Anda di halaman 1dari 43

RENCANA ANGGARAN BIAYA

PEKERJAAN : PEMBANGUNAN PERUMAHAN "GRIYA TIWI BARUGA" TYPE 36


LOKASI : JL. LINGKUNGAN PD. JL. ADE IRMA NASUTION KEL. WATUBANGGA KEC. BARUGA
VOLUME : 119 UNIT
PEMILIK : ASRIANTO ( PT. ALKOBAR ALAM RAYA )

I. PEKERJAAN PENDAHULUAN
HARGA JUMLAH
NO. URAIAN DAN JENIS PEKERJAAN VOLUME SATUAN SATUAN HARGA
(Rp) (Rp)

1 2 3 4 5 6
I PEKERJAAN PERSIAPAN / PENDAHULUAN
1 Pekerjaan Pembersihan Lokasi 1.00 Unit 25,000,000.00 25,000,000.00
2 Pek. Bangsal Kerja Ls Ls 7,800,000.00 7,800,000.00
3 Pek. Pas. Bowplank 119.00 Unit 150,000.00 17,850,000.00
4 Air Kerja / P3K 119.00 Unit 100,000.00 11,900,000.00
5 Administrasi dan Dokumentasi 119.00 Unit 50,000.00 5,950,000.00
Jumlah 68,500,000.00

II. PEMBANGUNAN PERUMAHAN TYPE 36


HARGA JUMLAH
NO. URAIAN DAN JENIS PEKERJAAN VOLUME SATUAN SATUAN HARGA
(Rp) (Rp)

1 2 3 4 5 6
I PEKERJAAN TANAH DAN PASIR
1 Pek. Galian Tanah Pondasi 12.96 m3 22,800.00 295,488.00
2 Pek. Urugan Tanah Eks. Galian Pondasi 3.24 m3 10,930.00 35,413.20
3 Pek. Urugan tanah bawah lantai 12.88 m3 58,500.00 753,597.00
4 Pek. Urugan pasir alas Pondasi 1.44 m3 105,700.00 152,208.00
5 Pek. Urugan pasir alas Lantai 3.39 m3 105,700.00 358,323.00
Jumlah 1,595,029.20
II PEKERJAAN BATU DAN PASANGAN
1 Pas. Batu kosong 4.32 m3 274,455.00 1,185,645.60
2 Pas. Pondasi batu gunung, adukan 1 Pc : 5 Psr 12.24 m3 536,550.00 6,567,372.00
3 Pas. Dinding batako, adukan 1 Pc : 2 Psr 10.80 m2 43,888.50 473,995.80
4 Pas. Dinding batako, adukan 1 Pc : 5 Psr 70.80 m2 42,295.00 2,994,486.00
Jumlah 11,221,499.40
III PEKERJAAN BETON BERTULANG
1 Pek. Sloof Praktis 15 x 20 Beton Bertulang 1 Pc : 2 Psr : 3 Krl 36.00 m' 52,880.00 1,903,680.00
2 Pek. Kolom praktis, 12 x 12 cm Beton Bertulang 1 Pc : 2 Psr : 3 Krl 45.00 m' 45,085.00 2,028,825.00
3 Pek. Ring Balk, Uk.12 x 15 cm Beton Bertulang 1 Pc : 2 Psr : 3 Krl 58.90 m' 52,880.00 3,114,632.00
Jumlah 7,047,137.00
IV PEKERJAAN PLESTERAN
1 Pek. Plesteran Trasram camp. 1 Pc : 2 Ps T. 15 mm 21.60 m2 35,526.00 767,361.60
2 Pek. Plesteran Dinding camp. 1 Pc : 5 Ps T. 15 mm 141.60 m2 30,691.00 4,345,845.60
3 Pek. Plesteran Beton camp. 1 Pc : 3 Ps T. 15 mm 7.20 m2 33,124.00 238,492.80
4 Pek. Pleteran Pondasi camp. 1 Pc : 3 Ps T. 15 mm 22.40 m2 33,124.00 741,977.60
Jumlah 6,093,677.60
V PEKERJAAN PASANGAN LANTAI KERAMIK DAN RABAT BETON
1 Pek. Pasangan keramik 40 x 40 cm 31.65 m2 139,019.00 4,399,951.35
2 Pek. Pasangan keramik 20 x 20 cm 2.25 m2 118,878.00 267,475.50
3 Pek. Pasangan keramik 20 x 25 cm 7.50 m2 144,019.00 1,080,142.50
4 Pek. Lantai Rabat beton 1 Pc : 3 Psr : 5 Krl 2.52 m3 608,125.00 1,532,475.00
Jumlah 7,280,044.35
VI PEKERJAAN KUSEN/JENDELA/KACA
1 Pek. Kosen pintu / jendela kayu Kelas II Uk. 5 x 13,5 cm 0.49 m3 4,131,000.00 2,037,409.20
2 Pek. Pintu panil kayu Jati 5.04 m2 343,250.00 1,729,980.00
3 Pek. Bingkai jendela kaca kayu Jati 2.52 m2 281,800.00 710,136.00
4 Pek. List Kaca 1 x 1 cm 25.20 m' 5,385.00 135,702.00
5 Pek. Pas. Kaca Bening 5 mm 5.04 m2 111,427.50 561,594.60
Jumlah 5,174,821.80
VII PEKERJAAN KAP DAN ATAP
1 Pek. Kuda-kuda, balok jurai dan konsol kayu II 0.52 m3 3,431,000.00 1,797,844.00
2 Pek. Gording dan balok angin kayu kls II 0.66 m3 3,136,000.00 2,082,304.00
3 Pek. Papan listplank papan Kayu Kelas II 20.58 m' 59,125.00 1,216,712.68
4 Pas. Atap seng Soka Jempol 48.00 m2 46,120.00 2,213,760.00
5 Pas. Nok seng Soka Jempol 8.00 m' 25,920.00 207,360.00
Jumlah 7,517,980.68
1 2 3 4 5 6
VIII PEKERJAAN PENGGANTUNG/PENGUNCI
1 Pas. Kunci tanam Anchor 693 LD, 2 x putar 3.00 buah 186,600.00 559,800.00
2 Pas. Engsel pintu dalam type kupu-kupu 6.00 buah 17,431.00 104,586.00
3 Pas. Grendel Pintu 3.00 buah 15,431.00 46,293.00
4 Pas. Engsel jendela type kupu-kupu standard 14.00 buah 12,285.00 171,990.00
5 Pas. Grendel jendela standard 7.00 buah 15,431.00 108,017.00
6 Pas. Kait angin jendela standard 14.00 buah 15,431.00 216,034.00
Jumlah 1,206,720.00
IX PEKERJAAN RANGKA DAN PLAFOND
1 Pek. Rangka Plafond Tripleks kayu kls II 58.90 m2 55,225.00 3,252,752.50
2 Pek. Plafond Tripleks 60 x 120 cm 58.90 m2 29,395.00 1,731,365.50
3 Pas. List Plafond Profil 90.00 m' 5,565.00 500,850.00
Jumlah 5,484,968.00
X PEKERJAAN INSTALASI LISTRIK
1 Pasangan titik instalasi 7.00 buah 50,000.00 350,000.00
2 Pasangan lampu TL 20 watt 1.00 buah 40,000.00 40,000.00
3 Pasangan lampu pijar 25 watt 4.00 buah 20,000.00 80,000.00
4 Pasangan lampu pijar 5 watt 2.00 buah 10,000.00 20,000.00
5 Pas. Stop kontak merk Broco 2.00 buah 10,000.00 20,000.00
6 Pas. Saklar tunggal merk Broco 3.00 buah 7,500.00 22,500.00
7 Pas. Saklar ganda merk Broco 2.00 buah 12,500.00 25,000.00
8 Pas. Box Skring ( MCB ) 1.00 buah 125,000.00 125,000.00
Jumlah 682,500.00
XI PEKERJAAN SANITASI
1 Pek. Instalasi Air bersih Ls Ls 250,000.00 250,000.00
2 Pek. Instalasi Air kotor Ls Ls 150,000.00 150,000.00
3 Pemasangan kran air 2.00 Bh 23,662.50 47,325.00
4 Pemasangan Floor drain 2.00 Bh 18,600.00 37,200.00
5 Pemasangan klosed jongkok 1.00 Bh 399,750.00 399,750.00
6 Pek. Pintu fiber 1.00 Bh 300,000.00 300,000.00
7 Pek. Septick tank dan peresapan 1.00 Unit 2,000,000.00 2,000,000.00
Jumlah 3,184,275.00
XII PEKERJAAN PENGECATAN / FINISHING
1 Pek. Plamur Tembok 163.20 m2 6,956.67 1,135,328.54
2 Pek. Cat tembok 2 x jalan 163.20 m2 7,683.34 1,253,921.09
3 Pek. Cat plafond 2 x jalan 58.90 m2 7,683.34 452,548.73
4 Pek. Cat dasar/kilap kosen 2 x jalan 17.18 m2 12,855.50 220,793.21
5 Pek. Vernis daun pintu/jendela 2 x jalan 15.12 m2 23,425.00 354,186.00
6 Pek. Mengamplas dan Menggosok kayu 32.30 m2 4,020.00 129,825.90
7 Pek. Pembersihan akhir ls ls 150,000.00 150,000.00
Jumlah 3,696,603.47

REKAPITULASI
JUMLAH
NO. URAIAN DAN JENIS PEKERJAAN HARGA
(Rp)

I ###
PEKERJAAN TANAH DAN PASIR . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp 1,595,029.20
II ###
PEKERJAAN BATU DAN PASANGAN . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp 11,221,499.40
III###PEKERJAAN BETON BERTULANG . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp 7,047,137.00
IV### PEKERJAAN PLESTERAN . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp 6,093,677.60
V ###PEKERJAAN PASANGAN LANTAI KERAMIK DAN RABAT BETON . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp 7,280,044.35
VI### PEKERJAAN KUSEN/JENDELA/KACA . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp 5,174,821.80
VII### PEKERJAAN KAP DAN ATAP . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp 7,517,980.68
VIII###PEKERJAAN PENGGANTUNG/PENGUNCI . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp 1,206,720.00
IX PEKERJAAN RANGKA DAN PLAFOND . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp 5,484,968.00
X ###PEKERJAAN INSTALASI LISTRIK . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp 682,500.00
XI PEKERJAAN SANITASI . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp 3,184,275.00
XII PEKERJAAN PENGECATAN / FINISHING . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp 3,696,603.47

A TOTAL . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp 60,185,256.50
B JUMLAH A X 94 UNIT . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp 7,162,045,523.71

III. PEMBANGUNAN FASILITAS UMUM

HARGA JUMLAH
NO. URAIAN DAN JENIS PEKERJAAN VOLUME SATUAN SATUAN HARGA
(Rp) (Rp)

1 2 3 4 5 6
I PEKERJAAN FASILITAS UMUM
1 Pek. Pintu Gerbang 2.00 Unit 5,000,000.00 10,000,000.00
2 Pek. Pembentukan Badan Jalan 930.00 m' 250,000.00 232,500,000.00
3 Pek. Perkerasan Badan Jalan 930.00 m' 750,000.00 697,500,000.00
4 Pek. Drainace Jalan 1,745.00 m' 150,000.00 261,750,000.00
5 Pek. Selokan Induk 215.00 m' 350,000.00 75,250,000.00
6 Pek. Duicker Plat Beton Bertulang 5.00 Unit 15,000,000.00 75,000,000.00
Jumlah 1,352,000,000.00

TOTAL REKAPITULASI

PEKERJAAN : PEMBANGUNAN PERUMAHAN "GRIYA TIWI BARUGA" TYPE 36


LOKASI : JL. LINGKUNGAN PD. JL. ADE IRMA NASUTION KEL. WATUBANGGA KEC. BARUGA
VOLUME : 119 UNIT
PEMILIK : ASRIANTO ( PT. ALKOBAR ALAM RAYA )

JUMLAH
NO. URAIAN DAN JENIS PEKERJAAN HARGA
(Rp)

I ###
PEKERJAAN PENDAHULUAN . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp 68,500,000.00

II###
PEMBANGUNAN PERUMAHAN TYPE 36 . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp 7,162,045,523.71

III. PEMBANGUNAN FASILITAS UMUM . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp 1,352,000,000.00

TOTAL . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp 8,582,545,523.71

DIBULATKAN . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp 8,582,545,000.00

TERBILANG : DELAPAN MILYAR LIMA RATUS DELAPAN PULUH DUA JUTA LIMA RATUS EMPAT PULUH LIMA RIBU RUPIAH

Disetujui : Kendari, 20 Desember 2016


PT. ALKOBAR ALAM RAYA Dibuat Oleh,
###

ASRIANTO WARJONO, A.Md


Direktur Coast Estimator
B. DANA IMBAL SWADAYA ( SHARING )

I PEKERJAAN MOBILER
HARGA JUMLAH
NO. URAIAN DAN JENIS PEKERJAAN VOLUME SATUAN SATUAN HARGA
(Rp) (Rp)
1 2 3 4 5 6
I PEKERJAAN MOBILER
1 Pengadaan meja 1/2 biro 20.00 buah 600,000.00 12,000,000.00
2 Pengadaan kursi guru 20.00 buah 350,000.00 7,000,000.00
3 Pengadaan meja siswa 160.00 buah 450,000.00 72,000,000.00
4 Pengadaan kursi siswa 160.00 buah 250,000.00 40,000,000.00
5 Pengadaan lemari 10.00 buah 900,000.00 9,000,000.00
6 Pengadaan papan tulis 4.00 buah 300,000.00 1,200,000.00
7 Pengadaan papan absen 4.00 buah 150,000.00 600,000.00
8 Pengadaan bak sampah 7.00 buah 150,000.00 1,050,000.00
9 Pengadaan tiang bendera ruangan 7.00 buah 250,000.00 1,750,000.00
10 Pengadaan rak buku 6.00 buah 700,000.00 4,200,000.00
11 Pengadaan meja dan kursi tamu 1.00 Set 2,400,000.00 2,400,000.00
12 Pengadaan tiang bendera sekolah 1.00 Unit 850,000.00 850,000.00
Jumlah 152,050,000.00

REKAPITULASI
JUMLAH
NO. URAIAN DAN JENIS PEKERJAAN HARGA
(Rp)

I PEKERJAAN MOBILER . . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp 152,050,000.00

TOTAL . . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp 152,050,000.00

TERBILANG : SERATUS LIMA PULUH DUA JUTA LIMA PULUH RIBU RUPIAH

II PEMBANGUNAN GEDUNG KANTOR


1 2 3 4 5 6
I PEKERJAAN PENGECATAN
1 Pek. Plamur Tembok 170.40 m2 6,956.67 1,185,416.57
2 Pek. Cat tembok 3 x jalan 170.40 m2 7,683.34 1,309,241.14
3 Pek. Cat plafond 3 x jalan 58.90 m2 7,683.34 452,548.73
4 Pek. Cat dasar/kilap kosen 3 x jalan 87.00 m2 12,855.50 1,118,428.50
5 Pek. Cat dasar/kilap jalusi 3 x jalan 26.00 m2 12,855.50 334,243.00
6 Pek. Cat dasar/kilap listplank 3 x jalan 29.75 m2 12,855.50 382,451.13
7 Pek. Vernis daun pintu/jendela 3 x jalan 34.50 m2 23,425.00 808,162.50
8 Pek. Mengamplas dan Menggosok kayu 178.22 m2 4,020.00 716,444.40
9 Pek. Residu kayu kap/rangka atap Ls Ls 500,000.00 500,000.00
Jumlah 6,806,935.96
II PEKERJAAN SALURAN AIR HUJAN KELILING BANGUNAN
1 Pek. Pas. Batu Gunung saluran air camp. 1 : 3 68.00 m' 50,000.00 3,400,000.00
2 Pek. Bak Kontrol Pas. Batu 1 : 5 4.00 buah 60,000.00 240,000.00
3 Pek. Hamparan kerikil keliling bangunan 6.57 m3 105,700.00 694,449.00
Jumlah 4,334,449.00
III PEKERJAAN PEMBERSIHAN AKHIR
1 Pek. Pembersihan akhir ls ls 150,000.00 150,000.00
Jumlah 150,000.00

REKAPITULASI
JUMLAH
NO. URAIAN DAN JENIS PEKERJAAN HARGA
(Rp)

I PEKERJAAN PENGECATAN . . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp 6,806,935.96


II PEKERJAAN SALURAN AIR HUJAN KELILING BANGUNAN . . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp 4,334,449.00
III PEKERJAAN PEMBERSIHAN AKHIR . . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp 150,000.00

TOTAL . . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp 11,291,384.96
DIBULATKAN . . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp 11,291,000.00

TERBILANG : DUA PULUH DUA JUTA TUJUH RATUS TUJUH PULUH TIGA RIBU RUPIAH

III PEMBANGUNAN 2 ( DUA ) RKB


1 2 3 4 5 6
I PEKERJAAN PENGECATAN
1 Pek. Plamur Tembok #VALUE! m2 6,956.67 #VALUE!
2 Pek. Cat tembok 3 x jalan #VALUE! m2 7,683.34 #VALUE!
3 Pek. Cat plafond 3 x jalan #REF! m2 7,683.34 #REF!
4 Pek. Cat dasar/kilap kosen 3 x jalan 70.56 m2 12,855.50 907,084.08
5 Pek. Cat dasar/kilap jalusi 3 x jalan 99.22 m2 12,855.50 1,275,522.71
6 Pek. Cat dasar/kilap listplank 3 x jalan 29.75 m2 12,855.50 382,451.13
7 Pek. Vernis daun pintu/jendela 3 x jalan 24.40 m2 23,425.00 571,570.00
8 Pek. Mengamplas dan Menggosok kayu 223.93 m2 4,020.00 900,198.60
9 Pek. Residu kayu kap/rangka atap Ls Ls 500,000.00 500,000.00
Jumlah #VALUE!
II PEKERJAAN SALURAN AIR HUJAN KELILING BANGUNAN
1 Pek. Pas. Batu Gunung saluran air camp. 1 : 3 68.00 m' 50,000.00 3,400,000.00
2 Pek. Bak Kontrol Pas. Batu 1 : 5 4.00 buah 60,000.00 240,000.00
3 Pek. Hamparan kerikil keliling bangunan 6.55 m3 150,000.00 982,500.00
Jumlah 4,622,500.00
III PEKERJAAN PEMBERSIHAN AKHIR
1 Pek. Pembersihan akhir ls ls 150,000.00 150,000.00
Jumlah 150,000.00

REKAPITULASI
JUMLAH
NO. URAIAN DAN JENIS PEKERJAAN HARGA
(Rp)

I PEKERJAAN PENGECATAN . . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp #VALUE!


II PEKERJAAN SALURAN AIR HUJAN KELILING BANGUNAN . . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp 4,622,500.00
III PEKERJAAN PEMBERSIHAN AKHIR . . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp 150,000.00

TOTAL . . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp #VALUE!
DIBULATKAN . . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp #VALUE!

TERBILANG : SEMBILAN BELAS JUTA EMPAT RATUS ENAM PULUH EMPAT RIBU RUPIAH

IV PEMBANGUNAN 2 ( DUA ) RKB DAN KM/WC


1 2 3 4 5 6
I PEKERJAAN PENGECATAN
1 Pek. Plamur Tembok #VALUE! m2 6,956.67 #VALUE!
2 Pek. Cat tembok 3 x jalan #VALUE! m2 7,683.34 #VALUE!
3 Pek. Cat plafond 3 x jalan #REF! m2 7,683.34 #REF!
4 Pek. Cat dasar/kilap kosen 3 x jalan 70.56 m2 12,855.50 907,084.08
5 Pek. Cat dasar/kilap jalusi 3 x jalan #VALUE! m2 12,855.50 #VALUE!
6 Pek. Cat dasar/kilap listplank 3 x jalan #VALUE! m2 12,855.50 #VALUE!
7 Pek. Vernis daun pintu/jendela 3 x jalan 24.40 m2 23,425.00 571,570.00
8 Pek. Mengamplas dan Menggosok kayu #VALUE! m2 4,020.00 #VALUE!
9 Pek. Residu kayu kap/rangka atap Ls Ls 500,000.00 500,000.00
Jumlah #VALUE!
II PEKERJAAN SALURAN AIR HUJAN KELILING BANGUNAN
1 Pek. Pas. Batu Gunung saluran air camp. 1 : 3 74.00 m' 50,000.00 3,700,000.00
2 Pek. Bak Kontrol Pas. Batu 1 : 5 4.00 buah 60,000.00 240,000.00
3 Pek. Hamparan kerikil keliling bangunan 6.58 m3 #REF! #REF!
Jumlah #REF!
III PEKERJAAN PEMBERSIHAN AKHIR
1 Pek. Pembersihan akhir ls ls 150,000.00 150,000.00
Jumlah 150,000.00

REKAPITULASI
JUMLAH
NO. URAIAN DAN JENIS PEKERJAAN HARGA
(Rp)

I PEKERJAAN PENGECATAN . . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp #VALUE!


II PEKERJAAN SALURAN AIR HUJAN KELILING BANGUNAN . . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp #REF!
III PEKERJAAN PEMBERSIHAN AKHIR . . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp 150,000.00

TOTAL . . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp #VALUE!
DIBULATKAN . . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp #VALUE!

TERBILANG : DUA PULUH TIGA JUTA ENAM RATUS DELAPAN PULUH DUA RIBU RUPIAH

V PEMBANGUNAN GEDUNG LABORATORIUM IPA


1 2 3 4 5 6
I PEKERJAAN PENGECATAN
1 Pek. Plamur Tembok #VALUE! m2 6,956.67 #VALUE!
2 Pek. Cat tembok 3 x jalan #VALUE! m2 7,683.34 #VALUE!
3 Pek. Cat plafond 3 x jalan #REF! m2 7,683.34 #REF!
4 Pek. Cat dasar/kilap kosen 3 x jalan 79.00 m2 12,855.50 1,015,584.50
5 Pek. Cat dasar/kilap jalusi 3 x jalan 85.32 m2 12,855.50 1,096,831.26
6 Pek. Cat dasar/kilap listplank 3 x jalan 27.65 m2 12,855.50 355,454.58
7 Pek. Vernis daun pintu/jendela 3 x jalan 23.71 m2 23,425.00 555,406.75
8 Pek. Mengamplas dan Menggosok kayu 215.68 m2 4,020.00 867,033.60
9 Pek. Residu kayu kap/rangka atap Ls Ls 500,000.00 500,000.00
Jumlah #VALUE!
II PEKERJAAN SALURAN AIR HUJAN KELILING BANGUNAN
1 Pek. Pas. Batu Gunung saluran air camp. 1 : 3 62.00 m' 50,000.00 3,100,000.00
2 Pek. Bak Kontrol Pas. Batu 1 : 5 4.00 buah 60,000.00 240,000.00
3 Pek. Hamparan kerikil keliling bangunan 5.87 m3 #REF! #REF!
Jumlah #REF!
III PEKERJAAN PEMBERSIHAN AKHIR
1 Pek. Pembersihan akhir ls ls 150,000.00 150,000.00
Jumlah 150,000.00

REKAPITULASI
JUMLAH
NO. URAIAN DAN JENIS PEKERJAAN HARGA
(Rp)

I PEKERJAAN PENGECATAN . . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp #VALUE!


II PEKERJAAN SALURAN AIR HUJAN KELILING BANGUNAN . . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp #REF!
III PEKERJAAN PEMBERSIHAN AKHIR . . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp 150,000.00

TOTAL . . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp #VALUE!
DIBULATKAN . . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp #VALUE!
TERBILANG : TUJUH BELAS JUTA TUJUH RATUS LIMA PULUH ENAM RIBU RUPIAH

VI PEMBANGUNAN GEDUNG PERPUSTAKAAN


1 2 3 4 5 6
I PEKERJAAN PENGECATAN
1 Pek. Plamur Tembok #VALUE! m2 6,956.67 #VALUE!
2 Pek. Cat tembok 3 x jalan #VALUE! m2 7,683.34 #VALUE!
3 Pek. Cat plafond 3 x jalan #REF! m2 7,683.34 #REF!
4 Pek. Cat dasar/kilap kosen 3 x jalan 47.00 m2 12,855.50 604,208.50
5 Pek. Cat dasar/kilap jalusi 3 x jalan 66.23 m2 12,855.50 851,419.77
6 Pek. Cat dasar/kilap listplank 3 x jalan 19.60 m2 12,855.50 251,967.80
7 Pek. Vernis daun pintu/jendela 3 x jalan 14.09 m2 23,425.00 330,058.25
8 Pek. Mengamplas dan Menggosok kayu 146.93 m2 4,020.00 590,658.60
9 Pek. Residu kayu kap/rangka atap Ls Ls 500,000.00 500,000.00
Jumlah #VALUE!
II PEKERJAAN SALURAN AIR HUJAN KELILING BANGUNAN
1 Pek. Pas. Batu Gunung saluran air camp. 1 : 3 56.00 m' 50,000.00 2,800,000.00
2 Pek. Bak Kontrol Pas. Batu 1 : 5 4.00 buah 60,000.00 240,000.00
3 Pek. Hamparan kerikil keliling bangunan 5.25 m3 #REF! #REF!
Jumlah #REF!
III PEKERJAAN PEMBERSIHAN AKHIR
1 Pek. Pembersihan akhir ls ls 150,000.00 150,000.00
Jumlah 150,000.00

REKAPITULASI
JUMLAH
NO. URAIAN DAN JENIS PEKERJAAN HARGA
(Rp)

I PEKERJAAN PENGECATAN . . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp #VALUE!


II PEKERJAAN SALURAN AIR HUJAN KELILING BANGUNAN . . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp #REF!
III PEKERJAAN PEMBERSIHAN AKHIR . . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp 150,000.00

TOTAL . . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp #VALUE!
DIBULATKAN . . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp #VALUE!

TERBILANG : EMPAT BELAS JUTA DUA RATUS TUJUH PULUH LIMA RIBU RUPIAH

REKAPITULASI DANA SWADAYA


JUMLAH
NO. URAIAN DAN JENIS PEKERJAAN HARGA
(Rp)

I PEKERJAAN MOBILER . . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp 152,050,000.00


II PEMBANGUNAN GEDUNG KANTOR . . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp 11,291,000.00
III PEMBANGUNAN 2 ( DUA ) RKB . . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp #VALUE!
IV PEMBANGUNAN 2 ( DUA ) RKB DAN KM/WC . . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp #VALUE!
V PEMBANGUNAN GEDUNG LABORATORIUM IPA . . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp #VALUE!
VI PEMBANGUNAN GEDUNG PERPUSTAKAAN . . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp #VALUE!

TOTAL DANA SWADAYA . . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp #VALUE!

TOTAL DANA SWADAYA . . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp #VALUE!

TERBILANG : DUA RATUS LIMA PULUH JUTA RUPIAH


Disetujui :
PT. ALKOBAR ALAM RAYA Kendari, 20 Desember 2016
### Dibuat Oleh,

ASRIANTO WARJONO, A.Md


Direktur Coast Estimator

TOTAL REKAPITULASI

PEKERJAAN : PEMBANGUNAN PERUMAHAN "GRIYA TIWI BARUGA" TYPE 36


LOKASI : JL. LINGKUNGAN PD. JL. ADE IRMA NASUTION KEL. WATUBANGGA KEC. BARUGA
VOLUME : 119 UNIT
PEMILIK : ASRIANTO ( PT. ALKOBAR ALAM RAYA )

JUMLAH
NO. URAIAN DAN JENIS PEKERJAAN HARGA
(Rp)

A. DANA BLOCK GRANT . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp 8,582,545,000.00

B. DANA IMBAL SWADAYA ( SHARING ) . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp #VALUE!

TOTAL HARGA . . .. . . . . . . .. . . . . . . . . . . . . . . . . Rp #VALUE!


TOTAL HARGA . . .. . . . . . . .. . . . . . . . . . . . . . . . . Rp #VALUE!

TERBILANG : SATU MILYAR DUA RATUS LIMA PULUH JUTA RUPIAH

Disetujui : Kendari, 20 Desember 2016


PT. ALKOBAR ALAM RAYA Dibuat Oleh,
###
ASRIANTO WARJONO, A.Md
Direktur Coast Estimator
90.396
119.33
59.66

12.81
15.25

17.52
49.34
64.14
238.55

33.07
61.95
70.75

21240

12.96
30.24

60185257.35
#REF!

#VALUE!

#VALUE!
#VALUE!
#VALUE!
DAFTAR ANALISA HARGA SATUAN PEKERJAAN

PEKERJAAN : PEMBANGUNAN PERUMAHAN "GRIYA TIWI BARUGA" TYPE 36


LOKASI : JL. LINGKUNGAN PD. JL. ADE IRMA NASUTION KEL. WATUBANGGA KEC. BARUGA
VOLUME : 119 UNIT
PEMILIK : ASRIANTO ( PT. ALKOBAR ALAM RAYA )

1 M3 Pek. Galian Tanah Biasa Sedalam 1 M


Satuan Harga Kuantitas Jumlah
No. Uraian Satuan Harga
A Tenaga Kerja
1 Pekerja Org/Hari 50,000.00 0.4000 20,000.00
2 Mandor Org/Hari 70,000.00 0.0400 2,800.00

Jumlah A 22,800.00
B Bahan

Jumlah B
Harga Satuan A + B 22,800.00

1 M3 Pek. Urugan Kembali


Satuan Harga Kuantitas Jumlah
No. Uraian Satuan Harga
A Tenaga Kerja
1 Pekerja Org/Hari 50,000.00 0.1920 9,600.00
2 Mandor Org/Hari 70,000.00 0.0190 1,330.00

Jumlah A 10,930.00
B Bahan

Jumlah B
Harga Satuan A + B 10,930.00

1 M3 Pek. Urugan Pasir


Satuan Harga Kuantitas Jumlah
No. Uraian Satuan Harga

A Tenaga Kerja
1 Pekerja Org/Hari 50,000.00 0.3000 15,000.00
2 Mandor Org/Hari 70,000.00 0.0100 700.00

Jumlah A 15,700.00

B Bahan
1 Pasir urug m3 75,000.00 1.2000 90,000.00

Jumlah B 90,000.00
Harga Satuan A + B 105,700.00

1 M3 Pek. Urugan Tanah


Satuan Harga Kuantitas Jumlah
No. Uraian Satuan Harga
A Tenaga Kerja
1 Pekerja Org/Hari 50,000.00 0.5000 25,000.00
2 Mandor Org/Hari 70,000.00 0.0500 3,500.00
Jumlah A 28,500.00
B Bahan
1 Tanah urug m3 25,000.00 1.2000 30,000.00
Jumlah B 30,000.00
Harga Satuan A + B 58,500.00
1 M3 Pek. Pasangan Pondasi Batu Kali 1 Pc : 5 Psr
Satuan Harga Kuantitas Jumlah
No. Uraian Satuan Harga

A Tenaga Kerja
1 Tukang Batu Org/Hari 70,000.00 0.6000 42,000.00
2 Kepala Tukang Org/Hari 75,000.00 0.0600 4,500.00
3 Pekerja Org/Hari 50,000.00 1.5000 75,000.00
4 Mandor Org/Hari 70,000.00 0.0750 5,250.00

Jumlah A 126,750.00

B Bahan
1 Batu gunung m3 150,000.00 1.1000 165,000.00
2 Semen Portland kg 1,300.00 136.0000 176,800.00
3 Pasir Pasang m3 125,000.00 0.5440 68,000.00

Jumlah B 409,800.00
Harga Satuan A + B 536,550.00

1 M3 Pek. Pasangan Pondasi Batu Kosong


Satuan Harga Kuantitas Jumlah
No. Uraian Satuan Harga

A Tenaga Kerja
1 Tukang Batu Org/Hari 70,000.00 0.3900 27,300.00
2 Kepala Tukang Org/Hari 75,000.00 0.0390 2,925.00
3 Pekerja Org/Hari 50,000.00 0.7800 39,000.00
4 Mandor Org/Hari 70,000.00 0.0390 2,730.00

Jumlah A 71,955.00

B Bahan
1 Batu gunung m3 150,000.00 1.2000 180,000.00
2 Pasir Urug m3 75,000.00 0.3000 22,500.00

Jumlah B 202,500.00
Harga Satuan A + B 274,455.00

1 M2 Pek. Pasangan Batako 1 Pc : 2 Psr

Satuan Harga Kuantitas Jumlah


No. Uraian Satuan Harga

A Tenaga Kerja
1 Tukang Batu Org/Hari 70,000.00 0.1000 7,000.00
2 Kepala Tukang Org/Hari 75,000.00 0.0100 750.00
3 Pekerja Org/Hari 50,000.00 0.3200 16,000.00
4 Mandor Org/Hari 70,000.00 0.0150 1,050.00

Jumlah A 24,800.00

B Bahan
1 Batako bh 3,700.00 1.2500 4,625.00
2 Semen Portland kg 1,300.00 1.8950 2,463.50
3 Pasir Pasang m3 125,000.00 0.0960 12,000.00

Jumlah B 19,088.50
Harga Satuan A + B 43,888.50
1 M2 Pek. Pasangan Batako 1 Pc : 5 Psr
Satuan Harga Kuantitas Jumlah
No. Uraian Satuan Harga

A Tenaga Kerja
1 Tukang Batu Org/Hari 70,000.00 0.1500 10,500.00
2 Kepala Tukang Org/Hari 75,000.00 0.0150 1,125.00
3 Pekerja Org/Hari 50,000.00 0.3500 17,500.00
4 Mandor Org/Hari 70,000.00 0.0170 1,190.00

Jumlah A 30,315.00

B Bahan
1 Batako bh 3,700.00 1.2500 4,625.00
2 Semen Portland kg 1,300.00 1.3500 1,755.00
3 Pasir Pasang m3 125,000.00 0.0448 5,600.00

Jumlah B 11,980.00

Harga Satuan A + B 42,295.00

1 M2 Pek. Plesteran 1 Pc : 2 Psr, Tebal 15 mm


Satuan Harga Kuantitas Jumlah
No. Uraian Satuan Harga

A Tenaga Kerja
1 Tukang Batu Org/Hari 70,000.00 0.1500 10,500.00
2 Kepala Tukang Org/Hari 75,000.00 0.0150 1,125.00
3 Pekerja Org/Hari 50,000.00 0.2000 10,000.00
4 Mandor Org/Hari 70,000.00 0.0100 700.00

Jumlah A 22,325.00

B Bahan
1 Semen Portland kg 1,300.00 8.5200 11,076.00
2 Pasir Pasang m3 125,000.00 0.0170 2,125.00

Jumlah B 13,201.00
Harga Satuan A + B 35,526.00

13 1 M2 Pek. Plesteran 1 Pc : 3 Psr, Tebal 15 mm


Satuan Harga Kuantitas Jumlah
No. Uraian Satuan Harga

A Tenaga Kerja
1 Tukang Batu Org/Hari 70,000.00 0.1500 10,500.00
2 Kepala Tukang Org/Hari 75,000.00 0.0150 1,125.00
3 Pekerja Org/Hari 50,000.00 0.2000 10,000.00
4 Mandor Org/Hari 70,000.00 0.0100 700.00

Jumlah A 22,325.00

B Bahan
1 Semen Portland kg 1,300.00 6.4800 8,424.00
2 Pasir Pasang m3 125,000.00 0.0190 2,375.00

Jumlah B 10,799.00
Harga Satuan A + B 33,124.00

1 M2 Pek. Plesteran 1 Pc : 5 Psr, Tebal 15 mm

Satuan Harga Kuantitas Jumlah


No. Uraian Satuan Harga

A Tenaga Kerja
1 Tukang Batu Org/Hari 70,000.00 0.1500 10,500.00
2 Kepala Tukang Org/Hari 75,000.00 0.0150 1,125.00
3 Pekerja Org/Hari 50,000.00 0.2000 10,000.00
4 Mandor Org/Hari 70,000.00 0.0100 700.00

Jumlah A 22,325.00

B Bahan
1 Semen Portland kg 1,300.00 4.3200 5,616.00
2 Pasir Pasang m3 125,000.00 0.0220 2,750.00

Jumlah B 8,366.00

Harga Satuan A + B 30,691.00

1 M2 Pek. Plesteran di aci 1 Pc : 3 Psr, Tebal 15 mm


Satuan Harga Kuantitas Jumlah
No. Uraian Satuan Harga

A Tenaga Kerja
1 Tukang Batu Org/Hari 70,000.00 0.1500 10,500.00
2 Kepala Tukang Org/Hari 75,000.00 0.0150 1,125.00
3 Pekerja Org/Hari 50,000.00 0.2000 10,000.00
4 Mandor Org/Hari 70,000.00 0.0100 700.00

Jumlah A 22,325.00

B Bahan
1 Semen Portland kg 1,300.00 8.4800 11,024.00
2 Pasir Pasang m3 125,000.00 0.0220 2,750.00

Jumlah B 13,774.00

Harga Satuan A + B 36,099.00

1 M3 Pek. Kusen Pintu/Jendela Kayu Klas II.A


Satuan Harga Kuantitas Jumlah
No. Uraian Satuan Harga

A Tenaga Kerja
1 Tukang Kayu Org/Hari 70,000.00 18.0000 1,260,000.00
2 Kepala Tukang Org/Hari 75,000.00 2.0000 150,000.00
3 Pekerja Org/Hari 50,000.00 6.0000 300,000.00
4 Mandor Org/Hari 70,000.00 0.3000 21,000.00

Jumlah A 1,731,000.00

B Bahan
1 Kayu KLs II.A (Kelapi) m3 2,000,000.00 1.2000 2,400,000.00
Jumlah B 2,400,000.00
Harga Satuan A + B 4,131,000.00

1 M3 Pek. Pasang Pintu Panil Jati


Satuan Harga Kuantitas Jumlah
No. Uraian Satuan Harga

A Tenaga Kerja
1 Tukang Kayu Org/Hari 70,000.00 2.5000 175,000.00
2 Kepala Tukang Org/Hari 75,000.00 0.2500 18,750.00
3 Pekerja Org/Hari 50,000.00 1.0000 50,000.00
4 Mandor Org/Hari 70,000.00 0.0500 3,500.00

Jumlah A 247,250.00

B Bahan
1 Papan Kayu Kls I m3 2,400,000.00 0.0400 96,000.00

Jumlah B 96,000.00
Harga Satuan A + B 343,250.00

1 M3 Pek. Pasang Pintu dan Jendela Kaca Kayu Jati


Satuan Harga Kuantitas Jumlah
No. Uraian Satuan Harga

A Tenaga Kerja
1 Tukang Kayu Org/Hari 70,000.00 2.0000 140,000.00
2 Kepala Tukang Org/Hari 75,000.00 0.2000 15,000.00
3 Pekerja Org/Hari 50,000.00 0.8000 40,000.00
4 Mandor Org/Hari 70,000.00 0.0400 2,800.00

Jumlah A 197,800.00

B Bahan
1 Papan Kayu Kls I m3 2,400,000.00 0.0350 84,000.00

Jumlah B 84,000.00
Harga Satuan A + B 281,800.00

1 M3 Pek. Pasang Jalusi Mati Kusen


Satuan Harga Kuantitas Jumlah
No. Uraian Satuan Harga

A Tenaga Kerja
1 Tukang Kayu Org/Hari 70,000.00 2.0000 140,000.00
2 Kepala Tukang Org/Hari 75,000.00 0.2000 15,000.00
3 Pekerja Org/Hari 50,000.00 0.5000 25,000.00
4 Mandor Org/Hari 70,000.00 0.0250 1,750.00

Jumlah A 181,750.00

B Bahan
1 Papan Kayu Kls II m3 1,800,000.00 0.0600 108,000.00
2 Paku Campur kg 15,000.00 0.1500 2,250.00

Jumlah B 110,250.00
Harga Satuan A + B 292,000.00

1 M2 Pek. Pasangan Kaca bening 5 mm

Satuan Harga Kuantitas Jumlah


No. Uraian Satuan Harga

A Tenaga Kerja
1 Tukang Kayu Org/Hari 70,000.00 0.1500 10,500.00
2 Kepala Tukang Org/Hari 75,000.00 0.0150 1,125.00
3 Pekerja Org/Hari 50,000.00 0.0150 750.00
4 Mandor Org/Hari 70,000.00 0.0008 52.50

Jumlah A 12,427.50

B Bahan
1 Kaca bening 5 mm m2 90,000.00 1.1000 99,000.00

Jumlah B 99,000.00

Harga Satuan A + B 111,427.50

1 M3 Pek. Pasang Konstruksi Kuda-Kuda Kayu Kelas II.A


Satuan Harga Kuantitas Jumlah
No. Uraian Satuan Harga

A Tenaga Kerja
1 Tukang Kayu Org/Hari 70,000.00 12.0000 840,000.00
2 Kepala Tukang Org/Hari 75,000.00 1.2000 90,000.00
3 Pekerja Org/Hari 50,000.00 4.0000 200,000.00
4 Mandor Org/Hari 70,000.00 0.2000 14,000.00

Jumlah A 1,144,000.00

B Bahan
1 Kayu Kls II m3 2,000,000.00 1.1000 2,200,000.00
2 Beugel/baut/Angker Besi, Besi Streep kg 5,000.00 15.0000 75,000.00
3 Paku 2" - 5" kg 15,000.00 0.8000 12,000.00

Jumlah B 2,287,000.00
Harga Satuan A + B 3,431,000.00

1 M3 Pek. Pasang Gording Kayu Kls II


Satuan Harga Kuantitas Jumlah
No. Uraian Satuan Harga

A Tenaga Kerja
1 Tukang Kayu Org/Hari 70,000.00 12.0000 840,000.00
2 Kepala Tukang Org/Hari 75,000.00 1.2000 90,000.00
3 Pekerja Org/Hari 50,000.00 4.0000 200,000.00
4 Mandor Org/Hari 70,000.00 0.2000 14,000.00
Jumlah A 1,144,000.00

B Bahan
1 Kayu Kls II m3 1,800,000.00 1.1000 1,980,000.00
2 Paku 2" - 5" kg 15,000.00 0.8000 12,000.00

Jumlah B 1,992,000.00
Harga Satuan A + B 3,136,000.00

1 M' Pek. Pasang Listplank 2 x (3 x 20) Cm, Kayu Klas II


Satuan Harga Kuantitas Jumlah
No. Uraian Satuan Harga

A Tenaga Kerja
1 Tukang Kayu Org/Hari 70,000.00 0.2500 17,500.00
2 Kepala Tukang Org/Hari 75,000.00 0.0250 1,875.00
3 Pekerja Org/Hari 50,000.00 0.1500 7,500.00
4 Mandor Org/Hari 70,000.00 0.0750 5,250.00

Jumlah A 32,125.00

B Bahan
1 Kayu Kls II m3 1,800,000.00 0.0145 26,100.00
2 Paku Campur kg 15,000.00 0.0600 900.00

Jumlah B 27,000.00
Harga Satuan A + B 59,125.00

1 M2 Pek. Rangka Plafond dan Penggantung

Satuan Harga Kuantitas Jumlah


No. Uraian Satuan Harga

A Tenaga Kerja
1 Tukang Kayu Org/Hari 70,000.00 0.2500 17,500.00
2 Kepala Tukang Org/Hari 75,000.00 0.0250 1,875.00
3 Pekerja Org/Hari 50,000.00 0.1500 7,500.00
4 Mandor Org/Hari 70,000.00 0.0750 5,250.00

Jumlah A 32,125.00

B Bahan
1 Kayu Kls II m3 1,800,000.00 0.0120 21,600.00
2 Paku Campur kg 15,000.00 0.1000 1,500.00

Jumlah B 23,100.00

Harga Satuan A + B 55,225.00

1 M2 Pek. Plafond Tripleks (60 x 120) 3 mm

Satuan Harga Kuantitas Jumlah


No. Uraian Satuan Harga

A Tenaga Kerja
1 Tukang Kayu Org/Hari 70,000.00 0.1000 7,000.00
2 Kepala Tukang Org/Hari 75,000.00 0.0100 750.00
3 Pekerja Org/Hari 50,000.00 0.0700 3,500.00
4 Mandor Org/Hari 70,000.00 0.0035 245.00
Jumlah A 11,495.00

B Bahan
1 Tripleks tebal 3 mm Lbr 50,000.00 0.3500 17,500.00
2 Paku Tripleks kg 20,000.00 0.0200 400.00

Jumlah B 17,900.00

Harga Satuan A + B 29,395.00

1 M' Pek. Pasang List Plafond Kayu 3/4 (profil)


Satuan Harga Kuantitas Jumlah
No. Uraian Satuan Harga

A Tenaga Kerja
1 Tukang Kayu Org/Hari 70,000.00 0.0210 1,470.00
2 Kepala Tukang Org/Hari 75,000.00 0.0020 150.00
3 Pekerja Org/Hari 50,000.00 0.0210 1,050.00
4 Mandor Org/Hari 70,000.00 0.0010 70.00
Jumlah A 2,740.00
B Bahan
1 List Plafond kayu klas II Uk. 1 x 4 cm m' 2,500.00 1.0500 2,625.00
2 Paku Campur kg 20,000.00 0.0100 200.00

Jumlah B 2,825.00

Harga Satuan A + B 5,565.00

1 M3 Membuat Beton Tumbuk 1 Pc : 3 Psr : 5 Krl


Satuan Harga Kuantitas Jumlah
No. Uraian Satuan Harga

A Tenaga Kerja
1 Tukang Batu Org/Hari 70,000.00 0.2500 17,500.00
2 Kepala Tukang Org/Hari 75,000.00 0.0250 1,875.00
3 Pekerja Org/Hari 50,000.00 1.6500 82,500.00
4 Mandor Org/Hari 70,000.00 0.0800 5,600.00
Jumlah A 107,475.00
B Bahan
1 Semen kg 1,300.00 218.0000 283,400.00
2 Pasir Beton m3 125,000.00 0.5200 65,000.00
3 Batu Pecah/Kerikil beton m3 175,000.00 0.8700 152,250.00
Jumlah B 500,650.00
Harga Satuan A + B 608,125.00

1 M1 Membuat Kolom Penguat Beton Bertulang (12 x 12) Cm


Satuan Harga Kuantitas Jumlah
No. Uraian Satuan Harga

A Tenaga Kerja
1 Tukang Batu Org/Hari 70,000.00 0.0200 1,400.00
2 Tukang Kayu Org/Hari 70,000.00 0.0200 1,400.00
3 Tukang Besi Org/Hari 70,000.00 0.0200 1,400.00
4 Kepala Tukang Org/Hari 75,000.00 0.0060 450.00
5 Pekerja Org/Hari 50,000.00 0.0600 3,000.00
6 Mandor Org/Hari 70,000.00 0.0030 210.00
Jumlah A 7,860.00

B Bahan
1 Kayu papan m3 900,000.00 0.0020 1,800.00
2 Paku campur kg 15,000.00 0.0100 150.00
3 Besi Beton kg 7,000.00 3.0000 21,000.00
4 Kawat Beton kg 15,000.00 0.4500 6,750.00
5 Semen kg 1,300.00 4.0000 5,200.00
6 Pasir Beton m3 125,000.00 0.0060 750.00
7 Batu Pecah/Kerikil beton m3 175,000.00 0.0090 1,575.00

Jumlah B 37,225.00
Harga Satuan A + B 45,085.00

1 M3 Membuat Kolom Beton Bertulang (234 Kg Besi + Bekisting)

Satuan Harga Kuantitas Jumlah


No. Uraian Satuan Harga
A Tenaga Kerja
1 Tukang Batu Org/Hari 70,000.00 0.2800 19,600.00
2 Tukang Kayu Org/Hari 70,000.00 2.6400 184,800.00
3 Tukang Besi Org/Hari 70,000.00 1.6800 117,600.00
4 Kepala Tukang Org/Hari 75,000.00 0.4560 34,200.00
5 Pekerja Org/Hari 50,000.00 5.8400 292,000.00
6 Mandor Org/Hari 70,000.00 0.2000 14,000.00
Jumlah A 662,200.00
B Bahan
1 Paku campur kg 15,000.00 3.2000 48,000.00
2 Minyak bekisting ltr 5,000.00 1.6000 8,000.00
3 Besi Beton kg 7,000.00 240.0000 1,680,000.00
4 Kawat Beton kg 15,000.00 3.6000 54,000.00
5 Semen kg 1,300.00 187.2000 243,360.00
6 Pasir Beton m3 125,000.00 0.4160 52,000.00
7 Batu Pecah/Kerikil beton m3 175,000.00 0.6240 109,200.00
8 Balok Kayu m3 900,000.00 0.1200 108,000.00
9 Papan bekisting m3 900,000.00 0.3200 288,000.00
10 Dolken dia. 8 cm / 4 cm btg 3,000.00 16.0000 48,000.00
11 Plywood 9 mm lbr 110,000.00 2.8000 308,000.00
Jumlah B 2,946,560.00
Harga Satuan A + B 3,608,760.00

1 M1 Membuat Sloof / Ringbalk Beton Bertulang (15 x 20) Cm


Satuan Harga Kuantitas Jumlah
No. Uraian Satuan Harga
A Tenaga Kerja
1 Tukang Batu Org/Hari 70,000.00 0.0330 2,310.00
2 Tukang Kayu Org/Hari 70,000.00 0.0330 2,310.00
3 Tukang Besi Org/Hari 70,000.00 0.0330 2,310.00
4 Kepala Tukang Org/Hari 75,000.00 0.0100 750.00
5 Pekerja Org/Hari 50,000.00 0.1000 5,000.00
6 Mandor Org/Hari 70,000.00 0.0050 350.00
Jumlah A 13,030.00
B Bahan
1 Kayu papan klas III m3 900,000.00 0.0030 2,700.00
2 Paku campur kg 15,000.00 0.0200 300.00
3 Besi Beton kg 7,000.00 3.6000 25,200.00
4 Kawat Beton kg 15,000.00 0.0500 750.00
5 Semen portland kg 1,300.00 5.5000 7,150.00
6 Pasir Beton m3 125,000.00 0.0090 1,125.00
7 Batu Pecah/Kerikil beton m3 175,000.00 0.0150 2,625.00
Jumlah B 39,850.00
Harga Satuan A + B 52,880.00

1 M2 Pek. Pasangan Atap Seng Soka Jempol


Satuan Harga Kuantitas Jumlah
No. Uraian Satuan Harga
A Tenaga Kerja
1 Tukang Kayu Org/Hari 70,000.00 0.0600 4,200.00
2 Kepala Tukang Org/Hari 75,000.00 0.0060 450.00
3 Pekerja Org/Hari 50,000.00 0.1200 6,000.00
4 Mandor Org/Hari 70,000.00 0.0060 420.00
Jumlah A 11,070.00
B Bahan
1 Atap seng BJLS 20, 9 KK Lbr 49,500.00 0.7000 34,650.00
2 Paku seng kg 20,000.00 0.0200 400.00
Jumlah B 35,050.00
Harga Satuan A + B 46,120.00

1 M2 Pek. Atap Nok Seng Soka Jempol


Satuan Harga Kuantitas Jumlah
No. Uraian Satuan Harga
A Tenaga Kerja
1 Tukang Kayu Org/Hari 70,000.00 0.0700 4,900.00
2 Kepala Tukang Org/Hari 75,000.00 0.0080 600.00
3 Pekerja Org/Hari 50,000.00 0.1500 7,500.00
4 Mandor Org/Hari 70,000.00 0.0060 420.00
Jumlah A 13,420.00
B Bahan
1 Seng plat BJLS 20 m1 15,000.00 0.3000 4,500.00
2 Papan Kayu Klas II 2/20 M3 1,800,000.00 0.0040 7,200.00
3 Paku seng kg 20,000.00 0.0400 800.00
Jumlah B 12,500.00
Harga Satuan A + B 25,920.00

1 M2 Pek. Plamur Tembok


Satuan Harga Kuantitas Jumlah
No. Uraian Satuan Harga
A Tenaga Kerja
1 Tukang Cat Org/Hari 70,000.00 0.0600 4,200.00
2 Kepala Tukang Org/Hari 75,000.00 0.0060 450.00
3 Pekerja Org/Hari 50,000.00 0.0333 1,666.67
4 Mandor Org/Hari 70,000.00 0.0020 140.00
Jumlah A 6,456.67
B Bahan
1 Plamur Tembok kg 5,000.00 0.1000 500.00

Jumlah B 500.00
Harga Satuan A + B 6,956.67

1 M2 Pek. Plamir, Cat Dasar, Cat Kilap Kayu 2 x


Satuan Harga Kuantitas Jumlah
No. Uraian Satuan Harga
A Tenaga Kerja
1 Tukang Cat Org/Hari 70,000.00 0.0700 4,900.00
2 Kepala Tukang Org/Hari 75,000.00 0.0027 202.50
3 Pekerja Org/Hari 50,000.00 0.0467 2,335.00
4 Mandor Org/Hari 70,000.00 0.0017 119.00
Jumlah A 7,556.50
B Bahan
1 Cat meny kg 10,000.00 0.1333 1,333.00
2 Plamir kg 5,000.00 0.1000 500.00
3 Cat dasar kg 10,000.00 0.1133 1,133.00
4 Cat penutup/kilap 3 x kg 10,000.00 0.2333 2,333.00
Jumlah B 5,299.00
Harga Satuan A + B 12,855.50

1 M2 Pek. Cat Tembok/Plafond 2 x


Satuan Harga Kuantitas Jumlah
No. Uraian Satuan Harga
A Tenaga Kerja
1 Tukang Cat Org/Hari 70,000.00 0.0600 4,200.00
2 Kepala Tukang Org/Hari 75,000.00 0.0060 450.00
3 Pekerja Org/Hari 50,000.00 0.0333 1,666.67
4 Mandor Org/Hari 70,000.00 0.0020 140.00
Jumlah A 6,456.67
B Bahan
3 Cat tembok/penutup 2 x kg 5,000.00 0.2453 1,226.67

Jumlah B 1,226.67
Harga Satuan A + B 7,683.34

1 M2 Pelaburan Bidang Kayu Dengan Vernis


Satuan Harga Kuantitas Jumlah
No. Uraian Satuan Harga
A Tenaga Kerja
1 Tukang Cat Org/Hari 70,000.00 0.1600 11,200.00
2 Kepala Tukang Org/Hari 75,000.00 0.0160 1,200.00
3 Pekerja Org/Hari 50,000.00 0.1600 8,000.00
4 Mandor Org/Hari 70,000.00 0.0025 175.00
Jumlah A 20,575.00
B Bahan
1 Vernis ltr 15,000.00 0.1500 2,250.00
2 Dempul kg 5,000.00 0.0500 250.00
3 Amplas lbr 2,500.00 0.1000 250.00
4 Kuas bh 10,000.00 0.0100 100.00
Jumlah B 2,850.00
Harga Satuan A + B 23,425.00

1 M2 Pengecatan Permukaan Seng 3 x jalan

Satuan Harga Kuantitas Jumlah


No. Uraian Satuan Harga

A Tenaga Kerja
1 Tukang Cat Org/Hari 70,000.00 0.7000 49,000.00
2 Kepala Tukang Org/Hari 75,000.00 0.0075 562.50
3 Pekerja Org/Hari 50,000.00 0.0500 2,500.00
4 Mandor Org/Hari 70,000.00 0.0025 175.00
Jumlah A 52,237.50

B Bahan
1 Cat Dasar / Meni besi kg 10,000.00 0.1100 1,100.00
2 Cat Antara kg 10,000.00 0.1700 1,700.00
3 Cat Penutup kg 10,000.00 0.0800 800.00
Jumlah B 3,600.00

Harga Satuan A + B 55,837.50

1 Buah Pasang Kunci Tanam Anchor 693 LD 2 x putar


Satuan Harga Kuantitas Jumlah
No. Uraian Satuan Harga
A Tenaga Kerja
1 Tukang Kayu Org/Hari 70,000.00 0.5000 35,000.00
2 Kepala Tukang Org/Hari 75,000.00 0.0100 750.00
3 Pekerja Org/Hari 50,000.00 0.0100 500.00
4 Mandor Org/Hari 70,000.00 0.0050 350.00
Jumlah A 36,600.00
B Bahan
1 Kunci Tanam Anchor 693 LD 2 x putar bh 150,000.00 1.0000 150,000.00
Jumlah B 150,000.00
Harga Satuan A + B 186,600.00

1 Buah Pasang Engsel Pintu


Satuan Harga Kuantitas Jumlah
No. Uraian Satuan Harga
A Tenaga Kerja
1 Tukang Kayu Org/Hari 70,000.00 0.1500 10,500.00
2 Kepala Tukang Org/Hari 75,000.00 0.0150 1,125.00
3 Pekerja Org/Hari 50,000.00 0.0150 750.00
4 Mandor Org/Hari 70,000.00 0.0008 56.00
Jumlah A 12,431.00
B Bahan
1 Engsel pintu bh 5,000.00 1.0000 5,000.00
Jumlah B 5,000.00
Harga Satuan A + B 17,431.00

1 Buah Pasang Engsel Jendela Kupu - Kupu


Satuan Harga Kuantitas Jumlah
No. Uraian Satuan Harga
A Tenaga Kerja
1 Tukang Kayu Org/Hari 70,000.00 0.1000 7,000.00
2 Kepala Tukang Org/Hari 75,000.00 0.0100 750.00
3 Pekerja Org/Hari 50,000.00 0.0100 500.00
4 Mandor Org/Hari 70,000.00 0.0005 35.00
Jumlah A 8,285.00
B Bahan
1 Engsel Kupu-kupu bh 4,000.00 1.0000 4,000.00
Jumlah B 4,000.00
Harga Satuan A + B 12,285.00

1 Buah Pasang Kait Angin


Satuan Harga Kuantitas Jumlah
No. Uraian Satuan Harga
A Tenaga Kerja
1 Tukang Kayu Org/Hari 70,000.00 0.1500 10,500.00
2 Kepala Tukang Org/Hari 75,000.00 0.0150 1,125.00
3 Pekerja Org/Hari 50,000.00 0.0150 750.00
4 Mandor Org/Hari 70,000.00 0.0008 56.00
Jumlah A 12,431.00
B Bahan
1 Kait angin bh 3,000.00 1.0000 3,000.00
Jumlah B 3,000.00
Harga Satuan A + B 15,431.00

1 Buah Pasang Grendel Pintu


Satuan Harga Kuantitas Jumlah
No. Uraian Satuan Harga
A Tenaga Kerja
1 Tukang Kayu Org/Hari 70,000.00 0.1500 10,500.00
2 Kepala Tukang Org/Hari 75,000.00 0.0150 1,125.00
3 Pekerja Org/Hari 50,000.00 0.0150 750.00
4 Mandor Org/Hari 70,000.00 0.0008 56.00
Jumlah A 12,431.00
B Bahan
1 Grendel Pintu bh 3,000.00 1.0000 3,000.00

Jumlah B 3,000.00

Harga Satuan A + B 15,431.00

1 Buah pasang Grendel Jendela


Satuan Harga Kuantitas Jumlah
No. Uraian Satuan Harga
A Tenaga Kerja
1 Tukang Kayu Org/Hari 70,000.00 0.1500 10,500.00
2 Kepala Tukang Org/Hari 75,000.00 0.0150 1,125.00
3 Pekerja Org/Hari 50,000.00 0.0150 750.00
4 Mandor Org/Hari 70,000.00 0.0008 56.00
Jumlah A 12,431.00

B Bahan
1 Grendel jendela bh 3,000.00 1.0000 3,000.00
Jumlah B 3,000.00
Harga Satuan A + B 15,431.00

Anl. SUPL : 1 M' Pek. Pasang List Kaca Kayu 1 x 1 cm


Satuan Harga Kuantitas Jumlah
No. Uraian Satuan Harga
A Tenaga Kerja
1 Tukang Kayu Org/Hari 70,000.00 0.0210 1,470.00
2 Kepala Tukang Org/Hari 75,000.00 0.0020 150.00
3 Pekerja Org/Hari 50,000.00 0.0210 1,050.00
4 Mandor Org/Hari 70,000.00 0.0010 70.00
Jumlah A 2,740.00
B Bahan
1 List Kaca 1 x 1 cm m' 2,500.00 1.0500 2,625.00
2 Paku Tripleks kg 20,000.00 0.0010 20.00
Jumlah B 2,645.00
Harga Satuan A + B 5,385.00

1 M2 Mendempul dan Menggosok Kayu


Satuan Harga Kuantitas Jumlah
No. Uraian Satuan Harga
A Tenaga Kerja
1 Tukang Cat Org/Hari 70,000.00 0.0400 2,800.00
2 Kepala Tukang Org/Hari 75,000.00 0.0040 300.00
3 Pekerja Org/Hari 50,000.00 0.0025 125.00
4 Mandor Org/Hari 70,000.00 0.0010 70.00
Jumlah A 3,295.00
B Bahan
1 Dempul Kg 5,000.00 0.0800 400.00
2 Minyak Cat kg 15,000.00 0.0200 300.00
3 Amplas kg 2,500.00 0.0100 25.00
Jumlah B 725.00
Harga Satuan A + B 4,020.00

1 M2 Pas. Tegel Keramik Uk. 30 x 30 cm

Satuan Harga Kuantitas Jumlah


No. Uraian Satuan Harga

A Tenaga Kerja
1 Tukang Batu Org/Hari 70,000.00 0.3500 24,500.00
2 Kepala Tukang Org/Hari 75,000.00 0.0350 2,625.00
3 Pekerja Org/Hari 50,000.00 0.6200 31,000.00
4 Mandor Org/Hari 70,000.00 0.0300 2,100.00

Jumlah A 60,225.00

B Bahan
1 Tegel keramik 30 x 30 cm bh 5,000.00 11.0000 55,000.00
2 Semen warna kg 2,500.00 1.5000 3,750.00
3 Semen portland kg 1,300.00 11.3800 14,794.00
4 Pasir Pasang m3 125,000.00 0.0420 5,250.00

Jumlah B 78,794.00

Harga Satuan A + B 139,019.00

1 M' Pas. Tegel Plint Keramik 15 x 30 cm

Satuan Harga Kuantitas Jumlah


No. Uraian Satuan Harga

A Tenaga Kerja
1 Tukang Batu Org/Hari 70,000.00 0.0900 6,300.00
2 Kepala Tukang Org/Hari 75,000.00 0.0090 675.00
3 Pekerja Org/Hari 50,000.00 0.9000 45,000.00
4 Mandor Org/Hari 70,000.00 0.0045 315.00
Jumlah A 52,290.00

B Bahan
1 Tegel keramik 15 x 30 cm bh 2,500.00 2.5000 6,250.00
2 Semen warna kg 2,500.00 0.1000 250.00
3 Semen portland kg 1,300.00 1.6500 2,145.00
4 Pasir Pasang m3 125,000.00 0.0032 400.00

Jumlah B 9,045.00

Harga Satuan A + B 61,335.00

1 M2 Pasangan Lantai Keramik Anti Slip 20 x 20 Cm

Satuan Harga Kuantitas Jumlah


No. Uraian Satuan Harga

A Tenaga Kerja
1 Tukang Batu Org/Hari 70,000.00 0.3500 15,750.00
2 Kepala Tukang Org/Hari 75,000.00 0.0350 1,925.00
3 Pekerja Org/Hari 50,000.00 0.6200 17,360.00
4 Mandor Org/Hari 70,000.00 0.0300 1,050.00

Jumlah A 36,085.00

B Bahan
1 Tegel keramik 20 x 20 cm bh 2,500.00 25.0000 62,500.00
2 Semen warna kg 2,500.00 1.5000 6,000.00
3 Semen portland kg 1,300.00 11.3800 9,673.00
4 Pasir Pasang m3 125,000.00 0.0420 4,620.00

Jumlah B 82,793.00
Harga Satuan A + B 118,878.00

1 M2 Pasangan dinding Tegel Keramik 20 x 25 Cm

Satuan Harga Kuantitas Jumlah


No. Uraian Satuan Harga

A Tenaga Kerja
1 Tukang Batu Org/Hari 70,000.00 0.3500 24,500.00
2 Kepala Tukang Org/Hari 75,000.00 0.0350 2,625.00
3 Pekerja Org/Hari 50,000.00 0.6200 31,000.00
4 Mandor Org/Hari 70,000.00 0.0300 2,100.00

Jumlah A 60,225.00

B Bahan
1 Tegel keramik 20 x 25 cm bh 3,000.00 20.0000 60,000.00
2 Semen warna kg 2,500.00 1.5000 3,750.00
3 Semen portland kg 1,300.00 11.3800 14,794.00
4 Pasir Pasang m3 125,000.00 0.0420 5,250.00

Jumlah B 83,794.00

Harga Satuan A + B 144,019.00

1 Buah pemasangan wastafel

Satuan Harga Kuantitas Jumlah


No. Uraian Satuan Harga

A Tenaga Kerja
1 Tukang Batu Org/Hari 70,000.00 1.4500 101,500.00
2 Kepala Tukang Org/Hari 75,000.00 0.1500 11,250.00
3 Pekerja Org/Hari 50,000.00 1.2000 60,000.00
4 Mandor Org/Hari 70,000.00 0.1000 7,000.00

Jumlah A 179,750.00

B Bahan
1 Wastafel bh 150,000.00 1.0000 150,000.00
2 Perlengkapan ( 12 % harga wastafel ) bh 150,000.00 0.1200 18,000.00
3 Semen portland kg 1,300.00 6.0000 7,800.00
4 Pasir Pasang m3 125,000.00 0.0100 1,250.00

Jumlah B 177,050.00

Harga Satuan A + B 356,800.00

1 Buah pemasangan bak mandi fiberglas

Satuan Harga Kuantitas Jumlah


No. Uraian Satuan Harga

A Tenaga Kerja
1 Tukang Batu Org/Hari 70,000.00 2.7000 189,000.00
2 Kepala Tukang Org/Hari 75,000.00 0.5400 40,500.00
3 Pekerja Org/Hari 50,000.00 1.8000 90,000.00
4 Mandor Org/Hari 70,000.00 0.1100 7,700.00

Jumlah A 327,200.00

B Bahan
1 Bak fiberglass bh 325,000.00 1.0000 325,000.00
2 Perlengkapan ( 18 % harga bak fiberglass ) bh 325,000.00 0.1800 58,500.00

Jumlah B 383,500.00

Harga Satuan A + B 710,700.00

1 Buah pemasangan klosed jongkok porselen

Satuan Harga Kuantitas Jumlah


No. Uraian Satuan Harga

A Tenaga Kerja
1 Tukang Batu Org/Hari 70,000.00 1.5000 105,000.00
2 Kepala Tukang Org/Hari 75,000.00 1.5000 112,500.00
3 Pekerja Org/Hari 50,000.00 1.0000 50,000.00
4 Mandor Org/Hari 70,000.00 0.1600 11,200.00

Jumlah A 278,700.00

B Bahan
1 Klosed jongkok bh 110,000.00 1.0000 110,000.00
2 Semen portland kg 1,300.00 6.0000 7,800.00
3 Pasir Pasang m3 325,000.00 0.0100 3,250.00

Jumlah B 121,050.00

Harga Satuan A + B 399,750.00

1 Buah pemasangan kran air

Satuan Harga Kuantitas Jumlah


No. Uraian Satuan Harga

A Tenaga Kerja
1 Tukang Batu Org/Hari 70,000.00 0.1000 7,000.00
2 Kepala Tukang Org/Hari 75,000.00 0.0100 750.00
3 Pekerja Org/Hari 50,000.00 0.0100 500.00
4 Mandor Org/Hari 70,000.00 0.0050 350.00

Jumlah A 8,600.00

B Bahan
1 Kran air bh 15,000.00 1.0000 15,000.00
2 Seal tape bh 2,500.00 0.0250 62.50

Jumlah B 15,062.50

Harga Satuan A + B 23,662.50

1 Buah pemasangan floor drain

Satuan Harga Kuantitas Jumlah


No. Uraian Satuan Harga

A Tenaga Kerja
1 Tukang Batu Org/Hari 70,000.00 0.1000 7,000.00
2 Kepala Tukang Org/Hari 75,000.00 0.0100 750.00
3 Pekerja Org/Hari 50,000.00 0.0100 500.00
4 Mandor Org/Hari 70,000.00 0.0050 350.00

Jumlah A 8,600.00

B Bahan
1 Floor drain bh 10,000.00 1.0000 10,000.00

Jumlah B 10,000.00

Harga Satuan A + B 18,600.00

Kendari, 20 Desember 2016


Disetujui : Dibuat Oleh,
PT. ALKOBAR ALAM RAYA

ASRIANTO WARJONO, A.Md


Direktur Coast Estimator
DAFTAR HARGA BAHAN DAN UPAH KERJA
PEKERJAAN : PEMBANGUNAN PERUMAHAN "GRIYA TIWI BARUGA" TYPE 36
LOKASI : JL. LINGKUNGAN PD. JL. ADE IRMA NASUTION KEL. WATUBANGGA KEC. BARUGA
VOLUME : 119 UNIT
PEMILIK : ASRIANTO ( PT. ALKOBAR ALAM RAYA )

HARGA
NO. URAIAN JENIS TENAGA / BAHAN SATUAN ( Rp )
1 2 3 4
I UPAH TENAGA KERJA
1 Pekerja Hari Rp. 50,000.00
2 Mandor Hari Rp. 70,000.00
3 Tukang Batu Hari Rp. 70,000.00
4 Tukang Batu Hari Rp. 70,000.00
5 Tukang Besi Hari Rp. 70,000.00
6 Tukang Cat Hari Rp. 70,000.00
7 Kepala Tukang Batu, Kayu, Besi, Cat Hari Rp. 75,000.00

II HARGA BAHAN
1 Tanah Urug M3 Rp. 25,000.00
2 Pasir Urug M3 Rp. 75,000.00
3 Pasir Pasang M3 Rp. 125,000.00
4 Pasir Beton M3 Rp. 125,000.00
5 Portland Cement (PC) merk Tonasa Kg Rp. 1,300.00
6 Semen Warna Kg Rp. 2,500.00
7 Kerikil Beton M3 Rp. 175,000.00
8 Batu Gunung / Batu Kali M3 Rp. 150,000.00
9 Batako Bh Rp. 500.00
10 Besi Beugel/baut/Angker Kuda-kuda Kg Rp. 5,000.00
11 Besi Beton Kg Rp. 7,000.00
12 Atap Seng Gelombang Besar Merk Kijang KK Rp. 5,500.00
13 Seng Plat BJLS 20 M1 Rp. 15,000.00
14 Kawat Bindrat Kg Rp. 15,000.00
15 Angkur kusen pintu/jendela besi dia. 8 mm Bh Rp. 5,000.00
16 Paku 1/2" - 1" Kg Rp. 15,000.00
17 Paku campur Kg Rp. 15,000.00
18 Paku Tripleks Kg Rp. 20,000.00
19 Paku Seng Kg Rp. 20,000.00
20 Paku Beton kg Rp. 25,000.00
21 Balok Kayu Klas II Kayu Jati M3 Rp. 2,000,000.00
22 Balok Kayu Kls II M3 Rp. 1,800,000.00
23 Papan Kayu Kls I M3 Rp. 2,400,000.00
24 Papan Kayu Klas III (Bekesting) M3 Rp. 900,000.00
25 Dolken Bh Rp. 3,000.00
26 List kaca 1 x 1 cm M1 Rp. 2,500.00
27 Tripleks Tebal 3 mm Lbr Rp. 50,000.00
28 List Plafond 1 x 4 cm M1 Rp. 2,500.00
29 Multipleks tebal 10 mm Lbr Rp. 110,000.00
30 Keramik 30 x 30 cm Lbr Rp. 5,000.00
31 Keramik plint 15 x 30 cm Lbr Rp. 2,500.00
32 Keramik anti slip 20 x 20 cm Lbr Rp. 2,500.00
33 Keramik 20 x 25 cm Lbr Rp. 3,000.00
34 Kaca bening 5 mm M2 Rp. 90,000.00
35 Kapur Tonasa Kg Rp. 5,000.00
36 Plamir Tembok Kg Rp. 5,000.00
37 Amplas Lbr Rp. 2,500.00
38 Cat dasar merk Glotex Kg Rp. 10,000.00
39 Cat kilap kayu merk Avian Kg Rp. 15,000.00
40 Cat Residu Merk EMCO Ltr Rp. 15,000.00
41 Cat Tembok Merk Wintex / INA Kg Rp. 5,000.00
42 Lem Kayu Merk Fox Kg Rp. 10,000.00
43 Lem Kayu Ltr Rp. 5,000.00
1 2 3 4
44 Dempul Kayu Merk EMCO Kg Rp. 5,000.00
45 Seal tape Bh Rp. 2,500.00
46 Kran air Bh Rp. 15,000.00
47 Klosed jongkok Bh Rp. 110,000.00
48 Wastafel Bh Rp. 150,000.00
49 Bak fiber Bh Rp. 325,000.00
50 Floor drain Bh Rp. 10,000.00
51 Pintu fiber Bh Rp. 300,000.00
52 Cat vernis kayu merk Glotex / Platone Kg Rp. 15,000.00
53 Kunci Tanam Anchor 693 LD 2 x putar Bh Rp. 150,000.00
54 Kunci Tanam Kamar Mandi Bh Rp. 100,000.00
55 Engsel Pintu Type H Bh Rp. 6,000.00
56 Engsel Pintu Type Kupu Kupu Bh Rp. 5,000.00
57 Engsel Jendela Type Kupu Kupu Bh Rp. 4,000.00
58 Grendel Jendela Bh Rp. 3,000.00
59 Kait-kait Angin Bh Rp. 3,000.00
60 Grendel Pintu bh Rp. 3,000.00
61 Cat Meny seng/besi Kg Rp. 10,000.00
62 Meny Kayu Kg Rp. 10,000.00
63 Minyak Cat Ltr Rp. 10,000.00
64 Minyak Bekisting Ltr Rp. 5,000.00
65 Kuas 5 " Bh Rp. 10,000.00
66 Pasangan Instalasi Titik Lampu Titik Rp. 50,000.00
67 Lampu SL 23 Watt Bh Rp. 35,000.00
68 Lampu Pijar 20-40 Watt Bh Rp. 10,000.00
69 Stop Kontak Bh Rp. 10,000.00
70 Saklar Tunggal Bh Rp. 7,500.00
71 Saklar Ganda Bh Rp. 12,500.00
###
72 Box Skring ( MCB ) Bh Rp. 125,000.00
73 Pasangan lampu TL 20 watt Bh Rp. 40,000.00

Mengetahui : Kendari, 20 Desember 2016


PT. ALKOBAR ALAM RAYA Dibuat Oleh,

ASRIANTO WARJONO, A.Md


Direktur Coast Estimator
DAFTAR HARGA SATUAN PEKERJAAN
PEKERJAAN : PEMBANGUNAN PERUMAHAN "GRIYA TIWI BARUGA" TYPE 36
#REF!
LOKASI : JL. LINGKUNGAN PD. JL. ADE IRMA NASUTION KEL. WATUBANGGA KEC. BARUGA
VOLUME : 119 UNIT
#REF! ### #REF!
PEMILIK : ASRIANTO ( PT. ALKOBAR ALAM RAYA )
Harga Satuan Pekerjaan. Hal. 01

NO JENIS PEKERJAAN HARGA SATUAN


(Rp)
1 2 3
1 1 M3 Pek. Galian Tanah Biasa Sedalam 1 M 22,800.00
2 1 M3 Pek. Urugan Kembali 10,930.00
3 1 M3 Pek. Urugan Pasir 105,700.00
4 1 M3 Pek. Urugan Tanah 58,500.00
5 #REF! #REF!
6 1 M3 Pek. Pasangan Pondasi Batu Kali 1 Pc : 5 Psr 536,550.00
7 1 M3 Pek. Pasangan Pondasi Batu Kosong 274,455.00
8 1 M2 Pek. Pasangan Batako 1 Pc : 2 Psr 43,888.50
9 #REF! #REF!
10 #REF! #REF!
11 1 M2 Pek. Pasangan Batako 1 Pc : 5 Psr 42,295.00
12 1 M2 Pek. Plesteran 1 Pc : 2 Psr, Tebal 15 mm 35,526.00
13 1 M2 Pek. Plesteran 1 Pc : 3 Psr, Tebal 15 mm 33,124.00
14 1 M2 Pek. Plesteran 1 Pc : 5 Psr, Tebal 15 mm 30,691.00
15 1 M2 Pek. Plesteran di aci 1 Pc : 3 Psr, Tebal 15 mm 36,099.00
16 1 M3 Pek. Kusen Pintu/Jendela Kayu Klas II.A 4,131,000.00
17 1 M3 Pek. Pasang Pintu Panil Jati 343,250.00
18 1 M3 Pek. Pasang Pintu dan Jendela Kaca Kayu Jati 281,800.00
19 1 M3 Pek. Pasang Jalusi Mati Kusen 292,000.00
20 1 M2 Pek. Pasangan Kaca bening 5 mm 111,427.50
21 1 M3 Pek. Pasang Konstruksi Kuda-Kuda Kayu Kelas II.A 3,431,000.00
22 1 M3 Pek. Pasang Gording Kayu Kls II 3,136,000.00
23 1 M' Pek. Pasang Listplank 2 x (3 x 20) Cm, Kayu Klas II 59,125.00
24 1 M2 Pek. Rangka Plafond dan Penggantung 55,225.00
25 1 M2 Pek. Plafond Tripleks (60 x 120) 3 mm 29,395.00
26 1 M' Pek. Pasang List Plafond Kayu 3/4 (profil) 5,565.00
27 1 M3 Membuat Beton Tumbuk 1 Pc : 3 Psr : 5 Krl 608,125.00
28 #REF! #REF!
29 1 M1 Membuat Kolom Penguat Beton Bertulang (12 x 12) Cm 45,085.00
30 #REF! #REF!
31 1 M3 Membuat Kolom Beton Bertulang (234 Kg Besi + Bekisting) 3,608,760.00
32 #REF! #REF!
33 #REF! #REF!
34 #REF! #REF!
35 1 M1 Membuat Sloof / Ringbalk Beton Bertulang (15 x 20) Cm 52,880.00
36 #REF! #REF!
37 #REF! #REF!
38 #REF! #REF!
39 1 M2 Pek. Pasangan Atap Seng Soka Jempol 46,120.00
40 1 M2 Pek. Atap Nok Seng Soka Jempol 25,920.00
41 #REF! #REF!
42 1 M2 Pek. Plamur Tembok 6,956.67
43 1 M2 Pek. Plamir, Cat Dasar, Cat Kilap Kayu 2 x 12,855.50
44 1 M2 Pek. Cat Tembok/Plafond 2 x 7,683.34
45 1 M2 Pelaburan Bidang Kayu Dengan Vernis 23,425.00
46 #REF! #REF!
47 #REF! #REF!
48 #REF! #REF!
49 #REF! #REF!
50 #REF! #REF!
51 #REF! #REF!
52 1 Buah Pasang Kunci Tanam Anchor 693 LD 2 x putar 186,600.00
Harga Satuan Pekerjaan. Hal. 02
1 2 3
53 1 Buah Pasang Engsel Pintu 17,431.00
54 1 Buah Pasang Engsel Jendela Kupu - Kupu 12,285.00
55 1 Buah Pasang Kait Angin 15,431.00
56 #REF! #REF!
57 #REF! #REF!
58 #REF! #REF!
59 #REF! #REF!
60 #REF! #REF!
61 #REF! #REF!
62 #REF! #REF!
63 #REF! #REF!
64 #REF! #REF!
65 #REF! #REF!
66 #REF! #REF!
67 #REF! #REF!
68 #REF! #REF!
69 #REF! #REF!
70 #REF! #REF!
71 #REF! #REF!
72 #REF! #REF!
73 #REF! #REF!
74 #REF! #REF!
75 #REF! #REF!
76 #REF! #REF!
77 #REF! #REF!
78 1 Buah Pasang Grendel Pintu 15,431.00
79 1 Buah pasang Grendel Jendela 15,431.00
80 #REF! #REF!
81 #REF! #REF!
82 #REF! #REF!
83 #REF! #REF!
84 #REF! #REF!
85 1 M' Pek. Pasang List Kaca Kayu 1 x 1 cm 5,385.00
86 1 M2 Mendempul dan Menggosok Kayu 4,020.00
87 #REF! #REF!

Kendari, 20 Desember 2016


Mengetahui : Dibuat Oleh,
PT. ALKOBAR ALAM RAYA #REF!

ASRIANTO WARJONO, A.Md


Direktur Coast Estimator
ALIRAN DANA PROYEK (CASH FLOW )

PEKERJAAN : PEMBANGUNAN PERUMAHAN "GRIYA TIWI BARUGA" TYPE 36


LOKASI : JL. LINGKUNGAN PD. JL. ADE IRMA NASUTION KEL. WATUBANGGA KEC. BARUGA
VOLUME : 119 UNIT
PEMILIK : ASRIANTO ( PT. ALKOBAR ALAM RAYA )

I. PEKERJAAN PENDAHULUAN

HARGA JUMLAH
NO. URAIAN DAN JENIS PEKERJAAN VOLUME SATUAN SATUAN HARGA
(Rp) (Rp)

1 2 3 4 5 6

I PEKERJAAN PERSIAPAN / PENDAHULUAN


1 Pekerjaan Pembersihan Lokasi 1.00 Unit 25,000,000.00 25,000,000.00

2 Pek. Bangsal Kerja Ls Ls 7,800,000.00 7,800,000.00


3 Pek. Pas. Bowplank 20.00 Unit 150,000.00 3,000,000.00
4 Air Kerja / P3K 20.00 Unit 100,000.00 2,000,000.00
5 Administrasi dan Dokumentasi 20.00 Unit 50,000.00 1,000,000.00
Jumlah 38,800,000.00
II. PEMBANGUNAN PERUMAHAN TYPE 36
1 Pek. Pembangunan Rumah Tipe 36 20.00 Unit 60,185,256.50 1,203,705,130.04
Jumlah 1,245,505,130.04
III. PEMBANGUNAN FASILITAS UMUM
I PEKERJAAN FASILITAS UMUM
1 Pek. Pembentukan Badan Jalan 500.00 m' 250,000.00 125,000,000.00

2 Pek. Perkerasan Badan Jalan 500.00 m' 750,000.00 375,000,000.00


3 Pek. Drainace Jalan 1,000.00 m' 150,000.00 150,000,000.00
4 Pek. Selokan Induk 188.00 m' 350,000.00 65,800,000.00
Jumlah 715,800,000.00
JUMLAH 2,000,105,130.04

DIBULATKAN 2,000,000,000.00
TERBILANG : DUA MILYAR RUPIAH

Kendari, 20 Desember 2016


Disetujui : Dibuat Oleh,
PT. ALKOBAR ALAM RAYA

ASRIANTO WARJONO, A.Md


Direktur Coast Estimator
TOTAL REKAPITULASI

PEKERJAAN : PEMBANGUNAN PERUMAHAN "GRIYA TIWI BARUGA" TYPE 36


LOKASI : JL. LINGKUNGAN PD. JL. ADE IRMA NASUTION KEL. WATUBANGGA KEC. BARUGA
VOLUME : 119 UNIT
PEMILIK : ASRIANTO ( PT. ALKOBAR ALAM RAYA )

JUMLAH
NO. URAIAN DAN JENIS PEKERJAAN HARGA
(Rp)

######
PEKERJAAN PENDAHULUAN . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp 38,800,000.00
######
PEMBANGUNAN PERUMAHAN TYPE 36 . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp #REF!
III. PEMBANGUNAN FASILITAS UMUM . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp 715,800,000.00

TOTAL . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp #REF!
DIBULATKAN . . . . . . . . . . . . . . . . . . . . . . . . . . . Rp #REF!

TERBILANG : DELAPAN MILYAR LIMA RATUS DELAPAN PULUH DUA JUTA LIMA RATUS EMPAT PULUH LIMA RIBU RUPIAH

Disetujui : -
### -
###

### WARJONO, A.Md


### -
JADWAL WAKTU PELAKSANAAN PEKERJAAN

PEKERJAAN : PEMBANGUNAN PERUMAHAN "GRIYA TIWI BARUGA" TYPE 36


LOKASI : JL. LINGKUNGAN PD. JL. ADE IRMA NASUTION KEL. WATUBANGGA KEC. BARUGA
VOLUME : 119 UNIT
PEMILIK : ASRIANTO ( PT. ALKOBAR ALAM RAYA )

I. PEMBANGUNAN PERUMAHAN TYPE 36

HARGA JUMLAH DURASI / MINGGU


NO. URAIAN DAN JENIS PEKERJAAN VOLUME SATUAN SATUAN HARGA BOBOT I II III IV V VI VII VIII
(Rp) (Rp)

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
I PEKERJAAN TANAH DAN PASIR
1 Pek. Galian Tanah Pondasi 12.96 m3 22,800.00 295,488.00 0.49 0.49
2 Pek. Urugan Tanah Eks. Galian Pondasi 3.24 m3 10,930.00 35,413.20 0.06 0.06
3 Pek. Urugan tanah bawah lantai 12.88 m3 58,500.00 753,597.00 1.25 1.25
4 Pek. Urugan pasir alas Pondasi 1.44 m3 105,700.00 152,208.00 0.25 0.25
5 Pek. Urugan pasir alas Lantai 3.39 m3 105,700.00 358,323.00 0.60 0.60
Jumlah 1,595,029.20 2.65
II PEKERJAAN BATU DAN PASANGAN
1 Pas. Batu kosong 4.32 m3 274,455.00 1,185,645.60 1.97 1.97
2 Pas. Pondasi batu gunung, adukan 1 Pc : 5 Psr 12.24 m3 536,550.00 6,567,372.00 10.91 10.91
3 Pas. Dinding batako, adukan 1 Pc : 2 Psr 10.80 m2 43,888.50 473,995.80 0.79 0.79
4 Pas. Dinding batako, adukan 1 Pc : 5 Psr 70.80 m2 42,295.00 2,994,486.00 4.98 4.98
Jumlah 11,221,499.40 18.64
III PEKERJAAN BETON BERTULANG
1 Pek. Sloof Praktis 15 x 20 Beton Bertulang 1 Pc : 2 Psr : 3 Krl 36.00 m' 52,880.00 1,903,680.00 3.16 3.16
2 Pek. Kolom praktis, 12 x 12 cm Beton Bertulang 1 Pc : 2 Psr : 3 Krl 45.00 m' 45,085.00 2,028,825.00 3.37 3.37
3 Pek. Ring Balk, Uk.12 x 15 cm Beton Bertulang 1 Pc : 2 Psr : 3 Krl 58.90 m' 52,880.00 3,114,632.00 5.18 5.18
Jumlah 7,047,137.00 11.71
IV PEKERJAAN PLESTERAN
1 Pek. Plesteran Trasram camp. 1 Pc : 2 Ps T. 15 mm 21.60 m2 35,526.00 767,361.60 1.27 1.27
2 Pek. Plesteran Dinding camp. 1 Pc : 5 Ps T. 15 mm 141.60 m2 30,691.00 4,345,845.60 7.22 7.22
3 Pek. Plesteran Beton camp. 1 Pc : 3 Ps T. 15 mm 7.20 m2 33,124.00 238,492.80 0.40 0.40
4 Pek. Pleteran Pondasi camp. 1 Pc : 3 Ps T. 15 mm 22.40 m2 33,124.00 741,977.60 1.23 1.23
Jumlah 6,093,677.60 10.12
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
V PEKERJAAN PASANGAN LANTAI KERAMIK DAN RABAT BETON
1 Pek. Pasangan keramik 40 x 40 cm 31.65 m2 139,019.00 4,399,951.35 7.31 7.31
2 Pek. Pasangan keramik 20 x 20 cm 2.25 m2 118,878.00 267,475.50 0.44 0.44
3 Pek. Pasangan keramik 20 x 25 cm 7.50 m2 144,019.00 1,080,142.50 1.79 1.79
4 Pek. Lantai Rabat beton 1 Pc : 3 Psr : 5 Krl 2.52 m3 608,125.00 1,532,475.00 2.55 2.55
Jumlah 7,280,044.35 12.10
VI PEKERJAAN KUSEN/JENDELA/KACA
1 Pek. Kosen pintu / jendela kayu Kelas II Uk. 5 x 13,5 cm 0.49 m3 4,131,000.00 2,037,409.20 3.39 3.39
2 Pek. Pintu panil kayu Jati 5.04 m2 343,250.00 1,729,980.00 2.87 2.87
3 Pek. Bingkai jendela kaca kayu Jati 2.52 m2 281,800.00 710,136.00 1.18 1.18
4 Pek. List Kaca 1 x 1 cm 25.20 m' 5,385.00 135,702.00 0.23 0.23
5 Pek. Pas. Kaca Bening 5 mm 5.04 m2 111,427.50 561,594.60 0.93 0.93
Jumlah 5,174,821.80 8.60
VII PEKERJAAN KAP DAN ATAP
1 Pek. Kuda-kuda, balok jurai dan konsol kayu II 0.52 m3 3,431,000.00 1,797,844.00 2.99 2.99
2 Pek. Gording dan balok angin kayu kls II 0.66 m3 3,136,000.00 2,082,304.00 3.46 3.46
3 Pek. Papan listplank papan Kayu Kelas II 20.58 m' 59,125.00 1,216,712.68 2.02 2.02
4 Pas. Atap seng Soka Jempol 48.00 m2 46,120.00 2,213,760.00 3.68 3.68
5 Pas. Nok seng Soka Jempol 8.00 m' 25,920.00 207,360.00 0.34 0.34
Jumlah 7,517,980.68 12.49
VIII PEKERJAAN PENGGANTUNG/PENGUNCI
1 Pas. Kunci tanam Anchor 693 LD, 2 x putar 3.00 buah 186,600.00 559,800.00 0.93 0.93
2 Pas. Engsel pintu dalam type kupu-kupu 6.00 buah 17,431.00 104,586.00 0.17 0.17
3 Pas. Grendel Pintu 3.00 buah 15,431.00 46,293.00 0.08 0.08
4 Pas. Engsel jendela type kupu-kupu standard 14.00 buah 12,285.00 171,990.00 0.29 0.29
5 Pas. Grendel jendela standard 7.00 buah 15,431.00 108,017.00 0.18 0.18
6 Pas. Kait angin jendela standard 14.00 buah 15,431.00 216,034.00 0.36 0.36
Jumlah 1,206,720.00 2.01
IX PEKERJAAN RANGKA DAN PLAFOND
1 Pek. Rangka Plafond Tripleks kayu kls II 58.90 m2 55,225.00 3,252,752.50 5.40 5.40
2 Pek. Plafond Tripleks 60 x 120 cm 58.90 m2 29,395.00 1,731,365.50 2.88 2.88
3 Pas. List Plafond Profil 90.00 m' 5,565.00 500,850.00 0.83 0.83
Jumlah 5,484,968.00 9.11
X PEKERJAAN INSTALASI LISTRIK
1 Pasangan titik instalasi 7.00 buah 50,000.00 350,000.00 0.58 0.58
2 Pasangan lampu TL 20 watt 1.00 buah 40,000.00 40,000.00 0.07 0.07
3 Pasangan lampu pijar 25 watt 4.00 buah 20,000.00 80,000.00 0.13 0.13
4 Pasangan lampu pijar 5 watt 2.00 buah 10,000.00 20,000.00 0.03 0.03
5 Pas. Stop kontak merk Broco 2.00 buah 10,000.00 20,000.00 0.03 0.03
6 Pas. Saklar tunggal merk Broco 3.00 buah 7,500.00 22,500.00 0.04 0.04
7 Pas. Saklar ganda merk Broco 2.00 buah 12,500.00 25,000.00 0.04 0.04
8 Pas. Box Skring ( MCB ) 1.00 buah 125,000.00 125,000.00 0.21 0.21
Jumlah 682,500.00 1.13
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
XI PEKERJAAN SANITASI
1 Pek. Instalasi Air bersih Ls Ls 250,000.00 250,000.00 0.42 0.42
2 Pek. Instalasi Air kotor Ls Ls 150,000.00 150,000.00 0.25 0.25
3 Pemasangan kran air 2.00 Bh 23,662.50 47,325.00 0.08 0.08
4 Pemasangan Floor drain 2.00 Bh 18,600.00 37,200.00 0.06 0.06
5 Pemasangan klosed jongkok 1.00 Bh 399,750.00 399,750.00 0.66 0.66
6 Pek. Pintu fiber 1.00 Bh 300,000.00 300,000.00 0.50 0.50
7 Pek. Septick tank dan peresapan 1.00 Unit 2,000,000.00 2,000,000.00 3.32 3.32
Jumlah 3,184,275.00 5.29
XII PEKERJAAN PENGECATAN / FINISHING
1 Pek. Plamur Tembok 163.20 m2 6,956.67 1,135,328.54 1.89 1.89
2 Pek. Cat tembok 2 x jalan 163.20 m2 7,683.34 1,253,921.09 2.08 2.08
3 Pek. Cat plafond 2 x jalan 58.90 m2 7,683.34 452,548.73 0.75 0.75
4 Pek. Cat dasar/kilap kosen 2 x jalan 17.18 m2 12,855.50 220,793.21 0.37 0.37
5 Pek. Vernis daun pintu/jendela 2 x jalan 15.12 m2 23,425.00 354,186.00 0.59 0.59
6 Pek. Mengamplas dan Menggosok kayu 32.30 m2 4,020.00 129,825.90 0.22 0.22
7 Pek. Pembersihan akhir ls ls 150,000.00 150,000.00 0.25 0.25
Jumlah 3,696,603.47 6.14
JUMLAH 100.00 24.08 27.05 25.18 23.69
24.08 51.13 76.31 100.00

Disetujui : Kendari, 20 Desember 2016


PT. ALKOBAR ALAM RAYA Dibuat Oleh,

ASRIANTO
Direktur WARJONO, A.Md
Coast Estimator
60,185,256.50 4.00 0.06
60,185,256.50 4.00 0.01
60,185,256.50 4.00 0.16
60,185,256.50 4.00 0.03
60,185,256.50 4.00 0.07
4.00 0.33
4.00 -
60,185,256.50 4.00 0.25
60,185,256.50 4.00 1.36
60,185,256.50 4.00 0.10
60,185,256.50 4.00 0.62
4.00 2.33
4.00 -
60,185,256.50 4.00 0.40
60,185,256.50 4.00 0.42
60,185,256.50 4.00 0.65
4.00 1.46
4.00 -
60,185,256.50 4.00 0.16
60,185,256.50 4.00 0.90
60,185,256.50 4.00 0.05
60,185,256.50 4.00 0.15
0.60 4.00 1.27
86.26 4.00 -
21.83 4.00 -
20.70 4.00 -
4.00 -
4.00 -
4.00 -
4.00 -
4.00 -
4.00 -
4.00 -
4.00 -
4.00 -
4.00 -
4.00 -
4.00 -
4.00 -
4.00 -
4.00 -
4.00 -
4.00 0.88
4.00 -
60,185,256.50 4.00 0.91
60,185,256.50 4.00 0.06
60,185,256.50 4.00 0.22
60,185,256.50 4.00 0.32
4.00 1.51
4.00 -
60,185,256.50 4.00 0.42
60,185,256.50 4.00 0.36
60,185,256.50 4.00 0.15
60,185,256.50 4.00 0.03
60,185,256.50 4.00 0.12
5.21 4.00 1.07
4.00 -
60,185,256.50 4.00 0.37
60,185,256.50 4.00 0.43
60,185,256.50 4.00 0.25
60,185,256.50 4.00 0.46
60,185,256.50 4.00 0.04
24.59 4.00 1.56
4.00 -
60,185,256.50 4.00 0.12
60,185,256.50 4.00 0.02
60,185,256.50 4.00 0.01
60,185,256.50 4.00 0.04
60,185,256.50 4.00 0.02
60,185,256.50 4.00 0.04
4.00 0.25
4.00 -
60,185,256.50 4.00 0.68
60,185,256.50 4.00 0.36
60,185,256.50 4.00 0.10
4.00 1.14
4.00 -
60,185,256.50 4.00 0.07
60,185,256.50 4.00 0.01
60,185,256.50 4.00 0.02
60,185,256.50 4.00 0.00
60,185,256.50 4.00 0.00
60,185,256.50 4.00 0.00
60,185,256.50 4.00 0.01
60,185,256.50 4.00 0.03
12.25 4.00 0.14
89.74 4.00 -
3.39 4.00 -
4.00 -
4.00 -
4.00 -
4.00 -
4.00 -
4.00 -
4.00 -
4.00 -
4.00 -
4.00 -
4.00 0.88
4.00 -
60,185,256.50 4.00 0.05
60,185,256.50 4.00 0.03
60,185,256.50 4.00 0.01
60,185,256.50 4.00 0.01
60,185,256.50 4.00 0.08
60,185,256.50 4.00 0.06
60,185,256.50 4.00 0.42
4.00 0.66
4.00 -
60,185,256.50 4.00 0.24
60,185,256.50 4.00 0.26
60,185,256.50 4.00 0.09
60,185,256.50 4.00 0.05
60,185,256.50 4.00 0.07
60,185,256.50 4.00 0.03
60,185,256.50 4.00 0.03
11.43 4.00 0.77
4.00 12.50
16.72 4.00 -

Anda mungkin juga menyukai