B Pelaporan 1,335,000.00
C Ekspose 1,970,000.00
Total 49,945,500.00
Dibulatkan 49,900,000.00
Terbilang :
HARGA
NO URAIAN VOL SAT JUMLAH HARGA (Rp)
SATUAN (Rp)
A Tenaga Ahli
- Ahli Muda Teknik Sungai dan Drainase [Team Leader] (1 org x 1 bln) 1 OB 19,600,000 19,600,000
Sub Jumlah A 19,600,000
B Tenaga Pendukung
- Surveyor (2 org x 1 bln) 2 OB 7,100,000 14,200,000
- Operator CAD/Juru Gambar (1 org x 1 bln) 1 OB 3,300,000 3,300,000
- Operator Komputer/Adm (1 org x 1 bln) 1 OB 3,300,000 3,300,000
Sub Jumlah B 20,800,000
JUMLAH TOTAL BIAYA LANGSUNG PERSONIL (A+B) 40,400,000
Lampiran 2
Total 50,385,500.00
Terbilang :
Empat puluh sembilan juta sembilan ratus enam puluh tujuh ribu lima ratus rupiah
HARGA
NO URAIAN VOL SAT JUMLAH HARGA (Rp)
SATUAN (Rp)
A LAPORAN PENDAHULUAN
- Ahli Pratama Teknik Sumber Daya Air [Team Leader] (1 org x 1 bulan) 1 OB 14,300,000 14,300,000
Biaya Alat Tulis Kantor (ATK), Alat Pendukung (APK) & Operasional 1 ls 200,000 200,000
Laporan Pendahuluan 3 eks 60,000 180,000
Makan minum/snack Presentasi Laporan Pendahuluan 8 Org 60,000 480,000
Bahan Paparan Laporan Pendahuluan 8 eks 10,000 80,000
Sub Jumlah A 15,240,000
B LAPORAN AKHIR DAN LAPORAN PENUNJANG
- Ahli Pratama Teknik Sumber Daya Air [Team Leader] (1 org x 1 bulan) 1 OB 14,300,000 14,300,000
- Surveyor (1 org x 1 bulan) 1 OB 7,100,000 7,100,000
- Operator CAD/Juru Gambar (1 org x 1 bulan) 1 OB 3,300,000 3,300,000
- Operator Komputer/Adm (1 org x 1 bulan) 1 OB 3,300,000 3,300,000
Biaya Alat Tulis Kantor (ATK), Alat Pendukung (APK) & Operasional 1 ls 300,000 300,000
Sewa alat ukur Waterpass (1 unit x 1 bulan) 1 ls 1,000,000 1,000,000
Laporan Akhir 3 eks 70,000 210,000
Laporan A3 ( Album Peta, Gambar dan Dokumentasi) 3 eks 85,000 255,000
Flashdisk 3 bh 80,000 240,000
Makan minum/snack Presentasi Laporan Akhir 8 Org 60,000 480,000
Bahan Paparan Laporan Akhir 8 eks 10,000 80,000
Sub Jumlah B 30,565,000
JUMLAH TOTAL (A+B) 45,805,000
REKAPITULASI PERINCIAN BIAYA
Pekerjaan : Penyusunan Angka Kebuthan Nyata Operasi Pemeliharaan (AKNOP) DAS Angke TA 2022
Total 65,754,332.60
Terbilang :
Harga SIPD
HARGA JUMLAH
NO URAIAN VOL SAT
SATUAN (Rp) HARGA (Rp)
A LAPORAN PENDAHULUAN
- Ahli Pratama Teknik Sumber Daya Air [Team Leader] (1 org x 2 minggu) 1 OK 20,666,000 10,333,000
- Surveyor (2 org x 2 minggu) 2 OK 10,333,333 10,333,333
- CAD/CAM Operator (2 org x 2 minggu) 2 OK 4,903,000 4,903,000
- Computer Operator/Typist (1 org x 2 minggu) 1 OK 4,903,000 2,451,500
- Laporan Pendahuluan 2 eks 108,000 216,000
- Makan minum/snack Presentasi Laporan Pendahuluan 15 Org 54,000 810,000
- Bahan Paparan Laporan Pendahuluan 4 eks 35,000 140,000
Sub Jumlah A 29,186,833
B LAPORAN AKHIR DAN LAPORAN PENUNJANG
- Ahli Pratama Teknik Sumber Daya Air [Team Leader] (1 org x 2 minggu) 1 OK 20,666,000 10,333,000
- Surveyor (2 org x 2 minggu) 2 OK 10,333,333 10,333,333
- CAD/CAM Operator (2 org x 2 minggu) 2 OK 4,903,000 4,903,000
- Computer Operator/Typist (1 org x 2 minggu) 1 OK 4,903,000 2,451,500
- Laporan Akhir 2 eks 108,000 216,000
- Laporan A3 2 eks 166,000 332,000
- Harddisk 1 bh 1,036,000 1,036,000
- Makan minum/snack Presentasi Laporan Akhir 15 Org 54,000 810,000
- Bahan Paparan Laporan Akhir 5 eks 35,000 175,000
Sub Jumlah B 30,589,833
JUMLAH TOTAL (A+B) 59,776,666
REKAPITULASI PERINCIAN BIAYA
: Pengelolaan SDA dan Bangunan Pengaman Pantai pada Wilayah Sungai (WS)
Kegiatan
dalam 1 (Satu) Daerah Kabupaten/Kota
: Penyusunan Rencana Teknis dan Dokumen Lingkungan Hidup untuk Konstruksi
Sub Kegiatan
Pengendali Banjir, Lahar, Drainase Utama Perkotaan dan Pengaman Pantai
: Perencanaan Pembangunan Tandon Perumahan Setneg, Kelurahan Pondok
Pekerjaan
Kacang Barat, Kecamatan Pondok Aren
Sumber Dana : APBD-P Kota Tangerang Selatan
Tahun Anggaran : 2022
Total 73,659,600.00
Terbilang :
Tujuh Puluh Tiga Juta Enam Ratus Lima Puluh Sembilan Ribu Enam Ratus Rupiah
HARGA JUMLAH
NO URAIAN VOL SAT PPN 11% TOTAL JUMLAH
SATUAN (Rp) HARGA (Rp)
5.1.02.02.08.0008 Belanja Jasa Konsultansi Perencanaan Rekayasa-Jasa Desain Rekayasa untuk Pekerjaan Teknik Sipil Air
A Tenaga Ahli