, Kayu Kelas II atau III 186,950.00
B115 Kayu kelas II (balok) 0.016 M3 3,500,000.00 57,050.00
733291305.xlsx ANALISA 52 /52
HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

B32 Paku biasa 0.250 Kg 30,000.00 7,500.00


U01 Pekerja/Kenek 0.200 O/h 180,000.00 36,000.00
U04 Tukang Kayu 0.300 O/h 250,000.00 75,000.00
U14 Kepala Tukang 0.030 O/h 280,000.00 8,400.00
U15 Mandor/Pengawas 0.010 O/h 300,000.00 3,000.00
JUMLAH : 186,950.00

1 1 m2 Pemasangan
Rangka rangka
metalBesi hollow40.40.2
hollow 1x40.40.2mm,
mm modul 60 x 60 cm, untuk plafon 216,150.00
B218 4.000 m 18,750.00 75,000.00
Assesoris
1.000 Ls 18,750.00 18,750.00
(perkuatan, las dll)
U01 Pekerja/Kenek 0.200 O/h 180,000.00 36,000.00
U03 Tukang 0.300 O/h 250,000.00 75,000.00
U14 Kepala Tukang 0.030 O/h 280,000.00 8,400.00
U15 Mandor/Pengawas 0.010 O/h 300,000.00 3,000.00
JUMLAH : 216,150.00

2 1 M2 Pasang Langit-Langit Gypsum Board, Ukuran (1200 x 2400 x 9) mm 105,680.00


B22 Gypsum Board 9 mm 0.364 Lembar 120,000.00 43,680.00
B37 Paku sekrup 0.110 Kg 260,000.00 28,600.00
U01 Pekerja/Kenek 0.100 O/h 180,000.00 18,000.00
U04 Tukang Kayu 0.050 O/h 250,000.00 12,500.00
U14 Kepala Tukang 0.005 O/h 280,000.00 1,400.00
U15 Mandor/Pengawas 0.005 O/h 300,000.00 1,500.00
JUMLAH : 105,680.00

3 1 M2 Pekerjaan Plafon Tripleks 6 Mm " 86,416.00


B14 Plywood 6 mm 0.336 Lbr 156,000.00 52,416.00
B34 Paku Plywood 0.020 Kg 30,000.00 600.00
U01 Pekerja/Kenek 0.100 o/h 180,000.00 18,000.00
U03 Tukang 0.050 o/h 250,000.00 12,500.00
U14 Kepala Tukang 0.005 o/h 280,000.00 1,400.00
U15 Mandor/Pengawas 0.005 o/h 300,000.00 1,500.00
JUMLAH : 86,416.00
Rangka Plafon 216,150.00
TOTAL : 302,566.00

4 1 M' Pekerjaan List Plafon Profil " 54,100.00


B27 List Plafon Profil Gypsum 1.200 m' 25,000.00 30,000.00
B32 Paku Biasa 0.010 kg 30,000.00 300.00
U01 Pekerja/Kenek 0.050 o/h 180,000.00 9,000.00
U04 Tukang kayu 0.050 o/h 250,000.00 12,500.00
U14 Kepala Tukang 0.005 o/h 280,000.00 1,400.00
U15 Mandor/Pengawas 0.003 o/h 300,000.00 900.00
JUMLAH : 54,100.00

5 1 M2 Pasang Langit-Langit Akustik Ukuran (30 x 30) cm 24,100.00


B28 List Profil DINDING 1.0500 m -
B32 Paku Biasa 0.0100 Kg 30,000.00 300.00
U01 Pekerja/Kenek 0.0500 O/h 180,000.00 9,000.00
U04 Tukang kayu 0.0500 O/h 250,000.00 12,500.00
U14 Kepala Tukang 0.0050 O/h 280,000.00 1,400.00
U15 Mandor/Pengawas 0.0030 O/h 300,000.00 900.00
JUMLAH : 24,100.00

6 1 M2 Pasang Langit-Langit Akustik Ukuran (30 x 60) cm 48,800.00


B23 Akustik 60 x 60 cm 5.800 Lembar -
B34 Paku Plywood 0.050 Kg 30,000.00 1,500.00
U01 Pekerja/Kenek 0.100 O/h 180,000.00 18,000.00

733291305.xlsx ANALISA 53 /53


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

U04 Tukang Kayu 0.100 O/h 250,000.00 25,000.00


U14 Kepala Tukang 0.010 O/h 280,000.00 2,800.00
U15 Mandor/Pengawas 0.005 O/h 300,000.00 1,500.00
JUMLAH : 48,800.00

7 1 M2 Pasang Langit-Langit Akustik Ukuran (60 x 120) cm 48,800.00


B25 Akustik 60 x 120 cm 1.500 Lembar -
B34 Paku Plywood 0.050 Kg 30,000.00 1,500.00
U01 Pekerja/Kenek 0.100 O/h 180,000.00 18,000.00
U04 Tukang Kayu 0.100 O/h 250,000.00 25,000.00
U14 Kepala Tukang 0.010 O/h 280,000.00 2,800.00
U15 Mandor/Pengawas 0.005 O/h 300,000.00 1,500.00
JUMLAH : 48,800.00

8 1 M2 Pasang Langit-Langit Tripleks Ukuran (120 x 240) cm, tebal 4 mm 106,700.00


B14 Plywood 6 mm 0.375 Lembar 156,000.00 58,500.00
B34 Paku Plywood 0.030 Kg 30,000.00 900.00
U01 Pekerja/Kenek 0.100 O/h 180,000.00 18,000.00
U04 Tukang Kayu 0.100 O/h 250,000.00 25,000.00
U14 Kepala Tukang 0.010 O/h 280,000.00 2,800.00
U15 Mandor/Pengawas 0.005 O/h 300,000.00 1,500.00
JUMLAH : 106,700.00

9 1 M2 Pasang Plafond Lambriziring 613,400.00


B78 Lumbersharing @4m 12.000 Lembar 38,000.00 456,000.00
B32 Paku biasa 0.100 Kg 30,000.00 3,000.00
U01 Pekerja/Kenek 0.100 O/h 180,000.00 18,000.00
U04 Tukang Kayu 0.500 O/h 250,000.00 125,000.00
U14 Kepala Tukang 0.030 O/h 280,000.00 8,400.00
U15 Mandor/Pengawas 0.010 O/h 300,000.00 3,000.00
JUMLAH : 613,400.00

10 1 M2 Pasang Langit-Langit Teakwood (60 x 120) cm, tebal 4 mm #N/A


Plywood 4 mm Ukuran 122 x 244 cm 0.375 #N/A #N/A #N/A
B32 Paku biasa 0.030 Kg 30,000.00 900.00
U01 Pekerja/Kenek 0.070 O/h 180,000.00 12,600.00
U04 Tukang Kayu 0.100 O/h 250,000.00 25,000.00
U14 Kepala Tukang 0.010 O/h 280,000.00 2,800.00
U15 Mandor/Pengawas 0.004 O/h 300,000.00 1,050.00
JUMLAH : #N/A

11 1 M2 Pasang Langit-Langit Lat Kayu Kelas I 339,100.00


B118 Kayu Kelas I (papan) 0.024 M3 5,000,000.00 120,000.00
B32 Paku biasa 0.010 Kg 30,000.00 300.00
B37 Paku sekrup 0.050 Kg 260,000.00 13,000.00
U01 Pekerja/Kenek 0.200 O/h 180,000.00 36,000.00
U04 Tukang Kayu 0.600 O/h 250,000.00 150,000.00
U14 Kepala Tukang 0.060 O/h 280,000.00 16,800.00
U15 Mandor/Pengawas 0.010 O/h 300,000.00 3,000.00
JUMLAH : 339,100.00

12 1 M2 Pasang Langit-Langit Lat Kayu Kelas II 309,100.00


B116 Kayu Kelas II (papan) 0.024 M3 3,750,000.00 90,000.00
B32 Paku biasa 0.010 Kg 30,000.00 300.00
B37 Paku sekrup 0.050 Kg 260,000.00 13,000.00
U01 Pekerja/Kenek 0.200 O/h 180,000.00 36,000.00
U04 Tukang Kayu 0.600 O/h 250,000.00 150,000.00
U14 Kepala Tukang 0.060 O/h 280,000.00 16,800.00
733291305.xlsx ANALISA 54 /54
HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

U15 Mandor/Pengawas 0.010 O/h 300,000.00 3,000.00


JUMLAH : 309,100.00

13 1 M' Pasang List Langit-Langit Kayu Profil 39,850.00


B26 List Plafon Profil 1.050 M1 15,000.00 15,750.00
B32 Paku biasa 0.010 Kg 30,000.00 300.00
U01 Pekerja/Kenek 0.050 O/h 180,000.00 9,000.00
U04 Tukang Kayu 0.050 O/h 250,000.00 12,500.00
U14 Kepala Tukang 0.005 O/h 280,000.00 1,400.00
U15 Mandor/Pengawas 0.003 O/h 300,000.00 900.00
JUMLAH : 39,850.00

22 1 m’ Pemasangan 1 m’ list langit-langit Gypsum 63,640.00


B27 List Plafon Profil Gypsum 1.050 m 25,000.00 26,250.00
B30 Sekrup Gypsum 0.110 Doz 250,000.00 27,500.00
U01 Pekerja/Kenek 0.021 O/h 180,000.00 3,780.00
U04 Tukang Kayu 0.021 O/h 250,000.00 5,250.00
U14 Kepala Tukang 0.002 O/h 280,000.00 560.00
U15 Mandor/Pengawas 0.001 O/h 300,000.00 300.00
JUMLAH : 63,640.00

280 1 M 2 Langit-Langit Akustik 60 X 120 Cm + Rangka Alluminium" #N/A


#N/A Profil Alluminium "I" 3.600 #N/A #N/A #N/A
#N/A Kawat Seng Polos 0.150 #N/A #N/A #N/A
#N/A Ramset / Dina Bolt 1.000 #N/A #N/A #N/A
#N/A Akustik Arm Strong 60 x 120 Cm 1.500 #N/A #N/A #N/A
U01 Pekerja/Kenek 0.150 O/h 180,000.00 27,000.00
U04 Tukang Kayu 0.500 O/h 250,000.00 125,000.00
U14 Kepala Tukang 0.050 O/h 280,000.00 14,000.00
U15 Mandor/Pengawas 0.008 O/h 300,000.00 2,250.00
JUMLAH : #N/A

X PEKERJAAN PLUMBING & SANITASI


1 Memasang 1 Buah Kloset Duduk/Monoblok 4,945,280.00
B266 Kloset duduk / monoblok 1.000 Set 3,800,000.00 3,800,000.00
Perlengkapan ( 6 % Harga Kloset ) 1.000 Ls 228,000.00 228,000.00
U01 Pekerja/Kenek 3.300 O/h 180,000.00 594,000.00
U05 Tukang batu 1.100 O/h 250,000.00 275,000.00
U14 Kepala Tukang 0.001 O/h 280,000.00 280.00
U15 Mandor/Pengawas 0.160 O/h 300,000.00 48,000.00
JUMLAH : 4,945,280.00

2 Memasang 1 Buah Kloset Jongkok Porselen 1,041,600.00


B262 Kloset jongkok porselen 1.000 Buah -
B01 Semen Portland 6.000 Kg 2,500.00 15,000.00
B110 Pasir Pasang 0.010 M3 360,000.00 3,600.00
U01 Pekerja/Kenek 1.000 O/h 180,000.00 180,000.00
U05 Tukang batu 1.500 O/h 250,000.00 375,000.00
U14 Kepala Tukang 1.500 O/h 280,000.00 420,000.00
U15 Mandor/Pengawas 0.160 O/h 300,000.00 48,000.00
JUMLAH : 1,041,600.00

3 Memasang 1 Buah Wastafel 2,230,100.00


B267 Wastafel lengkap TOTO 1.000 Buah 1,300,000.00 1,300,000.00
Perlengkapan ( 12 % Harga ) 1.000 Ls 156,000.00 156,000.00
B03 Semen Warna 6.000 Kg 20,000.00 120,000.00
B110 Pasir Pasang 0.010 M3 360,000.00 3,600.00
U01 Pekerja/Kenek 1.200 O/h 180,000.00 216,000.00
U05 Tukang batu 1.450 O/h 250,000.00 362,500.00
733291305.xlsx ANALISA 55 /55
HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

U14 Kepala Tukang 0.150 O/h 280,000.00 42,000.00


U15 Mandor/Pengawas 0.100 O/h 300,000.00 30,000.00
JUMLAH : 2,230,100.00

4 1 Bh Pasang Urinoir 4,484,100.00


B265 Urinoir 1.000 Buah 3,500,000.00 3,500,000.00
Perlengkapan (30 % Harga Urinoir) 0.300 % 1,050,000.00 315,000.00
B01 Semen portland 6.000 Kg 2,500.00 15,000.00
B110 Pasir Pasang 0.010 M3 360,000.00 3,600.00
U01 Pekerja/Kenek 1.000 O/h 180,000.00 216,000.00
U03 Tukang 1.000 O/h 250,000.00 362,500.00
U14 Kepala Tukang 0.100 O/h 280,000.00 42,000.00
U15 Mandor/Pengawas 0.100 O/h 300,000.00 30,000.00
JUMLAH : 4,484,100.00

5 1 Bh Pasang Floor Drain 533,640.00


B260 Floor Drain 1.000 Buah 250,000.00 250,000.00
Perlengkapan (12 % Harga F.Drain) 0.120 % 30,000.00 3,600.00
U01 Pekerja/Kenek 0.650 O/h 180,000.00 117,000.00
U03 Tukang 0.550 O/h 250,000.00 137,500.00
U14 Kepala Tukang 0.006 O/h 280,000.00 1,540.00
U15 Mandor/Pengawas 0.080 O/h 300,000.00 24,000.00
JUMLAH : 533,640.00

6 1 Unit Pasang Tangki Fiber Glass Cap 2.2 M3


Fiber Glass 1.000 #N/A #N/A #N/A
Perlengkapan (12 % Harga Heater) 0.300 % #N/A #N/A
U01 Pekerja/Kenek 1.800 O/h 180,000.00 6,480.00
U03 Tukang 2.700 O/h 250,000.00 15,000.00
U14 Kepala Tukang 0.540 O/h 280,000.00 1,680.00
U15 Mandor/Pengawas 0.110 O/h 300,000.00 600.00
JUMLAH : #N/A

7 Memasang 1 Buah Bak Mandi Batu Batako Volume 0,30 M3 2,689,500.00


B127 Batu batako 10 x 18 x 24 cm 21.000 Buah 7,500.00 157,500.00
B01 Semen portland 120.000 Kg 2,500.00 300,000.00
B110 Pasir Pasang 0.300 M3 360,000.00 108,000.00
B154 Tegel Porselin 11 x 11 cm 360.000 Buah -
B03 Semen Warna 6.000 Kg 20,000.00 120,000.00
U01 Pekerja/Kenek 6.000 O/h 180,000.00 1,080,000.00
U05 Tukang batu 3.000 O/h 250,000.00 750,000.00
U14 Kepala Tukang 0.300 O/h 280,000.00 84,000.00
U15 Mandor/Pengawas 0.300 O/h 300,000.00 90,000.00
JUMLAH : 2,689,500.00

8 1 M' Pasang Pipa Tanah Penyalur Air Limbah Diameter 15 cm #N/A


Pipa tanah 1.600 #N/A #N/A #N/A
B01 Semen portland 0.680 Kg 2,500.00 1,700.00
B110 Pasir Pasang 0.013 M3 360,000.00 4,680.00
B113 Pasir urug 0.011 M3 260,000.00 2,860.00
U01 Pekerja/Kenek 0.060 O/h 180,000.00 10,800.00
U05 Tukang batu 0.030 O/h 250,000.00 7,500.00
U14 Kepala Tukang 0.003 O/h 280,000.00 840.00
U15 Mandor/Pengawas 0.003 O/h 300,000.00 750.00
JUMLAH : #N/A

118 1 M' Pekerjaan Pipa Gip Ø ½ " " 125,496.25


B181 Pipa Gip Ø ½ " 1.200 M 62,500.00 75,000.00

733291305.xlsx ANALISA 56 /56


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

Perlengkapan (35 % Harga Pipa) 0.350 % 21,875.00 7,656.25


U01 Pekerja/Kenek 0.054 O/h 180,000.00 9,720.00
U03 Tukang 0.090 O/h 250,000.00 22,500.00
U14 Kepala Tukang 0.009 O/h 280,000.00 2,520.00
U15 Mandor/Pengawas 0.027 O/h 300,000.00 8,100.00
JUMLAH : 125,496.25

119 1 M' Pekerjaan PIPA GIP Ø ¾ " " 125,496.25


B183 Pipa Gip Ø ¾ " 1.200 M 62,500.00 75,000.00
Perlengkapan (35 % Harga Pipa) 0.350 % 21,875.00 7,656.25
U01 Pekerja/Kenek 0.054 O/h 180,000.00 9,720.00
U03 Tukang 0.090 O/h 250,000.00 22,500.00
U14 Kepala Tukang 0.009 O/h 280,000.00 2,520.00
U15 Mandor/Pengawas 0.027 O/h 300,000.00 8,100.00
JUMLAH : 125,496.25

120 1 M' Pekerjaan PIPA GIP Ø 1 " " 142,027.50


B185 Pipa Gip Ø 1 " 1.200 M 75,000.00 90,000.00
Perlengkapan (35 % Harga Pipa) 0.350 % 26,250.00 9,187.50
U01 Pekerja/Kenek 0.054 O/h 180,000.00 9,720.00
U03 Tukang 0.090 O/h 250,000.00 22,500.00
U14 Kepala Tukang 0.009 O/h 280,000.00 2,520.00
U15 Mandor/Pengawas 0.027 O/h 300,000.00 8,100.00
JUMLAH : 142,027.50

121 1 M' Pekerjaan PIPA GIP Ø 1 ¼ " " 196,076.25


B187 Pipa Gip Ø 1 ¼ " 1.200 M 94,500.00 113,400.00
Perlengkapan (35 % Harga Pipa) 0.350 % 33,075.00 11,576.25
U01 Pekerja/Kenek 0.108 O/h 180,000.00 19,440.00
U03 Tukang 0.180 O/h 250,000.00 45,000.00
U14 Kepala Tukang 0.018 O/h 280,000.00 5,040.00
U15 Mandor/Pengawas 0.005 O/h 300,000.00 1,620.00
JUMLAH : 196,076.25

122 1 M' Pekerjaan PIPA GIP Ø 1 ½ " " 181,308.33


B189 Pipa Gip Ø 1 ½ " 1.200 M 83,333.33 100,000.00
Perlengkapan (35 % Harga Pipa) 0.350 % 29,166.67 10,208.33
U01 Pekerja/Kenek 0.108 O/h 180,000.00 19,440.00
U03 Tukang 0.180 O/h 250,000.00 45,000.00
U14 Kepala Tukang 0.018 O/h 280,000.00 5,040.00
U15 Mandor/Pengawas 0.005 O/h 300,000.00 1,620.00
JUMLAH : 181,308.33

123 1 M' Pekerjaan PIPA GIP Ø 2 " " 236,412.50


B191 Pipa Gip Ø 2 " 1.200 M 125,000.00 150,000.00
Perlengkapan (35 % Harga Pipa) 0.350 % 43,750.00 15,312.50
U01 Pekerja/Kenek 0.108 O/h 180,000.00 19,440.00
U03 Tukang 0.180 O/h 250,000.00 45,000.00
U14 Kepala Tukang 0.018 O/h 280,000.00 5,040.00
U15 Mandor/Pengawas 0.005 O/h 300,000.00 1,620.00
JUMLAH : 236,412.50

124 1 M' Pekerjaan PIPA GIP Ø 3 " 71,100.00


B193 Pipa Gip Ø 3 " 1.200 M -
Perlengkapan (35 % Harga Pipa) 0.350 % - -
U01 Pekerja/Kenek 0.108 O/h 180,000.00 19,440.00
U03 Tukang 0.180 O/h 250,000.00 45,000.00

733291305.xlsx ANALISA 57 /57


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

U14 Kepala Tukang 0.018 O/h 280,000.00 5,040.00


U15 Mandor/Pengawas 0.005 O/h 300,000.00 1,620.00
JUMLAH : 71,100.00

124 1 M' Pekerjaan PIPA GIP Ø 4 " 88,890.00


B195 Pipa Gip Ø 4 " 1.200 M - -
Perlengkapan (35 % Harga Pipa) 0.350 % - -
U01 Pekerja/Kenek 0.135 O/h 180,000.00 24,300.00
U03 Tukang 0.225 O/h 250,000.00 56,250.00
U14 Kepala Tukang 0.023 O/h 280,000.00 6,300.00
U15 Mandor/Pengawas 0.007 O/h 300,000.00 2,040.00
JUMLAH : 88,890.00

733291305.xlsx ANALISA 58 /58


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

125 1 M' Pekerjaan PIPA PVC Ø 6 " 53,340.00


B177 Pipa PVC dia 6" 1.200 M - -
Perlengkapan (35 % Harga Pipa) 0.350 % - -
U01 Pekerja/Kenek 0.081 O/h 180,000.00 14,580.00
U03 Tukang 0.135 O/h 250,000.00 33,750.00
U14 Kepala Tukang 0.014 O/h 280,000.00 3,780.00
U15 Mandor/Pengawas 0.004 O/h 300,000.00 1,230.00
53,340.00

126 1 M' Pekerjaan PIPA PVC Ø 4 " 205,427.50


B173 Pipa PVC dia 4" 1.200 M 115,000.00 138,000.00
Perlengkapan (35 % Harga Pipa) 0.350 % 40,250.00 14,087.50
U01 Pekerja/Kenek 0.081 O/h 180,000.00 14,580.00
U03 Tukang 0.135 O/h 250,000.00 33,750.00
U14 Kepala Tukang 0.014 O/h 280,000.00 3,780.00
U15 Mandor/Pengawas 0.004 O/h 300,000.00 1,230.00
205,427.50

127 1 M' Pekerjaan PIPA PVC Ø 3 " 145,915.00


B171 Pipa PVC dia 3" 1.200 M 70,000.00 84,000.00
Perlengkapan (35 % Harga Pipa) 0.350 % 24,500.00 8,575.00
U01 Pekerja/Kenek 0.081 O/h 180,000.00 14,580.00
U03 Tukang 0.135 O/h 250,000.00 33,750.00
U14 Kepala Tukang 0.014 O/h 280,000.00 3,780.00
U15 Mandor/Pengawas 0.004 O/h 300,000.00 1,230.00
145,915.00

128 1 M' Pekerjaan PIPA PVC Ø 2 " 118,206.25


B169 Pipa PVC dia 2" 1.200 M 62,500.00 75,000.00
Perlengkapan (35 % Harga Pipa) 0.350 % 21,875.00 7,656.25
U01 Pekerja/Kenek 0.054 O/h 180,000.00 9,720.00
U03 Tukang 0.090 O/h 250,000.00 22,500.00
U14 Kepala Tukang 0.009 O/h 280,000.00 2,520.00
U15 Mandor/Pengawas 0.003 O/h 300,000.00 810.00
118,206.25

129 1 M' Pekerjaan PIPA PVC Ø 1 ½ " 41,731.25


Pipa PVC dia 1 1/2" 1.200 M 12,500.00 15,000.00
Perlengkapan (35 % Harga Pipa) 0.350 % 4,375.00 1,531.25
U01 Pekerja/Kenek 0.036 O/h 180,000.00 6,480.00
U03 Tukang 0.066 O/h 250,000.00 16,500.00
U14 Kepala Tukang 0.006 O/h 280,000.00 1,680.00
U15 Mandor/Pengawas 0.002 O/h 300,000.00 540.00
41,731.25

130 1 M' Pekerjaan PIPA PVC Ø 1 " 36,985.00


B165 Pipa PVC dia 1" 1.200 M 10,000.00 12,000.00
Perlengkapan (35 % Harga Pipa) 0.350 % 3,500.00 1,225.00
U01 Pekerja/Kenek 0.036 O/h 180,000.00 6,480.00
U03 Tukang 0.060 O/h 250,000.00 15,000.00
U14 Kepala Tukang 0.006 O/h 280,000.00 1,680.00
U15 Mandor/Pengawas 0.002 O/h 300,000.00 600.00
36,985.00

131 1 M' Pekerjaan PIPA PVC Ø 3/4" 35,331.88


B163 Pipa PVC dia 3/4" 1.200 M 8,750.00 10,500.00

733291305.xlsx ANALISA 59 /59


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

Perlengkapan (35 % Harga Pipa) 0.350 % 3,062.50 1,071.88


U01 Pekerja/Kenek 0.036 O/h 180,000.00 6,480.00
U03 Tukang 0.060 O/h 250,000.00 15,000.00
U14 Kepala Tukang 0.006 O/h 280,000.00 1,680.00
U15 Mandor/Pengawas 0.002 O/h 300,000.00 600.00
35,331.88

131 Memasang 1 Buah Bak Kontrol Pasangan Batu Bata ukuran ( 30 x 30 ) cm Tinggi 35 cm 1,070,310.00
B126 Batu Tela (m3) 0.145 M3 -
B01 Semen portland 44.000 Kg 2,500.00 110,000.00
B110 Pasir Pasang 0.070 M3 360,000.00 25,200.00
B95 kerikil 0.070 M3 480,000.00 33,600.00
B304 Besi beton 1.600 Kg 28,000.00 44,800.00
B111 Pasir beton (m3) 0.060 M3 360,000.00 21,600.00
U01 Pekerja/Kenek 3.200 O/h 180,000.00 576,000.00
U05 Tukang batu 1.015 O/h 250,000.00 253,750.00
U14 Kepala Tukang 0.002 O/h 280,000.00 560.00
U15 Mandor/Pengawas 0.016 O/h 300,000.00 4,800.00
JUMLAH : 1,070,310.00

132 Memasang 1 Buah Bak Kontrol Pasangan Batu Bata ukuran ( 45 x 45 ) cm Tinggi 50 cm 1,189,210.00
B126 Batu Tela (m3) 0.250 M3 -
B01 Semen portland 77.000 Kg 2,500.00 192,500.00
B110 Pasir Pasang 0.130 M3 360,000.00 46,800.00
B95 Kerikil 0.020 M3 480,000.00 9,600.00
B304 Besi beton 2.600 Kg 28,000.00 72,800.00
B111 Pasir beton (m3) 0.090 M3 360,000.00 32,400.00
U01 Pekerja/Kenek 3.200 O/h 180,000.00 576,000.00
U05 Tukang batu 1.015 O/h 250,000.00 253,750.00
U14 Kepala Tukang 0.002 O/h 280,000.00 560.00
U15 Mandor/Pengawas 0.016 O/h 300,000.00 4,800.00
JUMLAH : 1,189,210.00

133 Memasang 1 Buah Bak Kontrol Pasangan Batu Bata ukuran ( 60 x 60 ) cm Tinggi 65 cm 1,406,190.00
B126 Batu Tela (m3) 0.371 M3 -
B01 Semen portland 114.000 Kg 2,500.00 285,000.00
B110 Pasir Pasang 0.184 M3 360,000.00 66,240.00
B95 Kerikil 0.033 M3 480,000.00 15,840.00
B304 Besi beton 4.850 Kg 28,000.00 135,800.00
B111 Pasir beton (m3) 0.120 M3 360,000.00 43,200.00
U01 Pekerja/Kenek 3.200 O/h 180,000.00 576,000.00
U05 Tukang batu 1.015 O/h 250,000.00 253,750.00
U14 Kepala Tukang 0.002 O/h 280,000.00 560.00
U15 Mandor/Pengawas 0.016 O/h 300,000.00 4,800.00
U07 Tukang gali 0.100 O/h 250,000.00 25,000.00
JUMLAH : 1,406,190.00

134 Memasang 1 Buah Cuci Piring Stainles Steel 639,250.00


B258 Bak cuci stainless steel 1.000 Buah 500,000.00 500,000.00
Water drain + asesories 1.000 Set 50,000.00 50,000.00
U01 Pekerja/Kenek 0.030 O/h 180,000.00 5,400.00
U05 Tukang Batu 0.300 O/h 250,000.00 75,000.00
U14 Kepala Tukang 0.030 O/h 280,000.00 8,400.00
U15 Mandor/Pengawas 0.002 O/h 300,000.00 450.00
JUMLAH : 639,250.00

135 Memasang 1 Buah Kran Diameter 3/4" atau 1/2" 151,725.00


B269 Kran Air Stainless 1.000 Buah 120,000.00 120,000.00
B255 Seal tape 0.025 Roll 25,000.00 625.00

733291305.xlsx ANALISA 60 /60


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

U01 Pekerja/Kenek 0.010 O/h 180,000.00 1,800.00


U05 Tukang Batu 0.100 O/h 250,000.00 25,000.00
U14 Kepala Tukang 0.010 O/h 280,000.00 2,800.00
U15 Mandor/Pengawas 0.005 O/h 300,000.00 1,500.00
JUMLAH : 151,725.00

136 Memasang 1 Kran air + shower bilas dia 3/4


B249 Kran Shower 1.000 Buah 250,000.00 250,000.00
B255 Seal tape 0.026 Roll 25,000.00 637.50
U01 Pekerja/Kenek 0.011 O/h 180,000.00 1,980.00
U03 Tukang 0.110 O/h 250,000.00 27,500.00
U14 Kepala Tukang 0.011 O/h 280,000.00 3,080.00
U15 Mandor/Pengawas 0.006 O/h 300,000.00 1,650.00
JUMLAH : 284,847.50

136 1 Unit Ground Reservoar Untuk gedung


Galian Tanah Pondasi / Bak 16.000 #N/A #N/A #N/A
Urugan Tanah kembali 1.600 #N/A #N/A #N/A
Pondasi Poer Plat 2.520 #N/A #N/A #N/A
Sloof Beton Bertulang 15/20 0.360 #N/A #N/A #N/A
Kolom Beton Bertulang 25/25 0.216 #N/A #N/A #N/A
Plat Dinding & Lantai tebal 10 cm 2.680 #N/A #N/A #N/A
Plat Penutup tebal 12 cm 0.800 #N/A #N/A #N/A
Balok Beton 20/30 0.288 #N/A #N/A #N/A
Lantai Cor 1 : 3 : 5 tebal 10 cm 0.800 #N/A #N/A #N/A
Plester pada Plat Lantai 6.000 #N/A #N/A #N/A
Plesteran Bak Air 22.800 #N/A #N/A #N/A
Pasang Keramik 20/20 22.000 #N/A #N/A #N/A
Tangga Besi turun ke Reservoar 1.000 #N/A #N/A #N/A
Pintu Besi Bak Kontrol 50/50 + Acc 1.000 #N/A #N/A #N/A
JUMLAH : #N/A

137 1 Unit Pekerjaan Septictank & Rembesan 34,236,656.71


Galian tanah 21.365 #N/A 175,500.00 3,749,557.50
Urugan tanah kembali 6.410 #N/A 40,260.00 258,046.47
Urugan Pasir 0.380 #N/A 369,000.00 140,220.00
Pasangan Pondasi Batu Kali 1 : 4 1.219 #N/A 2,295,700.00 2,798,458.30
Pasangan Tembok 1 pc : 4 psr 22.240 #N/A 468,955.00 10,429,559.20
Cor rabat 1 pc : 3 psr : 5 krl 0.218 #N/A 1,540,300.00 335,785.40
Sloof, Kolom, Ringbalk 0.578 #N/A 10,586,790.00 6,119,164.62
Beton Plat Penutup 0.424 #N/A 11,055,900.00 4,687,701.60
Plesteran 1 pc : 2 psr 30.897 #N/A 132,960.00 4,108,065.12
Urugan Kerikil 0.448 #N/A 649,500.00 290,976.00
Pekerjaan Ijuk 0.522 #N/A 500,000.00 261,000.00
Pipa PVC Ø 4 " 4.000 #N/A 205,427.50 821,710.00
Pipa Udara Gip. Ø 2 " 1.000 #N/A 236,412.50 236,412.50
JUMLAH : 34,236,656.71

1 M' Saluran Type 1 (Tepi Pagar)


Galian Tanah 0.410 #N/A #N/A #N/A
Urugan Tanah kembali 0.102 #N/A #N/A #N/A
B113 Pasir Urug 0.030 M3 260,000.00 7,800.00
Pondasi Batu Kali 0.090 #N/A #N/A #N/A
Cor Lantai Rabat 0.040 #N/A #N/A #N/A
Plesteran 1 : 3 1.600 #N/A #N/A #N/A
Acian 1.000 #N/A #N/A #N/A
JUMLAH : #N/A

1 1 M' Saluran Type 2 (Dari Halaman Ke Saluran Type 1)

733291305.xlsx ANALISA 61 /61


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

Galian Tanah 0.250 #N/A #N/A #N/A


Urugan Tanah kembali 0.063 #N/A #N/A #N/A
B113 Pasir Urug 0.025 M3 260,000.00 6,500.00
Cor Rabat Bertulang 0.225 #N/A #N/A #N/A
Bekisting Dinding Cor 0.800 #N/A #N/A #N/A
Plesteran 1 : 3 1.200 #N/A #N/A #N/A
Plesteran Beton 1.200 #N/A #N/A #N/A
Besi Grill (Penutup saluran) 48.978 #N/A #N/A #N/A
JUMLAH : #N/A

2 1 M' Saluran Ditepi Jalan Type 3


Galian Tanah 0.960 #N/A #N/A #N/A
Urugan Tanah kembali 0.240 #N/A #N/A #N/A
B113 Pasir Urug 0.120 M3 260,000.00 31,200.00
Lapisan Batu Kosong 0.240 #N/A #N/A #N/A
Pondasi Batu Gunung 0.480 #N/A #N/A #N/A
Cor Lantai Rabat 0.120 #N/A #N/A #N/A
Plesteran 1 : 3 3.000 #N/A #N/A #N/A
Acian 3.000 #N/A #N/A #N/A
JUMLAH : #N/A

3 1 M' Pasang Kawat Duri Pada Pagar Keliling


B219 Besi Siku 50.50.5 1.200 Kg 24,000.00 28,800.00
B06 Kawat Duri 7.700 Kg 25,000.00 192,500.00
Cat Minyak pada Besi Siku 0.400 m2 57,240.00 22,896.00
JUMLAH : 244,196.00

4 1 M' Profil Beton


Semen PC 12.500 #N/A #N/A #N/A
B385 Paku beton 25.000 kg 150,000.00 3,750,000.00
Pasir pasang 0.001 #N/A #N/A #N/A
U01 Pekerja/Kenek 0.750 O/h 180,000.00 135,000.00
U03 Tukang 1.000 O/h 250,000.00 250,000.00
U14 Kepala tukang 0.500 O/h 280,000.00 140,000.00
U15 Mandor/Pengawas 0.100 O/h 300,000.00 30,000.00
JUMLAH : #N/A

5 1 M' Pekerjaan Saluran Keliling Bangunan 600,289.00


Cor Rabat 1 Pc : 3 Psr : 5 Krl 0.100 m3 1,540,300.00 154,030.00
Plesteran 1 Pc : 3 Psr 2.200 m2 127,920.00 281,424.00
Acian 2.200 m2 74,925.00 164,835.00
JUMLAH : 600,289.00

1 M' Pek. Saluran Pembuangan Ke Riol Kota -


Beton bertulang 0.250 #N/A #N/A #N/A
Plesteran 1 Pc : 3 Psr 1.700 #N/A #N/A #N/A
JUMLAH : #N/A

XII PEKERJAAN KUNCI DAN KACA


1 1 Buah Pasang Kunci Tanam Antik 178,500.00
B357 Kunci Tanam 2 Slaag SES/Kend 1.000 Buah -
U01 Pekerja/Kenek 0.060 O/h 180,000.00 10,800.00
U04 Tukang Kayu 0.600 O/h 250,000.00 150,000.00
U14 Kepala Tukang 0.060 O/h 280,000.00 16,800.00
U15 Mandor/Pengawas 0.003 O/h 300,000.00 900.00
JUMLAH : 178,500.00

733291305.xlsx ANALISA 62 /62


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

2 1 Buah Pasang Kunci Tanam Biasa 581,100.00


B356 Kunci tanam 1.000 Buah 450,000.00 450,000.00
U01 Pekerja/Kenek 0.010 O/h 180,000.00 1,800.00
U04 Tukang Kayu 0.500 O/h 250,000.00 125,000.00
U14 Kepala Tukang 0.010 O/h 280,000.00 2,800.00
U15 Mandor/Pengawas 0.005 O/h 300,000.00 1,500.00
JUMLAH : 581,100.00

3 1 Buah Pasang Kunci Cylinder 531,100.00


B358 Kunci Tanam Silinder 1 Slaag SES/Kend 1.000 Buah 400,000.00 400,000.00
U01 Pekerja/Kenek 0.010 O/h 180,000.00 1,800.00
U04 Tukang Kayu 0.500 O/h 250,000.00 125,000.00
U14 Kepala Tukang 0.010 O/h 280,000.00 2,800.00
U15 Mandor/Pengawas 0.005 O/h 300,000.00 1,500.00
JUMLAH : 531,100.00

4 1 Buah Pasang Engsel Pintu 219,625.00


B366 Engsel Pintu 1.000 Pasang 175,000.00 175,000.00
U01 Pekerja/Kenek 0.015 O/h 180,000.00 2,700.00
U04 Tukang Kayu 0.150 O/h 250,000.00 37,500.00
U14 Kepala Tukang 0.015 O/h 280,000.00 4,200.00
U15 Mandor/Pengawas 0.001 O/h 300,000.00 225.00
JUMLAH : 219,625.00

5 1 Bh Engsel Jendela 194,750.00


B365 Engsel jendela 1.000 Pasang 165,000.00 165,000.00
U01 Pekerja/Kenek 0.010 O/h 180,000.00 1,800.00
U03 Tukang 0.100 O/h 250,000.00 25,000.00
U14 Kepala Tukang 0.010 O/h 280,000.00 2,800.00
U15 Mandor/Pengawas 0.001 O/h 300,000.00 150.00
JUMLAH : 194,750.00

6 1 Buah Pasang Engsel Jendela Kupu-Kupu 194,750.00


B365 Engsel jendela 1.000 Pasang 165,000.00 165,000.00
U01 Pekerja/Kenek 0.010 O/h 180,000.00 1,800.00
U04 Tukang Kayu 0.100 O/h 250,000.00 25,000.00
U14 Kepala Tukang 0.010 O/h 280,000.00 2,800.00
U15 Mandor/Pengawas 0.001 O/h 300,000.00 150.00
JUMLAH : 194,750.00

7 1 Buah Pasang Kait Angin 164,625.00


B377 Hak Angin Lipat 1.000 Buah 120,000.00 120,000.00
U01 Pekerja/Kenek 0.015 O/h 180,000.00 2,700.00
U04 Tukang Kayu 0.150 O/h 250,000.00 37,500.00
U14 Kepala Tukang 0.015 O/h 280,000.00 4,200.00
U15 Mandor/Pengawas 0.001 O/h 300,000.00 225.00
JUMLAH : 164,625.00

8 1 Buah Pasang Pegangan Pintu/Door Holder 148,750.00


B373 Door holder 1.000 Buah -
U01 Pekerja/Kenek 0.050 O/h 180,000.00 9,000.00
U04 Tukang Kayu 0.500 O/h 250,000.00 125,000.00
U14 Kepala Tukang 0.050 O/h 280,000.00 14,000.00
U15 Mandor/Pengawas 0.003 O/h 300,000.00 750.00
JUMLAH : 148,750.00

733291305.xlsx ANALISA 63 /63


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

9 1 Bh Pasang Door Closer 1,348,750.00


B374 Door Closer 1.000 Buah 1,200,000.00 1,200,000.00
U01 Pekerja/Kenek 0.050 O/h 180,000.00 9,000.00
U04 Tukang Kayu 0.500 O/h 250,000.00 125,000.00
U14 Kepala Tukang 0.050 O/h 280,000.00 14,000.00
U15 Mandor/Pengawas 0.003 O/h 300,000.00 750.00
JUMLAH : 1,348,750.00

10 1 Bh Pasang Door Stop 379,750.00


B375 Door Stop 1.000 Buah 350,000.00 350,000.00
U01 Pekerja/Kenek 0.010 O/h 180,000.00 1,800.00
U04 Tukang Kayu 0.100 O/h 250,000.00 25,000.00
U14 Kepala Tukang 0.010 O/h 280,000.00 2,800.00
U15 Mandor/Pengawas 0.001 O/h 300,000.00 150.00
JUMLAH : 379,750.00

11 1 Bh Grendel Jendela 194,625.00


B370 Grendel Jendela 1.000 Buah 150,000.00 150,000.00
U01 Pekerja/Kenek 0.015 O/h 180,000.00 2,700.00
U04 Tukang Kayu 0.150 O/h 250,000.00 37,500.00
U14 Kepala Tukang 0.015 O/h 280,000.00 4,200.00
U15 Mandor/Pengawas 0.001 O/h 300,000.00 225.00
JUMLAH : 194,625.00

12 1 Psg Pasang Grendel Pintu Double 406,300.00


B372 Grendel Pintu Double 1.000 Buah 250,000.00 250,000.00
U01 Pekerja/Kenek 0.010 O/h 180,000.00 1,800.00
U04 Tukang Kayu 0.500 O/h 250,000.00 125,000.00
U14 Kepala Tukang 0.100 O/h 280,000.00 28,000.00
U15 Mandor/Pengawas 0.005 O/h 300,000.00 1,500.00
JUMLAH : 406,300.00

13 1 Buah Pasang Kunci Lemari 74,375.00


B361 Kunci lemari 1.000 Buah -
U01 Pekerja/Kenek 0.025 O/h 180,000.00 4,500.00
U04 Tukang Kayu 0.250 O/h 250,000.00 62,500.00
U14 Kepala Tukang 0.025 O/h 280,000.00 7,000.00
U15 Mandor/Pengawas 0.001 O/h 300,000.00 375.00
JUMLAH : 74,375.00

14 1 M2 Pasang Kaca, Tebal 3 mm 44,625.00


B80 Kaca Bening 3 mm 1.100 M2 -
U01 Pekerja/Kenek 0.015 O/h 180,000.00 2,700.00
U04 Tukang Kayu 0.150 O/h 250,000.00 37,500.00
U14 Kepala Tukang 0.015 O/h 280,000.00 4,200.00
U15 Mandor/Pengawas 0.001 O/h 300,000.00 225.00
JUMLAH : 44,625.00

15 1 M2 Pasang Kaca, Tebal 5 mm 314,625.00


B82 Kaca Polos 5 mm 1.000 M2 270,000.00 270,000.00
U01 Pekerja/Kenek 0.015 O/h 180,000.00 2,700.00
U04 Tukang Kayu 0.150 O/h 250,000.00 37,500.00
U14 Kepala Tukang 0.015 O/h 280,000.00 4,200.00
U15 Mandor/Pengawas 0.001 O/h 300,000.00 225.00
JUMLAH : 314,625.00

16 1 M2 Pasang Kaca, Tebal 8 mm 49,080.00


B83 Kaca Bening 8 mm 1.000 M2 -

733291305.xlsx ANALISA 64 /64


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

U01 Pekerja/Kenek 0.017 O/h 180,000.00 2,970.00


U04 Tukang Kayu 0.165 O/h 250,000.00 41,250.00
U14 Kepala Tukang 0.017 O/h 280,000.00 4,620.00
U15 Mandor/Pengawas 0.001 O/h 300,000.00 240.00
JUMLAH : 49,080.00
1 M2 Pemasangan 1 M2 kaca tebal 12 mm
1 3,909,580.00
Kaca wire glas tebal 12 mm 1.100 m2 3,500,000.00 3,850,000.00
Silicon sealant / lem kaca 0.070 Btl 150,000.00 10,500.00
U01 Pekerja/Kenek 0.017 O/h 180,000.00 2,970.00
U04 Tukang Kayu 0.165 O/h 250,000.00 41,250.00
U14 Kepala Tukang 0.017 O/h 280,000.00 4,620.00
U15 Mandor/Pengawas 0.001 O/h 300,000.00 240.00
JUMLAH : 3,909,580.00
2 1 M2 Pekerjan Daun Pintu Kaca Tempered 12 mm 7,868,240.00
Pekerjaan Kaca Wire Glaass 12mm 1.000 M2 3,909,580.00 3,909,580.00
Perlengkapan 1.000 Ls 3,909,580.00 3,909,580.00
U01 Pekerja/Kenek 0.017 O/h 180,000.00 2,970.00
U04 Tukang Kayu 0.165 O/h 250,000.00 41,250.00
U14 Kepala Tukang 0.017 O/h 280,000.00 4,620.00
U15 Mandor/Pengawas 0.001 O/h 300,000.00 240.00
JUMLAH : 7,868,240.00

XIII PEKERJAAN PENUTUP LANTAI DAN DINDING


131 1 M2 Pasangan Lantai Keramik 60/60 654,875.00
B144 Keramik Granitto 60 x 60 cm 1.100 Dus 320,000.00 352,000.00
B110 Pasir Pasang 0.045 M3 360,000.00 16,200.00
B01 Semen portland 8.190 Kg 2,500.00 20,475.00
B03 Semen Warna 1.620 Kg 20,000.00 32,400.00
U01 Pekerja/Kenek 0.700 O/h 180,000.00 126,000.00
U05 Tukang batu 0.350 O/h 250,000.00 87,500.00
U14 Kepala Tukang 0.035 O/h 280,000.00 9,800.00
U15 Mandor/Pengawas 0.035 O/h 300,000.00 10,500.00
JUMLAH : 654,875.00

132 1 M2 Pasang Lantai Keramik Ukuran (30 x 30 ) cm 497,294.00


B150 Tegel Keramik 30 x 30 cm 11.870 Buah 16,200.00 192,294.00
B01 Semen portland 10.000 Kg 2,500.00 25,000.00
B110 Pasir Pasang 0.045 M3 360,000.00 16,200.00
B03 Semen Warna 1.500 Kg 20,000.00 30,000.00
U01 Pekerja/Kenek 0.700 O/h 180,000.00 126,000.00
U05 Tukang batu 0.350 O/h 250,000.00 87,500.00
U14 Kepala Tukang 0.035 O/h 280,000.00 9,800.00
U15 Mandor/Pengawas 0.035 O/h 300,000.00 10,500.00
JUMLAH : 497,294.00

733291305.xlsx ANALISA 65 /65


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

133 1 M2 Pasang Lantai Keramik Ukuran (20 x 20 ) cm 504,500.00


B152 Tegel Keramik 20 x 20 cm 26.500 Buah 7,400.00 196,100.00
B01 Semen portland 10.400 Kg 2,500.00 26,000.00
B110 Pasir Pasang 0.045 M3 360,000.00 16,200.00
B03 Semen Warna 1.620 Kg 20,000.00 32,400.00
U01 Pekerja/Kenek 0.700 O/h 180,000.00 126,000.00
U05 Tukang batu 0.350 O/h 250,000.00 87,500.00
U14 Kepala Tukang 0.035 O/h 280,000.00 9,800.00
U15 Mandor/Pengawas 0.035 O/h 300,000.00 10,500.00
JUMLAH : 504,500.00

134 1 M2 Pasang Lantai Keramik Ukuran (10 x 20 ) cm, Variasi/Border 479,090.00


B153 Tegel Keramik 10 x 20 cm 33.000 Buah -
B01 Semen portland 9.800 Kg 2,500.00 24,500.00
B110 Pasir Pasang 0.045 M3 360,000.00 16,200.00
B03 Semen Warna 4.370 Kg 20,000.00 87,400.00
U01 Pekerja/Kenek 1.050 O/h 180,000.00 189,000.00
U05 Tukang batu 0.525 O/h 250,000.00 131,250.00
U14 Kepala Tukang 0.053 O/h 280,000.00 14,840.00
U15 Mandor/Pengawas 0.053 O/h 300,000.00 15,900.00
JUMLAH : 479,090.00

135 1 M2 Pasang Lantai Mosaik Ukuran (30 x 30 ) cm, Campuran Spesi 1 pc : 3 PP 394,435.00
B155 Tegel Mozaik 30 x 30 cm 11.870 Buah 6,000.00 71,220.00
B01 Semen portland 14.150 Kg 2,500.00 35,375.00
B110 Pasir Pasang 0.039 M3 360,000.00 14,040.00
B03 Semen Warna 2.000 Kg 20,000.00 40,000.00
U01 Pekerja/Kenek 0.700 O/h 180,000.00 126,000.00
U05 Tukang batu 0.350 O/h 250,000.00 87,500.00
U14 Kepala Tukang 0.035 O/h 280,000.00 9,800.00
U15 Mandor/Pengawas 0.035 O/h 300,000.00 10,500.00
JUMLAH : 394,435.00

136 1 M2 Pasang Dinding Porselen Ukuran (11 x 11) cm 393,730.00


B154 Tegel Porselin 11 x 11 cm 86.000 Buah -
B01 Semen portland 9.300 Kg 2,500.00 23,250.00
B110 Pasir Pasang 0.018 M3 360,000.00 6,480.00
B03 Semen Warna 1.500 Kg 20,000.00 30,000.00
U01 Pekerja/Kenek 1.000 O/h 180,000.00 180,000.00
U05 Tukang batu 0.500 O/h 250,000.00 125,000.00
U14 Kepala Tukang 0.050 O/h 280,000.00 14,000.00
U15 Mandor/Pengawas 0.050 O/h 300,000.00 15,000.00
JUMLAH : 393,730.00

134 1 M2 Pasang plint Dinding Keramik Ukuran (10 x 30) cm 72,410.00


B147 Keramik 10 x 30 cm 3.667 Buah 6,480.00 23,760.00
B01 Semen portland 1.140 Kg 2,500.00 2,850.00
B110 Pasir Pasang 0.003 M3 360,000.00 1,080.00
B03 Semen Warna 0.100 Kg 20,000.00 2,000.00
U01 Pekerja/Kenek 0.090 O/h 180,000.00 16,200.00
U05 Tukang batu 0.090 O/h 250,000.00 22,500.00
U14 Kepala Tukang 0.009 O/h 280,000.00 2,520.00
U15 Mandor/Pengawas 0.005 O/h 300,000.00 1,500.00
JUMLAH : 72,410.00

135 1 M2 Pasang Dinding Keramik Ukuran (20 x 25) cm 606,730.00


B151 Tegel Keramik 20 x 25 cm 21.600 Buah 11,000.00 237,600.00
B01 Semen portland 9.300 Kg 2,500.00 23,250.00
B110 Pasir Pasang 0.018 M3 360,000.00 6,480.00

733291305.xlsx ANALISA 66 /66


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

B03 Semen Warna 1.940 Kg 20,000.00 38,800.00


U01 Pekerja/Kenek 0.900 O/h 180,000.00 162,000.00
U05 Tukang batu 0.450 O/h 250,000.00 112,500.00
U14 Kepala Tukang 0.045 O/h 280,000.00 12,600.00
U15 Mandor/Pengawas 0.045 O/h 300,000.00 13,500.00
JUMLAH : 606,730.00

136 1 M2 Pasang Lantai Keramik Ukuran (10 x 20) cm 291,470.00


B153 Tegel Keramik 10 x 20 cm 50.000 Buah -
B01 Semen portland 11.380 Kg 2,500.00 28,450.00
B110 Pasir Pasang 0.042 M3 360,000.00 15,120.00
B03 Semen Warna 1.500 Kg 20,000.00 30,000.00
U01 Pekerja/Kenek 0.620 O/h 180,000.00 111,600.00
U05 Tukang batu 0.350 O/h 250,000.00 87,500.00
U14 Kepala Tukang 0.035 O/h 280,000.00 9,800.00
U15 Mandor/Pengawas 0.030 O/h 300,000.00 9,000.00
JUMLAH : 291,470.00

137 1 M' Pasang Plint Kayu Kelas II Tebal 2 cm, Lebar 10 cm 69,510.00
B116 Kayu kelas II (papan) 0.003 M3 3,750,000.00 11,250.00
B32 Paku biasa 0.050 Kg 30,000.00 1,500.00
U01 Pekerja/Kenek 0.120 O/h 180,000.00 21,600.00
U04 Tukang kayu 0.120 O/h 250,000.00 30,000.00
U14 Kepala Tukang 0.012 O/h 280,000.00 3,360.00
U15 Mandor/Pengawas 0.006 O/h 300,000.00 1,800.00
JUMLAH : 69,510.00

138 1 M' Pasangan Border Keramik 6/20 101,650.00


B148 List Keramik 6/20 cm 5.300 Buah 10,000.00 53,000.00
B01 Semen portland 1.140 Kg 2,500.00 2,850.00
B110 Pasir Pasang 0.003 M3 360,000.00 1,080.00
B03 Semen Warna 0.100 Kg 20,000.00 2,000.00
U01 Pekerja/Kenek 0.090 O/h 180,000.00 16,200.00
U05 Tukang batu 0.090 O/h 250,000.00 22,500.00
U14 Kepala Tukang 0.009 O/h 280,000.00 2,520.00
U15 Mandor/Pengawas 0.005 O/h 300,000.00 1,500.00
Jumlah 101,650.00

468 1 M2 Pemasangan Wall Paper #N/A


Wall Paper 1.200 #N/A #N/A #N/A
Perekat 0.200 #N/A #N/A #N/A
U01 Pekerja/Kenek 0.020 O/h 180,000.00 3,600.00
U08 Tukang Cat 0.200 O/h 250,000.00 50,000.00
U14 Kepala Tukang 0.002 O/h 280,000.00 560.00
U15 Mandor/Pengawas 0.003 O/h 300,000.00 750.00
JUMLAH : #N/A

XIV PEKERJAAN PENGECATAN


138 1 M2 Mengikis Bidang Permukaan Cat Tembok Lama 27,750.00
B343 Soda Api 0.050 Kg -
U01 Pekerja/Kenek 0.150 O/h 180,000.00 27,000.00
U08 Tukang Cat - O/h 250,000.00 -
U14 Kepala Tukang - O/h 280,000.00 -
U15 Mandor/Pengawas 0.003 O/h 300,000.00 750.00
JUMLAH : 27,750.00

139 1 M2 Mencuci Bidang Permukaan Cat Tembok Lama 27,750.00


B346 Sabun 0.050 -
U01 Pekerja/Kenek 0.150 O/h 180,000.00 27,000.00
733291305.xlsx ANALISA 67 /67
HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

U08 Tukang Cat - O/h 250,000.00 -


U14 Kepala Tukang - O/h 280,000.00 -
U15 Mandor/Pengawas 0.003 O/h 300,000.00 750.00
JUMLAH : 27,750.00

138 1 M2 Mendempul dan Menggosok Kayu 19,970.00


B349 Dempul 0.080 Kg -
B344 Minyak Cat 0.020 Kg 45,000.00 900.00
B142 Batu Apung 0.010 Kg -
U01 Pekerja/Kenek 0.040 O/h 180,000.00 7,200.00
U08 Tukang Cat 0.040 O/h 250,000.00 10,000.00
U14 Kepala Tukang 0.004 O/h 280,000.00 1,120.00
U15 Mandor/Pengawas 0.003 O/h 300,000.00 750.00
JUMLAH : 19,970.00

139 1 M2 Pengecatan Bidang Kayu Lama 66,900.00


B348 Plamur Kayu 0.150 Kg 65,000.00 9,750.00
B321 Cat Dasar 0.170 Kaleng 50,000.00 8,500.00
B331 Cat Kilat Kayu 0.170 Kaleng 85,000.00 14,450.00
U01 Pekerja/Kenek 0.070 O/h 180,000.00 12,600.00
U08 Tukang Cat 0.075 O/h 250,000.00 18,750.00
U14 Kepala Tukang 0.008 O/h 280,000.00 2,100.00
U15 Mandor/Pengawas 0.003 O/h 300,000.00 750.00
JUMLAH : 66,900.00

140 1 M2 Pengecatan Bidang Kayu Baru ( 1 Lapisan Plamir ), 1 Lapis Cat Dasar, 2 Lapis Cat Penutup 81,630.00
B323 Meni Kayu 0.200 Kg 120,000.00 24,000.00
B348 Plamur Kayu 0.150 Kg 65,000.00 9,750.00
B321 Cat Dasar 0.170 Kaleng 50,000.00 8,500.00
B331 Cat Kilat Kayu 0.260 Kaleng 85,000.00 22,100.00
U01 Pekerja/Kenek 0.070 O/h 180,000.00 12,600.00
U08 Tukang Cat 0.009 O/h 250,000.00 2,250.00
U14 Kepala Tukang 0.006 O/h 280,000.00 1,680.00
U15 Mandor/Pengawas 0.003 O/h 300,000.00 750.00
JUMLAH : 81,630.00

141 1 M2 Pengecatan Bidang Kayu Baru ( 1 Lapisan Plamir ), 1 Lapis Cat Dasar, 3 Lapis Cat Penutup 112,720.00
B323 Meni Kayu 0.200 Kg 120,000.00 24,000.00
B348 Plamur Kayu 0.150 Kg 65,000.00 9,750.00
B321 Cat Dasar 0.170 Kaleng 50,000.00 8,500.00
B331 Cat Kilat Kayu 0.350 Kaleng 85,000.00 29,750.00
U01 Pekerja/Kenek 0.070 O/h 180,000.00 12,600.00
U08 Tukang Cat 0.105 O/h 250,000.00 26,250.00
U14 Kepala Tukang 0.004 O/h 280,000.00 1,120.00
U15 Mandor/Pengawas 0.003 O/h 300,000.00 750.00
JUMLAH : 112,720.00

142 1 M2 Pelaburan Bidang Kayu Dengan Teak Oil 41,340.00


B341 Cat Teak oil 0.360 Kaleng -
U01 Pekerja/Kenek 0.040 O/h 180,000.00 7,200.00
U08 Tukang Cat 0.063 O/h 250,000.00 15,750.00
U14 Kepala Tukang 0.063 O/h 280,000.00 17,640.00
U15 Mandor/Pengawas 0.003 O/h 300,000.00 750.00
JUMLAH : 41,340.00

143 1 M2 Pelaburan Bidang Kayu Dengan Politur 98,800.00


B332 Politur Dasar 0.150 Kaleng 65,000.00 9,750.00
B333 Cat Vernis/Politur 0.372 Kaleng 85,000.00 31,620.00
B353 Ampelas 2.000 Lembar 15,000.00 30,000.00

733291305.xlsx ANALISA 68 /68


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

U01 Pekerja/Kenek 0.040 O/h 180,000.00 7,200.00


U08 Tukang Cat 0.060 O/h 250,000.00 15,000.00
U14 Kepala Tukang 0.016 O/h 280,000.00 4,480.00
U15 Mandor/Pengawas 0.003 O/h 300,000.00 750.00
JUMLAH : 98,800.00

144 1 M2 Pelaburan Bidang Kayu Dengan Cat Residu dan Ter 19,800.00
B338 Cat Residu 0.350 Kg -
U01 Pekerja/Kenek 0.100 O/h 180,000.00 18,000.00
U08 Tukang Cat - O/h 250,000.00 -
U14 Kepala Tukang - O/h 280,000.00 -
U15 Mandor/Pengawas 0.006 O/h 300,000.00 1,800.00
JUMLAH : 19,800.00

145 1 M2 Pelaburan Bidang Kayu Dengan Vernis 88,530.00


B333 Cat Vernis/Politur 0.150 Kaleng 85,000.00 12,750.00
B349 Dempul 0.050 Kg -
B353 Ampelas 0.100 Lembar 15,000.00 1,500.00
B351 Kuas Biasa 0.010 Buah 25,000.00 250.00
U01 Pekerja/Kenek 0.160 O/h 180,000.00 28,800.00
U08 Tukang Cat 0.160 O/h 250,000.00 40,000.00
U14 Kepala Tukang 0.016 O/h 280,000.00 4,480.00
U15 Mandor/Pengawas 0.003 O/h 300,000.00 750.00
JUMLAH : 88,530.00

146 1 M2 Pengecatan Tembok Baru ( 1 Lapis Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup ) 70,564.00
B347 Plamur Tembok 0.100 Kg 45,000.00 4,500.00
B322 Cat Dasar Tembok 0.100 Kg 80,000.00 8,000.00
B334 Cat Tembok 0.260 Kg 120,000.00 31,200.00
U01 Pekerja/Kenek 0.020 O/h 180,000.00 3,600.00
U08 Tukang Cat 0.063 O/h 250,000.00 15,750.00
U14 Kepala Tukang 0.006 O/h 280,000.00 1,764.00
U15 Mandor/Pengawas 0.003 O/h 300,000.00 750.00
Alat bantu, Scafolding 1.000 Ls 5,000.00 5,000.00
JUMLAH : 70,564.00

147 1 M2 Pengecatan Tembok Lama ( 1 Lapis Cat Dasar, 2 Lapis Cat Penutup) 53,666.00
B322 Cat Dasar Tembok 0.120 Kg 80,000.00 9,600.00
B334 Cat Tembok 0.180 Kg 120,000.00 21,600.00
U01 Pekerja/Kenek 0.028 O/h 180,000.00 5,040.00
U08 Tukang Cat 0.042 O/h 250,000.00 10,500.00
U14 Kepala Tukang 0.004 O/h 280,000.00 1,176.00
U15 Mandor/Pengawas 0.003 O/h 300,000.00 750.00
Alat bantu, Scafolding 1.000 Ls 5,000.00 5,000.00
JUMLAH : 53,666.00

148 1 M2 Pengecatan Permukaan Baja dengan Meni Besi 68,416.60


B339 Meni Besi 0.100 Kg 59,666.00 5,966.60
B351 Kuas Biasa 0.010 Buah 25,000.00 250.00
U01 Pekerja/Kenek 0.020 O/h 180,000.00 3,600.00
U08 Tukang Cat 0.200 O/h 250,000.00 50,000.00
U14 Kepala Tukang 0.020 O/h 280,000.00 5,600.00
U15 Mandor/Pengawas 0.010 O/h 300,000.00 3,000.00
JUMLAH : 68,416.60

149 1 M2 Duco Melamine Clear Dof 59,050.00


B324 Melamine IMPRA 0.250 Liter -
B344 Minyak Cat 0.250 Kg 45,000.00 11,250.00
B353 Ampelas 0.500 Lembar 15,000.00 7,500.00

733291305.xlsx ANALISA 69 /69


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

U01 Pekerja/Kenek 0.010 O/h 180,000.00 1,800.00


U08 Tukang Cat 0.100 O/h 250,000.00 25,000.00
U14 Kepala Tukang 0.025 O/h 280,000.00 7,000.00
U15 Mandor/Pengawas 0.005 O/h 300,000.00 1,500.00
A38 Alat bantu 1.000 ls 5,000.00 5,000.00
JUMLAH : 59,050.00

150 1 M2 Cat Plafon " 49,657.68


B337 Cat Plafon 0.110 Kg 28,888.00 3,177.68
U01 Pekerja/Kenek 0.080 O/h 180,000.00 14,400.00
U08 Tukang cat 0.110 O/h 250,000.00 27,500.00
U14 Kepala Tukang 0.011 O/h 280,000.00 3,080.00
U15 Mandor/Pengawas 0.005 O/h 300,000.00 1,500.00
JUMLAH : 49,657.68

151 1 M2 Cat Melamin" 117,800.00


B325 Wood Filler 0.400 Kg -
B326 Thinner 1.000 Kg -
B327 Sending 0.300 Kg - -
B328 Clear 0.300 Kg - -
B329 Pewarna 0.300 Kg -
B330 Kertas gosok 0.200 Lbr 15,000.00 3,000.00
U01 Pekerja/Kenek 0.250 O/h 180,000.00 45,000.00
U03 Tukang 0.250 O/h 250,000.00 62,500.00
U14 Kepala Tukang 0.025 O/h 280,000.00 7,000.00
U15 Mandor/Pengawas 0.001 O/h 300,000.00 300.00
JUMLAH : 117,800.00

450 1 M 2 Mengikis Bidang Permukaan Tmbok Yang Pernah Di Cat 27,750.00


B343 Soda Api 0.050 Kg -
U01 Pekerja/Kenek 0.150 O/h 180,000.00 27,000.00
U08 Tukang Cat - O/h 250,000.00 -
U14 Kepala Tukang - O/h 280,000.00 -
U15 Mandor/Pengawas 0.003 O/h 300,000.00 750.00
JUMLAH : 27,750.00

451 1 M 2 Mencuci Bidang Permukaan Tembok Yang Pernah Di Cat 27,750.00


B346 Sabun 0.050 -
U01 Pekerja/Kenek 0.150 O/h 180,000.00 27,000.00
U08 Tukang Cat - O/h 250,000.00 -
U14 Kepala Tukang - O/h 280,000.00 -
U15 Mandor/Pengawas 0.003 O/h 300,000.00 750.00
JUMLAH : 27,750.00

452 1 M 2 Mengorek Karat Cat Lama Permukaan Baja Dengancara Manual 27,750.00
B346 Sabun 0.050 -
U01 Pekerja/Kenek 0.150 O/h 180,000.00 27,000.00
U08 Tukang Cat - O/h 250,000.00 -
U14 Kepala Tukang - O/h 280,000.00 -
U15 Mandor/Pengawas 0.003 O/h 300,000.00 750.00
JUMLAH : 27,750.00

453 1 M 2 Menyabun Permukaan Tembok Lama 27,750.00


B346 Sabun 0.050 -
U01 Pekerja/Kenek 0.150 O/h 180,000.00 27,000.00
U08 Tukang Cat - O/h 250,000.00 -
U14 Kepala Tukang - O/h 280,000.00 -
U15 Mandor/Pengawas 0.003 O/h 300,000.00 750.00
JUMLAH : 27,750.00

733291305.xlsx ANALISA 70 /70


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

454 1 M 2 Mengerok Karat Atau Cat Lama Permukaan Baja Dengan Pancar Pasir ( Samblasting ) Dengan Tingkat Kebersihan Sa #N/A
Pasir Silika 40.000 #N/A #N/A #N/A
BBM 10.000 #N/A #N/A #N/A
Kompresor, Blasting Pot, Selang Dan Nozzel #N/A #N/A #N/A
Sewa Hari #N/A #N/A #N/A
U01 Pekerja/Kenek 1.600 O/h 180,000.00 288,000.00
U08 Tukang Cat 1.600 O/h 250,000.00 400,000.00
U14 Kepala Tukang 0.800 O/h 280,000.00 224,000.00
U15 Mandor/Pengawas 0.500 O/h 300,000.00 150,000.00
JUMLAH : #N/A

455 1 M 2Mendempul Dan Menggosok Kayu #N/A


Dempul Jadi 0.080 #N/A #N/A #N/A
B344 Minyak Cat 0.020 Kg 45,000.00 900.00
B142 Batu Apung 0.010 Kg -
U01 Pekerja/Kenek 0.040 O/h 180,000.00 7,200.00
U08 Tukang Cat 0.040 O/h 250,000.00 10,000.00
U14 Kepala Tukang 0.004 O/h 280,000.00 1,120.00
U15 Mandor/Pengawas 0.003 O/h 300,000.00 750.00
JUMLAH : 19,070.00

456 1 M 2Pengecatan Bidang Kayu Lama #N/A


Plamir 0.150 #N/A #N/A #N/A
Cat Dasar 0.170 #N/A #N/A #N/A
Cat Penutup 0.170 #N/A #N/A #N/A
U01 Pekerja/Kenek 0.070 O/h 180,000.00 12,600.00
U08 Tukang Cat 0.075 O/h 250,000.00 18,750.00
U14 Kepala Tukang 0.008 O/h 280,000.00 2,100.00
U15 Mandor/Pengawas 0.003 O/h 300,000.00 750.00
JUMLAH : #N/A

457 1 M 2 Pengecatan Bidang Kayu Baru ( 1 Lapisan Plamir ), 1 Lapis Cat Dasar, 2 Lapis Cat Penutup #N/A
Cat Meni 0.200 #N/A #N/A #N/A
Plamir 0.150 #N/A #N/A #N/A
Cat Dasar 0.170 #N/A #N/A #N/A
Cat Penutup 2 Kali 0.260 #N/A #N/A #N/A
U01 Pekerja/Kenek 0.070 O/h 180,000.00 12,600.00
U08 Tukang Cat 0.009 O/h 250,000.00 2,250.00
U14 Kepala Tukang 0.006 O/h 280,000.00 1,680.00
U15 Mandor/Pengawas 0.003 O/h 300,000.00 750.00
JUMLAH : #N/A

458 1 M 2 Pengecatan Bidang Kayu Baru ( 1 Lapisan Plamir ), 1 Lapis Cat Dasar, 3 Lapis Cat Penutup #N/A
Cat Meni 0.200 #N/A #N/A #N/A
Plamir 0.150 #N/A #N/A #N/A
Cat Dasar 0.170 #N/A #N/A #N/A
Cat Penutup 3 Kali 0.350 #N/A #N/A #N/A
U01 Pekerja/Kenek 0.070 O/h 180,000.00 12,600.00
U08 Tukang Cat 0.105 O/h 250,000.00 26,250.00
U14 Kepala Tukang 0.004 O/h 280,000.00 1,120.00
U15 Mandor/Pengawas 0.003 O/h 300,000.00 750.00
JUMLAH : #N/A

459 1 M 2 Pelaburan Bidang Kayu Dengan Teak Oil #N/A


Teak Oil 0.360 #N/A #N/A #N/A
U01 Pekerja/Kenek 0.040 O/h 180,000.00 7,200.00
U08 Tukang Cat 0.063 O/h 250,000.00 15,750.00
U14 Kepala Tukang 0.063 O/h 280,000.00 17,640.00

733291305.xlsx ANALISA 71 /71


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

U15 Mandor/Pengawas 0.003 O/h 300,000.00 750.00

460 1 M 2 Pelaburan Bidang Kayu Dengan Politur #N/A


Politur 0.150 #N/A #N/A #N/A
Politur Jadi 0.372 #N/A #N/A #N/A
B353 Ampelas 2.000 Lembar 15,000.00 30,000.00
U01 Pekerja/Kenek - O/h 180,000.00 -
U08 Tukang Cat 0.060 O/h 250,000.00 15,000.00
U14 Kepala Tukang 0.016 O/h 280,000.00 4,480.00
U15 Mandor/Pengawas 0.003 O/h 300,000.00 750.00
JUMLAH : 50,230.00

461 1 M 2 Pelaburan Bidang Kayu Dengan Cat Residu Dan Ter #N/A
Residu atau Ter 0.350 #N/A #N/A #N/A
U01 Pekerja/Kenek 0.100 O/h 180,000.00 18,000.00
U08 Tukang Cat - O/h 250,000.00 -
U14 Kepala Tukang - O/h 280,000.00 -
U15 Mandor/Pengawas 0.006 O/h 300,000.00 1,800.00
JUMLAH : #N/A

462 1 M2 Pelaburan Bidang Kayu Dengan Dengan Vernis #N/A


Vernis 0.150 #N/A #N/A #N/A
B349 Dempul 0.050 Kg -
B353 Ampelas 0.100 Lembar 15,000.00 1,500.00
Kuas 0.010 Buah 15,000.00 150.00
U01 Pekerja/Kenek 0.160 O/h 180,000.00 28,800.00
U08 Tukang Cat 0.160 O/h 250,000.00 40,000.00
U14 Kepala Tukang 0.016 O/h 280,000.00 4,480.00
U15 Mandor/Pengawas 0.003 O/h 300,000.00 750.00
JUMLAH : 74,180.00

463 1 M2 Pengecatan Tembok Baru ( 1 Lapis Plamir, 1 Lapis Cat Dasar,2 Lapis Cat Penutup ) #N/A
Plamir 0.100 #N/A #N/A #N/A
Cat Dasar 0.100 #N/A #N/A #N/A
Cat Penutup 2 x 0.260 #N/A #N/A #N/A
U01 Pekerja/Kenek 0.020 O/h 180,000.00 3,600.00
U08 Tukang Cat 0.063 O/h 250,000.00 15,750.00
U14 Kepala Tukang 0.006 O/h 280,000.00 1,764.00
U15 Mandor/Pengawas 0.003 O/h 300,000.00 750.00
JUMLAH : #N/A

464 1 M2 Pengecatan Tembok Lama ( 1 Lapis Cat Dasar 2 Lapis Cat Penutup #N/A
Cat Dasar 0.120 #N/A #N/A #N/A
Cat Penutup 2 x 0.180 #N/A #N/A #N/A
U01 Pekerja/Kenek 0.028 O/h 180,000.00 5,040.00
U08 Tukang Cat 0.042 O/h 250,000.00 10,500.00
U14 Kepala Tukang 0.004 O/h 280,000.00 1,176.00
U15 Mandor/Pengawas 0.003 O/h 300,000.00 750.00
JUMLAH : #N/A

465 1 M2 Melabur Tembok Dengan Kalkarium #N/A


Kalkarium 0.120 #N/A #N/A #N/A
U01 Pekerja/Kenek 0.028 O/h 180,000.00 5,040.00
U08 Tukang Cat 0.042 O/h 250,000.00 10,500.00
U14 Kepala Tukang 0.004 O/h 280,000.00 1,176.00
U15 Mandor/Pengawas 0.003 O/h 300,000.00 750.00
JUMLAH : #N/A

733291305.xlsx ANALISA 72 /72


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

466 1 M2 Melabur Tembok Dengan Kapur Sirih #N/A


B353 Ampelas 0.100 Lembar 15,000.00 1,500.00
Alang-Alang 0.250 #N/A #N/A #N/A
Perancah Kayu 0.002 #N/A #N/A #N/A
Kapur Sirih 0.150 #N/A #N/A #N/A
U01 Pekerja/Kenek 0.150 O/h 180,000.00 27,000.00
U08 Tukang Cat 0.001 O/h 250,000.00 250.00
U14 Kepala Tukang 0.000 O/h 280,000.00 28.00
U15 Mandor/Pengawas 0.003 O/h 300,000.00 750.00
JUMLAH : #N/A

467 1 M2 Melabur Tembok Lama Dengan Kapur Sirih ( Untuik Pemeliharaan ) #N/A
Peranca Kayu 0.002 #N/A #N/A #N/A
Kapur Sirih 0.300 #N/A #N/A #N/A
U01 Pekerja/Kenek 0.040 O/h 180,000.00 7,200.00
U08 Tukang Cat 0.005 O/h 250,000.00 1,250.00
U14 Kepala Tukang 0.001 O/h 280,000.00 140.00
U15 Mandor/Pengawas 0.003 O/h 300,000.00 750.00
JUMLAH : #N/A

469 1 M2 Pengecatan Permukaan Baja Dengan Meni Besi 68,316.60


B339 Meni Besi 0.100 Kg 59,666.00 5,966.60
Kuas 0.010 Buah 15,000.00 150.00
U01 Pekerja/Kenek 0.020 O/h 180,000.00 3,600.00
U08 Tukang Cat 0.200 O/h 250,000.00 50,000.00
U14 Kepala Tukang 0.020 O/h 280,000.00 5,600.00
U15 Mandor/Pengawas 0.010 O/h 300,000.00 3,000.00
JUMLAH : 62,350.00

470 1 M2 Pengecatan Permukaan Baja Dengan Meni Besi Dan Perancah #N/A
B339 Meni Besi 0.100 Kg 59,666.00 5,966.60
Kuas 0.010 Buah 15,000.00 150.00
Perancah Kayu 0.002 #N/A #N/A #N/A
U01 Pekerja/Kenek 0.250 O/h 180,000.00 45,000.00
U08 Tukang Cat 0.225 O/h 250,000.00 56,250.00
U14 Kepala Tukang 0.023 O/h 280,000.00 6,300.00
U15 Mandor/Pengawas 0.008 O/h 300,000.00 2,250.00
JUMLAH : #N/A

471 1 M2 Pengecatan Permukaan Baja Lapis Seng ( Galbani ) Secara Manual Sitem 4 Lapis Cat Konvensional Dengan Tebal 20 #N/A
Meni ( Read Lead ) A 0.100 #N/A #N/A #N/A
Meni ( Read Lead ) B 0.100 #N/A #N/A #N/A
Aluminium C 0.040 #N/A #N/A #N/A
Alluminium B 0.040 #N/A #N/A #N/A
Pengencer 0.010 #N/A #N/A #N/A
Perancah Kayu 0.002 #N/A #N/A #N/A
U01 Pekerja/Kenek 0.006 O/h 180,000.00 1,080.00
U08 Tukang Cat 0.006 O/h 250,000.00 1,500.00
U14 Kepala Tukang 0.225 O/h 280,000.00 63,000.00
U15 Mandor/Pengawas 0.008 O/h 300,000.00 2,250.00
JUMLAH : #N/A

472 1 M2 Pengecatan Permukaan Baja Lapis Seng ( Galbani ) Secara Manual Sitem 1 Lapis Cat Konvensional Dengan Tebal 20 57,240.00
B340 Cat Minyak Besi 0.300 Kg 120,000.00 36,000.00
U01 Pekerja/Kenek 0.006 O/h 180,000.00 1,080.00
U08 Tukang Cat 0.060 O/h 250,000.00 15,000.00
U14 Kepala Tukang 0.012 O/h 280,000.00 3,360.00
U15 Mandor/Pengawas 0.006 O/h 300,000.00 1,800.00
JUMLAH : 57,240.00

733291305.xlsx ANALISA 73 /73


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

473 1 M2 Pengecatan Permukaan Baja Lapis Seng ( Galbani ) Secara Manual Sitem 3 Lapis Cat Konvensional Dengan Tebal 20 #N/A
Cat Dasar 0.110 #N/A #N/A #N/A
Cat Antara 0.170 #N/A #N/A #N/A
Cat Penutup 0.080 #N/A #N/A #N/A
U01 Pekerja/Kenek 0.500 O/h 180,000.00 90,000.00
U08 Tukang Cat 0.800 O/h 250,000.00 200,000.00
U14 Kepala Tukang 0.300 O/h 280,000.00 84,000.00
U15 Mandor/Pengawas 0.200 O/h 300,000.00 60,000.00
JUMLAH : #N/A

474 1 M2 Pengecatan Permukaan Baja Lapis Seng ( Galbani ) Secara Semprot ( Airless Spray ) Dengan Sitem 1 Lapis Cat Muta #N/A
Cat Dasar 0.300 #N/A #N/A #N/A
U01 Pekerja/Kenek 0.400 O/h 180,000.00 72,000.00
U08 Tukang Cat 0.700 O/h 250,000.00 175,000.00
U14 Kepala Tukang 0.200 O/h 280,000.00 56,000.00
U15 Mandor/Pengawas 0.200 O/h 300,000.00 60,000.00
JUMLAH : #N/A

53 1 M2 Pemasangan Waterproofing Membrane 81,114.29


B58 Membrane Aspal 1.100 m2 -
A38 Alat Bantu 1.000 ls 5,000.00 5,000.00
U01 Pekerja/Kenek 0.143 O/h 180,000.00 25,714.29
U04 Tukang Kayu 0.150 O/h 250,000.00 37,500.00
U14 Kepala Tukang 0.030 O/h 280,000.00 8,400.00
U15 Mandor/Pengawas 0.015 O/h 300,000.00 4,500.00
JUMLAH : 81,114.29

105 1 M2 Water Proofing


B345 Water proofing 2.900 Kg 250,000.00 725,000.00
U01 Pekerja/Kenek 0.300 O/h 180,000.00 54,000.00
U05 Tukang batu 0.200 O/h 250,000.00 50,000.00
U14 Kepala Tukang 0.020 O/h 280,000.00 5,600.00
U15 Mandor/Pengawas 0.015 O/h 300,000.00 4,500.00
JUMLAH : 839,100.00

1 1 M2 Water Proofing (Coating) 131,489.58


pre treatment/ cleaning 1.000 m2 20,500.00 20,500.00
curbing sudut 0.003 m' 25,000.00 69.44
bahan waterproofting coating 0.087 kg 385,000.00 33,420.14
sewa mixer 0.010 bh 550,000.00 5,500.00
kuas 0.010 bh 25,000.00 250.00
U05 tukang batu 0.100 O/h 250,000.00 25,000.00
U14 kepala tukang 0.025 O/h 280,000.00 7,000.00
U01 Pekerja/Kenek 0.200 O/h 180,000.00 36,000.00
U15 Mandor/Pengawas 0.013 O/h 300,000.00 3,750.00
JUMLAH : 131,489.58

PEKERJAAN LISTRIK
151 1 Titik Instalasi Lampu / Penerangan 856,150.00
B235 Kabel NYM 3 X 2,5 mm2 4.500 m 20,800.00 93,600.00
B234 Kabel NYM 2 X 2,5 mm2 10.000 m 16,240.00 162,400.00
B243 Pipa Clipsal PVC 3/4 5.000 Bh 8,750.00 43,750.00
B244 Pipa PVC Maspion 5/8 3.500 Bh 6,800.00 23,800.00
B245 T.Doos PVC 3/4 2.000 Bh 5,000.00 10,000.00

733291305.xlsx ANALISA 74 /74


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

B246 Elbo Clipsal PVC 3/4 2.000 Bh 5,000.00 10,000.00


B241 Klem PVC Clipsal 4.000 m 5,675.00 22,700.00
B247 Sock PVC Clipsal 3/4 1.000 Bh 5,000.00 5,000.00
B242 Las Dop Legrand 4 mm2 3.000 Bh 5,800.00 17,400.00
B248 Isolasi Unibel 0.250 Bh 22,000.00 5,500.00
Lampu SL 18 Watt + Fitting 1.000 #N/A 185,000.00 185,000.00
U01 Pekerja/Kenek 0.750 O/h 180,000.00 135,000.00
U10 Tukang Listrik 0.500 O/h 250,000.00 125,000.00
U14 Kepala Tukang 0.050 O/h 280,000.00 14,000.00
U15 Mandor/Pengawas 0.010 O/h 300,000.00 3,000.00
JUMLAH : 856,150.00

152 1 Titik Instalasi Stop Kontak / Power Outlet 921,000.00


B235 Kabel NYM 3 x 2,5 mm2 12.000 m 20,800.00 249,600.00
B243 Pipa Clipsal PVC 3/4 12.000 Bh 8,750.00 105,000.00
B244 Pipa PVC Maspion 5/8 3.500 Bh 6,800.00 23,800.00
B245 T.Doos PVC 3/4 2.000 Bh 5,000.00 10,000.00
B246 Elbo Clipsal PVC 3/4 2.000 Bh 5,000.00 10,000.00
B241 Klem PVC Clipsal 4.000 m 5,675.00 22,700.00
B247 Sock PVC Clipsal 3/4 3.000 Bh 5,000.00 15,000.00
B242 Las Dop Legrand 4 mm2 3.000 Bh 5,800.00 17,400.00
Stop Kontok 1.000 #N/A 185,000.00 185,000.00
B248 Isolasi Unibel 0.250 Bh 22,000.00 5,500.00
U01 Pekerja/Kenek 0.750 O/h 180,000.00 135,000.00
U10 Tukang Listrik 0.500 O/h 250,000.00 125,000.00
U14 Kepala Tukang 0.050 O/h 280,000.00 14,000.00
U15 Mandor/Pengawas 0.010 O/h 300,000.00 3,000.00
JUMLAH : 921,000.00

153 1 Titik Instalasi Ac 1 Phase 1,639,750.00


B236 Kabel NYM 3 x 4 mm2 30.000 m 29,000.00 870,000.00
B243 Pipa Clipsal PVC 3/4 30.000 Bh 8,750.00 262,500.00
B246 Elbo Clipsal PVC 3/4 2.000 Bh 5,000.00 10,000.00
B247 Sock PVC Clipsal 3/4 10.000 Bh 5,000.00 50,000.00
B241 Klem PVC Clipsal 30.000 m 5,675.00 170,250.00
U01 Pekerja/Kenek 0.750 O/h 180,000.00 135,000.00
U10 Tukang Listrik 0.500 O/h 250,000.00 125,000.00
U14 Kepala Tukang 0.050 O/h 280,000.00 14,000.00
U15 Mandor/Pengawas 0.010 O/h 300,000.00 3,000.00
JUMLAH : 1,639,750.00

154 1 Titik Instalasi Ac 3 Phase 2,119,750.00


B237 Kabel NYM 4 x 4 mm2 30.000 m 45,000.00 1,350,000.00
B243 Pipa Clipsal PVC 3/4 30.000 Bh 8,750.00 262,500.00
B246 Elbo Clipsal PVC 3/4 2.000 Bh 5,000.00 10,000.00
B247 Sock PVC Clipsal 3/4 10.000 Bh 5,000.00 50,000.00
B241 Klem PVC Clipsal 30.000 m 5,675.00 170,250.00
U01 Pekerja/Kenek 0.750 O/h 180,000.00 135,000.00
U10 Tukang Listrik 0.500 O/h 250,000.00 125,000.00
U14 Kepala Tukang 0.050 O/h 280,000.00 14,000.00
U15 Mandor/Pengawas 0.010 O/h 300,000.00 3,000.00
JUMLAH : 2,119,750.00

155 1 Titik Instalasi Sound System 791,600.00


B238 Kabel NYM HY 3 X 2,5 mm2 12.000 m 20,800.00 249,600.00
B243 Pipa Clipsal PVC 3/4 12.000 Bh 8,750.00 105,000.00
B244 Pipa PVC Maspion 5/8 5.000 Bh 6,800.00 34,000.00
B245 T.Doos PVC 3/4 2.000 Bh 5,000.00 10,000.00

733291305.xlsx ANALISA 75 /75


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

B246 Elbo Clipsal PVC 3/4 2.000 Bh 5,000.00 10,000.00


B241 Klem PVC Clipsal 12.000 m 5,675.00 68,100.00
B247 Sock PVC Clipsal 3/4 3.000 Bh 5,000.00 15,000.00
B242 Las Dop Legrand 4 mm2 3.000 Bh 5,800.00 17,400.00
B248 Isolasi Unibel 0.250 Bh 22,000.00 5,500.00
U01 Pekerja/Kenek 0.750 O/h 180,000.00 135,000.00
U10 Tukang Listrik 0.500 O/h 250,000.00 125,000.00
U14 Kepala Tukang 0.050 O/h 280,000.00 14,000.00
U15 Mandor/Pengawas 0.010 O/h 300,000.00 3,000.00
JUMLAH : 791,600.00

156 1 Titik Instalasi Telephone 755,350.00


B233 Kabel ITC 2 x 2 x 0.6 mm2 35.000 m -
B243 Pipa Clipsal PVC 3/4 35.000 Bh 8,750.00 306,250.00
B244 Pipa PVC Maspion 5/8 5.000 Bh 6,800.00 34,000.00
B245 T.Doos PVC 3/4 1.000 Bh 5,000.00 5,000.00
B246 Elbo Clipsal PVC 3/4 3.000 Bh 5,000.00 15,000.00
B241 Klem PVC Clipsal 12.000 m 5,675.00 68,100.00
B247 Sock PVC Clipsal 3/4 10.000 Bh 5,000.00 50,000.00
U01 Pekerja/Kenek 0.750 O/h 180,000.00 135,000.00
U10 Tukang Listrik 0.500 O/h 250,000.00 125,000.00
U14 Kepala Tukang 0.050 O/h 280,000.00 14,000.00
U15 Mandor/Pengawas 0.010 O/h 300,000.00 3,000.00
JUMLAH : 755,350.00

157 1 Titik Instalasi Fire Alarm 748,675.00


B234 Kabel NYM 2 X 2,5 mm2 15.000 m 16,240.00 243,600.00
B243 Pipa Clipsal PVC 3/4 15.000 Bh 8,750.00 131,250.00
B245 T.Doos PVC 3/4 1.000 Bh 5,000.00 5,000.00
B246 Elbo Clipsal PVC 3/4 2.000 Bh 5,000.00 10,000.00
B241 Klem PVC Clipsal 7.000 m 5,675.00 39,725.00
B247 Sock PVC Clipsal 3/4 5.000 Bh 5,000.00 25,000.00
B242 Las Dop Legrand 4 mm2 2.000 Bh 5,800.00 11,600.00
B248 Isolasi Unibel 0.250 Bh 22,000.00 5,500.00
U01 Pekerja/Kenek 0.750 O/h 180,000.00 135,000.00
U10 Tukang Listrik 0.500 O/h 250,000.00 125,000.00
U14 Kepala Tukang 0.050 O/h 280,000.00 14,000.00
U15 Mandor/Pengawas 0.010 O/h 300,000.00 3,000.00
JUMLAH : 748,675.00

156 Pemasangan Penangkal Petir(Unit) 28,629,500.00


U01 Pekerja/Kenek 2.000 O/h 180,000.00 360,000.00
U15 Mandor/Pengawas 0.050 O/h 300,000.00 15,000.00
U14 Kepala Tukang 0.050 O/h 280,000.00 14,000.00
U10 Tukang Listrik 0.500 O/h 250,000.00 125,000.00
Split Tembaga dia. 1 1.000 bh 250,000.00 250,000.00
Timah 0.500 kg 55,000.00 27,500.00
Pipa Arde 6.000 m' 225,000.00 1,350,000.00
Pipa Galvanis Dia. 1" (6m) 0.250 Ljr 450,000.00 112,500.00
Pipa PVC tipe AW Dia 1/2 (6m) 10.000 Ljr 75,000.00 750,000.00
Kawat BC 26.000 m' 100,000.00 2,600,000.00
Air Curtain 1.000 unit 15,000,000.00 15,000,000.00
Grounding/Pentanahan 1.000 unit 8,025,500.00 8,025,500.00
JUMLAH : 28,629,500.00

157 1 Set Grounding Pentanahan 8,025,500.00


Pipa GIV Dia 2" 3.000 m' 62,500.00 187,500.00
B239 Kawat BC 2,5 mm 2.000 o/h 255,000.00 510,000.00
B240 Kabel BC 50 mm 3.000 o/h 2,176,000.00 6,528,000.00

733291305.xlsx ANALISA 76 /76


HARGA SATUAN
NO. KODE URAIAN KOEFISIEN SATUAN ( Rp )
TOTAL HARGA ( Rp )

Box Pengaman Pasangan Batu Tela 1.000 o/h 525,000.00 525,000.00


Upah Kerja 1.000 o/h 275,000.00 275,000.00
JUMLAH : 8,025,500.00

1 Ttk Lampu Tl 2 X 20 Watt


Lampu TL 2 x 20 Watt 1.000 #N/A #N/A #N/A
Kabel NGA 2,5 x 2 12.000 #N/A #N/A #N/A
U10 Tukang Listrik 0.250 O/h 250,000.00 62,500.00
U01 Pekerja/Kenek 0.050 O/h 180,000.00 9,000.00
JUMLAH : #N/A

1 Ttk Lampu Tl 20 Watt


Lampu TL 20 Watt 1.000 #N/A #N/A #N/A
Kabel NGA 2,5 x 2 12.000 #N/A #N/A #N/A
U10 Tukang Listrik 0.250 O/h 250,000.00 62,500.00
U01 Pekerja/Kenek 0.050 O/h 180,000.00 9,000.00
JUMLAH : #N/A

1 Ttk Lampu Pijar 40 Watt


Lampu Pinjar 40 Watt 1.0000 #N/A #N/A #N/A
Kabel NGA 2,5 x 2 12.0000 #N/A #N/A #N/A
U10 Tukang Listrik 0.2500 O/h 250,000.00 62,500.00
U01 Pekerja/Kenek 0.0500 O/h 180,000.00 9,000.00
JUMLAH : #N/A

1 Bh. Stop Kontak 2 Fase


Stop Kontak 2 Fase 1.0000 #N/A #N/A #N/A
Kabel NGA 2,5 x 2 10.0000 #N/A #N/A #N/A
U10 Tukang Listrik 0.2500 O/h 250,000.00 62,500.00
U01 Pekerja/Kenek 0.0500 O/h 180,000.00 9,000.00
JUMLAH : #N/A

1 Bh. Sekring Box 2 Group 412,500.00


Sekring Box 1.0000 #N/A 350,000.00 350,000.00
U10 Tukang Listrik 0.2500 O/h 250,000.00 62,500.00
JUMLAH : 412,500.00

1 Bh. Panel Instalasi


Panel Instalasi 1.0000 #N/A #N/A #N/A
Kabel NYM 3 x 2,5 10.0000 #N/A #N/A #N/A
Kabel NYF GbY 4 x 25 2.0000 #N/A #N/A #N/A
U10 Tukang Listrik 0.2500 O/h 250,000.00 62,500.00
JUMLAH : #N/A

1 Bh Saklar Double 212,500.00


Saklar Double 1.0000 #N/A 50,000.00 50,000.00
Kabel NGA 2,5 x 2 10.0000 #N/A 10,000.00 100,000.00
U10 Tukang Listrik 0.2500 O/h 250,000.00 62,500.00
JUMLAH : 212,500.00

1 Bh Saklar Tunggal 202,500.00


Saklar Tunggal 1.0000 #N/A 40,000.00 40,000.00
Kabel NGA 2,5 x 2 10.0000 #N/A 10,000.00 100,000.00
U10 Tukang Listrik 0.2500 O/h 250,000.00 62,500.00
JUMLAH : 202,500.00

733291305.xlsx ANALISA 77 /77


ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan : Uitset Pengukuran Jarak


Satuan / Unit : M'
Analisa : AHSP PU - T.04

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja/Kenek OH 0.0120 180,000.00 2,160
2 Asisten ahli ukur OH 0.0040 200,000.00 800
3 Juru Ukur OH 0.0040 280,000.00 1,120
Jumlah Tenaga Kerja 4,080
B. BAHAN

Jumlah Bahan
C. PERALATAN
1 Water Pass Sewa-Hari 0.0040 -
2 Theodolit Sewa-Hari 0.0040 -

Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 4,080
E Overhead & Profit 15% X D 612
F Harga Satuan Pekerjaan ( D + E ) 4,692

ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan : Memasang 1 M' pipa PVC dia. 200 mm


Satuan / Unit : M'
Analisa : AHSP PU A.8.4.1.5

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja/Kenek OH 0.1890 180,000.00 34,020
2 Tukang OH 0.0950 250,000.00 23,750
3 Mandor/Pengawas OH 0.0190 300,000.00 5,700
Jumlah Tenaga Kerja 63,470
B. BAHAN

Jumlah Bahan
C. PERALATAN

Jumlah Peralatan
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 63,470
E Overhead & Profit 15% X D 9,521
F Harga Satuan Pekerjaan ( D + E ) 72,991
ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan : Memasang 1 M' pipa Steel dia. 200 mm


Satuan / Unit : M'
Analisa : AHSP PU A.8.4.1.68

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja/Kenek OH 1.1130 180,000.00 200,340
2 Tukang OH 0.2230 250,000.00 55,750
3 Mandor/Pengawas OH 0.1110 300,000.00 33,300
Jumlah Tenaga Kerja 289,390
B. BAHAN

Jumlah Bahan
C. PERALATAN

Jumlah Peralatan
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 289,390
E Overhead & Profit 15% X D 43,409
F Harga Satuan Pekerjaan ( D + E ) 332,799

ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan : Pengecatan Permukaan Baja Secara Manual 2 Lapis


Satuan / Unit : M2
Analisa : AHSP PU A.4.7.1.20

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja/Kenek OH 0.4000 180,000.00 72,000
2 Tukang OH 0.8000 250,000.00 200,000
3 Kepala Tukang OH 0.0800 280,000.00 22,400
4 Mandor/Pengawas OH 0.0200 300,000.00 6,000
Jumlah Tenaga Kerja 300,400
B. BAHAN
1 Cat Dasar Kg 0.1100 #N/A #N/A
2 Cat Penutup/ epoxy Kg 0.0800 #N/A #N/A
3 Kuas Bh 0.0100 15,000.00 150
4 Pengencer Liter 0.0100 #N/A #N/A
Jumlah Bahan #N/A
C. PERALATAN

Jumlah Peralatan
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) #N/A
E Overhead & Profit 15% X D #N/A
F Harga Satuan Pekerjaan ( D + E ) #N/A
ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan : Memasang 1 M' pipa Steel dia. 150 mm


Satuan / Unit : M'
Analisa : AHSP PU A.8.4.1.67

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja/Kenek OH 0.7080 180,000.00 127,440
2 Tukang OH 0.1420 250,000.00 35,500
3 Kepala Tukang OH 280,000.00 -
4 Mandor/Pengawas OH 0.0710 300,000.00 21,300
Jumlah Tenaga Kerja 184,240
B. BAHAN
Jumlah Bahan
C. PERALATAN

Jumlah Peralatan
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 184,240
E Overhead & Profit 15% X D 27,636
F Harga Satuan Pekerjaan ( D + E ) 211,876

ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan : Pengetesan Pipa dia. 200 mm


Satuan / Unit : M'
Analisa : AHSP PU A.8.4.5.5

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja/Kenek OH 0.0080 180,000.00 1,440
2 Mandor/Pengawas OH 0.0010 300,000.00 300
Jumlah Tenaga Kerja 1,740
B. BAHAN
1 Air Bersih untuk Pengetesan M3 0.0310 #N/A #N/A
2 Bahan Bakar Solar Liter 0.0600 #N/A #N/A
3 Oli Liter 0.0020 #N/A #N/A
Jumlah Bahan #N/A
C. PERALATAN

Jumlah Peralatan
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) #N/A
E Overhead & Profit 15% X D #N/A
F Harga Satuan Pekerjaan ( D + E ) #N/A

ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan : Pengelasan Flange dia. 200 mm


Satuan / Unit : Bh
Analisa : Anl. L. F. 5

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja/Kenek OH 0.7910 180,000.00 142,380
2 Tukang OH 0.3960 250,000.00 99,000
3 Kepala Tukang OH 0.0400 280,000.00 11,200
4 Mandor/Pengawas OH 0.0400 300,000.00 12,000
Jumlah Tenaga Kerja 264,580
B. BAHAN
1 Kawat Las Listrik Kg 7.9130 225,000.00 1,780,425
2 Solar Liter 5.9350 5,800.00 34,423
3 Minyak Pelumas Liter 0.7910 45,000.00 35,595
Jumlah Bahan 1,850,443
C. PERALATAN
1 Sewa Mesin Las Jam 0.3360 50,000 50,000
Jumlah Peralatan
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 2,165,023
E Overhead & Profit 15% X D 324,753
F Harga Satuan Pekerjaan ( D + E ) 2,489,776

ANALISA HARGA SATUAN PEKERJAAN


Jenis Pekerjaan : Pengelasan Pipa Steel dia. 150 mm
Satuan / Unit : Titik
Analisa : Anl. L. 4

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja/Kenek OH 0.4010 180,000.00 72,180
2 Tukang OH 0.2010 250,000.00 50,250
3 Kepala Tukang OH 0.0200 280,000.00 5,600
4 Mandor/Pengawas OH 0.0200 300,000.00 6,000
Jumlah Tenaga Kerja 134,030
B. BAHAN
1 Kawat Las Listrik Kg 4.0120 225,000.00 902,700
2 Solar Liter 3.0090 5,800.00 17,452
3 Minyak Pelumas Liter 0.4010 45,000.00 18,045
Jumlah Bahan 938,197
C. PERALATAN
1 Sewa Mesin Las Jam 0.1705 #N/A #N/A
Jumlah Peralatan #N/A
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) #N/A
E Overhead & Profit 15% XD #N/A
F Harga Satuan Pekerjaan ( D + E ) #N/A
ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan : Pengelasan Pipa Steel dia. 200 mm


Satuan / Unit : Titik
Analisa : Anl. L. 5

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja/Kenek OH 0.5280 180,000.00 95,040
2 Tukang OH 0.2640 250,000.00 66,000
3 Kepala Tukang OH 0.0260 280,000.00 7,280
4 Mandor/Pengawas OH 0.0260 300,000.00 7,800
Jumlah Tenaga Kerja 176,120
B. BAHAN
1 Kawat Las Listrik Kg 5.2750 225,000.00 1,186,875
2 Solar Liter 3.9560 5,800.00 22,945
3 Minyak Pelumas Liter 0.5280 45,000.00 23,760
Jumlah Bahan 1,233,580
C. PERALATAN
1 Sewa Mesin Las Jam 0.2240 #N/A 50,000
Jumlah Peralatan 50,000
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 1,459,700
E Overhead & Profit 15% X D 218,955
F Harga Satuan Pekerjaan ( D + E ) 1,678,655

ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan : Pengelasan Pipa Steel dia. 250 mm


Satuan / Unit : Titik
Analisa : Anl. L. 6

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja/Kenek OH 0.5280 180,000.00 95,040
2 Tukang OH 0.2640 250,000.00 66,000
3 Kepala Tukang OH 0.0260 280,000.00 7,280
4 Mandor/Pengawas OH 0.0260 300,000.00 7,800
Jumlah Tenaga Kerja 176,120
B. BAHAN
1 Kawat Las Listrik Kg 6.5310 225,000.00 1,469,475
2 Solar Liter 4.8980 5,800.00 28,408
3 Minyak Pelumas Liter 0.6530 45,000.00 29,385
Jumlah Bahan 1,527,268
C. PERALATAN
1 Sewa Mesin Las Jam 0.2776 #N/A 50,000
Jumlah Peralatan 50,000
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 1,753,388
E Overhead & Profit 15% X D 263,008
F Harga Satuan Pekerjaan ( D + E ) 2,016,397
ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan : Pengelasan Flange dia. 150 mm


Satuan / Unit : Titik
Analisa : Anl. L. F. 4

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja/Kenek OH 0.6020 180,000.00 108,360
2 Tukang OH 0.3010 250,000.00 75,250
3 Kepala Tukang OH 0.0300 280,000.00 8,400
4 Mandor/Pengawas OH 0.0300 300,000.00 9,000
Jumlah Tenaga Kerja 201,010
B. BAHAN
1 Kawat Las Listrik Kg 6.0175 225,000.00 1,353,938
2 Solar Liter 4.5131 5,800.00 26,176
3 Minyak Pelumas Liter 0.6017 45,000.00 27,077
Jumlah Bahan 1,407,190
C. PERALATAN
1 Sewa Mesin Las Jam 0.2557 #N/A 50,000
Jumlah Peralatan 50,000
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 1,658,200
E Overhead & Profit 15% X D 248,730
F Harga Satuan Pekerjaan ( D + E ) 1,906,930

ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan : Pengelasan Flange dia. 250 mm


Satuan / Unit : Titik
Analisa : Anl. L. F. 6

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja/Kenek OH 0.9800 180,000.00 176,400
2 Tukang OH 0.4900 250,000.00 122,500
3 Kepala Tukang OH 0.0490 280,000.00 13,720
4 Mandor/Pengawas OH 0.0490 300,000.00 14,700
Jumlah Tenaga Kerja 327,320
B. BAHAN
1 Kawat Las Listrik Kg 9.7968 225,000.00 2,204,280
2 Solar Liter 7.3476 5,800.00 42,616
3 Minyak Pelumas Liter 0.9797 45,000.00 44,087
Jumlah Bahan 2,290,983
C. PERALATAN
1 Sewa Mesin Las Jam 0.4164 #N/A 50,000
Jumlah Peralatan 50,000
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 2,668,303
E Overhead & Profit 15% X D 400,245
F Harga Satuan Pekerjaan ( D + E ) 3,068,548
ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan : Pemotongan Pipa Steel dia. 200 mm


Satuan / Unit : Bh
Analisa : AHSP PU A.8.4.2.68

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja/Kenek OH 0.4760 180,000.00 85,680
2 Tukang OH 0.0950 250,000.00 23,750
3 Mandor/Pengawas OH 0.0480 300,000.00 14,400
Jumlah Tenaga Kerja 123,830
B. BAHAN

Jumlah Bahan
C. PERALATAN
1 Peralatan Potong Pipa T2/Mekanik/Clinder Saw hari 0.0600 #N/A #N/A
Jumlah Peralatan #N/A
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) #N/A
E Overhead & Profit 15% X D #N/A
F Harga Satuan Pekerjaan ( D + E ) #N/A

ANALISA HARGA SATUAN PEKERJAAN


Jenis Pekerjaan : Memasang 1 M' pipa Steel dia. 250 mm
Satuan / Unit : M'
Analisa : AHSP PU A.8.4.1.69

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja/Kenek OH 1.3250 180,000.00 238,500
2 Tukang OH 0.2650 250,000.00 66,250
3 Kepala Tukang OH - 280,000.00 -
4 Mandor/Pengawas OH 0.1330 300,000.00 39,900
Jumlah Tenaga Kerja 344,650
B. BAHAN

Jumlah Bahan -
C. PERALATAN

Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 344,650
E Overhead & Profit 15% X D 51,698
F Harga Satuan Pekerjaan ( D + E ) 396,348
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Memasang 1 M' pipa Steel dia. 250 mm
Satuan / Unit : 1 Buah
Analisa : AHSP PU A.8.4.3.3

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja/Kenek OH 1.7140 180,000.00 308,520
2 Tukang OH 0.8570 250,000.00 214,250
3 Kepala Tukang OH 280,000.00 -
4 Mandor/Pengawas OH 0.1710 300,000.00 51,300
Jumlah Tenaga Kerja 574,070
B. BAHAN

Jumlah Bahan -
C. PERALATAN

Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 574,070
E Overhead & Profit 15% X D 86,111
F Harga Satuan Pekerjaan ( D + E ) 660,181

ANALISA HARGA SATUAN PEKERJAAN


Jenis Pekerjaan : Pemasangan Valve dia. 50 - 150 mm
Satuan / Unit : 1 Buah
Analisa : AHSP PU A.8.4.3.1

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja/Kenek OH 1.4290 180,000.00 257,220
2 Tukang OH 0.7150 250,000.00 178,750
3 Kepala Tukang OH - 280,000.00 -
4 Mandor/Pengawas OH 0.1430 300,000.00 42,900
Jumlah Tenaga Kerja 478,870
B. BAHAN

Jumlah Bahan -
C. PERALATAN

Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 478,870
E Overhead & Profit 15% X D 71,831
F Harga Satuan Pekerjaan ( D + E ) 550,701
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Pemasangan Accessories dia. 200 mm
Satuan / Unit : 1 Buah
Analisa : AHSP PU A.8.4.3.16

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja/Kenek OH 0.2160 180,000.00 38,880
2 Tukang OH 0.1080 250,000.00 27,000
4 Mandor/Pengawas OH 0.0220 300,000.00 6,600
Jumlah Tenaga Kerja 72,480
B. BAHAN
1
2
Jumlah Bahan
C. PERALATAN
1
2
3
Jumlah Peralatan
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 72,480
E Overhead & Profit 15% X D 10,872
F Harga Satuan Pekerjaan ( D + E ) 83,352

ANALISA HARGA SATUAN PEKERJAAN


Jenis Pekerjaan : Pemasangan Accessories dia. 250 mm
Satuan / Unit : 1 Buah
Analisa : AHSP PU A.8.4.3.17

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja/Kenek OH 0.3260 180,000.00 58,680
2 Tukang OH 0.1630 250,000.00 40,750
3 Kepala Tukang OH 280,000.00 -
4 Mandor/Pengawas OH 0.0330 300,000.00 9,900
Jumlah Tenaga Kerja 109,330
B. BAHAN

Jumlah Bahan -
C. PERALATAN

Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 109,330
E Overhead & Profit 15% X D 16,400
F Harga Satuan Pekerjaan ( D + E ) 125,730
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Pemasangan Accessories dia. 50 - 150 mm
Satuan / Unit : 1 Buah
Analisa : AHSP PU A.8.4.3.15

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja/Kenek OH 0.1060 180,000.00 19,080
2 Tukang OH 0.0530 250,000.00 13,250
3 Kepala Tukang OH - 280,000.00
4 Mandor/Pengawas OH 0.0110 300,000.00 3,300
Jumlah Tenaga Kerja 35,630
B. BAHAN
1
2
Jumlah Bahan
C. PERALATAN
1
2
3
Jumlah Peralatan
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 35,630
E Overhead & Profit 15% X D 5,345
F Harga Satuan Pekerjaan ( D + E ) 40,975

ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan : Bongkaran Aspal Hotmix dan Beton


Satuan / Unit : M2
Analisa : Analisa EI-428.A

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja/Kenek OH 2.5460 180,000.00 458,280
4 Mandor/Pengawas OH 0.2550 300,000.00 76,500
Jumlah Tenaga Kerja 534,780
B. BAHAN
1 Solar Jam 1.0000 5,800.00 5,800
2 5,800
Jumlah Bahan
C. PERALATAN
1 Sewa Jack Hammer dan Mesin Cutter Jam 0.2500 #N/A #N/A
2
3
Jumlah Peralatan #N/A
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) #N/A
E Overhead & Profit 15% X D #N/A
F Harga Satuan Pekerjaan ( D + E ) #N/A
ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan : Penyambungan Pipa Baru Ke Pipa Lama dia. 200 mm


Satuan / Unit : 1 Buah
Analisa : AHSP PU A.8.4.4.4

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja/Kenek OH 2.5460 180,000.00 458,280
2 Tukang OH 1.2730 250,000.00 318,250
4 Mandor/Pengawas OH 0.2550 300,000.00 76,500
Jumlah Tenaga Kerja 853,030
B. BAHAN
1
2
Jumlah Bahan
C. PERALATAN
1 Peralatan Potong Pipa T2/Mekanik/Clinder Saw Hari 0.8700 #N/A #N/A
2
3
Jumlah Peralatan #N/A
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) #N/A
E Overhead & Profit 15% X D #N/A
F Harga Satuan Pekerjaan ( D + E ) #N/A

ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan : Pemotongan Pipa Steel dia. 250 mm


Satuan / Unit : 1 Buah
Analisa : AHSP PU A.8.4.2.69

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja/Kenek OH 0.6630 180,000.00 119,340
2 Tukang OH 0.1330 250,000.00 33,250
3 Kepala Tukang OH - -
4 Mandor/Pengawas OH 0.0660 300,000.00 19,800
Jumlah Tenaga Kerja 172,390
B. BAHAN
1
2
Jumlah Bahan
C. PERALATAN
1 Peralatan Potong Pipa T2/Mekanik/Clinder Saw Hari 0.0680 #N/A #N/A
2
3
Jumlah Peralatan #N/A
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) #N/A
E Overhead & Profit 15% X D #N/A
F Harga Satuan Pekerjaan ( D + E ) #N/A
ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan : Pemotongan Pipa Steel dia. 150 mm


Satuan / Unit : 1 Buah
Analisa : AHSP PU A.8.4.2.67

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja/Kenek OH 0.1840 180,000.00 33,120
2 Tukang OH 0.0370 250,000.00 9,250
3 Kepala Tukang OH - 280,000.00 -
4 Mandor/Pengawas OH 0.0180 300,000.00 5,400
Jumlah Tenaga Kerja 47,770
B. BAHAN
1
2
Jumlah Bahan
C. PERALATAN
1 Peralatan Potong Pipa T2/Mekanik/Clinder Saw Hari 0.0450 #N/A #N/A
2
3
Jumlah Peralatan #N/A
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) #N/A
E Overhead & Profit 15% X D #N/A
F Harga Satuan Pekerjaan ( D + E ) #N/A
ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan : Beton Mutu F'c = 19,3 Mpa (K 225), Slump (12 ± 2) cm, W/c = 0,58
Satuan / Unit : M3
Analisa : AHSP PU A.4.1.1.7

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga

A. TENAGA
1 Pekerja/Kenek L.01 OH 1,6500 180,000.00 #VALUE!
2 Tukang L.02 OH 0,2750 250,000.00 #VALUE!
3 Kepala Tukang L.03 OH 0,0280 280,000.00 #VALUE!
4 Mandor/Pengawas L.04 OH 0,0830 300,000.00 #VALUE!
Jumlah Tenaga Kerja #VALUE!
B. BAHAN
1 Semen Portland Kg 371,0000 2,500.00 #VALUE!
2 Pasir Beton Kg 698,0000 #N/A #N/A
3 Kerikil Kg 1.047,0000 480,000.00 #VALUE!
4 Air Liter 215,0000 #N/A #N/A
Jumlah Bahan #VALUE!
C. PERALATAN
1 Peralatan Potong Pipa T2/Mekanik/Clinder Saw Hari 0.0450 #N/A #N/A
2
3
Jumlah Peralatan #N/A
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) #N/A
E Overhead & Profit 15% X D #N/A
F Harga Satuan Pekerjaan ( D + E ) #N/A

ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan : Memasang Bekisting Untuk Kolom


Satuan / Unit : M2
Analisa : AHSP PU A.4.1.1.22

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA

1 Pekerja/Kenek L.01 OH 0,6600 180,000.00 #VALUE!


2 Tukang L.02 OH 0,3300 250,000.00 #VALUE!
3 Kepala Tukang L.03 OH 0,0330 280,000.00 #VALUE!
4 Mandor/Pengawas L.04 OH 0,0330 300,000.00 #VALUE!
Jumlah Tenaga Kerja #VALUE!
B. BAHAN

1 Kayu Kelas III M3 0,0400 #N/A #N/A


2 Paku 5 cm - 12 cm Kg 0,4000 #N/A #N/A
3 Minyak Bekisting Liter 0,2000 #N/A #N/A
4 Balok Kayu Kelas II M3 0,0150 #N/A #N/A
5 Plywood tebal 9 mm Lbr 0,3500 #N/A #N/A
6 kayu dolken dia. 8-10 cm, L = 4 M Batang 2,0000 #N/A #N/A
Jumlah Bahan #N/A
C. PERALATAN

Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) -
E Bekisting Dipakai 2 x = D / 2 #N/A
F Overhead & Profit 15% X E #N/A
G Harga Satuan Pekerjaan ( E + F ) #N/A
ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan Pemotongan Pipa Steel dia. 100 mm


Satuan / Unit Bh
Analisa AHSP PU A.8.4.2.65

No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA

1 Pekerja/Kenek L.01 OH 0,085 180,000.00 15,300,000


2 Tukang L.02 OH 0,017 250,000.00 4,250,000
3 Kepala Tukang L.03 OH - 280,000.00 -
4 Mandor/Pengawas L.04 OH 0,008 300,000.00 2,400,000
Jumlah Tenaga Kerja 21,950,000
B. BAHAN

Jumlah Bahan -
C. PERALATAN

1 Peralatan Potong Pipa T2/Mekanik/Clinder Saw hari 0,0400 #N/A #N/A


Jumlah Peralatan #N/A
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) #N/A
E Overhead & Profit 15% XD #N/A
F Harga Satuan Pekerjaan ( D + E ) #N/A

ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan Pemotongan Pipa Steel dia. 90 mm


Satuan / Unit Bh
Analisa AHSP PU A.8.4.2.64a

No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA

1 Pekerja/Kenek L.01 OH 0,057 180,000.00 10,260,000


2 Tukang L.02 OH 0,012 250,000.00 3,000,000
3 Kepala Tukang L.03 OH - 280,000.00 -
4 Mandor/Pengawas L.04 OH 0,006 300,000.00 1,800,000
Jumlah Tenaga Kerja 15,060,000
B. BAHAN
-
Jumlah Bahan -
C. PERALATAN

1 Peralatan Potong Pipa T2/Mekanik/Clinder Saw hari 0,0370 #N/A #N/A


Jumlah Peralatan #N/A
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) #N/A
E Overhead & Profit 15% XD #N/A
F Harga Satuan Pekerjaan ( D + E ) #N/A
ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan Pengelasan Pipa Steel dia. 100 mm


Satuan / Unit Titik
Analisa Anl. L. 3

No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA

1 Pekerja/Kenek L.01 OH 0,276 180,000.00 49,680,000


2 Tukang L.02 OH 0,138 250,000.00 34,500,000
3 Kepala Tukang L.03 OH 0,014 280,000.00 3,920,000
4 Mandor/Pengawas L.04 OH 0,014 300,000.00 4,200,000
Jumlah Tenaga Kerja 92,300,000
B. BAHAN

1 Kawat Las Listrik Kg 2,756 225,000.00 620,100,000


2 Solar Liter 2,067 5,800.00 11,988,600
3 Minyak Pelumas Liter 0,276 45,000.00 12,420,000
Jumlah Bahan 644,508,600
C. PERALATAN

1 Sewa Mesin Las Jam 0,1171 50,000 5,855


Jumlah Peralatan 5,855
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 736,814,455
E Overhead & Profit 15% XD 110,522,168
F Harga Satuan Pekerjaan ( D + E ) 847,336,623

ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan Galian Tanah Biasa Sedalam 1 Meter


Satuan / Unit M3
Analisa AHSP PU A.2.3.1.1

No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA

1 Pekerja Galian Tanah L.01 OH 0,7500 #N/A #N/A


2 Mandor/Pengawas L.04 OH 0,0250 300,000.00 #VALUE!
Jumlah Tenaga Kerja #N/A
B. BAHAN
-
Jumlah Bahan -
C. PERALATAN
-
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) #N/A
E Overhead & Profit 15% X D #N/A
F Harga Satuan Pekerjaan ( D + E ) #N/A

ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan Urugan Tanah Bekas Galian Termasuk Perataan dan Pemadatan (stamper)
Satuan / Unit M3
Analisa AHSP PU T.14.b

No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA

1 Pekerja Galian Tanah L.01 OH 0,5000 #N/A #N/A


2 Mandor/Pengawas L.04 OH 0,0500 300,000.00 #VALUE!
Jumlah Tenaga Kerja #N/A
B. BAHAN

Jumlah Bahan -
C. PERALATAN

1 Pemadat Timbunan (Stamper) Sewa-Hari 0,0500 #N/A #N/A


Jumlah Peralatan #N/A
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) #N/A
E Overhead & Profit 15% X D #N/A
F Harga Satuan Pekerjaan ( D + E ) #N/A
ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan Penyambungan Pipa HDPE dia. 250 mm


Satuan / Unit Titik
Analisa Anl. HDPE. A6

No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA

1 Pekerja/Kenek L.01 OH 0,327 180,000.00 58,860,000


2 Tukang L.02 OH 0,163 250,000.00 40,750,000
3 Kepala Tukang L.03 OH 0,016 280,000.00 4,480,000
4 Mandor/Pengawas L.04 OH 0,016 300,000.00 4,800,000
Jumlah Tenaga Kerja 108,890,000
B. BAHAN

1 Solar Liter 2,449 5,800.00 14,204,200


2 Minyak Pelumas Liter 0,327 45,000.00 14,715,000
Jumlah Bahan 28,919,200
C. PERALATAN

1 Sewa Mesin Penyambung HDPE Jam 0,1388 #N/A #N/A


Jumlah Peralatan #N/A
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) #N/A
E Overhead & Profit 15% X D #N/A
F Harga Satuan Pekerjaan ( D + E ) #N/A

ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan Memasang 1 M' pipa HDPE dia. 250 mm


Satuan / Unit M'
Analisa AHSP PU A.8.1.22

No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA

1 Pekerja/Kenek L.01 OH 0,1330 180,000.00 #VALUE!


2 Tukang L.02 OH 0,0670 250,000.00 #VALUE!
3 Kepala Tukang L.03 OH - 280,000.00 -
4 Mandor/Pengawas L.04 OH 0,0130 300,000.00 #VALUE!
Jumlah Tenaga Kerja #VALUE!
B. BAHAN

Jumlah Bahan -
C. PERALATAN

Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) #VALUE!
E Overhead & Profit 15% X D #VALUE!
F Harga Satuan Pekerjaan ( D + E ) #VALUE!
ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan Pengelasan Flange dia. 75 mm


Satuan / Unit Bh
Analisa Anl. L. F. 2

No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA

1 Pekerja/Kenek L.01 OH 0,313 180,000.00 56,340,000


2 Tukang L.02 OH 0,157 250,000.00 39,250,000
3 Kepala Tukang L.03 OH 0,016 280,000.00 4,480,000
4 Mandor/Pengawas L.04 OH 0,016 300,000.00 4,800,000
Jumlah Tenaga Kerja 104,870,000
B. BAHAN

1 Kawat Las Listrik Kg 3,1312 225,000.00 #VALUE!


2 Solar Liter 2,3484 5,800.00 #VALUE!
3 Minyak Pelumas Liter 0,3131 45,000.00 #VALUE!
Jumlah Bahan #VALUE!
C. PERALATAN

1 Sewa Mesin Las Jam 0,1331 #N/A #N/A


Jumlah Peralatan #N/A
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) #N/A
E Overhead & Profit 15% XD #N/A
F Harga Satuan Pekerjaan ( D + E ) #N/A

ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan Penyambungan Pipa Baru Ke Pipa Lama dia. 250 mm


Satuan / Unit 1 Buah
Analisa AHSP PU A.8.4.4.5

No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA

1 Pekerja/Kenek L.01 OH 2,996 180,000.00 539,280,000


2 Tukang L.02 OH 1,498 250,000.00 374,500,000
3 Kepala Tukang L.03 OH - 280,000.00 -
4 Mandor/Pengawas L.04 OH 0,300 300,000.00 90,000,000
Jumlah Tenaga Kerja 1,003,780,000
B. BAHAN
1 #N/A #N/A
2 #N/A #N/A
Jumlah Bahan #N/A
C. PERALATAN

1 Peralatan Potong Pipa T2/Mekanik/Clinder Saw Hari 0,9800 #N/A #N/A


2 Sewa Genset 1500 Watt Hari 0,7890 #N/A #N/A
3 Sewa Pompa Submersible 3 M3/h Hari 1,9030 #N/A #N/A
Jumlah Peralatan #N/A
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) #N/A
E Overhead & Profit 15% XD #N/A
F Harga Satuan Pekerjaan ( D + E ) #N/A
ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan Pengetesan Pipa dia. 250 mm


Satuan / Unit M'
Analisa AHSP PU A.8.4.5.6

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA

1 Pekerja/Kenek L.01 OH 0,0080 180,000.00 #VALUE!


2 Mandor/Pengawas L.04 OH 0,0008 300,000.00 #VALUE!
Jumlah Tenaga Kerja #VALUE!
B. BAHAN

1 Air Bersih untuk Pengetesan M3 0,0490 #N/A #N/A


2 Bahan Bakar Solar Liter 0,0600 #N/A #N/A
3 Oli Liter 0,0020 #N/A #N/A
Jumlah Bahan #N/A
C. PERALATAN

Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) #N/A
E Overhead & Profit 15% XD #N/A
F Harga Satuan Pekerjaan ( D + E ) #N/A
ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan Memasang 1 M' pipa Steel dia. 250 mm


Satuan / Unit M'
Analisa AHSP PU A.8.4.1.69

No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA

1 Pekerja/Kenek L.01 OH 1,3250 180,000.00 #VALUE!


2 Tukang L.02 OH 0,2650 250,000.00 #VALUE!
3 Kepala Tukang L.03 OH - 280,000.00 -
4 Mandor/Pengawas L.04 OH 0,1330 300,000.00 #VALUE!
Jumlah Tenaga Kerja #VALUE!
B. BAHAN

Jumlah Bahan -
C. PERALATAN

Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) #VALUE!
E Overhead & Profit 15% X D #VALUE!
F Harga Satuan Pekerjaan ( D + E ) #VALUE!

ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan Penyambungan Pipa HDPE dia. 250 mm


Satuan / Unit Titik
Analisa Anl. HDPE. A6

No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA

1 Pekerja/Kenek L.01 OH 0,327 180,000.00 58,860,000


2 Tukang L.02 OH 0,163 250,000.00 40,750,000
3 Kepala Tukang L.03 OH 0,016 280,000.00 4,480,000
4 Mandor/Pengawas L.04 OH 0,016 300,000.00 4,800,000
Jumlah Tenaga Kerja 108,890,000
B. BAHAN

1 Solar Liter 2,449 5,800.00 14,204,200


2 Minyak Pelumas Liter 0,327 45,000.00 14,715,000
Jumlah Bahan 28,919,200
C. PERALATAN

1 Sewa Mesin Penyambung HDPE Jam 0,1388 55,000 7,634


Jumlah Peralatan 7,634
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 137,816,834
E Overhead & Profit 15% X D 20,672,525
F Harga Satuan Pekerjaan ( D + E ) 158,489,359

ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan Pemasangan Baja Profil


Satuan / Unit Kg
Analisa AHSP PU A.4.2.1.1

No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA

1 Pekerja/Kenek L.01 OH 0,060 180,000.00 10,800,000


2 Tukang L.02 OH 0,060 250,000.00 15,000,000
3 Kepala Tukang L.03 OH 0,006 280,000.00 1,680,000
4 Mandor/Pengawas L.04 OH 0,003 300,000.00 900,000
Jumlah Tenaga Kerja 28,380,000
B. BAHAN

1 Baja Profil Kg 1,150 20,000 23,000


Jumlah Bahan 23,000
C. PERALATAN

Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 28,403,000
E Overhead & Profit 15% X D 4,260,450
F Harga Satuan Pekerjaan ( D + E ) 32,663,450

Jenis Pekerjaan Pengelasan Flange dia. 300 mm


Satuan / Unit Bh
Analisa Anl. L. F. 7

No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA

1 Pekerja/Kenek L.01 OH 1,178 180,000.00 212,040,000


2 Tukang L.02 OH 0,589 250,000.00 147,250,000
3 Kepala Tukang L.03 OH 0,059 280,000.00 16,520,000
4 Mandor/Pengawas L.04 OH 0,059 300,000.00 17,700,000
Jumlah Tenaga Kerja 393,510,000
B. BAHAN

1 Kawat Las Listrik Kg 11,7825 225,000.00 #VALUE!


2 Solar Liter 8,8369 5,800.00 #VALUE!
3 Minyak Pelumas Liter 1,1783 45,000.00 #VALUE!
Jumlah Bahan #VALUE!
C. PERALATAN

1 Sewa Mesin Las Jam 0,5008 #N/A #N/A


Jumlah Peralatan #N/A
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) #N/A
E Overhead & Profit 15% XD #N/A
F Harga Satuan Pekerjaan ( D + E ) #N/A

ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan Pemasangan Accessories dia. 300 mm


Satuan / Unit 1 Buah
Analisa AHSP PU A.8.4.3.18

No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA

1 Pekerja/Kenek L.01 OH 0,436 180,000.00 78,480,000


2 Tukang L.02 OH 0,218 250,000.00 54,500,000
3 Kepala Tukang L.03 OH - 280,000.00 -
4 Mandor/Pengawas L.04 OH 0,044 300,000.00 13,200,000
Jumlah Tenaga Kerja 146,180,000
B. BAHAN #N/A
1 #N/A #N/A
2 #N/A #N/A
Jumlah Bahan #N/A
C. PERALATAN

1 #N/A #N/A
2 #N/A #N/A
3 #N/A #N/A
Jumlah Peralatan #N/A
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) #N/A
E Overhead & Profit 15% XD #N/A
F Harga Satuan Pekerjaan ( D + E ) #N/A

ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan Memasang 1 M' pipa Steel dia. 300 mm


Satuan / Unit M'
Analisa AHSP PU A.8.4.1.70

No Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja/Kenek L.01 OH 1,4150 180,000.00 #VALUE!
2 Tukang L.02 OH 0,2830 250,000.00 #VALUE!
3 Kepala Tukang L.03 OH - 280,000.00 -
4 Mandor/Pengawas L.04 OH 0,1410 300,000.00 #VALUE!
Jumlah Tenaga Kerja #VALUE!
B. BAHAN

Jumlah Bahan -
C. PERALATAN

Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) #VALUE!
E Overhead & Profit 15% X D #VALUE!
F Harga Satuan Pekerjaan ( D + E ) #VALUE!
DAFTAR UPAH DAN BAHAN

HARGA SATUAN
NO. KODE NAMA BARANG / BAHAN / TENAGA SATUAN
(Rp.)
1 B01 Semen Portland Kg Rp 2,500.00
2 B02 Semen Putih Kg Rp 20,000.00
3 B03 Semen Warna Kg Rp 20,000.00
4 B04 Air Bersih Ltr Rp 600.00
5 B05 Kawat beton Kg Rp 67,000.00
6 B06 Kawat Duri Kg Rp 25,000.00
7 B07 Kawat Ram m2 Rp 125,000.00
8 B08 Kawat Las Listrik Kg Rp 225,000.00
9 B09 Plywood 3 mm Ukuran 122 x 224 cm Lembar
10 B10 Plywood tebal 4 mm ( 90 x 220 ) cm Lembar
11 B11 Plywood tebal 4 mm ( 120 x 240 ) cm Lembar
12 B12 Plywood 4 mm Lembar Rp -
13 B13 Plywood 5 mm Lembar
14 B14 Plywood 6 mm Lembar Rp 156,000.00
9 B15 Plywood 9 mm Lembar Rp 235,000.00
10 B16 Plywood 12 mm Lembar
11 B17 Plywood 18 mm Lembar
12 B18 Teakwood tebal 4 mm ( 90 x 220 ) cm Lembar
13 B19 Teakwood tebal 4 mm ( 120 x 240 ) cm Lembar
14 B20 Dolken Kayu Dia. 8-10/400 cm Batang Rp 35,000.00
15 B21 Formika Lembar
16 B22 Gypsum Board 9 mm Lembar Rp 120,000.00
17 B23 Akustik 60 x 60 cm Lembar
18 B24 Akustik 30 x 30 cm Lembar
19 B25 Akustik 60 x 120 cm Lembar
20 B26 List Plafon Profil M1 Rp 15,000.00
B27 List Plafon Profil Gypsum m Rp 25,000.00
B28 List Profil DINDING m
21 B29 Paku Kg Rp 30,000.00
22 B30 Sekrup Gypsum Doz Rp 250,000.00
23 B31 Paku campur Btg Rp 30,000.00
15 B32 Paku Biasa Kg Rp 30,000.00
16 B33 Paku Seng Kg
17 B34 Paku Plywood Kg Rp 30,000.00
18 B35 Paku Atap Kg Rp 220,000.00
19 B36 Paku Beton Kg
20 B37 Paku sekrup Kg Rp 260,000.00
21 B38 Paku Skrup bj Rp 1,300.00
22 B39 Paku hak panjang 15 cm Kg Rp 2,600.00
23 B40 Paku Pancing 60 x 230 Kg
24 B41 Besi Baja IWF Kg
25 B42 Gording Canal Kg
B43 Baja ringan profil C 75 0.75 M1 Rp 60,000.00
B44 Baut (screw driver) bh Rp 1,500.00
B45 Dynabolt bh Rp 15,000.00

733291305.xlsx Upah&Bahan 100/191


HARGA SATUAN
NO. KODE NAMA BARANG / BAHAN / TENAGA SATUAN
(Rp.)
B46 Reng 45 M1 Rp 30,000.00
B47 Talang jurai M1 Rp 271,674.80
25 B48 Besi strip tebal 5 mm Kg Rp 95,000.00
16 B49 Besi strip Btg Rp 95,000.00
26 B50 Mur Baut Dia. 12 - 14 mm Batang
17 B51 Mur Baut Dia. 14 - 19 mm Batang
27 B52 Glasswool Tebal 25mm m2 Rp 16,000.00
28 B53 Wiremesh Ø 2 mm (□ 3 x 3 cm) m2 Rp 65,000.00
29 B54 Alumunium foil Double Sided m2 Rp 16,000.00
30 B55 Genteng Aspal Shingles Owen m2
31 B56 Genteng Aspal Bitumen Merethon 20 Bdl
32 B57 Genteng Aspal Bitumen Merethon 20 m2 Rp -
33 B58 Membrane Aspal m2
34 B59 Mebrane Underlayer Armourbase Pro m2
35 B60 Flashing m Rp 60,000.00
36 B61 Seng Gelombang BJLS 0.30 Lembar Rp 100,000.00
37 B62 Seng Gelombang BLJS 20 Lembar Rp 75,000.00
38 B63 Seng Gelombang BJLS 30' Lembar Rp 100,000.00
39 B64 Seng Plat BJLS 0.20 Lembar Rp 125,000.00
40 B65 Seng Plat bjls 30 Lembar Rp 135,000.00
41 B66 Genteng Metal Multiroof Polos Lembar
42 B67 Nok Genteng Metal Multiroof Lembar
43 B68 Ardek Gelombang Besar Lembar
44 B69 Ardek Gelombang Kecil Lembar
45 B70 Seng Aluminium lebar 60 cm Lembar
46 B71 Seng Aluminium lebar 55 cm Lembar
47 B72 Atap Span Deck (type lebar 80 cm) Lembar Rp 285,000.00
48 B73 Nok Atap m Rp 45,000.00
49 B74 Pintu Besi Baja m2 Rp 850,000.00
50 B75 Genteng Metal Lembar
51 B76 Bubungan Genteng Metal Buah
52 B77 Polycarbonate M2
53 B78 Lumbersharing @4m Lembar Rp 38,000.00
54 B79 Kaca Polos M2 Rp 350,000.00
55 B80 Kaca Bening 3 mm M2
56 B81 Kaca Bening 4 mm M2
57 B82 Kaca Polos 5 mm M2 Rp 270,000.00
58 B83 Kaca Bening 8 mm M2
B84 Kaca wire glas tebal 12 mm m2 Rp 3,500,000.00
B85 Silicon sealant / lem kaca Btl Rp 150,000.00
59 B86 Kaca Louvers 5 mm, 8 klip Set
60 B87 Kaca Louvers 5 mm, 7 klip Set
61 B88 Jendela Nako Ser
62 B89 Kaca Ryben 5 mm M2
63 B90 Batu belah 15/20 M3 Rp 1,000,000.00
64 B91 Batu Kali M3 Rp 1,000,000.00
65 B92 Batu pecah 5/7 M3
66 B93 Batu Kali, ex quarry Mile 32 M3

733291305.xlsx Upah&Bahan 101/191


HARGA SATUAN
NO. KODE NAMA BARANG / BAHAN / TENAGA SATUAN
(Rp.)
67 B94 Batu Kali, ex quarry Iwaka M3
17 B95 Kerikil M3 Rp 480,000.00
18 B96 Kerikil Koral M3 Rp 480,000.00
19 B97 Koral beton (M3) M3 Rp 480,000.00
B98 Koral beton (Kg) 1800kg/m3 Kg Rp 266.67
20 B99 Kerikil Kali, ex quarry Kilo 7,8,14 M3
21 B100 Kerikil (Batu Pecah) : M3
22 B101 Split 1 - 2 cm (M3) M3 Rp 480,000.00
B102 Split 1 - 2 cm (Kg) 1800kg/m3 Kg Rp 266.67
23 B103 Split 2 - 3 cm (M3) M3 Rp 480,000.00
B104 Split 2 - 2 cm (Kg) 1800kg/m3 Kg Rp 266.67
24 B105 Split 3 - 5 cm M3
25 B106 Sirtu Timbunan Rp 260,000.00
26 B107 Sirtu Timbunan, ex quarry Mile 32 M3
27 B108 Sirtu Timbunan, ex quarry Iwaka M3
28 B109 Sirtu Timbunan, ex quarry Kilo 7,8,14 M3
29 B110 Pasir Pasang M3 Rp 360,000.00
30 B111 Pasir Beton (m3) M3 Rp 360,000.00
B112 Pasir Beton (Kg) 1400kg/m3 Kg Rp 257.14
31 B113 Pasir Urug M3 Rp 260,000.00
32 B114 Tanah Timbunan ex quarry Kilo 7,8,14 M3
32 B115 Kayu kelas II (balok) M3 Rp 3,500,000.00
33 B116 Kayu kelas II (papan) M3 Rp 3,750,000.00
34 B117 Kayu Kelas II Matoa ( Balok ) M3 Rp 3,500,000.00
35 B118 Kayu kelas I (papan) M3 Rp 5,000,000.00
36 B119 Kayu Kelas I (balok ) M3 Rp 5,000,000.00
35 B120 Kayu Kelas II Matoa ( Papan ) M3 Rp 3,750,000.00
36 B121 Kayu profil m
37 B122 Reng ( 2 x 3 ) cm M3
38 B123 Bambu Dia. 6 - 8 / 600 cm Batang
39 B124 Bilik Bambu M2
40 B125 Batu Tela Buah Rp 5,500.00
41 B126 Batu Tela (m3) M3
42 B127 Batu batako 10 x 18 x 24 cm Buah Rp 7,500.00
43 B128 Batu Hebel 10 x 18 x 40 cm Buah Rp 10,000.00
B129 Genteng Aspal
B130 Batu bata ringan (ex Hebel), 10x16x60 cm M3
B131 Batu bata ringan (Hebel), 10x16x60 cm BH
B132 Batu bata ringan (ex Hebel), 7x16x60 cm M3
B133 Batu bata ringan (Hebel), 7x16x60 cm BH
B134 Batu bata ringan (ex Broco), 10x16x60 cm M3
B135 Batu bata ringan (Broco), 10x16x60 cm BH
B136 Batu bata ringan (ex Broco), 7x16x60 cm M3
B137 Batu bata ringan (Broco), 7x16x60 cm BH
43 B138 Bata berongga ekspose Buah
43 B139 Roster/terawang Buah Rp 123,000.00
44 B140 Batu Bunga/Loster Buah
45 B141 Batu Tempel Hitam M2

733291305.xlsx Upah&Bahan 102/191


HARGA SATUAN
NO. KODE NAMA BARANG / BAHAN / TENAGA SATUAN
(Rp.)
46 B142 Batu Apung Kg
47 B143 Marmer ex lokal M2
48 B144 Keramik Granitto 60 x 60 cm Dus Rp 320,000.00
49 B145 Keramik Granitto 60 x 60 cm Buah Rp 106,666.67
50 B146 Keramik 10 x 60 cm Buah Rp 21,333.33
B147 Keramik 10 x 30 cm Buah Rp 6,480.00
44 B148 List Keramik 6/20 cm Buah Rp 10,000.00
45 B149 Tegel Keramik 40 x 40 cm Buah
46 B150 Tegel Keramik 30 x 30 cm Buah Rp 16,200.00
45 B151 Tegel Keramik 20 x 25 cm Buah Rp 11,000.00
46 B152 Tegel Keramik 20 x 20 cm Buah Rp 7,400.00
47 B153 Tegel Keramik 10 x 20 cm Buah
48 B154 Tegel Porselin 11 x 11 cm Buah
47 B155 Tegel Mozaik 30 x 30 cm Buah Rp 6,000.00
48 B156 Tegel Teraso 30 x 30 cm Buah
49 B157 Tegel PC Abu-Abu 20 x 20 cm Buah
50 B158 Plint keramik artistik Buah
51 B159 Batu Alam Palimanan Buah
52 B160 Pipa PVC dia 1/2" - 4m Batang Rp 25,000.00
53 B161 Pipa PVC dia 1/2" M Rp 6,250.00
54 B162 Pipa PVC dia 3/4" - 4m Batang Rp 35,000.00
55 B163 Pipa PVC dia 3/4" M Rp 8,750.00
56 B164 Pipa PVC dia 1" - 4m Batang Rp 40,000.00
57 B165 Pipa PVC dia 1" M Rp 10,000.00
58 B166 Pipa PVC dia 1 1/2" - 4m Batang Rp 50,000.00
59 B167 Pipa PVC dia 1 1/2" M Rp 12,500.00
60 B168 Pipa PVC dia 2" - 4m Batang Rp 250,000.00
61 B169 Pipa PVC dia 2" M Rp 62,500.00
62 B170 Pipa PVC dia 3" - 4m Batang Rp 280,000.00
63 B171 Pipa PVC dia 3" M Rp 70,000.00
64 B172 Pipa PVC dia 4" - 4m Batang Rp 460,000.00
65 B173 Pipa PVC dia 4" M Rp 115,000.00
66 B174 Pipa PVC dia 5" - 4m Batang
67 B175 Pipa PVC dia 5" M Rp -
68 B176 Pipa PVC dia 6" - 4m Batang
69 B177 Pipa PVC dia 6" M Rp -
69 B178 Koppling PVC dia 2" - 4m Buah
70 B179 Koppling PVC dia 4" - 6m Buah
71 B180 Pipa GIV Dia 1/2" - 6 m Batang Rp 375,000.00
72 B181 Pipa Gip Ø ½ " M Rp 62,500.00
72 B182 Pipa GIV Dia 3/4" - 6 m Batang Rp 375,000.00
73 B183 Pipa Gip Ø ¾ " M Rp 62,500.00
48 B184 Pipa GIV dia 1" - 6m Batang Rp 450,000.00
49 B185 Pipa Gip Ø 1 " M Rp 75,000.00
50 B186 Pipa GIV dia 1 1/4" - 6m Batang Rp 567,000.00
51 B187 Pipa Gip Ø 1 ¼ " M Rp 94,500.00
52 B188 Pipa GIV dia 1 1/2" - 6m Batang Rp 500,000.00
53 B189 Pipa Gip Ø 1 ½ " M Rp 83,333.33

733291305.xlsx Upah&Bahan 103/191


HARGA SATUAN
NO. KODE NAMA BARANG / BAHAN / TENAGA SATUAN
(Rp.)
54 B190 Pipa GIV Dia 2" - 6 m Batang Rp 750,000.00
55 B191 Pipa Gip Ø 2 " M Rp 125,000.00
56 B192 Pipa GIV dia 3" - 6m Batang
57 B193 Pipa Gip Ø 3 " M
58 B194 Pipa GIV dia 4" - 6m Batang Rp -
59 B195 Pipa Gip Ø 4 " M Rp -
60 B196 Pipa Leding dia 1 1/2" - 6 mtr Batang
61 B197 Pipa Leding dia 1 1/2" M Rp -
62 B198 Pipa Ø2½" -SCH 40 M
63 B199 Pipa Ø2½" -SCH 4 diroll Kg
64 B200 Pipa Ø3" -SCH 40 M
65 B201 Pipa Ø3" -SCH 40 diroll Kg
66 B202 Pipa Ø3½" -SCH 40 M Rp -
67 B203 Pipa Ø3½" -SCH 40 diroll Kg
68 B204 Pipa Ø4" -SCH 40 M
69 B205 Pipa Ø4" -SCH 40 diroll Kg
70 B206 Pipa Ø6" -SCH 40 M
71 B207 Pipa Ø6" -SCH 40 diroll Kg
72 B208 Pipa Ø3" -SCH 80 M
73 B209 Pipa Ø3" -SCH 80 diroll Kg
74 B210 Pipa Ø4" -SCH 80 M
75 B211 Pipa Ø4" -SCH 80 diroll Kg Rp -
76 B212 Pipa Ø6" -SCH 80 (41,83 kg/m) M
77 B213 Pipa Ø6" -SCH 80 diroll Kg Rp -
78 B214 Pipa Kotak 4x6x2,3 ( Hollow) 179,000.00
79 B215 Pipa Kotak 4x4x1,2 ( Hollow) M 132,000.00
80 B216 Pipa Kotak 4x2x1,0 ( Hollow) m 86,000.00
81 B217
Rangka metal hollow 40.40.2 mm
82 B218 m Rp 18,750.00
83 B219 Besi Siku 50.50.5 Kg Rp 24,000.00
84 B220 Profil L 60.60.6 Kg
84 B221 Besi Plat 2 mm kg Rp 25,000.00
85 B222 Besi Plat 8 mm kg
86 B223 Besi Plat 10 mm kg
87 B224 Besi Plat 12 mm kg
88 B225 Besi Plat 16 mm kg
89 B226 Besi Plat 18 mm kg
90 B227 Besi Plat 19 mm kg
91 B228 Besi Plat 20 mm kg
92 B229 Besi Plat 22 mm kg
93 B230 Besi Plat 25 mm kg
94 B231 Plat strip t = 4 mm Batang
80 B232 Pipa Mediuh Hitam 2½" Inc M
81 B233 Kabel ITC 2 x 2 x 0.6 mm2 m
85 B234 Kabel NYM 2 X 2,5 mm2 m Rp 16,240.00
86 B235 Kabel NYM 3 X 2,5 mm2 m Rp 20,800.00
87 B236 Kabel NYM 3 x 4 mm2 m Rp 29,000.00
88 B237 Kabel NYM 4 x 4 mm2 m Rp 45,000.00

733291305.xlsx Upah&Bahan 104/191


HARGA SATUAN
NO. KODE NAMA BARANG / BAHAN / TENAGA SATUAN
(Rp.)
89 B238 Kabel NYM HY 3 X 2,5 mm2 m Rp 20,800.00
90 B239 Kawat BC 2,5 mm m Rp 55,000.00
91 B240 Kabel BC 50 mm m Rp 1,176,000.00
92 B241 Klem PVC Clipsal m Rp 5,675.00
93 B242 Las Dop Legrand 4 mm2 Bh Rp 5,800.00
94 B243 Pipa Clipsal PVC 3/4 Bh Rp 8,750.00
95 B244 Pipa PVC Maspion 5/8 Bh Rp 6,800.00
96 B245 T.Doos PVC 3/4 Bh Rp 5,000.00
97 B246 Elbo Clipsal PVC 3/4 Bh Rp 5,000.00
98 B247 Sock PVC Clipsal 3/4 Bh Rp 5,000.00
99 B248 Isolasi Unibel Bh Rp 22,000.00
100 B249 Kran Shower Buah Rp 250,000.00
101 B250 Kran Leding (Stainles) Buah Rp 85,000.00
102 B251 Ijuk Kg
103 B252 Pompa Air Sanyo PH 100 Unit
104 B253 Pompa Air Honda (Alkon) Unit
105 B254 Permite/Penjaga jarak bekisting/spacer Buah
106 B255 Seal tape Roll Rp 25,000.00
102 B256 Minyak Bekesting Liter Rp 15,000.00
103 B257 Rapidrant Galon
104 B258 Bak Cuci Stainless Steel Buah Rp 500,000.00
105 B259 Water Drain + Acesories Set
106 B260 Floor Drain Buah Rp 250,000.00
107 B261 Tangki Air fibre Kap. 1000 Liter Buah
108 B262 Kloset jongkok porselen Buah
109 B263 Kloset Jongkok Biasa Buah
110 B264 Kloset Duduk Keramik KIA Buah
111 B265 Urinoir Buah Rp 3,500,000.00
112 B266 Kloset duduk / monoblok Set Rp 3,800,000.00
113 B267 Wastafel lengkap TOTO Buah Rp 1,300,000.00
114 B268 Floor Drain Stainless Steel Buah Rp 160,000.00
115 B269 Kran Air Stainless Buah Rp 120,000.00
116 B270 Lampu TL 2 x 40 Watt Phillips + Mirror inbow Buah
117 B271 Lampu TL 2 x 20 Watt Buah
118 B272 Lampu TL 20 Watt Buah
119 B273 Lampu Down Light + SL 15 Watt Lengkap Buah
120 B274 Lampu Baret SL 18 Watt Buah
121 B275 Lampu Pijar 5 - 100 Watt + Fitting Buah
122 B276 Kabel Snoor 2 x 0,23 "Supreme" roll
123 B277 Kabel NYA 2,5 sqmm "Supreme" roll
124 B278 Kabel NYA 1,5 sqmm "Supreme" roll
125 B279 Kabel NYA 2,5 sqmm "Supreme" M1 Rp -
126 B280 Kabel NYA 1,5 sqmm "Supreme" M1 Rp -
127 B281 Kabel NYM 2 x 1,5 sqmm "Supreme" M1
128 B282 Kabel NYM 2 x 2,5 mm (eterna) M1
129 B283 Kabel NYM 2 x 4 sqmm "Supreme" M1 Rp -
130 B284 Kabel NYM 3 x 1,5 sqmm "Supreme" M1 Rp -
131 B285 Kabel NYM 3 x 2,5 mm M1

733291305.xlsx Upah&Bahan 105/191


HARGA SATUAN
NO. KODE NAMA BARANG / BAHAN / TENAGA SATUAN
(Rp.)
132 B286 Kabel NYM 4 x 4 mm2 M1 Rp 45,000.00
133 B287 Kabel NYM 3 x 4 sqmm "Supreme" M1
134 B288 Kabel NYY 3 x 6 sqmm "Supreme" M1
135 B289 Kabel NYF GbY 4 x 25 mm M1
136 B290 Vitting Buah
137 B291 Stop Kontak 1000 W Buah
138 B292 Stop Kontak 5000 W Buah
139 B293 Sekring 1 Group Buah
140 B294 Sekring 3 Group Buah
141 B295 Sekring Otomatis Buah
142 B296 Saklar Seri Buah
143 B297 Saklar Tunggal Buah
144 B298 Box Sekring Grup
145 B299 MCB (Miniatur Circuit Breaker) Buah
146 B300 Box MCB Group
95 B301 Besi Ø 6 Kg
96 B302 Besi Beton (UK 8 mm x 12) Batang
97 B303 Besi Beton Segala Ukuran ( Polos ) Kg
103 B304 Besi beton Kg Rp 28,000.00
104 B305 Besi Ø 10 Kg
105 B306 Besi Ø 12 Kg
106 B307 Besi Siku 20.20-2m Batang
107 B308 Besi Siku 30.30-3m Batang
108 B309 Besi Siku 40 x 40 x 3mm Batang
109 B310 Besi Siku 40.40-6m Batang
104 B311 Besi Siku 50 x 50 x 5mm - 6M Batang Rp 250,000.00
105 B312 Profil L Kg Rp 45,000.00
85 B313 Besi Siku 100.100-6m Batang
86 B314 Wiremesh BRC Standar SNI, M8 Lembar
87 B315 Wiremesh BRC Standar SNI, M9 Lembar
88 B316 Wiremesh BRC Standar SNI, M10 Lembar
89 B317 Wiremesh BRC Standar SNI, M12 Lembar
90 B318 Plat Bondek 0,75 mm X 1 m m1
91 B319 Plat Bondek 0,85 mm X 1 m m2
92 B320 Plat Bondek 1,00 mm X 1 m m3
105 B321 Cat Dasar Kaleng Rp 50,000.00
106 B322 Cat Dasar Tembok Kg Rp 80,000.00
107 B323 Meni Kayu Kg Rp 120,000.00
108 B324 Melamine IMPRA Liter
109 B325 Wood Filler Kg
110 B326 Thinner Kg
111 B327 Sending Kg Rp -
112 B328 Clear Kg Rp -
113 B329 Pewarna Kg
114 B330 Kertas gosok Lbr Rp 15,000.00
108 B331 Cat Kilat Kayu Kaleng Rp 85,000.00
109 B332 Politur Dasar Kaleng Rp 65,000.00
110 B333 Cat Vernis/Politur Kaleng Rp 85,000.00

733291305.xlsx Upah&Bahan 106/191


HARGA SATUAN
NO. KODE NAMA BARANG / BAHAN / TENAGA SATUAN
(Rp.)
109 B334 Cat Tembok Kg Rp 120,000.00
110 B335 - Merk Mowilex Kaleng Rp 2,750,000.00
111 B336 - Merk Jotun Kaleng Rp 2,550,000.00
112 B337 Cat Plafon Kg Rp 28,888.00
113 B338 Cat Residu Kg
114 B339 Meni Besi Kg Rp 59,666.00
115 B340 Cat Minyak Besi Kg Rp 120,000.00
116 B341 Cat Teak oil Kaleng
117 B342 Cat Alluminium Kaleng
118 B343 Soda Api Kg
119 B344 Minyak Cat Kg Rp 45,000.00
120 B345 Water proofing Kg Rp 250,000.00
121 B346 Sabun
122 B347 Plamur Tembok Kg Rp 45,000.00
123 B348 Plamur Kayu Kg Rp 65,000.00
124 B349 Dempul Kg
B350 Kuas Buah Rp 15,000.00
125 B351 Kuas Biasa Buah Rp 25,000.00
126 B352 Kuas Roll (Besar) Buah
127 B353 Ampelas Lembar Rp 15,000.00
128 B354 Lem kayu Kg
129 B355 Lem Aibon Kaleng
130 B356 Kunci Tanam Buah Rp 450,000.00
131 B357 Kunci Tanam 2 Slaag SES/Kend Buah
132 B358 Kunci Tanam Silinder 1 Slaag SES/Kend Buah Rp 400,000.00
133 B359 Kunci Kuda Terbang 1 Slaag Buah
134 B360 Kunci Kuda Terbang 2 Slaag Buah
135 B361 Kunci lemari Buah
136 B362 Kunci Yale Besar Buah
137 B363 Kunci H Jendela Pasang
138 B364 Kunci H Pintu Pasang
139 B365 Engsel jendela Pasang Rp 165,000.00
140 B366 Engsel Pintu Pasang Rp 175,000.00
141 B367 Kunci Gembok Besar Buah
142 B368 Kunci Gembok Sedang Buah
143 B369 Kunci Gembok Kecil Buah
144 B370 Grendel Jendela Buah Rp 150,000.00
145 B371 Grendel Pintu Buah
146 B372 Grendel Pintu Double Buah Rp 250,000.00
147 B373 Door holder Buah
148 B374 Door Closer Buah Rp 1,200,000.00
149 B375 Door Stop Buah Rp 350,000.00
150 B376 Hak Angin Biasa Buah
151 B377 Hak Angin Lipat Buah Rp 120,000.00
152 B378 Solar Ltr Rp 5,800.00
153 B379 Minyak Pelumas Lter Rp 45,000.00
154 B380 Kayu Cerocok m Rp 15,000.00
155 B381 Baut 5/8" panjang 30 cm Bh Rp 15,000.00

733291305.xlsx Upah&Bahan 107/191


HARGA SATUAN
NO. KODE NAMA BARANG / BAHAN / TENAGA SATUAN
(Rp.)
156 B382 Alumunium Composite m2 Rp 450,000.00
157 B383 Hollow Besi Galvanis Uk 4 x 4 x 1 mm btg Rp 125,000.00
158 B384 Braket Siku / spigot / stiffener btg Rp 80,000.00
159 B385 Paku Beton kg Rp 150,000.00
160 B386 Dinabolt bh Rp 15,000.00
161 B387 Paku Skrup doz Rp 350,000.00
162 B388 Sealant/Silicon tube Rp 50,000.00
163 B389 Kalsiboard eksterior 6 mm m2 Rp 150,000.00
164 B390 Compound kg Rp 85,000.00

TENAGA KERJA
1 U01 Pekerja/Kenek O/h Rp 180,000.00
2 U02 Pekerja/Kenek Terampil O/h Rp 200,000.00
3 U03 Tukang O/h Rp 250,000.00
4 U04 Tukang Kayu O/h Rp 250,000.00
5 U05 Tukang Batu O/h Rp 250,000.00
6 U06 Tukang besi O/h Rp 250,000.00
7 U07 Tukang gali O/h Rp 250,000.00
8 U08 Tukang Cat O/h Rp 250,000.00
9 U09 Tuk.Bongkar Bekisting O/h Rp 250,000.00
10 U10 Tukang Listrik O/h Rp 250,000.00
11 U11 Tukang Las O/h Rp 250,000.00
11 U12 Tukang Pipa O/h Rp 250,000.00
12 U13 Tukang Aspal O/h Rp 250,000.00
13 U14 Kepala Tukang O/h Rp 280,000.00
14 U15 Mandor/Pengawas O/h Rp 300,000.00
15 U16 Pengawas / Ahli Teknik O/h Rp 833,333.33
16 U17 Juru Ukur O/h Rp 280,000.00
17 U18 Asisten ahli ukur O/h Rp 200,000.00
PERALATAN
1 A01 Mesin penyaring 8 HP jam
2 A02 Chip Spreader jam
3 A03 Mesin penghampar 1820 MM 30 HP jam
4 A04 Thriller gandeng 1 ton jam
5 A05 Dump Truck 3,5 ton 44 HP jam
6 A06 Bulldozer 100 - 150 Hp jam Rp 1,639,067.00
7 A07 Compressor 4000-6500 L/M jam Rp 316,622.76
8 A08 Concrete Mixer 0,3 - 0,6 M3 jam Rp 169,305.60
9 A09 Dump Truck 3 - 4 M3 jam Rp 1,007,092.31
10 A10 Excavator 80 - 140 Hp jam Rp 1,867,598.58
11 A11 Generator/Genset jam Rp 91,224.58
12 A12 Motor Grader > 100 Hp jam Rp 1,847,064.37
13 A13 Wheel Loader 1 - 1,6 M3 jam Rp 1,210,344.64
14 A14 Vibratory Roller 5 - 8 Ton jam Rp 686,805.15
15 A15 Concrete Vibrator jam Rp 140,460.05
16 A16 Water Tanker 3000 - 4500 L jam Rp 945,142.31
17 A17 Water Pump jam Rp 145,237.63
18 A18 Tamper jam Rp 167,339.15

733291305.xlsx Upah&Bahan 108/191


HARGA SATUAN
NO. KODE NAMA BARANG / BAHAN / TENAGA SATUAN
(Rp.)
19 A19 Jack Hammer jam Rp 192,765.29
20 A20 Welding Set jam Rp 344,623.06
21 A21 Chain Saw jam Rp 93,732.63
22 A22 Gruss Cutter jam Rp 102,870.43
23 A25 Pompa air (D 5 cm) 30 m3 / jam jam
24 A26 Thriller 1ton jam
25 A27 Traktor jam
26 A28 Alat Bor jam
27 A29 Sewa Alat Ukur Hr
28 A30 Beton Molen jam
29 A31 Mata Cutter bh
30 A32 Mesin Cutter jam
31 A33 Motor Walls jam
32 A34 Peralatan Las jam
33 A35 Sprayer jam
34 A36 Sewa Schafolding set/Hr Rp 50,000.00
35 A37 Sewa Alat Bending Pipa jam
36 A38 Alat bantu ls Rp 5,000.00
37 A39 Water Pass set/Hr
38 A40 Theodolit set/Hr
39 A41 Listrik Kerja set/Hr
40 A42 Alat bantu lainnya set/Hr

733291305.xlsx Upah&Bahan 109/191


DAFTAR UPAH DAN BAHAN

NO. KODE NAMA BARANG / BAHAN / TENAGA

UNIT PRICE (UP)


I A PEKERJAAN PERSIAPAN
1 A-01 100 M2 Pekerjaan Pengukuran Gedung
2 A-02 1 M' Pagar Sementara Dari Kayu Tinggi 2 M
3 A-03 1 M' Pagar Sementara Dari Seng Gelombang Tinggi 2 M
4 A-04 1 M' Pagar Sementara Dari Kawat Duri Tinggi 1,8 M
5 A-05 1 M' Pengukuran Dan Pemasangan Bouwplank
6 A-06 1 M2 Pembuatan Kantor Sementara Dengan Lantai Plesteran
7 A-07 1 M2 Pembuatan Rumah Jaga/Konstruksi Kayu
8 A-08 1 M2 Pembersihan Lapangan dan Peralatan
9 A-09 1 M2 Pembuatan Bedeng Buruh
10 A-10 1 M2 Pembuatan Stegger dari Bambu Ukuran ( 40 x 40 x 20 ) cm
11 A-11 1 M2 Pembuatan Jalan Sementara
12 A-12 1 M3 Bongkaran Beton Bertulang
13 A-13 1 M3 Bongkaran Dinding Tembok Batako

II B PEKERJAAN TANAH
1 B-01 1 M3 Galian Tanah Biasa Sedalam 1 M
2 B-02 1 M3 Galian Tanah Biasa Sedalam 2 M
3 B-03 1 M3 Galian Tanah Biasa Sedalam 3 M
4 B-04 1 M3 Galian Tanah Keras Sedalam 1 M
5 B-05 1 M3 Galian Tanah Cadas Sedalam 1 M
6 B-06 1 M3 Galian Tanah Lumpur Sedalam 1 M
7 B-07 1 M3 Pekerjaan Stripping Setinggi 1 M
8 B-08 1 M3 Pembuangan Tanah Sejauh 15 M
9 B-09 1 M3 Mengurug Kembali Galian
10 B-10 1 M3 Pemadatan Tanah ( per 20 cm)
11 B-11 1 M3 Urugan Pasir
12 B-12 1 M3 Urugan Sirtu
13 B-13 1 M3 Urugan Kerikil
14 B-14 1 M3 Pembuatan Jalan Sementara, Tebal 25 cm
15 B-15 Pek. Galian Tanah (Cut) Dengan Alat Berat / M3
16 B-16 Pek Urugan Sirtu (Fill) Dengan Alat Berat / M3

III C PEKERJAAN PONDASI


1 C-01 1 M3 Pasangan Pondasi Batu Belah, Campuran 1 PC : 3 PP
2 C-02 1 M3 Pasangan Pondasi Batu Belah, Campuran 1 PC : 4 PP
3 C-03 1 M3 Pasangan Pondasi Batu Belah, Campuran 1 PC : 5 PP
4 C-04 1 M3 Pasangan Pondasi Batu Belah, Campuran 1 PC : 6 PP
5 C-05 1 M3 Pasangan Pondasi Batu Belah, Campuran 1 PC : 8 PP
6 C-06 1 M3 Pasangan Batu Kosong (Anstamping)
7 C-07 1 M3 Pasangan Pondasi Siklop, 60% Beton Capuran 1 PC : 2 PB : 3 KR dan 40% Batu Belah
8 C-08 1 M3 Pasangan Pondasi Sumuran Diameter 100 cm
9 C-09 1 M' Pembuatan Tiang Pancang ( 40 x 40 ) Cm, Prestressed Beton
10 C-10 1 M' Pembuatan Tiang Pancang ( 35 x 35 ) Cm, Prestressed Beton

IV D PEKERJAAN DINDING
1 D-01 1 M2 Pasangan Batu Tela, 1 PC : 1 PP
2 D-02 1 M2 Pasangan Batu Tela, 1 PC : 2 PP
3 D-03 1 M2 Pasangan Batu Tela, 1 PC : 3 PP
4 D-04 1 M2 Pasangan Batu Tela, 1 PC : 4 PP
5 D-05 1 M2 Pasangan Batu Tela, 1 PC : 5 PP
6 D-06 1 M2 Pasangan Batu Batako Tebal 1 Batako, 1 PC : 1 PP
7 D-07 1 M2 Pasangan Batu Batako Tebal 1 Batako, 1 PC : 2 PP
8 D-08 1 M2 Pasangan Batu Batako Tebal 1 Batako, 1 PC : 3 PP
9 D-09 1 M2 Pasangan Batu Batako Tebal 1 Batako, 1 PC : 4 PP
10 D-10 1 M2 Pasangan Batu Batako Tebal 1 Batako, 1 PC : 5 PP
11 D-11 1 M2 Pasangan Dinding Roster/Terawang (10 X 20 X 20) cm, Campuran Spesi 1 PC : 3 PP
12 D-12 1 M2 Pasangan Dinding Roster/Terawang (12 X 11 X 24) cm, Campuran Spesi 1 PC : 4 PP
13 D-13 1 M2 Pasangan Dinding Bata Berongga Ekspose (5 X 11 X 24) cm, Campuran Spesi 1 PC : 3 PP
14 D-14 1 M2 Pasangan Dinding Batu bata ringan (Hebel), 10x16x60 cm, Campuran Spesi 1 PC : 3 PP

V E PEKERJAAN PLESTERAN
1 E-01 1 M2 Plesteran, 1 PC : 1 PP, tebal 15 mm
2 E-02 1 M2 Plesteran, 1 PC : 2 PP, tebal 15 mm
3 E-03 1 M2 Plesteran, 1 PC : 3 PP, tebal 15 mm
4 E-04 1 M2 Plesteran, 1 PC : 4 PP, tebal 15 mm
5 E-05 1 M2 Plesteran, 1 PC : 5 PP, tebal 15 mm
6 E-06 1 M2 Plesteran, 1 PC : 6 PP, tebal 15 mm
7 E-07 1 M2 Plesteran Beton, 1 PC : 2 PP, tebal 15 mm
8 E-08 1 M2 Plesteran Beton, 1 PC : 3 PP, tebal 15 mm
9 E-09 1 M2 Plesteran Skoning, 1 PC : 2 PP, Lebar 10 mm
10 E-10 1 M2 Acian

VI F PEKERJAAN KAYU
1 F-01 1 M3 Membuat dan Memasang Kusen Pintu dan Jendela Kayu Kelas I
2 F-02 1 M3 Membuat dan Memasang Kusen Pintu dan Jendela Kayu Kelas II dan III
3 F-03 1 M3 Membuat dan Memasang Pintu Klamp Standar, Kayu Kelas II
4 F-04 1 M2 Membuat dan Memasang Daun Pintu Panel Kayu Kelas I
5 F-05 1 M2 Membuat dan Memasang Pintu dan Jendela Jalusi Kayu Kelas I
6 F-06 1 M2 Membuat dan Memasang Daun Pintu dan Jendela Kaca Kayu Kelas I
7 F-07 1 M2 Membuat Pintu Kayu Lapis (Plywood), Rangkap, Rangka Tertutup Kayu Kelas II (Lebar sampa
8 F-08 1 M2 Membuat Pintu Kayu Lapis (Plywood), Rangkap, Rangka Expose Kayu Kelas I dan II
9 F-09 1 M2 Pasang Jalusi Kusen Kayu Kelas I
10 F-10 1 M2 Pasang Teakwood Rangkap, Rangka Expose Kayu Kelas I
11 F-11 1 M2 Pasang Teakwood Rangkap Lapis Formika, Rangka Expose Kayu Kelas II
12 F-12 1 M2 Pasang Kaca Tebal 6 Mm
13 F-13 1 M3 Pasang Konstruksi Kuda-Kuda Konvensional, Kayu Kelas II
14 F-14 1 M3 Pasang Konstruksi Kuda-Kuda Expose, Kayu Kelas I
15 F-15 1 M3 Pasang Konstruksi Gordeng, Kayu Kelas II
16 F-16 1 M2 Pasang Rangka Atap Genteng Keramik, Kayu Kelas II
17 F-17 1 M2 Pasang Rangka Atap Genteng Beton, Kayu Kelas II
18 F-18 1 M2 Pasang Rangka Atap Sirap, Kayu Kelas II
19 F-19 1 M' Pasang Lisplank Ukuran (3 X 20) cm, Kayu Kelas I atau II
20 F-20 1 M' Pasang Lisplank Ukuran (3 X 30) cm, Kayu Kelas I atau II
21 F-21 1 M' Papan Listplank Kayu Besi 3/30
22 F-22 1 M2 Pasang Rangka Dinding Pemisah (60 X 120) cm , Kayu Kelas II atau III
23 F-23 1 M2 Pasang Dinding Pemisah Teakwood Rangkap, Rangka Kayu Kelas II
24 F-24 1 M2 Pasang Dinding Pemisah Plywood Rangkap, Rangka Kayu Kelas II
25 F-25 1 M2 Pasang Dinding Lambriziring dari Papan Kayu Kelas I
26 F-26 1 M2 Pasang Dinding Partisi Dari Plywood ( 120 X 240 ) Cm
27 F-27 1 M2 Pasang Dinding Bilik, Rangka Kayu Kelas II
28 F-28 1 M2 Pekerjaan Rangka Dinding Pemisah / Partisi (60 X 120) Cm Kayu Besi
29 F-29 1 M2 Pekerjaan Dinding Gypsum Board 9 Mm/Satu Sisi "
30 F-30 1 M3 Balok Lantai Dan Skor Kayu Kelas I
31 F-31 1 M3 gelagar kayu kelas I (BOW)
32 F-32 1 M2 Lantai Papan Kayu Klas I
33 F-33 1 M2 lantai papan kayu kelas I diketam (BOW)
34 F-34 1 M' Pemancangan Cerocok Kayu
35 F-35 1 M2 Dinding papan dilidah/alur
36 F-36 1 M2 Dinding papan susun sirih
37 F-37 1 M2 Dinding triplek 4 mm rangka kayu Kls II
38 F-38 1 M2 Dinding double triplek 4 mm kayu Kls II
39 F-39 1 M2 Dinding double triplek Sungkai rangka kayu Kls II
40 F-40 1 Ptg Mencincin/melancip tiang pancang/potong
41 F-41 1 M Memancang tiang ke dalam tanah lunak/M
42 F-42 1 Ps Membuat pen dan lobang pada tiang balok pemikul/
43 F-43 1 M Membuat alur dan lidah pada papan bendung
44 F-44 1 M Memancang papan bendung ke dalam tanah lunak
45 F-45 1 M Memaku/meratakan kepala papan bendung
46 F-46 1 M3 Memasang leger/balok tumbuk
47 F-47 1 M3 Pasangan Rangka Bawah Kayu Besi
48 F-48 1 M3 Membuat kayu sandaran jembatan
49 F-49 1 M3 Pasangan Rangka Atas Kayu besi
50 F-50 1 M2 Memasang papan lantai tebal 2 s/d 8 cm

VII G PEKERJAAN BETON


1 G-001 1 M3 Membuat Beton Tumbuk, 1 PC : 3 PS : 5 KR
2 G-002 1 M3 Membuat Beton Tumbuk, 1 PC : 3 PS : 6 KR
3 G-003 1 M3 Membuat Beton Tumbuk, 1 PC : 4 PS : 6 KR
4 G-004 1 M2 Membuat Lantai Kerja Beton mutu fc = 7,4 Mpa (K 100), slump (3 - 6) cm, w/c = 0,87
5 G-005 1 M3 Membuat Beton Bertulang, 1 PC : 2 PS : 3 KR
6 G-006 1 M3 Membuat Beton Bertulang, 1 PC : 2 PS : 4 KR
7 G-007 1 M3 Membuat Beton Bertulang, 1 PC : 2 PS : 2,5 KR
8 G-008 1 M3 Membuat Beton Bertulang, 1 PC : 1,5 PS : 3 KR
9 G-009 1 M3 Membuat Beton Bertulang, 1 PC : 1,5 PS : 2,5 KR
10 G-010 1 M3 Membuat Beton Bertulang, 1 PC : 1,5 PS : 2 KR
11 G-011 1 M3 Membuat Beton Bertulang, 1 PC : 1 PS : 1 KR
12 G-012 1 M3 Membuat Beton dengan Mutu K 225
13 G-013 1 M3 Membuat Beton dengan Mutu K 250
14 G-014 1 M3 Membuat Beton dengan Mutu K 275
15 G-015 Membuat 1 m3 beton mutu f’c = 26,4 MPa (K 300), slump (12 ± 2) cm, w/c = 0,52
16 G-016 Pembesian 10 Kg dengan Besi polos atau Besi Ulir
17 G-017 Memasang 10 Kg Kabel Presstressed Polos/Strands
18 G-018 1 M2 Pasang Bekisting untuk Pondasi
19 G-019 1 M2 Pasang Bekisting untuk Sloof
20 G-020 1 M2 Pasang Bekisting untuk Kolom
G-021 1 M2 Pasang Bekisting untuk Kolom Bulat
21 G-022 1 M2 Pasang Bekisting untuk Balok
22 G-023 1 M2 Pasang Bekisting untuk Plat Lantai
23 G-024 1 M2 Pasang Bekisting untuk Dinding
G-025 1 M2 Pasang Bekisting untuk Lispaln Beton
24 G-026 1 M2 Pasang Bekisting untuk Tangga
25 G-027 1 M2 Pasang Jembatan untuk Pengecoran Beton
26 G-028 1 M3 Membuat Pondasi Beton Bertulang (150 kg besi + bekisting )
27 G-029 1 M3 Membuat Sloof Beton Bertulang (200 kg besi + bekisting )
28 G-030 1 M3 Membuat Kolom Beton Bertulang (300 kg besi + bekisting )
29 G-031 1 M3 Membuat Plat Beton Bertulang (150 kg besi + bekisting )
30 G-032 1 M3 Membuat Balok Beton Bertulang ( 200 Kg Besi + Bekisting )
31 G-033 1 M3 Membuat Balok Beton Bertulang ( 150 Kg Besi + Bekisting )
32 G-034 1 M3 Membuat Dinding Beton Bertulang (150 kg besi + bekisting )
33 G-035 1 M3 Membuat Dinding Beton Bertulang (200 kg besi + bekisting )
34 G-036 1 M' Membuat Kolom Praktis Beton Bertulang (11 x 11 ) cm
35 G-037 1 M' Membuat Ring Balok Beton Bertulang (10 x 15 ) cm
36 G-038 1 M3 Pekerjaan Pondasi Beton Bertulang
37 G-039 1 M3 Pekerjaan Pondasi tapak Beton
38 G-040 1 M3 Pekerjaan Kolom Beton Bertulang K1 (20/46)
39 G-041 1 M3 Pekerjaan Kolom Beton Bertulang K2 (30x30cm)
40 G-042 1 M3 Pekerjaan Kolom Beton Bertulang K1.a (25x40cm)
41 G-043 1 M3 Pekerjaan Balok Beton Bertulang B1 (25x40 cm)
42 G-044 1 M3 Pekerjaan Balok Beton Bertulang B2 (25x35 cm)
43 G-045 1 M3 Pekerjaan Balok Beton Bertulang R (25x35 cm)
44 G-046 1 M3 Pekerjaan Balok Beton Bertulang B3 (25x50 cm)
45 G-047 1 M3 Pekerjaan Balok Beton Bertulang B4 (25x40 cm)
46 G-048 1 M3 Pekerjaan Ring Balok Rb (20x30 cm)
47 G-049 1 M3 Pekerjaan Balok Beton Bertulang B5 (20x30 cm)
48 G-050 1 M3 Pekerjaan Beton Bertulang Slof (30x40 cm)
49 G-051 1 M3 Dinding Beton Reservoar 20Cm
50 G-052 1 M3 Dinding Beton Water Tangk 15Cm
51 G-053 1 M3 Dinding Beton Water Tangk 12Cm
52 G-054 1 M3 Plat Beton Water Tank 20Cm
53 G-055 1 M3 Plat Beton Lantai 15Cm
54 G-056 1 M3 Plat Atap Beton 12Cm
55 G-057 1 M3 Plat Atap Beton 10Cm
56 G-058 1 M3 Lisplan Beton 10Cm
57 G-059 Pekerjaan Beton Plat Lantai 2 Sistem Bondex / M2
G-060 Pengecoran/M2
G-061 Pembesian/M2
G-062 Bekisting/M2
57 G-063 1 M3 Lantai Beton Tumbuk K.100 (Bertulang)

VIII H PEKERJAAN PENUTUP ATAP


1 H-001 1 M2 Pasang Atap Seng Gelombang
2 H-002 1 M2 Pasang Atap Genteng Metal
3 H-003 1 M1 Pasang Bubungan Genteng Metal
4 H-004 1 M2 Pasang Atap Nok Seng
5 H-005 1m² Pasang Atap Genteng Palentong Kecil
6 H-006 1m² Pasang Atap Genteng Kodok / Glazzur
7 H-007 1m² Pasang Atap Genteng Palentong Super / Besar
8 H-008 1m' Pasang Genteng Bubung Palentong
9 H-009 1m' Pasang Genteng Bubung Kodok Glazzur
10 H-010 1m' Pasang Genteng Bubung Palentong Besar
11 H-011 1m' Pasang Rooflight Fiberglass ( 180 x 90 ) cm
12 H-012 1m' Pasang Atap Asbes Gelombang ( 2.50 x 0.92 m ) X 5mm
13 H-013 1m' Pasang Atap Asbes Gelombang ( 2.25 x 0.92 m ) X 5mm
14 H-014 1m' Pasang Atap Asbes Gelombang ( 2.00 x 0.92 m ) X 5mm
15 H-015 1m' Pasang Atap Asbes Gelombang ( 1.80 x 0.92 m ) X 5mm
16 H-016 1m² Pasang Atap Asbes Gelombang ( 300 x 1.05 m ) X 4mm
17 H-017 1m² Pasang Atap Asbes Gelombang ( 270 x 1.05 m ) X 4mm
18 H-018 1m² Pasang Atap Asbes Gelombang ( 240 x 1.05 m ) X 4mm
19 H-019 1m² Pasang Atap Asbes Gelombang ( 210 x 1.05 m ) X 4mm
20 H-020 1m² Pasang Atap Asbes Gelombang ( 1.5 x 1.05 m ) X 4mm
21 H-021 1m² Pasang Atap Asbes Gelombang ( 3.00 x 1.08 m ) X 6mm
22 H-022 1m² Pasang Atap Asbes Gelombang ( 2.7 x 1.08 m ) X 6mm
23 H-023 1m² Pasang Atap Asbes Gelombang ( 2.4 x 1.08 m ) X 6mm
24 H-024 1m² Pasang Atap Asbes Gelombang ( 2.1 x 1.08 m ) X 6mm
25 H-025 1m² Pasang Atap Asbes Gelombang ( 1.80 x 1.08 m ) X 6mm
26 H-026 1m' Pasang Bubung Stel Gelombang 0.92m
27 H-027 1m' Pasang Nok Stel Gelombang 0.92m
28 H-028 1m' Pasang Nok Stel Gelombang 1.05m
29 H-029 1m' Pasang Nok Stel Gelombang 1.08m
30 H-030 1m' Pasang Nok Paten 0.92m
31 H-031 1m' Pasang Nok Paten 1.05m
32 H-032 1m' Pasang Nok Paten 1.08m
33 H-033 1m' Pasang Nok Stel rata 0.92m
34 H-034 1m' Pasang Nok Stel rata 1.05m
35 H-035 1m² Pasang Atap Genteng Beton
36 H-036 1m² Pasang Atap Genteng Aspal
37 H-037 1m² Pasang Atap Genteng Metal
38 H-038 1m² Pasang Atap Sirap
39 H-039 1m' Pasang Nok Genteng Beton
40 H-040 1m' Pasang Nok Genteng Aspal
41 H-041 1m' Pasang Nok Genteng Metal
42 H-042 1m' Pasang Nok Genteng Metal
43 H-043 1m' Pasang Nok Sirap
44 H-044 1m² Pasang Atap Seng Gelombang
45 H-045 1m² Pasang Atap Nok Seng
46 H-046 1m² Pasang Atap Alluminium
47 H-047 1m² Pasang Nok Alluminium
48 H-048 1m² Pasang Alluminium Foil / Sisalation
49 H-049 1 M2 Pekerjaan Multipleks 12 Mm Pelapis Atap
50 H-050 1 M2 Pekerjaan Multipleks 9 Mm Pelapis Atap
51 H-051 I M2 Pasang Atap Genteng Shingles (Owens)
53 H-052 1 M2 Pasang Atap Alumunium (Spandek/Super Dek)
H-053 1 M2 Pemasangan Atap Zincalumn
H-054 1 M' Pasang Nok Atap Alumunium (Spandek/Super Dek
H-055 1 M2 Pemasangan Alumunium Foil Double Sided
H-056 1 M2 Pekerjaan Glass Wool + Kawat Ram (□ 3 X 3 Cm)
H-057 1m' Pasang Flasing

XI I PEKERJAAN BESI
1 H-001 10 Cm Pengelasan Dengan Las Listrik
2 H-002 1 Kg Rangka Baja
3 H-003 1 Kg Pekerjaan Gording Canal
4 H-004 100 Kg Pekerjaan Perakitan Kuda-Kuda Baja
5 H-005 1 Kg Pekerjaan Erection Konstruksi Baja
6 H-006 1 Kg Pekerjaan Kuda-Kuda Baja
7 H-007 1 Kg Pekerjaan Pabrikasi Baja (Site)
8 H-008 1 k Pekerjaan Skur Dobel Profil L 60.60.6
9 H-009 1m Pekerjaan Tangga Besi Siku L 50 50.5 (Type 1)
10 H-010 1m Pekerjaan Tangga Besi Kotak 40x40 x2,3mm (Type 2)
11 H-011 1m Pekerjaan Tangga Pipa Giv 2" (Type 3)
12 H-012 1m Pekerjaan Tangga Pipa Giv 1,5" (Type 4)
13 H-013 1 M2 Pasang Pintu Besi Baja
14 H-014 1 m2 Membuat pintu besi plat baja tebal 2 mm rangkap, rangka baja siku
15 H-015 1 m2 Membuat pintu besi plat baja tebal 2 mm 1 Layer, rangka baja siku
16 H-016 1 m Pekerjaan Bending Pipa 3-SCH 40 Untuk Kuda-kuda bulat (Dom)
17 H-017 1 m Pekerjaan Bending Pipa 4-SCH 40 Untuk Kuda-kuda bulat (Dom)
18 H-018 1 m Pekerjaan Bending Pipa 3-SCH 80 Untuk Kuda-kuda bulat (Dom)
19 H-019 1 m Pekerjaan Bending Pipa 4-SCH 80 Untuk Kuda-kuda bulat (Dom)
20 H-020 1 m Pekerjaan Bending Pipa Hollow 4x4x2,3 kaso (Dom)
21 H-021 1 m Pekerjaan Railing Pengaman Type 1
22 H-022 1 Unit Pekerjaan Pemasangan Kuda Kuda Pipa Type K2.
23 H-023 1 Unit Pekerjaan Pemasangan Kuda Kuda Pipa Type K3.
24 H-024 1 Unit Pekerjaan Pemasangan Kuda Kuda Pipa Type K4.
25 H-025 1 Unit Pekerjaan Pemasangan Kuda Kuda Pipa Type K5.
26 H-026 1 Unit Pekerjaan Pemasangan Kuda Kuda Pipa Type Kb1.
27 H-027 1 Unit Pekerjaan Pemasangan Kuda Kuda Pipa Type Kb2.
28 H-028 1 Unit Pekerjaan Pemasangan Kuda Kuda Pipa Type Kb2a.
29 H-029 1 Unit Pekerjaan Pemasangan Kuda Kuda Pipa Type Kb3.
30 H-030 1 Unit Pekerjaan Pemasangan Kuda Kuda Pipa Type Kb4.
31 H-031 1 Unit Pekerjaan Pemasangan Kuda Kuda Pipa Type Kb4a.
32 H-032 1 Unit Pekerjaan Pemasangan Kuda Kuda Pipa Type Kb5.
33 H-033 1 m Pekerjaan Pemasangan Pipa 2 1/2-SCH 40 Untuk Gording
34 H-034 1 m Pekerjaan Pipa Hollow 4x4x2,3 kaso (Dom)
35 H-035 1 m Pekerjaan Pipa Ø6" -SCH 80 Untuk Kuda-kuda bulat (Dom)
36 H-036 1 kg Pekerjaan Pembuatan Plat Buhul 8mm
37 H-037 1 kg Pekerjaan Pembuatan Plat Buhul 10mm
38 H-038 1 kg Pekerjaan Pembuatan Plat Buhul/Join 12mm
39 H-039 1 kg Pekerjaan Pembuatan Plat Buhul/Join 16mm
40 H-040 1 kg Pekerjaan Pembuatan Plat Buhul/Join 20mm
41 H-041 1 kg Pekerjaan Pembuatan Plat Buhul/Join 25mm
42 H-042 1 Bh Pekerjaan Pemasangan Plat gording 8 mm
43 H-043 1 Bh Pekerjaan Pemasangan Plat Joint Balok FB 100 X 12
44 H-044 1 Bh Pekerjaan Pemasangan Plat Joint Balok PL. 12 THK
45 H-045 1 Bh Pekerjaan Pemasangan Plat Joint Balok PL. 16 THK
46 H-046 1 Bh Pekerjaan Pemasangan Plat Joint Balok PL. 25 THK
47 H-047 1 Bh Pekerjaan Pemasangan Plat Buhul/Sabungan 10mm
48 H-048 1 Bh Pekerjaan Pemasangan Plat Buhul 12mm
49 H-049 1 Bh Pekerjaan Pemasangan Plat Join Kuda Kuda 16mm
50 H-050 1 Lbr Pekerjaan Pasangan Base Plat PL.20.900.400mm
51 H-051 1 Lbr Pekerjaan Pasangan Base Plat 20 x623x275 mm
52 H-052 1 Btg Anchor Bolt Øm 28 Mm
53 H-053 1 Btg Anchor Bolt Øm 19 Mm
54 H-054 1 Bh Pemasangan baut/mur Angkur Geser Øm 19 MM
55 H-055 1 M' Gording Pipa Medium Dia. 1 ½ "
56 H-056 1 M2 Pasang Jendela Nako 7 klip & Tralis
57 H-057 1 M' Pasang Talang Datar, Seng BJLS 30"
58 H-058 1 M' Pasang Talang Miring, Seng BJLS 30"
59 H-059 1 M' Pasang Talang 1/2 Lingkaran D - 10 cm, Seng BJLS 30"
60 H-060 1 M2 Pemasangan Kuda - kuda baja ringan
61 H-061 1 m2 Pemasangan Covering Aluminium Composite (ACP)
62 H-062 1 m2 Pemasangan Covering GRC Kalsiboard eksterior 6 mm

IX J PEKERJAAN LANGIT - LANGIT


1 J-001 1 M2 Pasang Rangka Langit-Langit (50 X 100) cm, Kayu Kelas II atau III
2 J-002 1 M2 Pasang Rangka Langit-Langit (60 X 60) cm, Kayu Kelas II atau III
3 J-003 1 m2 Pemasangan rangka Besi hollow 1x40.40.2mm, modul 60 x 60 cm, untuk plafon
4 J-004 1 M2 Pasang Langit-Langit Gypsum Board, Ukuran (1200 x 2400 x 9) mm
5 J-005 1 M2 Pekerjaan Plafon Tripleks 6 Mm "
6 J-006 1 M' Pekerjaan List Plafon Profil "
7 J-007 1 M2 Pasang Langit-Langit Akustik Ukuran (30 x 30) cm
8 J-008 1 M2 Pasang Langit-Langit Akustik Ukuran (30 x 60) cm
9 J-009 1 M2 Pasang Langit-Langit Akustik Ukuran (60 x 120) cm
10 J-010 1 M2 Pasang Langit-Langit Tripleks Ukuran (120 x 240) cm, tebal 4 mm
11 J-011 1 M2 Pasang Plafond Lambriziring
12 J-012 1 M2 Pasang Langit-Langit Teakwood (60 x 120) cm, tebal 4 mm
13 J-013 1 M2 Pasang Langit-Langit Lat Kayu Kelas I
14 J-014 1 M2 Pasang Langit-Langit Lat Kayu Kelas II
15 J-015 1 M' Pasang List Langit-Langit Kayu Profil
16 J-016 1 m’ Pemasangan 1 m’ list langit-langit Gypsum
17 J-017 1 M 2 Langit-Langit Akustik 60 X 120 Cm + Rangka Alluminium"

X K PEKERJAAN SANITASI
1 K-001 Memasang 1 Buah Kloset Duduk/Monoblok
2 K-002 Memasang 1 Buah Kloset Jongkok Porselen
3 K-003 Memasang 1 Buah Wastafel
4 K-004 1 Bh Pasang Urinoir
5 K-005 1 Bh Pasang Floor Drain
6 K-006 1 Unit Pasang Tangki Fiber Glass Cap 2.2 M3
7 K-007 Memasang 1 Buah Bak Mandi Batu Batako Volume 0,30 M3
8 K-008 1 M' Pasang Pipa Tanah Penyalur Air Limbah Diameter 15 cm
9 K-009 1 M' Pekerjaan Pipa Gip Ø ½ " "
10 K-010 1 M' Pekerjaan PIPA GIP Ø ¾ " "
11 K-011 1 M' Pekerjaan PIPA GIP Ø 1 " "
12 K-012 1 M' Pekerjaan PIPA GIP Ø 1 ¼ " "
13 K-013 1 M' Pekerjaan PIPA GIP Ø 1 ½ " "
14 K-014 1 M' Pekerjaan PIPA GIP Ø 2 " "
15 K-015 1 M' Pekerjaan PIPA GIP Ø 3 "
16 K-016 1 M' Pekerjaan PIPA GIP Ø 4 "
17 K-017 1 M' Pekerjaan PIPA PVC Ø 6 "
18 K-018 1 M' Pekerjaan PIPA PVC Ø 4 "
19 K-019 1 M' Pekerjaan PIPA PVC Ø 3 "
20 K-020 1 M' Pekerjaan PIPA PVC Ø 2 "
21 K-021 1 M' Pekerjaan PIPA PVC Ø 1 ½ "
22 K-022 1 M' Pekerjaan PIPA PVC Ø 1 "
K-023 1 M' Pekerjaan PIPA PVC Ø 3/4"
23 K-024 Memasang 1 Buah Bak Kontrol Pasangan Batu Bata ukuran ( 30 x 30 ) cm Tinggi 35 cm
24 K-025 Memasang 1 Buah Bak Kontrol Pasangan Batu Bata ukuran ( 45 x 45 ) cm Tinggi 50 cm
25 K-026 Memasang 1 Buah Bak Kontrol Pasangan Batu Bata ukuran ( 60 x 60 ) cm Tinggi 65 cm
26 K-027 Memasang 1 Buah Cuci Piring Stainles Steel
27 K-028 Memasang 1 Buah Kran Diameter 3/4" atau 1/2"
28 K-029 Memasang 1 Kran air + shower bilas dia 3/4
29 K-030 1 Unit Ground Reservoar
30 K-031 1 Unit Pekerjaan Septictank & Rembesan
31 K-032 1 M' Saluran Type 1 (Tepi Pagar)
32 K-033 1 M' Saluran Type 2 (Dari Halaman Ke Saluran Type 1)
33 K-034 1 M' Saluran Ditepi Jalan Type 3
34 K-035 1 M' Pasang Kawat Duri Pada Pagar Keliling
35 K-036 1 M' Profil Beton
36 K-037 1 M' Pekerjaan Saluran Keliling Bangunan
37 K-038 1 M' Pek. Saluran Pembuangan Ke Riol Kota

XII L PEKERJAAN KUNCI DAN KACA


1 L-001 1 Buah Pasang Kunci Tanam Antik
2 L-002 1 Buah Pasang Kunci Tanam Biasa
3 L-003 1 Buah Pasang Kunci Cylinder
4 L-004 1 Buah Pasang Engsel Pintu
5 L-005 1 Bh Engsel Jendela
6 L-006 1 Buah Pasang Engsel Jendela Kupu-Kupu
7 L-007 1 Buah Pasang Kait Angin
8 L-008 1 Buah Pasang Pegangan Pintu/Door Holder
9 L-009 1 Bh Pasang Door Closer
10 L-010 1 Bh Pasang Door Stop
11 L-011 1 Bh Grendel Jendela
12 L-012 1 Psg Pasang Grendel Pintu Double
13 L-013 1 Buah Pasang Kunci Lemari
14 L-014 1 M2 Pasang Kaca, Tebal 3 mm
15 L-015 1 M2 Pasang Kaca, Tebal 5 mm
16 L-016 1 M2 Pasang Kaca, Tebal 8 mm
1 M2 Pemasangan 1 M2 kaca tebal 12 mm
L-017
L-018 1 M2 Pekerjan Daun Pintu Kaca Tempered 12 mm

XIII M PEKERJAAN PENUTUP LANTAI DAN DINDING


1 M-001 1 M2 Pasangan Lantai Keramik 60/60
2 M-002 1 M2 Pasang Lantai Keramik Ukuran (30 x 30 ) cm
3 M-003 1 M2 Pasang Lantai Keramik Ukuran (20 x 20 ) cm
4 M-004 1 M2 Pasang Lantai Keramik Ukuran (10 x 20 ) cm, Variasi/Border
5 M-005 1 M2 Pasang Lantai Mosaik Ukuran (30 x 30 ) cm, Campuran Spesi 1 pc : 3 PP
6 M-006 1 M2 Pasang Dinding Porselen Ukuran (11 x 11) cm
4 M-007 1 M2 Pasang plint Dinding Keramik Ukuran (10 x 30) cm
5 M-008 1 M2 Pasang Dinding Keramik Ukuran (20 x 25) cm
6 M-009 1 M2 Pasang Lantai Keramik Ukuran (10 x 20) cm
7 M-010 1 M' Pasang Plint Kayu Kelas II Tebal 2 cm, Lebar 10 cm
8 M-011 1 M' Pasangan Border Keramik 6/20
M-012 1 M2 Pemasangan Wall Paper

XIV N PEKERJAAN PENGECATAN


1 N-001 1 M2 Mengikis Bidang Permukaan Cat Tembok Lama
2 N-002 1 M2 Mencuci Bidang Permukaan Cat Tembok Lama
3 N-003 1 M2 Mendempul dan Menggosok Kayu
4 N-004 1 M2 Pengecatan Bidang Kayu Lama
5 N-005 1 M2 Pengecatan Bidang Kayu Baru ( 1 Lapisan Plamir ), 1 Lapis Cat Dasar, 2 Lapis Cat Penutup
6 N-006 1 M2 Pengecatan Bidang Kayu Baru ( 1 Lapisan Plamir ), 1 Lapis Cat Dasar, 3 Lapis Cat Penutup
7 N-007 1 M2 Pelaburan Bidang Kayu Dengan Teak Oil
8 N-008 1 M2 Pelaburan Bidang Kayu Dengan Politur
9 N-009 1 M2 Pelaburan Bidang Kayu Dengan Cat Residu dan Ter
10 N-010 1 M2 Pelaburan Bidang Kayu Dengan Vernis
11 N-011 1 M2 Pengecatan Tembok Baru ( 1 Lapis Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup )
12 N-012 1 M2 Pengecatan Tembok Lama ( 1 Lapis Cat Dasar, 2 Lapis Cat Penutup)
13 N-013 1 M2 Pengecatan Permukaan Baja dengan Meni Besi
14 N-014 1 M2 Duco Melamine Clear Dof
15 N-015 1 M2 Cat Plafon "
16 N-016 1 M2 Cat Melamin"
17 N-017 1 M 2 Mengikis Bidang Permukaan Tmbok Yang Pernah Di Cat
18 N-018 1 M 2 Mencuci Bidang Permukaan Tembok Yang Pernah Di Cat
19 N-019 1 M 2 Mengorek Karat Cat Lama Permukaan Baja Dengancara Manual
20 N-020 1 M 2 Menyabun Permukaan Tembok Lama
21 N-021 1 M 2 Mengerok Karat Atau Cat Lama Permukaan Baja Dengan Pancar Pasir ( Samblasting ) Dengan Tingkat Ke
22 N-022 1 M 2Mendempul Dan Menggosok Kayu
23 N-023 1 M 2Pengecatan Bidang Kayu Lama
24 N-024 1 M 2 Pengecatan Bidang Kayu Baru ( 1 Lapisan Plamir ), 1 Lapis Cat Dasar, 2 Lapis Cat Penutup
25 N-025 1 M 2 Pengecatan Bidang Kayu Baru ( 1 Lapisan Plamir ), 1 Lapis Cat Dasar, 3 Lapis Cat Penutup
26 N-026 1 M 2 Pelaburan Bidang Kayu Dengan Teak Oil
27 N-027 1 M 2 Pelaburan Bidang Kayu Dengan Politur
28 N-028 1 M 2 Pelaburan Bidang Kayu Dengan Cat Residu Dan Ter
29 N-029 1 M2 Pelaburan Bidang Kayu Dengan Dengan Vernis
30 N-030 1 M2 Pengecatan Tembok Baru ( 1 Lapis Plamir, 1 Lapis Cat Dasar,2 Lapis Cat Penutup )
31 N-031 1 M2 Pengecatan Tembok Lama ( 1 Lapis Cat Dasar 2 Lapis Cat Penutup
32 N-032 1 M2 Melabur Tembok Dengan Kalkarium
33 N-033 1 M2 Melabur Tembok Dengan Kapur Sirih
34 N-034 1 M2 Melabur Tembok Lama Dengan Kapur Sirih ( Untuik Pemeliharaan )
35 N-035 1 M2 Pengecatan Permukaan Baja Dengan Meni Besi
36 N-036 1 M2 Pengecatan Permukaan Baja Dengan Meni Besi Dan Perancah
37 N-037 1 M2 Pengecatan Permukaan Baja Lapis Seng ( Galbani ) Secara Manual Sitem 4 Lapis Cat Konvensional Deng
38 N-038 1 M2 Pengecatan Permukaan Baja Lapis Seng ( Galbani ) Secara Manual Sitem 1 Lapis Cat Konvensional Deng
39 N-039 1 M2 Pengecatan Permukaan Baja Lapis Seng ( Galbani ) Secara Manual Sitem 3 Lapis Cat Konvensional Deng
40 N-040 1 M2 Pengecatan Permukaan Baja Lapis Seng ( Galbani ) Secara Semprot ( Airless Spray ) Dengan Sitem 1 Lap
41 N-041 1 M2 Pemasangan Waterproofing Membrane
52 N-042 1 M2 Water Proofing
54 N-043 1 M2 Water Proofing (Coating)

O PEKERJAAN LISTRIK
1 O-001 1 Titik Instalasi Lampu / Penerangan
2 O-002 1 Titik Instalasi Stop Kontak / Power Outlet
3 O-003 1 Titik Instalasi Ac 1 Phase
4 O-004 1 Titik Instalasi Ac 3 Phase
5 O-005 1 Titik Instalasi Sound System
6 O-006 1 Titik Instalasi Telephone
7 O-007 1 Titik Instalasi Fire Alarm
8 O-008 Pemasangan Penangkal Petir(Unit)
9 O-009 1 Set Grounding Pentanahan
10 O-010 1 Ttk Lampu Tl 2 X 20 Watt
11 O-011 1 Ttk Lampu Tl 20 Watt
12 O-012 1 Ttk Lampu Pijar 40 Watt
13 O-013 1 Bh. Stop Kontak 2 Fase
14 O-014 1 Bh. Sekring Box 2 Group
15 O-015 1 Bh. Panel Instalasi
16 O-016 1 Bh Saklar Double
17 O-017 1 Bh Saklar Tunggal
BAHAN

HARGA SATUAN
SATUAN
(Rp.)
-
-
A
M2 Rp 2,856,666.67 A-01
M' Rp 470,969.70 A-02
M' Rp 534,120.00 A-03
M' Rp 817,120.00 A-04
M' Rp 139,350.00 A-05
M2 Rp 1,728,050.00 A-06
M2 Rp 1,816,500.00 A-07
M2 Rp 33,000.00 A-08
M2 Rp 1,628,300.00 A-09
M2 Rp 53,710.00 A-10
M2 Rp 348,600.00 A-11
M3 Rp 1,299,960.00 A-12
M3 Rp 1,209,960.00 A-13
-
B
M3 Rp 142,500.00 B-01
M3 Rp 175,500.00 B-02
M3 Rp 209,100.00 B-03
M3 Rp 189,600.00 B-04
M3 Rp 288,000.00 B-05
M3 Rp 229,500.00 B-06
M3 Rp 10,500.00 B-07
M3 Rp 62,400.00 B-08
M3 Rp 40,260.00 B-09
M3 Rp 105,000.00 B-10
M3 Rp 369,000.00 B-11
M3 Rp 364,500.00 B-12
M3 Rp 649,500.00 B-13
M3 Rp 517,400.00 B-14
M3 Rp 242,379.55 B-15
M3 Rp 755,099.89 B-16
-
C
M3 Rp 2,380,600.00 C-01
M3 Rp 2,295,700.00 C-02
M3 Rp 2,236,840.00 C-03
M3 Rp 2,195,460.00 C-04
M3 Rp 2,138,740.00 C-05
M3 Rp 1,616,040.00 C-06
n 40% Batu Belah M3 Rp 4,310,300.00 C-07
M3 Rp 2,169,400.00 C-08
M' Rp 2,091,340.00 C-09
M' Rp 1,631,810.00 C-10
-
D
M2 Rp 500,415.00 D-01
M2 Rp 456,650.00 D-02
M2 Rp 434,235.00 D-03
M2 Rp 418,955.00 D-04
M2 Rp 411,320.00 D-05
M2 Rp 550,415.00 D-06
M2 Rp 506,650.00 D-07
M2 Rp 484,235.00 D-08
M2 Rp 468,955.00 D-09
M2 Rp 461,320.00 D-10
pesi 1 PC : 3 PP M2 Rp 3,207,820.00 D-11
pesi 1 PC : 4 PP M2 Rp 3,816,400.00 D-12
an Spesi 1 PC : 3 PP M2 Rp 146,720.00 D-13
Spesi 1 PC : 3 PP M2 Rp 172,233.00 D-14
-
E
M2 Rp 144,720.00 E-01
M2 Rp 132,960.00 E-02
M2 Rp 127,920.00 E-03 103%
M2 Rp 124,440.00 E-04 97%
M2 Rp 122,520.00 E-05
M2 Rp 120,960.00 E-06
M2 Rp 136,030.00 E-07
M2 Rp 131,535.00 E-08
M2 Rp 132,730.00 E-09
M2 Rp 74,925.00 E-10
-
F
M3 Rp 12,703,000.00 F-01
M3 Rp 10,374,000.00 F-02
M3 Rp 561,800.00 F-03
M2 Rp 1,229,000.00 F-04
M2 Rp 1,349,000.00 F-05
M2 Rp 1,223,200.00 F-06
yu Kelas II (Lebar sampa M2 Rp 814,950.00 F-07
u Kelas I dan II M2 Rp 920,100.00 F-08
M2 Rp 1,081,600.00 F-09
M2 Rp 949,100.00 F-10
M2 Rp 969,450.00 F-11
M2 F-12
M3 Rp 9,559,000.00 F-13
M3 Rp 14,487,300.00 F-14
M3 Rp 7,834,600.00 F-15
M2 Rp 103,800.00 F-16
M2 Rp 103,800.00 F-17
M2 Rp 640,260.00 F-18
M' Rp 132,100.00 F-19
M' Rp 130,600.00 F-20
M' Rp 131,600.00 F-21
M2 Rp 257,000.00 F-22
M2 Rp 257,000.00 F-23
M2 Rp 308,300.00 F-24
M2 Rp 694,400.00 F-25
M2 Rp 27,290.00 F-26
M2 Rp 82,760.00 F-27
M Rp 299,000.00 F-28
M Rp 102,566.67 F-29
M3 Rp 11,790,000.00 F-30
M3 #VALUE! F-31
M2 Rp 245,120.00 F-32
M2 #VALUE! F-33
M' Rp 221,762.50 F-34 1 M' Pemancangan Cerocok Kayu
M2 Rp 357,250.00 F-35
M2 Rp 328,000.00 F-36
M2 #N/A F-37
M2 #N/A F-38
M2 #N/A F-39
Pt Rp 150,200.00 F-40
M Rp 348,675,000.00 F-41
Ps Rp 186,000,000.00 F-42
M Rp 225,300,000.00 F-43
M Rp 209,781,250.00 F-44
M Rp 62,000,000.00 F-45
M3 #VALUE! F-46
M3 #VALUE! F-47
M3 #VALUE! F-48
M3 #VALUE! F-49
M2 Rp 178,267,000.00 F-50

-
G
M3 Rp 1,540,300.00 G-001
M3 Rp 1,503,400.00 G-002
M3 Rp 1,445,800.00 G-003
cm, w/c = 0,87 M2 Rp 345,080.00 G-004
M3 Rp 1,540,090.00 G-005
M3 Rp 1,692,490.00 G-006
M3 Rp 1,816,090.00 G-007
M3 Rp 1,701,390.00 G-008
M3 Rp 1,907,090.00 G-009
M3 Rp 2,084,390.00 G-010
M3 Rp 2,731,600.00 G-011
M3 Rp 3,056,252.38 G-012
M3 Rp 3,084,365.08 G-013
M3 Rp 3,132,685.71 G-014
M3 Rp 3,147,636.51 G-015
M3 Rp 337,310.00 G-016
M3 Rp 324,500.00 G-017
M2 Rp 334,180.00 G-018
M2 Rp 352,930.00 G-019
M2 Rp 590,190.00 G-020
M2 Rp 737,737.50
M2 Rp 600,690.00 G-022
M2 Rp 730,190.00 G-023
M2 Rp 642,690.00 G-024
M2 Rp 803,362.50
M2 Rp 565,300.00 G-026
M2 Rp 290,300.00 G-027
M3 Rp 8,338,060.00 G-028
M3 Rp 10,586,790.00 G-029
M3 Rp 16,754,200.00 G-030
M3 Rp 11,055,900.00 G-031
M3 Rp 12,362,300.00 G-032
M3 Rp 11,204,950.00 G-033
M3 Rp 10,582,560.00 G-034
M3 Rp 11,683,290.00 G-035
M' Rp 124,055.00 G-036
M' Rp 178,860.00 G-037
M3 Rp 8,952,551.25 G-038
M3 Rp 8,874,060.59 G-039
M3 Rp 12,301,258.38 G-040
M3 G-041
M3 G-042
M3 G-043
M3 G-044
M3 G-045
M3 G-046
M3 G-047
M3 Rp 13,933,941.84 G-048
M3 G-049
M3 G-050
M3 Rp 15,514,551.68 G-051
M3 G-052
M3 G-053
M3 Rp 12,074,840.92 G-054
M3 Rp 17,180,998.66 G-055
M3 Rp 19,129,744.89 G-056
M3 G-057
M3 G-058
M2 #N/A G-059
M3 Rp 584,451.48 G-060
KG #N/A G-061
M2 #N/A G-062
M3 G-063
-
H
M2 Rp 110,680.00 H-001
M2 Rp 158,100.00 H-002
M1 Rp 125,600.00 H-003
M2 Rp 90,240.00 H-004
m² #N/A H-005
m² #N/A H-006
m² #N/A H-007
m' #N/A H-008
m' #N/A H-009
m' #N/A H-010
m' #N/A H-011
m' #N/A H-012
m' #N/A H-013
m' #N/A H-014
m' #N/A H-015
m² #N/A H-016
m² #N/A H-017
m² #N/A H-018
m² #N/A H-019
m² #N/A H-020
m² #N/A H-021
m² #N/A H-022
m² #N/A H-023
m² #N/A H-024
m² #N/A H-025
m' #N/A H-026
m' #N/A H-027
m' #N/A H-028
m' #N/A H-029
m' #N/A H-030
m' #N/A H-031
m' #N/A H-032
m' #N/A H-033
m' #N/A H-034
m² #N/A H-035
m² #N/A H-036
m² Rp 70,100.00 H-037
m² #N/A H-038
m' #N/A H-039
m' #N/A H-040
m' #N/A H-041
m' #N/A H-042
m' #N/A H-043
m² #N/A H-044
m² #N/A H-045
m² #N/A H-046
m² #N/A H-047
m² Rp 60,100.00 H-048
M2 #N/A H-049
M2 #N/A H-050
M2 Rp 84,550.00 H-051
M2 Rp 312,002.50 H-052
M2 Rp 138,904.50 H-053
M' Rp 336,600.00 H-054
M2 Rp 60,100.00 H-055
M2 Rp 128,350.00 H-056
m' Rp 161,300.00 H-057

I
Cm Rp 95,650.00 H-001
Kg Rp 28,380.00 H-002
Kg Rp 28,380.00 H-003
Kg Rp 67,080.00 H-004
Kg Rp 13,455.02 H-005
Kg Rp 41,835.02 H-006
#VALUE! H-007
Rp 91,859.78 H-008
Rp 533,808.28 H-009
Rp 1,886,415.95 H-010
Rp 594,958.38 H-011
Rp 453,291.71 H-012
Rp 1,157,300.00 H-013
Rp 2,153,266.52 H-014
Rp 1,743,266.52 H-015
Rp 475,140.49 H-016
Rp 359,397.14 H-017
Rp 476,432.32 H-018
Rp 661,556.54 H-019
Rp 6,222.04 H-020
Rp 1,311,650.00 H-021
Rp 54,609,040.06 H-022
Rp 54,093,436.22 H-023
Rp 43,629,572.37 H-024
Rp 48,176,254.22 H-025
Rp 31,360,672.17 H-026
Rp 24,590,781.57 H-027
Rp 18,126,849.82 H-028
Rp 10,466,129.84 H-029
Rp 12,462,317.80 H-030
Rp 16,019,471.52 H-031
Rp 45,042,482.76 H-032
Rp 139,880.41 H-033
#N/A H-034
Rp 1,075,203.28 H-035
Rp 40,071.43 H-036
Rp 44,150.00 H-037
Rp 44,900.00 H-038
Rp 49,218.75 H-039
Rp 50,718.75 H-040
Rp 52,593.75 H-041
Rp 146,485.44 H-042
Rp 198,444.69 H-043
Rp 280,843.71 H-044
Rp 1,096,017.84 H-045
Rp 2,153,694.91 H-046
Rp 229,305.70 H-047
Rp 267,086.84 H-048
Rp 361,613.89 H-049
Rp 4,033,093.54 H-050
Rp 1,942,126.36 H-051
Rp 522,030.09 H-052
Rp 207,560.03 H-053
Rp 29,901.50 H-054
H-055
Rp 472,500.00 H-056
Rp 253,241.50 H-057
Rp 271,674.80 H-058
Rp 259,125.00 H-059
Rp 373,987.68 H-060
Rp 956,260.00 H-061
Rp 633,510.00 H-062
- Covering GRC Kalsiboard eksterior 6 mm x 1220 x 2440
J
Rp 192,800.00 J-001
Rp 186,950.00 J-002
cm, untuk plafon Rp 216,150.00 J-003
Rp 105,680.00 J-004
Rp 86,416.00 J-005
Rp 54,100.00 J-006
Rp 24,100.00 J-007
Rp 48,800.00 J-008
Rp 48,800.00 J-009
Rp 106,700.00 J-010
Rp 613,400.00 J-011
#N/A J-012
Rp 339,100.00 J-013
Rp 309,100.00 J-014
Rp 39,850.00 J-015
Rp 63,640.00 J-016
#N/A J-017
-
K
Rp 4,945,280.00 K-001
Rp 1,041,600.00 K-002
Rp 2,230,100.00 K-003
Rp 4,484,100.00 K-004
Rp 533,640.00 K-005
K-006
Rp 2,689,500.00 K-007
#N/A K-008
Rp 125,496.25 K-009
Rp 125,496.25 K-010
Rp 142,027.50 K-011
Rp 196,076.25 K-012
Rp 181,308.33 K-013
Rp 236,412.50 K-014
Rp 71,100.00 K-015
Rp 88,890.00 K-016
Rp 53,340.00 K-017
Rp 205,427.50 K-018
Rp 145,915.00 K-019
Rp 118,206.25 K-020
Rp 41,731.25 K-021
Rp 36,985.00 K-022
Rp 35,331.88 K-023
Tinggi 35 cm Rp 1,070,310.00 K-024
Tinggi 50 cm Rp 1,189,210.00 K-025
Tinggi 65 cm Rp 1,406,190.00 K-026
Rp 639,250.00 K-027
Rp 151,725.00 K-028
K-029
#N/A K-030
Rp 34,236,656.71 K-031
K-032
K-033
K-034
K-035
K-036
Rp 600,289.00 K-037
Rp - K-038
-
L
Rp 178,500.00 L-001
Rp 581,100.00 L-002
Rp 531,100.00 L-003
Rp 219,625.00 L-004
Rp 194,750.00 L-005
Rp 194,750.00 L-006
Rp 164,625.00 L-007
Rp 148,750.00 L-008
Rp 1,348,750.00 L-009
Rp 379,750.00 L-010
Rp 194,625.00 L-011
Rp 406,300.00 L-012
Rp 74,375.00 L-013
Rp 44,625.00 L-014
Rp 314,625.00 L-015
Rp 49,080.00 L-016
Rp 3,909,580.00 L-017
Rp 7,868,240.00 L-018
-
M
Rp 654,875.00 M-001
Rp 497,294.00 M-002
Rp 504,500.00 M-003
Rp 479,090.00 M-004 Rp 28,745.40
Rp 394,435.00 M-005
Rp 393,730.00 M-006
Rp 72,410.00 M-007
Rp 606,730.00 M-008
Rp 291,470.00 M-009
Rp 69,510.00 M-010
Rp 101,650.00 M-011
#N/A M-012
-
N
Rp 27,750.00 N-001
Rp 27,750.00 N-002
Rp 19,970.00 N-003
Rp 66,900.00 N-004
r, 2 Lapis Cat Penutup Rp 81,630.00 N-005
r, 3 Lapis Cat Penutup Rp 112,720.00 N-006
Rp 41,340.00 N-007
Rp 98,800.00 N-008
Rp 19,800.00 N-009
Rp 88,530.00 N-010
s Cat Penutup ) Rp 70,564.00 N-011
Rp 53,666.00 N-012
Rp 68,416.60 N-013
Rp 59,050.00 N-014
Rp 49,657.68 N-015
Rp 117,800.00 N-016
Rp 27,750.00 N-017
Rp 27,750.00 N-018
Rp 27,750.00 N-019
Rp 27,750.00 N-020
ir ( Samblasting ) Dengan Tingkat Keb #N/A N-021
#N/A N-022
#N/A N-023
ar, 2 Lapis Cat Penutup #N/A N-024
ar, 3 Lapis Cat Penutup #N/A N-025
#N/A N-026
#N/A N-027
#N/A N-028
#N/A N-029
Cat Penutup ) #N/A N-030
#N/A N-031
#N/A N-032
#N/A N-033
#N/A N-034
Rp 68,316.60 N-035
#N/A N-036
tem 4 Lapis Cat Konvensional Deng #N/A N-037
tem 1 Lapis Cat Konvensional Deng Rp 57,240.00 N-038
tem 3 Lapis Cat Konvensional Deng #N/A N-039
Airless Spray ) Dengan Sitem 1 Lap #N/A N-040
Rp 81,114.29 N-041
#N/A N-042
Rp 131,489.58 N-043
-
O
Rp 856,150.00O-001
Rp 921,000.00O-002
Rp 1,639,750.00O-003
Rp 2,119,750.00O-004
Rp 791,600.00O-005
Rp 755,350.00O-006
Rp 748,675.00O-007
Rp 28,629,500.00O-008
Rp 8,025,500.00O-009
O-010
O-011
O-012
O-013
Rp 412,500.00 O-014
O-015
Rp 212,500.00 O-016
Rp 202,500.00 O-017
RENC.BANGUN
Memancang Tiang Pancang galam dia.10/12 - 4m
Memancang Tonkat ulin 5/10 - 2m
Pek. Pemasangan Sunduk 5/10 - 0,5m /Ptg
Pek. Pemasangan Kalang / Lapak 5/10 - 0,5m /Ptg
Pek. Pemasangan Sloof 5/7 - 2m /Btg
Pek. Pemasangan Suai ulin 5/7 - 4m /Btg
Pek. Pemasangan Gelagar ulin 5/7 - 4m /Btg
Pek. Pemasangan Lantai ulin 1,5/20 - 2m /Kpg
Pek. Pemasangan Tiang ulin 5/10 - 4m /Btg
Pek. Pemasangan Rangka Badan Kayu ulin 5/7 - 4m /Btg
Pek. Pemasangan Rangka Atap Kayu ulin 5/7 - 2m /Btg
Pek. Pemasangan Rangka Atap Kayu ulin 5/10 - 2m /Btg
Pek. Memasang atap seng gelombang BJLS / M2
Memancang Tiang Pancang galam dia.10/12 - 2m
Pek. Pengurugan tanah biasa 1 m3
1 M2 Dinding papan dilidah/alur
1 M2 Dinding papan susun sirih
1 M2 Dinding triplek 4 mm rangka kayu Meranti
1 M2 Dinding double triplek 4 mm rangka kayu Meranti
1 M2 Dinding double triplek Sungkai rangka kayu Meranti
erior 6 mm x 1220 x 2440
RENCANA ANGGARAN BIAYA (RAB)
KEGIATAN :
PEKERJAAN : REHABILITASI KANTOR CABANG
INSTANSI PERUM BULOG CABANG TIMIKA
LOKASI : JL.YOS SUDARSO SP1 TIMIKA,KAB.MIMIKA
TAHUN :
HARGA SATUAN
NO URAIAN JENIS PEKERJAAN SAT VOLUME JUMLAH
(Rp)

(a) (b) (c) (d) (e)

I. PEKERJAAN PERSIAPAN Rp 58,000,000.00


. Pembongkaran bangunan lama dan pembersihan Ls 1.00 Rp 15,000,000.00 Rp 15,000,000.00
. Mobilisasi Ls 2.00 Rp 5,000,000.00 Rp 10,000,000.00
. Pembuatan Direksi Keet, Gudang/barak Kerja m2 16.00 Rp 500,000.00 Rp 8,000,000.00
. Managemen K3 Ls 1.00 Rp 15,000,000.00 Rp 15,000,000.00
. Shop Drowing Ls 1.00 Rp 10,000,000.00 Rp 10,000,000.00

II. PEKERJAAN TANAH & PASIR Rp 121,248,796.00


. Pengukuran dan Pemasangan Bouwplank m 193.33 Rp 139,350.00 Rp 26,941,000.00
. Galian Tanah Pondasi Tapak m3 64.13 Rp 142,500.00 Rp 9,137,812.50
. Galian Tanah Pondasi Bt,Kali m3 104.40 Rp 142,500.00 Rp 14,877,000.00
. Urugan Tanah kembali m3 56.17 Rp 40,260.00 Rp 2,261,605.50
. Urugan Pasir dibawah Pondasi m3 18.78 Rp 369,000.00 Rp 6,927,975.00
. Urugan Pasir dibawah Lantai m3 27.88 Rp 369,000.00 Rp 10,288,458.00
. Urugan Sirtu dibawah Lantai m3 139.41 Rp 364,500.00 Rp 50,814,945.00

III. PEKERJAAN BETON Rp 650,371,192.83


. Beton Lantai Kerja 1:3:5 m3 2.14 Rp 1,540,300.00 Rp 3,292,391.25
. Beton Rabat Lantai m3 19.52 Rp 1,540,300.00 Rp 30,062,651.22
. Beton Pondasi Poot Plat m3 5.70 Rp 8,338,060.00 Rp 47,526,942.00
. Beton Slof 20x30 Cm m3 8.70 Rp 10,586,790.00 Rp 92,105,073.00
. Beton Kolom (K-1) 20x30 Cm m3 6.03 Rp 16,754,200.00 Rp 101,027,826.00
. Beton Kolom Enterance (K-2) 30X30 Cm m3 0.99 Rp 16,754,200.00 Rp 16,586,658.00
. Kolom Pintu Utama 20X30 Cm m3 0.43 Rp 16,754,200.00 Rp 7,237,814.40
. Beton Ring Balk (RB-1) 15x25 m3 1.85 Rp 12,362,300.00 Rp 22,808,443.50
. Beton Balok atap/talang (BA-1) 20x35 m3 5.41 Rp 12,362,300.00 Rp 66,927,019.74
. Balok Atap Enterance 20x35 m3 1.20 Rp 12,362,300.00 Rp 14,797,673.10
. Beton Plat atap/talang m3 11.64 Rp 11,055,900.00 Rp 128,703,943.08
. Beton Plat atap Enterance m3 2.27 Rp 11,055,900.00 Rp 25,048,247.04
. Lispalan Beton m3 1.44 Rp 10,582,560.00 Rp 15,238,886.40
. Plat Kanopi m3 2.80 Rp 11,055,900.00 Rp 30,945,464.10
. Beton Kolom Ptaktis m 165.00 Rp 124,055.00 Rp 20,469,075.00
. Beton Ring Balk Ptaktis m 145.00 Rp 178,860.00 Rp 25,934,700.00
. Meja dapur m3 0.15 Rp 11,055,900.00 Rp 1,658,385.00

IV. PEKERJAAN BATU DAN FINISHING Rp 962,134,717.39


. Pas. Batu Kosong m3 31.20 Rp 1,616,040.00 Rp 50,420,448.00
. Pas. Pondasi atu Kali m3 72.50 Rp 2,295,700.00 Rp 166,438,250.00
. Pas. Pondasi Rolak m2 20.00 Rp 434,235.00 Rp 8,684,700.00
. Pas.Dinding Batu Tela 1:3 m2 56.46 Rp 434,235.00 Rp 24,514,736.93
. Pas.Dinding Batu Tela 1:4 m2 494.90 Rp 418,955.00 Rp 207,340,829.50
. Plesteran Dinding 1:4 m2 989.80 Rp 124,440.00 Rp 123,170,712.00
. Plesteran Dinding 1:3 m2 112.91 Rp 127,920.00 Rp 14,443,447.20
733291305.xlsx 3.REHAB KANTOR 135/191
(a) (b) (c) (d) (e)
. Plesteran Beton 1:2 m2 75.00 Rp 132,960.00 Rp 9,972,000.00
. Acian Total m2 1,177.71 Rp 74,925.00 Rp 88,239,921.75
. Pas. Lantai Keramik 60x60 m2 248.27 Rp 654,875.00 Rp 162,585,816.25
. Pas. Keramik Trap Tangga 60x60 m2 11.76 Rp 785,850.00 Rp 9,241,596.00
. Pas. Lantai keramik Teras m2 19.64 Rp 654,875.00 Rp 12,861,745.00
. Pas. Lantai Keramik Kamar Mandi m2 8.41 Rp 504,500.00 Rp 4,242,845.00
. Pas. Dinding Keramik Kamar Mandi m2 43.51 Rp 606,730.00 Rp 26,400,035.76
. Pas. Brder Keramik Kamar Mandi m 26.00 Rp 47,909.00 Rp 1,245,634.00
. Pas. Plin Keramik m 200.00 Rp 72,910.00 Rp 14,582,000.00
. Pas.dinding batu alam m2 35.00 Rp 350,000.00 Rp 12,250,000.00
. Pas. Loster/batu angin m2 2.00 Rp 250,000.00 Rp 500,000.00
. Pekerjaan Ornamen Kolom dan Profil-Profil Ls 1.00 Rp 25,000,000.00 Rp 25,000,000.00

V. PEKERJAAN KUSEN, PINTU DAN JENDELA Rp 145,525,277.90


. Pek. Kusen Pintu m3 0.60 Rp 12,703,000.00 Rp 7,621,800.00
. Pek. Kusen Jendela dan Ventilasi m3 0.80 Rp 12,703,000.00 Rp 10,162,400.00
. Pek. Daun Pintu Kaca Tempered 12 mm m2 3.46 Rp 7,868,240.00 Rp 27,227,257.70
. Pek. Daun Pintu Panil m2 17.30 Rp 1,229,000.00 Rp 21,264,158.00
. Pek. Daun Pintu Kamar Mandi m2 6.08 Rp 1,229,000.00 Rp 7,468,387.20
. Pek. Daun Jendela Kaca Buka m2 29.16 Rp 1,223,200.00 Rp 35,668,512.00
. Pek. Daun Ventilasi Kaca Buka m2 28.34 Rp 1,223,200.00 Rp 34,665,488.00
. Pek. Ventilasi Kaca mati m2 4.60 Rp 314,625.00 Rp 1,447,275.00

VI. PEKERJAAN ATAP, PLAFON DAN RAILING Rp 769,173,862.76


. Pas. Rangka Plafond Kayu Kelas 2 m2 29.25 Rp 192,800.00 Rp 5,639,400.00
. Pas. Rangka Plafond Besi Hollw m2 280.69 Rp 216,150.00 Rp 60,671,143.50
. Pas. Plafond Triplex 6mm m2 6.46 Rp 86,416.00 Rp 558,247.36
. Pas. Plafond Gypsum m2 280.69 Rp 105,680.00 Rp 29,663,319.20
. Pas. Plafon Kayu Lumberserng m2 22.79 Rp 613,400.00 Rp 13,979,386.00
. Pas. List plafond Kayu m 45.00 Rp 54,100.00 Rp 2,434,500.00
. Pas. List plafond Gypsum m 364.90 Rp 63,640.00 Rp 23,222,045.08
. Pas. List Kayu Profil Dinding m 200.00 Rp 85,000.00 Rp 17,000,000.00
. Pek. Rangka Atap Baja Ringan m2 338.57 Rp 373,987.68 Rp 126,621,007.19
. Pek. Lisplan Kayu Besi m 65.16 Rp 131,600.00 Rp 8,575,056.00
. Pek. Nok Atap m 43.00 Rp 336,600.00 Rp 14,473,800.00
. Pek. Pasangan Atap Spandek 0.35 mm m2 338.57 Rp 312,002.50 Rp 105,634,686.43
. Pek. Covering (ACP) m2 377.20 Rp 956,260.00 Rp 360,701,272.00

VII. PEKERJAAN MEKANIKAL DAN ELECRIKAL Rp 164,797,966.68


A. PEKERJAAN ELEKTRICAL Rp 116,505,450.00
. Pemasangan Meteran dan Penyambungan PLN Set 1.00 Rp 25,000,000.00 Rp 25,000,000.00
. Pekerjaan Panel Box Set 1.00 Rp 12,500,000.00 Rp 12,500,000.00
. Pekerjaan Instalasi Titik Lampu Ttk 38.00 Rp 856,150.00 Rp 32,533,700.00
. Pekerjaan Instalasi Stop Kontak Ttk 14.00 Rp 921,000.00 Rp 12,894,000.00
. Pekerjaan Instalasi Instalasi AC Ttk 9.00 Rp 2,119,750.00 Rp 19,077,750.00
. Pasangan Lampu Bared LED 22 Watt Set 6.00 Rp 450,000.00 Rp 2,700,000.00
. Pasangan Downlight 9 Watt Set 6.00 Rp 250,000.00 Rp 1,500,000.00
. Pasangan Downlight 18 Watt Set 26.00 Rp 150,000.00 Rp 3,900,000.00
. Pasangan Saklar Tunggal Set 10.00 Rp 90,000.00 Rp 900,000.00
. Pasangan Saklar Ganda Set 6.00 Rp 150,000.00 Rp 900,000.00
733291305.xlsx 3.REHAB KANTOR 136/191
(a) (b) (c) (d) (e)
. Pasangan Stop Kontak Set 23.00 Rp 200,000.00 Rp 4,600,000.00

B PEKERJAAN MEKANIKAL/PLUMBING DAN SANITASI Rp 48,292,516.68


PEK. INSTALASI PIPA AIR BERSIH/AIR KOTOR /AIR BEKAS Rp 20,227,566.68
. Pipa PVC AW Ø1,5 Inc m 30.00 Rp 35,331.88 Rp 1,059,956.25
. Pipa PVC AW Ø1 Inc m 20.00 Rp 36,985.00 Rp 739,700.00
. Pipa PVC AW Ø 3/4 Inc m 18.00 Rp 35,331.88 Rp 635,973.75
. Pipa PVC AW Ø4 Inc m 35.00 Rp 205,427.50 Rp 7,189,962.50
. Pipa PVC AW Ø3 Inc m 8.00 Rp 145,915.00 Rp 1,167,320.00
. Pipa PVC AW Ø2,5 Inc m 6.00 Rp 145,915.00 Rp 875,490.00
. Pek. Septiptank dan Peresapan Unit 1.00 Rp 8,559,164.18 Rp 8,559,164.18

PEKERJAAN SANITAIR Rp 28,064,950.00


. Closet duduk (lengkap) set 3.00 Rp 4,945,280.00 Rp 14,835,840.00
. Washtafel Dinding set 3.00 Rp 2,230,100.00 Rp 6,690,300.00
. Cermin Washtafel set 3.00 Rp 750,000.00 Rp 2,250,000.00
. Shower Spray set 3.00 Rp 150,000.00 Rp 450,000.00
. Soap Holder set 3.00 Rp 75,000.00 Rp 225,000.00
. Double Robe Hock set 3.00 Rp 80,000.00 Rp 240,000.00
. Kran dinding Bh 8.00 Rp 75,000.00 Rp 600,000.00
. Floor drain Bh 4.00 Rp 533,640.00 Rp 2,134,560.00
. Bak Cuci Piring Set 1.00 Rp 639,250.00 Rp 639,250.00

733291305.xlsx 3.REHAB KANTOR 137/191


(a) (b) (c) (d) (e)
VIII. PEKERJAAN PENGGANTUNG DAN PENGUNCI Rp 64,649,725.00
. Pek. Engsel Pintu Ps 21.00 Rp 219,625.00 Rp 4,612,125.00
. Pek. Engsel Jendela dan Ventilasi Ps 71.00 Rp 194,750.00 Rp 13,827,250.00
. Pek. Kunci Pintu Tnggal Set 4.00 Rp 581,100.00 Rp 2,324,400.00
. Pek. Kunci Pintu Doble Set 3.00 Rp 871,650.00 Rp 2,614,950.00
. Pek. Kunci Cylinder (KM/WC) Set 3.00 Rp 531,100.00 Rp 1,593,300.00
. Pek. Grendel Pintu Doble Set 3.00 Rp 406,300.00 Rp 1,218,900.00
. Pek. Grendel Pintu KM/WC Set 3.00 Rp 135,433.33 Rp 406,300.00
. Pek. Handel Pintu Doble Set 3.00 Rp 148,750.00 Rp 446,250.00
. Pek. Hak Angin Jendela dan Ventilasi Set 71.00 Rp 164,625.00 Rp 11,688,375.00
. Pek. Grendel Jendela Set 71.00 Rp 194,625.00 Rp 13,818,375.00
. Pek. Door Closer Set 7.00 Rp 1,348,750.00 Rp 9,441,250.00
. Pek. Door Stop Set 7.00 Rp 379,750.00 Rp 2,658,250.00

IX. PEKERJAAN PENGECATAN Rp 117,753,193.13


. Pek. Pengecatan Dinding Luar (Exterior) : Dinding, Kolom,
m2 471.08 Rp 70,564.00 Rp 33,241,571.38
Balok dan Lisplank
. Pek. Pengecatan Dinding Dalam (Interior) : Dinding, Kolom
m2 706.63 Rp 56,451.20 Rp 39,889,885.65
dan Balok
. Pek. Compound Plafon Gypsum m2 280.69 Rp 15,000.00 Rp 4,210,350.00
. Pek. Pengecatan Plafon Gypsum m2 280.69 Rp 49,657.68 Rp 13,938,414.20
. Pek. Pengecatan Plafon Triplex m2 6.46 Rp 56,451.20 Rp 364,674.75
. Pek. Cat Meni/Residu Ragka Plafond m2 29.25 Rp 19,800.00 Rp 579,150.00
. Pek. Cat Kayu : Kusen Pintu, Jendela dan List-List m2 34.19 Rp 68,316.60 Rp 2,335,848.40
. Pek. Cat Melamin Kayu : Daun Pintu dan Jendela m2 51.29 Rp 118,100.00 Rp 6,057,027.77
. Pek. Cat Vernish Kayu : Plafond Lumbersering m2 22.79 Rp 88,530.00 Rp 2,017,598.70
. Pek. Water Proving Plat talang beton (Coating) m2 114.98 Rp 131,489.58 Rp 15,118,672.29

X. PEKERJAAN AKHIR Rp 31,000,000.00


. Asbuilt Draing Ls 1.00 Rp 10,000,000.00 Rp 10,000,000.00
. Dokumentasi & Laporan Proyek Ls 1.00 Rp 6,000,000.00 Rp 6,000,000.00
. Demobilisasi Ls 1.00 Rp 10,000,000.00 Rp 10,000,000.00
. Pembersihan Akhir Ls 1.00 Rp 5,000,000.00 Rp 5,000,000.00

733291305.xlsx 3.REHAB KANTOR 138/191


REKAPITULASI TOTAL
RENCANA ANGGARAN BIAYA (RAB)
KEGIATAN : -
PEKERJAAN : REHABILITASI KANTOR CABANG
INSTANSI : PERUM BULOG CABANG TIMIKA
LOKASI : JL.YOS SUDARSO SP1 TIMIKA,KAB.MIMIKA
TAHUN : -

NO JENIS PEKERJAAN TOTAL KETERANGAN

a b c d

I. PEKERJAAN PERSIAPAN Rp 58,000,000.00

II. PEKERJAAN TANAH & PASIR Rp 121,248,796.00

III. PEKERJAAN BETON Rp 650,371,192.83

IV. PEKERJAAN BATU DAN FINISHING Rp 962,134,717.39

V. PEKERJAAN KUSEN, PINTU DAN JENDELA Rp 145,525,277.90

VI. PEKERJAAN ATAP, PLAFON DAN RAILING Rp 769,173,862.76

VII. PEKERJAAN MEKANIKAL DAN ELECRIKAL Rp 164,797,966.68

VIII. PEKERJAAN PENGGANTUNG DAN PENGUNCI Rp 64,649,725.00

IX. PEKERJAAN PENGECATAN Rp 117,753,193.13

X. PEKERJAAN AKHIR Rp 31,000,000.00

(a). TOTAL BIAYA FISIK, ……………………........................... Rp 3,084,654,731.68


(b). JASA KONSULTANSI (DESING/SUPERVISI), ............................................Rp 277,618,925.85
(c). TOTAL REAL COST, {(a) + (b)} …………………….......................... Rp 3,362,273,657.53
(d). PPN 11 %, {11% x '(c)}, .......................................................... Rp 369,850,102.33
(e). GRAND TOTAL, {'(c) + (d)}, ……………............................ Rp 3,732,123,759.86
(f). DIBULATKAN, ................................................................... Rp 3,732,124,000.00

TERBILANG : Tiga Milyar Tujuh Ratus Tiga Puluh Dua Juta Seratus Dua Puluh Empat Ribu Rupiah

Timika, Maret 2024


Hormat Kami,
Kepala Cabang Bulog Timika

RIYADI MUSLIM
--------------------------------

Page 139
RENCANA ANGGARAN BIAYA (RAB)
KEGIATAN :
PEKERJAAN : REHABILITASI RUMAH JABATAN KEPALA CABANG
INSTANSI PERUM BULOG CABANG TIMIKA
LOKASI : JL.YOS SUDARSO SP1 TIMIKA,KAB.MIMIKA
TAHUN :
HARGA SATUAN
NO URAIAN JENIS PEKERJAAN SAT VOLUME JUMLAH
(Rp)

(a) (b) (c) (d) (e)

I. PEKERJAAN PERSIAPAN Rp 23,500,000.00


. Pembongkaran bangunan lama dan pembersihan Ls 1.00 Rp 5,000,000.00 Rp 5,000,000.00
. Mobilisasi Ls 2.00 Rp 3,000,000.00 Rp 6,000,000.00
. Managemen K3 Ls 1.00 Rp 7,500,000.00 Rp 7,500,000.00
. Shop Drowing Ls 1.00 Rp 5,000,000.00 Rp 5,000,000.00

II. PEKERJAAN TANAH & PASIR Rp 39,852,042.74


. Pengukuran dan Pemasangan Bouwplank m 73.47 Rp 139,350.00 Rp 10,237,580.00
. Galian Tanah Pondasi Bt,Kali m3 39.67 Rp 142,500.00 Rp 5,653,260.00
. Urugan Tanah kembali m3 13.22 Rp 40,260.00 Rp 532,398.24
. Urugan Pasir dibawah Pondasi m3 5.51 Rp 369,000.00 Rp 2,033,190.00
. Urugan Pasir dibawah Lantai m3 9.76 Rp 369,000.00 Rp 3,602,547.00
. Urugan Sirtu dibawah Lantai m3 48.82 Rp 364,500.00 Rp 17,793,067.50

III. PEKERJAAN BETON Rp 103,025,938.92


. Beton Rabat Lantai m3 6.83 Rp 1,540,300.00 Rp 10,526,564.23
. Beton Slof 15x25 Cm 2.76 Rp 10,586,790.00 Rp 29,166,606.45
. Beton Kolom Enterance (K-2) 30X30 Cm m3 0.72 Rp 16,754,200.00 Rp 12,063,024.00
. Balok Atap Enterance 20x35 m3 0.49 Rp 12,362,300.00 Rp 6,057,527.00
. Beton Plat atap Enterance m3 1.16 Rp 11,055,900.00 Rp 12,776,198.04
. Lispalan Beton m3 0.42 Rp 10,582,560.00 Rp 4,444,675.20
. Beton Kolom Ptaktis m 105.00 Rp 124,055.00 Rp 13,025,775.00
. Beton Ring Balk Ptaktis m 74.40 Rp 178,860.00 Rp 13,307,184.00
. Meja dapur m3 0.15 Rp 11,055,900.00 Rp 1,658,385.00

IV. PEKERJAAN BATU DAN FINISHING Rp 331,049,642.75


. Pas. Batu Kosong m3 14.70 Rp 1,616,040.00 Rp 23,749,323.84
. Pas. Pondasi atu Kali m3 23.38 Rp 2,295,700.00 Rp 53,661,987.50
. Pas. Pondasi Rolak m2 8.00 Rp 434,235.00 Rp 3,473,880.00
. Pas.Dinding Batu Tela 1:3 m2 36.07 Rp 434,235.00 Rp 15,662,856.45
. Pas.Dinding Batu Tela 1:4 m2 163.79 Rp 418,955.00 Rp 68,620,639.45
. Plesteran Dinding 1:4 m2 284.99 Rp 124,440.00 Rp 35,464,728.02
. Plesteran Dinding 1:3 m2 72.14 Rp 127,920.00 Rp 9,228,148.80
. Plesteran Beton 1:2 m2 10.00 Rp 132,960.00 Rp 1,329,600.00
. Acian Total m2 367.13 Rp 74,925.00 Rp 27,507,559.91
. Pas. Lantai Keramik 60x60 m2 77.09 Rp 654,875.00 Rp 50,484,313.75
. Pas. Keramik Trap Tangga 60x60 m2 2.67 Rp 785,850.00 Rp 2,098,219.50
. Pas. Lantai keramik Teras m2 15.18 Rp 654,875.00 Rp 9,941,002.50
. Pas. Lantai Keramik Kamar Mandi m2 5.36 Rp 504,500.00 Rp 2,704,120.00
. Pas. Dinding Keramik Kamar Mandi m2 24.90 Rp 606,730.00 Rp 15,105,756.81
. Pas. Brder Keramik Kamar Mandi m 11.58 Rp 47,909.00 Rp 554,786.22
. Pas. Plin Keramik m 92.00 Rp 72,910.00 Rp 6,707,720.00
. Pas.dinding batu alam m2 4.90 Rp 350,000.00 Rp 1,715,000.00

733291305.xlsx 4.REHAB rujab 140/191


(a) (b) (c) (d) (e)
. Pas. Loster/batu angin m2 2.16 Rp 250,000.00 Rp 540,000.00
. Pekerjaan Ornamen Kolom dan Profil-Profil Ls 1.00 Rp 2,500,000.00 Rp 2,500,000.00

V. PEKERJAAN KUSEN, PINTU DAN JENDELA Rp 58,961,358.60


. Pek. Kusen Pintu m3 0.20 Rp 12,703,000.00 Rp 2,540,600.00
. Pek. Kusen Jendela dan Ventilasi m3 0.30 Rp 12,703,000.00 Rp 3,810,900.00
. Pek. Daun Pintu Panil m2 8.65 Rp 1,229,000.00 Rp 10,632,079.00
. Pek. Daun Pintu Kamar Mandi m2 3.04 Rp 1,229,000.00 Rp 3,734,193.60
. Pek. Daun Jendela Kaca Buka m2 30.24 Rp 1,223,200.00 Rp 36,989,568.00
. Pek. Daun Ventilasi Kaca Buka m2 0.84 Rp 1,223,200.00 Rp 1,027,488.00
. Pek. Ventilasi Angin2 m2 0.72 Rp 314,625.00 Rp 226,530.00

733291305.xlsx 4.REHAB rujab 141/191


(a) (b) (c) (d) (e)
VI. PEKERJAAN ATAP, PLAFON Rp 153,709,246.64
. Pas. Rangka Plafond Kayu Kelas 2 m2 118.76 Rp 192,800.00 Rp 22,896,928.00
. Pas. Plafond Triplex 6mm m2 118.76 Rp 86,416.00 Rp 10,262,764.16
. Pas. Plafon Kayu Lumberserng m2 8.98 Rp 613,400.00 Rp 5,508,332.00
. Pas. List plafond Kayu m 206.48 Rp 54,100.00 Rp 11,170,568.00
. Pek. Rangka Atap Baja Ringan m2 167.61 Rp 373,987.68 Rp 62,684,074.24
. Pek. Lisplan Kayu Besi m 68.25 Rp 131,600.00 Rp 8,981,700.00
. Pek. Nok Atap m 27.19 Rp 336,600.00 Rp 9,152,154.00
. Pek. Talang Atap m 16.57 Rp 271,674.80 Rp 4,501,651.44
. Pek. Pasangan Atap Seng Gelombang m2 167.61 Rp 110,680.00 Rp 18,551,074.80

VII. PEKERJAAN MEKANIKAL DAN ELECRIKAL Rp 73,932,084.18


A. PEKERJAAN ELEKTRICAL Rp 47,511,000.00
. Pemasangan Meteran dan Penyambungan PLN Set 1.00 Rp 12,500,000.00 Rp 12,500,000.00
. Pekerjaan Panel Box Set 1.00 Rp 3,500,000.00 Rp 3,500,000.00
. Pekerjaan Instalasi Titik Lampu Ttk 20.00 Rp 856,150.00 Rp 17,123,000.00
. Pekerjaan Instalasi Stop Kontak Ttk 8.00 Rp 921,000.00 Rp 7,368,000.00
. Pasangan Downlight 9 Watt Set 16.00 Rp 250,000.00 Rp 4,000,000.00
. Pasangan Downlight 18 Watt Set 4.00 Rp 150,000.00 Rp 600,000.00
. Pasangan Saklar Tunggal Set 8.00 Rp 90,000.00 Rp 720,000.00
. Pasangan Saklar Ganda Set 2.00 Rp 150,000.00 Rp 300,000.00
. Pasangan Stop Kontak Set 7.00 Rp 200,000.00 Rp 1,400,000.00

B PEKERJAAN MEKANIKAL/PLUMBING DAN SANITASI Rp 26,421,084.18


PEK. INSTALASI PIPA AIR BERSIH/AIR KOTOR /AIR BEKAS Rp 13,913,994.18
. Pipa PVC AW Ø1,5 Inc m 20.00 Rp 35,331.88 Rp 706,637.50
. Pipa PVC AW Ø1 Inc m 16.00 Rp 36,985.00 Rp 591,760.00
. Pipa PVC AW Ø 3/4 Inc m 12.00 Rp 35,331.88 Rp 423,982.50
. Pipa PVC AW Ø4 Inc m 12.00 Rp 205,427.50 Rp 2,465,130.00
. Pipa PVC AW Ø3 Inc m 4.00 Rp 145,915.00 Rp 583,660.00
. Pipa PVC AW Ø2,5 Inc m 4.00 Rp 145,915.00 Rp 583,660.00
. Pek. Septiptank dan Peresapan Unit 1.00 Rp 8,559,164.18 Rp 8,559,164.18

PEKERJAAN SANITAIR Rp 12,507,090.00


. Closet duduk (lengkap) set 2.00 Rp 4,945,280.00 Rp 9,890,560.00
. Shower Spray set 2.00 Rp 150,000.00 Rp 300,000.00
. Soap Holder set 2.00 Rp 75,000.00 Rp 150,000.00
. Double Robe Hock set 2.00 Rp 80,000.00 Rp 160,000.00
. Kran dinding Bh 4.00 Rp 75,000.00 Rp 300,000.00
. Floor drain Bh 2.00 Rp 533,640.00 Rp 1,067,280.00
. Bak Cuci Piring Set 1.00 Rp 639,250.00 Rp 639,250.00

VIII. PEKERJAAN PENGGANTUNG DAN PENGUNCI Rp 14,657,166.67


. Pek. Engsel Pintu Ps 12.00 Rp 219,625.00 Rp 2,635,500.00
. Pek. Engsel Jendela dan Ventilasi Ps 13.00 Rp 194,750.00 Rp 2,531,750.00
. Pek. Kunci Pintu Tnggal Set 6.00 Rp 581,100.00 Rp 3,486,600.00
. Pek. Kunci Cylinder (KM/WC) Set 2.00 Rp 531,100.00 Rp 1,062,200.00
. Pek. Grendel Pintu KM/WC Set 2.00 Rp 135,433.33 Rp 270,866.67
. Pek. Hak Angin Jendela dan Ventilasi Set 13.00 Rp 164,625.00 Rp 2,140,125.00
. Pek. Grendel Jendela Set 13.00 Rp 194,625.00 Rp 2,530,125.00

IX. PEKERJAAN PENGECATAN Rp 35,619,347.46

733291305.xlsx 4.REHAB rujab 142/191


(a) (b) (c) (d) (e)
. Pek. Pengecatan Dinding Luar (Exterior) : Dinding, Kolom, Balok dan m2 146.85 Rp 70,564.00 Rp 10,362,594.37
Lisplank
. Pek. Pengecatan Dinding Dalam (Interior) : Dinding, Kolom dan Balok m2 220.28 Rp 56,451.20 Rp 12,435,113.24
. Pek. Pengecatan Plafon Triplex m2 118.76 Rp 56,451.20 Rp 6,704,144.51
. Pek. Cat Meni/Residu Ragka Plafond m2 118.76 Rp 19,800.00 Rp 2,351,448.00
. Pek. Cat Kayu : Kusen Pintu, Jendela dan List-List m2 17.40 Rp 68,316.60 Rp 1,188,419.18
. Pek. Cat Kayu : Daun Pintu dan Jendela m2 26.09 Rp 68,316.60 Rp 1,782,628.77
. Pek. Cat Vernish Kayu : Plafond Lumbersering m2 8.98 Rp 88,530.00 Rp 794,999.40

X. PEKERJAAN AKHIR Rp 14,000,000.00


. Asbuilt Draing Ls 1.00 Rp 5,000,000.00 Rp 5,000,000.00
. Dokumentasi & Laporan Proyek Ls 1.00 Rp 2,000,000.00 Rp 2,000,000.00
. Demobilisasi Ls 1.00 Rp 5,000,000.00 Rp 5,000,000.00
. Pembersihan Akhir Ls 1.00 Rp 2,000,000.00 Rp 2,000,000.00

733291305.xlsx 4.REHAB rujab 143/191


REKAPITULASI TOTAL
RENCANA ANGGARAN BIAYA (RAB)
KEGIATAN : -
PEKERJAAN : REHABILITASI RUMAH JABATAN KEPALA CABANG
INSTANSI : PERUM BULOG CABANG TIMIKA
LOKASI : JL.YOS SUDARSO SP1 TIMIKA,KAB.MIMIKA
TAHUN : -

NO JENIS PEKERJAAN TOTAL KETERANGAN

a b c d

I. PEKERJAAN PERSIAPAN Rp 23,500,000.00

II. PEKERJAAN TANAH & PASIR Rp 39,852,042.74

III. PEKERJAAN BETON Rp 103,025,938.92

IV. PEKERJAAN BATU DAN FINISHING Rp 331,049,642.75

V. PEKERJAAN KUSEN, PINTU DAN JENDELA Rp 58,961,358.60

VI. PEKERJAAN ATAP, PLAFON Rp 153,709,246.64

VII. PEKERJAAN MEKANIKAL DAN ELECRIKAL Rp 73,932,084.18

VIII. PEKERJAAN PENGGANTUNG DAN PENGUNCI Rp 14,657,166.67

IX. PEKERJAAN PENGECATAN Rp 35,619,347.46

X. PEKERJAAN AKHIR Rp 14,000,000.00

(a). TOTAL BIAYA FISIK, ……………………........................... Rp 848,306,827.95


(b). JASA KONSULTANSI (DESING/SUPERVISI), ............................................Rp 76,347,614.52
(c). TOTAL REAL COST, {(a) + (b)} …………………….......................... Rp 924,654,442.47
(d). PPN , {11% x '(c)}, .......................................................... Rp 101,711,988.67
(e). GRAND TOTAL, {'(c) + (d)}, ……………............................ Rp 1,026,366,431.14
(f). DIBULATKAN, ................................................................... Rp 1,026,367,000.00

TERBILANG : Satu Milyar Dua Puluh Enam Juta Tiga Ratus Enam Puluh Tujuh Ribu Rupiah

Timika, Maret 2024


Hormat Kami,
Kepala Cabang Bulog Timika

RIYADI MUSLIM
--------------------------------

Page 144
RENCANA ANGGARAN BIAYA (RAB)
KEGIATAN :
PEKERJAAN : REHABILITASI RUMAH ASISTEN MANAGER (5 Unit)
INSTANSI PERUM BULOG CABANG TIMIKA
LOKASI : JL.YOS SUDARSO SP1 TIMIKA,KAB.MIMIKA
TAHUN : 2024

SAT HARGA SATUAN


NO URAIAN JENIS PEKERJAAN VOLUME JUMLAH
(Rp)

(a) (b) (c)

I. PEKERJAAN PERSIAPAN Rp 64,091,000.00


. Pembongkaran bangunan lama dan pembersihan Ls 1.00 Rp 13,636,000.00 Rp 13,636,000.00
. Mobilisasi Ls 2.00 Rp 8,182,000.00 Rp 16,364,000.00
. Managemen K3 Ls 1.00 Rp 20,455,000.00 Rp 20,455,000.00
. Shop Drowing Ls 1.00 Rp 13,636,000.00 Rp 13,636,000.00

II. PEKERJAAN TANAH & PASIR Rp 100,485,660.00


. Pengukuran dan Pemasangan Bouwplank m 140.00 Rp 139,350.00 Rp 19,509,000.00
. Galian Tanah Pondasi Bt,Kali m3 123.00 Rp 142,500.00 Rp 17,527,500.00
. Urugan Tanah kembali m3 41.00 Rp 40,260.00 Rp 1,650,660.00
. Urugan Pasir dibawah Pondasi m3 19.00 Rp 369,000.00 Rp 7,011,000.00
. Urugan Pasir dibawah Lantai m3 25.00 Rp 369,000.00 Rp 9,225,000.00
. Urugan Sirtu dibawah Lantai m3 125.00 Rp 364,500.00 Rp 45,562,500.00

III. PEKERJAAN BETON Rp 266,047,880.00


. Beton Rabat Lantai m3 17.00 Rp 1,540,300.00 Rp 26,185,100.00
. Beton Slof 15x20 m3 6.00 Rp 11,055,900.00 Rp 66,335,400.00
. Plat Kanopi m3 5.00 Rp 11,055,900.00 Rp 55,279,500.00
. Beton Kolom Ptaktis m 420.00 Rp 124,055.00 Rp 52,103,100.00
. Beton Ring Balk Ptaktis m 308.00 Rp 178,860.00 Rp 55,088,880.00
. Meja dapur m3 1.00 Rp 11,055,900.00 Rp 11,055,900.00

IV. PEKERJAAN BATU DAN FINISHING Rp 1,114,584,595.00


. Pas. Batu Kosong m3 48.00 Rp 1,616,040.00 Rp 77,569,920.00
. Pas. Pondasi atu Kali m3 79.00 Rp 2,295,700.00 Rp 181,360,300.00
. Pas. Pondasi Rolak m2 22.00 Rp 434,235.00 Rp 9,553,170.00
. Pas.Dinding Batu Tela 1:3 m2 153.00 Rp 434,235.00 Rp 66,437,955.00
. Pas.Dinding Batu Tela 1:4 m2 541.00 Rp 418,955.00 Rp 226,654,655.00
. Plesteran Dinding 1:4 m2 941.00 Rp 124,440.00 Rp 117,098,040.00
. Plesteran Dinding 1:3 m2 246.00 Rp 127,920.00 Rp 31,468,320.00
. Plesteran Beton 1:2 m2 33.00 Rp 132,960.00 Rp 4,387,680.00
. Acian Total m2 1,220.00 Rp 74,925.00 Rp 91,408,500.00
. Pas. Lantai Keramik 60x60 m2 179.00 Rp 654,875.00 Rp 117,222,625.00
. Pas. Keramik Trap Tangga 60x60 m2 12.00 Rp 785,850.00 Rp 9,430,200.00
. Pas. Lantai keramik Teras m2 49.00 Rp 654,875.00 Rp 32,088,875.00
. Pas. Lantai Keramik Kamar Mandi m2 21.00 Rp 504,500.00 Rp 10,594,500.00
. Pas. Dinding Keramik Kamar Mandi m2 118.00 Rp 606,730.00 Rp 71,594,140.00
. Pas. Brder Keramik Kamar Mandi m 55.00 Rp 47,909.00 Rp 2,634,995.00
. Pas. Plin Keramik m 392.00 Rp 72,910.00 Rp 28,580,720.00
. Pekerjaan Ornamen Kolom dan Profil-Profil Ls 14.00 Rp 2,500,000.00 Rp 35,000,000.00

733291305.xlsx 5.REHAB RUASSMAN 145/191


(a) (b) (c)

V. PEKERJAAN KUSEN, PINTU DAN JENDELA Rp 146,338,050.00


. Pek. Kusen Pintu m3 1.00 Rp 12,703,000.00 Rp 12,703,000.00
. Pek. Kusen Jendela dan Ventilasi m3 1.00 Rp 12,703,000.00 Rp 12,703,000.00
. Pek. Daun Pintu Panil m2 57.00 Rp 1,229,000.00 Rp 70,053,000.00
. Pek. Daun Pintu Kamar Mandi m2 17.00 Rp 1,229,000.00 Rp 20,893,000.00
. Pek. Daun Jendela Kaca Buka m2 19.00 Rp 1,223,200.00 Rp 23,240,800.00
. Pek. Daun Ventilasi Kaca Buka m2 5.00 Rp 1,223,200.00 Rp 6,116,000.00
. Pek. Ventilasi Angin2 m2 2.00 Rp 314,625.00 Rp 629,250.00

VI. PEKERJAAN ATAP, PLAFON Rp 284,962,350.22


. Pas. Rangka Plafond Kayu Kelas 2 m2 236.00 Rp 192,800.00 Rp 45,500,800.00
. Pas. Plafond Triplex 6mm m2 236.00 Rp 86,416.00 Rp 20,394,176.00
. Pas. List plafond Kayu m 491.00 Rp 54,100.00 Rp 26,563,100.00
. Pek. Rangka Atap Baja Ringan m2 338.00 Rp 373,987.68 Rp 126,407,834.22
. Pek. Lisplan Kayu Besi m 108.00 Rp 131,600.00 Rp 14,212,800.00
. Pek. Nok Atap m 43.00 Rp 336,600.00 Rp 14,473,800.00
. Pek. Pasangan Atap Seng Gelombang m2 338.00 Rp 110,680.00 Rp 37,409,840.00

VII. PEKERJAAN MEKANIKAL DAN ELECRIKAL Rp 205,445,180.89


A. PEKERJAAN ELEKTRICAL Rp 85,439,500.00
. Pemasangan Meteran dan Penyambungan PLN Set 5.00 Rp 5,000,000.00 Rp 25,000,000.00
. Pekerjaan Panel Box Set 5.00 Rp 1,500,000.00 Rp 7,500,000.00
. Pekerjaan Instalasi Titik Lampu Ttk 30.00 Rp 856,150.00 Rp 25,684,500.00
. Pekerjaan Instalasi Stop Kontak Ttk 15.00 Rp 921,000.00 Rp 13,815,000.00
. Pasangan Downlight 9 Watt Set 30.00 Rp 250,000.00 Rp 7,500,000.00
. Pasangan Saklar Tunggal Set 16.00 Rp 90,000.00 Rp 1,440,000.00
. Pasangan Saklar Ganda Set 10.00 Rp 150,000.00 Rp 1,500,000.00
. Pasangan Stop Kontak Set 15.00 Rp 200,000.00 Rp 3,000,000.00

B PEKERJAAN MEKANIKAL/PLUMBING DAN SANITASI Rp 120,005,680.89


PEK. INSTALASI PIPA AIR BERSIH/AIR KOTOR /AIR BEKAS Rp 88,170,680.89
. Pipa PVC AW Ø1,5 Inc m 87.00 Rp 35,331.88 Rp 3,073,873.13
. Pipa PVC AW Ø1 Inc m 87.00 Rp 36,985.00 Rp 3,217,695.00
. Pipa PVC AW Ø 3/4 Inc m 109.00 Rp 35,331.88 Rp 3,851,174.38
. Pipa PVC AW Ø4 Inc m 109.00 Rp 205,427.50 Rp 22,391,597.50
. Pipa PVC AW Ø3 Inc m 44.00 Rp 145,915.00 Rp 6,420,260.00
. Pipa PVC AW Ø2,5 Inc m 44.00 Rp 145,915.00 Rp 6,420,260.00
. Pek. Septiptank dan Peresapan Unit 5.00 Rp 8,559,164.18 Rp 42,795,820.89

PEKERJAAN SANITAIR Rp 31,835,000.00


. Closet Jongkok Bh 5.00 Rp 2,841,000.00 Rp 14,205,000.00
. Kran dinding Bh 8.00 Rp 205,000.00 Rp 1,640,000.00
. Floor drain Bh 5.00 Rp 1,455,000.00 Rp 7,275,000.00
. Bak Cuci Piring Set 5.00 Rp 1,743,000.00 Rp 8,715,000.00

VIII. PEKERJAAN PENGGANTUNG DAN PENGUNCI Rp 49,457,791.67


. Pek. Engsel Pintu Ps 49.00 Rp 219,625.00 Rp 10,761,625.00
. Pek. Engsel Jendela dan Ventilasi Ps 22.00 Rp 194,750.00 Rp 4,284,500.00

733291305.xlsx 5.REHAB RUASSMAN 146/191


(a) (b) (c)
. Pek. Kunci Pintu Tnggal Set 33.00 Rp 581,100.00 Rp 19,176,300.00
. Pek. Kunci Cylinder (KM/WC) Set 11.00 Rp 531,100.00 Rp 5,842,100.00
. Pek. Grendel Pintu KM/WC Set 11.00 Rp 135,433.33 Rp 1,489,766.67
. Pek. Hak Angin Jendela dan Ventilasi Set 22.00 Rp 164,625.00 Rp 3,621,750.00
. Pek. Grendel Jendela Set 22.00 Rp 194,625.00 Rp 4,281,750.00
Rp -
IX. PEKERJAAN PENGECATAN Rp 100,447,820.40
. Pek. Pengecatan Dinding Luar (Exterior) : Dinding, Kolom,
m2 488.00 Rp 70,564.00 Rp 34,435,232.00
Balok dan Lisplank
. Pek. Pengecatan Dinding Dalam (Interior) : Dinding, Kolom
m2 732.00 Rp 56,451.20 Rp 41,322,278.40
dan Balok
. Pek. Pengecatan Plafon Triplex m2 236.00 Rp 56,451.20 Rp 13,322,483.20
. Pek. Cat Meni/Residu Ragka Plafond m2 236.00 Rp 19,800.00 Rp 4,672,800.00
. Pek. Cat Kayu : Kusen Pintu, Jendela dan List-List m2 39.00 Rp 68,316.60 Rp 2,664,347.40
. Pek. Cat Kayu : Daun Pintu dan Jendela m2 59.00 Rp 68,316.60 Rp 4,030,679.40
. Pek. Cat Vernish Kayu : Plafond Lumbersering m2
. Pek. Water Proving Plat talang beton (Coating) m2

X. PEKERJAAN AKHIR Rp 14,510,000.00


. Asbuilt Draing Ls 1.00 Rp 5,182,000.00 Rp 5,182,000.00
. Dokumentasi & Laporan Proyek Ls 1.00 Rp 2,073,000.00 Rp 2,073,000.00
. Demobilisasi Ls 1.00 Rp 5,182,000.00 Rp 5,182,000.00
. Pembersihan Akhir Ls 1.00 Rp 2,073,000.00 Rp 2,073,000.00

733291305.xlsx 5.REHAB RUASSMAN 147/191


REKAPITULASI TOTAL
RENCANA ANGGARAN BIAYA (RAB)
KEGIATAN : -
PEKERJAAN : REHABILITASI RUMAH ASISTEN MANAGER (5 Unit)
INSTANSI : PERUM BULOG CABANG TIMIKA
LOKASI : JL.YOS SUDARSO SP1 TIMIKA,KAB.MIMIKA
TAHUN : 2024

NO JENIS PEKERJAAN TOTAL KETERANGAN

a b c d

I. PEKERJAAN PERSIAPAN Rp 64,091,000.00

II. PEKERJAAN TANAH & PASIR Rp 100,485,660.00

III. PEKERJAAN BETON Rp 266,047,880.00

IV. PEKERJAAN BATU DAN FINISHING Rp 1,114,584,595.00

V. PEKERJAAN KUSEN, PINTU DAN JENDELA Rp 146,338,050.00

VI. PEKERJAAN ATAP, PLAFON Rp 284,962,350.22

VII. PEKERJAAN MEKANIKAL DAN ELECRIKAL Rp 205,445,180.89

VIII. PEKERJAAN PENGGANTUNG DAN PENGUNCI Rp 49,457,791.67

IX. PEKERJAAN PENGECATAN Rp 100,447,820.40

X. PEKERJAAN AKHIR Rp 14,510,000.00

(a). TOTAL BIAYA FISIK, ……………………........................... Rp 2,346,370,328.17


(b). JASA KONSULTANSI (DESING/SUPERVISI), ............................................ Rp 234,637,032.82
(c). TOTAL REAL COST, {(a) + (b)} …………………….......................... Rp 2,581,007,360.99
(d). PPN 11 %, {11% x '(c)}, .......................................................... Rp 283,910,809.71
(e). GRAND TOTAL, {'(c) + (d)}, ……………............................ Rp 2,864,918,170.70
(f). DIBULATKAN, ................................................................... Rp 2,864,919,000.00

TERBILANG :
Satu Milyar Delapan Ratus Enam Puluh Dua Juta Sembilan Ratus Sembilan Belas Ribu Dua
Ratus Rupiah

Timika, Maret 2024


Hormat Kami,
Kepala Cabang Bulog Timika

733291305.xlsx 5.1.REKAP REHAB RUASSMAN 148/191


RIYADI MUSLIM
--------------------------------

733291305.xlsx 5.1.REKAP REHAB RUASSMAN 149/191


RENCANA ANGGARAN BIAYA (RAB)
KEGIATAN :
PEKERJAAN : REHAB GUDANG BAHAN ( PQC ) 463,949,146.14
INSTANSI PERUM BULOG CABANG TIMIKA
LOKASI : JL.YOS SUDARSO SP1 TIMIKA,KAB.MIMIKA
TAHUN :
HARGA SATUAN
NO URAIAN JENIS PEKERJAAN SAT VOLUME JUMLAH
(Rp)

(a) (b) (c) (d) (e)

I. PEKERJAAN PERSIAPAN Rp 18,074,000.00


1 Pengukuran & Pas. Bouwplank M' 40.000 Rp 139,350 Rp 5,574,000.00
2 Pembuatan Papan Nama Proyek Bh 1.000 Rp 500,000 Rp 500,000.00
3 Direksi Keet dan Barak Kerja Ls 1.000 Rp 12,000,000 Rp 12,000,000.00

II. PEKERJAAN TANAH DAN PASIR Rp 22,159,098.00


1 Galian Tanah Untuk Pondasi M³ 25.650 Rp 142,500 Rp 3,655,125.00
2 Urugan Tanah Kembali M³ 8.550 Rp 40,260 Rp 344,223.00
3 Urugan Pasir dibawah Lantai & Pondasi M³ 5.750 Rp 369,000 Rp 2,121,750.00
4 Urugan Sirtu M³ 44.000 Rp 364,500 Rp 16,038,000.00

III. PEKERJAAN PONDASI DAN LANTAI Rp 101,260,816.00


1 Pasangan Batu Kosong ( Aanstamping ) M³ 5.400 Rp 1,616,040 Rp 8,726,616.00
2 Pas. Pondasi Batu Kali, Camp. 1 : 4 M³ 9.975 Rp 2,295,700 Rp 22,899,607.50
3 Cor Lantai, Camp. 1 : 2 : 3 M³ 5.400 Rp 1,540,300 Rp 8,317,620.00
4 Cor Lantai Rabat M³ 7.075 Rp 1,540,300 Rp 10,897,622.50
5 Pas. Lantai Keramik Tile 30 x 30 M² 54.000 Rp 497,294 Rp 26,853,876.00
6 Pas. Plin Keramik 30 x 10 M' 27.000 Rp 72,410 Rp 1,955,070.00
7 Pas. Saluran Buangan Air Hujan M' 36.000 Rp 600,289 Rp 21,610,404.00

IV. PEKERJAAN DINDING Rp 123,959,231.40


1 Cor Sloef Beton 20/25 M³ 1.500 Rp 10,586,790 Rp 15,880,185.00
2 Cor Tiang Kolom Teras 25/25 Cm M³ 2.188 Rp 16,754,200 Rp 36,649,812.50
3 Cor Ring Balk 10/15 M³ 0.900 Rp 12,362,300 Rp 11,126,070.00
4 Pas. Dinding Batu Tela, Camp. 1 : 4 M² 88.340 Rp 418,955 Rp 37,010,484.70
5 Plesteran, Camp. 1 : 4 M² 187.180 Rp 124,440 Rp 23,292,679.20

V. PEKERJAAN KUZEN, PINTU DAN JENDELA Rp 29,456,230.50


1 Pas. Kuzen Kayu Besi M³ 0.864 Rp 12,703,000 Rp 10,975,392.00
2 Pas. Jaluzi Papan M² 6.900 Rp 705,225 Rp 4,866,052.50
3 Pas. Daun Pintu Panel M² 6.480 Rp 1,229,000 Rp 7,963,920.00
4 Pas. Kaca Mati 5 mm M² 7.675 Rp 736,250 Rp 5,650,866.00

VI. PEKERJAAN KAP DAN PLAFOND Rp 108,357,582.00


1 Pas. Rangka Kuda-kuda Kayu Besi 5/10 M³ 2.340 Rp 14,487,300 Rp 33,900,282.00
2 Pas. Gording Kayu Besi 5/10 M³ 2.480 Rp 14,487,300 Rp 35,928,504.00
3 Pas. Atap Seng Gelombang BJLS. 0.30 M² 132.800 Rp 110,680 Rp 14,698,304.00
4 Pas. Nok Seng Plat BJLS. 0,30 M' 20.000 Rp 90,240 Rp 1,804,800.00
5 Pas. Listplank Papan Kayu Besi 2/25 M' 49.000 Rp 131,600 Rp 6,448,400.00
6 Pas. Plafond Plywood 6 mm M² 99.500 Rp 86,416 Rp 8,598,392.00
7 Pas. List Plafond 5 cm M' 129.000 Rp 54,100 Rp 6,978,900.00

VII.PEKERJAAN PENGGANTUNG DAN KUNCI Rp 5,944,950.00


1 Pas. Kunci Pintu 2 Slag Bh 1.000 871,650 Rp 871,650.00

733291305.xlsx 6.REHAB GUDANG PQC 150/191


(a) (b) (c) (d) (e)
2 Pas. Engsel Pintu Bh 12.000 Rp 219,625 Rp 2,635,500.00
3 Pas. Grendel Pintu Bh 6.000 Rp 406,300 Rp 2,437,800.00

VIII.PEKERJAAN PENGECETAN Rp 23,624,988.24


1 Cat Dinding M² 187.180 Rp 70,564 Rp 13,208,169.52
2 Cat Plafond M² 99.500 Rp 56,451 Rp 5,616,894.40
3 Cat Kilap Kuzen M² 28.800 Rp 68,317 Rp 1,967,518.08
4 Cat Kilap Pintu, Jendela dan Ventilasi M² 26.760 Rp 68,317 Rp 1,828,152.22
5 Cat Kilap Listplank M² 14.700 Rp 68,317 Rp 1,004,254.02

IX. PEKERJAAN INSTALASI LISTRIK Rp 27,612,250.00


1 Pas. Instalasi Kabel + Titik Mata Lampu Ttk 25.000 Rp 856,150 Rp 21,403,750.00
2 Pas. Lampu Pijar XL 15 w + Fitting Psg 15.000 Rp 185,700 Rp 2,785,500.00
3 Pas. Stop Kontak Bh 2.000 Rp 399,000 Rp 798,000.00
4 Pas. Saklar Ganda Bh 2.000 Rp 237,500 Rp 475,000.00
5 Pas. Limit 4 Amp. Bh 2.000 Rp 75,000 Rp 150,000.00
6 Pas. Box Panel Bh 1.000 Rp 500,000 Rp 500,000.00
7 Pas. Arde Bh 1.000 Rp 1,500,000 Rp 1,500,000.00

X. PEKERJAAN AKHIR Rp 3,500,000.00


1 Pembersihan Akhir Ls 1.000 Rp 1,000,000 Rp 1,000,000.00
2 Administrasi Ls 1.000 Rp 2,500,000 Rp 2,500,000.00

733291305.xlsx 6.REHAB GUDANG PQC 151/191


RENCANA ANGGARAN BIAYA (RAB)
KEGIATAN :
PEKERJAAN : REHAB GUDANG BAHAN ( PQC )
INSTANSI PERUM BULOG CABANG TIMIKA
LOKASI : JL.YOS SUDARSO SP1 TIMIKA,KAB.MIMIKA
TAHUN : 2024
HARGA SATUAN
NO URAIAN JENIS PEKERJAAN SAT VOLUME JUMLAH
(Rp)

(a) (b) (c) (d) (e)

I. PEKERJAAN PERSIAPAN Rp 39,500,000.00


. Mobilisasi Ls 1.000 Rp 5,000,000 Rp 5,000,000.00
. Pembuatan Direksi Keet, Gudang/barak Kerja m2 1.000 Rp 12,000,000 Rp 12,000,000.00
. Managemen K3 Ls 1.000 Rp 15,000,000 Rp 15,000,000.00
. Shop Drowing Ls 1.000 Rp 7,500,000 Rp 7,500,000.00

II. PEKERJAAN TANAH & PASIR Rp 55,902,510.30


. Pengukuran dan Pemasangan Bouwplank m 64.000 Rp 139,350 Rp 8,918,400.00
. Galian Tanah Pondasi Tapak m3 27.000 Rp 175,500 Rp 4,738,500.00
. Galian Tanah Pondasi Bt,Kali m3 51.840 Rp 142,500 Rp 7,387,200.00
. Urugan Tanah kembali m3 26.280 Rp 40,260 Rp 1,058,032.80
. Urugan Pasir dibawah Pondasi m3 7.830 Rp 369,000 Rp 2,889,270.00
. Urugan Pasir dibawah Lantai m3 14.105 Rp 369,000 Rp 5,204,745.00
. Urugan Sirtu dibawah Lantai m3 70.525 Rp 364,500 Rp 25,706,362.50

III. PEKERJAAN BETON Rp 174,383,029.16


. Beton Lantai Kerja 1:3:5 m3 0.675 Rp 1,540,300 Rp 1,039,702.50
. Beton Rabat Lantai m3 21.157 Rp 1,925,375 Rp 40,736,121.56
. Beton Pondasi Poot Plat m3 1.800 Rp 8,338,060 Rp 15,008,508.00
. Beton Slof 20x30 Cm m3 3.240 Rp 10,586,790 Rp 34,301,199.60
. Beton Kolom 20x20 Cm m3 2.880 Rp 16,754,200 Rp 48,252,096.00
. Beton Ring Balk 15x25 m3 2.025 Rp 12,362,300 Rp 25,033,657.50
. Beton Kolom Ptaktis m3 28.800 Rp 124,055 Rp 3,572,784.00
. Beton Ring Balk Ptaktis m3 36.000 Rp 178,860 Rp 6,438,960.00

IV. PEKERJAAN BATU DAN FINISHING Rp 247,594,673.30


. Pas. Batu Kosong m3 11.880 Rp 1,616,040 Rp 19,198,555.20
. Pas. Pondasi atu Kali m3 18.900 Rp 2,295,700 Rp 43,388,730.00
. Pas. Pondasi Rolak m2 29.808 Rp 434,235 Rp 12,943,676.88
. Pas.Dinding Batu Tela 1:4 m2 156.100 Rp 418,955 Rp 65,398,875.50
. Plesteran Dinding 1:4 m2 312.200 Rp 124,440 Rp 38,850,168.00
. Plesteran Dinding 1:3 m2 59.616 Rp 127,920 Rp 7,626,078.72
. Plesteran Beton 1:2 m2 155.520 132,960 Rp 20,677,939.20
. Acian Total m2 527.336 Rp 74,925 Rp 39,510,649.80

V. PEKERJAAN KUSEN, PINTU DAN JENDELA Rp 124,660,766.68


. Pek. Kusen Jendela dan Ventilasi m3 1.480 Rp 12,703,000 Rp 18,800,440.00
. Pek. Daun Pintu Besi m2 9.000 Rp 2,153,267 Rp 19,379,398.68
. Pek. Daun Ventilasi Kaca Buka m2 55.040 Rp 1,223,200 Rp 67,324,928.00
. Pek. Ventilasi Jalusi Atap m2 4.000 Rp 1,349,000 Rp 5,396,000.00
. Pas. Teralis Pengaman Jendela dan Ventilasi m2 55.040 Rp 250,000 Rp 13,760,000.00

VI. PEKERJAAN ATAP, PLAFON Rp 190,209,171.03

733291305.xlsx 6.REHAB GUDANG PQC (2) 152/191


(a) (b) (c) (d) (e)
. Pas. Rangka Plafond Kayu Kelas 2 m2 155.590 Rp 192,800 Rp 29,997,752.00
. Pas. Plafond Triplex 6mm m2 155.590 Rp 86,416 Rp 13,445,465.44
. Pas. List plafond Kayu m 177.410 Rp 54,100 Rp 9,597,881.00
. Pek. Rangka Atap Baja Ringan m2 186.000 Rp 373,988 Rp 69,561,707.59
. Pek. Lisplan Kayu Besi m 58.350 Rp 131,600 Rp 7,678,860.00
. Pek. Nok Atap m 21.000 Rp 90,240 Rp 1,895,040.00
. Pek. Pasangan Atap Spandek Zincalume m2 186.000 Rp 312,003 Rp 58,032,465.00

VII.PEKERJAAN MEKANIKAL DAN ELECRIKAL Rp 32,791,600.00


. Pekerjaan Panel Box Set 1.000 Rp 2,500,000 Rp 2,500,000.00
. Pekerjaan Instalasi Titik Lampu Ttk 24.000 Rp 856,150 Rp 20,547,600.00
. Pekerjaan Instalasi Stop Kontak Ttk 4.000 Rp 921,000 Rp 3,684,000.00
. Pasangan Downlight 9 Watt Set 10.000 Rp 250,000 Rp 2,500,000.00
. Pasangan Downlight 18 Watt Set 14.000 Rp 150,000 Rp 2,100,000.00
. Pasangan Saklar Tunggal Set 4.000 Rp 90,000 Rp 360,000.00
. Pasangan Saklar Ganda Set 2.000 Rp 150,000 Rp 300,000.00
. Pasangan Stop Kontak Set 4.000 Rp 200,000 Rp 800,000.00

VIII.PEKERJAAN PENGGANTUNG DAN PENGUNCI Rp 16,620,000.00


. Pek. Engsel Jendela dan Ventilasi Ps 30.000 Rp 194,750 Rp 5,842,500.00
. Pek. Hak Angin Jendela dan Ventilasi Set 30.000 Rp 164,625 Rp 4,938,750.00
. Pek. Grendel Jendela Set 30.000 Rp 194,625 Rp 5,838,750.00

IX. PEKERJAAN PENGECATAN Rp 57,306,863.51


. Pek. Pengecatan Dinding Luar (Exterior) : Dinding, Kolom, Balok m2 316.402 Rp 70,564 Rp 22,326,562.50
. Pek. Pengecatan Dinding Dalam (Interior) : Dinding, Kolom dan B m2 210.934 Rp 56,451 Rp 11,907,500.00
. Pek. Pengecatan Plafon Triplex m2 155.590 Rp 56,451 Rp 8,783,242.21
. Pek. Cat Meni/Residu Ragka Plafond m2 155.590 Rp 19,800 Rp 3,080,682.00
. Pek. Cat Kayu : Kusen Pintu, Jendela dan List-List m2 44.400 Rp 112,720 Rp 5,004,768.00
. Pek. Cat Kayu : Daun Pintu dan Jendela m2 55.040 Rp 112,720 Rp 6,204,108.80

X. PEKERJAAN AKHIR Rp 18,000,000.00


. Asbuilt Draing Ls 1.000 Rp 7,500,000 Rp 7,500,000.00
. Dokumentasi & Laporan Proyek Ls 1.000 Rp 2,500,000 Rp 2,500,000.00
. Demobilisasi Ls 1.000 Rp 5,000,000 Rp 5,000,000.00
. Pembersihan Akhir Ls 1.000 Rp 3,000,000 Rp 3,000,000.00

733291305.xlsx 6.REHAB GUDANG PQC (2) 153/191


REKAPITULASI TOTAL
RENCANA ANGGARAN BIAYA (RAB)
KEGIATAN : -
PEKERJAAN : REHAB GUDANG BAHAN ( PQC )
INSTANSI : PERUM BULOG CABANG TIMIKA
LOKASI : JL.YOS SUDARSO SP1 TIMIKA,KAB.MIMIKA
TAHUN : 2024

NO JENIS PEKERJAAN TOTAL KETERANGAN

a b c d

I. PEKERJAAN PERSIAPAN Rp 39,500,000.00

II. PEKERJAAN TANAH & PASIR Rp 55,902,510.30

III. PEKERJAAN BETON Rp 174,383,029.16

IV. PEKERJAAN BATU DAN FINISHING Rp 247,594,673.30

V. PEKERJAAN KUSEN, PINTU DAN JENDELA Rp 124,660,766.68

VI. PEKERJAAN ATAP, PLAFON Rp 190,209,171.03

VII. PEKERJAAN MEKANIKAL DAN ELECRIKAL Rp 32,791,600.00

VIII. PEKERJAAN PENGGANTUNG DAN PENGUNCI Rp 16,620,000.00

IX. PEKERJAAN PENGECATAN Rp 57,306,863.51

X. PEKERJAAN AKHIR Rp 18,000,000.00

(a). TOTAL BIAYA FISIK, ……………………........................... Rp 956,968,613.98


(b). JASA KONSULTANSI (D/S), ............................................... Rp 86,127,175.26
(c). TOTAL REAL COST, {(a) + (b)} …………………….......................... Rp 1,043,095,789.24
(d). PPN 11 %, {11% x '(c)}, .......................................................... Rp 114,740,536.82
(e). GRAND TOTAL, {'(c) + (d)}, ……………............................ Rp 1,157,836,326.06
(f). DIBULATKAN, ................................................................... Rp 1,157,837,000.00

TERBILANG : Satu Milyar Seratus Lima Puluh Tujuh Juta Delapan Ratus Tiga Puluh Tujuh Ribu Rupiah

Timika, Maret 2024


Hormat Kami,
Kepala Cabang Bulog Timika

RIYADI MUSLIM
--------------------------------

Page 154
RENCANA ANGGARAN BIAYA (RAB)
KEGIATAN :
PEKERJAAN : REHAB TOILET UMUM
INSTANSI PERUM BULOG CABANG TIMIKA
LOKASI : JL.YOS SUDARSO SP1 TIMIKA,KAB.MIMIKA
TAHUN : 2024
HARGA SATUAN
NO URAIAN JENIS PEKERJAAN SAT VOLUME JUMLAH
(Rp)

(a) (b) (c) (d) (e)

I. PEKERJAAN PERSIAPAN Rp 21,010,286.67


. Pembersihan Lokasi M² 108.00 Rp 20,975 Rp 2,265,300.00
. Pengukuran & Pas. Bouwplank M¹ 62.76 Rp 139,350 Rp 8,744,986.67
. Managemen K3 Ls 1.00 Rp 5,000,000 Rp 5,000,000.00
. Shop Drowing Ls 1.00 Rp 5,000,000 Rp 5,000,000.00

II. PEKERJAAN TANAH DAN PASIR Rp 17,423,709.63


. Galian Tanah Untuk Pondasi M³ 37.65 Rp 144,720 Rp 5,449,190.40
. Urugan Tanah Kembali M³ 12.55 Rp 40,260 Rp 505,307.73
. Urugan Pasir dibawah Pondasi & Lantai t=5cm M³ 9.15 Rp 369,000 Rp 3,375,489.00
. Urugan Peninggian Lantai M³ 22.21 Rp 364,500 Rp 8,093,722.50

III. PEKERJAAN PONDASI DAN LANTAI Rp 94,324,738.54


. Pasangan Batu Kosong ( Aanstamping ) M³ 9.41 Rp 1,616,040 Rp 15,212,323.20
. Pas. Pondasi Batu Kali ( Camp. 1 : 4 ) M³ 15.53 Rp 2,295,700 Rp 35,656,812.40
. Cor Sloof 15/20 M³ 1.41 Rp 10,586,790 Rp 14,948,547.48
. Cor Lantai dan Rabat M³ 4.44 Rp 1,540,300 Rp 6,840,472.30
. Pas. Kramik 30x30 cm M² 33.14 Rp 497,294 Rp 16,480,323.16
. Pas. Kramik 20x20 cm M² 10.28 Rp 504,500 Rp 5,186,260.00

IV. PEKERJAAN DINDING Rp 141,608,200.10


. Cor Tiang Kolom Praktis 11/11 M¹ 49.60 Rp 124,055 Rp 6,153,128.00
. Cor Ring Balk 10/15 M¹ 59.07 Rp 178,860 Rp 10,564,664.00
. Pas. Dinding Bataco M² 115.00 Rp 434,235 Rp 49,937,025.00
. Plasteran Transram M² 55.70 Rp 127,920 Rp 7,125,144.00
. Plasteran Non Transram M² 174.30 Rp 124,440 Rp 21,689,892.00
. Acian M² 174.30 Rp 74,925 Rp 13,059,427.50
. Pas. Dinding Kramik 20x25 cm M² 54.52 Rp 606,730 Rp 33,078,919.60

V. PEKERJAAN KUSEN, PINTU DAN JENDELA Rp 17,260,831.75


. Pek. Kusen Pintu dan Jendela M³ 0.21 Rp 16,695,000 Rp 3,443,343.75
. Pas. Daun Pintu Panel Kayu Besi M² 8.44 Rp 1,229,000 Rp 10,372,760.00
. Pas. Ventilasi Kayu Besi M² 2.24 Rp 1,223,200 Rp 2,739,968.00
. Pas. Kaca Mati M² 2.24 Rp 314,625 Rp 704,760.00

VI. PEK. KUDA-KUDA, ATAP DAN PLAFOND Rp 113,283,172.37


. Pek. Rangka Baja Ringan m2 164.00 Rp 373,988 Rp 61,333,978.73
. Pas. Atap Seng Gelombang BJLS. 0.30 M² 164.00 Rp 110,680 Rp 18,151,520.00
. Pas. Bubungan Seng Plat BJLS. 0.30 mm M¹ 17.50 Rp 90,240 Rp 1,579,200.00
. Pas. Jurai Dalam Seng Plat BJLS. 0.30 mm M¹ 4.30 Rp 271,675 Rp 1,168,201.64
. Pas. Listplank M¹ 39.00 Rp 130,600 Rp 5,093,400.00
. Pas. Plafond Plywood 4 mm + Rangka M² 67.00 Rp 279,216 Rp 18,707,472.00
. Pas. List Plafond M¹ 134.00 Rp 54,100 Rp 7,249,400.00

733291305.xlsx 7.REHAB TOILET UMUM 155/191


(a) (b) (c) (d) (e)

VII. PEK. KUNCI DAN PENGGANTUNG Rp 4,982,500.00


. Pas. Kunci Pintu Tanam Set 1.00 Rp 581,100 Rp 581,100.00
. Pas. Kunci Slinder ( KM/WC ) Set 4.00 Rp 531,100 Rp 2,124,400.00
. Pas. Engsel Pintu Bh 8.00 Rp 219,625 Rp 1,757,000.00
. Pas. Grendel Pintu Bh 4.00 Rp 130,000 Rp 520,000.00

VIII.PEK. PENGECATAN Rp 37,415,645.30


. Cat Dinding M² 344.00 Rp 70,564 Rp 24,274,298.26
. Cat Plafond M² 77.85 Rp 56,451 Rp 4,394,725.92
. Cat Kuzen dan Ventilasi M² 36.88 Rp 112,720 Rp 4,157,113.60
. Cat Daun Pintu M² 27.22 Rp 112,720 Rp 3,067,787.52
. Cat Listplank M² 13.50 Rp 112,720 Rp 1,521,720.00

IX. PEKERJAAN SANITAIR Rp 41,423,859.18


. Closet Jongkok Bh 4.00 Rp 1,041,600 Rp 4,166,400.00
. Wastafel Kramik Bh 2.00 Rp 2,230,100 Rp 4,460,200.00
. Bak Air Bh 4.00 Rp 2,689,500 Rp 10,758,000.00
. Floor Drain Bh 8.00 Rp 533,640 Rp 4,269,120.00
. Pas. Kran Air Bh 15.00 Rp 151,725 Rp 2,275,875.00
. Pipa PVC dia 4" M¹ 20.00 Rp 205,428 Rp 4,108,550.00
. Pipa PVC dia 3/4" M¹ 80.00 Rp 35,332 Rp 2,826,550.00
. Septictank + Peresapan Unit 1.00 Rp 8,559,164 Rp 8,559,164.18

X. PEKERJAAN INSTALASI LISTRIK Rp 23,733,300.00


. Pas. Instalasi Kabel + Titik Mata Lampu Titik 18.00 Rp 856,150 Rp 15,410,700.00
. Pekerjaan Instalasi Stop Kontak Ttk 2.00 Rp 921,000 Rp 1,842,000.00
. Pas. Lampu XL15 Watt + Fitting Bh 18.00 Rp 185,700 Rp 3,342,600.00
. Pas. Stop Kontak Bh 2.00 Rp 399,000 Rp 798,000.00
. Pas. Saklar Ganda Bh 2.00 Rp 237,500 Rp 475,000.00
. Pas. Saklar Tunggal Bh 6.00 Rp 227,500 Rp 1,365,000.00
. Pas. Box Panel + Limit Grub 1.00 Rp 500,000 Rp 500,000.00

XI. PEKERJAAN AKHIR Rp 3,500,000.00


. Pembersihan Akhir Ls 1.00 Rp 1,000,000 Rp 1,000,000.00
. Foto/Dokumentasi/Pelaporan Ls 1.00 Rp 2,500,000 Rp 2,500,000.00

733291305.xlsx 7.REHAB TOILET UMUM 156/191


REKAPITULASI TOTAL
RENCANA ANGGARAN BIAYA (RAB)
KEGIATAN : -
PEKERJAAN : REHAB TOILET UMUM
INSTANSI : PERUM BULOG CABANG TIMIKA
LOKASI : JL.YOS SUDARSO SP1 TIMIKA,KAB.MIMIKA
TAHUN : 2024

NO JENIS PEKERJAAN TOTAL KETERANGAN

a b c d

I. PEKERJAAN PERSIAPAN Rp 21,010,286.67

II. PEKERJAAN TANAH DAN PASIR Rp 17,423,709.63

III. PEKERJAAN PONDASI DAN LANTAI Rp 94,324,738.54

IV. PEKERJAAN DINDING Rp 141,608,200.10

V. PEKERJAAN KUSEN, PINTU DAN JENDELA Rp 17,260,831.75

VI. PEK. KUDA-KUDA, ATAP DAN PLAFOND Rp 113,283,172.37

VII. PEK. KUNCI DAN PENGGANTUNG Rp 4,982,500.00

VIII. PEK. PENGECATAN Rp 37,415,645.30

IX. PEKERJAAN SANITAIR Rp 41,423,859.18

X. PEKERJAAN INSTALASI LISTRIK Rp 23,733,300.00

XI. PEKERJAAN AKHIR Rp 3,500,000.00

(a). TOTAL BIAYA FISIK, ……………………........................... Rp 515,966,243.54


(b). JASA KONSULTANSI (D/S), ............................................... Rp 51,596,624.35
(c). TOTAL REAL COST, {(a) + (b)} …………………….......................... Rp 567,562,867.89
(d). PPN 11 %, {11% x '(c)}, .......................................................... Rp 62,431,915.47
(e). GRAND TOTAL, {'(c) + (d)}, ……………............................ Rp 629,994,783.36
(f). DIBULATKAN, ................................................................... Rp 629,995,000.00

TERBILANG : Enam Ratus Dua Puluh Sembilan Juta Sembilan Ratus Sembilan Puluh Lima Ribu Rupiah

Timika, Maret 2024


Hormat Kami,
Page 157
Kepala Cabang Bulog Timika

RIYADI MUSLIM
--------------------------------

Page 158
RENCANA ANGGARAN BIAYA (RAB)
KEGIATAN :
PEKERJAAN : PEMBANGUNAN POS SECURITY
INSTANSI PERUM BULOG CABANG TIMIKA
LOKASI : JL.YOS SUDARSO SP1 TIMIKA,KAB.MIMIKA
TAHUN :
HARGA SATUAN
NO URAIAN JENIS PEKERJAAN SAT VOLUME JUMLAH
(Rp)

(a) (b) (c) (d) (e)

I. PEKERJAAN TANAH DAN PASIR Rp 8,732,337.50


. Pas. Bouwplank M' 24.00 Rp 139,350.00 Rp 3,344,400.00
. Galian Tanah Untuk Pondasi M³ 10.00 Rp 144,720.00 Rp 1,447,200.00
. Urugan Tanah Kembali M³ 6.67 Rp 40,260.00 Rp 268,400.00
. Urugan Sirtu M³ 10.08 Rp 364,500.00 Rp 3,672,337.50

II. PEKERJAAN PONDASI DAN LANTAI Rp 42,233,150.70


. Pasangan Batu Kosong ( Aanstamping ) M³ 3.50 Rp 1,616,040.00 Rp 5,656,140.00
. Pas. Pondasi Batu Kali, Camp. 1 : 4 M³ 5.62 Rp 2,295,700.00 Rp 12,913,312.50
. Cor Lantai M³ 0.80 Rp 1,540,300.00 Rp 1,232,240.00
. Cor Rabat M³ 2.53 Rp 1,540,300.00 Rp 3,889,257.50
. Cor Meja Dapur M³ 0.05 Rp 11,055,900.00 Rp 530,683.20
. Pas. Lantai Keramik 30 x 30 cm M² 13.75 Rp 497,294.00 Rp 6,837,792.50
. Pas. Lantai Keramik 20 x 20 cm ( KM/WC) M² 2.25 Rp 504,500.00 Rp 1,135,125.00
. Pas. Saluran Buangan Air Hujan M' 24.00 Rp 418,275.00 Rp 10,038,600.00

III. PEKERJAAN DINDING Rp 66,010,627.53


. Cor Sloef Beton 15/25 M³ 0.94 Rp 10,586,790.00 Rp 9,925,115.63
. Cor Tiang Kolom 20/20 Cm M³ 0.29 Rp 16,754,200.00 Rp 4,825,209.60
. Cor Tiang Kolom Praktis 11/11 M' 24.00 Rp 124,055.00 Rp 2,977,320.00
. Cor Ring Balk dan Balok Latiau 10/15 M¹ 42.50 Rp 178,860.00 Rp 7,601,550.00
. Pas. Dinding Batu Tela, Camp. 1 : 4 M² 50.78 Rp 418,955.00 Rp 21,274,534.90
. Plesteran, Camp. 1 : 4 M² 110.61 Rp 124,440.00 Rp 13,764,308.40
. Pas. Dinding Keramik 20 x 25 cm (KM/WC, dapur) M² 9.30 Rp 606,730.00 Rp 5,642,589.00

IV. PEKERJAAN KUZEN, PINTU DAN JENDELA Rp 12,275,125.50


. Pas. Kuzen Kayu Klas I M³ 0.39 Rp 12,703,000.00 Rp 4,938,926.40
. Pas. Daun Pintu Panel Kayu Klas I M² 2.81 Rp 1,229,000.00 Rp 3,458,406.00
. Pas. Daun Jendela Kaca 5 mm Bingkai Kayu M² 1.49 Rp 1,223,200.00 Rp 1,820,121.60
. Pas. Kaca Mati 5 mm M² 2.79 Rp 736,250.00 Rp 2,057,671.50

V. PEKERJAAN ATAP DAN PLAFOND Rp 49,814,087.66


. Pas. Kuda-Kuda Kayu Klas I M³ 0.56 Rp 10,462,500.00 Rp 5,859,000.00
. Pas. Gording Kayu Klas I M³ 0.22 Rp 10,192,500.00 Rp 2,242,350.00
. Pas. Kaso + Ring Kayu Klas I M² 41.40 Rp 119,400.00 Rp 4,943,160.00
. Pas. Atap Metal Roof M² 41.40 Rp 243,375.00 Rp 10,075,725.00
. Pas. Nok Metal Roof M' 22.00 Rp 349,075.00 Rp 7,679,650.00
. Pas. Pipa buangan Air Hujan PVC Ø3" M' 4.00 Rp 106,907.50 Rp 427,630.00
. Pas. Listplank Kayu Klas I M' 23.00 Rp 145,875.00 Rp 3,355,125.00
. Pas. Plafond Plywood 6 mm M² 33.06 Rp 394,162.50 Rp 13,031,997.66
. Pas. List Plafond M' 66.00 Rp 33,325.00 Rp 2,199,450.00

VI. PEKERJAAN PENGGANTUNG DAN KUNCI Rp 2,359,312.50

733291305.xlsx 8.REHAB POSEC 159/191


(a) (b) (c) (d) (e)
. Pas. Kunci Pintu 2 Slag Bh 2.00 Rp 365,675.00 Rp 731,350.00
. Pas. Engsel Pintu Bh 6.00 Rp 104,656.25 Rp 627,937.50
. Pas. Engsel Jendela Bh 4.00 Rp 100,350.00 Rp 401,400.00
. Pas. Grendel Jendela Bh 2.00 Rp 130,000.00 Rp 260,000.00
. Pas. Hak Angin Bh 4.00 Rp 84,656.25 Rp 338,625.00

VII.PEKERJAAN PENGECETAN Rp 12,120,483.80


. Cat Dinding M² 110.61 Rp 65,622.50 Rp 7,258,504.73
. Cat Plafond M² 33.06 Rp 70,910.00 Rp 2,344,461.88
. Cat Kilap Kuzen M² 12.48 Rp 97,487.50 Rp 1,216,644.00
. Cat Kilap Pintu, Jendela M² 6.44 Rp 97,487.50 Rp 628,209.45
. Cat Kilap Listplank M² 6.90 Rp 97,487.50 Rp 672,663.75

VIII.PEKERJAAN INSTALASI LISTRIK Rp 6,860,900.00


. Pas. Instalasi Kabel + Titik Mata Lampu Ttk 9.00 Rp 250,000.00 Rp 2,250,000.00
. Pas. Limit Bh 1.00 Rp 97,000.00 Rp 97,000.00
. Pas. Box Sekring 3 Group Bh 1.00 Rp 470,000.00 Rp 470,000.00
. Pas. Lampu XL 18 Watt + Fitting Bh 4.00 Rp 538,600.00 Rp 2,154,400.00
. Pas. Stop Kontak Bh 3.00 Rp 399,000.00 Rp 1,197,000.00
. Pas. Saklar Ganda Bh 1.00 Rp 237,500.00 Rp 237,500.00
. Pas. Saklar Tunggal Bh 2.00 Rp 227,500.00 Rp 455,000.00

IX. PEKERJAAN SANITAIR Rp 11,760,435.00


. Closet Jongkok Bh 1.00 Rp 1,326,500.00 Rp 1,326,500.00
. Floor Drain (Stainless Steel) Bh 1.00 Rp 102,675.00 Rp 102,675.00
. Pas. Kran Air Bh 1.00 Rp 62,750.00 Rp 62,750.00
. Pipa PVC Ø4" M¹ 4.00 Rp 116,595.00 Rp 466,380.00
. Pipa Air Buangan PVC Ø3" M¹ 4.00 Rp 106,907.50 Rp 427,630.00
. Pipa PVC Ø3/4" M¹ 40.00 Rp 46,862.50 Rp 1,874,500.00
. Septictank + Peresapan Unit 1.00 Rp 7,500,000.00 Rp 7,500,000.00

X. PEKERJAAN AKHIR Rp 3,500,000.00


. Pembersihan Akhir Ls 1.00 Rp 1,000,000.00 Rp 1,000,000.00
. Foto / Dokumentasi dan Pelaporan Ls 1.00 Rp 2,500,000.00 Rp 2,500,000.00

733291305.xlsx 8.REHAB POSEC 160/191


REKAPITULASI TOTAL
RENCANA ANGGARAN BIAYA (RAB)
KEGIATAN : -
PEKERJAAN : PEMBANGUNAN POS SECURITY
INSTANSI : PERUM BULOG CABANG TIMIKA
LOKASI : JL.YOS SUDARSO SP1 TIMIKA,KAB.MIMIKA
TAHUN : -

NO JENIS PEKERJAAN TOTAL KETERANGAN

a b c d

I. PEKERJAAN TANAH DAN PASIR Rp 8,732,337.50

II. PEKERJAAN PONDASI DAN LANTAI Rp 42,233,150.70

III. PEKERJAAN DINDING Rp 66,010,627.53

IV. PEKERJAAN KUZEN, PINTU DAN JENDELA Rp 12,275,125.50

V. PEKERJAAN ATAP DAN PLAFOND Rp 49,814,087.66

VI. PEKERJAAN PENGGANTUNG DAN KUNCI Rp 2,359,312.50

VII. PEKERJAAN PENGECETAN Rp 12,120,483.80

VIII. PEKERJAAN INSTALASI LISTRIK Rp 6,860,900.00

IX. PEKERJAAN SANITAIR Rp 11,760,435.00

X. PEKERJAAN AKHIR Rp 3,500,000.00

(a). TOTAL BIAYA FISIK, ……………………........................... Rp 215,666,460.18


(b). JASA KONSULTANSI (D/S), ............................................... Rp -
(c). TOTAL REAL COST, {(a) + (b)} …………………….......................... Rp 215,666,460.18
(d). PPN 11 %, {11% x '(c)}, .......................................................... Rp 23,723,310.62
(e). GRAND TOTAL, {'(c) + (d)}, ……………............................ Rp 239,389,770.80
(f). DIBULATKAN, ................................................................... Rp 239,390,000.00

TERBILANG : Dua Ratus Tiga Puluh Sembilan Juta Tiga Ratus Sembilan Puluh Ribu Rupiah

Timika, Agustus 2023


--------------------------------
--------------------------------

--------------------------------
--------------------------------

Page 161
REKAPITULASI TOTAL
#REF!
### : #REF!
### :
### : #REF!
### : #REF!
### : #REF!

SATUAN
VOLUME HARGA
NO UNIT PEKERJAAN JUMLAH
SATUAN

a b c d e f

A. PEKERJAAN UTAMA Rp 23,074,928,000.00

I PEMBANGUNAN GUDANG TYPE 3200 TON m2 1,440.00 10,280,000.00 Rp 14,803,200,000.00

II REHABILITASI GUDANG TYPE 1000 TON m2 450.00 7,890,000.00 Rp 3,550,500,000.00

III PEMBANGUNAN GUDANG PQG/GUDANG ALAT m2 108.00 6,780,000.00 Rp 732,240,000.00

IV REHABILITASI KANTOR KCP m2 300.00 6,780,000.00 Rp 2,034,000,000.00

V REAHABILITASI RUMAH DINAS m2 117.00 5,424,000.00 Rp 634,608,000.00

VI REHABILITASI RUMAH ASS.MANAGER m2 88.00 5,085,000.00 Rp 447,480,000.00

PEMBUATAN MENARA AIR BERSIH 6000 LTR DAN


VII set 1.00 300,000,000.00 Rp 300,000,000.00
SUMUR BOR

VIII INSTALASI AIR BERSIH ls 1.00 200,000,000.00 Rp 200,000,000.00

IX PEMBANGUNAN TOILET UMUM m2 55.00 6,780,000.00 Rp 372,900,000.00

B. PEKERJAAN SITE DEVELOPMENT Rp 5,875,496,340.00

I REHABILITASI PELATARAN GUDANG DAN JALAN MAS M2 4,071.65 750,000.00 Rp 3,053,737,500.00

II REHABILITASI PAGAR SAMPING M 385.14 3,680,000.00 Rp 1,417,307,840.00

II REHABILITASI PAGAR DEPAN M 75.00 4,040,000.00 Rp 303,000,000.00

III PEMBUATAN DRAINASE M 385.14 750,000.00 Rp 288,853,500.00

III REHABILITASI TIANG BENDERA UTAMA LS 1.00 12,000,000.00 Rp 12,000,000.00

III PEMBUATAN POS SECURITY KOMPLEX LS 16.00 5,085,000.00 Rp 81,360,000.00

III PEMBUATAN POS SECURITY KANTOR LS 4.00 5,085,000.00 Rp 20,340,000.00

IV PEMBUATAN TIANG BENDERA KANTOR LS 1.00 7,500,000.00 Rp 7,500,000.00

V PEMBUATAN PAGAR PEMBATAS KANTOR M 75.00 3,680,000.00 Rp 276,000,000.00

VI LANDSCAPING M2 1,661.59 250,000.00 Rp 415,397,500.00

VII LAPANGAN TENIS LS Rp -

VIII FAS. LAPANGAN TENIS LS Rp -

(a). TOTAL BIAYA FISIK, ……………………........................... Rp 28,950,424,340.00


(b). JASA KONSULTANSI (DS=5% + SV=4%), ............................ Rp 2,605,538,190.60
(c). TOTAL REAL COST, {(a) + (b)} ………….......................... Rp 31,555,962,530.60
(d). PPN 11 %, {11% x '(c)}, .......................................................... Rp 3,471,155,878.37
(e). GRAND TOTAL, {'(c) + (d)}, ……………............................ Rp 35,027,118,408.97
(f). DIBULATKAN, ................................................................... Rp 35,027,119,000.00

Page 162
TERBILANG : Tiga Puluh Lima Milyar Dua Puluh Tujuh Juta Seratus Sembilan Belas Ribu Rupiah

Timika, Maret 2024


--------------------------------
--------------------------------

--------------------------------
--------------------------------

Page 163
EKAPITULASI TOTAL
#REF!

JUMLAH KETERANGAN

Rp 14,627,774,000.00

Rp 3,732,124,000.00

Rp 1,026,367,000.00

Rp 2,864,919,000.00

Page 164
Seratus Sembilan Belas Ribu Rupiah

Page 165
RENCANA ANGGARAN BIAYA (RAB)
KEGIATAN :
PEKERJAAN : PEKERJAAN MENARA AIR BERSIH 349,975,148.30
INSTANSI PERUM BULOG CABANG TIMIKA
LOKASI : JL.YOS SUDARSO SP1 TIMIKA,KAB.MIMIKA
TAHUN :
HARGA SATUAN
NO URAIAN JENIS PEKERJAAN SAT VOLUME JUMLAH
(Rp)

(a) (b) (c) (d) (e)

I. PEKERJAAN TANAH DAN PASIR Rp 11,479,125.00


. Pas. Bouwplank M' 10.50 Rp 139,350.00 Rp 1,463,175.00
. Galian Tanah Untuk Pondasi M³ 50.00 Rp 144,720.00 Rp 7,236,000.00
. Urugan Tanah Kembali M³ 25.00 Rp 40,260.00 Rp 1,006,500.00
. Urugan Pasir Alas Pondasi m3 1.25 Rp 369,000.00 Rp 461,250.00
. Urugan Sirtu M³ 3.60 Rp 364,500.00 Rp 1,312,200.00

II. PEKERJAAN BATU DAN BETON Rp 141,905,265.58


. Pasangan Batu Kosong ( Aanstamping ) M³ 3.50 Rp 1,616,040.00 Rp 5,656,140.00
. Pas. Pondasi Batu Kali, Camp. 1 : 4 M³ 5.62 Rp 2,295,700.00 Rp 12,913,312.50
. Cor Lantai Kerja M³ 1.25 Rp 1,540,300.00 Rp 1,925,375.00
. Pek. Cor Pondasi Poot Plat M³ 6.40 Rp 8,338,060.00 Rp 53,363,584.00
. Pek. Cor Pedestal Kolom 60x60 M³ 2.45 Rp 16,754,200.00 Rp 41,014,281.60
. Pek. Cor Slof Pengikat 30x30 M³ 1.63 Rp 10,586,790.00 Rp 17,277,641.28
. Pek.Plesteran Beton M² 20.72 Rp 132,960.00 Rp 2,754,931.20
. Pek. Pengecoran Ankur baut dan Base Plat Ttk 4.00 Rp 500,000.00 Rp 2,000,000.00
. Pek. Rumah Pompa Unit 1.00 Rp 5,000,000.00 Rp 5,000,000.00

III. PEKERJAAN BAJA Rp 121,161,291.77


. Pengadaan Ankur Baut D12x60cm Bh 32.00 Rp 75,000.00 Rp 2,400,000.00
. Pengadaan & Pabrikasi Plat 12 mm Untuk Base Plat Kg 67.84 Rp 74,097.52 Rp 5,026,656.87
. Pekerjaan Tiang Besi Siku L 80.80.8 Kg 308.91 Rp 74,097.52 Rp 22,889,412.32
. Pekerjaan Kros Datar Besi Siku L 70.70.7 Kg 428.67 Rp 74,097.52 Rp 31,763,530.18
. Pekerjaan Kros Miring Besi Siku L 60.60.6 Kg 255.13 Rp 74,097.52 Rp 18,904,385.96
. Pekerjaan Andang/lantai :
- Besi Siku L 80.80.8 Kg 135.15 Rp 74,097.52 Rp 10,014,117.89
- Besi Siku L 70.70.7 Kg 92.39 Rp 74,097.52 Rp 6,845,588.40
- Besi Siku L 60.60.6 Kg 78.54 Rp 74,097.52 Rp 5,819,510.82
Besi Siku L 50.50.5 Kg 63.59 Rp 74,097.52 Rp 4,712,017.96
. Pekerjaan Reling Pengaman : Besi Siku L 50.50.5 Kg 81.88 Rp 74,097.52 Rp 6,066,777.10
. Pekerjaan Tangga :
- Besi Siku L 50.50.5 Kg 67.88 Rp 74,097.52 Rp 5,029,411.89
- Besi Siku L 40.40.4 Kg 22.81 Rp 74,097.52 Rp 1,689,882.39

IV. PEKERJAAN INSTALASI Rp 58,126,041.67


. Pengadaan Dan Pemasangan Tandon @1200 Ltr Unt 5.00 Rp 2,500,000.00 Rp 12,500,000.00
. Pek.Instalasi Pipa :
- PPR 1 Inc M' 40.00 Rp 125,496.25 Rp 5,019,850.00
- PPR 1,5 Inc M' 30.00 Rp 188,244.38 Rp 5,647,331.25
- PPR 2 Inc M' 20.00 Rp 250,992.50 Rp 5,019,850.00
- Aksesories Pipa PPR Ls 1.00 Rp 5,229,010.42 Rp 5,229,010.42
- Pas.Kran Pelampung M' 5.00 Rp 250,000.00 Rp 1,250,000.00
- Pas.Stop Kran M' 8.00 Rp 120,000.00 Rp 960,000.00
- Klam Pipa Bh 16.00 Rp 50,000.00 Rp 800,000.00

733291305.xlsx 9.MENARA AIR 166/191


(a) (b) (c) (d) (e)
. Pek.Instalasi Listrik :
- Pompa Air Jet Pump Set 1.00 Rp 15,000,000.00 Rp 15,000,000.00
- Istalasi Kabel Pompa Ttk 1.00 Rp 5,000,000.00 Rp 5,000,000.00
- Instalasi Penerangan Ttk 2.00 Rp 500,000.00 Rp 1,000,000.00
- Lampu Sorot autdoor Set 2.00 Rp 350,000.00 Rp 700,000.00

VII.PEKERJAAN PENGECETAN Rp 8,803,424.28


. Cat Tembok M² 20.72 Rp 65,622.50 Rp 1,359,698.20
. Cat Besi M² 108.80 Rp 68,416.60 Rp 7,443,726.08

X. PEKERJAAN AKHIR Rp 8,500,000.00


Softdrawing/Asbuiltdrawing Ls 1.00 Rp 5,000,000.00 Rp 5,000,000.00
. Pembersihan Akhir Ls 1.00 Rp 1,000,000.00 Rp 1,000,000.00
. Foto / Dokumentasi dan Pelaporan Ls 1.00 Rp 2,500,000.00 Rp 2,500,000.00

733291305.xlsx 9.MENARA AIR 167/191


REKAPITULASI TOTAL
RENCANA ANGGARAN BIAYA (RAB)
KEGIATAN : -
PEKERJAAN : PEKERJAAN MENARA AIR BERSIH
INSTANSI : PERUM BULOG CABANG TIMIKA
LOKASI : JL.YOS SUDARSO SP1 TIMIKA,KAB.MIMIKA
TAHUN : -

NO JENIS PEKERJAAN TOTAL KETERANGAN

a b c d

I. PEKERJAAN TANAH DAN PASIR Rp 11,479,125.00

II. PEKERJAAN BATU DAN BETON Rp 141,905,265.58

III. PEKERJAAN BAJA Rp 121,161,291.77

IV. PEKERJAAN INSTALASI Rp 58,126,041.67

VII. PEKERJAAN PENGECETAN Rp 8,803,424.28

X. PEKERJAAN AKHIR Rp 8,500,000.00

(a). TOTAL BIAYA FISIK, ……………………........................... Rp 349,975,148.30


(b). JASA KONSULTANSI (D/S), ............................................... Rp 34,997,514.83
(c). TOTAL REAL COST, {(a) + (b)} …………………….......................... Rp 384,972,663.13
(d). PPN 11 %, {11% x '(c)}, .......................................................... Rp 42,346,992.94
(e). GRAND TOTAL, {'(c) + (d)}, ……………............................ Rp 427,319,656.08
(f). DIBULATKAN, ................................................................... Rp 427,320,000.00

TERBILANG : Empat Ratus Dua Puluh Tujuh Juta Tiga Ratus Dua Puluh Ribu Rupiah

Timika, Agustus 2023


--------------------------------
--------------------------------

--------------------------------
--------------------------------

Page 168
REKAPITULASI TOTAL
RENCANA ANGGARAN BIAYA (RAB)
KEGIATAN :
PEKERJAAN :
INSTANSI :
LOKASI :
TAHUN :

JASA KONSULTAN TOTAL

SATUAN
VOLUME HARGA PPN 11%
NO UNIT PEKERJAAN JUMLAH HARGA TOTAL BIAYA
SATUAN PENGAWASAN/
DESIGN SUPERVISI REAL COST
5% 4% 11%
a b c d e f g h i j k

A. PEKERJAAN UTAMA Rp 24,465,429,398.91 Rp 1,223,271,469.95 Rp 978,617,175.96 Rp 26,667,318,044.81 Rp 2,933,404,984.93 Rp 29,600,723,029.74

I PEMBANGUNAN GUDANG TYPE 3200 TON m2 1,440.00 7,813,727.13 Rp 11,251,767,073.50 Rp 562,588,353.68 Rp 450,070,682.94 Rp 12,264,426,110.12 Rp 1,349,086,872.11 13,613,512,982.23

II REHABILITASI GUDANG TYPE 1000 TON m2 450.00 9,069,767.96 Rp 4,081,395,580.09 Rp 204,069,779.00 Rp 163,255,823.20 Rp 4,448,721,182.29 Rp 489,359,330.05 4,938,080,512.35

III PEMBANGUNAN GUDANG PQG/GUDANG ALAT m2 108.00 8,860,820.50 Rp 956,968,613.98 Rp 47,848,430.70 Rp 38,278,744.56 Rp 1,043,095,789.24 Rp 114,740,536.82 1,157,836,326.06

IV REHABILITASI KANTOR GEDUNG KANTOR CABANG m2 300.00 10,282,182.44 Rp 3,084,654,731.68 Rp 154,232,736.58 Rp 123,386,189.27 Rp 3,362,273,657.53 Rp 369,850,102.33 3,732,123,759.86

V REAHABILITASI RUMAH DINAS m2 117.00 7,250,485.71 Rp 848,306,827.95 Rp 42,415,341.40 Rp 33,932,273.12 Rp 924,654,442.47 Rp 101,711,988.67 1,026,366,431.14

VI REHABILITASI RUMAH ASISTEN MANAGER m2 88.00 26,663,299.18 Rp 2,346,370,328.17 Rp 117,318,516.41 Rp 93,854,813.13 Rp 2,557,543,657.71 Rp 281,329,802.35 2,838,873,460.06

PEMBUATAN MENARA AIR BERSIH 6000 LTR DAN


VII
SUMUR BOR
set 1.00 350,000,000.00 Rp 350,000,000.00 Rp 17,500,000.00 Rp 14,000,000.00 Rp 381,500,000.00 Rp 41,965,000.00 423,465,000.00

VIII INSTALASI AIR BERSIH ls 1.00 280,000,000.00 Rp 280,000,000.00 Rp 14,000,000.00 Rp 11,200,000.00 Rp 305,200,000.00 Rp 33,572,000.00 338,772,000.00

IX PEMBANGUNAN TOILET UMUM m2 55.00 9,381,204.43 Rp 515,966,243.54 Rp 25,798,312.18 Rp 20,638,649.74 Rp 562,403,205.45 Rp 61,864,352.60 624,267,558.05

X INSTALASI LISTRIK PENERANGAN LUAR LS 1.00 750,000,000.00 Rp 750,000,000.00 Rp 37,500,000.00 Rp 30,000,000.00 Rp 817,500,000.00 Rp 89,925,000.00 907,425,000.00

B. PEKERJAAN SITE DEVELOPMENT Rp 7,187,867,618.18 Rp 359,393,380.91 Rp 287,514,704.73 Rp 7,834,775,703.82 Rp 861,825,327.42 Rp 10,760,521,045.24

PEMATANGAN TANAH UNTUK AREA GUDANG TYPE 3200


I
TON
M3 3,600.00 473,850.00 Rp 1,705,860,000.00 Rp 85,293,000.00 Rp 68,234,400.00 Rp 1,859,387,400.00 Rp 204,532,614.00 2,063,920,014.00

II REHABILITASI JALAN KOMLEX DAN PELATARAN M2 4,071.65 900,000.00 Rp 3,664,485,000.00 Rp 183,224,250.00 Rp 146,579,400.00 Rp 3,994,288,650.00 Rp 439,371,751.50 4,433,660,401.50

III REHABILITASI PAGAR SAMPING/BELAKANG M 382.00 4,452,275.94 Rp 1,700,769,408.00 Rp 85,038,470.40 Rp 68,030,776.32 Rp 1,853,838,654.72 Rp 203,922,252.02 2,057,760,906.74

IV REHABILITASI PAGAR DEPAN M 75.00 4,646,000.00 Rp 348,450,000.00 Rp 17,422,500.00 Rp 13,938,000.00 Rp 379,810,500.00 Rp 41,779,155.00 421,589,655.00

X PEMBUATAN PAGAR KANTOR M 105.00 3,154,285.71 Rp 331,200,000.00 Rp 16,560,000.00 Rp 13,248,000.00 Rp 361,008,000.00 Rp 39,710,880.00 400,718,880.00
Page 169
V PEMBUATAN DRAINASE M 532.00 678,697.13 Rp 361,066,875.00 Rp 18,053,343.75 Rp 14,442,675.00 Rp 393,562,893.75 Rp 43,291,918.31 436,854,812.06

VI REHABILITASI TIANG BENDERA UTAMA LS 1.00 13,200,000.00 Rp 13,200,000.00 Rp 660,000.00 Rp 528,000.00 Rp 14,388,000.00 Rp 1,582,680.00 15,970,680.00

VII PEMBUATAN POS SECURITY KOMPLEX (UTAMA) LS 16.00 13,479,153.76 Rp 215,666,460.18 Rp 10,783,323.01 Rp 8,626,658.41 Rp 235,076,441.60 Rp 25,858,408.58 260,934,850.17

VIII PEMBUATAN POS SECURITY KANTOR LS 4.00 6,102,000.00 Rp 24,408,000.00 Rp 1,220,400.00 Rp 976,320.00 Rp 26,604,720.00 Rp 2,926,519.20 29,531,239.20

IX PEMBUATAN TIANG BENDERA KANTOR LS 1.00 9,375,000.00 Rp 9,375,000.00 Rp 468,750.00 Rp 375,000.00 Rp 10,218,750.00 Rp 1,124,062.50 11,342,812.50

XI LANDSCAPING M2 1,661.59 312,500.00 Rp 519,246,875.00 Rp 25,962,343.75 Rp 20,769,875.00 Rp 565,979,093.75 Rp 62,257,700.31 628,236,794.06

(a). GRAND TOTAL, ……………………........................... Rp 31,653,297,017.09 Rp 1,582,664,850.85 Rp 1,266,131,880.68 Rp 34,502,093,748.63 Rp 3,795,230,312.35 Rp 40,361,244,074.97
(f). DIBULATKAN, ...................................................................
Rp40,361,245,000.00

TERBILANG : Empat Puluh Milyar Tiga Ratus Enam Puluh Satu Juta Dua Ratus Empat Puluh Lima Ribu Rupiah

Page 170
Tabel Profil Baja

Ukuran Profil Baja Section Moment Inertia Jari jari Inertia Moment Lawa
Perimeter Berat Panjang
H B t1 t2 r Area Ix Iy ix iy Wx
mm mm mm mm mm Cm2 Cm1 Kg / M M Cm4 Cm Cm3
WF 100 x 50 x 5x 7 7.5 WF 100x50x5x7 11.78 37.71 9.25 12.00 178.15 14.67 3.90 1.12 35.63
WF 125 x 60 x 6x 8 8.8 WF 125x60x6x8 16.80 46.30 13.19 12.00 393.80 29.00 4.74 1.29 63.01
WF 148 x 100 x 6x 9 9.4 WF 148x100x6x9 26.55 66.79 20.85 12.00 980.51 150.23 5.33 2.09 132.50
WF 150 x 75 x 5x 7 7.5 WF 150x75x5x7 17.78 57.71 13.96 12.00 642.03 49.36 4.96 1.37 85.60
WF 175 x 90 x 5x 8 8.1 WF 175x90x5x8 22.92 68.61 17.99 12.00 1,172.26 97.37 5.66 1.63 133.97
WF 198 x 99 x 4.5 x 7 7.2 WF 198x99x4,5x7 22.58 77.07 17.73 12.00 1,498.24 113.34 5.75 1.58 151.34
WF 200 x 100 x 3.2 x 4.5 4.8 WF 200x100x3,2x4,5 15.31 78.53 12.02 12.00 1,045.92 75.05 4.76 1.28 104.59
WF 200 x 100 x 5.5 x 8 8.4 WF 200x100x5,5x8 26.73 77.45 20.98 12.00 1,760.93 133.59 6.16 1.70 176.09
WF 248 x 124 x 5x 8 8.1 WF 248x124x5x8 32.01 96.81 25.13 12.00 3,378.32 254.46 6.89 1.89 272.44
WF 250 x 125 x 6x 9 9.4 WF 250x125x6x9 37.17 97.19 29.18 12.00 3,892.93 293.39 7.33 2.01 311.43
WF 299 x 149 x 6x 8 8.8 WF 299x149x6x8 41.48 116.70 32.56 12.00 6,181.52 441.57 7.75 2.07 413.48
WF 300 x 150 x 6.5 x 9 9.7 WF 300x150x6,5x9 46.14 117.04 36.22 12.00 6,932.52 506.90 8.16 2.21 462.17
WF 346 x 174 x 6x 9 9.4 WF 346x174x6x9 51.75 135.99 40.63 12.00 10,658.94 790.79 8.76 2.38 616.12
WF 350 x 175 x 7x 11 11 WF 350x175x7x11 62.55 136.67 49.10 12.00 13,123.47 983.49 9.63 2.64 749.91
WF 400 x 200 x 8x 13 13 WF 400x200x8x13 83.40 156.15 65.47 12.00 22,964.87 1,734.93 11.14 3.06 1,148.24
WF 446 x 199 x 8x 12 13 WF 446x199x8x12 82.86 165.05 65.05 12.00 27,505.53 1,577.92 11.58 2.77 1,233.43
WF 450 x 200 x 9x 14 14 WF 450x200x9x14 95.75 165.73 75.17 12.00 32,258.95 1,869.23 12.45 3.00 1,433.73
WF 500 x 200 x 10 x 16 16 WF 500x200x10x16 113.07 175.21 88.76 12.00 46,036.55 2,137.23 14.10 3.04 1,841.46
WF 588 x 300 x 10 x 16 16 WF 588x300x10x16 153.87 232.81 120.79 12.00 92,867.94 7,204.63 15.10 4.21 3,158.77
WF 600 x 200 x 11 x 17 18 WF 600x200x11x17 132.89 194.80 104.32 12.00 74,418.64 2,272.94 16.37 2.86 2,480.62
WF 700 x 300 x 13 x 24 23 WF 700x300x13x24 233.35 253.43 183.18 12.00 194,606.99 10,811.94 20.01 4.72 5,560.20
WF 800 x 300 x 14 x 26 25 WF 800x300x14x26 266.09 272.91 208.88 12.00 282,553.57 11,717.10 22.55 4.59 7,063.84

Ukuran Profil Baja Section Moment Inertia Jari jari Inertia Moment Lawa
Perimeter Berat Panjang
H B t1 t2 r Area Ix Iy ix iy Wx
mm mm mm mm mm Cm2 Cm1 Kg / M M Cm4 Cm Cm3
H 100 x 100 x 6x 8 8 H 100x100x6x8 21.59 57.43 16.95 12.00 369.05 133.48 3.98 2.39 73.81
H 125 x 125 x 5x 7 7 H 125x125x5x7 23.47 72.80 18.42 12.00 666.87 227.98 4.29 2.51 106.70
H 125 x 125 x 6.5 x 9 9 H 125x125x6,5x9 30.15 72.15 23.67 12.00 824.78 293.21 4.76 2.84 131.96
H 150 x 150 x 7x 10 10 H 150x150x7x10 39.96 86.88 31.37 12.00 1,600.66 562.87 5.53 3.28 213.42
H 175 x 175 x 7x 11 11 H 175x175x7x11 50.25 101.71 39.45 12.00 2,801.55 982.99 6.27 3.72 320.18
H 200 x 200 x 8x 12 12 H 200x200x8x12 63.32 116.34 49.70 12.00 4,610.49 1,600.75 7.04 4.15 461.05
H 250 x 250 x 9x 14 14 H 250x250x9x14 91.66 145.80 71.96 12.00 10,578.81 3,647.18 8.54 5.01 846.30
H 300 x 300 x 10 x 15 15 H 300x300x10x15 118.93 175.42 93.36 12.00 19,932.75 6,752.25 9.77 5.69 1,328.85
H 350 x 350 x 12 x 19 19 H 350x350x12x19 173.54 204.34 136.23 12.00 39,506.18 13,581.58 11.79 6.91 2,257.50
H 400 x 400 x 13 x 21 21 H 400x400x13x21 218.33 233.79 171.39 12.00 65,361.59 22,406.55 13.27 7.77 3,268.08

Ukuran Profil Baja Section Moment Inertia Jari jari Inertia Moment Lawa
Perimeter Berat Panjang
H B t1 t2 r Area Ix Iy ix iy Wx
mm mm mm mm mm Cm2 Cm1 Kg / M M Cm4 Cm Cm3
UNP 50 x 38 x 5x 7.5 7.5 UNP 50x38x5 6.81 22.91 5.34 6.00 27.79 6.90 2.48 1.24 11.12
UNP 65 x 42 x 5x 7.5 7.5 UNP 65x42x5 8.16 27.51 6.40 6.00 57.58 9.31 2.99 1.20 17.72
UNP 75 x 40 x 5x 7.5 7.5 UNP 75x40x5 8.36 28.71 6.56 6.00 77.63 8.06 3.32 1.07 20.70
UNP 80 x 45 x 5x 7.5 7.5 UNP 80x45x5 9.36 31.71 7.35 6.00 100.46 11.46 3.45 1.16 25.11
UNP 100 x 50 x 5x 7.5 7.5 UNP 100x50x5 11.11 37.71 8.72 6.00 186.37 15.71 3.99 1.16 37.27
UNP 120 x 55 x 7x 10.5 11 UNP 120x55x7 17.22 42.80 13.52 6.00 403.88 29.40 5.10 1.38 67.31
UNP 125 x 65 x 6x 9 9 UNP 125x65x6 17.20 48.25 13.50 6.00 455.63 41.39 4.90 1.48 72.90
UNP 150 x 75 x 6.5 x 9.75 9.8 UNP 150x75x6,5 22.02 57.03 17.29 12.00 840.73 68.85 5.66 1.62 112.10
UNP 180 x 75 x 7x 10.5 11 UNP 180x75x7 25.62 62.80 20.11 12.00 1,367.18 74.28 6.59 1.54 151.91
UNP 200 x 80 x 7.5 x 11.3 11 UNP 200x80x7,5 29.87 68.57 23.45 12.00 1,954.62 96.62 7.24 1.61 195.46
UNP 250 x 90 x 9x 13.5 14 UNP 250x90x9 42.29 81.88 33.20 12.00 4,233.29 165.38 8.98 1.78 338.66
UNP 300 x 90 x 9x 13.5 14 UNP 300x90x9 46.79 91.88 36.73 12.00 6,516.17 165.68 10.18 1.62 434.41
UNP 300 x 100 x 10 x 16 16 UNP 300x100x10 55.88 95.25 43.86 12.00 8,063.38 268.90 10.73 1.96 537.56

Ukuran Profil Baja Section Moment Inertia Jari jari Inertia Moment Lawa
Perimeter Berat Panjang
H B t r1 r2 Area Ix Iy ix iy Wx
mm mm mm mm mm Cm2 Cm1 Kg / M M Cm4 Cm Cm3
L 20 x 20 x 3 3 1.5 L 20x20x3 1.13 11.14 0.89 6.00 0.94 0.40 1.00 0.65 0.94
L 25 x 25 x 3 3 1.5 L 25x25x3 1.43 14.14 1.12 6.00 2.00 0.79 1.16 0.73 1.60
L 25 x 25 x 5 5 2.5 L 25x25x5 2.30 13.57 1.81 6.00 2.69 1.32 1.34 0.94 2.15
L 30 x 30 x 3 3 1.5 L 30x30x3 1.73 17.14 1.36 6.00 3.64 1.36 1.31 0.80 2.43
L 40 x 40 x 3 3 1.5 L 40x40x3 2.33 23.14 1.83 6.00 9.21 3.21 1.57 0.93 4.61
L 40 x 40 x 4 4 2 L 40x40x4 3.07 22.86 2.41 6.00 11.50 4.28 1.75 1.07 5.75
L 40 x 40 x 5 5 2.5 L 40x40x5 3.80 22.57 2.99 6.00 13.46 5.36 1.89 1.19 6.73
L 45 x 45 x 4 4 2 L 45x45x4 3.47 25.86 2.73 6.00 16.87 6.09 1.89 1.13 7.50
L 45 x 45 x 5 5 2.5 L 45x45x5 4.30 25.57 3.38 6.00 19.88 7.63 2.04 1.26 8.84
L 50 x 50 x 4 4 2 L 50x50x4 3.87 28.86 3.04 6.00 23.68 8.36 2.01 1.20 9.47
L 50 x 50 x 5 5 2.5 L 50x50x5 4.80 28.57 3.77 6.00 28.08 10.46 2.19 1.33 11.23
L 50 x 50 x 6 6 3 L 50x50x6 5.72 28.28 4.49 6.00 31.96 12.57 2.33 1.46 12.79
L 60 x 60 x 5 5 2.5 L 60x60x5 5.80 34.57 4.56 6.00 50.71 18.05 2.45 1.46 16.90
L 60 x 60 x 6 6 3 L 60x60x6 6.92 34.28 5.43 6.00 58.23 21.69 2.62 1.60 19.41
L 65 x 65 x 6 6 3 L 65x65x6 7.52 37.28 5.90 6.00 75.56 27.56 2.76 1.67 23.25
L 70 x 70 x 6 6 3 L 70x70x6 8.12 40.28 6.37 6.00 96.02 34.40 2.89 1.73 27.44
L 70 x 70 x 7 7 3.5 L 70x70x7 9.42 40.00 7.39 6.00 107.88 40.18 3.06 1.87 30.82
L 75 x 75 x 6 6 3 L 75x75x6 8.72 43.28 6.84 6.00 119.89 42.30 3.02 1.79 31.97
L 75 x 75 x 7 7 3.5 L 75x75x7 10.12 43.00 7.94 6.00 135.05 49.39 3.20 1.93 36.01
L 75 x 75 x 8 8 4 L 75x75x8 11.50 42.71 9.03 6.00 149.00 56.50 3.35 2.07 39.73
L 80 x 80 x 6 6 3 L 80x80x6 9.32 46.28 7.31 6.00 147.43 51.32 3.14 1.85 36.86
L 80 x 80 x 8 8 4 L 80x80x8 12.30 45.71 9.65 6.00 184.05 68.54 3.50 2.13 46.01
L 90 x 90 x 8 8 4 L 90x90x8 13.90 51.71 10.91 6.00 269.85 97.52 3.77 2.27 59.97
L 90 x 90 x 9 9 4.5 L 90x90x9 15.56 51.43 12.22 6.00 294.81 109.79 3.94 2.40 65.51
L 90 x 90 x 10 10 5 L 90x90x10 17.21 51.14 13.51 6.00 318.08 122.08 4.08 2.53 70.69
L 100 x 100 x 8 8 4 L 100x100x8 15.50 57.71 12.17 6.00 378.93 133.69 4.02 2.39 75.79
L 100 x 100 x 10 10 5 L 100x100x10 19.21 57.14 15.08 6.00 449.33 167.33 4.37 2.67 89.87
L 120 x 120 x 11 11 5.5 L 120x120x11 25.45 68.86 19.98 12.00 873.08 317.89 5.08 3.07 145.51
L 120 x 120 x 12 12 6 L 120x120x12 27.67 68.57 21.72 12.00
L 125 x 125 x 12 12 6 L 125x125x12 28.87 71.57 22.66 12.00
L 130 x 130 x 9 9 4.5 L 130x130x9 22.76 75.43 17.87 12.00
L 130 x 130 x 12 12 6 L 130x130x12 30.07 74.57 23.60 12.00
L 150 x 150 x 12 12 6 L 150x150x12 34.87 86.57 27.37 12.00
L 150 x 150 x 15 15 7.5 L 150x150x15 43.23 85.71 33.94 12.00
L 200 x 200 x 15 15 7.5 L 200x200x15 58.23 115.71 45.71 12.00
L 200 x 200 x 20 20 10 L 200x200x20 76.86 114.28 60.33 12.00
L 200 x 200 x 25 25 13 L 200x200x25 95.09 112.85 74.65 12.00
L 250 x 250 x 25 25 13 L 250x250x25 120.09 142.85 94.27 12.00

Ukuran Profil Baja Section Moment Inertia Jari jari Inertia Moment Lawa
Perimeter Berat Panjang
H B h1 t r Area Ix Iy ix iy Wx
mm mm mm mm mm Cm2 Cm1 Kg / M M Cm4 Cm Cm3
C 60 x 30 x 10 x 1.6 4 C 60x30x10x1,6 2.08 25.99 1.63 6.00 23.46 1.19 2.35 0.53 7.82
C 75 x 35 x 15 x 1.6 4 C 75x35x15x1,6 2.64 32.99 2.07 6.00 61.36 3.16 3.13 0.71 16.36
C 74 x 45 x 15 x 1.6 4 C 74x45x15x1,6 2.94 36.79 2.31 6.00
C 74 x 45 x 15 x 2.3 4 C 74x45x15x2,3 4.20 36.51 3.30 6.00
C 100 x 50 x 20 x 1.6 4 C 100x50x20x1,6 3.68 45.99 2.89 6.00
C 100 x 50 x 20 x 2.3 4 C 100x50x20x2,3 5.26 45.71 4.13 6.00
C 100 x 50 x 20 x 3.2 4 C 100x50x20x3,2 7.26 45.35 5.70 6.00
C 125 x 50 x 20 x 2.3 6 C 125x50x20x2,3 5.75 50.02 4.52 6.00
C 125 x 50 x 20 x 3.2 6 C 125x50x20x3,2 7.95 49.66 6.24 6.00
C 150 x 50 x 20 x 2.3 6 C 150x50x20x2,3 6.33 55.02 4.97 6.00
C 150 x 50 x 20 x 3.2 6 C 150x50x20x3,2 8.75 54.66 6.87 6.00
C 150 x 65 x 20 x 2.3 6 C 150x65x20x2,3 7.02 61.02 5.51 6.00
C 150 x 65 x 20 x 3.2 6 C 150x65x20x3,2 9.71 60.66 7.62 6.00
C 200 x 75 x 20 x 3.2 7 C 200x75x20x3,2 11.89 74.32 9.33 6.00

Carbon Steel Pipe - SCH 40 Section Outer Moment Inertia Jari jari Inertia Moment Lawa
Berat Panjang
Size OD ID t Area Perimeter Ix Iy ix iy Wx
Inchi mm mm mm Cm2 Cm1 Kg / M M Cm4 Cm Cm3
SCH 40 1/2 21.7 16.1 2.8 PIPA SCH 40-0,5" 1.66 6.82 1.31 6.00 0.76 0.76 0.68 0.68 0.70
SCH 40 3/4 27.2 21.4 2.9 PIPA SCH 40-0,75" 2.21 8.55 1.74 6.00 1.66 1.66 0.87 0.87 1.22
SCH 40 1 34 27.2 3.4 PIPA SCH 40-1" 3.27 10.68 2.57 6.00 3.87 3.87 1.09 1.09 2.28
SCH 40 1 1/4 42.7 35.5 3.6 PIPA SCH 40-1,25" 4.42 13.41 3.47 6.00 8.52 8.52 1.39 1.39 3.99
SCH 40 1 1/2 48.6 41.2 3.7 PIPA SCH 40-1,5" 5.22 15.27 4.10 6.00 13.24 13.24 1.59 1.59 5.45
SCH 40 2 60.5 52.7 3.9 PIPA SCH 40-2" 6.93 19.01 5.44 6.00 27.90 27.90 2.01 2.01 9.22
SCH 40 2 1/2 76.3 65.9 5.2 PIPA SCH 40-2,5" 11.62 23.97 9.12 6.00 73.79 73.79 2.52 2.52 19.34
SCH 40 3 89.1 78.1 5.5 PIPA SCH 40-3" 14.45 27.99 11.34 6.00 126.74 126.74 2.96 2.96 28.45
SCH 40 4 114.3 102.3 6 PIPA SCH 40-4" 20.41 35.91 16.03 6.00 300.21 300.21 3.83 3.83 52.53
SCH 40 5 139.8 126.6 6.6 PIPA SCH 40-5" 27.62 43.92 21.68 6.00 614.02 614.02 4.72 4.72 87.84
SCH 40 6 165.2 151 7.1 PIPA SCH 40-6" 35.26 51.90 27.68 6.00 1,104.05 1,104.05 5.60 5.60 133.66
SCH 40 8 216.3 199.9 8.2 PIPA SCH 40-8" 53.61 67.95 42.08 6.00 2,906.46 2,906.46 7.36 7.36 268.74
SCH 40 10 267.4 248.8 9.3 PIPA SCH 40-10" 75.41 84.01 59.20 12.00 6,287.39 6,287.39 9.13 9.13 470.26
SCH 40 12 318.5 297.9 10.3 PIPA SCH 40-12" 99.73 100.06 78.29 12.00 11,854.41 11,854.41 10.90 10.90 744.39
SCH 40 14 355.6 333.4 11.1 PIPA SCH 40-14" 120.13 111.72 94.30 12.00 17,840.26 17,840.26 12.19 12.19 1,003.39
SCH 40 16 406.4 381 12.7 PIPA SCH 40-16" 157.08 127.67 123.31 12.00 30,465.73 30,465.73 13.93 13.93 1,499.30
Carbon Steel Pipe - SCH 80 Section Outer Moment Inertia Jari jari Inertia Moment Lawa
Berat Panjang
Size OD ID t Area Perimeter Ix Iy ix iy Wx
Inchi mm mm mm Cm2 Cm1 Kg / M M Cm4 Cm Cm3
SCH 80 1/2 21.7 14.3 3.7 PIPA SCH 80-0,5" 2.09 6.82 1.64 6.00 0.88 0.88 0.65 0.65 0.81
SCH 80 3/4 37.2 19.4 8.9 PIPA SCH 80-0,75" 7.91 11.69 6.21 6.00 8.70 8.70 1.05 1.05 4.68
SCH 80 1 34 25 4.5 PIPA SCH 80-1" 4.17 10.68 3.27 6.00 4.64 4.64 1.06 1.06 2.73
SCH 80 1 1/4 42.7 32.9 4.9 PIPA SCH 80-1,25" 5.82 13.41 4.57 6.00 10.57 10.57 1.35 1.35 4.95
SCH 80 1 1/2 48.6 38.4 5.1 PIPA SCH 80-1,5" 6.97 15.27 5.47 6.00 16.71 16.71 1.55 1.55 6.88
SCH 80 2 60.5 49.5 5.5 PIPA SCH 80-2" 9.50 19.01 7.46 6.00 36.29 36.29 1.95 1.95 12.00
SCH 80 2 1/2 76.3 62.3 7 PIPA SCH 80-2,5" 15.24 23.97 11.96 6.00 92.42 92.42 2.46 2.46 24.23
SCH 80 3 89.1 73.9 7.6 PIPA SCH 80-3" 19.46 27.99 15.28 6.00 162.97 162.97 2.89 2.89 36.58
SCH 80 4 114.3 97.1 8.6 PIPA SCH 80-4" 28.56 35.91 22.42 6.00 401.47 401.47 3.75 3.75 70.25
SCH 80 5 139.8 120.8 9.5 PIPA SCH 80-5" 38.89 43.92 30.53 6.00 829.70 829.70 4.62 4.62 118.70
SCH 80 6 165.2 143.2 11 PIPA SCH 80-6" 53.29 51.90 41.83 6.00 1,591.88 1,591.88 5.47 5.47 192.72
SCH 80 8 216.3 190.9 12.7 PIPA SCH 80-8" 81.23 67.95 63.77 6.00 4,225.55 4,225.55 7.21 7.21 390.71
SCH 80 10 267.4 237.2 15.1 PIPA SCH 80-10" 119.69 84.01 93.95 12.00 9,557.44 9,557.44 8.94 8.94 714.84
SCH 80 12 318.5 283.7 17.4 PIPA SCH 80-12" 164.59 100.06 129.21 12.00 18,714.98 18,714.98 10.66 10.66 1,175.19
SCH 80 14 355.6 317.6 19 PIPA SCH 80-14" 200.92 111.72 157.72 12.00 28,545.48 28,545.48 11.92 11.92 1,605.48
SCH 80 16 406.4 363.6 21.4 PIPA SCH 80-16" 258.84 127.67 203.19 12.00 48,105.59 48,105.59 13.63 13.63 2,367.40

SEAMLESS BOILER TUBE Section Outer Moment Inertia Jari jari Inertia Moment Lawa
Berat Panjang
Size OD ID t Area Perimeter Ix Iy ix iy Wx
Inchi mm mm mm Cm2 Cm1 Kg / M M Cm4 Cm Cm3
SBT 1/4 13.5 9.9 1.8 PIPA SBT-0,25" 0.66 4.24 0.52 6.00 0.12 0.12 0.42 0.42 0.17
SBT 3/8 17.2 13.6 1.8 PIPA SBT-0,375" 0.87 5.40 0.68 6.00 0.26 0.26 0.55 0.55 0.30
SBT 1/2 21.3 17.3 2 PIPA SBT-0,5" 1.21 6.69 0.95 6.00 0.57 0.57 0.69 0.69 0.54
SBT 3/4 26.9 22.3 2.3 PIPA SBT-0,75" 1.78 8.45 1.40 6.00 1.36 1.36 0.87 0.87 1.01
SBT 1 36.6 30.8 2.9 PIPA SBT-1" 3.07 11.50 2.41 6.00 4.39 4.39 1.20 1.20 2.40
SBT 1 31.8 26 2.9 PIPA SBT-1" 2.63 9.99 2.07 6.00 2.78 2.78 1.03 1.03 1.75
SBT 1 1/4 42.4 37.2 2.6 PIPA SBT-1,25" 3.25 13.32 2.55 6.00 6.46 6.46 1.41 1.41 3.05
SBT 1 1/4 44.5 39.3 2.6 PIPA SBT-1,25" 3.42 13.98 2.69 6.00 7.54 7.54 1.48 1.48 3.39
SBT 1 1/4 38 32.8 2.6 PIPA SBT-1,25" 2.89 11.94 2.27 6.00 4.55 4.55 1.25 1.25 2.40
SBT 1 1/2 48.3 42.5 2.9 PIPA SBT-1,5" 4.14 15.17 3.25 6.00 10.70 10.70 1.61 1.61 4.43
SBT 2 60.3 54.5 2.9 PIPA SBT-2" 5.23 18.94 4.11 6.00 21.59 21.59 2.03 2.03 7.16
SBT 2 57 51.2 2.9 PIPA SBT-2" 4.93 17.91 3.87 6.00 18.08 18.08 1.92 1.92 6.35
SBT 2 1/2 76.1 70.3 2.9 PIPA SBT-2,5" 6.67 23.91 5.24 6.00 44.74 44.74 2.59 2.59 11.76
SBT 3 88.9 82.5 3.2 PIPA SBT-3" 8.62 27.93 6.76 6.00 79.21 79.21 3.03 3.03 17.82
SBT 4 114.3 106.3 4 PIPA SBT-4" 13.86 35.91 10.88 6.00 211.07 211.07 3.90 3.90 36.93
SBT 5 139.7 131.7 4 PIPA SBT-5" 17.05 43.89 13.39 6.00 392.86 392.86 4.80 4.80 56.24
SBT 6 168.3 159.3 4.5 PIPA SBT-6" 23.16 52.87 18.18 6.00 777.22 777.22 5.79 5.79 92.36

PIPA HITAM STK 41 Section Outer Moment Inertia Jari jari Inertia Moment Lawa
Berat Panjang
Size OD ID t Area Perimeter Ix Iy ix iy Wx
Inchi mm mm mm Cm2 Cm1 Kg / M M Cm4 Cm Cm3
STK 41 2 1/2 76.3 70.7 2.8 PIPA STK 41-2,5" 6.47 23.97 5.08 6.00 43.72 43.72 2.60 2.60 11.46
STK 41 2 1/2 76.3 69.9 3.2 PIPA STK 41-2,5" 7.35 23.97 5.77 6.00 49.18 49.18 2.59 2.59 12.89
STK 41 3 89.1 82.7 3.2 PIPA STK 41-3" 8.64 27.99 6.78 6.00 79.76 79.76 3.04 3.04 17.90
STK 41 4 114.3 107.3 3.5 PIPA STK 41-4" 12.18 35.91 9.56 6.00 187.15 187.15 3.92 3.92 32.75
STK 41 4 114.3 105.3 4.5 PIPA STK 41-4" 15.52 35.91 12.19 6.00 234.32 234.32 3.89 3.89 41.00
STK 41 5 139.8 130.8 4.5 PIPA STK 41-5" 19.13 43.92 15.02 6.00 438.17 438.17 4.79 4.79 62.69
STK 41 5 139.8 127.8 6 PIPA STK 41-5" 25.22 43.92 19.80 6.00 565.53 565.53 4.74 4.74 80.90
STK 41 6 165.2 156.2 4.5 PIPA STK 41-6" 22.72 51.90 17.83 6.00 733.94 733.94 5.68 5.68 88.85
STK 41 6 165.2 155.2 5 PIPA STK 41-6" 25.16 51.90 19.75 6.00 808.05 808.05 5.67 5.67 97.83
STK 41 6 165.2 153.2 6 PIPA STK 41-6" 30.01 51.90 23.56 6.00 952.04 952.04 5.63 5.63 115.26
STK 41 7 190.7 180.1 5.3 PIPA STK 41-7" 30.87 59.91 24.23 6.00 1,327.45 1,327.45 6.56 6.56 139.22
STK 41 8 216.3 204.7 5.8 PIPA STK 41-8" 38.36 67.95 30.11 6.00 2,126.05 2,126.05 7.45 7.45 196.58
STK 41 8 216.3 199.9 8.2 PIPA STK 41-8" 53.61 67.95 42.08 6.00 2,906.46 2,906.46 7.36 7.36 268.74
STK 41 10 267.4 254.2 6.6 PIPA STK 41-10" 54.08 84.01 42.45 12.00 4,600.50 4,600.50 9.22 9.22 344.09
STK 41 12 318.5 304.7 6.9 PIPA STK 41-12" 67.55 100.06 53.02 12.00 8,201.90 8,201.90 11.02 11.02 515.03
STK 41 14 355.6 339.8 7.9 PIPA STK 41-14" 86.29 111.72 67.74 12.00 13,047.44 13,047.44 12.30 12.30 733.83

PIPA HITAM BLACK STEEL MEDIUM Section Outer Moment Inertia Jari jari Inertia Moment Lawa
Berat Panjang
Size OD ID t Area Perimeter Ix Iy ix iy Wx
Inchi mm mm mm Cm2 Cm1 Kg / M M Cm4 Cm Cm3
BS. MED. 1/2 21.4 16.2 2.6 PIPA BS. MED.-0,5" 1.54 6.72 1.21 6.00 0.69 0.69 0.67 0.67 0.65
BS. MED. 3/4 27 21.8 2.6 PIPA BS. MED.-0,75" 1.99 8.48 1.56 6.00 1.50 1.50 0.87 0.87 1.11
BS. MED. 1 33.7 27.3 3.2 PIPA BS. MED.-1" 3.07 10.59 2.41 6.00 3.60 3.60 1.08 1.08 2.14
BS. MED. 1 1/4 42.4 36 3.2 PIPA BS. MED.-1,25" 3.94 13.32 3.09 6.00 7.62 7.62 1.39 1.39 3.59
BS. MED. 1 1/2 48.3 41.9 3.2 PIPA BS. MED.-1,5" 4.53 15.17 3.56 6.00 11.59 11.59 1.60 1.60 4.80
BS. MED. 2 60.2 53 3.6 PIPA BS. MED.-2" 6.40 18.91 5.03 6.00 25.74 25.74 2.01 2.01 8.55
BS. MED. 2 1/2 76 68.8 3.6 PIPA BS. MED.-2,5" 8.19 23.88 6.43 6.00 53.78 53.78 2.56 2.56 14.15
BS. MED. 3 88.7 80.7 4 PIPA BS. MED.-3" 10.64 27.87 8.36 6.00 95.66 95.66 3.00 3.00 21.57
BS. MED. 4 113.9 104.9 4.5 PIPA BS. MED.-4" 15.47 35.78 12.14 6.00 231.77 231.77 3.87 3.87 40.70
BS. MED. 5 140.6 131 4.8 PIPA BS. MED.-5" 20.48 44.17 16.08 6.00 472.65 472.65 4.80 4.80 67.23
BS. MED. 6 166.1 156.5 4.8 PIPA BS. MED.-6" 24.32 52.18 19.09 6.00 791.75 791.75 5.71 5.71 95.33

PIPA HITAM BLACK STEEL LIGHT Section Outer Moment Inertia Jari jari Inertia Moment Lawa
Berat Panjang
Size OD ID t Area Perimeter Ix Iy ix iy Wx
Inchi mm mm mm Cm2 Cm1 Kg / M M Cm4 Cm Cm3
BS. Light 1/2 21.4 15.4 3 PIPA BS. Light-0,5" 1.73 6.72 1.36 6.00 0.75 0.75 0.66 0.66 0.70
BS. Light 3/4 27 22.4 2.3 PIPA BS. Light-0,75" 1.78 8.48 1.40 6.00 1.37 1.37 0.88 0.88 1.02
BS. Light 1 33.7 28.5 2.6 PIPA BS. Light-1" 2.54 10.59 1.99 6.00 3.09 3.09 1.10 1.10 1.84
BS. Light 1 1/4 42.4 37.2 2.6 PIPA BS. Light-1,25" 3.25 13.32 2.55 6.00 6.46 6.46 1.41 1.41 3.05
BS. Light 1 1/2 48.3 42.5 2.9 PIPA BS. Light-1,5" 4.14 15.17 3.25 6.00 10.70 10.70 1.61 1.61 4.43
BS. Light 2 60.2 54.4 2.9 PIPA BS. Light-2" 5.22 18.91 4.10 6.00 21.48 21.48 2.03 2.03 7.14
BS. Light 2 1/2 76 69.6 3.2 PIPA BS. Light-2,5" 7.32 23.88 5.75 6.00 48.58 48.58 2.58 2.58 12.78
BS. Light 3 88.7 82.3 3.2 PIPA BS. Light-3" 8.60 27.87 6.75 6.00 78.65 78.65 3.02 3.02 17.73
BS. Light 4 113.9 106.7 3.6 PIPA BS. Light-4" 12.47 35.78 9.79 6.00 189.91 189.91 3.90 3.90 33.35

PIPA BAJA LAPIS SENG LIGHT Section Outer Moment Inertia Jari jari Inertia Moment Lawa
Berat Panjang
Size OD ID t Area Perimeter Ix Iy ix iy Wx
Inchi mm mm mm Cm2 Cm1 Kg / M M Cm4 Cm Cm3
GSP. Light 3/8 17.1 13.5 1.8 PIPA GSP. Light-0,375" 0.87 5.37 0.68 6.00 0.26 0.26 0.54 0.54 0.30
GSP. Light 1/2 21.4 17.4 2 PIPA GSP. Light-0,5" 1.22 6.72 0.96 6.00 0.58 0.58 0.69 0.69 0.54
GSP. Light 3/4 26.9 22.2 2.35 PIPA GSP. Light-0,75" 1.81 8.45 1.42 6.00 1.38 1.38 0.87 0.87 1.02
GSP. Light 1 33.8 28.5 2.65 PIPA GSP. Light-1" 2.59 10.62 2.04 6.00 3.17 3.17 1.11 1.11 1.87
GSP. Light 1 1/4 42.5 37.2 2.65 PIPA GSP. Light-1,25" 3.32 13.35 2.60 6.00 6.61 6.61 1.41 1.41 3.11
GSP. Light 1 1/2 48.4 42.6 2.9 PIPA GSP. Light-1,5" 4.15 15.21 3.25 6.00 10.77 10.77 1.61 1.61 4.45
GSP. Light 2 60.2 54.4 2.9 PIPA GSP. Light-2" 5.22 18.91 4.10 6.00 21.48 21.48 2.03 2.03 7.14
GSP. Light 2 1/2 76 69.5 3.25 PIPA GSP. Light-2,5" 7.43 23.88 5.83 6.00 49.24 49.24 2.57 2.57 12.96
GSP. Light 3 88.7 82.2 3.25 PIPA GSP. Light-3" 8.72 27.87 6.85 6.00 79.75 79.75 3.02 3.02 17.98
GSP. Light 4 113.9 106.6 3.65 PIPA GSP. Light-4" 12.64 35.78 9.92 6.00 192.29 192.29 3.90 3.90 33.77
PIPA BAJA LAPIS SENG MEDIUM Section Outer Moment Inertia Jari jari Inertia Moment Lawa
Berat Panjang
Size OD ID t Area Perimeter Ix Iy ix iy Wx
Inchi mm mm mm Cm2 Cm1 Kg / M M Cm4 Cm Cm3
GSP. MED. 3/8 17.4 12.7 2.35 PIPA GSP. MED.-0,375 1.11 5.47 0.87 6.00 0.32 0.32 0.54 0.54 0.37
GSP. MED. 1/2 21.7 16.4 2.65 PIPA GSP. MED.-0,5" 1.59 6.82 1.24 6.00 0.73 0.73 0.68 0.68 0.68
GSP. MED. 3/4 27.2 21.9 2.65 PIPA GSP. MED.-0,75" 2.04 8.55 1.60 6.00 1.56 1.56 0.87 0.87 1.15
GSP. MED. 1 34.2 27.7 3.25 PIPA GSP. MED.-1" 3.16 10.74 2.48 6.00 3.83 3.83 1.10 1.10 2.24
GSP. MED. 1 1/4 42.9 36.4 3.25 PIPA GSP. MED.-1,25" 4.05 13.48 3.18 6.00 8.01 8.01 1.41 1.41 3.73
GSP. MED. 1 1/2 48.8 42.3 3.25 PIPA GSP. MED.-1,5" 4.65 15.33 3.65 6.00 12.12 12.12 1.61 1.61 4.97
GSP. MED. 2 60.8 53.5 3.65 PIPA GSP. MED.-2" 6.55 19.10 5.14 6.00 26.86 26.86 2.02 2.02 8.84
GSP. MED. 2 1/2 76.6 69.3 3.65 PIPA GSP. MED.-2,5" 8.37 24.06 6.57 6.00 55.78 55.78 2.58 2.58 14.57
GSP. MED. 3 89.5 81.4 4.05 PIPA GSP. MED.-3" 10.87 28.12 8.53 6.00 99.45 99.45 3.02 3.02 22.22
GSP. MED. 4 114.9 105.9 4.5 PIPA GSP. MED.-4" 15.61 36.10 12.25 6.00 238.18 238.18 3.91 3.91 41.46
GSP. MED. 5 140.6 130.9 4.85 PIPA GSP. MED.-5" 20.68 44.17 16.24 6.00 477.06 477.06 4.80 4.80 67.86
GSP. MED. 6 166.1 156.4 4.85 PIPA GSP. MED.-6" 24.57 52.18 19.29 6.00 799.27 799.27 5.70 5.70 96.24
GSP. MED. 8 216.3 204.7 5.8 PIPA GSP. MED.-8" 38.36 67.95 30.11 6.00 2,126.05 2,126.05 7.45 7.45 196.58
GSP. MED. 10 267.4 254.2 6.6 PIPA GSP. MED.-10" 54.08 84.01 42.45 12.00 4,600.50 4,600.50 9.22 9.22 344.09
GSP. MED. 12 318.5 304.7 6.9 PIPA GSP. MED.-12" 67.55 100.06 53.02 12.00 8,201.90 8,201.90 11.02 11.02 515.03

Besi beton polos Section Moment Inertia Jari jari Inertia Moment Lawa
Perimeter Berat Panjang
Dia. Area Ix Iy ix iy Wx
mm Cm2 Cm1 Kg / M M Cm4 Cm Cm3
P 6 mm x 12 M P6 0.28 1.88 0.22 12.00 0.01 0.01 0.15 0.15 0.02
P 8 mm x 12 M P8 0.50 2.51 0.39 12.00 0.02 0.02 0.20 0.20 0.05
P 9 mm x 12 M P9 0.64 2.83 0.50 12.00 0.03 0.03 0.23 0.23 0.07
P 10 mm x 12 M P 10 0.79 3.14 0.62 12.00 0.05 0.05 0.25 0.25 0.10
P 12 mm x 12 M P 12 1.13 3.77 0.89 12.00 0.10 0.10 0.30 0.30 0.17
P 13 mm x 12 M P 13 1.33 4.08 1.04 12.00 0.14 0.14 0.33 0.33 0.22
P 16 mm x 12 M P 16 2.01 5.03 1.58 12.00 0.32 0.32 0.40 0.40 0.40
P 19 mm x 12 M P 19 2.84 5.97 2.23 12.00 0.64 0.64 0.48 0.48 0.67
P 22 mm x 12 M P 22 3.80 6.91 2.98 12.00 1.15 1.15 0.55 0.55 1.05
P 25 mm x 12 M P 25 4.91 7.85 3.85 12.00 1.92 1.92 0.63 0.63 1.53
P 28 mm x 12 M P 28 6.16 8.80 4.83 12.00 3.02 3.02 0.70 0.70 2.16
P 32 mm x 12 M P 32 8.04 10.05 6.31 12.00 5.15 5.15 0.80 0.80 3.22
P 36 mm x 12 M P 36 10.18 11.31 7.99 12.00 8.24 8.24 0.90 0.90 4.58

Besi beton Deform Section Moment Inertia Jari jari Inertia Moment Lawa
Perimeter Berat Panjang
Dia. Area Ix Iy ix iy Wx
mm Cm2 Cm1 Kg / M M Cm4 Cm Cm3
D 10 mm x 12 M D 10 0.79 3.14 0.62 12.00 0.05 0.05 0.25 0.25 0.10
D 13 mm x 12 M D 13 1.33 4.08 1.04 12.00 0.14 0.14 0.33 0.33 0.22
D 16 mm x 12 M D 16 2.01 5.03 1.58 12.00 0.32 0.32 0.40 0.40 0.40
D 19 mm x 12 M D 19 2.84 5.97 2.23 12.00 0.64 0.64 0.48 0.48 0.67
D 22 mm x 12 M D 22 3.80 6.91 2.98 12.00 1.15 1.15 0.55 0.55 1.05
D 25 mm x 12 M D 25 4.91 7.85 3.85 12.00 1.92 1.92 0.63 0.63 1.53
D 29 mm x 12 M D 29 6.61 9.11 5.19 12.00 3.47 3.47 0.73 0.73 2.39
D 32 mm x 12 M D 32 8.04 10.05 6.31 12.00 5.15 5.15 0.80 0.80 3.22
D 36 mm x 12 M D 36 10.18 11.31 7.99 12.00 8.24 8.24 0.90 0.90 4.58

BESI PLAT STRIP Section Moment Inertia Jari jari Inertia Moment Lawa
Perimeter Berat Panjang
thick width length Area Ix Iy ix iy Wx
mm mm M Cm2 Cm1 Kg / M M Cm4 Cm Cm3
FB 3x 19 x 6 FB 3x19 0.57 44.00 0.45 6.00 0.00 0.01 0.10 0.20 0.01
FB 3x 25 x 6 FB 3x25 0.75 56.00 0.59 6.00 0.00 0.01 0.09 0.18 0.01
FB 3x 30 x 6 FB 3x30 0.90 66.00 0.71 6.00 0.00 0.01 0.08 0.16 0.01
FB 4x 19 x 6 FB 4x19 0.76 46.00 0.60 6.00
FB 4x 25 x 6 FB 4x25 1.00 58.00 0.79 6.00
FB 4x 30 x 6 FB 4x30 1.20 68.00 0.94 6.00
FB 4x 38 x 6 FB 4x38 1.52 84.00 1.19 6.00
FB 5x 19 x 6 FB 5x19 0.95 48.00 0.75 6.00
FB 5x 25 x 6 FB 5x25 1.25 60.00 0.98 6.00
FB 5x 30 x 6 FB 5x30 1.50 70.00 1.18 6.00
FB 5x 38 x 6 FB 5x38 1.90 86.00 1.49 6.00
FB 5x 50 x 6 FB 5x50 2.50 110.00 1.96 6.00
FB 6x 150 x 6 FB 6x150 9.00 312.00 7.07 6.00
FB 8x 38 x 6 FB 8x38 3.04 92.00 2.39 6.00
FB 9x 125 x 6 FB 9x125 11.25 268.00 8.83 6.00
FB 9x 150 x 6 FB 9x150 13.50 318.00 10.60 6.00

tabel plat baja


BERAT/ BERAT/
TEBAL UKURAN (M)
LEMBAR M2
NO
(mm) Lebar Panjang (Kg) (Kg/m2)

1.00 1.40 1.22 2.44 33.00 11.10


2.00 1.50 1.22 2.44 35.00 11.78
3.00 1.80 1.22 2.44 42.00 14.13
4.00 2.00 1.22 2.44 46.70 15.71
5.00 2.30 1.22 2.44 54.00 18.17
6.00 2.60 1.22 2.44 60.70 20.42
7.00 2.80 1.22 2.44 65.30 21.97
8.00 2.90 1.22 2.44 67.60 22.75
9.00 3.00 1.22 2.44 70.00 23.55
10.00 4.00 1.22 2.44 93.30 31.39
11.00 4.50 1.22 2.44 105.00 35.33
12.00 5.00 1.22 2.44 117.00 39.37
13.00 6.00 1.22 2.44 140.00 47.11
14.00 8.00 1.22 2.44 187.00 62.92
15.00 9.00 1.22 2.44 210.00 70.66
16.00 10.00 1.22 2.44 233.30 78.50
17.00 12.00 1.22 2.44 280.00 94.22
18.00 15.00 1.22 2.44 350.00 117.77
19.00 16.00 1.22 2.44 373.00 125.51
20.00 18.00 1.22 2.44 420.00 141.32
21.00 19.00 1.22 2.44 443.00 149.06
22.00 20.00 1.22 2.44 467.00 157.14
23.00 22.00 1.22 2.44 513.00 172.62
Moment Lawan
Wy
Cm3
5.87
9.67
30.05
13.16 167.51
21.64
22.90
15.01
26.72 251.81 WF 200x100x5,5x8
41.04 WF 200x100x5,5x8
46.94 WF 250x125x6x9
59.27
67.59
90.90
112.40
173.49
158.58
186.92
213.72
480.31
227.29
720.80
781.14

Moment Lawan
Wy
Cm3
26.70 203.37
36.48 221.09
46.91 284.02
75.05 376.41
112.34 473.34
160.08 596.44
291.77 863.46
450.15 1,120.33
776.09 1,634.74
1,120.33 2,056.63

Moment Lawan
Wy
Cm3
3.63 32.06
4.43 76.85
4.03 78.73
5.09 88.15
6.29 104.64 UNP 100x5 0.38 0.0432498
10.69 162.23
12.73 161.98
18.36 207.45
19.81 241.35
24.16 281.35
36.75 398.37
36.82 440.76
53.78 526.37

Moment Lawan
Wy
Cm3
0.40 5.32
0.63 6.73
1.05 10.85
0.90 8.15
1.60 10.97
2.14 14.48
2.68 17.92
2.71 16.36
3.39 20.27
3.34 18.25
4.18 22.63
5.03 26.93
6.02 27.34
7.23 32.58
8.48 35.41
9.83 38.23
11.48 44.35
11.28 41.06
13.17 47.64
15.07 54.15
12.83 43.88
17.13 57.92
21.67 65.46
24.40 73.31
27.13 81.08
26.74 72.99
33.47 90.50
52.98 119.87
130.32
135.97
107.22
141.63
164.23
203.63
274.28
362.00
447.88
565.63

Moment Lawan
Wy
Cm3
0.80 9.79
1.81 12.43
13.86
19.77
17.33
24.76
34.17
27.09
37.42
29.80 C 150x50x20x2,3
41.19
33.05
45.71
56.00

Moment Lawan
Wy
Cm3
0.70 7.83
1.22 10.43
2.28 15.39
3.99 20.83
5.45 24.58
9.22 32.66
19.34 54.71
28.45 68.04
52.53 96.15
87.84 130.08
133.66 166.10
268.74 252.50
470.26 355.17
744.39 469.72
1,003.39 565.83
1,499.30 739.84
Moment Lawan
Wy
Cm3
0.81 9.85
4.68 37.27
2.73 19.64
4.95 27.41
6.88 32.83
12.00 44.76
24.23 71.78
36.58 91.65
70.25 134.51
118.70 183.16
192.72 250.99
390.71 382.61
714.84 563.72
1,175.19 775.23
1,605.48 946.32
2,367.40 1,219.12

Moment Lawan
Wy
Cm3
0.17 3.12
0.30 4.10
0.54 5.71
1.01 8.37
2.40 14.46
1.75 12.40
3.05 15.31
3.39 16.12
2.40 13.62
4.43 19.48
7.16 24.63
6.35 23.21
11.76 31.41
17.82 40.58
36.93 65.28
56.24 80.32
92.36 109.07

Moment Lawan
Wy
Cm3
11.46 30.45
12.89 34.61
17.90 40.67
32.75 57.38
41.00 73.11
62.69 90.09
80.90 118.79
88.85 107.00
97.83 118.52
115.26 141.34
139.22 145.40
196.58 180.66
268.74 252.50
344.09 254.70
515.03 318.14
733.83 406.45

Moment Lawan
Wy
Cm3
0.65 7.23
1.11 9.39
2.14 14.44
3.59 18.56
4.80 21.35
8.55 30.15
14.15 38.57
21.57 50.13
40.70 72.85
67.23 96.45
95.33 114.56

Moment Lawan
Wy
Cm3
0.70 8.17
1.02 8.41
1.84 11.96
3.05 15.31
4.43 19.48
7.14 24.59
12.78 34.47
17.73 40.48
33.35 58.76

Moment Lawan
Wy
Cm3
0.30 4.08
0.54 5.74
1.02 8.54
1.87 12.21
3.11 15.63
4.45 19.52
7.14 24.59
12.96 34.99
17.98 41.09
33.77 59.54
Moment Lawan
Wy
Cm3
0.37 5.23
0.68 7.47 17.40 Hollow circle relationships:
1.15 9.63 ----------------------------
2.24 14.88 A= 111.11 A = 3.14159 / 4 * (d^2 - di^2)
3.73 19.07 I= 3,222.55 I = 3.14159 / 64 * (d^4 - di^4)
4.97 21.90 Z= 370.41 Z = 3.14159 / (32 * d) * (d^4 - di^4)
8.84 30.87 J= 6,445.09 J = 3.14159 / 32 * (d^4 - di^4)
14.57 39.40 12.7 k= 5.39 k = sqrt((d^2 + di^2) / 16)
22.22 51.21 y= 8.70 y=d/2
41.46 73.51 W= 370.41 W=I/y
67.86 97.42 i= 5.39 i = ( I / A )^0,5
96.24 115.72 wi = 87.22 kg/m wi = rho * A
196.58 180.66 fy = 210 mpa
344.09 254.70 s= 21,000 kgcm2
515.03 318.14

Moment Lawan
Wy
Cm3
0.02 2.66
0.05 4.74
0.07 5.99
0.10 7.40
0.17 10.65
0.22 12.50
0.40 18.94
0.67 26.71
1.05 35.81
1.53 46.24
2.16 58.00
3.22 75.76
4.58 95.88

Moment Lawan
Wy
Cm3
0.10 7.40
0.22 12.50
0.40 18.94
0.67 26.71
1.05 35.81
1.53 46.24
2.39 62.22
3.22 75.76
4.58 95.88

Moment Lawan
Wy
Cm3
0.01 2.68
0.00 3.53
0.00 4.24
3.58
4.71
5.65
7.16
4.47
5.89
7.06
8.95
11.78
42.39
14.32
52.99
63.59