1 Umum 148,900,000.00
2 Sistem Manajemen Keselamatan Konstruksi (Smkk) 50,564,301.18
8 Struktur 7,728,465,133.95
JUMLAH 8,022,409,895.57
DIVISI 1. UMUM
1.2. Mobilisasi LS 1.00 148,900,000.00 148,900,000.00 - - 1.00 148,900,000.00 - - - Item Pek. Hilang
Mobilisasi >10% LS - 929,712,540.99 - 1.00 929,712,540.99 - - 1.00 929,712,540.99 11.589 Item Pek. Baru
2.1.(1) Pembuatan dokumen RKK, RKPPL, RMLLP, RMPK Set 1.00 1,000,000.00 1,000,000.00 - - - - 1.00 1,000,000.00 0.012 Tetap
2.1.(2) Pembuatan Prosedur dan instruksi kerja Set 1.00 300,000.00 300,000.00 - - - - 1.00 300,000.00 0.004 Tetap
2.1.(3) Penyusunan pelaporan penerapan SMKK Set 1.00 300,000.00 300,000.00 - - - - 1.00 300,000.00 0.004 Tetap
2.2.(2) Pengarahan Keselamatan Konstruksi (Safety Briefing) Org 10.00 20,000.00 200,000.00 - - - - 10.00 200,000.00 0.002 Tetap
2.2.(8) Spanduk (Banner) Lb 1.00 200,000.00 200,000.00 - - - - 1.00 200,000.00 0.002 Tetap
2.2.(10) Papan Informasi Keselamatan konstruksi Bh 1.00 250,000.00 250,000.00 - - - - 1.00 250,000.00 0.003 Tetap
Topi pelindung (Safety Helmet) Bh 10.00 100,000.00 1,000,000.00 - - - - 10.00 1,000,000.00 0.012 Tetap
Pelindung mata (Goggles, Spectacles) Bh 10.00 150,000.00 1,500,000.00 - - - - 10.00 1,500,000.00 0.019 Tetap
Pelindung pernafasan dan mulut (masker, masker respirator) Bh 10.00 10,000.00 100,000.00 - - - - 10.00 100,000.00 0.001 Tetap
Sarung tangan (Safety Gloves) Psg 10.00 10,000.00 100,000.00 - - - - 10.00 100,000.00 0.001 Tetap
Sepatu keselamatan (Safety Shoes, rubber safety shoes and toe ca Psg 10.00 250,000.00 2,500,000.00 - - - - 10.00 2,500,000.00 0.031 Tetap
Rompi keselamatan (Safety Vest) Bh 10.00 350,000.00 3,500,000.00 - - - - 10.00 3,500,000.00 0.044 Tetap
2.5.(2) Ahli K3 konstruksi atau ahli keselamatan konstruksi Org/Bln 1.00 3,000,000.00 3,000,000.00 - - - - 1.00 3,000,000.00 0.037 Tetap
2.5.(6) Petugas P3K Org/Bln 2.00 1,000,000.00 2,000,000.00 - - 1.00 1,000,000.00 1.00 1,000,000.00 0.012 Item Pek. Kurang
2.5.(8) Petugas pengatur lalu lintas Org/Bln 2.00 1,000,000.00 2,000,000.00 - - 1.00 1,000,000.00 1.00 1,000,000.00 0.012 Item Pek. Kurang
2.6.(1) Peralatan P3K Set 1.00 700,000.00 700,000.00 - - - - 1.00 700,000.00 0.009 Tetap
2.6.(4) Biaya protokol kesehatan wabah menular (misal tempat cuci tangan, Ls 1.00 2,000,000.00 2,000,000.00 - - - - 1.00 2,000,000.00 0.025 Tetap
2.7 Rambu dan Perlengkapan lalu lintas yang diperlukan atau manajemen lalu lintas
2.7.(1) Rambu petunjuk Bh 4.00 50,000.00 200,000.00 - - 3.00 150,000.00 1.00 50,000.00 0.001 Item Pek. Kurang
2.7.(2) Rambu larangan Bh 4.00 50,000.00 200,000.00 - - 3.00 150,000.00 1.00 50,000.00 0.001 Item Pek. Kurang
2.7.(3) Rambu peringatan Bh 4.00 50,000.00 200,000.00 - - 3.00 150,000.00 1.00 50,000.00 0.001 Item Pek. Kurang
2.7.(5) Rambu informasi Bh 4.00 50,000.00 200,000.00 - - 3.00 150,000.00 1.00 50,000.00 0.001 Item Pek. Kurang
2.7.(18) Jembatan sementara Ls 1.00 28,914,301.18 28,914,301.18 - - 1.00 28,914,301.18 - - - Item Pek. Hilang
4.1.(1) Galian Biasa M3 37.50 96,248.27 3,609,309.94 - - 37.50 3,609,309.94 - - - Item Pek. Hilang
3.1.(4) Galian Struktur dengan kedalaman 0 - 2 meter M3 67.54 96,999.81 6,551,367.20 - - 67.54 6,551,367.20 - - Item Pek. Hilang
4.2.(2a) Timbunan Pilihan dari sumber galian M3 196.39 390,634.28 76,716,665.85 - - - - 196.39 76,716,665.85 0.956 Tetap
DIVISI 8. STRUKTUR
8.1.(5a) Beton Struktur fc30 MPa M3 135.00 3,410,494.17 460,416,713.05 - - 135.00 460,416,713.05 - - - Item Pek. Hilang
8.1 (7) a Beton Struktur, fc 20 MPa M3 24.80 3,078,740.34 76,352,760.31 - - 24.80 76,352,760.31 - - - Item Pek. Hilang
8.3 (1) Baja Tulangan Polos-BjTP 280 Kg 9,495.61 27,718.28 263,201,953.01 - - 9,495.61 263,201,953.01 - - - Item Pek. Hilang
7.3 (3) Baja Tulangan Sirip BjTS 420B Kg 12,576.35 32,222.14 405,236,878.95 - - 12,576.35 405,236,878.95 - - - Item Pek. Hilang
7.4 (1) b Penyediaan Baja Struktur Grade 345 (Titik Leleh 345 Mpa) Kg 140,152.00 39,226.41 5,497,659,592.20 - - - - 140,152.00 5,497,659,592.20 68.529 Tetap
7.4 (2) c Pemasangan Baja Struktur Kg 140,152.00 2,174.66 304,783,343.53 - - 140,152.00 304,783,343.53 - - - Item Pek. Hilang
Pemasangan Baja Struktur Kg - 10,697.46 - 140,152.00 1,499,271,096.53 - - 140,152.00 1,499,271,096.53 18.689 Item Pek. Baru
8.8.(1) Pasangan Batu M3 532.37 1,340,512.88 713,648,842.90 - - 532.37 713,648,842.90 - - - Item Pek. Hilang
8.13.(1) Papan Nama Jembatan buah 2.00 1,832,525.00 3,665,050.00 - - 2.00 3,665,050.00 - - - Item Pek. Hilang
8.15.(2).a Pipa Drainase Baja diameter 75 mm M 20.00 175,000.00 3,500,000.00 - - 20.00 3,500,000.00 - - - Item Pek. Hilang
10.2.(5) Patok Pengarah Buah 36.00 211,197.71 7,603,117.45 - - 36.00 7,603,117.45 - - - Item Pek. Hilang
DIVISI 1. UMUM 1.86 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.46 0.46
RENCANA 0.23
REALISASI
DIVISI 4. PEKERJAAN TANAH DAN
2.31 2.31
GEOSINTETIK
DIVISI 8. STRUKTUR 95.20 5.60 5.60 5.60 5.60 5.60 5.60 5.60 5.60 5.60 5.60 5.60 5.60 5.60 5.60 5.60 5.60 5.60
JUMLAH 100.00
0.08 0.08 0.08 0.08 0.71 5.68 5.68 5.68 5.68 5.60 5.60 5.60 8.38 6.06 5.60 5.60 5.60 5.60 5.60 5.60 5.60 5.60 0.23 - -
RENCANA (%)
- 0.08 0.15 0.23 0.31 1.02 6.69 12.37 18.05 23.73 29.33 34.93 40.53 48.90 54.97 60.57 66.17 71.77 77.37 82.97 88.57 94.17 99.77 100.00 100.00 100.00
KUMULATIF RENCANA (%)
- - - 0.19 30.85 - - - - - - 29.22 - - - 0.84 1.50 1.87 1.50 1.87 - 15.53 7.89 6.08 2.66
REALISASI (%)
- - - - 0.19 31.03 31.03 31.03 31.03 31.03 31.03 31.03 60.25 60.25 60.25 60.25 61.09 62.59 64.46 65.96 67.84 67.84 83.37 91.26 97.34 100.00
REALISASI KUMULATIF (%)
0.08 0.15 0.23 0.12 30.01 24.34 18.66 12.98 7.30 1.70 3.90 19.72 11.35 5.28 0.32 5.08 9.18 12.90 17.00 20.73 26.33 16.40 8.74 2.66 - 0.00
DEVAISI (%)
NIP. 19761106 201101 1 005 NIP. 19740120 200604 1 002 Site Engineer Direktur
LAPORAN KEMAJUAN PEKERJAAN MINGGUAN
Nama Paket : Pembangunan Jembatan Talapao, Ruas Keliling Makian (Lanjutan) Minggu Ke 25 (Dua Puluh Lima)
Lokasi : Kabupaten Halmahera Selatan Periode 19 Desember 2022 S/d 30 Desember 2022
No. Kontrak : SP/12272361/PPK.FISIK-BM/APBD/DPUPR-MU/2022, Tanggal 23 Juni 2022 Realisasi 100.00 %
Tahun Anggaran : 2022 Rencana 100.00 %
Pelaksana : CV. TRI SETYA NOVALIA Deviasi - %
ADDENDUM-01 REALISASI
NO. MATA MINGGU LALU MINGGU INI KUMULATIF BOBOT
PEMBAYA URAIAN
HARGA SATUAN THDP
RAN SAT. VOLUME JUMLAH HARGA (RP) BOBOT (%) JUMLAH HARGA (RP)
(RP) ITEM PEK
VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
(%)
DIVISI 1. UMUM
1.2 Mobilisasi LS 1.00 148,900,000.00 148,900,000.00 1.856 0.50 0.93 0.50 0.93 1.00 1.86 148,900,000.000 100.00
Jumlah Harga Pekerjaan Divisi 1. 148,900,000.00 1.856 0.93 0.93 1.86 148,900,000.000
2.2.(8) Spanduk (Banner) Lb 1.00 200,000.00 200,000.00 0.002 1.00 0.00 - - 1.00 0.00 200,000.000 100.00
Topi pelindung (Safety Helmet) Bh 10.00 100,000.00 1,000,000.00 0.012 10.00 0.01 - - 10.00 0.01 1,000,000.000 100.00
Sarung tangan (Safety Gloves) Psg 10.00 10,000.00 100,000.00 0.001 10.00 0.00 - - 10.00 0.00 100,000.000 100.00
ADDENDUM-01 REALISASI
NO. MATA MINGGU LALU MINGGU INI KUMULATIF BOBOT
PEMBAYA URAIAN
HARGA SATUAN THDP
RAN SAT. VOLUME JUMLAH HARGA (RP) BOBOT (%) JUMLAH HARGA (RP)
(RP) ITEM PEK
VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
(%)
Rompi keselamatan (Safety Vest) Bh 10.00 350,000.00 3,500,000.00 0.044 10.00 0.04 - - 10.00 0.04 3,500,000.000 100.00
2.5.(6) Petugas P3K Org/Bln 2.00 1,000,000.00 2,000,000.00 0.025 2.00 0.02 - - 2.00 0.02 2,000,000.000 100.00
2.5.(8) Petugas pengatur lalu lintas Org/Bln 2.00 1,000,000.00 2,000,000.00 0.025 2.00 0.02 - - 2.00 0.02 2,000,000.000 100.00
2.6.(1) Peralatan P3K Set 1.00 700,000.00 700,000.00 0.009 1.00 0.01 - - 1.00 0.01 700,000.000 100.00
2.7.(1) Rambu petunjuk Bh 4.00 50,000.00 200,000.00 0.002 4.00 0.00 - - 4.00 0.00 200,000.000 100.00
2.7.(2) Rambu larangan Bh 4.00 50,000.00 200,000.00 0.002 4.00 0.00 - - 4.00 0.00 200,000.000 100.00
2.7.(3) Rambu peringatan Bh 4.00 50,000.00 200,000.00 0.002 4.00 0.00 - - 4.00 0.00 200,000.000 100.00
2.7.(5) Rambu informasi Bh 4.00 50,000.00 200,000.00 0.002 4.00 0.00 - - 4.00 0.00 200,000.000 100.00
2.7.(18) Jembatan sementara Ls 1.00 28,914,301.18 28,914,301.18 0.360 1.00 0.36 - - 1.00 0.36 28,914,301.184 100.00
2.9.(4) Bendera K3 Bh 1.00 200,000.00 200,000.00 0.002 1.00 0.00 - - 1.00 0.00 200,000.000 100.00
4.1.(1) Galian Biasa M3 446.30 96,248.27 42,955,213.60 0.535 446.30 0.54 - - 446.30 0.54 42,955,213.603 100.00
4.2.(1a) Timbunan Biasa dari sumber galian M3 624.81 228,322.53 142,659,194.83 1.778 624.81 1.78 - - 624.81 1.78 142,659,194.830 100.00
DIVISI 8. STRUKTUR
7.4 (2) c Pemasangan Baja Struktur Kg 140,152.00 2,174.66 304,783,343.53 3.799 125,436.04 3.40 14,715.96 0.40 140,152.00 3.80 304,783,343.527 100.00
7.5.(1) Pemasangan perancah jembatan M2 420.00 1,431,453.01 601,210,262.47 7.494 420.00 7.49 - - 420.00 7.49 601,210,262.469 100.00
8.8.(1) Pasangan Batu M3 917.39 1,340,512.88 1,229,767,987.76 15.329 838.03 14.00 79.35 1.33 917.39 15.33 1,229,767,987.758 100.00
7.16.(3).a Pipa Drainase PVC diameter 60 mm M' 136.00 28,750.00 3,910,000.00 0.049 122.40 0.04 13.60 0.00 136.00 0.05 3,910,000.000 100.00
Jumlah Harga Perkiraan Divisi 8. 7,637,331,185.95 95.200 93.47 1.73 95.20 7,637,331,185.953
ADDENDUM-01 REALISASI
NO. MATA BULAN LALU BULAN INI KUMULATIF BOBOT
PEMBAYAR URAIAN
HARGA SATUAN THDP
AN SAT. VOLUME JUMLAH HARGA (RP) BOBOT (%) JUMLAH HARGA (RP)
(RP) ITEM PEK
VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
(%)
DIVISI 1. UMUM
1.2 Mobilisasi LS 1.00 148,900,000.00 148,900,000.00 1.856 0.50 0.928 0.50 0.93 1.00 1.86 148,900,000.000 1.00
Jumlah Harga Pekerjaan Divisi 1. 148,900,000.00 1.856 0.928 0.93 1.86 148,900,000.000
2.2.(8) Spanduk (Banner) Lb 1.00 200,000.00 200,000.00 0.002 1.00 0.002 - - 1.00 0.00 200,000.000 1.00
Topi pelindung (Safety Helmet) Bh 10.00 100,000.00 1,000,000.00 0.012 10.00 0.012 - - 10.00 0.01 1,000,000.000 1.00
Sarung tangan (Safety Gloves) Psg 10.00 10,000.00 100,000.00 0.001 10.00 0.001 - - 10.00 0.00 100,000.000 1.00
ADDENDUM-01 REALISASI
NO. MATA BULAN LALU BULAN INI KUMULATIF BOBOT
PEMBAYAR URAIAN
HARGA SATUAN THDP
AN SAT. VOLUME JUMLAH HARGA (RP) BOBOT (%) JUMLAH HARGA (RP)
(RP) ITEM PEK
VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%)
(%)
Rompi keselamatan (Safety Vest) Bh 10.00 350,000.00 3,500,000.00 0.044 10.00 0.044 - - 10.00 0.04 3,500,000.000 1.00
2.5.(6) Petugas P3K Org/Bln 2.00 1,000,000.00 2,000,000.00 0.025 2.00 0.025 - - 2.00 0.02 2,000,000.000 1.00
2.5.(8) Petugas pengatur lalu lintas Org/Bln 2.00 1,000,000.00 2,000,000.00 0.025 2.00 0.025 - - 2.00 0.02 2,000,000.000 1.00
2.6.(1) Peralatan P3K Set 1.00 700,000.00 700,000.00 0.009 1.00 0.009 - - 1.00 0.01 700,000.000 1.00
2.7.(1) Rambu petunjuk Bh 4.00 50,000.00 200,000.00 0.002 4.00 0.002 - - 4.00 0.00 200,000.000 1.00
2.7.(2) Rambu larangan Bh 4.00 50,000.00 200,000.00 0.002 4.00 0.002 - - 4.00 0.00 200,000.000 1.00
2.7.(3) Rambu peringatan Bh 4.00 50,000.00 200,000.00 0.002 4.00 0.002 - - 4.00 0.00 200,000.000 1.00
2.7.(5) Rambu informasi Bh 4.00 50,000.00 200,000.00 0.002 4.00 0.002 - - 4.00 0.00 200,000.000 1.00
2.7.(18) Jembatan sementara Ls 1.00 28,914,301.18 28,914,301.18 0.360 1.00 0.360 - - 1.00 0.36 28,914,301.184 1.00
2.9.(4) Bendera K3 Bh 1.00 200,000.00 200,000.00 0.002 1.00 0.002 - - 1.00 0.00 200,000.000 1.00
4.1.(1) Galian Biasa M3 446.30 96,248.27 42,955,213.60 0.535 446.30 0.535 - - 446.30 0.54 42,955,213.603 1.00
4.2.(1a) Timbunan Biasa dari sumber galian M3 624.81 228,322.53 142,659,194.83 1.778 374.89 1.067 249.93 0.71 624.81 1.78 142,659,194.830 1.00
Jumlah Harga Perkiraan Divisi 4. 185,614,408.43 2.314 1.602 0.71 2.31 185,614,408.433
DIVISI 8. STRUKTUR
7.4 (2) c Pemasangan Baja Struktur Kg 140,152.00 2,174.66 304,783,343.53 3.799 105,114.00 2.849 35,038.00 0.95 140,152.00 3.80 304,783,343.527 1.00
7.5.(1) Pemasangan perancah jembatan M2 420.00 1,431,453.01 601,210,262.47 7.494 420.00 7.494 - - 420.00 7.49 601,210,262.469 1.00
8.8.(1) Pasangan Batu M3 917.39 1,340,512.88 1,229,767,987.76 15.329 550.43 9.197 366.95 6.13 917.39 15.33 1,229,767,987.758 1.00
7.16.(3).a Pipa Drainase PVC diameter 60 mm M' 136.00 28,750.00 3,910,000.00 0.049 89.26 0.032 46.74 0.02 136.00 0.05 3,910,000.000 1.00
Jumlah Harga Perkiraan Divisi 8. 7,637,331,185.95 95.200 88.102 7.10 95.20 7,637,331,185.953
1
1 23 Juni 2022 30 Juni 2022 8 2
2 01 Juli 2022 07 Juli 2022 7
3 08 Juli 2022 14 Juli 2022 7
4 15 Juli 2022 21 Juli 2022 7
5 22 Juli 2022 31 Juli 2022 10
6 01 Agustus 2022 07 Agustus 2022 7
7 08 Agustus 2022 14 Agustus 2022 7
8 15 Agustus 2022 21 Agustus 2022 7
9 22 Agustus 2022 31 Agustus 2022 10
10 01 September 2022 07 September 2022 7
11 08 September 2022 14 September 2022 7
12 15 September 2022 21 September 2022 7
13 22 September 2022 30 September 2022 9
14 01 Oktober 2022 07 Oktober 2022 7
15 08 Oktober 2022 14 Oktober 2022 7
16 15 Oktober 2022 21 Oktober 2022 7
17 22 Oktober 2022 30 Oktober 2022 9
18 31 Oktober 2022 06 November 2022 7
19 07 November 2022 13 November 2022 7
20 14 November 2022 20 November 2022 7
21 21 November 2022 29 November 2022 9
22 30 November 2022 06 Desember 2022 7
23 07 Desember 2022 13 Desember 2022 7
24 14 Desember 2022 18 Desember 2022 5
19 Desember 2022 25 Desember 2022 7
26 Desember 2022 01 Januari 2023 7
02 Januari 2023 08 Januari 2023 7
09 Januari 2023 15 Januari 2023 7
16 Januari 2023 22 Januari 2023 7
23 Januari 2023 29 Januari 2023 7
30 Januari 2023 06 Februari 2023 8
50
179
23 Juni 2022 01 Juli 2022 08 Juli 2022 15 Juli 2022 22 Juli 2022 01 Agustus 2022
30 Juni 2022 07 Juli 2022 14 Juli 2022 21 Juli 2022 31 Juli 2022 07 Agustus 2022
23 Juni 2022 01 Agustus 2022 01 September 2022 01 Oktober 2022 31 Oktober 2022 30 November 2022
31 Juli 2022 31 Agustus 2022 30 September 2022 30 Oktober 2022 29 November 2022 18 Desember 2022
08 Agustus 2022 15 Agustus 2022 22 Agustus 2022 01 September 2022 08 September 2022
14 Agustus 2022 21 Agustus 2022 31 Agustus 2022 07 September 2022 14 September 2022
19 Desember 2022
30 Desember 2022
15 September 2022 22 September 2022 01 Oktober 2022 08 Oktober 2022 15 Oktober 2022
21 September 2022 30 September 2022 07 Oktober 2022 14 Oktober 2022 21 Oktober 2022
22 Oktober 2022 31 Oktober 2022 07 November 2022 14 November 2022 21 November 2022
30 Oktober 2022 06 November 2022 13 November 2022 20 November 2022 29 November 2022
30 November 2022 07 Desember 2022 14 Desember 2022 19 Desember 2022
06 Desember 2022 13 Desember 2022 18 Desember 2022 30 Desember 2022
No. Rincian Jumlah
1 Topi pelindung (Safety Helmet) Kunig 20 Bh
Putih 10 Bh
2 Pelindung mata (Goggles, Spectacles) 10 Bh
3 Pelindung pernafasan dan mulut (masker, masker respirator) 20 Bh
4 Sarung tangan (Safety Gloves) 20 Bh
5 Sepatu keselamatan (Safety Shoes, rubber safety shoes and toe cap) 20 Bh
6 Rompi keselamatan (Safety Vest) Merah 20 Bh
Hijau 10 Bh
7 Peralatan P3K 1 Bh
8 Rambu petunjuk 4 Bh
9 Rambu larangan 4 Bh
10 Rambu peringatan 4 Bh
11 Rambu informasi 4 Bh
12 Bendera K3 1 Bh
BACK UP DATA QUANTITY
PEKERJAAN : KONTRAKTOR PELAKSANA CV. TRI SETYA NOVALIA
KONSULTAN PENGAWAS
ITEM PEKERJAAN VOL. KONTRAK VOL. CCO SELISIH
Pembangunan Jembatan Talapao, Ruas Keliling Makian (Lanjutan)
PEKERJAAN STRUKTUR Pasangan Batu 37.50 337.50 300.00
URAIAN
Dimensi
NO SKETSA Lebar
Uraian Type Tebal / Volume Ket.
Panjang Luas
Galian Biasa Atas Bawah Tinggi
URAIAN
Dimensi
NO SKETSA Lebar
Uraian Type Tebal / Volume Ket.
Panjang Luas
Timbunan Biasa dari sumber galian Atas Bawah Tinggi
URAIAN
Dimensi
NO SKETSA Lebar
Uraian Type Tebal / Volume Ket.
Panjang Luas
Pasangan Batu Atas Bawah Tinggi
(A) Jumlah Harga Pekerjaan ( termasuk Biaya Umum dan Keuntungan ) #REF!
Terbilang : Delapan Milyar Sembilan Ratus Empat Juta Delapan Ratus Tujuh Puluh Empat Ribu Sembilan Ratus Delapan
ZAINUDIN, ST
DJAFAR ISMAIL,
NIP : 197611062010 01 SE. ST
1 005
NIP : 19620727 199703 1 002
DAFTAR KUANTITAS DAN HARGA
SPESIFIKASI TAHUN 2018 REVISI 2
DIVISI 1. UMUM
1.2 Mobilisasi
1.2 Mobilisasi LS 1.00 929,712,540.99 929,712,540.99
Jumlah Harga Pekerjaan DIVISI 1 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 929,712,540.99
Biaya protokol kesehatan wabah menular (misal: tempat cuci tangan, swab,
2.6.(4) Ls 1.00 1,500,000.00 1,500,000.00
vitamin di masa pandemi covid-19)
Jumlah Harga Pekerjaan DIVISI 2 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 58,170,125.86
DIVISI 4. PEKERJAAN TANAH DAN GEOSINTETIK
4.1.(1) Galian Biasa M3 37.50 #REF! #REF!
3.1.(4) Galian Struktur dengan kedalaman 0 - 2 meter M3 67.54 123,394.60 8,334,071.25
4.2.(2a) Timbunan Pilihan dari sumber galian M3 196.53 402,785.74 79,159,481.81
Jumlah Harga Perkiraan Divisi 4. (Masuk Pada Rekapitulasi Perkiraan Harga Pekerjaan) #REF!
DIVISI 8. STRUKTUR
Jumlah Harga Perkiraan Divisi 8. (Masuk Pada Rekapitulasi Perkiraan Harga Pekerjaan) #REF!
Jumlah Harga Perkiraan Divisi 10. (Masuk Pada Rekapitulasi Perkiraan Harga Pekerjaan) #REF!
HARGA DASAR SATUAN UPAH
BIAYA SEWA
KODE
No. URAIAN HP KAPASITAS HARGA ALAT ALAT/JAM KET
ALAT
(DILUAR PPN)
Bahan : Semen
BIAYA
NO URAIAN Jumlah Kombinasi (RP)
RP/SATUAN JUMLAH (RP)
Rp/Zak 6,842.06
Total Jumlah
Rp/Kg 136.84
Bahan : Aspal
BIAYA
NO URAIAN Jumlah Kombinasi (RP)
RP/SATUAN JUMLAH (RP)
Rp/Kg 20,083.75
Total Jumlah
Rp/Kg 0.00
BIAYA
NO URAIAN Jumlah Kombinasi (RP)
RP/SATUAN JUMLAH (RP)
Rp/Kg 115.25
Total Jumlah
Rp/Kg
BIAYA
NO URAIAN Jumlah Kombinasi (RP)
RP/SATUAN JUMLAH (RP)
Rp/Kg 171.75
Total Jumlah
Rp/Kg
BIAYA
NO URAIAN Jumlah Kombinasi (RP)
RP/SATUAN JUMLAH (RP)
BIAYA
NO URAIAN Jumlah Kombinasi (RP)
RP/SATUAN JUMLAH (RP)
BIAYA
NO URAIAN Jumlah Kombinasi (RP)
RP/SATUAN JUMLAH (RP)
Catatan : Harga Royalty sudah ditambah biaya retribusi sebesar Rp. 300,-/m3
ANALISA HARGA DASAR SATUAN BAHAN
HARGA SATUAN
No. URAIAN KODE KOEFISIEN SATUAN
(RP)
I. ASUMSI
1 Menggunakan alat berat
2 Kondisi Jalan : baik
3 Jarak Quarry ke lokasi Base Camp L 3.00 Km
4 Harga satuan pasir di Quarry RpM01 1.00 M3 336,000.00
5 Harga Satuan Dasar Excavator RpE10 1.00 Jam 659,258.23
6 Harga Satuan Dasar Dump Truck RpE09 1.00 Jam 678,244.85
7 Berat volume pasir Bil 1.42 ton/m3
III. PERHITUNGAN
EXCAVATOR (E10)
Kapasitas Bucket V 0.93 M3
Faktor Bucket Fb 0.90 -
Faktor Efisiensi alat Fa 0.83 -
Waktu siklus Ts1
- Menggali / memuat T1 0.50 menit
- Lain-lain T2 0.50 menit
Ts1 1.00 menit
Kap. Prod. / jam =
V x Fb x Fa x 60 Q1 41.68 M3 / Jam
Ts1
Biaya Excavator / M3 = (1 : Q1) x RpE10 Rp1 15,816.15 Rupiah
DUMP TRUCK (E09)
Kapasitas bak V 10.00 ton
Faktor efisiensi alat Fa 0.83 -
Kecepatan rata-rata bermuatan v1 30.00 KM/Jam
Kecepatan rata-rata kosong v2 40.00 KM/Jam
Waktu siklus Ts2
- Muat = (V x 60)/Q1 x Bil) T1 10.14 menit
- Waktu tempuh isi = (L/v1) x 60 T2 6.00 menit
- Waktu tempuh kosong = (L/v2) x 60 T3 4.50 menit
- Lain-lain T4 1.00 menit
Ts2 21.64 menit
Kapasitas Produksi / Jam =
V x Fa x 60 Q2 16.21 M3 / Jam
Ts2 x Bil
Biaya Dump Truck / M3 = (1 : Q2) x RpE08 Rp2 41,844.84 Rupiah
HARGA SATUAN
No. URAIAN KODE KOEFISIEN SATUAN
(RP)
I. ASUMSI
1 Menggunakan alat berat
2 Kondisi Jalan : baik
3 Jarak Quarry ke Lokasi Pekerjaan L 3.00 Km
4 Harga satuan batu kali di Quarry RpM02 1.00 M3 350,000.00
5 Harga Satuan Dasar Excavator RpE10 1.00 Jam 659,258.23
6 Harga Satuan Dasar Dump Truck RpE09 1.00 Jam 678,244.85
7 Berat volume batu kali Bil 1.44 ton/m3
III. PERHITUNGAN
EXCAVATOR (E10)
Kapasitas Bucket V 0.93 M3
Faktor Bucket Fb 0.90 -
Faktor Efisiensi alat Fa 0.83 -
Waktu siklus Ts1
- Menggali / memuat T1 0.50 menit
- Lain-lain T2 0.50 menit
Ts1 1.00 menit
Kap. Prod. / jam =
V x Fb x Fa x 60 Q1 41.6826 M3 / Jam
Ts1
Biaya Excavator / M3 = (1 : Q1) x RpE10 Rp1 15,816.15 Rupiah
DUMP TRUCK (E09)
Kapasitas bak V 10.00 ton
Faktor efisiensi alat Fa 0.83 -
Kecepatan rata-rata bermuatan v1 30.00 KM/Jam
Kecepatan rata-rata kosong v2 40.00 KM/Jam
Waktu siklus Ts2
- Muat = (V x 60)/(Q1 x Bil) T1 10.00 menit
- Waktu tempuh isi = (L/v1) x 60 T2 6.00 menit
- Waktu tempuh kosong = (L/v2) x 60 T3 4.50 menit
- Lain-lain T4 1.00 menit
Ts2 21.50 menit
Kapasitas Produksi / Jam =
V x Fa x 60 Q2 16.09 M3 / Jam
Ts2 x Bil
Biaya Dump Truck / M3 = (1 : Q2) x RpE08 Rp2 42,158.09 Rupiah
HARGA SATUAN
No. URAIAN KODE KOEFISIEN SATUAN
(RP)
I. ASUMSI
1 Menggunakan alat berat
2 Kondisi Jalan : baik
3 Jarak Quarry ke Lokasi Pekerjaan L 3.00 Km
4 Harga satuan batu kali di Quarry RpM06 1.00 M3 350,000.00
5 Harga Satuan Dasar Excavator RpE10 1.00 Jam 659,258.23
6 Harga Satuan Dasar Dump Truck RpE09 1.00 Jam 678,244.85
7 Harga Satuan Dasar Wheel Loader RpE15 1.00 Jam 607,256.87
8 Harga Satuan Upah Pekerja RpL01 1.00 Jam 14,285.71
9 Berat volume batu belah Bil 1.60 ton/m3
III. PERHITUNGAN
EXCAVATOR (E10)
Kapasitas Bucket V 0.93 M3
Faktor Bucket Fb 0.90 -
Faktor Efisiensi alat Fa 0.83 -
Waktu siklus Ts1
- Menggali / memuat T1 0.50 menit
- Lain-lain T2 0.50 menit
Ts1 1.00 menit
Kap. Prod. / jam =
V x Fb x Fa x 60 Q1 41.6826 M3 / Jam
Ts1
Biaya Excavator / M3 = (1 : Q1) x RpE10 Rp1 15,816.15 Rupiah
3.d PEKERJA
Produksi menentukan : Excavator Q1 41.6826 M3 / Jam
Hasil galian batu / hari = Q1 x 7 Jam Qt 291.7782 M3 / 7 jam
Kebutuhan Pekerja P 10.00 Orang
Biaya Pekerja / M3 =
{ (7 Jam x P) : Qt } x RpL01 Rp4 3,427.26 Rupiah
HARGA SATUAN
No. URAIAN KODE KOEFISIEN SATUAN
(RP)
I. ASUMSI
1 Menggunakan alat berat
2 Kondisi Jalan : baik
3 Jarak Quarry ke Lokasi Pekerjaan L 3.00 Km
4 Harga satuan Gravel di Quarry RpM07 1.00 M3 350,000.00
5 Harga Satuan Dasar Excavator RpE10 1.00 Jam 659,258.23
6 Harga Satuan Dasar Dump Truck RpE09 1.00 Jam 678,244.85
7 Berat volume gravel Bil 2.20 ton/m3
III. PERHITUNGAN
EXCAVATOR (E10)
Kapasitas Bucket V 0.93 M3
Faktor Bucket Fb 0.90 -
Faktor Efisiensi alat Fa 0.83 -
Waktu siklus Ts1
- Menggali / memuat T1 0.75 menit
- Lain-lain T2 0.50 menit
Ts1 1.25 menit
Kap. Prod. / jam =
V x Fb x Fa x 60 Q1 33.34608 M3 / Jam
Ts1
Biaya Excavator / M3 = (1 : Q1) x RpE10 Rp1 19,770.19 Rupiah
DUMP TRUCK (E09)
Kapasitas bak V 10.00 ton
Faktor efisiensi alat Fa 0.83 -
Kecepatan rata-rata bermuatan v1 30.00 KM/Jam
Kecepatan rata-rata kosong v2 40.00 KM/Jam
Waktu siklus Ts2
- Muat = (V x 60)/(Q1 x Bil) T1 8.18 menit
- Waktu tempuh isi = (L/v1) x 60 T2 6.00 menit
- Waktu tempuh kosong = (L/v2) x 60 T3 4.50 menit
- Lain-lain T4 1.00 menit
Ts2 19.68 menit
Kapasitas Produksi / Jam =
V x Fa x 60 Q2 11.50 M3 / Jam
Ts2 x Bil
Biaya Dump Truck / M3 = (1 : Q2) x RpE08 Rp2 58,962.52 Rupiah
HARGA SATUAN
No. URAIAN KODE KOEFISIEN SATUAN
(RP)
I. ASUMSI
1 Menggunakan alat berat
2 Kondisi Jalan : baik
3 Jarak Quarry ke lokasi Base Camp L 15.00 Km
4 Harga satuan Sirtu di Quarry RpM16 1.00 M3 301,000.00
5 Harga Satuan Dasar Excavator RpE10 1.00 Jam 659,258.23
6 Harga Satuan Dasar Dump Truck RpE09 1.00 Jam 678,244.85
7 Berat volume sirtu Bil 1.51 ton/m3
III. PERHITUNGAN
EXCAVATOR (E10)
Kapasitas Bucket V 0.93 M3
Faktor Bucket Fb 0.90 -
Faktor Efisiensi alat Fa 0.83 -
Waktu siklus Ts1
- Menggali / memuat T1 0.50 menit
- Lain-lain T2 0.50 menit
Ts1 1.00 menit
Kap. Prod. / jam =
V x Fb x Fa x 60 Q1 41.6826 M3 / Jam
Ts1
Biaya Excavator / M3 = (1 : Q1) x RpE10 Rp1 15,816.15 Rupiah
DUMP TRUCK (E09)
Kapasitas bak V 10.00 ton
Faktor efisiensi alat Fa 0.83 -
Kecepatan rata-rata bermuatan v1 30.00 KM/Jam
Kecepatan rata-rata kosong v2 40.00 KM/Jam
Waktu siklus Ts2
- Muat = (V x 60)/(Q1 x Bil) T1 9.53 menit
- Waktu tempuh isi = (L/v1) x 60 T2 30.00 menit
- Waktu tempuh kosong = (L/v2) x 60 T3 22.50 menit
- Lain-lain T4 1.00 menit
Ts2 63.03 menit
Kapasitas Produksi / Jam =
V x Fa x 60 Q2 5.23 M3 / Jam
Ts2 x Bil
Biaya Dump Truck / M3 = (1 : Q2) x RpE08 Rp2 129,628.52 Rupiah
HARGA SATUAN
No. URAIAN KODE KOEFISIEN SATUAN
(RP)
I. ASUMSI
1 Menggunakan alat berat
2 Kondisi Jalan : baik
3 Jarak Quarry ke lokasi pekerjaan L 3.00 Km
4 Harga satuan pasir urug di Quarry RpM44 1.00 M3 406,000.00
5 Harga Satuan Dasar Excavator RpE10 1.00 Jam 659,258.23
6 Harga Satuan Dasar Dump Truck RpE09 1.00 Jam 678,244.85
7 Berat volume pasir urug Bil 1.42 ton/m3
III. PERHITUNGAN
EXCAVATOR (E10)
Kapasitas Bucket V 0.93 M3
Faktor Bucket Fb 0.90 -
Faktor Efisiensi alat Fa 0.83 -
Waktu siklus Ts1
- Menggali / memuat T1 0.50 menit
- Lain-lain T2 0.50 menit
Ts1 1.00 menit
Kap. Prod. / jam =
V x Fb x Fa x 60 Q1 41.6826 M3 / Jam
Ts1
Biaya Excavator / M3 = (1 : Q1) x RpE10 Rp1 15,816.15 Rupiah
DUMP TRUCK (E09)
Kapasitas bak V 10.00 ton
Faktor efisiensi alat Fa 0.83 -
Kecepatan rata-rata bermuatan v1 30.00 KM/Jam
Kecepatan rata-rata kosong v2 40.00 KM/Jam
Waktu siklus Ts2
- Muat = (V x 60)/(Q1 x Bil) T1 10.14 menit
- Waktu tempuh isi = (L/v1) x 60 T2 6.00 menit
- Waktu tempuh kosong = (L/v2) x 60 T3 4.50 menit
- Lain-lain T4 1.00 menit
Ts2 21.64 menit
Kapasitas Produksi / Jam =
V x Fa x 60 Q2 16.21 M3 / Jam
Ts2 x Bil
HARGA SATUAN
No. URAIAN KODE KOEFISIEN SATUAN
(RP)
I. ASUMSI
1 Menggunakan alat berat
2 Kondisi Jalan : baik
3 Jarak Quarry ke lokasi pekerjaan L 15.00 Km
4 Harga satuan pasir urug di Quarry RpM44 1.00 M3 336,000.00
5 Harga Satuan Dasar Excavator RpE10 1.00 Jam 659,258.23
6 Harga Satuan Dasar Dump Truck RpE09 1.00 Jam 678,244.85
7 Berat isi volume pasir beton Bil 1.69 ton/m3
III. PERHITUNGAN
EXCAVATOR (E10)
Kapasitas Bucket V 0.50 M3
Faktor Bucket Fb 0.90 -
Faktor Efisiensi alat Fa 0.83 -
Waktu siklus Ts1
- Menggali / memuat T1 0.50 menit
- Lain-lain T2 0.50 menit
Ts1 1.00 menit
Kap. Prod. / jam =
V x Fb x Fa x 60 Q1 22.41 M3 / Jam
Ts1
Biaya Excavator / M3 = (1 : Q1) x RpE10 Rp1 29,418.04 Rupiah
DUMP TRUCK (E09)
Kapasitas bak V 10.00 ton
Faktor efisiensi alat Fa 0.83 -
Kecepatan rata-rata bermuatan v1 30.00 KM/Jam
Kecepatan rata-rata kosong v2 40.00 KM/Jam
Waktu siklus Ts2
- Muat = (V x 60)/(Q1 x Bil) T1 15.84 menit
- Waktu tempuh isi = (L/v1) x 60 T1 30.00 menit
- Waktu tempuh kosong = (L/v2) x 60 T2 22.50 menit
- Lain-lain T4 1.00 menit
Ts2 69.34 menit
Kapasitas Produksi / Jam =
V x Fa x 60 Q2 4.25 M3 / Jam
Ts2 x Bil
Biaya Dump Truck / M3 = (1 : Q2) x RpE08 Rp2 159,603.76 Rupiah
JUMLAH
HARGA
No. URAIAN SATUAN VOL. HARGA
SATUAN (RP)
(RP)
B. PERALATAN
Periksa lembar 1.2-2 695,000,000.00
3 Bituminous Testing
Marshall Asphalt Test Set - - -
Extraction Test, Centrifuge/Refflux Method Set - - -
Specific Gravity for Coarse Aggregate Set - - -
Specific Gravity for Fine Aggregate Set - - -
Mix Air Viod Content (Accurate Method) Set - - -
Core Drill Set - 1,500,000.00 -
Metal Thermometer Set - - -
Accessories and Tolls Set - - -
Penetration Test Set - - -
Softening Point Set - - -
Refusal Density Compactor Set - - -
4 Concrete Testing
Slump Cone Set - 500,000.00 -
Cylinder/Cube Mould for Compressive Strength Set - 500,000.00 -
Beam Mould for Flexural Strength (RIGID) Set - - -
Crushing Machine Set - - -
E. MOBILISASI LAINNYA
E.I. Pekerjaan Darurat LS - - -
1 Perkuatan Jembatan Lama
2 Pemeliharaan Jalan Kerja / Samping
3 ...................... ....
4 ...................... ....
5 ...................... ....
6 ...................... ....
E.II. Lain-lain
1 Komunikasi Lapangan Lengkap Ls 1.00 - -
2 Survey Detail / Survey Awal Ls 1.00 - -
3 As Build Drawing Ls 1.00 - -
4 Papan Proyek Set 1.00 1,000,000.00 1,000,000.00
5 Sewa Kendaraan Bulan 7.00 - -
6 Pengawasan Ls 1.00 - -
Catatan : Jumlah yang tercantum pada masing-masing item mobilisasi di atas sudah termasuk over-head dan laba serta seluruh pajak dan bea (kecuali
PPn), dan pengeluaran lainnya.
ITEM PEMBAYARAN NO. : 1.2
JENIS PEKERJAAN : MOBILISASI Lembar 1.2-2
B. PERALATAN
1 ASPHALT MIXING PLANT E01 Unit - 37,000,000.00 -
2 ASPHALT FINISHER E02 Unit - 3,500,000.00 -
3 ASPHALT SPRAYER E03 Unit - 2,000,000.00 -
4 COMPRESSOR 4000-6500 L\M E05 Unit 1.00 1,500,000.00 1,500,000.00
5 CONCRETE MIXER 0.3-0.6 M3 E06 Unit - 1,000,000.00 -
6 DUMP TRUCK 3.5 TON E08 Unit 1.00 1,500,000.00 1,500,000.00
7 DUMP TRUCK 10 TON E09 Unit - 2,500,000.00 -
8 EXCAVATOR 80-140 HP E10 Unit 1.00 5,000,000.00 5,000,000.00
9 GENERATOR SET E12 Unit 1.00 1,500,000.00 1,500,000.00
10 MOTOR GRADER >100 HP E13 Unit - 4,000,000.00 -
11 WHEEL LOADER 1.0-1.6 M3 E15 Unit - 4,000,000.00 -
12 TANDEM ROLLER 6-8 T. E17 Unit - 4,000,000.00 -
13 TIRE ROLLER 8-10 T. E18 Unit - 4,000,000.00 -
14 VIBRATORY ROLLER 5-8 T. E19 Unit - 4,000,000.00 -
15 CONCRETE VIBRATOR E20 Unit - 500,000.00 -
16 WATER PUMP 70-100 mm E22 Unit - 1,000,000.00 -
17 WATER TANKER 3000-4500 L. E23 Unit - 1,500,000.00 -
18 TRUK MIXER (AGITATOR) E49 Unit - 2,000,000.00 -
19 TRONTON Unit 1.00 30,000,000.00 30,000,000.00
20 EKSPEDISI KONTAINER Unit 6.00 23,000,000.00 138,000,000.00
21 LANDING CRAFT TANK (LCT) Trip 3.00 172,500,000.00 517,500,000.00
A. TENAGA
B. BAHAN
C. PERALATAN
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
ITEM PEMBAYARAN NO. : 3.1.(1)
JENIS PEKERJAAN : Galian untuk Selokan Drainase dan Saluran Air
SATUAN PEMBAYARAN : M3
URAIAN ANALISA HARGA SATUAN
I ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan : baik
4 Jam kerja efektif per-hari Tk 7.00 jam
5 Faktor pengembangan bahan Fk 1.20 -
6 Berat volume bahan D 1.60 Ton/M3
II URUTAN KERJA
1 Penggalian dilakukan dengan menggunakan Excavator
2 Selanjutnya Excavator menuangkan material hasil
galian kedalam Dump Truck
3 Dump Truck membuang material hasil galian keluar
lokasi jalan sejauh L 1.50 Km
4 Sekelompok pekerja akan merapikan hasil galian
2 ALAT
2.a EXCAVATOR (E10)
Kapasitas Bucket V 0.93 M3
Faktor Bucket Fb 1.00 -
Faktor Efisiensi alat Fa 0.83 -
Faktor Konversi
Waktu siklus = T1 + T2 Ts1 0.70 menit masuk dalam
- Menggali, memuat dan berputar T1 0.50 menit waktu siklus
- Lain lain T2 0.20 menit disesuaikan dgn
Kap. Prod. / jam = V x Fb x Fa x 60 x Fk Q1 79.40 M3 lapangan
Ts1
Koefisien Alat / M3 = 1 : Q1 - 0.01 Jam
2.b DUMP TRUCK (3,5 Ton) (E08)
Kapasitas bak V 3.50 ton
Faktor efisiensi alat Fa 0.83 -
Kecepatan rata-rata bermuatan v1 20.00 Km/Jam
Kecepatan rata-rata kosong v2 30.00 Km/Jam
Waktu siklus : Ts2
- Muat = (V x 60)/ D x Q1 T1 1.65 menit
- Waktu tempuh isi = (L : v1) x 60 T2 4.50 menit
- Waktu tempuh kosong = (L : v2) x 60 T3 3.00 menit
- Lain-lain T4 1.00 menit
10.15 menit
3 TENAGA
Produksi menentukan : EXCAVATOR Q1 79.40 M3/Jam
Produksi Galian / hari = Tk x Q1 Qt 555.77 M3
Kebutuhan tenaga :
- Pekerja P 3.00 orang
- Mandor M 1.00 orang
Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.04 Jam
- Mandor = (Tk x M) : Qt (L03) 0.01 Jam
A. TENAGA
B. BAHAN
C. PERALATAN
I ASUMSI
1 Menggunakan alat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar (batu, pasir dan semen) diterima
seluruhnya di lokasi pekerjaan
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 7.00 KM
5 Jam kerja efektif per-hari Tk 7.00 jam
6 Perbandingan Pasir & Semen : - Volume Semen Sm 20.00 % Kuat Tekan min.
: - Volume Pasir Ps 80.00 % 50 kg/cm2
7 Perbandingan Batu & Mortar :
- Batu Bt 60.00 %
- Mortar (campuran semen & pasir) Mr 40.00 %
8 Berat Jenis Bahan :
- Pasangan Batu Dengan Mortar D1 2.40 ton/M3
- Batu D2 1.60 ton/M3
- Adukan (mortar) D3 1.80 ton/M3
- Pasir D4 1.67 ton/M3
- Semen Portland D5 1.44 ton/M3
II URUTAN KERJA
1 Semen, pasir dan air dicampur dan diaduk menjadi
mortar dengan menggunakan alat bantu
2 Batu dibersihkan dan dibasahi seluruh permukaannya
sebelum dipasang
3 Penyelesaian dan perapihan setelah pemasangan
3 TENAGA
Produksi Pas. Batu yang menentukan ( Prod. C. Mixer ) Q1 3.11 M3/Jam
Produksi Pasangan Batu dalam 1 hari = Tk x Q1 Qt 21.79 M3
Kebutuhan tenaga : - Mandor M 1.00 orang
- Tukang Batu Tb 3.00 orang
- Pekerja P 5.00 orang
Koefisien Tenaga / M3 :
- Mandor = (Tk x M) : Qt (L03) 0.32 jam
- Tukang = (Tk x Tb) : Qt (L02) 0.96 jam
- Pekerja = (Tk x P) : Qt (L01) 1.61 jam
A. TENAGA
B. BAHAN
C. PERALATAN
I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan : baik
4 Jam kerja efektif per-hari Tk 7.00 Jam
5 Faktor pengembangan bahan Fk 1.20 -
6 Berat volume tanah (lepas) D 1.60 ton/m3 1.40 - 1.80
3. TENAGA
Produksi menentukan : EXCAVATOR Q1 32.69 M3/Jam
Produksi Galian / hari = Tk x Q1 Qt 228.85 M3
Kebutuhan tenaga :
- Pekerja P 4.00 orang
- Mandor M 1.00 orang
Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.12 Jam
- Mandor = (Tk x M) : Qt (L03) 0.03 Jam
A. TENAGA
B. BAHAN
C. PERALATAN
I. ASUMSI
1 Pekerjaan dilakukan secara manual
2 Lokasi pekerjaan : sekitar jembatan
3 Kondisi Jalan : baik
4 Jam kerja efektif per-hari Tk 7.00 Jam
5 Faktor pengembangan bahan Fk 1.20 -
7 Pengurugan kembali (backfill) untuk struktur Uk 30.00 %/M3
3. TENAGA
Produksi menentukan : EXCAVATOR Q1 51.46 M3/Jam
Produksi Galian / hari = Tk x Q1 Qt 360.22 M3
Kebutuhan tenaga :
- Pekerja P 4.00 orang
- Mandor M 1.00 orang
Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.08 Jam
- Mandor = (Tk x M) : Qt (L03) 0.02 Jam
A. TENAGA
B. BAHAN
C. PERALATAN
I. ASUMSI
1 Pekerjaan dilakukan secara manual
2 Lokasi pekerjaan : sekitar jembatan
3 Kondisi Jalan : baik
4 Jam kerja efektif per-hari Tk 7.00 Jam
5 Faktor pengembangan bahan Fk 1.20 -
6 Pengurugan kembali (backfill) untuk struktur Uk 30.00 %/M3
7 Faktor pembayaran Fp 1.50 1.5 - 2
3. TENAGA
Produksi menentukan : EXCAVATOR Q1 46.31 M3/Jam
Produksi Galian / hari = Tk x Q1 Qt 324.20 M3
Kebutuhan tenaga :
- Pekerja P 4.00 orang
- Mandor M 1.00 orang
Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.09 Jam
- Mandor = (Tk x M) : Qt (L03) 0.02 Jam
A. TENAGA
B. BAHAN
C. PERALATAN
I. ASUMSI
1 Pekerjaan dilakukan secara mekanis
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan : baik
4 Jam kerja efektif per-hari Tk 7.00 Jam
5 Faktor pengembangan bahan Fk 1.20 -
6 Faktor pengembangan bahan (padat ke asli) Fv 1.05 -
7 Tebal hamparan padat t 0.20 M
8 Berat volume bahan (lepas) D 1.60 Ton/M3
2. ALAT
2.a. WHEEL LOADER (E15)
Kapasitas Bucket V 1.50 M3
Faktor Bucket Fb 0.85 -
Faktor Efisiensi Alat Fa 0.83 -
Waktu sklus Ts1
- Muat T1 1.00 menit
Ts1 1.00 menit
Kapasitas Produksi / Jam = V x Fb x Fa x 60 Q1 52.91 M3
Fk x Ts1
Koefisienalat / M3 = = 1 : Q1 (E15) 0.0189 Jam
2.b. DUMP TRUCK 3,5 Ton (E08)
Kapasitas bak V 3.50 M3
Faktor efisiensi alat Fa 0.83 -
Faktor Konversi asli ke lepas Fv2 1.25
Kecepatan rata-rata bermuatan v1 20.00 Km / Jam
Kecepatan rata-rata kosong v2 30.00 Km / Jam
Waktusiklus : Ts2
- Waktu muat = = (V x 60)/(D x Fk x Q1) T1 2.07 menit
- Waktu tempuh isi = (L : v1) x 60 T2 9.00 menit
- Waktu tempuh kosong = (L : v2) x 60 T3 6.00 menit
- Lain-lain T4 0.50 menit
Ts2 17.57 menit
Kapasitas Produksi / Jam = V x Fa x 60 Q2 4.96 M3
D x Fv2 x Ts2
Koefisien Alat / m3 = 1 : Q2 (E08) 0.20 Jam
3. TENAGA
Produksi menentukan : DUMP TRUCK Q1 4.96 M3/Jam
Produksi Timbunan / hari = Tk x Q1 Qt 34.73 M3
Kebutuhan tenaga :
- Pekerja P 4.00 orang
- Mandor M 1.00 orang
Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.81 Jam
- Mandor = (Tk x M) : Qt (L03) 0.20 Jam
A. TENAGA
B. BAHAN
C. PERALATAN
I. ASUMSI
1 Pekerjaan dilaksanakan hanya pada tanah galian
2 Pekerjaan dilakukan secara mekanis
3 Lokasi pekerjaan : sepanjang jalan
4 Kondisi Jalan : jelek / belum padat
5 Jam kerja efektif per-hari Tk 7.00 Jam
2. ALAT
2.a. MOTOR GRADER (E13)
Panjang operasi grader sekali jalan Lh 50.00 M
Lebar Efektif kerja Blade b 2.60 M
Lebae overlap bo 0.30
Faktor Efisiensi Alat Fa 0.80 -
Kecepatan rata-rata alat v 4.00 Km / Jam
Jumlah lintasan n 8.00 lintasan
Jumlah lajur lintasan N 2.00 lajur
Waktu siklus Ts1
- Perataan 1 kali lintasan = Lh : (v x 1000) x 60 T1 0.75 menit
- Lain-lain T2 2.00 menit
Ts1 2.75 menit
Kapasitas Produksi / Jam = Lh x (N(b-bo)+bo) x Fa x 60 Q1 534.55 M2
n x Ts1
Koefisien Alat / m2 = 1 : Q1 (E13) 0.0019 Jam
2.b. VIBRATOR ROLLER (E19)
Kecepatan rata-rata alat v 4.00 Km / jam
Lebar Area pemadatan W 3.50 M
Lebar efektif pemadatan b 1.48 M
Jumlah lintasan n 6.00 lintasan
Lajur lintasan = w/(b-bo) N 3.00
Lebar Overlap bo 0.30 M
Faktor efisiensi alat Fa 0.83 -
nxN
Koefisien Alat / m2 = 1 : Q2 (E19) 0.0244 Jam
3. TENAGA
Produksi menentukan : MOTOR GRADER Q1 534.55 M2/Jam
Produksi Pekerjaan / hari = Tk x Q1 Qt 3,741.82 M2
Kebutuhan tenaga :
- Pekerja P 4.00 orang
- Mandor M 1.00 orang
Koefisien tenaga / M2
- Pekerja = (Tk x P) : Qt (L01) 0.0075 Jam
- Mandor = (Tk x M) : Qt (L02) 0.0019 Jam
A. TENAGA
B. BAHAN
C. PERALATAN
I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi existing jalan : sedang
4 Jarak rata-rata Base Camp ke lokasi pekerjaan L 7.000 KM
5 Tebal lapis agregat padat t 0.12 M
6 Berat isi padat Bip 1.810 -
7 Jam kerja efektif per-hari Tk 7.000 jam
8 Proporsi Campuran : - Agregat Pecah Mesin 20 - 30 mm 20-30 28.000 % Gradasi harus
- Agregat Pecah Mesin 5 - 10 & 10 - 20 mm 5-10&10-20 42.000 % memenuhi Spec.
- Fraksi lolos Scalping Screen 0 - 5 mm PU 30.000 %
9 Berat Isi Agregat (lepas) Bil 1.510 ton/m3
Faktor kehilangan - Agregat A Fh1 1.050
2. ALAT
2.a. WHEEL LOADER (E15)
Kapasitas bucket V 1.500 M3 (lepas)
Faktor bucket Fb 0.850 - kondisi sedang
Faktor Efisiensi alat Fa 0.830 -
Waktu Siklus :
- Memuat dan lain-lain Ts1 0.500 menit panduan
Kap. Prod. / jam = V x Fb x Fa x 60 Q1 105.942 M3
Ts1 x Bip/Bil
Koefisien Alat / M3 = 1 : Q1 (E15) 0.009 jam
2.b. DUMP TRUCK (E08)
Kapasitas bak V 3.500 ton
Faktor Efisiensi alat Fa 0.830 -
Kecepatan rata-rata bermuatan v1 20.000 KM/jam
Kecepatan rata-rata kosong v2 30.000 KM/jam
Waktu Siklus :
- Waktu memuat = V x 60/Q1 x Bil T1 1.313 menit
- Waktu tempuh isi = (L : v1) x 60 menit T2 21.000 menit
- Waktu tempuh kosong = (L : v2) x 60 menit T3 14.000 menit
- lain-lain T4 1.000 menit
Ts2 37.313 menit
Kap. Prod. / jam = V x Fa x 60 Q2 2.581 M3
Ts2 x Bip
Koefisien Alat / M3 = 1 : Q2 (E08) 0.387 jam
3. TENAGA
Produksi menentukan : WHEEL LOADER Q1 105.942 M3/jam
Produksi agregat / hari = Tk x Q1 Qt 741.594 M3
Kebutuhan tenaga :
- Pekerja P 6.000 orang
- Mandor M 1.000 orang
Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.057 jam
- Mandor = (Tk x M) : Qt (L03) 0.009 jam
A. TENAGA
B. BAHAN
C. PERALATAN
I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi existing jalan : sedang
4 Jarak rata-rata Base Camp ke lokasi pekerjaan L 7.000 KM
5 Tebal lapis agregat padat t 0.15 M
6 Berat isi padat Bip 1.810
7 Jam kerja efektif per-hari Tk 7.000 jam
8 Proporsi Campuran : - Agregat Pecah Mesin 20 - 30 mm 20-30 18.000 % Gradasi harus
- Agregat Pecah Mesin 5 - 10 & 10 - 20 mm 5-10&10-20 22.000 % memenuhi
- Fraksi lolos Scalping Screen 0 - 5 mm St 60.000 % Spesifikasi
9 Berat volume agregat (lepas) Bil 1.510 ton/m3
Faktor kehilangan - Agregat Pecah Mesin 20 - 30 mm Fh1 1.050
Faktor kehilangan - Agregat Pecah Mesin 5 - 10 & 10 - 20 mm Fh2 1.050
Faktor kehilangan - Fraksi lolos Scalping Screen 0 - 5 mm Fh3 1.050
2. ALAT
2.a. WHEEL LOADER (E15)
Kapasitas bucket V 1.500 M3
Faktor bucket Fb 0.850 - lepas
Faktor Efisiensi alat Fa 0.830 - kondisi sedang
Waktu Siklus : Ts1
- Memuat dan lain-lain T1 0.500 menit panduan
Ts1 0.500 menit
Kap. Prod. / jam = V x Fb x Fa x 60 Q1 105.942 M3
Ts1 x Bip/Bil
Koefisien Alat / M3 = 1 : Q1 (E15) 0.009 jam
2.b. DUMP TRUCK (E08)
Kapasitas bak V 3.500 ton
Faktor Efisiensi alat Fa 0.830 -
Kecepatan rata-rata bermuatan v1 20.000 KM/jam
Kecepatan rata-rata kosong v2 30.000 KM/jam
Waktu Siklus :
- Waktu memuat = V x 60/Q1 x Bil T1 1.313 menit
- Waktu tempuh isi = (L : v1) x 60 menit T2 21.000 menit
- Waktu tempuh kosong = (L : v2) x 60 menit T3 14.000 menit
- dan lain-lain T4 1.000 menit
Ts2 37.313 menit
Kap. Prod. / jam = V x Fa x 60 Q2 2.581 M3
Ts2 x Bip
Koefisien Alat / M3 = 1 : Q2 - 0.387 jam
A. TENAGA
B. BAHAN
C. PERALATAN
I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Jarak rata-rata Base Camp ke lokasi pekerjaan L 7.00 KM
4 Jam kerja efektif per-hari Tk 7.00 Jam
5 Faktor kehilangan bahan Fh 1.03 -
6 Komposisi campuran :
- Aspal Pen 60 atau Pen 80 As 65.00 % terhadap volume
- Kerosene K 35.00 % terhadap volume
7 Berat isi bahan :
- Aspal Pen 60 atau Pen 80 D1 1.03 Kg / liter
- Kerosene D2 0.80 Kg / liter
8 Bahan dasar (aspal & minyak pencair) semuanya
diterima di lokasi pekerjaan
1. BAHAN
Untuk mendapatkan 1 liter Lapis Resap Pengikat
diperlukan : ( 1 liter x Fh ) PC 1.03 liter
1.a. Aspal = As x PC x D1 (M10) 0.69 Kg.
1.b. Kerosene = K x PC (M11) 0.36 Liter
2. ALAT
2.a. ASPHALT DISTRIBUTOR (E41)
Lebar penyemprotan b 4.50 M
Kecepatan penyemprotan V 30.00 m/menit Asumsi
Kapasitas pompa aspal pas 100.00 liter/menit Panduan
Faktor effisiensi kerja Fa 0.80
Kap. Prod. / jam = pas x Fa x 60 Q1 4,800.00 liter
Koefisien Alat / Ltr = 1 : Q1 (E41) 0.00021 Jam
A. TENAGA
B. BAHAN
C. PERALATAN
I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi existing jalan : sedang
4 Jarak rata-rata Base Camp ke lokasi pekerjaan L 7.00 KM
5 Tebal Lapis (HRS BASE) padat t 0.04 M
6 Jam kerja efektif per-hari Tk 7.00 Jam
7 Faktor kehilanganmaterial : - Agregat Fh1 1.05 -
- Aspal Fh2 1.03 -
8 Berat isi Agregat (padat) Bip 1.81 ton/m3
9 Berat Isi Agregat (lepas) Bil 1.51 ton/m3
10 Komposisi campuran HRS BASE :
- Agr Pch Mesin 5 - 10 & 10 - 15 mm 5-10&10-15 40.00 % Gradasi harus -
- Agregat Pecah Mesin 0 - 5 mm 0-5 21.00 % memenuhi -
- Pasir Halus PH 31.50 % Spesifikasi
- Semen FF 1.50 %
- Asphalt As 6.00 %
- Anti Stripping Agent Asa 0.30 %As
11 Berat isi bahan :
- HRS BASE D1 2.23 ton / M3
- Agr Pch Mesin 5 - 10 & 10 - 15 mm D2 1.42 ton / M3
- Agr Pch Mesin 0 - 5 mm D3 1.57 ton / M3
- Pasir Halus D4 1.46 ton / M3
12 Jarak Stock pile ke Cold Bin l 0.05 km
3. TENAGA
Produksi menentukan : Asphalt Finisher Q5 69.96 ton
Produksi HRS BASE / hari = Tk x Q5 Qt 489.75 ton
Kebutuhan tenaga :
- Pekerja P 10.00 orang
- Mandor M 1.00 orang
Koefisien Tenaga / ton :
- Pekerja = (Tk x P) / Qt (L01) 0.143 Jam
- Mandor = (Tk x M) / Qt (L03) 0.014 Jam
A. TENAGA
B. BAHAN
C. PERALATAN
I. ASUMSI
1 Menggunakan alat (cara mekanik)
2 Material rangka baja di lokasi
3 Jarak rata-rata Base camp ke lokasi pekerjaan L 7.00 KM
4 Jam kerja efektif per-hari Tk 7.00 jam
5 Berat Rangka Baja Span 60 M (Class B) Br 140,152.00 Kg
6 Untuk perletakan sementara : perancah kayu
7 Berat rangka baja per komponen Bg 2,335.87 Kg rata-rata
A. TENAGA
B. BAHAN
C. PERALATAN
I. ASUMSI
1 Menggunakan alat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar (batu, pasir dan semen) diterima
seluruhnya di lokasi pekerjaan
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 7.000 KM
5 Jam kerja efektif per-hari Tk 7.000 jam
6 Perbandingan Pasir & Semen : - Volume Semen Sm 25.000 % Spec.
: - Volume Pasir Ps 75.000 % Spec.
7 Perbandingan Batu & Mortar :
- Batu Bt 65.000 %
- Mortar (campuran semen & pasir) Mr 35.000 %
8 Berat Jenis Bahan :
- Pasangan Batu Dengan Mortar D1 2.400 ton/M3
- Batu D2 1.600 ton/M3
- Adukan (mortar) D3 1.800 ton/M3
- Pasir D4 1.300 ton/M3
- Semen Portland D5 1.440 ton/M3
3. TENAGA
Produksi menetukan : Produksi Concrete Mxer Q1 2.264 M3/Jam
Produksi Pasangan Batu dengan Mortar / hari = Tk x Q1 Qt 15.845 M3
Kebutuhan tenaga : - Mandor M 1.000 orang
- Tukang Batu Tb 3.000 orang
- Pekerja P 6.000 orang
Koefisien Tenaga / M3 :
- Mandor = (Tk x M) : Qt (L03) 0.442 jam
- Tukang = (Tk x Tb) : Qt (L02) 1.325 jam
- Pekerja = (Tk x P) : Qt (L01) 2.651 jam
A. TENAGA
B. BAHAN
C. PERALATAN
I. ASUMSI
1 Menggunakan alat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jembatan
3 Bahan / material diterima seluruhnya di lokasi
pekerjaan proyek
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 7.000 KM
5 Jam kerja efektif per-hari Tk 7.000 jam
1. BAHAN
1.a. Pipa d = 8.91 cm Galvanised (MXX) 1.000 M
2. ALAT
2.a. Alat pertukangan dan lain-lain
3. TENAGA
Produksi pasang Railingk dalam 1 hari
= Tk x Q1 = Qt 25.000 M
A. TENAGA
B. BAHAN
C. PERALATAN
I. ASUMSI
1 Menggunakan alat (cara mekanik)
2 Lokasi pekerjaan di lokasi jembatan
3 Bahan / material diterima seluruhnya di lokasi
pekerjaan proyek
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 7.000 KM
5 Jam kerja efektif per-hari Tk 7.000 jam
1. BAHAN
1.a. Marmer 0.750 M2
1.b. Adukan Semen = 0.1*1 = 0.1 M3 Ls
2. ALAT
2.a. Alat bantu pertukangan
3. TENAGA
Produksi Papan Nama dalam 1 hari
= Tk x Q1 = Qt 1.000 Buah
Kebutuhan tenaga : - Mandor M 1.000 orang
- Tukang Tb - orang
- Pekerja P 2.000 orang
Koefisien Tenaga / M3 :
- Mandor = (Tk x M) : Qt (L03) 7.000 jam
- Tukang = (Tk x Tb) : Qt (L02) - jam
- Pekerja = (Tk x P) : Qt (L01) 14.000 jam
A. TENAGA
B. BAHAN
C. PERALATAN
I. ASUMSI
1 Pekerjaan dilakukan secara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Bronjong dengan kawat dilapisi galvanis diterima
seluruhnya di lokasi pekerjaan
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 7.000 KM
5 Jam kerja efektif per-hari Tk 7.000 jam
6 Faktor Kehilangan Material Fh 1.100 -
2. ALAT
2.a. ALAT BANTU
Diperlukan : LS
3. TENAGA
Produksi pekerjaan per hari Qt 8.000 M3
dibutuhkan tenaga : - Mandor M 1.000 orang
- Tukang Tb 3.000 orang
- Pekerja P 6.000 orang
Koefisien Tenaga / Kg :
- Mandor = ( M x Tk ) : Qt (L03) 0.875 jam
- Tukang = ( Tb x Tk ) : Qt (L02) 2.625 jam
- Pekerja = ( P x Tk ) : Qt (L01) 5.250 jam
A. TENAGA
B. BAHAN
C. PERALATAN
I. ASUMSI
1 Menggunakan alat (cara mekanik)
2 Lokasi pekerjaan : sepanjang flyover/ jembatan
3 Bahan / material diterima seluruhnya di lokasi
pekerjaan proyek
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 3.000 KM
5 Jam kerja efektif per-hari Tk 7.000 jam
1. BAHAN
1.a. Expansion joint tipe baja bersudut 1.000 M
2. ALAT
2.a. Cutter Machine
Memotong diperkirakan = 0.85 jam per m 0.850 jam
3. TENAGA
Produksi pasang Exp. Joint dalam 1 hari
= Tk x Q1 = Qt 12.000 M
A. TENAGA
B. BAHAN
C. PERALATAN
I. ASUMSI
1 Menggunakan alat (cara mekanik)
2 Lokasi pekerjaan di lokasi jembatan
3 Bahan / material diterima seluruhnya di lokasi
pekerjaan proyek
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 3.000 KM
5 Jam kerja efektif per-hari Tk 7.000 jam
1. BAHAN
1.a. Elastomer per buah 1.000 Buah
2. ALAT
2.a. Alat pertukangan dan lain-lain LS
3. TENAGA
Produksi pasang Elastomer dalam 1 hari
= Tk x Q1 = Qt 4.000 buah
Kebutuhan tenaga : - Mandor M 1.000 orang
- Tukang Tb 2.000 orang
- Pekerja P 3.000 orang
Koefisien Tenaga / M3 :
- Mandor = (Tk x M) : Qt (L03) 1.750 jam
- Tukang = (Tk x Tb) : Qt (L02) 3.500 jam
- Pekerja = (Tk x P) : Qt (L01) 5.250 jam
A. TENAGA
B. BAHAN
C. PERALATAN
I. ASUMSI
1 Pekerjaan dilakukan secara mekanik/manual
2 Lokasi pekerjaan : sekitar jembatan
3 Diameter bagian luar Caison d 2.500 M
4 Jarak rata-rata Base Camp ke lokasi pekerjaan L 3.000 Km
5 Jam kerja efektif per-hari Tk 7.000 Jam
6 Tebal Caison t 0.300 M
7 Kebutuhan baja tulangan Mb 200.000 Kg/M3
2. ALAT
ALAT BANTU
Diperlukan alat-alat bantu kecil LS
3. TENAGA
Produksi Caison / hari Qt 6.000 M'
Kebutuhan tenaga tambahan :
- Pekerja P 5.000 orang
- Tukang T 3.000 orang
- Mandor M 1.000 orang
Koefisien tenaga / M' :
- Pekerja = (Tk x P) : Qt (L01) 5.833 jam
- Tukang = (Tk x T) : Qt (L02) 3.500 jam
- Mandor = (Tk x M) : Qt (L03) 1.167 jam
4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT
Lihat lampiran.
A. TENAGA
B. BAHAN
C. PERALATAN
I. ASUMSI
1 Pekerjaan dilakukan secara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar (besi dan kawat) diterima seluruhnya
di lokasi pekerjaan
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 7.000 KM
5 Jam kerja efektif per-hari Tk 7.000 jam
6 Faktor Kehilangan Material Fh 1.050 -
7 Tebal lapisan cat secara manual t 0.015 M Spec.10.4.3(2)(d)
8 Berat Jenis Bahan Cat BJ.Cat 1.000 Kg/Liter
9 Perbandingan pemakaian bahan : - Cat C 65.000 %
- Thinner T 35.000 %
II. URUTAN KERJA
1 Permukaan jalan dibersihkan dari debu/kotoran
2 Cat disemprotkan dengan Compressor di atas maal
tripleks yang dipasang di permukaan jalan
3 Glass Beat ditaburkan segera setelah cat marka selesai
disemprotkan
2. ALAT
2.a. COMPRESSOR (E05)
Kapasitas penyemprotan V 40.000 Ltr/Jam
Jumlah cat cair = (1 M x 1 M) x t x 1000 R 3.000 Ltr/M2
Kap. Prod. / Jam = V:R Q1 13.333 M2/Jam
Koef. Alat / M2 = 1 : Q1 (E05) 0.075 Jam
A. TENAGA
B. BAHAN
C. PERALATAN
I. ASUMSI
1 Menggunakan cara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar (patok beton cetak, dll) diangkut dengan
Truk ke lokasi pekerjaan
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 7.000 KM
5 Jam kerja efektif per-hari Tk 7.000 jam
6 Faktor kehilangan bahan Fh 1.050 -
7 Tulangan praktis Rc 150.000 Kg/M3
2. ALAT
2.a. DUMP TRUCK 3,5 Ton (E08)
Kapasitas 1 kali Angkut Cp 20.000 Buah
Faktor Efisiensi Alat Fa 0.830 -
Waktu Siklus : Ts
- Memuat = atur, ikat, dll. T1 20.000 menit
- Angkut = (2 x L : 25 Km/Jam) x 60 menit T2 33.600 menit
- Menurunkan = Rata-rata 1 menit / buah T3 20.000 menit
- Lain-lain = geser, atur, tunggu, dll. T4 10.000 menit
Ts 83.600 menit
Kap. Prod. / Jam = Cp x Fa Q1 11.914 Buah
Ts : 60
Koefisien Alat / Buah = 1 : Q1 (E08) 0.084 Jam
A. TENAGA
B. BAHAN
C. PERALATAN
I. ASUMSI
1 Menggunakan cara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar (plat rambu jadi, pipa dan beton cetak)
diangkut dengan Truk ke lokasi pekerjaan
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 7.000 KM
5 Jam kerja efektif per-hari Tk 7.000 jam
2. ALAT
2.a. DUMP TRUCK (E08)
Kapasitas 1 kali Angkut Cp 15.000 Buah
Waktu Siklus : Ts
- Memuat = atur, ikat, dll. T1 30.000 menit
- Angkut = (2 x L : 25 Km/Jam) x 60 menit T2 33.600 menit
- Menurunkan = Rata-rata 2.5 menit / buah T3 37.500 menit
- Lain-lain = geser, atur, tunggu, dll. T4 20.000 menit
Ts 121.100 menit
Kap. Prod. / Jam = Cp Q1 7.432 Buah
Ts : 60
Koefisien Alat / Buah = 1 : Q1 (E08) 0.135 Jam
3. TENAGA
Produksi pemasangan rambu dalam 1 hari = Tk x Q1 Qt 52.023 Buah
Kebutuhan tenaga : - Mandor M 1.000 orang
- Tukang Tb 3.000 orang
- Pekerja P 5.000 orang
Koefisien Tenaga / Bh :
- Mandor = (Tk x M) : Qt (L03) 0.135 jam
- Tukang = (Tk x Tb) : Qt (L02) 0.404 jam
- Pekerja = (Tk x P) : Qt (L01) 0.673 jam
4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT
Lihat lampiran.
A. TENAGA
B. BAHAN
C. PERALATAN
I. ASUMSI
1 Menggunakan cara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar kerb pracetak jenis-1 dibuat di base camp, kemudian
diangkut dengan Truk ke lokasi pekerjaan
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 7.000 KM
5 Jam kerja efektif per-hari Tk 7.000 jam
6 Faktor kehilangan bahan Fh 1.050 -
2. ALAT
2.a. Flat Bed Truck (E11)
Kapsitas Bak Cp 40.000 Buah
Waktu Siklus : Ts
- Memuat = naik & atur rata-rata 3 menit/m T1 26.667 menit
- Angkut V=30 Km/jam = Lef x V x 60 T2 14.000 menit
- Kembali V=50 Km/ja = Lef x V x 60 T3 8.400 menit
- Menurunkan = Rata-rata 2 menit/m T4 40.000 menit
- Lain-lain = geser, atur, tunggu dll T5 10.000 menit
Ts 99.067 menit
A. TENAGA
B. BAHAN
C. PERALATAN
I. ASUMSI
1 Pekerjaan dilakukan secara manual dan Mekanis
2 Bahan di terima di Lokasi pekerjaan
3 Pengecatan dilakukan secara manual dengan kuas
4 Permukaan Beton yang akan di cat bebas dari kerusakan
5 Cat dasar Kebutuhan Kd 0.280 Kg/m2
Berat Volume Dd 1.300 Ton/m3
6 Cat Protektif Kebutuhan Kp 0.250 Kg/m2
Berat Volume Dp 1.400 Ton/m3
7 Jam kerja efektif per-hari Tk 7.000 jam
8 Faktor Kehilangan Material Fh 1.050 -
2. ALAT
2.a. Water Jet Blasting E64
Kapasitas pembersihan V 20 m2/jam Asumsi
Faktor Efisiensi alat (1 M x 1 M) x t x 1000 Fa 0.83 -
Kap. Prod. / jam = V:R Q1 16.60 M2/Jam
Koefisien Alat / M3 = 1 : Q1 E64 0.06 Jam