JADWAL PELAKSANAAN PEKERJAAN

KEGIATAN : BAGIAN TATA USAHA


SUB KEGIATAN : PEMBANGUNAN GEDUNG PENGEMBANGAN LAYANAN GERIATRI, RM, ANAK DAN TKT
PEKERJAAN : PEKERJAAN STRUKTUR
LOKASI : RSUD DOKTER SOESELO KABUPATEN TEGAL
TAHUN : 2021
1 2 3 4 5 6 7 8
PERIODE :
JUNI JULI AGUSTUS SEPTEMBER OKTOBER NOPEMBER DESEMBER
No. SISA BOBOT 17-20 21-27 28 -04 05-11 12-18 19-25 26-01 02-08 09-15 16-22 23-29 30-05 06-12 13-19 20-26 27-03 04-10 11-17 18-24 25-31 01-07 08-14 15-21 22-28 29-05 06-12 13-19 20-23
URAIAN BOBOT %
PEKERJAAN %
4 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 4
4 11 18 25 32 39 46 53 60 67 74 81 88 95 102 109 116 123 130 137 144 151 158 165 172 179 186 190
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28

A PEKERJAAN STRUKTUR

ADENDUM 2
I PEKERJAAN PERSIAPAN
II PEKERJAAN TANAH - -
III PEKERJAAN PONDASI TIANG PANCANG - -
Pekerjaan Pancang Sistem Jackpile - -
IV PEKERJAAN PILE CAP & PIT LIFT - -
V PEKERJAAN BETON BERTULANG - -
A LANTAI 01 - -
B LANTAI 02 - -

+ Water profing couting plat lantai 0.951 0.95 0.24 0.24 0.24 0.24
VI PEKERJAAN KONTRUKSI BAJA - -

Pekerjaan Drop Off Area -


1 Galian Tanah 0.056 0.06 0.01 0.01 0.01 0.01
2 Urugan Pasir 0.004 0.00 0.00 0.00 0.00 0.00
3 Pas Batu Kosong 0.042 0.04 0.01 0.01 0.01 0.01
4 Pas Batu Belah 1 PC : 6 PS 0.172 0.17 0.04 0.04 0.04 0.04
5 Urugan Tanah Kembali 0.006 0.01 0.00 0.00 0.00 0.00
6 Sloof Type SP - - - - - -
a. Beton f'c 14,5 Mpa 0.021 0.02 0.01 0.01 0.01 0.01
b. Tulangan 0.080 0.08 0.02 0.02 0.02 0.02
c. Bekisting 0.081 0.08 0.02 0.02 0.02 0.02
7 Lantai Kerja 0.067 0.07 0.02 0.02 0.02 0.02
8 Plat Type S1 - - - - - -
a. Beton f'c 24,9 Mpa 0.234 0.23 0.06 0.06 0.06 0.06
b. Tulangan 0.112 0.11 0.03 0.03 0.03 0.03
c. Bekisting 0.012 0.01 0.00 0.00 0.00 0.00
9 Rabat Lantai Beton f'c 14,5 Mpa 0.016 0.02 0.00 0.00 0.00 0.00
10 Granite Tile 60 x 60 Unpolished (Ex.Niro) 0.194 0.19 0.05 0.05 0.05 0.05
11 Penutup Atap Galvalum rangka baja ringan 0.262 0.26 0.07 0.07 0.07 0.07
- - - - - -
+ Penutupan Void Atap dengan galvalum rangka baja ringan - - - - - -
- Pit Lift 0.128 0.13 0.03 0.03 0.03 0.03
- Tangga 0.174 0.17 0.04 0.04 0.04 0.04
- Void Hall Depan 0.158 0.16 0.04 0.04 0.04 0.04
B PEKERJAAN ARSITEKTUR - -
I PEKERJAAN DINDING, KUSEN PINTU DAN JENDELA - -
A LANTAI BASEMENT - -
B LANTAI 01 - -
12 Stek Besi Pas. Bata P10-500 mm 0.011 0.01 0.00 0.00 0.00 0.00
+ Pintu kaca tamper framless 12 mm 0.545 0.55 0.14 0.14 0.14 0.14
c/w portal stainless steel plat tb.1mm -
+ Mesin Pintu Sliding otomatis 0.586 0.59 0.15 0.15 0.15 0.15
Op. L. 1000mm, t.3000mm, max leaf weihgt 2x100kgs -
type Tormax automatic Windrive LS 2201 Double -
C LANTAI 02 - -
12 Stek Besi Pas. Bata P10-500 mm 0.011 0.01 0.00 0.00 0.00 0.00
-
D LANTAI 02 -
Pekerjaan Dinding -
1 Pasangan bata merah, 1 PC : 6 PS 0.295 0.29 0.07 0.07 0.07 0.07
2 Plesteran 1 PC : 6 PS 0.343 0.34 0.09 0.09 0.09 0.09
3 Acian 0.205 0.21 0.05 0.05 0.05 0.05
II PEKERJAAN PLAFOND - -
A LANTAI BASEMENT - -
B LANTAI 01 - -
C LANTAI 02 - -
III PEKERJAAN FINISHING LANTAI DAN DINDING - -
LANTAI BASEMENT - -
LANTAI 01 - -
LANTAI 02 - -
IV PEKERJAAN CAT-CATAN - -
LANTAI BASEMENT - -
LANTAI 01 - -
LANTAI 02 - -
V PEKERJAAN RALLING TANGGA - -
LANTAI 01 - -
LANTAI 02 - -
VI PEKERJAAN SANITAIR - -
LANTAI 01 - -
LANTAI 02 - -
C PEKERJAAN MEKANIKAL ELEKTRIKAL & PLUMBING - -
I MDP, SDP & PANEL DAYA LAINNYA - -
MDP - -
+ Kabel dari LVMDP ke MDP 4 x 1 x 240 mm2 0.390 0.39 0.10 0.10 0.10 0.10
SDP PP - -
SDP AC - -
PEKERJAAN PANEL PENERANGAN - -
LANTAI 01 - -
PP-LT.1A - -
LANTAI 02 - -
PP-LT.2A - -
- -
PEKERJAAN PANEL AIR CONDITIONING - -
LANTAI 01 - -
PAC LT.01A - -
LANTAI 02 - -
PAC LT.02A - -
PEKERJAAN PANEL LAIN - LAIN - -
P.LIFT 1 - -
P.LIFT EMG - -
P. PRESSURE FAN - -
P. ELEKTRONIKA - -
II PEKERJAAN PENERANGAN - -
JULI OKTOBER NOPEMBER DESEMBER
No. SISA BOBOT 17-20 21-27 28 -04 05-11 12-18 19-25 26-01 02-08 09-15 16-22 23-29 30-05 06-12 13-19 20-26 27-03 04-10 11-17 18-24 25-31 01-07 08-14 15-21 22-28 29-05 06-12 13-19 20-23
URAIAN BOBOT %
PEKERJAAN %
4 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 4
4 11 18 25 32 39 46 53 60 67 74 81 88 95 102 109 116 123 130 137 144 151 158 165 172 179 186 190
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
LANTAI 01 - -
LANTAI 02 - -
III PEKERJAAN TATA UDARA - -
Pengadaan dan pemasangan unit AC VRF, Indoor + Outdoor dengan asesories - -
termasuk pondasi, penyangga, pipa refrigent, pipa drain, peredam suara - -
sesuai standar pabrik - -
PEKERJAAN INSTALASI AIR CONDITIONING LANTAI 01 - -
+ Outdoor Unit 34000 BTUH (DAIKIN ) 0.233 0.23 0.06 0.06 0.06 0.06
+ Outdoor Unit 27300 BTUH (DAIKIN ) 0.202 0.20 0.05 0.05 0.05 0.05
PEKERJAAN INSTALASI AIR CONDITIONING LANTAI 02 - -
+ Outdoor Unit 34000 BTUH (DAIKIN ) 0.466 0.466 0.12 0.12 0.12 0.12
IV PEKERJAAN TATA SUARA - -
PERALATAN UTAMA - -
TATA SUARA LANTAI 01 - - - -
TATA SUARA LANTAI 02 - - - -
V PEKERJAAN INSTALASI TELEPON & DATA - - - -
VI PEKERJAAN MATV - - - -
VII PEKERJAAN CCTV - - - -
VIII PEKERJAAN FIRE EXTINGUSHER & FIRE ALARM - - - - - - - -
IX PEKERJAAN LIFT - - - - - -
X PEKERJAAN PENANGKAL PETIR - - - - - -
XI PEKERJAAN FIRE HYDRANT, SPRINKLER, DAN FIRE EXTINGUISHER - - - - - -
LANTAI 01 - - - - - - - -
LANTAI 02 - - - - - -
XII PEKERJAAN PLUMBING - - - - - - - -
PEKERJAAN AIR BERSIH - - - - - - - -
LANTAI 1 - - - - - - - -
LANTAI 2 - - - - - - - -
PEKERJAAN AIR KOTOR - - - - - - - -
LANTAI 01 - - - - - - - -
+ Pompa Booster Distribusi 0.460 0.460 0.11 0.11 0.11 0.11
Cap : 2 x 5,5 m3/h - -
Head : 35 m - -
Power : 2 x 1,1 kW x 3 phase - 380 Volt, 2 Poles, 50 Hz - -
Include : - -
- Paralel Alternate with Press Switch - -
- Control panel - -
- pressure tank - -
- Control pressure switch - -
- power cable motor to control panel - -
- galvanized base frame - -
- panel indoor type - -
- NYY 4x6 mm 0.007 0.007 0.00 0.00 0.00 0.00
- - - - - -
+ Tangki Air Stainless1500 liter 0.121 0.121 0.03 0.03 0.03 0.03
Header pipa galvanis 3" + instalasi 0.048 0.048 0.01 0.01 0.01 0.01
Instlasi WLC kabel 3x2,5 mm 0.023 0.023 0.01 0.01 0.01 0.01
-
LANTAI 02 - - - - - -
PEKERJAAN AIR HUJAN - - - - - -
RAB SERVICE - - - - - - -
1 PEKERJAAN STRUKTUR - - - - - - - -
I PEKERJAAN TANAH - - - - - - - -
II PEKERJAAN PONDASI - -
Pekerjaan Pondasi Genset -
1 Galian Tanah 0.008 0.008 0.00 0.00 0.00 0.00
2 Urugan Pasir 0.001 0.001 0.00 0.00 0.00 0.00
3 Batu Kosong 0.007 0.007 0.00 0.00 0.00 0.00
4 Batu Belah 1Pc : 6Ps 0.026 0.026 0.01 0.01 0.01 0.01
5 Plat Beton T = 90 cm - - - - - -
- Beton f'c 24,9 Mpa 0.062 0.062 0.02 0.02 0.02 0.02
- Tulangan 0.025 0.025 0.01 0.01 0.01 0.01
- Bekisting Batako 0.015 0.015 0.00 0.00 0.00 0.00
6 Angkur D13 - 400 0.002 0.002 0.00 0.00 0.00 0.00
III PEKERJAAN BETON BERTULANG - -
IV PEKERJAAN KONTRUKSI BAJA - -
V PEKERJAAN GROUNDTANK - -
2 PEKERJAAN ARSITEKTUR - -
I PEKERJAAN DINDING, KUSEN PINTU DAN JENDELA - -
II PEKERJAAN PLAFOND - - - - - - - - -
III PEKERJAAN FINISHING LANTAI DAN DINDING - - - - - - - - -
IV PEKERJAAN CAT-CATAN - - - - - - - - -
3 PEKERJAAN MEKANIKAL ELEKTRIKAL & PLUMBING - - - - - - - - -
I PEKERJAAN PENYAMBUNGAN LISTRIK - - - - - - - - -
-
+ Biaya Pasang Baru Daya Listrik BP-UJL (Biaya resmi) 132 kVA 1.550 1.550 0.39 0.39 0.39 0.39
Catatan : Scope pekerjaan sudah termasuk Pengadaan Jaringan TM, -
biaya perijinan, SLO, gambar, hingga kondisi nyala & KWH meter terpasang. -
II INSTALASI PANEL TEGANGAN MENENGAH - - - - - - - - -
III PEKERJAAN TRANSFORMATOR - - - - - - - - -
IV PEKERJAAN GENSET - - - - - - - - -
V PEKERJAAN LVMDP, SDP & PANEL DAYA LAINNYA - - - - - - - - -
+ Instalasi Kabel Tegangan Rendah 132 KVA dari gardu induk PLN menuju LVMDP 1.872 1.872 0.47 0.47 0.47 0.47
NYY 4x1x240 mm -
VI PEKERJAAN PENERANGAN - - - - - -
VII PEKERJAAN TATA UDARA - - - - - - - - -
VIII PEKERJAAN FIRE EXTINGUISHER - - - - - -
IX PEKERJAAN PLUMBING - - - - - - - - -
+ Sambungan PDAM 0.044 0.044 0.01 0.01 0.01 0.01
+ Instalasi PDAM ke CWT - - - - - -
+ Pipa Galv. Medium A Dia. 2" 0.160 0.160 0.04 0.04 0.04 0.04
+ Gate Valve Kitz 2" 0.005 0.005 0.00 0.00 0.00 0.00
+ Floating Valve dia. 2" 0.004 0.004 0.00 0.00 0.00 0.00

X PEKERJAAN IPAL - - - - - - - - -
E. PEKERJAAN ADENDUM 2 -
1 Penyediaan Hospital Lift Lengkap dengan aksessories, ARD dan 4.159 4.158 0.52 0.52 0.52 0.52 0.52 0.52 0.52 0.52
semua material bantu yang diperlukan sesuai dengan spesifikasi
teknik dan petunjuk pabrik seperti pada gambar Digital Electronic Control, ACVVVF
pelatihan, perijinan, buku petunjuk operasional, Testing, Commissioning
2 Pengadaan Separator Beam dari konstruksi baja sebagai landasan Rel Lift
3 SDP Atap
4 GENERATOR DAN INSTALASI
5 Ground Tank CWT dengan panel system

100.00 35.03
JULI OKTOBER NOPEMBER DESEMBER
No. SISA BOBOT 17-20 21-27 28 -04 05-11 12-18 19-25 26-01 02-08 09-15 16-22 23-29 30-05 06-12 13-19 20-26 27-03 04-10 11-17 18-24 25-31 01-07 08-14 15-21 22-28 29-05 06-12 13-19 20-23
URAIAN BOBOT %
PEKERJAAN %
4 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 4
4 11 18 25 32 39 46 53 60 67 74 81 88 95 102 109 116 123 130 137 144 151 158 165 172 179 186 190
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
PROGRES RENCANA MINGGUAN ( SESUAI KONTRAK ) 0.04 0.10 0.74 1.95 5.21 7.49 6.77 6.58 8.41 2.57 2.25 3.41 5.36 4.59 4.13 4.81 4.35 4.35 3.77 4.71 6.56 5.50 4.48 1.45 0.34 0.04
PROGRES KUMULATIF MINGGUAN ( SESUAI KONTRAK ) - 0.04 0.15 0.89 2.84 8.05 15.53 22.31 28.89 37.31 39.87 42.12 45.54 50.90 55.49 59.63 64.44 68.79 73.13 76.91 81.62 81.62 88.18 93.68 98.16 99.62 99.96 100.00 100.00 100.00

PROGRES RENCANA MINGGUAN ( REVISI MC 0 ) 0.05 0.05 0.66 1.06 2.02 3.07 4.51 5.24 4.79 6.69 2.71 2.85 4.71 2.14 2.11 2.87 3.63 6.30 8.11 10.90 11.53 8.29 4.45 1.14 0.09 0.05
PROGRES RENCANA KUMULATIF MINGGUAN ( REVISI MC 0 ) - 0.05 0.10 0.76 1.82 3.84 6.91 11.42 16.65 21.44 28.13 30.84 33.69 38.39 40.54 42.65 45.51 49.14 55.44 63.55 74.45 74.45 85.98 94.27 98.72 99.86 99.95 100.00 100.00 100.00
PROGRES REALISASI MINGGUAN ( REVISI MC 0 ) 0.14 0.22 0.44 1.69 2.71 0.50 1.45 3.57 5.49 6.30 5.03 6.21 3.52 2.31 2.84 2.04 2.40 3.60 7.91 6.22
PROGRES REALISASI KUMULATIF MINGGUAN (MC 0 ) - 0.14 0.37 0.80 2.50 5.20 5.71 7.16 10.73 16.21 22.51 27.54 33.74 37.26 39.57 42.41 44.45 46.85 50.45 58.36 64.58 64.58

PROGRES RENCANA MINGGUAN ( ADENDUM 2 ) 1.48 1.48 1.48 1.63 7.13 7.34 7.27 7.22
PROGRES RENCANA KUMULATIF MINGGUAN ( ADENDUM 2 ) - 0.05 0.10 0.76 1.82 3.84 6.91 11.42 16.65 21.44 28.13 30.84 33.69 38.39 40.54 42.65 45.51 49.14 55.44 63.55 74.45 64.97 66.45 67.93 69.41 71.04 78.17 85.51 92.78 100.00
PROGRES REALISASI MINGGUAN ( ADENDUM 2 ) - - 4.52 6.18 6.71 3.58 2.42 9.05
PROGRES REALISASI KUMULATIF MINGGUAN ( ADENDUM 2 ) - 0.14 0.37 0.80 2.50 5.20 5.71 7.16 10.73 16.21 22.51 27.54 33.74 37.26 39.57 42.41 44.45 46.85 50.45 58.36 64.58 52.60 57.12 63.30 70.01 73.59 76.02 85.07
DEVIASI (%) 0.09 0.27 0.05 0.68 1.36 (1.20) (4.26) (5.93) (5.23) (5.62) (3.30) 0.06 (1.13) (0.97) (0.24) (1.07) (2.30) (5.00) (5.19) (9.87) (12.36) (9.33) (4.63) 0.60 2.55 (2.16) (0.45)

: TIME SCHEDULE KONTRAK AWAL Slawi, 01 November 2021


: TIME SCHEDULE REVISI MC 0
: TIME SCHEDULE ADENDUM 2 PEJABAT PEMBUAT KOMITMEN MANAJEMEN KONSTRUKSI PENYEDIA JASA
: REALISASI PT. DIENG AGUNG PT. MAJAPAHIT ASTABAJA

Dr. JOKO KURNIANTO, SKM, M.Kes RUMPOKO EKO PRASETYO, ST. ERNANTO BW, ST
NIP. 19680517 199203 1 006 Pengawas Lapangan Project Manager