REKAPITULASI RENCANA ANGGARAN BIAYA

PEKERJAAN : RUMAH KOST BAJI DAKKA 1 NO. 26A


LOKASI : KOTA MAKASSAR
TAHUN : 2024

NO ITEM PEKERJAAN JUMLAH

1 PEKERJAAN PENDAHULUAN Rp. 10,302,836.26


2 PEKERJAAN STRUKTUR Rp. 189,259,007.73
3 PEKERJAAN ARSITEKTUR Rp. 159,501,548.55
4 PEKERJAAN KUSEN, PINTU & JENDELA dll. Rp. 44,877,374.32
5 PEK.RANGKA, PLAFOND Rp. 33,033,747.55
6 PEKERJAAN INSTALASI LISTRIK Rp. 10,478,255.50
7 PEKERJAAN SANITASI Rp. 19,111,768.85
8 PEKERJAAN PENGECATAN Rp. 22,836,544.47

A. REAL COST Rp. 489,401,083.24


D. TOTAL BIAYA FISIK BANGUNAN ( DIBULATKAN ) Rp. 489,400,000.00

TERBILANG : EMPAT RATUS DELAPAN PULUH SEMBILAN JUTA EMPAT RATUS RIBU RUPIAH

MAKASSAR, APRIL 2024

Diperiksa Oleh Dibuat Oleh :


…......

….......... NUR MAHFUDDIN SALAMULLAH


…........... ….... . ...
PEKERJAAN : Rumah Kost Baji Dakka 1 No 26A
RENCANA ANGGARA BIAYA ( RAB )
LOKASI : KOTA MAKASSAR
TAHUN : 2024
Rumah Kost Baji Dakka 1 No. 26A

HARGA SAT. JUMLAH HARGA


URAIAN PEKERJAAN VOLUME SAT.
(Rp.) (Rp.)
1 2 3 4 5 6
1 PEKERJAAN PENDAHULUAN
Pek. Pengukuran /Pemasangan Bowplank 1.00 Ls 1,200,000.00 1,200,000.00
Pembongkaran dinding 1/2 bata 1.10 m3 32,340.00 35,412.30
pembongkaran rangka atap 96.00 m2 39,362.43 3,778,793.57
pebongkaran plafond 77.00 m2 12,106.04 932,165.08
pembongkaran kramik 62.40 m2 9,257.56 577,671.74
pembongkaran atap 96.00 m2 39,362.43 3,778,793.57
Sub Total I …………………………… 10,302,836.26
2 PEKERJAAN STRUKTUR
Pekerjaan Struktur Bawah
*Pek. Pondasi telapak P1 (dalam 125 cm)
Pekerjaan Galian Tanah 13.824 m3 86,900.00 1,201,305.60
bekisting 12.000 m2 103,642.00 1,243,704.00
Pembesian besi 12 Ulir 358.560 kg 16,420.69 5,887,802.61
BETON MUTU Fc = 19,3 Mpa (K 225), Slump (12±2)Cmw/c=0,58 4.824 m3 1,322,299.00 6,378,770.38
*Pek. Pondasi Garis, La : 80 cm) -
Pekerjaan Galian Tanah 14 m3 86,900 1,192,963.20
Pasangan pondasi batu kosong t 10 cm 1.760 m3 597,214.20 1,051,096.99
Pasangan Pondasi Batu Kali 1PC : 4Ps 13.728 m3 997,788.00 13,697,633.66
*Pekerjaan Sloff 20x20 -
Bekisting 8.800 m2 109,840.50 966,596.40
Pembesian Besi 12 Polos 78.320 kg 16,420.69 1,286,068.44
BETON MUTU Fc = 19,3 Mpa (K 225), Slump (12±2)Cmw/c=0,58 0.880 m3 1,322,299.00 1,163,623.12
*Pek. Tangga Lt.1 Ke Lt. 2
Bekisting 19.602 m2 176,275.00 3,455,342.55
Pembesian Besi 10 ulir 58.74 kg 16,420.69 964,551.33
BETON MUTU Fc = 19,3 Mpa (K 225), Slump (12±2)Cmw/c=0,58 1.844 m3 1,322,299.00 2,438,213.57

Pekerjaan Struktur atas -


*Kolom 30x30 LT.1 -
Bekisting 17.40 m2 153,081.50 2,663,618.10
Pembesian Besi 12 Polos 384.48 kg 16,420.69 6,313,426.89
BETON MUTU Fc = 19,3 Mpa (K 225), Slump (12±2)Cmw/c=0,58 4.86 m3 1,322,299.00 6,426,373.14
*Kolom 30x30 Lt.2
Bekisting 17.40 m2 153,082 2,663,618
Pembesian Besi 12 Polos 384.48 kg 16,421 6,313,427
BETON MUTU Fc = 19,3 Mpa (K 225), Slump (12±2)Cmw/c=0,58 4.86 m3 1,322,299 6,426,373
*Kolom KP (11x11) cm 6.000 m1 99,688.60 598,131.60
*Balok 20x25 -
Bekisting 32.389 m2 171,792.50 5,564,187.28
Pembesian Besi 12 Polos 291.066 kg 16,420.69 4,779,497.99
BETON MUTU Fc = 19,3 Mpa (K 225), Slump (12±2)Cmw/c=0,58 4.088 m3 1,322,299.00 5,405,558.31
*Plat Lt. 2 (12 cm) -
Bekisting 15.988 m2 176,275.00 2,818,224.77
Pembesian Besi 10 ulir 1,697.052 kg 16,420.69 27,866,771.05
BETON MUTU Fc = 19,3 Mpa (K 225), Slump (12±2)Cmw/c=0,58 13.369 m3 1,322,299.00 17,678,159.13
*Ring balok (20x20) -
Bekisting 26.184 m2 176,275.00 4,615,584.60
Pembesian Besi 10 ulir 219.117 kg 16,420.69 3,598,049.05
BETON MUTU Fc = 19,3 Mpa (K 225), Slump (12±2)Cmw/c=0,58 3.270 m3 1,322,299.00 4,324,446.65
Rangka atap -
*Pek. Rangka atap baja ringan 110.731 m2 249,590.00 27,637,450.13
*Pek. Atap spandeks 110.731 m2 114,136.00 12,638,439.07
-

Sub Total II …………………………… 189,259,007.73


3 PEKERJAAN ARSITEKTUR
Batu bata 1 : 4, dinding 1/2 batu Lt. 1 49.4205 M2 127,030.75 6,277,923.18
Plesteran 1 : 4, tebal 12 mm 98.84 M2 61,217.64 6,050,812.76
Acian 98.84 M2 37,262.50 3,683,062.76
habel (bata ringan) Lt.2 169.63 m2 193,072.50 32,750,791.13
Plesteran 1 : 4, tebal 12 mm 339.26 m2 61,217.64 20,768,635.33
Acian 339.26 m2 37,262.50 12,641,638.49
Pek partisi (loster pabrikasi) 7.04 m2 739,486.00 5,205,981.44
Pek. Finishing fasade (Bata Ekspose) 14.36 m2 135,228.50 1,941,205.12
Pek. Railing 56.94 m1 16,200.00 922,428.00
Pek. Paving Blok 56.50 M2 154,027.50 8,701,937.64
Lantai Keramik 40 x 40 cm Putih Polos 222.82 M2 271,774.80 60,557,132.71
Sub Total III ……………………………159,501,548.55
4 PEKERJAAN KUSEN, PINTU & JENDELA dll.
Pek. Bingkai P1
Pekerjaan Pintu Panil (P1) + (acccesoris) 15.00 Unit 1,028,500.0015,427,500.00
Pek Kusen Pintu Kayu (P1) 79.50 m1 134,115.0010,662,142.50
-
Pek. Kusen Jendela (J1) 52.50 m1 134,115.00 7,041,037.50
Pek. Bingkai jendela (J1) + (accesoris) 48.30 m1 118,890.00 5,742,387.00
Pek. Kaca 5 mm 8.25 m2 184,670.00 1,523,527.50
-
Pek. Kusen Jendela J2 5.28 m1 134,115.00 708,127.20
Pek. Bingkai Jendela J2 + (accesoris) 4.86 m1 118,890.00 577,520.06
Pek. Kaca 5 mm 0.80 m2 184,670.00 147,736.00
-
Pek. Kusen Jendela Mati (J3) 15.48 m1 134,115.00 2,076,100.20
Pek. Kaca 10 mm 3.20 m2 303,910.00 971,296.36
Sub Total IV …………………………… 44,877,374.32
5 PEK.RANGKA, PLAFOND
Pas Plafond gypsum + Rangka 111.41 M2 199,576.85 22,234,956.65
Lis plafon (gypsum) 312.01 m1 34,610.40 10,798,790.90
Sub Total V …………………………… 33,033,747.55
6 PEKERJAAN INSTALASI LISTRIK
Panel MCB 19.00 Ttk 132,300.00 2,513,700.00
Instalasi Titik Listrik 22.00 Ttk 188,718.75 4,151,812.50
Lampu LED 10 watt 15.00 Bh 37,125.00 556,875.00
LampU LED 20 watt 34.00 Bh 59,400.00 2,019,600.00
Stop kontak Putih dan instalasi 16.00 Ttk 41,654.25 666,468.00
Saklar ganda 16.00 Bh 35,612.50 569,800.00
Sub Total VI…………………………… 10,478,255.50
7 PEKERJAAN SANITASI
Floor Drain 15.00 m1 71,830.00 1,077,450.00
MEMASANG KLOSET JONGKOK PORSELEN 15.00 m1 814,698.50 12,220,477.50
MEMASANG PIPA PVC TIPE AW DIAMETER 1/2 " 33.82 m1 21,206.11 717,190.62
MEMASANG PIPA PVC TIPE AW DIAMETER 3/4 " 30.00 m1 23,879.21 716,376.38
MEMASANG PIPA PVC TIPE AW DIAMETER 4 " 35.82 m1 97,324.98 3,486,180.60
MEMASANG KRAN DIAMETER 3/4 " ATAU 1/2 " 15.00 bh 59,606.25 894,093.75
Sub Total VII…………………………… 19,111,768.85
8 PEKERJAAN PENGECATAN
Pek.Cat Plafond 111.41 M2 36,900.13 4,111,061.68
Pek.Cat Tembok 653.04 M2 28,674.33 18,725,482.79
Sub Total VIII……………………………22,836,544.47

TOTAL I+II+III+IV+V+VI+VII+VIII 489,401,083.24