Anda di halaman 1dari 12

Kabupaten : Banyumas Jenis Prasarana : Drainase

Kecamatan : Kembaran Take Of Sheet Lokasi : RT 5 RW 04


Desa : Ledug Volume : 93 m

0.12 0.12 Galian Tanah : Panjang = 93


0.54 x 0.64 x 93.00 = 32.14 m3
0.12
Cor Beton 1 : 2 : 3
0.4 1.88 x 0.10 x 93.00 = 17.48 m3

0.12 Begisting
0.3 1.10 x 93.00 = 102.30 m2

Perhitungan tulangan :
Arah memanjang :
2.12 + 1.00 x 93.00 = 1,407.40 m
0.20
Arah pendek
93.00 + 1.00 x 2.12 = 1,316.52 m
0.20
Total panjang = 2,723.92 = 2,723.92 m
12.00
= 226.99 btg
= 227.00 btg

Rekapitulasi Pekerjaan Drainase :


Galian tanah = 32.14 m3
Cor Beton = 17.48 m3
Begisting = 102.30 m2
Tulangan beton = 227.00 btg
m
GAMBAR RENCANA

KABUPATEN
BANYUMAS
KECAMATAN
KEMBARAN
DESA
PURWODADI
JENIS PRASARANA
SALURAN IRIGASI
LOKASI

JUDUL GAMBAR

Digambar Oleh
Pelaksana Kegiatan
(Kader Teknik)

Diperiksa dan Disetujui oleh :

( ........................... )

Lembar…..Dari…..Lembar
Catatan : Gambar dibuat secara manual ['[
XXIII. FORMAT RENCANA ANGGARAN DAN BIAYA (RAB)

RENCANA ANGGARAN BIAYA (RAB)

DESA : ……………….…………………………………..……………………...
KECAMATAN : …………………………… No.RAB : ……...……..………………
KABUPATEN : …………………………… Bidang : ……...……..………………
PROVINSI : …………………… Kegiatan : ……...……..………………

Harga Satuan Jumlah Total


URAIAN Volume Satuan
Rp Rp
a b c d e=bxd
1. BAHAN
1.1
1.2
1.3
1.4
1….
Sub Total 1) Rp -
2. ALAT
2.1
2.2
2.3
2.4
2. …
Sub Total 2) Rp -
3. UPAH
3.1
3.2
3.3
3. …
Sub Total 3 ) Rp -
Total Biaya
Keterangan :

Kategori Biaya
I-a Pembelian bahan hasil tenaga manusia
I-b Pembelian bahan hasil industri

II-a Pembelian alat tangan


II-b Pembelian / penyewaan alat mesin
III-a Pembayaran tenaga kerja untuk konstruksi
III-b Pembayaran tenaga untuk pengumpulan bahan

………..,Tanggal…….,…….,…
mengetahui :
Kepala Desa Tim Penyusun RKP Desa

(………………………………..) (………………………………..)
B)

…………………...
..……..………………
..……..………………
..……..………………

Jumlah

Rp -

Rp -

Rp -
.,Tanggal…….,…….,…

m Penyusun RKP Desa

……………………………..)
RENCANA ANGGARAN BIAYA

Desa : Ledug Nomor RAB : 01


Kecamatan : Kembaran Bidang : Pembangunan
Kabupaten : Banyumas Kegiatan : Drainase
Propinsi : Jawa Tengah Lokasi : RT 01 RW 02

Harga Jumlah Total Jumlah


No. Uraian Volume Satuan
Satuan (Rp) (Rp) (Rp.)

I. Bahan
1 Portland Cement 50 kg 118.00 zak 60,000 7,080,000
2 Batu pecah 2/3 14.20 m3 275,000 3,905,000
3 Besi dia. 8 mm 227.00 btg 45,000 10,215,000
4 Bendrat 17.00 kg 18,000 306,000
5 Pasir beton 10.00 m3 220,000 2,200,000
6 Kayu tahun 0.30 m3 2,500,000 750,000
7 Paku 41.00 m3 18,000 738,000
8 Kayu usuk 5/7 0.30 m3 2,500,000 750,000

25,944,000
II. Alat
1 Papan nama kegiatan 1.00 bh 50,000.00 50,000
2 Prasasti 1.00 bh 300,000.00 300,000
3 Benang 4.00 bh 5,000.00 20,000
4 Ember 15.00 bh 10,000.00 150,000

520,000
III. Upah
1 Pekerja 89.00 ho 60,000 5,340,000
2 Tukang 49.00 ho 75,000 3,675,000
3 Kepala Kelompok 22.00 ho 75,000 1,650,000

Sub Total 1) 10,665,000


Total Biaya DD 37,129,000
IV. Honor PPHP
1 Ketua 1.00 pkt 100,000 100,000
2 Sekretaris 1.00 pkt 75,000 75,000
3 Anggota 1.00 pkt 50,000 50,000
Sub Total 3) 225,000
Total Biaya ADD 225,000
Total Biaya 37,354,000

Ledug, Juli 2017


Mengetahui,
Kepala Desa …… Tim Penyusun RKP

Sito Nina Hariyani, S.Sn


NIP. 19601019 198408 1 001
PERHITUNGAN BAHAN DAN UPAH DRAINASE PLAT BETON
RT 03 RW 01

Volume Galian = 32.14 m3


Volume Pasangan Batu = - m3
Volume Cor Beton camp. 1 : 2 : 3 = 17.48 m3
Volume Pembesian = 227.00 x 4.74 = 1,075.98 kg
Volume Begisting = 102.30 m2

Volume Plesteran = - m2

1 1 m3 GALIAN TANAH BIASA SNI-B.6.1


Pekerja 0.4000 x 32.1408 = 12.86 = 13.00 m3
Kepala kelompok 0.0400 x 32.1408 = 1.29 = 2.00 hok
2 1 m3 PAS. PONDASI BATU KALI 1 pc : 4 ps SNI-C.6.5
Batu belah 1.1000 x 0 = - = - m3
Portland Cement 163.0000 x 0 = - = - zak = - Zak
Pasir pasang 0.5200 x 0 = - = - m3
Pekerja 1.5000 x 0 = - = - hok
Tukang batu 0.6000 x 0 = - = - hok
Kepala kelompok 0.0750 x 0 = - = - hok
3 1 m3 MEMBUAT BETON TUMBUK 1 pc : 2ps : 3kr SNI-G.6.13
Portland Cement 336.0000 x 17.484 = 5,874.62 = 117.49 zak = 118.00 Zak
Pasir pasang 0.5400 x 17.484 = 9.44 = 10.00 m3
Batu pecah 2/3 cm 0.8100 x 17.484 = 14.16 = 14.20 m3
Pekerja 2.0000 x 17.484 = 34.97 = 35.00 hok
Tukang batu 0.3500 x 17.484 = 6.12 = 7.00 hok
Kepala kelompok 1.0000 x 17.484 = 17.48 = 18.00 hok
4 1 Kg PEMBESIAN DENGAN BESI BETON POLOS SNI-G.6.25
Besi beton polos dia 10 1.0500 x 1,075.980 = 1,129.78 = 1,130.00 kg
Kawat beton (bindrat) 0.0150 x 1,075.980 = 16.14 = 17.00 kg
Pekerja 0.0070 x 1,075.980 = 7.53 = 8.00 hok
Tukang besi 0.0070 x 1,075.980 = 7.53 = 8.00 hok
Kepala kelompok 0.0003 x 1,075.980 = 0.32 = 1.00 hok

5 1 m2 PAS. BEKISTING UNTUK LANTAI SNI-G.6.32


Kayu tahun 0.0400 x 102.30 = 4.09 = 0.30 m3
Paku biasa (2'' - 5'') 0.4000 x 102.30 = 40.92 = 41.00 kg
Kayu usuk 5/7 0.0150 x 102.30 = 1.53 = 0.30 m3
Pekerja 0.3200 x 102.30 = 32.74 = 33.00 hok
Tukang kayu 0.3300 x 102.30 = 33.76 = 34.00 hok
Kepala kelompok 0.0060 x 102.30 = 0.6138 = 1.00 hok

6 1 m2 PLESTERAN 1 pc : 5 ps tb. 1,5 cm SNI-E.6.5


Portland Cement 4.3200 x - = - = - kg = - Zak
Pasir pasang 0.0220 x 0 = - = - m3
Pekerja 0.2000 x 0 = - = - hok
Tukang batu 0.1500 x 0 = - = - hok
Kepala kelompok 0.0100 x 0 = - = - hok
Langsir material Gorong-Gorong

Pekerja langsir
Hari orang kerja = 6 jam
REKAPITULASI RENCANA ANGGARAN BIAYA

DESA : PASIRAMAN LOR


KECAMATAN : BANYUMAS
KABUPATEN : BANYUMAS
BIDANG : PEMBANGUNAN DESA
TAHUN ANGGARAN : 2017

JUMLAH HARGA
NO URAIAN KEGIATAN
( Rp.)
1 2 3
A. DRAINASE JALAN #REF!

B. DRAINASE LINGKUNGAN #REF!

C. DRAINASE PLAT BETON 37,354,000.00

D. GORONG - GORONG #REF!

D. RABAT BETON BAHU JALAN #REF!

JUMLAH #REF!
TERBILANG :

Pasiraman Lor, ……………………..

Mengetahui,
Kepala Desa Pasiraman Lor Tim Penyusun RKP

( ………………………… ) ( ………………………… )
DAFTAR HARGA SATUAN BAHAN DAN UPAH

A. Bahan Bangunan
NO JENIS SATUAN HARGA

1 Batu belah m3 Rp 230,000.00


2 Pasir beton m3 Rp 220,000.00
3 Batu pecah 2/3 m3 Rp 275,000.00
4 Portland Cement zak Rp 60,000.00
5 Besi dia. 8 mm btg Rp 45,000.00
6 Bendrat kg Rp 18,000.00
7 Paku kg Rp 18,000.00
8 Kayu tahun m3 Rp 2,500,000.00
9 Bambu btg Rp 20,000.00
10 Benang bh Rp 5,000.00
11 Ember bh Rp 10,000.00

B. Upah Tenaga Kerja


NO. JENIS SATUAN HARGA

1 Kepala Kelompok Oh Rp 75,000.00


2 Pekerja Oh Rp 60,000.00
3 Tukang batu Oh Rp 75,000.00

Ledug, ………………………..
Dibuat oleh :