JENIS
TANGGAL PEKERJAAN PERIHAL TANGGAL MASUK MK
AGUSTUS INF PEKERJAAN PEMASANGAN BEKISTING DAN PEMBESIAN RIGID INFRASTRUKTUR 14-Aug-19
INF PEKERJAAN PEMASANGAN SALURAN BOX CULVERT DAN BAK KONTROL 14-Aug-19
INF PEKERJAAN PEMASANGAN PAVING BLOCK (PEDESTRIAN) 14-Aug-19
INF PEKERJAAN GALIAN,PEMBESIAN DAN BEKISTING SUMPIT 01;02;03;04;05;06 14-Aug-19
ARS PEKERJAAN PASANGAN DINDING BATA RINGAN (PLESTERDAN ACI) LANTAI 2 18-Aug-19
GEDUNG C
ARS PEKERJAAN PASANGAN DINDING BATA RINGAN (PLESTERDAN ACI) LANTAI 3 18-Aug-19
GEDUNG C
ARS PEKERJAAN PASANGAN DINDING BATA RINGAN (PLESTERDAN ACI) LANTAI 4 18-Aug-19
GEDUNG C
ARS PEKERJAAN PASANGAN DINDING BATA RINGAN (PLESTERDAN ACI) LANTAI 1 18-Aug-19
GEDUNG A
ARS PEKERJAAN PASANGAN DINDING BATA RINGAN (PLESTERDAN ACI) LANTAI 2 18-Aug-19
GEDUNG A
ARS PEKERJAAN HOMOGENEOUS TILE LANTAI 2 GEDUNG C 11-Sep-19
ARS PEKERJAAN HOMOGENEOUS TILE LANTAI 3 GEDUNG C 16-Sep-19
ARS PEKERJAAN HOMOGENEOUS TILE LANTAI 4 GEDUNG C 21-Sep-19
ARS PEKERJAAN HOMOGENEOUS TILE LANTAI 1 GEDUNG A 2-Dec-19
ARS PEKERJAAN HOMOGENEOUS TILE LANTAI 2 GEDUNG A 9-Dec-19
ARS PEKERJAAN PLINT HOMOGENEOUS TILE LANTAI 2 GEDUNG C 17-Sep-19
ARS PEKERJAAN PLINT HOMOGENEOUS TILE LANTAI 3 GEDUNG C 23-Sep-19
ARS PEKERJAAN PLINT HOMOGENEOUS TILE LANTAI 4 GEDUNG C 29-Sep-19
ARS PEKERJAAN PLINT HOMOGENEOUS TILE LANTAI 1 GEDUNG A
ARS PEKERJAAN PLINT HOMOGENEOUS TILE LANTAI 2 GEDUNG A
ARS PEKERJAAN KERAMIK TILE LANTAI 2 GEDUNG C
ARS PEKERJAAN KERAMIK TILE LANTAI 3 GEDUNG C
ARS PEKERJAAN KERAMIK TILE LANTAI 4 GEDUNG C
ARS PEKERJAAN KERAMIK TILE LANTAI 1 GEDUNG A
ARS PEKERJAAN KERAMIK TILE LANTAI 2 GEDUNG A
SEPTEMBER ARS PEKERJAAN PEMASANGAN PLAFOND LANTAI 2 GEDUNG AC 12 SEPTEMBER 2019
PEKERJAAN LANGIT - LANGIT GYPSUM BOARD LANTAI 2 GEDUNG C 15-Sep-19
PEKERJAAN LANGIT - LANGIT GYPSUM BOARD LANTAI 3 GEDUNG C 20-Sep-19
PEKERJAAN LANGIT - LANGIT GYPSUM BOARD LANTAI 4 GEDUNG C 27-Sep-19
PEKERJAAN LANGIT - LANGIT GYPSUM BOARD LANTAI 1 GEDUNG A
PEKERJAAN LANGIT - LANGIT GYPSUM BOARD LANTAI 2 GEDUNG A
PEKERJAAN LANGIT - LANGIT AKUSTIK LANTAI 2 GEDUNG C 19-Sep-19
PEKERJAAN LANGIT - LANGIT AKUSTIK LANTAI 3 GEDUNG C 24-Sep-19
PEKERJAAN LANGIT - LANGIT AKUSTIK LANTAI 4 GEDUNG C 30-Sep-19
PEKERJAAN LANGIT - LANGIT AKUSTIK LANTAI 2 GEDUNG A
PEKERJAAN STAINLESS STEEL PADA PLAFOND AKUSTIK LANTAI 2 GEDUNG C
PEKERJAAN STAINLESS STEEL PADA PLAFOND AKUSTIK LANTAI 3 GEDUNG C
PEKERJAAN STAINLESS STEEL PADA PLAFOND AKUSTIK LANTAI 4 GEDUNG C
PEKERJAAN CAT PLAFOND LANTAI 2 GEDUNG C
PEKERJAAN CAT PLAFOND LANTAI 3 GEDUNG C
PEKERJAAN CAT PLAFOND LANTAI 4 GEDUNG C
PEKERJAAN CAT PLAFOND LANTAI 1 GEDUNG A
PEKERJAAN CAT PLAFOND LANTAI 2 GEDUNG A
PEKERJAAN WATERPROOFING LANTAI 2 GEDUNG C 8-Nov-19
PEKERJAAN WATERPROOFING LANTAI 3 GEDUNG C 28-Nov-19
PEKERJAAN WATERPROOFING LANTAI 4 GEDUNG C 8-Dec-19
PEKERJAAN WATERPROOFING LANTAI 1 GEDUNG A -
PEKERJAAN WATERPROOFING LANTAI 2 GEDUNG A 8-Dec-19
PEKERJAAN SANITASI LANTAI 2 GEDUNG C 13-Nov-19
PEKERJAAN SANITASI LANTAI 3 GEDUNG C 3-Dec-19
MONITORING IPL
JENIS
TANGGAL PEKERJAAN PERIHAL TANGGAL MASUK MK
JENIS
TANGGAL PEKERJAAN PERIHAL TANGGAL MASUK MK
PEKERJAAN CAT DUKO RAILING DAN PINTU BESI LANTAI 5 GEDUNG C 5-Dec-19
PEKERJAAN LANTAI VINYL LANTAI 1 GEDUNG A -
PEKERJAAN LANTAI VINYL LANTAI 1 GEDUNG C 15-Dec-19
PEKERJAAN PLINT VINYL LANTAI 1 GEDUNG A -
PEKERJAAN PLINT VINYL LANTAI 1 GEDUNG C -
PEKERJAAN ANTI RADIASI RUANG RADIOLOGI LANTAI DASAR GEDUNG C 17-Nov-19
PEKERJAAN CURTAIN WALL LANTAI 1 GEDUNG C
PEKERJAAN CURTAIN WALL LANTAI 2 GEDUNG C
PEKERJAAN CURTAIN WALL LANTAI 3 GEDUNG C
PEKERJAAN CURTAIN WALL LANTAI 4 GEDUNG C
PEKERJAAN CURTAIN WALL LANTAI 1 GEDUNG A 19-Nov-19
PEKERJAAN CURTAIN WALL LANTAI 2 GEDUNG A 20-Nov-19
PEKERJAAN PLAFOND METAL STRIP AREA LIFT 7-Dec-19
PEKERJAAN METAL STRIP KANOPI GEDUNG CONNECTING 14-Dec-19
MONITORING APPROVAL MATERIAL
PROYEK : PEMBANGUNAN RSUD DEPOK ( LANJUTAN )
KONTRAKTOR KONSULTAN MK PEMBERI TUGAS
KONTRAKTOR : PT. BRANTAS ABIPRAYA
NO. KONTRAK :
TANGGAL NO SURAT JENIS PEKERJAAN JENIS MATERIAL MERK SUPPLIER/SUBKONTRAKTOR TANGGAL MASUK MK TANGGAL KEMBALI DEVIASI STATUS TANGGAL MASUK PPK TANGGAL KEMBALI DEVIASI STATUS
AGUSTUS 001/BA-RSUD/OPS/MTL/STR/VIII/2019 STR BETON READY MIX ex. PIONIR PIONIR BETON INDONESIA 7 AGUSTUS 2019 22 AGUSTUS 2019 15 HARI DITERIMA 7 AGUSTUS 2019 22 AGUSTUS 2019 15 HARI DISETUJUI / SUDAH KEMBALI KE MK
002/BA-RSUD/OPS/MTL/STR/VIII/2019 STR BESI BETON 27 AGUSTUS 2019 DITERIMA DI DINAS
003/BA-RSUD/OPS/MTL/STR/VIII/2019 STR WIREMESH M6-150 7 AGUSTUS 2019 22 AGUSTUS 2019 15 HARI DITERIMA 7 AGUSTUS 2019 22 AGUSTUS 2019 15 HARI DISETUJUI / SUDAH KEMBALI KE MK