Anda di halaman 1dari 38

HARGA UPAH DAN BAHAN BANGUNAN

KABUPATEN GUNUNG MAS TRIWULAN I


TAHUN 2015

A. HARGA UPAH
NO URAIAN SATUAN UPAH
1 Mandor Org/Hari Rp 146,250.00
2 Tukang Gali Tanah Org/Hari Rp 106,875.00
3 Kepala Tukang Batu Org/Hari Rp 135,000.00
4 Tukang Batu Org/Hari Rp 123,750.00
5 Laden Tukang Batu Org/Hari Rp 106,875.00
6 Kepala Tukang Kayu Org/Hari Rp 135,000.00
7 Tukang Kayu Org/Hari Rp 123,750.00
8 Laden Tukang Kayu Org/Hari Rp 106,875.00
9 Kepala Tukang Besi Org/Hari Rp 135,000.00
10 Tukang Besi Org/Hari Rp 123,750.00
11 Laden Tukang Besi Org/Hari Rp 106,875.00
12 Kepala Tukang Cat Org/Hari Rp 135,000.00
13 Tukang Cat Org/Hari Rp 123,750.00
14 Laden Tukang Cat Org/Hari Rp 106,875.00
15 Penjaga Malam Org/Hari Rp 106,875.00
16 Mekanik Org/Hari Rp 213,750.00
17 Operator Terlatih Org/Hari Rp 157,500.00
18 Operator Kurang Terlatih Org/Hari Rp 123,750.00
19 Pembantu Operator Org/Hari Rp 106,875.00
20 Supir Material/Truck Org/Hari Rp 135,000.00
21 Supir Personil Org/Hari Rp 135,000.00
22 Pembantu Supir Org/Hari Rp 101,250.00
23 Buruh Tak Terlatih Org/Hari Rp 106,875.00
24 Buruh Lapangan Agak Terlatih Org/Hari Rp 106,875.00
25 Buruh Lapangan Terlatih Org/Hari Rp 106,875.00
26 Tukang Listrik Org/Hari Rp 106,875.00
27 Tukang Las Org/Hari Rp 106,875.00
28 Tukang Pancang Org/Hari Rp 106,875.00
29 Tukang Tebas Org/Hari Rp 106,875.00
30 Tukang Anyam Org/Hari Rp 106,875.00

Harga Upah 1
HARGA UPAH DAN BAHAN BANGUNAN
KABUPATEN GUNUNG MAS TRIWULAN I
TAHUN 2015

B. BAHAN BANGUNAN
No Uraian Satuan Harga
1 Pasir urug M3 Rp 121,000.00
2 Pasir beton M3 Rp 181,500.00
3 Pasir pasang M3 Rp 247,500.00
4 Tanah urug biasa/Granit M3 Rp 110,000.00
5 Tanah urug pilihan M3 Rp 142,670.00
6 Kerikil M3 Rp 199,650.00
7 Batu kali/Batu belah M3 Rp 440,000.00
8 Semen PC (isi 40 Kg/Zak) Gresik Zak Rp 85,470.00
9 Semen PC Kg Rp 2,136.75
10 Semen putih (isi 40 Kg/Zak) Gresik Kg Rp 173,250.00
11 Semen Warna Kg Rp 12,320.00
12 Batu bata Biji Rp 1,100.00
13 Bataco Biji Rp 4,675.00
14 Beton kerawang (ukuran kecil) Biji Rp 18,150.00
15 Kawat beton Kg Rp 49,610.00
16 Besi beton polos Kg Rp 18,810.00
17 Besi beugel/Besi Strip Kg Rp 25,410.00
18 Baut-mur Bj Rp 4,235.00
19 Balok kayu klas I (Ulin) M3 Rp 8,288,500.00
20 Papan kayu klas I (Ulin) M3 Rp 8,250,000.00
21 Balok kayu klas II M3 Rp 3,751,000.00
22 Papan kayu klas II M3 Rp 3,300,000.00
23 Balok kayu klas III M3 Rp 2,722,500.00
24 Papan kayu klas III M3 Rp 2,750,000.00
25 Papan kayu bouwplank M3 Rp 2,750,000.00
26 Papan kayu begesting M3 Rp 2,750,000.00
27 Kayu Dolken/Galam dia. 10-12 cm P.4M Btng Rp 12,100.00
28 Kayu Dolken/knopel dia. 10-12 cm P.4M Btng Rp 9,680.00
29 Seng gelombang BJLS 30 Lbr Rp 47,190.00
30 Seng plat M' Rp 23,980.00
31 Genteng Metal Lbr Rp 43,340.00
32 Bubungan Genteng Metal Lbr Rp 32,670.00
33 Plywood 4 mm Lbr Rp 87,725.00
34 Formica Lbr Rp 220,000.00
35 Teaxwood 122 x 244 cm tebal 4 mm Lbr Rp 219,560.00
36 Kayu Moulding lap-lapan Keping Rp 53,900.00
37 Lis profil M' Rp 10,560.00
38 Lem Kayu Kg Rp 26,400.00
39 Pagar Galvanis M2 Rp 605,000.00

Harga Bahan Bangunan 2


HARGA UPAH DAN BAHAN BANGUNAN
KABUPATEN GUNUNG MAS TRIWULAN I
TAHUN 2015

B. BAHAN BANGUNAN
No Uraian Satuan Harga
40 Pagar Hollow M2 Rp 605,000.00
41 Pagar Besi Ulir M2 Rp 363,000.00
42 Pagar Stainlis M2 Rp 726,000.00
43 Paku kayu Kg Rp 24,200.00
44 Paku seng Kg Rp 52,580.00
45 Paku ulin Kg Rp 36,300.00
46 Paku reng Kg Rp 36,300.00
47 Paku sirap Kg Rp 44,110.00
48 Paku plywood/Teaxwood Kg Rp 35,090.00
49 Paku asbes Kg Rp 33,220.00
50 Paku kait buah Rp 605.00
51 Paku anti karat (Paku genteng Metal) Kg Rp 38,060.00
52 Paku Skrup Kg Rp 34,980.00
53 Cat Menie Kayu Kg Rp 42,350.00
54 Cat kayu mengkilat Kg Rp 53,240.00
55 Cat dasar kayu Kg Rp 51,040.00
56 Cat tembok (Avitex/Setara) isi 5 Kg Kg Rp 108,900.00
57 Plamur tembok isi 5 Kg Kg Rp 88,330.00
58 Plamur Kayu Kg Rp 31,130.00
59 Dempul jadi Kg Rp 34,430.00
60 Minyak cat Liter Rp 38,060.00
61 Residu/Ter Liter Rp 22,330.00
62 Solar Liter Rp 15,070.00
63 Olie Liter Rp 46,530.00
64 Minyak begesting Liter Rp 13,310.00
65 Kaca polos 5 mm M2 Rp 205,700.00
66 Kaca ryben 5 mm M2 Rp 211,750.00
67 Kaca polos 3 mm M2 Rp 179,080.00
68 Kaca ryben 3 mm M2 Rp 179,080.00
69 Kunci tanam Standart (pintu utama) Buah Rp 176,660.00
70 Kunci pintu Kamar Buah Rp 108,900.00
71 Profil Almunium M' Rp 127,050.00
72 Engsel lokal 4" untuk pintu Ps Rp 30,250.00
73 Engsel lokal 3" untuk jendela Ps Rp 18,150.00
74 Grendel lokal Ps Rp 9,020.00
75 Expagnolet besar (penuh) Ps Rp 102,850.00
76 Hak angin Ps Rp 12,100.00
77 Closet duduk merk American Standart Set Rp 1,527,570.00
78 Closet jongkok porselin putih merk INA Buah Rp 181,500.00

Harga Bahan Bangunan 3


HARGA UPAH DAN BAHAN BANGUNAN
KABUPATEN GUNUNG MAS TRIWULAN I
TAHUN 2015

B. BAHAN BANGUNAN
No Uraian Satuan Harga
79 Bak mandi Fibre 50x50x50 cm Buah Rp 384,175.00
80 Wastafel (Standart/KIA) Buah Rp 726,000.00
81 Kran air stainless + Sower Stainless Buah Rp 109,505.00
82 Floor drain Buah Rp 38,500.00
83 Seal tape Buah Rp 11,000.00
84 Keramik 10x20 cm M2 Rp 60,500.00
85 Keramik 20x20 cm M2 Rp 81,620.00
86 Keramik 25x20 cm M2 Rp 81,620.00
87 Keramik 30x30 cm polos M2 Rp 69,520.00
88 Mozaik 30 x 30 cm M2 Rp 84,700.00
89 Keramik 40x40 cm M2 Rp 102,850.00
90 Pipa PVC 3/4 " Panjang 4 M Bt Rp 28,380.00
91 Pipa PVC 1 1/2 " Panjang 4 M Bt Rp 75,020.00
92 Pipa PVC 1 " Panjang 4 M Bt Rp 47,190.00
93 Stop kran Buah Rp 21,120.00
94 Bak Resevoir Kapasitas 1200L merk Gapura Buah Rp 1,706,100.00
95 Titik nyala Lampu (konstruksi kayu) Titik Rp 302,500.00
96 Titik nyala Lampu (konstruksi beton) Titik Rp 302,500.00
97 Stop kontak (Konstruksi kayu) Titik Rp 302,500.00
98 Stop kontak (Konstruksi beton) Titik Rp 302,500.00
99 Schakelar (standart) Buah Rp 27,830.00
100 Lampu pijar Buah Rp 6,600.00
101 Lampu TL. Bulat + Down light Buah Rp 33,000.00
102 Lampu TL. Panjang 20 Watt Buah Rp 114,950.00
103 Lampu hemat Energi 20 Watt Buah Rp 45,210.00
104 MCB 1 Grup Buah Rp 89,540.00
106 Kawat Harmonika Rol Rp 302,500.00
107 Paving Stone Segi Enam M2 Rp 143,990.00
108 Wallpaper M Rp 132,000.00
109 Gypsum Lbr Rp 72,600.00
110 List Profil Gypsum M' Rp 60,500.00

Harga Bahan Bangunan 4


DAFTAR ANALISA BIAYA KONSTRUKSI (ABK) BANGUNAN GEDUNG DAN PERUMAHAN

ANALISA URAIAN PEKERJAAN HARGA SATUAN UPAH BAHAN JUMLAH


PEKERJAAN PENDAHULUAN
SNI-2002.01.4 1 M' PENGUKURAN DAN PASANG BOUWPLANK
0.0050 OH Mandor Rp. 146,250.00 Rp. 731.25
0.0100 OH Kepala Tukang Kayu Rp. 135,000.00 Rp. 1,350.00
0.1000 OH Tukang Kayu Rp. 123,750.00 Rp. 12,375.00
0.1000 OH Laden Tukang Kayu Rp. 106,875.00 Rp. 10,687.50
0.0120 M3 Balok kayu klas III Rp. 2,722,500.00 Rp. 32,670.00
0.0070 M3 Papan kayu begesting Rp. 2,750,000.00 Rp. 19,250.00
0.0200 Kg Paku kayu Rp. 24,200.00 Rp. 484.00
Rp. 25,143.75 Rp. 52,404.00 Rp. 77,547.75
SNI -2002.-01.8 1 M2 MEMBERSIHKAN LAPANGAN DAN PERATAAN
0.1000 OH Laden Tukang Kayu Rp. 106,875.00 Rp. 10,687.50
0.0500 OH Mandor Rp. 146,250.00 Rp. 7,312.50
Rp. 18,000.00 Rp. - Rp. 18,000.00
PEKERJAAN TANAH
SNI -2008.02.1 1 M3 MENGGALI TANAH BIASA SEDALAM 1 METER
0.7500 OH Tukang Gali Tanah Rp. 106,875.00 Rp. 80,156.25
0.0250 OH Mandor Rp. 146,250.00 Rp. 3,656.25
Rp. 83,812.50 Rp. - Rp. 83,812.50

SNI -2008.02.9 MENGURUG KEMBALI 1 M3 GALIAN


0.2500 OH Tukang Gali Tanah Rp. 106,875.00 Rp. 26,718.75
0.0083 OH Mandor Rp. 146,250.00 Rp. 1,218.75
Rp. 27,937.50 Rp. - Rp. 27,937.50

SNI -2008.02.10 MEMADATKAN 1 M3 TANAH (PER 20 CM)


0.5000 OH Tukang Gali Tanah Rp. 106,875.00 Rp. 53,437.50
0.0500 OH Mandor Rp. 146,250.00 Rp. 7,312.50
Rp. 60,750.00 Rp. - Rp. 60,750.00

SNI -2008.02.11 1 M3 MENGURUG TANAH URUG


0.3000 OH Tukang Gali Tanah Rp. 106,875.00 Rp. 32,062.50
0.0100 OH Mandor Rp. 146,250.00 Rp. 1,462.50
1.2000 M3 Tanah urug biasa/Granit Rp. 110,000.00 Rp. 132,000.00
Rp. 33,525.00 Rp. 132,000.00 Rp. 165,525.00

SNI -2008.02.11a 1 M3 MENGURUG PASIR URUG


0.3000 OH Tukang Gali Tanah Rp. 106,875.00 Rp. 32,062.50
0.0100 OH Mandor Rp. 146,250.00 Rp. 1,462.50
1.2000 M3 Pasir Urug Rp. 121,000.00 Rp. 145,200.00
Rp. 33,525.00 Rp. 145,200.00 Rp. 178,725.00

PEKERJAAN PONDASI
SNI -2008.03.2 1 M3 MEMASANG PONDASI BATU BELAH CAMP. 1 PC : 4 PSR
1.5000 OH Laden Tukang Batu Rp. 106,875.00 Rp. 160,312.50
0.7500 OH Tukang batu Rp. 123,750.00 Rp. 92,812.50
0.0750 OH Kepala Tukang batu Rp. 135,000.00 Rp. 10,125.00
0.0750 OH Mandor Rp. 146,250.00 Rp. 10,968.75
1.2000 M3 Batu kali/Batu belah Rp. 440,000.00 Rp. 528,000.00
163.0000 Kg Semen PC Rp. 2,136.75 Rp. 348,290.25
0.5200 M3 Pasir Pasang Rp. 247,500.00 Rp. 128,700.00
Rp. 274,218.75 Rp. 1,004,990.25 Rp. 1,279,209.00

SNI -2008.03.3 1 M3 MEMASANG PONDASI BATU BELAH CAMP. 1 PC : 5 PSR


1.5000 OH Laden Tukang Batu Rp. 106,875.00 Rp. 160,312.50
0.7500 OH Tukang batu Rp. 123,750.00 Rp. 92,812.50
0.0750 OH Kepala Tukang batu Rp. 135,000.00 Rp. 10,125.00
0.0750 OH Mandor Rp. 146,250.00 Rp. 10,968.75
1.2000 M3 Batu kali/Batu belah Rp. 440,000.00 Rp. 528,000.00
136.0000 Kg Semen PC Rp. 2,136.75 Rp. 290,598.00
0.5440 M3 Pasir Pasang Rp. 247,500.00 Rp. 134,640.00
Rp. 274,218.75 Rp. 953,238.00 Rp. 1,227,456.75

Analisa 5
ANALISA URAIAN PEKERJAAN HARGA SATUAN UPAH BAHAN JUMLAH
SNI -2008.03.9 1 M3 MEMASANG PONDASI BATU KOSONG (ANSTAMPENG)
0.7800 OH Laden Tukang Batu Rp. 106,875.00 Rp. 83,362.50
0.3900 OH Tukang batu Rp. 123,750.00 Rp. 48,262.50
0.0390 OH Kepala Tukang batu Rp. 135,000.00 Rp. 5,265.00
0.0390 OH Mandor Rp. 146,250.00 Rp. 5,703.75
1.2000 M3 Batu kali/Batu belah Rp. 440,000.00 Rp. 528,000.00
0.4320 M3 Pasir Urug Rp. 121,000.00 Rp. 52,272.00
Rp. 142,593.75 Rp. 580,272.00 Rp. 722,865.75

PEKERJAAN DINDING
SNI -2008.03.3 1 M2 MEMASANG BATA MERAH TEBAL 1 BATU CAMP. 1 PC : 4 PSR
0.6000 OH Laden Tukang Batu Rp. 106,875.00 Rp. 64,125.00
0.2000 OH Tukang batu Rp. 123,750.00 Rp. 24,750.00
0.0200 OH Kepala Tukang batu Rp. 135,000.00 Rp. 2,700.00
0.0300 OH Mandor Rp. 146,250.00 Rp. 4,387.50
140.0000 Bj Batu Bata Rp. 1,100.00 Rp. 154,000.00
26.5500 Kg Semen PC Rp. 2,136.75 Rp. 56,730.71
0.0930 M3 Pasir Pasang Rp. 247,500.00 Rp. 23,017.50
Rp. 95,962.50 Rp. 233,748.21 Rp. 329,710.71

SNI -2008.04.9 1 M2 MEMASANG BATA MERAH TEBAL 1/2 BATU CAMP. 1 PC : 4 PSR
0.3000 OH Laden Tukang Batu Rp. 106,875.00 Rp. 32,062.50
0.1000 OH Tukang batu Rp. 123,750.00 Rp. 12,375.00
0.0100 OH Kepala Tukang batu Rp. 135,000.00 Rp. 1,350.00
0.0150 OH Mandor Rp. 146,250.00 Rp. 2,193.75
70.0000 Bj Batu Bata Rp. 1,100.00 Rp. 77,000.00
11.5000 Kg Semen PC Rp. 2,136.75 Rp. 24,572.63
0.0430 M3 Pasir Pasang Rp. 247,500.00 Rp. 10,642.50
Rp. 47,981.25 Rp. 112,215.13 Rp. 160,196.38

SNI -2008.04.10 1 M2 MEMASANG BATA MERAH TEBAL 1/2 BATU CAMP. 1 PC : 5 PSR
0.3000 OH Laden Tukang Batu Rp. 106,875.00 Rp. 32,062.50
0.1000 OH Tukang batu Rp. 123,750.00 Rp. 12,375.00
0.0100 OH Kepala Tukang batu Rp. 135,000.00 Rp. 1,350.00
0.0150 OH Mandor Rp. 146,250.00 Rp. 2,193.75
70.0000 Bj Batu Bata Rp. 1,100.00 Rp. 77,000.00
9.6800 Kg Semen PC Rp. 2,136.75 Rp. 20,683.74
0.0450 M3 Pasir Pasang Rp. 247,500.00 Rp. 11,137.50
Rp. 47,981.25 Rp. 108,821.24 Rp. 156,802.49

SNI -2008.04.16 1 M2 MEMASANG BATACO 1/2 BATU CAMP. 1 PC : 3 PSR


0.0150 OH Laden Tukang Batu Rp. 106,875.00 Rp. 1,603.13
0.1000 OH Tukang batu Rp. 123,750.00 Rp. 12,375.00
0.1000 OH Kepala Tukang batu Rp. 135,000.00 Rp. 13,500.00
0.0150 OH Mandor Rp. 146,250.00 Rp. 2,193.75
12.5000 Bj Bataco Rp. 4,675.00 Rp. 58,437.50
7.5000 Kg Semen PC Rp. 2,136.75 Rp. 16,025.63
0.0270 M3 Pasir Pasang Rp. 247,500.00 Rp. 6,682.50
Rp. 29,671.88 Rp. 81,145.63 Rp. 110,817.50

PEKERJAAN BETON
SNI -2008.07.28 MEMBUAT 1 M3 PONDASI BETON BERTULANG (200 KG BESI + BEGESTING)
5.3000 OH Laden Tukang Batu Rp. 106,875.00 Rp. 566,437.50
0.2750 OH Tukang batu Rp. 123,750.00 Rp. 34,031.25
1.3000 OH Tukang kayu Rp. 123,750.00 Rp. 160,875.00
1.0500 OH Tukang besi Rp. 123,750.00 Rp. 129,937.50
0.2620 OH Kepala Tukang Batu Rp. 135,000.00 Rp. 35,370.00
0.2650 OH Mandor Rp. 146,250.00 Rp. 38,756.25
0.2000 M3 Papan kayu begesting Rp. 2,750,000.00 Rp. 550,000.00
1.5000 Kg Paku Kayu Rp. 24,200.00 Rp. 36,300.00
0.4000 Ltr Minyak begesting Rp. 13,310.00 Rp. 5,324.00
210.0000 Kg Besi Beton Polos Rp. 18,810.00 Rp. 3,950,100.00
2.2500 Kg Kawat Beton Rp. 49,610.00 Rp. 111,622.50
336.0000 Kg Semen PC Rp. 2,136.75 Rp. 717,948.00
0.5400 M3 Pasir Beton Rp. 181,500.00 Rp. 98,010.00
0.8100 M3 Kerikil Rp. 199,650.00 Rp. 161,716.50
Rp. 965,407.50 Rp. 5,631,021.00 Rp. 6,596,428.50

Analisa 6
ANALISA URAIAN PEKERJAAN HARGA SATUAN UPAH BAHAN JUMLAH
SNI -2008.07.29 MEMBUAT 1 M3 SLOOF BETON BERTULANG (200 KG BESI + BEGESTING)
5.6500 OH Laden Tukang Batu Rp. 106,875.00 Rp. 603,843.75
0.2750 OH Tukang batu Rp. 123,750.00 Rp. 34,031.25
1.5600 OH Tukang kayu Rp. 123,750.00 Rp. 193,050.00
1.4000 OH Tukang besi Rp. 123,750.00 Rp. 173,250.00
0.3230 OH Kepala Tukang Batu Rp. 135,000.00 Rp. 43,605.00
0.2830 OH Mandor Rp. 146,250.00 Rp. 41,388.75
0.2700 M3 Papan kayu begesting Rp. 2,750,000.00 Rp. 742,500.00
2.0000 Kg Paku Kayu Rp. 24,200.00 Rp. 48,400.00
0.6000 Ltr Minyak begesting Rp. 13,310.00 Rp. 7,986.00
210.0000 Kg Besi Beton Polos Rp. 18,810.00 Rp. 3,950,100.00
3.0000 Kg Kawat Beton Rp. 49,610.00 Rp. 148,830.00
336.0000 Kg Semen PC Rp. 2,136.75 Rp. 717,948.00
0.5400 M3 Pasir Beton Rp. 181,500.00 Rp. 98,010.00
0.8100 M3 Kerikil Rp. 199,650.00 Rp. 161,716.50
Rp. 1,089,168.75 Rp. 5,875,490.50 Rp. 6,964,659.25

UNTUK BETON DENGAN BESI 150 KG/M3 ADALAH


5.6500 OH Laden Tukang Batu Rp. 106,875.00 Rp. 603,843.75
0.2750 OH Tukang batu Rp. 123,750.00 Rp. 34,031.25
1.5600 OH Tukang kayu Rp. 123,750.00 Rp. 193,050.00
1.0500 OH Tukang besi Rp. 123,750.00 Rp. 129,937.50
0.3230 OH Kepala Tukang Batu Rp. 135,000.00 Rp. 43,605.00
0.2830 OH Mandor Rp. 146,250.00 Rp. 41,388.75
0.2700 M3 Papan kayu begesting Rp. 2,750,000.00 Rp. 742,500.00
2.0000 Kg Paku Kayu Rp. 24,200.00 Rp. 48,400.00
0.6000 Ltr Minyak begesting Rp. 13,310.00 Rp. 7,986.00
157.5000 Kg Besi Beton Polos Rp. 18,810.00 Rp. 2,962,575.00
2.2500 Kg Kawat Beton Rp. 49,610.00 Rp. 111,622.50
336.0000 Kg Semen PC Rp. 2,136.75 Rp. 717,948.00
0.5400 M3 Pasir Beton Rp. 181,500.00 Rp. 98,010.00
0.8100 M3 Kerikil Rp. 199,650.00 Rp. 161,716.50
Rp. 1,045,856.25 Rp. 4,850,758.00 Rp. 5,896,614.25

UNTUK BETON DENGAN BESI 100 KG/M3 ADALAH


5.6500 OH Laden Tukang Batu Rp. 106,875.00 Rp. 603,843.75
0.2750 OH Tukang batu Rp. 123,750.00 Rp. 34,031.25
1.5600 OH Tukang kayu Rp. 123,750.00 Rp. 193,050.00
0.7000 OH Tukang besi Rp. 123,750.00 Rp. 86,625.00
0.3230 OH Kepala Tukang Batu Rp. 135,000.00 Rp. 43,605.00
0.2830 OH Mandor Rp. 146,250.00 Rp. 41,388.75
0.2700 M3 Papan kayu begesting Rp. 2,750,000.00 Rp. 742,500.00
2.0000 Kg Paku Kayu Rp. 24,200.00 Rp. 48,400.00
0.6000 Ltr Minyak begesting Rp. 13,310.00 Rp. 7,986.00
105.0000 Kg Besi Beton Polos Rp. 18,810.00 Rp. 1,975,050.00
1.5000 Kg Kawat Beton Rp. 49,610.00 Rp. 74,415.00
336.0000 Kg Semen PC Rp. 2,136.75 Rp. 717,948.00
0.5400 M3 Pasir Beton Rp. 181,500.00 Rp. 98,010.00
0.8100 M3 Kerikil Rp. 199,650.00 Rp. 161,716.50
Rp. 1,002,543.75 Rp. 3,826,025.50 Rp. 4,828,569.25

SNI -2008.07.30 MEMBUAT 1 M3 KOLOM BETON BERTULANG (300 KG BESI + BEGESTING)


7.0500 OH Laden Tukang Batu Rp. 106,875.00 Rp. 753,468.75
0.2750 OH Tukang batu Rp. 123,750.00 Rp. 34,031.25
1.6500 OH Tukang kayu Rp. 123,750.00 Rp. 204,187.50
2.1000 OH Tukang besi Rp. 123,750.00 Rp. 259,875.00
0.4030 OH Kepala Tukang Batu Rp. 135,000.00 Rp. 54,405.00
0.3530 OH Mandor Rp. 146,250.00 Rp. 51,626.25
0.4000 M3 Papan kayu begesting Rp. 2,750,000.00 Rp. 1,100,000.00
4.0000 Kg Paku Kayu Rp. 24,200.00 Rp. 96,800.00
2.0000 Ltr Minyak begesting Rp. 13,310.00 Rp. 26,620.00
315.0000 Kg Besi Beton Polos Rp. 18,810.00 Rp. 5,925,150.00
4.5000 Kg Kawat Beton Rp. 49,610.00 Rp. 223,245.00
336.0000 Kg Semen PC Rp. 2,136.75 Rp. 717,948.00
0.5400 M3 Pasir Beton Rp. 181,500.00 Rp. 98,010.00
0.8100 M3 Kerikil Rp. 199,650.00 Rp. 161,716.50
Rp. 1,357,593.75 Rp. 8,349,489.50 Rp. 9,707,083.25

Analisa 7
ANALISA URAIAN PEKERJAAN HARGA SATUAN UPAH BAHAN JUMLAH
UNTUK 1 M3 KOLOM BETON DENGAN BESI 200 KG/M3 ADALAH :
7.0500 OH Laden Tukang Batu Rp. 106,875.00 Rp. 753,468.75
0.2750 OH Tukang batu Rp. 123,750.00 Rp. 34,031.25
1.6500 OH Tukang kayu Rp. 123,750.00 Rp. 204,187.50
1.4000 OH Tukang besi Rp. 123,750.00 Rp. 173,250.00
0.4030 OH Kepala Tukang Batu Rp. 135,000.00 Rp. 54,405.00
0.3530 OH Mandor Rp. 146,250.00 Rp. 51,626.25
0.4000 M3 Papan kayu begesting Rp. 2,750,000.00 Rp. 1,100,000.00
4.0000 Kg Paku Kayu Rp. 24,200.00 Rp. 96,800.00
2.0000 Ltr Minyak begesting Rp. 13,310.00 Rp. 26,620.00
210.0000 Kg Besi Beton Polos Rp. 18,810.00 Rp. 3,950,100.00
3.0000 Kg Kawat Beton Rp. 49,610.00 Rp. 148,830.00
336.0000 Kg Semen PC Rp. 2,136.75 Rp. 717,948.00
0.5400 M3 Pasir Beton Rp. 181,500.00 Rp. 98,010.00
0.8100 M3 Kerikil Rp. 199,650.00 Rp. 161,716.50
Rp. 1,270,968.75 Rp. 6,300,024.50 Rp. 7,570,993.25

UNTUK 1 M3 KOLOM BETON DENGAN BESI 150 KG/M3 ADALAH :


7.0500 OH Laden Tukang Batu Rp. 106,875.00 Rp. 753,468.75
0.2750 OH Tukang batu Rp. 123,750.00 Rp. 34,031.25
1.6500 OH Tukang kayu Rp. 123,750.00 Rp. 204,187.50
1.0500 OH Tukang besi Rp. 123,750.00 Rp. 129,937.50
0.4030 OH Kepala Tukang Batu Rp. 135,000.00 Rp. 54,405.00
0.3530 OH Mandor Rp. 146,250.00 Rp. 51,626.25
0.4000 M3 Papan kayu begesting Rp. 2,750,000.00 Rp. 1,100,000.00
4.0000 Kg Paku Kayu Rp. 24,200.00 Rp. 96,800.00
2.0000 Ltr Minyak begesting Rp. 13,310.00 Rp. 26,620.00
157.5000 Kg Besi Beton Polos Rp. 18,810.00 Rp. 2,962,575.00
2.2500 Kg Kawat Beton Rp. 49,610.00 Rp. 111,622.50
336.0000 Kg Semen PC Rp. 2,136.75 Rp. 717,948.00
0.5400 M3 Pasir Beton Rp. 181,500.00 Rp. 98,010.00
0.8100 M3 Kerikil Rp. 199,650.00 Rp. 161,716.50
Rp. 1,227,656.25 Rp. 5,275,292.00 Rp. 6,502,948.25

UNTUK 1 M3 KOLOM BETON DENGAN BESI 100 KG/M3 ADALAH :


7.0500 OH Laden Tukang Batu Rp. 106,875.00 Rp. 753,468.75
0.2750 OH Tukang batu Rp. 123,750.00 Rp. 34,031.25
1.6500 OH Tukang kayu Rp. 123,750.00 Rp. 204,187.50
0.7000 OH Tukang besi Rp. 123,750.00 Rp. 86,625.00
0.4030 OH Kepala Tukang Batu Rp. 135,000.00 Rp. 54,405.00
0.3530 OH Mandor Rp. 146,250.00 Rp. 51,626.25
0.4000 M3 Papan kayu begesting Rp. 2,750,000.00 Rp. 1,100,000.00
4.0000 Kg Paku Kayu Rp. 24,200.00 Rp. 96,800.00
2.0000 Ltr Minyak begesting Rp. 13,310.00 Rp. 26,620.00
105.0000 Kg Besi Beton Polos Rp. 18,810.00 Rp. 1,975,050.00
1.5000 Kg Kawat Beton Rp. 49,610.00 Rp. 74,415.00
336.0000 Kg Semen PC Rp. 2,136.75 Rp. 717,948.00
0.5400 M3 Pasir Beton Rp. 181,500.00 Rp. 98,010.00
0.8100 M3 Kerikil Rp. 199,650.00 Rp. 161,716.50
Rp. 1,184,343.75 Rp. 4,250,559.50 Rp. 5,434,903.25

SNI -2008.07.31 MEMBUAT 1 M3 BALOK BETON BERTULANG (200 KG BESI + BEGESTING)


6.3500 OH Laden Tukang Batu Rp. 106,875.00 Rp. 678,656.25
0.2750 OH Tukang batu Rp. 123,750.00 Rp. 34,031.25
1.6500 OH Tukang kayu Rp. 123,750.00 Rp. 204,187.50
1.4000 OH Tukang besi Rp. 123,750.00 Rp. 173,250.00
0.3330 OH Kepala Tukang Batu Rp. 135,000.00 Rp. 44,955.00
0.3180 OH Mandor Rp. 146,250.00 Rp. 46,507.50
0.3200 M3 Papan kayu begesting Rp. 2,750,000.00 Rp. 880,000.00
3.2000 Kg Paku Kayu Rp. 24,200.00 Rp. 77,440.00
1.6000 Ltr Minyak begesting Rp. 13,310.00 Rp. 21,296.00
210.0000 Kg Besi Beton Polos Rp. 18,810.00 Rp. 3,950,100.00
3.0000 Kg Kawat Beton Rp. 49,610.00 Rp. 148,830.00
336.0000 Kg Semen PC Rp. 2,136.75 Rp. 717,948.00
0.5400 M3 Pasir Beton Rp. 181,500.00 Rp. 98,010.00
0.8100 M3 Kerikil Rp. 199,650.00 Rp. 161,716.50
Rp. 1,181,587.50 Rp. 6,055,340.50 Rp. 7,236,928.00

Analisa 8
ANALISA URAIAN PEKERJAAN HARGA SATUAN UPAH BAHAN JUMLAH
UNTUK BALOK BETON DENGAN BESI 150 KG/M3 ADALAH :
6.3500 OH Laden Tukang Batu Rp. 106,875.00 Rp. 678,656.25
0.2750 OH Tukang batu Rp. 123,750.00 Rp. 34,031.25
1.6500 OH Tukang kayu Rp. 123,750.00 Rp. 204,187.50
1.0500 OH Tukang besi Rp. 123,750.00 Rp. 129,937.50
0.3330 OH Kepala Tukang Batu Rp. 135,000.00 Rp. 44,955.00
0.3180 OH Mandor Rp. 146,250.00 Rp. 46,507.50
0.3200 M3 Papan kayu begesting Rp. 2,750,000.00 Rp. 880,000.00
3.2000 Kg Paku Kayu Rp. 24,200.00 Rp. 77,440.00
1.6000 Ltr Minyak begesting Rp. 13,310.00 Rp. 21,296.00
157.5000 Kg Besi Beton Polos Rp. 18,810.00 Rp. 2,962,575.00
2.2500 Kg Kawat Beton Rp. 49,610.00 Rp. 111,622.50
336.0000 Kg Semen PC Rp. 2,136.75 Rp. 717,948.00
0.5400 M3 Pasir Beton Rp. 181,500.00 Rp. 98,010.00
0.8100 M3 Kerikil Rp. 199,650.00 Rp. 161,716.50
Rp. 1,138,275.00 Rp. 5,030,608.00 Rp. 6,168,883.00

UNTUK BALOK BETON DENGAN BESI 100 KG/M3 ADALAH :


6.3500 OH Laden Tukang Batu Rp. 106,875.00 Rp. 678,656.25
0.2750 OH Tukang batu Rp. 123,750.00 Rp. 34,031.25
1.6500 OH Tukang kayu Rp. 123,750.00 Rp. 204,187.50
0.7000 OH Tukang besi Rp. 123,750.00 Rp. 86,625.00
0.3330 OH Kepala Tukang Batu Rp. 135,000.00 Rp. 44,955.00
0.3180 OH Mandor Rp. 146,250.00 Rp. 46,507.50
0.3200 M3 Papan kayu begesting Rp. 2,750,000.00 Rp. 880,000.00
3.2000 Kg Paku Kayu Rp. 24,200.00 Rp. 77,440.00
1.6000 Ltr Minyak begesting Rp. 13,310.00 Rp. 21,296.00
105.0000 Kg Besi Beton Polos Rp. 18,810.00 Rp. 1,975,050.00
1.5000 Kg Kawat Beton Rp. 49,610.00 Rp. 74,415.00
336.0000 Kg Semen PC Rp. 2,136.75 Rp. 717,948.00
0.5400 M3 Pasir Beton Rp. 181,500.00 Rp. 98,010.00
0.8100 M3 Kerikil Rp. 199,650.00 Rp. 161,716.50
Rp. 1,094,962.50 Rp. 4,005,875.50 Rp. 5,100,838.00

SNI -2008.07.32 MEMBUAT 1 M3 PLAT BETON BERTULANG (150 KG BESI + BEGESTING)


5.3000 OH Laden Tukang Batu Rp. 106,875.00 Rp. 566,437.50
0.2750 OH Tukang batu Rp. 123,750.00 Rp. 34,031.25
1.3000 OH Tukang kayu Rp. 123,750.00 Rp. 160,875.00
1.0500 OH Tukang besi Rp. 123,750.00 Rp. 129,937.50
0.2650 OH Kepala Tukang Batu Rp. 135,000.00 Rp. 35,775.00
0.2650 OH Mandor Rp. 146,250.00 Rp. 38,756.25
0.3200 M3 Papan kayu begesting Rp. 2,750,000.00 Rp. 880,000.00
3.2000 Kg Paku Kayu Rp. 24,200.00 Rp. 77,440.00
0.1200 M3 Papan kayu klas III Rp. 2,750,000.00 Rp. 330,000.00
32.0000 Btng Kayu Dolken/Galam dia. 10-12 cm P.4M Rp. 12,100.00 Rp. 387,200.00
1.6000 Ltr Minyak begesting Rp. 13,310.00 Rp. 21,296.00
157.5000 Kg Besi Beton Polos Rp. 18,810.00 Rp. 2,962,575.00
2.2500 Kg Kawat Beton Rp. 49,610.00 Rp. 111,622.50
336.0000 Kg Semen PC Rp. 2,136.75 Rp. 717,948.00
0.5400 M3 Pasir Beton Rp. 181,500.00 Rp. 98,010.00
0.8100 M3 Kerikil Rp. 199,650.00 Rp. 161,716.50
Rp. 965,812.50 Rp. 5,747,808.00 Rp. 6,713,620.50

UNTUK 1 M3 PLAT BETON BERTULANG (100 KG BESI + BEGESTING)


5.3000 OH Laden Tukang Batu Rp. 106,875.00 Rp. 566,437.50
0.2750 OH Tukang batu Rp. 123,750.00 Rp. 34,031.25
1.3000 OH Tukang kayu Rp. 123,750.00 Rp. 160,875.00
0.7000 OH Tukang besi Rp. 123,750.00 Rp. 86,625.00
0.2650 OH Kepala Tukang Batu Rp. 135,000.00 Rp. 35,775.00
0.2650 OH Mandor Rp. 146,250.00 Rp. 38,756.25
0.3200 M3 Papan kayu begesting Rp. 2,750,000.00 Rp. 880,000.00
3.2000 Kg Paku Kayu Rp. 24,200.00 Rp. 77,440.00
0.1200 M3 Papan kayu klas III Rp. 2,750,000.00 Rp. 330,000.00
32.0000 Btng Kayu Dolken/Galam dia. 10-12 cm P.4M Rp. 12,100.00 Rp. 387,200.00
1.6000 Ltr Minyak begesting Rp. 13,310.00 Rp. 21,296.00
105.0000 Kg Besi Beton Polos Rp. 18,810.00 Rp. 1,975,050.00
1.5000 Kg Kawat Beton Rp. 49,610.00 Rp. 74,415.00
336.0000 Kg Semen PC Rp. 2,136.75 Rp. 717,948.00
0.5400 M3 Pasir Beton Rp. 181,500.00 Rp. 98,010.00
0.8100 M3 Kerikil Rp. 199,650.00 Rp. 161,716.50
Rp. 922,500.00 Rp. 4,723,075.50 Rp. 5,645,575.50

Analisa 9
ANALISA URAIAN PEKERJAAN HARGA SATUAN UPAH BAHAN JUMLAH

Analisa 10
ANALISA URAIAN PEKERJAAN HARGA SATUAN UPAH BAHAN JUMLAH
SNI -2008.07.35 MEMBUAT 1 M' KOLOM PRAKTIS BETON BERTULANG (11 X 11 CM)
0.1800 OH Laden Tukang Batu Rp. 106,875.00 Rp. 19,237.50
0.0200 OH Tukang batu Rp. 123,750.00 Rp. 2,475.00
0.0200 OH Tukang kayu Rp. 123,750.00 Rp. 2,475.00
0.0200 OH Tukang besi Rp. 123,750.00 Rp. 2,475.00
0.0060 OH Kepala Tukang Batu Rp. 135,000.00 Rp. 810.00
0.0090 OH Mandor Rp. 146,250.00 Rp. 1,316.25
0.0020 M3 Papan kayu begesting Rp. 2,750,000.00 Rp. 5,500.00
0.0100 Kg Paku Kayu Rp. 24,200.00 Rp. 242.00
3.0000 Kg Besi Beton Polos Rp. 18,810.00 Rp. 56,430.00
0.0450 Kg Kawat Beton Rp. 49,610.00 Rp. 2,232.45
4.0000 Kg Semen PC Rp. 2,136.75 Rp. 8,547.00
0.0060 M3 Pasir Beton Rp. 181,500.00 Rp. 1,089.00
0.0090 M3 Kerikil Rp. 199,650.00 Rp. 1,796.85
Rp. 28,788.75 Rp. 75,837.30 Rp. 104,626.05

SNI -2008.07.36 MEMBUAT 1 M' RING BALOK BETON BERTULANG (10 X 15 CM)
0.2970 OH Laden Tukang Batu Rp. 106,875.00 Rp. 31,741.88
0.0330 OH Tukang batu Rp. 123,750.00 Rp. 4,083.75
0.0330 OH Tukang kayu Rp. 123,750.00 Rp. 4,083.75
0.0330 OH Tukang besi Rp. 123,750.00 Rp. 4,083.75
0.0100 OH Kepala Tukang Batu Rp. 135,000.00 Rp. 1,350.00
0.0150 OH Mandor Rp. 146,250.00 Rp. 2,193.75
0.0030 M3 Papan kayu begesting Rp. 2,750,000.00 Rp. 8,250.00
0.0200 Kg Paku Kayu Rp. 24,200.00 Rp. 484.00
3.6000 Kg Besi Beton Polos Rp. 18,810.00 Rp. 67,716.00
0.0500 Kg Kawat Beton Rp. 49,610.00 Rp. 2,480.50
5.5000 Kg Semen PC Rp. 2,136.75 Rp. 11,752.13
0.0090 M3 Pasir Beton Rp. 181,500.00 Rp. 1,633.50
0.0150 M3 Kerikil Rp. 199,650.00 Rp. 2,994.75
Rp. 47,536.88 Rp. 95,310.88 Rp. 142,847.75

PEKERJAAN PLESTERAN
SNI -2008.05.2 1 M2 PLESTERAN TEBAL 15 MM CAMP. 1 PC : 2 PSR
0.3000 OH Laden Tukang Batu Rp. 106,875.00 Rp. 32,062.50
0.1500 OH Tukang batu Rp. 123,750.00 Rp. 18,562.50
0.0150 OH Kepala Tukang Batu Rp. 135,000.00 Rp. 2,025.00
0.0150 OH Mandor Rp. 146,250.00 Rp. 2,193.75
15.5040 Kg Semen PC Rp. 2,136.75 Rp. 33,128.17
0.0160 M3 Pasir pasang Rp. 247,500.00 Rp. 3,960.00
Rp. 54,843.75 Rp. 37,088.17 Rp. 91,931.92

SNI -2008.05.4 1 M2 PLESTERAN TEBAL 15 MM CAMP. 1 PC : 4 PSR


0.3000 OH Laden Tukang Batu Rp. 106,875.00 Rp. 32,062.50
0.1500 OH Tukang batu Rp. 123,750.00 Rp. 18,562.50
0.0150 OH Kepala Tukang Batu Rp. 135,000.00 Rp. 2,025.00
0.0150 OH Mandor Rp. 146,250.00 Rp. 2,193.75
6.2400 Kg Semen PC Rp. 2,136.75 Rp. 13,333.32
0.0240 M3 Pasir pasang Rp. 247,500.00 Rp. 5,940.00
Rp. 54,843.75 Rp. 19,273.32 Rp. 74,117.07

SNI -2008.05.5 1 M2 PLESTERAN TEBAL 15 MM CAMP. 1 PC : 5 PSR


0.3000 OH Laden Tukang Batu Rp. 106,875.00 Rp. 32,062.50
0.1500 OH Tukang batu Rp. 123,750.00 Rp. 18,562.50
0.0150 OH Kepala Tukang Batu Rp. 135,000.00 Rp. 2,025.00
0.0150 OH Mandor Rp. 146,250.00 Rp. 2,193.75
5.1840 Kg Semen PC Rp. 2,136.75 Rp. 11,076.91
0.0260 M3 Pasir pasang Rp. 247,500.00 Rp. 6,435.00
Rp. 54,843.75 Rp. 17,511.91 Rp. 72,355.66

SNI -2008.05.27 1 M2 MEMBUAT ACIAN


0.2000 OH Laden Tukang Batu Rp. 106,875.00 Rp. 21,375.00
0.1000 OH Tukang batu Rp. 123,750.00 Rp. 12,375.00
0.0100 OH Kepala Tukang Batu Rp. 135,000.00 Rp. 1,350.00
0.0100 OH Mandor Rp. 146,250.00 Rp. 1,462.50
3.2500 Kg Semen PC Rp. 2,136.75 Rp. 6,944.44
Rp. 36,562.50 Rp. 6,944.44 Rp. 43,506.94

Analisa 11
ANALISA URAIAN PEKERJAAN HARGA SATUAN UPAH BAHAN JUMLAH
PEKERJAAN PENUTUP LANTAI DAN DINDING
SNI -2008.13.35 1 M2 MEMASANG KERAMIK 30X30 CM
0.6200 OH Laden Tukang Batu Rp. 106,875.00 Rp. 66,262.50
0.3500 OH Tukang batu Rp. 123,750.00 Rp. 43,312.50
0.0350 OH Kepala Tukang Batu Rp. 135,000.00 Rp. 4,725.00
0.0300 OH Mandor Rp. 146,250.00 Rp. 4,387.50
11.8700 Bh Keramik 30x30 cm polos Rp. 6,256.80 Rp. 74,268.22
10.0000 Kg Semen PC Rp. 2,136.75 Rp. 21,367.50
0.0450 M3 Pasir pasang Rp. 247,500.00 Rp. 11,137.50
Rp. 118,687.50 Rp. 106,773.22 Rp. 225,460.72

SNI -2008.13.36 1 M2 MEMASANG KERAMIK 20X20 CM


0.6200 OH Laden Tukang Batu Rp. 106,875.00 Rp. 66,262.50
0.3500 OH Tukang batu Rp. 123,750.00 Rp. 43,312.50
0.0350 OH Kepala Tukang Batu Rp. 135,000.00 Rp. 4,725.00
0.0300 OH Mandor Rp. 146,250.00 Rp. 4,387.50
26.5000 Bh Keramik 20x20 cm Rp. 3,264.80 Rp. 86,517.20
10.4000 Kg Semen PC Rp. 2,136.75 Rp. 22,222.20
0.0450 M3 Pasir pasang Rp. 247,500.00 Rp. 11,137.50
Rp. 118,687.50 Rp. 119,876.90 Rp. 238,564.40

SNI -2008.13.38 1 M2 MEMASANG MOZAIK 30X30 CM CAMP. 1 PC : 3 PSR


0.6200 OH Laden Tukang Batu Rp. 106,875.00 Rp. 66,262.50
0.3500 OH Tukang batu Rp. 123,750.00 Rp. 43,312.50
0.0350 OH Kepala Tukang Batu Rp. 135,000.00 Rp. 4,725.00
0.0300 OH Mandor Rp. 146,250.00 Rp. 4,387.50
11.8700 Bh Mozaik 30 x 30 cm Rp. 7,623.00 Rp. 90,485.01
14.1500 Kg Semen PC Rp. 2,136.75 Rp. 30,235.01
0.0390 M3 Pasir pasang Rp. 247,500.00 Rp. 9,652.50
2.0000 Kg Semen Warna Rp. 12,320.00 Rp. 24,640.00
Rp. 118,687.50 Rp. 155,012.52 Rp. 273,700.02

SNI -2008.13.39a 1 M' MEMASANG PLINT KERAMIK 10X30 CM


0.0900 OH Laden Tukang Batu Rp. 106,875.00 Rp. 9,618.75
0.0900 OH Tukang batu Rp. 123,750.00 Rp. 11,137.50
0.0090 OH Kepala Tukang Batu Rp. 135,000.00 Rp. 1,215.00
0.0050 OH Mandor Rp. 146,250.00 Rp. 731.25
1.0000 M' Plint keramik 10 x 30 cm Rp. 6,952.00 Rp. 6,952.00
1.1400 Kg Semen PC Rp. 2,136.75 Rp. 2,435.90
0.0030 M3 Pasir pasang Rp. 247,500.00 Rp. 742.50
0.0250 Kg Semen Warna Rp. 12,320.00 Rp. 308.00
Rp. 22,702.50 Rp. 10,438.40 Rp. 33,140.90

SNI T-2008.13.54a1 M2 MEMASANG DINDING KERAMIK 20X25 CM


0.6000 OH Laden Tukang Batu Rp. 106,875.00 Rp. 64,125.00
0.4500 OH Tukang batu Rp. 123,750.00 Rp. 55,687.50
0.0450 OH Kepala Tukang Batu Rp. 135,000.00 Rp. 6,075.00
0.0300 OH Mandor Rp. 146,250.00 Rp. 4,387.50
20.0000 Bh keramik 20 X 25 cm Rp. 4,081.00 Rp. 81,620.00
9.3000 Kg Semen PC Rp. 2,136.75 Rp. 19,871.78
0.0180 M3 Pasir pasang Rp. 247,500.00 Rp. 4,455.00
2.7500 Kg Semen Warna Rp. 12,320.00 Rp. 33,880.00
Rp. 130,275.00 Rp. 139,826.78 Rp. 270,101.78

SNI -2008.13.35 1 M2 MEMASANG KERAMIK 40X40 CM


0.2500 OH Laden Tukang Batu Rp. 106,875.00 Rp. 26,718.75
0.1250 OH Tukang batu Rp. 123,750.00 Rp. 15,468.75
0.0130 OH Kepala Tukang Batu Rp. 135,000.00 Rp. 1,755.00
0.0130 OH Mandor Rp. 146,250.00 Rp. 1,901.25
6.6300 Bh Keramik 40x40 cm Rp. 16,456.00 Rp. 109,103.28
9.8000 Kg Semen PC Rp. 2,136.75 Rp. 20,940.15
0.0450 M3 Pasir pasang Rp. 247,500.00 Rp. 11,137.50
Rp. 45,843.75 Rp. 141,180.93 Rp. 187,024.68

Analisa 12
ANALISA URAIAN PEKERJAAN HARGA SATUAN UPAH BAHAN JUMLAH
PEKERJAAN KAYU
SNI -2008.06.1 1 M3 MEMBUAT DAN MEMASANG KOSEN PINTU/JENDELA KAYU ULIN
7.0000 OH Laden Tukang Kayu Rp. 106,875.00 Rp. 748,125.00
21.0000 OH Tukang kayu Rp. 123,750.00 Rp. 2,598,750.00
2.1000 OH Kepala Tukang Kayu Rp. 135,000.00 Rp. 283,500.00
0.3500 OH Mandor Rp. 146,250.00 Rp. 51,187.50
1.1000 M3 Balok kayu klas I (Ulin) Rp. 8,288,500.00 Rp. 9,117,350.00
1.2500 Kg Paku Ulin Rp. 36,300.00 Rp. 45,375.00
Rp. 3,681,562.50 Rp. 9,162,725.00 Rp. 12,844,287.50

SNI -2008.06.2 1 M3 MEMBUAT DAN MEMASANG KOSEN PINTU/JENDELA KAYU KLAS II


6.0000 OH Laden Tukang Kayu Rp. 106,875.00 Rp. 641,250.00
18.0000 OH Tukang kayu Rp. 123,750.00 Rp. 2,227,500.00
1.8000 OH Kepala Tukang Kayu Rp. 135,000.00 Rp. 243,000.00
0.3000 OH Mandor Rp. 146,250.00 Rp. 43,875.00
1.2000 M3 Balok kayu klas II Rp. 3,751,000.00 Rp. 4,501,200.00
1.2500 Kg Paku Kayu Rp. 24,200.00 Rp. 30,250.00
Rp. 3,155,625.00 Rp. 4,531,450.00 Rp. 7,687,075.00

SNI -2008.06.5 1 M2 MEMBUAT DAN MEMASANG DAUN PINTU PANEL KAYU KLAS I ATAU KLAS II
1.0000 OH Laden Tukang Kayu Rp. 106,875.00 Rp. 106,875.00
3.0000 OH Tukang kayu Rp. 123,750.00 Rp. 371,250.00
0.3000 OH Kepala Tukang Kayu Rp. 135,000.00 Rp. 40,500.00
0.0500 OH Mandor Rp. 146,250.00 Rp. 7,312.50
0.0400 M3 Papan kayu klas I (Ulin) Rp. 8,250,000.00 Rp. 330,000.00
0.0400 M3 Papan kayu klas II Rp. 3,300,000.00 Rp. 132,000.00
0.5000 Kg Lem kayu Rp. 26,400.00 Rp. 13,200.00
Untuk Daun pintu panel kayu klas I = Rp. 525,937.50 Rp. 343,200.00 Rp. 869,137.50
Untuk Daun pintu panel kayu klas II = Rp. 525,937.50 Rp. 145,200.00 Rp. 671,137.50

SNI -2008.06.6 1 M2 MEMBUAT DAN MEMASANG DAUN PINTU PANEL KACA KAYU KLAS I ATAU KLAS II
0.8000 OH Laden Tukang Kayu Rp. 106,875.00 Rp. 85,500.00
2.4000 OH Tukang kayu Rp. 123,750.00 Rp. 297,000.00
0.2400 OH Kepala Tukang Kayu Rp. 135,000.00 Rp. 32,400.00
0.0400 OH Mandor Rp. 146,250.00 Rp. 5,850.00
0.0240 M3 Papan kayu klas I (Ulin) Rp. 8,250,000.00 Rp. 198,000.00
0.0240 M3 Papan kayu klas II Rp. 3,300,000.00 Rp. 79,200.00
0.3000 Kg Lem kayu Rp. 26,400.00 Rp. 7,920.00
0.7500 M2 Kaca Polos 5 mm Rp. 205,700.00 Rp. 154,275.00
Untuk Daun pintu panel kaca dgn rangka kayu klas I = Rp. 420,750.00 Rp. 360,195.00 Rp. 780,945.00
Untuk Daun pintu panel kaca dgn rangka kayu klas II = Rp. 420,750.00 Rp. 241,395.00 Rp. 662,145.00

SNI3 -2008.06.10 1 M2 MEMBUAT DAN MEMASANG JALUSI KAYU KLAS II


0.6700 OH Laden Tukang Kayu Rp. 106,875.00 Rp. 71,606.25
2.0000 OH Tukang kayu Rp. 123,750.00 Rp. 247,500.00
0.2000 OH Kepala Tukang Kayu Rp. 135,000.00 Rp. 27,000.00
0.3350 OH Mandor Rp. 146,250.00 Rp. 48,993.75
0.0600 M3 Papan kayu klas II Rp. 3,300,000.00 Rp. 198,000.00
0.1500 Kg Paku kayu Rp. 24,200.00 Rp. 3,630.00
Rp. 395,100.00 Rp. 201,630.00 Rp. 596,730.00

SNI -2008.06.13 1 M3 MEMBUAT DAN MEMASANG KUDA-KUDA KONVENSIONAL KAYU KLAS II


4.0000 OH Laden Tukang Kayu Rp. 106,875.00 Rp. 427,500.00
12.0000 OH Tukang kayu Rp. 123,750.00 Rp. 1,485,000.00
1.2000 OH Kepala Tukang Kayu Rp. 135,000.00 Rp. 162,000.00
0.2000 OH Mandor Rp. 146,250.00 Rp. 29,250.00
1.1000 M3 Balok kayu klas II Rp. 3,751,000.00 Rp. 4,126,100.00
15.0000 Kg Besi beugel/Besi Strip Rp. 25,410.00 Rp. 381,150.00
5.6000 Kg Paku kayu Rp. 24,200.00 Rp. 135,520.00
Rp. 2,103,750.00 Rp. 4,642,770.00 Rp. 6,746,520.00

SNI -2008.06.15 1 M3 MEMBUAT DAN MEMASANG KONSTRUKSI GORDENG KAYU KLAS II


2.4000 OH Laden Tukang Kayu Rp. 106,875.00 Rp. 256,500.00
7.2000 OH Tukang kayu Rp. 123,750.00 Rp. 891,000.00
0.7200 OH Kepala Tukang Kayu Rp. 135,000.00 Rp. 97,200.00
0.1200 OH Mandor Rp. 146,250.00 Rp. 17,550.00
1.1000 M3 Balok kayu klas II Rp. 3,751,000.00 Rp. 4,126,100.00
3.0000 Kg Paku kayu Rp. 24,200.00 Rp. 72,600.00
15.0000 Kg Besi beugel/Besi Strip Rp. 25,410.00 Rp. 381,150.00
Rp. 1,262,250.00 Rp. 4,579,850.00 Rp. 5,842,100.00

Analisa 13
ANALISA URAIAN PEKERJAAN HARGA SATUAN UPAH BAHAN JUMLAH

Analisa 14
ANALISA URAIAN PEKERJAAN HARGA SATUAN UPAH BAHAN JUMLAH
SNI -2008.06.17 1 M2 RANGKA ATAP KASAU 5/7 DAN RENG 3/5 KAYU KLAS II
UNTUK GENTENG METAL ROOF
0.1000 OH Laden Tukang Kayu Rp. 106,875.00 Rp. 10,687.50
0.1000 OH Tukang kayu Rp. 123,750.00 Rp. 12,375.00
0.0100 OH Kepala Tukang Kayu Rp. 135,000.00 Rp. 1,350.00
0.0050 OH Mandor Rp. 146,250.00 Rp. 731.25
0.0140 M3 M3 Kasau 5/7 cm Rp. 3,751,000.00 Rp. 52,514.00
0.0072 M3 M3 Reng 3/4 cm Rp. 3,751,000.00 Rp. 27,007.20
0.2500 Kg Paku kayu Rp. 24,200.00 Rp. 6,050.00
Rp. 25,143.75 Rp. 85,571.20 Rp. 110,714.95

SNI -2008.06.20 1 M2 MEMASANG RANGKA LANGIT-LANGIT KAYU KLAS II (60X120 CM)


0.2000 OH Laden Tukang Kayu Rp. 106,875.00 Rp. 21,375.00
0.3000 OH Tukang kayu Rp. 123,750.00 Rp. 37,125.00
0.0300 OH Kepala Tukang Kayu Rp. 135,000.00 Rp. 4,050.00
0.0100 OH Mandor Rp. 146,250.00 Rp. 1,462.50
0.0163 M3 Balok kayu klas II Rp. 3,751,000.00 Rp. 61,141.30
0.2500 Kg Paku kayu Rp. 24,200.00 Rp. 6,050.00
Rp. 64,012.50 Rp. 67,191.30 Rp. 131,203.80

SNI -2008.06.21 1 M' LISPLANK 3/20 CM PAPAN


0.0500 OH Mandor Rp. 146,250.00 Rp. 7,312.50
0.0200 OH Kepala Tukang Kayu Rp. 135,000.00 Rp. 2,700.00
0.0200 OH Tukang kayu Rp. 123,750.00 Rp. 2,475.00
0.1000 OH Laden Tukang Kayu Rp. 106,875.00 Rp. 10,687.50
0.0108 M3 Papan kayu klas I (Ulin) Rp. 8,250,000.00 Rp. 89,100.00
0.1000 Kg Paku ulin Rp. 36,300.00 Rp. 3,630.00
0.0108 M3 Balok kayu klas II Rp. 3,751,000.00 Rp. 40,510.80
0.1000 Kg Paku kayu Rp. 24,200.00 Rp. 2,420.00
Rp. 23,175.00 Rp. 92,730.00 Rp. 115,905.00
Rp. 23,175.00 Rp. 42,930.80 Rp. 66,105.80

PEKERJAAN LANGIT-LANGIT
SNI -2008.09.5 1 M2 PENUTUP LANGIT-LANGIT PLYWOOD 3 MM
0.0035 OH Mandor Rp. 146,250.00 Rp. 511.88
0.0100 OH Kepala Tukang Kayu Rp. 135,000.00 Rp. 1,350.00
0.1000 OH Tukang kayu Rp. 123,750.00 Rp. 12,375.00
0.0700 OH Laden Tukang Kayu Rp. 106,875.00 Rp. 7,481.25
0.0300 Kg Paku plywood/Teaxwood Rp. 35,090.00 Rp. 1,052.70
0.3750 Lbr Plywood 4 mm Rp. 87,725.00 Rp. 32,896.88
Rp. 21,718.13 Rp. 33,949.58 Rp. 55,667.70

SNI -2008.09.6 1 M2 PENUTUP LANGIT-LANGIT MOULDING


0.0100 OH Mandor Rp. 146,250.00 Rp. 1,462.50
0.0600 OH Kepala Tukang Kayu Rp. 135,000.00 Rp. 8,100.00
0.6000 OH Tukang kayu Rp. 123,750.00 Rp. 74,250.00
0.2000 OH Laden Tukang Kayu Rp. 106,875.00 Rp. 21,375.00
0.1000 Kg Paku Kayu Rp. 24,200.00 Rp. 2,420.00
2.7500 Kpg Kayu Moulding lap-lapan Rp. 53,900.00 Rp. 148,225.00
Rp. 105,187.50 Rp. 150,645.00 Rp. 255,832.50
SNI -2008.09.7 1 M2 PENUTUP LANGIT-LANGIT GYPSUM
0.0050 OH Mandor Rp. 146,250.00 Rp. 731.25
0.0050 OH Kepala Tukang Kayu Rp. 135,000.00 Rp. 675.00
0.0500 OH Tukang kayu Rp. 123,750.00 Rp. 6,187.50
0.1000 OH Laden Tukang Kayu Rp. 106,875.00 Rp. 10,687.50
0.1100 Kg Paku Skrup Rp. 34,980.00 Rp. 3,847.80
0.3640 Lbr Gypsum Rp. 72,600.00 Rp. 26,426.40
Rp. 18,281.25 Rp. 30,274.20 Rp. 48,555.45

SNI -2008.09.10 1 M' LIS LANGIT-LANGIT KAYU PROFIL


0.0030 OH Mandor Rp. 146,250.00 Rp. 438.75
0.0050 OH Kepala Tukang Kayu Rp. 135,000.00 Rp. 675.00
0.0500 OH Tukang kayu Rp. 123,750.00 Rp. 6,187.50
0.0500 OH Laden Tukang Kayu Rp. 106,875.00 Rp. 5,343.75
0.0100 Kg Paku plywood/Teaxwood Rp. 35,090.00 Rp. 350.90
1.0500 m' Lis profil Rp. 10,560.00 Rp. 11,088.00
Rp. 12,645.00 Rp. 11,438.90 Rp. 24,083.90

Analisa 15
ANALISA URAIAN PEKERJAAN HARGA SATUAN UPAH BAHAN JUMLAH
SNI -2008.09.10a 1 M' LIS LANGIT-LANGIT GYPSUM
0.0030 OH Mandor Rp. 146,250.00 Rp. 438.75
0.0050 OH Kepala Tukang Kayu Rp. 135,000.00 Rp. 675.00
0.0500 OH Tukang kayu Rp. 123,750.00 Rp. 6,187.50
0.0500 OH Laden Tukang Kayu Rp. 106,875.00 Rp. 5,343.75
0.0100 Kg Paku Skrup Rp. 34,980.00 Rp. 349.80
1.0500 m' List profil Gypsum Rp. 5,000.00 Rp. 5,250.00
Rp. 12,645.00 Rp. 5,599.80 Rp. 18,244.80

PEKERJAAN ATAP
SNI. -2007.08.32 1 M2 PENUTUP ATAP GENTENG METAL
0.0010 OH Mandor Rp. 146,250.00 Rp. 146.25
0.0100 OH Kepala Tukang Kayu Rp. 135,000.00 Rp. 1,350.00
0.1000 OH Tukang kayu Rp. 123,750.00 Rp. 12,375.00
0.2000 OH Laden Tukang Kayu Rp. 106,875.00 Rp. 21,375.00
1.0200 M2 Genteng Metal Rp. 69,903.23 Rp. 71,301.29
0.2000 Kg Paku anti karat (Paku genteng Metal) Rp. 38,060.00 Rp. 7,612.00
Rp. 35,246.25 Rp. 78,913.29 Rp. 114,159.54
SNI -2007.08.36 1 M' BUBUNGAN ATAP GENTENG METAL
0.0130 OH Mandor Rp. 146,250.00 Rp. 1,901.25
0.0150 OH Kepala Tukang Kayu Rp. 135,000.00 Rp. 2,025.00
0.1500 OH Tukang kayu Rp. 123,750.00 Rp. 18,562.50
0.2500 OH Laden Tukang Kayu Rp. 106,875.00 Rp. 26,718.75
1.1000 M' Bubungan Genteng Metal Rp. 32,670.00 Rp. 35,937.00
0.0500 Kg Paku anti karat (Paku genteng Metal) Rp. 38,060.00 Rp. 1,903.00
Rp. 49,207.50 Rp. 37,840.00 Rp. 87,047.50

PEKERJAAN BETON
SNI.-2007.07.5 1 M3 MEMBUAT BETON CAMP. 1PC : 2 PSR : 3 KRL
0.0800 OH Mandor Rp. 146,250.00 Rp. 11,700.00
0.0250 OH Kepala Tukang Batu Rp. 135,000.00 Rp. 3,375.00
0.2500 OH Tukang Batu Rp. 123,750.00 Rp. 30,937.50
1.6500 OH Laden Tukang Batu Rp. 106,875.00 Rp. 176,343.75
232.0000 Kg Semen PC Rp. 2,136.75 Rp. 495,726.00
0.5200 M3 Pasir Beton Rp. 181,500.00 Rp. 94,380.00
0.7800 M3 Kerikil Rp. 199,650.00 Rp. 155,727.00
Rp. 222,356.25 Rp. 745,833.00 Rp. 968,189.25

SNI.-2007.07.2 1 M3 BETON TUMBUK CAMP. 1 PC : 3 PSR : 6 KRL


0.0800 OH Mandor Rp. 146,250.00 Rp. 11,700.00
0.0250 OH Kepala Tukang Batu Rp. 135,000.00 Rp. 3,375.00
0.2500 OH Tukang Batu Rp. 123,750.00 Rp. 30,937.50
1.6500 OH Laden Tukang Batu Rp. 106,875.00 Rp. 176,343.75
0.9400 M3 Kerikil Rp. 199,650.00 Rp. 187,671.00
197.0000 Kg Semen PC Rp. 2,136.75 Rp. 420,939.75
0.4700 M3 Pasir Beton Rp. 181,500.00 Rp. 85,305.00
Rp. 222,356.25 Rp. 693,915.75 Rp. 916,272.00

H.17 1 M' TALANG SENG LEBAR 25 CM


0.0150 OH Mandor Rp. 146,250.00 Rp. 2,193.75
0.0500 OH Kepala Tukang Kayu Rp. 135,000.00 Rp. 6,750.00
0.5000 OH Tukang kayu Rp. 123,750.00 Rp. 61,875.00
0.3000 OH Laden Tukang Kayu Rp. 106,875.00 Rp. 32,062.50
0.3000 Lbr Seng plat Rp. 23,980.00 Rp. 7,194.00
0.2000 LKg Paku Seng Rp. 52,580.00 Rp. 10,516.00
Rp. 102,881.25 Rp. 17,710.00 Rp. 120,591.25

PEKERJAAN SANITASI
SNI.-2002.10.1 MEMASANG 1 BH CLOSET DUDUK
0.1600 OH Mandor Rp. 146,250.00 Rp. 23,400.00
1.5000 OH Kepala Tukang Batu Rp. 135,000.00 Rp. 202,500.00
1.5000 OH Tukang batu Rp. 123,750.00 Rp. 185,625.00
1.0000 OH Laden Tukang Batu Rp. 106,875.00 Rp. 106,875.00
1.0000 Bh Closet duduk merk American Standart Rp. 1,527,570.00 Rp. 1,527,570.00
6.0000 Kg Semen PC Rp. 2,136.75 Rp. 12,820.50
0.0100 M3 Pasir Pasang Rp. 247,500.00 Rp. 2,475.00
Rp. 518,400.00 Rp. 1,542,865.50 Rp. 2,061,265.50

Analisa 16
ANALISA URAIAN PEKERJAAN HARGA SATUAN UPAH BAHAN JUMLAH
SNI.-2002.10.2 MEMASANG 1 BH CLOSET JONGKOK
0.1600 OH Mandor Rp. 146,250.00 Rp. 23,400.00
1.5000 OH Kepala Tukang Batu Rp. 135,000.00 Rp. 202,500.00
1.5000 OH Tukang batu Rp. 123,750.00 Rp. 185,625.00
1.0000 OH Laden Tukang Batu Rp. 106,875.00 Rp. 106,875.00
1.0000 Bh Closet jongkok porselin putih merk INA Rp. 181,500.00 Rp. 181,500.00
6.0000 Kg Semen PC Rp. 2,136.75 Rp. 12,820.50
0.0100 M3 Pasir Pasang Rp. 247,500.00 Rp. 2,475.00
Rp. 518,400.00 Rp. 196,795.50 Rp. 715,195.50

SNI.-2002.10.7 MEMASANG 1 BUAH BAK MANDI FIBRE


0.4500 OH Mandor Rp. 146,250.00 Rp. 65,812.50
0.4500 OH Kepala Tukang Batu Rp. 135,000.00 Rp. 60,750.00
2.2500 OH Tukang batu Rp. 123,750.00 Rp. 278,437.50
1.5000 OH Laden Tukang Batu Rp. 106,875.00 Rp. 160,312.50
1.0000 Bh Bak mandi Fibre 50x50x50 cm Rp. 384,175.00 Rp. 384,175.00
Perlengkapan = 12 % Harga bak Rp. 46,101.00 Rp. 46,101.00
Rp. 565,312.50 Rp. 430,276.00 Rp. 995,588.50

SNI.-2002.10.36 MEMASANG 1 BUAH FLOOR DRAIN (SARINGAN AIR)


0.0050 OH Mandor Rp. 146,250.00 Rp. 731.25
0.0100 OH Kepala Tukang Batu Rp. 135,000.00 Rp. 1,350.00
0.1000 OH Tukang batu Rp. 123,750.00 Rp. 12,375.00
0.0100 OH Laden Tukang Batu Rp. 106,875.00 Rp. 1,068.75
1.0000 Bh Floor drain Rp. 38,500.00 Rp. 38,500.00
0.0250 Bh Seal tape Rp. 11,000.00 Rp. 275.00
Rp. 15,525.00 Rp. 38,775.00 Rp. 54,300.00

SNI.-2002.10.35 MEMASANG 1 BUAH KRAN AIR


0.0050 OH Mandor Rp. 146,250.00 Rp. 731.25
0.0100 OH Kepala Tukang Batu Rp. 135,000.00 Rp. 1,350.00
0.1000 OH Tukang batu Rp. 123,750.00 Rp. 12,375.00
0.0100 OH Laden Tukang Batu Rp. 106,875.00 Rp. 1,068.75
1.0000 Bh Kran air stainless Rp. 109,505.00 Rp. 109,505.00
0.0250 Bh Seal tape Rp. 11,000.00 Rp. 275.00
Rp. 15,525.00 Rp. 109,780.00 Rp. 125,305.00

PEKERJAAN KUNCI DAN PENGGANTUNG


SNI.-2007.12.2 MEMASANG 1 BH KUNCI TANAM BIASA
0.0050 OH Mandor Rp. 146,250.00 Rp. 731.25
0.0100 OH Kepala Tukang Kayu Rp. 135,000.00 Rp. 1,350.00
0.5000 OH Tukang kayu Rp. 123,750.00 Rp. 61,875.00
0.0100 OH Laden Tukang Kayu Rp. 106,875.00 Rp. 1,068.75
1.0000 Bh Kunci tanam Standart (pintu utama) Rp. 176,660.00 Rp. 176,660.00
Rp. 65,025.00 Rp. 176,660.00 Rp. 241,685.00

SNI.-2007.12.5 MEMASANG 1 BH ENGSEL PINTU


0.0008 OH Mandor Rp. 146,250.00 Rp. 109.69
0.0150 OH Kepala Tukang Kayu Rp. 135,000.00 Rp. 2,025.00
0.1500 OH Tukang kayu Rp. 123,750.00 Rp. 18,562.50
0.0150 OH Laden Tukang Kayu Rp. 106,875.00 Rp. 1,603.13
1.0000 Ps Engsel lokal 4" untuk pintu Rp. 30,250.00 Rp. 30,250.00
Rp. 22,300.31 Rp. 30,250.00 Rp. 52,550.31

SNI.-2007.12.6 MEMASANG 1 BH ENGSEL JENDELA


0.0005 OH Mandor Rp. 146,250.00 Rp. 73.13
0.0100 OH Kepala Tukang Kayu Rp. 135,000.00 Rp. 1,350.00
0.1000 OH Tukang kayu Rp. 123,750.00 Rp. 12,375.00
0.0100 OH Laden Tukang Kayu Rp. 106,875.00 Rp. 1,068.75
1.0000 Ps Engsel lokal 3" untuk jendela Rp. 18,150.00 Rp. 18,150.00
Rp. 14,866.88 Rp. 18,150.00 Rp. 33,016.88

SNI.-2007.12.9 MEMASANG 1 BH HAK ANGIN


0.0080 OH Mandor Rp. 146,250.00 Rp. 1,170.00
0.0150 OH Kepala Tukang Kayu Rp. 135,000.00 Rp. 2,025.00
0.1500 OH Tukang kayu Rp. 123,750.00 Rp. 18,562.50
0.0150 OH Laden Tukang Kayu Rp. 106,875.00 Rp. 1,603.13
1.0000 Ps Hak angin Rp. 12,100.00 Rp. 12,100.00
Rp. 23,360.63 Rp. 12,100.00 Rp. 35,460.63

Analisa 17
ANALISA URAIAN PEKERJAAN HARGA SATUAN UPAH BAHAN JUMLAH
SNI.-2007.12.11 MEMASANG 1 BH KUNCI SELOT (GRENDEL)
0.0010 OH Mandor Rp. 146,250.00 Rp. 146.25
0.0200 OH Kepala Tukang Kayu Rp. 135,000.00 Rp. 2,700.00
0.2000 OH Tukang kayu Rp. 123,750.00 Rp. 24,750.00
0.0200 OH Laden Tukang Kayu Rp. 106,875.00 Rp. 2,137.50
1.0000 Ps Grendel lokal Rp. 9,020.00 Rp. 9,020.00
Rp. 29,733.75 Rp. 9,020.00 Rp. 38,753.75

SNI.-2007.12.12 MEMASANG 1 BH PEGANGAN JENDELA ATAU PINTU


0.0003 OH Mandor Rp. 146,250.00 Rp. 36.56
0.0500 OH Kepala Tukang Kayu Rp. 135,000.00 Rp. 6,750.00
0.5000 OH Tukang kayu Rp. 123,750.00 Rp. 61,875.00
0.0500 OH Laden Tukang Kayu Rp. 106,875.00 Rp. 5,343.75
1.0000 Ps Grendel lokal Rp. 9,020.00 Rp. 9,020.00
Rp. 74,005.31 Rp. 9,020.00 Rp. 83,025.31

SNI.-2007.12.17 MEMASANG 1 M2 KACA TEBAL 5MM


0.0008 OH Mandor Rp. 146,250.00 Rp. 117.00
0.0150 OH Kepala Tukang Kayu Rp. 135,000.00 Rp. 2,025.00
0.1500 OH Tukang kayu Rp. 123,750.00 Rp. 18,562.50
0.0150 OH Laden Tukang Kayu Rp. 106,875.00 Rp. 1,603.13
1.0000 M2 Kaca polos 5 mm Rp. 205,700.00 Rp. 205,700.00
1.0000 M2 Kaca Ryben 5 mm Rp. 211,750.00 Rp. 211,750.00
Rp. 22,307.63 Rp. 205,700.00 Rp. 228,007.63
Rp. 22,307.63 Rp. 211,750.00 Rp. 234,057.63

PEKERJAAN BESI DAN ALUMUNIUM


SNI.-2007.12.17 MEMASANG 1 M2 TERALIS BESI
0.0830 OH Mandor Rp. 146,250.00 Rp. 12,138.75
0.1670 OH Kepala Tukang Besi Rp. 135,000.00 Rp. 22,545.00
1.6700 OH Tukang Las Rp. 106,875.00 Rp. 178,481.25
1.6700 OH Laden Tukang Besi Rp. 106,875.00 Rp. 178,481.25
6.1770 M2 Besi beugel/Besi Strip Rp. 25,410.00 Rp. 156,957.57
27.0800 cm Pengelasan Rp. 5,000.00 Rp. 135,400.00
Rp. 391,646.25 Rp. 292,357.57 Rp. 684,003.82

SNI.-2008.12.10 MEMASANG 1 M' KUSEN ALMUNIUM


0.0020 OH Mandor Rp. 146,250.00 Rp. 292.50
0.0040 OH Kepala Tukang Besi Rp. 135,000.00 Rp. 540.00
0.0430 OH Tukang Las Rp. 106,875.00 Rp. 4,595.63
0.0430 OH Laden Tukang Besi Rp. 106,875.00 Rp. 4,595.63
1.1000 M' Profil Almunium Rp. 127,050.00 Rp. 139,755.00
2.0000 Buah Skrup Fixer Rp. 34,980.00 Rp. 69,960.00
0.0600 tube Sealant Rp. 5,000.00 Rp. 300.00
Rp. 10,023.75 Rp. 210,015.00 Rp. 220,038.75

PEKERJAAN PENGECATAN
SNI.-2002.14.9 1 M2 MENGECAT KILAP KAYU (1 LPS PLAMIR, 1 LPS CAT DASAR DAN 2 LPS CAT KILAP)
0.0025 OH Mandor Rp. 146,250.00 Rp. 365.63
0.0040 OH Kepala tukang cat Rp. 135,000.00 Rp. 540.00
0.1050 OH Tukang cat Rp. 123,750.00 Rp. 12,993.75
0.0700 OH Laden Tukang Cat Rp. 106,875.00 Rp. 7,481.25
0.2000 Kg Cat Menie Kayu Rp. 42,350.00 Rp. 8,470.00
0.1500 Kg Plamur Kayu Rp. 31,130.00 Rp. 4,669.50
0.1700 Kg Cat dasar kayu Rp. 51,040.00 Rp. 8,676.80
0.2600 Kg Cat kayu mengkilat Rp. 53,240.00 Rp. 13,842.40
Rp. 21,380.63 Rp. 35,658.70 Rp. 57,039.33

SNI.-2002.14.14 1 M2 MENGECAT TEMBOK (1 LPS PLAMIR, 1 LPS CAT DASAR DAN 2 LPS CAT TEMBOK)
0.0025 OH Mandor Rp. 146,250.00 Rp. 365.63
0.0063 OH Kepala tukang cat Rp. 135,000.00 Rp. 850.50
0.0630 OH Tukang cat Rp. 123,750.00 Rp. 7,796.25
0.0200 OH Laden Tukang Cat Rp. 106,875.00 Rp. 2,137.50
0.1000 Kg Plamur tembok Rp. 17,666.00 Rp. 1,766.60
0.1000 Kg Cat dasar tembok Rp. 21,780.00 Rp. 2,178.00
0.2600 Kg Cat tembok Rp. 21,780.00 Rp. 5,662.80
Rp. 11,149.88 Rp. 9,607.40 Rp. 20,757.28

SNI.-2002.14.12 1 M2 MENGETER BIDANG KAYU DENGAN RESIDU


0.0060 OH Mandor Rp. 146,250.00 Rp. 877.50
0.1000 OH Laden Tukang Kayu Rp. 106,875.00 Rp. 10,687.50

Analisa 18
ANALISA URAIAN PEKERJAAN HARGA SATUAN UPAH BAHAN JUMLAH
0.3500 Kg Residu/Ter Rp. 22,330.00 Rp. 7,815.50
Rp. 11,565.00 Rp. 7,815.50 Rp. 19,380.50

Analisa 19
ANALISA URAIAN PEKERJAAN HARGA SATUAN UPAH BAHAN JUMLAH

SNI.-2002.6.13 1 M2 MEMASANG KAWAT HARMONIKA


0.0005 OH Mandor Rp. 146,250.00 Rp. 73.13
0.0100 OH Kepala tukang Batu Rp. 135,000.00 Rp. 1,350.00
0.1000 OH Tukang Batu Rp. 123,750.00 Rp. 12,375.00
0.1000 OH Laden Tukang Batu Rp. 106,875.00 Rp. 10,687.50
1.1000 M2 Kawat Harmonika Rp. 302,500.00 Rp. 332,750.00
0.0200 Kg Paku Kayu Rp. 24,200.00 Rp. 484.00
Rp. 24,485.63 Rp. 333,234.00 Rp. 357,719.63

SNI. -2007.08.32 1 M2 PENUTUP ATAP SENG GELOMBANG


0.0050 OH Mandor Rp. 146,250.00 Rp. 731.25
0.0050 OH Kepala tukang kayu Rp. 135,000.00 Rp. 675.00
0.0600 OH Tukang kayu Rp. 123,750.00 Rp. 7,425.00
0.1200 OH Laden Tukang Kayu Rp. 106,875.00 Rp. 12,825.00
0.7000 Lbr Seng gelombang BJLS 30 Rp. 47,190.00 Rp. 33,033.00
0.0200 Kg Paku Kayu Rp. 24,200.00 Rp. 484.00
Rp. 21,656.25 Rp. 33,517.00 Rp. 55,173.25

SNI -2007.08.36 1 M' BUBUNGAN ATAP SENG


0.0060 OH Mandor Rp. 146,250.00 Rp. 877.50
0.0080 OH Kepala tukang kayu Rp. 135,000.00 Rp. 1,080.00
0.0700 OH Tukang kayu Rp. 123,750.00 Rp. 8,662.50
0.1500 OH Laden Tukang Kayu Rp. 106,875.00 Rp. 16,031.25
0.3000 Lbr Seng plat Rp. 23,980.00 Rp. 7,194.00
0.0400 Kg Paku Kayu Rp. 24,200.00 Rp. 968.00
Rp. 26,651.25 Rp. 8,162.00 Rp. 34,813.25

F. 19 1 M2 MEMASANG RANGKA ATAP SENG


0.0075 OH Mandor Rp. 146,250.00 Rp. 1,096.88
0.0100 OH Kepala tukang kayu Rp. 135,000.00 Rp. 1,350.00
0.1000 OH Tukang kayu Rp. 123,750.00 Rp. 12,375.00
0.1500 OH Laden Tukang Kayu Rp. 106,875.00 Rp. 16,031.25
0.0110 M3 Balok kayu klas II Rp. 3,751,000.00 Rp. 41,261.00
0.0400 Kg Paku Kayu Rp. 24,200.00 Rp. 968.00
Rp. 30,853.13 Rp. 42,229.00 Rp. 73,082.13

SNI -2008.06.8 1 M2 MEMBUAT DAN MEMASANG DAUN PINTU PLYWOOD RANGKAP KAYU KELAS II
0.7000 OH Laden Tukang Kayu Rp. 106,875.00 Rp. 74,812.50
2.1000 OH Tukang kayu Rp. 123,750.00 Rp. 259,875.00
0.2100 OH Kepala Tukang Kayu Rp. 135,000.00 Rp. 28,350.00
0.0350 OH Mandor Rp. 146,250.00 Rp. 5,118.75
0.0250 M3 Papan kayu klas II Rp. 3,300,000.00 Rp. 82,500.00
0.0300 Kg Paku Kayu Rp. 24,200.00 Rp. 726.00
0.5000 Kg Lem kayu Rp. 26,400.00 Rp. 13,200.00
1.0000 Lbr Plywood 4 mm Rp. 87,725.00 Rp. 87,725.00
Untuk Daun pintu panel kayu klas I = Rp. 368,156.25 Rp. 184,151.00 Rp. 552,307.25
SNI -2008.06.25c 1 M2 MEMASANG DINDING PLYWOOD
0.2000 OH Laden Tukang Kayu Rp. 106,875.00 Rp. 21,375.00
0.6000 OH Tukang kayu Rp. 123,750.00 Rp. 74,250.00
0.0600 OH Kepala Tukang Kayu Rp. 135,000.00 Rp. 8,100.00
0.0100 OH Mandor Rp. 146,250.00 Rp. 1,462.50
0.1500 Kg Paku Skrup Rp. 34,980.00 Rp. 5,247.00
0.4300 Lbr Plywood 4 mm Rp. 87,725.00 Rp. 37,721.75
0.5600 Kg Lem Kayu Rp. 26,400.00 Rp. 14,784.00
Rp. 105,187.50 Rp. 57,752.75 Rp. 162,940.25
SUV. VI 1 M2 MEMASANG PAVING STONE
0.015 OH Mandor Rp. 146,250.00 Rp. 2,193.75
0.018 OH Kepala Tukang Batu Rp. 135,000.00 Rp. 2,362.50
0.175 OH Tukang Batu Rp. 123,750.00 Rp. 21,656.25
0.310 OH Laden Tukang Batu Rp. 106,875.00 Rp. 33,131.25
1.000 M2 Paving Stone Segi Enam Rp. 143,990.00 Rp. 143,990.00
0.042 M3 Pasir Pasang Rp. 247,500.00 Rp. 10,395.00
Rp. 59,343.75 Rp. 154,385.00 Rp. 213,728.75
SNI -2008.13.60 1 M2 MEMASANG WALLPAPER LEBAR 50 CM
0.002 OH Mandor Rp. 146,250.00 Rp. 292.50
0.017 OH Kepala Tukang Batu Rp. 135,000.00 Rp. 2,295.00
0.175 OH Tukang Batu Rp. 123,750.00 Rp. 21,656.25
0.300 OH Laden Tukang Batu Rp. 106,875.00 Rp. 32,062.50
2.200 M Wallpaper Rp. 132,000.00 Rp. 290,400.00

Analisa 20
ANALISA URAIAN PEKERJAAN HARGA SATUAN UPAH BAHAN JUMLAH
0.250 Kg Lem kayu Rp. 26,400.00 Rp. 6,600.00
Rp. 56,306.25 Rp. 297,000.00 Rp. 353,306.25

Analisa 21
ANALISA URAIAN PEKERJAAN HARGA SATUAN UPAH BAHAN JUMLAH
ANALISA BOW
BOW.F.1 1 M3 MENGERJAKAN RANGKA BAWAH
0.2500 OH Mandor Rp. 146,250.00 Rp. 36,562.50
0.7500 OH Kepala tukang Kayu Rp. 135,000.00 Rp. 101,250.00
7.5000 OH Tukang Kayu Rp. 123,750.00 Rp. 928,125.00
5.0000 OH Laden Tukang Kayu Rp. 106,875.00 Rp. 534,375.00
1.1000 M3 Balok kayu klas I (Ulin) Rp. 8,288,500.00 Rp. 9,117,350.00
1.1000 M3 Balok kayu klas II Rp. 3,751,000.00 Rp. 4,126,100.00
5.0000 Kg Paku Ulin Rp. 36,300.00 Rp. 181,500.00
5.0000 Kg Paku Kayu Rp. 24,200.00 Rp. 121,000.00
Rp. 1,600,312.50 Rp. 9,298,850.00 Rp. 10,899,162.50
Rp. 1,600,312.50 Rp. 4,247,100.00 Rp. 5,847,412.50

BOW.F.8 1 M2 MENGERJAKAN DINDING PAPAN 2/20


0.0100 OH Mandor Rp. 146,250.00 Rp. 1,462.50
0.0500 OH Kepala tukang Kayu Rp. 135,000.00 Rp. 6,750.00
0.5000 OH Tukang Kayu Rp. 123,750.00 Rp. 61,875.00
0.0200 OH Laden Tukang Kayu Rp. 106,875.00 Rp. 2,137.50
0.0220 M3 Papan kayu klas I (Ulin) Rp. 8,250,000.00 Rp. 181,500.00
0.0220 M3 Papan kayu klas II Rp. 3,300,000.00 Rp. 72,600.00
0.2000 Kg Paku Ulin Rp. 36,300.00 Rp. 7,260.00
0.2000 Kg Paku Kayu Rp. 24,200.00 Rp. 4,840.00
Rp. 72,225.00 Rp. 188,760.00 Rp. 260,985.00
Rp. 72,225.00 Rp. 77,440.00 Rp. 149,665.00

BOW.F.22 1 M3 MENGERJAKAN RANGKA BADAN


0.4000 OH Mandor Rp. 146,250.00 Rp. 58,500.00
2.4000 OH Kepala tukang Kayu Rp. 135,000.00 Rp. 324,000.00
24.0000 OH Tukang Kayu Rp. 123,750.00 Rp. 2,970,000.00
8.0000 OH Laden Tukang Kayu Rp. 106,875.00 Rp. 855,000.00
1.1000 M3 Balok kayu klas I (Ulin) Rp. 8,288,500.00 Rp. 9,117,350.00
1.1000 M3 Balok kayu klas II Rp. 3,751,000.00 Rp. 4,126,100.00
3.0000 Kg Paku Ulin Rp. 36,300.00 Rp. 108,900.00
3.0000 Kg Paku Kayu Rp. 24,200.00 Rp. 72,600.00
Rp. 4,207,500.00 Rp. 9,226,250.00 Rp. 13,433,750.00
Rp. 4,207,500.00 Rp. 4,198,700.00 Rp. 8,406,200.00

BOW.F.38 1 M2 MENGERJAKAN LANTAI PAPAN TEBAL 3 CM DI SERUT RAPI


0.0300 OH Mandor Rp. 146,250.00 Rp. 4,387.50
0.1800 OH Kepala tukang Kayu Rp. 135,000.00 Rp. 24,300.00
1.8000 OH Tukang Kayu Rp. 123,750.00 Rp. 222,750.00
0.6000 OH Laden Tukang Kayu Rp. 106,875.00 Rp. 64,125.00
0.0350 M3 Papan kayu klas I (Ulin) Rp. 8,250,000.00 Rp. 288,750.00
0.0350 M3 Papan kayu klas II Rp. 3,300,000.00 Rp. 115,500.00
0.2000 Kg Paku Ulin Rp. 36,300.00 Rp. 7,260.00
0.2000 Kg Paku Kayu Rp. 24,200.00 Rp. 4,840.00
Rp. 315,562.50 Rp. 296,010.00 Rp. 611,572.50
Rp. 315,562.50 Rp. 120,340.00 Rp. 435,902.50

SNI .07.6.5 1 M3 MEMBUAT BETON BERTULANG CAMP. 1PC : 2 PSR : 3 KRL


0.08000 OH Mandor Rp. 146,250.00 Rp. 11,700.00
0.02500 OH Kepala Tukang batu Rp. 135,000.00 Rp. 3,375.00
0.25000 OH Tukang Batu Rp. 123,750.00 Rp. 30,937.50
1.65000 OH Laden Tukang Kayu Rp. 106,875.00 Rp. 176,343.75
232.00000 Kg semen PC Rp. 2,136.75 Rp. 495,726.00
0.52000 M3 Pasir Beton Rp. 181,500.00 Rp. 94,380.00
0.78000 M3 Kerikil Rp. 199,650.00 Rp. 155,727.00
Rp. 222,356.25 Rp. 745,833.00 Rp. 968,189.25

SNI .07.6.2 1 M3 BETON TUMBUK CAMP. 1 PC : 3 PSR : 6 KRL


0.08000 OH Mandor Rp. 146,250.00 Rp. 11,700.00
0.02500 OH Kepala Tukang batu Rp. 135,000.00 Rp. 3,375.00
0.25000 OH Tukang Batu Rp. 123,750.00 Rp. 30,937.50
1.65000 OH Laden Tukang Batu Rp. 106,875.00 Rp. 176,343.75
0.94000 M3 Kerikil Rp. 199,650.00 Rp. 187,671.00
197.00000 Kg semen PC Rp. 2,136.75 Rp. 420,939.75
0.47000 M3 Pasir Beton Rp. 181,500.00 Rp. 85,305.00
Rp. 222,356.25 Rp. 693,915.75 Rp. 916,272.00

Analisa 22
ANALISA URAIAN PEKERJAAN HARGA SATUAN UPAH BAHAN JUMLAH
SNI .07.6.25 1 Kg PEMBESIAN DENGAN BESI POLOS ATAU BESI ULIR
0.0003 OH Mandor Rp. 146,250.00 Rp. 43.88
0.0007 OH Kepala Tukang Besi Rp. 135,000.00 Rp. 94.50
0.0070 OH Tukang Besi Rp. 123,750.00 Rp. 866.25
0.0070 OH Laden Tukang Besi Rp. 106,875.00 Rp. 748.13
1.0500 Kg Besi Beton Polos Rp. 18,810.00 Rp. 19,750.50
0.0150 Kg Kawat Beton Rp. 49,610.00 Rp. 744.15
Rp. 1,752.75 Rp. 20,494.65 Rp. 22,247.40

SNI .07.6.28 1M2 PASANG BEGISTING PONDASI


0.0050 OH Mandor Rp. 146,250.00 Rp. 731.25
0.0260 OH Kepala Tukang batu Rp. 135,000.00 Rp. 3,510.00
0.2600 OH Tukang Batu Rp. 123,750.00 Rp. 32,175.00
0.3000 OH Laden Tukang Batu Rp. 106,875.00 Rp. 32,062.50
0.0400 M3 Papan kayu begesting Rp. 2,750,000.00 Rp. 110,000.00
0.3000 Kg Paku Kayu Rp. 24,200.00 Rp. 7,260.00
0.1000 Ltr Minyak begesting Rp. 13,310.00 Rp. 1,331.00
Rp. 68,478.75 Rp. 118,591.00 Rp. 187,069.75
10.00 X 187,069.75 Rp. 1,870,697.50

SNI .07.6.29 1M2 PASANG BEGISTING SLOOF


0.0050 OH Mandor Rp. 146,250.00 Rp. 731.25
0.0260 OH Kepala Tukang batu Rp. 135,000.00 Rp. 3,510.00
0.2600 OH Tukang Batu Rp. 123,750.00 Rp. 32,175.00
0.3000 OH Laden Tukang Batu Rp. 106,875.00 Rp. 32,062.50
0.0230 M3 Papan kayu begesting Rp. 2,750,000.00 Rp. 63,250.00
0.3000 Kg Paku Kayu Rp. 24,200.00 Rp. 7,260.00
0.1000 Ltr Minyak begesting Rp. 13,310.00 Rp. 1,331.00
Rp. 68,478.75 Rp. 71,841.00 Rp. 140,319.75
10.00 X 140,319.75 Rp. 1,403,197.50

SNI .07.6.30 1M2 PASANG BEGISTING KOLOM


0.0060 OH Mandor Rp. 146,250.00 Rp. 877.50
0.0330 OH Kepala Tukang batu Rp. 135,000.00 Rp. 4,455.00
0.3000 OH Tukang Batu Rp. 123,750.00 Rp. 37,125.00
0.3000 OH Laden Tukang Batu Rp. 106,875.00 Rp. 32,062.50
0.0400 M3 Papan kayu begesting Rp. 2,750,000.00 Rp. 110,000.00
0.4000 Kg Paku Kayu Rp. 24,200.00 Rp. 9,680.00
0.2000 Ltr Minyak begesting Rp. 13,310.00 Rp. 2,662.00
0.0150 M3 Balok kayu klas III Rp. 2,722,500.00 Rp. 40,837.50
0.3500 Lbr Plywood 4 mm Rp. 87,725.00 Rp. 30,703.75
2.0000 Btng Kayu Dolken/Galam dia. 10-12 cm P.4M Rp. 12,100.00 Rp. 24,200.00
Rp. 74,520.00 Rp. 218,083.25 Rp. 292,603.25
10.00 X 292,603.25 Rp. 2,926,032.50

SNI .07.6.31 1M2 PASANG BEGISTING BALOK


0.0060 OH Mandor Rp. 146,250.00 Rp. 877.50
0.0330 OH Kepala Tukang batu Rp. 135,000.00 Rp. 4,455.00
0.3300 OH Tukang Batu Rp. 123,750.00 Rp. 40,837.50
0.3200 OH Laden Tukang Batu Rp. 106,875.00 Rp. 34,200.00
0.0400 M3 Papan kayu begesting Rp. 2,750,000.00 Rp. 110,000.00
0.4000 Kg Paku Kayu Rp. 24,200.00 Rp. 9,680.00
0.2000 Ltr Minyak begesting Rp. 13,310.00 Rp. 2,662.00
0.0180 M3 Balok kayu klas III Rp. 2,722,500.00 Rp. 49,005.00
0.3500 Lbr Plywood 4 mm Rp. 87,725.00 Rp. 30,703.75
2.0000 Btng Kayu Dolken/Galam dia. 10-12 cm P.4M Rp. 12,100.00 Rp. 24,200.00
Rp. 80,370.00 Rp. 226,250.75 Rp. 306,620.75
10.00 X 306,620.75 Rp. 3,066,207.50

SNI .07.6.32 1M2 PASANG BEGISTING LANTAI


0.0060 OH Mandor Rp. 146,250.00 Rp. 877.50
0.0330 OH Kepala Tukang batu Rp. 135,000.00 Rp. 4,455.00
0.3300 OH Tukang Batu Rp. 123,750.00 Rp. 40,837.50
0.3200 OH Laden Tukang Batu Rp. 106,875.00 Rp. 34,200.00
0.0400 M3 Papan kayu begesting Rp. 2,750,000.00 Rp. 110,000.00
0.4000 Kg Paku Kayu Rp. 24,200.00 Rp. 9,680.00
0.2000 Ltr Minyak begesting Rp. 13,310.00 Rp. 2,662.00
0.0150 M3 Balok kayu klas III Rp. 2,722,500.00 Rp. 40,837.50
0.3500 Lbr Plywood 4 mm Rp. 87,725.00 Rp. 30,703.75
6.0000 Btng Kayu Dolken/Galam dia. 10-12 cm P.4M Rp. 12,100.00 Rp. 72,600.00
Rp. 80,370.00 Rp. 266,483.25 Rp. 346,853.25

Analisa 23
ANALISA URAIAN PEKERJAAN HARGA SATUAN UPAH BAHAN JUMLAH
10.00 X 346,853.25 Rp. 3,468,532.50

Analisa 24
ANALISA URAIAN PEKERJAAN HARGA SATUAN UPAH BAHAN JUMLAH

SNI .07.6.36 1M3 MEMBUAT BETON DENGAN MUTU K 225


0.3000 OH Mandor Rp. 146,250.00 Rp. 43,875.00
0.1000 OH Kepala Tukang batu Rp. 135,000.00 Rp. 13,500.00
1.0000 OH Tukang Batu Rp. 123,750.00 Rp. 123,750.00
6.0000 OH Laden Tukang Batu Rp. 106,875.00 Rp. 641,250.00
388.0000 Kg Semen PC Rp. 2,136.75 Rp. 829,059.00
0.6500 M3 Pasir Beton Rp. 181,500.00 Rp. 117,975.00
0.6500 M3 Kerikil Rp. 199,650.00 Rp. 129,772.50
Rp. 822,375.00 Rp. 1,076,806.50 Rp. 1,899,181.50

SNI .07.6.38a MEMBUAT 1 M3 PONDASI BETON BERTULANG (150 KG BESI + BEGESTING)


1.00000 MEMBUAT BETON BERTULANG CAMP. 1PC : 2 PSR : 3 KRL Rp. 968,189.25 Rp. 968,189.25
1.00000 BEGISTING PONDASI Rp. 1,870,697.50 Rp. 1,870,697.50
100.00000 PEMBESIAN DENGAN BESI POLOS ATAU BESI ULIR Rp. 22,247.40 Rp. 2,224,740.00
Rp. 5,063,626.75

SNI .07.6.39a MEMBUAT 1 M3 SLOOF BETON BERTULANG (150 KG BESI + BEGESTING)


1.00000 MEMBUAT BETON BERTULANG CAMP. 1PC : 2 PSR : 3 KRL Rp. 968,189.25 Rp. 968,189.25
1.00000 BEGISTING SLOOF Rp. 1,403,197.50 Rp. 1,403,197.50
100.00000 PEMBESIAN DENGAN BESI POLOS ATAU BESI ULIR Rp. 22,247.40 Rp. 2,224,740.00
Rp. 4,596,126.75

SNI .07.6.40a MEMBUAT 1 M3 KOLOM BETON BERTULANG (150 KG BESI + BEGESTING)


1.00000 MEMBUAT BETON BERTULANG CAMP. 1PC : 2 PSR : 3 KRL Rp. 968,189.25 Rp. 968,189.25
1.00000 BEGISTING KOLOM Rp. 2,926,032.50 Rp. 2,926,032.50
100.00000 PEMBESIAN DENGAN BESI POLOS ATAU BESI ULIR Rp. 22,247.40 Rp. 2,224,740.00
Rp. 6,118,961.75

SNI .07.6.41a MEMBUAT 1 M3 BALOK BETON BERTULANG (150 KG BESI + BEGESTING)


1.00000 MEMBUAT BETON BERTULANG CAMP. 1PC : 2 PSR : 3 KRL Rp. 968,189.25 Rp. 968,189.25
1.00000 BEGISTING BALOK Rp. 3,066,207.50 Rp. 3,066,207.50
100.00000 PEMBESIAN DENGAN BESI POLOS ATAU BESI ULIR Rp. 22,247.40 Rp. 2,224,740.00
Rp. 6,259,136.75

SNI .07.6.42a MEMBUAT 1 M3 LANTAI BETON BERTULANG (150 KG BESI + BEGESTING)


1.00000 MEMBUAT BETON BERTULANG CAMP. 1PC : 2 PSR : 3 KRL Rp. 968,189.25 Rp. 968,189.25
1.00000 BEGISTING LANTAI Rp. 3,468,532.50 Rp. 3,468,532.50
100.00000 PEMBESIAN DENGAN BESI POLOS ATAU BESI ULIR Rp. 22,247.40 Rp. 2,224,740.00
Rp. 6,661,461.75

Analisa 25
REKAPITULASI ANALISA
NO ANALISA URAIAN PEKERJAAN JUMLAH
PEKERJAAN PENDAHULUAN
SNI-2002.01.4 1 M' PENGUKURAN DAN PASANG BOUWPLANK Rp 77,547.75
SNI -2002.-01.8 1 M2 MEMBERSIHKAN LAPANGAN DAN PERATAAN Rp 18,000.00

PEKERJAAN TANAH
SNI -2008.02.1 1 M3 MENGGALI TANAH BIASA SEDALAM 1 METER Rp 83,812.50
SNI -2008.02.9 MENGURUG KEMBALI 1 M3 GALIAN Rp 27,937.50
SNI -2008.02.10 MEMADATKAN 1 M3 TANAH (PER 20 CM) Rp 60,750.00
SNI -2008.02.11 1 M3 MENGURUG TANAH URUG Rp 165,525.00
SNI -2008.02.11a 1 M3 MENGURUG PASIR URUG Rp 178,725.00

PEKERJAAN PONDASI
SNI -2008.03.2 1 M3 MEMASANG PONDASI BATU BELAH CAMP. 1 PC : 4 PSR Rp 1,279,209.00
SNI -2008.03.3 1 M3 MEMASANG PONDASI BATU BELAH CAMP. 1 PC : 5 PSR Rp 1,227,456.75
SNI -2008.03.9 1 M3 MEMASANG PONDASI BATU KOSONG (ANSTAMPENG) Rp 722,865.75

PEKERJAAN DINDING
SNI -2008.03.3 1 M2 MEMASANG BATA MERAH TEBAL 1 BATU CAMP. 1 PC : 4 PSR Rp 329,710.71
SNI -2008.04.9 1 M2 MEMASANG BATA MERAH TEBAL 1/2 BATU CAMP. 1 PC : 4 PSR Rp 160,196.38
SNI -2008.04.10 1 M2 MEMASANG BATA MERAH TEBAL 1/2 BATU CAMP. 1 PC : 5 PSR Rp 156,802.49
SNI -2008.04.16 1 M2 MEMASANG BATACO 1/2 BATU CAMP. 1 PC : 3 PSR Rp 110,817.50

PEKERJAAN BETON
SNI -2008.07.28 MEMBUAT 1 M3 PONDASI BETON BERTULANG (200 KG BESI + BEGESTING) Rp 6,596,428.50
SNI -2008.07.29 MEMBUAT 1 M3 SLOOF BETON BERTULANG (200 KG BESI + BEGESTING) Rp 6,964,659.25
SNI -2008.07.29 UNTUK BETON DENGAN BESI 150 KG/M3 ADALAH Rp 5,896,614.25
SNI -2008.07.29 UNTUK BETON DENGAN BESI 100 KG/M3 ADALAH Rp 4,828,569.25
SNI -2008.07.30 MEMBUAT 1 M3 KOLOM BETON BERTULANG (300 KG BESI + BEGESTING) Rp 9,707,083.25
SNI -2008.07.30 UNTUK 1 M3 KOLOM BETON DENGAN BESI 200 KG/M3 ADALAH : Rp 7,570,993.25
SNI -2008.07.30 UNTUK 1 M3 KOLOM BETON DENGAN BESI 150 KG/M3 ADALAH : Rp 6,502,948.25
SNI -2008.07.30 UNTUK 1 M3 KOLOM BETON DENGAN BESI 100 KG/M3 ADALAH : Rp 5,434,903.25
SNI -2008.07.31 MEMBUAT 1 M3 BALOK BETON BERTULANG (200 KG BESI + BEGESTING) Rp 7,236,928.00
SNI -2008.07.31 UNTUK BALOK BETON DENGAN BESI 150 KG/M3 ADALAH : Rp 6,168,883.00
SNI -2008.07.31 UNTUK BALOK BETON DENGAN BESI 100 KG/M3 ADALAH : Rp 5,100,838.00
SNI -2008.07.32 MEMBUAT 1 M3 PLAT BETON BERTULANG (150 KG BESI + BEGESTING) Rp 6,713,620.50
SNI -2008.07.32 UNTUK 1 M3 PLAT BETON BERTULANG (100 KG BESI + BEGESTING) Rp 5,645,575.50
SNI -2008.07.35 MEMBUAT 1 M' KOLOM PRAKTIS BETON BERTULANG (11 X 11 CM) Rp 104,626.05
SNI -2008.07.36 MEMBUAT 1 M' RING BALOK BETON BERTULANG (10 X 15 CM) Rp 142,847.75

PEKERJAAN PLESTERAN
SNI -2008.05.2 1 M2 PLESTERAN TEBAL 15 MM CAMP. 1 PC : 2 PSR Rp 91,931.92
SNI -2008.05.4 1 M2 PLESTERAN TEBAL 15 MM CAMP. 1 PC : 4 PSR Rp 74,117.07
SNI -2008.05.5 1 M2 PLESTERAN TEBAL 15 MM CAMP. 1 PC : 5 PSR Rp 72,355.66
SNI -2008.05.27 1 M2 MEMBUAT ACIAN Rp 43,506.94

PEKERJAAN PENUTUP LANTAI DAN DINDING


SNI -2008.13.35 1 M2 MEMASANG KERAMIK 30X30 CM Rp 225,460.72
SNI -2008.13.36 1 M2 MEMASANG KERAMIK 20X20 CM Rp 238,564.40
SNI -2008.13.38 1 M2 MEMASANG MOZAIK 30X30 CM CAMP. 1 PC : 3 PSR Rp 273,700.02
SNI -2008.13.39a 1 M' MEMASANG PLINT KERAMIK 10X30 CM Rp 33,140.90
SNI T-2008.13.54a 1 M2 MEMASANG DINDING KERAMIK 20X25 CM Rp 270,101.78
SNI -2008.13.35 1 M2 MEMASANG KERAMIK 40X40 CM Rp 187,024.68

PEKERJAAN KAYU
SNI -2008.06.1 1 M3 MEMBUAT DAN MEMASANG KOSEN PINTU/JENDELA KAYU ULIN Rp 12,844,287.50
SNI -2008.06.2 1 M3 MEMBUAT DAN MEMASANG KOSEN PINTU/JENDELA KAYU KLAS II Rp 7,687,075.00
SNI -2008.06.5 1 M2 MEMBUAT DAN MEMASANG DAUN PINTU PANEL KAYU KLAS I Rp 869,137.50
SNI -2008.06.5 1 M2 MEMBUAT DAN MEMASANG DAUN PINTU PANEL KAYU KLAS II Rp 671,137.50
SNI -2008.06.6 1 M2 MEMBUAT DAN MEMASANG DAUN PINTU PANEL KACA KAYU KLAS I Rp 780,945.00
SNI -2008.06.6 1 M2 MEMBUAT DAN MEMASANG DAUN PINTU PANEL KACA KAYU KLAS II Rp 662,145.00
SNI3 -2008.06.10 1 M2 MEMBUAT DAN MEMASANG JALUSI KAYU KLAS II Rp 596,730.00
SNI -2008.06.13 1 M3 MEMBUAT DAN MEMASANG KUDA-KUDA KONVENSIONAL KAYU KLAS II Rp 6,746,520.00
SNI -2008.06.15 1 M3 MEMBUAT DAN MEMASANG KONSTRUKSI GORDENG KAYU KLAS II Rp 5,842,100.00

Rekapitulasi Analisa 26
NO ANALISA URAIAN PEKERJAAN JUMLAH
SNI -2008.06.17 1 M2 RANGKA ATAP KASAU 5/7 DAN RENG 3/5 KAYU KLAS II Rp 110,714.95
SNI -2008.06.20 1 M2 MEMASANG RANGKA LANGIT-LANGIT KAYU KLAS II (60X120 CM) Rp 131,203.80
SNI -2008.06.21 1 M' LISPLANK 3/20 CM PAPAN KAYU KELAS I Rp 115,905.00
SNI -2008.06.21 1 M' LISPLANK 3/20 CM PAPAN KAYU KELAS II Rp 66,105.80

PEKERJAAN LANGIT-LANGIT
SNI -2008.09.5 1 M2 PENUTUP LANGIT-LANGIT PLYWOOD 3 MM Rp 55,667.70
SNI -2008.09.6 1 M2 PENUTUP LANGIT-LANGIT MOULDING Rp 255,832.50
SNI -2008.09.7 1 M2 PENUTUP LANGIT-LANGIT GYPSUM Rp 48,555.45
SNI -2008.09.10 1 M' LIS LANGIT-LANGIT KAYU PROFIL Rp 24,083.90
SNI -2008.09.10a 1 M' LIS LANGIT-LANGIT GYPSUM Rp 18,244.80

PEKERJAAN ATAP
SNI. -2007.08.32 1 M2 PENUTUP ATAP GENTENG METAL Rp 114,159.54
SNI -2007.08.36 1 M' BUBUNGAN ATAP GENTENG METAL Rp 87,047.50

PEKERJAAN BETON
SNI.-2007.07.5 1 M3 MEMBUAT BETON CAMP. 1PC : 2 PSR : 3 KRL Rp 968,189.25
SNI.-2007.07.2 1 M3 BETON TUMBUK CAMP. 1 PC : 3 PSR : 6 KRL Rp 916,272.00
H.17 1 M' TALANG SENG LEBAR 25 CM Rp 120,591.25

PEKERJAAN SANITASI
SNI.-2002.10.1 MEMASANG 1 BH CLOSET DUDUK Rp 2,061,265.50
SNI.-2002.10.2 MEMASANG 1 BH CLOSET JONGKOK Rp 715,195.50
SNI.-2002.10.7 MEMASANG 1 BUAH BAK MANDI FIBRE Rp 995,588.50
SNI.-2002.10.36 MEMASANG 1 BUAH FLOOR DRAIN (SARINGAN AIR) Rp 54,300.00
SNI.-2002.10.35 MEMASANG 1 BUAH KRAN AIR Rp 125,305.00

PEKERJAAN KUNCI DAN PENGGANTUNG


SNI.-2007.12.2 MEMASANG 1 BH KUNCI TANAM BIASA Rp 241,685.00
SNI.-2007.12.5 MEMASANG 1 BH ENGSEL PINTU Rp 52,550.31
SNI.-2007.12.6 MEMASANG 1 BH ENGSEL JENDELA Rp 33,016.88
SNI.-2007.12.9 MEMASANG 1 BH HAK ANGIN Rp 35,460.63
SNI.-2007.12.11 MEMASANG 1 BH KUNCI SELOT (GRENDEL) Rp 38,753.75
SNI.-2007.12.12 MEMASANG 1 BH PEGANGAN JENDELA ATAU PINTU Rp 83,025.31
SNI.-2007.12.17 MEMASANG 1 M2 KACA TEBAL 5MM KACA BENING Rp 228,007.63
SNI.-2007.12.17 MEMASANG 1 M2 KACA TEBAL 5MM KACA RYBEN Rp 234,057.63

PEKERJAAN BESI DAN ALUMUNIUM


SNI.-2007.12.17 MEMASANG 1 M2 TERALIS BESI Rp 684,003.82
SNI.-2008.12.10 MEMASANG 1 M' KUSEN ALMUNIUM Rp 220,038.75

PEKERJAAN PENGECATAN
SNI.-2002.14.9 1 M2 MENGECAT KILAP KAYU (1 LPS PLAMIR, 1 LPS CAT DASAR DAN 2 LPS CAT KILAP) Rp 57,039.33
SNI.-2002.14.14 1 M2 MENGECAT TEMBOK (1 LPS PLAMIR, 1 LPS CAT DASAR DAN 2 LPS CAT TEMBOK) Rp 20,757.28
SNI.-2002.14.12 1 M2 MENGETER BIDANG KAYU DENGAN RESIDU Rp 19,380.50
SNI.-2002.6.13 1 M2 MEMASANG KAWAT HARMONIKA Rp 357,719.63
SNI. -2007.08.32 1 M2 PENUTUP ATAP SENG GELOMBANG Rp 55,173.25
SNI -2007.08.36 1 M' BUBUNGAN ATAP SENG Rp 34,813.25
F. 19 1 M2 MEMASANG RANGKA ATAP SENG Rp 73,082.13
SNI -2008.06.8 1 M2 MEMBUAT DAN MEMASANG DAUN PINTU PLYWOOD RANGKAP KAYU KELAS II Rp 552,307.25
SNI -2008.06.25c 1 M2 MEMASANG DINDING PLYWOOD Rp 162,940.25
SUV. VI 1 M2 MEMASANG PAVING STONE Rp 213,728.75
SNI -2008.13.60 1 M2 MEMASANG WALLPAPER LEBAR 50 CM Rp 353,306.25

ANALISA BOW
BOW.F.1 1 M3 MENGERJAKAN RANGKA BAWAH KAYU KELAS I Rp 10,899,162.50
BOW.F.1 1 M3 MENGERJAKAN RANGKA BAWAH KAYU KELAS II Rp 5,847,412.50
BOW.F.8 1 M2 MENGERJAKAN DINDING PAPAN 2/20 KAYU KELAS I Rp 260,985.00
BOW.F.8 1 M2 MENGERJAKAN DINDING PAPAN 2/20 KAYU KELAS II Rp 149,665.00
BOW.F.22 1 M3 MENGERJAKAN RANGKA BADAN KAYU KELAS I Rp 13,433,750.00
BOW.F.22 1 M3 MENGERJAKAN RANGKA BADAN KAYU KELAS II Rp 8,406,200.00
BOW.F.38 1 M2 MENGERJAKAN LANTAI PAPAN TEBAL 3 CM DI SERUT RAPI KAYU KELAS I Rp 611,572.50
BOW.F.38 1 M2 MENGERJAKAN LANTAI PAPAN TEBAL 3 CM DI SERUT RAPI KAYU KELAS II Rp 435,902.50

Rekapitulasi Analisa 27
NO ANALISA URAIAN PEKERJAAN JUMLAH
SNI .07.6.5 1 M3 MEMBUAT BETON BERTULANG CAMP. 1PC : 2 PSR : 3 KRL Rp 968,189.25
SNI .07.6.2 1 M3 BETON TUMBUK CAMP. 1 PC : 3 PSR : 6 KRL Rp 916,272.00

Rekapitulasi Analisa 28
NO ANALISA URAIAN PEKERJAAN JUMLAH
SNI .07.6.25 1 Kg PEMBESIAN DENGAN BESI POLOS ATAU BESI ULIR Rp 22,247.40
SNI .07.6.28 1M2 PASANG BEGISTING PONDASI Rp 187,069.75
SNI .07.6.29 1M2 PASANG BEGISTING SLOOF Rp 140,319.75
SNI .07.6.30 1M2 PASANG BEGISTING KOLOM Rp 292,603.25
SNI .07.6.31 1M2 PASANG BEGISTING BALOK Rp 306,620.75
SNI .07.6.32 1M2 PASANG BEGISTING LANTAI Rp 346,853.25
SNI .07.6.36 1M3 MEMBUAT BETON DENGAN MUTU K 225 Rp 1,899,181.50
SNI .07.6.38a MEMBUAT 1 M3 PONDASI BETON BERTULANG (150 KG BESI + BEGESTING) Rp 5,063,626.75
SNI .07.6.39a MEMBUAT 1 M3 SLOOF BETON BERTULANG (150 KG BESI + BEGESTING) Rp 4,596,126.75
SNI .07.6.40a MEMBUAT 1 M3 KOLOM BETON BERTULANG (150 KG BESI + BEGESTING) Rp 6,118,961.75
SNI .07.6.41a MEMBUAT 1 M3 BALOK BETON BERTULANG (150 KG BESI + BEGESTING) Rp 6,259,136.75
SNI .07.6.42a MEMBUAT 1 M3 LANTAI BETON BERTULANG (150 KG BESI + BEGESTING) Rp 6,661,461.75

Rekapitulasi Analisa 29
REKAPITULASI
RENCANA ANGGARAN BIAYA
(R A B)

SATUAN KERJA : DINAS KEHUTANAN KABUPATEN GUNUNG MAS


PROGRAM : PENGEMBANGAN SARANA DAN PRASARANA KPH
KEGIATAN : PEMBANGUNAN KANTOR RESORT KPH
PEKERJAAN : PEMBANGUNAN KANTOR RESORT KPH
LOKASI : KECAMATAN TEWAH - KABUPATEN GUNUNG MAS
T. A : 2015

JUMLAH
No. URAIAN PEKERJAAN
(Rp)

I PEKERJAAAN PENDAHULUAN Rp 3,000,000.00


II PEKERJAAAN TANAH Rp 6,278,440.92
III PEKERJAAAN PONDASI Rp 17,059,883.36
IV PEKERJAAAN STRUKTUR, BATA DAN PLESTERAN Rp 89,676,211.48
V PEKERJAAAN ATAP Rp 43,640,406.13
VI PEKERJAAAN LANTAI DAN LAPISAN Rp 16,033,602.02
VII PEKERJAAAN DAUN PINTU DAN JENDELA Rp 16,290,895.24
VIII PEKERJAAAN KUNCI DAN PENGGANTUNG Rp 5,242,090.31
IX PEKERJAAAN PLAFOND DAN RANGKA Rp 13,431,146.74
X PEKERJAAAN CAT / FINISHING Rp 9,782,364.02
XI PEKERJAAAN INSTALASI LISTRIK Rp 10,160,287.00
XII PEKERJAAAN INSTALASI SANITASI Rp 11,408,531.70
JUMLAH BIAYA I - XII Rp 242,003,858.90

PPN 10% Rp 24,200,385.89

TOTAL BIAYA Rp 266,204,244.79

DIBULATKAN Rp 266,200,000.00

TERBILANG : /// DUA RATUS DUA PULUH ENAM JUTA DUA RATUS RIBU RUPIAH ///

Kuala Kurun, Juni 2015

Konsultan Perencana
CV. UNIKA CITRA MANDIRI
Pusat Palangka Raya

KRISWANDI, ST
DIREKTUR

Rekapitulasi Biaya Pembangunan Gedung Aula/Kantor 30


RENCANA ANGGARAN BIAYA
(R A B)

SATUAN KERJA : DINAS KEHUTANAN KABUPATEN GUNUNG MAS


PROGRAM : PENGEMBANGAN SARANA DAN PRASARANA KPH
KEGIATAN : PEMBANGUNAN KANTOR RESORT KPH
PEKERJAAN : PEMBANGUNAN KANTOR RESORT KPH
LOKASI : KECAMATAN TEWAH - KABUPATEN GUNUNG MAS
T. A : 2015

Harga
Jumlah Total
No. Uraian Pekerjaan Analisa Volume Satuan
(Rp) (Rp) (Rp)

I PEKERJAAAN PENDAHULUAN
1 Pek. Pembersihan Lapangan dan Perataan Ls 1.00 Kgtn 500,000.00 500,000.00
2 Pengukuran dan Pemasangan Bouwplank Ls 1.00 Kgtn 700,000.00 700,000.00
3 Pembuatan Papan Nama Proyek Ls 1.00 Kgtn 300,000.00 300,000.00
4 Pembuatan Bangsal Kerja Ls 1.00 Kgtn 1,500,000.00 1,500,000.00
Jumlah - I - 3,000,000.00

II PEKERJAAAN TANAH
1 Pek. Galian tanah pondasi setempat SNI -2008.02.1 13.42 M3 83,812.50 1,124,363.13
2 Pek. Urugan tanah bekas galian SNI -2008.02.9 10.52 M3 27,937.50 293,849.98
3 Pek. Urugan tanah peninggian peil lantai SNI -2008.02.11 29.36 M3 165,525.00 4,860,227.81
Jumlah - II - 6,278,440.92

III PEKERJAAAN PONDASI


1 Pek. Lapisan Pasir di Bawah Lantai Kerja SNI -2008.02.11a 0.59 M3 178,725.00 105,535.33
3 Pek. Lantai Kerja camp. 1 PC : 3 Psr : 6 Krl SNI.-2007.07.2 0.88 M3 916,272.00 808,151.90
4 Pek. Pondasi Setempat Beton Bertulang camp. 1PC : 2 Psr : SNI .07.6.5 1.02 M3 968,189.25 987,175.44
3 Krl
Pembesian Tul. Utama dengan besi polos dia. 10 mm SNI .07.6.25 96.42 Kg 22,247.40 2,145,147.70
Bekisting Pondasi SNI .07.6.28 8.64 M2 187,069.75 1,616,282.64
5 Pek. Kolom Pondasi Sampai Peil Lantai Beton Betulang SNI -2008.07.35 18.00 M' 104,626.05 1,883,268.90
camp. 1PC : 2 Psr : 3 Krl
6 Pek. Sloof 15 x 20 Beton Betulang camp. 1PC : 2 Psr : 3 Krl SNI .07.6.5 1.77 M3 968,189.25 1,713,694.97

Pembesian Tul. Utama dengan besi polos dia. 10 mm SNI .07.6.25 146.32 Kg 22,247.40 3,255,239.57
Pembesian Tul. Cincin dengan besi polos dia. 8 mm SNI .07.6.25 55.46 Kg 22,247.40 1,233,840.80
Bekisting Sloof SNI .07.6.29 23.60 M2 140,319.75 3,311,546.10
Jumlah - III - 17,059,883.36

IV PEKERJAAAN STRUKTUR, BATA DAN PLESTERAN


1 Pek. Kolom Praktis Beton Bertulang Camp. 1 PC : 2 Psr : 3 SNI -2008.07.35 72.00 M' 104,626.05 7,533,075.60
Krl
2 Pek. Pasangan Dinding Bata setengah batu Camp. 1 PC : 4 SNI -2008.04.9 202.26 M2 160,196.38 32,401,639.20
Psr
3 Pek. Plesteran Dinding Camp. 1 PC : 4 Psr SNI -2008.05.4 404.52 M2 74,117.07 29,982,133.62
4 Pek. Ring Balk 15 x 15 cm Beton Bertulang Camp, 1 PC :2 SNI -2008.07.36 68.00 M' 142,847.75 9,713,647.00
Psr : 3 Krl
5 Pek. Cor Tritisan Dag Beton Bertulang Camp, 1 PC :2 Psr : 3 SNI .07.6.5 2.35 M3 968,189.25 2,277,181.12
Krl
Pembesian Tulangan dengan besi polos dia. 8 mm SNI .07.6.25 32.00 Kg 22,247.40 711,805.56
Bekisting SNI .07.6.32 20.35 M2 346,853.25 7,056,729.37
Jumlah - IV - 89,676,211.48

V PEKERJAAAN ATAP
1 Pek. Rangka Kuda-kuda uk. 5/10 kayu kelas II SNI -2008.06.13 0.45 M3 6,746,520.00 3,002,876.05
2 Pek. Suai, Nok, Gording Atap Kayu Kelas II SNI -2008.06.15 0.68 M3 5,842,100.00 3,956,270.12
3 Pek. Kasau dan Reng Atap Kayu Kelas II SNI -2008.06.17 118.68 M2 110,714.95 13,139,650.27
4 Pek. Listplank Papan Kayu Kelas I SNI -2008.06.21 47.00 M' 115,905.00 5,447,535.00
5 Pek. Atap Genteng Metal SNI. -2007.08.32 118.68 M2 114,159.54 13,548,454.25
6 Pek. Bubungan Atap Genteng Metal SNI -2007.08.36 52.22 M' 87,047.50 4,545,620.45
Jumlah - V - 43,640,406.13

VI PEKERJAAAN LANTAI DAN LAPISAN


1 Pek. Lapisan Pasir Urug SNI -2008.02.11a 6.68 M3 178,725.00 1,192,989.38

Rincian Biaya Pembangunan Gedung Aula/Kantor 31


Harga
Jumlah Total
No. Uraian Pekerjaan Analisa Volume Satuan
(Rp) (Rp) (Rp)
2 Pek. Cor Beton Tumbuk Camp. 1 PC : 3 Psr : 6 Krl SNI.-2007.07.2 3.34 M3 916,272.00 3,058,057.80
3 Pek. Pasangan Keramik 40 x 40 Polos SNI -2008.13.35 63.00 M2 187,024.68 11,782,554.84
Jumlah - VI - 16,033,602.02

VII PEKERJAAAN DAUN PINTU DAN JENDELA


1 Pek. Kusen Kayu Kelas II SNI -2008.06.2 0.42 M3 7,687,075.00 3,197,438.85
2 Pek. Daun Pintu Panel Kayu Kelas II (Benuas) SNI -2008.06.5 10.30 M2 671,137.50 6,914,863.89
3 Pek. Daun Jendela Panel Kayu Kelas II (Benuas) Ls 11.00 Buah 350,000.00 3,850,000.00
4 Pek. Pasangan Kaca Ryben Jendela Tebal 5 mm SNI.-2007.12.17 9.95 M2 234,057.63 2,328,592.50
Jumlah - VII - 16,290,895.24

VIII PEKERJAAAN KUNCI DAN PENGGANTUNG


1 Pasangan Kunci Pintu Tanam SNI.-2007.12.2 6.00 Bh 241,685.00 1,450,110.00
2 Pasangan Engsel Pintu SNI.-2007.12.5 18.00 Bh 52,550.31 945,905.63
3 Pasangan Engsel Jendela SNI.-2007.12.6 22.00 Bh 33,016.88 726,371.25
4 Pasangan Pegangan Jendela SNI.-2007.12.12 11.00 Bh 83,025.31 913,278.44
5 Pasangan Kait Angin Jendela SNI.-2007.12.9 22.00 Bh 35,460.63 780,133.75
6 Pasangan Grendel Jendela SNI.-2007.12.11 11.00 Bh 38,753.75 426,291.25
Jumlah - VIII - 5,242,090.31

IX PEKERJAAAN PLAFOND DAN RANGKA


1 Pek. Rangka Plafond Kayu Kelas II SNI -2008.06.20 66.75 M2 131,203.80 8,757,853.65
2 Pek. Plafond Bahan Gypsum SNI -2008.09.7 66.75 M2 48,555.45 3,241,076.29
3 Pek. List Plafond SNI -2008.09.10a 78.50 M' 18,244.80 1,432,216.80
Jumlah - IX - 13,431,146.74

X PEKERJAAAN CAT / FINISHING


1 Pek. Pengecatan Dinding SNI.-2002.14.14 404.52 M2 20,757.28 8,396,815.91
2 Pek. Pengecatan Plafond SNI.-2002.14.14 66.75 M2 20,757.28 1,385,548.11
Jumlah - X - 9,782,364.02

XI PEKERJAAAN INSTALASI LISTRIK


1 Pek. Instalasi titik lampu Ls 7.00 Titik 332,750.00 2,329,250.00
2 Pasangan Lampu TL Bulat 20 Watt Ls 7.00 Titik 126,445.00 885,115.00
3 Pek. Stop Kontak + Instalasi Ls 5.00 Titik 332,750.00 1,663,750.00
4 Pek. Saklar Ganda lengkap Instalasi Ls 1.00 Titik 30,613.00 30,613.00
5 Pek. Saklar Tunggal lengkap Instalasi Ls 5.00 Titik 30,613.00 153,065.00
6 Pek. MCB 1 x 32 A - NC 45 A Ls 1.00 Buah 98,494.00 98,494.00
7 Penyambungan Listrik dari PLN Ls 1.00 Unit 5,000,000.00 5,000,000.00
Jumlah - XI - 10,160,287.00

XII PEKERJAAAN INSTALASI SANITASI


1 Pek. Instalasi Air Bersih Ls 1.00 Unit 320,000.00 320,000.00
2 Pek. Kran Air SNI.-2002.10.35 1.00 Bh 125,305.00 125,305.00
3 Pek. Bak Mandi SNI.-2002.10.7 1.00 Bh 995,588.50 995,588.50
4 Pek. Floor Drain (Saringan Air) SNI.-2002.10.36 1.00 Bh 54,300.00 54,300.00
5 Pek. Klosed Jongkok SNI.-2002.10.2 1.00 Bh 715,195.50 715,195.50
6 Pek. Pemb. Septic Tank 6 M3 + Resapan Ls 1.00 Unit 5,000,000.00 5,000,000.00
7 Pek. Pas Keramik Dinding KM/WC 20x20 SNI -2008.13.36 10.50 M2 238,564.40 2,504,926.20
8 Pek. Pas Keramik Lantai KM/WC 20x20 SNI -2008.13.36 3.75 M2 238,564.40 894,616.50
10 Pek. Washtafel Ls 1.00 Bh 798,600.00 798,600.00
Jumlah - XII - 11,408,531.70

Rincian Biaya Pembangunan Gedung Aula/Kantor 32


PERHITUNGAN VOLUME
PEMBANGUNAN GEDUNG AULA / KANTOR

SATUAN KERJA : DINAS KEHUTANAN KABUPATEN GUNUNG MAS


PROGRAM : PENGEMBANGAN SARANA DAN PRASARANA KPH
KEGIATAN : PEMBANGUNAN KANTOR RESORT KPH
PEKERJAAN : PEMBANGUNAN KANTOR RESORT KPH
LOKASI : KECAMATAN TEWAH - KABUPATEN GUNUNG MAS
T. A : 2015

No Uraian Pekerjaan Uraian Perkalian Jumlah

I PEKERJAAAN PENDAHULUAN
1 Pek. Pembersihan Lapangan dan Perataan = 1 Jumlah = 1.00 Kgtn

2 Pengukuran dan Pemasangan Bouwplank = 1 Jumlah = 1.00 Kgtn

3 Pembuatan Papan Nama Proyek = 1 Jumlah = 1.00 Kgtn

4 Pembuatan Bangsal Kerja = 1 Jumlah = 1.00 Kgtn

II PEKERJAAAN TANAH
1 Pek. Galian tanah pondasi setempat = 0.91 x 0.91 x 0.9 x 18 Jumlah = 13.42 M3

2 Pek. Urugan tanah bekas galian = 13.42 - 2.90 Jumlah = 10.52 M3

3 Pek. Urugan tanah peninggian peil lantai


R. Tamu = 5.25 x 4 x 0.45 x 1 = 9.45 M3
Dapur = 2.5 x 1.5 x 0.45 x 1 = 1.69 M3
Kamar Tidur = 3.5 x 3 x 0.45 x 1 = 4.73 M3
= 3 x 3 x 0.45 x 2 = 8.10 M3
Teras = 3.25 x 3 x 0.4 x 1 = 3.90 M3
KM/WC = 2.5 x 1.5 x 0.4 x 1 = 1.50 M3
Jumlah = 29.36 M3

III PEKERJAAAN PONDASI


1 Pek. Lapisan Pasir di Bawah Lantai Kerja = 0.81 x 0.81 x 0.05 x 18 Jumlah = 0.59 M3

3 Pek. Lantai Kerja camp. 1 PC : 3 Psr : 6 Krl = 0.7 x 0.7 x 0.1 x 18 Jumlah = 0.88 M3

4 Pek. Pondasi Setempat Beton Bertulang camp. 1PC : 2 Psr : 3 Krl


= 0.6 x 0.6 x 0.15 x 18 0.972 M3
= 0.23 x 0.23 x 0.05 x 18 0.05 M3
Jumlah = 1.02 M3
Pembesian Tul. Utama dengan besi polos dia. 10 mm
= 1.44 x 0.62 x 6 x 18 Jumlah = 96.42 Kg
Bekisting Pondasi
= 0.6 x 4 x 0.2 x 18 Jumlah = 8.64 M2

5 Pek. Kolom Pondasi Sampai Peil Lantai Beton Betulang camp. 1PC : 2 Psr : 3 Krl
= 1 x 18 Jumlah = 18.00 M'

6 Pek. Sloof 15 x 20 Beton Betulang camp. 1PC : 2 Psr : 3 Krl


= 0.15 x 0.2 x 1 x 59 Jumlah = 1.77 M3
Pembesian Tul. Utama dengan besi polos dia. 10 mm
= 59 x 4 x 0.62 Jumlah = 146.32 Kg
Pembesian Tul. Cincin dengan besi polos dia. 8 mm
= 0.47 x 295 x 0.4 Jumlah = 55.46 Kg
Bekisting Sloof
= 0.4 x 59 x 1 Jumlah = 23.60 M2

IV PEKERJAAAN STRUKTUR, BATA DAN PLESTERAN


1 Pek. Kolom Praktis Beton Bertulang Camp. 1 PC : 2 Psr : 3 Krl
= 4 x 18 Jumlah = 72.00 M'

Perhitungan Volume Pembangunan Gedung Aula/Kantor 33


PERHITUNGAN VOLUME
PEMBANGUNAN GEDUNG AULA / KANTOR

SATUAN KERJA : DINAS KEHUTANAN KABUPATEN GUNUNG MAS


PROGRAM : PENGEMBANGAN SARANA DAN PRASARANA KPH
KEGIATAN : PEMBANGUNAN KANTOR RESORT KPH
PEKERJAAN : PEMBANGUNAN KANTOR RESORT KPH
LOKASI : KECAMATAN TEWAH - KABUPATEN GUNUNG MAS
T. A : 2015

No Uraian Pekerjaan Uraian Perkalian Jumlah


2 Pek. Pasangan Dinding Bata setengah batu Camp. 1 PC : 4 Psr
Melintang = 27.8 x 4 = 111.20 M2
Memanjang = 24 x 4 = 96.00 M2
= 1.55 x 9 = 13.95 M2
Dinding Kolom Teras = 1 x 3 x 2 = 6.00 M2
Jumlah = 227.15 M2

Jadi Pas. Bata Keseluruhan = 227.15 - Lubang Kusen


= 227.15 - 24.89 Jumlah = 202.26 M2

Lubang Kusen
Kusen Pintu P1 = 1 buah = 1.7 x 2.17 x 1 = 3.69 M2
Kusen Pintu P2 = 4 buah = 0.9 x 2.17 x 4 = 7.81 M2
Kusen Pintu P3 = 1 buah = 0.85 x 2.17 x 1 = 1.84 M2
Kusen Jendela J1 = 9 buah = 0.5 x 1.7 x 9 = 7.65 M2
Kusen Jendela J2 = 1 buah = 1.4 x 1.7 x 1 = 2.38 M2
Kusen Jalusi = 31 buah = 0.15 x 0.25 x 31 = 1.16 M2
Kusen Ventilasi V1 = 1 buah = 0.7 x 0.5 x 1 = 0.35 M2
Jumlah = 24.89 M2

3 Pek. Plesteran Dinding Camp. 1 PC : 4 Psr = 202.26 x 2 Jumlah = 404.52 M2

4 Pek. Ring Balk 15 x 15 cm Beton Bertulang Camp, 1 PC :2 Psr : 3 Krl


= 68 Jumlah = 68.00 M'

5 Pek. Cor Tritisan Dag Beton Bertulang Camp, 1 PC :2 Psr : 3 Krl


Atas Teras = 5.65 x 0.75 x 0.2 x 1 = 0.85 M3
= 2.5 x 0.75 x 0.2 x 2 = 0.75 M3
Bawah Teras = 2.75 x 0.3 x 0.1 x 1 = 0.08 M3
= 2.2 x 0.3 x 0.1 x 2 = 0.13 M3
Jendela J1 = 2.6 x 0.5 x 0.15 x 2 = 0.39 M3
Jendela J2 = 2 x 0.5 x 0.15 x 1 = 0.15 M3
Jumlah = 2.35 M3
Pembesian Tulangan dengan besi polos dia. 8 mm
= 0.9 x 45 x 0.4 = 16.20 Kg
= 0.45 x 35.75 x 0.4 = 6.44 Kg
= 0.65 x 26.00 x 0.4 = 6.76 Kg
= 0.65 x 10.00 x 0.4 = 2.60 Kg
Jumlah = 32.00 Kg

Bekisting = 1 x 10.65 = 10.65 M2


= 0.5 x 7.15 = 3.58 M2
= 0.85 x 5.2 = 4.42 M2
= 0.85 x 2 = 1.70 M2
Jumlah = 20.35 M2

V PEKERJAAAN ATAP
1 Pek. Rangka Kuda-kuda uk. 5/10 kayu kelas II
Kuda-kuda K1
Balok Tarik 5/10 = 0.05 x 0.1 x 6.3 x 1 = 0.03 M3
Kaki Kuda-kuda 5/10 = 0.05 x 0.1 x 3.4 x 2 = 0.03 M3
Balok Gantung Tengah 5/10 = 0.05 x 0.1 x 1.7 x 1 = 0.01 M3
Balok Gapit 5/10 = 0.05 x 0.1 x 2.8 x 2 = 0.03 M3
Balok Sokong 5/10 = 0.05 x 0.1 x 1.4 x 2 = 0.01 M3
Balok Sambung 5/10 = 0.05 x 0.1 x 1 x 1 = 0.01 M3

Perhitungan Volume Pembangunan Gedung Aula/Kantor 34


PERHITUNGAN VOLUME
PEMBANGUNAN GEDUNG AULA / KANTOR

SATUAN KERJA : DINAS KEHUTANAN KABUPATEN GUNUNG MAS


PROGRAM : PENGEMBANGAN SARANA DAN PRASARANA KPH
KEGIATAN : PEMBANGUNAN KANTOR RESORT KPH
PEKERJAAN : PEMBANGUNAN KANTOR RESORT KPH
LOKASI : KECAMATAN TEWAH - KABUPATEN GUNUNG MAS
T. A : 2015

No Uraian Pekerjaan Uraian Perkalian Jumlah


= 0.12 M3
3 Buah Kuda-kuda = 3 x 0.12 Jumlah = 0.36 M3
Kuda-kuda K2
Balok Tarik 5/10 = 0.05 x 0.1 x 4.3 x 1 = 0.02 M3
Kaki Kuda-kuda 5/10 = 0.05 x 0.1 x 2.2 x 2 = 0.02 M3
Balok Gantung Tengah 5/10 = 0.05 x 0.1 x 1.2 x 1 = 0.01 M3
Balok Gapit 5/10 = 0.05 x 0.1 x 1.91 x 2 = 0.02 M3
Balok Sokong 5/10 = 0.05 x 0.1 x 0.85 x 2 = 0.01 M3
Balok Sambung 5/10 = 0.05 x 0.1 x 1 x 1 = 0.01 M3
= 0.08 M3
1 Buah Kuda-kuda = 1 x 0.08 Jumlah = 0.08 M3

Kuda-Kuda K1 + K2 Jumlah = 0.45 M3

Perhitungan Volume Pembangunan Gedung Aula/Kantor 35


PERHITUNGAN VOLUME
PEMBANGUNAN GEDUNG AULA / KANTOR

SATUAN KERJA : DINAS KEHUTANAN KABUPATEN GUNUNG MAS


PROGRAM : PENGEMBANGAN SARANA DAN PRASARANA KPH
KEGIATAN : PEMBANGUNAN KANTOR RESORT KPH
PEKERJAAN : PEMBANGUNAN KANTOR RESORT KPH
LOKASI : KECAMATAN TEWAH - KABUPATEN GUNUNG MAS
T. A : 2015

No Uraian Pekerjaan Uraian Perkalian Jumlah

2 Pek. Suai, Nok, Gording Atap Kayu Kelas II =


Balok Suai 5/10 = 0.05 x 0.07 x 2.5 x 4 = 0.04 M3
Balok Nook 5/10 = 0.05 x 0.1 x 7.7 x 1 = 0.04 M3
Balok Gording 5/10 = 0.05 x 0.1 x 8.79 x 2 = 0.09 M3
= 0.05 x 0.1 x 6.72 x 2 = 0.07 M3
= 0.05 x 0.1 x 5 x 1 = 0.03 M3
Balok Jurai 5/10 = 0.05 x 0.1 x 6.53 x 4 = 0.13 M3
= 0.05 x 0.1 x 4.9 x 4 = 0.10 M3
Balok Murplat 5/10 = 0.05 x 0.1 x 39 x 1 = 0.20 M3
Jumlah = 0.68 M3

3 Pek. Kasau dan Reng Atap Kayu Kelas II = Pek. Atap Genteng Metal Jumlah = 118.68 M2

4 Pek. Listplank Papan Kayu Kelas I = 13 + 16 + 7 + 6 + 5 Jumlah = 47.00 M'

5 Pek. Atap Genteng Metal


Sisi Depan = 8 x 4.62 x 2 = 73.92 M2
= 3 x 2.6 x 1 = 7.80 M2
Sisi Samping = 4 x 4.62 x 2 = 36.96 M2
= 3 x 3.4 x 2 = 20.40 M2
Jumlah = 118.68 M2

6 Pek. Bubungan Atap Genteng Metal = 19.60 + 26.12 + 4 + 2.5 Jumlah = 52.22 M'

VI PEKERJAAAN LANTAI DAN LAPISAN


1 Pek. Lapisan Pasir Urug
R. Tamu = 5.25 x 4 x 0.1 x 1 = 2.10 M3
Dapur = 2.5 x 1.5 x 0.1 x 1 = 0.38 M3
Kamar Tidur = 3.5 x 3 x 0.1 x 1 = 1.05 M3
= 3 x 3 x 0.1 x 2 = 1.80 M3
Teras = 3.25 x 3 x 0.1 x 1 = 0.98 M3
KM/WC = 2.5 x 1.5 x 0.1 x 1 = 0.38 M3
Jumlah = 6.68 M3
2 Pek. Cor Beton Tumbuk Camp. 1 PC : 3 Psr : 6 Krl
R. Tamu = 5.25 x 4 x 0.05 x 1 = 1.05 M3
Dapur = 2.5 x 1.5 x 0.05 x 1 = 0.19 M3
Kamar Tidur = 3.5 x 3 x 0.05 x 1 = 0.53 M3
= 3 x 3 x 0.05 x 2 = 0.90 M3
Teras = 3.25 x 3 x 0.05 x 1 = 0.49 M3
KM/WC = 2.5 x 1.5 x 0.05 x 1 = 0.19 M3
Jumlah = 3.34 M3
3 Pek. Pasangan Keramik 40 x 40 Polos
R. Tamu = 5.25 x 4 x 1 = 21.00 M2
Dapur = 2.5 x 1.5 x 1 = 3.75 M2
Kamar Tidur = 3.5 x 3 x 1 = 10.50 M2
= 3 x 3 x 2 = 18.00 M2
Teras = 3.25 x 3 x 1 = 9.75 M2
Jumlah = 63.00 M2

Perhitungan Volume Pembangunan Gedung Aula/Kantor 36


PERHITUNGAN VOLUME
PEMBANGUNAN GEDUNG AULA / KANTOR

SATUAN KERJA : DINAS KEHUTANAN KABUPATEN GUNUNG MAS


PROGRAM : PENGEMBANGAN SARANA DAN PRASARANA KPH
KEGIATAN : PEMBANGUNAN KANTOR RESORT KPH
PEKERJAAN : PEMBANGUNAN KANTOR RESORT KPH
LOKASI : KECAMATAN TEWAH - KABUPATEN GUNUNG MAS
T. A : 2015

No Uraian Pekerjaan Uraian Perkalian Jumlah


VII PEKERJAAAN DAUN PINTU DAN JENDELA
1 Pek. Kusen Kayu Kelas II
Kusen Pintu P1 = 1 buah = 0.05 x 0.1 x 6.14 x 1 = 0.03 M3
Kusen Pintu P2 = 4 buah = 0.05 x 0.1 x 5.34 x 4 = 0.11 M3
Kusen Pintu P3 = 1 buah = 0.05 x 0.1 x 5.29 x 1 = 0.03 M3
Kusen Jendela J1 = 9 buah = 0.05 x 0.1 x 4.6 x 9 = 0.21 M3
Kusen Jendela J2 = 1 buah = 0.05 x 0.1 x 6.4 x 1 = 0.03 M3
Kusen Ventilasi V1 = 1 buah = 0.05 x 0.1 x 2.6 x 1 = 0.01 M3
= = 0.00 M3
Jumlah = 0.42 M3

2 Pek. Daun Pintu Panel Kayu Kelas II (Benuas)


Daun Pintu P1 = 2 Buah = 0.81 x 2.12 x 2 = 3.43 M2
Daun Pintu P2 = 4 Buah = 0.81 x 2.12 x 4 = 6.87 M2
Jumlah = 10.30 M2

3 Pek. Daun Jendela Panel Kayu Kelas II (Benuas) = 11 Jumlah = 11.00 Buah

4 Pek. Pasangan Kaca Ryben Jendela Tebal 5 mm


Daun Jendela J1 = 9 Buah = 0.2 x 1.4 x 11 = 3.08 M2
Daun Jendela J2 = 3 Buah = 0.81 x 2.12 x 4 = 6.87 M2
Jumlah = 9.95 M2

VIII PEKERJAAAN KUNCI DAN PENGGANTUNG


1 Pasangan Kunci Pintu Tanam = 1 x 6 Jumlah = 6.00 Bh

2 Pasangan Engsel Pintu = 3 x 6 Jumlah = 18.00 Bh

3 Pasangan Engsel Jendela = 2 x 11 Jumlah = 22.00 Bh

4 Pasangan Pegangan Jendela = 1 x 11 Jumlah = 11.00 Bh

5 Pasangan Kait Angin Jendela = 2 x 11 Jumlah = 22.00 Bh

6 Pasangan Grendel Jendela = 1 x 11 Jumlah = 11.00 Bh

IX PEKERJAAAN PLAFOND DAN RANGKA


1 Pek. Rangka Plafond Kayu Kelas II =
R. Tamu = 5.25 x 4 x 1 = 21.00 M2
= 2.5 x 1.5 x 1 = 3.75 M2
Kamar Tidur = 3.5 x 3 x 1 = 10.50 M2
= 3 x 3 x 2 = 18.00 M2
Teras = 3.25 x 3 x 1 = 9.75 M2
KM/WC = 2.5 x 1.5 x 1 = 3.75 M2
Jumlah = 66.75 M2

2 Pek. Plafond Bahan Gypsum = Pek. Rangka Plafond Kayu Kelas II


= 66.75 Jumlah = 66.75 M2

3 Pek. List Plafond


R. Tamu = 5 + 5 + 5.5 + 5.5 = 21.00 M'
Kamar Tidur = 3.5 + 3.5 + 3 + 3 = 13.00 M'
= 3 + 3 + 3 + 3 x 2 = 24.00 M'
Teras = 3.25 + 3.25 + 3 + 3 = 12.50 M'
KM/WC = 2.5 + 2.5 + 1.5 + 1.5 = 8.00 M'
Jumlah = 78.50 M'

Perhitungan Volume Pembangunan Gedung Aula/Kantor 37


PERHITUNGAN VOLUME
PEMBANGUNAN GEDUNG AULA / KANTOR

SATUAN KERJA : DINAS KEHUTANAN KABUPATEN GUNUNG MAS


PROGRAM : PENGEMBANGAN SARANA DAN PRASARANA KPH
KEGIATAN : PEMBANGUNAN KANTOR RESORT KPH
PEKERJAAN : PEMBANGUNAN KANTOR RESORT KPH
LOKASI : KECAMATAN TEWAH - KABUPATEN GUNUNG MAS
T. A : 2015

No Uraian Pekerjaan Uraian Perkalian Jumlah


X PEKERJAAAN CAT / FINISHING
1 Pek. Pengecatan Dinding = 404.52 Jumlah = 404.52 M2

2 Pek. Pengecatan Plafond = 66.75 Jumlah = 66.75 M2

XI PEKERJAAAN INSTALASI LISTRIK


1 Pek. Instalasi titik lampu = 7.00 Jumlah = 7.00 Titik

2 Pasangan Lampu TL Bulat 20 Watt = 7.00 Jumlah = 7.00 Titik

3 Pek. Stop Kontak + Instalasi = 5.00 Jumlah = 5.00 Titik

4 Pek. Saklar Ganda lengkap Instalasi = 1.00 Jumlah = 1.00 Titik

5 Pek. Saklar Tunggal lengkap Instalasi = 5.00 Jumlah = 5.00 Titik

6 Pek. MCB 1 x 32 A - NC 45 A = 1.00 Jumlah = 1.00 Buah

7 Penyambungan Listrik dari PLN = 1.00 Jumlah = 1.00 Unit

XII PEKERJAAAN INSTALASI SANITASI


1 Pek. Instalasi Air Bersih = 1.00 Jumlah = 1.00 Unit

2 Pek. Kran Air = 1.00 Jumlah = 1.00 Bh

3 Pek. Bak Mandi = 1.00 Jumlah = 1.00 Bh

4 Pek. Floor Drain (Saringan Air) = 1.00 Jumlah = 1.00 Bh

5 Pek. Klosed Jongkok = 1.00 Jumlah = 1.00 Bh

6 Pek. Pemb. Septic Tank 6 M3 + Resapan = 1.00 Jumlah = 1.00 Unit

7 Pek. Pas Keramik Dinding KM/WC 20x20 = 1.5 x 7 x 1 x 1 Jumlah = 10.50 M2

8 Pek. Pas Keramik Lantai KM/WC 20x20 = 1.5 x 2.5 x 1 x 1 Jumlah = 3.75 M2

10 Pek. Washtafel = 1.00 Jumlah = 1.00 Bh