I PEKERJAAN PERSIAPAN
1 Pembersihan Lokasi m² 92.00 10,000.00 920,000.00
2 Pemasangan Bowplank Ttk 12.00 100,000.00 1,200,000.00
I. JUMLAH TOTAL HARGA PEKERJAAN PERSIAPAN 2,120,000.00
II LANTAI 1
A PEKERJAAN TANAH & PONDASI
1 Pek. Galian Tanah Pondasi Sloof/Batu Kali m³ 59.00 180,000.00 10,620,000.00
2 Pek. Galian Tanah Pondasi Pilecap m³ 10.20 200,000.00 2,040,000.00
3 Pek. Alas Pasir Pondasi m³ 5.90 420,000.00 2,478,000.00
4 Pek. Rabat Lantai Kerja tb 5cm m³ 0.59 2,300,000.00 1,357,000.00
5 Pek. Pondasi Beton Pilecap (60x80x30) m³ 6.49 4,900,000.00 31,801,000.00
6 Pek. Pondasi Pas.Batu Kali 1:4 m³ 23.60 350,000.00 8,260,000.00
7 Pek. Pondasi Rolag Pas.1 Bata m² 15.20 220,900.00 3,357,680.00
8 Pek.Beton Sloof (20/30) m³ 3.21 4,900,000.00 15,729,000.00
9 Pek.Beton Sloof (15/20) m³ 1.22 4,900,000.00 5,978,000.00
10 Pek.Urugan Tanah Sirtu m³ 4.13 420,000.00 1,734,600.00
Jumlah PEKERJAAN TANAH & PONDASI 83,355,280.00
B PEKERJAAN STRUKTUR BETON
1 Pek. Kolom Praktis KP (11/11) m¹ 31.21 850,000.00 26,528,500.00
2 Pek. Kolom K1 (30/30) m³ 3.11 4,900,000.00 15,239,000.00
3 Pek. Balok Praktis / Ringbalk Pagar (15/15) m¹ 16.89 900,000.00 15,201,000.00
4 Pek. Plat Leutel Kanopi Depan tb.10cm m³ 0.44 4,900,000.00 2,156,000.00
5 Pek. Anak Tangga Baja Ls 1.00 18,000,000.00 18,000,000.00
Jumlah PEKERJAAN STRUKTUR BETON 77,124,500.00
C PEKERJAAN DINDING
1 Pek. Pasangan Bata Ringan m² 132.00 142,000.00 18,744,000.00
2 Pek. Plesteran Dinding 1:5 m² 237.60 48,000.00 11,404,800.00
3 Pek. Acian 1:5 m² 237.60 23,000.00 5,464,800.00
Jumlah PEKERJAAN DINDING 35,613,600.00
D PEKERJAAN KUSEN, PINTU & JENDELA
1 Kusen Type PJ1 Sliding Unit 4.00 7,800,000.00 31,200,000.00
a. Kayu solid m¹ 5.42 - -
b. Daun Pintu Ky Kamper + Finish Cat Purnis m³ 0.98 - -
c. Kaca Polos 5mm m² 2.31 - -
d. Kunci Tanam 2x Putar Bh 1.00 - -
e. Track Rel Pintu + Accessories Unit 1.00 - -
Dibuat,
Jakarta, 6 Oktober 2022