Anda di halaman 1dari 3

REKAPITULASI HARGA PERKIRAAN SENDIRI

PERENCANAAN RTH BP BATAM


TAHUN ANGGARAN 2018

NO URAIAN/BIAYA JUMLAH BIAYA

A BIAYA LANGSUNG PERSONIL 196,500,000


1 Tenaga Ahli 96,000,000
2 Tenaga Asisten Ahli 100,500,000

B BIAYA LANGSUNG NON PERSONIL 36,750,000


1 Biaya Operasional Kantor 5,000,000
2 Biaya Pelaporan 7,750,000
3 Biaya Presentasi dan Asistensi 24,000,000

TOTAL ( A + B ) 233,250,000
PAJAK 10 % 23,325,000
TOTAL + PAJAK 10 % 256,575,000

Batam, 14 Februari 2018


A. BIAYA LANGSUNG PERSONIL

BIAYA
JUMLAH JUMLAH JUMLAH BIAYA
NO. URAIAN ORANG BULAN SATUAN PERSONIL (Rp.)
( Rp. )

I.1 TENAGA AHLI


1 Ahli Perencanaan Wilayah 1 3.00 OB 8,000,000.00 24,000,000.00
2 Ahli Arsitektur 1 3.00 OB 6,000,000.00 18,000,000.00
3 Ahli Teknik Sipil 1 3.00 OB 6,000,000.00 18,000,000.00
4 Ahli M/E 1 2.00 OB 6,000,000.00 12,000,000.00
5 Ahli Pertamanan 1 2.00 OB 6,000,000.00 12,000,000.00
6 Ahli Animasi 3D 1 2.00 OB 6,000,000.00 12,000,000.00

SUB TOTAL I.1 96,000,000.00

I.2 TENAGA ASISTEN AHLI


1 Asisten Ahli Arsitektur 1 3.00 OB 4,000,000.00 12,000,000.00
2 Asisten Ahli Teknik Sipil 1 3.00 OB 4,000,000.00 12,000,000.00
3 Asisten Ahli M/E 1 2.00 OB 4,000,000.00 8,000,000.00
4 Asisten Ahli Pertamanan 1 2.00 OB 4,000,000.00 8,000,000.00
5 Asisten Ahli Animasi 3D 1 2.00 OB 4,000,000.00 8,000,000.00
6 Drafter 5 3.00 OB 3,500,000.00 52,500,000.00

SUB TOTAL I.2 100,500,000.00


JUMLAH TOTAL BIAYA LANGSUNG PERSONIL 196,500,000.00
B. BIAYA LANGSUNG NON PERSONIL

HARGA
JUMLAH BIAYA
NO. URAIAN UNIT VOLUME SATUAN SATUAN (Rp.)
(Rp.)

II.1 BIAYA OPERASIONAL KANTOR


1. Biaya ATK dan Komunikasi 1 1 Paket 5,000,000.00 5,000,000.00

SUB TOTAL II.1 5,000,000.00

II.2 BIAYA PELAPORAN


1. Laporan Pendahuluan 1 5 Buku 200,000.00 1,000,000.00
2. Laporan Antara 1 5 Buku 300,000.00 1,500,000.00
3. Laporan Akhir 1 5 Buku 500,000.00 2,500,000.00
4. CD Animasi 1 5 Keping 50,000.00 250,000.00
5. DED RTH 1 5 Buku 500,000.00 2,500,000.00

SUB TOTAL II.2 7,750,000.00

II.3 BIAYA PRESENTASI DAN ASISTENSI


1. Transportasi 3 6 Trip 3,000,000.00 18,000,000.00
2. Penginapan 3 12 Hari 500,000.00 6,000,000.00

SUB TOTAL II.3 24,000,000.00


JUMLAH TOTAL 36,750,000.00