BAB IV

PEMBAHASAN

4.1 Perencanaan Beban


4.1.1 Perhitungan Pembebanan Atap
A. Data-data bangunan
Tinggi Kuda-Kuda = 10,542 m (Gambar kerja)
Jarak Antar Kuda-Kuda = 8,66 m (Gambar kerja)
Panjang Bentangan = 15,149 m (Gambar kerja)
Jarak Gording = 61 m (Gambar kerja)
Berat Plafon Gypsum = 15 kg (Sumber Aplus pasifik)
Jumlah Kuda-Kuda = 6 Buah (Gambar kerja)
Berat Penutup Atap Spandek = 3,55 kg/m (Sumber Aplus pasifik)

Gambar kuda-kuda 4.1


Sumber Gambar AutoCAD

B. Perhitungan Panjang Batang


Keterangan : a = batang atas
b = batang bawah
v = batang vertikal
d = batang diagonal

1
1) Batang atas (a)
b1
Batang a1 = a10 = cos α =
a1
b1
cos 35° =
a1
8,66
0,819 =
a1
8,66
a1= = 10,574 m
0,819
Jadi, batang a1 = a10 adalah 10,574 m
b 1+ b 2
Batang a2= a9 = cos α =
a1
8,66+8,51
0,819 ¿
10,574
17,17
0,819 =
10,574
a2 = 1,624 m
a2 = 10,574 m-1,624m
a2 = 8,95 m
Jadi, batang a2 =a9 adalah 8,95 m.
b 1+ b 2+b 3
Batang a3 = a8 = cos α =
a 1+ a 2+a 3
8,66+8,51+8,66
cos α =
10,574+8,95+ a3
25,83
0,819 =
19,524(a 3)
= 1,32 m
1,32
a3 = = 1,61m
0,819
a3 = 19,524 –1,61
a3 = 17,914 m
Jadi, batang a3 = a8 adalah 17,914 m.

2
Batang a4 = a7 = √ d 4 2−v 4 2
= √ 30,9822−18,9762
= √ 959,884−360,088
= √ 599,796
= 24,491 m
Jadi, batang a4 = a7 adalah 24,491 m.
Batang a5 = a6 = √ d 5 2−v 52
= √ 40,8102 −30,9582
= √ 1665,4−958,397
= √ 707,003
= 26,589 m
Jadi, batang a5 = a6 adalah 26,589 m.
Batang a6 = a5 = √ d 62−v 6 2
= √ 50,6382−40,7912
= √ 2564,2−1651,6
= √ 912,6
= 30,21
Jadi, batang a6 = a5 adalah 30,21 m.
2) Batang bawah (b)
b1= b10 = 8,66 m
b2 = b9 = 8,51 m
b3 = b8 = 8,66 m
b4 = b7 = 1,2 m
b5 = b6 = 1,2 m
b6 = b5 = 1,2 m
3) Batang vertikal (v)
Batang v1 = v10
= √ a 12 + d 12
= √ 10,5742 +7,092
= √ 61,541 m

3
= 7,844 m
Jadi, batang v1 = v10 adalah 7,844 m.
Batang v2 = v9
= √ a 12−b 12
= √ 10,5792−8,66 2
= √ 36,814 m
= 6,067 m
Jadi, batang v2 = v9 adalah 6,067 m.
Batang v3 = v8
= √ d 22−b 22
= √ 10,6972−8,512
= √ 113,3582−72,4202
= √ 40,938
= 6,398 m
Jadi, batang v3 = v8 adalah 6,398 m.
Batang v4 = v7
= √ d 32−b 32
= √ 20,8592−8,66 2
= √ 435,097−74,995
= √ 360,102m
= 18,976 m
Jadi, batang v4 = v7 adalah 18,976 m.
Batang v5 = v6
= √ d 4 2−b 4 2
= √ 30,9822−1,22
= √ 959,884−1,44
= √ 958,44 m
= 30,958 m
Jadi, batang v5 = v6 adalah 30,958 m.

4
Batang v6 = v5
= √ d 5 2−b 52
= √ 40,8102 −1,22
= √ 1665,4−1,44
= √ 1.663,96 m
= 40,791 m
Jadi, batang v6 = v5 adalah 40,791 m.
4) Batang diagonal (d)
d1 = d10 = cos α × b1
= cos 35° × 8,66
= 0,819 × 8,66
d1 = 7,09 m
Jadi, batang d1 = d10 adalah 7,09 m
d2 = d9 =√ a 22 +v 22
= √ 8,952 +6,0672
=√ 80,102+36,808
= √ 116,91
= 10,812 m
Jadi, batang d2 = d9 adalah 10,812 m.
d3 = d8 =cos α × b1 + b2 + b3
= cos 35° × 8,66 + 8,51 + 8,66
= 0,819 × 8,66 + 8,51 + 8,66
= 24,262 m
Jadi, batang d3 = d8 adalah 24,262 m.
d4 = d7 = cos α × b1 + b2 + b3 + b4
=cos 35°×8,66+8,51+8,66+12,00
= 0,819×(8,66+8,51+8,66+12,00)
= 30,982 m
Jadi, batang d4 = d7adalah 30,982 m.

5
d5 = d6 = cos α ×b1+b2+b3+b5
=(cos 35°×8,66+8,51+8,66+12,00+12,00)
= 0,819×(8,66+8,51+8,66+12,00+12,00)
= 40,810 m

Tabel 4.1 Rekapitulasi Perhitungan Panjang Batang


No Nama Batang Panjang Batang
1. Batang Atas
a1 10,574 m
a2 8,95 m
a3 17,914 m
a4 24,491 m
a5 26,589 m
a6 30,21 m
2. Batang Bawah
b1 8,66 m
b2 8,51 m
b3 8,66 m
b4 1,2 m
b5 1,2 m
b6 1,2 m
3. Batang Vertical
v1 7,844 m
v2 6,067 m
v3 6,398 m
v4 18,976 m
v5 30,958 m
V6 40,791 m
4. Batang Diagonal
d1 7,09 m
d2 10,812 m

6
d3 24,262 m
d4 30,982 m
d5 40,810 m
Total 373,148 m

C. Perhitungan Berat Atap


1) Berat penutup atap
Berat penutup atap spandek = 2,98 kg/m 2
Berat penutup atap = jarak kuda-kuda x jarak gording
= 6 m x 2,85 m x 2,98 kg/m2
= 45,82 kg/m2
2) Perhitungan beban akibat gording
Luas penampang gording (Agording) = 0,05 x 0,07 x 2.98 kg/m2
= 10,43 kg/m2
Berat persatuan volume (V ) = 112 kg/m2
Panjang bidang miring
(∑ gordimg = + 1) x 2
jarak gording
10,795
=( + 1) x 2= 24,714→ 24 buah
0,07
Berat gording = Agording x v x jarak kuda-kuda x ∑ gording
= 0,43 x 24,714 x 6 x 24 = 37,1184 kg/m2
3) Perhitungan beban akibat berat sendiri kuda-kuda.
Berat rangka kuda-kuda.
= total panjang kuda-kuda x dimensi baja ringan x v
= 373,148 kg/m2 x 0,05 x 0,07 x 24,714 buah
= 32,276 kg/cm2
4) Berat plafon + penggantung
P2 = panjang bentang x jarak kuda-kuda x berat plafon + penggantung
= 14,150 m x 8,66 m x 15 kg/m2+ 12 kg/m2
= 3.308,553 kg/m2

7
Berat penutup atap = 3,55 kg/m2
Berat gording = 32,1184 kg/m2
Berat rangka-rangka = 32,276 kg/m2
Berat plafon + penggantung = 27 kg/m2 +
Total berat satu rangka kuda-kuda = 3.403,49 kg/m2
Berat atap untuk satu rangka kuda-kuda = total berat satu rangka kuda-
kuda x jumlah kuda-kuda = 3.403,49 × 6 = 20.420,94 kg/m2
Jadi berat rangka kuda-kuda keseluruhan sebesar 20.420,94 kg/m2

4.2 Perhitungn Pelat Lantai


4.2.1 Data-Data Pelat Lantai
Mutu Beton = 25 Mpa
Mutu baja (Fy) = 300 Mpa
Tebal plat lantai (130 mm) = 13cm
Diameter Tulangan = D10 = 200 mm
D10 = 150 mm
Selimut Beton = 20 mm
Berat Beton Bertulang = 2.400 kg/m3 (PPURG 1989)
Berat Spesi = 21 kg/m2 (PPURG 1989)
Berat Keramik 40×40 = 18 kg/m2 (Online)
Berat Penggantung = 7 kg/m2 (PPURG 1989)
Berat Plafond Gypsung = 15 kg (Online)
Beban Hidup = Ruang Hunian = 1,92 kn/m2
(SNI 1727 : 2013)

4.2.2 Perhitungan Beban Yang Bekerja Pada Pelat Lantai


1) Beban Mati
a. Pelat (130 mm) = 0,13 m x 2.400 kg/m3 (x 60 m x 15,15 m)
= 283.608 kg/m2 = 2,78 Kn/m2
b. Plafond + Penggantung = 15 kg/m2 x 12 kg/m2 x 60 m x 15,15 m
= 16,362 kg/m2 = 1,6 Kn/m2

8
c. Keramik = 18 kg/m2 x 60 m x 15,15 m
= 16.362 kg/m2 = 0,16 Kn /m2
d. Spesi = 21 kg/m2 x 60 m x 15,15 m
= 19.089 kg/m2 = 0,18 Kn /m2
Total berat mati = 2,78 Kn /m2 + 1,6 Kn /m2 + 0,16 Kn/m2 + 0,18 Kn /m2
= 4,72 Kn/m2
2) Beban Hidup
Ruang Hunian = 1,92 kn/m2
3) Beban Perlu
= 1,2.qD + 1,6.qL = 1,2 (4,72 Kn/m2) + 1,6 (1,92 Kn/m2)
= 8,736 kn/m2

4.2.3 Pembagian Tipe Pelat lantai


Pembagian tipe pelat lantai berdasarkan ukuran pelat sebagai berikut :

Gambar 4.2 Denah Tipe Pelat Lantai


Sumber : Gambar AutoCAD

4.2.4 Perhitungan Pelat Lantai

9
Rasio bentang panjang dan pendek plat lantai tipe A1,
ly/lx = 6,45/6
= 1,1 m.
Dengan beban perlu qU = 8,736 kn/m2, maka momen perlu plat
lantai :
Keterangan :
Di ambil dari tabel PBI 1971, maka nilai : Clx = 25, Cly = 21,
Ctx = 59, Cty = 54.

Momen perlu, M = 0,001.Clx.qU.lx2

M : Mlx(+) = 0,001 x 25 x 8,736 x 62 = 7,86 kN.m

M : Mly(+) = 0,001 x 21 x 8,736 x 62 = 6,60 kN.m

M : Mtx(-) = 0,001 x 59 x 8,736 x 62 = 18,56 kN.m

M : Mty(-) = 0,001 x 54 x 8,736 x 62 = 16,98 kN.m

Rasio bentang panjang dan pendek plat lantai tipe A2, ly/lx =
6/2,25 = 2,7 Dengan beban perlu qU = 8,736 kN/m2, maka
momen perlu plat lantai :
Keterangan :

10
Ly/lx C M= 0,001.Clx.qu.lx2 (kN.m)

Clx = 41 Mlx(+)= 1,59 kN.m


Cly = 8 Mly(+)= 2,20 kN.m
2,7
Ctx = 83 Mtx(-) = 3,21 kN.m
Cty = 57 Mty(-)= 15,69 kN.m

Rasio bentang panjang dan pendek plat lantai tipe A3, ly/lx =
6,25/6 = 2,7. Dengan beban perlu qU = 8,736 kN/m2, maka mom
en perlu plat lantai :
Keterangan :

Ly/lx C M= 0,001.Clx.qu.lx2 (kN.m)


Clx = 37 Mlx(+)= 4,53 kN.m
Cly = 16 Mly(+)= 5,09 kN.m
1,6
Ctx = 79 Mtx(-) = 9,66 kN.m
Cty = 57 Mty(-)=18,13 kN.m

Rasio bentang panjang dan pendek plat lantai tipe A4, ly/lx = 4/2,25
= 1,8 Dengan beban perlu qU = 8,736 kN/m2, maka momen perlu
plat lantai
Keterangan :

11
Ly/lx C M= 0,001.Clx.qu.lx2 (kN.m)
Clx = 40 Mlx(+)= 1,55 kN.m
Cly = 13 Mly(+)= 1,59 kN.m
1,8
Ctx = 82 Mtx(-) = 3,17 kN.m
Cty = 57 Mty(-)= 6,97 kN.m

1. Gambar Tipe pelat A1

Momen perlu, M = 0,001.Clx.qU.lx2

M : Mlx(+) = 0,001 x 25 x 8,736 x 62 = 7,86 kN.m

M : Mly(+) = 0,001 x 21 x 8,736 x 62 = 6,60 kN.m

M : Mtx(-) = 0,001 x 59 x 8,736 x 62 = 18,56 kN.m

M : Mty(-) = 0,001 x 54 x 8,736 x 62 = 16,98 kN.m

12
2. Penulangan Arah x untuk tipe A1

Mlx(+) =7,86 kN.m =7.862.106 N mm

1). Tulangan Lapangan pada arah x

Data perencanaan :
b = 1000 mm
h = 120 mm
fc’ = 25 Mpa

fy = 300 Mpa

D = 10 mm
ds = 25 mm

dx = 120 – 25 = 95 mm

A). Faktor momen pikul (k)


Tabel 4.1 Faktor Momen Pikul Maksimal (Kmaks) Dalam Mpa
MutuBeto Mutu Baja Tulanganfy (MPa)
n fc’
240 300 350 400 450 500
(Mpa )
15 4,4838 4,267 4,1001 3,9442 3,9442 3,6627
3
20 5,9786 5,687 5,4668 5,2569 5,0649 4,8836
25 7,4732 7,112 6,8335 6,5736 6,3311 6,1045
1
30 8,967 8,534 8,2002 7,883 7,5973 7,3254
5

13
35 10,1445 9,644 9,2595 8,9016 8,5682 8,2573
2

Mu
k= → k ¿ kmaks
ϕ .b . d 2
Keterangan :
Mu = 7,86 kN.m x 106Nmm
b = 1000
ϕ = 0,8 (SNI 03- 2847- 2002, pasal 11)
d = 95
6
7,86 . 10
k= 2 = 1,089 Mpa¿ Kmaks ……………..(ok)
0,8 .1000 . 95

B). Hitung tulangan blok tegangan (a)

⟦ √
a = 1− 1−
2.k
0,85 . fc '⟧.d

⟦ √
a = 1− 1−
2 .0,891
0,85.25 ⟧
. 95

= 5,00 mm

C). Luas TulanganPokok (As)


0,85 . fc . a .b
As =
fy
0,85 .25 . 5,00 .1000
As =
300
= 354,2 mm2
1,4
Fc’ ¿ 31,36 Mpa, jadi As,u = .b.d
fy
1,4
= . 1000 . 95
300
= 433,333 mm2
Dipakai yang terbesar jadiAs,u = 433,333 mm2

14
D). Jarak Tulangan (s)
2
1
.π .D .b
s =4
As ,u
2
1
.3,14 .10 . 1000
= 4
433,333
= 177,229 mm
s ≤(2. h = 2.130 = 260 mm )
Dipilih s terkecil, jadi s = 170 mm (s¿177,229 mm )

E). Luas tulangan (As)


2
1
.π .D .b
= 4
s
2
1
.3,14 . 10 .1000
= 4
170
= 462,2 mm ≥As,u ………………………(ok)
Jadi tulangan pokok terpasang (As) = ∅ 10 – 170 = 462,185 mm2

F). Kontrol momen desain


As 462,2
ρ = . 100% = = . 100% = 0,487%
b.d 1000.95
1,4 1,4
ρ min = . 100% = . 100% = 0,467%
Fy 300
382,5. β 1 . fc 382,5 . 0,85 . 25
ρ maks= . 100% = . 100% = 2,957% mm2
( 600+ fy ) . fy ( 600+240 ) .300
Syarat : ρ min¿ ρ< ρ maks

G). Menghitung tinggi blok tegangan beton tekan


As . Fy 462,2.300
A= = = 6,525mm
0,85. Fc . b 0,85.25.1000
Momen nominal

15
Mn = As .fy .( d – a/2) = 462,2 . 300 . ( 95 –5,279/2)
= 12719908,032 Nmm
Momen desain plat
Md = ϕ .Mn = 0,9. 12719908,032 = 12719908,032 Nmm = 12,720 Nmm
Mu = 7,86 kNm
Syarat : Md > Mu (OK)

3. Penulangan Tumpuan (arah x) untuk tipe A1

M : Mly(+) = 0,001 x 21 x 8,736 x 62 = 6,60 kN.m2

Data perencanaan :
b = 1000 mm
H = 120 mm
fc’= 30 Mpa
fy = 240 MPa
D = 10 mm
ds = 25 mm
dx = 120 – 25 = 95 mm

A). Faktor Momen Pikul (k)


Mu = 6,60 kN.m = 6,60×106
b = 1000
ϕ = 0,8 (SNI 03- 2847- 2002, pasal 11)
d = 95
6
6,60 . 10
k= = 0,915 Mpa¿Kmaks ……………..(ok)
0,8 .1000 . 952

16
Faktor momen pikul¿ faktor momen pikul maksimal, maka ukuran tebal pelat
lantai dapat digunakan

B). Tinggi blok tegangan beton tekan persegi ekivalen (a)

⟦ √
a = 1− 1−
2 .k
0,85 . f c⟧' . d

⟦ √
a = 1− 1−
2 .0,915
0,85 .30 ⟧
. 95

= 4,181 mm

C). Luas Tulangan Pokok (As)


0,85 . fc . a .b 0,85 .30 . 4,181 . 1000
As = =
fy 240
= 296,2 mm2
Fc’ ¿ 31, 36 Mpa,
1,4 1,4
jadi As,u = . b . d= . 1000 . 95
fy 240
= 443,333 mm2
Dipilih yang terbesar, jadi As = 443,333 mm2

D). Jarak Tulangan (s)


2 2
1 1
.π .D .S .3,14 . 10 .1000
s= 4 = 4
As 443,333
= 177,229 mm
S ¿ (2 . h = 2 . 130 = 260 mm)
Dipilih yang terkecil, jadi dipakai s = 170 mm (s ¿177,229 mm)

E). Luas Tulangan Terpasang (As)


2 2
1 1
.π .D .s .3,14 . 10 .1000
As = 4 = 4
s 170

17
= 462,2 mm2 > As,u…… ……(ok)
Jadi tulangan pokok terpasang (As) = ∅ 10 – 170 = 462,2 mm2

F). Kontrol momen desain


- Rasio Tulangan Pokok ( ρ )
As 462,2
ρ = .100 % = .100 % = 0,487%
b.d 1000.85
1,4 1,4
ρ min = .100% = .100 % = 0,467%
fy 300
382,5. β 1 . fc 382,5. 00,583 . 24
ρ maks = .100 % = 100 %
( 600+ fy ) . fy ( 600+240 ) . 300
= 2,957 mm2
Syarat : ρ min¿ ρ< ρ maks
Menghitung tinggi blok tegangan beton tekan
As . Fy 462,2 .240
A= = = 6,525 mm
0,85. Fc . b 0,85.30.1000
Momen nominal
Mn = As .fy .( d – a/2) = 462,2 . 300 . ( 95 –12,283/2)
= 12719908,032 Nmm
Momen desain plat
Md = ϕ .Mn = 0,9. 212719908,032 = 12719908,032 Nmm = 12,720 kNm
Mu = 6,60 kNm
Syarat : Md > Mu (OK)

4. Penulangan Lapangan (Arah y) untuk tipe A1

M : Mtx(-) = 0,001 x 59 x 8,736 x 62 = 18,56 kN.m

Data perencanaan
B = 1000
H = 120

18
Fc = 30
Fy = 240
D = 10 mm
ds = 25
dy = 120 – 25 = 95 mm

a). Faktor momen pikul


Mtx
K =
ϕ .b . d 2
6
18,56 . 10
= 2 = 0,812 Mpa
09 ,.1000 . 95
= 2,570 Mpa¿Kmaks ……………..(ok)
Faktor momen pikul¿ faktor momen pikul maksimal, maka ukuran tebal pelat
lantai dapat digunakan

b). Tinggi blok tegangan beton tekan persegi ekivalen (a)

⟦ √
a = 1− 1−
2 .k
0,85 . f c⟧' . d

⟦ √
a = 1− 1−
2.2,570
0,85 .30 ⟧
. 95

= 12,283 mm
c). Luas Tulangan Pokok (As)
0,85 . fc . a .b 0,85 .30 . 12,283 .1000
As = =
fy 240
= 870,1 mm2
Fc’ ¿ 31, 36 Mpa,
1,4 1,4
jadi As,u = . b . d= . 1000 . 95
fy 240
= 443,333 mm2
Dipilih yang terbesar, jadi As = 870,1 mm2

d). Jarak Tulangan (s)

19
2 2
1 1
.π .D .S .3,14 . 10 .1000
s= 4 = 4
As 870,1
= 90,304 mm
S ¿ (2 . h = 2 . 130 = 260 mm)
Diambil yang terbesar, jadi 90 mm (s ¿90,304 mm)

e). Luas TulanganTerpasang (As)


2 2
1 1
.π .D .s .3,14 . 10 .1000
As = 4 = 4
s 90
= 873,016 mm2 > As,u…… ……(ok)
Jadi tulangan pokok terpasang (As) = ∅ 10 – 90 = 873,016 mm2
Tulangan bagi :
As,b = 20%. As,u =20%.873,016 = 174,603
As,b = 0,0020 . b . h = Asb,u = 260 mm2
Di gunakan tulangan bagi, D = 10 mm, maka jarak tulangan :
2 2
1 1
.π .D .s .3,14 . 10 .1000
s= 4 = 4
Asb , u 260
= 301,923 mm
S<(5.h =5.130 = 650)
Dipilih yanh kecil jadi, s = 300 mm (<301,923 mm)

f). Luas TulanganTerpasang (As)


2 2
1 1
.π .D .s .3,14 . 10 .1000
As,b = 4 = 4
s 300
= 261,799 mm2 > As,u…… ……(ok)
Jadi tulangan pokok terpasang (As) = ∅ 10 – 90 = 873,016 mm2
(As,b) = ∅ 10 – 300 =261,799 mm2
g). Kontrol momen desain

20
- Rasio Tulangan Pokok ( ρ )
As 873,016
ρ= .100 % = .100 % = 0,918%
b.d 1000.95
1,4 1,4
ρ min = .100% = .100 % = 0,467%
fy 240
382,5. β 1 . fc 382,5. 00,583 . 30
ρ maks = .100 % = 100 %
( 600+ fy ) . fy ( 600+240 ) . 240
= 2,957 mm2
Syarat : ρ min¿ ρ< ρ maks
Menghitung tinggi blok tegangan beton tekan
As . Fy 873,016.240
A= = = 8,216 mm
0,85. Fc . b 0,85.30.1000
Momen nominal
Mn = As .fy .( d – a/2) = 873,016 . 300 . ( 105 –8,216/2)
= 264240990816 Nmm
Momen desain plat
Md = ϕ .Mn = 0,9. 264240990816 = 23424099081617 Nmm = 23,781 kNm
Mu = 6,59 kNm
Syarat : Md > Mu (OK)

5. Tulangan Tumpuan (Arah y) untuk tipe A1

M : Mty(-) = 0,001 x 54 x 8,736 x 62 = 16,98 kN.m

Data perencanaan :
B = 1000
H = 120
Fc = 30
Fy = 240

21
D = 10 mm
ds = 25
dx = 120 – 25 = 95

a.) Faktor Momen Pikul


Mty
K =
ϕ .b . d 2
16,98 . 106
= 2 = 1,925 Mpa
09 ,.1000 . 85
= 2,352 Mpa¿Kmaks ……………..(ok)
Faktor momen pikul¿ faktor momen pikul maksimal, maka ukuran tebal pelat
lantai dapat digunakan

b). Tinggi blok tegangan beton tekan persegi ekivalen (a)

⟦ √
a = 1− 1−
2 .k
0,85 . f c⟧' . d

⟦ √
a = 1− 1−
2 .2,352
0,85 .30 ⟧
. 85

= 11,173 mm

c). Luas Tulangan Pokok (As)


0,85 . fc . a .b 0,85 .30 . 11,173 .1000
As = =
fy 300
= 791,4 mm2
Fc’ ¿ 31, 36 Mpa,
1,4 1,4
jadi As,u = . b . d= . 1000 . 85
fy 240
= 490,00 mm2
Dipilih yang terbesar, jadi As = 791,4 mm2

d). Jarak Tulangan (s)

22
2 2
1 1
.π .D .S .3,14 . 10 .1000
s= 4 = 4
As , u 791,4
= 99,282 mm
S ¿ (2 . h = 2 . 130 = 260 mm)
Diambil yang terkecil, jadi 90 mm

e). Luas TulanganTerpasang (As)


2 2
1 1
.π .D .s .3,14 . 10 .1000
As = 4 = 4
s 90
= 873 mm2 > As,u…… ……(ok)
Jadi tulangan pokok terpasang (As) = ∅ 10 – 90 = 873 mm2
Tulangan bagi :
As,b = 20%. As,u =20%.873= 174,6 mm2
As,b = 0,0020 . b . h = Asb,u = 260 mm2
Di gunakan tulangan bagi, D = 10 mm, maka jarak tulangan :
2 2
1 1
.π .D .s .3,14 . 10 .1000
s= 4 = 4
Asb , u 260
= 301,923 mm
S<(5.h =5.120 = 600)
Dipilih yanh kecil jadi, s = 300 mm (<301,923 mm)

f). Luas TulanganTerpasang (As)


2 2
1 1
.π .D .s .3,14 . 10 .1000
As,b = 4 = 4
s 300
= 261,799 mm2 > As,u…… ……(ok)
Jadi tulangan pokok terpasang (As) = ∅ 10 – 90 = 873 mm2
(As,b) = ∅ 10 – 300 =261,799 mm2

g). Kontrol momen desain

23
- Rasio Tulangan Pokok ( ρ )
As 873
ρ = .100 % = .100 % = 0,103%
b.d 1000.85
1,4 1,4
ρ min = .100% = .100 % = 0,567%
fy 240
382,5. β 1 . fc 382,5. 00,583 . 30
ρ maks = .100 % = 100 %
( 600+ fy ) . fy ( 600+240 ) . 300
= 2,957 mm2
Syarat : ρ min¿ ρ< ρ maks
Menghitung tinggi blok tegangan beton tekan
As . Fy 873.240
A= = = 8,216 mm
0,85. Fc . b 0,85.30.1000
Momen nominal
Mn = As .fy .( d – a/2) = 873. 300 . ( 105 –8,216/2)
= 264236148 Nmm
Momen desain plat
Md = ϕ .Mn = 0,9. 264236148 = 2378125332 Nmm = 23,781 kNm
Mu = 16,98 kNm
Syarat : Md > Mu (OK)

24
Tabel 4.2. Hasil Perhitungan Pelat Lantai
Tul. Pokok Tul. Pokok Tul. Bagi Tul. Bagi Momen
Momen Perlu
Tipe Plat Tumpuan Lapangan Tumpuan Lapangan Desain
(Kn/m)
(Mm) (Mm) (Mm) (Mm) (Knm)
Mlx(+)=7,86 ∅ 10-180 ∅ 10-180 12,720
Mly (+) =6,60 ∅ 10-180 ∅ 10-180 12,720
Mtx(-)=18,56 ∅ 10-90 ∅ 10-90 ∅ 10-300 ∅ 10-300 23,781
Mty(-)=16,98 ∅ 10-90 ∅ 10-90 ∅ 10-300 ∅ 10-300 23,781

Mlx(+) = 1,59 ∅ 10-180 ∅ 10-180 12,720


Mly (+) = 2,20 ∅ 10-180 ∅ 10-180 12,720
Mtx(-)= 3,21 ∅ 10-90 ∅ 10-90 ∅ 10-300 ∅ 10-300 23,781

Mty(-)= 15,69 ∅ 10-90 ∅ 10-90 ∅ 10-300 ∅ 10-300 23,781

Mlx(+)=4,53 ∅ 10-180 ∅ 10-180 12,720


Mly(+)=5,09 ∅ 10-180 ∅ 10-180 ∅ 10-300 ∅ 10-300 23,781
Mtx (-)= 9,66 ∅ 10-90 ∅ 10-90 ∅ 10-300 ∅ 10-300 23,781
Mty (-)= 18,13 ∅ 10-90 ∅ 10-90 ∅ 10-300 ∅ 10-300 23,781
Mlx(+)=1,55 ∅ 10-180 ∅ 10-180 12,720
Mly(+)=1,59 ∅ 10-180 ∅ 10-180 12,720
Mtx (-)= 3,17 ∅ 10-90 ∅ 10-90 ∅ 10-300 ∅ 10-300 23,781
Mty(-)= 6,97 ∅ 10-90 ∅ 10-90 ∅ 10-300 ∅ 10-300 23,781

25
Gambar. 4.3. Detail Penulangan plat lantai Type 1
Sumber : Gambar AutoCAD

26
4.3 Perhitungan Beban Gempa

Gambar 4.4 Denah Struktur Lantai 2


Sumber : Gambar AutoCAD

Gambar 4.5 Portal Arah X


Sumber : Gambar AutoCAD

Gambar 4.6 Portal Arah Y


Sumber : Gambar AutoCAD

65
1) Data
Lokasi = Kota Kupang
Fungsi Bangunan = Rumah Susun Kejaksaan Kupang
Kondisi Tanah = Tanah Keras (SC) (Asumsi)
Faktor Keutamaan = 1,0 (SNI 03-1726-2019)
Gempa (Ie)
Koef modifikasi respon = 8 (SNI 03-1726-2019)
Kategori Resiko = II (SNI 03-1726-2019)
Berat Atap Total = 20.420,94 kg
Tebal Pelat Lantai = 13 cm
Dimensi Balok = a. 25 cm x 55 cm (Gambar Kerja)
b. 25 cm x 55 cm (Gambar Kerja)
=
c. 25 cm x 55 cm (Gambar Kerja)
d. 25 cm x 30 cm (Gambar Kerja)
e. 25 cm x 40 cm (Gambar Kerja)
Dimensi Ring Balk = 25 cm x 40 cm (Gambar Kerja)
Dimemsi Kolom = a. 40 cm x 40 cm Gambar Kerja)
b. 30 cm x 30 cm (Gambar Kerja)
c. 30 cm x 55 cm (Gambar Kerja)
d. 30 cm x 55 cm (Gambar Kerja)
e. 40 cm x 40 cm (Gambar Kerja)
f. 30 cm x 55 cm (Gambar Kerja)
Beton Bertulang = 2400 kg/m (PeraturanPembebanan Indonesia
2

untuk Gedung 1987)


Dinding ½ Bata = 250 kg/m2(Peraturan Pembebanan Indonesia
untuk Gedung 1983)
Berat Keramik 60 x 60 = 45,5 kg/m2 (Sumber Online)

Lokasi bangunan termasuk kelas situs SC (kondisi tanah sedang).


Bangunan berfungsi sebagai Rumah Susun dengan kategori resiko II
seperti gambar dibawah ini dengan faktor keutamaan gempa (le) = 1,0
seperti gambar 4.6

66
Gambar 4.7 Jenis Pemanfaatan
Sumber : SNI 1726 : 2019

Gambar 4.6 Faktor Keutamaan


Sumber : SNI 1726 : 2019

Untuk Kota Kupang, diperoleh parameter respon spektra percepatan


gempa untuk perioda pendek Ss = 1.0473 g dan parameter respon spektra
percepatan gempa untuk perioda 1 detik S1 = 0.37 g.
Sehingga :
1. Faktor amplikasi getaran terkait percepatan pada getaran periode
pendek Fa = 1,2
2. Faktor amplikasi terkait percepatan yang mewakili getaran perioda 1
detik Fv = 1,5
3. Parameter spektrum respon percepatan pada perioda pendek SMS = Fa x
Ss = 1,2 x 1,0473 = 1,256 gr
4. Parameter spektrum respon percepatan pada periode 1 detik (SM1) = fv x
S1 = 1,5 x 0,37 = 0,55 gr

67
5. Parameter percepatan spektra desain untuk perioda pendek, SDS = 2/3 x
SMS = 0,837 gr
6. Parameter percepatan spektra desain untuk perioda pendek, SD1 = 2/3 x
SM1 = 0,36 gr
Tabel 4.2 Koefisien situs Fa

Sumber : SNI 03-1726-2019

Tabel 4.3 Koefisien situs Fv

Sumber : SNI 03-1726-2019

Kategori desain sismik berdasarkan parameter respon percepatan


pada perioda pendek SDS adalah KDS A(Tabel 4.4). Kategori desain
seismik berdasarkan parameter respons percepatan pada perioda 1 detik
(SD1) adalah KDS A (Tabel 4.5). Sehingga kategori desain sesmik
berdasarkan nilai SDS dan SD1 termasuk dalam KSD A
Struktur beton bertulang dan sistem penahan gaya seismik yang
digunakan adalah sistem rangka pemikul momen khusus. Untuk rangka
beton bertulang pemikul momen khusus SRMPK arah ortogonal sama
digunakan koefisien respons (R), Rx = Ry = 8,0.

Tabel 4.4 Kategori desain sismik berdasrkan parameter respons percepatan pada
periode pendek

68
Sumber : SNI 03-1726-2019

Tabel 4.5 Kategori desain seismik berdasarkan parameter respon percepatan pada
periode 1 detik

Sumber : SNI 03-1726-2019

Gambar 4.8 Sistem Pemikul Gaya Seismik


Sumber : SNI 1726 : 2019

69
3) Perhitungan Beban Mati Dan Beban Hidup Lantai 2
a) Beban Mati (Wm Lantai 2)
Berat Atap
= 20.420,94 kg = 20.420,94 kg
Total
Ring = 25 x 40
Balok (6,450m x 16) x (0,25m x 0,4m) x 2.400 kg/m3 = 24.768 kg
(6 m x 24) x (0,25m x 0,4m) x 2.400 kg/m3 = 34.560 kg
(4 m x 4) x (0,25m x 0,4m) x 2.400 kg/m3 = 3.840 kg
(2,250 m x 8) x (0,25m x 0,4m) x 2.400 kg/m3 = 4.320 kg
Kolom = (24 x 1,75m) x (0,4m x 0,4m) x 2.400 kg/m3 = 16.128 kg
(2 x 1,75m) x (0,3m x 0,3m) x 2.400 kg/m3 = 756 kg
(8 x 1,75m) x (0,3m x 0,55m) x 2.400 kg/m3 = 5.544 kg
Spesi = (15,15m x 40m) x 21 kg/ m2 = 12.726 kg
Keramik = (15,15m x 40m) x (0,6mm x 0,6mm) x 45,5 kg/m2 = 9.926 kg/m2
60 x 60
Dinding = 928,43m x 1,75m x 250 kg/m2 = 406.188 kg
Plafond = 465,57m x (15 kg/m2 +12 kg/m2) = 12.570,39 m +
Wm lantai = 7.014,822 kg/m
= 70.148,22 Kn/m
b) Beban Hidup
Qh Atap = 100 kg/m2
Koefisien reduksi = 0,80
Wh Atap = 100 kg/m2 x 0,80
= 4.412 kg/m2
c) Berat total lantai 2
= 4.412 kg/m2 + 7.014,822 kg/m
= 7.019,234 kg/m
4) Perhitungan Beban Mati Dan Beban Hidup Lantai 1
a) Beban Mati (Wm Lantai 1)
Balok = (6m x 8) x (0,3m x 0,55m) x 2.400 kg/m3 = 19008 kg
(4m x 4) x (0,3m x 0,55m) x 2.400 kg/m3 = 6336 kg
(6,450m x 14) x (0,25m x 0,55m) x 2.400 kg/m3 = 25.542 kg

70
(6m x 12) x (0,3m x 0,55m) x 2.400 kg/m3 = 28.512 kg
(2,25m x 7) x (0,25m x 0,3m) x 2.400 kg/m3 = 2.835 kg
(6,45m x 4) x (0,25m x 0,4m) x 2.400 kg/m3 = 6.192 kg
(2,25m x 2) x (0,25m x 0,4m) x 2.400 kg/m3 = 1.080 kg
Kolom = (34 x 1,75m) x (0,4m x 0,4m) x 2.400 kg/m3 = 22.848 kg
(2 x 1,75m) x (0,2m x 0,2m) x 2.400 kg/m3 = 336 kg
(8 x 1,75m) x (0,3m x 0,55m) x 2.400 kg/m3 = 5.544 kg
Pelat = (6m x 6,45m) x 12 x 0,13m x 2.400 kg/m3 = 144,893 kg
Lantai (4m x 6,45m) x 2 x 0,13m x 2.400 kg/m3 = 16,099 kg
(6m x 2,25m) x 6 x 0,13m x 2.400 kg/m3 = 25,272 kg
(4m x 2,25m) x 1 x 0,13m x 2.400 kg/m3 = 2,808 kg
Spesi = (15,15m x 40m) x 21 kg/ m2 = 12.726 kg
Keramik = (15,15m x 40m) x (0,6 mx 0,6m) x 45,5 kg/m2 = 27,573 kg/m2
60 x 60
Dinding = 1039m x 3,55m x 250 kg/m2 = 922.742,625 kg

Plafond = 465,43m x (15 kg/m2 +12 kg/m2) = 8.377,74 kg/m +


Wm lantai = 1.557,508 kg/m
= 15.575,08 KN/m

b) Beban Hidup (Wh)


Beban Hidup = 250 kg/m2
Koefisien Reduksi = 0,80
Wh Lantai 1 = 0,8 x (55,5m x 250m)
= 11.050 kg
d) Berat total lantai 1
= 11.050 kg + 1.557,508 kg/m
= 1.568,558 kg/m

71
5. Total Berat Bangunan
W = w2 + w1
W = 7.019,234 kg/m + 1.568,558 kg/m
W = 8.587,792 kg : 100 = 85.878 Kn

6. Hitung periode fudamental pendekatan (Ta)


Ta = Ct hnx
Ct = 0.0466 (Sumber SNI 03-1726-2019)
x = 0,9 (Sumber SNI 03-1726-2019)
hn = 7 m (Total Tinggi Lantai)
Ta = Ct hnx
Ta = 0.0466 x 7 m0,9 = 0,268 detik
SD1 = 0.4 detik > 0,4 detik maka Cu = 1,4 (Sumber SNI 03-1726-2019)
Tmax = Cu Ta = 0,37 detik
Digunakan nilai T = 0.268 detik
Perhitungan Gaya Geser Sismik (V)
TL = 6 detik
T = 0,268 detik < TL maka
Cs min = 0,044 x 0,837 x 1 = 0,36
SD 1 0,36
Cs max = R 8 = 0,16
T ( ) 0,268( )
Ie 1
SDS 0,837
Cs = R 8
( )
= 0,11
Ie 1
Maka digunakan Cs = 0,11

7. Distribusi Vertikal Gaya Gempa (fx)


Gaya seismik lateral Fx di sebarang tingkat harus ditentukan dari persamaan
berikut : Fx = Cs x w
Cs = 0,11
W = 85.878 Kn
V = 0,11 x 85.878 Kn = 9.446,58 Kn

72
Dimana :
Cvx = faktor distribusi vertikal,
V = gaya lateral disain total atau geser di dasar struktur (kN)
wi dan wx= bagian berat seismik efektif total struktur (W) yang ditempatkan
atau dikenakan pada tingkat i atau x;
hi dan hx = tinggi dari dasar sampai tingkat i atau x (m)
k = eksponen yang terkait dengan perioda struktur sebagai berikut:
1. untuk struktur yang mempunyai T ≤ 0,5 detik k = 1
2. untuk struktur yang mempunyai T ≥ 2,5 detik k = 2
3. untuk struktur yang mempunyai 0,5 < T > 2,5 detik, k ditentukan dengan
interpolasi linier antara point 1 dan 2 di atas
Sehingga untuk T = 0,268 detik maka
0,268−0,5 k−1
= k = 1,16
2,5−0,5 2−1

8. Gaya lateral tiap lantai


Lantai hi Tiap portal (kN)
hik wi (Kn) Wi hik Fi x-y (KN)
ke i (m) Fi x-y/4x Fi x-y/6y
2 7 9,55 7.019,234 67.033,685` 5,04325 1,261 0,841
1 3,5 4,27 1.557,508 6.650,508 4,13278 1,033 0,688

 8.576,742 73.684,244

73
Gambar 4.9 Distribusi beban gempa untuk portal arah X
Sumber : Gambar AutoCAD

Gambar 4.10 Distribusi beban gempa untuk portal arah Y


Sumber : Gambar AutoCAD

4.4 Perhitungan Beban Gravitasi

74
Gambar 4.11 Pembagian Beban Equivalen
Sumber : Gambar AutoCAD

1. Perhitungan Beban Gravitasi Merata Equivalen Untuk Portal Arah x


a. Ly = 6,45 m
Lx = 6 m

½. Lx . qu

Ly = 6,45 m

1
Qeq = lx . ¿
6
1
= 6m.¿
6
=1m ¿
= 1 m x 2,13 m
= 2,13 m

A. Perhitungan beban-beban yang bekerja pada tiap lantai, untuk potongan


portal

75
a–b
1. Beban merata pada lantai 2
Beban mati :
Atap = Beban Atap : Jarak Bentangan Kuda-Kuda
= 20.420,94kg/m2 : 15,149 m = 1.348,005 kg/m
Plafond = Berat Pengantung + Plafon ×Leg Total
= 15 kg/m2+ 12 kg/m2× 2,13 m = 57,51 kg/m
Ring Balok = Dimensi RingBalok × Berat Jenis
= 25 x 40
(0,25m x 0,4m) x 2.400 kg/m3 = 240 kg/m +
qeq =1.645,515kg/m

Beban hidup :
Qh atap = 100 kg/m2
= 100 kg/m2 × 2,13 m
= 213 kg/m

2 .Beban merata pada lantai 1


Beban mati :
Balok = 30 x 55
(0,3m x 0,55m) x 2.400 kg/m3 = 396 kg/m
25 x 55
(0,25m x 0,55m) x 2.400 kg/m3 = 330 kg/m
25 x 30
(0,25m x 0,3m) x 2.400 kg/m3 = 180 kg/m
Kolom = 40 x 40
(0,4m x 0,4m) x 2.400 kg/m3 = 384 kg/m
30 x 55
(0,3m x 0,55m) x 2.400 kg/m3 = 396 kg/m

Plat Lantai = Ukuran plat × (qeq) × berat jenis


(12 x 0,13m x 2,13m) × 2.400 kg/m3 = 7.974,72 kg/m

76
Spesi = (qeq) × berat jenis
2,13m x 21 kg/m2 = 44,73 kg/m
Keramik = (qeq) × berat jenis
60 x 60 2,13m × 45,5 kg/ m2 = 96,915 kg/m
Dinding = Ukuran bangunan × berat jenis
3,55m x 250 kg/m2 = 887,5 kg/m
Plafond = (qeq) × berat plafond
2,13m × (15 kg/m2 +12 kg/m2) = 57,51 kg/m +
Wm lantai 1 = 10.747,375 kg
= 105,4 Kn

Beban hidup :
qh lantai = 250 kg/m2
beban hidup equivalen = 250 kg/m2 x 2,13 m
= 532,5 kg/m

b. Ly = 2,250 m
Lx = 6 m

q = ½q . Lx

qeq
Lx = 6 m
q = ½ q . Lx
= ½. q .6 m
q=3
qeq = 1/3. qu . Lx
= 1/3 .1,25 . 3 q
qeq = 1,25 m

1. Beban merata pada lantai 2


Beban mati :

77
Atap = Beban Atap : Jarak Bentangan Kuda-Kuda
= 20.420,94kg/m2 : 15,149 meter = 1.348,005 kg/m
Plafond = Berat Pengantung + Plafon × Leg Total
= 15 kg/m2+ 12 kg/m2× 1,25 m = 33,75 kg/m
Ring Balok = Dimensi RingBalok × Berat Jenis
= 25 x 40
(0,25m x 0,4m) x 2.400 kg/m3 = 240 kg/m +
qeq =1.621,755kg/m

Beban hidup Lantai 2 :


qhatap = 100 kg/m2
= 100 kg/m2 ×1,25 m
= 125 kg/m

2 .Beban merata pada lantai 1


Beban mati :
Balok = 30 x 55
(0,3m x 0,55m) x 2.400 kg/m3 = 396 kg/m
25 x 55
(0,25m x 0,55m) x 2.400 kg/m3 = 330 kg/m
25 x 30
(0,25m x 0,3m) x 2.400 kg/m3 = 180 kg/m
25 x 40
(0,25m x 0,4m) x 2.400 kg/m3 = 240 kg/m
Kolom = 40 x 40
(0,4m x 0,4m) x 2.400 kg/m3 = 384 kg/m
30 x 55
(0,3m x 0,55m) x 2.400 kg/m3 = 396 kg/m
Plat Lantai = Ukuran plat × (qeq) × berat jenis
(12 x 0,13m x1,25m)× 2.400 kg/m3 = 4.680kg/m

Spesi = (qeq) × berat jenis

78
1,25m x 21 kg/ m2 = 26,25 kg/m
Keramik = (qeq) × berat jenis
60 x 60 1,25m × 45,5 kg/ m2 = 56,875 kg/m
Dinding = Ukuran bangunan × berat jenis
3,55m x 250 kg/m2 = 887,5 kg/m
Plafond = (qeq) × berat plafond
1,25m × (15 kg/m2 +12 kg/m2) = 33,75 kg/m +
Wm lantai 1 = 7.610,375 kg/m
= 74,632 Kn

Beban hidup Lantai 1 :


qh lantai = 250 kg/m2
beban hidup equivalen = 250 kg/m2 x 1,25m
= 312,5kg/m

2. Perhitungan Beban Gravitasi Merata Equivalen Untuk Portal Arah X


a. Ly = 2,25 m
Lx = 6 m

½. Lx .qu

Ly = 2,25 m

1
Qeq = lx .¿
6
1
= 6 m .¿
6
= 1,02m ¿
= 1,02 m x 4,13 m
= 4,21m

79
B. Perhitungan beban-beban yang bekerja pada tiap lantai, untuk potongan
portal Y
a–b
1. Beban merata pada lantai 2
Beban mati :
Atap = Beban Atap : Jarak Bentangan Kuda-Kuda
= 20.420,94kg/m2 : 15,149 meter = 1.348,005 kg/m
Plafond = Berat Pengantung + Plafon × Leg Total
= 15 kg/m2+ 12 kg/m2× 4,21 m = 113,67 kg/m
Ring Balok = Dimensi RingBalok × Berat Jenis
= 25 x 40
(0,25m x 0,4m) x 2.400 kg/m3 = 240 kg/m +
qeq =1701,675kg/m

Beban hidup :
qhatap = 100 kg/m2
= 100 kg/m2 ×4,21m
= 421 kg/m

2 .Beban merata pada lantai 1


Beban mati :
Balok = 30 x 55
(0,3m x 0,55m) x 2.400 kg/m3 = 396 kg/m
25 x 55
(0,25m x 0,55m) x 2.400 kg/m3 = 330 kg/m
25 x 30
(0,25m x 0,3m) x 2.400 kg/m3 = 180 kg/m
Kolom = 40 x 40
(0,4m x 0,4m) x 2.400 kg/m3 = 384 kg/m
30 x 55
(0,3m x 0,55m) x 2.400 kg/m3 = 396 kg/m
Plat Lantai = Ukuran plat × (qeq) × berat jenis

80
(12 x 0,13m x 4,21 m) × 2.400 kg/m3 =15.762,24 kg/m
Spesi = (qeq) × berat jenis
4,21 m x 21 kg/ m2 =88,41 kg/m
Keramik = (qeq) × berat jenis
60 x 60 4,21 m × 45,5 kg/ m2 = 191,555 kg/m
Dinding = Ukuran bangunan × berat jenis
3,55m x 250 kg/m2 = 887,5 kg/m
Plafond = (qeq) × berat plafond
4,21 m × (15 kg/m2 +12 kg/m2) = 113,67 kg/m +
Wm lantai 1 = 18.729,37Kg/m
= 187,293 Kn

Beban hidup :
qh lantai = 250 kg/m2
beban hidup equivalen = 250 kg/m2 x 4,21 m
= 1.052,5 kg/m

b. Ly = 2,25 m
Lx = 4 m

½. Lx .qu

Ly = 2,25 m

1
Qeq = lx .¿
6
1
= 4 m .¿
6
= 0,64m ¿
= 0,64 m x 0,17 m
= 0,11m

81
C. Perhitungan beban-beban yang bekerja pada tiap lantai, untuk potongan
portal Y
a–b
1. Beban merata pada lantai 2
Beban mati :
Atap = Beban Atap : Jarak Bentangan Kuda-Kuda
= 20.420,94kg/m2 : 15,149 meter = 1.348,005 kg/m
Plafond = Berat Pengantung + Plafon × Leg Total
= 15 kg/m2+ 12 kg/m2× 0,11 m = 2,97 kg/m
Ring Balok = Dimensi RingBalok × Berat Jenis
= 25 x 40
(0,25m x 0,4m) x 2.400 kg/m3 = 240 kg +
qeq =1590,975kg/m

Beban hidup :
qhatap = 100 kg/m2
= 100 kg/m2 ×0,11m
= 11 kg/m

2 .Beban merata pada lantai 1


Beban mati :
Balok = 30 x 55
(0,3m x 0,55m) x 2.400 kg/m3 = 396 kg/m
25 x 55
(0,25m x 0,55m) x 2.400 kg/m3 = 330 kg/m
25 x 30
(0,25m x 0,3m) x 2.400 kg/m3 = 180 kg/m

Kolom = 40 x 40
(0,4m x 0,4m) x 2.400 kg/m3 = 384 kg/m
30 x 55
(0,3m x 0,55m) x 2.400 kg/m3 = 396 kg/m

82
Plat Lantai = Ukuran plat × (qeq) × berat jenis
(12 x 0,13 x 2,13m) × 2.400 kg/m3 = 7.974,72 kg/m
Spesi = (qeq) × berat jenis
0,11 m x 21 kg/ m2 = 2,31 kg/m
Keramik = (qeq) × berat jenis
60 x 60 0,11 m × 45,5 kg/ m2 = 5,005 kg/m
Dinding = Ukuran bangunan × berat jenis
3,55m x 250 kg/m2 = 887,5 kg/m
Plafond = (qeq) × berat plafond
0,11 m × (15 kg/m2 +12 kg/m2) = 2,97 kg/m +
Wm lantai 1 = 10558,505 kg/m
= 105.585 Kn

Beban hidup :
qh lantai = 250 kg/m2
beban hidup equivalen = 250 kg/m2 x 0,11 m
= 27,5 kg/m

 Sketsa Beban Gravitasi


a. Beban Mati
Arah X

Gabaar 4.12 Portal Arah X


Sumber : AutoCAD

83
Gambar 4.13 Portal Arah Y
Sumber : AutoCAD

b. Beban Hidup
Arah X

Gambar 4.14 Portal Arah X


Sumber : AutoCAD

84
Gambar 4.15 Portal Arah Y
Sumber : AutoCAD

4.4. Analisa Gaya-Gaya Dalam Dengan Menggunakan Software SAP 2000


Dalam penulisan tugas akhir ini, penulis mengunakan bantuan program
SAP 2000 versi 18.1, untuk menganalisis gaya-gaya dalam yang terjadi.
Berikut hasil SAP 2000 versi 18.1 :

Gambar 4.16. Analisa gaya-gaya dalam


Sumber: Sofware SAP 2000 V18.1

85
Gambar 4.17. Momen kombinasi 2 arah x
Sumber: Sofware SAP 2000 V18.1

Gambar 4.18 Momen kombinasi 2 arah y


Sumber: Sofware SAP 2000 V18.1

86
Gambar 4.19 Lintang kombinasi 1 frame 191 dan 192
Sumber: Sofware SAP 2000 V18.1

4.5. Perancanaan Balok


Mutu beton (fc) = 25 Mpa
Mutu baja (fy) = 300 Mpa
Dimensi balok = 300 mm x 550 mm
Koefisie reduksi = 0,8
Tulangan Pokok = D 16
Tulangan Sengkang = Ø
1
0
tebal selimut beton (p) = 60 mm
Momen Tumpuan rencana = 68.64691Ton/m = 68646,91 (+) Kn/m
Momen Lapangan rencana = -74.16105 Ton/m = -74161,05(-) Kn/m
Gaya geser Lapangan = -87,4272 Ton-m = -87427,2 Kn/m
Gaya geser Tumpuan = 87.45234 Ton/m = 87452,34 Kn/m

87
A. Balok Induk 300 mm x 550 mm
a. Perhitungan Longitudinal
1. Tulangan longitudinal di daerah tumpuan
Dipilih nilai (Mu+) terbesar yaitu : 68.64691 Ton/m = 6864,91 (+)
Kn/m
d = h – ds
= 550 mm – 60 mm = 490 mm
Dari tabel III.4 dalam buku ” Balok Dan Pelat Beton Bertulang ”
karangan Ali Asroni, kita dapat melihat bahwa nilai Kmaks untuk
untuk fc’ 25 Mpa dan fy = 300 adalah = 7,1121 Mpa
6
Kn
Mu 6864,91 .10
K= 2 = m = 1,191 Mpa
∅.b.d 2
0,8 . 300 . 490
K ¿ Kmaks = dipakai tulangan tunggal

( √
a = 1− 1−
2 . K max
0,85 . fc ' )
.d

a=(
√1− 1−
2. 1,191
)
0,85 . 25
. 490 = 52,926 mm

Luas tulangan perlu As,u :


0,85 . f c ' . a . b 0,85 .25 . 52,926 .300
As = =
300
= 1.124,67 mm2
fy
Dari tabel III.3 ” Balok Dan Pelat Beton Bertulang ” karangan Ali
Asroni diperoleh nilai ρ min = 0,467%
As min = ρ min . b . d = 0,467 % . 300 . 490 = 686,49 mm2
Dipilih yang terbesar, jadi As,u = 1.124,67 mm2
Jumlah tulangan (n) :
2
As , u 1.124,67 mm
n = 1 . π . ∅2 = 1 2
.3,14 .( 16 mm)
4 4
= 5,59 → dipakai 6 batang ∅ 16)
Jumlah tulangan perbaris (m) :

88
Jarak bersih antar tulangan (Sn) disarankan untuk di ambil d ≥ 40
mm (SNI 03- 2847-2002 ; pasal 9.6 : 1)
b−2. ds 300−(2 x 60)
m= +1= + 1 = 3,36 → maksimal 4 batang
D+ Sn 16+ 60

Kontrol :
Kontrol keamanan momen rencana (Mr) dan regangan tegangan
beton (ε c’):
As = 18∅ 16 = 18 x ¼ x 3,14 x (16 mm)2 = 3.617,28 mm
As . fy 3.617,28. 300
a= ' = = 170,22 mm
0,85 . f c . b 0,85 .25 . 300
Mn = As . fy . (d-a/2)
= 3.617,28 x 300 . + (490 – 170,22 /2)
= 1.085.588,89 Nmm = 10.855,90 kNm
Syarat = Mr ¿ Mu
Mr = ∅ . Mn = 0,8 x 10.855,90 kNm = 8.644,72>¿ 6.864,91 →
aman.
Es = Modulus Elestisitas : 200.000 Mpa
εy = fy/Es = 300/200.000 = 0,0015
β1 = untuk fc’ ≤ 25 Mpa maka β 1 = 0,85
a
ε 'c = x εy
β 1 . d−a
170,22
= x 0,0015 = 0,626240
0,85 .(490−170,22)
Syarat = ε ' c ¿ 0,003 → aman

Dalam perhitungan di atas kita ketahui bahwa daerah tumpuan


maupun daerah tumpuan mimiliki nilai K ¿ K maks yang artinya bahwa
balok tersebut merupakan jenis balok dengan tulangan tunggal. Akan
tetapi dengan beberapa pertimbangan untuk menambahkan kekuatan balok
agar dapat menahan beban yang bekerja di atasnya, dan juga berfungsi
untuk memperkuat kekuatan begel. Maka perlu untuk menambahkan

89
tulangan tekan pada balok, minimal sebanyak 2 batang (Ali Asroni; Pelat
dan Balok Beton Bertulangan).
Dari perhitungan di atas penulis mendapatkan pemasangan tulangan
longitudinal didaerah tumpuan, balok dengan ukuran 300 mm x 550 mm
(untuk tulanngan pokok) 4 buah 4 D16. Sedangankan pemasangan
tulangan longitudinal untuk tulangan pokok di daerah lapangan tidak jauh
berbeda dengan hasil perhitungan penulis.
2. Tulangan longitudinal di daerah Lapangan
Dipilih nilai (Mu - ) terbesar yaitu 74.16105 Ton/m -74161,05 Kn/m
(dari hasil analisa SAP 2000)
d = h – ds
= 550 mm – 60 mm
= 490 mm
Dari tabel III.4 dalam buku” Balok Dan Pelat Beton Bertulang”
karangan Ali Asroni, kita dapat melihat bahwa nilai Kmaks untuk
untuk fc’ 25 Mpa dan fy = 300 adalah = 5,678 Mpa
Mu 74161,05 KN −m❑
K= =
∅ . b . d2 0,8 .300 . 490
2

=6,67 Mpa
K ¿ Kmaks = dipakai tulangan tunggal

( √
a = 1− 1−
2 . K max
0,85 . fc '
.d )
a=(

1− 1−
6 , 67
0,85 . 25 )
. 490

= 57,55 mm
Luas tulangan perlu As,u :
0,85 . f c ' . a . b 0,85 .25 . 57,55 .300
As = =
300
=1.222,937 mm2
fy
Dari tabel contoh III.3 ” Balok Dan Pelat Beton Bertulang ”
karangan Ali Asroni diperoleh nilai ρ min = 0,467%
As min = ρ min . b . d = 0,467 % . 300 . 490 = 686,49 mm2
Dipilih yang terbesar, jadi As,u = 1.222,937 mm2
Jumlah tulangan (n) :

90
As , u 1.222,937 mm2
n = 1 . π . ∅ = 1 .3,14 .( 16 mm)2
2

4 4
= 6,08 → dipakai 6 batang
Jumlah tulangan perbaris (m) :
Jarak bersih antar tulangan (Sn) disarankan untuk di ambil d ≥ 40
mm (SNI 03- 2847-2002; pasal 9.6 : 1)
b−2. ds 300−(2 x 60)
m= +1= + 1 = 3,36 → maksimal 4 batang
D+ Sn 16+ 60
Kontrol :
Kontrol keamanan momen rencana (Mr) dan regangan tegangan
beton (ε c’):
As = 6∅ 16 = 6 x ¼ x 3,14 x (16 mm)2 = 1.205,76 mm
As . fy 1.205,76 .300
a= ' = = 56,741 mm
0,85 . f c . b 0,85 .25 . 300
Mn = As . fy . (d-a/2)
= 1.205,76 x 300 + (490 – 56,741 /2)
= 362.189,63 Nmm = 362,18963 kNm
Syarat = Mr ¿ Mu
Mr = ∅ . Mn = 0,8 . 362,18963 = 289.751>¿ 6.864,91 → aman.
Es = Modulus Elestisitas : 200.000 Mpa
εy = fy/Es = 300/200.000 = 0,0015
β1 = untuk fc’ ≤ 25 Mpa maka β 1 = 0,85
a
ε 'c = x εy
β1.d.a
56,741
= x 0,0015 = 0,000231111684
0,85 .(490−56,741)
Syarat = ε ' c ¿ 0,003 → aman

Dalam perhitungan di atas kita ketahui bahwa daerah tumpuan


maupun daerah lapangan mimiliki nilai K ¿ K maks yang artinya bahwa
balok tersebut merupakan jenis balok dengan tulangan tunggal. Akan
tetapi dengan beberapa pertimbangan untuk menambahkan kekuatan balok
agar dapat menahan beban yang bekerja di atasnya, dan juga berfungsi

91
untuk memperkuat kekuatan begel. Maka perlu untuk menambahkan
tulangan tekan pada balok, minimal sebanyak 2 batang (Ali Asroni; Pelat
dan Balok Beton Bertulangan).
Dari perhitungan di atas penulis mendapatkan pemasangan tulangan
longitudinal didaerah tumpuan, balok dengan ukuran 300 x 550 mm
(untuk tulanngan pokok) 6 buah 6 D 16. Sedangankan pemasangan
tulangan longitudinal untuk tulangan pokok di daerah lapangan tidak jauh
berbeda dengan hasil perhitungan penulis.
b. Tulangan Geser Balok
1. Tulangan Geser Di Daerah Tumpuan

Dipilih nilai (Vu ) terbesar yaitu : 87.45234 Ton/m = 87452,34 Kn/m


(dari hasil analisa SAP 2000)
Mutu beton (fc) = 25 Mpa
Mutu baja (fy) = 300 Mpa
Dimensi balok = 300 mm x 550 mm
Koefisie reduksi = 0,8
Pokok ∅ 16
=
Sengkang = ∅ 10

tebal selimut beton (p) = 60 mm

Vc = 0 (kerena pada daerah sendi plastis gaya geser maksimal


seluruhnya dipkul oleh tulangan geser, hal ini dianggap demikian
karena gaya aksial yang terjadi

92
pada daerah sendi plastis besarnya sangat kecil (sumber : Buku
perencanan struktur beton bertulangan Tahan gempa ; Ir Rachmat
Purwano, M. Sc )
sehingga:
Vc = ∅ Vc = Vc/2
Vc > Φ Vc
Dihitung gaya geser yang ditahan begel (Vs) :
87,45234−0
Vs = ¿ ¿ = = 109,315425 Kn
0,8
Luas begel perlu permeter panjang balok (Av,u)
S = panjang balok 1000 mm (SNI 03- 2847- 2002; pasal 13.5.6.2)
75 √ f c . b . s 75 . √ 25 .300 .1000
'
Av,u = = =312,5 mm2
1200 . fy 1200 . 300
b . s 300 .1000
Av,u = = = 33,333 mm2
3 . fy 3 .300
Pilih Av,u yang paling besar, jadi Av,u = 33,333 mm2
Vs = 2/3 √ f c ' . b . d
= 2/3 √ 25 . 300 . 240
= 237.600 = 237.60 Kn
Vs = 1/3 √ 25 . b . d
= 1/3 . √ 25 . 300 . 240
= 118.800 = 118.80 Kn
Spesi begel (s)
1 1
n . . π .dp 2 . s 6 . . 3,14 . 102 .1000
S= 4 = 4 = 471.000 mm
Av , u 33,333
Kontrol spesi begel (s)
S ≤ d/2 = 240 /2 = 120 mm
S ≤ 300 mm
Diplih s yang paling kecil, yaitu s = 120 mm
Jadi digunakan begel ∅ 10 – 120

2. Tulangan Geser Di Daerah Lapangan

93
Dipilih nilai (Vu ) terbesar yaitu : -87,4272 Ton-m = -87427,2
Kn/m (dari hasil analisa SAP 2000)
Mutu beton (fc) = 25 Mpa
Mutu baja (fy) = 300 Mpa
Dimensi balok = 300 mm x 550 mm
Koefisie reduksi = 0,8
Pokok = ∅ 16
Sengkang = Ø
1
0
tebal selimut beton (p) = 60 mm
d = h – ds
= 550 mm – 60 mm = 490 mm
Vc = 1/6 √ f c ' . b . d = 1/6 √ 25 . 300 . 490
= 122.500 = 122,50 kN
Φ Vc/2 = 122.500/2 = 61.250 = 61,25 kN
Gaya geser yang ditahan begel (Vs) :
Vu ¿ ∅ . Vc
−87427,2−0,8−122,50
Vs = ¿ ¿ = = 87.303,9 kN
0,8
Luas begel perlu permeter panjang balok (Av,u)
75 √ f c' . b . s 75 . √ 25 .300 .1000
Av,u = = =31,25 mm2
1200 . fy 1200 . 300
b . s 300 .1000
Av,u = = = 333,33 mm2
3 . fy 3 .300
Pilih Av,u yang paling besar, jadi Av,u = 333,33 mm2
Vs = 2/3 √ f c ' . b . d
= 2/3 √ 25 . 300 . 490
= 485.100 = 485,1 Kn
Vs = 1/3 √ 25 . b . d
= 1/3 . √ 25 . 300 . 490
= 242.550 = 242,55 Kn

94
Vs = 242,55 karena nilai Vs ¿ 1/3 √ f c ' . b . d maka dipilih begel 2
kaki berdiameter 10 mm
spesi begel (s)
1 1
n . . π .dp 2 . s 2. . 3,14 .10 2 .1000
S= 4 = 4 = 471,00 mm
Av , u 333,33
Kontrol spasi begel (s)
S ≤ d/2 = 490 /2 = 245 mm
S ≤ 550 mm
Diplih s yang paling kecil, yaitu s = 245 mm
Jadi digunakan begel ∅ 10 – 250

Gambar 4.20 Perencanaan balok induk 30/50


Sumber : AutoCAD

95
BAB V
PENUTUP
5.1 Kesimpulan
Dari hasil perhitungan penulis dalam penyusun laporan Tugas Akhir
ini, penulis dapat menyimpulkan beberapa hal tersebut sebagai berikut :
1. Penulangan Plat Lantai
a. Daerah Tumpuan Arah x
- Tulangan Pokok Terhitung ∅ 10-180 mm
- Tulangan Bagi Terpasang ∅ 10-300 mm
b. Daerah Lapangan Arah y
- Tulangan Pokok Terhitung ∅ 10-90 mm
- Tulangan Bagi Terpasang ∅ 10-300 mm
2. Penulangan Balok Induk (30/55)
c. Daerah Tumpuan
- Tulangan Longitudinal 6 D 16
- Tulangan Geser ∅ 10 – 150 mm
d. Daerah lapangan
- Tulangan Longitudinal 6 D 16
- Tulangan Geser ∅ 10 – 250 mm

5.2 Saran

96
Ada beberapa hal yang perlu sarankan berdasarkan hasil perhitungan struktur
beton bertulangan dalam tugas akhir ini :
1. Dalam perhitungan analisis struktur diharapakan agar selalu teliti,
sehingga hasil desain dapat memenuhi syarat kekuatan dan ekonomis, oleh
sebab itu penulis sarankan agar menggunakan metode yang telah dikuasi
dengan baik.
2. Kepada rekan-rekan yang akan ataupun sedang menyusun laporan tugas
akhir khususnya struktur agar dapat memahami dengan benar seluruh
perhitungan dan gambar laporan tugas akhir tersebut.

97