III. ANALISA HARGA SATUAN PEKERJAAN KONSTRUKSI - PEK.

SWAKELOLA
PEMERINTAH KOTA SALATIGA

HARGA UPAH HARGA JUMLAH


NO. URAIAN PEKERJAAN KOEF. SAT SATUAN TENAGA BAHAN
( Rp ) ( Rp ) ( Rp ) ( Rp )
a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
I. PEKERJAAN PERSIAPAN
I.1 1 M' Pagar sementara dari kayu tinggi 2 meter 128,639.50
SNI Bahan 107,079.50
03-2835-2002 - Kayu dolken Ø 8-10 / 400 cm 1.2500 Btg 16,500.00 20,625.00
- Semen PC ( Portland Cement ) 40 kg 2.5000 Kg 1,100.00 2,750.00
- Pasir pasang (kaliworo) 0.0050 M3 115,500.00 577.50
- Koral Beton 0.0090 M3 143,000.00 1,287.00
- Kayu tahun/ lanan 0.0720 M3 1,100,000.00 79,200.00
- Paku usuk 0.0600 Kg 11,000.00 660.00
- Residu/ ter 0.4000 Ltr 4,950.00 1,980.00

Tenaga 21,560.00
- Pekerja 0.4000 Oh 30,250.00 12,100.00
- Tukang Kayu 0.2000 Oh 38,500.00 7,700.00
- Kepala Tukang Kayu 0.0200 Oh 44,000.00 880.00
- Mandor 0.0200 Oh 44,000.00 880.00

I. 2 1 M' Pagar sementara dari seng gelombang tinggi 2 meter 126,934.50


SNI Bahan 105,374.50
03-2835-2002 - Kayu dolken Ø 8-10 / 400 cm 1.2500 Btg 16,500.00 20,625.00
- Semen PC ( Portland Cement ) 40 kg 2.5000 Kg 1,100.00 2,750.00
- Pasir pasang (kaliworo) 0.0050 M3 115,500.00 577.50
- Koral Beton 0.0090 M3 143,000.00 1,287.00
- Seng BJLS 0,2 gelombang P = 180 cm 1.2000 Lbr 36,300.00 43,560.00
- Paku usuk 0.0600 Kg 11,000.00 660.00
- Cat Meni Besi "altex" 0.4500 Kg 18,700.00 8,415.00
- Kayu tahun/ lanan 0.0250 M3 1,100,000.00 27,500.00

Tenaga 21,560.00
- Pekerja 0.4000 Oh 30,250.00 12,100.00
- Tukang Kayu 0.2000 Oh 38,500.00 7,700.00
- Kepala Tukang Kayu 0.0200 Oh 44,000.00 880.00
- Mandor 0.0200 Oh 44,000.00 880.00

I. 3 1 M' Pagar sementara dari kawat duri tinggi 1,8 meter 222,874.50
SNI Bahan 222,874.50
03-2835-2002 - Kayu dolken Ø 8-10 / 400 cm 1.0000 Btg 16,500.00 16,500.00
- Semen PC ( Portland Cement ) 40 kg 2.0000 Kg 1,100.00 2,200.00
- Kawat Duri 25.0000 Kg 8,066.00 201,650.00
- Pasir pasang (kaliworo) 0.0050 M3 115,500.00 577.50
- Koral Beton 0.0090 M3 143,000.00 1,287.00
- Paku usuk 0.0600 Kg 11,000.00 660.00

Tenaga 18,535.00
- Pekerja 0.3000 Oh 30,250.00 9,075.00
- Tukang Kayu 0.2000 Oh 38,500.00 7,700.00
- Kepala Tukang Kayu 0.0200 Oh 44,000.00 880.00
- Mandor 0.0200 Oh 44,000.00 880.00

I. 4 1 M2 Pengukuran dan pemasangan bouwplank 30,195.00


SNI Bahan 22,660.00
03-2835-2002 - Kayu tahun/ lanan 0.0120 M3 1,100,000.00 13,200.00
- Paku reng 0.0200 Kg 11,000.00 220.00
- Papan 3/20 kayu tahun 0.0070 M3 1,320,000.00 9,240.00

Tenaga 7,535.00
- Pekerja 0.1000 Oh 30,250.00 3,025.00
- Tukang Kayu 0.1000 Oh 38,500.00 3,850.00
- Kepala Tukang Kayu 0.0100 Oh 44,000.00 440.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 1


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
- Mandor 0.0050 Oh 44,000.00 220.00

I .5 1 M2 Pembuatan kantor sementara, dengan lantai plesteran 605,770.00


SNI Bahan 414,370.00
03-2835-2002 - Kayu dolken Ø 8-10 / 400 cm 1.2500 Btg 16,500.00 20,625.00
- Kayu tahun/ lanan 0.1800 M3 1,100,000.00 198,000.00
- Paku usuk 0.8500 Kg 11,000.00 9,350.00
- Besi Beton ulir 1.1000 Kg 8,800.00 9,680.00
- Semen PC ( Portland Cement ) 40 kg 35.0000 Kg 1,100.00 38,500.00
- Pasir pasang (kaliworo) 0.1500 M3 115,500.00 17,325.00
- Pasir beton (muntilan) 0.1000 M3 129,250.00 12,925.00
- Koral Beton 0.1500 M3 143,000.00 21,450.00
- Batu Bata lokal 30.0000 Bh 484.00 14,520.00
- Seng BJLS 0,20 lembaran L = 90 cm 0.2500 Lbr 23,100.00 5,775.00
- Rangka nako + besi tralis nako 2.0000 Bh 20,900.00 41,800.00
- Kaca bening 5 mm 0.0800 M2 66,000.00 5,280.00
- Kunci tanam double slag/ Selot pintu kuda terbang 0.1500 Bh 60,500.00 9,075.00
- Plywood 4 mm 0.0600 Lmb 57,750.00 3,465.00
- Engsel pintu kuningan 4" 0.3000 Bh 22,000.00 6,600.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 2


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
Tenaga 191,400.00
- Pekerja 2.0000 Oh 30,250.00 60,500.00
- Tukang Kayu 2.0000 Oh 38,500.00 77,000.00
- Kepala Tukang Kayu 0.3000 Oh 44,000.00 13,200.00
- Mandor 0.0500 Oh 44,000.00 2,200.00
- Tukang Batu 1.0000 Oh 38,500.00 38,500.00

I. 6 1 M2 Pembuatan gudang semen dan alat-alat 338,965.00


SNI Bahan 338,965.00
03-2835-2002 - Kayu dolken Ø 8-10 / 400 cm 1.7000 Btg 16,500.00 28,050.00
- Semen PC ( Portland Cement ) 40 kg 10.5000 Kg 1,100.00 11,550.00
- Seng BJLS 0,2 gelombang P = 180 cm 1.5000 Lbr 36,300.00 54,450.00
- Pasir pasang (kaliworo) 0.0300 M3 115,500.00 3,465.00
- Koral Beton 0.0500 M3 143,000.00 7,150.00
- Paku usuk 0.3000 Kg 11,000.00 3,300.00
- Kayu tahun/ lanan 0.2100 M3 1,100,000.00 231,000.00

Tenaga 118,250.00
- Pekerja 1.0000 Oh 30,250.00 30,250.00
- Tukang Kayu 2.0000 Oh 38,500.00 77,000.00
- Kepala Tukang Kayu 0.2000 Oh 44,000.00 8,800.00
- Mandor 0.0500 Oh 44,000.00 2,200.00

I. 7 1 M2 Pembuatan rumah jaga/konstruksi kayu 512,050.00


SNI Bahan 415,250.00
03-2835-2002 - Kayu dolken Ø 8-10 / 400 cm 3.0000 Btg 16,500.00 49,500.00
- Kayu tahun/ lanan 0.2760 M3 1,100,000.00 303,600.00
- Paku usuk 0.7000 Kg 11,000.00 7,700.00
- Seng BJLS 0,2 gelombang P = 180 cm 1.5000 Lbr 36,300.00 54,450.00

Tenaga 96,800.00
- Pekerja 1.0000 Oh 30,250.00 30,250.00
- Tukang Kayu 1.5000 Oh 38,500.00 57,750.00
- Kepala Tukang Kayu 0.1500 Oh 44,000.00 6,600.00
- Mandor 0.0500 Oh 44,000.00 2,200.00

I. 8 1 M2 Membersihkan lapangan dan perataan 5,225.00


SNI Bahan -
03-2835-2002 Tenaga 5,225.00
- Pekerja 0.1000 Oh 30,250.00 3,025.00
- Mandor 0.0500 Oh 44,000.00 2,200.00

I. 9 1 M2 Pembuatan bedeng buruh 509,602.50


SNI Bahan 391,352.50
03-2835-2002 - Kayu dolken Ø 8-10 / 400 cm 1.2500 Btg 16,500.00 20,625.00
- Semen PC ( Portland Cement ) 40 kg 18.0000 Kg 1,100.00 19,800.00
- Seng BJLS 0,2 gelombang P = 180 cm 1.5000 Lbr 36,300.00 54,450.00
- Pasir pasang (kaliworo) 0.0300 M3 115,500.00 3,465.00
- Koral Beton 0.0500 M3 143,000.00 7,150.00
- Paku usuk 0.3000 Kg 11,000.00 3,300.00
- Kayu tahun/ lanan 0.1860 M3 1,100,000.00 204,600.00
- Plywood 4 mm 1.3500 Lbr 57,750.00 77,962.50

Tenaga 118,250.00
- Pekerja 1.0000 Oh 30,250.00 30,250.00
- Tukang Kayu 2.0000 Oh 38,500.00 77,000.00
- Kepala Tukang Kayu 0.2000 Oh 44,000.00 8,800.00
- Mandor 0.0500 Oh 44,000.00 2,200.00

I.10 1 M2 Pembuatan bak adukan dari kayu tahun ukuran (40 x 50 x 20) cm 94,666.00
SNI Bahan 83,050.00
03-2835-2002 - Papan 3/20 kayu tahun 0.0360 M3 1,320,000.00 47,520.00
- Paku usuk 0.0800 Kg 11,000.00 880.00
- Kayu 5/7 meranti 0.0105 M3 3,300,000.00 34,650.00

Tenaga 11,616.00
- Tukang Kayu 0.3000 Oh 38,500.00 11,550.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 3


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
- Mandor 0.0015 Oh 44,000.00 66.00

I. 11 1 M2 Pembuatan bak adukan dari bambu ukuran (40 x 50 x 20) cm 17,539.50


SNI Bahan 8,662.50
03-2835-2002 - Bambu 1.0000 Btg 6,600.00 6,600.00
- Tali ijuk 0.2500 Kg 8,250.00 2,062.50

Tenaga 8,877.00
- Pekerja 0.2500 Oh 30,250.00 7,562.50
- Tukang Kayu 0.0170 Oh 38,500.00 654.50
- Kepala Tukang Kayu 0.0020 Oh 44,000.00 88.00
- Mandor 0.0130 Oh 44,000.00 572.00

I. 12 1 M2 Pembuatan jalan sementara 58,685.00


SNI Bahan 26,235.00
03-2835-2002 - Batu Belah 0.1500 M3 117,700.00 17,655.00
- Kerikil 0.0900 M3 82,500.00 7,425.00
- Pasir pasang (kaliworo) 0.0100 M3 115,500.00 1,155.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 4


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
Tenaga 32,450.00
- Pekerja 1.0000 Oh 30,250.00 30,250.00
- Mandor 0.0500 Oh 44,000.00 2,200.00

I. 13 1 M2 Pasang pagar kawat jaring galvanis tinggi 1,00 m 18,550.50


SNI Bahan 15,190.00
03-2835-2002 - Kawat Jaring galvanis 0.4340 m2 35,000.00 15,190.00

Tenaga 3,360.50
- Pekerja 0.0420 Oh 30,250.00 1,270.50
- Tukang Kayu 0.0040 Oh 38,500.00 154.00
- Kepala Tukang Kayu 0.0420 Oh 44,000.00 1,848.00
- Mandor 0.0020 Oh 44,000.00 88.00

I. 14 1 M2 Pasang pagar beton pracetak (5 x 50 x 213) cm 530,637.25


SNI Bahan 513,117.00
03-2835-2002 - Panel beton pracetak 0.9860 Lbr 247,500.00 244,035.00
- Kolom beton pra cetak 0.5250 Btg 346,500.00 181,912.50
- Pasir beton (muntilan) 0.0740 M3 129,250.00 9,564.50
- Batu pecah 2/3 (split) 0.1460 M3 192,500.00 28,105.00
- Semen PC ( Portland Cement ) 40 kg 45.0000 Kg 1,100.00 49,500.00

Tenaga 17,520.25
- Tukang Batu 0.1250 Oh 38,500.00 4,812.50
- Pekerja 0.3750 Oh 30,250.00 11,343.75
- Kepala Tukang Batu 0.0120 Oh 44,000.00 528.00
- Mandor 0.0190 Oh 44,000.00 836.00

II. PEKERJAAN TANAH DAN PASIR


II. 1 1 M3 Galian Tanah Biasa Sedalam 1 m 23,787.50
SNI Bahan
03-2835-2008 Tenaga 23,787.50
- Mandor 0.0250 Oh 44,000.00 1,100.00
- Pekerja 0.7500 Oh 30,250.00 22,687.50

II. 2 1 M3 Galian Tanah Biasa Sedalam 1 - 2 m 29,205.00


SNI Bahan
03-2835-2008 Tenaga 29,205.00
- Mandor 0.0450 Oh 44,000.00 1,980.00
- Pekerja 0.9000 Oh 30,250.00 27,225.00

II. 3 1 M3 Galian Tanah Biasa Sedalam 2 - 3 m 25,445.75


SNI Bahan
03-2835-2008 Tenaga 25,445.75
- Mandor 0.0730 Oh 44,000.00 3,212.00
- Pekerja 0.7350 Oh 30,250.00 22,233.75

II. 4 1 M3 Galian Tanah Keras Sedalam 1 m 33,858.00


SNI Bahan
03-2835-2008 Tenaga 33,858.00
- Mandor 0.0820 Oh 44,000.00 3,608.00
- Pekerja 1.0000 Oh 30,250.00 30,250.00

II. 5 1 M3 Galian Tanah Cadas Sedalam 1 m 48,015.00


SNI Bahan
03-2835-2008 Tenaga 48,015.00
- Mandor 0.0600 Oh 44,000.00 2,640.00
- Pekerja 1.5000 Oh 30,250.00 45,375.00

II. 6 1 M3 Galian Tanah Lumpur Sedalam 1 m 38,280.00


SNI Bahan
03-2835-2008 Tenaga 38,280.00
- Mandor 0.0450 Oh 44,000.00 1,980.00
- Pekerja 1.2000 Oh 30,250.00 36,300.00

II. 7 1 M3 Stripping setinggi 1 m 38,280.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 5


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
SNI Bahan
03-2835-2008 Tenaga 38,280.00
- Mandor 0.0450 Oh 44,000.00 1,980.00
- Pekerja 1.2000 Oh 30,250.00 36,300.00

II. 8 1 M3 Tanah Diangkut Sejauh 15 m 10,422.50


SNI Bahan
03-2835-2008 Tenaga 10,422.50
- Mandor 0.0100 Oh 44,000.00 440.00
- Pekerja 0.3300 Oh 30,250.00 9,982.50

II. 9 1 M3 Urugan kembali bekas galian 7,929.17


SNI Bahan
03-2835-2008 Tenaga 7,929.17
- Mandor 0.0083 Oh 44,000.00 366.67
- Pekerja 0.2500 Oh 30,250.00 7,562.50

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 6


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
II. 10 1 M3 Tanah diratakan dan dipadatkan 17,325.00
SNI Bahan
03-2835-2008 Tenaga 17,325.00
- Mandor 0.0500 Oh 44,000.00 2,200.00
- Pekerja 0.5000 Oh 30,250.00 15,125.00

II. 11 1 M3 Urugan pasir 103,235.00


SNI Bahan 93,720.00
03-2835-2008 - Pasir Urug 1.2000 M3 78,100.00 93,720.00

Tenaga 9,515.00
- Mandor 0.0100 Oh 44,000.00 440.00
- Pekerja 0.3000 Oh 30,250.00 9,075.00

II. 12 1 M3 Pemasangan lapisan ijuk 282,975.00


SNI Bahan 231,000.00
03-2835-2008 - Ijuk 60.0000 kg 3,850.00 231,000.00

Tenaga 51,975.00
- Mandor 0.1500 Oh 44,000.00 6,600.00
- Pekerja 1.5000 Oh 30,250.00 45,375.00

II. 13 1 M3 Urugan Sirtu 134,062.50


SNI Bahan 125,400.00
03-2835-2008 - Sirtu 1.2000 M3 104,500.00 125,400.00

Tenaga 8,662.50
- Mandor 0.0250 Oh 44,000.00 1,100.00
- Pekerja 0.2500 Oh 30,250.00 7,562.50

II. 14 1 M3 Urugan tanah mendatangkan 88,715.00


SNI Bahan 79,200.00
03-2835-2008 - Tanah Urug 1.2000 M3 66,000.00 79,200.00

Tenaga 9,515.00
- Mandor 0.0100 Oh 44,000.00 440.00
- Pekerja 0.3000 Oh 30,250.00 9,075.00

III. PEKERJAAN PONDASI


III. 1 1 M3 Pasang Pondasi Batu Kali 1 Pc : 1 Ps 689,557.00
SNI Bahan 608,707.00
03-2836-2008 - Batu Belah 1.2000 M3 117,700.00 141,240.00
- Semen PC ( Portland Cement ) 40 kg 392.0000 Kg 1,100.00 431,200.00
- Pasir pasang (kaliworo) 0.3140 M3 115,500.00 36,267.00

Tenaga 80,850.00
- Pekerja 1.5000 Oh 30,250.00 45,375.00
- Tukang Batu 0.7500 Oh 38,500.00 28,875.00
- Kepala Tukang Batu 0.0750 Oh 44,000.00 3,300.00
- Mandor 0.0750 Oh 44,000.00 3,300.00

III. 2 1 m3 Pasang Pondasi batu kali 1 Pc : 2 Ps 565,108.50


SNI Bahan 484,258.50
03-2836-2008 - Batu Belah 1.2000 M3 117,700.00 141,240.00
- Semen PC ( Portland Cement ) 40 kg 267.0000 Kg 1,100.00 293,700.00
- Pasir pasang (kaliworo) 0.4270 M3 115,500.00 49,318.50

Tenaga 80,850.00
- Pekerja 1.5000 Oh 30,250.00 45,375.00
- Tukang Batu 0.7500 Oh 38,500.00 28,875.00
- Kepala Tukang Batu 0.0750 Oh 44,000.00 3,300.00
- Mandor 0.0750 Oh 44,000.00 3,300.00

III. 3 1 m3 Pasang Pondasi batu kali 1 Pc : 2.5 Ps 528,220.00


SNI Bahan 447,370.00
03-2836-2008 - Batu Belah 1.2000 M3 117,700.00 141,240.00
- Semen PC ( Portland Cement ) 40 kg 230.0000 Kg 1,100.00 253,000.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 7


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
- Pasir pasang (kaliworo) 0.4600 M3 115,500.00 53,130.00

Tenaga 80,850.00
- Pekerja 1.5000 Oh 30,250.00 45,375.00
- Tukang Batu 0.7500 Oh 38,500.00 28,875.00
- Kepala Tukang Batu 0.0750 Oh 44,000.00 3,300.00
- Mandor 0.0750 Oh 44,000.00 3,300.00

III. 4 1m3 Pasang Pondasi batu kali, 1 Pc : 3 Ps 500,307.50


SNI Bahan 419,457.50
03-2836-2008 - Batu Belah 1.2000 M3 117,700.00 141,240.00
- Semen PC ( Portland Cement ) 40 kg 202.0000 Kg 1,100.00 222,200.00
- Pasir pasang (kaliworo) 0.4850 M3 115,500.00 56,017.50

Tenaga 80,850.00
- Pekerja 1.5000 Oh 30,250.00 45,375.00
- Tukang Batu 0.7500 Oh 38,500.00 28,875.00
- Kepala Tukang Batu 0.0750 Oh 44,000.00 3,300.00
- Mandor 0.0750 Oh 44,000.00 3,300.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 8


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
III. 5 1 m3 Pasang Pondasi batu kali, 1 Pc : 4 Ps 461,450.00
SNI Bahan 380,600.00
03-2836-2008 - Batu Belah 1.2000 M3 117,700.00 141,240.00
- Semen PC ( Portland Cement ) 40 kg 163.0000 Kg 1,100.00 179,300.00
- Pasir pasang (kaliworo) 0.5200 M3 115,500.00 60,060.00

Tenaga 80,850.00
- Pekerja 1.5000 Oh 30,250.00 45,375.00
- Tukang Batu 0.7500 Oh 38,500.00 28,875.00
- Kepala Tukang Batu 0.0750 Oh 44,000.00 3,300.00
- Mandor 0.0750 Oh 44,000.00 3,300.00

III. 6 1 m3 Pasang Pondasi Batu kali 1 Pc : 5 Ps 434,522.00


SNI Bahan 353,672.00
03-2836-2008 - Batu Belah 1.2000 M3 117,700.00 141,240.00
- Semen PC ( Portland Cement ) 40 kg 136.0000 Kg 1,100.00 149,600.00
- Pasir pasang (kaliworo) 0.5440 M3 115,500.00 62,832.00

Tenaga 80,850.00
- Pekerja 1.5000 Oh 30,250.00 45,375.00
- Tukang Batu 0.7500 Oh 38,500.00 28,875.00
- Kepala Tukang Batu 0.0750 Oh 44,000.00 3,300.00
- Mandor 0.0750 Oh 44,000.00 3,300.00

III. 7 1 m3 Pasang Pondasi Batu kali 1 Pc : 6 Ps 415,585.50


SNI Bahan 334,735.50
03-2836-2008 - Batu Belah 1.2000 M3 117,700.00 141,240.00
- Semen PC ( Portland Cement ) 40 kg 117.0000 Kg 1,100.00 128,700.00
- Pasir pasang (kaliworo) 0.5610 M3 115,500.00 64,795.50

Tenaga 80,850.00
- Pekerja 1.5000 Oh 30,250.00 45,375.00
- Tukang Batu 0.7500 Oh 38,500.00 28,875.00
- Kepala Tukang Batu 0.0750 Oh 44,000.00 3,300.00
- Mandor 0.0750 Oh 44,000.00 3,300.00

III. 8 1 m3 Pasang Pondasi Batu kali 1 Pc : 8 Ps 389,642.00


SNI Bahan 308,792.00
03-2836-2008 - Batu Belah 1.2000 M3 117,700.00 141,240.00
- Semen PC ( Portland Cement ) 40 kg 91.0000 Kg 1,100.00 100,100.00
- Pasir pasang (kaliworo) 0.5840 M3 115,500.00 67,452.00

Tenaga 80,850.00
- Pekerja 1.5000 Oh 30,250.00 45,375.00
- Tukang Batu 0.7500 Oh 38,500.00 28,875.00
- Kepala Tukang Batu 0.0750 Oh 44,000.00 3,300.00
- Mandor 0.0750 Oh 44,000.00 3,300.00

III. 9 1 m3 Pasang Pondasi Batu kali 1 Pc : 1/4 Kp : 4 Ps 464,662.00


SNI Bahan 383,812.00
03-2836-2008 - Batu Belah 1.2000 M3 117,700.00 141,240.00
- Semen PC ( Portland Cement ) 40 kg 156.0000 Kg 1,100.00 171,600.00
- Kapur Pasang 0.0320 M3 110,000.00 3,520.00
- Pasir pasang (kaliworo) 0.5840 M3 115,500.00 67,452.00

Tenaga 80,850.00
- Pekerja 1.5000 Oh 30,250.00 45,375.00
- Tukang Batu 0.7500 Oh 38,500.00 28,875.00
- Kepala Tukang Batu 0.0750 Oh 44,000.00 3,300.00
- Mandor 0.0750 Oh 44,000.00 3,300.00

III. 10 1 m3 Pasang Pondasi Batu kali 1 Pc : 3 Kp : 10 Ps 362,186.00


SNI Bahan 281,336.00
03-2836-2008 - Batu Belah 1.2000 M3 117,700.00 141,240.00
- Semen PC ( Portland Cement ) 40 kg 61.0000 Kg 1,100.00 67,100.00
- Kapur Pasang 0.1470 M3 110,000.00 16,170.00
- Pasir pasang (kaliworo) 0.4920 M3 115,500.00 56,826.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 9


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)

Tenaga 80,850.00
- Pekerja 1.5000 Oh 30,250.00 45,375.00
- Tukang Batu 0.7500 Oh 38,500.00 28,875.00
- Kepala Tukang Batu 0.0750 Oh 44,000.00 3,300.00
- Mandor 0.0750 Oh 44,000.00 3,300.00

III. 11 1 m3 Pasang Pondasi Batu kali 1/4 Pc : 1 Kp : 4 Ps 338,426.00


SNI Bahan 257,576.00
03-2836-2008 - Batu Belah 1.2000 M3 117,700.00 141,240.00
- Semen PC ( Portland Cement ) 40 kg 41.0000 Kg 1,100.00 45,100.00
- Kapur Pasang 0.1310 M3 110,000.00 14,410.00
- Pasir pasang (kaliworo) 0.4920 M3 115,500.00 56,826.00

Tenaga 80,850.00
- Pekerja 1.5000 Oh 30,250.00 45,375.00
- Tukang Batu 0.7500 Oh 38,500.00 28,875.00
- Kepala Tukang Batu 0.0750 Oh 44,000.00 3,300.00
- Mandor 0.0750 Oh 44,000.00 3,300.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 10


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
III. 12 1 m3 Pasang Pondasi Batu Kosong 217,021.20
SNI Bahan 174,979.20
03-2836-2008 - Batu Belah 1.2000 m3 117,700.00 141,240.00
- Pasir Urug 0.4320 m3 78,100.00 33,739.20

Tenaga 42,042.00
- Pekerja 0.7800 Oh 30,250.00 23,595.00
- Tukang Batu 0.3900 Oh 38,500.00 15,015.00
- Kepala Tukang Batu 0.0390 Oh 44,000.00 1,716.00
- Mandor 0.0390 Oh 44,000.00 1,716.00

III. 13 1 m3 Pasang Pondasi sumuran diameter 100 cm 485,771.00


SNI Bahan 373,615.00
03-2836-2008 - Batu Belah 0.4500 Kg 117,700.00 52,965.00
- Semen PC ( Portland Cement ) 40 kg 194.0000 Kg 1,100.00 213,400.00
- Pasir beton (muntilan) 0.3120 m3 129,250.00 40,326.00
- Koral Beton 0.4680 m3 143,000.00 66,924.00

Tenaga 112,156.00
- Pekerja 2.4000 Oh 30,250.00 72,600.00
- Tukang Batu 0.8000 Oh 38,500.00 30,800.00
- Kepala Tukang Batu 0.0800 Oh 44,000.00 3,520.00
- Mandor 0.1190 Oh 44,000.00 5,236.00

III. 14 1 m' Pembuatan Tiang pancang ( 40 x 40 ) cm, Beton bertulang 679,276.40


SNI Bahan 618,083.40
03-2836-2002 - Pasir Urug 0.0190 m3 78,100.00 1,483.90
- Pasir beton (muntilan) 0.0940 m3 129,250.00 12,149.50
- Koral Beton 0.1500 m3 143,000.00 21,450.00
- Semen PC ( Portland Cement ) 40 kg 60.5000 kg 1,100.00 66,550.00
- Besi Beton polos 45.0000 kg 8,800.00 396,000.00
- Kawat Beton / Bendrat 0.9000 kg 11,550.00 10,395.00
- Kayu 5/7 meranti 0.0320 m3 3,300,000.00 105,600.00
- Paku usuk 0.1200 kg 11,000.00 1,320.00
- Minyak Begesting 0.0900 lt 16,500.00 1,485.00
- Plamur Tembok 0.2400 kg 6,875.00 1,650.00

Tenaga 61,193.00
- Pekerja 1.0000 Oh 30,250.00 30,250.00
- Tukang Batu 0.6700 Oh 38,500.00 25,795.00
- Kepala Tukang Batu 0.0670 Oh 44,000.00 2,948.00
- Mandor 0.0500 Oh 44,000.00 2,200.00

III. 15 1 m' Pembuatan Tiang pancang ( 35 x 35 ) cm, Beton bertulang 535,739.60


SNI Bahan 488,329.60
03-2836-2002 - Pasir Urug 0.0160 m3 78,100.00 1,249.60
- Pasir beton (muntilan) 0.0800 m3 129,250.00 10,340.00
- Koral Beton 0.1250 m3 143,000.00 17,875.00
- Semen PC ( Portland Cement ) 40 kg 49.0000 kg 1,100.00 53,900.00
- Besi Beton polos 34.5000 kg 8,800.00 303,600.00
- Kawat Beton / Bendrat 0.7000 kg 11,550.00 8,085.00
- Kayu 5/7 meranti 0.0270 m3 3,300,000.00 89,100.00
- Paku usuk 0.1200 kg 11,000.00 1,320.00
- Minyak Begesting 0.0900 lt 16,500.00 1,485.00
- Plamur Tembok 0.2000 kg 6,875.00 1,375.00

Tenaga 47,410.00
- Pekerja 0.8000 oh 30,250.00 24,200.00
- Tukang Batu 0.5000 oh 38,500.00 19,250.00
- Kepala Tukang Batu 0.0500 oh 44,000.00 2,200.00
- Mandor 0.0400 oh 44,000.00 1,760.00

III. 16 1 M3 Membuat bronjong dari kawat galvanis/bronjong 3 mm diisi batu belah 316,781.67
BOW Bahan 218,533.33
G.5a - Kawat Bronjong 8.3333 Kg 12,100.00 100,833.33
- Batu Belah 1.0000 m3 117,700.00 117,700.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 11


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
Tenaga 98,248.33
- Pekerja 1.5000 oh 30,250.00 45,375.00
- Tukang Batu 0.7333 oh 38,500.00 28,233.33
- Kepala Tukang Batu 0.5333 oh 44,000.00 23,466.67
- Mandor 0.0267 oh 44,000.00 1,173.33

III. 17 1 M3 Membuat bronjong dari kawat galvanis/bronjong 4 mm diisi batu belah 400,381.67
BOW Bahan 299,200.00
G.5b - Kawat Bronjong 15.0000 Kg 12,100.00 181,500.00
- Batu Belah 1.0000 m3 117,700.00 117,700.00

Tenaga 101,181.67
- Pekerja 1.5000 oh 30,250.00 45,375.00
- Tukang Batu 0.7333 oh 38,500.00 28,233.33
- Kepala Tukang Batu 0.6000 oh 44,000.00 26,400.00
- Mandor 0.0267 oh 44,000.00 1,173.33

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 12


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
III. 18 1 M3 Membuat bronjong dari kawat galvanis/bronjong 5 mm diisi batu belah 507,998.33
BOW Bahan 400,033.33
G.5b - Kawat Bronjong 23.3333 Kg 12,100.00 282,333.33
- Batu Belah 1.0000 m3 117,700.00 117,700.00

Tenaga 107,965.00
- Pekerja 1.5000 oh 30,250.00 45,375.00
- Tukang Batu 0.8333 oh 38,500.00 32,083.33
- Kepala Tukang Batu 0.6667 oh 44,000.00 29,333.33
- Mandor 0.0267 oh 44,000.00 1,173.33

IV. PEKERJAAN DINDING


IV.1 1 M2 Pasangan bata merah tebal 1 bata, 1 Pc : 1 Ps 173,057.50
SNI Bahan 145,007.50
03-6897-2008 - Batu Bata lokal 140.0000 Bh 484.00 67,760.00
- Semen PC ( Portland Cement ) 40 kg 64.0300 Kg 1,100.00 70,433.00
- Pasir pasang (kaliworo) 0.0590 M3 115,500.00 6,814.50

Tenaga 28,050.00
- Pekerja 0.6000 Oh 30,250.00 18,150.00
- Tukang Batu 0.2000 Oh 38,500.00 7,700.00
- Kepala Tukang Batu 0.0200 Oh 44,000.00 880.00
- Mandor 0.0300 Oh 44,000.00 1,320.00

IV.2 1 M2 Pasangan bata merah tebal 1 bata, 1 Pc : 2 Ps 152,900.00


SNI Bahan 124,850.00
03-6897-2008 - Batu Bata lokal 140.0000 Bh 484.00 67,760.00
- Semen PC ( Portland Cement ) 40 kg 43.5000 Kg 1,100.00 47,850.00
- Pasir pasang (kaliworo) 0.0800 M3 115,500.00 9,240.00

Tenaga 28,050.00
- Pekerja 0.6000 Oh 30,250.00 18,150.00
- Tukang Batu 0.2000 Oh 38,500.00 7,700.00
- Kepala Tukang Batu 0.0200 Oh 44,000.00 880.00
- Mandor 0.0300 Oh 44,000.00 1,320.00

IV. 3 1 M2 Pasangan bata merah tebal 1 bata, 1 Pc : 3 Ps 142,565.50


SNI Bahan 114,515.50
03-6897-2008 - Batu Bata lokal 140.0000 Bh 484.00 67,760.00
- Semen PC ( Portland Cement ) 40 kg 32.9500 Kg 1,100.00 36,245.00
- Pasir pasang (kaliworo) 0.0910 M3 115,500.00 10,510.50

Tenaga 28,050.00
- Pekerja 0.6000 Oh 30,250.00 18,150.00
- Tukang Batu 0.2000 Oh 38,500.00 7,700.00
- Kepala Tukang Batu 0.0200 Oh 44,000.00 880.00
- Mandor 0.0300 Oh 44,000.00 1,320.00

IV. 4 1 M2 Pasangan bata merah tebal 1 bata, 1 Pc : 4 Ps 135,756.50


SNI Bahan 107,706.50
03-6897-2008 - Batu Bata lokal 140.0000 Bh 484.00 67,760.00
- Semen PC ( Portland Cement ) 40 kg 26.5500 Kg 1,100.00 29,205.00
- Pasir pasang (kaliworo) 0.0930 M3 115,500.00 10,741.50

Tenaga 28,050.00
- Pekerja 0.6000 Oh 30,250.00 18,150.00
- Tukang Batu 0.2000 Oh 38,500.00 7,700.00
- Kepala Tukang Batu 0.0200 Oh 44,000.00 880.00
- Mandor 0.0300 Oh 44,000.00 1,320.00

IV. 5 1 M2 Pasangan bata merah tebal 1 bata, 1 Pc : 5 Ps 132,011.00


SNI Bahan 103,961.00
03-6897-2008 - Batu Bata lokal 140.0000 Bh 484.00 67,760.00
- Semen PC ( Portland Cement ) 40 kg 22.2000 Kg 1,100.00 24,420.00
- Pasir pasang (kaliworo) 0.1020 M3 115,500.00 11,781.00

Tenaga 28,050.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 13


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
- Pekerja 0.6000 Oh 30,250.00 18,150.00
- Tukang Batu 0.2000 Oh 38,500.00 7,700.00
- Kepala Tukang Batu 0.0200 Oh 44,000.00 880.00
- Mandor 0.0300 Oh 44,000.00 1,320.00

IV. 6 1 M2 Pasangan bata merah tebal 1 bata, 1 Pc : 6 Ps 130,251.00


SNI Bahan 102,201.00
03-6897-2008 - Batu Bata lokal 140.0000 Bh 484.00 67,760.00
- Semen PC ( Portland Cement ) 40 kg 18.5000 Kg 1,100.00 20,350.00
- Pasir pasang (kaliworo) 0.1220 M3 115,500.00 14,091.00

Tenaga 28,050.00
- Pekerja 0.6000 Oh 30,250.00 18,150.00
- Tukang Batu 0.2000 Oh 38,500.00 7,700.00
- Kepala Tukang Batu 0.0200 Oh 44,000.00 880.00
- Mandor 0.0300 Oh 44,000.00 1,320.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 14


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
IV. 7 1 M2 Pasangan bata merah tebal 1 bata, 1 Pc : 3 Kp : 10 Ps 120,606.75
SNI Bahan 92,556.75
03-6897-2008 - Batu Bata lokal 140.0000 Bh 484.00 67,760.00
- Semen PC ( Portland Cement ) 40 kg 10.0800 Kg 1,100.00 11,088.00
- Pasir pasang (kaliworo) 0.0925 M3 115,500.00 10,683.75
- Kapur Pasang 0.0275 M3 110,000.00 3,025.00

Tenaga 28,050.00
- Pekerja 0.6000 Oh 30,250.00 18,150.00
- Tukang Batu 0.2000 Oh 38,500.00 7,700.00
- Kepala Tukang Batu 0.0200 Oh 44,000.00 880.00
- Mandor 0.0300 Oh 44,000.00 1,320.00

IV. 8 1 M2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 1 Ps 81,719.00


SNI Bahan 67,694.00
03-6897-2008 - Batu Bata lokal 70.0000 Bh 484.00 33,880.00
- Semen PC ( Portland Cement ) 40 kg 27.8000 Kg 1,100.00 30,580.00
- Pasir pasang (kaliworo) 0.0280 M3 115,500.00 3,234.00

Tenaga 14,025.00
- Pekerja 0.3000 Oh 30,250.00 9,075.00
- Tukang Batu 0.1000 Oh 38,500.00 3,850.00
- Kepala Tukang Batu 0.0100 Oh 44,000.00 440.00
- Mandor 0.0150 Oh 44,000.00 660.00

IV. 9 1 M2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 2 Ps 73,139.00


SNI Bahan 59,114.00
03-6897-2008 - Batu Bata lokal 70.0000 Bh 484.00 33,880.00
- Semen PC ( Portland Cement ) 40 kg 18.9500 Kg 1,100.00 20,845.00
- Pasir pasang (kaliworo) 0.0380 M3 115,500.00 4,389.00

Tenaga 14,025.00
- Pekerja 0.3000 Oh 30,250.00 9,075.00
- Tukang Batu 0.1000 Oh 38,500.00 3,850.00
- Kepala Tukang Batu 0.0100 Oh 44,000.00 440.00
- Mandor 0.0150 Oh 44,000.00 660.00

IV. 10 1 M2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 3 Ps 68,332.00


SNI Bahan 54,307.00
03-6897-2008 - Batu Bata lokal 70.0000 Bh 484.00 33,880.00
- Semen PC ( Portland Cement ) 40 kg 14.3700 Kg 1,100.00 15,807.00
- Pasir pasang (kaliworo) 0.0400 M3 115,500.00 4,620.00

Tenaga 14,025.00
- Pekerja 0.3000 Oh 30,250.00 9,075.00
- Tukang Batu 0.1000 Oh 38,500.00 3,850.00
- Kepala Tukang Batu 0.0100 Oh 44,000.00 440.00
- Mandor 0.0150 Oh 44,000.00 660.00

IV. 11 1 M2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 4 Ps 65,521.50


SNI Bahan 51,496.50
03-6897-2008 - Batu Bata lokal 70.0000 Bh 484.00 33,880.00
- Semen PC ( Portland Cement ) 40 kg 11.5000 Kg 1,100.00 12,650.00
- Pasir pasang (kaliworo) 0.0430 M3 115,500.00 4,966.50

Tenaga 14,025.00
- Pekerja 0.3000 Oh 30,250.00 9,075.00
- Tukang Batu 0.1000 Oh 38,500.00 3,850.00
- Kepala Tukang Batu 0.0100 Oh 44,000.00 440.00
- Mandor 0.0150 Oh 44,000.00 660.00

IV. 12 1 M2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 5 Ps 63,750.50


SNI Bahan 49,725.50
03-6897-2008 - Batu Bata lokal 70.0000 Bh 484.00 33,880.00
- Semen PC ( Portland Cement ) 40 kg 9.6800 Kg 1,100.00 10,648.00
- Pasir pasang (kaliworo) 0.0450 M3 115,500.00 5,197.50

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 15


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
Tenaga 14,025.00
- Pekerja 0.3000 Oh 30,250.00 9,075.00
- Tukang Batu 0.1000 Oh 38,500.00 3,850.00
- Kepala Tukang Batu 0.0100 Oh 44,000.00 440.00
- Mandor 0.0150 Oh 44,000.00 660.00

IV. 13 1 M2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 6 Ps 62,716.50


SNI Bahan 48,691.50
03-6897-2008 - Batu Bata lokal 70.0000 Bh 484.00 33,880.00
- Semen PC ( Portland Cement ) 40 kg 8.3200 Kg 1,100.00 9,152.00
- Pasir pasang (kaliworo) 0.0490 M3 115,500.00 5,659.50

Tenaga 14,025.00
- Pekerja 0.3000 Oh 30,250.00 9,075.00
- Tukang Batu 0.1000 Oh 38,500.00 3,850.00
- Kepala Tukang Batu 0.0100 Oh 44,000.00 440.00
- Mandor 0.0150 Oh 44,000.00 660.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 16


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
IV. 14 1 M2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 8 Ps 60,830.00
SNI Bahan 46,805.00
03-6897-2008 - Batu Bata lokal 70.0000 Bh 484.00 33,880.00
- Semen PC ( Portland Cement ) 40 kg 6.5000 Kg 1,100.00 7,150.00
- Pasir pasang (kaliworo) 0.0500 M3 115,500.00 5,775.00

Tenaga 14,025.00
- Pekerja 0.3000 Oh 30,250.00 9,075.00
- Tukang Batu 0.1000 Oh 38,500.00 3,850.00
- Kepala Tukang Batu 0.0100 Oh 44,000.00 440.00
- Mandor 0.0150 Oh 44,000.00 660.00

IV. 15 1 M2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 3 Kp : 10 Ps 60,280.00


SNI Bahan 46,255.00
03-6897-2008 - Batu Bata lokal 70.0000 Bh 484.00 33,880.00
- Semen PC ( Portland Cement ) 40 kg 4.5000 Kg 1,100.00 4,950.00
- Pasir pasang (kaliworo) 0.0500 M3 115,500.00 5,775.00
- Kapur Pasang 0.0150 M3 110,000.00 1,650.00

Tenaga 14,025.00
- Pekerja 0.3000 Oh 30,250.00 9,075.00
- Tukang Batu 0.1000 Oh 38,500.00 3,850.00
- Kepala Tukang Batu 0.0100 Oh 44,000.00 440.00
- Mandor 0.0150 Oh 44,000.00 660.00

IV. 16 1 M2 pasang dinding roster/terawang (12x11x24) cm, 1Pc : 3 Ps 132,121.00


SNI Bahan 118,096.00
03-6897-2008 - Roster 25/25 30.0000 Bh 3,300.00 99,000.00
- Semen PC ( Portland Cement ) 40 kg 14.0000 Kg 1,100.00 15,400.00
- Pasir pasang (kaliworo) 0.0320 M3 115,500.00 3,696.00

Tenaga 14,025.00
- Pekerja 0.3000 Oh 30,250.00 9,075.00
- Tukang Batu 0.1000 Oh 38,500.00 3,850.00
- Kepala Tukang Batu 0.0100 Oh 44,000.00 440.00
- Mandor 0.0150 Oh 44,000.00 660.00

IV. 17 1 M2 Pasang dinding bataco 60,885.00


SNI Bahan 40,370.00
03-2837-2002 - Batako 12.5000 Bh 1,760.00 22,000.00
- Semen PC ( Portland Cement ) 40 kg 12.5000 Kg 1,100.00 13,750.00
- Pasir pasang (kaliworo) 0.0400 M3 115,500.00 4,620.00

Tenaga 20,515.00
- Pekerja 0.5000 Oh 30,250.00 15,125.00
- Tukang Batu 0.1000 Oh 38,500.00 3,850.00
- Kepala Tukang Batu 0.0100 Oh 44,000.00 440.00
- Mandor 0.0250 Oh 44,000.00 1,100.00

V. PEKERJAAN PLESTERAN
V. 1 1 M2 Plesteran 1 Pc : 1 Ps, tebal 15 mm 35,072.40
SNI Bahan 18,902.40
03-2837-2008 - Semen PC ( Portland Cement ) 40 kg 15.5040 Kg 1,100.00 17,054.40
- Pasir pasang (kaliworo) 0.0160 M3 115,500.00 1,848.00

Tenaga 16,170.00
- Pekerja 0.3000 Oh 30,250.00 9,075.00
- Tukang Batu 0.1500 Oh 38,500.00 5,775.00
- Kepala Tukang Batu 0.0150 Oh 44,000.00 660.00
- Mandor 0.0150 Oh 44,000.00 660.00

V. 2 1 M2 Plesteran 1 Pc : 2 Ps, tebal 15 mm 29,726.40


SNI Bahan 13,556.40
03-2837-2008 - Semen PC ( Portland Cement ) 40 kg 10.2240 Kg 1,100.00 11,246.40
- Pasir pasang (kaliworo) 0.0200 M3 115,500.00 2,310.00

Tenaga 16,170.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 17


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
- Pekerja 0.3000 Oh 30,250.00 9,075.00
- Tukang Batu 0.1500 Oh 38,500.00 5,775.00
- Kepala Tukang Batu 0.0150 Oh 44,000.00 660.00
- Mandor 0.0150 Oh 44,000.00 660.00

V. 3 1 M2 Plesteran 1 Pc : 3 Ps, tebal 15 mm 27,380.10


SNI Bahan 11,210.10
03-2837-2008 - Semen PC ( Portland Cement ) 40 kg 7.7760 Kg 1,100.00 8,553.60
- Pasir pasang (kaliworo) 0.0230 M3 115,500.00 2,656.50

Tenaga 16,170.00
- Pekerja 0.3000 Oh 30,250.00 9,075.00
- Tukang Batu 0.1500 Oh 38,500.00 5,775.00
- Kepala Tukang Batu 0.0150 Oh 44,000.00 660.00
- Mandor 0.0150 Oh 44,000.00 660.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 18


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
V. 4 1 M2 Plesteran 1 Pc : 4 Ps, tebal 15 mm 25,806.00
SNI Bahan 9,636.00
03-2837-2008 - Semen PC ( Portland Cement ) 40 kg 6.2400 Kg 1,100.00 6,864.00
- Pasir pasang (kaliworo) 0.0240 M3 115,500.00 2,772.00

Tenaga 16,170.00
- Pekerja 0.3000 Oh 30,250.00 9,075.00
- Tukang Batu 0.1500 Oh 38,500.00 5,775.00
- Kepala Tukang Batu 0.0150 Oh 44,000.00 660.00
- Mandor 0.0150 Oh 44,000.00 660.00

V. 5 1 M2 Plesteran 1 Pc : 5 Ps, tebal 15 mm 24,875.40


SNI Bahan 8,705.40
03-2837-2008 - Semen PC ( Portland Cement ) 40 kg 5.1840 Kg 1,100.00 5,702.40
- Pasir pasang (kaliworo) 0.0260 M3 115,500.00 3,003.00

Tenaga 16,170.00
- Pekerja 0.3000 Oh 30,250.00 9,075.00
- Tukang Batu 0.1500 Oh 38,500.00 5,775.00
- Kepala Tukang Batu 0.0150 Oh 44,000.00 660.00
- Mandor 0.0150 Oh 44,000.00 660.00

V. 6 1 M2 Plesteran 1 Pc : 6 Ps, tebal 15 mm 24,146.10


SNI Bahan 7,976.10
03-2837-2008 - Semen PC ( Portland Cement ) 40 kg 4.4160 Kg 1,100.00 4,857.60
- Pasir pasang (kaliworo) 0.0270 M3 115,500.00 3,118.50

Tenaga 16,170.00
- Pekerja 0.3000 Oh 30,250.00 9,075.00
- Tukang Batu 0.1500 Oh 38,500.00 5,775.00
- Kepala Tukang Batu 0.0150 Oh 44,000.00 660.00
- Mandor 0.0150 Oh 44,000.00 660.00

V. 7 1 M2 Plesteran 1 Pc : 8 Ps, tebal 15 mm 23,321.10


SNI Bahan 7,151.10
03-2837-2008 - Semen PC ( Portland Cement ) 40 kg 3.4560 Kg 1,100.00 3,801.60
- Pasir pasang (kaliworo) 0.0290 M3 115,500.00 3,349.50

Tenaga 16,170.00
- Pekerja 0.3000 Oh 30,250.00 9,075.00
- Tukang Batu 0.1500 Oh 38,500.00 5,775.00
- Kepala Tukang Batu 0.0150 Oh 44,000.00 660.00
- Mandor 0.0150 Oh 44,000.00 660.00

V. 8 1 M2 Plesteran 1 Pc : 2 Kp : 8 Ps, tebal 15 mm 22,990.00


SNI Bahan 6,160.00
03-2837-2008 - Semen PC ( Portland Cement ) 40 kg 3.0000 Kg 1,100.00 3,300.00
- Kapur Pasang 0.0050 M3 110,000.00 550.00
- Pasir pasang (kaliworo) 0.0200 M3 115,500.00 2,310.00

Tenaga 16,830.00
- Pekerja 0.3600 Oh 30,250.00 10,890.00
- Tukang Batu 0.1200 Oh 38,500.00 4,620.00
- Kepala Tukang Batu 0.0120 Oh 44,000.00 528.00
- Mandor 0.0180 Oh 44,000.00 792.00

V. 9 1 M2 Plesteran 1 Pc : 2 Ps, tebal 20 mm 39,761.70


SNI Bahan 18,113.70
03-2837-2008 - Semen PC ( Portland Cement ) 40 kg 13.6320 Kg 1,100.00 14,995.20
- Pasir pasang (kaliworo) 0.0270 M3 115,500.00 3,118.50

Tenaga 21,648.00
- Pekerja 0.4000 Oh 30,250.00 12,100.00
- Tukang Batu 0.2000 Oh 38,500.00 7,700.00
- Kepala Tukang Batu 0.0200 Oh 44,000.00 880.00
- Mandor 0.0220 Oh 44,000.00 968.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 19


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
V. 10 1 M2 Plesteran 1 Pc : 3 Ps, tebal 20 mm 36,633.30
SNI Bahan 14,985.30
03-2837-2008 - Semen PC ( Portland Cement ) 40 kg 10.3680 Kg 1,100.00 11,404.80
- Pasir pasang (kaliworo) 0.0310 M3 115,500.00 3,580.50

Tenaga 21,648.00
- Pekerja 0.4000 Oh 30,250.00 12,100.00
- Tukang Batu 0.2000 Oh 38,500.00 7,700.00
- Kepala Tukang Batu 0.0200 Oh 44,000.00 880.00
- Mandor 0.0220 Oh 44,000.00 968.00

V. 11 1 M2 Plesteran 1 Pc : 4 Ps, tebal 20 mm 34,496.00


SNI Bahan 12,848.00
03-2837-2008 - Semen PC ( Portland Cement ) 40 kg 8.3200 Kg 1,100.00 9,152.00
- Pasir pasang (kaliworo) 0.0320 M3 115,500.00 3,696.00

Tenaga 21,648.00
- Pekerja 0.4000 Oh 30,250.00 12,100.00
- Tukang Batu 0.2000 Oh 38,500.00 7,700.00
- Kepala Tukang Batu 0.0200 Oh 44,000.00 880.00
- Mandor 0.0220 Oh 44,000.00 968.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 20


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
V. 12 1 M2 Plesteran 1 Pc : 5 Ps, tebal 20 mm 33,293.70
SNI Bahan 11,645.70
03-2837-2008 - Semen PC ( Portland Cement ) 40 kg 6.9120 Kg 1,100.00 7,603.20
- Pasir pasang (kaliworo) 0.0350 M3 115,500.00 4,042.50
Tenaga 21,648.00
- Pekerja 0.4000 Oh 30,250.00 12,100.00
- Tukang Batu 0.2000 Oh 38,500.00 7,700.00
- Kepala Tukang Batu 0.0200 Oh 44,000.00 880.00
- Mandor 0.0220 Oh 44,000.00 968.00

V. 13 1 M2 Plesteran 1 Pc : 6 Ps, tebal 20 mm 32,282.80


SNI Bahan 10,634.80
03-2837-2008 - Semen PC ( Portland Cement ) 40 kg 5.8880 Kg 1,100.00 6,476.80
- Pasir pasang (kaliworo) 0.0360 M3 115,500.00 4,158.00

Tenaga 21,648.00
- Pekerja 0.4000 Oh 30,250.00 12,100.00
- Tukang Batu 0.2000 Oh 38,500.00 7,700.00
- Kepala Tukang Batu 0.0200 Oh 44,000.00 880.00
- Mandor 0.0220 Oh 44,000.00 968.00

V. 14 1 M2 Plesteran Beton 1 Pc : 2 Ps, tebal 15 mm 29,326.00


SNI Bahan 12,309.00
03-2837-2002 - Semen PC ( Portland Cement ) 40 kg 9.3000 Kg 1,100.00 10,230.00
- Pasir pasang (kaliworo) 0.0180 M3 115,500.00 2,079.00

Tenaga 17,017.00
- Pekerja 0.2600 Oh 30,250.00 7,865.00
- Tukang Batu 0.2000 Oh 38,500.00 7,700.00
- Kepala Tukang Batu 0.0200 Oh 44,000.00 880.00
- Mandor 0.0130 Oh 44,000.00 572.00

V. 15 1 M2 Plesteran Beton 1 Pc : 3 Ps, tebal 15 mm 27,219.50


SNI Bahan 10,202.50
03-2837-2002 - Semen PC ( Portland Cement ) 40 kg 7.0700 Kg 1,100.00 7,777.00
- Pasir pasang (kaliworo) 0.0210 M3 115,500.00 2,425.50

Tenaga 17,017.00
- Pekerja 0.2600 Oh 30,250.00 7,865.00
- Tukang Batu 0.2000 Oh 38,500.00 7,700.00
- Kepala Tukang Batu 0.0200 Oh 44,000.00 880.00
- Mandor 0.0130 Oh 44,000.00 572.00

V. 16 1 M' Plesteran Skoning 1 Pc : 2 Ps lebar 10 cm' 21,807.50


SNI Bahan 2,051.50
03-2837-2008 - Semen PC ( Portland Cement ) 40 kg 0.5000 Kg 1,100.00 550.00
- Pasir pasang (kaliworo) 0.0130 M3 115,500.00 1,501.50

Tenaga 19,756.00
- Pekerja 0.0800 Oh 30,250.00 2,420.00
- Tukang Batu 0.4000 Oh 38,500.00 15,400.00
- Kepala Tukang Batu 0.0400 Oh 44,000.00 1,760.00
- Mandor 0.0040 Oh 44,000.00 176.00

V. 17 1 M2 Plesteran Ciprat 1 Pc : 2 Ps 19,470.00


SNI Bahan 5,445.00
03-2837-2008 - Semen PC ( Portland Cement ) 40 kg 4.3200 Kg 1,100.00 4,752.00
- Pasir pasang (kaliworo) 0.0060 M3 115,500.00 693.00

Tenaga 14,025.00
- Pekerja 0.3000 Oh 30,250.00 9,075.00
- Tukang Batu 0.1000 Oh 38,500.00 3,850.00
- Kepala Tukang Batu 0.0100 Oh 44,000.00 440.00
- Mandor 0.0150 Oh 44,000.00 660.00

V. 18 1 M2 Plesteran Siar Pasangan Batu Kali, adukan 1 PC : 2 PS 24,530.00


SNI Bahan 8,360.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 21


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
03-2837-2008 - Semen PC ( Portland Cement ) 40 kg 6.3400 Kg 1,100.00 6,974.00
- Pasir pasang (kaliworo) 0.0120 M3 115,500.00 1,386.00

Tenaga 16,170.00
- Pekerja 0.3000 Oh 30,250.00 9,075.00
- Tukang Batu 0.1500 Oh 38,500.00 5,775.00
- Kepala Tukang Batu 0.0150 Oh 44,000.00 660.00
- Mandor 0.0150 Oh 44,000.00 660.00

V. 19 1 M' Sponengan ( untuk saluran dan sejenisnya ) 4,707.45


BOW Bahan 499.95
G.50b - Semen PC ( Portland Cement ) 40 kg 0.3600 Kg 1,100.00 396.00
- Pasir pasang (kaliworo) 0.0009 M3 115,500.00 103.95

Tenaga 4,207.50
- Pekerja 0.0900 Oh 30,250.00 2,722.50
- Tukang Batu 0.0300 Oh 38,500.00 1,155.00
- Kepala Tukang Batu 0.0030 Oh 44,000.00 132.00
- Mandor 0.0045 Oh 44,000.00 198.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 22


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
V. 20 1 M2 Acian 14,355.00
SNI Bahan 3,575.00
03-2837-2008 - Semen PC ( Portland Cement ) 40 kg 3.2500 Kg 1,100.00 3,575.00

Tenaga 10,780.00
- Pekerja 0.2000 Oh 30,250.00 6,050.00
- Tukang Batu 0.1000 Oh 38,500.00 3,850.00
- Kepala Tukang Batu 0.0100 Oh 44,000.00 440.00
- Mandor 0.0100 Oh 44,000.00 440.00

VI. PEKERJAAN KAYU


VI. 1 1 M3 Pasang kusen pintu dan jendela kayu jati lokal 8,911,650.00
SNI Bahan 7,944,750.00
03-3434-2008 - Kayu jati lokal 1.2000 M3 6,600,000.00 7,920,000.00
- Paku usuk 1.2500 kg 11,000.00 13,750.00
- Lem kayu "fox" 1.0000 kg 11,000.00 11,000.00

Tenaga 966,900.00
- Pekerja 6.0000 Oh 30,250.00 181,500.00
- Tukang Kayu 18.0000 Oh 38,500.00 693,000.00
- Kepala Tukang Kayu 1.8000 Oh 44,000.00 79,200.00
- Mandor 0.3000 Oh 44,000.00 13,200.00

VI. 2 1 M3 Pasang kusen pintu dan jendela kayu kamper 9,571,650.00


SNI Bahan 8,604,750.00
03-3434-2008 - Kayu Kamper 1.2000 M3 7,150,000.00 8,580,000.00
- Paku usuk 1.2500 kg 11,000.00 13,750.00
- Lem kayu "fox" 1.0000 kg 11,000.00 11,000.00

Tenaga 966,900.00
- Pekerja 6.0000 Oh 30,250.00 181,500.00
- Tukang Kayu 18.0000 Oh 38,500.00 693,000.00
- Kepala Tukang Kayu 1.8000 Oh 44,000.00 79,200.00
- Mandor 0.3000 Oh 44,000.00 13,200.00

VI. 3 1 M3 Pasang kusen pintu dan jendela kayu meranti 4,951,650.00


SNI Bahan 3,984,750.00
03-3434-2008 - Kayu meranti 1.2000 M3 3,300,000.00 3,960,000.00
- Paku usuk 1.2500 kg 11,000.00 13,750.00
- Lem kayu "fox" 1.0000 kg 11,000.00 11,000.00

Tenaga 966,900.00
- Pekerja 6.0000 Oh 30,250.00 181,500.00
- Tukang Kayu 18.0000 Oh 38,500.00 693,000.00
- Kepala Tukang Kayu 1.8000 Oh 44,000.00 79,200.00
- Mandor 0.3000 Oh 44,000.00 13,200.00

VI. 4 1 M3 Pasang kusen pintu dan jendela kayu kruing 6,931,650.00


SNI Bahan 5,964,750.00
03-3434-2008 - Kayu kruing 1.2000 M3 4,950,000.00 5,940,000.00
- Paku usuk 1.2500 kg 11,000.00 13,750.00
- Lem kayu "fox" 1.0000 kg 11,000.00 11,000.00

Tenaga 966,900.00
- Pekerja 6.0000 Oh 30,250.00 181,500.00
- Tukang Kayu 18.0000 Oh 38,500.00 693,000.00
- Kepala Tukang Kayu 1.8000 Oh 44,000.00 79,200.00
- Mandor 0.3000 Oh 44,000.00 13,200.00

VI. 5 1 M3 Pasang kusen pintu dan jendela kayu bengkirai 11,353,650.00


SNI Bahan 10,386,750.00
03-3434-2008 - Kayu bengkirai 1.2000 M3 8,635,000.00 10,362,000.00
- Paku usuk 1.2500 kg 11,000.00 13,750.00
- Lem kayu "fox" 1.0000 kg 11,000.00 11,000.00

Tenaga 966,900.00
- Pekerja 6.0000 Oh 30,250.00 181,500.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 23


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
- Tukang Kayu 18.0000 Oh 38,500.00 693,000.00
- Kepala Tukang Kayu 1.8000 Oh 44,000.00 79,200.00
- Mandor 0.3000 Oh 44,000.00 13,200.00

VI. 6 1 M2 Pasang pintu klam kayu kamper 386,974.50


SNI Bahan 330,550.00
03-3434-2008 - Papan kayu kamper 0.0400 M3 8,250,000.00 330,000.00
- Paku reng 0.0500 Kg 11,000.00 550.00

Tenaga 56,424.50
- Pekerja 0.3500 Oh 30,250.00 10,587.50
- Tukang Kayu 1.0500 Oh 38,500.00 40,425.00
- Kepala Tukang Kayu 0.1050 Oh 44,000.00 4,620.00
- Mandor 0.0180 Oh 44,000.00 792.00

VI. 7 1 M2 Pasang pintu klam kayu meranti 206,574.50


SNI Bahan 150,150.00
03-3434-2008 - Papan kayu meranti 0.0400 M3 3,740,000.00 149,600.00
- Paku reng 0.0500 Kg 11,000.00 550.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 24


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
Tenaga 56,424.50
- Pekerja 0.3500 Oh 30,250.00 10,587.50
- Tukang Kayu 1.0500 Oh 38,500.00 40,425.00
- Kepala Tukang Kayu 0.1050 Oh 44,000.00 4,620.00
- Mandor 0.0180 Oh 44,000.00 792.00

VI. 8 1 M2 Pasang pintu panel kayu jati lokal 452,650.00


SNI Bahan 291,500.00
03-3434-2008 - Papan kayu jati lokal 0.0400 M3 7,150,000.00 286,000.00
- Lem kayu "fox" 0.5000 kg 11,000.00 5,500.00

Tenaga 161,150.00
- Pekerja 1.0000 Oh 30,250.00 30,250.00
- Tukang Kayu 3.0000 Oh 38,500.00 115,500.00
- Kepala Tukang Kayu 0.3000 Oh 44,000.00 13,200.00
- Mandor 0.0500 Oh 44,000.00 2,200.00
VI. 9 1 M2 Pasang pintu panel kayu kamper 496,650.00
SNI Bahan 335,500.00
03-3434-2008 - Papan kayu kamper 0.0400 M3 8,250,000.00 330,000.00
- Lem kayu "fox" 0.5000 kg 11,000.00 5,500.00

Tenaga 161,150.00
- Pekerja 1.0000 Oh 30,250.00 30,250.00
- Tukang Kayu 3.0000 Oh 38,500.00 115,500.00
- Kepala Tukang Kayu 0.3000 Oh 44,000.00 13,200.00
- Mandor 0.0500 Oh 44,000.00 2,200.00

VI. 10 1 M2 Pasang pintu panel kayu meranti 316,250.00


SNI Bahan 155,100.00
03-3434-2008 - Papan kayu meranti 0.0400 M3 3,740,000.00 149,600.00
- Lem kayu "fox" 0.5000 kg 11,000.00 5,500.00

Tenaga 161,150.00
- Pekerja 1.0000 Oh 30,250.00 30,250.00
- Tukang Kayu 3.0000 Oh 38,500.00 115,500.00
- Kepala Tukang Kayu 0.3000 Oh 44,000.00 13,200.00
- Mandor 0.0500 Oh 44,000.00 2,200.00

VI. 11 1 M2 Pasang pintu panel kayu kruing 386,650.00


SNI Bahan 225,500.00
03-3434-2008 - Papan kayu kruing 0.0400 M3 5,500,000.00 220,000.00
- Lem kayu "fox" 0.5000 kg 11,000.00 5,500.00

Tenaga 161,150.00
- Pekerja 1.0000 Oh 30,250.00 30,250.00
- Tukang Kayu 3.0000 Oh 38,500.00 115,500.00
- Kepala Tukang Kayu 0.3000 Oh 44,000.00 13,200.00
- Mandor 0.0500 Oh 44,000.00 2,200.00

VI. 12 1 M2 Pasang pintu panel kayu bengkirai 562,650.00


SNI Bahan 401,500.00
03-3434-2008 - Papan kayu bengkirai 0.0400 M3 9,900,000.00 396,000.00
- Lem kayu "fox" 0.5000 kg 11,000.00 5,500.00

Tenaga 161,150.00
- Pekerja 1.0000 Oh 30,250.00 30,250.00
- Tukang Kayu 3.0000 Oh 38,500.00 115,500.00
- Kepala Tukang Kayu 0.3000 Oh 44,000.00 13,200.00
- Mandor 0.0500 Oh 44,000.00 2,200.00

VI. 13 1 M2 Pasang pintu dan jendela kaca kayu jati lokal 303,820.00
SNI Bahan 174,900.00
03-3434-2008 - Papan kayu jati lokal 0.0240 M3 7,150,000.00 171,600.00
- Lem kayu "fox" 0.3000 kg 11,000.00 3,300.00

Tenaga 128,920.00
- Pekerja 0.8000 Oh 30,250.00 24,200.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 25


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
- Tukang Kayu 2.4000 Oh 38,500.00 92,400.00
- Kepala Tukang Kayu 0.2400 Oh 44,000.00 10,560.00
- Mandor 0.0400 Oh 44,000.00 1,760.00

VI. 14 1 M2 Pasang pintu dan jendela kaca kayu kamper 330,220.00


SNI Bahan 201,300.00
03-3434-2008 - Papan kayu kamper 0.0240 M3 8,250,000.00 198,000.00
- Lem kayu "fox" 0.3000 kg 11,000.00 3,300.00

Tenaga 128,920.00
- Pekerja 0.8000 Oh 30,250.00 24,200.00
- Tukang Kayu 2.4000 Oh 38,500.00 92,400.00
- Kepala Tukang Kayu 0.2400 Oh 44,000.00 10,560.00
- Mandor 0.0400 Oh 44,000.00 1,760.00

VI. 15 1 M2 Pasang pintu dan jendela kaca kayu meranti 221,980.00


SNI Bahan 93,060.00
03-3434-2008 - Papan kayu meranti 0.0240 M3 3,740,000.00 89,760.00
- Lem kayu "fox" 0.3000 kg 11,000.00 3,300.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 26


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
Tenaga 128,920.00
- Pekerja 0.8000 Oh 30,250.00 24,200.00
- Tukang Kayu 2.4000 Oh 38,500.00 92,400.00
- Kepala Tukang Kayu 0.2400 Oh 44,000.00 10,560.00
- Mandor 0.0400 Oh 44,000.00 1,760.00

VI. 16 1 M2 Pasang pintu dan jendela kaca kayu kruing 264,220.00


SNI Bahan 135,300.00
03-3434-2008 - Papan kayu kruing 0.0240 M3 5,500,000.00 132,000.00
- Lem kayu "fox" 0.3000 kg 11,000.00 3,300.00

Tenaga 128,920.00
- Pekerja 0.8000 Oh 30,250.00 24,200.00
- Tukang Kayu 2.4000 Oh 38,500.00 92,400.00
- Kepala Tukang Kayu 0.2400 Oh 44,000.00 10,560.00
- Mandor 0.0400 Oh 44,000.00 1,760.00

VI. 17 1 M2 Pasang pintu dan jendela kaca kayu bengkirai 369,820.00


SNI Bahan 240,900.00
03-3434-2008 - Papan kayu bengkirai 0.0240 M3 9,900,000.00 237,600.00
- Lem kayu "fox" 0.3000 kg 11,000.00 3,300.00

Tenaga 128,920.00
- Pekerja 0.8000 Oh 30,250.00 24,200.00
- Tukang Kayu 2.4000 Oh 38,500.00 92,400.00
- Kepala Tukang Kayu 0.2400 Oh 44,000.00 10,560.00
- Mandor 0.0400 Oh 44,000.00 1,760.00

VI. 18 1 M2 Pasang daun pintu/ jendela kaca 3 mm rangka kayu jati 304,755.00
SNI Bahan 156,475.00
T-11-1993-03 - Kayu jati lokal 0.0180 M3 6,600,000.00 118,800.00
- Kaca bening 3 mm 0.7500 M2 49,500.00 37,125.00
- Paku reng 0.0500 Kg 11,000.00 550.00

Tenaga 148,280.00
- Pekerja 1.0000 Oh 30,250.00 30,250.00
- Tukang Kayu 2.7000 Oh 38,500.00 103,950.00
- Kepala Tukang Kayu 0.2700 Oh 44,000.00 11,880.00
- Mandor 0.0500 Oh 44,000.00 2,200.00

VI. 19 1 M2 Pasang daun pintu/ jendela kaca 3 mm rangka kayu kamper 314,655.00
SNI Bahan 166,375.00
T-11-1993-03 - Kayu Kamper 0.0180 M3 7,150,000.00 128,700.00
- Kaca bening 3 mm 0.7500 M2 49,500.00 37,125.00
- Paku reng 0.0500 Kg 11,000.00 550.00

Tenaga 148,280.00
- Pekerja 1.0000 Oh 30,250.00 30,250.00
- Tukang Kayu 2.7000 Oh 38,500.00 103,950.00
- Kepala Tukang Kayu 0.2700 Oh 44,000.00 11,880.00
- Mandor 0.0500 Oh 44,000.00 2,200.00

VI. 20 1 M2 Pasang daun pintu/ jendela kaca 3 mm rangka kayu meranti 245,355.00
SNI Bahan 97,075.00
T-11-1993-03 - Kayu meranti 0.0180 M3 3,300,000.00 59,400.00
- Kaca bening 3 mm 0.7500 M2 49,500.00 37,125.00
- Paku reng 0.0500 Kg 11,000.00 550.00

Tenaga 148,280.00
- Pekerja 1.0000 Oh 30,250.00 30,250.00
- Tukang Kayu 2.7000 Oh 38,500.00 103,950.00
- Kepala Tukang Kayu 0.2700 Oh 44,000.00 11,880.00
- Mandor 0.0500 Oh 44,000.00 2,200.00

VI. 21 1 M2 Pasang daun pintu/ jendela kaca 3 mm rangka kayu kruing 275,055.00
SNI Bahan 126,775.00
T-11-1993-03 - Kayu kruing 0.0180 M3 4,950,000.00 89,100.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 27


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
- Kaca bening 3 mm 0.7500 M2 49,500.00 37,125.00
- Paku reng 0.0500 Kg 11,000.00 550.00

Tenaga 148,280.00
- Pekerja 1.0000 Oh 30,250.00 30,250.00
- Tukang Kayu 2.7000 Oh 38,500.00 103,950.00
- Kepala Tukang Kayu 0.2700 Oh 44,000.00 11,880.00
- Mandor 0.0500 Oh 44,000.00 2,200.00

VI. 22 1 M2 Pasang daun pintu/ jendela kaca 3 mm rangka kayu bengkirai 341,385.00
SNI Bahan 193,105.00
T-11-1993-03 - Kayu bengkirai 0.0180 M3 8,635,000.00 155,430.00
- Kaca bening 3 mm 0.7500 M2 49,500.00 37,125.00
- Paku reng 0.0500 Kg 11,000.00 550.00

Tenaga 148,280.00
- Pekerja 1.0000 Oh 30,250.00 30,250.00
- Tukang Kayu 2.7000 Oh 38,500.00 103,950.00
- Kepala Tukang Kayu 0.2700 Oh 44,000.00 11,880.00
- Mandor 0.0500 Oh 44,000.00 2,200.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 28


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
VI. 23 1 M2 Pasang pintu dan jendela jalusi kayu jati lokal 624,250.00
SNI Bahan 463,100.00
03-3434-2008 - Papan kayu jati lokal 0.0640 M3 7,150,000.00 457,600.00
- Lem kayu "fox" 0.5000 kg 11,000.00 5,500.00

Tenaga 161,150.00
- Pekerja 1.0000 Oh 30,250.00 30,250.00
- Tukang Kayu 3.0000 Oh 38,500.00 115,500.00
- Kepala Tukang Kayu 0.3000 Oh 44,000.00 13,200.00
- Mandor 0.0500 Oh 44,000.00 2,200.00

VI. 24 1 M2 Pasang pintu dan jendela jalusi kayu kamper 694,650.00


SNI Bahan 533,500.00
03-3434-2008 - Papan kayu kamper 0.0640 M3 8,250,000.00 528,000.00
- Lem kayu "fox" 0.5000 kg 11,000.00 5,500.00

Tenaga 161,150.00
- Pekerja 1.0000 Oh 30,250.00 30,250.00
- Tukang Kayu 3.0000 Oh 38,500.00 115,500.00
- Kepala Tukang Kayu 0.3000 Oh 44,000.00 13,200.00
- Mandor 0.0500 Oh 44,000.00 2,200.00

VI. 25 1 M2 Pasang pintu dan jendela jalusi kayu meranti 406,010.00


SNI Bahan 244,860.00
03-3434-2008 - Papan kayu meranti 0.0640 M3 3,740,000.00 239,360.00
- Lem kayu "fox" 0.5000 kg 11,000.00 5,500.00

Tenaga 161,150.00
- Pekerja 1.0000 Oh 30,250.00 30,250.00
- Tukang Kayu 3.0000 Oh 38,500.00 115,500.00
- Kepala Tukang Kayu 0.3000 Oh 44,000.00 13,200.00
- Mandor 0.0500 Oh 44,000.00 2,200.00

VI. 26 1 M2 Pasang pintu dan jendela jalusi kayu kruing 518,650.00


SNI Bahan 357,500.00
03-3434-2008 - Papan kayu kruing 0.0640 M3 5,500,000.00 352,000.00
- Lem kayu "fox" 0.5000 kg 11,000.00 5,500.00

Tenaga 161,150.00
- Pekerja 1.0000 Oh 30,250.00 30,250.00
- Tukang Kayu 3.0000 Oh 38,500.00 115,500.00
- Kepala Tukang Kayu 0.3000 Oh 44,000.00 13,200.00
- Mandor 0.0500 Oh 44,000.00 2,200.00

VI. 27 1 M2 Pasang pintu dan jendela jalusi kayu bengkirai 800,250.00


SNI Bahan 639,100.00
03-3434-2008 - Papan kayu bengkirai 0.0640 M3 9,900,000.00 633,600.00
- Lem kayu "fox" 0.5000 kg 11,000.00 5,500.00

Tenaga 161,150.00
- Pekerja 1.0000 Oh 30,250.00 30,250.00
- Tukang Kayu 3.0000 Oh 38,500.00 115,500.00
- Kepala Tukang Kayu 0.3000 Oh 44,000.00 13,200.00
- Mandor 0.0500 Oh 44,000.00 2,200.00

VI. 28 1 M2 Pasang pintu plywood rangkap, rangka kayu jati lokal 355,135.00
SNI Bahan 242,330.00
03-3434-2008 - Papan kayu jati lokal 0.0250 M3 7,150,000.00 178,750.00
- Paku plepet 0.0300 Kg 11,000.00 330.00
- Lem kayu "fox" 0.5000 Kg 11,000.00 5,500.00
- Plywood 4 mm 1.0000 Lbr 57,750.00 57,750.00

Tenaga 112,805.00
- Pekerja 0.7000 Oh 30,250.00 21,175.00
- Tukang Kayu 2.1000 Oh 38,500.00 80,850.00
- Kepala Tukang Kayu 0.2100 Oh 44,000.00 9,240.00
- Mandor 0.0350 Oh 44,000.00 1,540.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 29


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)

VI. 29 1 M2 Pasang pintu plywood rangkap, rangka kayu kamper 382,635.00


SNI Bahan 269,830.00
03-3434-2008 - Papan kayu kamper 0.0250 M3 8,250,000.00 206,250.00
- Paku plepet 0.0300 Kg 11,000.00 330.00
- Lem kayu "fox" 0.5000 Kg 11,000.00 5,500.00
- Plywood 4 mm 1.0000 Lbr 57,750.00 57,750.00

Tenaga 112,805.00
- Pekerja 0.7000 Oh 30,250.00 21,175.00
- Tukang Kayu 2.1000 Oh 38,500.00 80,850.00
- Kepala Tukang Kayu 0.2100 Oh 44,000.00 9,240.00
- Mandor 0.0350 Oh 44,000.00 1,540.00

VI. 30 1 M2 Pasang pintu plywood rangkap, rangka kayu meranti 269,885.00


SNI Bahan 157,080.00
03-3434-2008 - Papan kayu meranti 0.0250 M3 3,740,000.00 93,500.00
- Paku plepet 0.0300 Kg 11,000.00 330.00
- Lem kayu "fox" 0.5000 Kg 11,000.00 5,500.00
- Plywood 4 mm 1.0000 Lbr 57,750.00 57,750.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 30


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
Tenaga 112,805.00
- Pekerja 0.7000 Oh 30,250.00 21,175.00
- Tukang Kayu 2.1000 Oh 38,500.00 80,850.00
- Kepala Tukang Kayu 0.2100 Oh 44,000.00 9,240.00
- Mandor 0.0350 Oh 44,000.00 1,540.00

VI. 31 1 M2 Pasang pintu plywood rangkap, rangka kayu kruing 313,885.00


SNI Bahan 201,080.00
03-3434-2008 - Papan kayu kruing 0.0250 M3 5,500,000.00 137,500.00
- Paku plepet 0.0300 Kg 11,000.00 330.00
- Lem kayu "fox" 0.5000 Kg 11,000.00 5,500.00
- Plywood 4 mm 1.0000 Lbr 57,750.00 57,750.00

Tenaga 112,805.00
- Pekerja 0.7000 Oh 30,250.00 21,175.00
- Tukang Kayu 2.1000 Oh 38,500.00 80,850.00
- Kepala Tukang Kayu 0.2100 Oh 44,000.00 9,240.00
- Mandor 0.0350 Oh 44,000.00 1,540.00

VI. 32 1 M2 Pasang pintu plywood rangkap, rangka kayu bengkirai 423,885.00


SNI Bahan 311,080.00
03-3434-2008 - Papan kayu bengkirai 0.0250 M3 9,900,000.00 247,500.00
- Paku plepet 0.0300 Kg 11,000.00 330.00
- Lem kayu "fox" 0.5000 Kg 11,000.00 5,500.00
- Plywood 4 mm 1.0000 Lbr 57,750.00 57,750.00
Tenaga 112,805.00
- Pekerja 0.7000 Oh 30,250.00 21,175.00
- Tukang Kayu 2.1000 Oh 38,500.00 80,850.00
- Kepala Tukang Kayu 0.2100 Oh 44,000.00 9,240.00
- Mandor 0.0350 Oh 44,000.00 1,540.00

VI. 33 1 M2 Pasang jalusi mati kusen kayu jati lokal 538,191.50


SNI Bahan 430,650.00
03-3434-2008 - Papan kayu jati lokal 0.0600 M3 7,150,000.00 429,000.00
- Paku plepet 0.1500 Kg 11,000.00 1,650.00

Tenaga 107,541.50
- Pekerja 0.6700 Oh 30,250.00 20,267.50
- Tukang Kayu 2.0000 Oh 38,500.00 77,000.00
- Kepala Tukang Kayu 0.2000 Oh 44,000.00 8,800.00
- Mandor 0.0335 Oh 44,000.00 1,474.00

VI. 34 1 M2 Pasang jalusi mati kusen kayu kamper 604,191.50


SNI Bahan 496,650.00
03-3434-2008 - Papan kayu kamper 0.0600 M3 8,250,000.00 495,000.00
- Paku plepet 0.1500 Kg 11,000.00 1,650.00

Tenaga 107,541.50
- Pekerja 0.6700 Oh 30,250.00 20,267.50
- Tukang Kayu 2.0000 Oh 38,500.00 77,000.00
- Kepala Tukang Kayu 0.2000 Oh 44,000.00 8,800.00
- Mandor 0.0335 Oh 44,000.00 1,474.00

VI. 35 1 M2 Pasang jalusi mati kusen kayu meranti 333,591.50


SNI Bahan 226,050.00
03-3434-2008 - Papan kayu meranti 0.0600 M3 3,740,000.00 224,400.00
- Paku plepet 0.1500 Kg 11,000.00 1,650.00

Tenaga 107,541.50
- Pekerja 0.6700 Oh 30,250.00 20,267.50
- Tukang Kayu 2.0000 Oh 38,500.00 77,000.00
- Kepala Tukang Kayu 0.2000 Oh 44,000.00 8,800.00
- Mandor 0.0335 Oh 44,000.00 1,474.00

VI. 36 1 M2 Pasang jalusi mati kusen kayu kruing 439,191.50


SNI Bahan 331,650.00
03-3434-2008 - Papan kayu kruing 0.0600 M3 5,500,000.00 330,000.00
- Paku plepet 0.1500 Kg 11,000.00 1,650.00

Tenaga 107,541.50

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 31


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
- Pekerja 0.6700 Oh 30,250.00 20,267.50
- Tukang Kayu 2.0000 Oh 38,500.00 77,000.00
- Kepala Tukang Kayu 0.2000 Oh 44,000.00 8,800.00
- Mandor 0.0335 Oh 44,000.00 1,474.00

VI. 37 1 M2 Pasang jalusi mati kusen kayu bengkirai 703,191.50


SNI Bahan 595,650.00
03-3434-2008 - Papan kayu bengkirai 0.0600 M3 9,900,000.00 594,000.00
- Paku plepet 0.1500 Kg 11,000.00 1,650.00

Tenaga 107,541.50
- Pekerja 0.6700 Oh 30,250.00 20,267.50
- Tukang Kayu 2.0000 Oh 38,500.00 77,000.00
- Kepala Tukang Kayu 0.2000 Oh 44,000.00 8,800.00
- Mandor 0.0335 Oh 44,000.00 1,474.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 32


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
VI. 38 1 M2 Pasang pintu teakwood rangkap, rangka expose kayu meranti 308,550.00
SNI Bahan 179,630.00
03-3434-2008 - Papan kayu meranti 0.0250 M3 3,740,000.00 93,500.00
- Paku plepet 0.0300 Kg 11,000.00 330.00
- Lem kayu "fox" 0.3000 Kg 11,000.00 3,300.00
- Teakwood 3 mm 120 x 240 cm 1.0000 Lbr 82,500.00 82,500.00

Tenaga 128,920.00
- Pekerja 0.8000 Oh 30,250.00 24,200.00
- Tukang Kayu 2.4000 Oh 38,500.00 92,400.00
- Kepala Tukang Kayu 0.2400 Oh 44,000.00 10,560.00
- Mandor 0.0400 Oh 44,000.00 1,760.00

VI. 39 1 M2 Pasang pintu teakwood rangkap, rangka expose kayu jati lokal 393,800.00
SNI Bahan 264,880.00
03-3434-2008 - Papan kayu jati lokal 0.0250 M3 7,150,000.00 178,750.00
- Paku plepet 0.0300 Kg 11,000.00 330.00
- Lem kayu "fox" 0.3000 Kg 11,000.00 3,300.00
- Teakwood 3 mm 120 x 240 cm 1.0000 Lbr 82,500.00 82,500.00

x Tenaga 128,920.00
- Pekerja 0.8000 Oh 30,250.00 24,200.00
- Tukang Kayu 2.4000 Oh 38,500.00 92,400.00
- Kepala Tukang Kayu 0.2400 Oh 44,000.00 10,560.00
- Mandor 0.0400 Oh 44,000.00 1,760.00

VI. 40 1 M2 Pasang pintu teakwood rangkap, rangka expose kayu kamper 421,300.00
SNI Bahan 292,380.00
03-3434-2008 - Papan kayu kamper 0.0250 M3 8,250,000.00 206,250.00
- Paku plepet 0.0300 Kg 11,000.00 330.00
- Lem kayu "fox" 0.3000 Kg 11,000.00 3,300.00
- Teakwood 3 mm 120 x 240 cm 1.0000 Lbr 82,500.00 82,500.00

Tenaga 128,920.00
- Pekerja 0.8000 Oh 30,250.00 24,200.00
- Tukang Kayu 2.4000 Oh 38,500.00 92,400.00
- Kepala Tukang Kayu 0.2400 Oh 44,000.00 10,560.00
- Mandor 0.0400 Oh 44,000.00 1,760.00

VI. 41 1 M2 Pasang pintu plywood & formika, rangkap rangka expose kayu jati lokal 423,879.50
SNI Bahan 286,880.00
03-3434-2008 - Papan kayu jati lokal 0.0250 M3 7,150,000.00 178,750.00
- Paku plepet 0.0300 Kg 11,000.00 330.00
- Lem kayu "fox" 0.8000 Kg 11,000.00 8,800.00
- Plywood 4 mm 1.0000 Lbr 57,750.00 57,750.00
- Formika 4" x 8" x 0,3 cm 0.5000 Lbr 82,500.00 41,250.00

Tenaga 136,999.50
- Pekerja 0.8500 Oh 30,250.00 25,712.50
- Tukang Kayu 2.5500 Oh 38,500.00 98,175.00
- Kepala Tukang Kayu 0.2550 Oh 44,000.00 11,220.00
- Mandor 0.0430 Oh 44,000.00 1,892.00

VI. 42 1 M2 Pasang pintu plywood & formika, rangkap rangka expose kayu kamper 451,379.50
SNI Bahan 314,380.00
03-3434-2008 - Papan kayu kamper 0.0250 M3 8,250,000.00 206,250.00
- Paku plepet 0.0300 Kg 11,000.00 330.00
- Lem kayu "fox" 0.8000 Kg 11,000.00 8,800.00
- Plywood 4 mm 1.0000 Lbr 57,750.00 57,750.00
- Formika 4" x 8" x 0,3 cm 0.5000 Lbr 82,500.00 41,250.00

Tenaga 136,999.50
- Pekerja 0.8500 Oh 30,250.00 25,712.50
- Tukang Kayu 2.5500 Oh 38,500.00 98,175.00
- Kepala Tukang Kayu 0.2550 Oh 44,000.00 11,220.00
- Mandor 0.0430 Oh 44,000.00 1,892.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 33


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
VI. 43 1 M2 Pasang pintu plywood & formika, rangkap rangka expose kayu meranti 338,629.50
SNI Bahan 201,630.00
03-3434-2008 - Papan kayu meranti 0.0250 M3 3,740,000.00 93,500.00
- Paku plepet 0.0300 Kg 11,000.00 330.00
- Lem kayu "fox" 0.8000 Kg 11,000.00 8,800.00
- Plywood 4 mm 1.0000 Lbr 57,750.00 57,750.00
- Formika 4" x 8" x 0,3 cm 0.5000 Lbr 82,500.00 41,250.00

Tenaga 136,999.50
- Pekerja 0.8500 Oh 30,250.00 25,712.50
- Tukang Kayu 2.5500 Oh 38,500.00 98,175.00
- Kepala Tukang Kayu 0.2550 Oh 44,000.00 11,220.00
- Mandor 0.0430 Oh 44,000.00 1,892.00

VI. 44 1 M2 Pasang pintu plywood & formika, rangkap rangka expose kayu kruing 382,629.50
SNI Bahan 245,630.00
03-3434-2008 - Papan kayu kruing 0.0250 M3 5,500,000.00 137,500.00
- Paku plepet 0.0300 Kg 11,000.00 330.00
- Lem kayu "fox" 0.8000 Kg 11,000.00 8,800.00
- Plywood 4 mm 1.0000 Lbr 57,750.00 57,750.00
- Formika 4" x 8" x 0,3 cm 0.5000 Lbr 82,500.00 41,250.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 34


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
Tenaga 136,999.50
- Pekerja 0.8500 Oh 30,250.00 25,712.50
- Tukang Kayu 2.5500 Oh 38,500.00 98,175.00
- Kepala Tukang Kayu 0.2550 Oh 44,000.00 11,220.00
- Mandor 0.0430 Oh 44,000.00 1,892.00

VI. 45 1 M2 Pasang pintu plywood & formika, rangkap rangka expose kayu bengkirai 492,629.50
SNI Bahan 355,630.00
03-3434-2008 - Papan kayu bengkirai 0.0250 M3 9,900,000.00 247,500.00
- Paku plepet 0.0300 Kg 11,000.00 330.00
- Lem kayu "fox" 0.8000 Kg 11,000.00 8,800.00
- Plywood 4 mm 1.0000 Lbr 57,750.00 57,750.00
- Formika 4" x 8" x 0,3 cm 0.5000 Lbr 82,500.00 41,250.00

Tenaga 136,999.50
- Pekerja 0.8500 Oh 30,250.00 25,712.50
- Tukang Kayu 2.5500 Oh 38,500.00 98,175.00
- Kepala Tukang Kayu 0.2550 Oh 44,000.00 11,220.00
- Mandor 0.0430 Oh 44,000.00 1,892.00

VI. 46 1 M2 Pasang pintu plywood & formika rangka kayu kamper (divernis) 430,754.50
SNI Bahan 293,755.00
03-3434-2008 - Papan kayu kamper 0.0250 M3 8,250,000.00 206,250.00
- Paku plepet 0.0300 Kg 11,000.00 330.00
- Lem kayu "fox" 0.8000 Kg 11,000.00 8,800.00
- Plywood 4 mm 0.5000 Lbr 57,750.00 28,875.00
- Pernis 0.5000 Lt 16,500.00 8,250.00
- Formika 4" x 8" x 0,3 cm 0.5000 Lbr 82,500.00 41,250.00

Tenaga 136,999.50
- Pekerja 0.8500 Oh 30,250.00 25,712.50
- Tukang Kayu 2.5500 Oh 38,500.00 98,175.00
- Kepala Tukang Kayu 0.2550 Oh 44,000.00 11,220.00
- Mandor 0.0430 Oh 44,000.00 1,892.00

VI. 47 1 M2 Pasang pintu plywood & formika rangka kayu meranti (divernis) 318,004.50
SNI Bahan 181,005.00
03-3434-2008 - Papan kayu meranti 0.0250 M3 3,740,000.00 93,500.00
- Paku plepet 0.0300 Kg 11,000.00 330.00
- Lem kayu "fox" 0.8000 Kg 11,000.00 8,800.00
- Plywood 4 mm 0.5000 Lbr 57,750.00 28,875.00
- Pernis 0.5000 Lt 16,500.00 8,250.00
- Formika 4" x 8" x 0,3 cm 0.5000 Lbr 82,500.00 41,250.00

Tenaga 136,999.50
- Pekerja 0.8500 Oh 30,250.00 25,712.50
- Tukang Kayu 2.5500 Oh 38,500.00 98,175.00
- Kepala Tukang Kayu 0.2550 Oh 44,000.00 11,220.00
- Mandor 0.0430 Oh 44,000.00 1,892.00

VI. 48 1 M2 Pasang pintu plywood & formika rangka kayu kruing (divernis) 362,004.50
SNI Bahan 225,005.00
03-3434-2008 - Papan kayu kruing 0.0250 M3 5,500,000.00 137,500.00
- Paku plepet 0.0300 Kg 11,000.00 330.00
- Lem kayu "fox" 0.8000 Kg 11,000.00 8,800.00
- Plywood 4 mm 0.5000 Lbr 57,750.00 28,875.00
- Pernis 0.5000 Lt 16,500.00 8,250.00
- Formika 4" x 8" x 0,3 cm 0.5000 Lbr 82,500.00 41,250.00

Tenaga 136,999.50
- Pekerja 0.8500 Oh 30,250.00 25,712.50
- Tukang Kayu 2.5500 Oh 38,500.00 98,175.00
- Kepala Tukang Kayu 0.2550 Oh 44,000.00 11,220.00
- Mandor 0.0430 Oh 44,000.00 1,892.00

VI. 49 1 M3 Pasang konstruksi kuda-kuda kayu jati lokal 8,114,700.00


SNI Bahan 7,470,100.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 35


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
03-3434-2008 - Kayu jati lokal 1.1000 M3 6,600,000.00 7,260,000.00
- Besi Strip 15.0000 Kg 9,900.00 148,500.00
- Paku usuk 5.6000 Kg 11,000.00 61,600.00

Tenaga 644,600.00
- Pekerja 4.0000 Oh 30,250.00 121,000.00
- Tukang Kayu 12.0000 Oh 38,500.00 462,000.00
- Kepala Tukang Kayu 1.2000 Oh 44,000.00 52,800.00
- Mandor 0.2000 Oh 44,000.00 8,800.00

VI. 50 1 M3 Pasang konstruksi kuda-kuda kayu kamper 8,719,700.00


SNI Bahan 8,075,100.00
03-3434-2008 - Kayu Kamper 1.1000 M3 7,150,000.00 7,865,000.00
- Besi Strip 15.0000 Kg 9,900.00 148,500.00
- Paku usuk 5.6000 Kg 11,000.00 61,600.00

Tenaga 644,600.00
- Pekerja 4.0000 Oh 30,250.00 121,000.00
- Tukang Kayu 12.0000 Oh 38,500.00 462,000.00
- Kepala Tukang Kayu 1.2000 Oh 44,000.00 52,800.00
- Mandor 0.2000 Oh 44,000.00 8,800.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 36


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
VI. 51 1 M3 Pasang konstruksi kuda-kuda kayu meranti 4,484,700.00
SNI Bahan 3,840,100.00
03-3434-2008 - Kayu meranti 1.1000 M3 3,300,000.00 3,630,000.00
- Besi Strip 15.0000 Kg 9,900.00 148,500.00
- Paku usuk 5.6000 Kg 11,000.00 61,600.00

Tenaga 644,600.00
- Pekerja 4.0000 Oh 30,250.00 121,000.00
- Tukang Kayu 12.0000 Oh 38,500.00 462,000.00
- Kepala Tukang Kayu 1.2000 Oh 44,000.00 52,800.00
- Mandor 0.2000 Oh 44,000.00 8,800.00

VI. 52 1 M3 Pasang konstruksi kuda-kuda kayu kruing v 6,299,700.00


SNI Bahan 5,655,100.00
03-3434-2008 - Kayu kruing 1.1000 M3 4,950,000.00 5,445,000.00
- Besi Strip 15.0000 Kg 9,900.00 148,500.00
- Paku usuk 5.6000 Kg 11,000.00 61,600.00

Tenaga 644,600.00
- Pekerja 4.0000 Oh 30,250.00 121,000.00
- Tukang Kayu 12.0000 Oh 38,500.00 462,000.00
- Kepala Tukang Kayu 1.2000 Oh 44,000.00 52,800.00
- Mandor 0.2000 Oh 44,000.00 8,800.00

VI. 53 1 M3 Pasang konstruksi kuda-kuda kayu bengkirai 10,353,200.00


SNI Bahan 9,708,600.00
03-3434-2008 - Kayu bengkirai 1.1000 M3 8,635,000.00 9,498,500.00
- Besi Strip 15.0000 Kg 9,900.00 148,500.00
- Paku usuk 5.6000 Kg 11,000.00 61,600.00

Tenaga 644,600.00
- Pekerja 4.0000 Oh 30,250.00 121,000.00
- Tukang Kayu 12.0000 Oh 38,500.00 462,000.00
- Kepala Tukang Kayu 1.2000 Oh 44,000.00 52,800.00
- Mandor 0.2000 Oh 44,000.00 8,800.00

VI. 54 1 M3 Pasang gording kayu jati lokal 7,679,760.00


SNI Bahan 7,293,000.00
03-3434-2008 - Kayu jati lokal 1.1000 M3 6,600,000.00 7,260,000.00
- Paku usuk 3.0000 Kg 11,000.00 33,000.00

Tenaga 386,760.00
- Pekerja 2.4000 Oh 30,250.00 72,600.00
- Tukang Kayu 7.2000 Oh 38,500.00 277,200.00
- Kepala Tukang Kayu 0.7200 Oh 44,000.00 31,680.00
- Mandor 0.1200 Oh 44,000.00 5,280.00

VI. 55 1 M3 Pasang gording kayu kamper 8,284,760.00


SNI Bahan 7,898,000.00
03-3434-2008 - Kayu Kamper 1.1000 M3 7,150,000.00 7,865,000.00
- Paku usuk 3.0000 Kg 11,000.00 33,000.00

Tenaga 386,760.00
- Pekerja 2.4000 Oh 30,250.00 72,600.00
- Tukang Kayu 7.2000 Oh 38,500.00 277,200.00
- Kepala Tukang Kayu 0.7200 Oh 44,000.00 31,680.00
- Mandor 0.1200 Oh 44,000.00 5,280.00

VI. 56 1 M3 Pasang gording kayu meranti 4,049,760.00


SNI Bahan 3,663,000.00
03-3434-2008 - Kayu meranti 1.1000 M3 3,300,000.00 3,630,000.00
- Paku usuk 3.0000 Kg 11,000.00 33,000.00

Tenaga 386,760.00
- Pekerja 2.4000 Oh 30,250.00 72,600.00
- Tukang Kayu 7.2000 Oh 38,500.00 277,200.00
- Kepala Tukang Kayu 0.7200 Oh 44,000.00 31,680.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 37


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
- Mandor 0.1200 Oh 44,000.00 5,280.00

VI. 57 1 M3 Pasang gording kayu kruing 5,864,760.00


SNI Bahan 5,478,000.00
03-3434-2008 - Kayu kruing 1.1000 M3 4,950,000.00 5,445,000.00
- Paku usuk 3.0000 Kg 11,000.00 33,000.00

Tenaga 386,760.00
- Pekerja 2.4000 Oh 30,250.00 72,600.00
- Tukang Kayu 7.2000 Oh 38,500.00 277,200.00
- Kepala Tukang Kayu 0.7200 Oh 44,000.00 31,680.00
- Mandor 0.1200 Oh 44,000.00 5,280.00

VI. 58 1 M3 Pasang gording kayu bengkirai 9,918,260.00


SNI Bahan 9,531,500.00
03-3434-2008 - Kayu bengkirai 1.1000 M3 8,635,000.00 9,498,500.00
- Paku usuk 3.0000 Kg 11,000.00 33,000.00

Tenaga 386,760.00
- Pekerja 2.4000 Oh 30,250.00 72,600.00
- Tukang Kayu 7.2000 Oh 38,500.00 277,200.00
- Kepala Tukang Kayu 0.7200 Oh 44,000.00 31,680.00
- Mandor 0.1200 Oh 44,000.00 5,280.00

VI. 59 1 M2 Rangka atap kayu jati lokal untuk seng 82,857.50


SNI Bahan 73,700.00
T-11-1993-03 - Kayu jati lokal 0.0110 M3 6,600,000.00 72,600.00
- Paku usuk 0.1000 Kg 11,000.00 1,100.00

Tenaga 9,157.50
- Pekerja 0.1500 Oh 30,250.00 4,537.50
- Tukang Kayu 0.1000 Oh 38,500.00 3,850.00
- Kepala Tukang Kayu 0.0100 Oh 44,000.00 440.00
- Mandor 0.0075 Oh 44,000.00 330.00

VI. 60 1 M2 Rangka atap kayu kamper untuk seng 88,907.50


SNI Bahan 79,750.00
T-11-1993-03 - Kayu Kamper 0.0110 M3 7,150,000.00 78,650.00
- Paku usuk 0.1000 Kg 11,000.00 1,100.00
Tenaga 9,157.50
- Pekerja 0.1500 Oh 30,250.00 4,537.50
- Tukang Kayu 0.1000 Oh 38,500.00 3,850.00
- Kepala Tukang Kayu 0.0100 Oh 44,000.00 440.00
- Mandor 0.0075 Oh 44,000.00 330.00

VI. 61 1 M2 Rangka atap kayu meranti untuk seng 46,557.50


SNI Bahan 37,400.00
T-11-1993-03 - Kayu meranti 0.0110 M3 3,300,000.00 36,300.00
- Paku usuk 0.1000 Kg 11,000.00 1,100.00

Tenaga 9,157.50
- Pekerja 0.1500 Oh 30,250.00 4,537.50
- Tukang Kayu 0.1000 Oh 38,500.00 3,850.00
- Kepala Tukang Kayu 0.0100 Oh 44,000.00 440.00
- Mandor 0.0075 Oh 44,000.00 330.00

VI. 62 1 M2 Rangka atap kayu kruing untuk seng 64,707.50


SNI Bahan 55,550.00
T-11-1993-03 - Kayu kruing 0.0110 M3 4,950,000.00 54,450.00
- Paku usuk 0.1000 Kg 11,000.00 1,100.00

Tenaga 9,157.50
- Pekerja 0.1500 Oh 30,250.00 4,537.50
- Tukang Kayu 0.1000 Oh 38,500.00 3,850.00
- Kepala Tukang Kayu 0.0100 Oh 44,000.00 440.00
- Mandor 0.0075 Oh 44,000.00 330.00

VI. 63 1 M2 Rangka atap kayu bengkirai untuk seng 105,242.50

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 38


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
SNI Bahan 96,085.00
T-11-1993-03 - Kayu bengkirai 0.0110 M3 8,635,000.00 94,985.00
- Paku usuk 0.1000 Kg 11,000.00 1,100.00

Tenaga 9,157.50
- Pekerja 0.1500 Oh 30,250.00 4,537.50
- Tukang Kayu 0.1000 Oh 38,500.00 3,850.00
- Kepala Tukang Kayu 0.0100 Oh 44,000.00 440.00
- Mandor 0.0075 Oh 44,000.00 330.00

VI. 64 1 M2 Pekerjaan usuk 5/7 dan reng 2/3 kayu jati lokal 126,445.00
SNI Bahan 118,910.00
03-3434-2008 - Kayu jati lokal 0.0176 M3 6,600,000.00 116,160.00
- Paku usuk 0.2500 Kg 11,000.00 2,750.00

Tenaga 7,535.00
- Pekerja 0.1000 Oh 30,250.00 3,025.00
- Tukang Kayu 0.1000 Oh 38,500.00 3,850.00
- Kepala Tukang Kayu 0.0100 Oh 44,000.00 440.00
- Mandor 0.0050 Oh 44,000.00 220.00

VI. 65 1 M2 Pekerjaan usuk 5/7 dan reng 2/3 kayu kamper 136,125.00
SNI Bahan 128,590.00
03-3434-2008 - Kayu Kamper 0.0176 M3 7,150,000.00 125,840.00
- Paku usuk 0.2500 Kg 11,000.00 2,750.00

Tenaga 7,535.00
- Pekerja 0.1000 Oh 30,250.00 3,025.00
- Tukang Kayu 0.1000 Oh 38,500.00 3,850.00
- Kepala Tukang Kayu 0.0100 Oh 44,000.00 440.00
- Mandor 0.0050 Oh 44,000.00 220.00

VI. 66 1 M2 Pekerjaan usuk 5/7 dan reng 2/3 kayu meranti 68,365.00
SNI Bahan 60,830.00
03-3434-2008 - Kayu meranti 0.0176 M3 3,300,000.00 58,080.00
- Paku usuk 0.2500 Kg 11,000.00 2,750.00

Tenaga 7,535.00
- Pekerja 0.1000 Oh 30,250.00 3,025.00
- Tukang Kayu 0.1000 Oh 38,500.00 3,850.00
- Kepala Tukang Kayu 0.0100 Oh 44,000.00 440.00
- Mandor 0.0050 Oh 44,000.00 220.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 39


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
VI. 67 1 M2 Pekerjaan usuk 5/7 dan reng 2/3 kayu kruing 97,405.00
SNI Bahan 89,870.00
03-3434-2008 - Kayu kruing 0.0176 M3 4,950,000.00 87,120.00
- Paku usuk 0.2500 Kg 11,000.00 2,750.00

Tenaga 7,535.00
- Pekerja 0.1000 Oh 30,250.00 3,025.00
- Tukang Kayu 0.1000 Oh 38,500.00 3,850.00
- Kepala Tukang Kayu 0.0100 Oh 44,000.00 440.00
- Mandor 0.0050 Oh 44,000.00 220.00

VI. 68 1 M2 Pekerjaan usuk 5/7 dan reng 2/3 kayu bengkirai 162,261.00
SNI Bahan 154,726.00
03-3434-2008 - Kayu bengkirai 0.0176 M3 8,635,000.00 151,976.00
- Paku usuk 0.2500 Kg 11,000.00 2,750.00

Tenaga 7,535.00
- Pekerja 0.1000 Oh 30,250.00 3,025.00
- Tukang Kayu 0.1000 Oh 38,500.00 3,850.00
- Kepala Tukang Kayu 0.0100 Oh 44,000.00 440.00
- Mandor 0.0050 Oh 44,000.00 220.00

VI. 69 1 M2 Pekerjaan usuk 5/7 dan reng 3/4 kayu jati lokal untuk genteng beton 150,205.00
SNI Bahan 142,670.00
03-3434-2008 - Kayu jati lokal 0.0212 M3 6,600,000.00 139,920.00
- Paku usuk 0.2500 Kg 11,000.00 2,750.00

Tenaga 7,535.00
- Pekerja 0.1000 Oh 30,250.00 3,025.00
- Tukang Kayu 0.1000 Oh 38,500.00 3,850.00
- Kepala Tukang Kayu 0.0100 Oh 44,000.00 440.00
- Mandor 0.0050 Oh 44,000.00 220.00

VI. 70 1 M2 Pekerjaan usuk 5/7 dan reng 3/4 kayu kamper untuk genteng beton 161,865.00
SNI Bahan 154,330.00
03-3434-2008 - Kayu Kamper 0.0212 M3 7,150,000.00 151,580.00
- Paku usuk 0.2500 Kg 11,000.00 2,750.00

Tenaga 7,535.00
- Pekerja 0.1000 Oh 30,250.00 3,025.00
- Tukang Kayu 0.1000 Oh 38,500.00 3,850.00
- Kepala Tukang Kayu 0.0100 Oh 44,000.00 440.00
- Mandor 0.0050 Oh 44,000.00 220.00

VI. 71 1 M2 Pekerjaan usuk 5/7 dan reng 3/4 kayu meranti untuk genteng beton 80,245.00
SNI Bahan 72,710.00
03-3434-2008 - Kayu meranti 0.0212 M3 3,300,000.00 69,960.00
- Paku usuk 0.2500 Kg 11,000.00 2,750.00

Tenaga 7,535.00
- Pekerja 0.1000 Oh 30,250.00 3,025.00
- Tukang Kayu 0.1000 Oh 38,500.00 3,850.00
- Kepala Tukang Kayu 0.0100 Oh 44,000.00 440.00
- Mandor 0.0050 Oh 44,000.00 220.00

VI. 72 1 M2 Pekerjaan usuk 5/7 dan reng 3/4 kayu kruing untuk genteng beton 115,225.00
SNI Bahan 107,690.00
03-3434-2008 - Kayu kruing 0.0212 M3 4,950,000.00 104,940.00
- Paku usuk 0.2500 Kg 11,000.00 2,750.00

Tenaga 7,535.00
- Pekerja 0.1000 Oh 30,250.00 3,025.00
- Tukang Kayu 0.1000 Oh 38,500.00 3,850.00
- Kepala Tukang Kayu 0.0100 Oh 44,000.00 440.00
- Mandor 0.0050 Oh 44,000.00 220.00

VI. 73 1 M2 Pekerjaan usuk 5/7 dan reng 3/4 kayu bengkirai untuk genteng beton 193,347.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 40


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
SNI Bahan 185,812.00
03-3434-2008 - Kayu bengkirai 0.0212 M3 8,635,000.00 183,062.00
- Paku usuk 0.2500 Kg 11,000.00 2,750.00

Tenaga 7,535.00
- Pekerja 0.1000 Oh 30,250.00 3,025.00
- Tukang Kayu 0.1000 Oh 38,500.00 3,850.00
- Kepala Tukang Kayu 0.0100 Oh 44,000.00 440.00
- Mandor 0.0050 Oh 44,000.00 220.00

VI. 74 1 M2 Pasang rangka langit-langit (0.50 x 1.00) m, kayu jati lokal 124,547.50
SNI Bahan 103,840.00
03-3434-2008 - Kayu jati lokal 0.0154 M3 6,600,000.00 101,640.00
- Paku usuk 0.2000 Kg 11,000.00 2,200.00

Tenaga 20,707.50
- Pekerja 0.1500 Oh 30,250.00 4,537.50
- Tukang Kayu 0.3000 Oh 38,500.00 11,550.00
- Kepala Tukang Kayu 0.0300 Oh 44,000.00 1,320.00
- Mandor 0.0750 Oh 44,000.00 3,300.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 41


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
VI. 75 1 M2 Pasang rangka langit-langit (0.50 x 1.00) m, kayu kamper 133,017.50
SNI Bahan 112,310.00
03-3434-2008 - Kayu Kamper 0.0154 M3 7,150,000.00 110,110.00
- Paku usuk 0.2000 Kg 11,000.00 2,200.00

Tenaga 20,707.50
- Pekerja 0.1500 Oh 30,250.00 4,537.50
- Tukang Kayu 0.3000 Oh 38,500.00 11,550.00
- Kepala Tukang Kayu 0.0300 Oh 44,000.00 1,320.00
- Mandor 0.0750 Oh 44,000.00 3,300.00

VI. 76 1 M2 Pasang rangka langit-langit (0.50 x 1.00) m, kayu meranti 73,727.50


SNI Bahan 53,020.00
03-3434-2008 - Kayu meranti 0.0154 M3 3,300,000.00 50,820.00
- Paku usuk 0.2000 Kg 11,000.00 2,200.00

Tenaga 20,707.50
- Pekerja 0.1500 Oh 30,250.00 4,537.50
- Tukang Kayu 0.3000 Oh 38,500.00 11,550.00
- Kepala Tukang Kayu 0.0300 Oh 44,000.00 1,320.00
- Mandor 0.0750 Oh 44,000.00 3,300.00

VI. 77 1 M2 Pasang rangka langit-langit (0.50 x 1.00) m, kayu kruing 99,137.50


SNI Bahan 78,430.00
03-3434-2008 - Kayu kruing 0.0154 M3 4,950,000.00 76,230.00
- Paku usuk 0.2000 Kg 11,000.00 2,200.00

Tenaga 20,707.50
- Pekerja 0.1500 Oh 30,250.00 4,537.50
- Tukang Kayu 0.3000 Oh 38,500.00 11,550.00
- Kepala Tukang Kayu 0.0300 Oh 44,000.00 1,320.00
- Mandor 0.0750 Oh 44,000.00 3,300.00

VI. 78 1 M2 Pasang rangka langit-langit (0.50 x 1.00) m, kayu bengkirai 155,886.50


SNI Bahan 135,179.00
03-3434-2008 - Kayu bengkirai 0.0154 M3 8,635,000.00 132,979.00
- Paku usuk 0.2000 Kg 11,000.00 2,200.00

Tenaga 20,707.50
- Pekerja 0.1500 Oh 30,250.00 4,537.50
- Tukang Kayu 0.3000 Oh 38,500.00 11,550.00
- Kepala Tukang Kayu 0.0300 Oh 44,000.00 1,320.00
- Mandor 0.0750 Oh 44,000.00 3,300.00

VI. 79 1 M2 Pasang rangka langit-langit (0.60 x 0.60) m, kayu jati lokal 129,690.00
SNI Bahan 110,330.00
03-3434-2008 - Kayu jati lokal 0.0163 M3 6,600,000.00 107,580.00
- Paku usuk 0.2500 Kg 11,000.00 2,750.00

Tenaga 19,360.00
- Pekerja 0.2000 Oh 30,250.00 6,050.00
- Tukang Kayu 0.3000 Oh 38,500.00 11,550.00
- Kepala Tukang Kayu 0.0300 Oh 44,000.00 1,320.00
- Mandor 0.0100 Oh 44,000.00 440.00

VI. 80 1 M2 Pasang rangka langit-langit (0.60 x 0.60) m, kayu meranti 75,900.00


SNI Bahan 56,540.00
03-3434-2008 - Kayu meranti 0.0163 M3 3,300,000.00 53,790.00
- Paku usuk 0.2500 Kg 11,000.00 2,750.00

Tenaga 19,360.00
- Pekerja 0.2000 Oh 30,250.00 6,050.00
- Tukang Kayu 0.3000 Oh 38,500.00 11,550.00
- Kepala Tukang Kayu 0.0300 Oh 44,000.00 1,320.00
- Mandor 0.0100 Oh 44,000.00 440.00

VI. 81 1 M2 Pasang rangka langit-langit (0.60 x 0.60) m, kayu kamper 138,655.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 42


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
SNI Bahan 119,295.00
03-3434-2008 - Kayu Kamper 0.0163 M3 7,150,000.00 116,545.00
- Paku usuk 0.2500 Kg 11,000.00 2,750.00

Tenaga 19,360.00
- Pekerja 0.2000 Oh 30,250.00 6,050.00
- Tukang Kayu 0.3000 Oh 38,500.00 11,550.00
- Kepala Tukang Kayu 0.0300 Oh 44,000.00 1,320.00
- Mandor 0.0100 Oh 44,000.00 440.00

VI. 82 1 M2 Pasang rangka langit-langit (0.60 x 0.60) m, kayu kruing 102,795.00


SNI Bahan 83,435.00
03-3434-2008 - Kayu kruing 0.0163 M3 4,950,000.00 80,685.00
- Paku usuk 0.2500 Kg 11,000.00 2,750.00

Tenaga 19,360.00
- Pekerja 0.2000 Oh 30,250.00 6,050.00
- Tukang Kayu 0.3000 Oh 38,500.00 11,550.00
- Kepala Tukang Kayu 0.0300 Oh 44,000.00 1,320.00
- Mandor 0.0100 Oh 44,000.00 440.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 43


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
VI. 83 1 M2 Pasang rangka langit-langit (0.60 x 0.60) m, kayu bengkirai 162,860.50
SNI Bahan 143,500.50
03-3434-2008 - Kayu bengkirai 0.0163 M3 8,635,000.00 140,750.50
, Paku usuk 0.2500 Kg 11,000.00 2,750.00

Tenaga 19,360.00
- Pekerja 0.2000 Oh 30,250.00 6,050.00
- Tukang Kayu 0.3000 Oh 38,500.00 11,550.00
- Kepala Tukang Kayu 0.0300 Oh 44,000.00 1,320.00
- Mandor 0.0100 Oh 44,000.00 440.00

VI. 84 1 M3 Pasang plafond hanger kayu jati lokal 8,065,750.00


Bahan 7,260,000.00
- Kayu jati lokal 1.1000 M3 6,600,000.00 7,260,000.00

Tenaga 805,750.00
- Pekerja 5.0000 Oh 30,250.00 151,250.00
- Tukang Kayu 15.0000 Oh 38,500.00 577,500.00
- Kepala Tukang Kayu 1.5000 Oh 44,000.00 66,000.00
- Mandor 0.2500 Oh 44,000.00 11,000.00

VI. 85 1 M3 Pasang plafond hanger kayu kamper 8,670,750.00


Bahan 7,865,000.00
- Kayu Kamper 1.1000 M3 7,150,000.00 7,865,000.00

Tenaga 805,750.00
- Pekerja 5.0000 Oh 30,250.00 151,250.00
- Tukang Kayu 15.0000 Oh 38,500.00 577,500.00
- Kepala Tukang Kayu 1.5000 Oh 44,000.00 66,000.00
- Mandor 0.2500 Oh 44,000.00 11,000.00

VI. 86 1 M3 Pasang plafond hanger kayu meranti 4,435,750.00


Bahan 3,630,000.00
- Kayu meranti 1.1000 M3 3,300,000.00 3,630,000.00

Tenaga 805,750.00
- Pekerja 5.0000 Oh 30,250.00 151,250.00
- Tukang Kayu 15.0000 Oh 38,500.00 577,500.00
- Kepala Tukang Kayu 1.5000 Oh 44,000.00 66,000.00
- Mandor 0.2500 Oh 44,000.00 11,000.00

VI. 87 1 M3 Pasang plafond hanger kayu kruing 6,250,750.00


Bahan 5,445,000.00
- Kayu kruing 1.1000 M3 4,950,000.00 5,445,000.00

Tenaga 805,750.00
- Pekerja 5.0000 Oh 30,250.00 151,250.00
- Tukang Kayu 15.0000 Oh 38,500.00 577,500.00
- Kepala Tukang Kayu 1.5000 Oh 44,000.00 66,000.00
- Mandor 0.2500 Oh 44,000.00 11,000.00

VI. 88 1 M3 Pasang plafond hanger kayu bengkirai 10,304,250.00


Bahan 9,498,500.00
- Kayu bengkirai 1.1000 M3 8,635,000.00 9,498,500.00

Tenaga 805,750.00
- Pekerja 5.0000 Oh 30,250.00 151,250.00
- Tukang Kayu 15.0000 Oh 38,500.00 577,500.00
- Kepala Tukang Kayu 1.5000 Oh 44,000.00 66,000.00
- Mandor 0.2500 Oh 44,000.00 11,000.00

VI. 89 1 M2 Pasang lisplang ukuran (3 x 20) cm, kayu jati lokal 63,855.00
SNI Bahan 52,030.00
03-3434-2008 - Papan kayu jati lokal 0.0072 M3 7,150,000.00 51,480.00
- Paku reng 0.0500 Kg 11,000.00 550.00

Tenaga 11,825.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 44


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
- Pekerja 0.1000 Oh 30,250.00 3,025.00
- Tukang Kayu 0.2000 Oh 38,500.00 7,700.00
- Kepala Tukang Kayu 0.0200 Oh 44,000.00 880.00
- Mandor 0.0050 Oh 44,000.00 220.00

VI. 90 1 M2 Pasang lisplang ukuran (3 x 20) cm, kayu kamper 71,775.00


SNI Bahan 59,950.00
03-3434-2008 - Papan kayu kamper 0.0072 M3 8,250,000.00 59,400.00
- Paku reng 0.0500 Kg 11,000.00 550.00

Tenaga 11,825.00
- Pekerja 0.1000 Oh 30,250.00 3,025.00
- Tukang Kayu 0.2000 Oh 38,500.00 7,700.00
- Kepala Tukang Kayu 0.0200 Oh 44,000.00 880.00
- Mandor 0.0050 Oh 44,000.00 220.00

VI. 91 1 M2 Pasang lisplang ukuran (3 x 20) cm, kayu meranti 39,303.00


SNI Bahan 27,478.00
03-3434-2008 - Papan kayu meranti 0.0072 M3 3,740,000.00 26,928.00
- Paku reng 0.0500 Kg 11,000.00 550.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 45


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
Tenaga 11,825.00
- Pekerja 0.1000 Oh 30,250.00 3,025.00
- Tukang Kayu 0.2000 Oh 38,500.00 7,700.00
- Kepala Tukang Kayu 0.0200 Oh 44,000.00 880.00
- Mandor 0.0050 Oh 44,000.00 220.00

VI. 92 1 M2 Pasang lisplang ukuran (3 x 20) cm, kayu kruing 49,167.80


SNI Bahan 40,150.00
03-3434-2008 - Papan kayu kruing 0.0072 M3 5,500,000.00 39,600.00
- Paku reng 0.0500 Kg 11,000.00 550.00

Tenaga 9,017.80
- Pekerja 0.0072 Oh 30,250.00 217.80
- Tukang Kayu 0.2000 Oh 38,500.00 7,700.00
- Kepala Tukang Kayu 0.0200 Oh 44,000.00 880.00
- Mandor 0.0050 Oh 44,000.00 220.00

VI. 93 1 M2 Pasang lisplang ukuran (3 x 20) cm, kayu bengkirai 83,655.00


SNI Bahan 71,830.00
03-3434-2008 - Papan kayu bengkirai 0.0072 M3 9,900,000.00 71,280.00
- Paku reng 0.0500 Kg 11,000.00 550.00

Tenaga 11,825.00
- Pekerja 0.1000 Oh 30,250.00 3,025.00
- Tukang Kayu 0.2000 Oh 38,500.00 7,700.00
- Kepala Tukang Kayu 0.0200 Oh 44,000.00 880.00
- Mandor 0.0050 Oh 44,000.00 220.00

VI. 94 1 M2 Pasang lisplang ukuran (3 x 30) cm, kayu jati 89,595.00


SNI Bahan 77,770.00
03-3434-2008 - Papan kayu jati lokal 0.0108 M3 7,150,000.00 77,220.00
- Paku reng 0.0500 Kg 11,000.00 550.00

Tenaga 11,825.00
- Pekerja 0.1000 Oh 30,250.00 3,025.00
- Tukang Kayu 0.2000 Oh 38,500.00 7,700.00
- Kepala Tukang Kayu 0.0200 Oh 44,000.00 880.00
- Mandor 0.0050 Oh 44,000.00 220.00

VI. 95 1 M2 Pasang lisplang ukuran (3 x 30) cm, kayu kamper 101,475.00


SNI Bahan 89,650.00
03-3434-2008 - Papan kayu kamper 0.0108 M3 8,250,000.00 89,100.00
- Paku reng 0.0500 Kg 11,000.00 550.00

Tenaga 11,825.00
- Pekerja 0.1000 Oh 30,250.00 3,025.00
- Tukang Kayu 0.2000 Oh 38,500.00 7,700.00
- Kepala Tukang Kayu 0.0200 Oh 44,000.00 880.00
- Mandor 0.0050 Oh 44,000.00 220.00

VI. 96 1 M2 Pasang lisplang ukuran (3 x 30) cm, kayu meranti 52,767.00


SNI Bahan 40,942.00
03-3434-2008 - Papan kayu meranti 0.0108 M3 3,740,000.00 40,392.00
- Paku reng 0.0500 Kg 11,000.00 550.00

Tenaga 11,825.00
- Pekerja 0.1000 Oh 30,250.00 3,025.00
- Tukang Kayu 0.2000 Oh 38,500.00 7,700.00
- Kepala Tukang Kayu 0.0200 Oh 44,000.00 880.00
- Mandor 0.0050 Oh 44,000.00 220.00

VI. 97 1 M2 Pasang lisplang ukuran (3 x 30) cm, kayu kruing 71,775.00


SNI Bahan 59,950.00
03-3434-2008 - Papan kayu kruing 0.0108 M3 5,500,000.00 59,400.00
- Paku reng 0.0500 Kg 11,000.00 550.00

Tenaga 11,825.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 46


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
- Pekerja 0.1000 Oh 30,250.00 3,025.00
- Tukang Kayu 0.2000 Oh 38,500.00 7,700.00
- Kepala Tukang Kayu 0.0200 Oh 44,000.00 880.00
- Mandor 0.0050 Oh 44,000.00 220.00

VI. 98 1 M2 Pasang lisplang ukuran (3 x 30) cm, kayu bengkirai 119,295.00


SNI Bahan 107,470.00
03-3434-2008 - Papan kayu bengkirai 0.0108 M3 9,900,000.00 106,920.00
- Paku reng 0.0500 Kg 11,000.00 550.00

Tenaga 11,825.00
- Pekerja 0.1000 Oh 30,250.00 3,025.00
- Tukang Kayu 0.2000 Oh 38,500.00 7,700.00
- Kepala Tukang Kayu 0.0200 Oh 44,000.00 880.00
- Mandor 0.0050 Oh 44,000.00 220.00

VI. 99 1 M2 Pasang lisplang ukuran 2 x (3 x 20) cm, kayu kamper 143,550.00


SNI Bahan 119,900.00
03-3434-2008 - Papan kayu kamper 0.0144 M3 8,250,000.00 118,800.00
- Paku reng 0.1000 Kg 11,000.00 1,100.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 47


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
Tenaga 23,650.00
- Pekerja 0.2000 Oh 30,250.00 6,050.00
- Tukang Kayu 0.4000 Oh 38,500.00 15,400.00
- Kepala Tukang Kayu 0.0400 Oh 44,000.00 1,760.00
- Mandor 0.0100 Oh 44,000.00 440.00

VI. 100 1 M2 Pasang lisplang ukuran 2 x (3 x 20) cm, kayu meranti 78,606.00
SNI Bahan 54,956.00
03-3434-2008 - Papan kayu meranti 0.0144 M3 3,740,000.00 53,856.00
- Paku reng 0.1000 Kg 11,000.00 1,100.00

Tenaga 23,650.00
- Pekerja 0.2000 Oh 30,250.00 6,050.00
- Tukang Kayu 0.4000 Oh 38,500.00 15,400.00
- Kepala Tukang Kayu 0.0400 Oh 44,000.00 1,760.00
- Mandor 0.0100 Oh 44,000.00 440.00

VI. 101 1 M2 Pasang lisplang ukuran 2 x (3 x 20) cm, kayu kruing 103,950.00
SNI Bahan 80,300.00
03-3434-2008 - Papan kayu kruing 0.0144 M3 5,500,000.00 79,200.00
- Paku reng 0.1000 Kg 11,000.00 1,100.00

Tenaga 23,650.00
- Pekerja 0.2000 Oh 30,250.00 6,050.00
- Tukang Kayu 0.4000 Oh 38,500.00 15,400.00
- Kepala Tukang Kayu 0.0400 Oh 44,000.00 1,760.00
- Mandor 0.0100 Oh 44,000.00 440.00

VI. 102 1 M2 Pasang lisplang ukuran 2 x (3 x 20) cm, kayu bengkirai 167,310.00
SNI Bahan 143,660.00
03-3434-2008 - Papan kayu bengkirai 0.0144 M3 9,900,000.00 142,560.00
- Paku reng 0.1000 Kg 11,000.00 1,100.00

Tenaga 23,650.00
- Pekerja 0.2000 Oh 30,250.00 6,050.00
- Tukang Kayu 0.4000 Oh 38,500.00 15,400.00
- Kepala Tukang Kayu 0.0400 Oh 44,000.00 1,760.00
- Mandor 0.0100 Oh 44,000.00 440.00

VI. 103 1 M2 Pasang lisplang ukuran 2 x (2 x 20) cm, kayu kamper 103,950.00
SNI Bahan 80,300.00
03-3434-2008 - Papan kayu kamper 0.0096 M3 8,250,000.00 79,200.00
- Paku reng 0.1000 Kg 11,000.00 1,100.00

Tenaga 23,650.00
- Pekerja 0.2000 Oh 30,250.00 6,050.00
- Tukang Kayu 0.4000 Oh 38,500.00 15,400.00
- Kepala Tukang Kayu 0.0400 Oh 44,000.00 1,760.00
- Mandor 0.0100 Oh 44,000.00 440.00

VI. 104 1 M2 Pasang lisplang ukuran 2 x (2 x 20) cm, kayu meranti 60,654.00
SNI Bahan 37,004.00
03-3434-2008 - Papan kayu meranti 0.0096 M3 3,740,000.00 35,904.00
- Paku reng 0.1000 Kg 11,000.00 1,100.00

Tenaga 23,650.00
- Pekerja 0.2000 Oh 30,250.00 6,050.00
- Tukang Kayu 0.4000 Oh 38,500.00 15,400.00
- Kepala Tukang Kayu 0.0400 Oh 44,000.00 1,760.00
- Mandor 0.0100 Oh 44,000.00 440.00

VI. 105 1 M2 Pasang lisplang ukuran 2 x (2 x 20) cm, kayu kruing 77,550.00
SNI Bahan 53,900.00
03-3434-2008 - Papan kayu kruing 0.0096 M3 5,500,000.00 52,800.00
- Paku reng 0.1000 Kg 11,000.00 1,100.00

Tenaga 23,650.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 48


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
- Pekerja 0.2000 Oh 30,250.00 6,050.00
- Tukang Kayu 0.4000 Oh 38,500.00 15,400.00
- Kepala Tukang Kayu 0.0400 Oh 44,000.00 1,760.00
- Mandor 0.0100 Oh 44,000.00 440.00

VI. 106 1 M2 Pasang lisplang ukuran 2 x (2 x 20) cm, kayu bengkirai 119,790.00
SNI Bahan 96,140.00
03-3434-2008 - Papan kayu bengkirai 0.0096 M3 9,900,000.00 95,040.00
- Paku reng 0.1000 Kg 11,000.00 1,100.00

Tenaga 23,650.00
- Pekerja 0.2000 Oh 30,250.00 6,050.00
- Tukang Kayu 0.4000 Oh 38,500.00 15,400.00
- Kepala Tukang Kayu 0.0400 Oh 44,000.00 1,760.00
- Mandor 0.0100 Oh 44,000.00 440.00

VI. 107 1 M2 Pasang rangka dinding pemisah (60x120)cm kayu kamper 6/12 226,044.50
SNI Bahan 201,850.00
03-3434-2008 - Kayu Kamper 0.0280 M3 7,150,000.00 200,200.00
- Paku reng 0.1500 Kg 11,000.00 1,650.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 49


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
Tenaga 24,194.50
- Pekerja 0.1500 Oh 30,250.00 4,537.50
- Tukang Kayu 0.4500 Oh 38,500.00 17,325.00
- Kepala Tukang Kayu 0.0450 Oh 44,000.00 1,980.00
- Mandor 0.0080 Oh 44,000.00 352.00

VI. 108 1 M2 Pasang rangka dinding pemisah (60x120)cm kayu meranti 6/12 118,244.50
SNI Bahan 94,050.00
03-3434-2008 - Kayu meranti 0.0280 M3 3,300,000.00 92,400.00
- Paku reng 0.1500 Kg 11,000.00 1,650.00

Tenaga 24,194.50
- Pekerja 0.1500 Oh 30,250.00 4,537.50
- Tukang Kayu 0.4500 Oh 38,500.00 17,325.00
- Kepala Tukang Kayu 0.0450 Oh 44,000.00 1,980.00
- Mandor 0.0080 Oh 44,000.00 352.00

VI. 109 1 M2 Pasang rangka dinding pemisah (60x120)cm kayu kruing 6/12 164,444.50
SNI Bahan 140,250.00
03-3434-2008 - Kayu kruing 0.0280 M3 4,950,000.00 138,600.00
- Paku reng 0.1500 Kg 11,000.00 1,650.00

Tenaga 24,194.50
- Pekerja 0.1500 Oh 30,250.00 4,537.50
- Tukang Kayu 0.4500 Oh 38,500.00 17,325.00
- Kepala Tukang Kayu 0.0450 Oh 44,000.00 1,980.00
- Mandor 0.0080 Oh 44,000.00 352.00

VI. 110 1 M2 Pasang rangka dinding pemisah (60x120)cm kayu bengkirai 6/12 267,624.50
SNI Bahan 243,430.00
03-3434-2008 - Kayu bengkirai 0.0280 M3 8,635,000.00 241,780.00
- Paku reng 0.1500 Kg 11,000.00 1,650.00

Tenaga 24,194.50
- Pekerja 0.1500 Oh 30,250.00 4,537.50
- Tukang Kayu 0.4500 Oh 38,500.00 17,325.00
- Kepala Tukang Kayu 0.0450 Oh 44,000.00 1,980.00
- Mandor 0.0080 Oh 44,000.00 352.00

VI. 111 1 M2 Pasang dinding pemisah plywood rangkap, rangka (60x120)cm kayu kamper 6/12 289,905.00
SNI Bahan 257,675.00
03-3434-2008 - Kayu Kamper 0.0280 M3 7,150,000.00 200,200.00
- Paku reng 0.1500 Kg 11,000.00 1,650.00
- Lem kayu "fox" 0.5600 Kg 11,000.00 6,160.00
- Plywood 4 mm 0.8600 Lbr 57,750.00 49,665.00

Tenaga 32,230.00
- Pekerja 0.2000 Oh 30,250.00 6,050.00
- Tukang Kayu 0.6000 Oh 38,500.00 23,100.00
- Kepala Tukang Kayu 0.0600 Oh 44,000.00 2,640.00
- Mandor 0.0100 Oh 44,000.00 440.00

VI. 112 1 M2 Pasang dinding pemisah plywood rangkap, rangka (60x120)cm kayu kruing 6/12 228,305.00
SNI Bahan 196,075.00
03-3434-2008 - Kayu kruing 0.0280 M3 4,950,000.00 138,600.00
- Paku reng 0.1500 Kg 11,000.00 1,650.00
- Lem kayu "fox" 0.5600 Kg 11,000.00 6,160.00
- Plywood 4 mm 0.8600 Lbr 57,750.00 49,665.00

Tenaga 32,230.00
- Pekerja 0.2000 Oh 30,250.00 6,050.00
- Tukang Kayu 0.6000 Oh 38,500.00 23,100.00
- Kepala Tukang Kayu 0.0600 Oh 44,000.00 2,640.00
- Mandor 0.0100 Oh 44,000.00 440.00

VI. 113 1 M2 Pasang dinding pemisah plywood rangkap, rangka (60x120)cm kayu meranti 6/12 182,105.00
SNI Bahan 149,875.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 50


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
03-3434-2008 - Kayu meranti 0.0280 M3 3,300,000.00 92,400.00
- Paku reng 0.1500 Kg 11,000.00 1,650.00
- Lem kayu "fox" 0.5600 Kg 11,000.00 6,160.00
- Plywood 4 mm 0.8600 Lbr 57,750.00 49,665.00

Tenaga 32,230.00
- Pekerja 0.2000 Oh 30,250.00 6,050.00
- Tukang Kayu 0.6000 Oh 38,500.00 23,100.00
- Kepala Tukang Kayu 0.0600 Oh 44,000.00 2,640.00
- Mandor 0.0100 Oh 44,000.00 440.00

VI. 114 1 M2 Pasang dinding pemisah teakwood rangkap, rangka (60x120)cm kayu kamper 6/12 303,154.50
SNI Bahan 278,960.00
03-3434-2008 - Kayu Kamper 0.0280 M3 7,150,000.00 200,200.00
- Paku reng 0.1500 Kg 11,000.00 1,650.00
- Lem kayu "fox" 0.5600 Kg 11,000.00 6,160.00
- Teakwood 3 mm 120 x 240 cm 0.8600 Lbr 82,500.00 70,950.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 51


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
Tenaga 24,194.50
- Pekerja 0.1500 Oh 30,250.00 4,537.50
- Tukang Kayu 0.4500 Oh 38,500.00 17,325.00
- Kepala Tukang Kayu 0.0450 Oh 44,000.00 1,980.00
- Mandor 0.0080 Oh 44,000.00 352.00

VI. 115 1 M2 Pasang dinding pemisah teakwood rangkap, rangka (60x120)cm kayu kruing 6/12 241,554.50
SNI Bahan 217,360.00
03-3434-2008 - Kayu kruing 0.0280 M3 4,950,000.00 138,600.00
- Paku reng 0.1500 Kg 11,000.00 1,650.00
- Lem kayu "fox" 0.5600 Kg 11,000.00 6,160.00
- Teakwood 3 mm 120 x 240 cm 0.8600 Lbr 82,500.00 70,950.00

Tenaga 24,194.50
- Pekerja 0.1500 Oh 30,250.00 4,537.50
- Tukang Kayu 0.4500 Oh 38,500.00 17,325.00
- Kepala Tukang Kayu 0.0450 Oh 44,000.00 1,980.00
- Mandor 0.0080 Oh 44,000.00 352.00

VI. 116 1 M2 Pasang dinding pemisah teakwood rangkap, rangka (60x120)cm kayu meranti 6/12 195,354.50
SNI Bahan 171,160.00
03-3434-2008 - Kayu meranti 0.0280 M3 3,300,000.00 92,400.00
- Paku reng 0.1500 Kg 11,000.00 1,650.00
- Lem kayu "fox" 0.5600 Kg 11,000.00 6,160.00
- Teakwood 3 mm 120 x 240 cm 0.8600 Lbr 82,500.00 70,950.00

Tenaga 24,194.50
- Pekerja 0.1500 Oh 30,250.00 4,537.50
- Tukang Kayu 0.4500 Oh 38,500.00 17,325.00
- Kepala Tukang Kayu 0.0450 Oh 44,000.00 1,980.00
- Mandor 0.0080 Oh 44,000.00 352.00

VI. 117 1 M2 Pasang plywood tebal 4 mm, untuk dinding 27,689.75


SNI Bahan 23,650.00
03-3434-2008 - Plywood 4 mm 0.4000 Lbr 57,750.00 23,100.00
- Paku plepet 0.0500 Kg 11,000.00 550.00

Tenaga 4,039.75
- Pekerja 0.0250 Oh 30,250.00 756.25
- Tukang Kayu 0.0750 Oh 38,500.00 2,887.50
- Kepala Tukang Kayu 0.0080 Oh 44,000.00 352.00
- Mandor 0.0010 Oh 44,000.00 44.00

VI. 118 1 M' Pasang list plafond kayu profil jadi 12,452.00
SNI Bahan 8,662.50
03-2839-2008 - List profil kayu 1.0500 M' 8,250.00 8,662.50

Tenaga 3,789.50
- Pekerja 0.0500 Oh 30,250.00 1,512.50
- Tukang Kayu 0.0500 Oh 38,500.00 1,925.00
- Kepala Tukang Kayu 0.0050 Oh 44,000.00 220.00
- Mandor 0.0030 Oh 44,000.00 132.00

VI. 119 1 M' Pasang list profil cornice gypsum lebar sampai 5 cm 15,041.76
Bahan 9,746.08
- List profile cornice gypsum 5 cm 1.1000 M' 7,000.00 7,700.00
- Cornice adhesive (tepung gypsum) @ 20 kg "A-plus" 0.7000 Kg 2,915.00 2,040.50
- Casting @ 20 kg "A-plus" 0.0035 Kg 1,595.00 5.58

Tenaga 5,295.68
- Pekerja 0.1125 Oh 30,250.00 3,403.13
- Tukang Kayu 0.0375 Oh 38,500.00 1,443.75
- Kepala Tukang Kayu 0.0037 Oh 44,000.00 162.80
- Mandor 0.0065 Oh 44,000.00 286.00

VI. 120 1 M' Pasang list profil cornice gypsum lebar sampai 5 - 10 cm 17,791.76
Bahan 12,496.08

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 52


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
- List profile cornice gypsum 5 - 10 cm 1.1000 M' 9,500.00 10,450.00
- Cornice adhesive (tepung gypsum) @ 20 kg "A-plus" 0.7000 Kg 2,915.00 2,040.50
- Casting @ 20 kg "A-plus" 0.0035 Kg 1,595.00 5.58

Tenaga 5,295.68
- Pekerja 0.1125 Oh 30,250.00 3,403.13
- Tukang Kayu 0.0375 Oh 38,500.00 1,443.75
- Kepala Tukang Kayu 0.0037 Oh 44,000.00 162.80
- Mandor 0.0065 Oh 44,000.00 286.00

VI. 121 1 M' Pasang list profil cornice gypsum lebar lebih dari 10 cm 23,841.76
Bahan 18,546.08
- List profile cornice gypsum lebih dari 10 cm 1.1000 M' 15,000.00 16,500.00
- Cornice adhesive (tepung gypsum) @ 20 kg "A-plus" 0.7000 Kg 2,915.00 2,040.50
- Casting @ 20 kg "A-plus" 0.0035 Kg 1,595.00 5.58

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 53


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
Tenaga 5,295.68
- Pekerja 0.1125 Oh 30,250.00 3,403.13
- Tukang Kayu 0.0375 Oh 38,500.00 1,443.75
- Kepala Tukang Kayu 0.0037 Oh 44,000.00 162.80
- Mandor 0.0065 Oh 44,000.00 286.00

VII. PEKERJAAN BETON


VII. 1 1 M3 Membuat beton tumbuk, 1Pc : 3 Ps : 5 Kr 495,577.50
SNI Bahan 431,420.00
03-2495-1991/ - Semen PC ( Portland Cement ) 40 kg 218.0000 Kg 1,100.00 239,800.00
SK SNI - Pasir beton (muntilan) 0.5200 M3 129,250.00 67,210.00
S-05-1990-F - Koral Beton 0.8700 M3 143,000.00 124,410.00

Tenaga 64,157.50
- Pekerja 1.6500 Oh 30,250.00 49,912.50
- Tukang Batu 0.2500 Oh 38,500.00 9,625.00
- Kepala Tukang Batu 0.0250 Oh 44,000.00 1,100.00
- Mandor 0.0800 Oh 44,000.00 3,520.00

VII. 2 1 M3 Membuat beton tumbuk, 1Pc : 3 Ps : 6 Kr 476,025.00


SNI Bahan 411,867.50
03-2495-1991/ - Semen PC ( Portland Cement ) 40 kg 197.0000 Kg 1,100.00 216,700.00
SK SNI - Pasir beton (muntilan) 0.4700 M3 129,250.00 60,747.50
S-05-1990-F - Koral Beton 0.9400 M3 143,000.00 134,420.00

Tenaga 64,157.50
- Pekerja 1.6500 Oh 30,250.00 49,912.50
- Tukang Batu 0.2500 Oh 38,500.00 9,625.00
- Kepala Tukang Batu 0.0250 Oh 44,000.00 1,100.00
- Mandor 0.0800 Oh 44,000.00 3,520.00

VII. 3 1 M3 Membuat beton tumbuk, 1Pc : 4 Ps : 6 Kr 452,540.00


SNI Bahan 388,382.50
03-2495-1991/ - Semen PC ( Portland Cement ) 40 kg 173.0000 Kg 1,100.00 190,300.00
SK SNI - Pasir beton (muntilan) 0.5700 M3 129,250.00 73,672.50
S-05-1990-F - Koral Beton 0.8700 M3 143,000.00 124,410.00

Tenaga 64,157.50
- Pekerja 1.6500 Oh 30,250.00 49,912.50
- Tukang Batu 0.2500 Oh 38,500.00 9,625.00
- Kepala Tukang Batu 0.0250 Oh 44,000.00 1,100.00
- Mandor 0.0800 Oh 44,000.00 3,520.00

VII. 4 1 M2 Membuat lantai kerja beton tumbuk, 1Pc : 3 Ps : 5 Kr, tebal 5 cm 56,562.00
SNI Bahan 20,652.50
03-2495-1991/ - Semen PC ( Portland Cement ) 40 kg 10.0000 Kg 1,100.00 11,000.00
SK SNI - Pasir beton (muntilan) 0.0260 M3 129,250.00 3,360.50
S-05-1990-F - Koral Beton 0.0440 M3 143,000.00 6,292.00

Tenaga 35,909.50
- Pekerja 1.1500 Oh 30,250.00 34,787.50
- Tukang Batu 0.0200 Oh 38,500.00 770.00
- Kepala Tukang Batu 0.0020 Oh 44,000.00 88.00
- Mandor 0.0060 Oh 44,000.00 264.00

VII. 5 1 M3 Membuat beton bertulang, 1 Pc : 2 Ps : 3 Kr 719,290.00


SNI Bahan 599,775.00
03-2495-1991/ - Semen PC ( Portland Cement ) 40 kg 336.0000 Kg 1,100.00 369,600.00
SK SNI - Pasir beton (muntilan) 0.5400 M3 129,250.00 69,795.00
S-05-1990-F - Batu pecah 2/3 giling 0.8100 M3 198,000.00 160,380.00

Tenaga 119,515.00
- Pekerja 2.0000 Oh 30,250.00 60,500.00
- Tukang Batu 0.3500 Oh 38,500.00 13,475.00
- Kepala Tukang Batu 0.0350 Oh 44,000.00 1,540.00
- Mandor 1.0000 Oh 44,000.00 44,000.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 54


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
VII. 6 1 M3 Membuat beton bertulang, 1 Pc : 2 Ps : 4 Kr 684,502.50
SNI Bahan 564,987.50
03-2495-1991/ - Semen PC ( Portland Cement ) 40 kg 291.0000 Kg 1,100.00 320,100.00
SK SNI - Pasir beton (muntilan) 0.4700 M3 129,250.00 60,747.50
S-05-1990-F - Batu pecah 2/3 giling 0.9300 M3 198,000.00 184,140.00

Tenaga 119,515.00
- Pekerja 2.0000 Oh 30,250.00 60,500.00
- Tukang Batu 0.3500 Oh 38,500.00 13,475.00
- Kepala Tukang Batu 0.0350 Oh 44,000.00 1,540.00
- Mandor 1.0000 Oh 44,000.00 44,000.00

VII. 7 1 M3 Membuat beton bertulang, 1 Pc : 1,5 Ps : 2,5 Kr 779,955.00


SNI Bahan 660,440.00
03-2495-1991/ - Semen PC ( Portland Cement ) 40 kg 400.0000 Kg 1,100.00 440,000.00
SK SNI - Pasir beton (muntilan) 0.4800 M3 129,250.00 62,040.00
S-05-1990-F - Batu pecah 2/3 giling 0.8000 M3 198,000.00 158,400.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 55


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
Tenaga 119,515.00
- Pekerja 2.0000 Oh 30,250.00 60,500.00
- Tukang Batu 0.3500 Oh 38,500.00 13,475.00
- Kepala Tukang Batu 0.0350 Oh 44,000.00 1,540.00
- Mandor 1.0000 Oh 44,000.00 44,000.00

VII. 8 1 Kg Pembesian / kabel presstressed dengan besi polos atau besi ulir 9,942.90
SNI Bahan 9,413.25
7394-2008 - Besi Beton (polos / ulir) 1.0500 Kg 8,800.00 9,240.00
- Kawat Beton / Bendrat 0.0150 Kg 11,550.00 173.25

Tenaga 529.65
- Pekerja 0.0070 Oh 30,250.00 211.75
- Tukang Besi 0.0070 Oh 38,500.00 269.50
- Kepala Tukang Besi 0.0007 Oh 44,000.00 30.80
- Mandor 0.0004 Oh 44,000.00 17.60

VII. 9 Bekisting untuk 1 M3 beton 763,400.00


Bahan 484,000.00
- Kayu tahun/ lanan 0.4000 M3 1,100,000.00 440,000.00
- Paku usuk 4.0000 Kg 11,000.00 44,000.00

Tenaga 279,400.00
- Pekerja 2.0000 Oh 30,250.00 60,500.00
- Tukang Kayu 5.0000 Oh 38,500.00 192,500.00
- Kepala Tukang Kayu 0.5000 Oh 44,000.00 22,000.00
- Mandor 0.1000 Oh 44,000.00 4,400.00

VII. 10 Membongkar bekisting untuk 1 M3 beton 121,000.00


Bahan -
Tenaga 121,000.00
- Pekerja 4.0000 Oh 30,250.00 121,000.00

VII. 11 Stutwerk untuk 1 M3 beton tinggi 3 - 4 m (memakai dolken) 1,334,025.00


Bahan 770,000.00
- Kayu dolken Ø 8-10/400 cm 0.7000 M3 1,100,000.00 770,000.00

Tenaga 564,025.00
- Pekerja 3.5000 Oh 30,250.00 105,875.00
- Tukang Kayu 10.5000 Oh 38,500.00 404,250.00
- Kepala Tukang Kayu 1.0500 Oh 44,000.00 46,200.00
- Mandor 0.1750 Oh 44,000.00 7,700.00

VII. 12 Stutwerk untuk 1 M3 beton tinggi 3 - 4 m (memakai bambu) 748,825.00


Bahan 184,800.00
- Bambu 28.0000 Btg 6,600.00 184,800.00

Tenaga 564,025.00
- Pekerja 3.5000 Oh 30,250.00 105,875.00
- Tukang Kayu 10.5000 Oh 38,500.00 404,250.00
- Kepala Tukang Kayu 1.0500 Oh 44,000.00 46,200.00
- Mandor 0.1750 Oh 44,000.00 7,700.00

VII. 13 Stutwerk untuk 1 M3 beton tinggi 3 - 4 m (memakai scafolding) 1,341,980.00


Bahan 1,120,000.00
- Scafolding 32.0000 unit 35,000.00 1,120,000.00

Tenaga 221,980.00
- Pekerja 2.2000 Oh 30,250.00 66,550.00
- Tukang Kayu 3.5000 Oh 38,500.00 134,750.00
- Kepala Tukang Kayu 0.3500 Oh 44,000.00 15,400.00
- Mandor 0.1200 Oh 44,000.00 5,280.00

VII. 14 1 M' Membuat kolom praktis/ kolom penguat beton bertulang (11 x 11) cm 44,547.25
SNI Bahan 36,132.25
7394-2008 - Papan 3/20 kayu tahun 0.0020 M3 1,320,000.00 2,640.00
- Paku usuk 0.0100 Kg 11,000.00 110.00
- Besi Beton polos 3.0000 Kg 8,800.00 26,400.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 56


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
- Kawat Beton / Bendrat 0.0450 Kg 11,550.00 519.75
- Semen PC ( Portland Cement ) 40 kg 4.0000 Kg 1,100.00 4,400.00
- Pasir beton (muntilan) 0.0060 M3 129,250.00 775.50
- Koral Beton 0.0090 M3 143,000.00 1,287.00

Tenaga 8,415.00
- Pekerja 0.1800 Oh 30,250.00 5,445.00
- Tukang Batu 0.0200 Oh 38,500.00 770.00
- Tukang Kayu 0.0200 Oh 38,500.00 770.00
- Tukang Besi 0.0200 Oh 38,500.00 770.00
- Kepala Tukang Batu 0.0060 Oh 44,000.00 264.00
- Mandor 0.0090 Oh 44,000.00 396.00

VII. 15 1 M' Membuat ring balok beton bertulang (10 x 15) cm 59,691.50
SNI Bahan 45,795.75
7394-2008 - Papan 3/20 kayu tahun 0.0030 M3 1,320,000.00 3,960.00
- Paku usuk 0.0200 Kg 11,000.00 220.00
- Besi Beton polos 3.6000 Kg 8,800.00 31,680.00
- Kawat Beton / Bendrat 0.0500 Kg 11,550.00 577.50
- Semen PC ( Portland Cement ) 40 kg 5.5000 Kg 1,100.00 6,050.00
- Pasir beton (muntilan) 0.0090 M3 129,250.00 1,163.25
- Koral Beton 0.0150 M3 143,000.00 2,145.00

Tenaga 13,895.75
- Pekerja 0.2970 Oh 30,250.00 8,984.25
- Tukang Batu 0.0330 Oh 38,500.00 1,270.50
- Tukang Kayu 0.0330 Oh 38,500.00 1,270.50
- Tukang Besi 0.0330 Oh 38,500.00 1,270.50
- Kepala Tukang Batu 0.0100 Oh 44,000.00 440.00
- Mandor 0.0150 Oh 44,000.00 660.00

VIII. PEKERJAAN PENUTUP ATAP


VIII. 1 1 M2 Pasang atap genteng palentong / vlampress kecil 42,504.00
SNI Bahan 34,375.00
03-3436-2002 - Genteng Plenthong / Vlampress kecil kebumen 25.0000 Bh 1,375.00 34,375.00

Tenaga 8,129.00
- Pekerja 0.1500 Oh 30,250.00 4,537.50
- Tukang Kayu 0.0750 Oh 38,500.00 2,887.50
- Kepala Tukang Kayu 0.0080 Oh 44,000.00 352.00
- Mandor 0.0080 Oh 44,000.00 352.00

VIII. 2 1 M2 Pasang atap genteng kodok 38,379.00


SNI Bahan 30,250.00
03-3436-2002 - Genteng kodok "sokka" 25.0000 Bh 1,210.00 30,250.00

Tenaga 8,129.00
- Pekerja 0.1500 Oh 30,250.00 4,537.50
- Tukang Kayu 0.0750 Oh 38,500.00 2,887.50
- Kepala Tukang Kayu 0.0080 Oh 44,000.00 352.00
- Mandor 0.0080 Oh 44,000.00 352.00

VIII. 3 1 M2 Pasang atap genteng palentong/ vlampress super/besar 25,283.50


SNI Bahan 17,820.00
03-3436-2002 - Genteng Plenthong / Vlampress besar kebumen 12.0000 Bh 1,485.00 17,820.00

Tenaga 7,463.50
- Pekerja 0.1500 Oh 30,250.00 4,537.50
- Tukang Kayu 0.0600 Oh 38,500.00 2,310.00
- Kepala Tukang Kayu 0.0060 Oh 44,000.00 264.00
- Mandor 0.0080 Oh 44,000.00 352.00

VIII. 4 1 M2 Pasang atap genteng beton warna natural 44,660.00


SNI Bahan 33,880.00
03-3436-2002 - Genteng beton kecil natural isi 11 biji "RA" 11.0000 Bh 3,080.00 33,880.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 57


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
Tenaga 10,780.00
- Pekerja 0.2000 Oh 30,250.00 6,050.00
- Tukang Kayu 0.1000 Oh 38,500.00 3,850.00
- Kepala Tukang Kayu 0.0100 Oh 44,000.00 440.00
- Mandor 0.0100 Oh 44,000.00 440.00

VIII. 5 1 M' Pasang atap genteng bubung palentong/ vlampress kecil 58,014.00
SNI Bahan 37,246.00
03-3436-2002 - Nok Genteng Plenthong / Vlampress kecil kebumen 5.0000 Bh 4,950.00 24,750.00
- Semen PC ( Portland Cement ) 40 kg 8.0000 Kg 1,100.00 8,800.00
- Pasir pasang (kaliworo) 0.0320 M3 115,500.00 3,696.00

Tenaga 20,768.00
- Pekerja 0.4000 Oh 30,250.00 12,100.00
- Tukang Kayu 0.2000 Oh 38,500.00 7,700.00
- Kepala Tukang Kayu 0.0200 Oh 44,000.00 880.00
- Mandor 0.0020 Oh 44,000.00 88.00

VIII. 6 1 M' Pasang atap genteng bubung kodok 52,514.00


SNI Bahan 31,746.00
03-3436-2002 - Nok genteng kodok 5.0000 Bh 3,850.00 19,250.00
- Semen PC ( Portland Cement ) 40 kg 8.0000 Kg 1,100.00 8,800.00
- Pasir pasang (kaliworo) 0.0320 M3 115,500.00 3,696.00

Tenaga 20,768.00
- Pekerja 0.4000 Oh 30,250.00 12,100.00
- Tukang Kayu 0.2000 Oh 38,500.00 7,700.00
- Kepala Tukang Kayu 0.0200 Oh 44,000.00 880.00
- Mandor 0.0020 Oh 44,000.00 88.00

VIII. 7 1 M' Pasang atap genteng bubung palentong/ vlampress super/ besar 53,064.00
SNI Bahan 32,296.00
03-3436-2002 - Nok Genteng Plenthong / Vlampress besar kebumen 4.0000 Bh 4,950.00 19,800.00
- Semen PC ( Portland Cement ) 40 kg 8.0000 Kg 1,100.00 8,800.00
- Pasir pasang (kaliworo) 0.0320 M3 115,500.00 3,696.00

Tenaga 20,768.00
- Pekerja 0.4000 Oh 30,250.00 12,100.00
- Tukang Kayu 0.2000 Oh 38,500.00 7,700.00
- Kepala Tukang Kayu 0.0200 Oh 44,000.00 880.00
- Mandor 0.0020 Oh 44,000.00 88.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 58


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
VIII. 8 1 M' Pasang atap genteng bubung beton warna natural 59,444.00
SNI Bahan 38,676.00
03-3436-2002 - Nok press beton natural 3.5000 Bh 5,500.00 19,250.00
- Semen PC ( Portland Cement ) 40 kg 10.8000 Kg 1,100.00 11,880.00
- Semen Warna 1.0000 Kg 3,850.00 3,850.00
- Pasir pasang (kaliworo) 0.0320 M3 115,500.00 3,696.00

Tenaga 20,768.00
- Pekerja 0.4000 Oh 30,250.00 12,100.00
- Tukang Kayu 0.2000 Oh 38,500.00 7,700.00
- Kepala Tukang Kayu 0.0200 Oh 44,000.00 880.00
- Mandor 0.0020 Oh 44,000.00 88.00

VIII. 9 1 M2 Pasang atap asbes gelombang gelombang besar (300 x 102 x 5 mm) 36,774.10
SNI Bahan 28,947.60
03-3436-2002 - Asbes Gelombang besar (300 x 102 x 0,5) 0.3600 Lbr 80,300.00 28,908.00
- Paku asbes 0.1200 Kg 330.00 39.60

Tenaga 7,826.50
- Pekerja 0.1400 Oh 30,250.00 4,235.00
- Tukang Kayu 0.0750 Oh 38,500.00 2,887.50
- Kepala Tukang Kayu 0.0080 Oh 44,000.00 352.00
- Mandor 0.0080 Oh 44,000.00 352.00

VIII. 10 1 M2 Pasang atas asbes gelombang gelombang besar (200 x 102 x 5 mm) 42,565.60
SNI Bahan 35,019.60
03-3436-2002 - Asbes Gelombang besar (200 x 102 x 0,5) 0.6000 Lbr 58,300.00 34,980.00
- Paku asbes 0.1200 Kg 330.00 39.60

Tenaga 7,546.00
- Pekerja 0.1400 Oh 30,250.00 4,235.00
- Tukang Kayu 0.0700 Oh 38,500.00 2,695.00
- Kepala Tukang Kayu 0.0070 Oh 44,000.00 308.00
- Mandor 0.0070 Oh 44,000.00 308.00

VIII. 11 1 M2 Pasang atas asbes gelombang gelombang besar (180 x 102 x 5 mm) 48,010.60
SNI Bahan 40,464.60
03-3436-2002 - Asbes Gelombang besar (180 x 102 x 0,5) 0.7500 Lbr 53,900.00 40,425.00
- Paku asbes 0.1200 Kg 330.00 39.60

Tenaga 7,546.00
- Pekerja 0.1400 Oh 30,250.00 4,235.00
- Tukang Kayu 0.0700 Oh 38,500.00 2,695.00
- Kepala Tukang Kayu 0.0070 Oh 44,000.00 308.00
- Mandor 0.0070 Oh 44,000.00 308.00

VIII. 12 1 M2 Pasang atas asbes gelombang gelombang kecil (300 x 105 x 4 mm) 30,685.60
SNI Bahan 23,139.60
03-3436-2002 - Asbes Gelombang kecil (300 x 105 x 0,4) Djabes 0.3500 Lbr 66,000.00 23,100.00
- Paku asbes 0.1200 Kg 330.00 39.60

Tenaga 7,546.00
- Pekerja 0.1400 Oh 30,250.00 4,235.00
- Tukang Kayu 0.0700 Oh 38,500.00 2,695.00
- Kepala Tukang Kayu 0.0070 Oh 44,000.00 308.00
- Mandor 0.0070 Oh 44,000.00 308.00

VIII. 13 1 M2 Pasang atas asbes gelombang gelombang kecil (270 x 105 x 4 mm) 35,074.60
SNI Bahan 27,528.60
03-3436-2002 - Asbes Gelombang kecil (270 x 105 x 0,4) Djabes 0.4200 Lbr 65,450.00 27,489.00
- Paku asbes 0.1200 Kg 330.00 39.60

Tenaga 7,546.00
- Pekerja 0.1400 Oh 30,250.00 4,235.00
- Tukang Kayu 0.0700 Oh 38,500.00 2,695.00
- Kepala Tukang Kayu 0.0070 Oh 44,000.00 308.00
- Mandor 0.0070 Oh 44,000.00 308.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 59


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)

VIII. 14 1 M2 Pasang atas asbes gelombang gelombang kecil (240 x 105 x 4 mm) 30,702.10
SNI Bahan 23,271.60
03-3436-2002 - Asbes Gelombang kecil (240 x 105 x 0,4) Djabes 0.4400 Lbr 52,800.00 23,232.00
- Paku asbes 0.1200 Kg 330.00 39.60

Tenaga 7,430.50
- Pekerja 0.1400 Oh 30,250.00 4,235.00
- Tukang Kayu 0.0670 Oh 38,500.00 2,579.50
- Kepala Tukang Kayu 0.0070 Oh 44,000.00 308.00
- Mandor 0.0070 Oh 44,000.00 308.00

VIII. 15 1 M2 Pasang atas asbes gelombang gelombang kecil (210 x 105 x 4 mm) 31,032.10
SNI Bahan 23,601.60
03-3436-2002 - Asbes Gelombang kecil (210 x 105 x 0,4) Djabes 0.5100 Lbr 46,200.00 23,562.00
- Paku asbes 0.1200 Kg 330.00 39.60

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 60


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
Tenaga 7,430.50
- Pekerja 0.1400 Oh 30,250.00 4,235.00
- Tukang Kayu 0.0670 Oh 38,500.00 2,579.50
- Kepala Tukang Kayu 0.0070 Oh 44,000.00 308.00
- Mandor 0.0070 Oh 44,000.00 308.00

VIII. 16 1 M2 Pasang atas asbes gelombang gelombang kecil (150 x 105 x 4 mm) 36,070.10
SNI Bahan 28,639.60
03-3436-2002 - Asbes Gelombang kecil (150 x 105 x 0,4) Djabes 0.8000 Lbr 35,750.00 28,600.00
- Paku asbes 0.1200 Kg 330.00 39.60

Tenaga 7,430.50
- Pekerja 0.1400 Oh 30,250.00 4,235.00
- Tukang Kayu 0.0670 Oh 38,500.00 2,579.50
- Kepala Tukang Kayu 0.0070 Oh 44,000.00 308.00
- Mandor 0.0070 Oh 44,000.00 308.00

VIII. 17 1 M2 Pasang atap seng BJLS 0,2 gelombang P = 300 cm 35,514.60


SNI Bahan 29,046.60
03-3436-2002 - Seng BJLS 0,2 gelombang P = 300 cm 0.4800 Lbr 60,500.00 29,040.00
- Paku asbes 0.0200 Kg 330.00 6.60

Tenaga 6,468.00
- Pekerja 0.1200 Oh 30,250.00 3,630.00
- Tukang Kayu 0.0600 Oh 38,500.00 2,310.00
- Kepala Tukang Kayu 0.0060 Oh 44,000.00 264.00
- Mandor 0.0060 Oh 44,000.00 264.00

VIII. 18 1 M2 Pasang atap seng BJLS 0,2 gelombang P = 240 cm 35,998.60


SNI Bahan 29,530.60
03-3436-2002 - Seng BJLS 0,2 gelombang P = 240 cm 0.6100 Lbr 48,400.00 29,524.00
- Paku asbes 0.0200 Kg 330.00 6.60

Tenaga 6,468.00
- Pekerja 0.1200 Oh 30,250.00 3,630.00
- Tukang Kayu 0.0600 Oh 38,500.00 2,310.00
- Kepala Tukang Kayu 0.0060 Oh 44,000.00 264.00
- Mandor 0.0060 Oh 44,000.00 264.00

VIII. 19 1 M2 Pasang atap seng BJLS 0,2 gelombang P = 210 cm 36,119.60


SNI Bahan 29,651.60
03-3436-2002 - Seng BJLS 0,2 gelombang P = 210 cm 0.7000 Lbr 42,350.00 29,645.00
- Paku asbes 0.0200 Kg 330.00 6.60

Tenaga 6,468.00
- Pekerja 0.1200 Oh 30,250.00 3,630.00
- Tukang Kayu 0.0600 Oh 38,500.00 2,310.00
- Kepala Tukang Kayu 0.0060 Oh 44,000.00 264.00
- Mandor 0.0060 Oh 44,000.00 264.00

VIII. 20 1 M2 Pasang atap seng BJLS 0,2 gelombang P = 180 cm 36,603.60


SNI Bahan 30,135.60
03-3436-2002 - Seng BJLS 0,2 gelombang P = 180 cm 0.8300 Lbr 36,300.00 30,129.00
- Paku asbes 0.0200 Kg 330.00 6.60

Tenaga 6,468.00
- Pekerja 0.1200 Oh 30,250.00 3,630.00
- Tukang Kayu 0.0600 Oh 38,500.00 2,310.00
- Kepala Tukang Kayu 0.0060 Oh 44,000.00 264.00
- Mandor 0.0060 Oh 44,000.00 264.00

VIII. 21 1 M' Pasang nok paten 1,05 m 43,081.50


SNI Bahan 34,980.00
03-3436-2002 - Asbes nok gelombang kecil 1.2000 Lbr 27,500.00 33,000.00
- Paku asbes 6.0000 Bh 330.00 1,980.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 61


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
Tenaga 8,101.50
- Pekerja 0.0840 Oh 30,250.00 2,541.00
- Tukang Kayu 0.1250 Oh 38,500.00 4,812.50
- Kepala Tukang Kayu 0.0130 Oh 44,000.00 572.00
- Mandor 0.0040 Oh 44,000.00 176.00

VIII. 22 1 M' Pasang nok paten 1,08 m 72,781.50


SNI Bahan 64,680.00
03-3436-2002 - Asbes nok gelombang besar 1.2000 Lbr 52,250.00 62,700.00
- Paku asbes 6.0000 Bh 330.00 1,980.00

Tenaga 8,101.50
- Pekerja 0.0840 Oh 30,250.00 2,541.00
- Tukang Kayu 0.1250 Oh 38,500.00 4,812.50
- Kepala Tukang Kayu 0.0130 Oh 44,000.00 572.00
- Mandor 0.0040 Oh 44,000.00 176.00

VIII. 23 1 M2 pasang alluminium foil/sisalation 16,852.00


SNI Bahan 9,817.50
03-3436-2002 - Alumunium foil 1.0500 M2 9,350.00 9,817.50

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 62


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
Tenaga 7,034.50
- Pekerja 0.1500 Oh 30,250.00 4,537.50
- Tukang Kayu 0.0500 Oh 38,500.00 1,925.00
- Kepala Tukang Kayu 0.0050 Oh 44,000.00 220.00
- Mandor 0.0080 Oh 44,000.00 352.00

VIII. 24 1 M' Pasang talang datar, seng bjls 28 71,186.50


Bahan 50,094.00
- Seng BJLS 0,30 lembaran L = 60 cm 0.5000 Lbr 18,700.00 9,350.00
- Paku usuk 0.0150 Kg 11,000.00 165.00
- Papan kayu meranti 0.0096 M3 3,740,000.00 35,904.00
- Cat Meni Besi "altex" 0.2500 Kg 18,700.00 4,675.00

Tenaga 21,092.50
- Pekerja 0.1500 Oh 30,250.00 4,537.50
- Tukang Kayu 0.4000 Oh 38,500.00 15,400.00
- Kepala Tukang Kayu 0.0250 Oh 44,000.00 1,100.00
- Mandor 0.0013 Oh 44,000.00 55.00

VIII. 25 1 M' Pasang talang miring, seng bjls 28 103,950.00


Bahan 86,185.00
- Seng BJLS 0,30 lembaran L = 60 cm 0.5000 Lbr 18,700.00 9,350.00
- Paku usuk 0.0150 Kg 11,000.00 165.00
- Papan kayu meranti 0.0190 M3 3,740,000.00 71,060.00
- Cat Meni Besi "altex" 0.3000 Kg 18,700.00 5,610.00

Tenaga 17,765.00
- Pekerja 0.0400 Oh 30,250.00 1,210.00
- Tukang Kayu 0.4000 Oh 38,500.00 15,400.00
- Kepala Tukang Kayu 0.0250 Oh 44,000.00 1,100.00
- Mandor 0.0013 Oh 44,000.00 55.00

VIII. 26 1 M' Pasang talang 1/2 lingkaran D-10 cm, seng bjls 28 99,687.50
Bahan 84,370.00
- Seng BJLS 0,30 lembaran L = 90 cm 0.3000 Lbr 24,200.00 7,260.00
- Paku usuk 0.1000 Kg 11,000.00 1,100.00
- Papan kayu meranti 0.0190 M3 3,740,000.00 71,060.00
- Besi Strip 0.5000 Kg 9,900.00 4,950.00

Tenaga 15,317.50
- Pekerja 0.1500 Oh 30,250.00 4,537.50
- Tukang Kayu 0.2500 Oh 38,500.00 9,625.00
- Kepala Tukang Kayu 0.0250 Oh 44,000.00 1,100.00
- Mandor 0.0013 Oh 44,000.00 55.00

VIII. 27 1 M' Pasang talang 1/2 lingkaran D-10 cm, seng bjls 24 99,357.50
Bahan 84,040.00
- Seng BJLS 0,20 lembaran L = 90 cm 0.3000 Lbr 23,100.00 6,930.00
- Paku usuk 0.1000 Kg 11,000.00 1,100.00
- Papan kayu meranti 0.0190 M3 3,740,000.00 71,060.00
- Besi Strip 0.5000 Kg 9,900.00 4,950.00

Tenaga 15,317.50
- Pekerja 0.1500 Oh 30,250.00 4,537.50
- Tukang Kayu 0.2500 Oh 38,500.00 9,625.00
- Kepala Tukang Kayu 0.0250 Oh 44,000.00 1,100.00
- Mandor 0.0013 Oh 44,000.00 55.00

IX. PEKERJAAN PASANG LANGIT-LANGIT


IX. 1 1 M2 Pasang langit-langit asbes "Elepent"(1,00 x 1,00) m, tebal 3 mm 19,354.50
SNI Bahan 15,268.00
03-2839-2008 - Asbes plat (100 x 100 x 0,3) Elephant 1.1000 Lbr 13,750.00 15,125.00
- Paku eternit 0.0100 Kg 14,300.00 143.00

Tenaga 4,086.50
- Pekerja 0.0300 Oh 30,250.00 907.50
- Tukang Kayu 0.0700 Oh 38,500.00 2,695.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 63


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
- Kepala Tukang Kayu 0.0070 Oh 44,000.00 308.00
- Mandor 0.0040 Oh 44,000.00 176.00

IX. 2 1 M2 Pasang langit-langit asbes "Atrisco"(1,00 x 1,00) m, tebal 3 mm 19,354.50


SNI Bahan 15,268.00
03-2839-2008 - Asbes plat (100 x 100 x 0,3) Atrisco 1.1000 Lbr 13,750.00 15,125.00
- Paku eternit 0.0100 Kg 14,300.00 143.00

Tenaga 4,086.50
- Pekerja 0.0300 Oh 30,250.00 907.50
- Tukang Kayu 0.0700 Oh 38,500.00 2,695.00
- Kepala Tukang Kayu 0.0070 Oh 44,000.00 308.00
- Mandor 0.0040 Oh 44,000.00 176.00

IX. 3 1 M2 Pasang langit-langit asbes "Kerang super" (1,00 x 1,00) m, tebal 3 mm 13,304.50
SNI Bahan 9,218.00
03-2839-2008 - Asbes plat (100 x 100 x 0,3) Kerang super 1.1000 Lbr 8,250.00 9,075.00
- Paku eternit 0.0100 Kg 14,300.00 143.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 64


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
Tenaga 4,086.50
- Pekerja 0.0300 Oh 30,250.00 907.50
- Tukang Kayu 0.0700 Oh 38,500.00 2,695.00
- Kepala Tukang Kayu 0.0070 Oh 44,000.00 308.00
- Mandor 0.0040 Oh 44,000.00 176.00

IX. 4 1 M2 Pasang langit-langit asbes "Djabes" (1,00 x 1,00) m, tebal 3 mm 18,749.50


SNI Bahan 14,663.00
03-2839-2008 - Asbes plat (100 x 100 x 0,3) Djabes 1.1000 Lbr 13,200.00 14,520.00
- Paku eternit 0.0100 Kg 14,300.00 143.00

Tenaga 4,086.50
- Pekerja 0.0300 Oh 30,250.00 907.50
- Tukang Kayu 0.0700 Oh 38,500.00 2,695.00
- Kepala Tukang Kayu 0.0070 Oh 44,000.00 308.00
- Mandor 0.0040 Oh 44,000.00 176.00

IX. 5 1 M2 Pasang langit-langit playwood (30 x 60) cm, tebal 4 mm 29,620.25


SNI Bahan 22,085.25
03-2839-2008 - Plywood 4 mm 0.3750 Lbr 57,750.00 21,656.25
- Paku eternit 0.0300 Kg 14,300.00 429.00

Tenaga 7,535.00
- Pekerja 0.1000 Oh 30,250.00 3,025.00
- Tukang Kayu 0.1000 Oh 38,500.00 3,850.00
- Kepala Tukang Kayu 0.0100 Oh 44,000.00 440.00
- Mandor 0.0050 Oh 44,000.00 220.00

IX. 6 1 M2 Pasang langit-langit playwood (30 x 60) cm, tebal 6 mm 36,839.00


SNI Bahan 29,304.00
03-2839-2008 - Plywood 6 mm 0.3750 Lbr 77,000.00 28,875.00
- Paku eternit 0.0300 Kg 14,300.00 429.00

Tenaga 7,535.00
- Pekerja 0.1000 Oh 30,250.00 3,025.00
- Tukang Kayu 0.1000 Oh 38,500.00 3,850.00
- Kepala Tukang Kayu 0.0100 Oh 44,000.00 440.00
- Mandor 0.0050 Oh 44,000.00 220.00

IX. 7 1 M2 Pasang langit-langit playwood (60 x 120) cm, tebal 4 mm 29,620.25


SNI Bahan 22,085.25
03-2839-2008 - Plywood 4 mm 0.3750 Lbr 57,750.00 21,656.25
- Paku eternit 0.0300 Kg 14,300.00 429.00

Tenaga 7,535.00
- Pekerja 0.1000 Oh 30,250.00 3,025.00
- Tukang Kayu 0.1000 Oh 38,500.00 3,850.00
- Kepala Tukang Kayu 0.0100 Oh 44,000.00 440.00
- Mandor 0.0050 Oh 44,000.00 220.00

IX. 8 1 M2 Pasang langit-langit playwood (60 x 120) cm, tebal 6 mm 36,839.00


SNI Bahan 29,304.00
03-2839-2008 - Plywood 6 mm 0.3750 Lbr 77,000.00 28,875.00
- Paku eternit 0.0300 Kg 14,300.00 429.00

Tenaga 7,535.00
- Pekerja 0.1000 Oh 30,250.00 3,025.00
- Tukang Kayu 0.1000 Oh 38,500.00 3,850.00
- Kepala Tukang Kayu 0.0100 Oh 44,000.00 440.00
- Mandor 0.0050 Oh 44,000.00 220.00

IX. 9 1 M2 Pasang langit-langit teakwood (30 x 60) cm, tebal 4 mm 38,901.50


SNI Bahan 31,366.50
03-2839-2008 - Teakwood 3 mm 120 x 240 cm 0.3750 Lbr 82,500.00 30,937.50
- Paku eternit 0.0300 Kg 14,300.00 429.00

Tenaga 7,535.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 65


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
- Pekerja 0.1000 Oh 30,250.00 3,025.00
- Tukang Kayu 0.1000 Oh 38,500.00 3,850.00
- Kepala Tukang Kayu 0.0100 Oh 44,000.00 440.00
- Mandor 0.0050 Oh 44,000.00 220.00

IX. 10 1 M2 Pasang langit-langit teakwood (60 x 120) cm, tebal 4 mm 38,901.50


SNI Bahan 31,366.50
03-2839-2008 - Teakwood 3 mm 120 x 240 cm 0.3750 Lbr 82,500.00 30,937.50
- Paku eternit 0.0300 Kg 14,300.00 429.00

Tenaga 7,535.00
- Pekerja 0.1000 Oh 30,250.00 3,025.00
- Tukang Kayu 0.1000 Oh 38,500.00 3,850.00
- Kepala Tukang Kayu 0.0100 Oh 44,000.00 440.00
- Mandor 0.0050 Oh 44,000.00 220.00

IX. 11 1 M2 Pasang langit-langit lat kayu jati lokal 204,523.00


SNI Bahan 172,293.00
03-2838-2002 - Papan kayu jati lokal 0.0240 M3 7,150,000.00 171,600.00
- Paku eternit 0.0100 Kg 14,300.00 143.00
- Lem kayu "fox" 0.0500 Kg 11,000.00 550.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 66


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
Tenaga 32,230.00
- Pekerja 0.2000 Oh 30,250.00 6,050.00
- Tukang Kayu 0.6000 Oh 38,500.00 23,100.00
- Kepala Tukang Kayu 0.0600 Oh 44,000.00 2,640.00
- Mandor 0.0100 Oh 44,000.00 440.00

IX. 12 1 M2 Pasang langit-langit lat kayu kamper 230,890.00


SNI Bahan 198,660.00
03-2838-2002 - Papan kayu kamper 0.0240 M3 8,250,000.00 198,000.00
- Paku reng 0.0100 Kg 11,000.00 110.00
- Lem kayu "fox" 0.0500 Kg 11,000.00 550.00

Tenaga 32,230.00
- Pekerja 0.2000 Oh 30,250.00 6,050.00
- Tukang Kayu 0.6000 Oh 38,500.00 23,100.00
- Kepala Tukang Kayu 0.0600 Oh 44,000.00 2,640.00
- Mandor 0.0100 Oh 44,000.00 440.00

IX. 13 1 M1 List pasang list langit-langit kayu dibuat profil 12,562.00


SNI Bahan 8,772.50
03-2839-2008 - List profil kayu 1.0500 M3 8,250.00 8,662.50
- Paku reng 0.0100 Kg 11,000.00 110.00

Tenaga 3,789.50
- Pekerja 0.0500 Oh 30,250.00 1,512.50
- Tukang Kayu 0.0500 Oh 38,500.00 1,925.00
- Kepala Tukang Kayu 0.0050 Oh 44,000.00 220.00
- Mandor 0.0030 Oh 44,000.00 132.00

IX. 14 1 M2 Pasang langit-langit asbes "Kerang super" (1,00 x 1,00) m, tebal 3 mm, rangka kayu meranti 68,904.00
SNI Bahan 49,335.00
03-2838-2002 - Kayu meranti 0.0120 M3 3,300,000.00 39,600.00
- Paku reng 0.0600 Kg 11,000.00 660.00
- Asbes plat (100 x 100 x 0,3) Kerang super 1.1000 Lbr 8,250.00 9,075.00

Tenaga 19,569.00
- Pekerja 0.1800 Oh 30,250.00 5,445.00
- Tukang Kayu 0.3200 Oh 38,500.00 12,320.00
- Kepala Tukang Kayu 0.0320 Oh 44,000.00 1,408.00
- Mandor 0.0090 Oh 44,000.00 396.00

IX. 15 1 M2 Pasang langit-langit Triplek 4 mm + rangka kayu meranti 125,004.00


SNI Bahan 99,082.50
03-2838-2002 - Kayu meranti 0.0230 M3 3,300,000.00 75,900.00
- Paku reng 0.0600 Kg 11,000.00 660.00
- Plywood 4 mm 0.3900 Lbr 57,750.00 22,522.50

Tenaga 25,921.50
- Pekerja 0.2700 Oh 30,250.00 8,167.50
- Tukang Kayu 0.4000 Oh 38,500.00 15,400.00
- Kepala Tukang Kayu 0.0400 Oh 44,000.00 1,760.00
- Mandor 0.0135 Oh 44,000.00 594.00

IX. 16 1 M2 Pasang langit-langit gypsum board, tebal 9 mm 27,625.40


SNI Bahan 22,235.40
03-2839-2008 - Gypsum Board 9 mm " Elephant " 0.3640 Lbr 56,100.00 20,420.40
- Paku Gypsum 0.1100 Kg 16,500.00 1,815.00

Tenaga 5,390.00
- Pekerja 0.1000 Oh 30,250.00 3,025.00
- Tukang Kayu 0.0500 Oh 38,500.00 1,925.00
- Kepala Tukang Kayu 0.0050 Oh 44,000.00 220.00
- Mandor 0.0050 Oh 44,000.00 220.00

IX. 17 1 M2 Pasang langit-langit gypsum board tebal 9 mm, rangka 60 x 120 kayu kamper 140,877.94
Bahan 117,216.94
- Kayu Kamper 0.0130 M3 7,150,000.00 92,950.00
- Gypsum Board 9 mm " Elephant " 0.3640 Lbr 56,100.00 20,420.40

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 67


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
- Kassa gypsum 0.0500 Roll 7,700.00 385.00
- Cornice adhesive (tepung gypsum) @ 20 kg "A-plus" 0.4500 Kg 2,915.00 1,311.75
- Casting @ 20 kg "A-plus" 0.0030 Kg 1,595.00 4.79
- Paku Gypsum 0.0500 Kg 16,500.00 825.00
- Paku usuk 0.1200 Kg 11,000.00 1,320.00

Tenaga 23,661.00
- Pekerja 0.2400 Oh 30,250.00 7,260.00
- Tukang Kayu 0.3700 Oh 38,500.00 14,245.00
- Kepala Tukang Kayu 0.0370 Oh 44,000.00 1,628.00
- Mandor 0.0120 Oh 44,000.00 528.00

IX. 18 1 M2 Pasang langit-langit gypsum board tebal 9 mm, rangka 60 x 120 kayu meranti 90,827.94
Bahan 67,166.94
- Kayu meranti 0.0130 M3 3,300,000.00 42,900.00
- Gypsum Board 9 mm " Elephant " 0.3640 Lbr 56,100.00 20,420.40
- Kassa gypsum 0.0500 Roll 7,700.00 385.00
- Cornice adhesive (tepung gypsum) @ 20 kg "A-plus" 0.4500 Kg 2,915.00 1,311.75
- Casting @ 20 kg "A-plus" 0.0030 Kg 1,595.00 4.79
- Paku Gypsum 0.0500 Kg 16,500.00 825.00
- Paku usuk 0.1200 Kg 11,000.00 1,320.00

Tenaga 23,661.00
- Pekerja 0.2400 Oh 30,250.00 7,260.00
- Tukang Kayu 0.3700 Oh 38,500.00 14,245.00
- Kepala Tukang Kayu 0.0370 Oh 44,000.00 1,628.00
- Mandor 0.0120 Oh 44,000.00 528.00

IX. 19 1 M2 Pasang langit-langit gypsum board tebal 9 mm, rangka 60 x 120 kayu kruing 112,277.94
Bahan 88,616.94
- Kayu kruing 0.0130 M3 4,950,000.00 64,350.00
- Gypsum Board 9 mm " Elephant " 0.3640 Lbr 56,100.00 20,420.40
- Kassa gypsum 0.0500 Roll 7,700.00 385.00
- Cornice adhesive (tepung gypsum) @ 20 kg "A-plus" 0.4500 Kg 2,915.00 1,311.75
- Casting @ 20 kg "A-plus" 0.0030 Kg 1,595.00 4.79
- Paku Gypsum 0.0500 Kg 16,500.00 825.00
- Paku usuk 0.1200 Kg 11,000.00 1,320.00

Tenaga 23,661.00
- Pekerja 0.2400 Oh 30,250.00 7,260.00
- Tukang Kayu 0.3700 Oh 38,500.00 14,245.00
- Kepala Tukang Kayu 0.0370 Oh 44,000.00 1,628.00
- Mandor 0.0120 Oh 44,000.00 528.00
IX. 20 1 M2 Pasang langit-langit gypsum board tebal 9 mm, rangka 60 x 120 kayu bengkirai 160,182.94
Bahan 136,521.94
- Kayu bengkirai 0.0130 M3 8,635,000.00 112,255.00
- Gypsum Board 9 mm " Elephant " 0.3640 Lbr 56,100.00 20,420.40
- Kassa gypsum 0.0500 Roll 7,700.00 385.00
- Cornice adhesive (tepung gypsum) @ 20 kg "A-plus" 0.4500 Kg 2,915.00 1,311.75
- Casting @ 20 kg "A-plus" 0.0030 Kg 1,595.00 4.79
- Paku Gypsum 0.0500 Kg 16,500.00 825.00
- Paku usuk 0.1200 Kg 11,000.00 1,320.00

Tenaga 23,661.00
- Pekerja 0.2400 Oh 30,250.00 7,260.00
- Tukang Kayu 0.3700 Oh 38,500.00 14,245.00
- Kepala Tukang Kayu 0.0370 Oh 44,000.00 1,628.00
- Mandor 0.0120 Oh 44,000.00 528.00

IX. 21 1 M2 Pasang langit-langit kalsiboard tebal 3,5 mm, rangka 60 x 120 kayu kamper 137,089.54
Bahan 113,428.54
- Kayu Kamper 0.0130 M3 7,150,000.00 92,950.00
- Kalsiboard 3,5 mm 0.3600 Lbr 46,200.00 16,632.00
- Kassa gypsum 0.0500 Roll 7,700.00 385.00
- Cornice adhesive (tepung gypsum) @ 20 kg "A-plus" 0.4500 Kg 2,915.00 1,311.75
- Casting @ 20 kg "A-plus" 0.0030 Kg 1,595.00 4.79
- Paku Gypsum 0.0500 Kg 16,500.00 825.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 68


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
- Paku usuk 0.1200 Kg 11,000.00 1,320.00

Tenaga 23,661.00
- Pekerja 0.2400 Oh 30,250.00 7,260.00
- Tukang Kayu 0.3700 Oh 38,500.00 14,245.00
- Kepala Tukang Kayu 0.0370 Oh 44,000.00 1,628.00
- Mandor 0.0120 Oh 44,000.00 528.00

IX. 22 1 M2 Pasang langit-langit kalsiboard tebal 3,5 mm, rangka 60 x 120 kayu meranti 87,404.54
Bahan 63,743.54
- Kayu meranti 0.0130 M3 3,300,000.00 42,900.00
- Kalsiboard 3,5 mm 0.3600 Lbr 46,200.00 16,632.00
- Kassa gypsum 0.0500 Roll 15,000.00 750.00
- Cornice adhesive (tepung gypsum) @ 20 kg "A-plus" 0.4500 Kg 2,915.00 1,311.75
- Casting @ 20 kg "A-plus" 0.0030 Kg 1,595.00 4.79
- Paku Gypsum 0.0500 Kg 16,500.00 825.00
- Paku usuk 0.1200 Kg 11,000.00 1,320.00

Tenaga 23,661.00
- Pekerja 0.2400 Oh 30,250.00 7,260.00
- Tukang Kayu 0.3700 Oh 38,500.00 14,245.00
- Kepala Tukang Kayu 0.0370 Oh 44,000.00 1,628.00
- Mandor 0.0120 Oh 44,000.00 528.00

IX. 23 1 M2 Pasang langit-langit kalsiboard tebal 3,5 mm, rangka 60 x 120 kayu kruing 108,489.54
Bahan 84,828.54
- Kayu kruing 0.0130 M3 4,950,000.00 64,350.00
- Kalsiboard 3,5 mm 0.3600 Lbr 46,200.00 16,632.00
- Kassa gypsum 0.0500 Roll 7,700.00 385.00
- Cornice adhesive (tepung gypsum) @ 20 kg "A-plus" 0.4500 Kg 2,915.00 1,311.75
- Casting @ 20 kg "A-plus" 0.0030 Kg 1,595.00 4.79
- Paku Gypsum 0.0500 Kg 16,500.00 825.00
- Paku usuk 0.1200 Kg 11,000.00 1,320.00

Tenaga 23,661.00
- Pekerja 0.2400 Oh 30,250.00 7,260.00
- Tukang Kayu 0.3700 Oh 38,500.00 14,245.00
- Kepala Tukang Kayu 0.0370 Oh 44,000.00 1,628.00
- Mandor 0.0120 Oh 44,000.00 528.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 69


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
IX. 24 1 M2 Pasang langit-langit kalsiboard tebal 3,5 mm, rangka 60 x 120 kayu bengkirai 156,394.54
Bahan 132,733.54
- Kayu bengkirai 0.0130 M3 8,635,000.00 112,255.00
- Kalsiboard 3,5 mm 0.3600 Lbr 46,200.00 16,632.00
- Kassa gypsum 0.0500 Roll 7,700.00 385.00
- Cornice adhesive (tepung gypsum) @ 20 kg "A-plus" 0.4500 Kg 2,915.00 1,311.75
- Casting @ 20 kg "A-plus" 0.0030 Kg 1,595.00 4.79
- Paku Gypsum 0.0500 Kg 16,500.00 825.00
- Paku usuk 0.1200 Kg 11,000.00 1,320.00

Tenaga 23,661.00
- Pekerja 0.2400 Oh 30,250.00 7,260.00
- Tukang Kayu 0.3700 Oh 38,500.00 14,245.00
- Kepala Tukang Kayu 0.0370 Oh 44,000.00 1,628.00
- Mandor 0.0120 Oh 44,000.00 528.00

X. PEKERJAAN SANITASI
X. 1 Memasang 1 buah kloset duduk/monoblok 1,018,105.00
Bahan 932,800.00
- Closet duduk standar INA lengkap warna muda 1.0000 Bh 880,000.00 880,000.00
- Perlengkapan 6% 52,800.00

Tenaga 85,305.00
- Pekerja 1.1000 Oh 30,250.00 33,275.00
- Tukang Batu 1.1000 Oh 38,500.00 42,350.00
- Kepala Tukang Batu 0.1100 Oh 44,000.00 4,840.00
- Mandor 0.1100 Oh 44,000.00 4,840.00

X. 2 Memasang 1 buah kloset jongkok 146,657.50


Bahan 104,005.00
- Closet jongkok type CE 8 standard INA 1.0000 Bh 96,250.00 96,250.00
- Semen PC ( Portland Cement ) 40 kg 6.0000 Kg 1,100.00 6,600.00
- Pasir pasang (kaliworo) 0.0100 M3 115,500.00 1,155.00

Tenaga 42,652.50
- Pekerja 0.5500 Oh 30,250.00 16,637.50
- Tukang Batu 0.5500 Oh 38,500.00 21,175.00
- Kepala Tukang Batu 0.0550 Oh 44,000.00 2,420.00
- Mandor 0.0550 Oh 44,000.00 2,420.00

X. 3 Memasang 1 buah urinoir 1,368,604.00


Bahan 1,291,054.00
- Urinoir lengkap INA 1.0000 Bh 1,210,000.00 1,210,000.00
- Perlengkapan 6% 72,600.00
- Semen PC ( Portland Cement ) 40 Kg 6.0000 1,224.00 7,344.00
- Pasir Pasang (Kali woro) 0.0100 111,000.00 1,110.00

Tenaga 77,550.00
- Pekerja 1.0000 Oh 30,250.00 30,250.00
- Tukang Batu 1.0000 Oh 38,500.00 38,500.00
- Kepala Tukang Batu 0.1000 Oh 44,000.00 4,400.00
- Mandor 0.1000 Oh 44,000.00 4,400.00

X. 4 Memasang 1 buah wastafel kecil 313,005.00


Bahan 209,880.00
- Wastafel standar uk. Kecil komplit INA 1.0000 Bh 198,000.00 198,000.00
- Perlengkapan 6% 11,880.00

Tenaga 103,125.00
- Pekerja 1.2000 Oh 30,250.00 36,300.00
- Tukang Batu 1.4500 Oh 38,500.00 55,825.00
- Kepala Tukang Batu 0.1500 Oh 44,000.00 6,600.00
- Mandor 0.1000 Oh 44,000.00 4,400.00

X. 5 Memasang 1 buah wastafel besar 347,985.00


Bahan 244,860.00
- Wastafel standar uk. Besar komplit INA 1.0000 Bh 231,000.00 231,000.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 70


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
- Perlengkapan 6% 13,860.00

Tenaga 103,125.00
- Pekerja 1.2000 Oh 30,250.00 36,300.00
- Tukang Batu 1.4500 Oh 38,500.00 55,825.00
- Kepala Tukang Batu 0.1500 Oh 44,000.00 6,600.00
- Mandor 0.1000 Oh 44,000.00 4,400.00

X. 6 Memasang 1 buah bak mandi buthtub fiber 658,075.00


Bahan 557,755.00
- Bak mandi buthtub standar bahan fiber 1.0000 Bh 550,000.00 550,000.00
- Semen PC ( Portland Cement ) 40 kg 6.0000 Kg 1,100.00 6,600.00
- Pasir pasang (kaliworo) 0.0100 M3 115,500.00 1,155.00

Tenaga 100,320.00
- Pekerja 2.1000 Oh 30,250.00 63,525.00
- Tukang Batu 0.7500 Oh 38,500.00 28,875.00
- Kepala Tukang Batu 0.0700 Oh 44,000.00 3,080.00
- Mandor 0.1100 Oh 44,000.00 4,840.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 71


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
X. 7 Memasang 1 buah bak mandi fiberglass volume 0,30 m3 361,900.00
Bahan 174,900.00
- bak mandi fiberglass 0,3 m3 1.0000 Bh 165,000.00 165,000.00
- Perlengkapan 6% 9,900.00

Tenaga 187,000.00
- Pekerja 1.8000 Oh 30,250.00 54,450.00
- Tukang Batu 2.7000 Oh 38,500.00 103,950.00
- Kepala Tukang Batu 0.5400 Oh 44,000.00 23,760.00
- Mandor 0.1100 Oh 44,000.00 4,840.00

X. 8 Memasang 1 buah bak mandi batu bata volume 0,30 m3 908,815.60


Bahan 585,415.60
- Pasangan 1/2 batu bata 1 : 5 0.4000 M3 510,004.00 204,001.60
- Semen PC ( Portland Cement ) 40 kg 120.0000 Kg 1,100.00 132,000.00
- Pasir pasang (kaliworo) 0.3000 M3 115,500.00 34,650.00
- Keramik 20 x 25 cm warna polos "kia" 4.3560 m2 44,000.00 191,664.00
- Semen Warna 6.0000 Kg 3,850.00 23,100.00

Tenaga 323,400.00
- Pekerja 6.0000 Oh 30,250.00 181,500.00
- Tukang Batu 3.0000 Oh 38,500.00 115,500.00
- Kepala Tukang Batu 0.3000 Oh 44,000.00 13,200.00
- Mandor 0.3000 Oh 44,000.00 13,200.00

X. 9 Memasang 1 buah badkip fiber 644,911.58


Bahan 641,300.00
- Bandkip fiber 1.0000 Bh 605,000.00 605,000.00
- Perlengkapan 6% 36,300.00

Tenaga 3,611.58
- Pekerja 0.0075 Oh 30,250.00 226.88
- Tukang Batu 0.0750 Oh 38,500.00 2,887.50
- Kepala Tukang Batu 0.0075 Oh 44,000.00 330.00
- Mandor 0.0038 Oh 44,000.00 167.20

X. 10 Membuat 1 buah bak beton volume 1 M3 air 4,687,449.80


Bahan 4,329,124.80
- Beton 1 : 1 1/2 : 2 1/2 0.9000 M3 779,955.00 701,959.50
- Besi Beton ulir 180.0000 Kg 8,800.00 1,584,000.00
- Pipa Galvanis medium (GIP) 1 1/4" 8.0000 M3 220,000.00 1,760,000.00
- Keramik 20 x 25 cm warna polos "kia" 5.0000 M2 44,000.00 220,000.00
- Perlengkapan 6% 63,165.30

Tenaga 358,325.00
- Pekerja 3.5000 Oh 30,250.00 105,875.00
- Tukang Batu 4.5000 Oh 38,500.00 173,250.00
- Kepala Tukang Batu 0.9000 Oh 44,000.00 39,600.00
- Mandor 0.9000 Oh 44,000.00 39,600.00

X. 11 Memasang 1 M' Got U-15 46,895.03


Bahan 16,895.03
- Pasangan batu bata 1 : 4 0.0060 M3 524,172.00 3,145.03
- Got U-15 1.0000 Bh 13,750.00 13,750.00

Tenaga 30,000.00
- Upah 1.0000 30,000.00 30,000.00

X. 12 Memasang 1 M' Got U-20 52,395.03


Bahan 22,395.03
- Pasangan batu bata 1 : 4 0.0060 M3 524,172.00 3,145.03
- Buis beton U 20 cm 1.0000 Bh 19,250.00 19,250.00

Tenaga 30,000.00
- Upah 1.0000 30,000.00 30,000.00

X. 13 Memasang 1 M' Got U-30 55,145.03

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 72


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
Bahan 25,145.03
- Pasangan batu bata 1 : 4 0.0060 M3 524,172.00 3,145.03
- Buis beton U 30 cm 1.0000 Bh 22,000.00 22,000.00

Tenaga 30,000.00
- Upah 1.0000 30,000.00 30,000.00

X. 14 Memasang 1 buah bak kontrol pasangan batu bata ukuran (30 x 30) cm, tinggi 35 cm 274,345.50
Bahan 137,698.00
- Batu Bata lokal 102.0000 Bh 484.00 49,368.00
- Semen PC ( Portland Cement ) 40 kg 44.0000 Kg 1,100.00 48,400.00
- Pasir pasang (kaliworo) 0.0700 M3 115,500.00 8,085.00
- Koral Beton 0.0700 M3 143,000.00 10,010.00
- Besi Beton polos 1.6000 Kg 8,800.00 14,080.00
- Pasir beton (muntilan) 0.0600 M3 129,250.00 7,755.00

Tenaga 136,647.50
- Pekerja 3.2000 Oh 30,250.00 96,800.00
- Tukang Batu 1.0150 Oh 38,500.00 39,077.50
- Kepala Tukang Batu 0.0015 Oh 44,000.00 66.00
- Mandor 0.0160 Oh 44,000.00 704.00

X. 15 Memasang 1 buah bak kontrol pasangan batu bata ukuran (45 x 45) cm, tinggi 50 cm 288,145.00
Bahan 221,787.50
- Batu Bata lokal 175.0000 Bh 484.00 84,700.00
- Semen PC ( Portland Cement ) 40 kg 77.0000 Kg 1,100.00 84,700.00
- Pasir pasang (kaliworo) 0.1300 M3 115,500.00 15,015.00
- Koral Beton 0.0200 M3 143,000.00 2,860.00
- Besi Beton polos 2.6000 Kg 8,800.00 22,880.00
- Pasir beton (muntilan) 0.0900 M3 129,250.00 11,632.50

Tenaga 66,357.50
- Pekerja 1.4200 Oh 30,250.00 42,955.00
- Tukang Batu 0.4730 Oh 38,500.00 18,210.50
- Kepala Tukang Batu 0.0470 Oh 44,000.00 2,068.00
- Mandor 0.0710 Oh 44,000.00 3,124.00

X. 16 Memasang 1 buah bak kontrol pasangan batu bata ukuran (60 x 60) cm, tinggi 65 cm 440,231.00
Bahan 335,401.00
- Batu Bata lokal 260.0000 Bh 484.00 125,840.00
- Semen PC ( Portland Cement ) 40 kg 114.0000 Kg 1,100.00 125,400.00
- Pasir pasang (kaliworo) 0.1840 M3 115,500.00 21,252.00
- Koral Beton 0.0330 M3 143,000.00 4,719.00
- Besi Beton polos 4.8500 Kg 8,800.00 42,680.00
- Pasir beton (muntilan) 0.1200 M3 129,250.00 15,510.00

Tenaga 104,830.00
- Pekerja 2.1600 Oh 30,250.00 65,340.00
- Tukang Batu 0.7200 Oh 38,500.00 27,720.00
- Kepala Tukang Batu 0.0720 Oh 44,000.00 3,168.00
- Mandor 0.1080 Oh 44,000.00 4,752.00
- Tukang gali 0.1000 Oh 38,500.00 3,850.00

X. 17 Memasang 1 M' pipa galvanis diameter 1/2" 35,099.17


Bahan 28,416.67
- Pipa Galvanis medium (GIP) 1/2" 1.2000 M' 18,333.33 22,000.00
- Perlengkapan 35% 6,416.67

Tenaga 6,682.50
- Tukang Gali 0.0540 Oh 30,250.00 1,633.50
- Tukang Leideng 0.0900 Oh 38,500.00 3,465.00
- Kepala Tukang Batu 0.0090 Oh 44,000.00 396.00
- Mandor 0.0270 Oh 44,000.00 1,188.00

X. 18 Memasang 1 M' pipa galvanis diameter 3/4" 40,782.50


Bahan 34,100.00
- Pipa Galvanis medium (GIP) 3/4" 1.2000 M' 22,000.00 26,400.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 73


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
- Perlengkapan 35% 7,700.00

Tenaga 6,682.50
- Tukang Gali 0.0540 Oh 30,250.00 1,633.50
- Tukang Leideng 0.0900 Oh 38,500.00 3,465.00
- Kepala Tukang Batu 0.0090 Oh 44,000.00 396.00
- Mandor 0.0270 Oh 44,000.00 1,188.00

X. 19 Memasang 1 M' pipa galvanis diameter 1" 50,728.33


Bahan 44,045.83
- Pipa Galvanis medium (GIP) 1" 1.2000 M' 28,416.67 34,100.00
- Perlengkapan 35% 9,945.83

Tenaga 6,682.50
- Tukang Gali 0.0540 Oh 30,250.00 1,633.50
- Tukang Leideng 0.0900 Oh 38,500.00 3,465.00
- Kepala Tukang Batu 0.0090 Oh 44,000.00 396.00
- Mandor 0.0270 Oh 44,000.00 1,188.00

X. 20 Memasang 1 M' pipa galvanis diameter 1 1/2" 75,164.10


Bahan 63,937.50
- Pipa Galvanis medium (GIP) 1 1/2" 1.2000 M' 41,250.00 49,500.00
- Perlengkapan 35% 14,437.50

Tenaga 11,226.60
- Tukang Gali 0.1080 Oh 30,250.00 3,267.00
- Tukang Leideng 0.1800 Oh 38,500.00 6,930.00
- Kepala Tukang Batu 0.0180 Oh 44,000.00 792.00
- Mandor 0.0054 Oh 44,000.00 237.60

X. 21 Memasang 1 M' pipa galvanis diameter 2" 93,634.93


Bahan 82,408.33
- Pipa Galvanis medium (GIP) 2" 1.2000 M' 53,166.67 63,800.00
- Perlengkapan 35% 18,608.33

Tenaga 11,226.60
- Tukang Gali 0.1080 Oh 30,250.00 3,267.00
- Tukang Leideng 0.1800 Oh 38,500.00 6,930.00
- Kepala Tukang Batu 0.0180 Oh 44,000.00 792.00
- Mandor 0.0054 Oh 44,000.00 237.60

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 74


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
X. 22 Memasang 1 M' pipa galvanis diameter 3" 210,110.45
Bahan 196,075.00
- Pipa Galvanis medium (GIP) 3" 1.2000 M' 126,500.00 151,800.00
- Perlengkapan 35% 44,275.00

Tenaga 14,035.45
- Tukang Gali 0.1350 Oh 30,250.00 4,083.75
- Tukang Leideng 0.2250 Oh 38,500.00 8,662.50
- Kepala Tukang Batu 0.0225 Oh 44,000.00 990.00
- Mandor 0.0068 Oh 44,000.00 299.20

X. 23 Memasang 1 M' pipa PVC tipe AW diameter 1/2" 9,283.45


Bahan 5,541.25
- Pipa PVC class AW 1/2" 1.2000 M' 3,575.00 4,290.00
- Perlengkapan 35% 1,251.25

Tenaga 3,742.20
- Tukang Gali 0.0360 Oh 30,250.00 1,089.00
- Tukang Leideng 0.0600 Oh 38,500.00 2,310.00
- Kepala Tukang Batu 0.0060 Oh 44,000.00 264.00
- Mandor 0.0018 Oh 44,000.00 79.20

X. 24 Memasang 1 M' pipa PVC tipe AW diameter 3/4" 11,201.58


Bahan 7,459.38
- Pipa PVC class AW 3/4" 1.2000 M' 4,812.50 5,775.00
- Perlengkapan 35% 1,684.38
Tenaga 3,742.20
- Tukang Gali 0.0360 Oh 30,250.00 1,089.00
- Tukang Leideng 0.0600 Oh 38,500.00 2,310.00
- Kepala Tukang Batu 0.0060 Oh 44,000.00 264.00
- Mandor 0.0018 Oh 44,000.00 79.20

X. 25 Memasang 1 M' pipa PVC tipe AW diameter 1" 13,972.20


Bahan 10,230.00
- Pipa PVC class AW 1" 1.2000 M' 6,600.00 7,920.00
- Perlengkapan 35% 2,310.00

Tenaga 3,742.20
- Tukang Gali 0.0360 Oh 30,250.00 1,089.00
- Tukang Leideng 0.0600 Oh 38,500.00 2,310.00
- Kepala Tukang Batu 0.0060 Oh 44,000.00 264.00
- Mandor 0.0018 Oh 44,000.00 79.20

X. 26 Memasang 1 M' pipa PVC tipe AW diameter 1 1/2" 22,497.20


Bahan 18,755.00
- Pipa PVC class AW 1 1/2" 1.2000 M' 12,100.00 14,520.00
- Perlengkapan 35% 4,235.00

Tenaga 3,742.20
- Tukang Gali 0.0360 Oh 30,250.00 1,089.00
- Tukang Leideng 0.0600 Oh 38,500.00 2,310.00
- Kepala Tukang Batu 0.0060 Oh 44,000.00 264.00
- Mandor 0.0018 Oh 44,000.00 79.20

X. 27 Memasang 1 M' pipa PVC tipe AW diameter 2" 28,204.55


Bahan 22,591.25
- Pipa PVC class AW 2" 1.2000 M' 14,575.00 17,490.00
- Perlengkapan 35% 5,101.25

Tenaga 5,613.30
- Tukang Gali 0.0540 Oh 30,250.00 1,633.50
- Tukang Leideng 0.0900 Oh 38,500.00 3,465.00
- Kepala Tukang Batu 0.0090 Oh 44,000.00 396.00
- Mandor 0.0027 Oh 44,000.00 118.80

X. 28 Memasang 1 M' pipa PVC tipe AW diameter 2 1/2" 29,743.45


Bahan 26,001.25

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 75


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
- Pipa PVC class AW 2 1/2" 1.2000 M' 16,775.00 20,130.00
- Perlengkapan 35% 5,871.25

Tenaga 3,742.20
- Tukang Gali 0.0360 Oh 30,250.00 1,089.00
- Tukang Leideng 0.0600 Oh 38,500.00 2,310.00
- Kepala Tukang Batu 0.0060 Oh 44,000.00 264.00
- Mandor 0.0018 Oh 44,000.00 79.20

X. 29 Memasang 1 M' pipa PVC tipe AW diameter 3" 52,752.15


Bahan 44,330.00
- Pipa PVC class AW 3" 1.2000 M' 28,600.00 34,320.00
- Perlengkapan 35% 10,010.00

Tenaga 8,422.15
- Tukang Gali 0.0810 Oh 30,250.00 2,450.25
- Tukang Leideng 0.1350 Oh 38,500.00 5,197.50
- Kepala Tukang Batu 0.0135 Oh 44,000.00 594.00
- Mandor 0.0041 Oh 44,000.00 180.40

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 76


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
X. 30 Memasang 1 M' pipa PVC tipe AW diameter 4" 82,163.40
Bahan 73,741.25
- Pipa PVC class AW 4" 1.2000 M' 47,575.00 57,090.00
- Perlengkapan 35% 16,651.25

Tenaga 8,422.15
- Tukang Gali 0.0810 Oh 30,250.00 2,450.25
- Tukang Leideng 0.1350 Oh 38,500.00 5,197.50
- Kepala Tukang Batu 0.0135 Oh 44,000.00 594.00
- Mandor 0.0041 Oh 44,000.00 180.40

X. 31 Memasang 1 bh bak cuci piring / Kitchen zinc 225,843.50


Bahan 212,000.00
- Kitchen zinc standar "Royal" 1.0000 Bh 176,000.00 176,000.00
- Water drain + asesoris 1.0000 Set 36,000.00 36,000.00

Tenaga 13,843.50
- Tukang Gali 0.0300 Oh 30,250.00 907.50
- Tukang Leideng 0.3000 Oh 38,500.00 11,550.00
- Kepala Tukang Batu 0.0300 Oh 44,000.00 1,320.00
- Mandor 0.0015 Oh 44,000.00 66.00

X. 32 Memasang 1 bh kran diameter 3/4" atau 1/2" 16,940.00


Bahan 12,127.50
- Kran air 3/4" atau 1/2 " 1.0000 Bh 12,100.00 12,100.00
- Sealtape kecil 0.0250 Bh 1,100.00 27.50

Tenaga 4,812.50
- Tukang Gali 0.0100 Oh 30,250.00 302.50
- Tukang Leideng 0.1000 Oh 38,500.00 3,850.00
- Kepala Tukang Batu 0.0100 Oh 44,000.00 440.00
- Mandor 0.0050 Oh 44,000.00 220.00

X. 33 Memasang 1 bh Floor drain 18,562.50


Bahan 13,750.00
- Floor drain stainless 1.0000 Bh 13,750.00 13,750.00

Tenaga 4,812.50
- Tukang Gali 0.0100 Oh 30,250.00 302.50
- Tukang Leideng 0.1000 Oh 38,500.00 3,850.00
- Kepala Tukang Batu 0.0100 Oh 44,000.00 440.00
- Mandor 0.0050 Oh 44,000.00 220.00

XI. PEKERJAAN BESI DAN ALLUMINIUM


XI. 1 1 Kg Pasang rangka atap baja 18,843.00
Bahan 14,322.00
- Besi Profil IWF 1.1500 Kg 11,000.00 12,650.00
- Kawat Las 0.0800 Kg 20,900.00 1,672.00

Tenaga 4,521.00
- Tukang Besi 0.0600 Oh 38,500.00 2,310.00
- Pekerja 0.0600 Oh 30,250.00 1,815.00
- Kepala Tukang Besi 0.0060 Oh 44,000.00 264.00
- Mandor 0.0030 Oh 44,000.00 132.00

XI. 2 1 M2 Pasang pintu besi baja 983,955.50


Bahan 935,000.00
- Pintu Besi Baja 1.0000 M2 935,000.00 935,000.00

Tenaga 48,955.50
- Tukang Besi 0.6500 Oh 38,500.00 25,025.00
- Pekerja 0.6500 Oh 30,250.00 19,662.50
- Kepala Tukang Besi 0.0650 Oh 44,000.00 2,860.00
- Mandor 0.0320 Oh 44,000.00 1,408.00

XI. 3 1 M2 Pasang jendela besi 1,012,038.50

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 77


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
Bahan 935,000.00
- Jendela besi 1.0000 M2 935,000.00 935,000.00

Tenaga 77,038.50
- Tukang Besi 1.0500 Oh 38,500.00 40,425.00
- Pekerja 1.0500 Oh 30,250.00 31,762.50
- Kepala Tukang Besi 0.1050 Oh 44,000.00 4,620.00
- Mandor 0.0053 Oh 44,000.00 231.00

XI. 4 1 M2 Pasang jendela besi tahan api 1,897,659.50


Bahan 1,815,000.00
- Jendela besi tahan api 1.0000 M2 1,815,000.00 1,815,000.00

Tenaga 82,659.50
- Tukang Besi 1.2000 Oh 38,500.00 46,200.00
- Pekerja 1.0220 Oh 30,250.00 30,915.50
- Kepala Tukang Besi 0.1200 Oh 44,000.00 5,280.00
- Mandor 0.0060 Oh 44,000.00 264.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 78


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
XI. 5 1 M2 Pasang pintu gulung besi 385,159.50
Bahan 302,500.00
- Pintu gulung besi 1.0000 M2 302,500.00 302,500.00

Tenaga 82,659.50
- Tukang Besi 1.2000 Oh 38,500.00 46,200.00
- Pekerja 1.0220 Oh 30,250.00 30,915.50
- Kepala Tukang Besi 0.1200 Oh 44,000.00 5,280.00
- Mandor 0.0060 Oh 44,000.00 264.00

XI. 6 1 M2 Pasang Rolling door bahan besi 324,536.30


Bahan 247,500.00
- Rolling door bahan besi 1.0000 M2 247,500.00 247,500.00

Tenaga 77,036.30
- Tukang Besi 1.0500 Oh 38,500.00 40,425.00
- Pekerja 1.0500 Oh 30,250.00 31,762.50
- Kepala Tukang Besi 0.1050 Oh 44,000.00 4,620.00
- Mandor 0.0052 Oh 44,000.00 228.80

XI. 7 1 M2 Pasang pintu Sunscreen alluminium 366,916.00


Bahan 330,000.00
- Sunscreen Alumunium 1.0000 M2 330,000.00 330,000.00

Tenaga 36,916.00
- Tukang Besi 0.8000 Oh 38,500.00 30,800.00
- Pekerja 0.0800 Oh 30,250.00 2,420.00
- Kepala Tukang Besi 0.0800 Oh 44,000.00 3,520.00
- Mandor 0.0040 Oh 44,000.00 176.00
XI. 8 1 M2 Pasang Rolling door bahan alumunium 377,850.00
Bahan 302,500.00
- Rolling door bahan alumunium 1.0000 M2 302,500.00 302,500.00

Tenaga 75,350.00
- Tukang Besi 1.0000 Oh 38,500.00 38,500.00
- Pekerja 1.0000 Oh 30,250.00 30,250.00
- Kepala Tukang Besi 0.1000 Oh 44,000.00 4,400.00
- Mandor 0.0500 Oh 44,000.00 2,200.00

XI. 9 1 M2 Pasang pintu alluminium 198,036.30


Bahan 121,000.00
- Pintu Alumunium 1.0000 M2 121,000.00 121,000.00

Tenaga 77,036.30
- Tukang Besi 1.0500 Oh 38,500.00 40,425.00
- Pekerja 1.0500 Oh 30,250.00 31,762.50
- Kepala Tukang Besi 0.1050 Oh 44,000.00 4,620.00
- Mandor 0.0052 Oh 44,000.00 228.80

XI. 10 1 M2 Pasang Vertikals blinds 163,179.50


Bahan 137,500.00
- Vertical blind 1.0000 M2 137,500.00 137,500.00

Tenaga 25,679.50
- Tukang Kayu 0.3500 Oh 38,500.00 13,475.00
- Pekerja 0.3500 Oh 30,250.00 10,587.50
- Kepala Tukang Kayu 0.0350 Oh 44,000.00 1,540.00
- Mandor 0.0018 Oh 44,000.00 77.00

XI. 11 1 M2 Pasang terali besi 314,054.40


Bahan 231,000.00
- Teralis besi 1.0500 M2 220,000.00 231,000.00

Tenaga 83,054.40
- Tukang Las 1.2000 Oh 38,500.00 46,200.00
- Pekerja 1.2000 Oh 30,250.00 36,300.00
- Kepala Tukang Besi 0.0120 Oh 44,000.00 528.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 79


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
- Mandor 0.0006 Oh 44,000.00 26.40

XI. 12 1 M2 Pasang kawat harmonika 38,489.00


Bahan 31,152.00
- Kawat Harmonika 12 x 24 mm 1.1000 M2 22,000.00 24,200.00
- Paku usuk 0.0200 Kg 11,000.00 220.00
- Papan kayu meranti 0.0018 M3 3,740,000.00 6,732.00

Tenaga 7,337.00
- Pekerja 0.1000 Oh 30,250.00 3,025.00
- Tukang Kayu 0.1000 Oh 38,500.00 3,850.00
- Kepala Tukang Kayu 0.0100 Oh 44,000.00 440.00
- Mandor 0.0005 Oh 44,000.00 22.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 80


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
XI. 13 1 M2 Pasang kawat kassa almunium 32,439.00
Bahan 25,102.00
- Kawat Nyamuk Kasa Almunium 1.1000 M2 16,500.00 18,150.00
- Paku usuk 0.0200 Kg 11,000.00 220.00
- Papan kayu meranti 0.0018 M3 3,740,000.00 6,732.00

Tenaga 7,337.00
- Pekerja 0.1000 Oh 30,250.00 3,025.00
- Tukang Kayu 0.1000 Oh 38,500.00 3,850.00
- Kepala Tukang Kayu 0.0100 Oh 44,000.00 440.00
- Mandor 0.0005 Oh 44,000.00 22.00

XI. 14 1 M2 Pasang kawat kassa plastik 20,339.00


Bahan 13,002.00
- Kawat Nyamuk Kasa Plastik 1.1000 M2 5,500.00 6,050.00
- Paku usuk 0.0200 Kg 11,000.00 220.00
- Papan kayu meranti 0.0018 M3 3,740,000.00 6,732.00

Tenaga 7,337.00
- Pekerja 0.1000 Oh 30,250.00 3,025.00
- Tukang Kayu 0.1000 Oh 38,500.00 3,850.00
- Kepala Tukang Kayu 0.0100 Oh 44,000.00 440.00
- Mandor 0.0005 Oh 44,000.00 22.00

XI. 15 1 M2 Pasang jendela nako & tralis 38,104.00


Bahan 23,430.00
- Rangka nako + besi tralis nako 1.1000 M2 20,900.00 22,990.00
- Paku usuk 0.0200 Kg 11,000.00 220.00
- Besi Beton polos 0.0250 M3 8,800.00 220.00

Tenaga 14,674.00
- Pekerja 0.2000 Oh 30,250.00 6,050.00
- Tukang Kayu 0.2000 Oh 38,500.00 7,700.00
- Kepala Tukang Kayu 0.0200 Oh 44,000.00 880.00
- Mandor 0.0010 Oh 44,000.00 44.00

XII. PEKERJAAN KUNCI DAN KACA


XII. 1 1 Buah pasang kunci tanam antik 209,187.00
Bahan 181,500.00
- Kunci tanam antik 1.000 Bh 181,500.00 181,500.00

Tenaga 27,687.00
- Pekerja 0.060 Oh 30,250.00 1,815.00
- Tukang Kayu 0.600 Oh 38,500.00 23,100.00
- Kepala Tukang Kayu 0.060 Oh 44,000.00 2,640.00
- Mandor 0.003 Oh 44,000.00 132.00

XII. 2 1 Buah pasang kunci tanam biasa 80,712.50


Bahan 60,500.00
- Kunci tanam double slag/ Selot pintu kuda terbang 1.000 Bh 60,500.00 60,500.00

Tenaga 20,212.50
- Pekerja 0.010 Oh 30,250.00 302.50
- Tukang Kayu 0.500 Oh 38,500.00 19,250.00
- Kepala Tukang Kayu 0.010 Oh 44,000.00 440.00
- Mandor 0.005 Oh 44,000.00 220.00

XII. 3 1 Buah pasang kunci tanam kamar mandi 63,731.25


Bahan 44,000.00
- Kunci Kamar mandi "alpha" 1.000 Bh 44,000.00 44,000.00

Tenaga 19,731.25
- Pekerja 0.005 Oh 30,250.00 151.25
- Tukang Kayu 0.500 Oh 38,500.00 19,250.00
- Kepala Tukang Kayu 0.005 Oh 44,000.00 220.00
- Mandor 0.0025 Oh 44,000.00 110.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 81


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
XII. 4 1 Buah pasang kunci silinder 63,632.25
Bahan 44,000.00
- Kunci tanam slinder 1.000 Bh 44,000.00 44,000.00

Tenaga 19,632.25
- Pekerja 0.005 Oh 30,250.00 151.25
- Tukang Kayu 0.500 Oh 38,500.00 19,250.00
- Kepala Tukang Kayu 0.005 Oh 44,000.00 220.00
- Mandor 0.00025 Oh 44,000.00 11.00

XII. 5 1 Buah pasang engsel pintu 15,171.75


Bahan 8,250.00
- Engsel Pintu 77 1.000 Bh 8,250.00 8,250.00

Tenaga 6,921.75
- Pekerja 0.015 Oh 30,250.00 453.75
- Tukang Kayu 0.150 Oh 38,500.00 5,775.00
- Kepala Tukang Kayu 0.015 Oh 44,000.00 660.00
- Mandor 0.00075 Oh 44,000.00 33.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 82


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
XII. 6 1 Buah pasang engsel jendela 10,664.50
Bahan 6,050.00
- Engsel jendela 77 1.000 Bh 6,050.00 6,050.00

Tenaga 4,614.50
- Pekerja 0.010 Oh 30,250.00 302.50
- Tukang Kayu 0.100 Oh 38,500.00 3,850.00
- Kepala Tukang Kayu 0.010 Oh 44,000.00 440.00
- Mandor 0.0005 Oh 44,000.00 22.00

XII. 7 1 Buah pasang engsel piano 17,875.00


Bahan 8,250.00
- Engsel Piano 1.000 Bh 8,250.00 8,250.00

Tenaga 9,625.00
- Pekerja 0.020 Oh 30,250.00 605.00
- Tukang Kayu 0.200 Oh 38,500.00 7,700.00
- Kepala Tukang Kayu 0.020 Oh 44,000.00 880.00
- Mandor 0.010 Oh 44,000.00 440.00
XII. 8 1 Buah pasang spring knip 13,521.75
Bahan 6,600.00
- Spring knip 1.000 Bh 6,600.00 6,600.00

Tenaga 6,921.75
- Pekerja 0.015 Oh 30,250.00 453.75
- Tukang Kayu 0.150 Oh 38,500.00 5,775.00
- Kepala Tukang Kayu 0.015 Oh 44,000.00 660.00
- Mandor 0.00075 Oh 44,000.00 33.00

XII. 9 1 Buah pasang hak angin 9,121.75


Bahan 2,200.00
- Hak angin 8" 1.000 Bh 2,200.00 2,200.00

Tenaga 6,921.75
- Pekerja 0.015 Oh 30,250.00 453.75
- Tukang Kayu 0.150 Oh 38,500.00 5,775.00
- Kepala Tukang Kayu 0.015 Oh 44,000.00 660.00
- Mandor 0.00075 Oh 44,000.00 33.00

XII. 10 1 Buah pasang door closer 133,072.50


Bahan 110,000.00
- Door closser type 81 new star 1.000 Bh 110,000.00 110,000.00

Tenaga 23,072.50
- Pekerja 0.050 Oh 30,250.00 1,512.50
- Tukang Kayu 0.500 Oh 38,500.00 19,250.00
- Kepala Tukang Kayu 0.050 Oh 44,000.00 2,200.00
- Mandor 0.0025 Oh 44,000.00 110.00

XII. 11 1 Buah pasang kunci selot 59,125.00


Bahan 49,500.00
- Kunci tanam double slag/ Selot pintu Union 1.000 Bh 49,500.00 49,500.00

Tenaga 9,625.00
- Pekerja 0.020 Oh 30,250.00 605.00
- Tukang Kayu 0.200 Oh 38,500.00 7,700.00
- Kepala Tukang Kayu 0.020 Oh 44,000.00 880.00
- Mandor 0.010 Oh 44,000.00 440.00

XII. 12 1 Buah pasang pegangan pintu/door holder 160,572.50


Bahan 137,500.00
- Door holder 1.000 Bh 137,500.00 137,500.00

Tenaga 23,072.50
- Pekerja 0.050 Oh 30,250.00 1,512.50
- Tukang Kayu 0.500 Oh 38,500.00 19,250.00
- Kepala Tukang Kayu 0.050 Oh 44,000.00 2,200.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 83


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
- Mandor 0.0025 Oh 44,000.00 110.00

XII. 13 1 Buah pasang door stop 12,864.50


Bahan 8,250.00
- Door stop lokal 1.000 Bh 8,250.00 8,250.00

Tenaga 4,614.50
- Pekerja 0.010 Oh 30,250.00 302.50
- Tukang Kayu 0.100 Oh 38,500.00 3,850.00
- Kepala Tukang Kayu 0.010 Oh 44,000.00 440.00
- Mandor 0.0005 Oh 44,000.00 22.00

XII. 14 1 Buah pasang rel pintu dorong 165,187.00


Bahan 137,500.00
- Rel pintu dorong 1.000 Bh 137,500.00 137,500.00

Tenaga 27,687.00
- Pekerja 0.060 Oh 30,250.00 1,815.00
- Tukang Kayu 0.600 Oh 38,500.00 23,100.00
- Kepala Tukang Kayu 0.060 Oh 44,000.00 2,640.00
- Mandor 0.003 Oh 44,000.00 132.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 84


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
XII. 15 1 Buah pasang kunci lemari 19,236.25
Bahan 7,700.00
- Kunci lemari 1.000 Bh 7,700.00 7,700.00

Tenaga 11,536.25
- Pekerja 0.025 Oh 30,250.00 756.25
- Tukang Kayu 0.250 Oh 38,500.00 9,625.00
- Kepala Tukang Kayu 0.025 Oh 44,000.00 1,100.00
- Mandor 0.00125 Oh 44,000.00 55.00

XII. 16 1 M2 pasang kaca, tebal 3 mm 61,371.75


Bahan 54,450.00
- Kaca bening 3 mm 1.100 M2 49,500.00 54,450.00

Tenaga 6,921.75
- Pekerja 0.015 Oh 30,250.00 453.75
- Tukang Kayu 0.150 Oh 38,500.00 5,775.00
- Kepala Tukang Kayu 0.015 Oh 44,000.00 660.00
- Mandor 0.00075 Oh 44,000.00 33.00

XII. 17 1 M2 pasang kaca, tebal 5 mm 79,521.75


Bahan 72,600.00
- Kaca bening 5 mm 1.100 M2 66,000.00 72,600.00

Tenaga 6,921.75
- Pekerja 0.015 Oh 30,250.00 453.75
- Tukang Kayu 0.150 Oh 38,500.00 5,775.00
- Kepala Tukang Kayu 0.015 Oh 44,000.00 660.00
- Mandor 0.00075 Oh 44,000.00 33.00

XII. 18 1 M2 pasang kaca es, tebal 5 mm 103,721.75


Bahan 96,800.00
- Kaca es 5 mm 1.100 M2 88,000.00 96,800.00

Tenaga 6,921.75
- Pekerja 0.015 Oh 30,250.00 453.75
- Tukang Kayu 0.150 Oh 38,500.00 5,775.00
- Kepala Tukang Kayu 0.015 Oh 44,000.00 660.00
- Mandor 0.00075 Oh 44,000.00 33.00

XII. 19 1 M2 pasang kaca rayben, tebal 5 mm 91,621.75


Bahan 84,700.00
- Kaca riben 5 mm 1.100 M2 77,000.00 84,700.00

Tenaga 6,921.75
- Pekerja 0.015 Oh 30,250.00 453.75
- Tukang Kayu 0.150 Oh 38,500.00 5,775.00
- Kepala Tukang Kayu 0.015 Oh 44,000.00 660.00
- Mandor 0.00075 Oh 44,000.00 33.00

XIII. PEKERJAAN PENUTUP LANTAI DAN DINDING


XIII. 1 1 M2 Pasang lantai keramik warna putih polos 20x20 cm 76,059.50
Bahan 46,497.00
- Keramik 20 x 20 cm warna putih "mulia" 1.0000 m2 27,500.00 27,500.00
- Semen PC ( Portland Cement ) 40 kg 7.1200 Kg 1,100.00 7,832.00
- Pasir pasang (kaliworo) 0.0900 M3 115,500.00 10,395.00
- Semen Warna 0.2000 Kg 3,850.00 770.00

Tenaga 29,562.50
- Pekerja 0.2500 Oh 30,250.00 7,562.50
- Tukang Batu 0.5000 Oh 38,500.00 19,250.00
- Kepala Tukang Batu 0.0500 Oh 44,000.00 2,200.00
- Mandor 0.0125 Oh 44,000.00 550.00

XIII. 2 1 M2 Pasang lantai keramik bermotif 20x20 cm 91,459.50


Bahan 61,897.00
- Keramik 20 x 25 cm "asia nepal" 1.0000 m2 42,900.00 42,900.00
- Semen PC ( Portland Cement ) 40 kg 7.1200 Kg 1,100.00 7,832.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 85


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
- Pasir pasang (kaliworo) 0.0900 M3 115,500.00 10,395.00
- Semen Warna 0.2000 Kg 3,850.00 770.00

Tenaga 29,562.50
- Pekerja 0.2500 Oh 30,250.00 7,562.50
- Tukang Batu 0.5000 Oh 38,500.00 19,250.00
- Kepala Tukang Batu 0.0500 Oh 44,000.00 2,200.00
- Mandor 0.0125 Oh 44,000.00 550.00

XIII. 3 1 M2 Pasang keramik lantai kamar mandi 20x20 cm 87,059.50


Bahan 57,497.00
- Keramik Lantai Kamar Mandi 20 x 20 cm "mulia" 1.0000 m2 38,500.00 38,500.00
- Semen PC ( Portland Cement ) 40 kg 7.1200 Kg 1,100.00 7,832.00
- Pasir pasang (kaliworo) 0.0900 M3 115,500.00 10,395.00
- Semen Warna 0.2000 Kg 3,850.00 770.00

Tenaga 29,562.50
- Pekerja 0.2500 Oh 30,250.00 7,562.50
- Tukang Batu 0.5000 Oh 38,500.00 19,250.00
- Kepala Tukang Batu 0.0500 Oh 44,000.00 2,200.00
- Mandor 0.0125 Oh 44,000.00 550.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 86


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
XIII. 4 1 M2 Pasang lantai keramik warna putih polos 30x30 cm 75,025.50
Bahan 45,463.00
- Keramik 30 x 30 cm warna putih "mulia" 1.0000 m2 27,500.00 27,500.00
- Semen PC ( Portland Cement ) 40 kg 6.1800 Kg 1,100.00 6,798.00
- Pasir pasang (kaliworo) 0.0900 M3 115,500.00 10,395.00
- Semen Warna 0.2000 Kg 3,850.00 770.00

Tenaga 29,562.50
- Pekerja 0.2500 Oh 30,250.00 7,562.50
- Tukang Batu 0.5000 Oh 38,500.00 19,250.00
- Kepala Tukang Batu 0.0500 Oh 44,000.00 2,200.00
- Mandor 0.0125 Oh 44,000.00 550.00

XIII. 5 1 M2 Pasang lantai keramik bermotif warna muda 30x30 cm 83,275.50


Bahan 53,713.00
- Keramik 30 x 30 cm bermotif warna muda "asia tile" 1.0000 m2 35,750.00 35,750.00
- Semen PC ( Portland Cement ) 40 kg 6.1800 Kg 1,100.00 6,798.00
- Pasir pasang (kaliworo) 0.0900 M3 115,500.00 10,395.00
- Semen Warna 0.2000 Kg 3,850.00 770.00

Tenaga 29,562.50
- Pekerja 0.2500 Oh 30,250.00 7,562.50
- Tukang Batu 0.5000 Oh 38,500.00 19,250.00
- Kepala Tukang Batu 0.0500 Oh 44,000.00 2,200.00
- Mandor 0.0125 Oh 44,000.00 550.00

XIII. 6 1 M2 Pasang lantai keramik bermotif warna tua 30x30 cm 89,875.50


Bahan 60,313.00
- Keramik 30 x 30 cm bermotif warna tua "asia tile" 1.0000 m2 42,350.00 42,350.00
- Semen PC ( Portland Cement ) 40 kg 6.1800 Kg 1,100.00 6,798.00
- Pasir pasang (kaliworo) 0.0900 M3 115,500.00 10,395.00
- Semen Warna 0.2000 Kg 3,850.00 770.00

Tenaga 29,562.50
- Pekerja 0.2500 Oh 30,250.00 7,562.50
- Tukang Batu 0.5000 Oh 38,500.00 19,250.00
- Kepala Tukang Batu 0.0500 Oh 44,000.00 2,200.00
- Mandor 0.0125 Oh 44,000.00 550.00

XIII. 7 1 M2 Pasang lantai keramik bermotif warna muda 40x40 cm 90,975.50


Bahan 61,413.00
- Keramik 40 x 40 cm bermotif warna muda "hercules" 1.0000 m2 43,450.00 43,450.00
- Semen PC ( Portland Cement ) 40 kg 6.1800 Kg 1,100.00 6,798.00
- Pasir pasang (kaliworo) 0.0900 M3 115,500.00 10,395.00
- Semen Warna 0.2000 Kg 3,850.00 770.00

Tenaga 29,562.50
- Pekerja 0.2500 Oh 30,250.00 7,562.50
- Tukang Batu 0.5000 Oh 38,500.00 19,250.00
- Kepala Tukang Batu 0.0500 Oh 44,000.00 2,200.00
- Mandor 0.0125 Oh 44,000.00 550.00

XIII. 8 1 M2 Pasang lantai keramik bermotif warna tua 40x40 cm 93,725.50


Bahan 64,163.00
- Keramik 40 x 40 cm bermotif warna tua "hercules" 1.0000 Bh 46,200.00 46,200.00
- Semen PC ( Portland Cement ) 40 kg 6.1800 Kg 1,100.00 6,798.00
- Pasir pasang (kaliworo) 0.0900 M3 115,500.00 10,395.00
- Semen Warna 0.2000 Kg 3,850.00 770.00

Tenaga 29,562.50
- Pekerja 0.2500 Oh 30,250.00 7,562.50
- Tukang Batu 0.5000 Oh 38,500.00 19,250.00
- Kepala Tukang Batu 0.0500 Oh 44,000.00 2,200.00
- Mandor 0.0125 Oh 44,000.00 550.00

XIII. 9 1 M2 Pasang keramik teras/ garasi bermotif warna tua 30x30 cm 91,525.50
Bahan 61,963.00
- Keramik teras / garasi 30 x 30 "masterina" 1.0000 m2 44,000.00 44,000.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 87


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
- Semen PC ( Portland Cement ) 40 kg 6.1800 Kg 1,100.00 6,798.00
- Pasir pasang (kaliworo) 0.0900 M3 115,500.00 10,395.00
- Semen Warna 0.2000 Kg 3,850.00 770.00

Tenaga 29,562.50
- Pekerja 0.2500 Oh 30,250.00 7,562.50
- Tukang Batu 0.5000 Oh 38,500.00 19,250.00
- Kepala Tukang Batu 0.0500 Oh 44,000.00 2,200.00
- Mandor 0.0125 Oh 44,000.00 550.00

XIII. 10 1 M2 Pasang dinding keramik bermotif 20 x 20 cm 89,259.50


Bahan 59,697.00
- Keramik 20 x 20 cm bermotif "asia tile" 1.0000 m2 40,700.00 40,700.00
- Semen PC ( Portland Cement ) 40 kg 7.1200 Kg 1,100.00 7,832.00
- Pasir pasang (kaliworo) 0.0900 M3 115,500.00 10,395.00
- Semen Warna 0.2000 Kg 3,850.00 770.00

Tenaga 29,562.50
- Pekerja 0.2500 Oh 30,250.00 7,562.50
- Tukang Batu 0.5000 Oh 38,500.00 19,250.00
- Kepala Tukang Batu 0.0500 Oh 44,000.00 2,200.00
- Mandor 0.0125 Oh 44,000.00 550.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 88


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)

XIII. 11 1 M2 Pasang dinding keramik warna polos 20 x 25 cm 92,559.50


Bahan 62,997.00
- Keramik 20 x 25 cm warna polos "kia" 1.0000 Bh 44,000.00 44,000.00
- Semen PC ( Portland Cement ) 40 kg 7.1200 Kg 1,100.00 7,832.00
- Pasir pasang (kaliworo) 0.0900 M3 115,500.00 10,395.00
- Semen Warna 0.2000 Kg 3,850.00 770.00

Tenaga 29,562.50
- Pekerja 0.2500 Oh 30,250.00 7,562.50
- Tukang Batu 0.5000 Oh 38,500.00 19,250.00
- Kepala Tukang Batu 0.0500 Oh 44,000.00 2,200.00
- Mandor 0.0125 Oh 44,000.00 550.00

XIII. 12 1 M2 Pasang dinding keramik bermotif warna muda 20 x 33 cm 99,775.50


Bahan 70,213.00
- Keramik 20 x 33 cm motif warna muda "platinum" 1.0000 m2 52,250.00 52,250.00
- Semen PC ( Portland Cement ) 40 kg 6.1800 Kg 1,100.00 6,798.00
- Pasir pasang (kaliworo) 0.0900 M3 115,500.00 10,395.00
- Semen Warna 0.2000 Kg 3,850.00 770.00

Tenaga 29,562.50
- Pekerja 0.2500 Oh 30,250.00 7,562.50
- Tukang Batu 0.5000 Oh 38,500.00 19,250.00
- Kepala Tukang Batu 0.0500 Oh 44,000.00 2,200.00
- Mandor 0.0125 Oh 44,000.00 550.00

XIII. 13 1 M2 Pasang dinding keramik bermotif warna tua 20 x 33 cm 105,275.50


Bahan 75,713.00
- Keramik 20 x 33 cm motif warna tua "platinum" 1.0000 m2 57,750.00 57,750.00
- Semen PC ( Portland Cement ) 40 kg 6.1800 Kg 1,100.00 6,798.00
- Pasir pasang (kaliworo) 0.0900 M3 115,500.00 10,395.00
- Semen Warna 0.2000 Kg 3,850.00 770.00

Tenaga 29,562.50
- Pekerja 0.2500 Oh 30,250.00 7,562.50
- Tukang Batu 0.5000 Oh 38,500.00 19,250.00
- Kepala Tukang Batu 0.0500 Oh 44,000.00 2,200.00
- Mandor 0.0125 Oh 44,000.00 550.00

XIII. 14 1 M' Pasang plint keramik ukuran 7,5 x 20 cm 27,528.60


Bahan 20,747.10
- Keramik 7,5 x 20 cm (plint) 5.0000 Bh 3,850.00 19,250.00
- Semen PC ( Portland Cement ) 40 kg 0.8500 Kg 1,100.00 935.00
- Pasir pasang (kaliworo) 0.0022 M3 115,500.00 254.10
- Semen Warna 0.0800 Kg 3,850.00 308.00

Tenaga 6,781.50
- Pekerja 0.0900 Oh 30,250.00 2,722.50
- Tukang Batu 0.0900 Oh 38,500.00 3,465.00
- Kepala Tukang Batu 0.0090 Oh 44,000.00 396.00
- Mandor 0.0045 Oh 44,000.00 198.00

XIII. 15 1 M' Pasang plint keramik ukuran 8 x 25 cm 25,878.60


Bahan 19,097.10
- Keramik 8 x 25 cm (plint) 4.0000 Bh 4,400.00 17,600.00
- Semen PC ( Portland Cement ) 40 kg 0.8500 Kg 1,100.00 935.00
- Pasir pasang (kaliworo) 0.0022 M3 115,500.00 254.10
- Semen Warna 0.0800 Kg 3,850.00 308.00

Tenaga 6,781.50
- Pekerja 0.0900 Oh 30,250.00 2,722.50
- Tukang Batu 0.0900 Oh 38,500.00 3,465.00
- Kepala Tukang Batu 0.0090 Oh 44,000.00 396.00
- Mandor 0.0045 Oh 44,000.00 198.00

XIII. 16 1 M' Pasang keramik kuku macan 13,131.80

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 89


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
Bahan 7,219.30
- Kuku macan 10.0000 Bh 550.00 5,500.00
- Semen PC ( Portland Cement ) 40 kg 0.4080 Kg 1,100.00 448.80
- Pasir pasang (kaliworo) 0.0090 M3 115,500.00 1,039.50
- Semen Warna 0.0600 Kg 3,850.00 231.00

Tenaga 5,912.50
- Pekerja 0.0500 Oh 30,250.00 1,512.50
- Tukang Batu 0.1000 Oh 38,500.00 3,850.00
- Kepala Tukang Batu 0.0100 Oh 44,000.00 440.00
- Mandor 0.0025 Oh 44,000.00 110.00

XIII. 17 1 M' Pasang keramik stepnozing 5 x 30 cm 65,381.80


Bahan 59,469.30
- Step nosing 3.5000 Bh 16,500.00 57,750.00
- Semen PC ( Portland Cement ) 40 kg 0.4080 Kg 1,100.00 448.80
- Pasir pasang (kaliworo) 0.0090 M3 115,500.00 1,039.50
- Semen Warna 0.0600 Kg 3,850.00 231.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 90


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
Tenaga 5,912.50
- Pekerja 0.0500 Oh 30,250.00 1,512.50
- Tukang Batu 0.1000 Oh 38,500.00 3,850.00
- Kepala Tukang Batu 0.0100 Oh 44,000.00 440.00
- Mandor 0.0025 Oh 44,000.00 110.00

XIII. 18 1 M2 Pasang dinding batu palimanan 151,057.50


Bahan 115,967.50
- Batu Palimanan 1.0000 m2 99,000.00 99,000.00
- Semen PC ( Portland Cement ) 40 kg 11.7500 Kg 1,100.00 12,925.00
- Pasir pasang (kaliworo) 0.0350 M3 115,500.00 4,042.50

Tenaga 35,090.00
- Pekerja 0.6200 Oh 30,250.00 18,755.00
- Tukang Batu 0.3500 Oh 38,500.00 13,475.00
- Kepala Tukang Batu 0.0350 Oh 44,000.00 1,540.00
- Mandor 0.0300 Oh 44,000.00 1,320.00

XIII. 19 1 M2 Pasang dinding batu tempel hitam 131,807.50


SNI Bahan 95,617.50
03-7395-2008 - Batu Hias Tempel 1.1000 Bh 71,500.00 78,650.00
- Semen PC ( Portland Cement ) 40 kg 11.7500 Kg 1,100.00 12,925.00
- Pasir pasang (kaliworo) 0.0350 M3 115,500.00 4,042.50
Tenaga 36,190.00
- Pekerja 0.7000 Oh 30,250.00 21,175.00
- Tukang Batu 0.3500 Oh 38,500.00 13,475.00
- Kepala Tukang Batu 0.0350 Oh 44,000.00 1,540.00

XIII. 20 1 M2 Pasang dinding batu candi 149,737.50


Bahan 115,967.50
- Batu Candi 1.0000 Bh 99,000.00 99,000.00
- Semen PC ( Portland Cement ) 40 kg 11.7500 Kg 1,100.00 12,925.00
- Pasir pasang (kaliworo) 0.0350 M3 115,500.00 4,042.50

Tenaga 33,770.00
- Pekerja 0.6200 Oh 30,250.00 18,755.00
- Tukang Batu 0.3500 Oh 38,500.00 13,475.00
- Kepala Tukang Batu 0.0350 Oh 44,000.00 1,540.00

XIV. PEKERJAAN PENGECATAN


XIV. 1 1 M2 mengikis/mengerok permukaan cat tembok lama 4,757.50
Bahan 110.00
- Soda Api 0.0500 Kg 2,200.00 110.00

Tenaga 4,647.50
- Pekerja 0.1500 Oh 30,250.00 4,537.50
- Tukang Cat 38,500.00 -
- Kepala Tukang Cat 44,000.00 -
- Mandor 0.0025 Oh 44,000.00 110.00

XIV. 2 1 M2 Mencuci bidang permukaan tembok yang pernah di cat 5,472.50


Bahan 825.00
- Sabun 0.0500 Kg 16,500.00 825.00

Tenaga 4,647.50
- Pekerja 0.1500 Oh 30,250.00 4,537.50
- Tukang Cat 38,500.00 -
- Kepala Tukang Cat 44,000.00 -
- Mandor 0.0025 Oh 44,000.00 110.00
XIV. 3 1 M2 Mengerok karat cat lama permukaan baja dengan cara manual 5,472.50
Bahan 825.00
- Sabun 0.0500 Kg 16,500.00 825.00

Tenaga 4,647.50
- Pekerja 0.1500 Oh 30,250.00 4,537.50

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 91


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
- Tukang Cat 38,500.00 -
- Kepala Tukang Cat 44,000.00 -
- Mandor 0.0025 Oh 44,000.00 110.00

XIV. 4 1 M2 Menyabun permukaan tembok lama 5,472.50


Bahan 825.00
- Sabun 0.0500 Kg 16,500.00 825.00

Tenaga 4,647.50
- Pekerja 0.1500 Oh 30,250.00 4,537.50
- Tukang Cat 38,500.00 -
- Kepala Tukang Cat 44,000.00 -
- Mandor 0.0025 Oh 44,000.00 110.00

XIV. 5 1 M2 Mendempul dan menggosok kayu 5,148.00


Bahan 2,112.00
- Dempul Kayu "altex" 0.0800 Kg 22,000.00 1,760.00
- Minyak Cat 0.0200 Kg 9,350.00 187.00
- Ampelas 0.1000 Lbr 1,650.00 165.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 92


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
Tenaga 3,036.00
- Pekerja 0.0400 Oh 30,250.00 1,210.00
- Tukang Cat 0.0400 Oh 38,500.00 1,540.00
- Kepala Tukang Cat 0.0040 Oh 44,000.00 176.00
- Mandor 0.0025 Oh 44,000.00 110.00

XIV. 6 1 M2 Pengecatan bidang kayu lama 23,331.00


Bahan 17,886.00
- Plamur Kayu jago 0.1500 Kg 22,000.00 3,300.00
- Cat dasar 0.1700 Kg 42,900.00 7,293.00
- Cat Besi/ Kayu "Emco" warna standar 0.1700 Kg 42,900.00 7,293.00

Tenaga 5,445.00
- Pekerja 0.0700 Oh 30,250.00 2,117.50
- Tukang Cat 0.0750 Oh 38,500.00 2,887.50
- Kepala Tukang Cat 0.0075 Oh 44,000.00 330.00
- Mandor 0.0025 Oh 44,000.00 110.00

XIV. 7 1 M2 Pengecatan bidang kayu baru (1 lapis plamir), 1 lapis cat dasar, 2 lapis cat penutup 28,325.00
Bahan 25,487.00
- Cat Meni Kayu "altex" 0.2000 Kg 18,700.00 3,740.00
- Plamur Kayu jago 0.1500 Kg 22,000.00 3,300.00
- Cat dasar 0.1700 Kg 42,900.00 7,293.00
- Cat Besi/ Kayu "Emco" warna standar 0.2600 Kg 42,900.00 11,154.00
Tenaga 2,838.00
- Pekerja 0.0700 Oh 30,250.00 2,117.50
- Tukang Cat 0.0090 Oh 38,500.00 346.50
- Kepala Tukang Cat 0.0060 Oh 44,000.00 264.00
- Mandor 0.0025 Oh 44,000.00 110.00

XIV. 8 1 M2 Pengecatan bidang kayu baru (1 lapis plamir), 1 lapis cat dasar, 3 lapis cat penutup 35,794.00
Bahan 29,348.00
- Cat Meni Kayu "altex" 0.2000 Kg 18,700.00 3,740.00
- Plamur Kayu jago 0.1500 Kg 22,000.00 3,300.00
- Cat dasar 0.1700 Kg 42,900.00 7,293.00
- Cat Besi/ Kayu "Emco" warna standar 0.3500 Kg 42,900.00 15,015.00

Tenaga 6,446.00
- Pekerja 0.0700 Oh 30,250.00 2,117.50
- Tukang Cat 0.1050 Oh 38,500.00 4,042.50
- Kepala Tukang Cat 0.0040 Oh 44,000.00 176.00
- Mandor 0.0025 Oh 44,000.00 110.00

XIV. 9 1 M2 Pelaburan bidang kayu dengan teak oil 16,417.50


Bahan 9,900.00
- Teak Oil 0.3600 Ltr 27,500.00 9,900.00

Tenaga 6,517.50
- Pekerja 0.0400 Oh 30,250.00 1,210.00
- Tukang Cat 0.0630 Oh 38,500.00 2,425.50
- Kepala Tukang Cat 0.0630 Oh 44,000.00 2,772.00
- Mandor 0.0025 Oh 44,000.00 110.00

XIV. 10 1 M2 Pelaburan bidang kayu dengan politur/ pernis 18,293.00


Bahan 13,959.00
- Pernis 0.1500 Ltr 16,500.00 2,475.00
- Politur Jadi 0.3720 Ltr 22,000.00 8,184.00
- Ampelas 2.0000 Lbr 1,650.00 3,300.00

Tenaga 4,334.00
- Pekerja 0.0400 Oh 30,250.00 1,210.00
- Tukang Cat 0.0600 Oh 38,500.00 2,310.00
- Kepala Tukang Cat 0.0160 Oh 44,000.00 704.00
- Mandor 0.0025 Oh 44,000.00 110.00

XIV. 11 1 M2 Pelaburan bidang kayu dengan cat residu dan ter 5,021.50
Bahan 1,732.50

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 93


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
- Residu/ ter 0.3500 Ltr 4,950.00 1,732.50

Tenaga 3,289.00
- Pekerja 0.1000 Oh 30,250.00 3,025.00
- Tukang Cat - Oh 38,500.00 -
- Kepala Tukang Cat - Oh 44,000.00 -
- Mandor 0.0060 Oh 44,000.00 264.00

XIV. 12 1 M2 Pelaburan bidang kayu dengan vernis 15,587.00


Bahan 3,773.00
- Pernis 0.1500 Ltr 16,500.00 2,475.00
- Dempul Kayu "altex" 0.0500 Kg 22,000.00 1,100.00
- Ampelas 0.1000 Lbr 1,650.00 165.00
- Kuas 2,5 " 0.0100 Bh 3,300.00 33.00

Tenaga 11,814.00
- Pekerja 0.1600 Oh 30,250.00 4,840.00
- Tukang Cat 0.1600 Oh 38,500.00 6,160.00
- Kepala Tukang Cat 0.0160 Oh 44,000.00 704.00
- Mandor 0.0025 Oh 44,000.00 110.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 94


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
XIV. 13 1 M2 Pengecatan tembok baru (1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup) 8,778.00
Bahan 5,360.30
- Plamur Tembok 0.1000 Kg 6,875.00 687.50
- Cat dasar 0.1000 Kg 12,980.00 1,298.00
- Cat tembok "Decolith" warna standar 0.2600 Kg 12,980.00 3,374.80

Tenaga 3,417.70
- Pekerja 0.0200 Oh 30,250.00 605.00
- Tukang Cat 0.0630 Oh 38,500.00 2,425.50
- Kepala Tukang Cat 0.0063 Oh 44,000.00 277.20
- Mandor 0.0025 Oh 44,000.00 110.00

XIV. 14 1 M2 Pengecatan tembok lama (1 lapis cat dasar, 2 lapis cat penutup) 6,652.80
Bahan 3,894.00
- Cat dasar 0.1200 Kg 12,980.00 1,557.60
- Cat tembok "Decolith" warna standar 0.1800 Kg 12,980.00 2,336.40

Tenaga 2,758.80
- Pekerja 0.0280 Oh 30,250.00 847.00
- Tukang Cat 0.0420 Oh 38,500.00 1,617.00
- Kepala Tukang Cat 0.0042 Oh 44,000.00 184.80
- Mandor 0.0025 Oh 44,000.00 110.00

XIV. 15 1 M2 Pengecatan permukaan baja dengan meni besi 11,528.00


Bahan 1,903.00
- Cat Meni Besi "altex" 0.1000 Kg 18,700.00 1,870.00
- Kuas 2,5 " 0.0100 Bh 3,300.00 33.00

Tenaga 9,625.00
- Pekerja 0.0200 Oh 30,250.00 605.00
- Tukang Cat 0.2000 Oh 38,500.00 7,700.00
- Kepala Tukang Cat 0.0200 Oh 44,000.00 880.00
- Mandor 0.0100 Oh 44,000.00 440.00

XIV. 16 1 M2 Pengecatan permukaan baja dengan meni besi dan perancah 22,116.05
Bahan 4,571.05
- Cat Meni Besi "altex" 0.1000 Kg 18,700.00 1,870.00
- Kuas 2,5 " 0.0100 Bh 3,300.00 33.00
- Perancah kayu 0.0020 M3 1,334,025.00 2,668.05

Tenaga 17,545.00
- Pekerja 0.2500 Oh 30,250.00 7,562.50
- Tukang Cat 0.2250 Oh 38,500.00 8,662.50
- Kepala Tukang Cat 0.0225 Oh 44,000.00 990.00
- Mandor 0.0075 Oh 44,000.00 330.00

XV. PEKERJAAN BONGKARAN


XV. 1 1 M3 Membongkar pasangan batu kali 166,100.00
Bahan -
Tenaga 166,100.00
- Pekerja 0.4000 Oh 30,250.00 12,100.00
- Tukang Batu 4.0000 Oh 38,500.00 154,000.00

XV. 2 1 M3 Membongkar beton bertulang dan membersihkan 193,600.00


Bahan -
Tenaga 193,600.00
- Pekerja 6.0000 Oh 30,250.00 181,500.00
- Tukang Batu 0.2000 Oh 38,500.00 7,700.00
- Mandor 0.1000 Oh 44,000.00 4,400.00

XV. 3 1 M3 Membongkar dinding tembok bata merah dan membersihkan 80,025.00


Bahan -
Tenaga 80,025.00
- Pekerja 0.1000 Oh 30,250.00 3,025.00
- Tukang Batu 2.0000 Oh 38,500.00 77,000.00

XV. 4 1 M2 Membongkar lantai tegel 6,490.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 95


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
Bahan -
Tenaga 6,490.00
- Pekerja 0.2000 Oh 30,250.00 6,050.00
- Mandor 0.0100 Oh 44,000.00 440.00

XV. 5 1 M2 Mengupas plesteran lama 1,622.50


Bahan -
Tenaga 1,622.50
- Pekerja 0.0500 Oh 30,250.00 1,512.50
- Mandor 0.0025 Oh 44,000.00 110.00

XV. 6 1 M2 Membongkar genteng/ sirap 6,490.00


Bahan -
Tenaga 6,490.00
- Pekerja 0.2000 Oh 30,250.00 6,050.00
- Mandor 0.0100 Oh 44,000.00 440.00

XV. 7 1 M2 Membongkar atap seng 4,950.00


Bahan -
Tenaga 4,950.00
- Pekerja 0.1000 Oh 30,250.00 3,025.00
- Tukang Kayu 0.0500 Oh 38,500.00 1,925.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 96


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)

XV. 8 1 M2 Membongkar usuk/ reng untuk dipakai lagi 9,064.00


Bahan -
Tenaga 9,064.00
- Pekerja 0.2000 Oh 30,250.00 6,050.00
- Tukang Kayu 0.0600 Oh 38,500.00 2,310.00
- Kepala Tukang Kayu 0.0060 Oh 44,000.00 264.00
- Mandor 0.0100 Oh 44,000.00 440.00

XV. 9 1 M2 Membongkar usuk/ reng untuk tidak dipakai lagi 6,490.00


Bahan -
Tenaga 6,490.00
- Pekerja 0.2000 Oh 30,250.00 6,050.00
- Mandor 0.0100 Oh 44,000.00 440.00

XV. 10 1 M3 Membongkar kayu balok loteng/ kuda-kuda/ dlurung/ jembatan untuk dipakai lagi 387,200.00
Bahan -
Tenaga 387,200.00
- Pekerja 4.0000 Oh 30,250.00 121,000.00
- Tukang Kayu 6.0000 Oh 38,500.00 231,000.00
- Kepala Tukang Kayu 0.6000 Oh 44,000.00 26,400.00
- Mandor 0.2000 Oh 44,000.00 8,800.00

XV. 11 1 M3 Membongkar usuk/ reng untuk tidak dipakai lagi 39,050.00


Bahan -
Tenaga 39,050.00
- Pekerja 1.0000 Oh 30,250.00 30,250.00
- Mandor 0.2000 Oh 44,000.00 8,800.00

XVI. PEKERJAAN PAVING DAN KANSTIN


XVI. 1 1 M' Pasang kanstin batu bata 1:2 55,307.91
BOW Bahan 20,307.91
- Galian tanah 0.0400 M3 23,787.50 951.50
- Pasir Urug 0.0075 M3 78,100.00 585.75
- Pasangan bata 1 : 2 0.0270 M3 585,112.00 15,798.02
- Pleateran 1 : 2 tebal 15 mm 0.1000 M2 29,726.40 2,972.64

Tenaga 35,000.00
- Upah 1.0000 Ls 35,000.00 35,000.00

XVI. 12 1 M' Pasang kanstin batu bata 1:4 53,270.49


BOW Bahan 18,270.49
- Galian tanah 0.0400 M3 23,787.50 951.50
- Pasir Urug 0.0075 M3 78,100.00 585.75
- Pasangan bata 1 : 4 0.0270 M3 524,172.00 14,152.64
- Pleateran 1 : 4 tebal 15 mm 0.1000 M2 25,806.00 2,580.60

Tenaga 35,000.00
- Upah 1.0000 Ls 35,000.00 35,000.00

XVI. 3 1 M' Pasang kanstin 20 x 30 x 60 cm 76,780.00


BOW Bahan 50,600.00
- Kansten panjang 0,6 m' 2.0000 Bh 25,300.00 50,600.00

Tenaga 26,180.00
- Tukang Batu 0.2000 Oh 38,500.00 7,700.00
- Kepala Tukang Batu 0.4000 Oh 44,000.00 17,600.00
- Mandor 0.0200 Oh 44,000.00 880.00

XVI. 4 1 M2 Pasang paving block tebal 6 cm 72,160.00


BOW Bahan 50,600.00
- Paving block tebal 6 cm 1.0000 M3 27,500.00 27,500.00
- Pasir pasang (kaliworo) 0.2000 M3 115,500.00 23,100.00

Tenaga 21,560.00
- Mandor 0.0200 Oh 44,000.00 880.00
- Kepala Tukang Batu 0.0200 Oh 44,000.00 880.00
- Tukang Batu 0.2000 Oh 38,500.00 7,700.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 97


a. b. c. d. e. f = (c x e) g = (c x e) h =( f + g)
- Pekerja 0.4000 Oh 30,250.00 12,100.00
XVI. 5 1 M2 Pasang paving block (mesin) tebal 6 cm 83,160.00
BOW Bahan 61,600.00
- Paving block tebal 6 cm (mesin) 1.0000 M3 38,500.00 38,500.00
- Pasir pasang (kaliworo) 0.2000 M3 115,500.00 23,100.00

Tenaga 21,560.00
- Mandor 0.0200 Oh 44,000.00 880.00
- Kepala Tukang Batu 0.0200 Oh 44,000.00 880.00
- Tukang Batu 0.2000 Oh 38,500.00 7,700.00
- Pekerja 0.4000 Oh 30,250.00 12,100.00

XVI. 6 1 M2 Pasang paving block kawung (mutu sedang) tebal 6 cm 80,410.00


BOW Bahan 58,850.00
- Paving kawung tebal 6 sm mutu sedang 1.0000 M3 35,750.00 35,750.00
- Pasir pasang (kaliworo) 0.2000 M3 115,500.00 23,100.00

Tenaga 21,560.00
- Mandor 0.0200 Oh 44,000.00 880.00
- Kepala Tukang Batu 0.0200 Oh 44,000.00 880.00
- Tukang Batu 0.2000 Oh 38,500.00 7,700.00
- Pekerja 0.4000 Oh 30,250.00 12,100.00

XVI. 7 1 M2 Pasang paving block kawung (mutu baik) tebal 6 cm 85,910.00


BOW Bahan 64,350.00
- Paving kawung tebal 6 sm mutu baik 1.0000 M3 41,250.00 41,250.00
- Pasir pasang (kaliworo) 0.2000 M3 115,500.00 23,100.00

Tenaga 21,560.00
- Mandor 0.0200 Oh 44,000.00 880.00
- Kepala Tukang Batu 0.0200 Oh 44,000.00 880.00
- Tukang Batu 0.2000 Oh 38,500.00 7,700.00
- Pekerja 0.4000 Oh 30,250.00 12,100.00

Analisa Harga Satuan Pekerjaan Konstruksi - Swakelola - Hal. 98


IV. HARGA SATUAN PEKERJAAN KONSTRUKSI (HSPK) - PEK. SWAKELOLA
PEMERINTAH KOTA SALATIGA

NO. URAIAN / MACAM PEKERJAAN

a. b.
I. PEKERJAAN PERSIAPAN
I.1 1 M' Pagar sementara dari kayu tinggi 2 meter
I. 2 1 M' Pagar sementara dari seng gelombang tinggi 2 meter
I. 3 1 M' Pagar sementara dari kawat duri tinggi 1,8 meter
I. 4 1 M2 Pengukuran dan pemasangan bouwplank
I .5 1 M2 Pembuatan kantor sementara, dengan lantai plesteran
I. 6 1 M2 Pembuatan gudang semen dan alat-alat
I. 7 1 M2 Pembuatan rumah jaga/konstruksi kayu
I. 8 1 M2 Membersihkan lapangan dan perataan
I. 9 1 M2 Pembuatan bedeng buruh
I.10 1 M2 Pembuatan bak adukan dari kayu tahun ukuran (40 x 50 x 20) cm
I. 11 1 M2 Pembuatan bak adukan dari bambu ukuran (40 x 50 x 20) cm
I. 12 1 M2 Pembuatan jalan sementara
I. 13 1 M2 Pasang pagar kawat jaring galvanis tinggi 1,00 m
I. 14 1 M2 Pasang pagar beton pracetak (5 x 50 x 213) cm

II. PEKERJAAN TANAH DAN PASIR


II. 1 1 M3 Galian Tanah Biasa Sedalam 1 m
II. 2 1 M3 Galian Tanah Biasa Sedalam 1 - 2 m
II. 3 1 M3 Galian Tanah Biasa Sedalam 2 - 3 m
II. 4 1 M3 Galian Tanah Keras Sedalam 1 m
II. 5 1 M3 Galian tanah cadas sedalam 1 m
II. 6 1 M3 Galian Tanah Lumpur Sedalam 1 m
II. 7 1 M3 Stripping setinggi 1 m
II. 8 1 M3 Tanah Diangkut Sejauh 15 m
II. 9 1 M3 Urugan kembali bekas galian
II. 10 1 M3 Tanah diratakan dan dipadatkan
II. 11 1 M3 Urugan pasir
II. 12 1 M3 Pemasangan lapisan ijuk
II. 13 1 M3 Urugan Sirtu
II. 14 1 M3 Urugan tanah mendatangkan

III. PEKERJAAN PONDASI


III. 1 1 M3 Pasang Pondasi Batu Kali 1 Pc : 1 Ps
III. 2 1 m3 Pasang Pondasi batu kali 1 Pc : 2 Ps
III. 3 1 m3 Pasang Pondasi batu kali 1 Pc : 2.5 Ps
III. 4 1m3 Pasang Pondasi batu kali, 1 Pc : 3 Ps
III. 5 1 m3 Pasang Pondasi batu kali, 1 Pc : 4 Ps
III. 6 1 m3 Pasang Pondasi Batu kali 1 Pc : 5 Ps
III. 7 1 m3 Pasang Pondasi Batu kali 1 Pc : 6 Ps
III. 8 1 m3 Pasang Pondasi Batu kali 1 Pc : 8 Ps
III. 9 1 m3 Pasang Pondasi Batu kali 1 Pc : 1/4 Kp : 4 Ps
III. 10 1 m3 Pasang Pondasi Batu kali 1 Pc : 3 Kp : 10 Ps

HSPK-Swakelola Page 99
NO. URAIAN / MACAM PEKERJAAN

a. b.
III. 11 1 m3 Pasang Pondasi Batu kali 1/4 Pc : 1 Kp : 4 Ps
III. 12 1 m3 Pasang Pondasi Batu Kosong
III. 13 1 m3 Pasang Pondasi sumuran diameter 100 cm
III. 14 1 m' Pembuatan Tiang pancang ( 40 x 40 ) cm, Beton bertulang
III. 15 1 m' Pembuatan Tiang pancang ( 35 x 35 ) cm, Beton bertulang
III. 16 1 M3 Membuat bronjong dari kawat galvanis/bronjong 3 mm diisi batu belah
III. 17 1 M3 Membuat bronjong dari kawat galvanis/bronjong 4 mm diisi batu belah
III. 18 1 M3 Membuat bronjong dari kawat galvanis/bronjong 5 mm diisi batu belah

IV. PEKERJAAN DINDING


IV.1 1 M2 Pasangan bata merah tebal 1 bata, 1 Pc : 1 Ps
IV.2 1 M2 Pasangan bata merah tebal 1 bata, 1 Pc : 2 Ps
IV. 3 1 M2 Pasangan bata merah tebal 1 bata, 1 Pc : 3 Ps
IV. 4 1 M2 Pasangan bata merah tebal 1 bata, 1 Pc : 4 Ps
IV. 5 1 M2 Pasangan bata merah tebal 1 bata, 1 Pc : 5 Ps
IV. 6 1 M2 Pasangan bata merah tebal 1 bata, 1 Pc : 6 Ps
IV. 7 1 M2 Pasangan bata merah tebal 1 bata, 1 Pc : 3 Kp : 10 Ps
IV. 8 1 M2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 1 Ps
IV. 9 1 M2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 2 Ps
IV. 10 1 M2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 3 Ps
IV. 11 1 M2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 4 Ps
IV. 12 1 M2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 5 Ps
IV. 13 1 M2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 6 Ps
IV. 14 1 M2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 8 Ps
IV. 15 1 M2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 3 Kp : 10 Ps
IV. 16 1 M2 pasang dinding roster/terawang (12x11x24) cm, 1Pc : 3 Ps
IV. 17 1 M2 Pasang dinding bataco

V. PEKERJAAN PLESTERAN
V. 1 1 M2 Plesteran 1 Pc : 1 Ps, tebal 15 mm
V. 2 1 M2 Plesteran 1 Pc : 2 Ps, tebal 15 mm
V. 3 1 M2 Plesteran 1 Pc : 3 Ps, tebal 15 mm
V. 4 1 M2 Plesteran 1 Pc : 4 Ps, tebal 15 mm
V. 5 1 M2 Plesteran 1 Pc : 5 Ps, tebal 15 mm
V. 6 1 M2 Plesteran 1 Pc : 6 Ps, tebal 15 mm
V. 7 1 M2 Plesteran 1 Pc : 8 Ps, tebal 15 mm
V. 8 1 M2 Plesteran 1 Pc : 2 Kp : 8 Ps, tebal 15 mm
V. 9 1 M2 Plesteran 1 Pc : 2 Ps, tebal 20 mm
V. 10 1 M2 Plesteran 1 Pc : 3 Ps, tebal 20 mm
V. 11 1 M2 Plesteran 1 Pc : 4 Ps, tebal 20 mm
V. 12 1 M2 Plesteran 1 Pc : 5 Ps, tebal 20 mm
V. 13 1 M2 Plesteran 1 Pc : 6 Ps, tebal 20 mm
V. 14 1 M2 Plesteran Beton 1 Pc : 2 Ps, tebal 15 mm
V. 15 1 M2 Plesteran Beton 1 Pc : 3 Ps, tebal 15 mm
V. 16 1 M' Plesteran Skoning 1 Pc : 2 Ps lebar 10 cm'
V. 17 1 M2 Plesteran Ciprat 1 Pc : 2 Ps
V. 18 1 M2 Plesteran Siar Pasangan Batu Kali, adukan 1 PC : 2 PS
V. 19 1 M' Sponengan ( untuk saluran dan sejenisnya )

HSPK-Swakelola Page 100


NO. URAIAN / MACAM PEKERJAAN

a. b.
V. 20 1 M2 Acian

VI. PEKERJAAN KAYU


VI. 1 1 M3 Pasang kusen pintu dan jendela kayu jati lokal
VI. 2 1 M3 Pasang kusen pintu dan jendela kayu kamper
VI. 3 1 M3 Pasang kusen pintu dan jendela kayu meranti
VI. 4 1 M3 Pasang kusen pintu dan jendela kayu kruing
VI. 5 1 M3 Pasang kusen pintu dan jendela kayu bengkirai
VI. 6 1 M2 Pasang pintu klam kayu kamper
VI. 7 1 M2 Pasang pintu klam kayu meranti
VI. 8 1 M2 Pasang pintu panel kayu jati lokal
VI. 9 1 M2 Pasang pintu panel kayu kamper
VI. 10 1 M2 Pasang pintu panel kayu meranti
VI. 11 1 M2 Pasang pintu panel kayu kruing
VI. 12 1 M2 Pasang pintu panel kayu bengkirai
VI. 13 1 M2 Pasang pintu dan jendela kaca kayu jati lokal
VI. 14 1 M2 Pasang pintu dan jendela kaca kayu kamper
VI. 15 1 M2 Pasang pintu dan jendela kaca kayu meranti
VI. 16 1 M2 Pasang pintu dan jendela kaca kayu kruing
VI. 17 1 M2 Pasang pintu dan jendela kaca kayu bengkirai
VI. 18 1 M2 Pasang daun pintu/ jendela kaca 3 mm rangka kayu jati
VI. 19 1 M2 Pasang daun pintu/ jendela kaca 3 mm rangka kayu kamper
VI. 20 1 M2 Pasang daun pintu/ jendela kaca 3 mm rangka kayu meranti
VI. 21 1 M2 Pasang daun pintu/ jendela kaca 3 mm rangka kayu kruing
VI. 22 1 M2 Pasang daun pintu/ jendela kaca 3 mm rangka kayu bengkirai
VI. 23 1 M2 Pasang pintu dan jendela jalusi kayu jati lokal
VI. 24 1 M2 Pasang pintu dan jendela jalusi kayu kamper
VI. 25 1 M2 Pasang pintu dan jendela jalusi kayu meranti
VI. 26 1 M2 Pasang pintu dan jendela jalusi kayu kruing
VI. 27 1 M2 Pasang pintu dan jendela jalusi kayu bengkirai
VI. 28 1 M2 Pasang pintu plywood rangkap, rangka kayu jati lokal
VI. 29 1 M2 Pasang pintu plywood rangkap, rangka kayu kamper
VI. 30 1 M2 Pasang pintu plywood rangkap, rangka kayu meranti
VI. 31 1 M2 Pasang pintu plywood rangkap, rangka kayu kruing
VI. 32 1 M2 Pasang pintu plywood rangkap, rangka kayu bengkirai
VI. 33 1 M2 Pasang jalusi mati kusen kayu jati lokal
VI. 34 1 M2 Pasang jalusi mati kusen kayu kamper
VI. 35 1 M2 Pasang jalusi mati kusen kayu meranti
VI. 36 1 M2 Pasang jalusi mati kusen kayu kruing
VI. 37 1 M2 Pasang jalusi mati kusen kayu bengkirai
VI. 38 1 M2 Pasang pintu teakwood rangkap, rangka expose kayu meranti
VI. 39 1 M2 Pasang pintu teakwood rangkap, rangka expose kayu jati lokal
VI. 40 1 M2 Pasang pintu teakwood rangkap, rangka expose kayu kamper
VI. 41 1 M2 Pasang pintu plywood & formika, rangkap rangka expose kayu jati lokal
VI. 42 1 M2 Pasang pintu plywood & formika, rangkap rangka expose kayu kamper
VI. 43 1 M2 Pasang pintu plywood & formika, rangkap rangka expose kayu meranti
VI. 44 1 M2 Pasang pintu plywood & formika, rangkap rangka expose kayu kruing
VI. 45 1 M2 Pasang pintu plywood & formika, rangkap kayu bengkirai

HSPK-Swakelola Page 101


NO. URAIAN / MACAM PEKERJAAN

a. b.
VI. 46 1 M2 Pasang pintu plywood & formika rangka kayu kamper (divernis)
VI. 47 1 M2 Pasang pintu plywood & formika rangka kayu meranti (divernis)
VI. 48 1 M2 Pasang pintu plywood & formika rangka kayu kruing (divernis)
VI. 49 1 M3 Pasang konstruksi kuda-kuda kayu jati lokal
VI. 50 1 M3 Pasang konstruksi kuda-kuda kayu kamper
VI. 51 1 M3 Pasang konstruksi kuda-kuda kayu meranti
VI. 52 1 M3 Pasang konstruksi kuda-kuda kayu kruing
VI. 53 1 M3 Pasang konstruksi kuda-kuda kayu bengkirai
VI. 54 1 M3 Pasang gording kayu jati lokal
VI. 55 1 M3 Pasang gording kayu kamper
VI. 56 1 M3 Pasang gording kayu meranti
VI. 57 1 M3 Pasang gording kayu kruing
VI. 58 1 M3 Pasang gording kayu bengkirai
VI. 59 1 M2 Rangka atap kayu jati lokal untuk seng
VI. 60 1 M2 Rangka atap kayu kamper untuk seng
VI. 61 1 M2 Rangka atap kayu meranti untuk seng
VI. 62 1 M2 Rangka atap kayu kruing untuk seng
VI. 63 1 M2 Rangka atap kayu bengkirai untuk seng
VI. 64 1 M2 Pekerjaan usuk 5/7 dan reng 2/3 kayu jati lokal
VI. 65 1 M2 Pekerjaan usuk 5/7 dan reng 2/3 kayu kamper
VI. 66 1 M2 Pekerjaan usuk 5/7 dan reng 2/3 kayu meranti
VI. 67 1 M2 Pekerjaan usuk 5/7 dan reng 2/3 kayu kruing
VI. 68 1 M2 Pekerjaan usuk 5/7 dan reng 2/3 kayu bengkirai
VI. 69 1 M2 Pekerjaan usuk 5/7 dan reng 3/4 kayu jati lokal untuk genteng beton
VI. 70 1 M2 Pekerjaan usuk 5/7 dan reng 3/4 kayu kamper untuk genteng beton
VI. 71 1 M2 Pekerjaan usuk 5/7 dan reng 3/4 kayu meranti untuk genteng beton
VI. 72 1 M2 Pekerjaan usuk 5/7 dan reng 3/4 kayu kruing untuk genteng beton
VI. 73 1 M2 Pekerjaan usuk 5/7 dan reng 3/4 kayu bengkirai untuk genteng beton
VI. 74 1 M2 Pasang rangka langit-langit (0.50 x 1.00) m, kayu jati lokal
VI. 75 1 M2 Pasang rangka langit-langit (0.50 x 1.00) m, kayu kamper
VI. 76 1 M2 Pasang rangka langit-langit (0.50 x 1.00) m, kayu meranti
VI. 77 1 M2 Pasang rangka langit-langit (0.50 x 1.00) m, kayu kruing
VI. 78 1 M2 Pasang rangka langit-langit (0.50 x 1.00) m, kayu bengkirai
VI. 79 1 M2 Pasang rangka langit-langit (0.60 x 0.60) m, kayu jati lokal
VI. 80 1 M2 Pasang rangka langit-langit (0.60 x 0.60) m, kayu meranti
VI. 81 1 M2 Pasang rangka langit-langit (0.60 x 0.60) m, kayu kamper
VI. 82 1 M2 Pasang rangka langit-langit (0.60 x 0.60) m, kayu kruing
VI. 83 1 M2 Pasang rangka langit-langit (0.60 x 0.60) m, kayu bengkirai
VI. 84 1 M3 Pasang plafond hanger kayu jati lokal
VI. 85 1 M3 Pasang plafond hanger kayu kamper
VI. 86 1 M3 Pasang plafond hanger kayu meranti
VI. 87 1 M3 Pasang plafond hanger kayu kruing
VI. 88 1 M3 Pasang plafond hanger kayu bengkirai
VI. 89 1 M2 Pasang lisplang ukuran (3 x 20) cm, kayu jati lokal
VI. 90 1 M2 Pasang lisplang ukuran (3 x 20) cm, kayu kamper
VI. 91 1 M2 Pasang lisplang ukuran (3 x 20) cm, kayu meranti
VI. 92 1 M2 Pasang lisplang ukuran (3 x 20) cm, kayu kruing
VI. 93 1 M2 Pasang lisplang ukuran (3 x 20) cm, kayu bengkirai

HSPK-Swakelola Page 102


NO. URAIAN / MACAM PEKERJAAN

a. b.
VI. 94 1 M2 Pasang lisplang ukuran (3 x 30) cm, kayu jati
VI. 95 1 M2 Pasang lisplang ukuran (3 x 30) cm, kayu kamper
VI. 96 1 M2 Pasang lisplang ukuran (3 x 30) cm, kayu meranti
VI. 97 1 M2 Pasang lisplang ukuran (3 x 30) cm, kayu kruing
VI. 98 1 M2 Pasang lisplang ukuran (3 x 30) cm, kayu bengkirai
VI. 99 1 M2 Pasang lisplang ukuran 2 x (3 x 20) cm, kayu kamper
VI. 100 1 M2 Pasang lisplang ukuran 2 x (3 x 20) cm, kayu meranti
VI. 101 1 M2 Pasang lisplang ukuran 2 x (3 x 20) cm, kayu kruing
VI. 102 1 M2 Pasang lisplang ukuran 2 x (3 x 20) cm, kayu bengkirai
VI. 103 1 M2 Pasang lisplang ukuran 2 x (2 x 20) cm, kayu kamper
VI. 104 1 M2 Pasang lisplang ukuran 2 x (2 x 20) cm, kayu meranti
VI. 105 1 M2 Pasang lisplang ukuran 2 x (2 x 20) cm, kayu kruing
VI. 106 1 M2 Pasang lisplang ukuran 2 x (2 x 20) cm, kayu bengkirai
VI. 107 1 M2 Pasang rangka dinding pemisah (60x120)cm kayu kamper 6/12
VI. 108 1 M2 Pasang rangka dinding pemisah (60x120)cm kayu meranti 6/12
VI. 109 1 M2 Pasang rangka dinding pemisah (60x120)cm kayu kruing 6/12
VI. 110 1 M2 Pasang rangka dinding pemisah (60x120)cm kayu bengkirai 6/12
VI. 111 1 M2 Pasang dinding pemisah plywood rangkap, rangka (60x120)cm kayu kamper 6/12
VI. 112 1 M2 Pasang dinding pemisah plywood rangkap, rangka (60x120)cm kayu kruing 6/12
VI. 113 1 M2 Pasang dinding pemisah plywood rangkap, rangka (60x120)cm kayu meranti 6/12
VI. 114 1 M2 Pasang dinding pemisah teakwood rangkap, rangka (60x120)cm kayu kamper 6/12
VI. 115 1 M2 Pasang dinding pemisah teakwood rangkap, rangka (60x120)cm kayu kruing 6/12
VI. 116 1 M2 Pasang dinding pemisah teakwood rangkap, rangka (60x120)cm kayu meranti 6/12
VI. 117 1 M2 Pasang plywood tebal 4 mm, untuk dinding
VI. 118 1 M' Pasang list plafond kayu profil jadi
VI. 119 1 M' Pasang list profil cornice gypsum lebar sampai 5 cm
VI. 120 1 M' Pasang list profil cornice gypsum lebar sampai 5 - 10 cm
VI. 121 1 M' Pasang list profil cornice gypsum lebar lebih dari 10 cm

VII. PEKERJAAN BETON


VII. 1 1 M3 Membuat beton tumbuk, 1Pc : 3 Ps : 5 Kr
VII. 2 1 M3 Membuat beton tumbuk, 1Pc : 3 Ps : 6 Kr
VII. 3 1 M3 Membuat beton tumbuk, 1Pc : 4 Ps : 6 Kr
VII. 4 1 M2 Membuat lantai kerja beton tumbuk, 1Pc : 3 Ps : 5 Kr, tebal 5 cm
VII. 5 1 M3 Membuat beton bertulang, 1 Pc : 2 Ps : 3 Kr
VII. 6 1 M3 Membuat beton bertulang, 1 Pc : 2 Ps : 4 Kr
VII. 7 1 M3 Membuat beton bertulang, 1 Pc : 1,5 Ps : 2,5 Kr
VII. 8 1 Kg Pembesian / kabel presstressed dengan besi polos atau besi ulir
VII. 9 Bekisting untuk 1 M3 beton
VII. 10 Membongkar bekisting untuk 1 M3 beton
VII. 11 Stutwerk untuk 1 M3 beton tinggi 3 - 4 m (memakai dolken)
VII. 12 Stutwerk untuk 1 M3 beton tinggi 3 - 4 m (memakai bambu)
VII. 13 Stutwerk untuk 1 M3 beton tinggi 3 - 4 m (memakai scafolding)
VII. 14 1 M' Membuat kolom praktis/ kolom penguat beton bertulang (11 x 11) cm
VII. 15 1 M' Membuat ring balok beton bertulang (10 x 15) cm

VIII. PEKERJAAN PENUTUP ATAP


VIII. 1 1 M2 Pasang atap genteng palentong / vlampress kecil

HSPK-Swakelola Page 103


NO. URAIAN / MACAM PEKERJAAN

a. b.
VIII. 2 1 M2 Pasang atap genteng kodok
VIII. 3 1 M2 Pasang atap genteng palentong/ vlampress super/besar
VIII. 4 1 M2 Pasang atap genteng beton warna natural
VIII. 5 1 M' Pasang atap genteng bubung palentong/ vlampress kecil
VIII. 6 1 M' Pasang atap genteng bubung kodok
VIII. 7 1 M' Pasang atap genteng bubung palentong/ vlampress super/ besar
VIII. 8 1 M' Pasang atap bubungan genteng beton warna natural
VIII. 9 1 M2 Pasang atap asbes gelombang gelombang besar (300 x 102 x 5 mm)
VIII. 10 1 M2 Pasang atas asbes gelombang gelombang besar (200 x 102 x 5 mm)
VIII. 11 1 M2 Pasang atas asbes gelombang gelombang besar (180 x 102 x 5 mm)
V.III. 12 1 M2 Pasang atas asbes gelombang gelombang kecil (300 x 105 x 4 mm)
VIII. 13 1 M2 Pasang atas asbes gelombang gelombang kecil (270 x 105 x 4 mm)
VIII. 14 1 M2 Pasang atas asbes gelombang gelombang kecil (240 x 105 x 4 mm)
VIII. 15 1 M2 Pasang atas asbes gelombang gelombang kecil (210 x 105 x 4 mm)
VIII. 16 1 M2 Pasang atas asbes gelombang gelombang kecil (150 x 105 x 4 mm)
VIII. 17 1 M2 Pasang atap seng BJLS 0,2 gelombang P = 300 cm
VIII. 18 1 M2 Pasang atap seng BJLS 0,2 gelombang P = 240 cm
VIII. 19 1 M2 Pasang atap seng BJLS 0,2 gelombang P = 210 cm
VIII. 20 1 M2 Pasang atap seng BJLS 0,2 gelombang P = 180 cm
VIII. 21 1 M' Pasang nok paten 1,05 m
VIII. 22 1 M' Pasang nok paten 1,08 m
VIII. 23 1 M2 pasang alluminium foil/sisalation
VIII. 24 1 M' Pasang talang datar, seng bjls 28
VIII. 25 1 M' Pasang talang miring, seng bjls 28
VIII. 26 1 M' Pasang talang 1/2 lingkaran D-10 cm, seng bjls 28
VIII. 27 1 M' Pasang talang 1/2 lingkaran D-10 cm, seng bjls 24

IX. PEKERJAAN PASANG LANGIT-LANGIT


IX. 1 1 M2 Pasang langit-langit asbes "Elepent"(1,00 x 1,00) m, tebal 3 mm
IX. 2 1 M2 Pasang langit-langit asbes "Atrisco"(1,00 x 1,00) m, tebal 3 mm
IX. 3 1 M2 Pasang langit-langit asbes "Kerang super" (1,00 x 1,00) m, tebal 3 mm
IX. 4 1 M2 Pasang langit-langit asbes "Djabes" (1,00 x 1,00) m, tebal 3 mm
IX. 5 1 M2 Pasang langit-langit playwood (30 x 60) cm, tebal 4 mm
IX. 6 1 M2 Pasang langit-langit playwood (30 x 60) cm, tebal 6 mm
IX. 7 1 M2 Pasang langit-langit playwood (60 x 120) cm, tebal 4 mm
IX. 8 1 M2 Pasang langit-langit playwood (60 x 120) cm, tebal 6 mm
IX. 9 1 M2 Pasang langit-langit teakwood (30 x 60) cm, tebal 4 mm
IX. 10 1 M2 Pasang langit-langit teakwood (60 x 120) cm, tebal 4 mm
IX. 11 1 M2 Pasang langit-langit lat kayu jati lokal
IX. 12 1 M2 Pasang langit-langit lat kayu kamper
IX. 13 1 M1 List pasang list langit-langit kayu dibuat profil
IX. 14 1 M2 Pasang langit-langit asbes "Kerang super" (1,00 x 1,00) m, tebal 3 mm, rangka kayu meranti
IX. 15 1 M2 Pasang langit-langit Triplek 4 mm + rangka kayu meranti
IX. 16 1 M2 Pasang langit-langit gypsum board, tebal 9 mm
IX. 17 1 M2 Pasang langit-langit gypsum board tebal 9 mm, rangka 60 x 120 kayu kamper
IX. 18 1 M2 Pasang langit-langit gypsum board tebal 9 mm, rangka 60 x 120 kayu meranti
IX. 19 1 M2 Pasang langit-langit gypsum board tebal 9 mm, rangka 60 x 120 kayu kruing
IX. 20 1 M2 Pasang langit-langit gypsum board tebal 9 mm, rangka 60 x 120 kayu bengkirai

HSPK-Swakelola Page 104


NO. URAIAN / MACAM PEKERJAAN

a. b.
IX. 21 1 M2 Pasang langit-langit kalsiboard tebal 3,5 mm, rangka 60 x 120 kayu kamper
IX. 22 1 M2 Pasang langit-langit kalsiboard tebal 3,5 mm, rangka 60 x 120 kayu meranti
IX. 23 1 M2 Pasang langit-langit kalsiboard tebal 3,5 mm, rangka 60 x 120 kayu kruing
IX. 24 1 M2 Pasang langit-langit kalsiboard tebal 3,5 mm, rangka 60 x 120 kayu bengkirai

X. PEKERJAAN SANITASI
X. 1 Memasang 1 buah kloset duduk/monoblok
X. 2 Memasang 1 buah kloset jongkok
X. 3 Memasang 1 buah urinoir
X. 4 Memasang 1 buah wastafel kecil
X. 5 Memasang 1 buah wastafel besar
X. 6 Memasang 1 buah bak mandi buthtub fiber
X. 7 Memasang 1 buah bak mandi fiberglass volume 0,30 m3
X. 8 Memasang 1 buah bak mandi batu bata volume 0,30 m3
X. 9 Memasang 1 buah badkip fiber
X. 10 Membuat 1 buah bak beton volume 1 M3 air
X. 11 Memasang 1 M' Got U-15
X. 12 Memasang 1 M' Got U-20
X. 13 Memasang 1 M' Got U-30
X. 14 Memasang 1 buah bak kontrol pasangan batu bata ukuran (30 x 30) cm, tinggi 35 cm
X. 15 Memasang 1 buah bak kontrol pasangan batu bata ukuran (45 x 45) cm, tinggi 50 cm
X. 16 Memasang 1 buah bak kontrol pasangan batu bata ukuran (60 x 60) cm, tinggi 65 cm
X. 17 Memasang 1 M' pipa galvanis diameter 1/2"
X. 18 Memasang 1 M' pipa galvanis diameter 3/4"
X. 19 Memasang 1 M' pipa galvanis diameter 1"
X. 20 Memasang 1 M' pipa galvanis diameter 1 1/2"
X. 21 Memasang 1 M' pipa galvanis diameter 2"
X. 22 Memasang 1 M' pipa galvanis diameter 3"
X. 23 Memasang 1 M' pipa PVC tipe AW diameter 1/2"
X. 24 Memasang 1 M' pipa PVC tipe AW diameter 3/4"
X. 25 Memasang 1 M' pipa PVC tipe AW diameter 1"
X. 26 Memasang 1 M' pipa PVC tipe AW diameter 1 1/2"
X. 27 Memasang 1 M' pipa PVC tipe AW diameter 2"
X. 28 Memasang 1 M' pipa PVC tipe AW diameter 2 1/2"
X. 29 Memasang 1 M' pipa PVC tipe AW diameter 3"
X. 30 Memasang 1 M' pipa PVC tipe AW diameter 4"
X. 31 Memasang 1 bh bak cuci piring / Kitchen zinc
X. 32 Memasang 1 bh kran diameter 3/4" atau 1/2"
X. 33 Memasang 1 bh Floor drain

XI. PEKERJAAN BESI DAN ALLUMINIUM


XI. 1 1 Kg Pasang rangka atap baja
XI. 2 1 M2 Pasang pintu besi baja
XI. 3 1 M2 Pasang jendela besi
XI. 4 1 M2 Pasang jendela besi tahan api
XI. 5 1 M2 Pasang pintu gulung besi
XI. 6 1 M2 Pasang Rolling door bahan besi
XI. 7 1 M2 Pasang pintu Sunscreen alluminium

HSPK-Swakelola Page 105


NO. URAIAN / MACAM PEKERJAAN

a. b.
XI. 8 1 M2 Pasang Rolling door bahan alumunium
XI. 9 1 M2 Pasang pintu alluminium
XI. 10 1 M2 Pasang Vertikals blinds
XI. 11 1 M2 Pasang terali besi
XI. 12 1 M2 Pasang kawat harmonika
XI. 13 1 M2 Pasang kawat kassa almunium
XI. 14 1 M2 Pasang kawat kassa plastik
XI. 15 1 M2 Pasang jendela nako & tralis

XII. PEKERJAAN KUNCI DAN KACA


XII. 1 1 Buah pasang kunci tanam antik
XII. 2 1 Buah pasang kunci tanam biasa
XII. 3 1 Buah pasang kunci tanam kamar mandi
XII. 4 1 Buah pasang kunci silinder
XII. 5 1 Buah pasang engsel pintu
XII. 6 1 Buah pasang engsel jendela
XII. 7 1 Buah pasang engsel piano
XII. 8 1 Buah pasang spring knip
XII. 9 1 Buah pasang hak angin
XII. 10 1 Buah pasang door closer
XII. 11 1 Buah pasang kunci selot
XII. 12 1 Buah pasang pegangan pintu/door holder
XII. 13 1 Buah pasang door stop
XII. 14 1 Buah pasang rel pintu dorong
XII. 15 1 Buah pasang kunci lemari
XII. 16 1 M2 pasang kaca, tebal 3 mm
XII. 17 1 M2 pasang kaca, tebal 5 mm
XII. 18 1 M2 pasang kaca es, tebal 5 mm
XII. 19 1 M2 pasang kaca rayben, tebal 5 mm

XIII. PEKERJAAN PENUTUP LANTAI DAN DINDING


XIII. 1 1 M2 Pasang lantai keramik warna putih polos 20x20 cm
XIII. 2 1 M2 Pasang lantai keramik bermotif 20x20 cm
XIII. 3 1 M2 Pasang keramik lantai kamar mandi 20x20 cm
XIII. 4 1 M2 Pasang lantai keramik warna putih polos 30x30 cm
XIII. 5 1 M2 Pasang lantai keramik bermotif warna muda 30x30 cm
XIII. 6 1 M2 Pasang lantai keramik bermotif warna tua 30x30 cm
XIII. 7 1 M2 Pasang lantai keramik bermotif warna muda 40x40 cm
XIII. 8 1 M2 Pasang lantai keramik bermotif warna tua 40x40 cm
XIII. 9 1 M2 Pasang keramik teras/ garasi bermotif warna tua 30x30 cm
XIII. 10 1 M2 Pasang dinding keramik bermotif 20 x 20 cm
XIII. 11 1 M2 Pasang dinding keramik warna polos 20 x 25 cm
XIII. 12 1 M2 Pasang dinding keramik bermotif warna muda 20 x 33 cm
XIII. 13 1 M2 Pasang dinding keramik bermotif warna tua 20 x 33 cm
XIII. 14 1 M' Pasang plint keramik ukuran 7,5 x 20 cm
XIII. 15 1 M' Pasang plint keramik ukuran 8 x 25 cm
XIII. 16 1 M' Pasang keramik kuku macan
XIII. 17 1 M' Pasang keramik stepnozing 5 x 30 cm

HSPK-Swakelola Page 106


NO. URAIAN / MACAM PEKERJAAN

a. b.
XIII. 18 1 M2 Pasang dinding batu palimanan
XIII. 19 1 M2 Pasang dinding batu tempel hitam
XIII. 20 1 M2 Pasang dinding batu candi

XIV. PEKERJAAN PENGECATAN


XIV. 1 1 M2 mengikis/mengerok permukaan cat tembok lama
XIV. 2 1 M2 Mencuci bidang permukaan tembok yang pernah di cat
XIV. 3 1 M2 Mengerok karat cat lama permukaan baja dengan cara manual
XIV. 4 1 M2 Menyabun permukaan tembok lama
XIV. 5 1 M2 Mendempul dan menggosok kayu
XIV. 6 1 M2 Pengecatan bidang kayu lama
XIV. 7 1 M2 Pengecatan bidang kayu baru (1 lapis plamir), 1 lapis cat dasar, 2 lapis cat penutup
XIV. 8 1 M2 Pengecatan bidang kayu baru (1 lapis plamir), 1 lapis cat dasar, 3 lapis cat penutup
XIV. 9 1 M2 Pelaburan bidang kayu dengan teak oil
XIV. 10 1 M2 Pelaburan bidang kayu dengan politur/ pernis
XIV. 11 1 M2 Pelaburan bidang kayu dengan cat residu dan ter
XIV. 12 1 M2 Pelaburan bidang kayu dengan vernis
XIV. 13 1 M2 Pengecatan tembok baru (1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup)
XIV. 14 1 M2 Pengecatan tembok lama (1 lapis cat dasar, 2 lapis cat penutup)
XIV. 15 1 M2 Pengecatan permukaan baja dengan meni besi
XIV. 16 1 M2 Pengecatan permukaan baja dengan meni besi dan perancah

XV. PEKERJAAN BONGKARAN


XV. 1 1 M3 Membongkar pasangan batu kali
XV. 2 1 M3 Membongkar beton bertulang dan membersihkan
XV. 3 1 M3 Membongkar dinding tembok bata merah dan membersihkan
XV. 4 1 M2 Membongkar lantai tegel
XV. 5 1 M2 Mengupas plesteran lama
XV. 6 1 M2 Membongkar genteng/ sirap
XV. 7 1 M2 Membongkar atap seng
XV. 8 1 M2 Membongkar usuk/ reng untuk dipakai lagi
XV. 9 1 M2 Membongkar usuk/ reng untuk tidak dipakai lagi
XV. 10 1 M3 Membongkar kayu balok loteng/ kuda-kuda/ dlurung/ jembatan untuk dipakai lagi
XV. 11 1 M3 Membongkar usuk/ reng untuk tidak dipakai lagi

XVI. PEKERJAAN PERKERASAN JALAN


XVI. 1 1 M' Pasang kanstin batu bata 1:2
XVI. 2 1 M' Pasang kanstin batu bata 1:4
XVI. 3 1 M' Pasang kanstin 20 x 30 x 60 cm
XVI. 4 1 M2 Pasang paving block tebal 6 cm
XVI. 5 1 M2 Pasang paving block (mesin) tebal 6 cm
XVI. 6 1 M2 Pasang paving block kawung (mutu sedang) tebal 6 cm
XVI. 7 1 M2 Pasang paving block kawung (mutu baik) tebal 6 cm

HSPK-Swakelola Page 107


ERJAAN KONSTRUKSI (HSPK) - PEK. SWAKELOLA

HARGA SAT.
(Rp.)

c.

128,639.50
126,934.50
222,874.50
30,195.00
605,770.00
338,965.00
512,050.00
5,225.00
509,602.50
94,666.00
17,539.50
58,685.00
18,550.50
530,637.25

23,787.50
29,205.00
25,445.75
33,858.00
48,015.00
38,280.00
38,280.00
10,422.50
7,929.17
17,325.00
103,235.00
282,975.00
134,062.50
88,715.00

689,557.00
565,108.50
528,220.00
500,307.50
461,450.00
434,522.00
415,585.50
389,642.00
464,662.00
362,186.00

HSPK-Swakelola Page 108


HARGA SAT.
(Rp.)

c.
338,426.00
217,021.20
485,771.00
679,276.40
535,739.60
316,781.67
430,576.67
507,998.33

173,057.50
152,900.00
142,565.50
135,756.50
132,011.00
130,251.00
120,606.75
81,719.00
73,139.00
68,332.00
65,521.50
63,750.50
62,716.50
60,830.00
60,280.00
132,121.00
60,885.00

35,072.40
29,726.40
27,380.10
25,806.00
24,875.40
24,146.10
23,321.10
22,990.00
39,761.70
36,633.30
34,496.00
33,293.70
32,282.80
29,326.00
27,219.50
21,807.50
19,470.00
24,530.00
4,707.45

HSPK-Swakelola Page 109


HARGA SAT.
(Rp.)

c.
14,355.00

8,911,650.00
9,571,650.00
4,951,650.00
6,931,650.00
11,353,650.00
386,974.50
206,574.50
452,650.00
496,650.00
316,250.00
386,650.00
562,650.00
303,820.00
330,220.00
221,980.00
264,220.00
369,820.00
304,755.00
314,655.00
245,355.00
275,055.00
341,385.00
624,250.00
694,650.00
406,010.00
518,650.00
800,250.00
355,135.00
382,635.00
269,885.00
313,885.00
423,885.00
538,191.50
604,191.50
333,591.50
439,191.50
703,191.50
308,550.00
393,800.00
421,300.00
423,879.50
451,379.50
338,629.50
382,629.50
492,629.50

HSPK-Swakelola Page 110


HARGA SAT.
(Rp.)

c.
430,754.50
318,004.50
362,004.50
8,114,700.00
8,719,700.00
4,484,700.00
6,299,700.00
10,353,200.00
7,679,760.00
8,284,760.00
4,049,760.00
5,864,760.00
9,918,260.00
82,857.50
88,907.50
46,557.50
64,707.50
105,242.50
126,445.00
136,125.00
68,365.00
97,405.00
162,261.00
150,205.00
161,865.00
80,245.00
115,225.00
193,347.00
124,547.50
133,017.50
73,727.50
99,137.50
155,886.50
129,690.00
75,900.00
138,655.00
102,795.00
162,860.50
8,065,750.00
8,670,750.00
4,435,750.00
6,250,750.00
10,304,250.00
63,855.00
71,775.00
39,303.00
49,167.80
83,655.00

HSPK-Swakelola Page 111


HARGA SAT.
(Rp.)

c.
89,595.00
101,475.00
52,767.00
71,775.00
119,295.00
143,550.00
78,606.00
103,950.00
167,310.00
103,950.00
60,654.00
77,550.00
119,790.00
226,044.50
118,244.50
164,444.50
267,624.50
289,905.00
228,305.00
182,105.00
303,154.50
241,554.50
195,354.50
27,689.75
12,452.00
15,041.76
17,791.76
23,841.76

495,577.50
476,025.00
452,540.00
56,562.00
719,290.00
684,502.50
779,955.00
9,942.90
763,400.00
121,000.00
1,334,025.00
748,825.00
1,341,980.00
44,547.25
59,691.50

42,504.00

HSPK-Swakelola Page 112


HARGA SAT.
(Rp.)

c.
38,379.00
25,283.50
44,660.00
58,014.00
52,514.00
53,064.00
59,444.00
36,774.10
42,565.60
48,010.60
30,685.60
35,074.60
30,702.10
31,032.10
36,070.10
35,514.60
35,998.60
36,119.60
36,603.60
43,081.50
72,781.50
16,852.00
71,186.50
103,950.00
99,687.50
99,357.50

19,354.50
19,354.50
13,304.50
18,749.50
29,620.25
36,839.00
29,620.25
36,839.00
38,901.50
38,901.50
204,523.00
230,890.00
12,562.00
68,904.00
125,004.00
27,625.40
140,877.94
90,827.94
112,277.94
160,182.94

HSPK-Swakelola Page 113


HARGA SAT.
(Rp.)

c.
137,089.54
87,404.54
108,489.54
156,394.54

1,018,105.00
146,657.50
1,368,604.00
313,005.00
347,985.00
658,075.00
361,900.00
908,815.60
644,911.58
4,687,449.80
46,895.03
52,395.03
55,145.03
274,345.50
288,145.00
440,231.00
35,099.17
40,782.50
50,728.33
75,164.10
93,634.93
210,110.45
9,283.45
11,201.58
13,972.20
22,497.20
28,204.55
29,743.45
52,752.15
82,163.40
225,843.50
16,940.00
18,562.50

18,843.00
983,955.50
1,012,038.50
1,897,659.50
385,159.50
324,536.30
366,916.00

HSPK-Swakelola Page 114


HARGA SAT.
(Rp.)

c.
377,850.00
198,036.30
163,179.50
314,054.40
38,489.00
32,439.00
20,339.00
38,104.00

209,187.00
80,712.50
63,731.25
63,632.25
15,171.75
10,664.50
17,875.00
13,521.75
9,121.75
133,072.50
59,125.00
160,572.50
12,864.50
165,187.00
19,236.25
61,371.75
79,521.75
103,721.75
91,621.75

76,059.50
91,459.50
87,059.50
75,025.50
83,275.50
89,875.50
90,975.50
93,725.50
91,525.50
89,259.50
92,559.50
99,775.50
105,275.50
27,528.60
25,878.60
13,131.80
65,381.80

HSPK-Swakelola Page 115


HARGA SAT.
(Rp.)

c.
151,057.50
131,807.50
149,737.50

4,757.50
5,472.50
5,472.50
5,472.50
5,148.00
23,331.00
28,325.00
35,794.00
16,417.50
18,293.00
5,021.50
15,587.00
8,778.00
6,652.80
11,528.00
22,116.05

166,100.00
193,600.00
80,025.00
6,490.00
1,622.50
6,490.00
4,950.00
9,064.00
6,490.00
387,200.00
39,050.00

55,307.91
53,270.49
76,780.00
72,160.00
83,160.00
80,410.00
85,910.00

HSPK-Swakelola Page 116


I. HARGA SATUAN UPAH - PEKERJAAN SWAKELOLA

Harga
No Pekerja Sat. Upah Tenaga Keterangan
(Rp.)
(1) (2) (3) (4) (5)
1 Mandor Hari 44,000.00
2 Kepala Tukang Batu Hari 44,000.00
3 Kepala Tukang Besi Hari 44,000.00
4 Kepala Tukang Cat Hari 44,000.00
5 Kepala Tukang Kayu Hari 44,000.00
6 Kepala Tukang Listrik Hari 44,000.00
7 Tukang Batu Hari 38,500.00
8 Tukang Besi Hari 38,500.00
9 Tukang Cat Hari 38,500.00
10 Tukang Plitur Hari 38,500.00
11 Tukang Kayu Hari 38,500.00
12 Tukang Listrik Hari 38,500.00
13 Tukang Las Hari 38,500.00
14 Tukang Leideng Hari 38,500.00
15 Tukang Gali Hari 30,250.00
16 Pekerja Hari 30,250.00
17 Masinis Hari 38,500.00
18 Pembantu Masinis Hari 33,000.00
19 Pemasak Aspal Hari 33,000.00
20 Penjaga Malam Hari 30,250.00

Harga Satuan Upah dan Bahan/Material - Swakelola Hal. 117


II. HARGA SATUAN BAHAN/ MATERIAL - PEKERJAAN BORONG

No Jenis Bahan Sat. Harga Bahan Keterangan


(Rp.)
(1) (2) (3) (4) (5)
I PASIR DAN BATU
1 Pasir beton (muntilan) m3 129,250.00
2 Pasir pasang (kaliworo) m3 115,500.00
3 Pasir Urug m3 78,100.00
4 Batu Belah m3 117,700.00
5 Batu pecah 5/7 m3 123,750.00
6 Batu pecah 2/3 (split) m3 192,500.00
7 Batu pecah 2/3 giling m3 198,000.00
8 Batu pecah 1/2 giling m3 220,000.00
9 Batu pecah 1/1 giling m3 247,500.00
10 Batu pecah 0.5/1 giling m3 220,000.00
11 Koral Beton m3 143,000.00
12 Kerikil m3 82,500.00
13 Tanah Urug m3 66,000.00
14 Tanah Liat m3 35,750.00
15 Sirtu m3 104,500.00
16 Batu Bata lokal bh 484.00
17 Batako bh 1,760.00
18 Roster 25/25 bh 3,300.00
19 Roster 20/20 bh 3,850.00
20 Roster 10/20 bh 3,850.00
21 Roster 30/30 bh 7,535.00
22 Roster 15/25 bh 6,545.00
23 Roster 15/30 bh 6,875.00
24 Batu Hias Tempel m2 71,500.00
25 Batu Palimanan m2 99,000.00
26 Batu Candi m2 99,000.00
27 Panel beton pracetak lbr 247,500.00
28 Kolom beton pra cetak btg 346,500.00

II SEMEN ( PORTLAND CEMENT)


1 Semen PC ( Portland Cement ) 40 kg kg 1,100.00
2 Semen Putih kg 1,980.00
3 Semen Warna kg 3,850.00

III KAPUR DAN GYPSUMBOARD + ACCESORIS


1 Kapur Pasang m3 110,000.00
2 Kapur Sirih kg 1,980.00
3 Cornice adhesive (tepung gypsum) @ 20 kg "A-plus" kg 2,915.00
4 Casting @ 20 kg "A-plus" kg 1,595.00
5 Paku Gypsum kg 16,500.00
6 Kassa gypsum roll 7,700.00
7 Gypsum Board 9 mm " Elephant " lbr 56,100.00
8 Gypsum Board 9 mm " Jaya Board " lbr 58,300.00
9 Gypsum Board 9 mm " Knuff " lbr 53,900.00
10 Kalsiboard 3 mm 120 x 240 lbr 49,500.00
11 Kalsiboard 6 mm 120 x 240 lbr 96,250.00

Harga Satuan Upah dan Bahan/Material - Swakelola Hal. 118


No Jenis Bahan Sat. Harga Bahan Keterangan
(Rp.)
(1) (2) (3) (4) (5)
12 Kalsiboard 9 mm 120 x 240 lbr 137,500.00
13 Akustik uk 30 x 30 lbr 6,050.00
14 Akustik uk 30 x 60 lbr 8,800.00
15 Akustik uk 60 x 120 lbr 39,600.00
16 Hardbord 4" x 8" lbr 72,600.00
17 Hollow 20 x 40 warna hijau btg 12,650.00
18 Hollow 40 x 40 warna hijau btg 14,850.00
19 Hollow 20 x 40 galvanis steel btg 15,400.00
20 Hollow 40 x 40 galvanis steel btg 18,700.00

Harga Satuan Upah dan Bahan/Material - Swakelola Hal. 119


No Jenis Bahan Sat. Harga Bahan Keterangan
(Rp.)
(1) (2) (3) (4) (5)
IV BESI, BAJA, DAN ALMUNIUM
1 Besi Beton Polos Diameter 6 mm Panjang 12 m' btg 15,400.00
2 Besi Beton Polos Diameter 8 mm Panjang 12 m' btg 26,400.00
3 Besi Beton Polos Diameter 10 mm Panjang 12 m' btg 34,100.00
4 Besi Beton Polos Diameter 12 mm Panjang 12 m' btg 55,000.00
5 Besi Beton Polos Diameter 16 mm Panjang 12 m' btg 123,200.00
6 Besi Beton Polos Diameter 19 mm Panjang 12 m' btg 192,500.00
7 Besi Beton Ulir Diameter 10 mm btg 40,700.00
8 Besi Beton Ulir Diameter 13 mm btg 85,250.00
9 Besi Beton Ulir Diameter 16 mm btg 143,000.00
10 Besi Beton Ulir Diameter 19 mm btg 209,000.00
11 Besi Beton polos kg 8,800.00
12 Besi Beton ulir kg 8,800.00
13 Besi Beton prestress kg 11,000.00
14 Besi Strip kg 9,900.00
15 Besi Profil IWF kg 11,000.00
16 Besi Siku L 30 x 30 x 3 btg 47,300.00
17 Besi Siku L 40 x 40 x 4 btg 82,500.00
18 Besi Siku L 50 x 50 x 5 btg 143,000.00
19 Besi Siku L 60 x 60 x 6 btg 286,000.00

V KAWAT
1 Kawat Beton / Bendrat kg 11,550.00
2 Kawat Ayakan m2 11,000.00
3 Kawat Bronjong kg 12,100.00
4 Kawat Nyamuk Kasa Almunium m2 16,500.00
5 Kawat Nyamuk Kasa Plastik m2 5,500.00
6 Kawat Las kg 20,900.00
7 Kawat seng polos kg 19,250.00
8 Kawat Duri kg 8,066.00
9 Kawat Galvanis m2 19,250.00
10 Kawat Harmonika 12 x 24 mm m2 22,000.00
11 Kawat Harmonika 12 x 45 mm m2 15,400.00
12 Kawat Harmonika 14 x 30 mm m2 27,500.00
13 Kawat Harmonika 14 x 35 mm m2 18,700.00

VI CAT dan MINYAK


1 Cat Besi/ Kayu "Emco" warna standar kg 42,900.00
2 Cat Besi/ Kayu "Emco" warna khusus kg 47,850.00
3 Cat Besi/ Kayu :Avian" kg 39,600.00
4 Cat tembok "Maxilite" kg 10,450.00
5 Cat tembok "Catylac" warna standar kg 15,400.00
6 Cat tembok "Decolith" warna standar kg 12,980.00
7 Cat tembok Interior "mowilex" warna stansar ltr 44,880.00
8 Cat tembok Exterior "mowilex" warna standar ltr 50,600.00
9 Cat tembok Interior "dulux" warna standar ltr 51,920.00
10 Cat tembok Exterior "dulux" warna standar ltr 83,600.00
11 Waterproofing "aguaproof" kg 44,000.00
12 Cat Meni Besi "altex" kg 18,700.00
13 Cat Meni Kayu "altex" kg 18,700.00

Harga Satuan Upah dan Bahan/Material - Swakelola Hal. 120


No Jenis Bahan Sat. Harga Bahan Keterangan
(Rp.)
(1) (2) (3) (4) (5)
14 Dempul Kayu "altex" kg 22,000.00
15 Dempul Lilin / Kayu btg 2,200.00
16 Plamur Kayu jago kg 22,000.00
17 Plamur Tembok kg 6,875.00
18 Sirlak Putih Batangan kg 19,250.00
19 Sirlak Kuning Serbuk kg 8,250.00
20 Oker Kuning kg 8,250.00
21 Oker Hitam kg 8,250.00
22 Oker Pewarna Politur Merah / Coklat btl 1,650.00
23 Politur Jadi ltr 22,000.00

Harga Satuan Upah dan Bahan/Material - Swakelola Hal. 121


No Jenis Bahan Sat. Harga Bahan Keterangan
(Rp.)
(1) (2) (3) (4) (5)
24 Teak Oil ltr 27,500.00
25 Pernis ltr 16,500.00
26 Terpentin ltr 13,200.00
27 Minyak Cat ltr 9,350.00
28 Thinner A ltr 8,800.00
29 Thinner Biasa ltr 9,350.00
30 Spiritus ltr 6,050.00
31 Wood Filler "impra" kg 26,400.00
32 Soda Api bungks 2,200.00
33 Ampelas lbr 1,650.00
34 Ampelas m' 1,650.00
35 Kuas Roll bh 11,000.00
36 Kuas 1 " bh 2,200.00
37 Kuas 2,5 " bh 3,300.00
38 Kuas 4 " bh 7,700.00
39 Lem kayu "aica aibon" kg 46,750.00
40 Lem kayu "fox" kg 11,000.00
41 Lem kayu "rajawali" kg 8,800.00
42 Residu/ ter ltr 4,950.00
43 Minyak Begesting ltr 16,500.00
44 Sabun kg 16,500.00
45 Pasir silika/ Batu apung kg 8,470.00

VII KERAMIK/ GRANIT


1 Keramik 20 x 20 cm warna putih "mulia" m2 27,500.00
2 Keramik 20 x 20 cm bermotif "roman" m2 71,500.00
3 Keramik 20 x 20 cm bermotif "granmaster" m2 49,500.00
4 Keramik 20 x 20 cm bermotif "picasso" m2 46,750.00
5 Keramik 20 x 20 cm bermotif "asia tile" m2 40,700.00
6 Keramik 20 x 25 cm warna polos "picasso" m2 38,500.00
7 Keramik 20 x 25 cm motif warna muda "picasso" m2 38,500.00
8 Keramik 20 x 25 cm motif warna tua "picasso" m2 38,500.00
9 Keramik 20 x 25 cm warna polos "kia" m2 44,000.00
10 Keramik 20 x 25 cm "asia bombay" m2 41,250.00
11 Keramik 20 x 25 cm "asia nepal" m2 42,900.00
12 Keramik 20 x 25 cm "accura" m2 27,500.00
13 Keramik 20 x 25 cm "asia tile" m2 28,600.00
14 Keramik 20 x 25 cm "mulia" m2 29,700.00
15 Keramik 20 x 25 cm "kia" m2 44,550.00
16 Keramik 20 x 33 cm motif warna muda "platinum" m2 52,250.00
17 Keramik 20 x 33 cm motif warna tua "platinum" m2 57,750.00
18 Keramik 30 x 30 cm warna putih "accura" m2 27,500.00
19 Keramik 30 x 30 cm warna putih "asia tile" m2 30,250.00
20 Keramik 30 x 30 cm warna putih "mulia" m2 27,500.00
21 Keramik 30 x 30 cm warna putih "ikad" m2 30,800.00
22 Keramik 40 x 40 cm warna putih "asia tile" m2 36,300.00
23 Keramik 30 x 30 cm bermotif warna muda "asia tile" m2 35,750.00
24 Keramik 30 x 30 cm bermotif warna tua "asia tile" m2 42,350.00
25 Keramik 30 x 30 cm bermotif warna muda "mulia" m2 35,200.00
26 Keramik 30 x 30 cm bermotif "winston" m2 38,500.00

Harga Satuan Upah dan Bahan/Material - Swakelola Hal. 122


No Jenis Bahan Sat. Harga Bahan Keterangan
(Rp.)
(1) (2) (3) (4) (5)
27 Keramik 30 x 30 cm bermotif "jaguar" m2 35,750.00
28 Keramik 40 x 40 cm bermotif warna muda "milan" m2 42,900.00
29 Keramik 40 x 40 cm bermotif warna tua "milan" m2 46,200.00
30 Keramik 40 x 40 cm bermotif warna muda "platinum" m2 48,400.00
31 Keramik 40 x 40 cm bermotif warna muda "hercules" m2 43,450.00
32 Keramik 40 x 40 cm bermotif warna tua "hercules" m2 46,200.00
33 Keramik 40 x 40 cm bermotif "Impreso" m2 44,000.00
34 Keramik Lantai Kamar Mandi 20 x 20 cm "accura" m2 36,300.00
35 Keramik Lantai Kamar Mandi 20 x 20 cm "asia tile" m2 38,500.00
36 Keramik Lantai Kamar Mandi 20 x 20 cm "mulia" m2 38,500.00

Harga Satuan Upah dan Bahan/Material - Swakelola Hal. 123


No Jenis Bahan Sat. Harga Bahan Keterangan
(Rp.)
(1) (2) (3) (4) (5)
37 Keramik teras / garasi 30 x 30 "masterina" m2 44,000.00
38 Keramik 7,5 x 20 cm (plint) buah 3,850.00
39 Keramik 8 x 25 cm (plint) buah 4,400.00
40 Step nosing buah 16,500.00
41 Kuku macan buah 550.00
42 Granit 30 x 30 cm "Granito" m2 40,700.00
43 Granit 40 x 40 cm "Granito" m2 44,000.00
44 Granit 60 x 60 cm ex RRT warna muda m2 104,500.00
45 Granit 60 x 60 cm ex RRT warna tua m2 187,000.00

VIII UBIN/ TEGEL/ PAVING BLOCK


1 Ubin abu-abu 20/20 m2 25,300.00
2 Ubin super hitam 20/20 m2 30,250.00
3 Ubin badak 30/30 m2 33,000.00
4 Ubin segi enam merah tebal 3 cm m2 44,000.00
5 Paving block tebal 6 cm m2 27,500.00
6 Paving block tebal 6 cm (mesin) m2 38,500.00
7 Paving kawung tebal 6 sm mutu sedang m2 35,750.00
8 Paving kawung tebal 6 sm mutu baik m2 41,250.00
9 Kansten panjang 0,6 m' buah 25,300.00
10 Trapez Grass Block abu-abu m2 45,650.00
11 Standard Grass Block abu-abu m2 47,300.00
12 Kansteen m' 27,500.00

IX ASBES
1 Asbes plat (100 x 100 x 0,3) Atrisco lbr 13,750.00
2 Asbes plat (100 x 100 x 0,3) Kerang super lbr 8,250.00
3 Asbes plat (100 x 100 x 0,3) Indoplek lbr 12,100.00
4 Asbes plat (100 x 100 x 0,3) Elephant lbr 13,750.00
5 Asbes plat (100 x 100 x 0,3) Djabes lbr 13,200.00
6 Asbes Gelombang besar (300 x 102 x 0,5) lbr 80,300.00
7 Asbes Gelombang besar (200 x 102 x 0,5) lbr 58,300.00
8 Asbes Gelombang besar (180 x 102 x 0,5) lbr 53,900.00
9 Asbes Gelombang kecil (300 x 105 x 0,4) Djabes lbr 66,000.00
10 Asbes Gelombang kecil (270 x 105 x 0,4) Djabes lbr 65,450.00
11 Asbes Gelombang kecil (210 x 105 x 0,4) Djabes lbr 46,200.00
12 Asbes Gelombang kecil (180 x 105 x 0,4) Djabes lbr 39,600.00
13 Asbes Gelombang kecil (150 x 105 x 0,4) Djabes lbr 35,750.00
14 Asbes Gelombang kecil (240 x 105 x 0,4) Djabes lbr 52,800.00
15 Asbes nok gelombang besar lbr 52,250.00
16 Asbes nok gelombang kecil lbr 27,500.00

X SENG DAN ALUMUNIUM FOIL


1 Seng BJLS 0,2 gelombang P = 180 cm lbr 36,300.00
2 Seng BJLS 0,2 gelombang P = 210 cm lbr 42,350.00
3 Seng BJLS 0,2 gelombang P = 240 cm lbr 48,400.00
4 Seng BJLS 0,2 gelombang P = 300 cm lbr 60,500.00
5 Seng BJLS 0,20 lembaran L = 40 cm m' 12,100.00
6 Seng BJLS 0,20 lembaran L = 50 cm m' 16,500.00
7 Seng BJLS 0,20 lembaran L = 90 cm m' 23,100.00

Harga Satuan Upah dan Bahan/Material - Swakelola Hal. 124


No Jenis Bahan Sat. Harga Bahan Keterangan
(Rp.)
(1) (2) (3) (4) (5)
8 Seng BJLS 0,30 lembaran L = 40 cm m' 22,550.00
9 Seng BJLS 0,30 lembaran L = 50 cm m' 15,400.00
10 Seng BJLS 0,30 lembaran L = 60 cm m' 18,700.00
11 Seng BJLS 0,30 lembaran L = 90 cm m' 24,200.00
12 Alumunium foil m2 9,350.00

XI GENTENG
1 Genteng beton besar natural isi 9 biji "monier" bh 3,300.00
2 Genteng beton besar warna isi 9 biji "monier" bh 4,950.00
3 Genteng beton kecil natural isi 11 biji "RA" bh 3,080.00
4 Genteng beton bubungan natural bh 4,950.00

Harga Satuan Upah dan Bahan/Material - Swakelola Hal. 125


No Jenis Bahan Sat. Harga Bahan Keterangan
(Rp.)
(1) (2) (3) (4) (5)
5 Nok press beton natural bh 5,500.00
6 Nok press beton warna bh 7,150.00
7 Genteng keramik glasur natural KIA bh 6,325.00
8 Genteng keramik glasur warna KIA bh 9,625.00
9 Genteng keramik glasur natural "morando" kebumen bh 2,200.00
10 Genteng keramik glasur natural "morando" jatiwangi bh 3,025.00
11 Genteng keramik glasur warna "morando" jatiwangi bh 3,025.00
12 Genteng kodok "sokka" bh 1,210.00
13 Genteng Plenthong / Vlampress kecil kebumen bh 1,375.00
14 Genteng Plenthong / Vlampress besar kebumen bh 1,485.00
15 Genteng Plenthong / Vlampress kecil jatiwangi bh 1,375.00
16 Genteng Plenthong / Vlampress besar jatiwangi bh 1,925.00
17 Genteng keramik bubungan glasur natural KIA bh 16,500.00
18 Genteng keramik bubungan glasur natural MORANDO bh 9,350.00
19 Nok genteng kodok bh 3,850.00
20 Nok Genteng Plenthong / Vlampress kecil kebumen bh 4,950.00
21 Nok Genteng Plenthong / Vlampress besar kebumen bh 4,950.00
22 Nok Genteng Plenthong / Vlampress kecil jatiwangi bh 5,500.00
23 Nok genteng Plenthong / Vlampress besar jatiwangi bh 5,500.00
24 Atap Polycarbonat m2 82,500.00

XII PAKU
1 Paku usuk kg 11,000.00
2 Paku reng kg 11,000.00
3 Paku plepet kg 11,000.00
4 Paku eternit kg 14,300.00
5 Paku asbes bh 330.00
6 Paku sekrup 3,5" (dos) bh 165.00
7 Paku gypsum kg 16,500.00
8 Paku ramset/ dinabolt kg 1,100.00
9 Paku beton kecil bh 110.00
10 Paku beton besar bh 495.00
11 Angkur/ Beugel kg 17,600.00

XIII KAYU
1 Kayu jati m3 18,700,000.00
2 Papan kayu jati m3 22,000,000.00
3 Kayu jati lokal m3 6,600,000.00
4 Papan kayu jati lokal m3 7,150,000.00
5 Kayu bengkirai m3 8,635,000.00
6 Papan kayu bengkirai m3 9,900,000.00
7 Kayu Kamper m3 7,150,000.00
8 Papan kayu kamper m3 8,250,000.00
9 Kayu kruing m3 4,950,000.00
10 Papan kayu kruing m3 5,500,000.00
11 Kayu 5/7 meranti m3 3,300,000.00
12 Kayu meranti m3 3,300,000.00
13 Papan kayu meranti m3 3,740,000.00
14 List profil kayu m' 8,250.00
15 Kayu tahun/ lanan m3 1,100,000.00

Harga Satuan Upah dan Bahan/Material - Swakelola Hal. 126


No Jenis Bahan Sat. Harga Bahan Keterangan
(Rp.)
(1) (2) (3) (4) (5)
16 Papan 3/20 kayu tahun m3 1,320,000.00
17 Kayu dolken Ø 8-10/400 cm m3 1,100,000.00
18 Kayu dolken Ø 8-10 / 400 cm btg 16,500.00
19 Kayu bakar m3 82,500.00
20 Bambu btg 6,600.00
21 Tali ijuk kg 8,250.00
22 Ijuk kg 3,850.00

Harga Satuan Upah dan Bahan/Material - Swakelola Hal. 127


No Jenis Bahan Sat. Harga Bahan Keterangan
(Rp.)
(1) (2) (3) (4) (5)
XIV KAYU LAPIS
1 Plywood 3 mm lbr 41,250.00
2 Plywood 4 mm lbr 57,750.00
3 Plywood 6 mm lbr 77,000.00
4 Plywood 9 mm lbr 77,000.00
5 Plywood 12 mm lbr 159,500.00
6 Melamin wood 120 x 210 cm lbr 41,250.00
7 Formika 4" x 8" x 0,3 cm lbr 82,500.00
8 Formika ukuran pintu lbr 55,000.00
9 Teakwood 3 mm 120 x 240 cm lbr 82,500.00

XV BAHAN KACA
1 Genteng kaca vlam cekung 2 mm bh 7,150.00
2 Genteng kaca vlam cekung 3 mm bh 8,250.00
3 Genteng kaca kodok cekung 2 mm bh 7,700.00
4 Genteng kaca kodok cekung 3 mm bh 8,250.00
5 Kaca bening 3 mm m2 49,500.00
6 Kaca bening 5 mm m2 66,000.00
7 Kaca bening 8 mm m2 132,000.00
8 Kaca riben 3 mm m2 60,500.00
9 Kaca riben 5 mm m2 77,000.00
10 Kaca riben 8 mm m2 313,500.00
11 Kaca es 3 mm m2 55,000.00
12 Kaca es 5 mm m2 88,000.00
13 Kaca cermin 3 mm m2 77,000.00
14 Kaca cermin 5 mm m2 99,000.00
15 Rangka nako + besi tralis nako bh 20,900.00
16 Kaca nako polos 5 mm uk. 14 x 100 cm bh 9,900.00

XVI PIPA GALVANIS, PVC, DAN FITTING


PIPA GALVANIS - SII, panjang 6 m'
1 Pipa Galvanis medium (GIP) 1/2" btg 110,000.00
2 Pipa Galvanis medium (GIP) 3/4" btg 132,000.00
3 Pipa Galvanis medium (GIP) 1" btg 170,500.00
4 Pipa Galvanis medium (GIP) 1 1/4" btg 220,000.00
5 Pipa Galvanis medium (GIP) 1 1/2" btg 247,500.00
6 Pipa Galvanis medium (GIP) 2" btg 319,000.00
7 Pipa Galvanis medium (GIP) 2 1/2" btg 412,500.00
8 Pipa Galvanis medium (GIP) 3" btg 759,000.00
9 Pipa Carbon medium (SGP) 1/2" x 2 m btg 55,000.00
10 Pipa Carbon medium (SGP) 3/4" x 2 m btg 71,500.00
11 Pipa Carbon medium (SGP) 1" x 2 m btg 85,250.00
12 Pipa Carbon medium (SGP) 1 1/4" x 2 m btg 104,500.00
13 Pipa Carbon medium (SGP) 1 1/2" x 2 m btg 121,000.00
14 Pipa Carbon medium (SGP) 2" x 2 m btg 154,000.00
PIPA PVC CLASS AW "WAVIN" panjang 4 m'
1 Pipa PVC class AW 1/2" btg 14,300.00
2 Pipa PVC class AW 3/4" btg 19,250.00
3 Pipa PVC class AW 1" btg 26,400.00
4 Pipa PVC class AW 1 1/4" btg 39,600.00

Harga Satuan Upah dan Bahan/Material - Swakelola Hal. 128


No Jenis Bahan Sat. Harga Bahan Keterangan
(Rp.)
(1) (2) (3) (4) (5)
5 Pipa PVC class AW 1 1/2" btg 48,400.00
6 Pipa PVC class AW 2" btg 58,300.00
7 Pipa PVC class AW 2 1/2" btg 67,100.00
8 Pipa PVC class AW 3" btg 114,400.00
9 Pipa PVC class AW 4" btg 190,300.00
10 Pipa PVC class AW 5" btg 314,600.00
11 Pipa PVC class AW 6" btg 442,200.00
12 Pipa PVC class AW 8" btg 753,500.00
PIPA PVC CLASS AW "MASPION" panjang 4 m'
1 Pipa PVC class AW 1/2" btg 14,300.00
2 Pipa PVC class AW 3/4" btg 19,250.00
3 Pipa PVC class AW 1" btg 26,400.00
4 Pipa PVC class AW 1 1/4" btg 39,600.00

Harga Satuan Upah dan Bahan/Material - Swakelola Hal. 129


No Jenis Bahan Sat. Harga Bahan Keterangan
(Rp.)
(1) (2) (3) (4) (5)
5 Pipa PVC class AW 1 1/2" btg 48,400.00
6 Pipa PVC class AW 2" btg 58,300.00
7 Pipa PVC class AW 2 1/2" btg 67,100.00
8 Pipa PVC class AW 3" btg 114,400.00
9 Pipa PVC class AW 4" btg 190,300.00
10 Pipa PVC class AW 5" btg 314,600.00
11 Pipa PVC class AW 6" btg 442,200.00
12 Pipa PVC class AW 8" btg 753,500.00
PIPA PVC CLASS C "MASPION" panjang 4 m'
1 Pipa PVC class C 1/2" btg 9,350.00
2 Pipa PVC class C 3/4" btg 13,200.00
3 Pipa PVC class C 1" btg 17,050.00
4 Pipa PVC class C 2" btg 32,450.00
5 Pipa PVC class C 2 1/2" btg 41,250.00
6 Pipa PVC class C 3" btg 48,400.00
7 Pipa PVC class C 4" btg 61,600.00
PIPA PVC CLASS D "MASPION" panjang 4 m'
1 Pipa PVC clasc D 1 1/4" btg 20,350.00
2 Pipa PVC clasc D 1 1/2" btg 24,750.00
3 Pipa PVC clasc D 2" btg 33,000.00
4 Pipa PVC clasc D 2 1/2" btg 45,100.00
5 Pipa PVC clasc D 3" btg 56,100.00
6 Pipa PVC clasc D 4" btg 93,500.00
7 Pipa PVC clasc D 5" btg 141,350.00
8 Pipa PVC clasc D 6" btg 197,450.00
9 Pipa PVC clasc D 8" btg 338,800.00

XVII FITTING GALVANIS


1 Tee bh 4,950.00
2 Duble nippe bh 3,850.00
3 Socket bh 3,850.00
4 Plug bh 3,025.00
5 Dop bh 3,300.00
6 Knie 90 o bh 3,850.00

XVIII FITTING PVC "RUCIKA"


1 Knie 90 o - 1/2" bh 1,210.00
2 Knie 90 o - 3/4" bh 1,650.00
3 Knie 90 o - 1" bh 2,200.00
4 Knie 90 o - 1 1/4" bh 2,750.00
5 Knie 90 o - 1 1/2" bh 2,750.00
6 Knie 90 o - 2" bh 3,300.00
7 Knie 90 o - 2 1/2" bh 4,400.00
8 Knie 90 o - 3" bh 6,600.00
9 Knie 90 o - 4" bh 11,000.00
10 Knie 90 o - 5" bh 55,000.00
11 Knie 90 o - 6" bh 66,000.00
12 Tee - 1/2" bh 1,650.00
13 Tee - 3/4" bh 2,200.00
14 Tee - 1" bh 2,750.00

Harga Satuan Upah dan Bahan/Material - Swakelola Hal. 130


No Jenis Bahan Sat. Harga Bahan Keterangan
(Rp.)
(1) (2) (3) (4) (5)
15 Tee - 1 1/4" bh 2,750.00
16 Tee - 1 1/2" bh 3,300.00
17 Tee - 2" bh 4,400.00
18 Tee - 2 1/2" bh 5,500.00
19 Tee - 3" bh 6,600.00
20 Tee - 4" bh 6,600.00
21 Tee - 5" bh 38,500.00
22 Tee - 6" bh 44,000.00
23 Socket - 1/2" bh 1,100.00
24 Socket - 3/4" bh 1,650.00

Harga Satuan Upah dan Bahan/Material - Swakelola Hal. 131


No Jenis Bahan Sat. Harga Bahan Keterangan
(Rp.)
(1) (2) (3) (4) (5)
25 Socket - 1" bh 2,200.00
26 Socket - 1 1/4" bh 2,750.00
27 Socket - 1 1/2" bh 2,200.00
28 Socket - 2" bh 3,300.00
29 Socket - 2 1/2" bh 3,300.00
30 Socket - 3" bh 3,300.00
31 Socket - 4" bh 4,400.00
32 Socket - 5" bh 19,250.00
33 Socket - 6" bh 22,000.00
34 Knie 45 o - 2" bh 3,850.00
35 Knie 45 o - 2 1/2" bh 5,500.00
36 Knie 45 o - 3" bh 8,800.00
37 Knie 45 o - 4" bh 15,950.00

XIX BUIS BETON / KERB


1 Buis beton U 15 cm bh 13,750.00
2 Buis beton U 20 cm bh 19,250.00
3 Buis beton U 30 cm bh 22,000.00
4 Buis beton 0 15 cm bh 20,350.00
5 Buis beton 0 20 cm bh 22,000.00
6 Buis beton 0 30 cm bh 33,550.00
7 Buis beton 0 40 cm bh 49,500.00
8 Buis beton 0 50 cm bh 60,500.00
9 Buis beton 0 60 cm bh 80,850.00
10 Buis beton 0 80, pj. 50 cm bh 72,875.00
11 Buis beton 0 100, pj. 50 cm bh 126,500.00

XX PENGGANTUNG / PENGUNCI
1 Kunci tanam double slag/ Selot pintu kuda terbang bh 60,500.00
2 Kunci tanam double slag/ Selot pintu SES bh 275,000.00
3 Kunci tanam double slag/ Selot pintu Yale bh 71,500.00
4 Kunci tanam double slag/ Selot pintu Union bh 49,500.00
5 Kunci tanam/ selot pintu ex RRT bh 275,000.00
6 Kunci tanam antik bh 181,500.00
7 Kunci lemari bh 7,700.00
8 Door holder bh 137,500.00
9 Kunci tanam slinder bh 44,000.00
10 Kunci Kamar mandi "alpha" bh 44,000.00
11 Engsel pintu kuningan 3" bh 19,250.00
12 Engsel pintu kuningan 4" bh 22,000.00
13 Engsel pintu nilon 3" bh 7,150.00
14 Engsel pintu nilon 4" bh 8,250.00
15 Engsel Stainless steel 3" bh 19,250.00
16 Engsel Stainless steel 4" bh 22,000.00
17 Engsel Piano m' 8,250.00
18 Grendel ukuran 5 - 10 cm bh 8,525.00
19 Grendel ukuran 11 - 15 cm bh 13,750.00
20 Grendel ukuran 16 - 20 cm bh 13,750.00
21 Kait Angin kuningan ukuran 10 - 20 cm bh 8,250.00
22 Kait Angin kuningan ukuran 21 - 30 cm bh 22,000.00

Harga Satuan Upah dan Bahan/Material - Swakelola Hal. 132


No Jenis Bahan Sat. Harga Bahan Keterangan
(Rp.)
(1) (2) (3) (4) (5)
23 Espagnolet tanam ukuran 21 - 30 cm bh 27,500.00
24 Door closser type 81 new star bh 110,000.00
25 Door stop lokal bh 8,250.00
26 Engsel Pintu 77 bh 8,250.00
27 Engsel jendela 77 bh 6,050.00
28 Hak angin 8" bh 2,200.00
29 Spring knip bh 6,600.00
30 Rel pintu dorong bh 137,500.00
31 Pintu PVC KM/WC bh 176,000.00
32 Pintu Alumunium bh 121,000.00

Harga Satuan Upah dan Bahan/Material - Swakelola Hal. 133


No Jenis Bahan Sat. Harga Bahan Keterangan
(Rp.)
(1) (2) (3) (4) (5)
XXI PERALATAN SANITASI
1 bak mandi fiberglass 0,3 m3 bh 165,000.00
2 Bak mandi buthtub standar bahan fiber bh 550,000.00
3 Bak mandi buthtub standar bahan onyx bh 2,200,000.00
4 Closet jongkok type CE 8 standard TOTO bh 165,000.00
5 Closet jongkok type CE 8 standard INA bh 96,250.00
6 Closet jongkok LOLO bh 66,000.00
7 Closet duduk standar TOTO lengkap warna muda bh 1,595,000.00
8 Closet duduk standar TOTO lengkap warna tua bh 1,705,000.00
9 Closet duduk standar INA lengkap warna muda bh 880,000.00
10 Closet duduk standar INA lengkap warna tua bh 990,000.00
11 Closet duduk standar LOLO lengkap warna muda bh 341,000.00
12 Urinoir lengkap INA bh 1,210,000.00
13 Urinoir lengkap TOTO bh 2,420,000.00
14 Wastafel standar uk. Kecil komplit TOTO bh 440,000.00
15 Wastafel standar uk. Besar komplit TOTO bh 550,000.00
16 Wastafel standar uk. Kecil komplit INA bh 198,000.00
17 Wastafel standar uk. Besar komplit INA bh 231,000.00
18 Kitchen zinc standar "Royal" bh 176,000.00
19 Bandkip fiber bh 605,000.00
20 Kran air 3/4" atau 1/2 " bh 12,100.00
21 Kran air wastafel bh 27,500.00
22 Kran air bak cuci dapur bh 33,000.00
23 Floor drain stainless bh 13,750.00
24 Floor drain bahan plastik/PVC bh 3,850.00
25 Tempat sabun porselin bh 22,000.00
26 Kurasan bak bh 4,400.00
27 Tandon Air Fiberglass bulat 500 lt Pinguin bh 660,000.00
28 Tandon Air Fiberglass bulat 1000 lt Pinguin bh 1,072,500.00
29 Tandon Air Fiberglass bulat 500 lt Paus bh 495,000.00
30 Tandon Air Fiberglass bulat 1000 lt Paus bh 770,000.00
31 Sealtape kecil bh 1,100.00
32 Pipa fleksibel m' 49,500.00

XXII LAIN - LAIN


1 Jendela besi m2 935,000.00
2 Jendela besi tahan api m2 1,815,000.00
3 Pintu gulung besi m2 302,500.00
4 Pintu Besi Baja m2 935,000.00
5 Sunscreen Alumunium m2 330,000.00
6 Rolling door bahan besi m2 247,500.00
7 Rolling door bahan alumunium m2 302,500.00
8 Folding gate m2 605,000.00
9 Vertical blind m2 137,500.00
10 Wallpaper m2 49,500.00
11 Teralis besi m2 220,000.00
12 Pagar BRC 90 A2 lbr 121,000.00
13 Pagar BRC 120 A2 lbr 154,000.00
14 Bahan Bakar, pelumas, perawatan hari 33,000.00
15 Sewa mesin gilas hari 38,500.00

Harga Satuan Upah dan Bahan/Material - Swakelola Hal. 134


No Jenis Bahan Sat. Harga Bahan Keterangan
(Rp.)
(1) (2) (3) (4) (5)
16 Aspal kg 7,081.00 1 $ = Rp. 10.000,-
17 Aspal Curah kg 6,094.00 1 $ = Rp. 10.000,-
18 Oli mesran SAE 40 ltr 36,300.00
19 Solar ltr 4,950.00
20 Solar Industri ltr 6,050.00
21 Premium ltr 4,950.00
22 Premium industri ltr 5,610.00
23 Minyak bakar industri ltr 6,050.00

Harga Satuan Upah dan Bahan/Material - Swakelola Hal. 135


RENCANA ANGGARAN DAN BIAYA ( RAB)

HARGA
NO JENIS PEKERJAAN ANALIS VOL JUMLAH
SATUAN
A PEKERJAAN PEMBONGKARAN
1. Pembongkaran lantai tegel XV.4 434.00 m² 6,490.00 2,816,660.00
2. Pek. Dokumen proyek Ls Ls 500,000.00 500,000.00
3. Tanah diangkut sejauh 150 m II.8 21.70 m³ 10,422.50 226,168.25

B PEKERJAAN LANTAI
1. Pekerjaan Lantai keramik 30 x 30 cm XIII.4 434.00 75,025.05 32,560,871.70

JUMLAH 36,103,699.95
DIBULATKAN
B. RENCANA ANGGARAN DAN BIAYA ( RAB)

NO JENIS PEKERJAAN VOLUME HARGA


SATUAN
A PEKERJAAN KAYU
1. Pasang gording kayu kamper / m3 5.63 m3 8,284,760.00
2. Pekerjaan kaso 5/7 dan reng 2/3 kayu kamper per m2 855.30 m2 136,125.00
3. Pekerjaan rangka langit-langit kayu kamper 1 x 1 m per m2 1444.30 m2 133,017.05
4. Pekerjaan langit-langit asbes elepent 1 x 1 m tebal 3mm per m2 1444.30 m2 19,354.50
5. Pekerjaan lisplang 3 x 20 cm kayu kamper per m2 56.58 m2 71,775.00
6. Menutup atap dengan genting kodok per m2 1444.30 m2 38,379.00
7. Menutup bubungan pada genting kodok per m2 9.81 m' 52,514.00

B PEKERJAAN PEMBONGKARAN
1. Pembongkaran lantai 1014.00 m2 6,490.00
2. Pek. Pembuatan alat-alat kerja Ls 400,000.00
3. Pek. Dokumen proyek Ls 500,000.00

C PEKERJAAN LANTAI
1. Pekerjaan Lantai keramik 30 x 30 cm 1041.00 75,025.05
JUMLAH

46,643,198.80
116,427,712.50
192,116,525.32
27,953,704.35
4,061,029.50
55,430,789.70
515,162.34

6,580,860.00
400,000.00
500,000.00

78,101,077.05