NO URAIAN
I PEKERJAAN FISIK
A Persiapan
B Pembangunan Baru
1 - RPS 1 P: 12 m, L : 10.0 m, Selasar P: 10.0 m, L : ( 2.0 x 0.5 ) m, di Lantai : 1
2 - RPS 2 P: 12 m, L : 10.0 m, Selasar P: 10.0 m, L : ( 2.0 x 0.5 ) m, di Lantai : 1
3 - RPS 3 P: 12 m, L : 10.0 m, Selasar P: 10.0 m, L : ( 2.0 x 0.5 ) m, di Lantai : 1
4 - RPS 4 P: 12 m, L : 10.0 m, Selasar P: 10.0 m, L : ( 2.0 x 0.5 ) m, di Lantai : 1
5 - RPS 5 P: 12 m, L : 10.0 m, Selasar P: 10.0 m, L : ( 2.0 x 0.5 ) m, di Lantai : 1
C Renovasi
1 - RPS 1 P: 12 m, L : 10.0 m, Selasar P: 10.0 m, L : ( 2.0 x 0.5 ) m, di Lantai : 1
2 - RPS 2 P: 12 m, L : 10.0 m, Selasar P: 10.0 m, L : ( 2.0 x 0.5 ) m, di Lantai : 1
3 - RPS 3 P: 12 m, L : 10.0 m, Selasar P: 10.0 m, L : ( 2.0 x 0.5 ) m, di Lantai : 1
4 - RPS 4 P: 12 m, L : 10.0 m, Selasar P: 10.0 m, L : ( 2.0 x 0.5 ) m, di Lantai : 1
5 - RPS 5 P: 12 m, L : 10.0 m, Selasar P: 10.0 m, L : ( 2.0 x 0.5 ) m, di Lantai : 1
D Rehabilitasi
1 - RPS 1 P: 12 m, L : 10.0 m, Selasar P: 10.0 m, L : ( 2.0 x 0.5 ) m, di Lantai : 1
2 - RPS 2 P: 12 m, L : 10.0 m, Selasar P: 10.0 m, L : ( 2.0 x 0.5 ) m, di Lantai : 1
3 - RPS 3 P: 12 m, L : 10.0 m, Selasar P: 10.0 m, L : ( 2.0 x 0.5 ) m, di Lantai : 1
4 - RPS 4 P: 12 m, L : 10.0 m, Selasar P: 10.0 m, L : ( 2.0 x 0.5 ) m, di Lantai : 1
5 - RPS 5 P: 12 m, L : 10.0 m, Selasar P: 10.0 m, L : ( 2.0 x 0.5 ) m, di Lantai : 1
E Redesain
1 - RPS 1 P: 12 m, L : 10.0 m, Selasar P: 10.0 m, L : ( 2.0 x 0.5 ) m, di Lantai : 1
2 - RPS 2 P: 12 m, L : 10.0 m, Selasar P: 10.0 m, L : ( 2.0 x 0.5 ) m, di Lantai : 1
3 - RPS 3 P: 12 m, L : 10.0 m, Selasar P: 10.0 m, L : ( 2.0 x 0.5 ) m, di Lantai : 1
4 - RPS 4 P: 12 m, L : 10.0 m, Selasar P: 10.0 m, L : ( 2.0 x 0.5 ) m, di Lantai : 1
5 - RPS 5 P: 12 m, L : 10.0 m, Selasar P: 10.0 m, L : ( 2.0 x 0.5 ) m, di Lantai : 1
Sub Total I
II PEKERJAAN INTERIOR DAN PERABOT
Biaya Perabot RPS Perhotelan
Sub Total II
III PERENCANAAN DAN PENGAWASAN
A Biaya Perencanaan
B Biaya Pengawasan
Sub Total III
IV BIAYA PENGELOLAAN
Biaya Pengelolaan Administrasi
Sub Total IV
TOTAL (I + II + III + IV )
PEMBULATAN TOTAL (I + II + III + IV )
0
Perencana Kepala Sekolah
0
NIP 0
HARGA TOTAL BANTUAN (Rp.
VOL SAT
SATUAN )
ls
130.0 m² - -
130.0 m² - -
130.0 m² - -
130.0 m² - -
130.0 m² - -
130.0 m² - -
130.0 m² - -
130.0 m² - -
130.0 m² - -
130.0 m² - -
130.0 m² - -
130.0 m² - -
130.0 m² - -
130.0 m² - -
130.0 m² - -
130.0 m² - -
130.0 m² - -
130.0 m² - -
130.0 m² - -
130.0 m² - -
-
1 Ls -
-
1 Ls -
1 Ls -
-
1 Ls -
-
-
-
0
epala Sekolah
0
FORM PENGISIAN
No Urut
Program :
Sektor
NPSN :
Nama Sekolah :
Kab/ kota :
Propinsi :
Konstruksi :
Nama Kepala sekolah :
NIP Kepala Sekolah :
Kota Tempat Bintek :
Tanggal Bintek :
Kopentensi :
3
BANTUAN SMK PUSAT KEUNGGULAN (PK)
Ekonomi Kreatif
10404048
SMKS PGRI PEKANBARU
Kota Pekanbaru
Prov. Riau
Teknologi Informasi
Beton
Kayu
Pro
Bobot Renovasi
terhadap Bobot
NO Uraian
seluruh Maksimal
RPS 1 RPS 2 RPS 3 RPS 4 RPS 5 RPS 1
bangunan
1 Nama Ruang
2 Jumlah
3 Panjang
4 Lebar
5 Atap Penutup Atap 6.20% 100%
0.000%
0.000%
0.000%
0.000%
0.000%
0.000%
0.000%
0.000%
0.000%
0.000%
0.000%
0.000%
0.000%
0.000%
0.000%
0.000%
0.000%
0.000%
0.000%
0.000%
0.000%
0.000%
0.000%
0.000%
0.000%
0.000%
0.000%
0.000%
BANTUAN SMK PUSAT KEUNGGULAN (PK)
NPSN : 10404048
Desa : SMKS PGRI PEKANBARU
HARGA
NO JENIS UPAH SATUAN
Rp.
J. Bahan Paku
89 Paku Biasa Kg
90 Paku Tripleks Kg
91 Paku Seng + karet seal Kg
92 Paku Ulir bh
93 Paku Gypsum kg
94 Dina Bolt Gypsum bh
Q. Alat-alat Listrik
171 Kabel 1x2,5mm NYM M1
172 Kabel 2x2,5mm NYM M1
173 Kabel 3x2,5mm NYM M1
174 Kabel 3x2,5mm NYM M1
175 Kabel 3x4mm NYY M1
176 Saklar Tunggal setara Broco Bh
177 Saklar Ganda setara Broco Bh
178 Stop Kontak setara Broco Bh
179 Lampu TL 2 x 40 watt + armaturnya, setara Phillips Set
180 Lampu Pijar 25 watt setara Phillips + fitting Bh
181 Box Sekring Bh
182 Inbowdoos Bh
183 Isolasi/Seal Tape Bh
184 Klem Kabel Bh
185 MCB Bh
186 Panel Box Utama Bh
187 Air m3
1 Kursi Kerja Bh
2 Meja Kerja Bh
3 Bangku Kerja Bh
4 Meja Alat Bh
5 Meja Persiapan Bh
6 Stool/Kursi kerja bengkel Bh
7 Papan Tulis Dorong Bh
8 Lemari Alat / Tools Cabinet Bh
9 Lemari Simpan Bh
10 Bh
11 Bh
12 Bh
13 Bh
14 Bh
15 Bh
16 Bh
17 Bh
18 Bh
19 Bh
20 Bh
1 Kursi Kerja Bh
2 Meja Kerja Bh
3 Bangku Kerja Bh
4 Meja Alat Bh
5 Meja Persiapan Bh
6 Stool/Kursi kerja bengkel Bh
7 Papan Tulis Dorong Bh
8 Lemari Alat / Tools Cabinet Bh
9 Lemari Simpan Bh
10 Bh
11 Bh
12 Bh
13 Bh
14 Bh
15 Bh
16 Bh
17 Bh
18 Bh
19 Bh
20 Bh
1 Kursi Kerja Bh
2 Meja Kerja Bh
3 Bangku Kerja Bh
4 Meja Alat Bh
5 Meja Persiapan Bh
6 Stool/Kursi kerja bengkel Bh
7 Papan Tulis Dorong Bh
8 Lemari Alat / Tools Cabinet Bh
9 Lemari Simpan Bh
10 Bh
11 Bh
12 Bh
13 Bh
14 Bh
15 Bh
16 Bh
17 Bh
18 Bh
19 Bh
20 Bh
1 Kursi Kerja Bh
2 Meja Kerja Bh
3 Bangku Kerja Bh
4 Meja Alat Bh
5 Meja Persiapan Bh
6 Stool/Kursi kerja bengkel Bh
7 Papan Tulis Dorong Bh
8 Lemari Alat / Tools Cabinet Bh
9 Lemari Simpan Bh
10 Bh
11 Bh
12 Bh
13 Bh
14 Bh
15 Bh
16 Bh
17 Bh
18 Bh
19 Bh
20 Bh
1 Kursi Kerja Bh
2 Meja Kerja Bh
3 Bangku Kerja Bh
4 Meja Alat Bh
5 Meja Persiapan Bh
6 Stool/Kursi kerja bengkel Bh
7 Papan Tulis Dorong Bh
8 Lemari Alat / Tools Cabinet Bh
9 Lemari Simpan Bh
10 Bh
11 Bh
12 Bh
13 Bh
14 Bh
15 Bh
16 Bh
17 Bh
18 Bh
19 Bh
20 Bh
Analisa Satuan Pekerjaan
Pekerjaan 1 2 3 4 5 6=(3x5)
A.01.06 1 M1 PENGUKURAN DAN PASANGAN BOUWPLANK
BAHAN :
Kayu Kelas III Balok 0.0037 m3 - -
Paku Biasa 0.0200 Kg - -
Kayu Kayu Kelas III Papan 3/20 0.0060 m3 - -
Jumlah Bahan -
UPAH :
Pekerja 0.1000 Oh - -
P PK05 Tukang Kayu 0.1000 Oh - -
P PK03 Kepala Tukang 0.0100 Oh - -
LL01 Mandor 0.0050 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.02.01 1 M3 GALIAN TANAH BIASA KEDALAMAN MAX 1 M
BAHAN :
-
Jumlah Bahan -
UPAH :
Pekerja 0.7500 Oh - -
P PK05 Mandor 0.0250 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.02.02 1 M3 GALIAN TANAH BIASA KEDALAMAN MAX 2 M
BAHAN :
-
Jumlah Bahan -
UPAH :
Pekerja 0.9000 Oh - -
P PK05 Mandor 0.0450 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.02.03 1 M3 GALIAN TANAH BIASA KEDALAMAN MAX 3 M
BAHAN :
-
Jumlah Bahan -
UPAH :
Pekerja 1.0500 Oh - -
P PK05 Mandor 0.0670 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.02.11 1 M3 URUGAN TANAH KEMBALI
BAHAN :
Tanah Urug 1.2000 m³ - -
Jumlah Bahan -
UPAH :
Pekerja 0.2500 Oh - -
P PK05 Mandor 0.0250 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.02.12 1 M3 URUGAN TANAH DIPADATKAN
BAHAN :
Tanah Urug 1.2000 m³ - -
Jumlah Bahan -
UPAH :
Pekerja 0.5000 Oh - -
P PK05 Mandor 0.0500 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.02.13 1 M3 URUGAN PASIR
BAHAN :
Pasir Urug 1.2000 m³ - -
Jumlah Bahan -
UPAH :
Pekerja 0.3000 Oh - -
P PK05 Mandor 0.0100 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.02.22 1 M3 PENIMBUNAN TANAH DIPADATKAN (TANAH DARI LUAR)
BAHAN :
Tanah Urug (didatangkan) 1.2000 m³ - -
Jumlah Bahan -
UPAH :
Pekerja 0.5000 Oh - -
Mandor 0.0500 Oh - -
P PK05 Alat Bantu (sewa Stamper) 0.1250 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Page 30 of 707
Analisa Satuan Pekerjaan
A001 Dibulatkan -
A.03.02 1 M3 PASANG PONDASI BATU KALI 1 Pc : 2 Ps
BAHAN :
Batu Kali / Belah Belah 1.1000 m³ - -
Semen PC (50 kg) 267.0000 Kg - -
Pasir Pasang 0.4270 m³ - -
Jumlah Bahan -
UPAH :
Pekerja 1.5000 Oh - -
Tukang Batu 0.7500 Oh - -
Kepala Tukang 0.0750 Oh - -
P PK05 Mandor 0.0750 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.03.03 1 M3 PASANG PONDASI BATU KALI 1 Pc : 3 Ps
BAHAN :
Batu Kali / Belah Belah 1.1000 m³ - -
Semen PC (50 kg) 202.0000 Kg - -
Pasir Pasang 0.4850 m³ - -
Jumlah Bahan -
UPAH :
Pekerja 1.5000 Oh - -
Tukang Batu 0.7500 Oh - -
Kepala Tukang 0.0750 Oh - -
P PK05 Mandor 0.0750 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.03.04 1 M3 PASANG PONDASI BATU KALI 1 Pc : 4 Ps
BAHAN :
Batu Kali / Belah Belah 1.2000 m³ - -
Semen PC (50 kg) 163.0000 Kg - -
Pasir Pasang 0.5200 m³ - -
Jumlah Bahan -
UPAH :
Pekerja 1.5000 Oh - -
Tukang Batu 0.7500 Oh - -
Kepala Tukang 0.0750 Oh - -
P PK05 Mandor 0.0750 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.03.05 1 M3 PASANG PONDASI BATU KARANG MATI 1 Pc : 4 Ps
BAHAN :
Batu Kali / Belah Belah 1.2000 m³ - -
Semen PC (50 kg) 163.0000 Kg - -
Pasir Pasang 0.5200 m³ - -
Jumlah Bahan -
UPAH :
Pekerja 1.5000 Oh - -
Tukang Batu 0.7500 Oh - -
Kepala Tukang 0.0750 Oh - -
P PK05 Mandor 0.0750 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.03.13 1 M3 PASANG BATU KOSONG ( AANSTAMPING ), JENIS BATU KALI
BAHAN :
Batu Kali / Belah Belah 1.2000 m³ - -
Pasir Urug 0.4320 m³ - -
Jumlah Bahan -
UPAH :
Pekerja 0.7800 Oh - -
Tukang Batu 0.3900 Oh - -
Kepala Tukang 0.0390 Oh - -
P PK05 Mandor 0.0390 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.03.13.a 1 M3 PASANG BATU KOSONG ( AANSTAMPING ), JENIS BATU KARANG MATI
BAHAN :
Batu Karang Mati 1.2000 m³ - -
Pasir Urug 0.3000 m³ - -
Jumlah Bahan -
UPAH :
Pekerja 0.7800 Oh - -
Tukang Batu 0.3900 Oh - -
Kepala Tukang 0.0390 Oh - -
P PK05 Mandor 0.0200 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.04.09 1 M2 PASANGAN DINDING BATA MERAH TEBAL 1/2 BATA, 1 Pc : 2 Ps
BAHAN :
Bata Merah Bakar Kelas I 140.0000 bh - -
Semen PC (50 kg) 43.5000 Kg - -
Pasir Pasang 0.0800 m³ - -
Jumlah Bahan -
UPAH :
Pekerja 0.6000 Oh - -
Tukang Batu 0.2000 Oh - -
Kepala Tukang 0.0200 Oh - -
P PK05 Mandor 0.0300 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
Page 31 of 707
Analisa Satuan Pekerjaan
A.04.10 1 M2 PASANGAN DINDING BATAKO 1/2 BATA, 1 Pc : 2 Ps
BAHAN :
Batako 35.0000 bh - -
Semen PC (50 kg) 9.4750 Kg - -
Pasir Pasang 0.0380 m³ - -
Jumlah Bahan -
UPAH :
Pekerja 0.3200 Oh - -
Tukang Batu 0.1000 Oh - -
Kepala Tukang 0.0100 Oh - -
P PK05 Mandor 0.0050 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.04.11 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 Pc : 4 Ps
BAHAN :
Bata Merah Bakar Kelas I 70.0000 bh - -
Semen PC (50 kg) 11.5000 Kg - -
Pasir Pasang 0.0430 m³ - -
Jumlah Bahan -
UPAH :
Pekerja 0.3000 Oh - -
Tukang Batu 0.1000 Oh - -
Kepala Tukang 0.0100 Oh - -
P PK05 Mandor 0.0150 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.04.12 1 M2 PASANGAN DINDING BATAKO 1/2 BATA, 1 Pc : 4 Ps
BAHAN :
Batako 35.0000 bh - -
Semen PC (50 kg) 5.7500 Kg - -
Pasir Pasang 0.0430 m³ - -
Jumlah Bahan -
UPAH :
Pekerja 0.3200 Oh - -
Tukang Batu 0.1000 Oh - -
Kepala Tukang 0.0100 Oh - -
P PK05 Mandor 0.0150 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.05.19 1 M2 PASANGAN PLESTERAN 1 Pc : 2 Ps, TEBAL 20 MM
BAHAN :
Semen PC (50 kg) 13.6320 Kg - -
Pasir Pasang 0.0270 m³ - -
Jumlah Bahan -
UPAH :
Pekerja 0.4000 Oh - -
Tukang Batu 0.2000 Oh - -
Kepala Tukang 0.0200 Oh - -
P PK05 Mandor 0.0220 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.05.21 1 M2 PASANGAN PLESTERAN 1 Pc : 4 Ps, TEBAL 25 MM + ACIAN
BAHAN :
Semen PC (50 kg) 9.4800 Kg - -
Pasir Pasang 0.0380 m³ - -
Jumlah Bahan -
UPAH :
Pekerja 0.3000 Oh - -
Tukang Batu 0.2000 Oh - -
Kepala Tukang 0.0200 Oh - -
P PK05 Mandor 0.0130 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.05.36 1 M2 ACIAN PC
BAHAN :
BA34 Semen PC (50 kg) 3.2500 zak - -
Jumlah Bahan -
UPAH :
P PK02 Pekerja 0.2000 org - -
P PK04 Tukang Batu 0.1000 org - -
P PK06 Kepala Tukang batu 0.0100 org - -
P PK19 Mandor 0.0100 org - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Jumlah -
A077 Dibulatkan -
A.06.01 1 M3 PEKERJAAN KUSEN PINTU DAN JENDELA KAYU KLS II
BAHAN :
Kayu Kelas II Balok 1.2000 m³ - -
Paku Biasa 1.2500 Kg - -
Lem kayu 1.0000 Kg - -
Jumlah Bahan -
UPAH :
Pekerja 6.0000 Oh - -
Tukang Kayu 18.0000 Oh - -
Kepala Tukang 1.8000 Oh - -
P PK05 Mandor 0.3000 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.06.02 1 UNIT PEK. KUSEN PINTU P1 (L=170 cm) + JALUZI
BAHAN :
Page 32 of 707
Analisa Satuan Pekerjaan
Pek. Kusen pintu P1 + Jaluzi 0.06760 m³ - -
Jumlah Bahan -
A001 Dibulatkan -
A.06.03 1 UNIT PEK. KUSEN PINTU P2 (L=90 cm) + JALUZI
BAHAN :
Pek. Kusen pintu P2 + Jaluzi 0.0500 m³ - -
Jumlah Bahan -
A001 Dibulatkan -
A.06.04 1 UNIT PEK. KUSEN PINTU P3 (L=70 cm)
BAHAN :
Pek. Kusen pintu P3 0.0290 m³ - -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.06.05 1 UNIT PEK. KUSEN PINTU P5 (L=100 cm)
BAHAN :
Pek. Kusen pintu P5 0.0510 m³ - -
Jumlah Bahan -
A001 Dibulatkan -
A.06.06 1 UNIT PEK. KUSEN PINTU JENDELA PJ1/PJ1A + JALUZI
BAHAN :
Kusen Pintu Jendela PJ1 + Jaluzi 0.1010 m³ - -
Jumlah Bahan -
A001 Dibulatkan -
A.06.07 1 UNIT PEK. KUSEN PINTU JENDELA PJ2 + JALUZI
BAHAN :
Kusen Pintu Jendela PJ2 + Jaluzi 0.1010 m³ - -
Jumlah Bahan -
A001 Dibulatkan -
A.06.08 1 UNIT PEK. KUSEN PINTU JENDELA PJ3 + JALUZI
BAHAN :
Kusen Pintu Jendela PJ3 + Jaluzi 0.1630 m³ - -
Jumlah Bahan -
A001 Dibulatkan -
A.06.09 1 UNIT PEK. KUSEN JENDELA J2 + JALUZI
BAHAN :
Kusen Jendela J2 + Jaluzi 0.0690 m³ - -
Jumlah Bahan -
A001 Dibulatkan -
A.06.10 1 UNIT PEK. KUSEN JENDELA J3 + JALUZI
BAHAN :
Kusen Jendela J3 + Jaluzi 0.0950 m³ - -
Jumlah Bahan -
A001 Dibulatkan -
A.06.11 1 UNIT PEK. KUSEN JENDELA J4 + JALUZI
BAHAN :
Kusen Jendela J4 + Jaluzi 0.1470 m³ - -
Jumlah Bahan -
A001 Dibulatkan -
A.06.12 1 UNIT PEK. KUSEN JENDELA J
BAHAN :
Kusen Jendela J 0.0300 m³ - -
Jumlah Bahan -
A001 Dibulatkan -
A.06.13 1 UNIT PEK. KUSEN BOUVENLICH BV1
BAHAN :
Kusen Bouvenlich BV1 0.0240 m³ - -
Jumlah Bahan -
A001 Dibulatkan -
A.06.14 1 UNIT PEK. KUSEN BOUVENLICH BV2
BAHAN :
Kusen Bouvenlich BV2 0.0430 m³ - -
Jumlah Bahan -
A001 Dibulatkan -
A.06.15 1 UNIT PEK. KUSEN BOUVENLICH BV3
BAHAN :
Kusen Bouvenlich BV3 0.0610 m³ - -
Jumlah Bahan -
A001 Dibulatkan -
A.06.16 1 UNIT PEK. KUSEN ANGIN-ANGIN LA-LB + JALUZI
BAHAN :
Kusen Angin-Angin LA-LB + Jaluzi 0.0340 m³ - -
Jumlah Bahan -
A001 Dibulatkan -
A.06.17 1 M2 PEKERJAAN DAUN PINTU PANEL KAYU LOKAL KLS II
BAHAN :
Kayu Kelas II Papan 0.0400 m³ - -
Lem Kayu 0.0500 kg - -
Jumlah Bahan -
UPAH :
Pekerja 1.0000 Oh - -
Tukang Kayu 3.0000 Oh - -
Kepala Tukang 0.3000 Oh - -
P PK05 Mandor 0.0500 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.06.18 1 BH PASANGAN DAUN PINTU PANIL
BAHAN :
Pintu Panil 1.6800 m2 - -
Jumlah Bahan -
A001 Dibulatkan -
A.06.19 1 BH PASANGAN DAUN PINTU PANIL P5
BAHAN :
Pintu Panil 1.8900 m2 - -
Jumlah Bahan -
A001 Dibulatkan -
A.06.20 1 M2 PEKERJAAN DAUN PINTU TRIPLEKS RANGKAP, RANGKA KAYU KLS II
Page 33 of 707
Analisa Satuan Pekerjaan
BAHAN :
Kayu Kls. II Balok 0.0196 m³ - -
Paku Biasa Tripleks 0.0300 kg - -
Lem Kayu 0.3000 kg - -
Tripleks 6 mm 1.0000 lbr - -
Jumlah Bahan -
UPAH :
Pekerja 0.8500 Oh - -
Tukang Kayu 2.5500 Oh - -
Kepala Tukang 0.2550 Oh - -
P PK05 Mandor 0.0430 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.06.21 1 BH PASANGAN DAUN PINTU TRIPLEKS P3
BAHAN :
Pintu Tripleks P3 1.2600 m2 - -
Jumlah Bahan -
A001 Dibulatkan -
A.06.22 1 M2 PEKERJAAN DAUN JENDELA + KACA
BAHAN :
Kayu Kelas II Papan 0.1000 m³ - -
Kaca Polos 5 mm 1.1000 m2 - -
Lem Kayu 0.3000 kg - -
Jumlah Bahan -
UPAH :
Pekerja 0.8500 Oh - -
Tukang Kayu 2.5500 Oh - -
Kepala Tukang 0.2550 Oh - -
P PK05 Mandor 0.0430 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.06.23 1 BH PASANGAN DAUN JENDELA + KACA (PJ1 dan PJ2)
BAHAN :
Daun Jendela + Kaca (PJ1 dan PJ2) 0.5070 m2 - -
Jumlah Bahan -
A001 Dibulatkan -
A.06.24 1 BH PASANGAN DAUN JENDELA + KACA PJ3
BAHAN :
Daun Jendela + Kaca PJ3 1.2480 m2 - -
Jumlah Bahan -
A001 Dibulatkan -
A.06.25 1 BH PASANGAN DAUN PINTU + KACA PJ3
BAHAN :
Daun Pintu + Kaca PJ3 1.6800 m2 - -
Jumlah Bahan -
A001 Dibulatkan -
A.06.26 1 BH PASANGAN DAUN JENDELA + KACA J2
BAHAN :
Daun Jendela + Kaca J2 0.5070 m2 - -
Jumlah Bahan -
A001 Dibulatkan -
A.06.27 1 BH PASANGAN DAUN JENDELA + KACA J3
BAHAN :
Daun Jendela + Kaca J3 0.5915 m2 - -
Jumlah Bahan -
Dibulatkan -
A.06.28 1 BH PASANGAN DAUN JENDELA + KACA J4
BAHAN :
Daun Jendela + Kaca J4 1.2480 m2 - -
Jumlah Bahan -
Dibulatkan -
A.06.29 1 BH PASANGAN DAUN JENDELA + KACA J5
BAHAN :
Daun Jendela + Kaca J5 0.8050 m2 - -
Jumlah Bahan -
Dibulatkan -
A.06.30 1 BH PASANGAN DAUN JENDELA + KACA J6
BAHAN :
Daun Jendela + Kaca J6 0.5980 m2 - -
Jumlah Bahan -
Dibulatkan -
A.06.31 1 UNIT PEK. KUSEN JENDELA J5
BAHAN :
Kusen Jendela J5 0.0310 m³ - -
Jumlah Bahan -
Dibulatkan -
A.06.32 1 UNIT PEK. KUSEN JENDELA J6
BAHAN :
Kusen Jendela J6 0.0490 m³ - -
Jumlah Bahan -
Dibulatkan -
A.06.32.a 1 M2 PASANG KACA TEBAL 5 MM
BAHAN :
- m³ - -
Kaca Polos 5 mm 1.1000 m2 - -
Paku Biasa Tripleks 0.0300 kg - -
Jumlah Bahan -
UPAH :
Pekerja 0.5000 Oh - -
Tukang Kayu 0.1500 Oh - -
Kepala Tukang 0.0150 Oh - -
P PK05 - Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
Page 34 of 707
Analisa Satuan Pekerjaan
A.06.33 1 M1 PASANG KONSTRUKSI NOK BUBUNGAN 6/12 KAYU KLS II
BAHAN :
Kayu Kls. II Balok 1.1000 m³ - -
Paku Biasa 0.0500 kg - -
Jumlah Bahan -
UPAH :
Pekerja 0.2500 Oh - -
Tukang Kayu 0.1500 Oh - -
Kepala Tukang 0.0150 Oh - -
P PK05 Mandor 0.0130 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.06.34 1 M3 PASANG KONSTRUKSI SKOOR ANGIN 6/12 KAYU KLS II
BAHAN :
Kayu Kls. II Balok 1.1000 m³ - -
Paku Biasa 5.8000 kg - -
Jumlah Bahan -
UPAH :
Pekerja 4.0000 Oh - -
Tukang Kayu 12.0000 Oh - -
Kepala Tukang 1.2000 Oh - -
P PK05 Mandor 0.2000 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.06.35 1 M3 PASANGAN KONSTRUKSI KUDA - KUDA 8/12 KAYU KAYU LOKAL KLS II
BAHAN :
Kayu Kls. II Balok 1.1000 m³ - -
Paku Biasa 5.6000 kg - -
Jumlah Bahan -
UPAH :
Pekerja 4.0000 Oh - -
Tukang Kayu 12.0000 Oh - -
Kepala Tukang 1.2000 Oh - -
P PK05 Mandor 0.2000 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.06.36 1 M3 PASANG KONSTRUKSI GORDING 5/10 KAYU KLS II
BAHAN :
Kayu Kls. II Balok 1.1000 m³ - -
Paku Biasa 3.0000 kg - -
Jumlah Bahan -
UPAH :
Pekerja 6.7000 Oh - -
Tukang Kayu 20.1000 Oh - -
Kepala Tukang 2.0100 Oh - -
P PK05 Mandor 0.3350 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.06.37 1 M2 PASANG KASO 5/7 KAYU KLS II
BAHAN :
Kayu Kls. II Balok 0.0110 m³ - -
Paku Biasa 0.2500 kg - -
Jumlah Bahan -
UPAH :
Pekerja 0.0700 Oh - -
Tukang Kayu 0.0100 Oh - -
Kepala Tukang 0.0700 Oh - -
P PK05 Mandor 0.0050 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.06.38 1 M2 PASANG Rangka Atap 5/7 dan 3/4 KAYU KLS II
BAHAN :
Kayu Kls. II Balok 0.0120 m³ - -
Paku Biasa 0.1500 kg - -
Jumlah Bahan -
UPAH :
Pekerja 0.1000 Oh - -
Tukang Kayu 0.1000 Oh - -
Kepala Tukang 0.0100 Oh - -
P PK05 Mandor 0.0050 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.06.39 1 M1 PASANG KONSTRUKSI NOK TEPI PAPAN 6/12 KAYU KLS II
BAHAN :
Kayu Kelas II Papan 1.0000 m³ - -
Paku Biasa 0.0450 kg - -
Jumlah Bahan -
UPAH :
Pekerja 0.1000 Oh - -
Tukang Kayu 0.2000 Oh - -
Kepala Tukang 0.0200 Oh - -
P PK05 Mandor 0.0050 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.06.44 1 M2 PASANG RANGKA PLAFOND BALOK 5/7 KAYU LOKAL KLS II
BAHAN :
Kayu Kls II, Kaso 5/7 Rangka Plafon 0.0163 m³ - -
Paku Biasa 0.2500 kg - -
Jumlah Bahan -
UPAH :
Page 35 of 707
Analisa Satuan Pekerjaan
Pekerja 0.2000 Oh - -
Tukang Kayu 0.3000 Oh - -
Kepala Tukang 0.0300 Oh - -
P PK05 Mandor 0.0100 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.06.50 1 M2 PASANG LISPLANG UKURAN (3 x 25) cm, KAYU LOKAL KLS II
BAHAN :
Kayu Kelas II Papan 0.0110 m³ - -
Paku Biasa 0.0500 kg - -
Jumlah Bahan -
UPAH :
Pekerja 0.1000 Oh - -
Tukang Kayu 0.2000 Oh - -
Kepala Tukang 0.0200 Oh - -
P PK05 Mandor 0.0050 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.06.60 1 M1 PASANG LIST PLAFOND PROFIL KAYU LOKAL KLS II 3/3
BAHAN :
List Plafond 3/3 1.0500 m' - -
Paku Biasa 0.0100 kg - -
Jumlah Bahan -
UPAH :
Pekerja 0.0500 Oh - -
Tukang Kayu 0.0500 Oh - -
Kepala Tukang 0.0050 Oh - -
P PK05 Mandor Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.07.01 1 M3 MEMBUAT BETON TUMBUK, 1 Pc : 3 Ps : 5 Kr
BAHAN :
Semen PC (50 kg) 230.0000 kg - -
Pasir Beton 0.8930 M3 - -
Batu Kerikil / Split 2/3 cm 1.0270 m³ - -
Jumlah Bahan -
UPAH :
Pekerja 1.2000 Oh - -
Tukang Batu 0.2000 Oh - -
Kepala Tukang 0.0200 Oh - -
P PK05 Mandor 0.0600 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.07.13 1 M3 MEMBUAT BETON BERTULANG 1 Pc : 2 Ps : 3 Kr
BAHAN :
Semen PC (50 kg) 384.0000 kg - -
Pasir Beton 0.5400 m3 - -
Batu Kerikil / Split 2/3 cm 0.8100 m³ - -
Jumlah Bahan -
UPAH :
Pekerja 1.6500 Oh - -
Tukang Batu 0.2570 Oh - -
Kepala Tukang 0.0280 Oh - -
P PK05 Mandor 10.0830 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.07.25 1 Kg PEMBESIAN DENGAN BESI POLOS ATAU BESI ULIR
BAHAN :
Besi Beton Polos 1.0500 kg - -
Kawat Beton 0.0150 kg - -
Jumlah Bahan -
UPAH :
Pekerja 0.0070 Oh - -
Tukang Besi 0.0070 Oh - -
P PK05 Kepala Tukang 0.0007 Oh - -
P PK05 Mandor 0.0003 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.07.28 1 m2 PASANG BEKISTING UNTUK PONDASI
BAHAN :
Kayu Kelas III Papan 0.0400 m³ - -
Paku Biasa 0.3000 m³ - -
Minyak Bekisting 0.1000 ltr - -
Jumlah Bahan -
UPAH :
Pekerja 0.3000 Oh - -
Tukang Kayu 0.2600 Oh - -
P PK05 Kepala Tukang 0.0260 Oh - -
P PK05 Mandor 0.0050 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.07.29 1 m2 PASANG BEKISTING UNTUK SLOOF
BAHAN :
Kayu Kelas III Papan 0.0044 m³ - -
Paku Biasa 0.3000 m³ - -
Minyak Bekisting 0.1000 m³ - -
Jumlah Bahan -
UPAH :
Pekerja 0.3000 Oh - -
Tukang Kayu 0.2600 Oh - -
Page 36 of 707
Analisa Satuan Pekerjaan
P PK05 Kepala Tukang 0.0260 Oh - -
P PK05 Mandor 0.0050 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.07.30 1 m2 PASANG BEKISTING UNTUK KOLOM
BAHAN :
Kayu Kelas III Papan 0.0040 m³ - -
Paku Biasa 0.4000 kg - -
Minyak Bekisting 0.2000 ltr - -
Kayu Kelas III Balok 0.0015 m³ - -
Jumlah Bahan -
UPAH :
Pekerja 0.3000 Oh - -
Tukang Kayu 0.3300 Oh - -
P PK05 Kepala Tukang 0.0330 Oh - -
P PK05 Mandor 0.0060 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.07.31 1 m2 PASANG BEKISTING UNTUK BALOK
BAHAN :
Kayu Kelas III Papan 0.0040 m³ - -
Paku Biasa 0.4000 kg - -
Minyak Bekisting 0.2000 ltr - -
Kayu Kelas III Balok 0.0018 m³ - -
Kayu Dolken 2.0000 btg - -
Jumlah Bahan -
UPAH :
Pekerja 0.3200 Oh - -
Tukang Kayu 0.3300 Oh - -
P PK05 Kepala Tukang 0.0330 Oh - -
P PK05 Mandor 0.0060 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.07.32 1 m2 PASANG BEKISTING UNTUK LANTAI
BAHAN :
Kayu Kelas III Papan 0.0020 m³ - -
Paku Biasa 0.4000 kg - -
Minyak Bekisting 0.2000 ltr - -
Kayu Kelas III Balok 0.0015 m³ - -
Polywood tebal 9 mm 0.3500 lbr - -
Kayu Dolken 4.0000 btg - -
Jumlah Bahan -
UPAH :
Pekerja 0.3200 Oh - -
Tukang Kayu 0.3300 Oh - -
P PK05 Kepala Tukang 0.0330 Oh - -
P PK05 Mandor 0.0060 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.07.33 1 m2 PASANG BEKISTING UNTUK DINDING
BAHAN :
Kayu Kelas III Papan 0.0300 m³ - -
Paku Biasa 0.4000 kg - -
Minyak Bekisting 0.2000 ltr - -
Kayu Kelas III Balok 0.0200 m³ - -
Polywood tebal 9 mm 0.3500 lbr - -
Kayu Dolken 3.0000 btg - -
Formtie / Penjaga Jarak Berkisar / Spacer 4.0000 bh -
Jumlah Bahan -
UPAH :
Pekerja 0.3200 Oh - -
Tukang Kayu 0.3300 Oh - -
P PK05 Kepala Tukang 0.0330 Oh - -
P PK05 Mandor 0.0060 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.07.47 1 M3 MEMBUAT SOFI-SOFI 12/15 (220,80 Kg Besi + Bekesting)
DENGAN TULANGAN 4 BATANG DIA 10 BEUGEL DIA 6 JARAK 15 CM 190.1393
BAHAN :
Kayu Kelas III Papan 0.3700 m³ - -
Paku Biasa 1.5000 kg - -
Pelumas Bekesting 0.4000 lt - -
Besi Beton Polos Dia. 10 mm 152.6578 kg - -
Besi Beton Polos Dia. 8 mm 37.4815 kg - -
Kawat Beton 2.2500 kg - -
Semen PC (50 kg) 6.4600 zak - -
Pasir Beton 0.5200 m³ - -
Batu Kerikil / Split 2/3 cm 0.7800 m³ - -
Jumlah Bahan -
UPAH :
Tukang Batu 0.3500 org - -
Tukang Kayu 1.0400 org - -
Tukang Besi 1.0500 org - -
Kepala Tukang 0.2450 org - -
Pekerja 3.0000 org - -
Mandor 0.1225 org - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
A.07.48 1 M3 MEMBUAT RING BALOK 15/20 (145,92 Kg Besi + Bekesting)
DENGAN TULANGAN 4 BATANG DIA 10 BEUGEL DIA 8 JARAK 15 CM
BAHAN :
Page 37 of 707
Analisa Satuan Pekerjaan
Kayu Kelas III Papan 0.3700 m³ - -
Paku Biasa 1.5000 kg - -
Pelumas Bekesting 0.4000 lt - -
Besi Beton Polos Dia. 10 mm 92.5867 kg - -
Besi Beton Polos Dia. 8 mm 53.3333 kg - -
Kawat Beton 2.2500 kg - -
Semen PC (50 kg) 6.4600 zak - -
Pasir Beton 0.5200 m³ - -
Batu Kerikil / Split 2/3 cm 0.7800 m³ - -
Jumlah Bahan -
UPAH :
Tukang Batu 0.3500 org - -
Tukang Kayu 1.0400 org - -
Tukang Besi 1.0500 org - -
Kepala Tukang 0.2450 org - -
Pekerja 3.0000 org - -
Mandor 0.1225 org - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
A.07.48'' 1 M3 MEMBUAT RING BALOK 12/20 (177,9556 Kg Besi + Bekesting) 177.9556
DENGAN TULANGAN 4 BATANG DIA 10 BEUGEL DIA 8 JARAK 15 CM
BAHAN :
Kayu Kelas III Papan 0.3700 m³ 0 -
Paku Biasa 1.5000 kg 0 -
Pelumas Bekesting 0.4000 lt 0 -
Besi Beton Polos Dia. 10 mm 115.7333 kg 0 -
Besi Beton Polos Dia. 8 mm 62.2222 kg 0 -
Kawat Beton 2.2500 kg 0 -
Semen PC (50 kg) 6.4600 zak 0 -
Pasir Beton 0.5200 m³ 0 -
Batu Kerikil / Split 2/3 cm 0.7800 m³ 0 -
Jumlah Bahan -
UPAH :
Tukang Batu 0.3500 org 0 -
Tukang Kayu 1.0400 org 0 -
Tukang Besi 1.0500 org 0 -
Kepala Tukang 0.2450 org 0 -
Pekerja 3.0000 org 0 -
Mandor 0.1225 org 0 -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
A.07.49 1 M3 MEMBUAT KOLOM 20/25 (169,67 Kg Besi + Bekesting)
DENGAN TULANGAN 6 BATANG DIA 12 BEUGEL DIA 8 JARAK 15 CM
BAHAN :
Kayu Kelas III Bekesting 0.3700 m³ - -
Paku Biasa 1.5000 kg - -
Pelumas Bekesting 0.4000 lt - -
5.88 Besi Beton Polos Dia. 12 mm 122.8200 kg - -
4.19 Besi Beton Polos Dia. 8 mm 42.6667 kg - -
Kawat Beton 2.2500 kg - -
Semen PC (50 kg) 6.4600 zak - -
Pasir Beton 0.5200 m³ - -
Batu Kerikil / Split 2/3 cm 0.7800 m³ - -
Jumlah Bahan -
UPAH :
Tukang Batu 0.3500 org - -
Tukang Kayu 1.0400 org - -
Tukang Besi 1.0500 org - -
Kepala Tukang 0.2450 org - -
Pekerja 3.0000 org - -
Mandor 0.1225 org - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
A.07.50 1 M3 MEMBUAT SLOOF SELASAR 15/20 (188,88 Kg Besi + Bekesting)
DENGAN TULANGAN 4 BATANG DIA 12 BEUGEL DIA 8 JARAK 15 CM
BAHAN :
Kayu Kelas III Bekesting 0.2900 m³ - -
Paku Biasa 1.5000 kg - -
Pelumas Bekesting 0.4000 lt - -
3.70 Besi Beton Polos Dia. 12 mm 132.9067 kg - -
2.64 Besi Beton Polos Dia. 8 mm 53.3333 kg - -
Kawat Beton 2.2500 kg - -
Semen PC (50 kg) 6.4600 zak - -
Pasir Beton 0.5200 m³ - -
Batu Kerikil / Split 2/3 cm 0.7800 m³ - -
Jumlah Bahan -
UPAH :
Tukang Batu 0.3500 org - -
Tukang Kayu 1.0400 org - -
Tukang Besi 1.0500 org - -
Kepala Tukang 0.2450 org - -
Pekerja 3.0000 org - -
Mandor 0.1225 org - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Jumlah -
Dibulatkan -
A.07.51 1 M3 PEK. BETON BERTULANG PLAT MEJA, adukan 1 : 2 : 3
BAHAN :
Kayu Kelas III Bekesting 0.3300 m3 - -
Paku Biasa 3.0000 kg - -
Besi Beton Polos Dia. 10 mm 110.0000 kg - -
Kawat Beton 3.0000 kg - -
Semen PC (50 kg) 6.4600 Zak - -
Page 38 of 707
Analisa Satuan Pekerjaan
Pasir Beton 0.5200 m3 - -
Kerikil beton 0.7800 m3 - -
Jumlah Bahan -
UPAH :
Tukang Batu 0.3500 org - -
Tukang Kayu 1.0400 org - -
Tukang Besi 1.0500 org - -
Kepala Tukang 0.2450 org - -
Pekerja 3.0000 org - -
Mandor 0.1225 org - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Jumlah -
Dibulatkan -
A.07.52 1 M3 MEMBUAT KOLOM 12/15 (197 Kg Besi + Bekesting)
DENGAN TULANGAN 4 BATANG DIA 10 BEUGEL DIA 6 JARAK 15 CM 190.1393
BAHAN :
Kayu Kelas III Bekesting 0.4000 m³ - -
Paku Biasa 1.5000 kg - -
Pelumas Bekesting 0.4000 lt - -
20.42 Besi Beton Polos Dia. 10 mm 152.6578 kg - -
10.13 Besi Beton Polos Dia. 6 mm 37.4815 kg - -
Kawat Beton 2.2500 kg - -
Semen PC (50 kg) 6.4600 zak - -
Pasir Beton 0.5200 m³ - -
Batu Kerikil / Split 2/3 cm 0.7800 m³ - -
Jumlah Bahan -
UPAH :
Tukang Batu 0.3500 org - -
Tukang Kayu 1.0400 org - -
Tukang Besi 1.0500 org - -
Kepala Tukang 0.2450 org - -
Pekerja 3.0000 org - -
Mandor 0.1225 org - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
A.07.60 1 M3 MEMBUAT KOLOM SELASAR 15/15 (181,88 Kg Besi + Bekesting)
DENGAN TULANGAN 4 BATANG DIA 10 BEUGEL DIA 8 JARAK 15 CM
BAHAN :
Kayu Kelas III Bekesting 0.4400 m³ - -
Paku Biasa 1.5000 kg - -
Pelumas Bekesting 0.4000 lt - -
8.33 Besi Beton Polos Dia. 10 mm 122.6222 kg - -
4.13 Besi Beton Polos Dia. 8 mm 59.2593 kg - -
Kawat Beton 2.2500 kg - -
Semen PC (50 kg) 6.4600 zak - -
Pasir Beton 0.5200 m³ - -
Batu Kerikil / Split 2/3 cm 0.7800 m³ - -
Jumlah Bahan -
UPAH :
Tukang Batu 0.3500 org - -
Tukang Kayu 1.0400 org - -
Tukang Besi 1.0500 org - -
Kepala Tukang 0.2450 org - -
Pekerja 3.0000 org - -
Mandor 0.1225 org - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
A.07.75 1 M3 PEK. PLAT BETON BERTULANG, TULANGAN 1 LAPIS DIA.10 JARAK 10 cm TEBAL 10 cm
BAHAN :
Semen PC (50 kg) 232.0000 kg - -
Pasir Beton 0.5200 lbr - -
Batu Kerikil / Split 2/3 cm 0.7800 m³ - -
Besi Beton Polos Dia. 10 mm 137.3610 Kg - -
Kawat Beton 1.9623 Kg - -
Kayu Kelas III Bekesting 0.2450 m³ - -
Paku Biasa 0.1500 kg - -
Minyak Bekisting 1.4000 Ltr - -
Kayu Kelas III Balok 0.0700 m³ - -
Jumlah Bahan -
UPAH :
Pekerja 6.4697 Oh - -
Tukang Batu 0.2500 Oh - -
Tukang Kayu 4.0260 Oh - -
Tukang Besi 1.0073 Oh - -
Kepala Tukang 0.5192 Oh - -
Mandor 0.1924 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
A.08.02 1 M2 PASANG ATAP GENTENG TANAH
BAHAN :
Genteng Tanah 25.0000 buah - -
Jumlah Bahan -
UPAH :
Pekerja 0.1500 Oh - -
Tukang Kayu 0.0750 Oh - -
P PK05 Kepala Tukang 0.0080 Oh - -
P PK05 Mandor 0.0080 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.08.03 1 M2 PASANG ATAP SPANDEK / GALVALYUM 0,3mm
BAHAN :
Atap Spandek/Galvalyum 1.0200 Lbr - -
Page 39 of 707
Analisa Satuan Pekerjaan
Paku Seng +seal 0.2000 Kg - -
Jumlah Bahan -
UPAH :
Pekerja 0.2000 Oh - -
Tukang Kayu 0.1000 Oh - -
P PK05 Kepala Tukang 0.0100 Oh - -
P PK05 Mandor 0.0010 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.08.05 1 M2 PASANG NOK BUBUNGAN GENTENG TANAH
BAHAN :
Bubungan Genteng Tanah 5.0000 Bh - -
Semen PC (50 kg) 8.0000 kg - -
Pasir Pasang 0.0320 m3 - -
Jumlah Bahan -
UPAH :
Pekerja 0.4000 Oh - -
Tukang Kayu 0.2000 Oh - -
P PK05 Kepala Tukang 0.0200 Oh - -
P PK05 Mandor 0.0020 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.08.06 1 M2 PASANG NOK BUBUNGAN GENTENG METAL
BAHAN :
Nok Genteng Metal 1.1000 buah - -
Paku Seng + karet seal 0.0500 kg - -
Jumlah Bahan -
UPAH :
Pekerja 0.2500 Oh - -
Tukang Kayu 0.1500 Oh - -
P PK05 Kepala Tukang 0.0150 Oh - -
P PK05 Mandor 0.0130 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.08.11 1 M2 PASANG ATAP SENG GELOMBANG BJLS 0,3 mm
BAHAN :
Seng Gelombang BJLS 0,3 0.7000 lbr - -
Paku Seng 0.0200 kg - -
Jumlah Bahan -
UPAH :
Pekerja 0.1200 Oh - -
Tukang Kayu 0.0600 Oh - -
P PK05 Kepala Tukang 0.0060 Oh - -
P PK05 Mandor 0.0060 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.08.12 1 M2 PASANG ATAP ZYNCALUM 0,3 mm
BAHAN :
Atap Spandex Zyncalum 1.0200 lbr - -
Paku Seng + karet seal 0.2000 kg - -
Jumlah Bahan -
UPAH :
Pekerja 0.1200 Oh - -
Tukang Kayu 0.0600 Oh - -
P PK05 Kepala Tukang 0.0060 Oh - -
P PK05 Mandor 0.0060 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.08.13 1 M2 PASANG ATAP GENTENG METAL 0,3 mm
BAHAN :
Genteng Metal/metal roof 1.0200 lbr - -
Paku Seng + karet seal 0.2000 kg - -
Jumlah Bahan -
UPAH :
Pekerja 0.2000 Oh - -
Tukang Kayu 0.1000 Oh - -
P PK05 Kepala Tukang 0.0100 Oh - -
P PK05 Mandor 0.0010 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.08.14 1 M' PASANG NOK SENG POLOS 0,3 mm
BAHAN :
Seng Plat Polos 0.3000 lbr - -
Paku Seng + karet seal 0.0400 kg - -
Jumlah Bahan -
UPAH :
Pekerja 0.0150 Oh - -
Tukang Kayu 0.0700 Oh - -
P PK05 Kepala Tukang 0.0080 Oh - -
P PK05 Mandor 0.0060 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.08.30 1 M1 PASANG NOK TEPI SENG GELOMBANG
BAHAN :
Nok Tepi Seng Gelombang 1.0000 m¹ - -
Paku Seng + karet seal 0.0450 kg - -
Jumlah Bahan -
UPAH :
Pekerja 0.2500 Oh - -
Tukang Kayu 0.0750 Oh - -
Page 40 of 707
Analisa Satuan Pekerjaan
P PK05 Kepala Tukang 0.0080 Oh - -
P PK05 Mandor 0.0080 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.08.31 1 M1 PASANG NOK TEPI ZYNCALUM
BAHAN :
Nok Tepi Zyncalum 1.0000 Bh - -
Paku Seng + karet seal 0.0450 kg - -
Jumlah Bahan -
UPAH :
Pekerja 0.2500 Oh - -
Tukang Kayu 0.0750 Oh - -
P PK05 Kepala Tukang 0.0080 Oh - -
P PK05 Mandor 0.0080 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.08.32 1 M1 PASANG NOK TEPI GENTENG METAL
BAHAN :
Nok Tepi Genteng Metal 1.0000 Bh - -
Paku Seng + karet seal 0.0450 kg - -
Jumlah Bahan -
UPAH :
Pekerja 0.2500 Oh - -
Tukang Kayu 0.0750 Oh - -
P PK05 Kepala Tukang 0.0080 Oh - -
P PK05 Mandor 0.0080 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.08.33 1 M1 PASANG NOK TEPI GENTENG TANAH
BAHAN :
Nok Tepi Genteng Metal 1.0000 Bh - -
Semen PC (50 kg) 0.1600 zak - -
Pasir Pasang 0.0320 m3 - -
Jumlah Bahan -
UPAH :
Pekerja 0.2500 Oh - -
Tukang Kayu 0.0750 Oh - -
P PK05 Kepala Tukang 0.0080 Oh - -
P PK05 Mandor 0.0080 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.08.34 1 M1 PASANG NOK TEPI ATAP SPANDEK/GALVALYUM
BAHAN :
Nok Tepi Atap Spandek 1.0000 Bh - -
Paku Seng 0.0450 kg - -
Jumlah Bahan -
UPAH :
Pekerja 0.2500 Oh - -
Tukang Kayu 0.0750 Oh - -
P PK05 Kepala Tukang 0.0080 Oh - -
P PK05 Mandor 0.0080 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.09.02 1 M2 PASANG PLAFOND TRIPLEKS , TEBAL 4 mm
BAHAN :
Tripleks 4 mm 0.3750 lbr - -
Paku Biasa 0.0300 kg - -
Jumlah Bahan -
UPAH :
Pekerja 0.1000 Oh - -
Tukang Kayu 0.1000 Oh - -
P PK05 Kepala Tukang 0.0100 Oh - -
P PK05 Mandor 0.0050 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.10.01 MEMASANG 1 BUAH KLOSET DUDUK
BAHAN :
Kloset Duduk 1.0000 bh - -
Perlengkapan 0.0600 harga kloset - -
Jumlah Bahan -
UPAH :
P PK05 Pekerja 3.3000 Oh - -
P PK05 Tukang Batu 1.1000 Oh - -
Kepala Tukang 0.0100 Oh - -
Mandor 0.1600 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
A.10.02 MEMASANG 1 BUAH KLOSET JONGKOK PORSELEN
BAHAN :
Kloset Jongkok 1.0000 bh - -
Semen PC (50 kg) 6.0000 kg - -
Pasir Pasang 0.0100 m³ - -
Jumlah Bahan -
P PK05 UPAH :
P PK05 Pekerja 1.0000 Oh - -
Tukang Batu 1.5000 Oh - -
Kepala Tukang 0.1500 Oh - -
Mandor 0.1600 Oh - -
Jumlah Pekerja -
A001 Jumlah Bahan + Pekerja -
Page 41 of 707
Analisa Satuan Pekerjaan
Dibulatkan -
A.10.04 MEMASANG 1 BUAH URINOIR
BAHAN :
Urinoir 1.0000 bh - -
P PK05 Perlengkapan 0.3000 hrg urinoir - -
P PK05 Semen PC (50 kg) 6.0000 kg - -
Pasir Pasang 0.0100 m³ - -
Jumlah Bahan -
UPAH :
Pekerja 1.0000 Oh - -
A001 Tukang Batu 1.0000 Oh - -
Kepala Tukang 0.1000 Oh - -
Mandor 0.0500 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
A.10.05 MEMASANG 1 BUAH WASTAFEL
P PK05 BAHAN :
P PK05 Wastafel 1.2000 bh - -
Perlengkapan 0.1200 hrg kloset - -
Semen PC (50 kg) 6.0000 kg - -
Pasir Pasang 0.0100 m³ - -
Jumlah Bahan -
A001 UPAH :
Pekerja 1.2000 Oh - -
Tukang Batu 1.4500 Oh - -
Kepala Tukang 0.1500 Oh - -
Mandor 0.0600 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
P PK05 Dibulatkan -
A.10.07 MEMASANG 1 BUAH BAK MANDI FIBREGLASS VOLUME 0,3 M3
BAHAN :
Bak Fibreglass 1.0000 bh - -
Perlengkapan 0.1800 hrg bak - -
A001 Jumlah Bahan -
UPAH :
Pekerja 2.0000 Oh - -
Tukang Batu 1.0000 Oh - -
Kepala Tukang 0.5000 Oh - -
Mandor 0.0500 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
P PK05 Dibulatkan -
A.10.08 MEMASANG 1 BUAH BAK MANDI BATU BATA VOLUME 0,3 M3
BAHAN :
Bata Merah Bakar Kelas I 150.0000 bh - -
Semen PC (50 kg) 120.0000 kg - -
A001 Pasir Pasang 0.3000 m³ - -
Keramik 20 x 20 cm 216.0000 bh - -
Semen Warna 6.0000 kg - -
Jumlah Bahan -
UPAH :
Pekerja 6.0000 Oh - -
Tukang Batu 3.0000 Oh - -
Kepala Tukang 0.3000 Oh - -
Mandor 0.0300 Oh - -
P PK05 Jumlah Pekerja -
P PK05 Jumlah Bahan + Pekerja -
Dibulatkan -
A.10.16 MEMASANG 1 BUAH BAK KONTROL PASANGAN BATU BATA UKURAN (30X30) TINGGI 35 CM
BAHAN :
Bata Merah Bakar Kelas I 0.1450 bh - -
P PK05 Semen PC (50 kg) 44.0000 kg - -
P PK05 Pasir Pasang 0.0700 m3 - -
Batu Kerikil / Split 2/3 cm 0.0700 m³ - -
Besi Beton Polos Dia. 10 mm 1.6000 kg - -
Pasir Beton 0.0600 m3 - -
Jumlah Bahan -
A001 UPAH :
Pekerja 3.5000 Oh - -
Tukang Batu 4.5000 Oh - -
Kepala Tukang 0.0500 Oh - -
Mandor 0.0180 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
P PK05 A.10.17 MEMASANG 1 BUAH BAK KONTROL PASANGAN BATU BATA UKURAN (45X45) TINGGI 50 CM
P PK05 BAHAN :
Bata Merah Bakar Kelas I 0.2500 m3 - -
Semen PC (50 kg) 77.0000 kg - -
Pasir Pasang 0.1300 m3 - -
Batu Kerikil / Split 2/3 cm 0.0200 m³ - -
A001 Besi Beton Polos Dia. 10 mm 2.6000 kg - -
Pasir Beton 0.0900 m3 - -
Jumlah Bahan -
UPAH :
Pekerja 3.5000 Oh - -
Tukang Batu 4.5000 Oh - -
Kepala Tukang 0.0500 Oh - -
Mandor 0.0180 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan - -
A.10.18 MEMASANG 1 BUAH BAK KONTROL PASANGAN BATU BATA UKURAN (60X60) TINGGI 65 CM
BAHAN :
Bata Merah Bakar Kelas I 0.3710 m3 - -
Page 42 of 707
Analisa Satuan Pekerjaan
A001 Semen PC (50 kg) 114.0000 kg - -
Pasir Pasang 0.1840 m3 - -
Batu Kerikil / Split 2/3 cm 0.0330 m³ - -
Besi Beton Polos Dia. 10 mm 4.8500 kg - -
Pasir Beton 0.1200 m3 - -
Jumlah Bahan -
UPAH :
Pekerja 2.1600 Oh - -
Tukang 0.1000 Oh - -
Tukang Batu 0.7200 Oh - -
P PK05 Kepala Tukang 0.0720 Oh - -
P PK05 Mandor 0.1080 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.10.19 MEMASANG 1 M' PIPA GALVANIS DIAMETER 0,5"
BAHAN :
Pipa Galvanis 0,5" 1.0000 m' - -
Perlengkapan 0.3500 hrg pipa - -
Jumlah Bahan -
UPAH :
Pekerja 0.0540 Oh - -
Tukang Batu 0.0900 Oh - -
P PK05 Kepala Tukang 0.0090 Oh - -
P PK05 Mandor 0.0270 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.10.20 MEMASANG 1 M' PIPA GALVANIS DIAMETER 0,75"
BAHAN :
Pipa Galvanis 0,75" 1.0000 m' - -
Perlengkapan 0.3500 hrg pipa - -
Jumlah Bahan -
UPAH :
Pekerja 0.0540 Oh - -
Tukang Batu 0.0900 Oh - -
Kepala Tukang 0.0090 Oh - -
P PK05 Mandor 0.0270 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.10.21 MEMASANG 1 M' PIPA GALVANIS DIAMETER 1"
BAHAN :
Pipa Galvanis 1" 1.0000 1,2 m' - -
Perlengkapan 0.3500 hrg pipa - -
Jumlah Bahan -
UPAH :
Pekerja 0.0540 Oh - -
Tukang Batu 0.0900 Oh - -
Kepala Tukang 0.0090 Oh - -
Mandor 0.0270 Oh - -
P PK05 Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
A001 A.10.22.a MEMASANG 1 M' PIPA GALVANIS DIAMETER 1,5"
BAHAN :
Pipa Galvanis 1,5" 1.0000 1,2 m' - -
Perlengkapan 0.3500 hrg pipa - -
Jumlah Bahan -
UPAH :
Pekerja 0.1080 Oh - -
Tukang Batu 0.1800 Oh - -
Kepala Tukang 0.0180 Oh - -
Mandor 0.0054 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
A001 A.10.22 MEMASANG 1 M' PIPA GALVANIS DIAMETER 2"
BAHAN :
Pipa Galvanis 2" 1.0000 1,2 m' - -
Perlengkapan 0.3500 hrg pipa - -
Jumlah Bahan -
UPAH :
Pekerja 0.1080 Oh - -
Tukang Batu 0.1800 Oh - -
Kepala Tukang 0.0180 Oh - -
Mandor 0.0054 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
A.10.23 MEMASANG 1 M' PIPA GALVANIS DIAMETER 3"
BAHAN :
A001 Pipa Galvanis 3" 1.0000 1,2 m' - -
Perlengkapan 0.3500 hrg pipa - -
Jumlah Bahan -
UPAH :
Pekerja 0.1080 Oh - -
Tukang Batu 0.1800 Oh - -
Kepala Tukang 0.0180 Oh - -
Mandor 0.0054 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
P PK05 Dibulatkan -
A.10.24 MEMASANG 1 M' PIPA GALVANIS DIAMETER 4"
BAHAN :
Pipa Galvanis 4" 1.0000 1,2 m' - -
Perlengkapan 0.3500 hrg pipa - -
Page 43 of 707
Analisa Satuan Pekerjaan
A001 Jumlah Bahan -
UPAH :
Pekerja 0.1350 Oh - -
Tukang Batu 0.2250 Oh - -
Kepala Tukang 0.0225 Oh - -
Mandor 0.0068 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
A.10.25 MEMASANG 1 M' PIPA PVC TIPE AW DIAMETER 0,5"
P PK05 BAHAN :
Pipa PVC AW 0,5" 1.0000 m' - -
Perlengkapan 0.3500 hrg pipa - -
Jumlah Bahan -
UPAH :
A001 Pekerja 0.0360 Oh - -
Tukang Batu 0.0600 Oh - -
Kepala Tukang 0.0060 Oh - -
Mandor 0.0018 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
A.10.26 MEMASANG 1 M' PIPA PVC TIPE AW DIAMETER 0,75"
BAHAN :
P PK05 Pipa PVC AW 0,75" 1.0000 m' - -
Perlengkapan 0.3500 hrg pipa - -
Jumlah Bahan -
UPAH :
Pekerja 0.0360 Oh - -
A001 Tukang Batu 0.0600 Oh - -
Kepala Tukang 0.0060 Oh - -
Mandor 0.0018 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
A.10.27 MEMASANG 1 M' PIPA PVC TIPE AW DIAMETER 1"
BAHAN :
P PK05 Pipa PVC AW 1" 1.0000 m' - -
Perlengkapan 0.3500 hrg pipa - -
Jumlah Bahan -
UPAH :
Pekerja 0.0360 Oh - -
A001 Tukang Batu 0.0600 Oh - -
Kepala Tukang 0.0060 Oh - -
Mandor 0.0018 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
A.10.28 MEMASANG 1 M' PIPA PVC TIPE AW DIAMETER 1,5"
BAHAN :
Pipa PVC AW 1,5" 1.0000 m' - -
Perlengkapan 0.3500 hrg pipa - -
Jumlah Bahan -
P PK05 UPAH :
Pekerja 0.0360 Oh - -
Tukang Batu 0.0600 Oh - -
Kepala Tukang 0.0060 Oh - -
Mandor 0.0018 Oh - -
A001 Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
A.10.29 MEMASANG 1 M' PIPA PVC TIPE AW DIAMETER 2"
BAHAN :
Pipa PVC AW 2" 1.0000 m' - -
Perlengkapan 0.3500 hrg pipa - -
Jumlah Bahan -
P PK05 UPAH :
Pekerja 0.0540 Oh - -
Tukang Batu 0.0900 Oh - -
Kepala Tukang 0.0090 Oh - -
Mandor 0.0027 Oh - -
A001 Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
A.10.30 MEMASANG 1 M' PIPA PVC TIPE AW DIAMETER 2,5"
BAHAN :
Pipa PVC AW 2,5" 1.0000 m' - -
Perlengkapan 0.3500 hrg pipa - -
Jumlah Bahan -
UPAH :
Pekerja 0.0360 Oh - -
Tukang Batu 0.0600 Oh - -
P PK05 Kepala Tukang 0.0060 Oh - -
Mandor 0.0018 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
A.10.31 MEMASANG 1 M' PIPA PVC TIPE AW DIAMETER 3"
BAHAN :
Pipa PVC AW 3" 1.0000 m' - -
Perlengkapan 0.3500 hrg pipa - -
Jumlah Bahan -
UPAH :
Pekerja 0.0810 Oh - -
Tukang Batu 0.1350 Oh - -
P PK05 Kepala Tukang 0.0135 Oh - -
Mandor 0.0041 Oh - -
Page 44 of 707
Analisa Satuan Pekerjaan
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
A.10.32 MEMASANG 1 M' PIPA PVC TIPE AW DIAMETER 4"
BAHAN :
Pipa PVC AW 4" 1.0000 m' - -
Perlengkapan 0.3500 hrg pipa - -
Jumlah Bahan -
UPAH :
Pekerja 0.0810 Oh - -
Tukang Batu 0.1350 Oh - -
Kepala Tukang 0.0135 Oh - -
Mandor 0.0041 Oh - -
P PK05 Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
A001 A.10.33 MEMASANG 1 BH BAK CUCI PIRING STAILES STEEL
BAHAN :
Bak Cuci Stainless Steel 1.0000 bh - -
Water Drain + asesories 1.0000 Set - -
Jumlah Bahan -
UPAH :
Pekerja 0.0300 Oh - -
Tukang Batu 0.3000 Oh - -
Kepala Tukang 0.0300 Oh - -
Mandor 0.0015 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
A.10.35 MEMASANG 1 BH KRAN DIAMETER 0,75' ATAU 0,5"
BAHAN :
Kran Air 1.0000 bh - -
A001 Seal tape 0.0250 bh - -
Jumlah Bahan -
UPAH :
Pekerja 0.0100 Oh - -
Tukang Batu - Oh - -
Kepala Tukang 0.0010 Oh - -
Mandor 0.0005 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
A.10.36 MEMASANG 1 BH FLOOR DRAIN
P PK05 BAHAN :
Floor Drain 1.0000 bh - -
Jumlah Bahan -
UPAH :
A001 Pekerja 0.0100 Oh - -
Tukang Batu - Oh - -
Kepala Tukang 0.0010 Oh - -
Mandor 0.0005 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
A.10.37 1 UNIT SEPTICTANK 4,8 X 2,1 X 2,4 M + REMBESANNYA
Galian tanah 17.1360 m³ - -
Pasir Urug 0.5600 m³ - -
Lantai kerja 3.7500 m³ - -
Pas. bata 1 PC : 2 PS + Plesteran 60.0000 m² - -
Plasteran Dinding 60.0000 m² - -
P PK05 Plat beton penutup 0.5000 m³ - -
Pipa PVC AW 4" 9.0000 m' - -
Pipa GIP 2" 2.0000 m1 - -
Galian tanah untuk rembesan 5.6250 m³ - -
Pas. injuk 20.0000 m² - -
A001 Urugan kerikil 3,5 cm 2.5000 m³ - -
Pipa PVC AW 4" 10.0000 m' - -
Urugan kembali perataan tanah 1.8750 m³ - -
Jumlah Bahan -
UPAH :
Pekerja Oh
Tukang Batu Oh
Kepala Tukang Oh
Mandor Oh
Jumlah -
Jumlah -
Dibulatkan -
A.11.01 1 M2 PASANG RANGKA ATAP BAJA RINGAN
BAHAN :
A001 Baja Ringan 1.1000 m2 - -
Jumlah Bahan -
UPAH :
Pekerja 0.0600 Oh - -
Tukang Besi 0.0060 Oh - -
Kepala Tukang 0.0060 Oh - -
Mandor 0.0003 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
A.11.09 1 M2 PASANG PINTU ALUMINIUM
BAHAN :
Pintu Alluminium 1.0000 m2 - -
Jumlah Bahan -
P PK05 UPAH :
Pekerja 1.0500 Oh - -
Tukang Besi 1.0500 Oh - -
Page 45 of 707
Analisa Satuan Pekerjaan
Kepala Tukang 0.1050 Oh - -
Mandor 0.0052 Oh - -
A001 Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
A.11.12 1 M2 PASANG TERALIS BESI
BAHAN :
Besi Plat 2x3 1.0000 m2 - -
Jumlah Bahan -
UPAH :
Pekerja 1.2000 Oh - -
Tukang Kayu 1.2000 Oh - -
P PK05 Kepala Tukang 0.0120 Oh - -
Mandor 0.0006 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
A.11.18 1 M2 PASANG TALANG DATAR, SENG BJLS 30
LL64 BAHAN :
BT64 Seng Plat 3 x 6 bjls 28 0.5000 lbr - -
BT18 Paku Biasa Tripleks 0.0150 kg - -
Kayu Kelas II Papan 0.0096 m3 - -
LL65 Meni Besi/Flincote 0.2500 kg - -
LL66 Jumlah Bahan -
BT67 UPAH :
Pekerja 0.1500 Oh - -
Tukang Kayu 0.4000 Oh - -
Kepala Tukang 0.0250 Oh - -
Mandor 0.0013 Oh - -
A080 Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
A.11.19 1 M2 PASANG TALANG MIRING, SENG BJLS 28
BAHAN :
BT64 Seng Plat 3 x 6 bjls 28 0.5000 lbr - -
BT18 Paku Biasa Tripleks 0.0150 kg - -
Kayu Kelas II Papan 0.0190 m3 - -
Meni Besi/Flincote 0.3000 kg - -
Jumlah Bahan -
BT67 UPAH :
Pekerja 0.0400 Oh - -
Tukang Kayu 0.4000 Oh - -
Kepala Tukang 0.0250 Oh - -
Mandor 0.0013 Oh - -
A081 Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
A.11.20 1 M2 PASANG TALANG 1/2 LINGKARAN D-10 CM, SENG BJLS 28
BAHAN :
BT64 Seng Plat 3 x 6 bjls 28 0.3000 lbr - -
BT18 Paku Biasa Tripleks 0.1000 kg - -
Kayu Kelas II Papan 0.0190 m3 - -
Besi Strip 0.5000 kg - -
Jumlah Bahan -
BT67 UPAH :
Pekerja 0.1500 Oh - -
Tukang Kayu 0.2500 Oh - -
Kepala Tukang 0.0250 Oh - -
Mandor 0.0013 Oh - -
A082 Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
A.11.22 1 M2 PEK. RESIDU/TEER RANGKA ATAP/KUDA-KUDA/GORDING
BAHAN :
Teer/residu 0.0300 ltr - -
Jumlah Bahan -
UPAH :
A001 Pekerja 0.0080 Oh - -
Tukang Kayu 0.0060 Oh - -
LL99 Kepala Tukang 0.0120 Oh - -
BN02 Mandor 0.0060 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
LLL01 Dibulatkan -
P PK05 A.12.02 1 BUAH PASANG KUNCI TANAM BIASA
BAHAN :
Kunci Tanam biasa 1.0000 bh - -
Jumlah Bahan -
UPAH :
A001 Pekerja 0.0100 Oh - -
Tukang Kayu 0.5000 Oh - -
Kepala Tukang 0.0100 Oh - -
Mandor 0.0050 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
P PK05 A.12.03 1 BUAH PASANG KUNCI TANAM KAMAR MANDI
BAHAN :
Kunci Tanam Kamar Mandi 1.0000 bh - -
Jumlah Bahan -
UPAH :
A001 Pekerja 0.0050 Oh - -
Tukang Kayu 0.5000 Oh - -
Kepala Tukang 0.0050 Oh - -
Mandor 0.0025 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Page 46 of 707
Analisa Satuan Pekerjaan
Dibulatkan -
P PK05 A.12.04 1 BUAH PASANG KUNCI BULAT
BAHAN :
Kunci Bulat 1.0000 bh - -
Jumlah Bahan -
UPAH :
A001 Pekerja 0.0050 Oh - -
Tukang Kayu 0.5000 Oh - -
Kepala Tukang 0.0050 Oh - -
Mandor 0.0003 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
P PK05 A.12.05 1 BUAH PASANG ENGSEL PINTU
BAHAN :
Engsel Pintu 1.0000 bh - -
Jumlah Bahan -
UPAH :
A001 Pekerja 0.0150 Oh - -
Tukang Kayu 0.1500 Oh - -
Kepala Tukang 0.0150 Oh - -
Mandor 0.0008 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
P PK05 A.12.06 1 BUAH PASANG ENGSEL JENDELA KUPU-KUPU
BAHAN :
Engsel Jendela 1.0000 bh - -
Jumlah Bahan -
UPAH :
A001 Pekerja 0.0100 Oh - -
Tukang Kayu 0.1000 Oh - -
Kepala Tukang 0.0100 Oh - -
Mandor 0.0005 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
P PK05 A.12.09 1 BUAH PASANG KAIT ANGIN
BAHAN :
Kait Angin 1.0000 bh - -
Jumlah Bahan -
UPAH :
A001 Pekerja 0.0150 Oh - -
Tukang Kayu 0.1500 Oh - -
Kepala Tukang 0.0150 Oh - -
Mandor 0.0008 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
P PK05 A.12.10 1 BUAH PASANG SLOOT TANAM
BAHAN :
Sloot Tanam 1.0000 bh - -
Jumlah Bahan -
UPAH :
A001 Pekerja 0.0200 Oh - -
Tukang Kayu 0.2000 Oh - -
Kepala Tukang 0.0500 Oh - -
Mandor 0.0025 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
P PK05 A.12.11 1 BUAH PASANG GRENDEL JENDELA
BAHAN :
Grendel Jendela/Spring Knob 1.0000 bh - -
Jumlah Bahan -
UPAH :
A001 Pekerja 0.0200 Oh - -
Tukang Kayu 0.2000 Oh - -
Kepala Tukang 0.0500 Oh - -
Mandor 0.0025 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
P PK05 A.12.12 1 BUAH PASANG PEGANGAN PINTU + KUNCI PINTU 2 X PUTAR
BAHAN :
Kunci Tanam 2 x Putar 1.0000 bh - -
Pegangan/Handle Pintu 1.0000 bh - -
Jumlah Bahan -
UPAH :
A001 Pekerja 0.0500 Oh - -
Tukang Kayu 0.5000 Oh - -
Kepala Tukang 0.0500 Oh - -
Mandor 0.0025 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
A.12.14 1 BUAH PASANG KUNCI PINTU 2 X PUTAR ( lever handle )
BAHAN :
P PK05 Kunci Pintu 2 x Putar ( lever handle ) 1.0000 bh - -
Jumlah Bahan -
UPAH :
Pekerja 0.0100 Oh - -
Tukang Kayu 0.5000 Oh - -
A001 Kepala Tukang 0.0600 Oh - -
Mandor 0.0030 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Page 47 of 707
Analisa Satuan Pekerjaan
Dibulatkan -
A.12.17 1 M2 PASANG KACA, TEBAL 5 MM
BAHAN :
Kaca Polos 5 mm 1.1000 m2 - -
Jumlah Bahan -
UPAH :
Pekerja 0.0150 Oh - -
Tukang Kayu 0.1500 Oh - -
Kepala Tukang 0.0150 Oh - -
P PK05 Mandor 0.0008 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A.12.28 1 KG PEK. KONSTRUKSI BESI SIKU
BAHAN :
P PK05 Besi Siku 50.50.5 panjang 6 m 1.0000 kg - -
Jumlah Bahan -
UPAH :
Pekerja 0.0600 Oh - -
A001 Tukang Besi 0.0040 org - -
Kepala tukang besi profil 0.0010 org - -
Mandor 0.0002 org - -
Peralatan ( Alat las, dll) 0.1250 lot - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
A.12.34 1 M1 PEK. PAGAR BELAKANG / SAMPING KAWAT DURI
Galian Tanah 0.4500 m³ - -
P PK05 Urugan Pasir 10 cm' 0.0080 m³ - -
Pekerja 0.0750 Oh - -
Tukang Batu 0.0250 Oh - -
Jumlah -
Dibulatkan -
Page 48 of 707
Analisa Satuan Pekerjaan
BAHAN :
P PK05 Ubin Keramik 15 x 20 cm 35.0000 bh - -
Semen PC (50 kg) 8.4000 kg - -
Pasir Pasang 0.0420 m3 - -
Semen Warna 0.5000 kg - -
Jumlah Bahan -
A001 UPAH :
Pekerja 0.7000 Oh - -
Tukang Batu 0.3500 Oh - -
Kepala Tukang 0.0350 Oh - -
Mandor 0.0030 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
A.13.47 1 M2 PASANG LANTAI KERAMIK 30 X 30 CM
BAHAN :
P PK05 Keramik 30 x 30 cm 11.8700 bh - -
Semen PC (50 kg) 14.1500 kg - -
Pasir Pasang 0.0390 m3 - -
Semen Warna 2.0000 kg - -
Jumlah Bahan -
A001 UPAH :
Pekerja 0.7000 Oh - -
Tukang Batu 0.3500 Oh - -
Kepala Tukang 0.0350 Oh - -
Mandor 0.0030 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
A.13.48 1 M2 PASANG LANTAI KERAMIK 30 X 30 CM ANTISLIP
BAHAN :
P PK05 Ubin Keramik 30 x 30 cm Antislip 11.8700 bh - -
Semen PC (50 kg) 14.1500 kg - -
Pasir Pasang 0.0390 m3 - -
Semen Warna 2.0000 kg - -
Jumlah Bahan -
A001 UPAH :
Pekerja 0.7000 Oh - -
Tukang Batu 0.3500 Oh - -
Kepala Tukang 0.0350 Oh - -
Mandor 0.0030 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
A.13.58 1 M2 PASANG DINDING PORSELEN 11 X 11 CM, PUTIH
BAHAN :
Keramik Porselen 11 x 11 cm 83.0000 bh - -
Semen PC (50 kg) 8.4000 kg - -
Pasir Pasang 0.0180 m3 - -
Semen Warna 0.5000 kg - -
Jumlah Bahan -
UPAH :
P PK05 Pekerja 0.7000 Oh - -
Tukang Batu 0.3500 Oh - -
Kepala Tukang 0.0350 Oh - -
Mandor 0.0030 Oh - -
Jumlah Pekerja -
A001 Jumlah Bahan + Pekerja -
Dibulatkan -
A.13.59 1 M2 PASANG DINDING PORSELEN 11 X 11 CM, WARNA
BAHAN :
Keramik Porselen 11 x 11 cm, Warna 83.0000 bh - -
Semen PC (50 kg) 8.4000 kg - -
Pasir Pasang 0.0180 m3 - -
Semen Warna 0.5000 kg - -
Jumlah Bahan -
UPAH :
P PK05 Pekerja 0.7000 Oh - -
Tukang Batu 0.3500 Oh - -
Kepala Tukang 0.0350 Oh - -
Mandor 0.0030 Oh - -
Jumlah Pekerja -
A001 Jumlah Bahan + Pekerja -
Dibulatkan -
A.13.62 1 M2 PASANG DINDING PORSELEN 10 X 20 CM, WARNA
BAHAN :
Keramik Porselen 10 x 20 cm, Warna 2.6500 bh - -
Semen PC (50 kg) 1.1400 kg - -
Pasir Pasang 0.0300 m3 - -
Semen Warna 0.1000 kg - -
P PK05 Jumlah Bahan -
UPAH :
Pekerja 0.0900 Oh - -
Tukang Batu 0.0900 Oh - -
Kepala Tukang 0.0090 Oh - -
A001 Mandor 0.0090 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
A.13.63 1 M2 PASANG DINDING PORSELEN 20 X 20 CM, WARNA
BAHAN :
Keramik Porselen 20 x 20 cm, Warna 26.5000 bh - -
Semen Abu-abu 8.4000 kg - -
Pasir Pasang 0.0180 m3 - -
Semen Warna 0.5000 kg - -
P PK05 Jumlah Bahan -
UPAH :
Page 49 of 707
Analisa Satuan Pekerjaan
Pekerja 0.6000 Oh - -
Tukang Batu 0.4500 Oh - -
Kepala Tukang 0.0450 Oh - -
A001 Mandor 0.0300 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
A.13.66 1 M2 PASANG DINDING KERAMIK 10 X 20 CM,
BAHAN :
Keramik 10 x 20 cm 53.0000 bh - -
Semen Abu-abu 8.1900 kg - -
Pasir Pasang 0.0450 m3 - -
Semen Warna 2.7500 kg - -
P PK05 Jumlah Bahan -
UPAH :
Pekerja 0.7000 Oh - -
Tukang Batu 0.3500 Oh - -
Kepala Tukang 0.0350 Oh - -
A001 Mandor 0.0350 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
A.13.68 1 M2 PASANG DINDING KERAMIK 20 X 20 CM,
BAHAN :
Keramik 20 x 20 cm 26.5000 bh - -
Semen Abu-abu 10.4000 kg - -
Pasir Pasang 0.0450 m3 - -
Semen Warna 1.6500 kg - -
P PK05 Jumlah Bahan -
UPAH :
Pekerja 0.7000 Oh - -
Tukang Batu 0.3500 Oh - -
Kepala Tukang 0.0350 Oh - -
A001 Mandor 0.0350 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
A.13.69 1 M2 PASANG DINDING KERAMIK 10 X 20 CM,
BAHAN :
Keramik 10 x 20 cm 2.6500 bh - -
Semen Abu-abu 1.1400 kg - -
Pasir Pasang 0.0300 m3 - -
Semen Warna 0.1000 kg - -
P PK05 Jumlah Bahan -
UPAH :
Pekerja 0.0900 Oh - -
Tukang Batu 0.0900 Oh - -
Kepala Tukang 0.0090 Oh - -
A001 Mandor 0.0090 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
A.13.74 1 M2 PASANG DINDING BATU TEMPEL
P PK05 BAHAN :
Batu Tempel 1.0500 m2 - -
Semen Abu-abu 11.7500 kg - -
Pasir Pasang 0.0350 m3 - -
Jumlah Bahan -
A001 UPAH :
Pekerja 0.9000 Oh - -
Tukang Batu 0.4500 Oh - -
Kepala Tukang 0.0450 Oh - -
Mandor 0.0450 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
A001 A.13.75 1 M2 PASANG LANTAI KERAMIK 30 X 30 CM DN PUTIH POLOS
BAHAN :
Lantai Keramik 30 x 30 cm 11.8700 bh - -
Semen PC (50 kg) 10.0000 kg - -
Pasir Pasang 0.0390 m3 - -
Semen Warna 1.5000 kg - -
Jumlah Bahan -
UPAH :
Pekerja 0.2600 Oh - -
Tukang Batu 0.1300 Oh - -
Kepala Tukang 0.0130 Oh - -
Mandor 0.0130 Oh - -
P PK05 Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
A001 A.13.76 1 M2 PASANG LANTAI KERAMIK 30 X 30 CM WARNA / CORAK / ANTI SLIP
BAHAN :
Lantai Keramik 30 x 30 cm Warna/Corak/Anti Slip 11.8700 bh - -
Semen PC (50 kg) 14.1500 kg - -
Pasir Pasang 0.0390 m3 - -
Semen Warna 2.0000 kg - -
Jumlah Bahan -
UPAH :
Pekerja 0.7000 Oh - -
Tukang Batu 0.3500 Oh - -
Kepala Tukang 0.0350 Oh - -
Mandor 0.0030 Oh - -
P PK05 Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
A001 A.13.77 1 M2 PASANG LANTAI KERAMIK 40 X 40 CM
Page 50 of 707
Analisa Satuan Pekerjaan
BAHAN :
Keramik 40 x 40 cm 6.6300 bh - -
Semen PC (50 kg) 9.8000 kg - -
Pasir Pasang 0.0450 m3 - -
Semen Warna 1.3000 kg - -
Jumlah Bahan -
UPAH :
Pekerja 0.2500 Oh - -
Tukang Batu 0.1250 Oh - -
Kepala Tukang 0.0130 Oh - -
Mandor 0.0130 Oh - -
P PK05 Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
A001 A.13.78 1 M2 PASANG DINDING KERAMIK 20 X 25 CM,
BAHAN :
Keramik 20 x 25 cm 20.0000 bh - -
Semen PC (50 kg) 8.4000 kg - -
Pasir Pasang 0.0180 m3 - -
Semen Warna 0.5000 kg - -
Jumlah Bahan -
UPAH :
Pekerja 0.7000 Oh - -
Tukang Batu 0.3500 Oh - -
Kepala Tukang 0.0350 Oh - -
Mandor 0.0030 Oh - -
P PK05 Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
P PK05 A.13.83 1 M2 PASANGAN PAVING BLOCK WARNA (6 CM)
BAHAN :
Paving Block Warna 6 cm 1.0100 m2 - -
Pasir Beton 0.1000 m³ - -
Jumlah Bahan -
A001 UPAH :
Pekerja 0.2500 org - -
Tukang Batu 0.5000 org - -
Kepala Tukang Batu 0.0250 org - -
Mandor 0.0030 org - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Jumlah -
Dibulatkan -
A.13.84 1 M2 PASANGAN PAVING BLOCK WARNA (8 CM)
BAHAN :
P PK05 Paving Block Warna 8 cm 1.0100 m2 - -
Pasir Beton 0.1000 m³ - -
Jumlah Bahan -
UPAH :
Pekerja 0.2500 org - -
A001 Tukang Batu 0.5000 org - -
Kepala Tukang Batu 0.0250 org - -
Mandor 0.0030 org - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Jumlah -
Dibulatkan -
A.13.86 1 M2 PASANGAN PAVING BLOCK NATURAL (6 CM)
BAHAN :
Paving Block Natural 6 cm 1.0100 m² - -
Pasir Beton 0.1000 m³ - -
Jumlah Bahan -
UPAH :
Pekerja 0.2500 org - -
P PK05 Tukang Batu 0.5000 org - -
Kepala Tukang Batu 0.0250 org - -
Mandor 0.0030 org - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Jumlah -
Dibulatkan -
A.13.87 1 M2 PASANGAN PAVING BLOCK NATURAL (8 CM)
BAHAN :
Paving Block Natural 8 cm 1.0100 m² - -
Pasir Beton 0.1000 m³ - -
Jumlah Bahan -
UPAH :
Pekerja 0.2500 org - -
Tukang Batu 0.5000 org - -
P PK05 Kepala Tukang Batu 0.0250 org - -
Mandor 0.0030 org - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Jumlah -
Dibulatkan -
A.14.12 1 M2 MENI KAYU
BAHAN :
Cat Meni Kayu 0.3500 Kg - -
Jumlah Bahan -
P PK05 UPAH :
Pekerja 0.1000 Oh - -
Tukang Cat - Oh - -
Kepala Tukang - Oh - -
Mandor 0.0060 Oh - -
A001 Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
Page 51 of 707
Analisa Satuan Pekerjaan
A.14.13 1 M2 MENI BESI
BAHAN :
Cat Meni BESI 0.3500 Kg - -
Jumlah Bahan -
P PK05 UPAH :
Pekerja 0.1000 Oh - -
Tukang Cat - Oh - -
Kepala Tukang - Oh - -
Mandor 0.0060 Oh - -
A001 Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
A.14.14 1 M2 PLAMUR TEMBOK
BAHAN :
Plamir Tembok 0.1000 ltr - -
Jumlah Bahan -
UPAH :
P PK05 Pekerja 0.0200 Oh - -
Tukang Cat 0.0630 Oh - -
Kepala Tukang 0.0063 Oh - -
Mandor 0.0025 Oh - -
Jumlah Pekerja -
A001 Jumlah Bahan + Pekerja -
Dibulatkan -
A.14.25 1 M2 PENGECATAN DINDING SEKELAS VINILEX (3x)
BAHAN :
P PK05 Cat Tembok 0.3600 kg - -
Plamir Tembok 0.1000 kg - -
Kuas Roll 0.0100 bh - -
Ampelas 0.5000 lbr - -
Jumlah Bahan -
A001 UPAH :
Pekerja 0.0200 org - -
Tukang Cat 0.0630 org - -
Kepala Tukang cat 0.0063 org - -
Mandor 0.0030 org - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Jumlah -
Dibulatkan -
P PK05 A.14.26 1 M2 PENGECATAN PLAFOND SEKELAS VINILEX (3x)
BAHAN :
Cat Tembok 0.3600 kg - -
Plamir Tembok 0.1000 kg - -
Kuas Roll 0.0100 bh - -
A001 Ampelas 0.5000 lbr - -
Jumlah Bahan -
UPAH :
Pekerja 0.0200 org - -
Tukang Cat 0.0630 org - -
Kepala Tukang cat 0.0063 org - -
Mandor 0.0030 org - -
Jumlah Pekerja -
P PK05 Jumlah Bahan + Pekerja -
Jumlah -
Dibulatkan -
A.14.30 1 M2 PENGECATAN BIDANG KAYU (3X) BERIKUT MENI
BAHAN :
Meni kayu 0.2000 kg - -
Plamir kayu 0.1500 kg - -
P PK05 Cat Kayu 0.4300 kg - -
Ampelas 0.2000 lbr - -
Minyak cat / Thinner 0.0300 ltr - -
Kwas 0.0100 bh - -
Jumlah Bahan -
A001 UPAH :
Pekerja 0.0700 org - -
Tukang Cat 0.0090 org - -
Kepala Tukang cat 0.0060 org - -
Mandor 0.0030 org - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Jumlah -
Dibulatkan -
A.14.30'' 1 M2 PENGECATAN BIDANG DINDING ( PLINT )
BAHAN :
Cat Kayu / Besi / Cat minyak 0.2000 kg 0 -
Ampelas 0.4000 lbr 0 -
Minyak Thinner 0.1500 ltr 0 -
Kwas 0.0500 bh 0 -
Jumlah Bahan -
UPAH :
Pekerja 0.2000 org 0 -
Tukang Cat 0.0600 org 0 -
Kepala Tukang cat 0.0300 org 0 -
Mandor 0.0100 org 0 -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Jumlah -
Dibulatkan -
A.14.31 1 M2 PENGECATAN BESI (3X)
BAHAN :
P PK05 Meni Besi/Flincote 0.1670 kg - -
Cat Besi 0.2000 kg - -
Ampelas 0.4000 lbr - -
Minyak cat / Thinner 0.1500 ltr - -
Page 52 of 707
Analisa Satuan Pekerjaan
Kwas 0.0500 bh - -
A001 Jumlah Bahan -
UPAH :
Pekerja 0.2000 org - -
Tukang Cat 0.0600 org - -
Kepala Tukang cat 0.0300 org - -
Mandor 0.0100 org - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Jumlah -
P PK05 Dibulatkan -
B6 MENANAM 1 BATANG TANAMAN BERIKUT PELINDUNGNYA
Tanaman Keras 1.0000 btg - -
Bambu 1.0000 btg - -
Pekerja 0.4000 org - -
Mandor 0.0050 org - -
Jumlah -
Jumlah -
Dibulatkan -
E 13 1 M1 TIANG DIPANCANGKAN KE DALAM TANAH LUNAK
Tukang Kayu 0.0400 org - -
Kepala Tukang 0.0040 org - -
Pekerja 1.8000 org - -
Mandor 0.0430 org - -
Untuk tanah biasa dihitung = 1, 25 x analis E. 13
Untuk tanah biasa dihitung = 1, 50x analis E. 13
Untuk tanah biasa dihitung = 2, 00 x analis E. 13
Jumlah -
Jumlah -
Dibulatkan -
M.01 1 M' JEMBATAN SEMENTARA KAYU BULAT f 30 CM PANJANG 3M' ( ASUMSI LEBAR JEMBATAN 3M' & TANPA TIANG)
Kayu Bulat f 30 cm 7.5000 btg -
Paku Biasa 0.5600 kg - -
Pasak Besi f 12 mm 2.8000 kg - -
Tukang Kayu 1.2000 org - -
Kepala Tukang Kayu 0.1200 org - -
Pekerja 4.8000 org - -
Mandor 0.0120 org - -
Alat Bantu 0.0100 ls - -
Jumlah -
Jumlah -
Dibulatkan -
M.02 1 M' JEMBATAN SEMENTARA KAYU BULAT f 30 CM PANJANG 6M' ( ASUMSI LEBAR JEMBATAN 3M' & DENGAN TIANG)
Kayu Bulat f 30 cm 18.0000 btg -
Paku Biasa 1.1200 kg - -
Pasak Besi f 12 mm 5.6000 kg - -
Tukang Kayu 1.4000 org - -
Kepala Tukang Kayu 0.1400 org - -
Pekerja 5.3000 org - -
Mandor 0.0140 org - -
Alat Bantu 0.0100 ls - -
Jumlah -
Jumlah -
Dibulatkan -
M.03 1 M' JEMBATAN SEMENTARA KAYU BULAT f 30 CM PANJANG 9M' ( ASUMSI LEBAR JEMBATAN 3M' & DENGAN TIANG)
Kayu Bulat f 30 cm 28.5000 btg -
Paku Biasa 1.6800 kg - -
Pasak Besi f 12 mm 8.4000 kg - -
Tukang Kayu 1.7000 org - -
Kepala Tukang Kayu 7.0000 org - -
Pekerja 5.9000 org - -
Mandor 0.0170 org - -
Alat Bantu 0.0100 ls - -
Jumlah -
Jumlah -
Dibulatkan -
M.04 1 M' JEMBATAN SEMENTARA KAYU BULAT f 30 CM PANJANG 12M' ( ASUMSI LEBAR JEMBATAN 3M' & DENGAN TIANG)
Kayu Bulat f 30 cm 39.0000 btg -
Paku Biasa 1.6800 kg - -
Pasak Besi f 12 mm 11.2000 kg - -
Tukang Kayu 2.1000 org - -
Kepala Tukang Kayu 0.2100 org - -
Pekerja 6.3000 org - -
Mandor 0.0210 org - -
Alat Bantu 0.0100 ls - -
Jumlah -
Jumlah -
Dibulatkan -
A7.R. UPAH ANGKUTAN 1 ZAK SEMEN PC ( BID. PENGAIRAN )
Jumlah -
Jumlah -
Dibulatkan -
A6 ONGKOS ANGKUT 1 M3 TANAH ( BID. PENGAIRAN )
Sejauh 30 meter
Pekerja 0.3300 org - -
Mandor 0.0100 org -
Lebih dari 30 meter
Jumlah -
Jumlah -
Dibulatkan -
A. R 1 M2 PEK. ANTI RAYAP
BAHAN :
Bahan Anti Rayap 0.0900 Ltr - -
Alat Semprot 0.0500 lsm - -
Jumlah Bahan -
Page 53 of 707
Analisa Satuan Pekerjaan
UPAH :
Pekerja 0.0100 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A001 Dibulatkan -
A. B 1 M1 PEK. ANGKUR BESI Dia. 10 - 45 cm
BAHAN :
Besi Beton Polos Dia. 10 mm 0.2667 M1 - -
Jumlah Bahan -
UPAH :
Pekerja 0.0100 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
A. B 1 M2 PEKERJAAN SALURAN AIR PASANGAN BT BATA ad 1 : 4
BAHAN :
Bata Merah Bakar Kelas I 70.0000 bh - -
Semen PC (50 kg) 18.9500 kg - -
Pasir Pasang 0.0430 m3 -
Jumlah Bahan -
UPAH :
Pekerja 0.3200 Oh - -
Tukang Batu 0.1000 Oh - -
Kepala Tukang 0.0100 Oh -
Mandor 0.0050 Oh -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
L. 01. 01 1 M1 PAS. INSTALASI LISTRIK KABEL UTAMA 3x2,5 NYM
BAHAN :
Kabel 3x2,5mm NYM 1.0000 m' - -
Pipa konduit dia 5/8 inch 1.0000 m' - -
Klem kabel 3.0000 bh - -
Isolasi 0.0500 bh - -
Jumlah Bahan -
UPAH :
Tukang 0.1600 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
L. 01. 02 1 TITIK INSTALASI TITIK LAMPU 2x2,5 NYM
BAHAN :
Kabel 2x2,5mm NYM 3.5000 m' - -
Pipa konduit dia 5/8 inch 4.0000 m' - -
Klem kabel 16.0000 bh - -
Isolasi 0.0500 bh - -
Tedoos 1.0000 bh -
Jumlah Bahan -
UPAH :
Tukang 0.1600 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
L. 01. 03 1 Titik Pas. Instalasi Titik Saklar Tunggal 2x2,5 NYM
BAHAN :
Saklar Tunggal 1.0000 bh - -
Kabel 2x2,5mm NYM 2.5000 m' - -
Pipa konduit dia 5/8 inch 4.0000 m' - -
Isolasi 0.0500 bh - -
Inbouwdoos 1.0000 bh - -
Jumlah Bahan -
UPAH :
Tukang 0.1600 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
L. 01. 04 1 Titik Instalasi Titik Saklar Double 3x2,5 NYM
BAHAN :
Saklar Double 1.0000 bh - -
Kabel 3x2,5mm NYM 1.5000 m' - -
Pipa konduit dia 5/8 inch 4.0000 m' - -
Isolasi 0.0500 bh - -
Inbouwdoos 1.0000 bh - -
Jumlah Bahan -
UPAH :
Tukang 0.1600 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
L. 01. 05 1 Titik Pas. Instalasi Titik Stop Kontak 3x2,5 NYM
BAHAN :
Stop Kontak 1.0000 bh -
Kabel 3x2,5mm NYM 1.5000 m' - -
Pipa konduit dia 5/8 inch 4.0000 m' - -
Isolasi 0.0500 bh - -
Inbouwdoos 1.0000 bh - -
Jumlah Bahan -
UPAH :
Tukang 0.1600 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
L. 01. 06 1 Titik Pas. Instalasi Lampu Pijar
BAHAN :
Lampu Pijar 1.0000 bh - -
Kabel 1x2,5mm NYM 6.5000 m' - -
Pipa konduit dia 5/8 inch 6.0000 m' - -
Page 54 of 707
Analisa Satuan Pekerjaan
Isolasi 0.0500 bh - -
Klem kabel 3.0000 bh - -
Tedoos 1.0000 bh -
Jumlah Bahan -
UPAH :
Tukang 0.1600 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
L. 01. 07 1 Titik Pas. Instalasi Lampu TL 2x40 Watt + fitting
BAHAN :
Lampu TL 2x40 Watt + fitting 1.0000 bh - -
Kabel 1x2,5mm NYM 4.5000 m' - -
Pipa konduit dia 5/8 inch 4.0000 m' - -
Isolasi 0.0500 bh - -
Klem kabel 3.0000 bh - -
Tedoos 1.0000 bh -
Jumlah Bahan -
UPAH :
Tukang 0.1600 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
L. 01. 08 1 Titik Pas. MCB + Box Sekring
BAHAN :
MCB 4.0000 bh - -
Kabel 1x2,5mm NYM 4.5000 m' - -
Pipa konduit dia 5/8 inch 10.0000 m' - -
Isolasi 0.0500 bh - -
Box Sekring 1.0000 bh - -
Jumlah Bahan -
UPAH :
Tukang 0.1600 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
L. 01. 09 1 M1 Pas. Kabel Antar Bangunan 3x4mm NYY
BAHAN :
Kabel 3x4mm NYY 10.0000 m' - -
Isolasi 0.0500 bh - -
Jumlah Bahan -
UPAH :
Tukang 0.8000 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
L. 01. 10 1 Bh pasang Panel Box Utama +MCB
BAHAN :
Panel Box Utama 1.0000 bh - -
MCB 6.0000 bh - -
Kabel 3x2,5mm NYM 5.0000 m' - -
Isolasi 0.0500 bh - -
Jumlah Bahan -
UPAH :
Tukang 0.1600 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
S.D.U 1 M' PAS. SALURAN DRAINASE UTAMA
BAHAN :
Batu kali 0.5000 m3 - -
Plesteran 3.0000 m² - -
Kabel 3x2,5mm NYM 5.0000 m' - -
Isolasi 0.0500 bh - -
Jumlah Bahan -
UPAH :
Tukang 0.1600 Oh - -
Pekerja 0.2500 Oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
A.02.23 1 M2 PASANG GEBALAN RUMPUT
BAHAN :
LL42 Lempengan Rumput 1.0000 m² - -
Pupuk Kandang 1.0000 ls - -
Tanah Urug (Tebal 20 cm) 0.2000 m3 - -
Jumlah Bahan -
UPAH :
P PK02 Upah Pasang 1.0000 org - -
P PK19 Mandor 0.0100 org - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A052 Dibulatkan -
A.01.P.01 1 BH TANAM POHON PELINDUNG
BAHAN :
LL42 Pohon Pelindung 1.0000 btg - -
Pupuk kandang 1.0000 ls - -
Jumlah Bahan -
UPAH :
P PK02 Upah Tanam 1.0000 org - -
P PK19 Mandor 0.0100 org - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A052 Dibulatkan -
A.01.P.02 1 M2 PEMBUATAN TAMAN
BAHAN :
LL42 Pembentukan Lahan Taman 1.0000 Unit - -
Page 55 of 707
Analisa Satuan Pekerjaan
Pupuk Kandang 1.0000 ls - -
Pohon Perdu/Bunga dll 1.0000 btg - -
Jumlah Bahan -
UPAH :
P PK02 Upah Tanam 1.0000 org - -
P PK19 Mandor 0.0100 org - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A052 Dibulatkan -
A.01.P.03 1 BH PENANAMAN POHON HIAS
BAHAN :
LL42 Pohon Hias 1.0000 btg - -
Pupuk Kandang 1.0000 krg - -
Jumlah Bahan -
UPAH :
P PK02 Upah Tanam 1.0000 org - -
P PK19 Mandor 0.0100 org - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A052 Dibulatkan -
A.01.P.04 1 M' SELASAR PENGHUBUNG BANGUNAN DENGAN ATAP
BAHAN :
LL42 Kayu Kelas II Balok (Selasar Penghubung) 0.0459 m3 - -
Seng Gelombang BJLS 0,3 3.3000 lbr - -
Seng Plat BJLS 30 lebar 90 cm 0.3000 lbr - -
Rabat Beton 0.0230 m3 - -
Paku Seng 0.0200 kg - -
Mur - Baut dia 10 mm panjang 30 cm 1.6700 bh - -
Jumlah Bahan -
UPAH :
P PK02 Pekerja 0.7500 oh - -
P PK19 Tukang Kayu 0.5000 oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A052 Dibulatkan -
A.01.P.05 1 M' PEKERJAAN PANCANG CERUCUK BAMBU
BAHAN :
LL42 Bambu 1.0000 m¹ - -
-
-
-
-
-
Jumlah Bahan -
UPAH :
P PK02 Pekerja 1.4286 oh - -
P PK19 Tukang Kayu oh -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A052 Dibulatkan -
A.01.P.06 1 BTG (pj = 45cm) PEKERJAAN PEMASANGAN ANGKUR BESI DIA. 10mm
BAHAN :
LL42 Besi Beton Polos Dia. 10 mm 0.3085 kg - -
Jumlah Bahan -
UPAH :
P PK02 Pekerja 0.1000 oh - -
P PK19 Tukang Kayu oh -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A052 Dibulatkan -
A.01.P.07 1 BH PEKERJAAN BEGHEL U POJOK (BESI POLOS 12MM) + BAUT DIA.10
BAHAN :
LL42 Beghel U Besi Polos Dia. 12mm 1.0000 bh - -
Baut Dia. 10mm 1.0000 bh - -
Jumlah Bahan -
UPAH :
P PK02 Pekerja oh - -
P PK19 Tukang Kayu 0.1000 oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A052 Dibulatkan -
A.01.P.08 1 BH PEKERJAAN BEGHEL U ALAS KUDA-KUDA (PLAT BAJA 4.40 MM) + BAUT DIA.10
BAHAN :
LL42 Beghel U Besi Plat Baja U 4.40mm 1.0000 bh - -
Baut Dia. 10mm 1.0000 bh - -
Jumlah Bahan -
UPAH :
P PK02 Pekerja oh - -
P PK19 Tukang Kayu 0.1000 oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A052 Dibulatkan -
A.01.P.08 1 BH PEKERJAAN BEGHEL U ALAS KUDA-KUDA (PLAT BAJA 4.40 MM) + BAUT DIA.10
BAHAN :
Beghel U Besi Plat Baja U 4.40mm 1.0000 bh - -
Baut Dia. 10mm 1.0000 bh - -
Jumlah Bahan -
UPAH :
Pekerja oh - -
Tukang Kayu 0.1000 oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
A.01.P.08" 2 BH PEKERJAAN BAUT DIA.10 mm Sambungan gording 5/10 atau 6/12 cm per titik
BAHAN :
Baut Dia. 10mm 2.0000 bh - -
Jumlah Bahan -
Page 56 of 707
Analisa Satuan Pekerjaan
UPAH :
P PK02 Pekerja oh - -
P PK19 Tukang Kayu 0.1000 oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A052 Dibulatkan -
A.01.P.09 1 SET PEK BEGHEL, BEGHEL U, PLAT BAJA, BAUT UNTUK 1 BH KUDA2-KUDA
BAHAN :
LL42 Beghel U (Plat Baja U 4.40mm) 2.0000 bh - -
Beghel U (Besi Polos 12mm) - bh - -
Plat Baja 4.40mm 6.0000 bh - -
Baut Dia. 10mm (25-30cm) 22.0000 bh - -
Jumlah Bahan -
UPAH :
P PK02 Pekerja oh - -
P PK19 Tukang Kayu 0.1000 oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
A052 Dibulatkan -
A.01.P.10 1 BH PEKERJAAN TIANG DAN RING BASKET BALL KOMPLIT
BAHAN :
Galian tanah 1.2000 m3 - -
Cor beton tumbuk Ad 1:3:5 0.5000 m3 - -
Tiang pipa galvanis dia 3" 1.0000 btg - -
Papan plank komplit rangka 1.0000 bh - -
Ring Basket 1.0000 Set - -
Jumlah Bahan -
UPAH :
Pekerja oh - -
Tukang 0.1000 oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
A.01.P.11 1 M1 PEKERJAAN HAND RAILING
BAHAN :
Cor beton tumbuk Ad 1:3:5 0.0120 m3 - -
Pipa Stainless Steel Dia. 1,5" 1.3200 m¹ - -
Jumlah Bahan -
UPAH :
Pekerja 1.0000 oh - -
Tukang oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
A.01.P.12 1 TITIK PEKERJAAN PANCANG CERUCUK BAMBU
BAHAN :
Bambu 0.5000 btg - -
Kayu Kelas III Papan 0.0033 m3 - -
Kawat Beton (Pengikat) 0.0150 kg - -
Jumlah Bahan -
UPAH :
Pekerja 0.1000 oh - -
Tukang oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
A.01.P.13 1 TITIK PEKERJAAN PANCANG CERUCUK KAYU DOLKEN
BAHAN :
Kayu Dolken Dia. 8 cm 0.5000 btg - -
Kayu Kelas III Papan 0.0033 m3 - -
Kawat Beton (Pengikat) 0.0150 kg - -
Jumlah Bahan -
UPAH :
Pekerja 0.1000 oh - -
Tukang oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
A.01.P.14 1 M³ PEKERJAAN BALOK GAPIT
BAHAN :
Kayu Kls. II Balok 1.1000 m³ - -
Jumlah Bahan -
UPAH :
Pekerja oh - -
Tukang 0.1000 oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
A.01.P.15 1 M³ PEKERJAAN TATAKAN GORDING/KLOS KAYU
BAHAN :
Kayu Kls. II Balok 1.1000 m³ - -
Paku Biasa 0.0500 kg - -
Jumlah Bahan -
UPAH :
Pekerja oh - -
Tukang 0.1000 oh - -
Jumlah Pekerja -
Jumlah Bahan + Pekerja -
Dibulatkan -
A.01.P.16 1 M1 PEKERJAAN PINTU GERBANG BESI
BAHAN :
Pintu Gerbang Besi 1.0000 m1 - -
Jumlah Bahan -
UPAH :
Pekerja oh - -
Tukang oh - -
Jumlah Pekerja -
Page 57 of 707
Analisa Satuan Pekerjaan
Jumlah Bahan + Pekerja -
Dibulatkan -
Bahan
1.25 Kg Paku 10 cm - -
1 Kg Lem kayu - -
Upah
18 Org/Tukang kayu - -
6 Org/Pekerja - -
0.3 Org/Mandor Rp Rp -
Alat bantu Rp -
Total Rp -
Dibulatkan -
BAHAN :
Tripleks 6 mm 2 lbr - -
Jumlah Bahan -
UPAH :
Pekerja 0.6 Oh - -
Tukang Kayu 2 Oh - -
Mandor 0.03 Oh 0 0
Jumlah Pekerja -
BAHAN :
Jumlah Bahan -
Dibulatkan -
1 M2 MENGECAT KAYU
BAHAN :
Kwas 0.05 bh 0 -
Jumlah Bahan -
UPAH :
Jumlah Pekerja -
Jumlah -
Dibulatkan -
1.0548 BAHAN :
Page 58 of 707
Analisa Satuan Pekerjaan
Keramik 60 x 60 cm 2.9300 bh - -
Jumlah Bahan -
UPAH :
Pekerja 0.2500 Oh - -
Mandor 0.0130 Oh - -
Jumlah Pekerja -
Dibulatkan -
BAHAN :
Granit 60 x 60 cm 2.9300 bh - -
Jumlah Bahan -
UPAH :
Pekerja 0.2500 Oh - -
Mandor 0.0130 Oh - -
Jumlah Pekerja -
Dibulatkan -
BAHAN :
Karpet 1.0500 m2 - -
- -
- -
Jumlah Bahan -
UPAH :
Pekerja 0.1700 Oh - -
Mandor 0.0130 Oh - -
Jumlah Pekerja -
Dibulatkan -
BAHAN :
Dina Bolt 4 bh - -
Jumlah Bahan -
UPAH :
Pekerja 0.2000 Oh - -
Mandor 0.0100 Oh - -
Jumlah Pekerja -
Dibulatkan -
Page 59 of 707
Analisa Satuan Pekerjaan
BAHAN :
Jumlah Bahan -
UPAH :
Pekerja 0.3500 Oh - -
Mandor 0.0025 Oh - -
Jumlah Pekerja -
Dibulatkan -
Page 60 of 707
Analisa Satuan Pekerjaan
0.01
1.00
71.42857142857
71
-
-
Page 61 of 707
Analisa Satuan Pekerjaan
1.2
202
0.485
1.2
163
0.52
Page 62 of 707
Analisa Satuan Pekerjaan
35.000 bh Batako
9.475 kg Semen PC
0.038 m3 Pasir Pasangan
0.617 kg Ankur besi dia 10 - 40cm
0.100 Org/Hr Tukang batu
0.010 Org/Hr Kepala tukang
0.320 Org/Hr Pekerja
0.015 Org/Hr Mandor
35.000 bh Batako
5.750 kg Semen PC
0.043 m3 Pasir Pasangan
0.617 kg Ankur besi dia 10 - 40cm
0.100 Org/Hr Tukang Batu
0.010 Org/Hr Kepala Tukang
0.320 Org/Hr Pekerja
0.015 Org/Hr Mandor
Page 63 of 707
Analisa Satuan Pekerjaan
A.06.03a 1 UNIT PEK. KUSEN PINTU P2 (L=90 cm), antar ruang kelas
BAHAN :
Pek. Kusen pintu P2 0.0410 - -
Jumlah Bahan
Dibulatkan -
A.06.10a 1 UNIT PEK. KUSEN JENDELA J3a + JALUZI (KUSEN DEPAN RKB/RBL)
BAHAN :
Kusen Jendela J3 + Jaluzi 0.08460 - Rp -
Jumlah Bahan
Dibulatkan Rp -
Kusen 0.0678
Jalusi 0.0168
0.08460
Err:520 Err:520
Err:520 Err:520
Err:520 Err:520
Err:520 Err:520
Err:520 Err:520
Err:520 Err:520
Err:520 Err:520
Err:520 Err:520
Err:520 Err:520
Err:520 Err:520
Page 64 of 707
Analisa Satuan Pekerjaan
1.89
Page 65 of 707
Analisa Satuan Pekerjaan
0.17
Page 66 of 707
Analisa Satuan Pekerjaan
0.17
Page 67 of 707
Analisa Satuan Pekerjaan
226.80
0.17
5.88
274.22
Page 68 of 707
Analisa Satuan Pekerjaan
115.33
Page 69 of 707
Analisa Satuan Pekerjaan
1,776.00
1.78
Page 70 of 707
Analisa Satuan Pekerjaan
Page 71 of 707
Analisa Satuan Pekerjaan
484.34
900.00
1,800.00
Page 72 of 707
Analisa Satuan Pekerjaan
Keramik 40 x 40 9100
Keramik 20 x 25 2150
Keramik 10 x 20 1500
Keramik 20 x 20 1,800.00
Keramik 30 x 30 5,500.00
Keramik 40 x 40 9,100.00
Keramik 20 x 25 2,150.00
Keramik 10 x 20 1,500.00
Keramik 20 x 20 1,800.00
Keramik 30 x 30 5500
Keramik 40 x 40 9100
Keramik 20 x 25 2150
Keramik 10 x 20 1500
Keramik 20 x 20 1,800.00
Keramik 40 x 40 9100
Keramik 20 x 25 2150
Keramik 10 x 20 1500
Keramik 20 x 20 1,800.00
Keramik 30 x 30 5,500.00
Keramik 40 x 40 9,100.00
Keramik 20 x 25 2,150.00
Keramik 10 x 20 1,500.00
Keramik 20 x 20 1,800.00
Keramik 30 x 30 5500
Keramik 40 x 40 9100
Keramik 20 x 25 2150
Keramik 10 x 20 1500
Keramik 20 x 20 1,800.00
Keramik 40 x 40 9100
Keramik 20 x 25 2150
Keramik 10 x 20 1500
Keramik 20 x 20 1,800.00
Keramik 30 x 30 5,500.00
Keramik 40 x 40 9,100.00
Keramik 20 x 25 2,150.00
Keramik 10 x 20 1,500.00
Keramik 20 x 20 1,800.00
Keramik 30 x 30 5500
Keramik 40 x 40 9100
Keramik 20 x 25 2150
Keramik 10 x 20 1500
Keramik 20 x 20 1,800.00
Keramik 30 x 30 5,500.00
Keramik 40 x 40 9,100.00
Keramik 20 x 25 2,150.00
Keramik 10 x 20 1,500.00
Keramik 20 x 20 1,800.00
Keramik 30 x 30 5500
Keramik 40 x 40 9100
Keramik 20 x 25 2150
Keramik 10 x 20 1500
Keramik 20 x 20 1,800.00
Keramik 30 x 30 5500
Keramik 40 x 40 9100
Keramik 20 x 25 2,150.00
Keramik 10 x 20 1500
Keramik 20 x 20 1800
Keramik 30 x 30 5500
Keramik 40 x 40 9100
Keramik 20 x 25 2150
Keramik 10 x 20 1500
Keramik 20 x 20 1,800.00
Keramik 30 x 30 5500
Keramik 40 x 40 9100
Keramik 20 x 25 2150
Keramik 10 x 20 1500
Keramik 20 x 20 1,800.00
Keramik 30 x 30 5,500.00
Keramik 40 x 40 9,100.00
Keramik 20 x 25 2,150.00
Keramik 10 x 20 1500
Keramik 20 x 20 1800
Keramik 30 x 30 5500
Keramik 40 x 40 9100
Keramik 20 x 25 2150
Keramik 10 x 20 1500
Keramik 20 x 20 1,800.00
Keramik 30 x 30 5500
Keramik 40 x 40 9100
Keramik 20 x 25 2150
Keramik 10 x 20 1500
Keramik 20 x 20 1,800.00
Keramik 30 x 30 5,500.00
Keramik 40 x 40 9,100.00
Keramik 20 x 25 2,150.00
Page 73 of 707
Analisa Satuan Pekerjaan
Keramik 10 x 20 1500
Keramik 30 x 30 5500
Keramik 40 x 40 9100
Keramik 20 x 25 2150
Keramik 10 x 20 1500
Keramik 20 x 20 1,800.00
Keramik 30 x 30 5500
Keramik 40 x 40 9100
Keramik 20 x 25 2150
Keramik 10 x 20 1500
Keramik 20 x 20 1,800.00
Keramik 30 x 30 5,500.00
Keramik 40 x 40 9,100.00
Keramik 20 x 25 2,150.00
Keramik 10 x 20 1500
Page 74 of 707
Analisa Satuan Pekerjaan
7.11
Page 75 of 707
Analisa Satuan Pekerjaan
0.27
Page 76 of 707
Analisa Satuan Pekerjaan
0.20
Page 77 of 707
Analisa Satuan Pekerjaan
Page 78 of 707
Analisa Satuan Pekerjaan
Page 79 of 707
Analisa Satuan Pekerjaan
0.111328 M3
1.876
Page 80 of 707
Analisa Satuan Pekerjaan
4.04
3.26
3.26
2
1.2
Page 81 of 707
Analisa Satuan Pekerjaan
0.0105
0.0024
0.0129
0.01419
Page 82 of 707
Analisa Satuan Pekerjaan
4.60
0.004
0.0044
Page 83 of 707
Analisa Satuan Pekerjaan
0.004
Page 84 of 707
Analisa Satuan Pekerjaan
10
0.2448
0.07
Page 85 of 707
Analisa Satuan Pekerjaan
1.44
100.8
2.16
10
20
Err:520
.
0.09 0.72 8
Page 86 of 707
Analisa Satuan Pekerjaan
112000
168000
39080 1 16044
8882334883
Page 87 of 707
Analisa Satuan Pekerjaan
Page 88 of 707
Analisa Satuan Pekerjaan
-
-
-
-
-
-
-
-
-
-
Page 89 of 707
Harga Satuan Pekerjaan
1 2 3
Page 90 of 707
Harga Satuan Pekerjaan
Page 91 of 707
Harga Satuan Pekerjaan
A.06.37 1 M2 PASANG KASO 5/7 KAYU KLS II -
A.06.38 1 M2 PASANG Rangka Atap 5/7 dan 3/4 KAYU KLS II -
A.06.39 1 M1 PASANG KONSTRUKSI NOK TEPI PAPAN 6/12 KAYU KLS II -
A.06.44 1 M2 PASANG RANGKA PLAFOND BALOK 5/7 KAYU LOKAL KLS II -
A.06.50 1 M2 PASANG LISPLANG UKURAN (3 x 30) cm, KAYU LOKAL KLS II -
A.06.60 1 M1 PASANG LIST PLAFOND PROFIL KAYU LOKAL KLS II 4/4 -
A.07.01 1 M3 MEMBUAT BETON TUMBUK, 1 Pc : 3 Ps : 5 Kr -
A.07.13 1 M3 MEMBUAT BETON BERTULANG 1 Pc : 2 Ps : 3 Kr -
A.07.25 1 Kg PEMBESIAN DENGAN BESI POLOS ATAU BESI ULIR -
A.07.28 1 m2 PASANG BEKISTING UNTUK PONDASI -
A.07.29 1 m2 PASANG BEKISTING UNTUK SLOOF -
A.07.30 1 m2 PASANG BEKISTING UNTUK KOLOM -
A.07.31 1 m2 PASANG BEKISTING UNTUK BALOK -
A.07.32 1 m2 PASANG BEKISTING UNTUK LANTAI -
A.07.33 1 m2 PASANG BEKISTING UNTUK DINDING -
A.07.47 1 M3 MEMBUAT SOFI-SOFI 12/15 (220,80 Kg Besi + Bekesting) -
DENGAN TULANGAN 4 BATANG DIA 10 BEUGEL DIA 6 JARAK 15 CM
A.07.48 1 M3 MEMBUAT RING BALOK 15/20 (145,92 Kg Besi + Bekesting) -
DENGAN TULANGAN 4 BATANG DIA 10 BEUGEL DIA 8 JARAK 15 CM
A.07.49 1 M3 MEMBUAT KOLOM 20/25 (169,67 Kg Besi + Bekesting) -
DENGAN TULANGAN 6 BATANG DIA 12 BEUGEL DIA 8 JARAK 15 CM
A.07.50 1 M3 MEMBUAT SLOOF 15/20 (274,22 Kg Besi + Bekesting) -
DENGAN TULANGAN 4 BATANG DIA 12 BEUGEL DIA 8 JARAK 15 CM
A.07.51 1 M3 PEK. BETON BERTULANG PLAT MEJA, adukan 1 : 2 : 3 -
A.07.52 1 M3 MEMBUAT KOLOM 12/15 (197 Kg Besi + Bekesting) -
DENGAN TULANGAN 4 BATANG DIA 10 BEUGEL DIA 6 JARAK 15 CM
A.07.60 1 M3 MEMBUAT KOLOM SELASAR 15/15 (181,88 Kg Besi + Bekesting) -
DENGAN TULANGAN 4 BATANG DIA 10 BEUGEL DIA 8 JARAK 15 CM
A.07.75 1 M3 PEK. PLAT BETON BERTULANG, TULANGAN 1 LAPIS DIA.10 JARAK 10 cm TEBAL 10 cm -
A.08.02 1 M2 PASANG ATAP GENTENG TANAH -
A.08.03 1 M2 PASANG ATAP SPANDEK / GALVALYUM 0,3mm -
A.08.05 1 M2 PASANG NOK BUBUNGAN GENTENG TANAH -
A.08.06 1 M2 PASANG NOK BUBUNGAN GENTENG METAL -
A.08.11 1 M2 PASANG ATAP SENG GELOMBANG BJLS 0,3 mm -
A.08.12 1 M2 PASANG ATAP ZYNCALUM 0,3 mm -
A.08.13 1 M2 PASANG ATAP GENTENG METAL 0,3 mm -
A.08.14 1 M' PASANG NOK SENG POLOS 0,3 mm -
A.08.30 1 M1 PASANG NOK TEPI SENG GELOMBANG -
A.08.31 1 M1 PASANG NOK TEPI ZYNCALUM -
A.08.32 1 M1 PASANG NOK TEPI GENTENG METAL -
A.08.33 1 M1 PASANG NOK TEPI GENTENG TANAH -
A.08.34 1 M1 PASANG NOK TEPI ATAP SPANDEK/GALVALYUM -
A.09.02 1 M2 PASANG PLAFOND TRIPLEKS , TEBAL 4 mm -
A.10.01 MEMASANG 1 BUAH KLOSET DUDUK -
A.10.02 MEMASANG 1 BUAH KLOSET JONGKOK PORSELEN -
A.10.04 MEMASANG 1 BUAH URINOIR -
A.10.05 MEMASANG 1 BUAH WASTAFEL -
A.10.07 MEMASANG 1 BUAH BAK MANDI FIBREGLASS VOLUME 0,3 M3 -
A.10.08 MEMASANG 1 BUAH BAK MANDI BATU BATA VOLUME 0,3 M3 -
A.10.16 MEMASANG 1 BUAH BAK KONTROL PASANGAN BATU BATA UKURAN (30X30) TINGGI 35 CM -
A.10.17 MEMASANG 1 BUAH BAK KONTROL PASANGAN BATU BATA UKURAN (45X45) TINGGI 50 CM -
A.10.18 MEMASANG 1 BUAH BAK KONTROL PASANGAN BATU BATA UKURAN (60X60) TINGGI 65 CM -
A.10.19 MEMASANG 1 M' PIPA GALVANIS DIAMETER 0,5" -
A.10.20 MEMASANG 1 M' PIPA GALVANIS DIAMETER 0,75" -
A.10.21 MEMASANG 1 M' PIPA GALVANIS DIAMETER 1" -
A.10.22.a MEMASANG 1 M' PIPA GALVANIS DIAMETER 1,5" -
A.10.22 MEMASANG 1 M' PIPA GALVANIS DIAMETER 2" -
A.10.23 MEMASANG 1 M' PIPA GALVANIS DIAMETER 3" -
Page 92 of 707
Harga Satuan Pekerjaan
Page 93 of 707
Harga Satuan Pekerjaan
A.10.29 MEMASANG 1 M' PIPA PVC TIPE AW DIAMETER 2" -
A.10.30 MEMASANG 1 M' PIPA PVC TIPE AW DIAMETER 2,5" -
A.10.31 MEMASANG 1 M' PIPA PVC TIPE AW DIAMETER 3" -
A.10.32 MEMASANG 1 M' PIPA PVC TIPE AW DIAMETER 4" -
A.10.33 MEMASANG 1 BH BAK CUCI PIRING STAILES STEEL -
A.10.35 MEMASANG 1 BH KRAN DIAMETER 0,75' ATAU 0,5" -
A.10.36 MEMASANG 1 BH FLOOR DRAIN -
A.10.37 1 UNIT SEPTICTANK 4,8 X 2,1 X 2,4 M + REMBESANNYA -
A.11.01 1 M2 PASANG RANGKA ATAP BAJA RINGAN -
A.11.09 1 M2 PASANG PINTU ALUMINIUM -
A.11.12 1 M2 PASANG TERALIS BESI -
A.11.18 1 M2 PASANG TALANG DATAR, SENG BJLS 28 -
A.11.19 1 M2 PASANG TALANG MIRING, SENG BJLS 28 -
A.11.20 1 M2 PASANG TALANG 1/2 LINGKARAN D-10 CM, SENG BJLS 28 -
A.11.22 1 M2 PEK. RESIDU/TEER RANGKA ATAP/KUDA-KUDA/GORDING -
A.12.02 1 BUAH PASANG KUNCI TANAM BIASA -
A.12.03 1 BUAH PASANG KUNCI TANAM KAMAR MANDI -
A.12.04 1 BUAH PASANG KUNCI BULAT -
A.12.05 1 BUAH PASANG ENGSEL PINTU -
A.12.06 1 BUAH PASANG ENGSEL JENDELA KUPU-KUPU -
A.12.09 1 BUAH PASANG KAIT ANGIN -
A.12.10 1 BUAH PASANG SLOOT TANAM -
A.12.11 1 BUAH PASANG GRENDEL JENDELA -
A.12.12 1 BUAH PASANG PEGANGAN PINTU + KUNCI PINTU 2 X PUTAR -
A.12.14 1 BUAH PASANG KUNCI PINTU 2 X PUTAR ( lever handle ) -
A.12.17 1 M2 PASANG KACA, TEBAL 5 MM -
A.12.28 1 KG PEK. KONSTRUKSI BESI SIKU -
A.12.34 1 M1 PEK. PAGAR BELAKANG / SAMPING KAWAT DURI -
A.12.34a 1 M1 PEK.PAGAR BRC Ø 6 mm -
A.13.42 1 M2 PASANG LANTAI KERAMIK 10 X 20 CM -
A.13.44 1 M2 PASANG LANTAI KERAMIK 20 X 20 CM -
A.13.45 1 M2 PASANG LANTAI KERAMIK 25 X 25 CM -
A.13.46 1 M2 PASANG LANTAI KERAMIK 15 X 20 CM -
A.13.47 1 M2 PASANG LANTAI KERAMIK 30 X 30 CM -
A.13.48 1 M2 PASANG LANTAI KERAMIK 30 X 30 CM ANTISLIP -
A.13.58 1 M2 PASANG DINDING PORSELEN 11 X 11 CM, PUTIH -
A.13.59 1 M2 PASANG DINDING PORSELEN 11 X 11 CM, WARNA -
A.13.62 1 M2 PASANG DINDING PORSELEN 10 X 20 CM, WARNA -
A.13.63 1 M2 PASANG DINDING PORSELEN 20 X 20 CM, WARNA -
A.13.66 1 M2 PASANG DINDING KERAMIK 10 X 20 CM, -
A.13.68 1 M2 PASANG DINDING KERAMIK 20 X 20 CM, -
A.13.69 1 M2 PASANG DINDING KERAMIK 10 X 20 CM, -
A.13.74 1 M2 PASANG DINDING BATU TEMPEL -
A.13.75 1 M2 PASANG LANTAI KERAMIK 30 X 30 CM DN PUTIH POLOS -
A.13.76 1 M2 PASANG LANTAI KERAMIK 30 X 30 CM WARNA / CORAK / ANTI SLIP -
A.13.77 1 M2 PASANG LANTAI KERAMIK 40 X 40 CM -
A.13.78 1 M2 PASANG DINDING KERAMIK 20 X 25 CM, -
A.13.83 1 M2 PASANGAN PAVING BLOCK WARNA (6 CM) -
A.13.84 1 M2 PASANGAN PAVING BLOCK WARNA (8 CM) -
A.13.86 1 M2 PASANGAN PAVING BLOCK NATURAL (6 CM) -
A.13.87 1 M2 PASANGAN PAVING BLOCK NATURAL (8 CM) -
A.14.12 1 M2 MENI KAYU -
A.14.13 1 M2 MENI BESI -
A.14.14 1 M2 PLAMUR TEMBOK -
A.14.25 1 M2 PENGECATAN DINDING SEKELAS VINILEX (3x) -
A.14.26 1 M2 PENGECATAN PLAFOND SEKELAS VINILEX (3x) -
A.14.30 1 M2 PENGECATAN BIDANG KAYU (3X) BERIKUT MENI -
A.14.31 1 M2 PENGECATAN BESI (2X) -
Page 94 of 707
Harga Satuan Pekerjaan
Page 95 of 707
Harga Satuan Pekerjaan
Page 96 of 707
Harga Satuan Pekerjaan
22
Page 97 of 707
BANTUAN SMK PUSAT KEUNGGULAN (PK)
Ekonomi Kreatif
NPSN : 10404048
NAMA SEKOLAH : SMKS PGRI PEKANBARU
KABUPATEN : Kota Pekanbaru
PROVINSI : Prov. Riau
Pekerjaan : PERSIAPAN
Harga Satuan
No Uraian Pekerjaan Analisa Volume Sat
( Rp )
1 2 3 4 5 6
I. PEK. PERSIAPAN
1 Pek. Papan Nama Program + Papan Informasi 1.00 unit
2 Pek. Direksi Keet + Gudang 1.00 ls
3 Pengadaan Air Kerja 1.00 ls
4 Bongkaran 1.00 ls
Total
SMK PUSAT KEUNGGULAN (PK)
Ekonomi Kreatif
Jumlah Harga
( Rp )
7
-
-
-
- Harga Tertinggi
0
BANTUAN SMK PUSAT KEUNGGULAN (PK)
Ekonomi Kreatif
Teknologi Informasi
PEMBANGUNAN BARU
Total XII -
XIII. PEKERJAAN PENGGANTUNG / PENGUNCI
1 Pas. Engsel Pintu 4" (3bh/pintu) A.12.05 bh - -
2 Pas. Engsel Jendela 3" (2bh/jendela) A.12.06 bh - -
3 Pas. Kait / Hak Angin (2bh/jendela) A.12.09 bh - -
4 Pas. Slot Pintu (2 bh/pintu)/grendel panjang A.12.10 bh - -
5 Pas. Grendel Jendela A.12.11 bh - -
6 Pas. Kunci Pintu 2 X Putar ( lever handle ) A.12.14 bh - -
7 Pas. Handel tarik jendela ls bh - -
Total XIII -
XIV. PEKERJAAN LAIN-LAIN
1 Pas. Bata Saluran Keliling Bangunan A. B m2 - -
2 Pek. Plesteran Saluran A.05.19 m2 - -
3 Pek. Urugan Pasir bawah rabat beton A.02.13 m3 - - 1
4 Pek. Pasangan Batubata dudukan Rabat Beton A.04.11 m' - -
5 Pek. Pasangan Batako dudukan Rabat Beton A.04.12 m' - -
6 Pek. Rabat Beton Keliling Bangunan A.07.01 m3 - -
7 Pek. Plank Nama Ruang ls Set - -
8 -
9 -
10 -
11 -
12 -
13 -
14 -
15 -
Total XIV -
XV. PEK. RAMPA + HAND RAILING
1 Pek. Galian Tanah A.02.01 m3 - -
2 Pek. Urugan Kembali bekas Galian A.02.11 m3 - -
3 Pek. Urugan Pasir A.02.13 m3 - - 1
4 Pek. Pasangan Pondasi Batu Kali 1 Pc : 4 Ps A.03.04 m3 - -
5 Pek. Urugan Tanah Bawah Beton A.02.12 m3 - -
6 Pek. Beton Tumbuk 1: 3 : 5 A.07.01 m3 - -
7 Pek. Canstien Pasangan Bata A.04.11 m2 - -
8 Pek. Canstien Pasangan Batako A.04.12 m2 - -
9 Pek. Pasangan Paving Block Warna (6 cm) A.13.83 m3 - -
10 Pek. Pasangan Paving Block Natural (6 cm) A.13.86 m2 - -
12 Pek. Pemasangan Hand Railing, pipa Ø 1,5 " A.01.P.11 m' - -
Total XV -
Grand Total -
Pembulatan -
Harga Satuan -
Pembulatan Harga satuan -
Nilai Pembulatan -
Pasir Beto Batu Batu Batu Batu KBata Mera Batako Paving Bl Paving Bl Paving Bl Paving Bl Semen PC Semen WaTanah uru Batu TemPlamir Te Plamir KayCat TemboKuas Roll Kuas Minyak cat
3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
1 1 1
1 1 1
1 1 1
1
1 1
1
1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1 1 1
1 1
1 1
1 1
1 1
1 1
1 1
1 1
1 1 1
1 1
1 1 1
1 1 1
1 1
1
1
1 1 1
1 1 1 1 1
1 1
1
1 1
1 1
1 1 1
1 1
1
1 1 1
1 1
1 1
1 1
1 1
1 1 1
0
0
Amplas Meni Kayu Meni Besi Cat Kayu Cat Besi Residu Lem Kayu Politur Cat Minya Cotton Pla Compoun Kayu KelasKayu KelasKayu KelasKayu KelasKayu Dolk List Plafon Baja RingaBambu Hollow 4/4
24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43
1 1
1 1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1 1
1
1 1
1
1
1 1 1
1
1 1 1
1 1
Hollow 2/4 Triplek 4m Triplek 6m Polywood Gypsum BoMultipleks Multipleks Multipleks JabarwoodKeramik 3 Keramik 4 Keramik 20Keramik 10Keramik 20Keramik 15Keramik PoKeramik PoKeramik PoKeramik PoKeramik 60
44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63
1
1 1
1
1
1
1
1
1
Granit 60 Karpet Lem KarpeWall PaperLem Wall Buis belah Besi BetonBesi BetonBesi BetonBesi Siku Besi Strip Besi Strip Kawat Bet Beghel U ( Beghel U ( Plat Baja Baut Dia. Kawat berdPagar BRCAlmunium
64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83
1
1
1 1
1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1 1
1 1 1
1
1
1 1 1
1
1 1 1
1 1
Pasak BesiRing BaskePapan PanKaca Polo Kaca Polo Paku Bias Paku Tripl Paku SengPaku Ulir Paku Gyp Dina Bolt Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa kondui
84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1
1
1
1
1
1 1
Pipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GIP 1Pipa Stainl Elbow 4" Kran Air Floor Drai Closet Jon Closet Du Bak Air MaBak Cuci SBak FibregWashtafel Urinoir Tangki Air
104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123
1
1
1
1
1
1
1
Mesin Pomp
Water Drai Jet Washe Pas. GrabbKran ShowGenteng TaBubungan Seng Gelo Seng Plat Atap Span Genteng Me
Nok Gente Nok Tepi Nok Tepi Nok Tepi GNok Tepi Kunci Pint Kunci Bula Kunci Tan Kunci Tan
124 125 126 127 128 129 130 131 132 133 134 135 136 137 138 139 140 141 142 143
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
Kunci PintuSloot Tan Grendel JeKait Angin Engsel PintEngsel JenKunci laci Pegangan/Knop TarikKasur BusaImitatie Le Sekrup 5 Kunci LemaEngsel PitaRel Pita Promika Sekrup Pe Kasur BusaKaca / Ce Gantungan
144 145 146 147 148 149 150 151 152 153 154 155 156 157 158 159 160 161 162 163
1
1
1
1
1
1
Plank nam Handel tariGrabbed BIjuk Minyak SolOli Mesra Pelumas BKabel 1x2 Kabel 2x2 Kabel 3x2 Kabel 3x2 Kabel 3x Saklar TunSaklar GanStop KontaLampu TL 2Lampu PijarBox SekrinInbowdoosIsolasi/Se
164 165 166 167 168 169 170 171 172 173 174 175 176 177 178 179 180 181 182 183
1 1
1 1
1 1 1 1
1 1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1
1
Klem KabeMCB Panel Box Air Anti RayapPupuk KanTanaman PTanama KeRumput PembentukStemper Concrete MConcrete VManual To Alat Semprot
184 185 186 187 188 189 190 191 192 193 194 195 196 197 198
1 1
1
1
1
1
1
BANTUAN SMK PUSAT KEUNGGULAN (PK)
Ekonomi Kreatif
Teknologi Informasi
PEMBANGUNAN BARU
Total XII -
XIII. PEKERJAAN PENGGANTUNG / PENGUNCI
1 Pas. Engsel Pintu 4" (3bh/pintu) A.12.05 bh - -
2 Pas. Engsel Jendela 3" (2bh/jendela) A.12.06 bh - -
3 Pas. Kait / Hak Angin (2bh/jendela) A.12.09 bh - -
4 Pas. Slot Pintu (2 bh/pintu)/grendel panjang A.12.10 bh - -
5 Pas. Grendel Jendela A.12.11 bh - -
6 Pas. Kunci Pintu 2 X Putar ( lever handle ) A.12.14 bh - -
7 Pas. Handel tarik jendela ls bh - -
Total XIII -
XIV. PEKERJAAN LAIN-LAIN
1 Pas. Bata Saluran Keliling Bangunan A. B m2 - -
2 Pek. Plesteran Saluran A.05.19 m2 - -
3 Pek. Urugan Pasir bawah rabat beton A.02.13 m3 - - 1
4 Pek. Pasangan Batubata dudukan Rabat Beton A.04.11 m' - -
5 Pek. Pasangan Batako dudukan Rabat Beton A.04.12 m' - -
6 Pek. Rabat Beton Keliling Bangunan A.07.01 m3 - -
7 Pek. Plank Nama Ruang ls Set - -
8 -
9 -
10 -
11 -
12 -
13 -
14 -
15 -
Total XIV -
XV. PEK. RAMPA + HAND RAILING
1 Pek. Galian Tanah A.02.01 m3 - -
2 Pek. Urugan Kembali bekas Galian A.02.11 m3 - -
3 Pek. Urugan Pasir A.02.13 m3 - - 1
4 Pek. Pasangan Pondasi Batu Kali 1 Pc : 4 Ps A.03.04 m3 - -
5 Pek. Urugan Tanah Bawah Beton A.02.12 m3 - -
6 Pek. Beton Tumbuk 1: 3 : 5 A.07.01 m3 - -
7 Pek. Canstien Pasangan Bata A.04.11 m2 - -
8 Pek. Canstien Pasangan Batako A.04.12 m2 - -
9 Pek. Pasangan Paving Block Warna (6 cm) A.13.83 m3 - -
10 Pek. Pasangan Paving Block Natural (6 cm) A.13.86 m2 - -
12 Pek. Pemasangan Hand Railing, pipa Ø 1,5 " A.01.P.11 m' - -
Total XV -
Grand Total -
Pembulatan -
Harga Satuan -
Pembulatan Harga satuan -
Nilai Pembulatan -
Pasir Beto Batu Batu Batu Batu KBata Mera Batako Paving Bl Paving Bl Paving Bl Paving Bl Semen PC Semen WaTanah uru Batu TemPlamir Te Plamir KayCat TemboKuas Roll Kuas Minyak cat
3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
1 1 1
1 1 1
1 1 1
1
1 1
1
1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1 1 1
1 1
1 1
1 1
1 1
1 1
1 1
1 1
1 1 1
1 1
1 1 1
1 1 1
1 1
1
1
1 1 1
1 1 1 1 1
1 1
1
1 1
1 1
1 1 1
1 1
1
1 1 1
1 1
1 1
1 1
1 1
1 1 1
0
0
Amplas Meni Kayu Meni Besi Cat Kayu Cat Besi Residu Lem Kayu Politur Cat Minya Cotton Pla Compoun Kayu KelasKayu KelasKayu KelasKayu KelasKayu Dolk List Plafon Baja RingaBambu Hollow 4/4
24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43
1 1
1 1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1 1
1
1 1
1
1
1 1 1
1
1 1 1
1 1
Hollow 2/4 Triplek 4m Triplek 6m Polywood Gypsum BoMultipleks Multipleks Multipleks JabarwoodKeramik 3 Keramik 4 Keramik 20Keramik 10Keramik 20Keramik 15Keramik PoKeramik PoKeramik PoKeramik PoKeramik 60
44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63
1
1 1
1
1
1
1
1
1
Granit 60 Karpet Lem KarpeWall PaperLem Wall Buis belah Besi BetonBesi BetonBesi BetonBesi Siku Besi Strip Besi Strip Kawat Bet Beghel U ( Beghel U ( Plat Baja Baut Dia. Kawat berdPagar BRCAlmunium
64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83
1
1
1 1
1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1 1
1 1 1
1
1
1 1 1
1
1 1 1
1 1
Pasak BesiRing BaskePapan PanKaca Polo Kaca Polo Paku Bias Paku Tripl Paku SengPaku Ulir Paku Gyp Dina Bolt Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa kondui
84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1
1
1
1
1
1 1
Pipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GIP 1Pipa Stainl Elbow 4" Kran Air Floor Drai Closet Jon Closet Du Bak Air MaBak Cuci SBak FibregWashtafel Urinoir Tangki Air
104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123
1
1
1
1
1
1
1
Mesin Pomp
Water Drai Jet Washe Pas. GrabbKran ShowGenteng TaBubungan Seng Gelo Seng Plat Atap Span Genteng Me
Nok Gente Nok Tepi Nok Tepi Nok Tepi GNok Tepi Kunci Pint Kunci Bula Kunci Tan Kunci Tan
124 125 126 127 128 129 130 131 132 133 134 135 136 137 138 139 140 141 142 143
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
Kunci PintuSloot Tan Grendel JeKait Angin Engsel PintEngsel JenKunci laci Pegangan/Knop TarikKasur BusaImitatie Le Sekrup 5 Kunci LemaEngsel PitaRel Pita Promika Sekrup Pe Kasur BusaKaca / Ce Gantungan
144 145 146 147 148 149 150 151 152 153 154 155 156 157 158 159 160 161 162 163
1
1
1
1
1
1
Plank nam Handel tariGrabbed BIjuk Minyak SolOli Mesra Pelumas BKabel 1x2 Kabel 2x2 Kabel 3x2 Kabel 3x2 Kabel 3x Saklar TunSaklar GanStop KontaLampu TL 2Lampu PijarBox SekrinInbowdoosIsolasi/Se
164 165 166 167 168 169 170 171 172 173 174 175 176 177 178 179 180 181 182 183
1 1
1 1
1 1 1 1
1 1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1
1
Klem KabeMCB Panel Box Air Anti RayapPupuk KanTanaman PTanama KeRumput PembentukStemper Concrete MConcrete VManual To Alat Semprot
184 185 186 187 188 189 190 191 192 193 194 195 196 197 198
1 1
1
1
1
1
1
BANTUAN SMK PUSAT KEUNGGULAN (PK)
Ekonomi Kreatif
Teknologi Informasi
PEMBANGUNAN BARU
Total XII -
XIII. PEKERJAAN PENGGANTUNG / PENGUNCI
1 Pas. Engsel Pintu 4" (3bh/pintu) A.12.05 bh - -
2 Pas. Engsel Jendela 3" (2bh/jendela) A.12.06 bh - -
3 Pas. Kait / Hak Angin (2bh/jendela) A.12.09 bh - -
4 Pas. Slot Pintu (2 bh/pintu)/grendel panjang A.12.10 bh - -
5 Pas. Grendel Jendela A.12.11 bh - -
6 Pas. Kunci Pintu 2 X Putar ( lever handle ) A.12.14 bh - -
7 Pas. Handel tarik jendela ls bh - -
Total XIII -
XIV. PEKERJAAN LAIN-LAIN
1 Pas. Bata Saluran Keliling Bangunan A. B m2 - -
2 Pek. Plesteran Saluran A.05.19 m2 - -
3 Pek. Urugan Pasir bawah rabat beton A.02.13 m3 - - 1
4 Pek. Pasangan Batubata dudukan Rabat Beton A.04.11 m' - -
5 Pek. Pasangan Batako dudukan Rabat Beton A.04.12 m' - -
6 Pek. Rabat Beton Keliling Bangunan A.07.01 m3 - -
7 Pek. Plank Nama Ruang ls Set - -
8 -
9 -
10 -
11 -
12 -
13 -
14 -
15 -
Total XIV -
XV. PEK. RAMPA + HAND RAILING
1 Pek. Galian Tanah A.02.01 m3 - -
2 Pek. Urugan Kembali bekas Galian A.02.11 m3 - -
3 Pek. Urugan Pasir A.02.13 m3 - - 1
4 Pek. Pasangan Pondasi Batu Kali 1 Pc : 4 Ps A.03.04 m3 - -
5 Pek. Urugan Tanah Bawah Beton A.02.12 m3 - -
6 Pek. Beton Tumbuk 1: 3 : 5 A.07.01 m3 - -
7 Pek. Canstien Pasangan Bata A.04.11 m2 - -
8 Pek. Canstien Pasangan Batako A.04.12 m2 - -
9 Pek. Pasangan Paving Block Warna (6 cm) A.13.83 m3 - -
10 Pek. Pasangan Paving Block Natural (6 cm) A.13.86 m2 - -
12 Pek. Pemasangan Hand Railing, pipa Ø 1,5 " A.01.P.11 m' - -
Total XV -
Grand Total -
Pembulatan -
Harga Satuan -
Pembulatan Harga satuan -
Nilai Pembulatan -
Pasir Beto Batu Batu Batu Batu KBata Mera Batako Paving Bl Paving Bl Paving Bl Paving Bl Semen PC Semen WaTanah uru Batu TemPlamir Te Plamir KayCat TemboKuas Roll Kuas Minyak cat
3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
1 1 1
1 1 1
1 1 1
1
1 1
1
1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1 1 1
1 1
1 1
1 1
1 1
1 1
1 1
1 1
1 1 1
1 1
1 1 1
1 1 1
1 1
1
1
1 1 1
1 1 1 1 1
1 1
1
1 1
1 1
1 1 1
1 1
1
1 1 1
1 1
1 1
1 1
1 1
1 1 1
0
0
Amplas Meni Kayu Meni Besi Cat Kayu Cat Besi Residu Lem Kayu Politur Cat Minya Cotton Pla Compoun Kayu KelasKayu KelasKayu KelasKayu KelasKayu Dolk List Plafon Baja RingaBambu Hollow 4/4
24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43
1 1
1 1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1 1
1
1 1
1
1
1 1 1
1
1 1 1
1 1
Hollow 2/4 Triplek 4m Triplek 6m Polywood Gypsum BoMultipleks Multipleks Multipleks JabarwoodKeramik 3 Keramik 4 Keramik 20Keramik 10Keramik 20Keramik 15Keramik PoKeramik PoKeramik PoKeramik PoKeramik 60
44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63
1
1 1
1
1
1
1
1
1
Granit 60 Karpet Lem KarpeWall PaperLem Wall Buis belah Besi BetonBesi BetonBesi BetonBesi Siku Besi Strip Besi Strip Kawat Bet Beghel U ( Beghel U ( Plat Baja Baut Dia. Kawat berdPagar BRCAlmunium
64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83
1
1
1 1
1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1 1
1 1 1
1
1
1 1 1
1
1 1 1
1 1
Pasak BesiRing BaskePapan PanKaca Polo Kaca Polo Paku Bias Paku Tripl Paku SengPaku Ulir Paku Gyp Dina Bolt Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa kondui
84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1
1
1
1
1
1 1
Pipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GIP 1Pipa Stainl Elbow 4" Kran Air Floor Drai Closet Jon Closet Du Bak Air MaBak Cuci SBak FibregWashtafel Urinoir Tangki Air
104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123
1
1
1
1
1
1
1
Mesin Pomp
Water Drai Jet Washe Pas. GrabbKran ShowGenteng TaBubungan Seng Gelo Seng Plat Atap Span Genteng Me
Nok Gente Nok Tepi Nok Tepi Nok Tepi GNok Tepi Kunci Pint Kunci Bula Kunci Tan Kunci Tan
124 125 126 127 128 129 130 131 132 133 134 135 136 137 138 139 140 141 142 143
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
Kunci PintuSloot Tan Grendel JeKait Angin Engsel PintEngsel JenKunci laci Pegangan/Knop TarikKasur BusaImitatie Le Sekrup 5 Kunci LemaEngsel PitaRel Pita Promika Sekrup Pe Kasur BusaKaca / Ce Gantungan
144 145 146 147 148 149 150 151 152 153 154 155 156 157 158 159 160 161 162 163
1
1
1
1
1
1
Plank nam Handel tariGrabbed BIjuk Minyak SolOli Mesra Pelumas BKabel 1x2 Kabel 2x2 Kabel 3x2 Kabel 3x2 Kabel 3x Saklar TunSaklar GanStop KontaLampu TL 2Lampu PijarBox SekrinInbowdoosIsolasi/Se
164 165 166 167 168 169 170 171 172 173 174 175 176 177 178 179 180 181 182 183
1 1
1 1
1 1 1 1
1 1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1
1
Klem KabeMCB Panel Box Air Anti RayapPupuk KanTanaman PTanama KeRumput PembentukStemper Concrete MConcrete VManual To Alat Semprot
184 185 186 187 188 189 190 191 192 193 194 195 196 197 198
1 1
1
1
1
1
1
BANTUAN SMK PUSAT KEUNGGULAN (PK)
Ekonomi Kreatif
Teknologi Informasi
PEMBANGUNAN BARU
Total XII -
XIII. PEKERJAAN PENGGANTUNG / PENGUNCI
1 Pas. Engsel Pintu 4" (3bh/pintu) A.12.05 bh - -
2 Pas. Engsel Jendela 3" (2bh/jendela) A.12.06 bh - -
3 Pas. Kait / Hak Angin (2bh/jendela) A.12.09 bh - -
4 Pas. Slot Pintu (2 bh/pintu)/grendel panjang A.12.10 bh - -
5 Pas. Grendel Jendela A.12.11 bh - -
6 Pas. Kunci Pintu 2 X Putar ( lever handle ) A.12.14 bh - -
7 Pas. Handel tarik jendela ls bh - -
Total XIII -
XIV. PEKERJAAN LAIN-LAIN
1 Pas. Bata Saluran Keliling Bangunan A. B m2 - -
2 Pek. Plesteran Saluran A.05.19 m2 - -
3 Pek. Urugan Pasir bawah rabat beton A.02.13 m3 - - 1
4 Pek. Pasangan Batubata dudukan Rabat Beton A.04.11 m' - -
5 Pek. Pasangan Batako dudukan Rabat Beton A.04.12 m' - -
6 Pek. Rabat Beton Keliling Bangunan A.07.01 m3 - -
7 Pek. Plank Nama Ruang ls Set - -
8 -
9 -
10 -
11 -
12 -
13 -
14 -
15 -
Total XIV -
XV. PEK. RAMPA + HAND RAILING
1 Pek. Galian Tanah A.02.01 m3 - -
2 Pek. Urugan Kembali bekas Galian A.02.11 m3 - -
3 Pek. Urugan Pasir A.02.13 m3 - - 1
4 Pek. Pasangan Pondasi Batu Kali 1 Pc : 4 Ps A.03.04 m3 - -
5 Pek. Urugan Tanah Bawah Beton A.02.12 m3 - -
6 Pek. Beton Tumbuk 1: 3 : 5 A.07.01 m3 - -
7 Pek. Canstien Pasangan Bata A.04.11 m2 - -
8 Pek. Canstien Pasangan Batako A.04.12 m2 - -
9 Pek. Pasangan Paving Block Warna (6 cm) A.13.83 m3 - -
10 Pek. Pasangan Paving Block Natural (6 cm) A.13.86 m2 - -
12 Pek. Pemasangan Hand Railing, pipa Ø 1,5 " A.01.P.11 m' - -
Total XV -
Grand Total -
Pembulatan -
Harga Satuan -
Pembulatan Harga satuan -
Nilai Pembulatan -
Pasir Beto Batu Batu Batu Batu KBata Mera Batako Paving Bl Paving Bl Paving Bl Paving Bl Semen PC Semen WaTanah uru Batu TemPlamir Te Plamir KayCat TemboKuas Roll Kuas Minyak cat
3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
1 1 1
1 1 1
1 1 1
1
1 1
1
1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1 1 1
1 1
1 1
1 1
1 1
1 1
1 1
1 1
1 1 1
1 1
1 1 1
1 1 1
1 1
1
1
1 1 1
1 1 1 1 1
1 1
1
1 1
1 1
1 1 1
1 1
1
1 1 1
1 1
1 1
1 1
1 1
1 1 1
0
0
Amplas Meni Kayu Meni Besi Cat Kayu Cat Besi Residu Lem Kayu Politur Cat Minya Cotton Pla Compoun Kayu KelasKayu KelasKayu KelasKayu KelasKayu Dolk List Plafon Baja RingaBambu Hollow 4/4
24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43
1 1
1 1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1 1
1
1 1
1
1
1 1 1
1
1 1 1
1 1
Hollow 2/4 Triplek 4m Triplek 6m Polywood Gypsum BoMultipleks Multipleks Multipleks JabarwoodKeramik 3 Keramik 4 Keramik 20Keramik 10Keramik 20Keramik 15Keramik PoKeramik PoKeramik PoKeramik PoKeramik 60
44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63
1
1 1
1
1
1
1
1
1
Granit 60 Karpet Lem KarpeWall PaperLem Wall Buis belah Besi BetonBesi BetonBesi BetonBesi Siku Besi Strip Besi Strip Kawat Bet Beghel U ( Beghel U ( Plat Baja Baut Dia. Kawat berdPagar BRCAlmunium
64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83
1
1
1 1
1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1 1
1 1 1
1
1
1 1 1
1
1 1 1
1 1
Pasak BesiRing BaskePapan PanKaca Polo Kaca Polo Paku Bias Paku Tripl Paku SengPaku Ulir Paku Gyp Dina Bolt Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa kondui
84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1
1
1
1
1
1 1
Pipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GIP 1Pipa Stainl Elbow 4" Kran Air Floor Drai Closet Jon Closet Du Bak Air MaBak Cuci SBak FibregWashtafel Urinoir Tangki Air
104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123
1
1
1
1
1
1
1
Mesin Pomp
Water Drai Jet Washe Pas. GrabbKran ShowGenteng TaBubungan Seng Gelo Seng Plat Atap Span Genteng Me
Nok Gente Nok Tepi Nok Tepi Nok Tepi GNok Tepi Kunci Pint Kunci Bula Kunci Tan Kunci Tan
124 125 126 127 128 129 130 131 132 133 134 135 136 137 138 139 140 141 142 143
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
Kunci PintuSloot Tan Grendel JeKait Angin Engsel PintEngsel JenKunci laci Pegangan/Knop TarikKasur BusaImitatie Le Sekrup 5 Kunci LemaEngsel PitaRel Pita Promika Sekrup Pe Kasur BusaKaca / Ce Gantungan
144 145 146 147 148 149 150 151 152 153 154 155 156 157 158 159 160 161 162 163
1
1
1
1
1
1
Plank nam Handel tariGrabbed BIjuk Minyak SolOli Mesra Pelumas BKabel 1x2 Kabel 2x2 Kabel 3x2 Kabel 3x2 Kabel 3x Saklar TunSaklar GanStop KontaLampu TL 2Lampu PijarBox SekrinInbowdoosIsolasi/Se
164 165 166 167 168 169 170 171 172 173 174 175 176 177 178 179 180 181 182 183
1 1
1 1
1 1 1 1
1 1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1
1
Klem KabeMCB Panel Box Air Anti RayapPupuk KanTanaman PTanama KeRumput PembentukStemper Concrete MConcrete VManual To Alat Semprot
184 185 186 187 188 189 190 191 192 193 194 195 196 197 198
1 1
1
1
1
1
1
BANTUAN SMK PUSAT KEUNGGULAN (PK)
Ekonomi Kreatif
Teknologi Informasi
PEMBANGUNAN BARU
Total XII -
XIII. PEKERJAAN PENGGANTUNG / PENGUNCI
1 Pas. Engsel Pintu 4" (3bh/pintu) A.12.05 bh - -
2 Pas. Engsel Jendela 3" (2bh/jendela) A.12.06 bh - -
3 Pas. Kait / Hak Angin (2bh/jendela) A.12.09 bh - -
4 Pas. Slot Pintu (2 bh/pintu)/grendel panjang A.12.10 bh - -
5 Pas. Grendel Jendela A.12.11 bh - -
6 Pas. Kunci Pintu 2 X Putar ( lever handle ) A.12.14 bh - -
7 Pas. Handel tarik jendela ls bh - -
Total XIII -
XIV. PEKERJAAN LAIN-LAIN
1 Pas. Bata Saluran Keliling Bangunan A. B m2 - -
2 Pek. Plesteran Saluran A.05.19 m2 - -
3 Pek. Urugan Pasir bawah rabat beton A.02.13 m3 - - 1
4 Pek. Pasangan Batubata dudukan Rabat Beton A.04.11 m' - -
5 Pek. Pasangan Batako dudukan Rabat Beton A.04.12 m' - -
6 Pek. Rabat Beton Keliling Bangunan A.07.01 m3 - -
7 Pek. Plank Nama Ruang ls Set - -
8 -
9 -
10 -
11 -
12 -
13 -
14 -
15 -
Total XIV -
XV. PEK. RAMPA + HAND RAILING
1 Pek. Galian Tanah A.02.01 m3 - -
2 Pek. Urugan Kembali bekas Galian A.02.11 m3 - -
3 Pek. Urugan Pasir A.02.13 m3 - - 1
4 Pek. Pasangan Pondasi Batu Kali 1 Pc : 4 Ps A.03.04 m3 - -
5 Pek. Urugan Tanah Bawah Beton A.02.12 m3 - -
6 Pek. Beton Tumbuk 1: 3 : 5 A.07.01 m3 - -
7 Pek. Canstien Pasangan Bata A.04.11 m2 - -
8 Pek. Canstien Pasangan Batako A.04.12 m2 - -
9 Pek. Pasangan Paving Block Warna (6 cm) A.13.83 m3 - -
10 Pek. Pasangan Paving Block Natural (6 cm) A.13.86 m2 - -
12 Pek. Pemasangan Hand Railing, pipa Ø 1,5 " A.01.P.11 m' - -
Total XV -
Grand Total -
Pembulatan -
Harga Satuan -
Pembulatan Harga satuan -
Nilai Pembulatan -
Pasir Beto Batu Batu Batu Batu KBata Mera Batako Paving Bl Paving Bl Paving Bl Paving Bl Semen PC Semen WaTanah uru Batu TemPlamir Te Plamir KayCat TemboKuas Roll Kuas Minyak cat
3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
1 1 1
1 1 1
1 1 1
1
1 1
1
1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1 1 1
1 1
1 1
1 1
1 1
1 1
1 1
1 1
1 1 1
1 1
1 1 1
1 1 1
1 1
1
1
1 1 1
1 1 1 1 1
1 1
1
1 1
1 1
1 1 1
1 1
1
1 1 1
1 1
1 1
1 1
1 1
1 1 1
0
0
Amplas Meni Kayu Meni Besi Cat Kayu Cat Besi Residu Lem Kayu Politur Cat Minya Cotton Pla Compoun Kayu KelasKayu KelasKayu KelasKayu KelasKayu Dolk List Plafon Baja RingaBambu Hollow 4/4
24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43
1 1
1 1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1 1
1
1 1
1
1
1 1 1
1
1 1 1
1 1
Hollow 2/4 Triplek 4m Triplek 6m Polywood Gypsum BoMultipleks Multipleks Multipleks JabarwoodKeramik 3 Keramik 4 Keramik 20Keramik 10Keramik 20Keramik 15Keramik PoKeramik PoKeramik PoKeramik PoKeramik 60
44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63
1
1 1
1
1
1
1
1
1
Granit 60 Karpet Lem KarpeWall PaperLem Wall Buis belah Besi BetonBesi BetonBesi BetonBesi Siku Besi Strip Besi Strip Kawat Bet Beghel U ( Beghel U ( Plat Baja Baut Dia. Kawat berdPagar BRCAlmunium
64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83
1
1
1 1
1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1 1
1 1 1
1
1
1 1 1
1
1 1 1
1 1
Pasak BesiRing BaskePapan PanKaca Polo Kaca Polo Paku Bias Paku Tripl Paku SengPaku Ulir Paku Gyp Dina Bolt Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa kondui
84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1
1
1
1
1
1 1
Pipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GIP 1Pipa Stainl Elbow 4" Kran Air Floor Drai Closet Jon Closet Du Bak Air MaBak Cuci SBak FibregWashtafel Urinoir Tangki Air
104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123
1
1
1
1
1
1
1
Mesin Pomp
Water Drai Jet Washe Pas. GrabbKran ShowGenteng TaBubungan Seng Gelo Seng Plat Atap Span Genteng Me
Nok Gente Nok Tepi Nok Tepi Nok Tepi GNok Tepi Kunci Pint Kunci Bula Kunci Tan Kunci Tan
124 125 126 127 128 129 130 131 132 133 134 135 136 137 138 139 140 141 142 143
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
Kunci PintuSloot Tan Grendel JeKait Angin Engsel PintEngsel JenKunci laci Pegangan/Knop TarikKasur BusaImitatie Le Sekrup 5 Kunci LemaEngsel PitaRel Pita Promika Sekrup Pe Kasur BusaKaca / Ce Gantungan
144 145 146 147 148 149 150 151 152 153 154 155 156 157 158 159 160 161 162 163
1
1
1
1
1
1
Plank nam Handel tariGrabbed BIjuk Minyak SolOli Mesra Pelumas BKabel 1x2 Kabel 2x2 Kabel 3x2 Kabel 3x2 Kabel 3x Saklar TunSaklar GanStop KontaLampu TL 2Lampu PijarBox SekrinInbowdoosIsolasi/Se
164 165 166 167 168 169 170 171 172 173 174 175 176 177 178 179 180 181 182 183
1 1
1 1
1 1 1 1
1 1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1
1
Klem KabeMCB Panel Box Air Anti RayapPupuk KanTanaman PTanama KeRumput PembentukStemper Concrete MConcrete VManual To Alat Semprot
184 185 186 187 188 189 190 191 192 193 194 195 196 197 198
1 1
1
1
1
1
1
BANTUAN SMK PUSAT KEUNGGULAN (PK)
Ekonomi Kreatif
Teknologi Informasi
RENOVASI
Total XII -
XIII. PEKERJAAN PENGGANTUNG / PENGUNCI
1 Pas. Engsel Pintu 4" (3bh/pintu) A.12.05 bh - -
2 Pas. Engsel Jendela 3" (2bh/jendela) A.12.06 bh - -
3 Pas. Kait / Hak Angin (2bh/jendela) A.12.09 bh - -
4 Pas. Slot Pintu (2 bh/pintu)/grendel panjang A.12.10 bh - -
5 Pas. Grendel Jendela A.12.11 bh - -
6 Pas. Kunci Pintu 2 X Putar ( lever handle ) A.12.14 bh - -
7 Pas. Handel tarik jendela ls bh - -
Total XIII -
XIV. PEKERJAAN LAIN-LAIN
1 Pas. Bata Saluran Keliling Bangunan A. B m2 - -
2 Pek. Plesteran Saluran A.05.19 m2 - -
3 Pek. Urugan Pasir bawah rabat beton A.02.13 m3 - - 1
4 Pek. Pasangan Batubata dudukan Rabat Beton A.04.11 m' - -
5 Pek. Pasangan Batako dudukan Rabat Beton A.04.12 m' - -
6 Pek. Rabat Beton Keliling Bangunan A.07.01 m3 - -
7 Pek. Plank Nama Ruang ls Set - -
8 -
9 -
10 -
11 -
12 -
13 -
14 -
15 -
Total XIV -
XV. PEK. RAMPA + HAND RAILING
1 Pek. Galian Tanah A.02.01 m3 - -
2 Pek. Urugan Kembali bekas Galian A.02.11 m3 - -
3 Pek. Urugan Pasir A.02.13 m3 - - 1
4 Pek. Pasangan Pondasi Batu Kali 1 Pc : 4 Ps A.03.04 m3 - -
5 Pek. Urugan Tanah Bawah Beton A.02.12 m3 - -
6 Pek. Beton Tumbuk 1: 3 : 5 A.07.01 m3 - -
7 Pek. Canstien Pasangan Bata A.04.11 m2 - -
8 Pek. Canstien Pasangan Batako A.04.12 m2 - -
9 Pek. Pasangan Paving Block Warna (6 cm) A.13.83 m3 - -
10 Pek. Pasangan Paving Block Natural (6 cm) A.13.86 m2 - -
12 Pek. Pemasangan Hand Railing, pipa Ø 1,5 " A.01.P.11 m' - -
Total XV -
Grand Total -
Pembulatan -
Harga Satuan -
Pembulatan Harga satuan -
Nilai Pembulatan -
Pasir Beto Batu Batu Batu Batu KBata Mera Batako Paving Bl Paving Bl Paving Bl Paving Bl Semen PC Semen WaTanah uru Batu TemPlamir Te Plamir KayCat TemboKuas Roll Kuas Minyak cat
3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
1 1 1
1 1 1
1 1 1
1
1 1
1
1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1 1 1
1 1
1 1
1 1
1 1
1 1
1 1
1 1
1 1 1
1 1
1 1 1
1 1 1
1 1
1
1
1 1 1
1 1 1 1 1
1 1
1
1 1
1 1
1 1 1
1 1
1
1 1 1
1 1
1 1
1 1
1 1
1 1 1
0
0
Amplas Meni Kayu Meni Besi Cat Kayu Cat Besi Residu Lem Kayu Politur Cat Minya Cotton Pla Compoun Kayu KelasKayu KelasKayu KelasKayu KelasKayu Dolk List Plafon Baja RingaBambu Hollow 4/4
24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43
1 1
1 1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1 1
1
1 1
1
1
1 1 1
1
1 1 1
1 1
Hollow 2/4 Triplek 4m Triplek 6m Polywood Gypsum BoMultipleks Multipleks Multipleks JabarwoodKeramik 3 Keramik 4 Keramik 20Keramik 10Keramik 20Keramik 15Keramik PoKeramik PoKeramik PoKeramik PoKeramik 60
44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63
1
1 1
1
1
1
1
1
1
Granit 60 Karpet Lem KarpeWall PaperLem Wall Buis belah Besi BetonBesi BetonBesi BetonBesi Siku Besi Strip Besi Strip Kawat Bet Beghel U ( Beghel U ( Plat Baja Baut Dia. Kawat berdPagar BRCAlmunium
64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83
1
1
1 1
1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1 1
1 1 1
1
1
1 1 1
1
1 1 1
1 1
Pasak BesiRing BaskePapan PanKaca Polo Kaca Polo Paku Bias Paku Tripl Paku SengPaku Ulir Paku Gyp Dina Bolt Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa kondui
84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1
1
1
1
1
1 1
Pipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GIP 1Pipa Stainl Elbow 4" Kran Air Floor Drai Closet Jon Closet Du Bak Air MaBak Cuci SBak FibregWashtafel Urinoir Tangki Air
104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123
1
1
1
1
1
1
1
Mesin Pomp
Water Drai Jet Washe Pas. GrabbKran ShowGenteng TaBubungan Seng Gelo Seng Plat Atap Span Genteng Me
Nok Gente Nok Tepi Nok Tepi Nok Tepi GNok Tepi Kunci Pint Kunci Bula Kunci Tan Kunci Tan
124 125 126 127 128 129 130 131 132 133 134 135 136 137 138 139 140 141 142 143
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
Kunci PintuSloot Tan Grendel JeKait Angin Engsel PintEngsel JenKunci laci Pegangan/Knop TarikKasur BusaImitatie Le Sekrup 5 Kunci LemaEngsel PitaRel Pita Promika Sekrup Pe Kasur BusaKaca / Ce Gantungan
144 145 146 147 148 149 150 151 152 153 154 155 156 157 158 159 160 161 162 163
1
1
1
1
1
1
Plank nam Handel tariGrabbed BIjuk Minyak SolOli Mesra Pelumas BKabel 1x2 Kabel 2x2 Kabel 3x2 Kabel 3x2 Kabel 3x Saklar TunSaklar GanStop KontaLampu TL 2Lampu PijarBox SekrinInbowdoosIsolasi/Se
164 165 166 167 168 169 170 171 172 173 174 175 176 177 178 179 180 181 182 183
1 1
1 1
1 1 1 1
1 1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1
1
Klem KabeMCB Panel Box Air Anti RayapPupuk KanTanaman PTanama KeRumput PembentukStemper Concrete MConcrete VManual To Alat Semprot
184 185 186 187 188 189 190 191 192 193 194 195 196 197 198
1 1
1
1
1
1
1
BANTUAN SMK PUSAT KEUNGGULAN (PK)
Ekonomi Kreatif
Teknologi Informasi
RENOVASI
Total XII -
XIII. PEKERJAAN PENGGANTUNG / PENGUNCI
1 Pas. Engsel Pintu 4" (3bh/pintu) A.12.05 bh - -
2 Pas. Engsel Jendela 3" (2bh/jendela) A.12.06 bh - -
3 Pas. Kait / Hak Angin (2bh/jendela) A.12.09 bh - -
4 Pas. Slot Pintu (2 bh/pintu)/grendel panjang A.12.10 bh - -
5 Pas. Grendel Jendela A.12.11 bh - -
6 Pas. Kunci Pintu 2 X Putar ( lever handle ) A.12.14 bh - -
7 Pas. Handel tarik jendela ls bh - -
Total XIII -
XIV. PEKERJAAN LAIN-LAIN
1 Pas. Bata Saluran Keliling Bangunan A. B m2 - -
2 Pek. Plesteran Saluran A.05.19 m2 - -
3 Pek. Urugan Pasir bawah rabat beton A.02.13 m3 - - 1
4 Pek. Pasangan Batubata dudukan Rabat Beton A.04.11 m' - -
5 Pek. Pasangan Batako dudukan Rabat Beton A.04.12 m' - -
6 Pek. Rabat Beton Keliling Bangunan A.07.01 m3 - -
7 Pek. Plank Nama Ruang ls Set - -
8 -
9 -
10 -
11 -
12 -
13 -
14 -
15 -
Total XIV -
XV. PEK. RAMPA + HAND RAILING
1 Pek. Galian Tanah A.02.01 m3 - -
2 Pek. Urugan Kembali bekas Galian A.02.11 m3 - -
3 Pek. Urugan Pasir A.02.13 m3 - - 1
4 Pek. Pasangan Pondasi Batu Kali 1 Pc : 4 Ps A.03.04 m3 - -
5 Pek. Urugan Tanah Bawah Beton A.02.12 m3 - -
6 Pek. Beton Tumbuk 1: 3 : 5 A.07.01 m3 - -
7 Pek. Canstien Pasangan Bata A.04.11 m2 - -
8 Pek. Canstien Pasangan Batako A.04.12 m2 - -
9 Pek. Pasangan Paving Block Warna (6 cm) A.13.83 m3 - -
10 Pek. Pasangan Paving Block Natural (6 cm) A.13.86 m2 - -
12 Pek. Pemasangan Hand Railing, pipa Ø 1,5 " A.01.P.11 m' - -
Total XV -
Grand Total -
Pembulatan -
Harga Satuan -
Pembulatan Harga satuan -
Nilai Pembulatan -
Pasir Beto Batu Batu Batu Batu KBata Mera Batako Paving Bl Paving Bl Paving Bl Paving Bl Semen PC Semen WaTanah uru Batu TemPlamir Te Plamir KayCat TemboKuas Roll Kuas Minyak cat
3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
1 1 1
1 1 1
1 1 1
1
1 1
1
1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1 1 1
1 1
1 1
1 1
1 1
1 1
1 1
1 1
1 1 1
1 1
1 1 1
1 1 1
1 1
1
1
1 1 1
1 1 1 1 1
1 1
1
1 1
1 1
1 1 1
1 1
1
1 1 1
1 1
1 1
1 1
1 1
1 1 1
0
0
Amplas Meni Kayu Meni Besi Cat Kayu Cat Besi Residu Lem Kayu Politur Cat Minya Cotton Pla Compoun Kayu KelasKayu KelasKayu KelasKayu KelasKayu Dolk List Plafon Baja RingaBambu Hollow 4/4
24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43
1 1
1 1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1 1
1
1 1
1
1
1 1 1
1
1 1 1
1 1
Hollow 2/4 Triplek 4m Triplek 6m Polywood Gypsum BoMultipleks Multipleks Multipleks JabarwoodKeramik 3 Keramik 4 Keramik 20Keramik 10Keramik 20Keramik 15Keramik PoKeramik PoKeramik PoKeramik PoKeramik 60
44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63
1
1 1
1
1
1
1
1
1
Granit 60 Karpet Lem KarpeWall PaperLem Wall Buis belah Besi BetonBesi BetonBesi BetonBesi Siku Besi Strip Besi Strip Kawat Bet Beghel U ( Beghel U ( Plat Baja Baut Dia. Kawat berdPagar BRCAlmunium
64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83
1
1
1 1
1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1 1
1 1 1
1
1
1 1 1
1
1 1 1
1 1
Pasak BesiRing BaskePapan PanKaca Polo Kaca Polo Paku Bias Paku Tripl Paku SengPaku Ulir Paku Gyp Dina Bolt Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa kondui
84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1
1
1
1
1
1 1
Pipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GIP 1Pipa Stainl Elbow 4" Kran Air Floor Drai Closet Jon Closet Du Bak Air MaBak Cuci SBak FibregWashtafel Urinoir Tangki Air
104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123
1
1
1
1
1
1
1
Mesin Pomp
Water Drai Jet Washe Pas. GrabbKran ShowGenteng TaBubungan Seng Gelo Seng Plat Atap Span Genteng Me
Nok Gente Nok Tepi Nok Tepi Nok Tepi GNok Tepi Kunci Pint Kunci Bula Kunci Tan Kunci Tan
124 125 126 127 128 129 130 131 132 133 134 135 136 137 138 139 140 141 142 143
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
Kunci PintuSloot Tan Grendel JeKait Angin Engsel PintEngsel JenKunci laci Pegangan/Knop TarikKasur BusaImitatie Le Sekrup 5 Kunci LemaEngsel PitaRel Pita Promika Sekrup Pe Kasur BusaKaca / Ce Gantungan
144 145 146 147 148 149 150 151 152 153 154 155 156 157 158 159 160 161 162 163
1
1
1
1
1
1
Plank nam Handel tariGrabbed BIjuk Minyak SolOli Mesra Pelumas BKabel 1x2 Kabel 2x2 Kabel 3x2 Kabel 3x2 Kabel 3x Saklar TunSaklar GanStop KontaLampu TL 2Lampu PijarBox SekrinInbowdoosIsolasi/Se
164 165 166 167 168 169 170 171 172 173 174 175 176 177 178 179 180 181 182 183
1 1
1 1
1 1 1 1
1 1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1
1
Klem KabeMCB Panel Box Air Anti RayapPupuk KanTanaman PTanama KeRumput PembentukStemper Concrete MConcrete VManual To Alat Semprot
184 185 186 187 188 189 190 191 192 193 194 195 196 197 198
1 1
1
1
1
1
1
BANTUAN SMK PUSAT KEUNGGULAN (PK)
Ekonomi Kreatif
Teknologi Informasi
RENOVASI
Total XII -
XIII. PEKERJAAN PENGGANTUNG / PENGUNCI
1 Pas. Engsel Pintu 4" (3bh/pintu) A.12.05 bh - -
2 Pas. Engsel Jendela 3" (2bh/jendela) A.12.06 bh - -
3 Pas. Kait / Hak Angin (2bh/jendela) A.12.09 bh - -
4 Pas. Slot Pintu (2 bh/pintu)/grendel panjang A.12.10 bh - -
5 Pas. Grendel Jendela A.12.11 bh - -
6 Pas. Kunci Pintu 2 X Putar ( lever handle ) A.12.14 bh - -
7 Pas. Handel tarik jendela ls bh - -
Total XIII -
XIV. PEKERJAAN LAIN-LAIN
1 Pas. Bata Saluran Keliling Bangunan A. B m2 - -
2 Pek. Plesteran Saluran A.05.19 m2 - -
3 Pek. Urugan Pasir bawah rabat beton A.02.13 m3 - - 1
4 Pek. Pasangan Batubata dudukan Rabat Beton A.04.11 m' - -
5 Pek. Pasangan Batako dudukan Rabat Beton A.04.12 m' - -
6 Pek. Rabat Beton Keliling Bangunan A.07.01 m3 - -
7 Pek. Plank Nama Ruang ls Set - -
8 -
9 -
10 -
11 -
12 -
13 -
14 -
15 -
Total XIV -
XV. PEK. RAMPA + HAND RAILING
1 Pek. Galian Tanah A.02.01 m3 - -
2 Pek. Urugan Kembali bekas Galian A.02.11 m3 - -
3 Pek. Urugan Pasir A.02.13 m3 - - 1
4 Pek. Pasangan Pondasi Batu Kali 1 Pc : 4 Ps A.03.04 m3 - -
5 Pek. Urugan Tanah Bawah Beton A.02.12 m3 - -
6 Pek. Beton Tumbuk 1: 3 : 5 A.07.01 m3 - -
7 Pek. Canstien Pasangan Bata A.04.11 m2 - -
8 Pek. Canstien Pasangan Batako A.04.12 m2 - -
9 Pek. Pasangan Paving Block Warna (6 cm) A.13.83 m3 - -
10 Pek. Pasangan Paving Block Natural (6 cm) A.13.86 m2 - -
12 Pek. Pemasangan Hand Railing, pipa Ø 1,5 " A.01.P.11 m' - -
Total XV -
Grand Total -
Pembulatan -
Harga Satuan -
Pembulatan Harga satuan -
Nilai Pembulatan -
Pasir Beto Batu Batu Batu Batu KBata Mera Batako Paving Bl Paving Bl Paving Bl Paving Bl Semen PC Semen WaTanah uru Batu TemPlamir Te Plamir KayCat TemboKuas Roll Kuas Minyak cat
3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
1 1 1
1 1 1
1 1 1
1
1 1
1
1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1 1 1
1 1
1 1
1 1
1 1
1 1
1 1
1 1
1 1 1
1 1
1 1 1
1 1 1
1 1
1
1
1 1 1
1 1 1 1 1
1 1
1
1 1
1 1
1 1 1
1 1
1
1 1 1
1 1
1 1
1 1
1 1
1 1 1
0
0
Amplas Meni Kayu Meni Besi Cat Kayu Cat Besi Residu Lem Kayu Politur Cat Minya Cotton Pla Compoun Kayu KelasKayu KelasKayu KelasKayu KelasKayu Dolk List Plafon Baja RingaBambu Hollow 4/4
24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43
1 1
1 1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1 1
1
1 1
1
1
1 1 1
1
1 1 1
1 1
Hollow 2/4 Triplek 4m Triplek 6m Polywood Gypsum BoMultipleks Multipleks Multipleks JabarwoodKeramik 3 Keramik 4 Keramik 20Keramik 10Keramik 20Keramik 15Keramik PoKeramik PoKeramik PoKeramik PoKeramik 60
44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63
1
1 1
1
1
1
1
1
1
Granit 60 Karpet Lem KarpeWall PaperLem Wall Buis belah Besi BetonBesi BetonBesi BetonBesi Siku Besi Strip Besi Strip Kawat Bet Beghel U ( Beghel U ( Plat Baja Baut Dia. Kawat berdPagar BRCAlmunium
64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83
1
1
1 1
1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1 1
1 1 1
1
1
1 1 1
1
1 1 1
1 1
Pasak BesiRing BaskePapan PanKaca Polo Kaca Polo Paku Bias Paku Tripl Paku SengPaku Ulir Paku Gyp Dina Bolt Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa kondui
84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1
1
1
1
1
1 1
Pipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GIP 1Pipa Stainl Elbow 4" Kran Air Floor Drai Closet Jon Closet Du Bak Air MaBak Cuci SBak FibregWashtafel Urinoir Tangki Air
104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123
1
1
1
1
1
1
1
Mesin Pomp
Water Drai Jet Washe Pas. GrabbKran ShowGenteng TaBubungan Seng Gelo Seng Plat Atap Span Genteng Me
Nok Gente Nok Tepi Nok Tepi Nok Tepi GNok Tepi Kunci Pint Kunci Bula Kunci Tan Kunci Tan
124 125 126 127 128 129 130 131 132 133 134 135 136 137 138 139 140 141 142 143
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
Kunci PintuSloot Tan Grendel JeKait Angin Engsel PintEngsel JenKunci laci Pegangan/Knop TarikKasur BusaImitatie Le Sekrup 5 Kunci LemaEngsel PitaRel Pita Promika Sekrup Pe Kasur BusaKaca / Ce Gantungan
144 145 146 147 148 149 150 151 152 153 154 155 156 157 158 159 160 161 162 163
1
1
1
1
1
1
Plank nam Handel tariGrabbed BIjuk Minyak SolOli Mesra Pelumas BKabel 1x2 Kabel 2x2 Kabel 3x2 Kabel 3x2 Kabel 3x Saklar TunSaklar GanStop KontaLampu TL 2Lampu PijarBox SekrinInbowdoosIsolasi/Se
164 165 166 167 168 169 170 171 172 173 174 175 176 177 178 179 180 181 182 183
1 1
1 1
1 1 1 1
1 1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1
1
Klem KabeMCB Panel Box Air Anti RayapPupuk KanTanaman PTanama KeRumput PembentukStemper Concrete MConcrete VManual To Alat Semprot
184 185 186 187 188 189 190 191 192 193 194 195 196 197 198
1 1
1
1
1
1
1
BANTUAN SMK PUSAT KEUNGGULAN (PK)
Ekonomi Kreatif
Teknologi Informasi
RENOVASI
Total XII -
XIII. PEKERJAAN PENGGANTUNG / PENGUNCI
1 Pas. Engsel Pintu 4" (3bh/pintu) A.12.05 bh - -
2 Pas. Engsel Jendela 3" (2bh/jendela) A.12.06 bh - -
3 Pas. Kait / Hak Angin (2bh/jendela) A.12.09 bh - -
4 Pas. Slot Pintu (2 bh/pintu)/grendel panjang A.12.10 bh - -
5 Pas. Grendel Jendela A.12.11 bh - -
6 Pas. Kunci Pintu 2 X Putar ( lever handle ) A.12.14 bh - -
7 Pas. Handel tarik jendela ls bh - -
Total XIII -
XIV. PEKERJAAN LAIN-LAIN
1 Pas. Bata Saluran Keliling Bangunan A. B m2 - -
2 Pek. Plesteran Saluran A.05.19 m2 - -
3 Pek. Urugan Pasir bawah rabat beton A.02.13 m3 - - 1
4 Pek. Pasangan Batubata dudukan Rabat Beton A.04.11 m' - -
5 Pek. Pasangan Batako dudukan Rabat Beton A.04.12 m' - -
6 Pek. Rabat Beton Keliling Bangunan A.07.01 m3 - -
7 Pek. Plank Nama Ruang ls Set - -
8 -
9 -
10 -
11 -
12 -
13 -
14 -
15 -
Total XIV -
XV. PEK. RAMPA + HAND RAILING
1 Pek. Galian Tanah A.02.01 m3 - -
2 Pek. Urugan Kembali bekas Galian A.02.11 m3 - -
3 Pek. Urugan Pasir A.02.13 m3 - - 1
4 Pek. Pasangan Pondasi Batu Kali 1 Pc : 4 Ps A.03.04 m3 - -
5 Pek. Urugan Tanah Bawah Beton A.02.12 m3 - -
6 Pek. Beton Tumbuk 1: 3 : 5 A.07.01 m3 - -
7 Pek. Canstien Pasangan Bata A.04.11 m2 - -
8 Pek. Canstien Pasangan Batako A.04.12 m2 - -
9 Pek. Pasangan Paving Block Warna (6 cm) A.13.83 m3 - -
10 Pek. Pasangan Paving Block Natural (6 cm) A.13.86 m2 - -
12 Pek. Pemasangan Hand Railing, pipa Ø 1,5 " A.01.P.11 m' - -
Total XV -
Grand Total -
Pembulatan -
Harga Satuan -
Pembulatan Harga satuan -
Nilai Pembulatan -
Pasir Beto Batu Batu Batu Batu KBata Mera Batako Paving Bl Paving Bl Paving Bl Paving Bl Semen PC Semen WaTanah uru Batu TemPlamir Te Plamir KayCat TemboKuas Roll Kuas Minyak cat
3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
1 1 1
1 1 1
1 1 1
1
1 1
1
1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1 1 1
1 1
1 1
1 1
1 1
1 1
1 1
1 1
1 1 1
1 1
1 1 1
1 1 1
1 1
1
1
1 1 1
1 1 1 1 1
1 1
1
1 1
1 1
1 1 1
1 1
1
1 1 1
1 1
1 1
1 1
1 1
1 1 1
0
0
Amplas Meni Kayu Meni Besi Cat Kayu Cat Besi Residu Lem Kayu Politur Cat Minya Cotton Pla Compoun Kayu KelasKayu KelasKayu KelasKayu KelasKayu Dolk List Plafon Baja RingaBambu Hollow 4/4
24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43
1 1
1 1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1 1
1
1 1
1
1
1 1 1
1
1 1 1
1 1
Hollow 2/4 Triplek 4m Triplek 6m Polywood Gypsum BoMultipleks Multipleks Multipleks JabarwoodKeramik 3 Keramik 4 Keramik 20Keramik 10Keramik 20Keramik 15Keramik PoKeramik PoKeramik PoKeramik PoKeramik 60
44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63
1
1 1
1
1
1
1
1
1
Granit 60 Karpet Lem KarpeWall PaperLem Wall Buis belah Besi BetonBesi BetonBesi BetonBesi Siku Besi Strip Besi Strip Kawat Bet Beghel U ( Beghel U ( Plat Baja Baut Dia. Kawat berdPagar BRCAlmunium
64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83
1
1
1 1
1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1 1
1 1 1
1
1
1 1 1
1
1 1 1
1 1
Pasak BesiRing BaskePapan PanKaca Polo Kaca Polo Paku Bias Paku Tripl Paku SengPaku Ulir Paku Gyp Dina Bolt Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa kondui
84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1
1
1
1
1
1 1
Pipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GIP 1Pipa Stainl Elbow 4" Kran Air Floor Drai Closet Jon Closet Du Bak Air MaBak Cuci SBak FibregWashtafel Urinoir Tangki Air
104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123
1
1
1
1
1
1
1
Mesin Pomp
Water Drai Jet Washe Pas. GrabbKran ShowGenteng TaBubungan Seng Gelo Seng Plat Atap Span Genteng Me
Nok Gente Nok Tepi Nok Tepi Nok Tepi GNok Tepi Kunci Pint Kunci Bula Kunci Tan Kunci Tan
124 125 126 127 128 129 130 131 132 133 134 135 136 137 138 139 140 141 142 143
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
Kunci PintuSloot Tan Grendel JeKait Angin Engsel PintEngsel JenKunci laci Pegangan/Knop TarikKasur BusaImitatie Le Sekrup 5 Kunci LemaEngsel PitaRel Pita Promika Sekrup Pe Kasur BusaKaca / Ce Gantungan
144 145 146 147 148 149 150 151 152 153 154 155 156 157 158 159 160 161 162 163
1
1
1
1
1
1
Plank nam Handel tariGrabbed BIjuk Minyak SolOli Mesra Pelumas BKabel 1x2 Kabel 2x2 Kabel 3x2 Kabel 3x2 Kabel 3x Saklar TunSaklar GanStop KontaLampu TL 2Lampu PijarBox SekrinInbowdoosIsolasi/Se
164 165 166 167 168 169 170 171 172 173 174 175 176 177 178 179 180 181 182 183
1 1
1 1
1 1 1 1
1 1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1
1
Klem KabeMCB Panel Box Air Anti RayapPupuk KanTanaman PTanama KeRumput PembentukStemper Concrete MConcrete VManual To Alat Semprot
184 185 186 187 188 189 190 191 192 193 194 195 196 197 198
1 1
1
1
1
1
1
BANTUAN SMK PUSAT KEUNGGULAN (PK)
Ekonomi Kreatif
Teknologi Informasi
RENOVASI
Total XII -
XIII. PEKERJAAN PENGGANTUNG / PENGUNCI
1 Pas. Engsel Pintu 4" (3bh/pintu) A.12.05 bh - -
2 Pas. Engsel Jendela 3" (2bh/jendela) A.12.06 bh - -
3 Pas. Kait / Hak Angin (2bh/jendela) A.12.09 bh - -
4 Pas. Slot Pintu (2 bh/pintu)/grendel panjang A.12.10 bh - -
5 Pas. Grendel Jendela A.12.11 bh - -
6 Pas. Kunci Pintu 2 X Putar ( lever handle ) A.12.14 bh - -
7 Pas. Handel tarik jendela ls bh - -
Total XIII -
XIV. PEKERJAAN LAIN-LAIN
1 Pas. Bata Saluran Keliling Bangunan A. B m2 - -
2 Pek. Plesteran Saluran A.05.19 m2 - -
3 Pek. Urugan Pasir bawah rabat beton A.02.13 m3 - - 1
4 Pek. Pasangan Batubata dudukan Rabat Beton A.04.11 m' - -
5 Pek. Pasangan Batako dudukan Rabat Beton A.04.12 m' - -
6 Pek. Rabat Beton Keliling Bangunan A.07.01 m3 - -
7 Pek. Plank Nama Ruang ls Set - -
8 -
9 -
10 -
11 -
12 -
13 -
14 -
15 -
Total XIV -
XV. PEK. RAMPA + HAND RAILING
1 Pek. Galian Tanah A.02.01 m3 - -
2 Pek. Urugan Kembali bekas Galian A.02.11 m3 - -
3 Pek. Urugan Pasir A.02.13 m3 - - 1
4 Pek. Pasangan Pondasi Batu Kali 1 Pc : 4 Ps A.03.04 m3 - -
5 Pek. Urugan Tanah Bawah Beton A.02.12 m3 - -
6 Pek. Beton Tumbuk 1: 3 : 5 A.07.01 m3 - -
7 Pek. Canstien Pasangan Bata A.04.11 m2 - -
8 Pek. Canstien Pasangan Batako A.04.12 m2 - -
9 Pek. Pasangan Paving Block Warna (6 cm) A.13.83 m3 - -
10 Pek. Pasangan Paving Block Natural (6 cm) A.13.86 m2 - -
12 Pek. Pemasangan Hand Railing, pipa Ø 1,5 " A.01.P.11 m' - -
Total XV -
Grand Total -
Pembulatan -
Harga Satuan -
Pembulatan Harga satuan -
Nilai Pembulatan -
Pasir Beto Batu Batu Batu Batu KBata Mera Batako Paving Bl Paving Bl Paving Bl Paving Bl Semen PC Semen WaTanah uru Batu TemPlamir Te Plamir KayCat TemboKuas Roll Kuas Minyak cat
3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
1 1 1
1 1 1
1 1 1
1
1 1
1
1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1 1 1
1 1
1 1
1 1
1 1
1 1
1 1
1 1
1 1 1
1 1
1 1 1
1 1 1
1 1
1
1
1 1 1
1 1 1 1 1
1 1
1
1 1
1 1
1 1 1
1 1
1
1 1 1
1 1
1 1
1 1
1 1
1 1 1
0
0
Amplas Meni Kayu Meni Besi Cat Kayu Cat Besi Residu Lem Kayu Politur Cat Minya Cotton Pla Compoun Kayu KelasKayu KelasKayu KelasKayu KelasKayu Dolk List Plafon Baja RingaBambu Hollow 4/4
24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43
1 1
1 1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1 1
1
1 1
1
1
1 1 1
1
1 1 1
1 1
Hollow 2/4 Triplek 4m Triplek 6m Polywood Gypsum BoMultipleks Multipleks Multipleks JabarwoodKeramik 3 Keramik 4 Keramik 20Keramik 10Keramik 20Keramik 15Keramik PoKeramik PoKeramik PoKeramik PoKeramik 60
44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63
1
1 1
1
1
1
1
1
1
Granit 60 Karpet Lem KarpeWall PaperLem Wall Buis belah Besi BetonBesi BetonBesi BetonBesi Siku Besi Strip Besi Strip Kawat Bet Beghel U ( Beghel U ( Plat Baja Baut Dia. Kawat berdPagar BRCAlmunium
64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83
1
1
1 1
1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1 1
1 1 1
1
1
1 1 1
1
1 1 1
1 1
Pasak BesiRing BaskePapan PanKaca Polo Kaca Polo Paku Bias Paku Tripl Paku SengPaku Ulir Paku Gyp Dina Bolt Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa kondui
84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1
1
1
1
1
1 1
Pipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GIP 1Pipa Stainl Elbow 4" Kran Air Floor Drai Closet Jon Closet Du Bak Air MaBak Cuci SBak FibregWashtafel Urinoir Tangki Air
104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123
1
1
1
1
1
1
1
Mesin Pomp
Water Drai Jet Washe Pas. GrabbKran ShowGenteng TaBubungan Seng Gelo Seng Plat Atap Span Genteng Me
Nok Gente Nok Tepi Nok Tepi Nok Tepi GNok Tepi Kunci Pint Kunci Bula Kunci Tan Kunci Tan
124 125 126 127 128 129 130 131 132 133 134 135 136 137 138 139 140 141 142 143
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
Kunci PintuSloot Tan Grendel JeKait Angin Engsel PintEngsel JenKunci laci Pegangan/Knop TarikKasur BusaImitatie Le Sekrup 5 Kunci LemaEngsel PitaRel Pita Promika Sekrup Pe Kasur BusaKaca / Ce Gantungan
144 145 146 147 148 149 150 151 152 153 154 155 156 157 158 159 160 161 162 163
1
1
1
1
1
1
Plank nam Handel tariGrabbed BIjuk Minyak SolOli Mesra Pelumas BKabel 1x2 Kabel 2x2 Kabel 3x2 Kabel 3x2 Kabel 3x Saklar TunSaklar GanStop KontaLampu TL 2Lampu PijarBox SekrinInbowdoosIsolasi/Se
164 165 166 167 168 169 170 171 172 173 174 175 176 177 178 179 180 181 182 183
1 1
1 1
1 1 1 1
1 1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1
1
Klem KabeMCB Panel Box Air Anti RayapPupuk KanTanaman PTanama KeRumput PembentukStemper Concrete MConcrete VManual To Alat Semprot
184 185 186 187 188 189 190 191 192 193 194 195 196 197 198
1 1
1
1
1
1
1
BANTUAN SMK PUSAT KEUNGGULAN (PK)
Ekonomi Kreatif
Teknologi Informasi
REHABILITASI
Total XII -
XIII. PEKERJAAN PENGGANTUNG / PENGUNCI
1 Pas. Engsel Pintu 4" (3bh/pintu) A.12.05 bh - -
2 Pas. Engsel Jendela 3" (2bh/jendela) A.12.06 bh - -
3 Pas. Kait / Hak Angin (2bh/jendela) A.12.09 bh - -
4 Pas. Slot Pintu (2 bh/pintu)/grendel panjang A.12.10 bh - -
5 Pas. Grendel Jendela A.12.11 bh - -
6 Pas. Kunci Pintu 2 X Putar ( lever handle ) A.12.14 bh - -
7 Pas. Handel tarik jendela ls bh - -
Total XIII -
XIV. PEKERJAAN LAIN-LAIN
1 Pas. Bata Saluran Keliling Bangunan A. B m2 - -
2 Pek. Plesteran Saluran A.05.19 m2 - -
3 Pek. Urugan Pasir bawah rabat beton A.02.13 m3 - - 1
4 Pek. Pasangan Batubata dudukan Rabat Beton A.04.11 m' - -
5 Pek. Pasangan Batako dudukan Rabat Beton A.04.12 m' - -
6 Pek. Rabat Beton Keliling Bangunan A.07.01 m3 - -
7 Pek. Plank Nama Ruang ls Set - -
8 -
9 -
10 -
11 -
12 -
13 -
14 -
15 -
Total XIV -
XV. PEK. RAMPA + HAND RAILING
1 Pek. Galian Tanah A.02.01 m3 - -
2 Pek. Urugan Kembali bekas Galian A.02.11 m3 - -
3 Pek. Urugan Pasir A.02.13 m3 - - 1
4 Pek. Pasangan Pondasi Batu Kali 1 Pc : 4 Ps A.03.04 m3 - -
5 Pek. Urugan Tanah Bawah Beton A.02.12 m3 - -
6 Pek. Beton Tumbuk 1: 3 : 5 A.07.01 m3 - -
7 Pek. Canstien Pasangan Bata A.04.11 m2 - -
8 Pek. Canstien Pasangan Batako A.04.12 m2 - -
9 Pek. Pasangan Paving Block Warna (6 cm) A.13.83 m3 - -
10 Pek. Pasangan Paving Block Natural (6 cm) A.13.86 m2 - -
12 Pek. Pemasangan Hand Railing, pipa Ø 1,5 " A.01.P.11 m' - -
Total XV -
Grand Total -
Pembulatan -
Harga Satuan -
Pembulatan Harga satuan -
Nilai Pembulatan -
Pasir Beto Batu Batu Batu Batu KBata Mera Batako Paving Bl Paving Bl Paving Bl Paving Bl Semen PC Semen WaTanah uru Batu TemPlamir Te Plamir KayCat TemboKuas Roll Kuas Minyak cat
3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
1 1 1
1 1 1
1 1 1
1
1 1
1
1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1 1 1
1 1
1 1
1 1
1 1
1 1
1 1
1 1
1 1 1
1 1
1 1 1
1 1 1
1 1
1
1
1 1 1
1 1 1 1 1
1 1
1
1 1
1 1
1 1 1
1 1
1
1 1 1
1 1
1 1
1 1
1 1
1 1 1
0
0
Amplas Meni Kayu Meni Besi Cat Kayu Cat Besi Residu Lem Kayu Politur Cat Minya Cotton Pla Compoun Kayu KelasKayu KelasKayu KelasKayu KelasKayu Dolk List Plafon Baja RingaBambu Hollow 4/4
24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43
1 1
1 1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1 1
1
1 1
1
1
1 1 1
1
1 1 1
1 1
Hollow 2/4 Triplek 4m Triplek 6m Polywood Gypsum BoMultipleks Multipleks Multipleks JabarwoodKeramik 3 Keramik 4 Keramik 20Keramik 10Keramik 20Keramik 15Keramik PoKeramik PoKeramik PoKeramik PoKeramik 60
44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63
1
1 1
1
1
1
1
1
1
Granit 60 Karpet Lem KarpeWall PaperLem Wall Buis belah Besi BetonBesi BetonBesi BetonBesi Siku Besi Strip Besi Strip Kawat Bet Beghel U ( Beghel U ( Plat Baja Baut Dia. Kawat berdPagar BRCAlmunium
64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83
1
1
1 1
1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1 1
1 1 1
1
1
1 1 1
1
1 1 1
1 1
Pasak BesiRing BaskePapan PanKaca Polo Kaca Polo Paku Bias Paku Tripl Paku SengPaku Ulir Paku Gyp Dina Bolt Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa kondui
84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1
1
1
1
1
1 1
Pipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GIP 1Pipa Stainl Elbow 4" Kran Air Floor Drai Closet Jon Closet Du Bak Air MaBak Cuci SBak FibregWashtafel Urinoir Tangki Air
104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123
1
1
1
1
1
1
1
Mesin Pomp
Water Drai Jet Washe Pas. GrabbKran ShowGenteng TaBubungan Seng Gelo Seng Plat Atap Span Genteng Me
Nok Gente Nok Tepi Nok Tepi Nok Tepi GNok Tepi Kunci Pint Kunci Bula Kunci Tan Kunci Tan
124 125 126 127 128 129 130 131 132 133 134 135 136 137 138 139 140 141 142 143
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
Kunci PintuSloot Tan Grendel JeKait Angin Engsel PintEngsel JenKunci laci Pegangan/Knop TarikKasur BusaImitatie Le Sekrup 5 Kunci LemaEngsel PitaRel Pita Promika Sekrup Pe Kasur BusaKaca / Ce Gantungan
144 145 146 147 148 149 150 151 152 153 154 155 156 157 158 159 160 161 162 163
1
1
1
1
1
1
Plank nam Handel tariGrabbed BIjuk Minyak SolOli Mesra Pelumas BKabel 1x2 Kabel 2x2 Kabel 3x2 Kabel 3x2 Kabel 3x Saklar TunSaklar GanStop KontaLampu TL 2Lampu PijarBox SekrinInbowdoosIsolasi/Se
164 165 166 167 168 169 170 171 172 173 174 175 176 177 178 179 180 181 182 183
1 1
1 1
1 1 1 1
1 1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1
1
Klem KabeMCB Panel Box Air Anti RayapPupuk KanTanaman PTanama KeRumput PembentukStemper Concrete MConcrete VManual To Alat Semprot
184 185 186 187 188 189 190 191 192 193 194 195 196 197 198
1 1
1
1
1
1
1
BANTUAN SMK PUSAT KEUNGGULAN (PK)
Ekonomi Kreatif
Teknologi Informasi
REHABILITASI
Total XII -
XIII. PEKERJAAN PENGGANTUNG / PENGUNCI
1 Pas. Engsel Pintu 4" (3bh/pintu) A.12.05 bh - -
2 Pas. Engsel Jendela 3" (2bh/jendela) A.12.06 bh - -
3 Pas. Kait / Hak Angin (2bh/jendela) A.12.09 bh - -
4 Pas. Slot Pintu (2 bh/pintu)/grendel panjang A.12.10 bh - -
5 Pas. Grendel Jendela A.12.11 bh - -
6 Pas. Kunci Pintu 2 X Putar ( lever handle ) A.12.14 bh - -
7 Pas. Handel tarik jendela ls bh - -
Total XIII -
XIV. PEKERJAAN LAIN-LAIN
1 Pas. Bata Saluran Keliling Bangunan A. B m2 - -
2 Pek. Plesteran Saluran A.05.19 m2 - -
3 Pek. Urugan Pasir bawah rabat beton A.02.13 m3 - - 1
4 Pek. Pasangan Batubata dudukan Rabat Beton A.04.11 m' - -
5 Pek. Pasangan Batako dudukan Rabat Beton A.04.12 m' - -
6 Pek. Rabat Beton Keliling Bangunan A.07.01 m3 - -
7 Pek. Plank Nama Ruang ls Set - -
8 -
9 -
10 -
11 -
12 -
13 -
14 -
15 -
Total XIV -
XV. PEK. RAMPA + HAND RAILING
1 Pek. Galian Tanah A.02.01 m3 - -
2 Pek. Urugan Kembali bekas Galian A.02.11 m3 - -
3 Pek. Urugan Pasir A.02.13 m3 - - 1
4 Pek. Pasangan Pondasi Batu Kali 1 Pc : 4 Ps A.03.04 m3 - -
5 Pek. Urugan Tanah Bawah Beton A.02.12 m3 - -
6 Pek. Beton Tumbuk 1: 3 : 5 A.07.01 m3 - -
7 Pek. Canstien Pasangan Bata A.04.11 m2 - -
8 Pek. Canstien Pasangan Batako A.04.12 m2 - -
9 Pek. Pasangan Paving Block Warna (6 cm) A.13.83 m3 - -
10 Pek. Pasangan Paving Block Natural (6 cm) A.13.86 m2 - -
12 Pek. Pemasangan Hand Railing, pipa Ø 1,5 " A.01.P.11 m' - -
Total XV -
Grand Total -
Pembulatan -
Harga Satuan -
Pembulatan Harga satuan -
Nilai Pembulatan -
Pasir Beto Batu Batu Batu Batu KBata Mera Batako Paving Bl Paving Bl Paving Bl Paving Bl Semen PC Semen WaTanah uru Batu TemPlamir Te Plamir KayCat TemboKuas Roll Kuas Minyak cat
3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
1 1 1
1 1 1
1 1 1
1
1 1
1
1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1 1 1
1 1
1 1
1 1
1 1
1 1
1 1
1 1
1 1 1
1 1
1 1 1
1 1 1
1 1
1
1
1 1 1
1 1 1 1 1
1 1
1
1 1
1 1
1 1 1
1 1
1
1 1 1
1 1
1 1
1 1
1 1
1 1 1
0
0
Amplas Meni Kayu Meni Besi Cat Kayu Cat Besi Residu Lem Kayu Politur Cat Minya Cotton Pla Compoun Kayu KelasKayu KelasKayu KelasKayu KelasKayu Dolk List Plafon Baja RingaBambu Hollow 4/4
24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43
1 1
1 1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1 1
1
1 1
1
1
1 1 1
1
1 1 1
1 1
Hollow 2/4 Triplek 4m Triplek 6m Polywood Gypsum BoMultipleks Multipleks Multipleks JabarwoodKeramik 3 Keramik 4 Keramik 20Keramik 10Keramik 20Keramik 15Keramik PoKeramik PoKeramik PoKeramik PoKeramik 60
44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63
1
1 1
1
1
1
1
1
1
Granit 60 Karpet Lem KarpeWall PaperLem Wall Buis belah Besi BetonBesi BetonBesi BetonBesi Siku Besi Strip Besi Strip Kawat Bet Beghel U ( Beghel U ( Plat Baja Baut Dia. Kawat berdPagar BRCAlmunium
64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83
1
1
1 1
1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1 1
1 1 1
1
1
1 1 1
1
1 1 1
1 1
Pasak BesiRing BaskePapan PanKaca Polo Kaca Polo Paku Bias Paku Tripl Paku SengPaku Ulir Paku Gyp Dina Bolt Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa kondui
84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1
1
1
1
1
1 1
Pipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GIP 1Pipa Stainl Elbow 4" Kran Air Floor Drai Closet Jon Closet Du Bak Air MaBak Cuci SBak FibregWashtafel Urinoir Tangki Air
104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123
1
1
1
1
1
1
1
Mesin Pomp
Water Drai Jet Washe Pas. GrabbKran ShowGenteng TaBubungan Seng Gelo Seng Plat Atap Span Genteng Me
Nok Gente Nok Tepi Nok Tepi Nok Tepi GNok Tepi Kunci Pint Kunci Bula Kunci Tan Kunci Tan
124 125 126 127 128 129 130 131 132 133 134 135 136 137 138 139 140 141 142 143
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
Kunci PintuSloot Tan Grendel JeKait Angin Engsel PintEngsel JenKunci laci Pegangan/Knop TarikKasur BusaImitatie Le Sekrup 5 Kunci LemaEngsel PitaRel Pita Promika Sekrup Pe Kasur BusaKaca / Ce Gantungan
144 145 146 147 148 149 150 151 152 153 154 155 156 157 158 159 160 161 162 163
1
1
1
1
1
1
Plank nam Handel tariGrabbed BIjuk Minyak SolOli Mesra Pelumas BKabel 1x2 Kabel 2x2 Kabel 3x2 Kabel 3x2 Kabel 3x Saklar TunSaklar GanStop KontaLampu TL 2Lampu PijarBox SekrinInbowdoosIsolasi/Se
164 165 166 167 168 169 170 171 172 173 174 175 176 177 178 179 180 181 182 183
1 1
1 1
1 1 1 1
1 1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1
1
Klem KabeMCB Panel Box Air Anti RayapPupuk KanTanaman PTanama KeRumput PembentukStemper Concrete MConcrete VManual To Alat Semprot
184 185 186 187 188 189 190 191 192 193 194 195 196 197 198
1 1
1
1
1
1
1
BANTUAN SMK PUSAT KEUNGGULAN (PK)
Ekonomi Kreatif
Teknologi Informasi
REHABILITASI
Total XII -
XIII. PEKERJAAN PENGGANTUNG / PENGUNCI
1 Pas. Engsel Pintu 4" (3bh/pintu) A.12.05 bh - -
2 Pas. Engsel Jendela 3" (2bh/jendela) A.12.06 bh - -
3 Pas. Kait / Hak Angin (2bh/jendela) A.12.09 bh - -
4 Pas. Slot Pintu (2 bh/pintu)/grendel panjang A.12.10 bh - -
5 Pas. Grendel Jendela A.12.11 bh - -
6 Pas. Kunci Pintu 2 X Putar ( lever handle ) A.12.14 bh - -
7 Pas. Handel tarik jendela ls bh - -
Total XIII -
XIV. PEKERJAAN LAIN-LAIN
1 Pas. Bata Saluran Keliling Bangunan A. B m2 - -
2 Pek. Plesteran Saluran A.05.19 m2 - -
3 Pek. Urugan Pasir bawah rabat beton A.02.13 m3 - - 1
4 Pek. Pasangan Batubata dudukan Rabat Beton A.04.11 m' - -
5 Pek. Pasangan Batako dudukan Rabat Beton A.04.12 m' - -
6 Pek. Rabat Beton Keliling Bangunan A.07.01 m3 - -
7 Pek. Plank Nama Ruang ls Set - -
8 -
9 -
10 -
11 -
12 -
13 -
14 -
15 -
Total XIV -
XV. PEK. RAMPA + HAND RAILING
1 Pek. Galian Tanah A.02.01 m3 - -
2 Pek. Urugan Kembali bekas Galian A.02.11 m3 - -
3 Pek. Urugan Pasir A.02.13 m3 - - 1
4 Pek. Pasangan Pondasi Batu Kali 1 Pc : 4 Ps A.03.04 m3 - -
5 Pek. Urugan Tanah Bawah Beton A.02.12 m3 - -
6 Pek. Beton Tumbuk 1: 3 : 5 A.07.01 m3 - -
7 Pek. Canstien Pasangan Bata A.04.11 m2 - -
8 Pek. Canstien Pasangan Batako A.04.12 m2 - -
9 Pek. Pasangan Paving Block Warna (6 cm) A.13.83 m3 - -
10 Pek. Pasangan Paving Block Natural (6 cm) A.13.86 m2 - -
12 Pek. Pemasangan Hand Railing, pipa Ø 1,5 " A.01.P.11 m' - -
Total XV -
Grand Total -
Pembulatan -
Harga Satuan -
Pembulatan Harga satuan -
Nilai Pembulatan -
Pasir Beto Batu Batu Batu Batu KBata Mera Batako Paving Bl Paving Bl Paving Bl Paving Bl Semen PC Semen WaTanah uru Batu TemPlamir Te Plamir KayCat TemboKuas Roll Kuas Minyak cat
3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
1 1 1
1 1 1
1 1 1
1
1 1
1
1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1 1 1
1 1
1 1
1 1
1 1
1 1
1 1
1 1
1 1 1
1 1
1 1 1
1 1 1
1 1
1
1
1 1 1
1 1 1 1 1
1 1
1
1 1
1 1
1 1 1
1 1
1
1 1 1
1 1
1 1
1 1
1 1
1 1 1
0
0
Amplas Meni Kayu Meni Besi Cat Kayu Cat Besi Residu Lem Kayu Politur Cat Minya Cotton Pla Compoun Kayu KelasKayu KelasKayu KelasKayu KelasKayu Dolk List Plafon Baja RingaBambu Hollow 4/4
24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43
1 1
1 1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1 1
1
1 1
1
1
1 1 1
1
1 1 1
1 1
Hollow 2/4 Triplek 4m Triplek 6m Polywood Gypsum BoMultipleks Multipleks Multipleks JabarwoodKeramik 3 Keramik 4 Keramik 20Keramik 10Keramik 20Keramik 15Keramik PoKeramik PoKeramik PoKeramik PoKeramik 60
44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63
1
1 1
1
1
1
1
1
1
Granit 60 Karpet Lem KarpeWall PaperLem Wall Buis belah Besi BetonBesi BetonBesi BetonBesi Siku Besi Strip Besi Strip Kawat Bet Beghel U ( Beghel U ( Plat Baja Baut Dia. Kawat berdPagar BRCAlmunium
64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83
1
1
1 1
1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1 1
1 1 1
1
1
1 1 1
1
1 1 1
1 1
Pasak BesiRing BaskePapan PanKaca Polo Kaca Polo Paku Bias Paku Tripl Paku SengPaku Ulir Paku Gyp Dina Bolt Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa kondui
84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1
1
1
1
1
1 1
Pipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GIP 1Pipa Stainl Elbow 4" Kran Air Floor Drai Closet Jon Closet Du Bak Air MaBak Cuci SBak FibregWashtafel Urinoir Tangki Air
104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123
1
1
1
1
1
1
1
Mesin Pomp
Water Drai Jet Washe Pas. GrabbKran ShowGenteng TaBubungan Seng Gelo Seng Plat Atap Span Genteng Me
Nok Gente Nok Tepi Nok Tepi Nok Tepi GNok Tepi Kunci Pint Kunci Bula Kunci Tan Kunci Tan
124 125 126 127 128 129 130 131 132 133 134 135 136 137 138 139 140 141 142 143
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
Kunci PintuSloot Tan Grendel JeKait Angin Engsel PintEngsel JenKunci laci Pegangan/Knop TarikKasur BusaImitatie Le Sekrup 5 Kunci LemaEngsel PitaRel Pita Promika Sekrup Pe Kasur BusaKaca / Ce Gantungan
144 145 146 147 148 149 150 151 152 153 154 155 156 157 158 159 160 161 162 163
1
1
1
1
1
1
Plank nam Handel tariGrabbed BIjuk Minyak SolOli Mesra Pelumas BKabel 1x2 Kabel 2x2 Kabel 3x2 Kabel 3x2 Kabel 3x Saklar TunSaklar GanStop KontaLampu TL 2Lampu PijarBox SekrinInbowdoosIsolasi/Se
164 165 166 167 168 169 170 171 172 173 174 175 176 177 178 179 180 181 182 183
1 1
1 1
1 1 1 1
1 1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1
1
Klem KabeMCB Panel Box Air Anti RayapPupuk KanTanaman PTanama KeRumput PembentukStemper Concrete MConcrete VManual To Alat Semprot
184 185 186 187 188 189 190 191 192 193 194 195 196 197 198
1 1
1
1
1
1
1
BANTUAN SMK PUSAT KEUNGGULAN (PK)
Ekonomi Kreatif
Teknologi Informasi
REHABILITASI
Total XII -
XIII. PEKERJAAN PENGGANTUNG / PENGUNCI
1 Pas. Engsel Pintu 4" (3bh/pintu) A.12.05 bh - -
2 Pas. Engsel Jendela 3" (2bh/jendela) A.12.06 bh - -
3 Pas. Kait / Hak Angin (2bh/jendela) A.12.09 bh - -
4 Pas. Slot Pintu (2 bh/pintu)/grendel panjang A.12.10 bh - -
5 Pas. Grendel Jendela A.12.11 bh - -
6 Pas. Kunci Pintu 2 X Putar ( lever handle ) A.12.14 bh - -
7 Pas. Handel tarik jendela ls bh - -
Total XIII -
XIV. PEKERJAAN LAIN-LAIN
1 Pas. Bata Saluran Keliling Bangunan A. B m2 - -
2 Pek. Plesteran Saluran A.05.19 m2 - -
3 Pek. Urugan Pasir bawah rabat beton A.02.13 m3 - - 1
4 Pek. Pasangan Batubata dudukan Rabat Beton A.04.11 m' - -
5 Pek. Pasangan Batako dudukan Rabat Beton A.04.12 m' - -
6 Pek. Rabat Beton Keliling Bangunan A.07.01 m3 - -
7 Pek. Plank Nama Ruang ls Set - -
8 -
9 -
10 -
11 -
12 -
13 -
14 -
15 -
Total XIV -
XV. PEK. RAMPA + HAND RAILING
1 Pek. Galian Tanah A.02.01 m3 - -
2 Pek. Urugan Kembali bekas Galian A.02.11 m3 - -
3 Pek. Urugan Pasir A.02.13 m3 - - 1
4 Pek. Pasangan Pondasi Batu Kali 1 Pc : 4 Ps A.03.04 m3 - -
5 Pek. Urugan Tanah Bawah Beton A.02.12 m3 - -
6 Pek. Beton Tumbuk 1: 3 : 5 A.07.01 m3 - -
7 Pek. Canstien Pasangan Bata A.04.11 m2 - -
8 Pek. Canstien Pasangan Batako A.04.12 m2 - -
9 Pek. Pasangan Paving Block Warna (6 cm) A.13.83 m3 - -
10 Pek. Pasangan Paving Block Natural (6 cm) A.13.86 m2 - -
12 Pek. Pemasangan Hand Railing, pipa Ø 1,5 " A.01.P.11 m' - -
Total XV -
Grand Total -
Pembulatan -
Harga Satuan -
Pembulatan Harga satuan -
Nilai Pembulatan -
Pasir Beto Batu Batu Batu Batu KBata Mera Batako Paving Bl Paving Bl Paving Bl Paving Bl Semen PC Semen WaTanah uru Batu TemPlamir Te Plamir KayCat TemboKuas Roll Kuas Minyak cat
3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
1 1 1
1 1 1
1 1 1
1
1 1
1
1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1 1 1
1 1
1 1
1 1
1 1
1 1
1 1
1 1
1 1 1
1 1
1 1 1
1 1 1
1 1
1
1
1 1 1
1 1 1 1 1
1 1
1
1 1
1 1
1 1 1
1 1
1
1 1 1
1 1
1 1
1 1
1 1
1 1 1
0
0
Amplas Meni Kayu Meni Besi Cat Kayu Cat Besi Residu Lem Kayu Politur Cat Minya Cotton Pla Compoun Kayu KelasKayu KelasKayu KelasKayu KelasKayu Dolk List Plafon Baja RingaBambu Hollow 4/4
24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43
1 1
1 1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1 1
1
1 1
1
1
1 1 1
1
1 1 1
1 1
Hollow 2/4 Triplek 4m Triplek 6m Polywood Gypsum BoMultipleks Multipleks Multipleks JabarwoodKeramik 3 Keramik 4 Keramik 20Keramik 10Keramik 20Keramik 15Keramik PoKeramik PoKeramik PoKeramik PoKeramik 60
44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63
1
1 1
1
1
1
1
1
1
Granit 60 Karpet Lem KarpeWall PaperLem Wall Buis belah Besi BetonBesi BetonBesi BetonBesi Siku Besi Strip Besi Strip Kawat Bet Beghel U ( Beghel U ( Plat Baja Baut Dia. Kawat berdPagar BRCAlmunium
64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83
1
1
1 1
1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1 1
1 1 1
1
1
1 1 1
1
1 1 1
1 1
Pasak BesiRing BaskePapan PanKaca Polo Kaca Polo Paku Bias Paku Tripl Paku SengPaku Ulir Paku Gyp Dina Bolt Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa kondui
84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1
1
1
1
1
1 1
Pipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GIP 1Pipa Stainl Elbow 4" Kran Air Floor Drai Closet Jon Closet Du Bak Air MaBak Cuci SBak FibregWashtafel Urinoir Tangki Air
104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123
1
1
1
1
1
1
1
Mesin Pomp
Water Drai Jet Washe Pas. GrabbKran ShowGenteng TaBubungan Seng Gelo Seng Plat Atap Span Genteng Me
Nok Gente Nok Tepi Nok Tepi Nok Tepi GNok Tepi Kunci Pint Kunci Bula Kunci Tan Kunci Tan
124 125 126 127 128 129 130 131 132 133 134 135 136 137 138 139 140 141 142 143
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
Kunci PintuSloot Tan Grendel JeKait Angin Engsel PintEngsel JenKunci laci Pegangan/Knop TarikKasur BusaImitatie Le Sekrup 5 Kunci LemaEngsel PitaRel Pita Promika Sekrup Pe Kasur BusaKaca / Ce Gantungan
144 145 146 147 148 149 150 151 152 153 154 155 156 157 158 159 160 161 162 163
1
1
1
1
1
1
Plank nam Handel tariGrabbed BIjuk Minyak SolOli Mesra Pelumas BKabel 1x2 Kabel 2x2 Kabel 3x2 Kabel 3x2 Kabel 3x Saklar TunSaklar GanStop KontaLampu TL 2Lampu PijarBox SekrinInbowdoosIsolasi/Se
164 165 166 167 168 169 170 171 172 173 174 175 176 177 178 179 180 181 182 183
1 1
1 1
1 1 1 1
1 1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1
1
Klem KabeMCB Panel Box Air Anti RayapPupuk KanTanaman PTanama KeRumput PembentukStemper Concrete MConcrete VManual To Alat Semprot
184 185 186 187 188 189 190 191 192 193 194 195 196 197 198
1 1
1
1
1
1
1
BANTUAN SMK PUSAT KEUNGGULAN (PK)
Ekonomi Kreatif
Teknologi Informasi
REHABILITASI
Total XII -
XIII. PEKERJAAN PENGGANTUNG / PENGUNCI
1 Pas. Engsel Pintu 4" (3bh/pintu) A.12.05 bh - -
2 Pas. Engsel Jendela 3" (2bh/jendela) A.12.06 bh - -
3 Pas. Kait / Hak Angin (2bh/jendela) A.12.09 bh - -
4 Pas. Slot Pintu (2 bh/pintu)/grendel panjang A.12.10 bh - -
5 Pas. Grendel Jendela A.12.11 bh - -
6 Pas. Kunci Pintu 2 X Putar ( lever handle ) A.12.14 bh - -
7 Pas. Handel tarik jendela ls bh - -
Total XIII -
XIV. PEKERJAAN LAIN-LAIN
1 Pas. Bata Saluran Keliling Bangunan A. B m2 - -
2 Pek. Plesteran Saluran A.05.19 m2 - -
3 Pek. Urugan Pasir bawah rabat beton A.02.13 m3 - - 1
4 Pek. Pasangan Batubata dudukan Rabat Beton A.04.11 m' - -
5 Pek. Pasangan Batako dudukan Rabat Beton A.04.12 m' - -
6 Pek. Rabat Beton Keliling Bangunan A.07.01 m3 - -
7 Pek. Plank Nama Ruang ls Set - -
8 -
9 -
10 -
11 -
12 -
13 -
14 -
15 -
Total XIV -
XV. PEK. RAMPA + HAND RAILING
1 Pek. Galian Tanah A.02.01 m3 - -
2 Pek. Urugan Kembali bekas Galian A.02.11 m3 - -
3 Pek. Urugan Pasir A.02.13 m3 - - 1
4 Pek. Pasangan Pondasi Batu Kali 1 Pc : 4 Ps A.03.04 m3 - -
5 Pek. Urugan Tanah Bawah Beton A.02.12 m3 - -
6 Pek. Beton Tumbuk 1: 3 : 5 A.07.01 m3 - -
7 Pek. Canstien Pasangan Bata A.04.11 m2 - -
8 Pek. Canstien Pasangan Batako A.04.12 m2 - -
9 Pek. Pasangan Paving Block Warna (6 cm) A.13.83 m3 - -
10 Pek. Pasangan Paving Block Natural (6 cm) A.13.86 m2 - -
12 Pek. Pemasangan Hand Railing, pipa Ø 1,5 " A.01.P.11 m' - -
Total XV -
Grand Total -
Pembulatan -
Harga Satuan -
Pembulatan Harga satuan -
Nilai Pembulatan -
Pasir Beto Batu Batu Batu Batu KBata Mera Batako Paving Bl Paving Bl Paving Bl Paving Bl Semen PC Semen WaTanah uru Batu TemPlamir Te Plamir KayCat TemboKuas Roll Kuas Minyak cat
3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
1 1 1
1 1 1
1 1 1
1
1 1
1
1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1 1 1
1 1
1 1
1 1
1 1
1 1
1 1
1 1
1 1 1
1 1
1 1 1
1 1 1
1 1
1
1
1 1 1
1 1 1 1 1
1 1
1
1 1
1 1
1 1 1
1 1
1
1 1 1
1 1
1 1
1 1
1 1
1 1 1
0
0
Amplas Meni Kayu Meni Besi Cat Kayu Cat Besi Residu Lem Kayu Politur Cat Minya Cotton Pla Compoun Kayu KelasKayu KelasKayu KelasKayu KelasKayu Dolk List Plafon Baja RingaBambu Hollow 4/4
24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43
1 1
1 1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1 1
1
1 1
1
1
1 1 1
1
1 1 1
1 1
Hollow 2/4 Triplek 4m Triplek 6m Polywood Gypsum BoMultipleks Multipleks Multipleks JabarwoodKeramik 3 Keramik 4 Keramik 20Keramik 10Keramik 20Keramik 15Keramik PoKeramik PoKeramik PoKeramik PoKeramik 60
44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63
1
1 1
1
1
1
1
1
1
Granit 60 Karpet Lem KarpeWall PaperLem Wall Buis belah Besi BetonBesi BetonBesi BetonBesi Siku Besi Strip Besi Strip Kawat Bet Beghel U ( Beghel U ( Plat Baja Baut Dia. Kawat berdPagar BRCAlmunium
64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83
1
1
1 1
1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1 1
1 1 1
1
1
1 1 1
1
1 1 1
1 1
Pasak BesiRing BaskePapan PanKaca Polo Kaca Polo Paku Bias Paku Tripl Paku SengPaku Ulir Paku Gyp Dina Bolt Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa kondui
84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1
1
1
1
1
1 1
Pipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GIP 1Pipa Stainl Elbow 4" Kran Air Floor Drai Closet Jon Closet Du Bak Air MaBak Cuci SBak FibregWashtafel Urinoir Tangki Air
104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123
1
1
1
1
1
1
1
Mesin Pomp
Water Drai Jet Washe Pas. GrabbKran ShowGenteng TaBubungan Seng Gelo Seng Plat Atap Span Genteng Me
Nok Gente Nok Tepi Nok Tepi Nok Tepi GNok Tepi Kunci Pint Kunci Bula Kunci Tan Kunci Tan
124 125 126 127 128 129 130 131 132 133 134 135 136 137 138 139 140 141 142 143
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
Kunci PintuSloot Tan Grendel JeKait Angin Engsel PintEngsel JenKunci laci Pegangan/Knop TarikKasur BusaImitatie Le Sekrup 5 Kunci LemaEngsel PitaRel Pita Promika Sekrup Pe Kasur BusaKaca / Ce Gantungan
144 145 146 147 148 149 150 151 152 153 154 155 156 157 158 159 160 161 162 163
1
1
1
1
1
1
Plank nam Handel tariGrabbed BIjuk Minyak SolOli Mesra Pelumas BKabel 1x2 Kabel 2x2 Kabel 3x2 Kabel 3x2 Kabel 3x Saklar TunSaklar GanStop KontaLampu TL 2Lampu PijarBox SekrinInbowdoosIsolasi/Se
164 165 166 167 168 169 170 171 172 173 174 175 176 177 178 179 180 181 182 183
1 1
1 1
1 1 1 1
1 1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1
1
Klem KabeMCB Panel Box Air Anti RayapPupuk KanTanaman PTanama KeRumput PembentukStemper Concrete MConcrete VManual To Alat Semprot
184 185 186 187 188 189 190 191 192 193 194 195 196 197 198
1 1
1
1
1
1
1
BANTUAN SMK PUSAT KEUNGGULAN (PK)
Ekonomi Kreatif
Teknologi Informasi
REDESAIN
Total XII -
XIII. PEKERJAAN PENGGANTUNG / PENGUNCI
1 Pas. Engsel Pintu 4" (3bh/pintu) A.12.05 bh - -
2 Pas. Engsel Jendela 3" (2bh/jendela) A.12.06 bh - -
3 Pas. Kait / Hak Angin (2bh/jendela) A.12.09 bh - -
4 Pas. Slot Pintu (2 bh/pintu)/grendel panjang A.12.10 bh - -
5 Pas. Grendel Jendela A.12.11 bh - -
6 Pas. Kunci Pintu 2 X Putar ( lever handle ) A.12.14 bh - -
7 Pas. Handel tarik jendela ls bh - -
Total XIII -
XIV. PEKERJAAN LAIN-LAIN
1 Pas. Bata Saluran Keliling Bangunan A. B m2 - -
2 Pek. Plesteran Saluran A.05.19 m2 - -
3 Pek. Urugan Pasir bawah rabat beton A.02.13 m3 - - 1
4 Pek. Pasangan Batubata dudukan Rabat Beton A.04.11 m' - -
5 Pek. Pasangan Batako dudukan Rabat Beton A.04.12 m' - -
6 Pek. Rabat Beton Keliling Bangunan A.07.01 m3 - -
7 Pek. Plank Nama Ruang ls Set - -
8 -
9 -
10 -
11 -
12 -
13 -
14 -
15 -
Total XIV -
XV. PEK. RAMPA + HAND RAILING
1 Pek. Galian Tanah A.02.01 m3 - -
2 Pek. Urugan Kembali bekas Galian A.02.11 m3 - -
3 Pek. Urugan Pasir A.02.13 m3 - - 1
4 Pek. Pasangan Pondasi Batu Kali 1 Pc : 4 Ps A.03.04 m3 - -
5 Pek. Urugan Tanah Bawah Beton A.02.12 m3 - -
6 Pek. Beton Tumbuk 1: 3 : 5 A.07.01 m3 - -
7 Pek. Canstien Pasangan Bata A.04.11 m2 - -
8 Pek. Canstien Pasangan Batako A.04.12 m2 - -
9 Pek. Pasangan Paving Block Warna (6 cm) A.13.83 m3 - -
10 Pek. Pasangan Paving Block Natural (6 cm) A.13.86 m2 - -
12 Pek. Pemasangan Hand Railing, pipa Ø 1,5 " A.01.P.11 m' - -
Total XV -
Grand Total -
Pembulatan -
Harga Satuan -
Pembulatan Harga satuan -
Nilai Pembulatan -
Pasir Beto Batu Batu Batu Batu KBata Mera Batako Paving Bl Paving Bl Paving Bl Paving Bl Semen PC Semen WaTanah uru Batu TemPlamir Te Plamir KayCat TemboKuas Roll Kuas Minyak cat
3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
1 1 1
1 1 1
1 1 1
1
1 1
1
1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1 1 1
1 1
1 1
1 1
1 1
1 1
1 1
1 1
1 1 1
1 1
1 1 1
1 1 1
1 1
1
1
1 1 1
1 1 1 1 1
1 1
1
1 1
1 1
1 1 1
1 1
1
1 1 1
1 1
1 1
1 1
1 1
1 1 1
0
0
Amplas Meni Kayu Meni Besi Cat Kayu Cat Besi Residu Lem Kayu Politur Cat Minya Cotton Pla Compoun Kayu KelasKayu KelasKayu KelasKayu KelasKayu Dolk List Plafon Baja RingaBambu Hollow 4/4
24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43
1 1
1 1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1 1
1
1 1
1
1
1 1 1
1
1 1 1
1 1
Hollow 2/4 Triplek 4m Triplek 6m Polywood Gypsum BoMultipleks Multipleks Multipleks JabarwoodKeramik 3 Keramik 4 Keramik 20Keramik 10Keramik 20Keramik 15Keramik PoKeramik PoKeramik PoKeramik PoKeramik 60
44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63
1
1 1
1
1
1
1
1
1
Granit 60 Karpet Lem KarpeWall PaperLem Wall Buis belah Besi BetonBesi BetonBesi BetonBesi Siku Besi Strip Besi Strip Kawat Bet Beghel U ( Beghel U ( Plat Baja Baut Dia. Kawat berdPagar BRCAlmunium
64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83
1
1
1 1
1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1 1
1 1 1
1
1
1 1 1
1
1 1 1
1 1
Pasak BesiRing BaskePapan PanKaca Polo Kaca Polo Paku Bias Paku Tripl Paku SengPaku Ulir Paku Gyp Dina Bolt Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa kondui
84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1
1
1
1
1
1 1
Pipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GIP 1Pipa Stainl Elbow 4" Kran Air Floor Drai Closet Jon Closet Du Bak Air MaBak Cuci SBak FibregWashtafel Urinoir Tangki Air
104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123
1
1
1
1
1
1
1
Mesin Pomp
Water Drai Jet Washe Pas. GrabbKran ShowGenteng TaBubungan Seng Gelo Seng Plat Atap Span Genteng Me
Nok Gente Nok Tepi Nok Tepi Nok Tepi GNok Tepi Kunci Pint Kunci Bula Kunci Tan Kunci Tan
124 125 126 127 128 129 130 131 132 133 134 135 136 137 138 139 140 141 142 143
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
Kunci PintuSloot Tan Grendel JeKait Angin Engsel PintEngsel JenKunci laci Pegangan/Knop TarikKasur BusaImitatie Le Sekrup 5 Kunci LemaEngsel PitaRel Pita Promika Sekrup Pe Kasur BusaKaca / Ce Gantungan
144 145 146 147 148 149 150 151 152 153 154 155 156 157 158 159 160 161 162 163
1
1
1
1
1
1
Plank nam Handel tariGrabbed BIjuk Minyak SolOli Mesra Pelumas BKabel 1x2 Kabel 2x2 Kabel 3x2 Kabel 3x2 Kabel 3x Saklar TunSaklar GanStop KontaLampu TL 2Lampu PijarBox SekrinInbowdoosIsolasi/Se
164 165 166 167 168 169 170 171 172 173 174 175 176 177 178 179 180 181 182 183
1 1
1 1
1 1 1 1
1 1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1
1
Klem KabeMCB Panel Box Air Anti RayapPupuk KanTanaman PTanama KeRumput PembentukStemper Concrete MConcrete VManual To Alat Semprot
184 185 186 187 188 189 190 191 192 193 194 195 196 197 198
1 1
1
1
1
1
1
BANTUAN SMK PUSAT KEUNGGULAN (PK)
Ekonomi Kreatif
Teknologi Informasi
REDESAIN
Total XII -
XIII. PEKERJAAN PENGGANTUNG / PENGUNCI
1 Pas. Engsel Pintu 4" (3bh/pintu) A.12.05 bh - -
2 Pas. Engsel Jendela 3" (2bh/jendela) A.12.06 bh - -
3 Pas. Kait / Hak Angin (2bh/jendela) A.12.09 bh - -
4 Pas. Slot Pintu (2 bh/pintu)/grendel panjang A.12.10 bh - -
5 Pas. Grendel Jendela A.12.11 bh - -
6 Pas. Kunci Pintu 2 X Putar ( lever handle ) A.12.14 bh - -
7 Pas. Handel tarik jendela ls bh - -
Total XIII -
XIV. PEKERJAAN LAIN-LAIN
1 Pas. Bata Saluran Keliling Bangunan A. B m2 - -
2 Pek. Plesteran Saluran A.05.19 m2 - -
3 Pek. Urugan Pasir bawah rabat beton A.02.13 m3 - - 1
4 Pek. Pasangan Batubata dudukan Rabat Beton A.04.11 m' - -
5 Pek. Pasangan Batako dudukan Rabat Beton A.04.12 m' - -
6 Pek. Rabat Beton Keliling Bangunan A.07.01 m3 - -
7 Pek. Plank Nama Ruang ls Set - -
8 -
9 -
10 -
11 -
12 -
13 -
14 -
15 -
Total XIV -
XV. PEK. RAMPA + HAND RAILING
1 Pek. Galian Tanah A.02.01 m3 - -
2 Pek. Urugan Kembali bekas Galian A.02.11 m3 - -
3 Pek. Urugan Pasir A.02.13 m3 - - 1
4 Pek. Pasangan Pondasi Batu Kali 1 Pc : 4 Ps A.03.04 m3 - -
5 Pek. Urugan Tanah Bawah Beton A.02.12 m3 - -
6 Pek. Beton Tumbuk 1: 3 : 5 A.07.01 m3 - -
7 Pek. Canstien Pasangan Bata A.04.11 m2 - -
8 Pek. Canstien Pasangan Batako A.04.12 m2 - -
9 Pek. Pasangan Paving Block Warna (6 cm) A.13.83 m3 - -
10 Pek. Pasangan Paving Block Natural (6 cm) A.13.86 m2 - -
12 Pek. Pemasangan Hand Railing, pipa Ø 1,5 " A.01.P.11 m' - -
Total XV -
Grand Total -
Pembulatan -
Harga Satuan -
Pembulatan Harga satuan -
Nilai Pembulatan -
Pasir Beto Batu Batu Batu Batu KBata Mera Batako Paving Bl Paving Bl Paving Bl Paving Bl Semen PC Semen WaTanah uru Batu TemPlamir Te Plamir KayCat TemboKuas Roll Kuas Minyak cat
3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
1 1 1
1 1 1
1 1 1
1
1 1
1
1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1 1 1
1 1
1 1
1 1
1 1
1 1
1 1
1 1
1 1 1
1 1
1 1 1
1 1 1
1 1
1
1
1 1 1
1 1 1 1 1
1 1
1
1 1
1 1
1 1 1
1 1
1
1 1 1
1 1
1 1
1 1
1 1
1 1 1
0
0
Amplas Meni Kayu Meni Besi Cat Kayu Cat Besi Residu Lem Kayu Politur Cat Minya Cotton Pla Compoun Kayu KelasKayu KelasKayu KelasKayu KelasKayu Dolk List Plafon Baja RingaBambu Hollow 4/4
24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43
1 1
1 1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1 1
1
1 1
1
1
1 1 1
1
1 1 1
1 1
Hollow 2/4 Triplek 4m Triplek 6m Polywood Gypsum BoMultipleks Multipleks Multipleks JabarwoodKeramik 3 Keramik 4 Keramik 20Keramik 10Keramik 20Keramik 15Keramik PoKeramik PoKeramik PoKeramik PoKeramik 60
44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63
1
1 1
1
1
1
1
1
1
Granit 60 Karpet Lem KarpeWall PaperLem Wall Buis belah Besi BetonBesi BetonBesi BetonBesi Siku Besi Strip Besi Strip Kawat Bet Beghel U ( Beghel U ( Plat Baja Baut Dia. Kawat berdPagar BRCAlmunium
64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83
1
1
1 1
1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1 1
1 1 1
1
1
1 1 1
1
1 1 1
1 1
Pasak BesiRing BaskePapan PanKaca Polo Kaca Polo Paku Bias Paku Tripl Paku SengPaku Ulir Paku Gyp Dina Bolt Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa kondui
84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1
1
1
1
1
1 1
Pipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GIP 1Pipa Stainl Elbow 4" Kran Air Floor Drai Closet Jon Closet Du Bak Air MaBak Cuci SBak FibregWashtafel Urinoir Tangki Air
104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123
1
1
1
1
1
1
1
Mesin Pomp
Water Drai Jet Washe Pas. GrabbKran ShowGenteng TaBubungan Seng Gelo Seng Plat Atap Span Genteng Me
Nok Gente Nok Tepi Nok Tepi Nok Tepi GNok Tepi Kunci Pint Kunci Bula Kunci Tan Kunci Tan
124 125 126 127 128 129 130 131 132 133 134 135 136 137 138 139 140 141 142 143
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
Kunci PintuSloot Tan Grendel JeKait Angin Engsel PintEngsel JenKunci laci Pegangan/Knop TarikKasur BusaImitatie Le Sekrup 5 Kunci LemaEngsel PitaRel Pita Promika Sekrup Pe Kasur BusaKaca / Ce Gantungan
144 145 146 147 148 149 150 151 152 153 154 155 156 157 158 159 160 161 162 163
1
1
1
1
1
1
Plank nam Handel tariGrabbed BIjuk Minyak SolOli Mesra Pelumas BKabel 1x2 Kabel 2x2 Kabel 3x2 Kabel 3x2 Kabel 3x Saklar TunSaklar GanStop KontaLampu TL 2Lampu PijarBox SekrinInbowdoosIsolasi/Se
164 165 166 167 168 169 170 171 172 173 174 175 176 177 178 179 180 181 182 183
1 1
1 1
1 1 1 1
1 1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1
1
Klem KabeMCB Panel Box Air Anti RayapPupuk KanTanaman PTanama KeRumput PembentukStemper Concrete MConcrete VManual To Alat Semprot
184 185 186 187 188 189 190 191 192 193 194 195 196 197 198
1 1
1
1
1
1
1
BANTUAN SMK PUSAT KEUNGGULAN (PK)
Ekonomi Kreatif
Teknologi Informasi
REDESAIN
Total XII -
XIII. PEKERJAAN PENGGANTUNG / PENGUNCI
1 Pas. Engsel Pintu 4" (3bh/pintu) A.12.05 bh - -
2 Pas. Engsel Jendela 3" (2bh/jendela) A.12.06 bh - -
3 Pas. Kait / Hak Angin (2bh/jendela) A.12.09 bh - -
4 Pas. Slot Pintu (2 bh/pintu)/grendel panjang A.12.10 bh - -
5 Pas. Grendel Jendela A.12.11 bh - -
6 Pas. Kunci Pintu 2 X Putar ( lever handle ) A.12.14 bh - -
7 Pas. Handel tarik jendela ls bh - -
Total XIII -
XIV. PEKERJAAN LAIN-LAIN
1 Pas. Bata Saluran Keliling Bangunan A. B m2 - -
2 Pek. Plesteran Saluran A.05.19 m2 - -
3 Pek. Urugan Pasir bawah rabat beton A.02.13 m3 - - 1
4 Pek. Pasangan Batubata dudukan Rabat Beton A.04.11 m' - -
5 Pek. Pasangan Batako dudukan Rabat Beton A.04.12 m' - -
6 Pek. Rabat Beton Keliling Bangunan A.07.01 m3 - -
7 Pek. Plank Nama Ruang ls Set - -
8 -
9 -
10 -
11 -
12 -
13 -
14 -
15 -
Total XIV -
XV. PEK. RAMPA + HAND RAILING
1 Pek. Galian Tanah A.02.01 m3 - -
2 Pek. Urugan Kembali bekas Galian A.02.11 m3 - -
3 Pek. Urugan Pasir A.02.13 m3 - - 1
4 Pek. Pasangan Pondasi Batu Kali 1 Pc : 4 Ps A.03.04 m3 - -
5 Pek. Urugan Tanah Bawah Beton A.02.12 m3 - -
6 Pek. Beton Tumbuk 1: 3 : 5 A.07.01 m3 - -
7 Pek. Canstien Pasangan Bata A.04.11 m2 - -
8 Pek. Canstien Pasangan Batako A.04.12 m2 - -
9 Pek. Pasangan Paving Block Warna (6 cm) A.13.83 m3 - -
10 Pek. Pasangan Paving Block Natural (6 cm) A.13.86 m2 - -
12 Pek. Pemasangan Hand Railing, pipa Ø 1,5 " A.01.P.11 m' - -
Total XV -
Grand Total -
Pembulatan -
Harga Satuan -
Pembulatan Harga satuan -
Nilai Pembulatan -
Pasir Beto Batu Batu Batu Batu KBata Mera Batako Paving Bl Paving Bl Paving Bl Paving Bl Semen PC Semen WaTanah uru Batu TemPlamir Te Plamir KayCat TemboKuas Roll Kuas Minyak cat
3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
1 1 1
1 1 1
1 1 1
1
1 1
1
1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1 1 1
1 1
1 1
1 1
1 1
1 1
1 1
1 1
1 1 1
1 1
1 1 1
1 1 1
1 1
1
1
1 1 1
1 1 1 1 1
1 1
1
1 1
1 1
1 1 1
1 1
1
1 1 1
1 1
1 1
1 1
1 1
1 1 1
0
0
Amplas Meni Kayu Meni Besi Cat Kayu Cat Besi Residu Lem Kayu Politur Cat Minya Cotton Pla Compoun Kayu KelasKayu KelasKayu KelasKayu KelasKayu Dolk List Plafon Baja RingaBambu Hollow 4/4
24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43
1 1
1 1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1 1
1
1 1
1
1
1 1 1
1
1 1 1
1 1
Hollow 2/4 Triplek 4m Triplek 6m Polywood Gypsum BoMultipleks Multipleks Multipleks JabarwoodKeramik 3 Keramik 4 Keramik 20Keramik 10Keramik 20Keramik 15Keramik PoKeramik PoKeramik PoKeramik PoKeramik 60
44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63
1
1 1
1
1
1
1
1
1
Granit 60 Karpet Lem KarpeWall PaperLem Wall Buis belah Besi BetonBesi BetonBesi BetonBesi Siku Besi Strip Besi Strip Kawat Bet Beghel U ( Beghel U ( Plat Baja Baut Dia. Kawat berdPagar BRCAlmunium
64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83
1
1
1 1
1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1 1
1 1 1
1
1
1 1 1
1
1 1 1
1 1
Pasak BesiRing BaskePapan PanKaca Polo Kaca Polo Paku Bias Paku Tripl Paku SengPaku Ulir Paku Gyp Dina Bolt Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa kondui
84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1
1
1
1
1
1 1
Pipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GIP 1Pipa Stainl Elbow 4" Kran Air Floor Drai Closet Jon Closet Du Bak Air MaBak Cuci SBak FibregWashtafel Urinoir Tangki Air
104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123
1
1
1
1
1
1
1
Mesin Pomp
Water Drai Jet Washe Pas. GrabbKran ShowGenteng TaBubungan Seng Gelo Seng Plat Atap Span Genteng Me
Nok Gente Nok Tepi Nok Tepi Nok Tepi GNok Tepi Kunci Pint Kunci Bula Kunci Tan Kunci Tan
124 125 126 127 128 129 130 131 132 133 134 135 136 137 138 139 140 141 142 143
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
Kunci PintuSloot Tan Grendel JeKait Angin Engsel PintEngsel JenKunci laci Pegangan/Knop TarikKasur BusaImitatie Le Sekrup 5 Kunci LemaEngsel PitaRel Pita Promika Sekrup Pe Kasur BusaKaca / Ce Gantungan
144 145 146 147 148 149 150 151 152 153 154 155 156 157 158 159 160 161 162 163
1
1
1
1
1
1
Plank nam Handel tariGrabbed BIjuk Minyak SolOli Mesra Pelumas BKabel 1x2 Kabel 2x2 Kabel 3x2 Kabel 3x2 Kabel 3x Saklar TunSaklar GanStop KontaLampu TL 2Lampu PijarBox SekrinInbowdoosIsolasi/Se
164 165 166 167 168 169 170 171 172 173 174 175 176 177 178 179 180 181 182 183
1 1
1 1
1 1 1 1
1 1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1
1
Klem KabeMCB Panel Box Air Anti RayapPupuk KanTanaman PTanama KeRumput PembentukStemper Concrete MConcrete VManual To Alat Semprot
184 185 186 187 188 189 190 191 192 193 194 195 196 197 198
1 1
1
1
1
1
1
BANTUAN SMK PUSAT KEUNGGULAN (PK)
Ekonomi Kreatif
Teknologi Informasi
REDESAIN
Total XII -
XIII. PEKERJAAN PENGGANTUNG / PENGUNCI
1 Pas. Engsel Pintu 4" (3bh/pintu) A.12.05 bh - -
2 Pas. Engsel Jendela 3" (2bh/jendela) A.12.06 bh - -
3 Pas. Kait / Hak Angin (2bh/jendela) A.12.09 bh - -
4 Pas. Slot Pintu (2 bh/pintu)/grendel panjang A.12.10 bh - -
5 Pas. Grendel Jendela A.12.11 bh - -
6 Pas. Kunci Pintu 2 X Putar ( lever handle ) A.12.14 bh - -
7 Pas. Handel tarik jendela ls bh - -
Total XIII -
XIV. PEKERJAAN LAIN-LAIN
1 Pas. Bata Saluran Keliling Bangunan A. B m2 - -
2 Pek. Plesteran Saluran A.05.19 m2 - -
3 Pek. Urugan Pasir bawah rabat beton A.02.13 m3 - - 1
4 Pek. Pasangan Batubata dudukan Rabat Beton A.04.11 m' - -
5 Pek. Pasangan Batako dudukan Rabat Beton A.04.12 m' - -
6 Pek. Rabat Beton Keliling Bangunan A.07.01 m3 - -
7 Pek. Plank Nama Ruang ls Set - -
8 -
9 -
10 -
11 -
12 -
13 -
14 -
15 -
Total XIV -
XV. PEK. RAMPA + HAND RAILING
1 Pek. Galian Tanah A.02.01 m3 - -
2 Pek. Urugan Kembali bekas Galian A.02.11 m3 - -
3 Pek. Urugan Pasir A.02.13 m3 - - 1
4 Pek. Pasangan Pondasi Batu Kali 1 Pc : 4 Ps A.03.04 m3 - -
5 Pek. Urugan Tanah Bawah Beton A.02.12 m3 - -
6 Pek. Beton Tumbuk 1: 3 : 5 A.07.01 m3 - -
7 Pek. Canstien Pasangan Bata A.04.11 m2 - -
8 Pek. Canstien Pasangan Batako A.04.12 m2 - -
9 Pek. Pasangan Paving Block Warna (6 cm) A.13.83 m3 - -
10 Pek. Pasangan Paving Block Natural (6 cm) A.13.86 m2 - -
12 Pek. Pemasangan Hand Railing, pipa Ø 1,5 " A.01.P.11 m' - -
Total XV -
Grand Total -
Pembulatan -
Harga Satuan -
Pembulatan Harga satuan -
Nilai Pembulatan -
Pasir Beto Batu Batu Batu Batu KBata Mera Batako Paving Bl Paving Bl Paving Bl Paving Bl Semen PC Semen WaTanah uru Batu TemPlamir Te Plamir KayCat TemboKuas Roll Kuas Minyak cat
3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
1 1 1
1 1 1
1 1 1
1
1 1
1
1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1 1 1
1 1
1 1
1 1
1 1
1 1
1 1
1 1
1 1 1
1 1
1 1 1
1 1 1
1 1
1
1
1 1 1
1 1 1 1 1
1 1
1
1 1
1 1
1 1 1
1 1
1
1 1 1
1 1
1 1
1 1
1 1
1 1 1
0
0
Amplas Meni Kayu Meni Besi Cat Kayu Cat Besi Residu Lem Kayu Politur Cat Minya Cotton Pla Compoun Kayu KelasKayu KelasKayu KelasKayu KelasKayu Dolk List Plafon Baja RingaBambu Hollow 4/4
24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43
1 1
1 1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1 1
1
1 1
1
1
1 1 1
1
1 1 1
1 1
Hollow 2/4 Triplek 4m Triplek 6m Polywood Gypsum BoMultipleks Multipleks Multipleks JabarwoodKeramik 3 Keramik 4 Keramik 20Keramik 10Keramik 20Keramik 15Keramik PoKeramik PoKeramik PoKeramik PoKeramik 60
44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63
1
1 1
1
1
1
1
1
1
Granit 60 Karpet Lem KarpeWall PaperLem Wall Buis belah Besi BetonBesi BetonBesi BetonBesi Siku Besi Strip Besi Strip Kawat Bet Beghel U ( Beghel U ( Plat Baja Baut Dia. Kawat berdPagar BRCAlmunium
64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83
1
1
1 1
1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1 1
1 1 1
1
1
1 1 1
1
1 1 1
1 1
Pasak BesiRing BaskePapan PanKaca Polo Kaca Polo Paku Bias Paku Tripl Paku SengPaku Ulir Paku Gyp Dina Bolt Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa kondui
84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1
1
1
1
1
1 1
Pipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GIP 1Pipa Stainl Elbow 4" Kran Air Floor Drai Closet Jon Closet Du Bak Air MaBak Cuci SBak FibregWashtafel Urinoir Tangki Air
104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123
1
1
1
1
1
1
1
Mesin Pomp
Water Drai Jet Washe Pas. GrabbKran ShowGenteng TaBubungan Seng Gelo Seng Plat Atap Span Genteng Me
Nok Gente Nok Tepi Nok Tepi Nok Tepi GNok Tepi Kunci Pint Kunci Bula Kunci Tan Kunci Tan
124 125 126 127 128 129 130 131 132 133 134 135 136 137 138 139 140 141 142 143
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
Kunci PintuSloot Tan Grendel JeKait Angin Engsel PintEngsel JenKunci laci Pegangan/Knop TarikKasur BusaImitatie Le Sekrup 5 Kunci LemaEngsel PitaRel Pita Promika Sekrup Pe Kasur BusaKaca / Ce Gantungan
144 145 146 147 148 149 150 151 152 153 154 155 156 157 158 159 160 161 162 163
1
1
1
1
1
1
Plank nam Handel tariGrabbed BIjuk Minyak SolOli Mesra Pelumas BKabel 1x2 Kabel 2x2 Kabel 3x2 Kabel 3x2 Kabel 3x Saklar TunSaklar GanStop KontaLampu TL 2Lampu PijarBox SekrinInbowdoosIsolasi/Se
164 165 166 167 168 169 170 171 172 173 174 175 176 177 178 179 180 181 182 183
1 1
1 1
1 1 1 1
1 1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1
1
Klem KabeMCB Panel Box Air Anti RayapPupuk KanTanaman PTanama KeRumput PembentukStemper Concrete MConcrete VManual To Alat Semprot
184 185 186 187 188 189 190 191 192 193 194 195 196 197 198
1 1
1
1
1
1
1
BANTUAN SMK PUSAT KEUNGGULAN (PK)
Ekonomi Kreatif
Teknologi Informasi
REDESAIN
Total XII -
XIII. PEKERJAAN PENGGANTUNG / PENGUNCI
1 Pas. Engsel Pintu 4" (3bh/pintu) A.12.05 bh - -
2 Pas. Engsel Jendela 3" (2bh/jendela) A.12.06 bh - -
3 Pas. Kait / Hak Angin (2bh/jendela) A.12.09 bh - -
4 Pas. Slot Pintu (2 bh/pintu)/grendel panjang A.12.10 bh - -
5 Pas. Grendel Jendela A.12.11 bh - -
6 Pas. Kunci Pintu 2 X Putar ( lever handle ) A.12.14 bh - -
7 Pas. Handel tarik jendela ls bh - -
Total XIII -
XIV. PEKERJAAN LAIN-LAIN
1 Pas. Bata Saluran Keliling Bangunan A. B m2 - -
2 Pek. Plesteran Saluran A.05.19 m2 - -
3 Pek. Urugan Pasir bawah rabat beton A.02.13 m3 - - 1
4 Pek. Pasangan Batubata dudukan Rabat Beton A.04.11 m' - -
5 Pek. Pasangan Batako dudukan Rabat Beton A.04.12 m' - -
6 Pek. Rabat Beton Keliling Bangunan A.07.01 m3 - -
7 Pek. Plank Nama Ruang ls Set - -
8 -
9 -
10 -
11 -
12 -
13 -
14 -
15 -
Total XIV -
XV. PEK. RAMPA + HAND RAILING
1 Pek. Galian Tanah A.02.01 m3 - -
2 Pek. Urugan Kembali bekas Galian A.02.11 m3 - -
3 Pek. Urugan Pasir A.02.13 m3 - - 1
4 Pek. Pasangan Pondasi Batu Kali 1 Pc : 4 Ps A.03.04 m3 - -
5 Pek. Urugan Tanah Bawah Beton A.02.12 m3 - -
6 Pek. Beton Tumbuk 1: 3 : 5 A.07.01 m3 - -
7 Pek. Canstien Pasangan Bata A.04.11 m2 - -
8 Pek. Canstien Pasangan Batako A.04.12 m2 - -
9 Pek. Pasangan Paving Block Warna (6 cm) A.13.83 m3 - -
10 Pek. Pasangan Paving Block Natural (6 cm) A.13.86 m2 - -
12 Pek. Pemasangan Hand Railing, pipa Ø 1,5 " A.01.P.11 m' - -
Total XV -
Grand Total -
Pembulatan -
Harga Satuan -
Pembulatan Harga satuan -
Nilai Pembulatan -
Pasir Beto Batu Batu Batu Batu KBata Mera Batako Paving Bl Paving Bl Paving Bl Paving Bl Semen PC Semen WaTanah uru Batu TemPlamir Te Plamir KayCat TemboKuas Roll Kuas Minyak cat
3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
1 1 1
1 1 1
1 1 1
1
1 1
1
1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1 1 1
1 1
1 1
1 1
1 1
1 1
1 1
1 1
1 1 1
1 1
1 1 1
1 1 1
1 1
1
1
1 1 1
1 1 1 1 1
1 1
1
1 1
1 1
1 1 1
1 1
1
1 1 1
1 1
1 1
1 1
1 1
1 1 1
0
0
Amplas Meni Kayu Meni Besi Cat Kayu Cat Besi Residu Lem Kayu Politur Cat Minya Cotton Pla Compoun Kayu KelasKayu KelasKayu KelasKayu KelasKayu Dolk List Plafon Baja RingaBambu Hollow 4/4
24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43
1 1
1 1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1 1
1 1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1 1
1
1 1
1
1
1 1 1
1
1 1 1
1 1
Hollow 2/4 Triplek 4m Triplek 6m Polywood Gypsum BoMultipleks Multipleks Multipleks JabarwoodKeramik 3 Keramik 4 Keramik 20Keramik 10Keramik 20Keramik 15Keramik PoKeramik PoKeramik PoKeramik PoKeramik 60
44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63
1
1 1
1
1
1
1
1
1
Granit 60 Karpet Lem KarpeWall PaperLem Wall Buis belah Besi BetonBesi BetonBesi BetonBesi Siku Besi Strip Besi Strip Kawat Bet Beghel U ( Beghel U ( Plat Baja Baut Dia. Kawat berdPagar BRCAlmunium
64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83
1
1
1 1
1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1 1
1 1 1
1
1
1 1 1
1
1 1 1
1 1
Pasak BesiRing BaskePapan PanKaca Polo Kaca Polo Paku Bias Paku Tripl Paku SengPaku Ulir Paku Gyp Dina Bolt Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa PVC Pipa kondui
84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 1
1
1
1
1
1
1
1
1
1
1
1
1 1
Pipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GalvaPipa GIP 1Pipa Stainl Elbow 4" Kran Air Floor Drai Closet Jon Closet Du Bak Air MaBak Cuci SBak FibregWashtafel Urinoir Tangki Air
104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123
1
1
1
1
1
1
1
Mesin Pomp
Water Drai Jet Washe Pas. GrabbKran ShowGenteng TaBubungan Seng Gelo Seng Plat Atap Span Genteng Me
Nok Gente Nok Tepi Nok Tepi Nok Tepi GNok Tepi Kunci Pint Kunci Bula Kunci Tan Kunci Tan
124 125 126 127 128 129 130 131 132 133 134 135 136 137 138 139 140 141 142 143
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
Kunci PintuSloot Tan Grendel JeKait Angin Engsel PintEngsel JenKunci laci Pegangan/Knop TarikKasur BusaImitatie Le Sekrup 5 Kunci LemaEngsel PitaRel Pita Promika Sekrup Pe Kasur BusaKaca / Ce Gantungan
144 145 146 147 148 149 150 151 152 153 154 155 156 157 158 159 160 161 162 163
1
1
1
1
1
1
Plank nam Handel tariGrabbed BIjuk Minyak SolOli Mesra Pelumas BKabel 1x2 Kabel 2x2 Kabel 3x2 Kabel 3x2 Kabel 3x Saklar TunSaklar GanStop KontaLampu TL 2Lampu PijarBox SekrinInbowdoosIsolasi/Se
164 165 166 167 168 169 170 171 172 173 174 175 176 177 178 179 180 181 182 183
1 1
1 1
1 1 1 1
1 1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1
1 1
1
1
Klem KabeMCB Panel Box Air Anti RayapPupuk KanTanaman PTanama KeRumput PembentukStemper Concrete MConcrete VManual To Alat Semprot
184 185 186 187 188 189 190 191 192 193 194 195 196 197 198
1 1
1
1
1
1
1
Perencanaan Dan Pengawasan
NPSN : 10404048
NAMA SEKOLAH : SMKS PGRI PEKANBARU
KABUPATEN : Kota Pekanbaru 12568987.0000
PROVINSI : Prov. Riau 4189662.3333
4,189,000
Pekerjaan : PERENCANAAN Dan PENGAWASAN
Harga Satuan
No Uraian Pekerjaan Volume Sat Periode Sat
( Rp )
2 3 5 6 7 8
I. Biaya Perencanaan dan Pengawasan
Jumlah Harga
( Rp )
9
Harga
- 3% dari Biaya Fisik jika lebih dari 50jt, maka ditetapkan nilai maksimal 50jt
- 2% dari Biaya Fisik jika lebih dari 30jt, maka ditetapkan nilai maksimal 30jt
-
-
-
-
BIAYA PENGELOLAAN
NPSN : 10404048
NAMA SEKOLAH : SMKS PGRI PEKANBARU
KABUPATEN : Kota Pekanbaru
PROVINSI : Prov. Riau
Harga Satuan
No Uraian Pekerjaan Volume Sat Periode Sat
( Rp )
2 3 5 6 7 8
I OPERASIONAL KOMITE PEMBANGUNAN
1 Alat Tulis Kantor
- Kertas 2.00 rim 4.00 bln
- Tinta Printer 1.00 unit 4.00 bln
- Pulpen, Spidol, Pinsil, Penghapus, Penggaris, dll 1.00 set 4.00 bln
- Odner 5.00 bh 1.00 kali
- ……. 1.00 unit 1.00 kali
- ……. 1.00 unit 1.00 kali
- ……. 1.00 unit 1.00 kali
- ……. 1.00 unit 1.00 kali
- ……. 1.00 unit 1.00 kali
- ……. 1.00 unit 1.00 kali
- ……. 1.00 unit 1.00 kali
- …….
2 Komunikasi Kerja
- Pulsa Telepon/HP 2.00 unit 4.00 bln
3 Penyelenggaraan Rapat Koordinasi Mingguan
- Konsumsi 1.00 ls 16.00 minggu
4 Transportasi
- Survey Harga Material & Bahan 2.00 trip (PP) 4.00 bln
- Pengambilan Dana ke Bank 4.00 trip (PP) 4.00 bln
5 Penyusunan dan Penggandaan Pelaporan
- Laporan Bulanan 2.00 set 4.00 bln
- Laporan Tahap 1 4.00 set 1.00 kali
- Laporan Tahap 2 / Laporan Akhir 4.00 set 1.00 kali
- Dokumentasi 4.00 ls 1.00 kali
Total
Jumlah Harga
( Rp )
9
1% dari Biaya Fisik Harga
-
- jika lebih dari 20jt, maka
- ditetapkan nilai maksimal
- 20jt
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- Harga Tertinggi 0
-
-
-
PEKERJAAN INTERIOR DAN PERABOT
NPSN : 10404048
Nama Sekolah : SMKS PGRI PEKANBARU
Kabupaten : Kota Pekanbaru
Propinsi : Prov. Riau
Pekerjaan : Perabot
Grand Total -