TR Juni 5-11 KPA
TR Juni 5-11 KPA
Contact Person
Location Bontang
Work Order No :
Car/Petrol Hotel/Acco-
No Explanation UM TLK Ferry Others TOTAL
Expenses modation
1 UM & TLK 7 hari Ma'ruf 35000 35000 490000
2 UM & TLK 7 hari Agus S 50000 45000 665000
3 UM & TLK 7 hari Akmal 35000 35000 490000
4 UM & TLK 7 hari Amir 35000 35000 420000
5 UM & TLK 7 hari Suhariady 35000 35000 490000
6 UM & TLK 7 hari Yogi 25000 25000 350000
7 UM & TLK 7 hari M.Ari 15000 25000 280000
8 UM 7 hari Heri 25000 175000
9 BBM Pertalite KT 1972 KL 400,000 400,000
10 BBM Pertalite KT 1810 KG 250,000 250,000
11 BBM Pertalite KT 1975 ZW 250,000 250,000
12 BBM Genset 1&2 200000 400000
13 BBM Motor 1 & 2 200000
14 Isi Ulang Oxygen Blender 185000
TOTAL 5,045,000