HARGA PERKIRAAN SENDIRI (HPS)

PENGADAAN JASA KONSULTASI

PEKERJAAN : BELANJA JASA KONSULTANSI PENYUSUNAN DED PEMBANGUNAN GEDUNG INSTALASI PENGUJIAN KEMETROLOGIAN
KEGIATAN : PENYUSUNAN DED PEMBANGUNAN GEDUNG INSTALASI PENGUJIAN KEMETROLOGIAN
LOKASI : KABUPATEN BADUNG
TAHUN ANGGARAN : APBD PERUBAHAN KABUPATEN BADUNG TAHUN ANGGARAN 2019

Unit/
No Uraian Kuantitas/ volume Harga Satuan (Rp) Jumlah (Rp)
satuan

I Biaya Langsung Personil


I.1 Biaya Tenaga Ahli
1 Team Leader/Ahli (Arsitek S1, 4 th) 1 org 60 / 30 = 2.00 bln 11,954,000.00 23,908,000.00
Jumlah 23,908,000.00

I.2 Biaya Ass. Tenaga Ahli/ Sub profesional


1 Surveyor (Sipil D3, 1 th) 2 org 7 / 30 = 0.23 bln 4,737,000.00 2,210,600.00
2 Cad operator (Sipil D3, 1 th) 1 org 45 / 30 = 1.50 bln 4,737,000.00 7,105,500.00
Jumlah 9,316,100.00

I.3 Biaya Tenaga Pendukung


1 Tenaga administrasi (SMA, 4 th) 1 org 30 / 30 = 1.00 bln 3,275,000.00 3,275,000.00
Jumlah 3,275,000.00

II Biaya Langsung Non Personil


II.1 Biaya Operasional Kantor
1 Biaya ATK + Bahan Habis Pakai 1 ls 435,000.00 435,000.00
Jumlah 435,000.00

II.2 Biaya Pelaporan


1 Laporan Pendahuluan 3 eks 22,500.00 67,500.00
2 Laporan Akhir (Final Report) 4 eks 230,000.00 920,000.00
3 Soft Copy Dokumen DalamBentuk Flashdisk 1 bh 80,000.00 80,000.00
Jumlah 1,067,500.00

I JUMLAH BIAYA LANGSUNG PERSONIL 36,499,100.00


II JUMLAH BIAYA LANGSUNG NON PERSONIL 1,502,500.00
Jumlah I + II : 38,001,600.00
PPn 10% : 3,800,160.00
Jumlah Biaya : 41,801,760.00
Dibulatkan : 41,801,000.00
Terbilang : Empat Puluh Satu Juta Delapan Ratus Satu Ribu Rupiah

Mangupura , 1 April 2019


Pejabat Pembuat Komitmen/PPK

I Gusti Ayu Kadek Yudiani, S.Sos


NIP. 19660625 198603 2 006
BACK UP LAPORAN AKHIR

NO KETERANGAN HARGA SATUAN (Rp.) VOLUME HARGA (Rp.)


1 Laporan pendahuluan 250.00 50 Hal 12,500.00
Biaya jilid 10,000.00 1 Jilid 10,000.00
22,500.00

Jumlah Total : 22,500.00

Mangupura 2017
Pejabat Pembuat Komitmen/PPK
Kepala Bidang Cipta Karya Dinas Pekerjaan
Umum dan Penataan Ruang Kabupaten Badung

I G A Ngr. Arinda Trisnawati, ST


NIP. 196905241998032 005
BACK UP LAPORAN AKHIR

NO KETERANGAN HARGA SATUAN (Rp.) VOLUME HARGA (Rp.)


1 Gambar A3 700.00 75 Hal 52,500.00
Biaya jilid 20,000.00 1 Jilid 20,000.00
72,500.00

2 Spesifikasi teknis 250.00 150 Hal 37,500.00


Biaya jilid 10,000.00 1 Jilid 10,000.00
47,500.00

3 Rencana anggaran biaya (RAB) 250.00 300 Hal 75,000.00


Biaya jilid 10,000.00 1 Jilid 10,000.00
85,000.00

4 Laporan akhir 250.00 60 Hal 15,000.00


Biaya jilid 10,000.00 1 Jilid 10,000.00
25,000.00

Jumlah Total : 230,000.00

Mangupura 2017
Pejabat Pembuat Komitmen/PPK
Kepala Bidang Cipta Karya Dinas Pekerjaan
Umum dan Penataan Ruang Kabupaten Badung

I G A Ngr. Arinda Trisnawati, ST


NIP. 196905241998032 005
Lampiran 3
DAFTAR BIAYA LANGSUNG PERSONIL DAN BIAYA TIDAK LANGSUNG PERSONIL
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KAB. BADUNG TAHUN ANGGARAN 2019
BIAYA LANGSUNG PERSONIL
BIDANG GAJI DASAR Jasa / DIBULATKAN /
NO TAHUN BBS BBU TP Total
AKADEMIK/KEAHLIAN PENDIDI (GD) Keuntungan DASAR
PENGAL
KAN PENYUSUNAN
AMAN
(0,3-0,4)XGD (0,5-1,3)XGD (0,1-0,3)XGD 0,10x(GD+BBS+BBU) (Rupiah) HPS (Rupiah)

1 2 3 4 5 6 7 8 9 10 11
A. TENAGA AHLI DENGAN PENDIDIKAN S2 KOTA DPS 2019

12 S2 11,238,000.00 4,495,200.00 7,866,600.00 1,123,800.00 2,359,980.00 27,083,580.00 27,084,000.00


1 11 S2 10,711,000.00 4,284,400.00 7,497,700.00 1,071,100.00 2,249,310.00 25,813,510.00 25,814,000.00
AHLI UTAMA
10 S2 10,234,000.00 4,093,600.00 7,163,800.00 1,023,400.00 2,149,140.00 24,663,940.00 24,664,000.00
9 S2 9,734,000.00 3,893,600.00 6,813,800.00 973,400.00 2,044,140.00 23,458,940.00 23,459,000.00
8 S2 9,207,000.00 3,682,800.00 6,444,900.00 920,700.00 1,933,470.00 22,188,870.00 22,189,000.00
2 7 S2 8,731,000.00 3,492,400.00 6,111,700.00 873,100.00 1,833,510.00 21,041,710.00 21,042,000.00
AHLI MADYA
6 S2 8,178,000.00 3,271,200.00 5,724,600.00 817,800.00 1,717,380.00 19,708,980.00 19,709,000.00
5 S2 7,703,000.00 3,081,200.00 5,392,100.00 770,300.00 1,617,630.00 18,564,230.00 18,565,000.00
4 S2 7,203,000.00 2,881,200.00 5,042,100.00 720,300.00 1,512,630.00 17,359,230.00 17,360,000.00
3 S2 6,701,000.00 2,680,400.00 4,690,700.00 670,100.00 1,407,210.00 16,149,410.00 16,150,000.00
AHLI MUDA
5 2 S2 6,199,000.00 2,479,600.00 4,339,300.00 619,900.00 1,301,790.00 14,939,590.00 14,940,000.00
1 S2 5,672,000.00 2,268,800.00 3,970,400.00 567,200.00 1,191,120.00 13,669,520.00 13,670,000.00
B TENAGA AHLI DENGAN PENDIDIKAN S1
16 S1 10,393,000.00 4,157,200.00 7,275,100.00 1,039,300.00 2,182,530.00 25,047,130.00 25,048,000.00
1 15 S1 9,919,000.00 3,967,600.00 6,943,300.00 991,900.00 2,082,990.00 23,904,790.00 23,905,000.00
AHLI UTAMA
14 S1 9,497,000.00 3,798,800.00 6,647,900.00 949,700.00 1,994,370.00 22,887,770.00 22,888,000.00
13 S1 9,074,000.00 3,629,600.00 6,351,800.00 907,400.00 1,905,540.00 21,868,340.00 21,869,000.00
12 S1 8,600,000.00 3,440,000.00 6,020,000.00 860,000.00 1,806,000.00 20,726,000.00 20,726,000.00
2 11 S1 8,125,000.00 3,250,000.00 5,687,500.00 812,500.00 1,706,250.00 19,581,250.00 19,582,000.00
AHLI MADYA
10 S1 7,650,000.00 3,060,000.00 5,355,000.00 765,000.00 1,606,500.00 18,436,500.00 18,437,000.00
9 S1 7,123,000.00 2,849,200.00 4,986,100.00 712,300.00 1,495,830.00 17,166,430.00 17,167,000.00
8 S1 6,753,000.00 2,701,200.00 4,727,100.00 675,300.00 1,418,130.00 16,274,730.00 16,275,000.00
3 7 S1 6,332,000.00 2,532,800.00 4,432,400.00 633,200.00 1,329,720.00 15,260,120.00 15,261,000.00
AHLI MUDA
6 S1 5,884,000.00 2,353,600.00 4,118,800.00 588,400.00 1,235,640.00 14,180,440.00 14,181,000.00
5 S1 5,408,000.00 2,163,200.00 3,785,600.00 540,800.00 1,135,680.00 13,033,280.00 13,034,000.00
4 S1 4,960,000.00 1,984,000.00 3,472,000.00 496,000.00 1,041,600.00 11,953,600.00 11,954,000.00
4 AHLI PRATAMA
3 S1 4,512,000.00 1,804,800.00 3,158,400.00 451,200.00 947,520.00 10,873,920.00 10,874,000.00
2 S1 3,244,000.00 1,297,600.00 1,622,000.00 324,400.00 616,360.00 7,104,360.00 7,105,000.00
SUB PR0FESIONAL STAF 1 S1 2,798,000.00 1,119,200.00 1,399,000.00 279,800.00 531,620.00 6,127,620.00 6,128,000.00
5 (Surveyor, Inspector, Lab
Technition, Cad Operator) 1 D3 2,163,000.00 865,200.00 1,081,500.00 216,300.00 410,970.00 4,736,970.00 4,737,000.00
2 STM 1,782,000.00 712,800.00 891,000.00 178,200.00 338,580.00 3,902,580.00 3,903,000.00
C TENAGA PENDUKUNG
2 S1 1,654,000.00 661,600.00 827,000.00 165,400.00 314,260.00 3,622,260.00 3,623,000.00
Sekretaris, Tenaga Administrasi / 1 S1 1,591,000.00 636,400.00 795,500.00 159,100.00 302,290.00 3,484,290.00 3,485,000.00
1
operator komputer 2 D3 1,527,000.00 610,800.00 763,500.00 152,700.00 290,130.00 3,344,130.00 3,345,000.00
4 SMA/SMK 1,495,000.00 598,000.00 747,500.00 149,500.00 284,050.00 3,274,050.00 3,275,000.00
2 S1 1,463,000.00 585,200.00 731,500.00 146,300.00 277,970.00 3,203,970.00 3,204,000.00
1 S1 1,399,000.00 559,600.00 699,500.00 139,900.00 265,810.00 3,063,810.00 3,064,000.00
2 Sopir, Pekerja, Office Boy
2 D3 1,311,000.00 524,400.00 655,500.00 131,100.00 249,090.00 2,871,090.00 2,872,000.00
4 SMA/SMK 1,311,000.00 524,400.00 655,500.00 131,100.00 249,090.00 2,871,090.00 2,872,000.00

KETERANGAN :
AHLI SUB PROFESIONAL STAF DAN PENDUKUNG
- Gaji Dasar (GD) - Gaji Dasar (GD)
- Beban Biaya Sosial (BBS) = 0.40 x GD - Beban Biaya Sosial (BBS) = 0.30 x GD
- Beban Biaya Umum (BBU) = 0.70 x GD - Beban Biaya Umum (BBU) = 0.50 x GD
- Tunjangan Penugasan (TP)= 0.10 x GD - Tunjangan Penugasan (TP)= 0.10 x GD
- Jasa / Keuntungan = 0.10 x (GD + BBS + BBU) - Jasa / Keuntungan = 0.10 x (GD + BBS + BBU)

BIAYA TIDAK LANGSUNG PERSONIL


SEWA BIAYA LAPORAN
1 SEWA MOBIL Rp. 5,500,000.00 / BULAN LAPORAN PENDAHULUAN Rp. 100,000.00 / BUKU
2 SEWA MOTOR Rp. 550,000.00 / BULAN LAPORAN BULANAN Rp. 100,000.00 Menyesuaikan
3 SEWA KOMPUTER DAN PRINTER Rp. 950,000.00 / BULAN LAPORAN TRIWULAN Rp. 100,000.00 / BUKU
4 SEWA KANTOR (DILUAR SARBAGITA) Rp. 3,000,000.00 / BULAN LAPORAN AKHIR Rp. 150,000.00 / BUKU
5 SEWA ALAT UKUR DAN GPS, BB, SONDIR Rp. 550,000.00 / HARI
6 SEWA ALAT BORING (MEKANIS) Rp. 1,250,000.00 / HARI
7 SEWA ALAT SPT Rp. 400,000.00 / HARI LAINNYA
8 SEWA ALAT DCP Rp. 350,000.00 / HARI ATK Maksimum Rp. 2,500,000.00 Menyesuaikan
9 SEWA TRUK + BEBAN Rp. 2,000,000.00 / HARI KOMUNIKASI KANTOR Rp. 700,000.00 / BULAN

Catatan : Mangupura, Januari 2019


- Biaya Personil berdasarkan Pengalaman Kerja Kepala Dinas Pekerjaan Umum dan Penataan Ruang
dimaksud : dihitung dari Tahun mulai bekerjanya/ Kabupaten Badung
Hasil Karya yang telah dihasilkan
- Biaya Non Personil mengacu kepada
Survey Pasar
- Tenaga Pendukung menyesuaikan
dengan Upah Minimum Kabupaten (UMK)
Kabupaten Badung Tahun 2017 sebesar: Ida Bagus Surya Suamba, ST.MT
Rp. 2.299.311,- Pembina Utama Muda
NIP. 19720916 199703.1.004
ANALISA BIAYA NON PERSONIL

NO URAIAN SATUAN HARGA SATUAN JUMLAH HARGA


A TES SONDIR
I Tes Lapangan
1 Tes Sondir 1 titik 500,000.00 500,000.00
2 Jasa Tenaga Ahli (Pengolahan data) 1 titik 250,000.00 250,000.00
JUMLAH 750,000.00

B TES BORING (Mesin)


I Tes Lapangan
1 Tes Boring 1 ttk 700,000.00 700,000.00
2 Pengambilan Sampel 2 sample 75,000.00 150,000.00
850,000.00
II Tes Laboratorium
1 Tes Kadar Air 2 sample 50,000.00 100,000.00
2 Tes Berat Jenis 2 sample 50,000.00 100,000.00
3 Tes Berat Volume 2 sample 50,000.00 100,000.00
4 Tes Kuat Tekan 2 sample 150,000.00 300,000.00
JUMLAH 600,000.00
C PENGUKURAN TOPOGRAFI SITE
1 Pengukuran Site 1 Ha 3,000,000.00 3,000,000.00
JUMLAH 3,000,000.00
D BIAYA KONSULTASI/PRESENTASI
I Biaya Konsumsi
1 Nasi Kotak 30 bh 30,000.00 900,000.00
2 Snack 30 bh 12,000.00 360,000.00
II Biaya Penggandaan Materi
1 Foto Copy A4 300 lbr 215.00 64,500.00
2 Foto Copy A3 300 lbr 600.00 180,000.00
JUMLAH 1,504,500.00
E BIAYA DOKUMENTASI
1 Cetak Foto Digital 60 lbr 1,500.00 90,000.00
2 Album Foto 1 lbr 50,000.00 50,000.00
JUMLAH 140,000.00
F BIAYA GAMBAR 3 DIMENSI
1 Biaya Cetak Gambar 3 D 18 lbr 20,000.00 360,000.00
2 Jilid 1 bh 40,000.00 40,000.00
400,000.00