PERHITUNGAN BIAYA

PEMBUATAN TERAS SAMPING

HARGA JUMLAH
NO RINCIAN BAHAN/UPAH VOLUME SATUAN SATUAN HARGA
(Rp) (Rp)

A MATERIAL/BAHAN
1 Baja ringan canal C 75.50 162,00 Btg 125.000 20.250.000
2 Reng baja ringan K01 286,00 Btg 60.000 17.160.000
3 Spandeck Galvalum 0,25mm (6 mtr) 50,00 Lbr 300.000 15.000.000
4 Dinabold 12mm 50,00 bh 5.000 250.000
5 Baut screw 15,00 Doz 75.000 1.125.000
6 Listplank woodplank L = 30cm 10,00 Lbr 85.000 850.000
7 Pilar beton (kaki teras) 14,00 Bh 300.000 4.200.000
8 Cat listplank (AVIAN) 4,00 Kg 60.000 240.000
9 Minyak cat 2,00 Ltr 35.000 70.000
10 Kuas 4,00 Bh 10.000 40.000
11 Semen 3,00 Zak 50.000 150.000
12 Pasir pasangan (sumlili) 1,00 Ret 600.000 600.000
13 Assesories tak terduga, dll 1,00 Ls 500.000 500.000
--------------------------
Jumlah A 60.435.000
B BIAYA KERJA
1 Biaya kerja rangka baja ringan (20x9) 180,00 M2 50.000 9.000.000
2 Biaya galian dan pasang pilar beton 14,00 Pilar 100.000 1.400.000
3 Biaya pengecatan listplank 1,00 Ls 1.000.000 1.000.000
--------------------------
Jumlah B 11.400.000
C BIAYA LAIN-LAIN
1 Biaya angkutan/akomodasi, dll 1,00 Ls 2.500.000 2.500.000
--------------------------
Jumlah C 2.500.000

Total A+B+C 74.335.000


Dibulatkan 75.000.000

Kupang, November 2021